JPH02248527A - Constructing foundation structure - Google Patents
Constructing foundation structureInfo
- Publication number
- JPH02248527A JPH02248527A JP6607789A JP6607789A JPH02248527A JP H02248527 A JPH02248527 A JP H02248527A JP 6607789 A JP6607789 A JP 6607789A JP 6607789 A JP6607789 A JP 6607789A JP H02248527 A JPH02248527 A JP H02248527A
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- foundation structure
- excavated
- slab
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009412 basement excavation Methods 0.000 claims abstract description 24
- 238000009415 formwork Methods 0.000 claims description 46
- 230000003014 reinforcing effect Effects 0.000 claims description 12
- 238000010276 construction Methods 0.000 claims description 11
- 238000000034 method Methods 0.000 claims description 10
- 239000002184 metal Substances 0.000 claims description 9
- 229910052751 metal Inorganic materials 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 229920003002 synthetic resin Polymers 0.000 claims description 5
- 239000000057 synthetic resin Substances 0.000 claims description 5
- 239000002689 soil Substances 0.000 abstract description 9
- 230000002787 reinforcement Effects 0.000 abstract description 7
- 238000005266 casting Methods 0.000 abstract 1
- 239000004575 stone Substances 0.000 abstract 1
- 239000004576 sand Substances 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 3
- 230000000149 penetrating effect Effects 0.000 description 3
- 239000004698 Polyethylene Substances 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 229920000573 polyethylene Polymers 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- -1 polyethylene Polymers 0.000 description 1
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は建築物等の基礎工事に適用される基礎、地中梁
等の基礎構築物の施工方法に係るものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method of constructing foundation structures such as foundations and underground beams applied to foundation construction of buildings and the like.
(従来の技術)
従来、建築物等の基礎工事においては、基礎や地中梁を
構築する場合、型枠の組立、解体が行なわれるように、
同基礎、地中梁の大きさよりも広い面積に亘って掘削し
、掘削土を場内または場外に搬出する。(Conventional technology) Conventionally, in foundation work for buildings, etc., when constructing foundations and underground beams, formwork is assembled and dismantled.
An area larger than the size of the foundation and underground beams will be excavated, and the excavated soil will be carried inside or outside the site.
かくして所定の深さまで掘削したのち割栗地業を施し、
捨てコンクリートを打設し、基礎や地中梁の位置を墨出
して、同位置に鉄筋を組立てる。After excavating to a predetermined depth in this way, we applied the Waricuri method.
Pour concrete, mark out the locations of the foundation and underground beams, and assemble reinforcing bars at the same locations.
次いで基礎、地中梁の型枠を組立てスラブコンクリート
下端までコンクリートを打設し、同打設コンクリートの
硬化後、前記型枠を解体したのち、基礎、地中梁の余堀
り部に土砂等を埋戻し、地盤の転圧後砂利地業を施す。Next, formwork for the foundation and underground beams is assembled and concrete is poured to the bottom edge of the slab concrete. After the poured concrete has hardened, the formwork is dismantled, and earth and sand etc. are poured into the excess excavations of the foundation and underground beams. After backfilling and compacting the ground, apply gravel.
次いで防濡、断熱処理後、スラブ補強筋を配筋してスラ
ブコンクリートを打設する。Next, after moisture-proofing and heat insulation treatment, slab reinforcement is placed and slab concrete is poured.
かくして基礎工事を完了し、次の工程に移る。In this way, the foundation work is completed and we move on to the next process.
(発明が解決しようとするtJllり
しかしながら前記従来の方法には、次のような問題点が
ある。However, the conventional method has the following problems.
+il 型枠が組立て解体されるように、基礎、地中
梁の所定の大きさよりも広く掘削するため、掘削土量が
多くなり、掘削土砂を場内、または場外へ搬出し、埋戻
し時には場外より土砂を搬入するため、作業量が増大し
、工費が嵩む。+il In order to assemble and dismantle the formwork, the excavation is carried out wider than the prescribed size of the foundation and underground beams, so the amount of excavated soil is large, and the excavated soil is carried inside or outside the site, and when backfilling, it is carried out from outside the site. Carrying in earth and sand increases the amount of work and construction costs.
Ti1l 基礎、地中梁の型枠を組み、スラブコンク
リート下端までコンクリートを打設し、同打設コンクリ
ートの硬化後でなければ型枠を解体することができず、
作業手順が悪く作業性に難点がある。Ti1l Formwork for the foundation and underground beams was constructed, concrete was poured to the bottom of the slab concrete, and the formwork could not be dismantled until the poured concrete had hardened.
The work procedure is poor and there are difficulties in workability.
(iiil 型枠の組立、解体により労務が増大し、
多くの資材が必要となる。(iii) Labor increases due to assembly and dismantling of formwork,
Many materials are required.
本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、型枠工事が簡素化され
、型枠組立時の余堀りが最小限に抑制され、掘削土量の
削減と省力化とが図られ、工期が短縮され、工費が節減
される基礎構築物の施工法を提供する点にある。The present invention has been proposed in view of the problems of the prior art, and its objectives are to simplify formwork construction, minimize over-drilling during formwork assembly, and minimize excavation. The object of the present invention is to provide a construction method for a foundation structure that reduces the amount of soil and labor, shortens the construction period, and reduces construction costs.
(課題を解決するための手段)
前記の目的を達成するため、本発明に係る基礎構築物の
施工方法は、基礎地盤を、同地盤に構築される基礎構築
物の形状よりやや大きめに所定深゛度まで掘削し、次い
で同掘削孔内に前記基礎構築物のコンクリート打設用型
枠パネルを組立て、同型枠パネル外側の余堀り部分を埋
戻し、次いで前記掘削孔に基礎構築物の鉄筋を配筋する
とともにスラブ補強筋を配筋し、次いで前記基礎構築物
及びスラブのコンクリート打設を同時に行なうように構
成されている。(Means for Solving the Problems) In order to achieve the above-mentioned object, the method for constructing a foundation structure according to the present invention is to prepare the foundation ground to a predetermined depth slightly larger than the shape of the foundation structure to be constructed on the same ground. Then, a formwork panel for concrete pouring of the foundation structure is assembled in the same excavation hole, the excess area outside the formwork panel is backfilled, and then reinforcing bars for the foundation structure are placed in the excavation hole. At the same time, slab reinforcing bars are arranged, and then concrete is placed for the foundation structure and the slab at the same time.
この際前記型枠パネルは軽量化とコストの節減とを図る
ため鉄骨フレームに金属製網状片を張設して構成され、
前記フレームより垂設された脚片を前記掘削孔の底部地
盤に貫入して同掘削孔に前記型枠パネルを簡単に建込み
、同パネルの外側面に合成樹脂フィルムを張設して打設
コンクリートの養生、及び漏出防止を図るものである。In this case, in order to reduce weight and cost, the formwork panel is constructed of a steel frame with metal mesh pieces stretched over it.
The formwork panel is easily erected in the excavation hole by penetrating the leg pieces hanging from the frame into the ground at the bottom of the excavation hole, and a synthetic resin film is stretched on the outer surface of the panel and cast. This is to cure concrete and prevent leakage.
更に前記型枠パネルを固定するため、前記掘削孔の周辺
地盤に貫入した杭に線条を介して緊結するものである。Furthermore, in order to fix the formwork panel, it is fastened via wires to a pile that has penetrated into the ground around the excavation hole.
(作用)
本発明によれば前記したように、基礎地盤を、同地盤に
構築される基礎構築物の形状よりやや大きめに所定深度
まで掘削し、同掘削孔内に前記基礎構築物のコンクリー
ト打設用型枠パネルを組立て、同パネル外側の小容積の
余堀り部を埋戻し、前記掘削孔に基礎構築物の鉄筋を配
筋するとともに、スラブ補強筋を配筋し、前記型枠パネ
ルを解体することなく前記基礎構築物のコンクリート並
にスラブのコンクリートを同時に打設して、前記型枠パ
ネルを埋殺したまま基礎構築物を施工するものである。(Function) According to the present invention, as described above, the foundation ground is excavated to a predetermined depth slightly larger than the shape of the foundation structure to be constructed on the same ground, and the concrete for the foundation structure is poured into the excavated hole. Assemble the formwork panel, backfill the small-volume surplus area on the outside of the panel, place reinforcing bars for the foundation structure in the excavated hole, place slab reinforcing bars, and dismantle the formwork panel. The concrete for the foundation structure and the concrete for the slab are poured at the same time without any problems, and the foundation structure is constructed while the form panels are buried.
請求項2の発明は前記型枠パネルを鉄骨フレームに金属
製網状片を張設して構成し、前記フレームより垂設した
脚片を利用して同脚片を前記掘削孔底部地盤に貫入する
ことによって、前記型枠パネルを簡単に建込み、更に同
型枠パネルにおける前記金属製網状片の外側面に、コン
クリートの漏出を防止する合成樹脂フィルムを張設する
ものである。According to a second aspect of the invention, the formwork panel is constructed by extending a metal mesh piece to a steel frame, and the leg piece is penetrated into the ground at the bottom of the excavation hole using a leg piece hanging down from the frame. This allows the formwork panel to be easily erected, and furthermore, a synthetic resin film for preventing leakage of concrete is provided on the outer surface of the metal mesh piece in the formwork panel.
請求項3の発明は前記型枠パネルの建込まれた、前記掘
削孔の周辺地盤に、杭を貫入し、同杭に前記型枠パネル
を線条で緊結して、同型枠パネルを固定するものである
。The invention according to claim 3 is characterized in that a pile is penetrated into the ground around the excavation hole in which the formwork panel is erected, and the formwork panel is fastened to the pile with a wire, thereby fixing the formwork panel. It is something.
(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.
!&礎地盤囚を同地盤に構築される基礎構築物の形状よ
りやや大きめに所定深度まで掘削し、(第5図参照)次
いで掘削孔(1)内に型枠パネル(印を組立てる。(第
6図参照)
同型枠パネル(lは第12図及び第13図に示すように
上下水平枠(2)(3)及び両端垂直枠(4)(4)並
に中間垂直枠(5)とよりなる鉄骨フレームに、リブラ
ス、エキスバンドメタル等の金属製網状片(6)を張設
して構成され、前記各垂直枠(4)(5)より埋込み用
脚片(4a) (5a)が延設されている。図中(7)
は上下水平枠(2)(3)間に配設された縦胴縁である
。! & Excavate the foundation soil to a predetermined depth to a size slightly larger than the shape of the foundation structure to be constructed on the same ground (see Figure 5), then assemble the formwork panel (marked) in the excavation hole (1). (See figure) The same form panel (l consists of upper and lower horizontal frames (2) (3), vertical frames (4) (4) at both ends, and middle vertical frame (5) as shown in Figures 12 and 13) It consists of a steel frame with metal mesh pieces (6) made of ribrass, expanded metal, etc. stretched, and embedding leg pieces (4a) (5a) extend from each of the vertical frames (4) and (5). (7) in the figure.
is a vertical torso border placed between the upper and lower horizontal frames (2) and (3).
従って前記型枠パネル(印における各垂直枠(4)(5
)の脚片(4a) (5a)を掘削孔(1)の底部に貫
入することによって、同型枠パネル(Bの組立が簡単に
行なわれるものである。Therefore each vertical frame (4) (5) at said formwork panel (marked
The same formwork panel (B) can be easily assembled by inserting the leg pieces (4a) and (5a) of ) into the bottom of the excavated hole (1).
次いで前記掘削孔(1)の底部に割栗地業(8)を施し
、捨コンクリート(9)を打設する。(第7図参照)次
いで前記型枠パネル(Bの金属製鋼状片(6)にポリエ
チレンフィルムOIの如き合成樹脂フィルムを張設する
。(第8図参照)
次いで前記地盤囚における掘削孔(1)の外側に固定用
の木杭(11)を貫入し、前記型枠(印を鉄線0りで固
定し、前記掘削孔(1)における型枠パネル(B外側の
余堀り部側に掘削土砂等を埋戻し、スラブの敷砂利部ま
で転圧し、スラブの敷砂利を行なう1図中04は理戻し
土砂を示す、(第9図参照)次いで基礎と地中梁の捨コ
ンクリート(9)部に墨出しを行ったのち、基礎及び地
中梁の各鉄筋05)Of9を配筋し、続いてスラブ補強
筋q力を配筋する。Next, a cracking method (8) is applied to the bottom of the excavation hole (1), and concrete concrete (9) is poured. (See Figure 7) Next, a synthetic resin film such as polyethylene film OI is stretched over the metal steel piece (6) of the form panel (B). (See Figure 8) Next, the excavated hole (1 ), insert a wooden stake (11) for fixing into the outside of the formwork (marked with iron wire), and drill the formwork panel in the excavation hole (1) on the side of the over-excavation part outside B. Backfilling with earth and sand, compacting down to the gravel part of the slab, and laying gravel on the slab. 04 in Figure 1 shows the earth and sand that has been reclaimed (see Figure 9). Next, concrete for the foundation and underground beams (9) After marking out the sections, each reinforcing bar 05)Of9 of the foundation and underground beam is placed, and then the slab reinforcement q force is placed.
(第10図参照)しかるのち基礎(0、地中梁0及びス
ラブDのコンクリートOmを同時に打設する。(See Figure 10) Then, the foundation (0, underground beam 0, and concrete Om of slab D are poured simultaneously).
(第11図参照)
(発明の効果)
本発明によれば前記したように、基礎地盤を、同地盤に
構築される基礎構築物の形状よりやや大きめに所定深度
まで掘削し、同掘削孔内に前記基礎構築物のコンクリー
ト打設用型枠パネルを組立てることによって、余堀り部
分を小さくすることができ、基礎構築物のコンクリート
打設前に土砂等で埋戻すことができ、スラブの土間まで
同時に転圧することができ、掘削土量を大幅に削減しう
るものである。更に基礎構築物の鉄筋の配筋と、スラブ
補強筋の配筋を同時に行なうことができ、前記基礎構築
物とスラブのコンクリートを一体に打設することができ
る。(See Figure 11) (Effects of the Invention) According to the present invention, as described above, the foundation ground is excavated to a predetermined depth slightly larger than the shape of the foundation structure to be constructed on the same ground, and By assembling the formwork panels for concrete pouring of the foundation structure, the over-excavation area can be made smaller, and it can be backfilled with earth and sand before concrete pouring of the foundation structure, and it can be rolled to the floor of the slab at the same time. It is possible to significantly reduce the amount of excavated soil. Further, the reinforcing bars of the foundation structure and the slab reinforcing bars can be placed at the same time, and the concrete of the foundation structure and the slab can be cast together.
このように本発明の方法によれば、型枠を埋殺し型とす
ることによって、型枠組立時の余堀り量を最小限として
掘削土量を削減し、型枠組立作業を簡素化し、省力化を
図り、工期を短縮し、工費をm減しうるちのである。As described above, according to the method of the present invention, by making the formwork a buried type, the amount of over-excavation during formwork assembly is minimized, reducing the amount of excavated soil, simplifying the formwork assembly work, It saves labor, shortens the construction period, and reduces construction costs by m.
請求項2の発明は、前記型枠パネルを鉄骨フレームに金
属製網状片を張設して構成したことによって軽量化を図
り、型枠自体のコストを節減しうるちのである。更に前
記フレームからは脚片が垂設されているので、同脚片を
前記掘削孔の底部に貫入することによって、型枠パネル
の組立作業が簡素化される。According to the second aspect of the present invention, the formwork panel is constructed by extending a metal mesh piece to a steel frame, thereby reducing the weight of the formwork panel and reducing the cost of the formwork itself. Furthermore, since the leg pieces are suspended from the frame, the work of assembling the form panel is simplified by penetrating the leg piece into the bottom of the excavation hole.
更にまた同型枠パネルの外側面に合成樹脂フィルムを張
設することによって、打設コンクリートの漏出が防止さ
れるとともに、同コンクリートの養生が行なわれるもの
である。Furthermore, by placing a synthetic resin film on the outer surface of the form panel, leakage of poured concrete is prevented and the concrete is cured.
請求項3の発明は前記掘削孔の周辺に型枠パネル固定用
の杭を貫入し、同杭と前記型枠パネルとを線条で緊結す
ることによって、型枠パネルを所定位置に固定すること
ができるものである。The invention according to claim 3 is characterized in that the formwork panel is fixed in a predetermined position by penetrating the formwork panel fixing stake around the excavation hole and tightening the formwork panel with the pile with a wire. It is something that can be done.
第1図は本発明の施工方法によって構築された基礎構築
物及びスラブの縦断面図、第2図及び第3図はその平面
図、第4図は第2図の部分■の拡大図、第5図乃至第1
1図は本発明の施工方法の一実施例の工程を示す縦断面
図、第12図は型枠パネルの正面図、第13図はその側
面図である。
囚・・−基礎地盤、 (a・・−型枠パネル、(0
−・・基礎、 0・−・地中梁、D・−・スラ
ブ、 (1)・・・ 掘削孔、(2)(3)−m
−水平枠、 (4)・−両端垂直枠、(4a)・・
・脚片、 (5)−・−中間垂直枠、(5a)−
・・脚片、 (6)−・・金属製網状片、01I
)・・・ポリエチレンフィルム、θI)−・−木杭、
Q2)−・−鉄線、0■−・余堀り部、
09−・−基礎鉄筋、0[il・・−地中梁鉄筋、
0′I)−・・スラブ補強筋、0ff)・・・コンクリ
ート。
代理人 弁理士 岡 本 重 文
外2名Fig. 1 is a vertical cross-sectional view of the foundation structure and slab constructed by the construction method of the present invention, Figs. 2 and 3 are its plan views, Fig. 4 is an enlarged view of part ① in Fig. 2, and Fig. 5 Figure to 1st
FIG. 1 is a longitudinal sectional view showing the steps of an embodiment of the construction method of the present invention, FIG. 12 is a front view of a formwork panel, and FIG. 13 is a side view thereof. prisoner...-foundation ground, (a...-formwork panel, (0
-... Foundation, 0... Underground beam, D... Slab, (1)... Excavation hole, (2) (3) -m
-Horizontal frame, (4)・-Vertical frame at both ends, (4a)...
・Leg piece, (5)--Middle vertical frame, (5a)-
...Leg piece, (6)--Metal mesh piece, 01I
)...polyethylene film, θI)--wooden stake,
Q2)--iron wire, 0■--extra hori section,
09--Foundation reinforcing bars, 0[il...-Underground beam reinforcing bars,
0'I)--Slab reinforcement, 0ff)--Concrete. Agent: Patent attorney: Shige Okamoto, 2 other people
Claims (3)
状よりやや大きめに所定深度まで掘削し、次いで同掘削
孔内に前記基礎構築物のコンクリート打設用型枠パネル
を組立て、同型枠パネル外側の余堀り部分を埋戻し、次
いで前記掘削孔に基礎構築物の鉄筋を配筋するとともに
スラブ補強筋を配筋し、次いで前記基礎構築物及びスラ
ブのコンクリート打設を同時に行なうことを特徴とする
基礎構築物の施工方法。(1) The foundation ground is excavated to a predetermined depth slightly larger than the shape of the foundation structure to be constructed on the same ground, and then a formwork panel for pouring concrete for the foundation structure is assembled in the same excavation hole, and the same formwork panel is The method is characterized in that the outer excavated portion is backfilled, then reinforcing bars for the foundation structure are placed in the excavated hole, and slab reinforcing bars are placed in the excavated hole, and then concrete is placed for the foundation structure and the slab at the same time. Construction methods for foundation structures.
張設して構成され、前記フレームより垂設された脚片を
前記掘削孔の底部地盤に貫入して同掘削孔に前記型枠パ
ネルを建て込み、同パネルの外側面に合成樹脂フィルム
を張設する請求項1記載の基礎構築物の施工方法。(2) The formwork panel is composed of a metal mesh piece stretched over a steel frame, and the leg pieces hanging from the frame are inserted into the bottom ground of the excavation hole to insert the formwork into the excavation hole. 2. The method for constructing a foundation structure according to claim 1, wherein the panel is erected and a synthetic resin film is stretched on the outer surface of the panel.
入し、同杭と前記型枠パネルとを線条で緊結する請求項
1記載の基礎構築物の施工方法。(3) The method for constructing a foundation structure according to claim 1, wherein a formwork panel fixing pile is penetrated into the ground around the excavation hole, and the formwork panel is fastened to the formwork panel with a wire.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6607789A JPH02248527A (en) | 1989-03-20 | 1989-03-20 | Constructing foundation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6607789A JPH02248527A (en) | 1989-03-20 | 1989-03-20 | Constructing foundation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH02248527A true JPH02248527A (en) | 1990-10-04 |
Family
ID=13305425
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6607789A Pending JPH02248527A (en) | 1989-03-20 | 1989-03-20 | Constructing foundation structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH02248527A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04221129A (en) * | 1990-12-19 | 1992-08-11 | Okumura Corp | Foundation forming method for building |
JPH0626060A (en) * | 1992-04-01 | 1994-02-01 | Shizuoka Resuko House Kk | Reinforced base using geothermal energy |
JP2015038265A (en) * | 2011-11-30 | 2015-02-26 | 高伸建設株式会社 | Construction method for foundation |
-
1989
- 1989-03-20 JP JP6607789A patent/JPH02248527A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04221129A (en) * | 1990-12-19 | 1992-08-11 | Okumura Corp | Foundation forming method for building |
JPH0626060A (en) * | 1992-04-01 | 1994-02-01 | Shizuoka Resuko House Kk | Reinforced base using geothermal energy |
JP2015038265A (en) * | 2011-11-30 | 2015-02-26 | 高伸建設株式会社 | Construction method for foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001241053A (en) | Method for constructing underground structure | |
JP2000008394A (en) | Construction method for underground structure such as underground pit for installation of parking lot | |
KR20210154337A (en) | Construction Method of Underground Structures | |
JP2000265484A (en) | CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
US5806262A (en) | Post and method of emplacing a post | |
JP3107716B2 (en) | Soil retaining wall | |
JP4083334B2 (en) | Underground structure having arch roof and method for constructing the same | |
KR100376590B1 (en) | Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts | |
JP2000144769A (en) | Method of landslide protection work for preparing housing lot | |
JPH02248527A (en) | Constructing foundation structure | |
JPH0684690B2 (en) | Building basement extension method | |
JP3390081B2 (en) | How to build an underground parking | |
JP3790310B2 (en) | Construction method of the building by the prior construction of steel frame | |
JP2641182B2 (en) | Slope stabilization method and slope expansion method | |
JPS63280153A (en) | Underground inverted lining method | |
JP2001164559A (en) | Construction method of continuous underground wall guide wall making use of l-type precast member | |
JPH10299003A (en) | Foundation work using precast concrete member | |
JP3588523B2 (en) | Construction method of underground storage | |
JPH0477764B2 (en) | ||
JPH04366229A (en) | Temporary corresponding standard used for method of reverse driving construction | |
JPH0726569A (en) | Pile foundation construction method for structure exposed to partial earth pressure | |
JPH0517955A (en) | Execution method for direct foundation and form panel for direct foundation | |
JP2004285613A (en) | Construction method for building foundation | |
KR910003748B1 (en) | Building method for underground structures |