JP3095376B2 - Construction method of building foundation - Google Patents
Construction method of building foundationInfo
- Publication number
- JP3095376B2 JP3095376B2 JP09348841A JP34884197A JP3095376B2 JP 3095376 B2 JP3095376 B2 JP 3095376B2 JP 09348841 A JP09348841 A JP 09348841A JP 34884197 A JP34884197 A JP 34884197A JP 3095376 B2 JP3095376 B2 JP 3095376B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- pillar
- base plate
- tip
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Foundations (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は建屋の構造部分、い
わゆる建屋基礎の工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method of a structural part of a building, that is, a so-called building foundation.
【0002】[0002]
【従来の技術】建屋の構造部分、いわゆる基礎は建屋を
構成する柱をフーチングで支えて成る。フーチングとは
基礎の広がり部分を言い、独立基礎、一つの基礎で二本
以上の柱を支える複合基礎、フーチングを連続して形成
する布基礎等がある。2. Description of the Related Art A structural part of a building, a so-called foundation, is formed by supporting columns constituting the building with footings. Footing refers to a spread portion of a foundation, and includes an independent foundation, a composite foundation that supports two or more pillars with one foundation, and a cloth foundation that continuously forms a footing.
【0003】[0003]
【発明が解決しようとする課題】建屋構造部である基礎
について従来の独立基礎を例にとって説明すると図2に
示すように、柱1を支持する杭36を立設する地盤3を
所定深さまで掘削して所定形状の孔部を形成した後、孔
部に型枠を嵌め込みコンクリート37を打設して数日間
の養生期間を経てコンクリートを硬化させフーチング2
を形成する。又、水平材である基礎梁4で各基礎を結び
基礎の不等沈下を防ぐと共に、建屋全体の剛性を高める
のである。ところが従来の基礎工事には以下のような問
題点がある。 1、地盤を深く掘削する必要があり、大量の残土が排出
され産業廃棄物でもある残土を適切に処理する手間及び
費用を要する。 2、杭の立設場所の周辺を広範囲にわたって深く掘削す
るため振動、騒音、土ぼこりが生じ、工事現場周辺に迷
惑をかける等、環境上問題がある。 3、コンクリート打設の手間、費用がかかる上、養生に
日数が係るため工期が長くなる。 4、立設する柱の周囲を広範囲に掘削してフーチングを
形成する必要があり、過密を余儀なくされている都市空
間や狭い敷地内での作業が困難である。図3に示す仮装
線5で囲まれた敷地が本発明に係る工法に必要な面積で
あるが、従来の基礎工法に必要な面積は仮装線41で示
されるものであり、広い面積が必要となることが明らか
である。The foundation as a building structure will be described with reference to a conventional independent foundation as an example. As shown in FIG. 2, a ground 3 on which a pile 36 for supporting a column 1 is erected is excavated to a predetermined depth. After a hole having a predetermined shape is formed, a concrete frame is inserted into the hole, and concrete 37 is poured into the hole. After a curing period of several days, the concrete is hardened and the footing 2 is formed.
To form In addition, the foundations are connected by the foundation beams 4 which are horizontal members, thereby preventing uneven settlement of the foundations and increasing the rigidity of the whole building. However, conventional foundation works have the following problems. 1. It is necessary to excavate the ground deeply, and it takes a lot of time and effort to properly treat the residual soil, which is a large amount of residual soil and is also industrial waste. 2. Excavation of a large area around the erected place of piles causes environmental problems, such as vibration, noise, and dust accumulation, which inconvenience the construction site. 3. It takes time and money to cast concrete, and it takes a long time to cure, so the construction period is long. 4. It is necessary to form a footing by excavating a wide area around the pillar to be erected, and it is difficult to work in an urban space that is overcrowded or in a narrow site. The site surrounded by the temporary dressing line 5 shown in FIG. 3 is the area required for the construction method according to the present invention, but the area required for the conventional foundation method is indicated by the temporary dressing line 41 and requires a large area. It is clear that
【0004】そこで本発明では都市部や建屋隣接地域等
の狭い敷地でも短期間で容易に杭の立設が可能であると
共に、残土の量も少なくクリアで静かな、環境上でも優
れた、鋼管杭等を使用する剛強な建屋の基礎工法を提供
することを目的とする。Therefore, according to the present invention, it is possible to easily set up piles in a short period of time even in a narrow site such as an urban area or an area adjacent to a building. An object of the present invention is to provide a foundation method for a rigid building using piles and the like.
【0005】[0005]
【課題を解決するための手段】鋼管杭を沈設後、適当長
さで切断し、中央にボルトを有する杭頭キャップを杭頭
に溶接し、その上に略正方形の杭側ベースプレートを溶
接する。この上に柱付ベースプレートを載置すると共
に、両ベースプレート間に挟み板を挟み込んでボルト及
び挟み板の枚数で柱の高さ及び水平レベルを調整しなが
ら、穿設したアンカー穴に高力ボルトを締結して鋼管杭
上に柱を立設するのである。After the steel pipe pile is laid, it is cut into a suitable length, a pile head cap having a bolt in the center is welded to the pile head, and a substantially square pile side base plate is welded thereon. Place the base plate with pillars on top of this, insert the sandwiching plate between both base plates, adjust the height and horizontal level of the pillar with the number of bolts and sandwiching plates, and insert high-strength bolts into the anchor holes drilled. It is fastened and a pillar is erected on the steel pipe pile.
【0006】また、隣接する二本以上の鋼管杭にそれぞ
れ杭頭キャップと杭側ベースプレートを取り付け、これ
らの杭にわたる面積を有する柱側ベースプレートを用い
て隣接する二本以上の鋼管杭を連結して中央に柱を立設
し、リブ板を取り付けることで二本以上の鋼管杭により
支えられる、より強固な建屋基礎を構成するのである。Further, a pile head cap and a pile base plate are attached to two or more adjacent steel pipe piles, and two or more adjacent steel pipe piles are connected by using a column base plate having an area extending over these piles. The pillars are erected in the center and the ribs are attached to form a stronger building foundation supported by two or more steel pipe piles.
【0007】更に、鋼管杭の代わりに鉄筋コンクリート
杭(以下「PC杭」という。)を沈設後、PC杭の内径
より小さな径を有する鋼管杭を継ぎ杭としてPC杭の端
板に溶着後、高さ調整を行うための継ぎ杭としての鋼管
杭の先端に、中央にボルトを嵌合した杭頭キャップを嵌
合すると共に、通孔を有する二分割された柱側ベースプ
レートで継ぎ杭先端を挟み込んだ後、継ぎ杭先端に溶着
し、柱を立設した柱側ベースプレートをボルト上に載置
し、通孔に合わせて柱側ベースプレートに穿設したアン
カー孔と通孔に仮ボルトを挿通し、両ベースプレート間
に挟み板を挟入して柱の位置決めを行った後、溝を切欠
した挟みプレートで仮ボルトを挟み込み、仮ボルトを抜
きとった後に高力ボルトで両ベースプレートを締結して
PC杭上に柱を立設した建屋基礎を構築するのであり、
また、隣接する二本以上のPC杭にそれぞれ端板を取り
付け、PC杭の内径より小さな径を有する鋼管杭を継ぎ
杭として端板に溶着し、中央にボルトを高さ調整自在に
取り付けた杭頭キャップを継ぎ杭の先端に溶着すると共
に、これらのPC杭にわたる面積を有する柱側ベースプ
レートを取り付けることにより隣接する二本以上のPC
杭を連結して中央に柱を立設し、柱にリブ板を取り付け
ることで二本以上のPC杭により支えられる、より強固
な建屋基礎を構築するのである。Further, after a reinforced concrete pile (hereinafter referred to as a "PC pile") is laid instead of a steel pipe pile, a steel pipe pile having a diameter smaller than the inner diameter of the PC pile is welded to an end plate of the PC pile as a joint pile. A pile head cap with a bolt fitted in the center was fitted to the tip of a steel pipe pile as a joining pile for performing the adjustment, and the tip of the joining pile was sandwiched between two divided column-side base plates with through holes. After that, welded to the end of the joint pile, the column base plate with the columns erected was placed on the bolts, and the temporary bolts were inserted through the anchor holes and the through holes drilled in the column side base plate in accordance with the through holes. After inserting the sandwiching plate between the base plates and positioning the pillars, insert the temporary bolts with the sandwiching plates with grooves cut out, remove the temporary bolts, fasten both base plates with high-strength bolts, and place them on the PC pile Standing pillar And of building a the building foundation,
An end plate is attached to two or more adjacent PC piles, and a steel pipe pile having a diameter smaller than the inner diameter of the PC pile is welded to the end plate as a joint pile, and a bolt is attached at the center so that the height can be adjusted freely. The head cap is welded to the tip of the joint pile and two or more adjacent PCs are attached by attaching a column base plate having an area over these PC piles.
By connecting the piles and erecting a pillar in the center and attaching a rib plate to the pillar, a stronger building foundation supported by two or more PC piles is constructed.
【0008】以下、本発明がどのように作用して上記課
題を解決するかを説明する。Hereinafter, how the present invention works to solve the above problems will be described.
【0009】まず、杭本体の下端に掘削刃を取り付ける
と共に下端部外周面に螺旋状の羽根を取り付けた鋼管杭
を地盤にねじり込み沈設した後、あらかじめ決められた
長さで鋼管杭先端を切断した後、後の作業を容易にする
ために当該杭の周囲を20cm程度部分堀りする。First, a steel pipe pile having a drill blade attached to the lower end of the pile body and a spiral blade attached to the outer peripheral surface of the lower end is screwed into the ground and laid, and then the tip of the steel pipe pile is cut at a predetermined length. After that, the periphery of the pile is partially dug about 20 cm in order to facilitate the subsequent work.
【0010】次に中央にボルトを取り付けた杭頭キャッ
プを杭先端に溶着し、二分割された杭側ベースプレート
で杭頭を挟み込み、ボルト上に柱を立設した柱側ベース
プレートを載置する。両ベースプレートに穿設した孔に
仮ボルトを挿通し、両ベースプレート間に挟み込んだ所
望枚数の挟み板で柱の水平レベルの調整を行うと共に、
ボルトで柱高さの調整を行った後、挟み板の代わりに挟
みプレートを挟み込み、仮ボルト抜き取り後、高力ボル
トで杭側ベースプレートと柱側ベースプレートを締結す
るのである。Next, a pile head cap with a bolt attached at the center is welded to the tip of the pile, the pile head is sandwiched between the two divided pile side base plates, and a pillar side base plate having pillars erected on the bolts is placed. Insert the temporary bolts into the holes drilled in both base plates, and adjust the horizontal level of the pillars with the desired number of sandwich plates sandwiched between both base plates,
After adjusting the height of the column with bolts, the plate is inserted instead of the plate, and after removing the temporary bolts, the pile base plate and the column base plate are fastened with high strength bolts.
【0011】又、沈設した二本以上の鋼管杭上に、二本
以上の鋼管杭間にわたる面積を有する柱側ベースプレー
トを載置し、リブ板で補強をするのである。Further, a column base plate having an area extending between two or more steel pipe piles is placed on the two or more steel pipe piles laid down, and reinforced with a rib plate.
【0012】鋼管杭の代わりに先端にスチールの端板を
取り付けたPC杭を地盤に沈設し、鋼管杭を継ぎ杭とし
て端板に溶接し、上述のとおり鋼管杭に取り付けた杭側
ベースプレートに柱側ベースプレートを取り付けてPC
杭上に柱を立設するのである。In place of the steel pipe pile, a PC pile with a steel end plate attached to the tip is sunk on the ground, the steel pipe pile is welded to the end plate as a joint pile, and the pillar is attached to the pile base plate attached to the steel pipe pile as described above. PC with side base plate attached
Pillars are erected on piles.
【0013】以下、本発明がどのように作用して課題を
解決するかを説明する。Hereinafter, how the present invention works to solve the problem will be described.
【0014】本発明に使用する当該杭の先端には掘削刃
が取り付けられているため地盤に食い込み易く、更に鋼
管杭を回転させ、螺旋状に取り付けられた羽根の回転食
い込み力によってが土中を容易に推進すると共に土砂を
杭の側面に押圧するためほとんど残土が排出されず、従
来の基礎工事に比し騒音、土ぼこりも生じない。Since the excavation blade is attached to the tip of the pile used in the present invention, it is easy to bite into the ground, and furthermore, the steel pipe pile is rotated, and the rotary penetrating force of the spirally mounted blade causes the pile to penetrate the soil. Since it is easily propelled and the earth and sand is pressed against the side of the pile, almost no residual soil is discharged, and noise and dust are not generated as compared with the conventional foundation work.
【0015】また、鋼管杭の周囲を部分堀するが作業が
終了後は排出土で埋設するため、残土がほとんど排出さ
れない。また、鋼管杭を沈設後すぐに柱の立設工程に進
めるため工期の短縮を図ることができる。[0015] In addition, the periphery of the steel pipe pile is partially dug, but after the work is completed, the pile is buried with the discharged soil, so that the residual soil is hardly discharged. In addition, the construction period can be shortened because the steel pipe piles are immediately laid down and the process proceeds to the pillar erection process.
【0016】又、鋼管杭自体が強固であるため、従来の
基礎に必要とされていた基礎梁が不要となり、費用及び
工事の手間も省けるのである。Further, since the steel pipe pile itself is strong, the foundation beam required for the conventional foundation is not required, and the cost and labor for the construction can be reduced.
【0017】さらに、基礎杭の周囲を大きく掘削しない
ため狭い敷地内又は敷地境界近くであっても杭の沈設及
び柱の立設が可能である。Further, since the periphery of the foundation pile is not greatly excavated, the pile can be submerged and the pillar can be erected even in a narrow site or near the site boundary.
【0018】[0018]
【発明の実施の形態】以下、この発明の好適な実施例に
ついて添付図面を参照しながら詳細に説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings.
【0019】図5〜図10は鋼管杭を使用した基礎工法
の手順を示す工程図である。FIGS. 5 to 10 are process diagrams showing the procedure of the foundation method using steel pipe piles.
【0020】図5は中央部に切断レベル9を表示した鋼
管杭6を地盤8に沈設した様子を示す説明図である。鋼
管杭6の下端6aは平坦ではなく図1に示すように切削
刃10、先端部の外周面には螺旋状の羽根11が取り付
けられている。地盤8上に鋼管杭6を立設し、駆動装置
によって鋼管杭6をねじ込むように回転させて地中に押
圧し、下端の切削刃10で掘削軟化した土砂を羽根11
が杭6の側面に押圧しながら進むため残土をほとんど排
出せずに所定場所に杭6を埋設できるのである。FIG. 5 is an explanatory view showing a state in which the steel pipe pile 6 indicating the cutting level 9 at the center is laid down on the ground 8. The lower end 6a of the steel pipe pile 6 is not flat, but has a cutting blade 10 as shown in FIG. The steel pipe pile 6 is erected on the ground 8, the steel pipe pile 6 is rotated by a driving device so as to be screwed in, pressed into the ground, and the excavated and softened earth and sand excavated by the cutting blade 10 at the lower end.
Can be buried at a predetermined place with almost no remaining soil being discharged because the pile advances while pressing against the side surface of the pile 6.
【0021】次に杭6の周囲を地下20cm程度掘る。
これは以降の作業を容易にするためであって、作業終了
後は排出土で当該孔を埋設する。Next, the pile 6 is dug about 20 cm underground.
This is to facilitate the subsequent work, and after the work is completed, the hole is buried with the discharged soil.
【0022】杭6を沈設後に切断レベル出し作業を行い
切断レベル9で杭6の先端を切断、図6に示すように中
央にボルトを嵌合した杭頭キャップ12を杭6の先端に
嵌合する。その後杭頭キャップ12と杭6とを溶接によ
り固定する。After the pile 6 is laid, a cutting level setting operation is performed and the tip of the pile 6 is cut at the cutting level 9. A pile head cap 12 with a bolt fitted at the center is fitted to the tip of the pile 6 as shown in FIG. I do. Thereafter, the pile head cap 12 and the pile 6 are fixed by welding.
【0023】図7は杭6の一部断面図である。杭6の内
周面に鉄環15の底面を溶接で取り付けて杭頭キャップ
12を受承し、杭6の外周面には裏当金16を溶接で取
り付ける。FIG. 7 is a partial sectional view of the pile 6. The bottom surface of the iron ring 15 is attached to the inner peripheral surface of the pile 6 by welding to receive the pile head cap 12, and the backing metal 16 is attached to the outer peripheral surface of the pile 6 by welding.
【0024】長辺の中央部を半円形に切欠した2枚の長
方形の杭側ベースプレート17のそれぞれの切欠部17
aを対向させて杭6の先端部を挟み込み、杭外周面に溶
着した裏当金16で受承した後、杭側ベースプレート1
7の裏面と裏当金16を溶着する。Each of the notches 17 of the two rectangular pile-side base plates 17 in which the center of the long side is cut off in a semicircular shape.
a, the tip of the pile 6 is sandwiched between the piles 6 and received by the backing metal 16 welded to the outer peripheral surface of the pile 6.
7 and the backing metal 16 are welded.
【0025】杭側ベースプレート17の長辺の両端部に
はあらかじめアンカーボルトの通孔20が穿設されてお
り、杭頭キャップ中央部に突設したボルト13上に、柱
21を溶接により立設した柱側ベースプレート18を載
置する。杭側ベースプレート17の通孔20の位置に合
わせて柱側ベースプレート18のアンカー穴19の位置
決めを行い柱側ベースプレート18の四隅にアンカー穴
19を穿設後、杭側ベースプレート17の通孔20と柱
側ベースプレート18のアンカー穴19とをそれぞれ合
わせ仮ボルト23を挿通して取り付ける。両方のベース
プレートの位置ずれ防止のためである。At both ends of the long side of the pile side base plate 17, through holes 20 for anchor bolts are drilled in advance, and columns 21 are erected by welding on bolts 13 projecting from the center of the pile cap. The pillar-side base plate 18 is placed. The anchor holes 19 of the pillar side base plate 18 are positioned in accordance with the positions of the through holes 20 of the pile side base plate 17, and the anchor holes 19 are formed at the four corners of the pillar side base plate 18. The anchor holes 19 of the side base plate 18 are aligned with each other, and the temporary bolts 23 are inserted and attached. This is to prevent displacement of both base plates.
【0026】両ベースプレート17ー18間に薄い鉄板
等からなる挟み板22を適当枚数重ねて挟入し、柱付ベ
ースプレート18のぐらつきを防止しながらボルトを回
転させてはしらの高さを調整すると共に、挟み板22の
枚数によって柱の水平レベルの調整を行う。An appropriate number of sandwiching plates 22 made of a thin iron plate or the like are sandwiched between the two base plates 17-18, and the bolts are rotated while the wobble of the pillared base plate 18 is prevented to adjust the height of the shims. The horizontal level of the pillar is adjusted by the number of the sandwiching plates 22.
【0027】両ベースプレートの間隔、即ち柱21の取
り付け水平位置及び高さが定まると略正方形であって一
角から中心に向け溝38aが切欠されている挟みプレー
ト38の溝38aで仮ボルト23を挟み込むように両ベ
ースプレート間の四隅に挟入する。仮ボルト23を抜い
た後に高力ボルトから成るアンカーボルト24をアンカ
ー穴19及び通孔20に挿通して杭側ベースプレート1
7及び柱側ベースプレート18を締結するのである。When the distance between the two base plates, that is, the mounting horizontal position and height of the column 21, is determined, the temporary bolt 23 is sandwiched between the grooves 38a of the sandwiching plate 38 which is substantially square and has a groove 38a cut from one corner toward the center. Between the base plates at the four corners. After removing the temporary bolts 23, the anchor bolts 24 made of high-strength bolts are inserted into the anchor holes 19 and the through holes 20, and the pile-side base plate 1 is removed.
7 and the column-side base plate 18 are fastened.
【0028】次に請求項2記載の隣接する二本以上の鋼
管杭の上に柱を立設する工法について説明する。Next, a method of erecting columns on two or more adjacent steel pipe piles according to the second aspect will be described.
【0029】図11が実施例の正面図、図12が同、平
面図である。図11のように二本の鋼管杭40ー40を
前述の工法で地盤に沈設し、中央にボルトを突設した杭
頭キャップをそれぞれの杭先端に嵌合、溶着する。各杭
頭に二分割された杭側ベースプレート25を溶接し、中
央に柱26を溶接で立設した、杭40ー40間にわたる
面積を有する長方形の柱側ベースプレート27をボルト
上に載置する。杭側ベースプレート25に穿設した通孔
28に合わせて柱側ベースプレート27にアンカー穴2
9を8ケ所穿設し、当該アンカー穴29と通孔28を合
わせて仮ボルトを挿通し、両ベースプレート間に挟み板
を挟入する。ボルトで柱26の高さ調整を行うと共に、
挟み板の枚数で柱の水平レベルの調整を行い、柱26の
立設位置が定まると、挟みプレート30の溝に仮ボルト
が挿通するように両ベースプレート間に挟みプレートを
挟み込んだ後挟み板を取り除き、続いて仮ボルトを高力
ボルトから成るアンカーボルト31と取り替えでアンカ
ー穴に挿通し、杭側ベースプレート25及び柱側ベース
プレート27を締結するのである。FIG. 11 is a front view of the embodiment, and FIG. 12 is a plan view of the embodiment. As shown in FIG. 11, two steel pipe piles 40-40 are submerged in the ground by the above-described method, and a pile head cap having a bolt protruded at the center is fitted and welded to the tip of each pile. A two-part pile side base plate 25 is welded to each pile head, and a pillar 26 is erected in the center by welding. A rectangular pillar side base plate 27 having an area between piles 40 and 40 is placed on the bolts. The anchor holes 2 are formed in the pillar side base plate 27 in accordance with the through holes 28 formed in the pile side base plate 25.
Eight holes 9 are drilled, temporary bolts are inserted by aligning the anchor holes 29 and the through holes 28, and a sandwiching plate is inserted between both base plates. While adjusting the height of the pillar 26 with bolts,
The horizontal level of the pillar is adjusted by the number of the sandwiching plates, and when the standing position of the pillar 26 is determined, the sandwiching plate is sandwiched between the base plates so that the temporary bolt is inserted into the groove of the sandwiching plate 30, and then the sandwiching plate is inserted. Then, the temporary bolts are replaced with anchor bolts 31 made of high-strength bolts and inserted into the anchor holes to fasten the pile base plate 25 and the column base plate 27.
【0030】柱26をより剛強に立設するために、2以
上のリブ板32の底面を柱側ベースプレート27の表面
に、リブ板側面を柱26の側面に溶接あるいはボルト等
で固着するのである。In order to erect the column 26 more rigidly, the bottom surfaces of the two or more rib plates 32 are fixed to the surface of the column base plate 27 and the side surfaces of the rib plate 32 are fixed to the side surfaces of the column 26 by welding or bolts. .
【0032】最後に請求項3記載のPC杭を使用した建
屋の基礎工法について説明する。Finally, a foundation construction method using a PC pile according to claim 3 will be described.
【0033】図13aは杭頭にスチールからなる端板3
3を取り付けたPC杭34の斜視図である。当該PC杭
34を前述の工法により地盤に沈設し、高さ調節を行う
継ぎ杭となる鋼管35を図13bに示すように端板33
に溶接により取り付けるのである。FIG. 13a shows an end plate 3 made of steel at the pile head.
FIG. 3 is a perspective view of a PC pile 34 to which the third PC 3 is attached. The PC pile 34 is sunk on the ground by the above-described method, and the steel pipe 35 serving as a joint pile for adjusting the height is connected to the end plate 33 as shown in FIG.
It is attached by welding.
【0034】以降、同様にして当該鋼管35にボルトを
突設した杭頭キャップを嵌合して杭側ベースプレートを
取り付け、柱側ベースプレートをボルト上に載置し、両
ベースプレート間に挟み板を挟入して、柱の高さ及び水
平レベルを確認後、挟みプレートを両ベースプレート間
であって、仮ボルトの挿通位置に挟み込み、仮ボルトを
高力ボルトに取り替えて、柱側ベースプレートと杭側プ
レートを締結して、PC杭上に柱を立設するのである。Thereafter, similarly, a pile head cap with a bolt protruding is fitted to the steel pipe 35, a pile base plate is attached, the column base plate is placed on the bolt, and a sandwich plate is sandwiched between the base plates. After checking the height and horizontal level of the column, insert the pinch plate between the two base plates at the position where the temporary bolts are inserted, replace the temporary bolts with high-strength bolts, and replace the column base plate and the pile side plate. And a pillar is erected on the PC pile.
【0035】もちろん、隣接する二本以上の当該PC杭
にわたる柱側ベースプレートを取り付けることにより請
求項2記載の二本以上の基礎杭により支承される剛強な
基礎を有する柱を立設することも可能である。Of course, it is also possible to erect a column having a rigid foundation supported by two or more foundation piles according to claim 2 by attaching a column-side base plate extending over two or more adjacent PC piles. It is.
【0036】[0036]
【発明の効果】1、従来の建屋基礎工事に伴う大量の残
土の排出や騒音、埃等が生じず、環境面で優れている。 2、図3の二つの仮装線は内側が本発明による工法に必
要な面積、外側が従来の基礎工事に必要な面積を示して
いる。これから明らかなように、本願の工法によると狭
い場所や隣接地域での建屋基礎工事が可能となる。 3、土台となる鋼管杭の沈設後直ちに柱を立設すること
ができ、従来の建屋基礎工事に必要であった掘削、型枠
の嵌め込み作業がなくなる上に、コンクリート等の養生
期間が不要となるため、工事の手間及び工期が著しく低
減できる。 4、ベースプレートの形状や大きさを変えることで隣接
する二本以上の杭からなる剛強な基礎を形成することが
できる。 5、本発明の工法は鋼管杭又はPC杭のみならず、他の
素材からなる杭にも応用が可能である。The present invention is excellent in terms of environment because it does not generate a large amount of residual soil, noise, dust, etc. due to the conventional building foundation work. 2, the inside of the two temporary wires shown in FIG. 3 indicates the area required for the construction method according to the present invention, and the outside indicates the area required for the conventional foundation work. As is clear from this, according to the construction method of the present application, it is possible to perform building foundation work in a narrow place or an adjacent area. 3. Pillars can be erected immediately after the foundation of steel pipe piles is laid down, eliminating the need for excavation and formwork fitting work required for conventional building foundation work, and eliminating the need for curing time for concrete etc. Therefore, labor and time required for construction can be significantly reduced. 4. By changing the shape and size of the base plate, a rigid foundation consisting of two or more adjacent piles can be formed. 5. The method of the present invention can be applied not only to steel pipe piles or PC piles but also to piles made of other materials.
【図1】 本発明に係る工法で建設した建屋の正面図。FIG. 1 is a front view of a building constructed by a construction method according to the present invention.
【図2】 従来の工法で建設した建屋の正面図。FIG. 2 is a front view of a building constructed by a conventional method.
【図3】 本発明に係る工法で立設した柱の平面図。FIG. 3 is a plan view of a pillar erected by the method according to the present invention.
【図4】 従来の工法で立設した柱の平面図。FIG. 4 is a plan view of a pillar erected by a conventional method.
【図5】 本発明に係る鋼管杭を地盤に沈設した様子を
示す斜視図。FIG. 5 is a perspective view showing a state where the steel pipe pile according to the present invention is laid in the ground.
【図6】 切断した鋼管杭に杭頭キャップを嵌合した様
子を示す斜視図。FIG. 6 is a perspective view showing a state in which a pile head cap is fitted to the cut steel pipe pile.
【図7】 同、一部断面図。FIG. 7 is a partial sectional view of the same.
【図8】 鋼管杭に杭側プレートを溶接した様子を示す
斜視図。FIG. 8 is a perspective view showing a state where a pile side plate is welded to a steel pipe pile.
【図9】 鋼管杭に柱側プレートを載置した様子を示す
斜視図。FIG. 9 is a perspective view showing a state where a column side plate is placed on a steel pipe pile.
【図10】 鋼管杭と柱をアンカーボルトで締結した様
子を示す斜視図。FIG. 10 is a perspective view showing a state in which a steel pipe pile and a column are fastened with anchor bolts.
【図11】 二本の鋼管杭で一本の柱を支えている様子
を示す正面図。FIG. 11 is a front view showing a state where one pillar is supported by two steel pipe piles.
【図12】 同、平面図。FIG. 12 is a plan view of the same.
【図13】 a 先端に端板を取り付けたPC杭の斜視
図。b 継ぎ杭を溶接したPC杭の斜視図。FIG. 13 a is a perspective view of a PC pile with an end plate attached to the tip. b Perspective view of the PC pile to which the joint pile was welded.
6、40、鋼管杭 7、21、26、柱 12、杭
頭キャップ 13、ボルト 14、ナット 1
5、鉄環 16、裏当金 17、25、杭側ベース
プレート 18、27、柱側ベースプレート 1
9、29、アンカー穴20、28、通孔 22、挟み
板 23、仮ボルト 24、31、高力ボルト
30、38、挟みプレート 32、リブ板 33、
端板 34、PC杭 35、継ぎ杭6, 40, steel pipe piles 7, 21, 26, pillar 12, pile head cap 13, bolt 14, nut 1
5, Iron ring 16, Backing metal 17, 25, Pile side base plate 18, 27, Column side base plate 1
9, 29, anchor holes 20, 28, through holes 22, sandwiching plate 23, temporary bolts 24, 31, high-strength bolts
30, 38, sandwiching plate 32, rib plate 33,
End plate 34, PC pile 35, joint pile
Claims (3)
し、中央にボルトを嵌合した杭頭キャップを杭先端に嵌
合すると共に通孔を有する二分割された杭側ベースプレ
ートで杭先端を挟み込んだ後杭先端に溶着し、柱を立設
した柱側ベースプレートをボルト上に載置し、通孔に合
わせて柱側ベースプレートに穿設したアンカー穴と通孔
に仮ボルトを挿通し、両ベースプレート間に挟み板を挟
入して柱の位置決めを行った後、溝を切欠した挟みプレ
ートで仮ボルトを挟み込み、仮ボルト抜き取り後に高力
ボルトで両ベースプレートを締結してなる建屋基礎の施
工法。A steel pipe pile submerged in the ground is cut to a desired length, a pile head cap fitted with a bolt in the center is fitted to the pile tip, and a pile-side base plate having a through hole is provided. After sandwiching the tip, weld it to the tip of the pile, place the pillar-side base plate with the pillar standing on the bolt, and insert the temporary bolt into the anchor hole and through hole drilled in the pillar-side base plate according to the through hole After positioning the pillars by inserting the sandwiching plate between both base plates, sandwiching the temporary bolts with the sandwiched plate with the groove cut out, fastening the base plates with high-strength bolts after removing the temporary bolts, Construction method.
し、中央にボルトを嵌合した杭頭キャップを杭先端に嵌
合すると共に通孔を有する二分割された杭側ベースプレ
ートで杭先端を挟み込んだ後杭先端に溶着し、二本以上
の鋼管杭にわたる面積を有する、柱を立設した柱側ベー
スプレートをボルト上に載置し、通孔に合わせて柱側ベ
ースプレートに穿設したアンカー穴と通孔に仮ボルトを
挿通し、両ベースプレート間に挟み板を挟入して柱の位
置決めを行った後、溝を切欠した挟みプレートで仮ボル
トを挟み込み、仮ボルト抜き取り後に高力ボルトで両ベ
ースプレートを締結してなる建屋基礎の施工法。2. A two-part pile base plate having two or more adjacent steel pipe piles cut at a desired length, a pile head cap fitted with a bolt at the center, fitted to the pile tip, and having a through hole. After sandwiching the tip of the pile, it is welded to the tip of the pile, and the pillar-side base plate, which has an area extending over two or more steel pipe piles, with the pillar standing upright, is placed on the bolt and drilled in the pillar-side base plate in accordance with the through hole Temporary bolts are inserted through the anchor holes and through holes that have been inserted, the sandwiching plate is inserted between both base plates, and the pillars are positioned. Construction method of the building foundation which fastens both base plates with bolts.
小さな径を有する鋼管杭を継ぎ杭としPC杭の端板に溶
着後、高さ調節を行うための継ぎ杭としての鋼管杭の先
端に、中央にボルトを嵌合した杭頭キャップを嵌合する
と共に、通孔を有する二分割された杭側ベースプレート
で杭先端を挟み込んだ後杭先端に溶着し、柱を立設した
柱側ベースプレートをボルト上に載置し、通孔に合わせ
て柱側ベースプレートに穿設したアンカー穴と通孔に仮
ボルトを挿通し、両ベースプレート間に挟み板を挟入し
て柱の位置決めを行った後、溝を切欠した挟みプレート
で仮ボルトを挟み込み、仮ボルト抜き取り後に高力ボル
トで両ベースプレートを締結してなる建屋基礎の施工
法。3. A steel pipe pile having a diameter smaller than the inner diameter of the PC pile is joined to the PC pile submerged in the ground, and after welding to the end plate of the PC pile, the steel pipe pile is used as a joint pile for height adjustment. At the tip, a pile head cap fitted with a bolt at the center is fitted, and the pile tip is sandwiched between two divided pile-side base plates with through holes, then welded to the pile tip, and the pillar side where the pillar is erected The base plate was placed on the bolt, the temporary bolt was inserted into the anchor hole and the through hole drilled in the pillar side base plate in accordance with the through hole, and the pillar was positioned by inserting the sandwiching plate between both base plates. After that, the temporary bolts are sandwiched between pinched plates with grooves cut out, and after removing the temporary bolts, both base plates are fastened with high-strength bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09348841A JP3095376B2 (en) | 1997-12-18 | 1997-12-18 | Construction method of building foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09348841A JP3095376B2 (en) | 1997-12-18 | 1997-12-18 | Construction method of building foundation |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11181790A JPH11181790A (en) | 1999-07-06 |
JP3095376B2 true JP3095376B2 (en) | 2000-10-03 |
Family
ID=18399748
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP09348841A Expired - Lifetime JP3095376B2 (en) | 1997-12-18 | 1997-12-18 | Construction method of building foundation |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3095376B2 (en) |
Families Citing this family (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003056060A (en) * | 2001-08-08 | 2003-02-26 | Shimizu Corp | Frame structure of building |
JP4693299B2 (en) * | 2001-08-09 | 2011-06-01 | 旭化成建材株式会社 | Column base connection structure |
FR2839092B1 (en) * | 2002-04-26 | 2004-10-22 | Jean Jacques Combrouze | DEVICE FOR CONNECTING AND TAKING UP POST-BASED EFFORTS FOR CONSTRUCTION |
JP4550534B2 (en) * | 2004-09-14 | 2010-09-22 | 森 直樹 | Building basic structure |
JP4427603B1 (en) * | 2009-04-27 | 2010-03-10 | 株式会社西部工建 | Construction method of building foundation and joint board for building foundation construction |
JP6210759B2 (en) * | 2013-07-01 | 2017-10-11 | 株式会社竹中工務店 | Pile beam joint structure and pile beam joint method |
JP5844781B2 (en) * | 2013-08-23 | 2016-01-20 | 大和ハウス工業株式会社 | Joining structure of solar cell mount and steel pipe pile and pile head cap hardware |
JP6776505B2 (en) * | 2016-05-12 | 2020-10-28 | 前田建設工業株式会社 | How to build the foundation of offshore facilities, the foundation of offshore facilities and the foundation of offshore facilities |
JP6999281B2 (en) * | 2017-03-22 | 2022-02-10 | 大和ハウス工業株式会社 | Pile foundation structure and its construction method |
JP6999282B2 (en) * | 2017-03-22 | 2022-02-10 | 大和ハウス工業株式会社 | Pile foundation structure and its construction method |
JP7272589B2 (en) * | 2019-12-11 | 2023-05-12 | 久野商事株式会社 | support structure |
CN114375759B (en) * | 2021-12-13 | 2023-10-24 | 六安市叶集区绿叶果木种植专业合作社 | Grape trellis with prevent wind effect |
-
1997
- 1997-12-18 JP JP09348841A patent/JP3095376B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH11181790A (en) | 1999-07-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3647841B2 (en) | Joining structure and joining method of pile and building | |
JP3095376B2 (en) | Construction method of building foundation | |
JP2831909B2 (en) | Connection structure of steel columns, piles and foundation beams | |
JP2006207265A (en) | Joining method of pile and column and its structure | |
JP3931034B2 (en) | Construction method using steel pipe pile as column | |
JP3671344B2 (en) | Joint structure between foundation pile and column base and its construction method | |
JP3641783B2 (en) | Rigidity suppression steel pipe pile head rigid binding material | |
JP3491116B2 (en) | Pillar and pile joints | |
JP2012057433A (en) | Structure and method for connecting pile and steel column | |
JP3790310B2 (en) | Construction method of the building by the prior construction of steel frame | |
JP3185129B2 (en) | Column-integrated column base fixed foundation structure and its construction method | |
JP2002021096A (en) | Building and constructing method therefor | |
JP2858997B2 (en) | Temporary support column used for reverse driving method | |
JP2002194748A (en) | Foundation constructing method and building foundation structure | |
JP3236541B2 (en) | Joint method between knotted pile and steel pipe pile | |
JPS63280153A (en) | Underground inverted lining method | |
JP3246321B2 (en) | Column and pile joint structure | |
JP2004100281A (en) | Positioning method for permanent substructural column without using casing | |
JP2005240430A (en) | Building foundation and construction method therefor | |
JP4473400B2 (en) | Foundation of construction and construction method | |
JP3700119B2 (en) | Pillar construction method | |
JPH0645475Y2 (en) | Steel pile foundation | |
JP4589506B2 (en) | Pre-installation method of large steel columns for constructing buildings with superstructure structure by the reverse driving method | |
JPH10299019A (en) | Joining method for permanent sub-structural column and main steel in inverted construction method | |
JPH0336369B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080804 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090804 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100804 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110804 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120804 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120804 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130804 Year of fee payment: 13 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |