JP4760548B2 - Side-by-side tunnel structure and its construction method - Google Patents

Side-by-side tunnel structure and its construction method Download PDF

Info

Publication number
JP4760548B2
JP4760548B2 JP2006155198A JP2006155198A JP4760548B2 JP 4760548 B2 JP4760548 B2 JP 4760548B2 JP 2006155198 A JP2006155198 A JP 2006155198A JP 2006155198 A JP2006155198 A JP 2006155198A JP 4760548 B2 JP4760548 B2 JP 4760548B2
Authority
JP
Japan
Prior art keywords
tunnel
mine
split
ground
center pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2006155198A
Other languages
Japanese (ja)
Other versions
JP2007321508A (en
Inventor
秀雄 木梨
輝夫 鈴木
秀明 西浦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2006155198A priority Critical patent/JP4760548B2/en
Publication of JP2007321508A publication Critical patent/JP2007321508A/en
Application granted granted Critical
Publication of JP4760548B2 publication Critical patent/JP4760548B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

この発明は、隣接して並行配設されるトンネルの側部同士がセンターピラーを介して結合されている並設トンネル構造およびその構築方法に関する。   The present invention relates to a side-by-side tunnel structure in which side portions of adjacent tunnels arranged in parallel are coupled via a center pillar and a construction method thereof.

並行する2本のトンネル本坑を隣接させて構築する場合には、両トンネル本坑間に地山の上載荷重が集中するため、当該上載荷重に対処する必要がある。これ故、従来にあっては、両トンネル本坑間の中央部に位置させて、予め中央先進導坑を掘削し、この中央先進導坑内に両トンネル本坑の共有支持構造体としてセンターピラーを形成するようにしている。そして、当該センターピラーの形成後に、中央先進導坑に沿わせてその一方側に先進本坑を掘削してその内周に支保工を設置し、当該支保工の中央先進導坑側の端部はセンターピラーに一体的に結合させてあずけ、爾後、中央先進導坑に沿わせてその他方側に後進本坑を掘削し、同様にして当該後進本坑の支保工をセンターピラーに一体的に結合させてあずけるようにしている(下記の特許文献等を参照)。
特開2002−322898号公報 特開2005−344318号公報
When two adjacent tunnel main shafts are constructed adjacent to each other, the ground load is concentrated between the two tunnel main shafts, and therefore it is necessary to deal with the load. Therefore, in the past, the central advanced tunnel was excavated in advance at the center between the two tunnel main shafts, and the center pillar was installed as a shared support structure for both tunnel main shafts in the central advanced tunnel. Try to form. And after the formation of the center pillar, along the central advanced guide shaft, the advanced main shaft is excavated on one side thereof, and a support is installed on the inner periphery thereof. Is integrated with the center pillar, and after dredging, the reverse main shaft is excavated along the central advanced guide shaft to the other side. Similarly, the support work for the reverse main shaft is integrated with the center pillar. They are combined (see the following patent documents).
JP 2002-322898 A JP 2005-344318 A

しかしながら、上記従来の構築方法にあっては、並行設置するトンネル本坑の掘削に先だって、両トンネル本坑間の中央部に小断面の中央先進導坑を予め先行掘削し、その狭い空間の内部にて両トンネル本坑の支保工を支持する共有のセンターピラーを予め形成しておくようにしたものであるため、中央先進導坑の掘削形成に時間と工費とを費やされてしまう。また、そればかりか、当該中央先進導坑の狭い空間内でセンターピラーを形成する作業は甚だ面倒なものであって、このセンターピラーの形成にも時間と工費とを要することになり、もって工期が長期化するとともに、工費が非常に嵩んでしまうとい課題があった。   However, in the conventional construction method described above, prior to excavation of the tunnel main shaft installed in parallel, a central advanced guide shaft with a small cross section is pre-excavated in the center between both tunnel main shafts, and the interior of the narrow space is Since a common center pillar for supporting the support work of both tunnel main shafts is formed in advance, time and construction costs are spent on excavation formation of the central advanced guide shaft. In addition, the work of forming the center pillar in the narrow space of the central advanced guide shaft is very troublesome, and it takes time and cost to form the center pillar. However, there is a problem that the construction cost becomes very large as the manufacturing process becomes longer.

本発明は、上記事情に鑑みてなされたものであり、その目的は、トンネル本坑の掘削に先だって中央先進導坑を掘削することなく、大断面の先進坑及び後進坑の広い空間内部にてそれらトンネル本坑間の中央部側に位置した側壁部にそれぞれセンターピラーを形成して、両トンネル本坑間に集中する地山の上載荷重を支持することができ、もって工期の短縮化と工費の低減化とを可及的に図ることができる並設トンネル構造およびその構築方法を提供することにある。   The present invention has been made in view of the above circumstances. The purpose of the present invention is in a large space inside a large cross-section advanced mine and a reverse mine without excavating a central advanced guide prior to excavation of a tunnel main mine. Center pillars can be formed on the side walls located on the center side between these tunnel main shafts, respectively, to support the overload of the natural ground concentrated between the two tunnel main shafts. It is an object of the present invention to provide a side-by-side tunnel structure capable of reducing the reduction as much as possible and a construction method thereof.

上記の目的を達成するために、本発明に係る並設トンネル構造にあっては、トンネル本坑の側部同士が隣接されて並設される並設トンネル構造において、両トンネル本坑に配設するそれぞれの支保工の互いに隣接する側の脚部をトンネルの幅方向に分裂する分裂脚とし、該分裂基部はトンネル本坑上半部の下端部に位置させ、該分裂基部より下方のトンネル本坑下半部には、該分裂基部に一体的に結合された複数の分裂脚間にこれらを結合して補強する補強部材が設けられてセンターピラーが形成されていることを特徴とする。   In order to achieve the above object, in the side-by-side tunnel structure according to the present invention, in the side-by-side tunnel structure in which the side portions of the tunnel main shaft are adjacent to each other, the two tunnel main shafts are arranged. The adjacent leg portions of each supporting work are split legs that split in the width direction of the tunnel, and the split base is located at the lower end of the upper half of the tunnel main tunnel, and the tunnel book below the split base A center pillar is formed by providing a reinforcing member for connecting and reinforcing a plurality of split legs integrally connected to the split base in the half-bottom half part.

ここで、前記補強部材は吹き付けコンクリートとなし得る。あるいは、前記補強部材は前記分裂脚間を繋ぐ鋼材となし得る。さらに、前記補強部材は前記分裂脚部の下端部間を繋いで本坑のインバートと一体に形成される床版となし得る。また、前記補強部材として、前記吹きつけコンクリートと前記鋼材及び前記床版とのいずれか2つ以上を適宜に組み合わせるようにしても良い。   Here, the reinforcing member may be sprayed concrete. Alternatively, the reinforcing member may be a steel material that connects the split legs. Further, the reinforcing member may be a floor slab formed integrally with the invert of the main mine by connecting the lower ends of the split legs. Further, as the reinforcing member, any two or more of the sprayed concrete, the steel material, and the floor slab may be appropriately combined.

また、前記センターピラー近傍の地山は、鋼棒や薬液注入等によって補強した改良地盤となしても良い。ここで、当該改良地盤は、前記センターピラーの下方部の地山に形成し、該改良地盤には、並設されたトンネル本抗の双方からトンネル幅方向と軸方向との2方向に指向して斜めに延び、相互に三次元的に絡み合って網状体をなす多数の補強ボルト等の鋼棒が設けられている構成となし得る。あるいは、前記改良地盤は、前記センターピラーの上方部の地山に形成し、該改良地盤には、並設されたトンネル本抗におけるそれぞれの上半部の支保工同士を繋いで締結固定する複数のタイロッド等の鋼棒が上下に並行に設けられている構成となし得る。   Moreover, the natural ground in the vicinity of the center pillar may be an improved ground reinforced by a steel rod or chemical injection. Here, the improved ground is formed on the ground below the center pillar, and the improved ground is oriented in both directions of the tunnel width direction and the axial direction from both of the tunnel main walls arranged side by side. It is possible to adopt a configuration in which a large number of steel rods such as reinforcing bolts extending obliquely and entangled three-dimensionally to form a net-like body are provided. Alternatively, the improved ground is formed on a ground in the upper part of the center pillar, and the improved ground is connected to the upper half supporters of the tunnel main body arranged side by side and fastened together. The steel rods such as tie rods may be provided in parallel in the vertical direction.

また、上記の目的を達成するために、本発明に係る並設トンネルの構築方法にあっては、先行掘削した先進坑の側方に後進坑を隣接させて並行に後行掘削し、該先進坑と後進坑との隣接する側壁同士にセンターピラーを形成してトンネル本坑を並設構築して行く並設トンネルの構築方法において、該先進坑と該後進坑とのトンネル本坑の内周に沿って支保工を設置するに際して、該先進坑と該後進坑とが隣接する側の各支保工脚部をトンネルの幅方向に分裂させて複数の分裂脚を形成し、爾後、該分裂脚間にこれらを結合して補強する補強部材を設けてセンターピラーを形成することを特徴とする。
In order to achieve the above object, in the method for constructing a side-by-side tunnel according to the present invention, a rearward excavation is made adjacent to a side of an advanced excavation that has been excavated in advance, and the advanced excavation is performed in parallel. In the method of constructing a side-by-side tunnel in which a center pillar is formed side by side between adjacent side walls of a pit and a reverse pit, the inner periphery of the tunnel main pit between the advanced pit and the reverse pit When the supporting work is installed along the pit, the supporting limbs on the side where the advanced mine and the reverse mine are adjacent are split in the width direction of the tunnel to form a plurality of split legs. The center pillar is formed by providing a reinforcing member that reinforces them by connecting them therebetween.

ここで、前記補強部材としては、前記分裂脚間に吹き付けコンクリートを充填して施工する構成となし得る。あるいは、前記補強部材としては、前記分裂脚間を繋いで鋼材を設置する構成となし得る。さらに、前記補強部材としては、前記分裂脚部の下端部間を繋いで本坑のインバートと一体に床版を形成する構成となし得る。また、前記補強部材としては、前記分裂脚間への吹きつけコンクリートの施工と、前記分裂脚間を繋ぐ鋼材の設置と、前記分裂脚部の下端部間を繋いで本坑のインバートに一体形成する床版の設置とのいずれか2つ以上を適宜に組み合わせるようにしても良い。   Here, the reinforcing member may be configured to be filled with sprayed concrete between the split legs. Alternatively, the reinforcing member may be configured to install a steel material by connecting the split legs. Furthermore, the reinforcing member may be configured to form a floor slab integrally with the invert of the main mine by connecting the lower ends of the split legs. In addition, as the reinforcing member, construction of sprayed concrete between the split legs, installation of a steel material connecting the split legs, and the invert of the main mine connecting the lower ends of the split legs are integrally formed Any two or more of the installation of floor slabs to be performed may be appropriately combined.

また、前記後進坑の掘削をする前に、前記センターピラー近傍の地山に鋼棒や薬液注入等による地山補強処理を施して地盤改良を行うようにしても良い。ここで、前記改良地盤は前記センターピラーの下方部の地山に形成し、該改良地盤は、並設された先進坑と後進抗との双方から、トンネル幅方向と軸方向との2方向に斜めに指向させて多数の補強ボルト等の鋼棒を打設して、該多数の補強ボルトを相互に三次元的に絡み合わせて網状体に配して形成する構成となし得る。あるいは、前記改良地盤は前記センターピラーの上方部の地山に形成し、該改良地盤は、並設された先進坑と後進抗とのそれぞれの上半部の支保工同士を繋いで締結固定する複数のタイロッド等の鋼棒を上下に並行に打設して形成する構成となし得る。   Further, before excavation of the reverse shaft, the ground improvement in the ground near the center pillar may be performed by performing a ground reinforcement process such as a steel rod or chemical injection. Here, the improved ground is formed in the ground below the center pillar, and the improved ground is formed in both directions of the tunnel width direction and the axial direction from both the advanced pit and the reverse resistance. A structure in which a large number of steel rods such as reinforcing bolts are placed in an oblique direction, and the large number of reinforcing bolts are entangled with each other in a three-dimensional manner and arranged in a net-like body. Alternatively, the improved ground is formed on the ground above the center pillar, and the improved ground is fastened by connecting the upper half supporters of the advanced mine and the reverse resistance installed side by side. A structure in which a plurality of steel bars such as tie rods are driven in parallel up and down can be used.

上記のようにしてなる本発明の並設トンネル構造及びその構築方法によれば、先進坑と後進坑とを並設して掘削するにあたって、それらの中央部間に小断面の中央先進導坑を先がけて掘削して、その狭い空間内にセンターピラーを先行設置するという作業工程を行うことなく、大断面に掘削した先進坑及び後進坑の広い空間内でその隣接する側の側壁部にそれぞれセンターピラーを設置して、両トンネル本坑間に集中する地山の上載荷重を支持することができるとともに、当該センターピラーの形成を容易に行うことが出来る。このため、工期の短縮化と工費の削減化とを可及的に図れるようになる。   According to the side-by-side tunnel structure and the construction method thereof according to the present invention as described above, when excavating an advanced mine and a reverse mine in parallel, a central advanced guide shaft having a small cross section is provided between the central portions thereof. Centering on the side wall on the adjacent side in the wide space of the advanced mine and the reverse mine excavated in a large cross section without performing the work process of excavating ahead and installing the center pillar in the narrow space in advance By installing a pillar, it is possible to support the overload of the natural ground concentrated between the two main tunnels, and the center pillar can be easily formed. For this reason, it is possible to shorten the construction period and reduce the construction cost as much as possible.

以下に、本発明に係る並設トンネル構造およびその構築方法の好適な一実施の形態について、本線道路の上下線をなす2つのトンネルを土砂地山に隣接させて並行に設ける場合を例にして、図1〜図9の添付図面に基づいて説明する。   In the following, a preferred embodiment of the side-by-side tunnel structure and its construction method according to the present invention will be described by taking as an example the case where two tunnels forming the upper and lower lines of the main road are provided in parallel adjacent to the earth and sand mountain. The description will be made with reference to the accompanying drawings of FIGS.

図1は並設トンネルの構築途中状態を概略的に示す概略平断面図である。また、図2(I)〜(V)及び図3(VI)〜(IIX)はそれぞれ図1中においてI−I線乃至IIX−IIX線にて示す部位の矢視断面図であり、施工工程順に示してある。   FIG. 1 is a schematic cross-sectional view schematically showing a state where a parallel tunnel is being constructed. 2 (I) to (V) and FIGS. 3 (VI) to (IIX) are cross-sectional views taken along the lines I-I to IIX-IIX in FIG. They are shown in order.

図1に示すように、並設トンネル2は本線道路の上下線をそれぞれ画成する2つのトンネル本坑が隣接されて並行に設けられてなる。当該並設トンネル2を構築するにあたっては、一方のトンネル本坑を先進坑4として先行掘削し、この先進坑4に対して所定の工程遅れを持たせて追従させながら他方のトンネル本坑を後進坑6として後行掘削していく。   As shown in FIG. 1, the side-by-side tunnel 2 is provided in parallel with two tunnel main shafts that respectively define the upper and lower lines of the main road. In constructing the side-by-side tunnel 2, one tunnel main mine is advanced as an advanced mine 4, and the other tunnel main mine is moved backward while following this advanced mine 4 with a predetermined process delay. The excavation will continue as the mine 6.

先ず、最初の工程として先進坑掘削工程とこれに続く支保工設置工程とが順次に行われる。先進坑掘削工程では、所定のトンネル設置計画ラインに沿って掘削機械等を用いて切り羽5を掘削・ズリ出しして先進坑4を形成していく。そして、掘削した先進坑4の内周には、逐次にコンクリートを1次吹き付けして土砂の崩落の防止を図る。爾後、当該1次吹き付け層の内側に沿わせてH形鋼による支保工10を逐次建て込んで設置していく。この支保工10は先進坑4の長手方向に所定の間隔を空けて設けられる。当該支保工10の設置後には、支保工10,10間を埋めるようにしてコンクリートの2次吹き付けが行われて、この2次吹き付け層により吹き付けコンクリート層の強度向上が図られる。   First, an advanced mine excavation process and a subsequent support installation process are sequentially performed as the first process. In the advanced mine excavation process, the advanced pit 4 is formed by excavating and slipping the face 5 using a drilling machine or the like along a predetermined tunnel installation plan line. And concrete is sequentially sprayed to the inner periphery of the excavated advanced mine 4 in order to prevent the collapse of earth and sand. After the dredging, the support 10 made of H-section steel is sequentially built and installed along the inside of the primary spray layer. This supporting work 10 is provided at a predetermined interval in the longitudinal direction of the advanced mine 4. After the support 10 is installed, the concrete is sprayed so as to fill the space between the supports 10 and 10, and the strength of the sprayed concrete layer is improved by the secondary spray layer.

ここで、図2の(I)及び(II)に示すように、当該先進坑4の掘削から2次吹き付け迄の施工工程は、先進坑4の上半部4aと下半部4bとに区分けされて2段階で行われるようになっている。図4〜図9は、その1段階目に行われる先進坑4の上半部4aの掘削から2次吹き付け迄と、その後のロックボルトの打設工程との各施工工程をより詳しく説明したものである。なお、これら図4〜図9の各図において(a)は横断面、(b)は平断面、(C)は側断面を示している。即ち、図4の前進掘削開始前状態と図5の掘削・ズリ出し工程との図に示すように、先進坑4はその上半部4aが先に掘削される。そして、上半部4aが所定形状に掘削されると、図6の1次吹き付け工程に示すように、その内周面にコンクリートが1次吹き付けされて1次吹き付け層8aが形成される。   Here, as shown in (I) and (II) of FIG. 2, the construction process from excavation of the advanced mine 4 to the secondary spraying is divided into an upper half 4a and a lower half 4b of the advanced mine 4. Has been done in two stages. FIGS. 4 to 9 illustrate in detail the respective construction steps from the excavation of the upper half 4a of the advanced mine 4 to the secondary spraying, and the subsequent locking bolt placing step, which are performed in the first stage. It is. 4 to 9, (a) shows a cross section, (b) shows a plane section, and (C) shows a side section. That is, as shown in the drawing of the state before the start of forward excavation in FIG. 4 and the excavation / slipping step in FIG. 5, the upper half 4a of the advanced mine 4 is excavated first. Then, when the upper half 4a is excavated into a predetermined shape, as shown in the primary spraying step of FIG. 6, the primary spray layer 8a is formed by primarily spraying concrete on the inner peripheral surface thereof.

当該1次吹き付け層8aが形成されると、次ぎに図7に示すように、内周面に沿ってH型鋼製の支保工10の建て込みが行われる。ここで、当該先進坑4の上半部4aの支保工10の両側下端部には、図2及び図10に示してあるように、この後に掘削される下半部4bの両側部に建て込まれる支保工脚部102を結合させるためのブラケット101が設けられている。即ち、このブラケット101は先進坑4の下半部4bよりもやや上方に位置されることになる。   When the primary spray layer 8a is formed, as shown in FIG. 7, the H-shaped steel support 10 is built along the inner peripheral surface. Here, as shown in FIG. 2 and FIG. 10, the lower half 4b to be excavated later is built into both sides of the lower half 4b of the support half 10 of the upper half 4a of the advanced mine 4 as shown in FIGS. A bracket 101 for connecting the supporting leg 102 to be mounted is provided. That is, the bracket 101 is positioned slightly above the lower half 4b of the advanced mine 4.

そして、先進坑4の上半部4aに支保工10が建て込まれると、図8に示すように、既に先行して建て込まれている支保工10との間にコンクリートの2次吹き付けが行われて2次コンクリート層8bが形成され、もって吹き付けコンクリート層8の強度向上が図られる。爾後、必要に応じて図9に示すように、支保工10,10間のコンクリート層8を貫通して多数のロックボルト12等の鋼棒が地山中に放射状に打設されて地盤の補強が行われる。ここで、ロックボルト12は後進坑6と干渉しないようにその掘削予定領域を避けて配設することになるが、地山の上載荷重が集中する先進坑4と後進坑6との間の中央部近傍の地山部分を重点的に地盤補強するのが効果的である。この様にして先進坑4と後進坑6との間の中央部近傍の地山部分を改良地盤13となして固化させておくことで、上記地山の上載荷重の集中を軽減し得る。なお、当該地盤改良は必須のものではない。   Then, when the support work 10 is built in the upper half 4a of the advanced mine 4, as shown in FIG. 8, secondary spraying of concrete is performed between the support work 10 already built in advance. As a result, the secondary concrete layer 8b is formed, whereby the strength of the sprayed concrete layer 8 is improved. After the dredging, as shown in FIG. 9, if necessary, steel rods such as a number of lock bolts 12 are radiated into the natural ground through the concrete layer 8 between the support works 10 and 10 to reinforce the ground. Done. Here, the rock bolt 12 is disposed so as to avoid the planned excavation area so as not to interfere with the reverse shaft 6, but the central portion between the advanced shaft 4 and the reverse shaft 6 where the overlay load is concentrated. It is effective to reinforce the ground in the nearby ground. In this way, by consolidating the natural ground portion in the vicinity of the center between the advanced mine 4 and the reverse mine 6 as the improved ground 13, the concentration of the above-mentioned natural ground load can be reduced. The ground improvement is not essential.

そして、上記の各施工工程を経て先進坑4の上半部4aの掘削形成が終了したならば、引き続いて下半部4bの掘削形成を行う。この下半部4bの掘削形成も上半部4aと同様に、掘削・ズリだし施工工程、1次吹き付け施工工程、支保工建て込み施工工程、2次吹き付け施工工程を経て行う。   And if excavation formation of upper half part 4a of advanced mine 4 is completed through each above-mentioned construction process, excavation formation of lower half part 4b will be performed continuously. Excavation formation of this lower half part 4b is performed through excavation / slip-out construction process, primary spraying construction process, support construction building construction process, and secondary spraying construction process as well as upper half part 4a.

ところで、上記先進坑4の上半部4aに建て込まれた支保工10の下端部に設けられるブラケット101はトンネル本坑の幅方向に複数に分岐された形状とされている。即ち、本図示例の実施の形態では、上記ブラケット101は、先進坑4の下方の内外に2本の分裂脚102a,102bを支保工脚部102として結合可能とすべく2股状に分岐形成されて分裂基部101a,101bとして構成されている。そして、先進坑4の下半部4bの支保工建て込み設置工程では、2つのトンネル本坑同士が隣接することになる並設トンネル2の中央部側に配される支保工脚部102を建て込むに際して、ブラケット101の2股状に分岐された外側の分裂基部101bには下方に向けて垂直に延びる外側分裂脚102bが一体的に結合されるとともに、内側の分裂基部101aにはやや内方に向けて湾曲する内側分裂脚102aが一体的に結合される。一方、並設トンネル2全体としての外側に位置する支保工脚部102を建て込む際には、2股状のブラケット101の内側の分裂基部101a側に対して湾曲した内側分裂脚102aのみが単独で建て込まれて結合される。   By the way, the bracket 101 provided in the lower end part of the support 10 built in the upper half part 4a of the said advanced mine 4 is made into the shape branched in multiple in the width direction of the tunnel main mine. That is, in the embodiment of the illustrated example, the bracket 101 is bifurcated so as to be able to couple the two split legs 102a and 102b as the support legs 102 inside and outside the advanced mine 4 below. Thus, the split bases 101a and 101b are configured. And in the support construction installation process of the lower half part 4b of the advanced mine 4, the support work leg part 102 distribute | arranged to the center part side of the parallel tunnel 2 with which two tunnel main mines adjoin each other is built. The outer split base portion 101b branched from the bracket 101 is integrally joined to the outer split leg portion 102b extending vertically downward, and the inner split base portion 101a is slightly inward. The inner split leg 102a that curves toward is integrally coupled. On the other hand, when the support leg 102 located outside the entire side-by-side tunnel 2 is built, only the inner split leg 102a curved with respect to the split base 101a side inside the bifurcated bracket 101 is alone. Built in and combined.

そして、支保工脚部102の設置が終わるとセンターピラー形成工程が行われる。即ち、このセンターピラーの形成工程では、並設トンネル2中央部側に設置された内側分裂脚102aと外側分裂脚102bとの間にこれらを結合して補強する補強部材16が一体的に設けられてセンターピラー18が形成される。ここで本実施の形態では、当該補強部材16としては、内側分裂脚102aと外側分裂脚102bとの下端部同士を繋ぐ鋼材161、及び内側分裂脚102aと外側分裂脚102bとの間に吹き付け充填される吹き付けコンクリート162の双方が採用されている。   Then, when the support leg 102 is installed, a center pillar forming step is performed. That is, in this center pillar forming process, the reinforcing member 16 is integrally provided between the inner split leg 102a and the outer split leg 102b installed on the central side of the side-by-side tunnel 2 to reinforce them. Thus, the center pillar 18 is formed. Here, in the present embodiment, the reinforcing member 16 includes a steel material 161 that connects the lower ends of the inner split leg 102a and the outer split leg 102b, and spray filling between the inner split leg 102a and the outer split leg 102b. Both of the sprayed concrete 162 to be used are employed.

センターピラー18の形成が終了したならば、次ぎに、図1及び図2(III)に示すように、先進坑4の底面にコンクリートを打設して先進坑インバート20を施工し、先進坑4に床部を形成する。この先進坑インバート20は支保工10の両側に設けられた内側分裂脚102aの下端部に連続させて一体化して施工する。これにより、支保工脚部102を含んで支保工10と先進坑インバート20とが環状に一体的に繋がって閉断面部となり、耐荷重能力が向上する。   When the formation of the center pillar 18 is finished, next, as shown in FIG. 1 and FIG. 2 (III), concrete is cast on the bottom surface of the advanced mine 4 to construct the advanced mine invert 20, and the advanced mine 4 Form the floor. This advanced mine invert 20 is constructed by being integrated with the lower end portion of the inner split leg 102 a provided on both sides of the support work 10. Thereby, the support work 10 and the advanced mine invert 20 including the support work leg part 102 are integrally connected in an annular shape to form a closed cross section, and the load bearing capacity is improved.

そして、上記先進坑インバート20のコンクリートが強度発現した時点で、図1及び図2(IV),(V)に示すように、その強度発現した部位の側方部分の地山を並行掘削して後進坑6の掘削工程及び支保工設置工程とを行う。この後進坑6の掘削工程と支保工設置工程にあっても、先進坑4の場合と同様に、上半部6aと下半部6bとが2段階で施工され、各段階毎に掘削・ズリ出し、1次吹き付け、支保工建て込み、2次吹き付けの各施工工程が順次同様の手順で行われる。   Then, when the concrete of the advanced mine invert 20 develops strength, as shown in FIGS. 1 and 2 (IV), (V), the ground part of the side portion of the portion where the strength is developed is excavated in parallel. The excavation process of the reverse shaft 6 and the support installation process are performed. Even in the excavation process and the support installation process of the reverse mine 6, as in the case of the advanced mine 4, the upper half 6a and the lower half 6b are constructed in two stages. Each construction process of taking out, primary spraying, support construction, and secondary spraying is sequentially performed in the same procedure.

次に、図3(VI)に示すように、後進坑6の底面にコンクリートを打設して後進坑インバート22を施工し、後進坑6の床部を形成する。この後進坑インバート22も先進坑インバートと全く同様に施工される。これにより、先進坑4の場合と同様に、支保工脚部102を含む支保工10と後進坑インバート22とが環状に一体的に繋がって閉断面部となり、耐荷重能力が向上する。爾後、図3(VII)に示すように、先進坑4の支保工10と吹きつけコンクリート層8とを覆って先進坑覆工24を、先進坑インバート20に連続させて一体的に打設形成し、引き続いて図3(IIX)に示すように、後進坑6の支保工10と吹きつけコンクリート層8とを覆って後進坑覆工26を、後進坑インバート22に連続させて一体的に打設形成する。   Next, as shown in FIG. 3 (VI), concrete is cast on the bottom surface of the reverse shaft 6 to construct the reverse shaft invert 22, and the floor portion of the reverse shaft 6 is formed. This reverse mine invert 22 is constructed in exactly the same manner as the advanced mine invert. Thereby, like the case of the advanced mine 4, the support work 10 including the support work leg 102 and the reverse mine invert 22 are integrally connected in a ring shape to form a closed cross section, and the load bearing capacity is improved. After the dredging, as shown in FIG. 3 (VII), the advanced mine lining work 24 is covered with the advanced mine invert 20 so as to cover the supporting work 10 and the sprayed concrete layer 8 of the advanced mine 4 and integrally formed. Subsequently, as shown in FIG. 3 (IIX), the reverse pit cover 26 is covered with the reverse pit invert 22 so as to cover the support shaft 10 and the sprayed concrete layer 8 of the reverse pit 6 and is integrally driven. Set up.

従って、並行配設されるトンネル本坑の側壁部同士が隣接する並設トンネル2を、以上の様にして構築すると、先進坑4と後進坑6とを並設して掘削するにあたって、それらの中央部間に小断面の中央先進導坑を先がけて掘削して、その狭い空間内にセンターピラーを先行設置するという作業工程を全く行うことなく、大断面に掘削した先進坑4及び後進坑6の広い空間内でその隣接する側の側壁部にそれぞれセンターピラー18,18を設置して、両トンネル本坑間に集中する地山の上載荷重を支持することができるようになるとともに、当該センターピラー18の形成を容易に行うことが出来るようになる。このため、並設トンネル2の構築工期を可及的に短縮化できるばかりか、工費の可及的な低減化を図れるようになる。   Therefore, when the side-by-side tunnels 2 adjacent to each other in the side wall portions of the tunnel main pits arranged in parallel are constructed as described above, when excavating the advanced mine 4 and the reverse mine 6 side by side, Advanced mine 4 and reverse mine 6 excavated in a large cross section without excavating a central advanced guide shaft with a small cross section between the central portions and performing a work process of installing a center pillar in the narrow space in advance. Center pillars 18 and 18 are respectively installed on adjacent side wall portions in a large space of the tunnel, so that it is possible to support the overload of the natural ground concentrated between the two main tunnels. 18 can be easily formed. For this reason, not only can the construction period of the side-by-side tunnel 2 be shortened as much as possible, but also the construction cost can be reduced as much as possible.

図11は前記センターピラー18を構成する分裂脚102a,102bの補強部材16として、当該分裂脚102a,102bの下端部間を繋いでトンネル本坑のインバート20,22と一体に床版163を設置した例を示すものである。この場合、当該床版163はインバート20,22の施工と同時に行う。そして、内側分裂脚102aと外側分裂脚102bとは共に下方に延長してその延長端同士を鋼材161で結合するとともに、床版163内に埋め込むようにする。また、内側分裂脚102aはその下端部側の湾曲を大きくしてインバート20,22の外形状に沿わせるようにするのが好ましい。この様な床版163を補強部材16として設けることにより、センターピラー18の強度を一段と高めることができるばかりか、センターピラー18にかかる荷重をインバート20,22にスムーズに伝達することで、当該センターピラー18の下方部の地山への荷重集中を低減することができる。また、補強部材16としては、前記分裂脚102a,102b間への吹きつけコンクリート162の充填施工と、前記分裂脚102a,102b間を繋ぐ鋼材161の設置と、前記分裂脚102a,102bの下端部間を繋いで本坑のインバート20,22に一体形成する床版163の設置とのいずれか2つ以上を適宜に組み合わせるようにしても良い。   FIG. 11 shows a reinforcing member 16 of the split legs 102a and 102b constituting the center pillar 18, and a floor slab 163 is installed integrally with the inverts 20 and 22 of the tunnel main shaft by connecting the lower ends of the split legs 102a and 102b. An example is shown. In this case, the floor slab 163 is performed simultaneously with the construction of the inverts 20 and 22. Then, both the inner split leg 102a and the outer split leg 102b extend downward, and their extended ends are joined by the steel material 161 and embedded in the floor slab 163. Moreover, it is preferable that the inner split leg 102a has a larger curvature on the lower end side so as to follow the outer shape of the inverts 20 and 22. By providing such a floor slab 163 as the reinforcing member 16, not only can the strength of the center pillar 18 be further increased, but also the load applied to the center pillar 18 can be smoothly transmitted to the inverts 20 and 22. The load concentration on the natural ground in the lower part of the pillar 18 can be reduced. Further, as the reinforcing member 16, filling concrete 162 between the split legs 102a and 102b is filled, a steel material 161 connecting the split legs 102a and 102b, and the lower ends of the split legs 102a and 102b. Any two or more of the installation of the floor slab 163 integrally formed with the inverts 20 and 22 of the main mine may be combined as appropriate.

図12は並設トンネル2の中央部間に形成されたセンターピラー18下方部の地山に地盤補強処理を施して改良地盤13となした例を示すものである。図示するように、この改良地盤13は補強ボルト12A等の鋼棒が多数打設されて形成されている。当該補強ボルト12Aは並設された先進坑4側と後進坑6側との双方から打設されている。ここで、先進坑4と後進抗6とから打設される各補強ボルト12Aは、それぞれ斜め下方に指向されるとともに、トンネル軸方向にも斜めに指向されて配され、トンネル幅方向と軸方向との2方向において相互にクロスされて設けられている。つまり、これにより多数の補強ボルト12Aは相互に三次元的にクロスして絡み合う網状体に形成され、当該網状体により地盤補強を行う。   FIG. 12 shows an example in which a ground reinforcement process is applied to a natural ground below the center pillar 18 formed between the central portions of the side-by-side tunnels 2 to form an improved ground 13. As shown in the figure, this improved ground 13 is formed by placing a large number of steel bars such as reinforcing bolts 12A. The reinforcement bolts 12A are driven from both the advanced mine 4 side and the reverse mine 6 side which are arranged side by side. Here, each reinforcement bolt 12A driven from the advanced mine 4 and the reverse resistance 6 is directed obliquely downward and is also obliquely oriented in the tunnel axis direction, and is arranged in the tunnel width direction and the axial direction. Are crossed with each other in two directions. That is, as a result, a large number of the reinforcing bolts 12A are formed into a mesh body that crosses and entangles with each other three-dimensionally, and ground reinforcement is performed by the mesh body.

即ち、この改良地盤13には、並設されたトンネル本抗である先進坑4と後進抗6との双方から、それぞれトンネル幅方向と軸方向との2方向に指向して斜めに延びて相互に三次元的に絡み合って網状体をなす多数の補強ボルト12A等の鋼棒が設けられている。また、必要に応じ、当該補強ボルト12Aには中空な管体製のものを用い、これを利用して更に地山中に薬液を注入して地盤改良を行う様にしても良い。   In other words, this improved ground 13 extends obliquely from both the advanced tunnel 4 and the reverse resistance 6 which are the tunnel main walls arranged side by side in the tunnel width direction and the axial direction, respectively. Steel rods such as a number of reinforcing bolts 12A that are intertwined three-dimensionally to form a net-like body are provided. Further, if necessary, the reinforcing bolt 12A may be made of a hollow tube, and by using this, a chemical solution may be further injected into the ground to improve the ground.

図13は図2(IV)に示す後進坑6の上半部6aの掘削形成工程の終了段階にて、当該後進坑6と先進坑4との間の中央部分上方に位置したセンターピーラー18近傍の地山に地盤補強を施した例を示すものである。この地盤補強は、並設された先進坑4と後進坑6とのそれぞれの上半部4a,6aの支保工10,10同士を繋ぐように複数のタイロッド12B等の鋼棒を上下に並行に打設して締結固定することで、改良地盤13を形成している。   FIG. 13 shows the vicinity of the center peeler 18 located above the central portion between the reverse shaft 6 and the advanced shaft 4 at the end of the excavation formation process of the upper half 6a of the reverse shaft 6 shown in FIG. This shows an example in which ground reinforcement is applied to a natural ground. In this ground reinforcement, a plurality of steel rods such as tie rods 12B are vertically aligned in parallel so as to connect the support members 10 of the upper half portions 4a, 6a of the advanced mine 4 and the reverse mine 6 arranged side by side. The improved ground 13 is formed by placing and fastening.

即ち、この改良地盤13には、並設されたトンネル本抗である先進坑4と後進抗6とにおけるそれぞれの上半部の支保工同士を繋いで締結固定する複数のタイロッド等の鋼棒が上下に並行に設けられている。また、この場合にあっても、必要に応じて当該タイロッド12Bには中空な管体製のものを用い、これを利用して更に地山中に薬液を注入して地盤改良を行う様にしても良い。   That is, the improved ground 13 has steel rods such as a plurality of tie rods for connecting and fixing the upper half supporters of the advanced tunnel 4 and the reverse drag 6 which are tunnel main walls arranged side by side. It is provided in parallel up and down. Even in this case, if necessary, the tie rod 12B is made of a hollow tube, and by using this, a chemical solution is further injected into the ground to improve the ground. good.

この様に、センターピラー18の上方部や下方部等の近傍の地山を補強して地盤改良し、その地耐力を高めることで、地山の上載荷重のセンターピラー18部への集中やセンターピラー18部下方の地盤沈下を抑制し得る。   In this way, the ground pile in the vicinity of the upper part and the lower part of the center pillar 18 is reinforced to improve the ground, and the earth bearing strength is increased, so that the load on the center pillar is concentrated on the center pillar 18 part and the center pillar. Land subsidence below 18 parts can be suppressed.

なお、図示した実施の形態例では、並行する2本のトンネル本坑を隣接させて構築する場合を例示しているが、本発明はこれに限らず、3本以上のトンネル本抗を並行に隣接させて構築する場合にも適用することができる。   In the illustrated embodiment, the case where two parallel tunnel main shafts are constructed adjacent to each other is illustrated. However, the present invention is not limited to this, and three or more tunnel cores are provided in parallel. The present invention can also be applied to a case where they are built adjacent to each other.

本発明に係る並設トンネルの構築途中状態を概略的に示す概略平断面図である。It is a schematic plane sectional view which shows roughly the construction middle state of the parallel tunnel which concerns on this invention. 同図(I)〜(V)はそれぞれ図1中においてI−I線乃至V−V線にて示す各部位の矢視断面図である。FIGS. (I) to (V) are cross-sectional views taken along lines I-I to V-V in FIG. 同図(VI)〜(IIX)はそれぞれ図1中においてVI−VI線乃至IIX−IIX線にて示す各部位の矢視断面図である。FIGS. (VI) to (IIX) are sectional views taken along arrows VI-VI to IIX-IIX in FIG. 先進坑の前進掘削前の状態を示すもので、(a)は横断面図、(b)は平断面図、(C)は側断面図である。The state before a forward excavation of an advanced mine is shown, (a) is a cross-sectional view, (b) is a plane cross-sectional view, and (C) is a side cross-sectional view. 先進坑上半部の掘削・ズリ出し工程を示すもので、(a)は横断面図、(b)は平断面図、(C)は側断面図である。The excavation / slipping process of the upper half of the advanced mine is shown, (a) is a cross-sectional view, (b) is a plane cross-sectional view, and (C) is a side cross-sectional view. 先進坑上半部の1次吹き付け工程を示すもので、(a)は横断面図、(b)は平断面図、(C)は側断面図である。The primary spraying process of the upper half of an advanced mine is shown, (a) is a cross-sectional view, (b) is a plane cross-sectional view, and (C) is a side cross-sectional view. 先進坑上半部の鋼製支保工建て込み工程を示すもので、(a)は横断面図、(b)は平断面図、(C)は側断面図である。The steel support construction process of an upper half part of an advanced mine is shown, (a) is a cross-sectional view, (b) is a plane cross-sectional view, and (C) is a side cross-sectional view. 先進坑上半部の2次吹き付け工程を示すもので、(a)は横断面図、(b)は平断面図、(C)は側断面図である。The secondary spraying process of an upper half of an advanced mine is shown, (a) is a cross-sectional view, (b) is a plane cross-sectional view, and (C) is a side cross-sectional view. 先進坑上半部のロックボルト打設工程を示すもので、(a)は横断面図、(b)は平断面図、(C)は側断面図である。FIG. 2A shows a process for placing a rock bolt in the upper half of an advanced mine, wherein FIG. 3A is a cross-sectional view, FIG. 2B is a cross-sectional view, and FIG. 図3(VI)中に示すA部の拡大図である。It is an enlarged view of the A section shown in FIG. 図10に相応する部位の拡大図で、補強部材として床版を設けた場合の変形例を示す図である。It is an enlarged view of the site | part corresponding to FIG. 10, and is a figure which shows the modification at the time of providing a floor slab as a reinforcement member. 図10に相応する部位の拡大図で、センターピラー下方部位の地山に地盤改良を施した場合の変形例を示す図である。It is an enlarged view of the part corresponding to FIG. 10, and is a figure which shows the modification at the time of performing ground improvement to the natural ground of the center pillar lower part. 先進坑と後進坑との間の中央部分上方の地山に地盤改良を施した場合の変形例を示す図である。It is a figure which shows the modification at the time of giving ground improvement to the natural ground above the center part between an advanced mine and a reverse mine.

符号の説明Explanation of symbols

2 並設トンネル
4 先進坑
4a 上半部
4b 下半部
6 後進坑
6a 上半部
6b 下半部
8 吹き付けコンクリート層
8a 1次吹き付け層
8b 2次吹き付け層
10 支保工
101 ブラケット
101a 内側の分裂基部
101b 外側の分裂基部
102 支保工脚部
102a 内側の分裂脚
102b 外側の分裂脚
12 ロックボルト
16 補強部材
161 鋼材
162 吹き付けコンクリート
163 床版
18 センターピラー
20 先進坑インバート
22 後進坑インバート
24 先進坑覆工
26 後進坑覆工
2 Side-by-side tunnel 4 Advanced mine 4a Upper half 4b Lower half 6 Reverse mine 6a Upper half 6b Lower half 8 Sprayed concrete layer 8a Primary spray layer 8b Secondary spray layer 10 Supporting work 101 Bracket 101a Splitting base inside 101b Outer split base 102 Support leg 102a Inner split leg 102b Outer split leg 12 Rock bolt 16 Reinforcement member 161 Steel material 162 Shotcrete 163 Floor slab 18 Center pillar 20 Advanced mine invert 22 Reverse mine invert 24 Advanced mine lining 26 Reverse mine lining

Claims (14)

トンネル本坑の側部同士が隣接されて並設される並設トンネル構造であって、
両トンネル本坑に配設するそれぞれの支保工の互いに隣接する側の脚部を、トンネルの幅方向に分裂する分裂脚とし、
該分裂基部はトンネル本坑上半部の下端部に位置させ、該分裂基部より下方のトンネル本坑下半部には、該分裂基部に一体的に結合された複数の分裂脚間にこれらを結合して補強する補強部材が設けられてセンターピラーが形成されていることを特徴とする並設トンネル構造。
It is a side-by-side tunnel structure in which the sides of the tunnel main shaft are adjacent to each other,
The legs on the sides adjacent to each of the supporting works arranged in both tunnel main shafts are split legs that split in the width direction of the tunnel,
The split base is positioned at the lower end of the upper half of the tunnel main shaft, and the lower half of the tunnel main shaft below the split base is disposed between a plurality of split legs integrally connected to the split base. A side-by-side tunnel structure, wherein a center pillar is formed by providing a reinforcing member that is coupled and reinforced.
前記補強部材が吹き付けコンクリートであることを特徴とする請求項1に記載の並設トンネル構造。   The parallel tunnel structure according to claim 1, wherein the reinforcing member is sprayed concrete. 前記補強部材が前記分裂脚間を繋ぐ鋼材であることを特徴とする請求項1または2のいずれかに記載の並設トンネル構造。   The side-by-side tunnel structure according to claim 1, wherein the reinforcing member is a steel material that connects the split legs. 前記補強部材が前記分裂脚部の下端部間を繋いで本坑のインバートと一体に形成される床版であることを特徴とする請求項1〜3のいずれかに記載の並設トンネル構造。   The side-by-side tunnel structure according to any one of claims 1 to 3, wherein the reinforcing member is a floor slab formed integrally with an invert of a main pit by connecting lower ends of the split legs. 前記センターピラー近傍の地山が、鋼棒や薬液注入等によって補強された改良地盤とされていることを特徴とする請求項1〜4のいずれかに記載の並設トンネル構造。   The side-by-side tunnel structure according to any one of claims 1 to 4, wherein a natural ground in the vicinity of the center pillar is an improved ground reinforced by a steel rod, chemical injection, or the like. 前記改良地盤が前記センターピラーの下方部の地山に形成され、該改良地盤には、並設されたトンネル本抗の双方からトンネル幅方向と軸方向との2方向に指向して斜めに延び、相互に三次元的に絡み合って網状体をなす多数の補強ボルト等の鋼棒が設けられていることを特徴とする請求項5に記載の並設トンネル構造。   The improved ground is formed in a natural ground below the center pillar, and the improved ground extends obliquely in both directions of the tunnel width direction and the axial direction from both of the tunnel main walls arranged side by side. 6. The side-by-side tunnel structure according to claim 5, wherein a plurality of steel rods such as reinforcing bolts that are three-dimensionally entangled with each other to form a net-like body are provided. 前記改良地盤が前記センターピラーの上方部の地山に形成され、該改良地盤には、並設されたトンネル本抗におけるそれぞれの上半部の支保工同士を繋いで締結固定する複数のタイロッド等の鋼棒が上下に並行に設けられていることを特徴とする請求項5または6のいずれかに記載の並設トンネル構造。   The improved ground is formed in a natural ground above the center pillar, and a plurality of tie rods and the like for connecting and fixing the upper half supporters in the tunnel main wall arranged in parallel to the improved ground, etc. The parallel tunnel structure according to claim 5, wherein the steel rods are provided in parallel in the vertical direction. 先行掘削した先進坑の側方に後進坑を隣接させて並行に後行掘削し、該先進坑と後進坑との隣接する側部同士にそれぞれセンターピラーを形成してトンネル本坑を並設構築して行く並設トンネルの構築方法であって、
該先進坑と該後進坑とのトンネル本坑の内周に沿って支保工を設置するに際して、該先進坑と該後進坑とが隣接する側の各支保工脚部をトンネルの幅方向に分裂させて複数の分裂脚を形成し、
爾後、該分裂脚間にこれらを結合して補強する補強部材を設けてセンターピラーを形成することを特徴とする並設トンネルの構築方法。
Adjacent to the side of the advanced mine where the excavation was carried out, the backward mine was laid in parallel, and the tunnel main mine was built side by side by forming a center pillar between adjacent sides of the advanced mine and the reverse mine. A method for constructing a side-by-side tunnel,
When installing a support along the inner circumference of the tunnel main pit between the advanced mine and the reverse mine, split the support legs on the side where the advanced mine and the reverse mine are adjacent in the width direction of the tunnel. To form multiple split legs,
A method for constructing a side-by-side tunnel, wherein a center pillar is formed by providing a reinforcing member for connecting and reinforcing these split legs between the split legs.
前記補強部材として、前記分裂脚間に吹き付けコンクリートを充填して施工することを特徴とする請求項8に記載の並設トンネルの構築方法。   The construction method for a side-by-side tunnel according to claim 8, wherein the reinforcing member is constructed by filling sprayed concrete between the split legs. 前記補強部材として、前記分裂脚間を繋いで鋼材を設置することを特徴とする請求項8または9のいずれかに記載の並設トンネルの構築方法。   The method for constructing a side-by-side tunnel according to claim 8, wherein a steel material is installed as the reinforcing member so as to connect the split legs. 前記補強部材として、前記分裂脚部の下端部間を繋いで本坑のインバートと一体に床版を設置することを特徴とする請求項8〜10のいずれかに記載の並設トンネルの構築方法。   The method for constructing a side-by-side tunnel according to any one of claims 8 to 10, wherein a floor slab is installed as the reinforcing member integrally with an invert of a main mine by connecting lower ends of the split legs. . 前記後進坑の掘削をする前に、前記センターピラー近傍の地山に鋼棒や薬液注入等による地山補強処理を施して地盤改良を行うことを特徴とする請求項8〜11のいずれかに記載の並設トンネルの構築方法。   Before excavation of the reverse shaft, the ground improvement in the ground near the center pillar is performed by performing ground reinforcement by a steel rod, chemical injection, or the like. The method for constructing the parallel tunnel as described. 前記改良地盤を前記センターピラーの下方部の地山に形成し、該改良地盤は、並設された先進坑と後進抗との双方から、トンネル幅方向と軸方向との2方向に斜めに指向させて多数の補強ボルト等の鋼棒を打設して、該多数の補強ボルトを相互に三次元的に絡み合わせて網状体に配して形成することを特徴とする請求項12に記載の並設トンネルの構築方法。   The improved ground is formed in the ground below the center pillar, and the improved ground is oriented obliquely in two directions, the tunnel width direction and the axial direction, from both the advanced pit and the rearward resistance. The steel rods such as a large number of reinforcing bolts are placed, and the large number of reinforcing bolts are three-dimensionally entangled with each other and arranged in a net-like body. How to build a side-by-side tunnel. 前記改良地盤を前記センターピラーの上方部の地山に形成し、該改良地盤は、並設された先進坑と後進抗とのそれぞれの上半部の支保工同士を繋いで締結固定する複数のタイロッド等の鋼棒を上下に並行に打設して形成することを特徴とする請求項12または13のいずれかに記載の並設トンネルの構築方法。
The improved ground is formed in a natural ground above the center pillar, and the improved ground is connected to the upper half supporters of the advanced mine and the reverse resistance arranged side by side, and is fastened and fixed. 14. The method for constructing a side-by-side tunnel according to claim 12 or 13, wherein steel rods such as tie rods are formed by vertically driving in parallel.
JP2006155198A 2006-06-02 2006-06-02 Side-by-side tunnel structure and its construction method Expired - Fee Related JP4760548B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006155198A JP4760548B2 (en) 2006-06-02 2006-06-02 Side-by-side tunnel structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006155198A JP4760548B2 (en) 2006-06-02 2006-06-02 Side-by-side tunnel structure and its construction method

Publications (2)

Publication Number Publication Date
JP2007321508A JP2007321508A (en) 2007-12-13
JP4760548B2 true JP4760548B2 (en) 2011-08-31

Family

ID=38854565

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006155198A Expired - Fee Related JP4760548B2 (en) 2006-06-02 2006-06-02 Side-by-side tunnel structure and its construction method

Country Status (1)

Country Link
JP (1) JP4760548B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5382432B2 (en) * 2009-06-08 2014-01-08 清水建設株式会社 Excavation method of adjacent twin tunnel
KR102593945B1 (en) * 2020-12-14 2023-10-24 전영권 Construction method of an ultra-close parallel tunnel using steel beams and shotcrete reinforcement pillars
CN117780362B (en) * 2024-02-27 2024-04-30 中铁十七局集团第五工程有限公司 Rock column replacement and reinforcement structure in ultra-small clear distance tunnel and construction method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07119548B2 (en) * 1989-12-28 1995-12-20 清水建設株式会社 Reinforcement structure of eyeglass type tunnel
JP2002322898A (en) * 2001-04-24 2002-11-08 Mitsui Constr Co Ltd Binocular tunnel with center pillar and its construction method
JP4296545B2 (en) * 2004-06-01 2009-07-15 清水建設株式会社 Center-pillar structure of eyeglass tunnel

Also Published As

Publication number Publication date
JP2007321508A (en) 2007-12-13

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
JP2006322222A (en) Construction method of large-sectional tunnel
JP2007217911A (en) Construction method of underground cavity and tunnel construction method
JP2007303155A (en) Construction method of underground cavity and tunnel construction method
JP4760548B2 (en) Side-by-side tunnel structure and its construction method
JP2788953B2 (en) Structure of tunnel structure
JP2008144510A (en) Construction method for multiple circular arc tunnel
JP2004124489A (en) Underground structure and its construction method
CN102777066A (en) Spiral-tunneling reverse construction method of bucket-shaped screw-type underground garage
JP4750568B2 (en) Tunnel junction construction method and tunnel junction structure
JP4730595B2 (en) Construction method of underground cavity
JP3937588B2 (en) Construction method for underground structures
JPH03202599A (en) Reinforced structure of twin tunnels
JP2017043983A (en) Underground structure, and construction method of underground structure
JPH10227199A (en) Construction method of large sectional tunnel
JP4665834B2 (en) Side-by-side tunnel structure and its construction method
JP4407716B2 (en) Construction method of earth retaining wall
JP4243069B2 (en) Construction method of earth retaining wall
JP4714928B2 (en) Tunnel excavation method
JP2008255614A (en) Support structure of natural ground and support method of natural ground
JP4485373B2 (en) Construction method of tunnel junction
JP4730607B2 (en) Construction method of shield tunnel
JP3584416B2 (en) Tunnel and its construction method
JP6092359B1 (en) Large section lining body and large section tunnel construction method
KR101762207B1 (en) The speed up construction method using hemispherical joint

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090520

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101203

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101214

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110210

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110510

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110523

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140617

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees