JP3790310B2 - Construction method of the building by the prior construction of steel frame - Google Patents

Construction method of the building by the prior construction of steel frame Download PDF

Info

Publication number
JP3790310B2
JP3790310B2 JP30239396A JP30239396A JP3790310B2 JP 3790310 B2 JP3790310 B2 JP 3790310B2 JP 30239396 A JP30239396 A JP 30239396A JP 30239396 A JP30239396 A JP 30239396A JP 3790310 B2 JP3790310 B2 JP 3790310B2
Authority
JP
Japan
Prior art keywords
construction
foundation
ground
steel
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP30239396A
Other languages
Japanese (ja)
Other versions
JPH10131300A (en
Inventor
秀一 朋田
鈴夫 熊谷
春彦 上田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP30239396A priority Critical patent/JP3790310B2/en
Publication of JPH10131300A publication Critical patent/JPH10131300A/en
Application granted granted Critical
Publication of JP3790310B2 publication Critical patent/JP3790310B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、鉄骨建方を伴う建築物の施工技術に関するものである。
【0002】
【従来の技術】
従来、鉄骨・鉄筋コンクリート造の建築物の施工は、次のような工程で行われている。
(1) 基礎及び地中梁(以下、単に基礎という)の施工予定領域に沿って地盤中に所定間隔で場所打ちコンクリート杭を造成する。
(2) 前記基礎の施工予定領域の地盤を根切り掘削し、この根切り部内に型枠及び鉄筋を組み立てる。
(3) 前記型枠内における前記各場所打ちコンクリート杭と対応する位置に、それぞれ鉄骨柱の建て込みのための所要数のアンカーボルトを設置する。
(4) 前記型枠内にコンクリートを打設することによって基礎を構築する。
(5) 基礎のコンクリートが一定の養生期間を経て硬化した後、その周囲を掘削土で埋め戻して転圧する。
(6) 前記基礎上の所定位置に前記アンカーボルト及びベースプレートを介して鉄骨柱を建て込み、この鉄骨柱に鉄骨梁を架設する。
(7) 躯体コンクリート工事及びその仕上工事を行う。
【0003】
【発明が解決しようとする課題】
上記従来技術においては、次のような問題点が指摘される。
(a) コンクリート杭の施工後、更に基礎を構築して基礎のコンクリートが十分に養生硬化してからでないと鉄骨の建方作業を行うことができないため、工期が長くなる。
(b) 鉄骨の建方作業が、基礎の構築後に根切り掘削部を埋め戻した地盤、すなわち埋め戻しによる乱された地盤上で重機によって行われるため、作業の安全性を確保するためには、基礎の周囲の埋め戻し地盤を十分に転圧する必要がある。
【0004】
本発明は、上記のような事情のもとになされたもので、その技術的課題とするところは、鉄骨建方作業を基礎の構築に先行して行うことを可能とすることによって工期の短縮を図り、かつ安全に作業を遂行することにある。
【0005】
【課題を解決するための手段】
上述した技術的課題は、本願発明によって有効に解決することができる。すなわち本願発明に係る鉄骨の先行建方による建築物の施工方法は、まず基礎の施工予定領域の地盤中に所定間隔で場所打ちコンクリート杭を造成する過程で前記場所打ちコンクリート杭に鉄骨材からなる仮柱を地上の所定高さに突出した状態で埋設する。仮柱の天端は地上の一定の高さとなるように切り揃え、捨てプレートを溶接しておく。この捨てプレートは、後述する基礎のコンクリートに一体化されるものであって、鉄骨柱との継手部となるものである。なお、ここでいう「基礎」とは、地中梁等を含むものである。
【0006】
次に、仮柱の天端の捨てプレート上に鉄骨柱を建て込んでこの捨てプレートと鉄骨柱とを結合する。これによって、鉄骨柱が各場所打ちコンクリート杭上にそれぞれ仮柱を介して立設され、すなわち基礎の施工及びその養生期間を待つことなく、これに先行して鉄骨建方が行われる。
【0007】
鉄骨建方終了後、基礎の施工予定領域の地盤を根切り掘削し、この根切り掘削部内に場所打ちコンクリート杭の天端と一体の基礎を構築する。そしてこの構築過程で、前記基礎のコンクリート中に前記仮柱全体を埋設状態とすることによって、鉄骨柱の下端部が捨てプレート及び仮柱を介して前記基礎に一体化される。また、この基礎の構築作業に並行して、地上の躯体工事を行う。
【0008】
【発明の実施の形態】
以下、本発明に係る鉄骨の先行建方による建築物の施工方法の好適な一実施形態を、図1乃至図5を参照しながら説明する。
【0009】
本実施形態の施工方法によれば、まず図1の要部断面斜視図に示すように、基礎の施工予定領域に沿って地盤1中に所定間隔で場所打ちコンクリート杭2を造成する。この場所打ちコンクリート杭2は、後述する鉄骨柱の建て込み位置に対応して造成され、その造成方法としては既知の方法、例えば地中に鋼管を打ち込んでその中にコンクリートを流し込みながら前記鋼管を引き抜く方法や、予め地盤を削孔してからこの孔にコンクリートを流し込む方法などが採用される。
【0010】
場所打ちコンクリート杭2の造成過程においては、その上端部のコンクリート中に、例えばH型鋼等の鉄骨材からなる仮柱3が、地上の所定高さまで突出した状態となるように埋設される。したがってこの仮柱3は、経時的に硬化して行く前記場所打ちコンクリート杭2に一体化される。この仮柱3の天端3aは一定の高さとなるように切り揃え、図2の要部断面斜視図に示すように、前記天端3a上には鋼板からなる略正方形状の捨てプレート31を水平な鍔状に張り出した状態に配置して溶接する。捨てプレート31には所要数のボルト挿通孔31aが開設されている。
【0011】
場所打ちコンクリート杭2が硬化することによって仮柱3が強固に固定されたら、図3の立面図に示すように、仮柱3の天端の捨てプレート31上にH型鋼等からなる鉄骨柱4を建て込む。鉄骨柱4の下端部には捨てプレート31と同様のベースプレート41が予め溶接されており、このベースプレート41と捨てプレート31を、互いに位置合わせした双方のボルト挿通孔に挿通したボルト6(図5参照)及びこれに螺合するナット(図示省略)で緊結することによって、鉄骨柱4は、仮柱3に結合され、この仮柱3を介して場所打ちコンクリート杭2にしっかり保持される。また、このようにして建て込んだ各鉄骨柱4,4間には各階の鉄骨梁5を架設する。
【0012】
上述の鉄骨柱4の建て込み及び鉄骨梁5の架設といった鉄骨建方作業には重機が用いられるが、この鉄骨建方は、場所打ちコンクリート杭2に設けた仮柱3によって、後述する根切り掘削を伴う基礎7の施工に先行して行われるため、前記重機は未掘削の原地盤1(土粒子の結合組織が乱されていない地盤)上で安全に走行することができる。
【0013】
次に図4の立面図及び図5の要部断面斜視図に示すように、仮柱3の周囲を含む基礎の施工予定領域の地盤1を根切り掘削して、場所打ちコンクリート杭2の天端部が露出する根切り部11を形成し、この根切り部11に沿って基礎7を構築する。基礎7の構築は、根切り部11に沿って型枠を組み立て、その中に所要の鉄筋を配設してからコンクリートを打設するといった既知の方法で行われる。前記型枠は、場所打ちコンクリート杭2の天端部と、そこから突出した仮柱3及び捨てプレート31を包囲するように組み立てられ、したがって、前記場所打ちコンクリート杭2の天端部と、仮柱3及び捨てプレート31は、前記型枠へのコンクリート打設によって施工される基礎7に埋設状態となり、経時的に養生硬化して行くこのコンクリート(基礎7)に一体化される。
【0014】
一方、鉄骨柱4及び鉄骨梁5の建方作業後は、この鉄骨への型枠組み立てや配筋、コンクリート打設といった工程を経て、図4に示すように上階の躯体8を順次施工して行くが、これらの作業は、基礎7の施工完了を待つことなく、前記鉄骨建方の終了後に直ちに継続して行うことができる。これは、鉄骨柱4が基礎7の構築以前にすでに仮柱3を介して地中の場所打ちコンクリート杭2にしっかり支持固定されているからである。したがって、上階の躯体8の施工は基礎7の施工と並行して行うことができ、工期が短縮される。
【0015】
基礎7はそのコンクリートの硬化と共に、躯体8の荷重に対する支持力を発現する。また、基礎7のコンクリート硬化後は、その周囲の根切り部11を埋め戻すが、既に鉄骨建方は終了しているのであるから、鉄骨建方のための重機が走行することを想定した埋め戻し地盤の転圧は不要となる。
【0016】
なお、本発明は、図示の実施形態によって限定的に解釈されるものではない。例えば上記実施形態では、仮柱3は場所打ちコンクリート杭2に一体化した後、その天端3aを一定の高さで切り揃えて捨てプレート31を溶接したが、捨てプレート31は予め仮柱3に溶接しておくこともできる。
【0017】
【発明の効果】
本発明に係る鉄骨の先行建方による建築物の施工方法によれば、次のような効果が実現される。
(1) 鉄骨建方が基礎の施工に先行して行われ、その後の躯体工事も基礎の施工完了を待つことなく行うことができるので、工期が著しく短縮される。
(2) 鉄骨建方が基礎の施工のための根切り掘削に先行して、掘削により乱されていない原地盤上で行われるため、作業の安全性が向上する。
(3) 基礎の施工後の埋め戻し地盤を、鉄骨建方に用いられる重機の走行を想定して転圧する必要がない。
【図面の簡単な説明】
【図1】本発明に係る施工方法の一実施形態において、地盤中に場所打ちコンクリート杭を造成する過程でこの場所打ちコンクリート杭に仮柱を地上の所定高さに突出した状態を示す要部断面斜視図である。
【図2】上記実施形態において、仮柱の天端に捨てプレートを溶接した状態を示す要部断面斜視図である。
【図3】上記実施形態において、仮柱の天端の捨てプレート上での鉄骨建方の工程を示す立面図である。
【図4】上記実施形態において、地盤を根切り掘削して場所打ちコンクリート杭上に基礎を構築しこの基礎に仮柱を埋設した状態を示す立面図である。
【図5】上記実施形態において、地盤を根切り掘削して場所打ちコンクリート杭上に基礎を構築しこの基礎に仮柱を埋設した状態を示す要部断面斜視図である。
【符号の説明】
1 地盤
11 根切り部(根切り掘削部)
2 場所打ちコンクリート杭
3 仮柱
31 捨てプレート
4 鉄骨柱
7 基礎
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction technique for a building with a steel frame construction.
[0002]
[Prior art]
Conventionally, construction of steel frames and reinforced concrete buildings has been performed in the following processes.
(1) Create cast-in-place concrete piles at predetermined intervals in the ground along the planned construction area of foundations and underground beams (hereinafter simply referred to as foundations).
(2) Excavate the ground in the planned construction area of the foundation, and assemble the formwork and rebar in the root cut.
(3) Install the required number of anchor bolts for the construction of steel columns at positions corresponding to the cast-in-place concrete piles in the formwork.
(4) Build a foundation by placing concrete in the formwork.
(5) After the concrete foundation has hardened after a certain curing period, backfill the surrounding area with excavated soil and roll it.
(6) A steel column is installed at a predetermined position on the foundation via the anchor bolt and the base plate, and a steel beam is installed on the steel column.
(7) Conduct concrete construction and finishing work.
[0003]
[Problems to be solved by the invention]
In the above prior art, the following problems are pointed out.
(a) After the construction of the concrete pile, the construction period of the steel frame can be extended only after the foundation is constructed and the foundation concrete is sufficiently cured and hardened.
(b) Since the construction work of the steel frame is performed by heavy machinery on the ground where the root excavation part was backfilled after the foundation was constructed, that is, the ground that was disturbed by backfilling, in order to ensure the safety of the work It is necessary to fully roll the backfill ground around the foundation.
[0004]
The present invention has been made under the circumstances as described above, and the technical problem is that the construction period can be shortened by making it possible to perform the steel frame construction work prior to the foundation construction. And to work safely.
[0005]
[Means for Solving the Problems]
The technical problem described above can be effectively solved by the present invention. That construction method of a building prior erection of steel according to the present invention comprises a steel material to the place concrete pile is first to ground during construction region for the foundation in the process of reclamation to place concrete pile at predetermined intervals The temporary pillar is buried in a state protruding to a predetermined height above the ground. Cut and align the top of the temporary column so that it is at a certain height above the ground, and weld the discarded plate. This discard plate is integrated with the foundation concrete described later and serves as a joint portion with the steel column. Here, the “foundation” includes an underground beam.
[0006]
Next, a steel column is built on the discard plate at the top of the temporary column, and the discard plate and the steel column are coupled. As a result, the steel column is erected on each cast-in-place concrete pile via the temporary column, that is, the steel frame is built prior to this without waiting for the foundation construction and its curing period.
[0007]
After the construction of the steel frame is completed, the ground in the planned construction area of the foundation is excavated, and a foundation integrated with the top of the cast-in-place concrete pile is constructed in this excavation part. In this construction process, the entire temporary column is embedded in the concrete of the foundation, whereby the lower end portion of the steel column is integrated with the foundation via the discard plate and the temporary column. In parallel with this foundation construction work, groundwork will be carried out on the ground .
[0008]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EMBODIMENTS Hereinafter, a preferred embodiment of a building construction method according to a steel frame preceding construction according to the present invention will be described with reference to FIGS. 1 to 5.
[0009]
According to the construction method of the present embodiment, first, cast-in-place concrete piles 2 are created at predetermined intervals in the ground 1 along the planned construction area of the foundation, as shown in the cross-sectional perspective view of the main part in FIG. This cast-in-place concrete pile 2 is constructed corresponding to the steel column post-installation position, which will be described later, and as a construction method thereof, for example, a steel pipe is driven into the ground and concrete is poured into the steel pipe. A method of pulling out or a method of pouring concrete into the hole after previously drilling the ground is adopted.
[0010]
In the process of creating the cast-in-place concrete pile 2, the temporary column 3 made of a steel frame material such as H-shaped steel is embedded in the concrete at the upper end so as to protrude to a predetermined height on the ground. Therefore, the temporary pillar 3 is integrated with the cast-in-place concrete pile 2 that hardens with time. The top end 3a of the temporary pillar 3 is cut and aligned so as to have a certain height, and as shown in the cross-sectional perspective view of the main part of FIG. 2, a substantially square shaped discard plate 31 made of a steel plate is placed on the top end 3a. Place and weld in a horizontal overhang. The discard plate 31 has a required number of bolt insertion holes 31a.
[0011]
When the cast-in-place concrete pile 2 is hardened and the temporary column 3 is firmly fixed, as shown in the elevation view of FIG. 3, the steel column made of H-shaped steel or the like is disposed on the discard plate 31 at the top end of the temporary column 3. 4 is built. A base plate 41 similar to the discard plate 31 is welded to the lower end of the steel column 4 in advance, and the bolt 6 (see FIG. 5) is inserted into both bolt insertion holes that are aligned with each other. ) And a nut (not shown) screwed to the steel column 4, the steel column 4 is coupled to the temporary column 3, and is securely held by the cast-in-place concrete pile 2 via the temporary column 3. Further, a steel beam 5 on each floor is installed between the steel columns 4 and 4 built in this way.
[0012]
Heavy machinery is used for the construction work of the steel frame such as the construction of the steel column 4 and the construction of the steel beam 5 as described above. This steel construction method is performed by a temporary pillar 3 provided in the cast-in-place concrete pile 2 to be described later. Since it is performed prior to the construction of the foundation 7 with excavation, the heavy machinery can safely travel on the unexcavated raw ground 1 (the ground where the connective structure of soil particles is not disturbed).
[0013]
Next, as shown in the elevation view of FIG. 4 and the cross-sectional perspective view of the main part of FIG. 5, the ground 1 in the planned construction area of the foundation including the periphery of the temporary column 3 is excavated, and the cast-in-place concrete pile 2 The root cutting part 11 where the top end part is exposed is formed, and the foundation 7 is constructed along the root cutting part 11. The foundation 7 is constructed by a known method in which a formwork is assembled along the root cutting part 11 and a concrete is placed after a necessary reinforcing bar is disposed therein. The formwork is assembled so as to surround the top end portion of the cast-in-place concrete pile 2 and the temporary pillar 3 and the discard plate 31 protruding from the top end portion. The pillar 3 and the discard plate 31 are embedded in the foundation 7 constructed by placing the concrete in the formwork, and are integrated with the concrete (foundation 7) that is cured and cured over time.
[0014]
On the other hand, after the construction work of the steel column 4 and the steel beam 5, through the steps such as formwork assembly, bar arrangement and concrete placement to the steel frame, the upper-level frame 8 is sequentially constructed as shown in FIG. However, these operations can be continued immediately after completion of the steel frame construction without waiting for the completion of the construction of the foundation 7. This is because the steel column 4 is already firmly supported and fixed to the underground cast-in-place concrete pile 2 via the temporary column 3 before the foundation 7 is constructed. Therefore, the construction of the frame 8 on the upper floor can be performed in parallel with the construction of the foundation 7 and the construction period is shortened.
[0015]
The foundation 7 develops a supporting force against the load of the frame 8 along with the hardening of the concrete. Moreover, after the concrete of the foundation 7 is hardened, the surrounding root cutting portion 11 is backfilled, but since the steel frame construction has already been completed, it is assumed that heavy machinery for the steel frame construction will travel. There is no need to roll back the ground.
[0016]
In addition, this invention is not limitedly interpreted by embodiment of illustration. For example, in the above embodiment, the temporary column 3 is integrated with the cast-in-place concrete pile 2, and then the top end 3a is trimmed at a certain height and the discard plate 31 is welded. It can also be welded.
[0017]
【The invention's effect】
According to the construction method of the building by the prior construction of the steel frame concerning the present invention, the following effects are realized.
(1) Since the steel frame is constructed prior to foundation construction, and subsequent frame construction can be carried out without waiting for completion of foundation construction, the construction period is significantly shortened.
(2) Since the construction of the steel frame is performed on the original ground undisturbed by excavation prior to the root excavation for the foundation construction, the safety of the work is improved.
(3) There is no need to roll the backfill ground after the foundation construction assuming heavy machinery used for steel construction.
[Brief description of the drawings]
FIG. 1 shows an essential part of a construction method according to an embodiment of the present invention showing a state in which a temporary column protrudes to a predetermined height on the ground cast-in-place concrete pile in the process of creating the cast-in-place concrete pile in the ground. It is a cross-sectional perspective view.
FIG. 2 is a cross-sectional perspective view of a main part showing a state in which a discard plate is welded to the top end of the temporary column in the embodiment.
FIG. 3 is an elevational view showing a process for constructing a steel frame on a discard plate at the top end of the temporary column in the embodiment.
FIG. 4 is an elevational view showing a state where a foundation is constructed on a cast-in-place concrete pile by excavating the ground and excavating a temporary column in the foundation in the embodiment.
FIG. 5 is a cross-sectional perspective view of a main part showing a state in which a foundation is constructed on a cast-in-place concrete pile by root excavation of the ground and a temporary column is embedded in the foundation in the embodiment.
[Explanation of symbols]
1 Ground 11 Root cutting part (Root cutting excavation part)
2 Cast-in-place concrete pile 3 Temporary column 31 Discard plate 4 Steel column 7 Foundation

Claims (1)

基礎の施工予定領域の地盤中に所定間隔で場所打ちコンクリート杭を造成すると共にその造成過程で前記場所打ちコンクリート杭に鉄骨材からなる仮柱を地上の所定高さに突出した状態で埋設してから、
前記仮柱の天端の捨てプレート上に鉄骨柱を建て込んでこの捨てプレートと鉄骨柱とを結合し、
その後前記基礎の施工予定領域の地盤を根切り掘削してこの根切り掘削部内に前記場所打ちコンクリート杭の天端と一体の基礎を構築しこの基礎のコンクリート中に前記仮柱全体を埋設状態とし、この基礎構築作業に並行して、地上の躯体の施工を行うことを特徴とする鉄骨の先行建方による建築物の施工方法。
A cast-in-place concrete pile is created at predetermined intervals in the ground of the planned construction area of the foundation, and a temporary column made of steel frame is embedded in the cast-in-place concrete pile in a state of projecting to a predetermined height above the ground. From
A steel column is built on the discard plate at the top of the temporary column, and this discard plate and the steel column are combined .
Thereafter, the ground of the construction planned area of the base and roots cut excavated this root cutting an embedded state the whole of the provisional pillar to build the heavens end and the foundation of the integral with the concrete in the foundation of the cast-in-place concrete piles in the drilling portion In parallel with this foundation construction work, the construction method of the building by the preceding construction of the steel frame, characterized in that construction of the ground frame is performed .
JP30239396A 1996-10-29 1996-10-29 Construction method of the building by the prior construction of steel frame Expired - Fee Related JP3790310B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30239396A JP3790310B2 (en) 1996-10-29 1996-10-29 Construction method of the building by the prior construction of steel frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30239396A JP3790310B2 (en) 1996-10-29 1996-10-29 Construction method of the building by the prior construction of steel frame

Publications (2)

Publication Number Publication Date
JPH10131300A JPH10131300A (en) 1998-05-19
JP3790310B2 true JP3790310B2 (en) 2006-06-28

Family

ID=17908378

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30239396A Expired - Fee Related JP3790310B2 (en) 1996-10-29 1996-10-29 Construction method of the building by the prior construction of steel frame

Country Status (1)

Country Link
JP (1) JP3790310B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505705A (en) * 2011-10-26 2012-06-20 铜陵有色建安钢构有限责任公司 Method for pre-embedding bolts by using positioning steel plates

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3671344B2 (en) * 2000-07-14 2005-07-13 清水建設株式会社 Joint structure between foundation pile and column base and its construction method
KR101411935B1 (en) * 2013-03-12 2014-06-26 김운수 Prefabricated basic structure of frame of pavilion
CN103195167B (en) * 2013-04-10 2015-03-25 中建六局第三建筑工程有限公司 Method for lifting concrete in ultrahigh reducing steel pipe column

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505705A (en) * 2011-10-26 2012-06-20 铜陵有色建安钢构有限责任公司 Method for pre-embedding bolts by using positioning steel plates

Also Published As

Publication number Publication date
JPH10131300A (en) 1998-05-19

Similar Documents

Publication Publication Date Title
JP4069509B2 (en) Construction method of reverse struts in the outer periphery of underground excavation space
JP3095376B2 (en) Construction method of building foundation
JP2006207265A (en) Joining method of pile and column and its structure
JP3790310B2 (en) Construction method of the building by the prior construction of steel frame
JP3002126B2 (en) Temporary receiving method for structures
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
KR102277470B1 (en) Basement Composite Wall Using Retaing Wall And Method for Constructing the Same
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JP2868651B2 (en) Earth retaining method above existing underground structure
JP3185129B2 (en) Column-integrated column base fixed foundation structure and its construction method
JP3390081B2 (en) How to build an underground parking
KR20080059951A (en) Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor
JPS63280153A (en) Underground inverted lining method
JP2858997B2 (en) Temporary support column used for reverse driving method
JPH0559215B2 (en)
JP2799266B2 (en) How to join columns in building a new building
JP3678695B2 (en) Fixing method of column to concrete foundation
JPH04185816A (en) Construction of beam in underground wall
JPH09279609A (en) Building method of precast reinforced concrete-made underground structure
JP2838019B2 (en) Caisson blade framing method
JPH02248527A (en) Constructing foundation structure
JP2899669B2 (en) Simple mountain retaining method
JP3171716B2 (en) Foundation construction method on inclined surface
JP2002115324A (en) Column base unit, column integrated column base fixing foundation structure using the column base unit, and construction method therefor
JP3020882B2 (en) Construction method of building structure with underground space

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050726

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050803

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051003

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060301

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060331

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100407

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110407

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees