JPH0584773B2 - - Google Patents

Info

Publication number
JPH0584773B2
JPH0584773B2 JP21640187A JP21640187A JPH0584773B2 JP H0584773 B2 JPH0584773 B2 JP H0584773B2 JP 21640187 A JP21640187 A JP 21640187A JP 21640187 A JP21640187 A JP 21640187A JP H0584773 B2 JPH0584773 B2 JP H0584773B2
Authority
JP
Japan
Prior art keywords
pipe
conduit
tube
sheath
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP21640187A
Other languages
Japanese (ja)
Other versions
JPS6462524A (en
Inventor
Kenichi Tsura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP21640187A priority Critical patent/JPS6462524A/en
Publication of JPS6462524A publication Critical patent/JPS6462524A/en
Publication of JPH0584773B2 publication Critical patent/JPH0584773B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】 (技術分野) 本発明は、地上に低層建築物、鉄道、道路等の
施設が設けられている土地に地中梁を構築する方
法に関し、特に、既存の施設の上方に新設する構
造物の基礎として好適な地中梁の構築方法に関す
る。
[Detailed Description of the Invention] (Technical Field) The present invention relates to a method for constructing underground beams on land where facilities such as low-rise buildings, railways, roads, etc. This paper relates to a method for constructing underground beams suitable for the foundation of new structures.

(従来技術) 地上に設けられた鉄道、道路等の施設の使用を
妨げることなく、既存の施設の上方に構造物を新
たに構築する方法としては、一般に、新設の構造
物用の基礎を既存の施設の設置箇所の地中に設
け、該基礎の上部に支柱を接続し、該支柱の上部
に構造物を構築する方法が採用されている。この
ような構造物の構築に際しては、支柱および構造
物のみならず、基礎自体も、既存の施設の使用を
妨げることなく、構築する必要がある。
(Prior art) As a method of constructing a new structure above an existing facility without interfering with the use of above-ground facilities such as railways and roads, the foundation for the new structure is generally A method has been adopted in which a structure is installed underground at the location where the facility is installed, a support is connected to the top of the foundation, and a structure is constructed on top of the support. When constructing such structures, it is necessary to construct not only the supports and structures but also the foundations themselves without interfering with the use of existing facilities.

既存の施設の使用を妨げることなく、新設の構
造物用の基礎を構築する方法の1つとして、複数
の杭を既存の施設の側部に設け、該杭を基礎とし
て用いる方法がある。しかし、このような方法で
は、基礎が複数の前記杭を備えるだけであつて基
礎梁のような地中梁、特に既存の施設を横切る方
向へ伸びる梁を備えないため、新設の構造物の耐
水平力が小さい。このようなことから、従来の方
法では、低層建築物、高架橋等高さ寸法および重
量の小さい構造物に適用することはできても、高
層建築物のように高さ寸法および重量が大きい構
造物の構築に適用することは困難である。
One method of constructing a foundation for a new structure without interfering with the use of existing facilities is to install a plurality of piles on the side of an existing facility and use the piles as a foundation. However, with this method, the foundation only includes a plurality of piles and does not include underground beams such as foundation beams, especially beams that extend across the existing facility, so the durability of the newly constructed structure is reduced. Horizontal force is small. For this reason, although conventional methods can be applied to structures with small height and weight such as low-rise buildings and viaducts, they cannot be applied to structures with large height and weight such as high-rise buildings. It is difficult to apply it to the construction of

(発明の目的) 本発明は、大きな荷重に抵抗する地中梁を、地
上に設けられた既存の施設の使用を妨げることな
く、該既存の施設の下方に梁を容易に構築するこ
とができる、地中梁の構築方法を提供することを
目的とする。
(Objective of the Invention) The present invention makes it possible to easily construct an underground beam that resists large loads under an existing facility on the ground without interfering with the use of the existing facility. , aims to provide a method for constructing underground beams.

(発明の構成) 本発明の地中梁の構築方法は、管主体部に埋設
されかつ一部が前記管主体部の内面により規定さ
れる空間内に突出する少なくとも1つの金物を備
える複数の管により規定されかつ竪坑から水平方
向に伸びる管路を管推進工法により設ける第1の
工程と、前記管路内に該管路に沿つて伸びる鉄筋
を配置する第2の工程と、前記管路内にコンクリ
ートを打設して梁を構築する第3の工程とを含む
ことを特徴とする。
(Structure of the Invention) A method for constructing an underground beam according to the present invention provides a method for constructing a plurality of pipes including at least one metal fitting buried in a main pipe part and partially protruding into a space defined by the inner surface of the pipe main part. a first step of providing a conduit defined by and extending horizontally from the shaft by a pipe propulsion method; a second step of arranging reinforcing bars extending along the conduit within the conduit; and a third step of constructing a beam by pouring concrete.

(発明の作用、効果) 第1の工程により、地上に設けられた低層建築
物、鉄道、道路等、既存の施設の下方に水平方向
に伸びる管路が設けられる。この管路は、これが
管推進工法により構築されるから、既存の施設の
使用を妨げることなく、構築される。
(Operations and Effects of the Invention) In the first step, a conduit extending horizontally below existing facilities such as low-rise buildings, railways, roads, etc. provided on the ground is provided. Since this pipeline is constructed using the pipe propulsion method, it can be constructed without interfering with the use of existing facilities.

第2および第3の工程により、地中の管路を利
用して地中梁が構築される。管路内の鉄筋とコン
クリートの固化物とからなる鉄筋コンクリート
は、管路の内部に突出する金物により管路と一体
化される。これにより、管路に作用する荷重が鉄
筋コンクリートに確実に伝達され、また鉄筋コン
クリートのみならず、管路自体も荷重を受ける梁
の一部として作用し、それらの結果大きな荷重を
梁に作用させることができる。
Through the second and third steps, underground beams are constructed using underground conduits. Reinforced concrete, which is made up of reinforcing bars and solidified concrete in the pipe, is integrated with the pipe by metal fittings that protrude into the pipe. As a result, the load acting on the pipe is reliably transmitted to the reinforced concrete, and not only the reinforced concrete but also the pipe itself acts as part of the beam that receives the load, and as a result, large loads cannot be applied to the beam. can.

本発明によれば、管主体部内に突出する金物を
備える管を用いるから、上記のように、管路自体
も梁の一部として作用し、その結果、管推進工法
により設けられた管路を利用することとあいまつ
て、大きな荷重に抵抗する地中梁を、地上に設け
られた既存の施設の使用を妨げることなく、該既
存の施設の下方に、容易に構築することができ
る。
According to the present invention, since a pipe provided with a metal fitting protruding into the main body of the pipe is used, the pipe itself also acts as a part of the beam, as described above, and as a result, the pipe installed by the pipe propulsion method can be In conjunction with this, underground beams capable of resisting large loads can be easily constructed below existing facilities on the ground without interfering with their use.

推進させる管としてヒユーム管を用いてもよい
が、ヒユーム管を用いると、管路内の鉄筋コンク
リートが管路と一体化されないから、管路に作用
する荷重が鉄筋コンクリートに効果的に伝達され
ず、また管路内の鉄筋コンクリートは荷重に抵抗
する梁として作用するが、管路自体は荷重に抵抗
する梁として効果的に作用せず、それらの結果と
して本発明に比べ梁に大きな荷重を作用させるこ
とができない。
A hume pipe may be used as the propulsion pipe, but when a hume pipe is used, the reinforced concrete inside the pipe is not integrated with the pipe, so the load acting on the pipe is not effectively transmitted to the reinforced concrete. Although the reinforced concrete in the conduit acts as a beam that resists loads, the conduit itself does not effectively act as a beam that resists loads, and as a result, it is possible to apply a larger load to the beam than in the present invention. Can not.

(実施例) 以下、図面に示す本発明の実施例について説明
する。
(Example) Hereinafter, an example of the present invention shown in the drawings will be described.

第1図Aに示すように、地上に設けられた既存
の施設20の側部には、竪坑22が掘削される。
竪坑22内には、ヒユーム管ような複数の管24
をほぼ水平方向へ推進させて管路26を形成する
既存の推進装置28が設置される。各管24の断
面形状は、矩形であつてもよいし、円形であつて
もよい。また、管24は、鋼管とすることもでき
る。各管24は、同一の寸法および形状を有す
る。推進装置28は、管24を前進させる複数の
ジヤツキを含む。
As shown in FIG. 1A, a shaft 22 is excavated on the side of an existing facility 20 provided on the ground.
Inside the shaft 22, there are a plurality of pipes 24 such as Huyume pipes.
An existing propulsion device 28 is installed which propels the pipe in a substantially horizontal direction to form the conduit 26. The cross-sectional shape of each tube 24 may be rectangular or circular. Moreover, the pipe 24 can also be made into a steel pipe. Each tube 24 has the same size and shape. Propulsion device 28 includes a plurality of jacks that advance tube 24.

各管24は、該管24をこれの最先端に配置さ
れた刃口30とともに一つの管の長さ寸法だけ推
進装置28により前進させた後、最後部に新たな
管を配置する工程の繰返しにより、徐々に前進さ
れる。これにより、管路26は徐々に延長され
る。
Each tube 24 is moved forward by the propulsion device 28 by the length of one tube with the cutting edge 30 placed at the most distal end thereof, and then a new tube is placed at the rearmost end.The process is repeated. This will lead to gradual progress. As a result, the conduit 26 is gradually extended.

管路26が竪坑22から隔てられた竪坑掘削子
定位置32,34間の距離に相当する距離だけ形
成されると、第1図B〜Dに示す伸縮体36が管
24の最後部に配置される。
When the pipe 26 is formed by a distance corresponding to the distance between the shaft excavator fixed positions 32 and 34 separated from the shaft 22, the telescopic body 36 shown in FIGS. be done.

伸縮体36は、第2図および第3図に示すよう
に、管24とほぼ同じ外径形状および寸法を有す
る矩形の鋼製ケーシング38と、ケーシング38
の内側に支承された複数のジヤツキ40とを含
む。各ジヤツキ40は、これらが管24の軸線の
周りにあつて管路26の軸線方向へ伸縮するよう
に、ベルトによりケーシング38に取り外し可能
に固定されている。
As shown in FIGS. 2 and 3, the expandable body 36 includes a rectangular steel casing 38 having approximately the same outer diameter shape and dimensions as the tube 24, and a rectangular steel casing 38.
and a plurality of jacks 40 supported inside. Each jack 40 is removably fixed to the casing 38 by a belt so that it extends and contracts around the axis of the tube 24 and in the axial direction of the conduit 26.

伸縮体36は、各ジヤツキ40が収縮された状
態で先行する管の後端に配置され、伸縮体36の
後方に新たな管が配置された後、推進装置28に
より各管24とともに前進される。
The expandable body 36 is placed at the rear end of the preceding tube with each jack 40 contracted, and after a new tube is placed behind the expandable body 36, it is advanced together with each tube 24 by the propulsion device 28. .

刃口30の前半部が第1図Cに示すように竪坑
掘削予定位置34の下方に達するまで各管24が
前進されると、伸縮体36は刃口30が竪坑掘削
予定位置34と整合するまで伸長される。これに
より、第1図Dに示すように、竪坑22から、竪
坑掘削予定位置32を経て竪坑掘削予定位置34
へ達する管路26が形成される。
When each tube 24 is advanced until the front half of the cutting edge 30 reaches below the planned shaft excavation position 34 as shown in FIG. is extended to. As a result, as shown in FIG. 1D, from the shaft 22, through the planned shaft excavation position 32,
A conduit 26 is formed that reaches the.

上記の各作業は、これらの作業を発進竪坑22
内と、地中とで行なうことができるから、地上の
既存の施設20の使用を妨げない。
Each of the above operations is carried out in the starting shaft 22.
Since it can be carried out both indoors and underground, it does not interfere with the use of existing facilities 20 above ground.

次に、第4図Aに示すように、推進装置28が
取り外されるとともに、伸縮体36のジヤツキ4
0が取り外され、竪坑22の底部および竪坑掘削
予定位置32,34にそれぞれ杭42が設けられ
る。竪坑掘削予定位置32に杭を設けるときは、
伸縮体36のケーシング38の底部の一部が切断
され、除去される。杭42は、場所打杭とするこ
とが望ましい。
Next, as shown in FIG. 4A, the propulsion device 28 is removed and the jack 4 of the telescoping body 36 is
0 is removed, and piles 42 are provided at the bottom of the shaft 22 and at the planned shaft excavation positions 32 and 34, respectively. When installing piles at the planned shaft excavation position 32,
A portion of the bottom of the casing 38 of the telescopic body 36 is cut and removed. The piles 42 are preferably cast-in-place piles.

ジヤツキ40の徹去作業、ケーシングの切断作
業および杭構築作業のための大口径ボーリング掘
削機の搬入は、管路26を利用して行なうことが
できる。また、掘削土砂は、管路26を利用し
て、竪坑22から排出することができる。従つ
て、これらの杭打のための各作業も、既設の施設
20の使用を妨げることなく行なうことができ
る。
A large-diameter boring excavator for removing the jack 40, cutting the casing, and constructing the pile can be carried in using the conduit 26. Moreover, excavated earth and sand can be discharged from the shaft 22 using the pipe line 26. Therefore, each of these pile driving operations can be performed without interfering with the use of the existing facility 20.

次に、第4図Bに示すように、刃口30が除去
され、竪坑掘削予定位置32,34に竪坑44,
46が掘削される。竪坑44,46は、管路26
を利用して所定の部位を下方から上方へ掘削すれ
ば、既存の施設20の使用を妨げることなく、掘
削することができる。このときの掘削土砂も、管
路26を利用して竪坑22から排出することがで
きる。
Next, as shown in FIG. 4B, the cutting edge 30 is removed, and the shaft 44 is placed at the planned shaft excavation positions 32, 34.
46 will be excavated. The shafts 44 and 46 are connected to the pipe line 26
If a predetermined portion is excavated from below to above using the excavation method, the excavation can be performed without interfering with the use of the existing facility 20. The excavated earth and sand at this time can also be discharged from the shaft 22 using the pipe line 26.

次いで、管路26内に複数の鉄筋を用いた鉄筋
籠48が挿入され、竪坑22,44,46のそれ
ぞれに上下方向へ伸びる鉄筋籠50が配置された
後、各竪坑22,44,46の各鉄筋籠50の周
りに型枠が配置され、該型枠により規定される空
間内および管路26内にコンクリートが打設され
る。
Next, a reinforcing bar cage 48 using a plurality of reinforcing bars is inserted into the conduit 26, and a reinforcing bar cage 50 extending in the vertical direction is placed in each of the shafts 22, 44, 46. A formwork is arranged around each reinforcing bar cage 50, and concrete is poured into the space defined by the formwork and into the pipe line 26.

これにより、第4図Cに示すように、管路26
に梁52が形成され、各竪坑22,44,46に
該竪坑から地上へ伸びる支柱54が形成される。
梁52および各支柱54は、相互におよび杭42
に連結される。これらの作業も、管路26を利用
して行なうことができる。管路26を規定する管
24は、これが管路26内に打設されたコンクリ
ートと結合されるから、梁52の一部として機能
する。
As a result, as shown in FIG. 4C, the pipe line 26
A beam 52 is formed in each of the shafts 22, 44, and 46, and a support column 54 is formed in each shaft 22, 44, 46, extending from the shaft to the ground.
The beam 52 and each post 54 are connected to each other and to the pile 42
connected to. These operations can also be performed using the conduit 26. The tube 24 defining the conduit 26 functions as part of the beam 52 because it is bonded to the concrete placed within the conduit 26.

上記の手法により、既存の施設20の下方に
は、第5図に示すように、竪坑22,44,46
から梁52と直交する方向へ伸びる梁56および
他の複数の竪坑58,60から梁52と平行に伸
びる梁62が形成される。このため、既存の施設
20の下方には、梁が格子状に構築される。
With the above method, the vertical shafts 22, 44, 46 are located below the existing facility 20, as shown in FIG.
A beam 56 extending from the shaft in a direction perpendicular to the beam 52 and a beam 62 extending parallel to the beam 52 from the other plurality of shafts 58 and 60 are formed. For this reason, beams are constructed in a grid pattern below the existing facility 20.

第5図に示す格子状の梁は、たとえば、第4図
Bに示すように竪坑22から竪坑46へ向かう管
路26を形成した後、竪坑44,46への構築作
業、第5図に示すように竪坑22,44,46か
ら矢印64の方向へ伸びる管路の構築作業、該管
路の途中および先端部への竪坑58,60の構築
作業、第5図に示すように竪坑60から矢印66
の方向へ伸びる管路の構築作業、各竪坑22,4
4,46,58,60への坑42および支柱(図
示せず)の構築作業、各管路への鉄筋籠の配置作
業、および、各管路へのコンクリートの打設作業
をその順にまたは適宜な順番で行なうことにより
構築することができる。
The lattice-shaped beams shown in FIG. 5 are constructed, for example, after forming the pipe 26 from the shaft 22 to the shaft 46 as shown in FIG. As shown in FIG. 66
Construction work for pipelines extending in the direction of each shaft 22, 4
4, 46, 58, and 60, construction work of the shafts 42 and supports (not shown), placement work of reinforcing bar cages in each conduit, and work of pouring concrete into each conduit in that order or as appropriate. It can be constructed by performing the steps in the following order.

第5図における各坑、各支柱および各梁の構築
時の管24等の資材の搬入作業、掘削土砂の搬出
作業は、竪坑22からのみ行なつてもよいし、他
の竪坑44,46,56を利用して行なつてもよ
い。
The work of carrying in materials such as the pipe 24 and the work of transporting excavated earth and sand during the construction of each shaft, each support and each beam in FIG. 5 may be performed only from the shaft 22, or from the other shafts 44, 46, 56 may also be used.

第6図は、上記の手法により複々線の鉄道線路
70の下方に形成された梁52を、竪坑22,4
4,46に設けられた杭42および支柱54とと
もに示す。竪坑44は、鉄道線路70の用地の幅
方向中央部に掘削される。
FIG. 6 shows a beam 52 formed below a multiple-track railway track 70 by the above-described method.
4 and 46 with the piles 42 and struts 54 provided therein. The shaft 44 is excavated at the center in the width direction of the land for the railway line 70.

第7図は、上記の手法により道路の下方に構築
された梁52および杭42から上方へ伸びる支柱
54の上部に構築されたコンクリート建築物72
を示す。中央に配置された支柱54は、左右の車
道74を相互に分離する中央分離帯76から地上
に突出する。これに対し、両側部の支柱は、車道
74の側部から地上に突出させることができる
し、歩道78から地上に突出させることもでき
る。なお、杭42、梁52および支柱54は、ガ
ス管、水道管のような埋設物80および下水管の
ような埋設物82を避けて構築される。
FIG. 7 shows a concrete building 72 constructed on top of the pillars 54 extending upward from the beams 52 and piles 42 constructed below the road by the method described above.
shows. The centrally located pillar 54 projects above the ground from a median strip 76 that separates the left and right roadways 74 from each other. On the other hand, the pillars on both sides can be made to protrude above the ground from the sides of the roadway 74, or can be made to protrude above the ground from the sidewalk 78. Note that the piles 42, beams 52, and supports 54 are constructed avoiding buried objects 80 such as gas pipes and water pipes, and buried objects 82 such as sewer pipes.

第8図および第9図は、上記のような構築方法
における管推進工法で用いる管24の一実施例を
示す。管24は、管主体部にこれの軸線の周りに
間隔をおいて埋設されかつ管主体部を前記軸線方
向へ貫通する複数のシース管84と、該シース管
を取り巻くように配置された環状の複数の鉄筋8
6と、シース管84から管24の中心に向け伸び
て一部が前記管主体部の内面により規定される空
間内に突出する短尺の複数の鉄筋すなわち金物8
8とを備える。
FIGS. 8 and 9 show an embodiment of the pipe 24 used in the pipe propulsion method in the construction method described above. The tube 24 includes a plurality of sheath tubes 84 which are embedded in the tube main body at intervals around the axis of the tube and which penetrate the tube main body in the axial direction, and an annular sheath tube arranged to surround the sheath tubes. multiple reinforcing bars 8
6, and a plurality of short reinforcing bars or hardware 8 that extend from the sheath pipe 84 toward the center of the pipe 24 and partially protrude into the space defined by the inner surface of the main body of the pipe.
8.

第8図および第9図に示す管24は、第10図
に示すように、管24を該管のシース管84が隣
接する管24のシース管84と整合するように管
推進工法により地中に配置される。シース管84
には、各管24を経て管路の軸線方向へ伸びる長
尺の鉄筋90が通される。長尺の鉄筋90は、そ
の後シース管84内に注入されるグラフト材によ
り、管24に定着される。
The pipe 24 shown in FIGS. 8 and 9 is inserted into the ground by a pipe propulsion method so that the sheath pipe 84 of the pipe is aligned with the sheath pipe 84 of the adjacent pipe 24, as shown in FIG. 10. will be placed in sheath tube 84
A long reinforcing bar 90 is passed through each pipe 24 and extends in the axial direction of the pipe line. The elongated reinforcing bar 90 is then secured to the tube 24 by a graft material that is injected into the sheath tube 84.

これにより、隣り合う管24が鉄筋90および
グラウト材により互いに連結されるから、隣り合
う管が互いに連結されない場合に比べ、強固な管
路が形成され、その管路で大きな荷重を受けるこ
とができる。
As a result, the adjacent pipes 24 are connected to each other by the reinforcing bars 90 and the grout material, so that a stronger pipe is formed than in the case where adjacent pipes are not connected to each other, and the pipe can bear a large load. .

第10図に示す管路26内にも、鉄筋籠48が
配置され、コンクリートが打設される。これによ
り、金物88のうち、管路26内に突出する部分
は、コンクリート内に埋め込まれる。竪坑44に
配置された鉄筋籠50の周りの型枠92により規
定される空間にも打設される。
A reinforcing bar cage 48 is also placed inside the conduit 26 shown in FIG. 10, and concrete is placed therein. As a result, the portion of the hardware 88 that protrudes into the pipe line 26 is embedded in the concrete. It is also cast in the space defined by the formwork 92 around the reinforcing bar cage 50 placed in the shaft 44.

管路26内の鉄筋籠48とコンクリートの固化
物とからなる鉄筋コンクリートは、管路26の内
部に突出する金物88により管路26と一体化さ
れる。これにより、管路26に作用する荷重が効
果的に鉄筋コンクリートに伝達され、また鉄筋コ
ンクリートのみならず、管路26自体が荷重を受
ける梁として作用し、それらの結果大きな荷重を
地中梁に作用させることができる。
The reinforced concrete made up of the reinforcing bar cage 48 and solidified concrete in the pipe line 26 is integrated with the pipe line 26 by a metal fitting 88 protruding into the pipe line 26 . As a result, the load acting on the pipe 26 is effectively transmitted to the reinforced concrete, and not only the reinforced concrete but also the pipe 26 itself acts as a beam receiving the load, and as a result, a large load is applied to the underground beam. be able to.

しかし、推進させる管としてヒユーム管を用い
ると、管路内の鉄筋コンクリートが管路と一体化
されないから、管路に作用する荷重が鉄筋コンク
リートに効果的に伝達されず、また管路内の鉄筋
コンクリートは荷重に抵抗する梁として作用する
が、管路自体は荷重に抵抗する梁として効果的に
作用せず、それらの結果梁に大きな荷重を作用さ
せることができないことは、既に述べたとおりで
ある。
However, when a Huyum pipe is used as a propulsion pipe, the reinforced concrete inside the pipe is not integrated with the pipe, so the load acting on the pipe is not effectively transmitted to the reinforced concrete, and the reinforced concrete inside the pipe is However, as already mentioned, the conduit itself does not effectively act as a beam that resists the load, and as a result, it is not possible to apply a large load to the beam.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は管推進工法により管路を形成する過程
を説明するための縦断面図、第2図は管推進工法
で用いる伸縮体の一実施例を示す縦断面図、第3
図は第2図に示す伸縮体の右側面図、第4図は
杭、梁および支柱を構築する過程を説明するため
の縦断面図、第5図は構築された梁の一実施例を
示す平面図、第6図は鉄道線路の下方に構築され
た梁を示す縦断面図、第7図は道路の下方に構築
された梁を基礎として使用する建築物の一実施例
を示す図、第8図は本発明で用いる管の一実施例
を示す縦断面図、第9図は第8図の9−9線に沿
つて得た断面図、第10図は第9図に示す管を用
いて梁を構築する例を示す断面図である。 20:既存の施設、22,44,46,58,
60:竪坑、24:管、26:管路、28:推進
装置、30:刃口、42:杭、48,50:鉄筋
籠、52,56,62:梁、54:支柱、84:
シース管、86:環状の鉄筋、88:金物、9
0:長尺の鉄筋。
Fig. 1 is a longitudinal cross-sectional view for explaining the process of forming a conduit by the pipe propulsion method, Fig. 2 is a longitudinal cross-sectional view showing an example of an expandable body used in the pipe propulsion method, and Fig. 3
The figure is a right side view of the expandable body shown in Fig. 2, Fig. 4 is a vertical cross-sectional view for explaining the process of constructing piles, beams, and supports, and Fig. 5 shows an example of the constructed beam. A plan view, Fig. 6 is a vertical cross-sectional view showing a beam constructed below a railway track, Fig. 7 is a diagram showing an example of a building using a beam constructed below a road as a foundation, and Fig. FIG. 8 is a longitudinal cross-sectional view showing one embodiment of the tube used in the present invention, FIG. 9 is a cross-sectional view taken along line 9-9 in FIG. 8, and FIG. FIG. 3 is a sectional view showing an example of constructing a beam using 20: Existing facilities, 22, 44, 46, 58,
60: Pit, 24: Pipe, 26: Conduit, 28: Propulsion device, 30: Blade, 42: Pile, 48, 50: Rebar cage, 52, 56, 62: Beam, 54: Support, 84:
Sheath pipe, 86: Annular reinforcing bar, 88: Hardware, 9
0: Long reinforcing bar.

Claims (1)

【特許請求の範囲】 1 管主体部に埋設されかつ一部が前記管主体部
の内面により規定される空間内に突出する少なく
とも1つの金物を備える複数の管により規定され
かつ竪坑から水平方向に伸びる管路を管推進工法
により設ける第1の工程と、前記管路内に該管路
に沿つて伸びる鉄筋を配置する第2の工程と、前
記管路内にコンクリートを打設して梁を構築する
第3の工程とを含む、地中梁の構築方法。 2 前記各管は、前記管主体部に埋設されかつ該
管主体部を前記管の軸線方向に貫通する少なくと
も1つのシース管を備え、前記第1の工程は、前
記シース管が前記管路の軸線方向に伸びるよう
に、隣り合う管の前記シース管を整合させた状態
で、前記各管を前進させ、前記各管を経て前記軸
線方向に伸びる長尺の鉄筋を前記シース管内に通
し、前記長尺の鉄筋をグラウト材により前記シー
ス管路に定着することを含む、特許請求の範囲第
1項に記載の地中梁の構築方法。
[Scope of Claims] 1. Defined by a plurality of pipes including at least one metal fitting buried in a pipe main body and partially protruding into a space defined by the inner surface of the pipe main body, and extending horizontally from a shaft. A first step of installing an extending conduit using the pipe propulsion method, a second step of arranging reinforcing bars extending along the conduit within the conduit, and placing concrete within the conduit to form a beam. and a third step of constructing an underground beam. 2. Each of the pipes includes at least one sheath pipe that is embedded in the pipe main body and passes through the pipe main body in the axial direction of the pipe, and in the first step, the sheath pipe is connected to the pipe line. With the sheath tubes of adjacent tubes aligned so as to extend in the axial direction, each tube is advanced, and a long reinforcing bar extending in the axial direction is passed through each tube into the sheath tube, and the The method for constructing an underground beam according to claim 1, which includes fixing long reinforcing bars to the sheath pipe with grout.
JP21640187A 1987-09-01 1987-09-01 Construction of underground beam Granted JPS6462524A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21640187A JPS6462524A (en) 1987-09-01 1987-09-01 Construction of underground beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21640187A JPS6462524A (en) 1987-09-01 1987-09-01 Construction of underground beam

Publications (2)

Publication Number Publication Date
JPS6462524A JPS6462524A (en) 1989-03-09
JPH0584773B2 true JPH0584773B2 (en) 1993-12-03

Family

ID=16687985

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21640187A Granted JPS6462524A (en) 1987-09-01 1987-09-01 Construction of underground beam

Country Status (1)

Country Link
JP (1) JPS6462524A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4529631B2 (en) * 2004-10-15 2010-08-25 株式会社大林組 Underground structure and construction method of underground structure
JP4722783B2 (en) * 2006-07-03 2011-07-13 株式会社竹中工務店 Foundation reinforcement method for existing buildings
JP4993131B2 (en) * 2008-03-03 2012-08-08 新日本製鐵株式会社 Foundation reinforcement method for existing structures
JP4751425B2 (en) * 2008-07-11 2011-08-17 株式会社フジタ Construction method of foundation structure
JP6675173B2 (en) * 2015-11-10 2020-04-01 株式会社竹中工務店 Foundation building method

Also Published As

Publication number Publication date
JPS6462524A (en) 1989-03-09

Similar Documents

Publication Publication Date Title
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
JP4881555B2 (en) Construction method of underground structure
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JP2006328666A (en) Construction method for integrating pile with column
JP2001520340A (en) Arch support structure
KR100784201B1 (en) Method for construction of tunnel
JPH0584773B2 (en)
JP4165531B2 (en) Tunnel construction method and tunnel constructed by this tunnel construction method
JP2762133B2 (en) How to build a large architectural space underground
JP3930954B2 (en) Construction method of structure
KR100753140B1 (en) Steel pipe roof assembly and the construction method for tunnel using thereof
JP5073960B2 (en) Construction method of underground structure and underground structure
JP3999853B2 (en) How to build a tunnel
JPH07243269A (en) Method of building underground parking lot
JP2700694B2 (en) How to build a large architectural space underground
KR102170804B1 (en) Construction method of underground structure using special guidance pipe
JPH07103583B2 (en) Construction method for large span underground structure
JP2733542B2 (en) How to build underground structures
JPH0414599A (en) Construction of branch section of underground level and construction method
JP4319122B2 (en) Branch and junction structure of branching tunnel and its construction method
JPH04185816A (en) Construction of beam in underground wall
KR19980014364A (en) New installation method of temporary structures for tunnel formation
JP2003206697A (en) Construction method of underground structure
KR20030088398A (en) Underway Tunneling Methods of arch typed Triangle Elementary pipe-roof
JPS61134441A (en) Method of reinforcing foundation ground of building