JPH04202905A - Elevated railway bridge and its construction process - Google Patents

Elevated railway bridge and its construction process

Info

Publication number
JPH04202905A
JPH04202905A JP32965190A JP32965190A JPH04202905A JP H04202905 A JPH04202905 A JP H04202905A JP 32965190 A JP32965190 A JP 32965190A JP 32965190 A JP32965190 A JP 32965190A JP H04202905 A JPH04202905 A JP H04202905A
Authority
JP
Japan
Prior art keywords
slab
railway bridge
elevated railway
installation
main beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP32965190A
Other languages
Japanese (ja)
Other versions
JPH0689525B2 (en
Inventor
Toshio Umehara
梅原 俊夫
Takeo Miyazaki
武雄 宮崎
Iyao Tsuruta
鶴田 五八男
Yoshihiro Murayama
好弘 村山
Kenji Saito
斉藤 建次
Tatsuo Wakai
達夫 若井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON TETSUDO KENSETSU KODAN
SUPANKURIITO CORP KK
Original Assignee
NIPPON TETSUDO KENSETSU KODAN
SUPANKURIITO CORP KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON TETSUDO KENSETSU KODAN, SUPANKURIITO CORP KK filed Critical NIPPON TETSUDO KENSETSU KODAN
Priority to JP32965190A priority Critical patent/JPH0689525B2/en
Publication of JPH04202905A publication Critical patent/JPH04202905A/en
Publication of JPH0689525B2 publication Critical patent/JPH0689525B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To construct an elevated railway bridge easily and in a short time by erecting an installation slab between lateral beams, which are laterally built at the top of a pedestal for an elevated railway bridge, and in the laying direction of the rail and providing main girder, which faces to the pedestal for the elevated railway bridge, on the upper part of the slab together with arranging a snow-storage part between a sound-proof wall, which is formed on the installation slab placed and the main girder. CONSTITUTION:A lateral beam 2 is formed on the top of a pedestal 1 for an elevated railway bridge, and an installation slab 3, which extends in the laying direction of a railway 4a, is formed on the upper surface of the beam 2. Next, a main girder 4 extending across the lateral beam 2 is formed above the installation slab 3. In addition, a snow-storage part 5 is formed between a sound-proof wall 3b, which is formed on both sides of the installation slab 3, and the main girder 4. With this contrivance, the elevated railway bridge can be constructed easily and in a short time.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は高架鉄道橋及びその構築工法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to an elevated railway bridge and its construction method.

(従来の技術) 現在、鉄道に用いられている高架鉄道僑は、第5図に示
すように主梁40、スラブ50、横梁2o及び防音壁3
0が夫々一体に構築されている。
(Prior art) As shown in FIG.
0 are constructed integrally.

これは、現場において柱脚10の上端まで型枠を建ち上
げ、該型枠に現場打ちコンクリートを打設して構築する
ものである。
This is constructed by erecting a formwork up to the upper end of the column base 10 on site and pouring cast-in-place concrete into the formwork.

しかし、この構築方法はわざわざ柱脚1oの上端績で型
枠を建ち上げ、この型枠を柱脚10と同等或はそれ以上
の長さの支保工で支えなければならないため、工費が嵩
むと共に工期も長期化するという問題があった。
However, with this construction method, the formwork must be erected at the top of the column base 1o, and this formwork must be supported with shoring that is equal to or longer than the column base 10, which increases construction costs and There was also the problem of prolonging the construction period.

さらに高架鉄道橋は多雪地帯において、線路上の雪をど
のように処理するかが大きな課題であリ、従来はこの線
路上の雪の処理対策として、散水消雷、ラッセル車又は
ロータリ車等による強制排雪が行われていたが、これら
はいずれも多大の経費を必要とするという問題があった
Furthermore, elevated railway bridges are located in areas with heavy snowfall, so how to deal with snow on the tracks is a major issue. Conventionally, measures to deal with snow on the tracks include water extinguishing, Russell cars, rotary cars, etc. Forced snow removal was carried out by means of a method, but there was a problem in that all of these methods required a large amount of expense.

そこで、これらの問題を解決するなめに、主梁の脇に線
路上等の雪を収容するための貯雪部を備えた高架鉄道橋
が考えられた。
Therefore, in order to solve these problems, an elevated railway bridge was devised with a snow storage section next to the main beam to store snow on the tracks.

これは、現場打ちコンクリートで主梁、スラブ、横梁、
ダクトを夫々一体的に構築するものや、前記スラブを除
くこれらの三部材に鋼材を取り付けてこの四部材とプレ
キャストコンクリート版とを組合わせて構成するものと
がある。
This is cast-in-place concrete with main beams, slabs, cross beams,
There are those in which the ducts are constructed individually, and those in which steel is attached to these three members except the slab, and these four members are combined with a precast concrete slab.

(発明が解決しようとする課題) しかしながら、上記の主梁、スラブ、横梁、ダクトが一
体となったものは、貯雪部のスラブが薄いためひび割れ
が発生する恐れがあり、また主梁とスラブとが一体とな
っているため列車走行時に、主梁の振動がスラブに直接
伝達してスラブも振動させる二次騒音の原因となってい
た。
(Problem to be solved by the invention) However, in the case where the main beam, slab, cross beam, and duct are integrated, there is a risk that cracks may occur because the slab in the snow storage area is thin, and the main beam and slab are Because they are integrated, when the train is running, vibrations from the main beam are directly transmitted to the slab, causing secondary noise that causes the slab to vibrate as well.

また、主梁、横梁、タクトの三部材に鋼材を取り付ける
ものは、鋼材を使用するために材料費が高価になるばか
りでなく、防水工や施工も複雑となるため非経済的であ
った。
Furthermore, attaching steel to the main beam, cross beam, and tactile members was uneconomical because not only did the use of steel increase material costs, but also complicated waterproofing and construction.

本発明は上記のような問題に鑑みてなされたものであり
、その目的は、短期間でかつ容易に構築することができ
、しかも建設費や排雪前等の維持管理費が安価な高架鉄
道橋及びその構築工法を提供することである。
The present invention was made in view of the above-mentioned problems, and its purpose is to provide an elevated railway that can be constructed easily in a short period of time, and that has low construction costs and maintenance costs such as before snow removal. Our objective is to provide bridges and their construction methods.

(課題を達成するための手段) 以上のような課題を達成するための本発明の高架鉄道橋
は、高架鉄道橋用柱脚の上端に横幅方向に掛け渡した横
梁と、該横梁間に線路の敷設方向へ架け渡したプレキャ
ストコンクリート類の設置スラブと、該設置スラブ上で
前記各高架鉄道橋用柱脚間にわたって形成した主梁と、
該主梁と設置スラブの両側に立設した防音壁との間に形
成した貯雪部とによりなることを特徴とする構成にする
ことであり、 埜た、高架鉄道橋の構築工法は、適宜間隔をもって連続
的に立設した高架鉄道橋用柱脚の上端に横梁を掛け渡し
、該横梁間にプレキャストコンクリート版を敷設して線
路の敷設方向へ伸びる設置スラブを形成し、該設置スラ
ブの上面に設置スラブを基盤として支保工を建てて型枠
を設置した後、該型枠内にコンクリートを打設して前記
横梁間に主梁を架設し、設置スラブの両側に防音壁を立
設して該防音壁と前記主梁との間に貯雪部を形成するこ
とを特徴とする構成にすることである。
(Means for Achieving the Objects) The elevated railway bridge of the present invention for achieving the above-mentioned objects includes a cross beam spanned in the width direction at the upper end of the column pedestal for the elevated railway bridge, and a railway track between the cross beams. A precast concrete installation slab spanned in the laying direction, and a main beam formed across the pillar bases for each elevated railway bridge on the installation slab,
The structure is characterized by a snow storage area formed between the main beam and soundproof walls erected on both sides of the installation slab. A cross beam is spanned over the upper end of the column pedestals for an elevated railway bridge that have been erected continuously, and a precast concrete slab is laid between the cross beams to form an installation slab extending in the track laying direction, and the top surface of the installation slab is After constructing shoring based on the installation slab and installing a formwork, concrete is poured into the formwork, a main beam is erected between the horizontal beams, and soundproof walls are erected on both sides of the installation slab. The present invention is characterized in that a snow storage portion is formed between the soundproof wall and the main beam.

(作用) 而して、上記のような構成の高架鉄道橋によれば、主梁
の下側における防音壁との間に貯雪部が形成されること
により、該貯雪部のスペースを大きくとることができる
ので、排雪が容易となって排雪前等の維持管理費を低減
することができると共に、設置スラブ面の上に主梁を架
設するので設置スラブのスペースも大きくとることがで
きる。
(Function) According to the elevated railway bridge configured as described above, a snow storage section is formed between the main beam and the soundproof wall under the main beam, so that a large space can be taken up for the snow storage section. As a result, snow removal becomes easy and maintenance costs before snow removal can be reduced, and since the main beam is constructed on the surface of the installation slab, a large space can be taken up for the installation slab.

また、上記のような高架鉄道橋の構築工法によれば、設
置スラブをプレキャストコンクリート版で形成したこと
により、短期間で構築することができ、しかも長大な支
保工を必要としないなめ、建設費も低減することができ
る。
In addition, according to the method of constructing an elevated railway bridge as described above, the installation slab is formed from a precast concrete slab, so it can be constructed in a short period of time, and there is no need for extensive shoring, which reduces construction costs. can also be reduced.

(実施例) 以下、本発明の一実施例を図面に基ついて詳細に説明す
る。
(Example) Hereinafter, an example of the present invention will be described in detail based on the drawings.

第1図は高架鉄道橋の横断面図、第2図は同側面図を夫
々示す。
Figure 1 shows a cross-sectional view of the elevated railway bridge, and Figure 2 shows a side view of the same.

高架鉄道橋Aは高架鉄道橋用柱脚1の上端に横梁2を形
成し、該横梁2の上面にテレキャストコンクリート版3
aを敷設して線路4aの敷設方向に伸びる設置スラブ3
を形成し、該設置スラブ3上の前記横梁2間に渡って主
梁4を形成することにより、該主梁4と設置スラブ3両
側の防音壁3bとの間に貯雪部5を形成して構成されて
いる。
The elevated railway bridge A has a cross beam 2 formed at the upper end of the column pedestal 1 for the elevated railway bridge, and a telecast concrete slab 3 on the upper surface of the cross beam 2.
Installation slab 3 that extends in the direction in which the track 4a is laid by laying the track 4a.
By forming a main beam 4 across between the horizontal beams 2 on the installation slab 3, a snow storage section 5 is formed between the main beam 4 and the soundproof walls 3b on both sides of the installation slab 3. It is configured.

前記主梁4は設置スラブ3上に形成した型枠に現場打ち
コンクリートを打設することにより、横梁2で支持され
るように形成される。そして、この主梁4の形成により
隣接する横梁2が強固に結合されて耐震的に優れた構造
となる。
The main beam 4 is formed so as to be supported by the cross beams 2 by pouring cast-in-place concrete into a formwork formed on the installation slab 3. By forming the main beam 4, the adjacent cross beams 2 are firmly connected, resulting in a structure with excellent earthquake resistance.

また、主梁4はその荷重を高架鉄道橋用柱脚1で支持す
るように、高架鉄道橋用柱脚1上に形成され、その上面
に線路4aが敷設される。
Further, the main beam 4 is formed on the elevated railway bridge column pedestal 1 so that the load thereof is supported by the elevated railway bridge column pedestal 1, and a track 4a is laid on the upper surface thereof.

このように主梁4が横梁2と設置スラブ3上に設置され
なので、該主梁4の脇の下側に貯雪部5が形成され、該
貯雪部5へ線路4a上に積もった雪を排雪することがで
きる。
Since the main beam 4 is installed on the cross beam 2 and the installation slab 3 in this way, a snow storage section 5 is formed under the armpit of the main beam 4, and the snow accumulated on the track 4a is removed to the snow storage section 5. be able to.

次に、この高架鉄道橋Aの構築工法について説明する。Next, the construction method for this elevated railway bridge A will be explained.

第3図及び第4図は高架鉄道橋Aの構築工法を示した横
断面図及び側面図である。
Figures 3 and 4 are a cross-sectional view and a side view showing the construction method of the elevated railway bridge A.

〔横梁の形成〕[Formation of cross beams]

先ず初めに、線路4aの敷設方向にそって適宜間隔をも
って立設された、各高架鉄道横用柱脚1の上端に横梁2
を形成する。これは高架鉄道横用柱脚1の上端に型枠を
形成し、該型枠に鉄筋を配筋して、現場打ちコンクリー
トを打設することにより形成するものである。
First of all, cross beams 2 are attached to the upper ends of each elevated railway horizontal column base 1, which are erected at appropriate intervals along the laying direction of the track 4a.
form. This is formed by forming a formwork at the upper end of the elevated railway horizontal column base 1, arranging reinforcing bars in the formwork, and pouring cast-in-place concrete.

[設置スラブの敷設j 次に、前記横梁2間にわたってプレキャストコンクリー
ト版3aを夫々掛け渡して、線路4aの敷設方向に設置
スラブ3を形成する。
[Laying of Installation Slabs j Next, precast concrete slabs 3a are stretched between the cross beams 2 to form installation slabs 3 in the laying direction of the track 4a.

[主梁の形成コ             ζ上記のよ
うに横梁2と設置スラブ3を形成した後、該設置スラブ
3を基盤としてその上面に支保工を立設して主梁4用の
型枠を形成する。
[Formation of the main beam ζ After forming the cross beam 2 and the installation slab 3 as described above, a formwork for the main beam 4 is formed by using the installation slab 3 as a base and erecting a support on its upper surface.

この際、主梁4のコンクリートの自重による支保工の沈
下量を予め計算し、所要の量だけ上げ越しをしておく。
At this time, the amount of subsidence of the support due to the weight of the concrete of the main beam 4 is calculated in advance, and the amount of settlement is exceeded by the required amount.

そして、型枠内に鉄筋を配筋して現場打ちコンクリート
を打設すると、主梁4と横梁2とが接続される。
Then, when reinforcing bars are arranged within the formwork and cast-in-place concrete is placed, the main beam 4 and the cross beam 2 are connected.

[貯雪部の形成] 次に、前記型枠に打設したコンクリートが硬化した後に
型枠を解体する。そして、設置スラブ3の両側に防音壁
3b用の支持柱3Cを横梁2の間隔ごとに立設すると共
に、防音壁3bをクレーンで吊り上げて支持柱3Cに取
り付けることにより、主梁4の脇の下側と防音壁3bと
の開に貯雪部5が形成される。
[Formation of snow storage section] Next, after the concrete cast in the formwork has hardened, the formwork is dismantled. Then, support columns 3C for the soundproof walls 3b are erected on both sides of the installation slab 3 at intervals of the cross beams 2, and the soundproof walls 3b are lifted up with a crane and attached to the support columns 3C, so that A snow storage section 5 is formed between the soundproof wall 3b and the soundproof wall 3b.

(発明の効果) 本発明は以上のような構成にしたことにより下記の効果
を有する。
(Effects of the Invention) The present invention has the following effects by having the above configuration.

■ 設置スラブをプレキャストコンクリート版で形成す
ると共に、主梁を設置スラブの上面に設けたので、該主
梁の下側における防音壁との間に、貯雪スペースを大き
くとることができる。
(2) Since the installation slab is formed from a precast concrete slab and the main beam is provided on the top surface of the installation slab, a large snow storage space can be provided between the main beam and the soundproof wall below the main beam.

■ スラブ面が広く使用できるので、該スラブ面での作
業性及び安全性が向上すると共に、ケーブル用ダクトの
設置場所を任意の箇所に選択することができる。
(2) Since the slab surface can be used widely, workability and safety on the slab surface are improved, and the installation location of the cable duct can be selected at any location.

■ 主梁と設置スラブとが一体に形成されていないので
、列車通過時における主梁の振動が直接スラブに伝わる
ことがなく、二次騒音が大幅に軽減される。
■ Since the main beam and installation slab are not integrally formed, the vibrations of the main beam when a train passes are not directly transmitted to the slab, significantly reducing secondary noise.

■ プレキャストコンクリート版の力学的性状がはっき
りしているなめ、支保工の上げ越し計算予測値の確度が
高い。
■ Because the mechanical properties of the precast concrete slab are clear, the predicted values for the shoring overhang calculation are highly accurate.

■ 高架鉄道橋において大きな割合を占めるスラブがプ
レキャストコンクリート版で形成されることにより、型
枠設置、鉄筋組立、コンクリート養生等の工程がなくな
るので、短期間に高架鉄道橋を構築することができる。
■ Since the slab, which makes up a large proportion of elevated railway bridges, is formed from precast concrete slabs, processes such as formwork installation, reinforcing steel assembly, and concrete curing are eliminated, making it possible to construct elevated railway bridges in a short period of time.

■ 主梁を形成する際に、該主梁の型枠を支持する支保
工を設置スラブ面から建てることができるので、支保工
の空立槓が大幅に減少し、軽済的でかつ短期間に高架鉄
道橋を構築することができる。
■ When forming the main beam, the support that supports the formwork of the main beam can be erected from the installation slab surface, which greatly reduces the amount of empty erecting of the support, which is economical and short-term. Elevated railway bridges can be built.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は高架鉄道橋の横断面図、第2図は同側面図、第
3図は高架鉄道橋の構築方法を示す横断面図、第4図は
同側面図、第5図は従来の高架鉄道橋の横断面図、第6
図は同縦断面図である。 図中、 A°高架鉄道橋 1 高架鉄道横用柱脚    2・横梁3:プレキャス
トコンクリート版で構築した設置スラブ 3a プレキャストコンクリート版 3b:防音壁   3c、防音壁用支柱4 主梁   
  5.貯雪部 である。 第1図 第2図 第5図 第6図 美
Figure 1 is a cross-sectional view of an elevated railway bridge, Figure 2 is a side view of the same, Figure 3 is a cross-sectional view showing the method of constructing an elevated railway bridge, Figure 4 is a side view of the same, and Figure 5 is a conventional Cross section of elevated railway bridge, No. 6
The figure is a longitudinal sectional view of the same. In the diagram, A° Elevated railway bridge 1 Elevated railway horizontal column base 2/Horizontal beam 3: Installation slab constructed from precast concrete slab 3a Precast concrete slab 3b: Soundproof wall 3c, Soundproof wall support 4 Main beam
5. This is the snow storage section. Figure 1 Figure 2 Figure 5 Figure 6 Beauty

Claims (2)

【特許請求の範囲】[Claims] (1)高架鉄道橋用柱脚の上端に横幅方向に掛け渡した
横梁と、該横梁間に線路の敷設方向へ架け渡したプレキ
ャストコンクリート製の設置スラブと、該設置スラブ上
で前記各高架鉄道橋用柱脚間にわたって形成した主梁と
、該主梁と設置スラブの両側に立設した防音壁との間に
形成した貯雪部とによりなることを特徴とする高架鉄道
橋。
(1) A cross beam spanned across the upper end of the column pedestal for an elevated railway bridge in the width direction, a precast concrete installation slab installed between the cross beams in the track laying direction, and each of the above-mentioned elevated railways on the installation slab. 1. An elevated railway bridge comprising a main beam extending between bridge columns, and a snow storage section formed between the main beam and soundproof walls erected on both sides of an installation slab.
(2)適宜間隔をもって連続的に立設した高架鉄道橋用
柱脚の上端に横梁を掛け渡し、該横梁間にプレキャスト
コンクリート版を敷設して線路の敷設方向へ伸びる設置
スラブを形成し、該設置スラブの上面に設置スラブを基
盤として支保工を建てて型枠を設置した後、該型枠内に
コンクリートを打設して前記横梁間に主梁を架設し、設
置スラブの両側に防音壁を立設して該防音壁と前記主梁
との間に貯雪部を形成することを特徴とする高架鉄道橋
の構築工法。
(2) Cross beams are spanned over the upper ends of elevated railway bridge pillars that have been erected continuously at appropriate intervals, and a precast concrete slab is laid between the cross beams to form an installation slab that extends in the direction in which the railway is laid. After constructing a support structure and installing a formwork on the top surface of the installation slab using the installation slab as a base, concrete is poured into the formwork and a main beam is erected between the horizontal beams, and soundproof walls are installed on both sides of the installation slab. A method for constructing an elevated railway bridge, characterized in that a snow storage section is formed between the soundproof wall and the main beam by erecting the soundproof wall.
JP32965190A 1990-11-30 1990-11-30 Elevated railway bridge and its construction method Expired - Lifetime JPH0689525B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32965190A JPH0689525B2 (en) 1990-11-30 1990-11-30 Elevated railway bridge and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32965190A JPH0689525B2 (en) 1990-11-30 1990-11-30 Elevated railway bridge and its construction method

Publications (2)

Publication Number Publication Date
JPH04202905A true JPH04202905A (en) 1992-07-23
JPH0689525B2 JPH0689525B2 (en) 1994-11-09

Family

ID=18223729

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32965190A Expired - Lifetime JPH0689525B2 (en) 1990-11-30 1990-11-30 Elevated railway bridge and its construction method

Country Status (1)

Country Link
JP (1) JPH0689525B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100601100B1 (en) * 2004-12-21 2006-07-19 재단법인 포항산업과학연구원 Personal rapid transit bridge with steel tubes
JP2011157720A (en) * 2010-02-01 2011-08-18 Fujita Corp Method for constructing railway reinforced concrete rigid-frame structure viaduct

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100601100B1 (en) * 2004-12-21 2006-07-19 재단법인 포항산업과학연구원 Personal rapid transit bridge with steel tubes
JP2011157720A (en) * 2010-02-01 2011-08-18 Fujita Corp Method for constructing railway reinforced concrete rigid-frame structure viaduct

Also Published As

Publication number Publication date
JPH0689525B2 (en) 1994-11-09

Similar Documents

Publication Publication Date Title
GB1398435A (en) Concrete bridges
WO2006062801A2 (en) Bridge construction system and method
JP2022023107A (en) System for construction of complex u-shaped reinforcement beam bridge deck, and method thereof
KR100603901B1 (en) Girder bridge construction make use of a part existing girder and that execution method
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
JP3737475B2 (en) Box girder bridge structure and construction method
JPH04202905A (en) Elevated railway bridge and its construction process
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
JP3701078B2 (en) Road slab construction method
GB2343205A (en) Construction of track side platforms
JP2536376B2 (en) Foundation structure of shed for road protection
KR910007423B1 (en) Method for construction p.c - beam on the bridge
JP2000104220A (en) Erection of combined truss bridge
JP3028157B2 (en) Railroad viaduct structure
JP2020186516A (en) Method of constructing bridge railing
US1212759A (en) Composite beam.
JP3824242B2 (en) Viaduct-free support construction method
KR102670768B1 (en) Steel composite ramen bridge reinforced with section steel supports and crossing rebars and its construction method
JP7483594B2 (en) How to build a box girder bridge
JPH05287759A (en) Construction method of reinforced concrete foundation beam
JP7242821B1 (en) Concrete balustrade construction method
US11732428B2 (en) System for construction of double u and single u steel concrete composite structure for bridges
KR100729844B1 (en) Repair work of railroad bridge and that structure
JP3665909B2 (en) Bridge reconstruction method
JP3008040B2 (en) Large span composite slab erection method