JP3665909B2 - Bridge reconstruction method - Google Patents
Bridge reconstruction method Download PDFInfo
- Publication number
- JP3665909B2 JP3665909B2 JP32974194A JP32974194A JP3665909B2 JP 3665909 B2 JP3665909 B2 JP 3665909B2 JP 32974194 A JP32974194 A JP 32974194A JP 32974194 A JP32974194 A JP 32974194A JP 3665909 B2 JP3665909 B2 JP 3665909B2
- Authority
- JP
- Japan
- Prior art keywords
- girder
- concrete
- iron
- rail
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Description
【0001】
【産業上の利用分野】
本発明は、鉄道線路等の鉄桁を、列車運行を停止させることなく、コンクリート桁等に改築する工法である。
【0002】
【従来の技術】
通常、鉄道線路等の橋梁は、橋台どうしの間に鉄桁が架設される場合と、コンクリート桁が架設される場合とがある。鉄桁の場合は、鉄桁の上面側に枕木が直接設置され、該枕木の上にレールが敷設される。またコンクリート桁の場合は、該コンクリート桁の上にバラストが投入され、該バラスト上に枕木が設置されて更にこの枕木上にレールが敷設される。
【0003】
鉄桁の場合は、この領域ではマルチプルタイタンパ等による自動的な保線作業を中断しなければならず、保線作業の自動化が困難であった。そのため、最近では鉄桁を保線作業の自動化が可能なコンクリート桁等へ変更する傾向にある。
従来にあって、鉄道線路等の鉄桁をコンクリート桁やコンクリート中にH形鋼を埋設した埋め込み桁に取り替える場合は、クレーンによる一括架設法や横取り架設法又は縦取り架設法と呼ばれる方法が行われていた。
【0004】
クレーンによる一括架設法は、予め新たに架設するコンクリート桁等を別の場所で構築し、既設の鉄桁をクレーンで撤去した後、新規のコンクリート桁等をクレーンで吊り上げて橋台へ設置するものである。
【0005】
また横取り架設法は、線路脇の隣位の位置で新たに架設するコンクリート桁を構築し、既設の鉄桁を撤去した後、前記新規なコンクリート桁を横取り梁及び台車を介して横スライドさせ、設置する方法である。
【0006】
更に、縦取り架設法は、線路脇に門型クレーンの移動レールを設置し、橋梁から線路方向に離れた広い場所でコンクリート桁を構築すると共に、橋梁に架設してある既設の鉄桁をこの門型クレーンで吊り上げて撤去し、撤去した後に予め構築しておいた前記コンクリート桁を門型クレーンで吊り上げて橋梁の位置まで運搬し、設置するようにしている。
【0007】
【発明が解決しようとする課題】
然しながら、前記クレーンによる一括架設法にあっては、橋梁の近傍にクレーンスペースが必要であって、これらのスペースのない場所では実施不可能であった。またクレーンに要する費用が高くなるという欠点があった。
一方、横取り架設法にあっては、線路脇にスペアのコンクリート桁を構築するスペースが必要であった。
更に、縦取り架設法にあっては、門型クレーンを使用するため設備の全体が大型化するという欠点があった。そのため、この縦取り架設法は、多数の線路が併設されている場所では採用することができないでいた。
【0008】
またこれらの従来法にあっては、いずれの場合も既設の鉄桁の撤去作業開始からコンクリート桁設置完了までの長時間にわたって列車の運行を停止させなければならなかった。そのため、列車運行間隔の短い線路区間では、採用できないでいた。
更にまた、本線や引き込み線用の架線等が設けられている部分では、クレーンを用いる方法は架線と干渉する虞れがあり、採用できないのが通常であった。
【0009】
【課題を解決するための手段】
本発明は従来の前記課題に鑑みてこれを改良除去したものであって、列車運行を停止させることなく、しかもクレーン等の重機を使用することなく、鉄桁をコンクリート桁等に改築することのできる工法を提供せんとするものである。
【0010】
而して、前記課題を解決するために本発明が採用した手段は、鉄道線路等の鉄桁を、列車運行を停止させることなく、コンクリート桁等に改築する工法であって、レールを支持する鉄桁の両側面部に設けられた保守用通路を撤去し、撤去した領域の橋台台座のレール方向に沿った両サイドに鋼材を配設して側型枠とし、これらの側型枠間に所定幅の鋼板を多数配設して底型枠とし、前記側型枠と底型枠との間に鉄筋を配設してコンクリートを打設することにより第1のコンクリート桁を構築し、鉄桁の両側面部における第1のコンクリート桁上にレール方向に沿った工事用桁を設置し、既設の枕木どうしの間のレール下方に前記工事用桁どうしの間に跨がる横桁を配設した後、既設の枕木を撤去し、続いて既設の鉄桁を撤去し、鉄桁を撤去した後の空間に面する前記側型枠どうしの間に所定幅の鋼板を多数配設して底型枠とし、これらの側型枠と底型枠との間に鉄筋を配設してコンクリートを打設して第2のコンクリート桁を構築し、最後にバラストを投入して工事用桁を撤去したことを特徴とする橋梁の改築工法である。
【0011】
【作用】
本発明の橋梁の改築工法にあっては、先ず、鉄桁が架設された橋梁のレールの両側面部に設けられた各保守用通路を撤去している。そして、撤去後の橋台の台座部分を補修し、該補修した各領域部分の両サイドにレール方向に沿った鋼材からなる側型枠を配設する。続いて、側型枠どうしの間に鋼板からなる底型枠を配置し、これらの側型枠と底型枠とからなる空間領域に、鉄筋を配設後、コンクリートを打設し、前記側型枠と底型枠とを一体的に埋め込んだ第1のコンクリート桁を構築する。
【0012】
次に、この第1のコンクリート桁上に鉄桁の両側面に沿った工事用桁を載置し、既設の枕木どうしの間のレール下方に、前記工事用桁どうしの間に跨がる横桁を配設する。これにより、レール荷重を前記横桁と、工事用桁及び第1のコンクリート桁で支持することが可能である。
【0013】
然る後は、既設の枕木を撤去し、続いて既設の鉄桁を撤去する。この鉄桁の撤去は、橋梁の下面側から所定寸法に鉄桁を溶断して行えばよい。そして、鉄桁を撤去した後の空間領域において、前記第1のコンクリート桁の片面に露呈する側型枠どうしの間に、底型枠を配置する。次に、これらの側型枠と底型枠との間に、鉄筋を配し、コンクリートを打設する。これにより、レールを支持する第2のコンクリート桁を構築することが可能である。
【0014】
このレール支持用の第2のコンクリート桁構築後は、レール下方にバラストを投入し、工事用桁を撤去すればよい。
これにより、鉄桁をコンクリート桁に改築することが可能であり、また第1のコンクリート桁は、そのまま保守点検用のコンクリート桁として利用することが可能である。
本発明の改築工法であれば、列車運行を停止させることなく行うことが可能であり、また各構成部材を小さく且つ分断することができ、重機等を使用しなくても施工することが可能である。
【0015】
【実施例】
以下に、本発明の工法を図面に示す実施例に基づいて説明すると次の通りである。
図1乃至図4は本発明の一実施例に係るものであり、図1の図(a)〜図(e)はそれぞれ工程途中を示す図面であり、図2は第1のコンクリート桁と工事用桁との関係を示す縦断面図、図3は横桁を示す縦断面図、図4は第1のコンクリート桁とレール支持用の第2のコンクリート桁との連結関係を示す縦断面図である。
【0016】
図1の図(a)は、従来の鉄桁1を有する橋梁の縦断面図である。この従来のままの橋梁は、橋台2どうしの間に鉄桁1が架設され、鉄桁1の上面に直接枕木3が配設され、更に枕木3の上面側にレール4が敷設されている。この場合、鉄桁1及びレール4は、上り用と下り用とが設けられた複線区間である。
【0017】
鉄桁1の両サイドには、それぞれ保守用の点検通路5が設けられている。この保守用の点検通路5は、橋台2どうしの間に並列状に架設された複数個のH型鋼6の上面に、鋼板7を設置したものであり、線路の両脇及び線路どうしの間の三箇所に設けられている。
【0018】
改築は、このような状態から先ず、保守用の点検通路5を構成する鋼板7とH型鋼6とを撤去することから開始される。そして、撤去後の橋台2の台座上面側を図(a)の斜線で示す分だけ削り取って、後工程で行われる鉄桁1を撤去した場合の鉄桁1の台座面と同一平坦面になるように補修する。
【0019】
そして、各点検通路5の補修後の橋台2の台座上面にあって、レール方向に沿った両サイドに、H形鋼の鋼材からなる側型枠8又は溝形鋼の鋼材からなる側型枠9を設置する。H形鋼の側型枠8は、高さ400mm、幅200mm、フランジの厚み6mm、ウエブの厚み9mm、全体の長さ5.12mで重さが246Kgである。また溝形鋼の側型枠9は、高さ382mm、幅150mm、フランジの厚み6mm、ウエブの厚み9mm、全体の長さ5.12mで重さが235Kgである。このような長さ及び重さの側型枠8及び9であれば、クレーンを使用せずとも、人手によって運搬施工することが可能である。
【0020】
このような鋼材からなる側型枠8及び9を補修後の橋台1の台座上面に設置した後は、線路両脇の側型枠8及び9どうし並びに線路間の側型枠8どうしの対向するフランジに、幅300mm、厚み6mmで所定間隔ごとにリブが立設された鋼板多数からなる底型枠10をレール方向とクロスする方向に架設する。
然る後は、これらの側型枠8及び9どうしと底型枠10とで形成される空間領域内に、鉄筋を配設し、コンクリートを打設して線路間及び線路両脇の保守用点検通路5の代わりに、図1の図(b)に示すような、第1のコンクリート桁11を構築する。
【0021】
次に、該第1のコンクリート桁11の上面にあって、鉄桁1の両サイドにH形鋼の上面側の片面のフランジを切除した軽量形鋼からなる工事用桁12を設置する。この設置は、図2に示すように第1のコンクリート桁11に埋設した植え込みボルト13を利用してナット14で締結すればよい。
またこの工事用桁12は、コンクリート桁11の上面に設置するので、橋台2どうしの間に跨がる長さにする必要はなく、作業員の運搬に適した重さになる長さに分断して設置するようにすればよい。
【0022】
然る後は、図3に示すように、溝形鋼15で枕木3の上面を除く三側面をカバーした横桁16を、鉄桁1の上面側の既設の枕木3どうしの間に装入し、その両端を工事用桁12どうしの間に載置して架設する。これにより、レール4に作用する荷重を前記横桁16と、工事用桁12及び第1のコンクリート桁11で支持することが可能である。
【0023】
このようにしてレール4に作用する荷重を受け代えた後は、既設の枕木3及びこれを支持する鉄桁1は機能しなくなるので、図1の図(c)に示すように、これらを撤去する。既設の枕木3の撤去は、線路面側で行えばよく、また鉄桁1の撤去は、橋梁の下面側から鉄桁1を撤去し易い所定寸法に溶断して行えばよい。
【0024】
次に、鉄桁1を撤去した後の空間領域において、前記第1のコンクリート桁11の片面に露呈する側型枠8どうしの間に、例えば、幅300mm、厚み6mm、長さ1.70mで所定間隔ごとにリブの立設された鋼板多数からなる底型枠17を配置する。
そして、これらの側型枠8と底型枠17とで囲まれた空間領域内に、鉄筋を配設し、コンクリートを打設する。これにより、図1の図(d)に示すように、レール4を支持する第2のコンクリート桁18を構築することが可能である。
【0025】
なお、鉄筋の配設は、底型枠17を架設する以前に、側型枠8のフランジに載置準備しておき、底型枠17を架設した後、所定位置へ配設するようにすれば、橋梁の下面側から全ての作業が行え、便利である。また鉄筋は、図4に示すように、第1のコンクリート桁11を構築するときに、つなぎ用の鉄筋19を鉄桁1側の方へ突出させておき、第2のコンクリート桁18の鉄筋20を配設するときに連結するようにすれば、第1のコンクリート桁11とレール支持用の第2のコンクリート桁18との連結強度が向上する。
【0026】
然る後は、図1の図(e)に示すように、左右のコンクリート桁11,11の両端に堤21を設けた上で、レール4の下方にバラスト22を投入し、工事用桁12を撤去すればよい。これにより、鉄桁1を第2のコンクリート桁18に改築することが可能であり、また第1のコンクリート桁11は、そのまま保守点検用として利用することが可能である。
【0027】
ところで、本発明は上述した実施例に限定されるものではなく、適宜の変更が可能である。例えば、第1のコンクリート桁11及びレール支持用の第2のコンクリート桁18は、その内部にH形鋼を埋め込んだものとしてもよい。また橋台2間の長さにほぼ等しい桁長は、5.12mに限られるものではなく、現場に応じて適宜決定されるものである。12m程度までの桁長であれば、重機を用いることなく作業員のみで行うことができ、経済的に有利な施工が得られる。
【0028】
【発明の効果】
以上説明したように本発明にあっては、列車運行を停止させることなく、鉄桁をコンクリート桁に改築することが可能である。また各構成部材を小さく且つ分断することができるので、作業員の手作業による運搬作業が可能で、クレーン等の重機を使用しなくても施工することが可能であり、施工費用を削減することができると共に、重機使用に伴う一般道路等の交通を遮断する必要もない。
【図面の簡単な説明】
【図1】図(a)〜図(e)は本発明の一実施例に係る工程途中を示す縦断面図である。
【図2】本発明に係る第1のコンクリート桁と工事用桁との取付関係を示す縦断面図である。
【図3】本発明に係る横桁を示す縦断面図である。
【図4】本発明に係る第1のコンクリート桁とレール支持用の第2のコンクリート桁との鉄筋による連結構造を示す縦断面図である。
【符号の説明】
1…鉄桁 2…橋台
3…枕木 4…レール
8…H形鋼の側型枠 9…溝形鋼の側型枠
10…底型枠 11…第1のコンクリート桁
12…工事用桁 16…横桁
17…底型枠 18…レール支持用の第2のコンクリー
ト桁 21…バラスト[0001]
[Industrial application fields]
The present invention is a method for rebuilding an iron girder such as a railway track into a concrete girder or the like without stopping train operation.
[0002]
[Prior art]
Usually, a bridge such as a railway track has a case where an iron girder is erected between abutments and a case where a concrete girder is erected. In the case of iron girders, sleepers are directly installed on the upper surface side of the iron girders, and rails are laid on the sleepers. In the case of a concrete girder, ballast is put on the concrete girder, a sleeper is installed on the ballast, and a rail is laid on the sleeper.
[0003]
In the case of iron girders, in this area, automatic track maintenance work such as multiple tie tampers has to be interrupted, making it difficult to automate track maintenance work. Therefore, recently, there is a tendency to change iron girders to concrete girders that can automate track maintenance.
In the past, when replacing iron girders such as railway tracks with concrete girders or embedded girders with H-shaped steel embedded in concrete, a method called a collective erection method, a horizontal erection method, or a vertical erection method is performed. It was broken.
[0004]
The method of erection using a crane is to construct a new concrete girder, etc., to be newly constructed in advance in another location, remove the existing iron girder with a crane, and then lift the new concrete girder, etc. with a crane and install it on the abutment. is there.
[0005]
In addition, the side-by-side construction method is to construct a concrete girder to be newly constructed at a position next to the track side, remove the existing iron girder, and then slide the new concrete girder laterally through a side-beam and a carriage. How to install.
[0006]
In addition, the vertical installation method is to install a gate-type crane moving rail on the side of the track, construct a concrete girder in a wide place away from the bridge in the track direction, and replace the existing iron girder installed on the bridge with this The concrete girder that has been built in advance after being lifted by a portal crane is lifted by a portal crane, transported to the position of the bridge, and installed.
[0007]
[Problems to be solved by the invention]
However, in the collective erection method using the crane, a crane space is required in the vicinity of the bridge, and cannot be performed in a place without these spaces. In addition, there is a drawback that the cost required for the crane is high.
On the other hand, in the horizontal installation method, a space for constructing a spare concrete girder was required beside the track.
Furthermore, the vertical installation method has a drawback that the entire equipment is enlarged because a portal crane is used. Therefore, this vertical installation method cannot be adopted in a place where a large number of tracks are provided.
[0008]
Moreover, in these conventional methods, in any case, the train operation had to be stopped for a long time from the start of the removal work of the existing iron girder to the completion of the concrete girder installation. For this reason, it was not possible to adopt it in the track section where the train operation interval was short.
Furthermore, in a portion where a main line, a lead-in line overhead line, or the like is provided, a method using a crane may interfere with the overhead line, and cannot usually be adopted.
[0009]
[Means for Solving the Problems]
The present invention is an improvement and removal in view of the above-described problems of the prior art, and without changing train operation and without using heavy equipment such as cranes, the iron girder can be remodeled into a concrete girder or the like. It is intended to provide a method that can be used.
[0010]
Thus, the means adopted by the present invention in order to solve the above problems is a method of reconstructing an iron girder such as a railway line into a concrete girder or the like without stopping the train operation, and supports the rail. Remove the maintenance passages on both sides of the steel girder, and place steel on both sides along the rail direction of the abutment pedestal in the removed area to form side molds. A first concrete girder is constructed by arranging a large number of steel plates of width to form a bottom mold, placing a reinforcing bar between the side mold and the bottom mold and placing concrete. A construction girder along the rail direction was installed on the first concrete girder on both side surfaces of the slab, and a horizontal girder straddling the construction girder was arranged below the rails between the existing sleepers After that, the existing sleepers are removed, then the existing iron girders are removed, and the iron girders are removed. A large number of steel plates with a predetermined width are arranged between the side molds facing the rear space to form a bottom mold, and reinforcing bars are arranged between these side molds and the bottom mold to provide concrete. This is a bridge remodeling method characterized in that a second concrete girder was constructed by casting and the ballast was inserted at the end to remove the construction girder.
[0011]
[Action]
In the bridge remodeling method of the present invention, first, the respective maintenance passages provided on both side portions of the rail of the bridge on which the iron girder is installed are removed. And the base part of the abutment after removal is repaired, and the side formwork which consists of steel materials along a rail direction is arrange | positioned on both sides of each repaired area | region part. Subsequently, a bottom mold made of a steel plate is arranged between the side molds, and after placing reinforcing bars in a space region composed of these side molds and the bottom mold, the concrete is placed, A first concrete girder in which the formwork and the bottom formwork are integrally embedded is constructed.
[0012]
Next, a work girder along both sides of the iron girder is placed on the first concrete girder, and the side spanning between the work girder is placed below the rails between the existing sleepers. Arrange the girders. As a result, the rail load can be supported by the cross beam, the construction beam and the first concrete beam.
[0013]
After that, the existing sleepers will be removed, and then the existing iron girders will be removed. The removal of the iron girder may be performed by fusing the iron girder to a predetermined dimension from the lower surface side of the bridge. And in the space area | region after removing an iron girder, a bottom mold is arrange | positioned between the side molds exposed on the single side | surface of a said 1st concrete girder. Next, reinforcing bars are placed between these side molds and bottom molds, and concrete is placed. Thereby, it is possible to construct | assemble the 2nd concrete girder which supports a rail.
[0014]
After the construction of the second concrete girder for supporting the rail, ballast may be put under the rail and the construction girder may be removed.
Thereby, it is possible to reconstruct an iron girder into a concrete girder, and the first concrete girder can be used as it is as a concrete girder for maintenance inspection.
With the reconstruction method of the present invention, it is possible to carry out without stopping the train operation, and each component can be made small and divided, and construction can be performed without using heavy machinery or the like. is there.
[0015]
【Example】
The construction method of the present invention will be described below based on the embodiments shown in the drawings.
FIGS. 1 to 4 relate to one embodiment of the present invention, and FIGS. 1 (a) to (e) are drawings showing the course of the process, and FIG. 2 is the first concrete girder and construction. FIG. 3 is a longitudinal cross-sectional view showing a relationship with a girder, FIG. 3 is a longitudinal cross-sectional view showing a transverse girder, and FIG. 4 is a longitudinal cross-sectional view showing a connection relationship between a first concrete girder and a second concrete girder for rail support. is there.
[0016]
FIG. 1A is a longitudinal sectional view of a bridge having a
[0017]
[0018]
The reconstruction is started from removing the
[0019]
And it is in the upper surface of the base of the
[0020]
After installing the
After that, in the space formed by these
[0021]
Next, on the upper surface of the first
Moreover, since this
[0022]
After that, as shown in FIG. 3, the
[0023]
After the load acting on the
[0024]
Next, in the space region after the
Then, reinforcing bars are placed in the space region surrounded by the
[0025]
It should be noted that the reinforcing bars are arranged to be placed on the flange of the
[0026]
After that, as shown in FIG. 1 (e), the
[0027]
By the way, this invention is not limited to the Example mentioned above, A suitable change is possible. For example, the first
[0028]
【The invention's effect】
As described above, in the present invention, an iron girder can be remodeled into a concrete girder without stopping train operation. In addition, since each component can be made small and divided, it can be transported manually by workers, and can be constructed without using heavy equipment such as cranes, reducing construction costs. In addition, it is not necessary to block traffic on general roads associated with the use of heavy machinery.
[Brief description of the drawings]
FIG. 1A to FIG. 1E are vertical cross-sectional views showing a process in the middle of an embodiment of the present invention.
FIG. 2 is a longitudinal sectional view showing a mounting relationship between a first concrete girder and a construction girder according to the present invention.
FIG. 3 is a longitudinal sectional view showing a cross beam according to the present invention.
FIG. 4 is a longitudinal sectional view showing a connecting structure of a first concrete girder according to the present invention and a second concrete girder for rail support by reinforcing bars.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP32974194A JP3665909B2 (en) | 1994-11-21 | 1994-11-21 | Bridge reconstruction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP32974194A JP3665909B2 (en) | 1994-11-21 | 1994-11-21 | Bridge reconstruction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08144205A JPH08144205A (en) | 1996-06-04 |
JP3665909B2 true JP3665909B2 (en) | 2005-06-29 |
Family
ID=18224766
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP32974194A Expired - Lifetime JP3665909B2 (en) | 1994-11-21 | 1994-11-21 | Bridge reconstruction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3665909B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002194704A (en) * | 2000-12-26 | 2002-07-10 | Taisei Corp | Method for constructing girder |
JP6276152B2 (en) * | 2014-09-22 | 2018-02-07 | 鹿島建設株式会社 | Construction girder removal method and earth retaining plate for construction girder removal |
-
1994
- 1994-11-21 JP JP32974194A patent/JP3665909B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH08144205A (en) | 1996-06-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100891961B1 (en) | The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system | |
KR101127130B1 (en) | A precast type pre-stress box girder bridge excution method | |
JP4540632B2 (en) | Erection girder | |
KR102105230B1 (en) | Railroad bridge construction method for keeping preexistence railroad track and rail service | |
KR100415768B1 (en) | Process and frame for substituting steel girder of a railway bridge for concrete slab | |
JP3665909B2 (en) | Bridge reconstruction method | |
JP4162291B2 (en) | Railway work girder cradle and rail work girder cradle construction method | |
CN217324965U (en) | Face track laying base bridge that combines forever | |
JP4136959B2 (en) | "How to build underground structures and installation girder" | |
JP7368685B2 (en) | Bridge reconstruction method and bridge superstructure | |
CN210341507U (en) | Temporary overhead device for ballastless track line of high-speed rail suitable for high-speed traveling | |
JP7409952B2 (en) | Viaduct construction method and viaduct construction equipment | |
RU2352705C1 (en) | Method for installation of permanent way | |
JP5666329B2 (en) | Railway viaduct replacement method | |
JP3788774B2 (en) | Railroad track structure and railroad track construction method | |
JP2005232922A (en) | Track concrete slab board of tramcar and its construction method | |
KR101258841B1 (en) | Precast concrete slab construction method of bridge | |
KR101653559B1 (en) | Method of repairing railway | |
KR20060028234A (en) | Method for carrying out replacement of an upper structure of a railway bridge | |
CN110029531B (en) | Temporary high-speed rail ballastless track line overhead device and method suitable for high-speed traveling | |
KR100729844B1 (en) | Repair work of railroad bridge and that structure | |
CN220847057U (en) | Hoisting construction railway simply supported beam | |
CN114875771B (en) | Design and construction method of track laying base bridge | |
JP7414658B2 (en) | How to repair existing rails | |
RU132090U1 (en) | METAL PLATE OF THE BALLOWLESS BRIDGE CANVAS OF THE ROADWAY OF RAILWAY BRIDGES (OPTIONS) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050301 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050323 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110415 Year of fee payment: 6 |
|
RD03 | Notification of appointment of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: R3D03 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |