JPH0480161B2 - - Google Patents

Info

Publication number
JPH0480161B2
JPH0480161B2 JP14517885A JP14517885A JPH0480161B2 JP H0480161 B2 JPH0480161 B2 JP H0480161B2 JP 14517885 A JP14517885 A JP 14517885A JP 14517885 A JP14517885 A JP 14517885A JP H0480161 B2 JPH0480161 B2 JP H0480161B2
Authority
JP
Japan
Prior art keywords
girders
girder
bridge
main
prestress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14517885A
Other languages
Japanese (ja)
Other versions
JPS626005A (en
Inventor
Genji Abe
Toyofumi Ito
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON KOGEN CONCRETE
Original Assignee
NIPPON KOGEN CONCRETE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON KOGEN CONCRETE filed Critical NIPPON KOGEN CONCRETE
Priority to JP14517885A priority Critical patent/JPS626005A/en
Publication of JPS626005A publication Critical patent/JPS626005A/en
Publication of JPH0480161B2 publication Critical patent/JPH0480161B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、橋桁のプレストレス導入方法に関
する。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention relates to a method for introducing prestress into a bridge girder.

従来の技術 一般に、橋桁は自重、スパンおよび積載荷重が
大きくなるに伴つて断面サイズが相当大きくな
る。特に、プレキヤストコンクリート製の橋桁の
自重は鋼製橋桁のそれよりはるかに大きく、しか
も主桁間をこれらの部材間にコンクリートを打設
して一体化する必要があるため断面サイズは一段
と増す。この場合、橋桁内に直接PC鋼材による
プレストレスを導入することによつて断面サイズ
の縮小化が図られているがPC鋼材一本あたりに
相当大きなテンンシヨンを導入する必要があり、
これに対応できる様々な装置が使用されている。
BACKGROUND OF THE INVENTION In general, the cross-sectional size of a bridge girder increases considerably as its own weight, span, and live load increase. In particular, the dead weight of a precast concrete bridge girder is much greater than that of a steel bridge girder, and the cross-sectional size of the main girder is further increased because it is necessary to pour concrete between these members to integrate them. In this case, the cross-sectional size has been reduced by introducing prestress directly into the bridge girder using prestressing steel, but it is necessary to introduce a considerably large tension per prestressing steel.
Various devices are used that can handle this.

発明が解決しようとする問題点 このため、従来の橋桁は多くの重機械を必要と
し、大型化しやすいという欠点があつた。
Problems to be Solved by the Invention For this reason, conventional bridge girders require a lot of heavy machinery and have the disadvantage of being easily upsized.

また、橋桁の背が大きくなつた分だけ、橋桁下
の高さが低くなるため船舶や自動車の往来に支障
をきたすことがあつた。
Additionally, as the height of the bridge girder increased, the height beneath the bridge girder became lower, which sometimes caused problems for ships and automobiles.

さらに、橋桁のPC鋼材によるプレストレスの
導入方法は主にプレキヤストコンクリートの橋桁
に実施され、鋼製橋桁には実施されていない。
Furthermore, the method of introducing prestress using prestressing steel for bridge girders is mainly implemented for precast concrete bridge girders, but not for steel bridge girders.

この発明は、前記従来の問題点を解消するため
に提案されたもので、プレキヤストコンクリート
の橋桁だけでなく鋼製の橋桁にもプレストレスを
導入することができ、しかも小規模な装置で導入
することができて、橋桁断面の縮小化が図れる橋
桁のプレストレス導入方法を提供することを目的
とする。
This invention was proposed to solve the above-mentioned conventional problems, and it is possible to introduce prestress not only to precast concrete bridge girders but also to steel bridge girders, and moreover, it can be introduced with small-scale equipment. It is an object of the present invention to provide a method for introducing prestress into a bridge girder, which can reduce the cross section of the bridge girder.

問題点を解決するための手段 この発明に係る橋桁のプレストレス導入方法は
橋脚間に側部に複数個のシアコネクターを有する
複数本の橋桁を平行に架設するとともにこの左右
橋桁間にPC鋼材を橋桁の長手方向に沿つて架設
し、続いて前記左右橋桁間にコンクリートを打設
し、続いて前記コンクリート硬化後前記PC鋼材
に軸力を導入して橋桁内にプレストレスを導入す
ることによつて前記目的を達成するものである。
Means for Solving the Problems The method of introducing prestress into a bridge girder according to the present invention involves constructing a plurality of bridge girders having a plurality of shear connectors on the sides between the piers in parallel, and inserting PC steel materials between the left and right bridge girders. The bridge girder is constructed along the longitudinal direction, concrete is poured between the left and right bridge girders, and after the concrete hardens, axial force is introduced into the prestressing steel material to introduce prestress into the bridge girder. In this way, the above objective is achieved.

実施例 以下、この発明に係る橋桁のプレストレス導入
方法を順を追つて説明する。
EXAMPLE Hereinafter, a method for introducing prestress into a bridge girder according to the present invention will be explained step by step.

プレキヤストコンクリートからなる複数本の
主桁1,1を橋脚2,2間に平行に架設する。
左右主桁1,1間には所定幅の溝部3,3を主
桁1の全長に渡つて設けるとともに溝部3の下
端部は、左右主桁1,1の下端部にフランジ1
a,1aを主桁1の全長に渡つて形成すること
により完全に塞ぐ。また、主桁1の側面部、す
なわち、溝部3の両側部にはプレキヤストコン
クリート、鉄筋、あるいはスタツドボルト等か
らなる複数個のシアコネクター4,…を主桁1
の側面部全体に渡つて形成する。
A plurality of main girders 1, 1 made of precast concrete are erected in parallel between piers 2, 2.
Grooves 3, 3 of a predetermined width are provided between the left and right main girders 1, 1 over the entire length of the main girder 1.
a, 1a are formed over the entire length of the main girder 1 to completely close it. In addition, a plurality of shear connectors 4 made of precast concrete, reinforcing bars, stud bolts, etc. are attached to the side surfaces of the main girder 1, that is, on both sides of the groove 3.
Formed over the entire side surface of the

実施例では主桁1の成型に際し、プレキヤス
トコンクリートによつて主桁1と一体に形成し
てある。
In the embodiment, when the main girder 1 is molded, it is formed integrally with the main girder 1 using precast concrete.

続いて、主桁1,1間の溝 3内にPC鋼材
5を主桁1の長手方向に沿つて架設する。PC
鋼材5の中央部は下方向に円弧状に懸垂するか
あるいは上方向に円弧状に張る(第2図、第3
図参照)。また、主桁1,1の幅方向に横締め
用のボルト又はPC鋼材10を挿通する。ボル
ト又はPC鋼材10は少なくとも主桁中央を含
む主桁1の長手方向に一定間隔おきに挿通す
る。
Subsequently, the prestressing steel material 5 is erected in the groove 3 between the main girders 1 and 1 along the longitudinal direction of the main girder 1. PC
The central part of the steel material 5 is suspended downward in an arc shape or stretched upward in an arc shape (Figs. 2 and 3).
(see figure). Further, horizontal tightening bolts or PC steel materials 10 are inserted in the width direction of the main girders 1,1. Bolts or PC steel materials 10 are inserted at regular intervals in the longitudinal direction of the main girder 1 including at least the center of the main girder.

続いて、主桁1,1間の溝部3内にコンクリ
ート6を溝部3の全体に渡つて打設し、このコ
ンクリート6が充分に硬化するまで養生する。
Subsequently, concrete 6 is placed in the groove 3 between the main girders 1, 1 over the entire groove 3, and is cured until the concrete 6 is sufficiently hardened.

続いて、コンクリート6が充分に硬化し、左
右主桁1,1が一体化したらPC鋼材5を緊張
または圧縮することによつて橋桁内に所定大の
プレストレスを導入する。また、ボルト又は
PC鋼材10を締付け又は緊張することによつ
て主桁1の幅方向にもプレストレスを導入す
る。なお、必要により主桁1内にも従来通り
PC鋼材によるプレストレスを導入してもよい。
Subsequently, when the concrete 6 is sufficiently hardened and the left and right main girders 1, 1 are integrated, a prestress of a predetermined amount is introduced into the bridge girder by tensioning or compressing the PC steel material 5. Also, bolts or
By tightening or tensioning the PC steel material 10, prestress is also introduced in the width direction of the main girder 1. In addition, if necessary, the inside of main girder 1 can also be installed as before.
Prestressing using prestressing steel may also be introduced.

第4図、第5図は、主桁1としてH形断面やI
形断面の形鋼を使用してなる橋桁を示したもので
以下その施工方法を順を追つて説明する。
Figures 4 and 5 show an H-shaped cross section and an I-shaped cross section as the main girder 1.
This figure shows a bridge girder made of shaped steel with a shaped cross section, and the construction method will be explained step by step below.

第4図において、H形断面の形鋼からからな
る複数本の主桁1,1を橋脚2,2間に平行に
かつ主桁1の幅方向に所定間隔離して架設す
る。主桁1のウエブ部1bの両側には、鉄筋や
スタツドボルトあるいは小片のプレートを溶接
することによつて複数個のシアコネクター4を
ウエブ部1bの全体に渡つて形成する。実施例
では小片のプレートよりシアコネクター4が形
成してある。また、左右主桁1,1間の下端部
は左右主桁1,1のフランジ部1c,1c間に
プレート9を架設することによつて完全に塞
ぐ。プレート9はフランジ部1cに溶接する。
In FIG. 4, a plurality of main girders 1, 1 made of section steel with an H-shaped cross section are constructed parallel to each other between piers 2, 2 and separated by a predetermined distance in the width direction of the main girder 1. On both sides of the web portion 1b of the main girder 1, a plurality of shear connectors 4 are formed over the entire web portion 1b by welding reinforcing bars, stud bolts, or small pieces of plates. In the embodiment, the shear connector 4 is formed from a small plate. Further, the lower end portion between the left and right main girders 1, 1 is completely closed by installing a plate 9 between the flange portions 1c, 1c of the left and right main girders 1, 1. Plate 9 is welded to flange portion 1c.

続いて、左右主桁1,1間にPC鋼材5を主
桁1の長手方向に沿つて架設する(第2図、第
3図参照)。
Subsequently, the PC steel material 5 is erected between the left and right main girders 1, 1 along the longitudinal direction of the main girder 1 (see FIGS. 2 and 3).

続いて左右主桁1,1間にコンクリート6が
硬化するまで充分に養生する。
Subsequently, the concrete 6 between the left and right main girders 1, 1 is sufficiently cured until it hardens.

続いて、コンクリート6が充分に硬化し、左
右主桁1,1が一体化したらPC鋼材5を緊張
または圧縮することによつて橋桁内に所定大の
プレストレスを導入する。
Subsequently, when the concrete 6 is sufficiently hardened and the left and right main girders 1, 1 are integrated, a prestress of a predetermined amount is introduced into the bridge girder by tensioning or compressing the PC steel material 5.

第5図はPC鋼材によるプレストレスの導入が
あまり必要でない場合等に、左右主桁1,1間の
すべてにPC鋼材を架設しないで、左右主桁1,
1間に1ケ所〜2ケ所おきに空洞部7を橋桁の全
長に渡つて設け、この空洞部7を通信用ケーブル
や水道管を通すスペースとして使用する場合の実
施例を示したものである。
Figure 5 shows that in cases where it is not necessary to introduce prestress using prestressing steel materials, prestressing the left and right main girders 1, 1, and 1 without installing prestressing steel materials between the left and right main girders 1 and 1 is not necessary.
This embodiment shows a case where cavities 7 are provided at every one to two locations throughout the entire length of the bridge girder, and the cavities 7 are used as spaces for passing communication cables and water pipes.

第6図は主桁1として円形断面の鋼管を使用し
てなる橋桁を示したもので、そのプレストレス導
入方法は第4図の場合とほぼ同じである。
FIG. 6 shows a bridge girder using a steel pipe with a circular cross section as the main girder 1, and the method of introducing prestress is almost the same as that shown in FIG.

かかる方法によつて構成された橋桁の上に現場
打ちコンクリート等によるスラブ8を構成する。
A slab 8 made of cast-in-place concrete or the like is constructed on the bridge girder constructed by this method.

発明の効果 この発明は、以上の構成からなるので以下の効
果を有する。
Effects of the Invention This invention has the following effects because it has the above configuration.

主桁としてプレキヤストコンクリート部材を
使用して構成された橋桁にプレストレスを導入
する場合、主桁に直接PC鋼材を挿通しないで、
左右主桁間にPC鋼材を挿通し、これに軸力を
導入することにより、在来方法よりはるかに簡
単に必要大のプレストレスを導入することがで
き、主桁断面の縮少化が図れる。
When introducing prestress to a bridge girder constructed using precast concrete members as the main girder, do not insert the prestressing steel directly into the main girder.
By inserting prestressed steel material between the left and right main girders and introducing axial force into it, it is much easier to introduce the necessary amount of prestress than with conventional methods, and the cross section of the main girder can be reduced. .

また、主桁に直接挿通したPC鋼材による従
来のプレストレスの導入方法と、左右主桁間に
挿通したPC鋼材による本願のプレストレスの
導入方法とを併用すれば、PC鋼材1本あたり
の軸力を大幅に小さくすることができ、その結
果として、プレテンシヨン製作用のベンチやそ
の他の装置、機械類の小型化が図れる。
In addition, if the conventional prestress introduction method using prestressed steel materials inserted directly into the main girder and the prestress introduction method of the present application using prestressed steel materials inserted between the left and right main girders are used together, it is possible to The forces can be significantly reduced, resulting in smaller pretensioning benches and other equipment and machinery.

さらに、主桁として形鋼が使用されている場
合にもプレストレスを導入することができるの
で実用性はきわめて高い。
Furthermore, since prestress can be introduced even when section steel is used as the main girder, it is extremely practical.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第3図は、この発明の一実施例を示し
たもので、第1図は橋桁の断面図、第2図、第3
図はPC鋼材の架設状態を示す橋桁の側面図、第
4図〜第6図はこの発明の他の実施例を示す橋桁
の断面図、第7図は従来の橋桁の断面図である。 1……主桁、2……橋脚、3……溝部、4……
シアコネクター、5……PC鋼材、6……コンク
リート、7……空洞部、8……スラブ、9……プ
レート。
Figures 1 to 3 show one embodiment of the present invention, with Figure 1 being a sectional view of a bridge girder, Figures 2 and 3
The figure is a side view of a bridge girder showing the installed state of prestressed steel, FIGS. 4 to 6 are cross-sectional views of bridge girders showing other embodiments of the present invention, and FIG. 7 is a cross-sectional view of a conventional bridge girder. 1... Main girder, 2... Pier, 3... Groove, 4...
Shear connector, 5...PC steel material, 6...Concrete, 7...Cavity part, 8...Slab, 9...Plate.

Claims (1)

【特許請求の範囲】[Claims] 1 橋脚間に側部に複数個のシアコネクターを有
する複数本の主桁を平行に架設するとともにこの
左右橋桁間にPC鋼材を橋桁長手方向に沿つて架
設し、続いて前記左右橋桁間にコンクリートを打
設し、続いて前記コンクリート硬化後、前記PC
鋼材に軸力を導入することにより橋桁内にプレス
トレスを導入することを特徴とする橋桁のプレス
トレス導入方法。
1. A plurality of main girders having multiple shear connectors on the sides are erected in parallel between the piers, and prestressed steel is erected along the longitudinal direction of the bridge girders between the left and right girders, and then concrete is installed between the left and right girders. Then, after the concrete hardens, the PC
A method for introducing prestress into a bridge girder, which is characterized by introducing prestress into the bridge girder by introducing axial force into the steel material.
JP14517885A 1985-07-02 1985-07-02 Introduction of prestress into bridge girdle Granted JPS626005A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14517885A JPS626005A (en) 1985-07-02 1985-07-02 Introduction of prestress into bridge girdle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14517885A JPS626005A (en) 1985-07-02 1985-07-02 Introduction of prestress into bridge girdle

Publications (2)

Publication Number Publication Date
JPS626005A JPS626005A (en) 1987-01-13
JPH0480161B2 true JPH0480161B2 (en) 1992-12-17

Family

ID=15379230

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14517885A Granted JPS626005A (en) 1985-07-02 1985-07-02 Introduction of prestress into bridge girdle

Country Status (1)

Country Link
JP (1) JPS626005A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997032084A1 (en) * 1996-02-29 1997-09-04 Corporation Hork Method of repairing and reinforcing prestressed concrete structure

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62162009A (en) * 1979-09-27 1987-07-17 Asahi Chem Ind Co Ltd Viscose rayon hollow fiber
JP2548264Y2 (en) * 1991-04-02 1997-09-17 株式会社東芝 Mixed-pressure steam turbine
JP6116086B2 (en) * 2012-08-31 2017-04-19 岩佐 隆 Portal culvert structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997032084A1 (en) * 1996-02-29 1997-09-04 Corporation Hork Method of repairing and reinforcing prestressed concrete structure

Also Published As

Publication number Publication date
JPS626005A (en) 1987-01-13

Similar Documents

Publication Publication Date Title
KR101177342B1 (en) Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same
KR100986207B1 (en) Precast psc t-type girder bridge and its construction method
JP2004285738A (en) Box girder bridge structure and method of constructing the same
JP3635004B2 (en) Bridge cantilever construction method
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
JP2003253620A (en) Cable stayed bridge and its construction method
JP2928475B2 (en) Precast concrete girder for composite floor slab
KR101664997B1 (en) Constructing method of precast T type modular composite rahmen bridge and composite rahmen bridge constructed by the same, and construction thing therefor
JPH0480161B2 (en)
JPH0782709A (en) Reinforcing method for concrete structure, employing hollow pc steel bar
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
JP4086863B2 (en) Continuous girder structure in double span girder bridge
KR20060017949A (en) Field-fabricated prestressing steel-composed girder and construction method of continuous bridge using the girder
JPS6282147A (en) Novel prestressed synthetic beam and its construction
JPH03156094A (en) Under-roadbed traverse round section structure and its construction
KR100393132B1 (en) Construction method of composite steel-box bridge using prestress
KR100691664B1 (en) Method of construction for girder bridge
JP2826200B2 (en) Box culvert construction method and block
KR101340507B1 (en) Pretension type composite girder and the bridge construction method therewith
KR100622449B1 (en) Hybrid pier and continuity execution method using the hybrid pier
JP3418606B2 (en) Girder members for PC bridge
JPH0315605Y2 (en)
JPH0426483Y2 (en)
US20030061672A1 (en) Bridge construction method and composite girder for use in same
KR930003436B1 (en) Assembly bridge structure