JP3406370B2 - Horizontal shaft construction method - Google Patents

Horizontal shaft construction method

Info

Publication number
JP3406370B2
JP3406370B2 JP07088994A JP7088994A JP3406370B2 JP 3406370 B2 JP3406370 B2 JP 3406370B2 JP 07088994 A JP07088994 A JP 07088994A JP 7088994 A JP7088994 A JP 7088994A JP 3406370 B2 JP3406370 B2 JP 3406370B2
Authority
JP
Japan
Prior art keywords
excavation
support
shoring
shaft
horizontal shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP07088994A
Other languages
Japanese (ja)
Other versions
JPH07279576A (en
Inventor
恒夫 米田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP07088994A priority Critical patent/JP3406370B2/en
Publication of JPH07279576A publication Critical patent/JPH07279576A/en
Application granted granted Critical
Publication of JP3406370B2 publication Critical patent/JP3406370B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 【0001】 【産業上の利用分野】本発明は横坑を施工する方法に係
り、特に、大断面の横坑を施工するに好適な施工方法に
関する。 【0002】 【従来の技術】地盤中に大径の配管工事や、地下鉄工事
用の横坑を施す場合の一例として、従来、掘削断面を多
数の区画に分割し、各区画ごとに支保工を設置しつつ先
端に向けて掘削を行う方法が知られている。図6および
図7は前記従来の横坑の施工方法を説明するためのもの
で、これらの図において、符号1は立坑を示す。この立
坑1は横坑2を施工する際に使用される作業用の立坑で
あり、横坑2の施工前に予め施工され、親杭3、矢板、
腹起こし4、切張り5等によって山止めがなされてい
る。 【0003】前記立坑1から横坑2を施工する場合、坑
口の補強支保工6を設置した後、坑口に位置する親杭3
を切断し、図7に示すように、24分割された各区画7
を掘削して、各区画7ごとに、支保工8を設置しつつ、
先端に向けて掘削して行く。支保工8は、区画ごとに若
干タイプが異なり、適宜、正面視ロ字状をなすもの、門
形をなすものが設置され、また、地山の壁面に対向する
面には、木矢板が設けられ、また、横坑2の長さ方向に
隣接するものどうしは、互いに支保工継手8aによって
連結されている。なお、上記横坑2の施工の際には、設
置された支保工8…の周囲に、地山の壁面に沿って、パ
イプルーフ9を設け、地山壁面を補強して、その崩壊を
防止している。なお、図1において符号10で示すもの
は、既設の下水管である。 【0004】 【発明が解決しようとする課題】ところが、上記横坑の
施工方法においては、以下に述べるような不都合があ
る。すなわち、横坑2の掘削断面を多数に分割(24分
割)して、各区画7ごとに支保工8を設置しているの
で、つまり、支保工材が細分化されているので、支保工
8どうしを連結している支保工継手8aの緩みが累積さ
れて、支持力が低下し易く、しかも、掘削断面が小さく
なるので、掘削勾配を安定した勾配にとりにくく、前方
の上方の支保工8の支持力低下を招くので、地盤面の沈
下を招くおそれがある。 【0005】また、上述したように、支保工材が細分化
されているので、掘削された横坑内には支保工8…が密
集しており、このため、横坑2の内壁を鉄筋コンクリー
トで覆工する際に、長い横工鉄筋を挿入して組み立てる
のが困難であるため、横工鉄筋を短くせざるを得ず、横
工鉄筋の継手箇所が多くなってしまう。さらに、掘削さ
れた横坑内には、支保工8…が密集しているので、上記
鉄筋コンクリートによる覆工の際に、型枠組、箱抜き等
が煩雑であるばかりか、覆工以降の作業効率が著しく低
下し、工期が長期化してしまう。 【0006】本発明は上記事情に鑑みてなされたもの
で、支保工間のスペースを広くとることができ、しか
も、支保工の支持力低下を招くことない横坑施工方法を
提供することを目的としている。 【0007】 【課題を解決するための手段】上記目的を達成するため
に、本発明の請求項1の横坑施工方法は、横坑を掘削す
る際の掘削断面を上下に分割し、まず上段の掘削断面を
掘削した後、この上部掘削坑に上部支保工を設置し、次
いで、該上部掘削坑に、前記上部支保工を支持する通し
桁を上部掘削坑の長手方向に挿通して、当該通し桁に上
部支保工を支持させ、次いで、下段の掘削断面を掘削し
た後、この下部掘削に下部支保工を設置してなり、掘削
すべき横坑の先端部に地盤面から杭を打ち込み、この杭
と横坑の基端部に設けた支持体とに、前記通し桁を支持
させることを特徴としている。 【0008】 【0009】 【作用】本発明の請求項1の横坑施工方法にあっては、
上部掘削坑に設置された上部支保工を、該上部掘削坑に
挿通された通し桁によって支持することにより、上部支
保工に作用する上部荷重を通し桁により受ける。これに
より、従来に比べ、支保工の数を少なくして掘削断面を
広くとるとともに、支保工の支持力低下を防止する。ま
た、支保工の数を少なくすることにより、支保工間のス
ペースが拡がるので、比較的大型の機械を導入すること
ができ、これにより作業者にかかる負担を軽減するとと
もに、工期の大幅な短縮を図る。さらに、設置する支保
工の数、間隔を少なくすることができるので、横坑の内
壁を鉄筋コンクリートにより覆工する際において、鉄筋
の組立、型枠組、箱抜き等が容易であり、作業効率が向
上する。 【0010】また、横坑の先端部に地盤面から打ち込ま
れた杭と、横坑の基端部に設けた支持体とによって通し
桁を支持することにより、上部支保工に作用する上部荷
重を通し桁によって確実に受ける。 【0011】 【実施例】以下、図面を参照して本発明の横坑施工方法
の一実施例を説明する。図1は、横坑2を示す側面図、
図2は図1におけるA−A線視断面図であるこれらの図
に示す横坑2を施工するには、掘削断面を上下2段に分
割して、上方の掘削断面を掘削した後、下方の掘削断面
を掘削する。すなわち、まず、坑口上部に補強支保工1
0を設置して、上段部掘削作業ステージを組み立てる。
なお、補強支保工10より奥側には、山止親杭11が施
工されている。次に、坑口を正面視して、上段右側の山
止親杭11を切断した後、支保工建て込みに必要な空間
を確保し、ミニバックホー等によって掘削を行う。この
掘削は、図2において、符号P1で示す部分を掘削す
る。そして、この掘削後、上部第1支保工JS1の右側
部分を構成する支保工材13を建て込む。 【0012】この支保工材13は、図2に示すように、
鋼材14…を門形に組んでなるもので、横坑3の壁面側
の角部は斜材15によって補強されている。支保工材1
3を構成する鋼材14…のうち、右側の鉛直な鋼材14
の下端部には、図3に示すように、左側に突出する受け
材16がボルトとナットによって固定されており、ま
た、左側の鉛直な鋼材14の下端部には、図4に示すよ
うに、左右両側に突出する一対の受け材16,16がボ
ルトとナットによって固定されている。また、これら受
け材16…は鋼材14の高さ位置に固定されている。 【0013】次に、上段左側の山止親杭11を切断した
後、支保工建て込みに必要な空間を確保し、ミニバック
ホー等によって掘削を行う。この掘削は、図2におい
て、符号P2で示す部分を掘削する。そして、この掘削
後、上部第1支保工JS1の左側部分を構成する支保工
材17を建て込む。この支保工材17は、前記支保工材
13と同様に、鋼材14…を門形に組んでなるもので、
横坑3の壁面側の角部は斜材15によって補強され、支
保工材17を構成する2本の鉛直な鋼材14には、支保
工材13と同様に、受け材16…が固定されている。 【0014】次に、上段中央左側の山止親杭11を切断
し、土質を確認して安定しておれば、上段中央右側の山
止親杭11を切断して、支保工建て込みに必要な空間を
確保し、上記と同様にして切削を行う。この切削は、図
2において、符号P3,P4で示す部分を掘削する。そ
して、この掘削後、上部第1支保工JS1の中央部分を
構成する支保工材18を建て込む。この支保工材18
は、鋼材14…を略T字状に組んでなるもので、その水
平な鋼材14の両端部が、図5に示すように、前記支保
工材13,17のそれぞれの水平な鋼材14と鉛直な鋼
材14にボルトとナットによって固定されている。ま
た、支保工材18鉛直な鋼材14の下端部には、左右両
側に突出する一対の受け材16,16がボルトとナット
によって固定されている。 【0015】このようにして、符号P1〜P4に示す部
分を掘削して、支保工材13,17,18からなる上部
第1支保工JS1を建て込むことにより、横坑2の入口
の掘削断面上段の施工を行った後、同様にして、上段の
掘削を進めて上部掘削坑20を形成しつつ、上部第2支
保工JS2〜上部第9支保工S9の建て込みを順次行っ
て、横坑2の上段の上部掘削坑20の施工を終了する。
なお、上部第2支保工JS2〜上部第9支保工S9のそ
れぞれは、前記上部第1支保工JS1と同様の構成であ
り、鉛直な鋼材14の下端部には受け材16がそれぞれ
固定されている。また、横坑2の長さ方向に隣接する支
保工どうしは、交差筋かい21によって互いに連結され
ている。 【0016】上記のようにして、上部掘削坑20の施工
が終了した後、この上部掘削坑20に、8本の通し桁2
2…を該上部掘削坑20の長手方向に挿通する。これら
通し桁22…は、前記上部第1支保工JS1〜上部第9
支保工S9を仮受けして支持するもので、例えば、H鋼
で形成されている。通し桁22…を挿通する場合、上部
第1支保工JS1〜上部第9支保工S9にそれぞれ固定
された前記受け材16…の直下に挿通し、これら受け材
16を通し桁22…に載置することによって、上部第1
支保工JS1〜上部第9支保工S9を下方から仮支持す
る。 【0017】前記通し桁22…のそれぞれの左端部、つ
まり横坑2の入口側のそれぞれ端部は、図1に示すよう
に、横坑2の入口部に設けられた、鋼材を門形に組んで
形成された支持体23により支持し、通し桁22…のそ
れぞれのの右端部、つまり横坑2の先端側のそれぞれ端
部は、それぞれ杭24…によって支持する。これら杭2
4…は、横坑2の先端部に地盤面から打ち込まれたもの
で、以下のようにして施工する。 【0018】すなわち、まず、横坑2の先端部近傍の地
盤を改良する。この地盤改良は、「コラムジェットグラ
ウト工法」と称される工法にて行う。この工法は、空気
を伴った超高圧水を地盤中に回転して噴射させて地盤を
切削し、そのスライムを地表に排出させるとともに、硬
化材を同時充填させ円柱状の固結体を鉛直に造成するも
のであり、本実施例では、図1において紙面と直交する
方向に互いに若干オーバーラップして造成された多数の
固結体からなる固結体列25を、横坑2の長さ方向に2
列若干オーバーラップして形成することによって地盤改
良を行っている。 【0019】そして、この固結体列25のうち、横坑2
の入口側に位置する固結体列25に、前記杭24…を打
ち込むか、あるいは、固結体列25をボーリングして、
各ボーリング孔に杭24を挿通して、さらに下方の地盤
に打ち込む。杭24…を打ち込む場合、前記通し桁22
…の先端が当接する位置に打ち込み、これら杭24…に
通し桁22…をそれぞれ連結固定する。したがって、通
し桁22はその両端部が支持体23と杭24によって支
持されるので、前記上部第1支保工JS1〜上部第9支
保工S9は、通し桁22によって確実に支持される。な
お、本実施例では地盤改良を行ってから、杭24を打ち
込んだが、地盤が堅い場合、地盤改良を行わず、直接杭
24を打ち込んでもよい。、また、杭24の打ち込み時
期は、前記上部掘削坑20の施工終了前であれば、どの
時期に行ってもよく、上部掘削坑20の施工終了後で
も、下部掘削坑26の施工前であれば、どの時期に行っ
てもよい。 【0020】さて、上記のようにして、上部掘削坑20
に建て込まれた上部第1支保工JS1〜上部第9支保工
S9が、通し桁22によって仮支持されたならば、坑口
下部に補強支保工27を設置して、下段部掘削作業ステ
ージを組み立て、次いで、下段右側の山止親杭11を切
断した後、支保工建て込みに必要な空間を確保し、ミニ
バックホー等によって掘削を行う。この掘削は、図2に
おいて、符号P5で示す部分を掘削する。そして、この
掘削後、下部第1支保工KS1の右側部分を構成する支
保工材28を建て込む。 【0021】この支保工材28は鋼材14…を正面視略
ロ字状に組んでなるもので、図3および図4に示すよう
に、その鉛直な一対の鋼材14の上端部が、前記支保工
材13の鉛直な一対の鋼材14の下端部端面にボルトと
ナットによって接合固定され、また、水平な上部の鋼材
14が、支保工材13の鉛直な一対の鋼材14の下端部
側面にボルトとナットによって接合固定されている。 【0022】次に、下段左側の山止親杭11を切断した
後、支保工建て込みに必要な空間を確保し、ミニバック
ホー等によって掘削を行う。この掘削は、図2おいて、
符号P6で示す部分を掘削する。そして、この掘削後、
下部第1支保工KS1の左側部分を構成する支保工材3
0を建て込む。この支保工材30は、前記支保工材28
と同様に、鋼材14…をロ字状に組んでなるもので、そ
の鉛直な一対の鋼材14が、前記支保工材17の鉛直な
一対の鋼材14の下端部端面にボルトとナットによって
接合固定され、また、水平な上部の鋼材14が、支保工
材17の鉛直な一対の鋼材14の下端部側面にボルトと
ナットによって接合固定されている。 【0023】次に、下段中央左側と下段右側のそれぞれ
の山止親杭11を切断して、支保工建て込みに必要な空
間を確保し、上記と同様にして切削を行う。この切削
は、図2において、符号P7,P8で示す部分を掘削す
る。そして、この掘削後、下部部第1支保工KS1の中
央部分を構成する支保工材31を建て込む。この支保工
材31は、鋼材14…を略エ字状に組んでなるもので、
その水平な上部の鋼材14の両端部が、前記支保工材1
3,17のそれぞれの鉛直な鋼材14の下端部側面にボ
ルトとナットによって固定されている。また、支保工材
31の下部の水平な鋼材14の両端部は、前記支保工材
28,30の下部の水平な鋼材14の端部にボルトとナ
ットによって固定されている。さらに、支保工材31の
上部の水平な鋼材14の突き合わされた端部は、前記支
保工材18の垂直な鋼材14の下端部側面にボルトとナ
ットによって固定され、また、下部の水平な鋼材14ど
うしは突き合わされたてボルトとナットによって固定さ
れている。 【0024】このようにして、符号P5〜P8に示す部
分を掘削して、支保工材28,30,31からなる下部
第1支保工KS1を建て込むことにより、横坑2の入口
の掘削断面下段の施工を行った後、同様にして、下段の
掘削を進めて下部掘削坑26を形成しつつ、下部第2支
保工KS2〜下部第9支保工KS9の建て込みを順次行
って、横坑2の下段の下部掘削坑26の施工を終了す
る。なお、下部第2支保工KS2〜下部第9支保工KS
9のそれぞれは、前記下部第1支保工KS1と同様の構
成であり、横坑2の長さ方向に隣接する支保工どうし
は、交差筋かい21によって互いに連結されている。ま
た、前記上部掘削坑20および下部掘削坑26の施工の
際には、設置される支保工の周囲に、地山の壁面に沿っ
て、パイプルーフ9を設け、地山壁面を補強して、その
崩壊を防止している。 【0025】その後、横坑2の内壁を鉄筋コンクリート
で覆工するが、上述したように、横坑2内に設置された
支保工は、通し桁22によって上部第1支保工JS1〜
上部第9支保工JS9に作用する上部荷重が受けられて
いるので、従来に比べ、設置する支保工の数、間隔を少
なくすることができる。したがって、前記鉄筋コンクリ
ートによる覆工の際に、鉄筋の組立、型枠組、箱抜き等
が容易であり、作業効率が向上し、工期の短縮化を図る
ことができる。 【0026】また、本実施例では、通し桁22によって
上部第1支保工JS1〜上部第9支保工JS9に作用す
る上部荷重が受けられているので、従来に比べ、支保工
の数を少なくすることができ、当然、支保工どうしの継
手部分の数も少なくなり、よって、継手部分の緩みの累
積も少なくなり、しかも、支保工の数を少なくすること
によって、掘削断面を広くとることができ、掘削対象土
質に応じて安全な掘削勾配を確保できるので、支保工の
支持力低下を招くことがなく、よって、地盤面の沈下を
防止することができる。 【0027】さらに、支保工の数を少なくすることによ
り、支保工間のスペースが拡がるので、掘削および支保
工設置のいずれにおいても、比較的大型の機械を導入す
ることができ、よって、作業者にかかる負担を軽減でき
るとともに、工期の大幅な短縮を図ることができる。 【0028】また、横坑2の先端部に地盤面から打ち込
まれた杭24と、横坑2の基端部に設けた支持体23と
によって、通し桁22を支持するようにしたので、この
通し桁22によって上部第1支保工JS1〜上部第9支
保工JS9に作用する上部荷重を確実に受けることがで
き、よって、地盤面の沈下を確実に防止することができ
る。 【0029】 【発明の効果】以上説明したように、本発明の請求項1
の横坑施工方法によれば、上部掘削坑に設置された上部
支保工を、該上部掘削坑に挿通された通し桁によって支
持するようにしたので、上部支保工に作用する上部荷重
が通し桁により受けられる。したがって、従来に比べ、
支保工の数を少なくすることができ、当然、支保工どう
しの継手部分の数も少なくなり、よって、継手部分の緩
みの累積も少なくなり、しかも、支保工の数を少なくす
ることによって、掘削断面を広くとることができ、掘削
対象土質に応じて安全な掘削勾配を確保できるので、支
保工の支持力低下を招くことがなく、よって、地盤面の
沈下を防止することができる。 【0030】また、支保工の数を少なくすることによ
り、支保工間のスペースが拡がるので、掘削および支保
工設置のいずれにおいても、比較的大型の機械を導入す
ることができ、よって、作業者にかかる負担を軽減でき
るとともに、工期の大幅な短縮を図ることができる。 【0031】さらに、従来に比べ、設置する支保工の
数、間隔を少なくすることができるので、横坑の内壁を
鉄筋コンクリートにより覆工する際において、鉄筋の組
立、型枠組、箱抜き等が容易であり、作業効率が向上
し、工期の短縮化を図ることができる。 【0032】また、横坑の先端部に地盤面から打ち込ま
れた杭と、横坑の基端部に設けた支持体とによって、通
し桁を支持するようにしたので、この通し桁によって上
部支保工に作用する上部荷重を確実に受けることがで
き、よって、地盤面の沈下を確実に防止することができ
る。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a horizontal shaft, and more particularly to a method suitable for constructing a horizontal shaft having a large cross section. 2. Description of the Related Art As an example of a case where a large-diameter plumbing or subway construction is carried out in the ground, conventionally, an excavated cross section is divided into a number of sections, and a support is provided for each section. A method of excavating toward the tip while installing is known. FIGS. 6 and 7 are for explaining the conventional method of constructing a horizontal shaft, and in these figures, reference numeral 1 denotes a shaft. The shaft 1 is a working shaft used when the horizontal shaft 2 is constructed, and is constructed before the horizontal shaft 2 is constructed, and the parent pile 3, the sheet pile,
The stomach is stopped by the belly 4 and the tension 5. [0003] When the horizontal shaft 2 is constructed from the shaft 1, after the reinforcement support 6 for the wellhead is installed, the parent pile 3 located at the wellhead is installed.
Is cut, and as shown in FIG.
Excavation, and while installing the shoring 8 for each section 7,
Drill towards the tip. As for the shoring 8, the type is slightly different for each section, and the one having a square shape in a front view and the one having a gate shape are appropriately installed, and a wooden sheet is provided on a surface facing a wall surface of the ground. The shafts 2 that are adjacent to each other in the longitudinal direction are connected to each other by a shoring joint 8a. When the horizontal shaft 2 is constructed, a pipe roof 9 is provided along the wall of the ground around the installed supports 8... To reinforce the wall of the ground and prevent its collapse. are doing. In addition, what is shown with the code | symbol 10 in FIG. 1 is an existing sewer pipe. [0004] However, the method for constructing the horizontal shaft has the following inconveniences. That is, the excavation cross section of the horizontal shaft 2 is divided into a large number (24 divisions), and the shoring 8 is installed for each section 7. That is, since the shoring material is subdivided, the shoring 8 Since the looseness of the shoring joints 8a connecting each other is accumulated, the supporting force is easily reduced, and the digging cross section becomes small, so that it is difficult to set the digging gradient to a stable gradient. Since the bearing capacity is reduced, there is a possibility that the ground surface will sink. Further, as described above, since the support material is subdivided, the supports 8 are densely packed in the excavated shaft, so that the inner wall of the shaft 2 is covered with reinforced concrete. Since it is difficult to insert and assemble a long horizontal reinforcing bar at the time of construction, the horizontal reinforcing bar must be shortened, and the joints of the horizontal reinforcing bar increase. In addition, since the supports 8 are densely packed in the excavated horizontal shaft, when the lining with the reinforced concrete is performed, not only is the formwork, box removal, etc. complicated, but also the work efficiency after the lining is reduced. It will decrease significantly and the construction period will be prolonged. The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a method of constructing a cross shaft capable of increasing a space between supports and preventing a decrease in support force of the supports. And [0007] In order to achieve the above object, a cross shaft construction method according to claim 1 of the present invention divides a cross section when excavating a cross shaft into upper and lower parts, and After excavating the excavated cross section, an upper support is installed in this upper excavation pit, and then a girder supporting the upper support is inserted into the upper excavation pit in the longitudinal direction of the upper excavation pit, and The upper girder is supported by the girder, and then the lower excavation section is excavated.
Driving a pile from the ground surface into the tip of the horizontal shaft
And the support provided at the base end of the shaft, supporting the girder
It is characterized by having In the method for constructing a cross shaft according to claim 1 of the present invention,
An upper load installed on the upper excavation pit is supported by a girder inserted into the upper excavation pit, so that an upper load acting on the upper support is received by the girder. As a result, the number of shoring works is reduced as compared with the related art, the excavation section is widened, and a decrease in the supporting force of the shoring works is prevented. Also, by reducing the number of shoring, the space between the shorings is expanded, so that a relatively large machine can be introduced, which reduces the burden on the workers and greatly shortens the construction period. Plan. Furthermore, since the number and spacing of the supports to be installed can be reduced, when the inner wall of the horizontal shaft is reinforced with reinforced concrete, it is easy to assemble reinforcing bars, formwork, remove boxes, and improve work efficiency. I do. Further, the pile that is driven from the ground surface to the tip of the Adit, by supporting the digits through by the support provided to the base end portion of the adit, the upper load acting on the upper shoring Be sure to receive by the girder. An embodiment of the cross shaft construction method of the present invention will be described below with reference to the drawings. FIG. 1 is a side view showing the horizontal shaft 2,
FIG. 2 is a sectional view taken along the line AA in FIG. 1. In order to construct the cross shaft 2 shown in these figures, the excavated section is divided into upper and lower sections, and after excavating the upper excavated section, Excavate the excavation section. That is, first, reinforcement support 1
0 is set and the upper excavation work stage is assembled.
In addition, a mountain stop parent pile 11 is constructed on the back side of the reinforcing support 10. Next, after the pit entrance is viewed from the front, the upper right side of the mountain retaining stake 11 is cut, and a space necessary for the erection work is secured, and excavation is performed by a mini backhoe or the like. In this excavation, a portion indicated by a reference numeral P1 in FIG. 2 is excavated. After this excavation, the support material 13 constituting the right side portion of the upper first support JS1 is built. [0012] As shown in FIG.
The steel members 14 are assembled in a gate shape, and the corners on the wall surface side of the horizontal shaft 3 are reinforced by diagonal members 15. Shoring material 1
3 among the steel materials 14 constituting the right side, the right vertical steel material 14
As shown in FIG. 3, a receiving member 16 protruding to the left is fixed to the lower end of the left side by bolts and nuts. Also, as shown in FIG. A pair of receiving members 16, 16 protruding on both left and right sides are fixed by bolts and nuts. The receiving members 16 are fixed at the height position of the steel member 14. [0013] Next, after cutting the upper mountain left parent stake 11 on the left side of the upper stage, a space necessary for the erection work is secured, and excavation is performed by a mini backhoe or the like. This excavation excavates a portion indicated by reference numeral P2 in FIG. Then, after this excavation, the support material 17 constituting the left portion of the upper first support JS1 is built. The support material 17 is formed by assembling steel materials 14 in a gate shape, like the support material 13.
The corners on the wall side of the horizontal shaft 3 are reinforced by diagonal members 15, and receiving members 16 are fixed to two vertical steel members 14 constituting the supporting member 17, similarly to the supporting member 13. I have. Next, if the stake 11 on the center left of the upper stage is cut and the soil quality is confirmed and stable, the stake 11 on the center right of the upper stage is cut and necessary for erection. A sufficient space is secured, and cutting is performed in the same manner as above. This cutting excavates portions indicated by reference numerals P3 and P4 in FIG. After this excavation, the supporting material 18 constituting the central portion of the upper first supporting structure JS1 is built. This support material 18
Is formed by assembling steel members 14 in a substantially T-shape. Both ends of the horizontal steel member 14 are vertically connected to the respective horizontal steel members 14 of the support members 13 and 17 as shown in FIG. A steel member 14 is fixed by bolts and nuts. Further, a pair of receiving members 16, 16 protruding to the left and right sides are fixed to the lower end portion of the vertical steel material 14 by the bolts and nuts. In this way, by excavating the portions indicated by reference numerals P1 to P4 and building the upper first support JS1 including the support materials 13, 17, and 18, the excavation section at the entrance of the horizontal shaft 2 is obtained. After the construction of the upper berth is performed, similarly, the upper berth 20 is formed by digging the upper berth, and the upper second shoring JS2 to the upper ninth shoring S9 are sequentially built, and the horizontal pit is formed. The construction of the upper excavation pit 20 in the second upper stage is completed.
Each of the upper second shoring JS2 to the upper ninth shoring S9 has the same configuration as the upper first shoring JS1, and a receiving member 16 is fixed to the lower end of the vertical steel member 14, respectively. I have. In addition, the support structures adjacent in the length direction of the horizontal shaft 2 are connected to each other by a cross bracing 21. After the completion of the construction of the upper excavation pit 20 as described above, eight continuous girder 2
2 are inserted in the longitudinal direction of the upper excavation pit 20. .. Are connected to the upper first support JS1 to the upper ninth.
The support S9 is temporarily received and supported, and is formed of, for example, H steel. In the case where the continuous girder 22 is inserted, the continuous girder 22 is inserted directly below the receiving members 16 fixed to the upper first shoring JS1 to the upper ninth shoring S9, and these receiving members 16 are placed on the continuous girder 22. By doing
The shoring JS1 to the upper ninth shoring S9 are temporarily supported from below. As shown in FIG. 1, the left end of each of the stringers 22..., That is, the end on the entrance side of the shaft 2, is made of a steel material provided at the entrance of the shaft 2. The right ends of the stringers 22, that is, the ends on the tip side of the horizontal shaft 2 are supported by piles 24, respectively. These piles 2
Reference numerals 4 are driven into the tip of the horizontal shaft 2 from the ground surface, and are constructed as follows. That is, first, the ground near the tip of the horizontal shaft 2 is improved. This ground improvement is performed by a method called “column jet grouting method”. In this method, ultra-high pressure water with air is rotated and injected into the ground to cut the ground, discharge the slime to the surface, fill the hardening material at the same time, and turn the columnar consolidated body vertically. In the present embodiment, the solidified body row 25 composed of a large number of solidified bodies formed so as to slightly overlap each other in a direction perpendicular to the paper surface in FIG. To 2
The ground is improved by slightly overlapping the rows. Then, of the solid row 25, the shaft 2
The piles 24 are driven into the consolidated body row 25 located at the entrance side of the or the solidified body row 25 is drilled,
The pile 24 is inserted into each of the boring holes and driven into the ground further below. When driving piles 24...
. Are driven into contact with the tips of the piles 24, and the stringers 22 are connected and fixed to the piles 24, respectively. Therefore, since both ends of the girder 22 are supported by the support body 23 and the pile 24, the upper first shoring JS1 to the upper ninth shoring S9 are reliably supported by the girder 22. In this embodiment, the pile 24 is driven after the ground is improved. However, when the ground is hard, the pile 24 may be driven directly without performing the ground improvement. The driving of the pile 24 may be performed at any time as long as it is before the completion of the construction of the upper excavation pit 20, and may be performed before the construction of the lower excavation pit 26 even after the construction of the upper excavation pit 20 is completed. It may be done at any time. Now, as described above, the upper excavation pit 20
If the upper first shoring JS1 to the ninth shoring S9 built in the tent are temporarily supported by the girder 22, the reinforcing shoring 27 is installed at the lower part of the wellbore, and the lower excavation work stage is assembled. Then, after cutting the lower right retaining pile 11 on the right side of the lower stage, a space necessary for the erection work is secured, and excavation is performed by a mini backhoe or the like. This excavation excavates the portion indicated by reference numeral P5 in FIG. Then, after this excavation, the support material 28 constituting the right side portion of the lower first support KS1 is built. The support member 28 is formed by assembling the steel members 14 in a substantially rectangular shape when viewed from the front. As shown in FIGS. 3 and 4, the upper ends of the pair of vertical steel members 14 Bolts and nuts are joined and fixed to the lower end surfaces of the pair of vertical steel materials 14 of the work material 13, and the horizontal upper steel material 14 is bolted to the lower end side surfaces of the pair of vertical steel materials 14 of the support material 13. And is fixedly joined by a nut. Then, after cutting the lower left mountain retaining pile 11, a space necessary for erection work is secured, and excavation is performed by a mini backhoe or the like. This excavation
The portion indicated by the reference numeral P6 is excavated. And after this excavation,
Shoring material 3 that constitutes the left part of the lower first shoring KS1
Build 0. The support material 30 is the support material 28
In the same manner as described above, the steel materials 14 are assembled in a square shape, and the pair of vertical steel materials 14 are joined and fixed to the end surfaces of the lower end portions of the pair of vertical steel materials 14 of the support material 17 with bolts and nuts. The horizontal upper steel member 14 is joined and fixed to the lower end side surfaces of the pair of vertical steel members 14 of the support member 17 with bolts and nuts. Next, each of the stakes 11 on the lower left side and the lower right side is cut to secure a space necessary for the erection work, and cutting is performed in the same manner as described above. This cutting excavates portions indicated by reference numerals P7 and P8 in FIG. Then, after this excavation, the support material 31 constituting the central portion of the lower first support KS1 is laid. This support material 31 is formed by assembling steel materials 14 in a substantially E-shape.
Both ends of the horizontal upper steel material 14 are supported by the supporting material 1.
Each of the vertical steel members 3 and 17 is fixed to the lower end side surface by bolts and nuts. Further, both ends of the horizontal steel material 14 below the support material 31 are fixed to ends of the horizontal steel material 14 below the support materials 28 and 30 by bolts and nuts. Further, the butted ends of the upper horizontal steel material 14 of the support material 31 are fixed to the lower end side surfaces of the vertical steel material 14 of the support material 18 by bolts and nuts. 14 are butted and fixed by bolts and nuts. In this way, by excavating the portions indicated by reference numerals P5 to P8 and building the lower first shoring KS1 including the shoring materials 28, 30, and 31, the digging section at the entrance of the horizontal shaft 2 is obtained. After constructing the lower berth, similarly, the lower berth KS2 to the lower ninth berth KS9 are sequentially built while the lower berth is advanced to form the lower excavation pit 26, and the horizontal shaft is formed. The construction of the lower excavation pit 26 at the lower stage of 2 is completed. The lower second support KS2 to the lower ninth support KS
Each of 9 has the same configuration as the lower first shoring KS1, and the shorings adjacent in the length direction of the horizontal shaft 2 are connected to each other by a cross strut 21. In addition, at the time of the construction of the upper excavation pit 20 and the lower excavation pit 26, a pipe roof 9 is provided along the wall of the ground around the installed shoring to reinforce the wall of the ground, The collapse is prevented. After that, the inner wall of the horizontal shaft 2 is reinforced with reinforced concrete. As described above, the supports installed in the horizontal shaft 2 are connected to the upper first supporting structures JS1 to JS1 by the girder 22.
Since the upper load acting on the upper ninth shoring JS9 is received, the number and intervals of the shorings to be installed can be reduced as compared with the related art. Therefore, at the time of lining with the reinforced concrete, assembling of a reinforcing bar, formwork, box removal, and the like are easy, work efficiency is improved, and the construction period can be shortened. In this embodiment, since the upper load acting on the upper first shoring JS1 to the upper ninth shoring JS9 is received by the girder 22, the number of the shoring is reduced as compared with the prior art. Naturally, the number of joints between the supports is reduced, and therefore, the accumulation of looseness of the joints is also reduced.Moreover, by reducing the number of supports, the excavated cross section can be widened. In addition, since a safe excavation gradient can be ensured according to the excavation target soil, a decrease in the support force of the shoring work is not caused, and therefore, subsidence of the ground surface can be prevented. Further, by reducing the number of the supports, the space between the supports is expanded, so that a relatively large-sized machine can be introduced in both excavation and support installation. Can be reduced, and the construction period can be significantly reduced. Also, the girder 22 is supported by the pile 24 driven into the tip of the shaft 2 from the ground surface and the support 23 provided at the base end of the shaft 2. The bridge girder 22 can reliably receive the upper load acting on the upper first shoring JS1 to the upper ninth shoring JS9, and thus can reliably prevent the ground surface from sinking. As described above, according to the first aspect of the present invention,
According to the horizontal shaft construction method, the upper shoring installed in the upper digging pit is supported by the girder inserted into the upper digging pit, so that the upper load acting on the upper shoring is subjected to the girder. Received by Therefore, compared to the past,
The number of supports can be reduced, and naturally, the number of joints between the supports decreases, and therefore, the accumulation of looseness of the joints also decreases. Since the cross section can be widened and a safe excavation gradient can be secured in accordance with the excavated soil, the supporting force of the shoring does not decrease, and therefore, the settlement of the ground surface can be prevented. Since the space between the supports is increased by reducing the number of the supports, a relatively large-sized machine can be introduced for both excavation and support installation. Can be reduced, and the construction period can be significantly reduced. Further, since the number and intervals of the shorings to be installed can be reduced as compared with the conventional case, when the inner wall of the horizontal shaft is reinforced with reinforced concrete, it is easy to assemble the reinforcing bar, form the frame, and remove the box. Therefore, the working efficiency is improved and the construction period can be shortened. Also, the girder is supported by the pile driven into the tip of the cross shaft from the ground surface and the support provided at the base end of the cross shaft, and the upper girder is supported by the girder. It is possible to reliably receive the upper load acting on the work, and therefore, it is possible to reliably prevent the settlement of the ground surface.

【図面の簡単な説明】 【図1】本発明の横坑施工方法の一実施例を示すもの
で、横坑の側面図である。 【図2】図1におけるA−A線視断面図である。 【図3】図2におけるX円部の拡大図である。 【図4】図2におけるY円部の拡大図である。 【図5】図2におけるZ円部の拡大図である。 【図6】従来の横坑施工方法の一例を示すもので、横坑
の側断面図である。 【図7】同、横坑の正面図である。 【符号の説明】 2 横坑 20 上部掘削坑 22 通し桁 23 支持体 24 杭 26 下部掘削坑 JS1〜JS9 上部支保工 KS1〜KS9 下部支保工
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a side view of a cross shaft, showing one embodiment of a cross shaft construction method of the present invention. FIG. 2 is a sectional view taken along line AA in FIG. FIG. 3 is an enlarged view of an X circle portion in FIG. 2; FIG. 4 is an enlarged view of a Y circle portion in FIG. 2; FIG. 5 is an enlarged view of a Z circle portion in FIG. FIG. 6 is a side sectional view of a horizontal shaft, showing an example of a conventional horizontal shaft construction method. FIG. 7 is a front view of the horizontal shaft. [Description of Signs] 2 Horizontal shaft 20 Upper excavation shaft 22 Continuous girder 23 Support body 24 Pile 26 Lower excavation shaft JS1 to JS9 Upper support KS1 to KS9 Lower support

Claims (1)

(57)【特許請求の範囲】 【請求項1】 横坑を掘削する際の掘削断面を上下に分
割し、まず上段の掘削断面を掘削した後、この上部掘削
坑に上部支保工を設置し、次いで、該上部掘削坑に、前
記上部支保工を支持する通し桁を上部掘削坑の長手方向
に挿通して、当該通し桁に上部支保工を支持させ、次い
で、下段の掘削断面を掘削した後、この下部掘削に下部
支保工を設置してなり、掘削すべき横坑の先端部に地盤
面から杭を打ち込み、この杭と横坑の基端部に設けた支
持体とに、前記通し桁を支持させることを特徴とする横
坑施工方法。
(57) [Claims] [Claim 1] The excavation cross section for excavating the horizontal shaft is divided into upper and lower parts, and first, the upper excavation section is excavated, and then an upper support is installed in the upper excavation pit. Then, a girder supporting the upper support was inserted into the upper excavation pit in the longitudinal direction of the upper excavation pit to support the upper support on the girder, and then a lower excavation section was excavated. Later, a lower support was installed for this lower excavation.
Driving a pile from the surface,
A method for constructing a cross shaft, comprising: supporting a continuous girder with a holding body .
JP07088994A 1994-04-08 1994-04-08 Horizontal shaft construction method Expired - Fee Related JP3406370B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07088994A JP3406370B2 (en) 1994-04-08 1994-04-08 Horizontal shaft construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07088994A JP3406370B2 (en) 1994-04-08 1994-04-08 Horizontal shaft construction method

Publications (2)

Publication Number Publication Date
JPH07279576A JPH07279576A (en) 1995-10-27
JP3406370B2 true JP3406370B2 (en) 2003-05-12

Family

ID=13444554

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07088994A Expired - Fee Related JP3406370B2 (en) 1994-04-08 1994-04-08 Horizontal shaft construction method

Country Status (1)

Country Link
JP (1) JP3406370B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101249660B1 (en) * 2011-07-04 2013-04-08 신일씨엔아이(주) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure
CN113668601B (en) * 2021-07-22 2023-04-14 中铁八局集团昆明铁路建设有限公司 Subway station assembly section construction method for open cut foundation pit steel support supporting system

Also Published As

Publication number Publication date
JPH07279576A (en) 1995-10-27

Similar Documents

Publication Publication Date Title
JP4069509B2 (en) Construction method of reverse struts in the outer periphery of underground excavation space
JP3406370B2 (en) Horizontal shaft construction method
JPH07119549B2 (en) Twin tunnel
KR20070079675A (en) Method for construction of tunnel
JP3166007B2 (en) Underground structure and its construction method
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP2000291398A (en) Underground structure and construction method therefor
JP3930954B2 (en) Construction method of structure
JP2005002671A (en) Underpinning method and viaduct
JP2973815B2 (en) Construction method of pressure-resistant wall under the building
JPS63280153A (en) Underground inverted lining method
JP3135495B2 (en) Construction method of avalanche and rock fall protection fence and avalanche and rock fall protection fence
JP3109038B2 (en) Underground skeleton structure and construction method
JP2857995B2 (en) Messel shield machine
JP4319231B2 (en) Approach caisson and method for constructing tunnel approach section composed of caisson
JP2571426B2 (en) Construction method of retaining wall
JP2725972B2 (en) Underground structure construction method and segment piece used therefor
JPH0584773B2 (en)
JP2977985B2 (en) Underground space construction method
JPS63277342A (en) Reverse execution of underground story
JP3245260B2 (en) Foundation structure and construction method
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JP2572680B2 (en) Underground structure by reverse strike method
JP4399062B2 (en) Construction method of viaduct underground beam
JPH10159094A (en) Timbering structure of earth retaining wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080307

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090307

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090307

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100307

Year of fee payment: 7

LAPS Cancellation because of no payment of annual fees