JP2700694B2 - How to build a large architectural space underground - Google Patents
How to build a large architectural space undergroundInfo
- Publication number
- JP2700694B2 JP2700694B2 JP1234075A JP23407589A JP2700694B2 JP 2700694 B2 JP2700694 B2 JP 2700694B2 JP 1234075 A JP1234075 A JP 1234075A JP 23407589 A JP23407589 A JP 23407589A JP 2700694 B2 JP2700694 B2 JP 2700694B2
- Authority
- JP
- Japan
- Prior art keywords
- constructing
- shaft
- traveling
- underground
- shield
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】 産業上の利用分野 この発明は、主に大都市の既存建物の下の所謂50m以
深の大深度地下に、床面直径が100mにも及ぶ大規模な建
築大空間を作る目的で実施される、大深度地下の建築大
空間の構築方法関する。The present invention relates to a large-scale architectural space with a floor diameter as large as 100m, which is mainly located under a so-called 50m deep under an existing building in a large city. It relates to a method of constructing a large underground architectural space to be implemented for the purpose of making.
従来の技術 従来、地下空間を構築する技術としては、開削工法や
シールド工法などが一般的に実施されている。2. Description of the Related Art Conventionally, as a technique for constructing an underground space, a digging method, a shield method, and the like are generally implemented.
開削工法は、まず地上から地下空間の外周壁に相当す
る部分を掘削し、その掘削部分に鉄筋を挿入しコンクリ
ートを打設して地下壁を構築し、しかる後に地下壁に囲
まれた地盤を掘削する工法である。In the excavation method, first, a portion corresponding to the outer peripheral wall of the underground space is excavated from the ground, a reinforcing bar is inserted into the excavated portion, concrete is cast, and an underground wall is constructed, and then the ground surrounded by the underground wall is constructed. Excavation method.
また、シールド工法は、シールドマシンと呼ばれる強
固な円筒形の鋼殻を地中に押し込み、この鋼殻によって
防護された部分の前面の地山を掘削し、後部では円筒形
の鋼殻とほぼ同じ大きさのリング状の覆工(セグメン
ト)を組み立てて既に掘削されたトンネル空間を保護す
ると共に、この覆工に反力をとってシールドマシンを前
進させる手順を繰り返してトンネルを構築する工法であ
る。In the shield method, a strong cylindrical steel shell called a shield machine is pushed into the ground, the ground in front of the part protected by this steel shell is excavated, and the rear part is almost the same as a cylindrical steel shell. This is a method of assembling a ring-shaped lining (segment) to protect the already excavated tunnel space, and constructing a tunnel by repeating the procedure of moving the shield machine forward by taking a reaction force to this lining. .
なお、シールド工法の特殊な応用技術として、特開昭
64−43699号公報に記載された地下空洞の施工法は、地
上から縦坑を構築し、この縦坑の下端部からシールドマ
シンを発進させて環状又はスパイラル状のシールドトン
ネルを構築し、このシールドトンネルの断面内をコンク
リートで充填して補強し、こうして構築された地下外周
壁躯体で囲まれた内側の地盤を掘削して大空洞を形成す
る内容になっている。As a special application technology of the shield method,
The method of constructing an underground cavity described in Japanese Patent Publication No. 64-43699 discloses a method of constructing a shaft from the ground, starting a shield machine from the lower end of the shaft, and constructing an annular or spiral shield tunnel. The inside of the tunnel section is filled with concrete and reinforced, and the inside ground surrounded by the underground outer wall frame constructed in this way is excavated to form a large cavity.
本発明が解決しようとする課題 上述した開削工法の場合は、地上の既存建物の下に地
下空間を構築することはできない。また、地下壁を地上
から掘削するために施工精度に技術的な限界があり、地
下の深度が深くなると正確な鉛直性を保持し難い。しか
も途中には土砂の崩壊もあるため、せいぜい地下30m程
度の深さまでしか施工することができない。Problems to be Solved by the Present Invention In the case of the above-described open-cutting method, an underground space cannot be constructed under an existing building on the ground. In addition, there is a technical limit in construction accuracy for excavating the underground wall from the ground, and it is difficult to maintain accurate verticality when the depth of the underground is deep. In addition, because of the collapse of earth and sand on the way, it can be constructed only up to a depth of about 30m underground.
シールド工法の場合は、既存建物の下にも50m以深の
大深度に及ぶトンネルを構築することは可能である。し
かし、現在のシールドトンネルは直径がせいぜい10数m
のトンネル空間しか構築することができない。したがっ
て、床面直径が100m前後に及ぶ地下大空間を構築する目
的にはとうてい供し得ないので、これらの点が解決する
べき課題となっている。In the case of the shield method, it is possible to construct a tunnel that extends deeper than 50m below existing buildings. However, the current shield tunnel is at most 10 meters in diameter
Only the tunnel space can be built. Therefore, it cannot be used for the purpose of constructing a large underground space with a floor diameter of about 100 m, and these points are issues to be solved.
次に、上記特開昭64−43699号公報に記載された地下
空洞の施工法は、大深度の地下大空間の実現性を予感さ
せるほど画期的な技術思想であることは認められる。し
かし、シールドトンネルの構築、及びシールドトンネル
を外周壁躯体に完成する手順とその信頼性、さらにはせ
っかく形成された地下大空洞を人間の有効空間としてど
の様に活用するかの具体性に乏しい内容と言わねばなら
ない。例えば環状又はスパイラル状のシールドトンネル
の断面内にコンクリートを充填しただけでは、土圧や地
下水圧に対して十分な強度、剛性を期待し難く安全とは
云えない。また、地下に大空洞を創るだけが最終目的で
はなく、その大空洞を如何に合理的に有用な建築大空間
に創るかが究極の目的であるはずだから、これらの諸点
がなお解決するべき課題と言わねばならないのである。Next, it is recognized that the method of constructing an underground cavity described in the above-mentioned Japanese Patent Application Laid-Open No. 64-43699 is a groundbreaking technical idea that foresees the realization of a large underground large space. However, the procedure for building the shield tunnel and completing the shield tunnel in the outer wall frame and its reliability, and the specifics of how to use the formed underground large cavity as an effective space for humans are poorly specific. I must say. For example, simply filling concrete in the cross section of an annular or spiral shield tunnel is not safe because it is difficult to expect sufficient strength and rigidity against earth pressure and groundwater pressure. In addition, creating a hollow space under the ground is not the ultimate purpose, but how to create the hollow space in a reasonably useful architectural space should be the ultimate purpose, so these issues still need to be solved. I must say.
課題を解決するための手段 上記従来技術の課題を解決するための手段として、こ
の発明に係る大深度地下に建築大空間を構築する方法
は、図面に実施例を示したとおり、 地下の建築大空間に十分達する深さの縦坑1を構築
し、前記縦坑1の途中の大深度位置から水平方向に先進
導坑2を構築する段階と、 前記縦坑1の途中位置からシールドマシンを発進させ
て前記先進導坑2に外接するスパイラル状のシールドト
ンネル3を順次水平方向に構築すると共に前後に隣接す
るシールドトンネル3,3同士は互いに緊結し、シールド
トンネル3の断面内に補強材10を充填して外周壁躯体4
を構築する段階と、 前記外周壁躯体4で囲まれた内側部分の地盤5を掘削
して大空洞6を形成する段階と、 前記大空洞6の床部のトラベリング用レール7を敷設
し、該トラベリング用レール上7の前記縦坑1に相当す
る部位で柱8a、梁8b、床8cによる多層階の内部建築躯体
9のトラベリング用ユニット8を1ユニット分だけ構築
し、この1ユニットはトラペリング用レール7上を前方
へ所定ストローク移動させ、以下トラベリング用ユニッ
ト8の構築とそのトラベリングとを繰り返す段階と、 から成ることを特徴とする。Means for Solving the Problems As a means for solving the problems of the prior art, a method for constructing an architectural large space in a deep underground according to the present invention is described as follows. Constructing a vertical shaft 1 having a depth sufficient to reach a space, constructing an advanced shaft 2 in a horizontal direction from a large depth position in the middle of the vertical shaft 1, and starting a shield machine from a middle position in the vertical shaft 1 Then, a spiral shield tunnel 3 circumscribing the advanced shaft 2 is sequentially constructed in a horizontal direction, and the shield tunnels 3, 3 adjacent to each other in front and rear are tightly connected to each other, and a reinforcing material 10 is provided in the cross section of the shield tunnel 3. Filling and outer wall frame 4
Building a large cavity 6 by excavating the ground 5 at the inner portion surrounded by the outer peripheral wall skeleton 4, laying a traveling rail 7 on the floor of the large cavity 6, At a position corresponding to the shaft 1 on the traveling rail 7, a traveling unit 8 of a multi-story internal building frame 9 composed of columns 8 a, beams 8 b, and floor 8 c is constructed for one unit, and this one unit is trapping. Moving the rail forward a predetermined stroke on the rail 7 and repeating the construction of the traveling unit 8 and the traveling thereof thereafter.
作用 縦坑1と先進導坑2はシールドマシンの発進基地とな
る。また、大深度地下の工事のための資材類、機械、設
備類の搬出入や掘削した土の搬出にも使用される。先進
導坑2は、地盤調査や地下水圧調査にも使用され、さら
に外周壁躯体4の工事に必要な資材類の搬出入にも利用
される。Operation The shaft 1 and the advanced shaft 2 are the starting points for the shield machine. It is also used for loading and unloading materials, machinery and equipment for deep underground construction, and for removing excavated soil. The advanced shaft 2 is also used for ground surveys and groundwater pressure surveys, and is also used for carrying in and out materials necessary for construction of the outer peripheral wall frame 4.
大口径のシールドマシンで掘削を進めることにより、
スパイラルの直径が100m前後のスパイラル状のシールド
トンネル3が構築される。By drilling with a large-diameter shield machine,
A spiral shield tunnel 3 having a spiral diameter of about 100 m is constructed.
前後に重なり合ったシールドトンネル3同士を互いに
緊結し、さらにシールドトンネル3内に鉄骨や鉄筋など
の補強材を配置しコンクリート10を充填して補強するこ
とにより、巨大な断面で大強度、大剛性の外周壁躯体4
が構築される。この外周壁躯体4は、内部建築躯体9に
負荷されるべき土圧や地下水圧を支える超大形構造物と
して働く。The shield tunnels 3 that overlap each other are tied to each other, and reinforcing materials such as steel frames and rebars are placed in the shield tunnels 3 and filled with concrete 10 to reinforce them. Outer wall frame 4
Is constructed. The outer wall skeleton 4 functions as a super-large structure that supports earth pressure and groundwater pressure to be applied to the inner building skeleton 9.
従って、前記外周壁躯体4の内側の地盤5を掘削する
ことにより大空洞6ができる。Therefore, a large cavity 6 is formed by excavating the ground 5 inside the outer peripheral wall frame 4.
前記外周壁躯体4で保護された内側の大空洞6におい
て、内部建築躯体9のトラベリング用ユニット8を1ユ
ニットずつ構築する事は、地上での作業とほとんど変わ
らぬ条件で行なわれる。その1ユニットずつをトラベリ
ングして相互の接合を行なうことで大規模な内部建築躯
体9が完成するので、地下空洞内での工事であっても安
全で信頼性の高い工事を能率良くできる。In the inner large cavity 6 protected by the outer peripheral wall frame 4, building the traveling units 8 of the internal building frame 9 one by one is performed under almost the same conditions as the work on the ground. A large-scale internal building frame 9 is completed by traveling each unit and joining them together, so that safe and highly reliable construction can be efficiently performed even in construction in an underground cavity.
実 施 例 次に、図示した本発明の実施例を説明する。Embodiment Next, the illustrated embodiment of the present invention will be described.
第1図は、地上に既存建物11が存在する場所の大深度
地下に建築大空間を構築するための足がかりとなるよう
に、前記の既存建物11より少し離れた位置から縦坑1を
ほぼ垂直に所要の深さまで掘削して構築し、さらに前記
縦坑1の途中大深度位置から水平方向に先進導坑2を掘
削して構築した階段を示している。縦坑1及び先進導坑
2は、既存建物11の安全性を毀損しないように注意して
掘削し構築される。この縦坑1と先進導坑2は、シール
ドマシンの発進基地として使用され、あるいは機械や設
備類の搬出入、掘削した土の搬出に使用されるものなの
で、そうした用途に適合する大きさの口径で掘削し構築
される。縦坑1は、地下の建築大空間の外周壁躯体4の
最深部にまで達する深さまで掘削し構築されている(第
2図以下を参照)。先進導坑2は、同じ外周壁躯体4の
奥行きよりも十分に長く掘削し構築されている(第2図
以下を参照)。FIG. 1 shows that the shaft 1 is almost vertical from a position slightly away from the existing building 11 so that it can be used as a foothold for constructing an architectural large space deep underground where the existing building 11 exists on the ground. 2 shows a staircase constructed by excavating to a required depth, and further excavating and constructing an advanced shaft 2 in a horizontal direction from a large depth position in the vertical shaft 1. The shaft 1 and the advanced shaft 2 are excavated and constructed with care so as not to impair the safety of the existing building 11. The shaft 1 and the advanced shaft 2 are used as a starting base for shield machines, or used to carry in and out machines and equipment, and carry out excavated soil. Excavated and built. The shaft 1 is excavated and constructed to a depth reaching the deepest portion of the outer peripheral wall frame 4 of the large underground building space (see FIG. 2 and subsequent figures). The advanced shaft 2 is excavated and constructed sufficiently longer than the depth of the same outer peripheral wall skeleton 4 (see FIG. 2 et seq.).
第2図は、前記縦坑1の途中位置、即ち、先進導坑2
を構築した地下50m以深の所謂大深度位置において水平
方向左向きにシールドマシンを発進させ、スパイラル状
をなすシールドトンネル3を構築した段階を示してい
る。シールドトンネル3は、その横断面の直径を10数
m、スパイラルの直径を100m程度の規模で構築されてい
る。そのためシールドマシンの鋼殻はスパイラルの曲率
と同じ曲率に湾曲された所謂R付き胴のシールドマシン
が使用され、シールドトンネル3は順次図中の左向きに
構築が進められている。但し、シールドトンネル3は円
形のスパイラルに限らず、角形のスパイラルなどとして
構築することも行なわれる。FIG. 2 shows the position of the shaft 1 in the middle, that is, the advanced shaft 2.
This shows a stage in which the shield machine is started to the left in the horizontal direction at a so-called deep position at a depth of 50 m or less underground, and the spiral shield tunnel 3 is constructed. The shield tunnel 3 is constructed on a scale having a cross section diameter of about several tens of meters and a spiral diameter of about 100 m. For this reason, a so-called R-barreled shield machine in which the steel shell of the shield machine is curved to the same curvature as that of the spiral is used, and the shield tunnel 3 is being constructed sequentially to the left in the figure. However, the shield tunnel 3 is not limited to a circular spiral, but may be constructed as a square spiral or the like.
シールドトンネル3は1周回の度に先進導坑2との接
点を持ち、その接点に設けられた通路12を利用して、掘
削された土の搬出が先進導坑2に向かって短距離に行な
われる。スパイラル状のシールドトンネル3は、前後の
シールド同士が重なり合う状態に構築され、前後に重な
り合ったシールドトンネル同士は、例えばトンネル長手
方向に一定のピッチで相互に貫通する孔13を掘り、該孔
13の中に補強材としての鉄筋や鉄骨を入れ、コンクリー
トを充填する等の方法で強固に緊結して一体化と剛性の
確保が行なわれている。The shield tunnel 3 has a contact point with the advanced shaft 2 every round, and the excavated soil is carried out a short distance toward the advanced shaft 2 by using the passage 12 provided at the contact point. It is. The spiral shield tunnel 3 is constructed in a state where the front and rear shields overlap each other. The shield tunnels which overlap each other are digged, for example, through holes 13 penetrating each other at a constant pitch in the longitudinal direction of the tunnel.
A reinforcing bar or steel frame as a reinforcing material is put in the block 13 and concrete is filled, for example, to firmly tie them together to secure integration and rigidity.
第3図は、上記シールドトンネル3の内部に補強材と
しての鉄骨や鉄筋を配設し、さらにコンクリート10を全
断面に充填して地下に外周壁躯体4の構築を完成した段
階を示している。この結果、断面の厚さが10数mに及ぶ
巨大な外周壁躯体4ができる。FIG. 3 shows a stage in which a steel frame or a reinforcing bar as a reinforcing material is disposed inside the shield tunnel 3 and concrete 10 is filled in all sections to complete the construction of the outer peripheral wall frame 4 underground. . As a result, a huge outer peripheral wall body 4 having a cross-sectional thickness of several tens of meters is formed.
第4図は、上記のようにして完成された地下の外周壁
躯体4で囲まれた内側の地盤5を掘削して大空洞6を形
成しつつある段階を示している。FIG. 4 shows a stage in which a large cavity 6 is being formed by excavating the inner ground 5 surrounded by the underground outer peripheral wall frame 4 completed as described above.
第5図は、上記のようにして形成された大空洞6の床
部にトラベリング用レール7を敷設し、このトラベリン
グ用レール7上の特に上記縦坑1に相当する部位(つま
り図中右端の縦坑壁に近接した部位)で内部建築躯体9
の構成要素であるトラベリング用ユニット8を1ユニッ
ト分だけ構築を始めた段階を示し、第6図はその1ユニ
ットを縦坑1の坑壁に反力を取った油圧ジャッキ14で所
定のストロークだけ左方へトラベリング(移動)させた
段階を示している。FIG. 5 shows that a traveling rail 7 is laid on the floor of the large cavity 6 formed as described above, and a portion of the traveling rail 7 particularly corresponding to the shaft 1 (that is, a right end in the figure). Internal building frame 9 at the site near the shaft wall)
Fig. 6 shows a stage in which the construction of a single traveling unit 8 as a component of the above is started, and FIG. This shows a stage in which traveling (moving) is performed to the left.
内部建築躯体9は、通常の鉄筋コンクリート造又は鉄
骨鉄筋コンクリート造建物と同様に柱8aと梁8b及び床8c
とから成る多層階の建築構造物として構築されている。
そのトラベリング用ユニット8は、前記構造の内部建築
躯体9を縦割りに数分割した構成とされている。1ユニ
ットの規模は、縦坑1の坑壁部に反力をとった油圧ジャ
ッキ14のような駆動手段で所定ストロークのトラベリン
グが可能な形状、重量の大きさとされている。The internal building frame 9 includes columns 8a, beams 8b and floors 8c as in a normal reinforced concrete or steel reinforced concrete building.
It is constructed as a multi-story building structure consisting of:
The traveling unit 8 has a structure in which the internal building frame 9 of the above structure is vertically divided into several parts. The size of one unit is set to a shape and weight capable of traveling a predetermined stroke by a driving means such as a hydraulic jack 14 which takes a reaction force on the shaft wall of the shaft 1.
第7図は、前記1ユニットずつのトラベリング用ユニ
ット8の構築とトラベリングとを数回繰り返して内部建
築躯体9をある程度の大きさにまで築造した段階を示し
ている。こうして大空洞6内に内部建築躯体9の完成さ
れることにより地上の人々に有用な地下の建築大空間が
提供されるのである。FIG. 7 shows a stage in which the construction of the traveling unit 8 for each unit and the traveling are repeated several times to construct the internal building frame 9 to a certain size. The completion of the internal building frame 9 in the large cavity 6 in this way provides a large underground architectural space useful for people on the ground.
本発明が奏する効果 以上に実施例と併せて詳述した通りであって、この発
明に係る大深度地下の建築大空間の構築方法によれば、
地上の既存建物11の存在は何等障害とならず、同既存建
物11の支持地盤の下の大深度地下に、既存建物11や地表
面に一切の悪影響を及ぼすことなく、床面直径が100m前
後の建築大空間を構築することができる。地上には縦坑
1を掘削できるだけの工事用スペースがあれば十分に施
工ができ、どんな大深度にでも安全に正確に地下大空間
の内部建築躯体9を構築することができる。しかも現在
の施工技術の延長として容易に実施ができる。Effects of the present invention As described in detail in conjunction with the embodiment above, according to the method of constructing a large deep underground building large space according to the present invention,
The presence of the existing building 11 on the ground does not cause any obstacles, and the floor diameter is around 100 m in the deep underground below the supporting ground of the existing building 11 without any adverse effect on the existing building 11 or the ground surface Architectural large space can be constructed. If there is enough construction space on the ground to excavate the shaft 1, construction can be performed sufficiently, and the internal building frame 9 of the large underground space can be safely and accurately constructed at any depth. Moreover, it can be easily implemented as an extension of the current construction technology.
従って、本発明によれば、人口が集中し地価が以上に
高い都市部の地下に大きな生活大空間を創出して地価の
高騰にブレーキをかける効果を期待できるのである。Therefore, according to the present invention, it is possible to expect an effect of creating a large living space underground in an urban area where the population is concentrated and the land price is higher, thereby braking the rise in land price.
第1図〜第7図は本発明に係る大深度地下の建築大空間
の構築方法の枢要な工程を示した断面図である。 1……縦坑、2……先進導坑 3……シールドトンネル、10……補強材 8a……柱、8b……梁 8c……床、9……内部建築躯体 5……地盤、6……大空洞 7……トラベリング用レール 8……トラベリング用ユニットFIGS. 1 to 7 are sectional views showing the essential steps of the method for constructing a large underground architectural space according to the present invention. 1 Vertical shaft 2 Advanced shaft 3 Shield tunnel 10 Reinforcement 8a Column 8b Beam 8c Floor 9 Internal building frame 5 Ground 6 … Large cavity 7 …… Traveling rail 8 …… Traveling unit
Claims (1)
を構築し、前記縦坑の途中の大深度位置から水平方向に
先進導坑を構築する段階と、 前記縦坑の途中位置からシールドマシンを発進させて前
記先進導坑に外接するスパイラル状のシールドトンネル
を順次水平方向に構築すると共に前後のシールドトンネ
ル同士を互いに緊結し、シールドトンネル内に補強材を
充填して外周壁躯体を構築する段階と、 前記外周壁躯体で囲まれた内側部分の地盤を掘削して大
空洞を形成する段階と、 前記大空洞の床部のトラベリング用レールを敷設し、該
トラベリング用レール上の前記縦坑に相当する部位で
柱、梁、床による多層階の内部建築躯体のトラベリング
用ユニットを1ユニット分だけ構築し、この1ユニット
はトラペリング用レール上を前方へ所定ストローク移動
させ、以下トラベリング用ユニットの構築とそのトラベ
リングとを繰り返す段階と、から成ることを特徴とする
大深度地下に建築大空間を構築する方法。A step of constructing a vertical shaft having a depth sufficiently reaching a large underground architectural space, and constructing an advanced shaft in a horizontal direction from a large depth position in the middle of the vertical shaft; Starting the shield machine from and constructing a spiral shield tunnel circumscribing the advanced shaft sequentially in the horizontal direction and tightening the front and rear shield tunnels with each other, filling the shield tunnel with a reinforcing material and filling the outer peripheral wall frame Constructing, and excavating the ground of the inner portion surrounded by the outer peripheral wall skeleton to form a large cavity, laying a traveling rail on the floor of the large cavity, on the traveling rail At the site corresponding to the shaft, a unit for traveling of the internal building frame of the multi-story building consisting of columns, beams and floors is constructed for only one unit, and this one unit moves forward on the rail for trapping. It is a constant stroke movement, a method of constructing a building large space deep underground, characterized in that it consists of the steps of repeating the construction of traveling for units below its traveling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1234075A JP2700694B2 (en) | 1989-09-08 | 1989-09-08 | How to build a large architectural space underground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1234075A JP2700694B2 (en) | 1989-09-08 | 1989-09-08 | How to build a large architectural space underground |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0396600A JPH0396600A (en) | 1991-04-22 |
JP2700694B2 true JP2700694B2 (en) | 1998-01-21 |
Family
ID=16965206
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1234075A Expired - Fee Related JP2700694B2 (en) | 1989-09-08 | 1989-09-08 | How to build a large architectural space underground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2700694B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2893349B2 (en) * | 1990-02-23 | 1999-05-17 | 日本シビックコンサルタント株式会社 | Large section tunnel structure and its construction method. |
JP4660822B2 (en) * | 2006-07-25 | 2011-03-30 | 清水建設株式会社 | Construction method of support structure in branching junction |
JP6268522B2 (en) * | 2014-02-10 | 2018-01-31 | 株式会社大林組 | Widening part formation method of shield tunnel |
-
1989
- 1989-09-08 JP JP1234075A patent/JP2700694B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0396600A (en) | 1991-04-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001262595A (en) | Building construction method of underground building frame | |
CN113958322B (en) | Tunnel excavation method under existing subway line | |
JPH04343995A (en) | Middle part covering structure of juxtaposed tunnels | |
JP2869569B2 (en) | Construction method of large depth, large scale underground space by ground freezing method and ground freezing pipe | |
JP2700694B2 (en) | How to build a large architectural space underground | |
JP2762133B2 (en) | How to build a large architectural space underground | |
JPH04213695A (en) | Segment for shield tunnel | |
JP2700693B2 (en) | How to build a large architectural space underground | |
JP2700695B2 (en) | How to build a large architectural space underground | |
JP2979044B2 (en) | Large-scale underground structures and their construction methods | |
JP3930954B2 (en) | Construction method of structure | |
JP3125171B2 (en) | How to build underground structures | |
JPH02200917A (en) | Landslide suppressing well cylinder and its building method | |
JP4760548B2 (en) | Side-by-side tunnel structure and its construction method | |
JP2005002671A (en) | Underpinning method and viaduct | |
JPH0559728A (en) | Sheathing work above underground structure | |
JPH0584773B2 (en) | ||
JPH02300422A (en) | Construction of underground structure | |
CN207062996U (en) | Cross the constructing structure of urban road underpass | |
JP2656892B2 (en) | Underground structure construction method and continuous underground wall construction method | |
JPS6245958B2 (en) | ||
JPH10159094A (en) | Timbering structure of earth retaining wall | |
JP2996113B2 (en) | How to build a shaft | |
JPH07259477A (en) | Structure of tunnel, its construction and construction device | |
JPH09125405A (en) | Deep foundation for inclined tower leg |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |