JP3171716B2 - Foundation construction method on inclined surface - Google Patents
Foundation construction method on inclined surfaceInfo
- Publication number
- JP3171716B2 JP3171716B2 JP03877493A JP3877493A JP3171716B2 JP 3171716 B2 JP3171716 B2 JP 3171716B2 JP 03877493 A JP03877493 A JP 03877493A JP 3877493 A JP3877493 A JP 3877493A JP 3171716 B2 JP3171716 B2 JP 3171716B2
- Authority
- JP
- Japan
- Prior art keywords
- continuous wall
- foundation
- inclined surface
- constructing
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Foundations (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は傾斜面に建造物を構築す
る際の基礎部分の構築方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a foundation for constructing a building on an inclined surface.
【0002】[0002]
【従来の技術】一般に、傾斜面に建造物を構築する場合
には、図4ないし図6に示すような方法で施工される。
即ち、図4に示すように傾斜面20に建造物21を構築
する場合、まず図5に示すように、傾斜面20に山留め
22を施し、この打山留め22にアースアンカー23を
打って崩壊を防ぐ。この山留め22は仮設のものであ
り、図6に示すように建造物21を構築する際、谷側の
山留め22を撤去する。このとき杭24、24を打ちこ
れを基礎として建造物21を構築する。2. Description of the Related Art Generally, when constructing a building on an inclined surface, the construction is carried out by a method as shown in FIGS.
That is, when constructing a building 21 on the inclined surface 20 as shown in FIG. 4, first, as shown in FIG. prevent. As shown in FIG. 6, when the building 21 is constructed, the valley 22 is removed. At this time, the stakes 24 are hit and the building 21 is constructed on the basis of the stakes.
【0003】[0003]
【発明が解決しようとする課題】ところで、前記した従
来の方法ではアースアンカーが不可欠であるが、地盤が
特に軟弱である場合にはこれを打ち込めない場合があ
る。また、傾斜地は一般に湧水の可能性が高く、アース
アンカーの施工や山留めを撤去する作業には危険を伴
い、充分な安全性が確保できないことがある。In the above-mentioned conventional method, an earth anchor is indispensable. However, if the ground is particularly soft, it may not be able to be driven. In addition, sloping land generally has a high possibility of spring water, and construction of earth anchors and removal of mountain retaining parts involves danger, and sufficient safety may not be ensured in some cases.
【0004】また、従来の方法では山留めは仮設のもの
であるためこれを撤去して埋め戻す工程が不可欠である
が、一般にはこれらの工程が全施工上のクリチカルパス
となり工期を決定するため、これら工程での工期短縮が
望まれている。Further, in the conventional method, since the mountain retaining is a temporary one, it is essential to remove and refill the retaining, but in general, these steps become critical paths for the entire construction and determine the construction period. It is desired to shorten the construction period in these steps.
【0005】本発明は前記事項に鑑みてなされたもの
で、傾斜面において山留めと基礎構築とを効率的かつ安
全に行うことができる基礎構築方法を提供することを技
術的課題とする。The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a foundation construction method capable of efficiently and safely performing a mountain retaining and foundation construction on an inclined surface.
【0006】[0006]
【課題を解決するための手段】本発明は前記技術的課題
を解決するために、傾斜面に建造物を構築するに際しそ
の基礎部分を構築するための方法において以下のような
方法とした。Means for Solving the Problems In order to solve the above-mentioned technical problems, the present invention employs the following method for constructing a foundation portion when constructing a building on an inclined surface.
【0007】即ち、 (1)傾斜面の等高線に略沿った直線上に穿孔部1を多
数形成する。 (2)この穿孔部1を連続させて溝状の空洞とし、この
空洞部分にコンクリートを打設して連壁2とする。 (3)同様にしてこの連壁2を斜面の適宜位置に形成す
る。 (4)続いて、各連壁2、2間及び谷側に位置する連壁
2の谷側を切削して平面部3を形成する。 (5)この平面部3から突出させた前記連壁2の上端に
おいて前記連壁2、2間を橋絡するプレキャストコンク
リート製の横梁4を固定する。 (6)前記連壁2及び横梁4の上面を覆うよう基礎コン
クリート5を打設する。[0007] (1) A large number of perforations 1 are formed on a straight line substantially along the contour of the inclined surface. (2) The perforated portion 1 is made continuous to form a groove-like cavity, and concrete is cast into the cavity to form a continuous wall 2. (3) Similarly, the continuous wall 2 is formed at an appropriate position on the slope. (4) Subsequently, the flat portion 3 is formed by cutting the valley side of the continuous wall 2 located between the continuous walls 2 and 2 and on the valley side. (5) At the upper end of the connecting wall 2 protruding from the flat portion 3, a precast concrete beam 4 bridging between the connecting walls 2, 2 is fixed. (6) Pour foundation concrete 5 so as to cover the upper surfaces of the continuous wall 2 and the cross beam 4.
【0008】[0008]
【作用】前記(1)〜(3)の方法によって、建造物を
構築しようとする傾斜面が軟弱地盤である場合や湧水の
ある層があっても、アースアンカーを使用せずに安全
に、連壁2からなる山留が形成できる。According to the above-mentioned methods (1) to (3), even if the slope on which the building is to be constructed is soft ground or there is a layer with a spring, it can be safely used without using an earth anchor. A ridge consisting of the continuous wall 2 can be formed.
【0009】この山留としての連壁2は基礎形成後に取
り除かれるものではなく、そのまま基礎杭となる。した
がって埋め戻しや山留めを撤去する作業が不要となる。
また、前記方法によって さらに前記連壁2、2間をプ
レキャストコンクリート製の横梁4で橋絡して地中梁を
形成するので、コンクリート型枠の組み立て、撤去等の
作業がなくなり、基礎部の構築工程が簡素化される。The connecting wall 2 serving as a ridge is not removed after the foundation is formed, but becomes a foundation pile as it is. Therefore, there is no need to perform the work of backfilling and removing the mountain retaining.
In addition, since the underground beams are formed by bridging the connecting walls 2 and 2 with the precast concrete cross beams 4 by the above method, the work of assembling and removing the concrete formwork is eliminated, and the foundation is constructed. The process is simplified.
【0010】[0010]
【実施例】本発明の実施例を図1ないし図3に基づいて
説明する。この実施例は、傾斜面A上に建造物構築のた
めの基礎を形成するものである。まず、傾斜面Aの等高
線に略沿った直線上に、単軸オーガ掘削機によって多数
の穿孔部1を形成する。このとき孔の直径を2段階と
し、図2に示すように小経孔部分に鋼材2aを打ち込む
ようにする。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to FIGS. This embodiment forms the foundation for building construction on the inclined plane A. First, a large number of perforations 1 are formed by a single-axis auger excavator on a straight line substantially along the contour line of the inclined surface A. In this case the diameter of the hole and two stages, so as drive the steel 2 a to small Keiana portion as shown in FIG.
【0011】そして、前記した多数の穿孔部1の間にあ
る土砂を除去して連結させ、溝状の空洞とする。この空
洞部分にはソイルセメントを流入し連壁2とする。な
お、連壁2の他の形成方法としては前記穿孔部1を形成
した時点で、穿孔部1に内嵌する鋼管を打ち込みこの鋼
管内にソイルセメントを流入し、その後穿孔部1間を連
続させるようなONS工法を用いてもよい。Then, the earth and sand between the large number of perforated portions 1 is removed and connected to form a groove-shaped cavity. Soil cement flows into this hollow portion to form a continuous wall 2. As another method for forming the continuous wall 2, at the time when the perforated portion 1 is formed, a steel pipe to be fitted into the perforated portion 1 is driven in, soil cement flows into the steel pipe, and then the space between the perforated portions 1 is continued. Such an ONS method may be used.
【0012】前記した工程と同様にして、連壁2を斜面
の山側または谷側の適宜位置に形成する。これにより連
壁2は階段状に配置されることとなる。続いて、ソイル
セメントを充分に養生させた後、各連壁2、2間及び谷
側に位置する連壁2の谷側を切削して平面部3を形成す
る。ここで、前記各連壁2、2は山留め壁として作用
し、また、コンクリートを土中に流入させて形成したも
のであるため土壌との密着性が良好でアースアンカーは
不要となる。In the same manner as described above, the continuous wall 2 is formed at an appropriate position on the mountain side or the valley side of the slope. As a result, the continuous wall 2 is arranged in a stepped manner. Subsequently, after the soil cement is sufficiently cured, the flat portion 3 is formed by cutting the valley side of the continuous wall 2 located between the continuous walls 2 and 2 and on the valley side. Here, each of the connecting walls 2, 2 functions as a retaining wall, and is formed by flowing concrete into the soil, so that it has good adhesion to the soil and does not require an earth anchor.
【0013】前記連壁2は、整地した平面部3からその
上端が数十センチ程度突出するように設定してある。な
お、各連壁2の内部は図3に示すように鉄筋10を縦横
に通してあるが、各連壁2の上端を予めはつり鉄筋10
を上端から露出させておく。The connecting wall 2 is set so that its upper end protrudes from the leveled flat portion 3 by about several tens of centimeters. As shown in FIG. 3, the inside of each connecting wall 2 passes through the reinforcing bar 10 vertically and horizontally, but the upper end of each connecting wall 2 is
Is exposed from the top.
【0014】続いて各連壁2の側面に仕口ガゼットプレ
ート6が取り付けられる。この仕口ガゼットプレート6
は長方形の鉄板製で、仕口ガゼットプレート6の両端が
各連壁2の両側面から突出するようボルト締めされてい
る。そして、連壁2の両側面から突出する部分にボルト
孔(図示せず)が設けられている。Subsequently, a connection gusset plate 6 is attached to the side surface of each connecting wall 2. This connection gusset plate 6
Is made of a rectangular iron plate, and is bolted so that both ends of the connection gusset plate 6 protrude from both side surfaces of each connecting wall 2. Bolt holes (not shown) are provided at portions protruding from both side surfaces of the continuous wall 2.
【0015】その後、前記した連壁2の上端において前
記連壁2、2間を橋絡する横梁4を固定する。この横梁
4はプレキャストコンクリート製であり、予め工場や作
業ヤード等で所定の形状に成形したものを用いる。この
横梁4の両端部には前記仕口ガゼットプレート6のボル
ト孔に対応した穿孔部が設けられており、図3に示すよ
うにボルト7によって仕口ガゼットプレート6に固定さ
れる。Thereafter, a cross beam 4 bridging between the connecting walls 2 and 2 is fixed at the upper end of the connecting wall 2. The cross beam 4 is made of precast concrete, and is formed in a predetermined shape in a factory or a work yard in advance. Perforations corresponding to the bolt holes of the connection gusset plate 6 are provided at both ends of the cross beam 4, and are fixed to the connection gusset plate 6 by bolts 7 as shown in FIG.
【0016】そして前記連壁2及び横梁4の上面を覆う
よう基礎コンクリート5を現場打ちする。このとき前記
したように露出させた鉄筋10は基礎コンクリート5で
覆われ強固に固着される。Then, a foundation concrete 5 is cast in place so as to cover the upper surfaces of the connecting wall 2 and the cross beam 4. At this time, the exposed reinforcing bar 10 is covered with the foundation concrete 5 and firmly fixed.
【0017】以上述べたように、連壁2は山留めと基礎
杭との両方を兼ねているため、従来のように山留めを撤
去する等の作業は不要となる。また、アースアンカーも
不要となるため大幅な省力化が可能となる。しかも連壁
2は安全性に優れており、悪条件下でも安全に作業する
ことができる。As described above, since the connecting wall 2 serves as both the stake and the foundation pile, it is not necessary to remove the stake as in the prior art. In addition, since an earth anchor is not required, a large labor saving can be achieved. Moreover, the connecting wall 2 is excellent in safety, and can work safely even under bad conditions.
【0018】また、連壁2、2そのものを基礎として使
用するとともに、これら連壁2、2をプレキャストコン
クリート製の横梁4で橋絡するようにしたので生産性が
高く、工期を大幅に短縮することができる。In addition, since the connecting walls 2 and 2 are used as a foundation and the connecting walls 2 and 2 are bridged by the cross beams 4 made of precast concrete, the productivity is high and the construction period is greatly shortened. be able to.
【0019】[0019]
【発明の効果】本発明によれば、傾斜面において山留め
と基礎構築とを効率的に行うことができ、工期の短縮を
図ることができる。According to the present invention, it is possible to efficiently perform the mountain retaining and the foundation construction on the inclined surface, and to shorten the construction period.
【0020】また、連壁は強度が高く土壌の悪い現場で
も土留め能力が高く安全である。Further, the continuous wall has a high strength and a high soil retaining ability even at a site where the soil is poor, and is safe.
【図1】本発明の一実施例を示す施工初期状態の断面図FIG. 1 is a cross-sectional view of an initial state of construction showing an embodiment of the present invention.
【図2】本発明の一実施例を示す全体の断面図FIG. 2 is an overall sectional view showing one embodiment of the present invention.
【図3】本発明の一実施例を示す連壁と梁との接続部分
を示す側面図FIG. 3 is a side view showing a connecting portion between a continuous wall and a beam according to an embodiment of the present invention.
【図4】従来の傾斜面における基礎構築方法を示す概念
図FIG. 4 is a conceptual diagram showing a conventional method of building a foundation on an inclined surface.
【図5】従来の傾斜面における基礎構築方法を示す施工
前期の側面図FIG. 5 is a side view of the first half of construction showing a conventional method of building a foundation on a slope.
【図6】従来の傾斜面における基礎構築方法を示す施工
後期の側面図FIG. 6 is a side view of a later stage of construction showing a conventional method of building a foundation on a slope.
1・・穿孔部、 2・・連壁、 3・・平面部、 4・・横梁、 5・・基礎コンクリート。 1. Perforated part, 2. Connected wall, 3. Plane part, 4. Cross beam, 5. Basic concrete.
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 27/32 E02D 17/20 106 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 7 , DB name) E02D 27/32 E02D 17/20 106
Claims (1)
礎部分を構築するための方法において、 傾斜面の等高線に略沿った直線上に穿孔部を多数形成す
るとともに、この穿孔部を連続させて溝状の空洞とし、
この空洞部分にコンクリートを打設して連壁とし、同様
にしてこの連壁を斜面の適宜位置に形成し、続いて、各
連壁間及び谷側に位置する連壁の谷側を切削して平面部
を形成し、この平面部から突出させた前記連壁の上端に
おいて前記連壁間を橋絡するプレキャストコンクリート
製の横梁を固定した後、前記連壁及び横梁の上面を覆う
よう基礎コンクリートを打設することを特徴とする傾斜
面における基礎構築方法。1. A method for constructing a foundation on an inclined surface when constructing a building, comprising: forming a large number of perforated portions on a straight line substantially along a contour line of the inclined surface; Into a grooved cavity,
Concrete is cast into this hollow portion to form a continuous wall, and similarly, the continuous wall is formed at an appropriate position on the slope, and subsequently, the valley side of the continuous wall located between each continuous wall and the valley side is cut. After fixing a horizontal beam made of precast concrete bridging between the continuous walls at the upper end of the continuous wall protruding from the flat portion, the foundation concrete is formed so as to cover the upper surfaces of the continuous wall and the horizontal beam. A method for constructing a foundation on an inclined surface, comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03877493A JP3171716B2 (en) | 1993-02-26 | 1993-02-26 | Foundation construction method on inclined surface |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03877493A JP3171716B2 (en) | 1993-02-26 | 1993-02-26 | Foundation construction method on inclined surface |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06248653A JPH06248653A (en) | 1994-09-06 |
JP3171716B2 true JP3171716B2 (en) | 2001-06-04 |
Family
ID=12534643
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP03877493A Expired - Fee Related JP3171716B2 (en) | 1993-02-26 | 1993-02-26 | Foundation construction method on inclined surface |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3171716B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6206841B2 (en) * | 2013-06-26 | 2017-10-04 | 株式会社竹中工務店 | Support structure of structure |
-
1993
- 1993-02-26 JP JP03877493A patent/JP3171716B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH06248653A (en) | 1994-09-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH11303087A (en) | Retaining wall using corrosion-resistant structure anchor | |
KR100784201B1 (en) | Method for construction of tunnel | |
JP2003193495A (en) | Underground structure constructing method | |
JP2899463B2 (en) | Material | |
JP3171716B2 (en) | Foundation construction method on inclined surface | |
JPS62288269A (en) | Method for extending underground stair of building | |
JPS6354093B2 (en) | ||
JPS63280153A (en) | Underground inverted lining method | |
JPS584094A (en) | Method of constructing low road cross | |
JP3790310B2 (en) | Construction method of the building by the prior construction of steel frame | |
JPS58143020A (en) | Slope protection work | |
JP2001164559A (en) | Construction method of continuous underground wall guide wall making use of l-type precast member | |
JP3020882B2 (en) | Construction method of building structure with underground space | |
JPS6062327A (en) | Construction of underwater continuous wall | |
JPH04185816A (en) | Construction of beam in underground wall | |
JPS61266732A (en) | Reverse driving work | |
JP3079421B2 (en) | Construction method of L-shaped retaining wall and prefabricated wall element used therefor | |
JP2838019B2 (en) | Caisson blade framing method | |
JP3108898B2 (en) | Construction method of underground structure by reverse construction method | |
JP2620035B2 (en) | Construction method and structure of gas station office building | |
JP2829717B2 (en) | Construction method of installation foundation for heavy objects | |
JPH10152853A (en) | Method of building underground structure and structure member used therein | |
JPS5921831A (en) | Reverse placement work | |
JPH10152852A (en) | Method of building underground structure and structural member used therein | |
JPH05321244A (en) | Method of constructing self-standing sheathing wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080323 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090323 Year of fee payment: 8 |
|
LAPS | Cancellation because of no payment of annual fees |