JP7242821B1 - Concrete balustrade construction method - Google Patents

Concrete balustrade construction method Download PDF

Info

Publication number
JP7242821B1
JP7242821B1 JP2021202573A JP2021202573A JP7242821B1 JP 7242821 B1 JP7242821 B1 JP 7242821B1 JP 2021202573 A JP2021202573 A JP 2021202573A JP 2021202573 A JP2021202573 A JP 2021202573A JP 7242821 B1 JP7242821 B1 JP 7242821B1
Authority
JP
Japan
Prior art keywords
concrete
floor slab
wall balustrade
overhanging
balustrade
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021202573A
Other languages
Japanese (ja)
Other versions
JP2023087983A (en
Inventor
圭一 青木
剛規 小保田
優華 大野
茂樹 山下
正 豊田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central Nippon Expressway Co Ltd
Original Assignee
Central Nippon Expressway Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central Nippon Expressway Co Ltd filed Critical Central Nippon Expressway Co Ltd
Priority to JP2021202573A priority Critical patent/JP7242821B1/en
Application granted granted Critical
Publication of JP7242821B1 publication Critical patent/JP7242821B1/en
Publication of JP2023087983A publication Critical patent/JP2023087983A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

【課題】橋梁上部工のコンクリート製壁高欄の構築に要する作業時間を短縮する。【解決手段】このコンクリート製壁高欄の構築方法は、コンクリート床版用の底枠を配置し、コンクリート製のプレキャスト壁高欄部材を前記コンクリート床版の先端に仮置きするとともに、前記型枠内にコンクリート床版用の鉄筋を組み立て、前記コンクリート床版のコンクリートを打設する、ことによって行われる。【選択図】図7An object of the present invention is to shorten the work time required for constructing a concrete wall balustrade of a bridge superstructure. In this concrete wall balustrade construction method, a bottom frame for a concrete floor slab is placed, a concrete precast wall balustrade member is temporarily placed at the tip of the concrete floor slab, and placed inside the formwork. This is done by assembling reinforcing bars for concrete floor slabs and pouring concrete for the concrete floor slabs. [Selection drawing] Fig. 7

Description

本発明は、橋梁上部工のコンクリート製防護壁(壁高欄)の構築方法に関する。 TECHNICAL FIELD The present invention relates to a method for constructing a concrete protection wall (wall balustrade) for a bridge superstructure.

張り出し床版を有する既設橋梁の橋梁防護柵の更新工事として、既設の鋼製橋梁防護柵をコンクリート製の橋梁防護壁(コンクリート製壁高欄)に更新する工事がある。鋼製橋梁防護柵とコンクリート製壁高欄では自重の差が大きいため、新しいコンクリート製壁高欄を構築すると、既設の張り出し床版付け根部の耐力が不足する場合がある。この耐力不足に対し、外的な補強が困難な場合には、張り出し床版も同時に更新することが行われる。 There is a construction to replace the existing steel bridge protection fence with a concrete bridge protection wall (concrete wall balustrade) as a renewal work of the bridge protection fence of the existing bridge with the overhang floor slab. Since there is a large difference in weight between the steel bridge guard fence and the concrete wall balustrade, when a new concrete wall balustrade is constructed, the strength of the base of the existing overhanging floor slab may be insufficient. If it is difficult to externally reinforce this lack of strength, the overhanging floor slabs are also renewed at the same time.

このような張り出し床版の更新を伴うコンクリート製壁高欄の構築は、張り出し床版を付け根で切断し、必要な耐力を満足する新たな張り出し床版を現場打ちコンクリートにて再構築し、張り出し床版先端部に新たなコンクリート製壁高欄を構築する、という手順で行われる。ここで、張り出し床版と壁高欄のコンクリート配合は一般的に異なるため、張り出し床版と壁高欄はそれぞれ個別に構築することが一般的である。この場合、例えば、張り出し床版先端部の上面に壁高欄と接続する鉄筋を突出させておき、張り出し床版の構築完了後、突出した鉄筋に接続して壁高欄の鉄筋を組立て、型枠の設置、 コンクリート打設を行って壁高欄を構築する。しかし、この手順では、現場打ちコンクリートによる構造物の構築が個別に2回必要であるため、作業に要する時間が長くなる。このため、工程短縮および交通規制の早期解放が望まれる現場においては、張り出し床版および壁高欄の構築方法の改善が望まれる。 Construction of a concrete wall balustrade that accompanies such renewal of the overhanging floor slabs involves cutting the overhanging slabs at their roots, reconstructing new overhanging slabs that satisfy the required bearing strength with cast-in-place concrete, and constructing the overhanging floors. This is done by constructing a new concrete balustrade on the tip of the plate. Here, the overhanging floor slab and the wall balustrade generally have different concrete mixes, so the overhanging floor slab and the wall balustrade are generally constructed separately. In this case, for example, rebars that connect to the balustrade are protruded from the top surface of the overhanging floor slab, and after the construction of the overhanging slab is completed, the reinforcing bars of the wall balustrade are assembled by connecting to the protruding rebars, and the formwork is installed. Install and pour concrete to construct the wall balustrade. However, this procedure requires two separate constructions of the cast-in-place concrete structure, which increases the time required for the operation. For this reason, it is desirable to improve construction methods for overhanging floor slabs and wall balustrades at sites where a shortened construction process and early release of traffic restrictions are desired.

近年、工期短縮及び交通規制時間の短縮を目的として、既設の床板を撤去した後、工場で製作された、橋軸方向に2m程度の幅を持つプレキャスト床版を敷設する方法が採用されている。壁高欄の構築はプレキャスト床版敷設後に行われることが一般的であるが、壁高欄の構築に際しても、工期短縮を目的として工場で製作されたプレキャスト壁高欄をプレキャスト床版上に構築する方法が採用されている。この方法によると、コンクリートの打設及び養生に時間を費やす必要が無くなるため、全体工期の短縮又は交通規制時間の短縮が可能である。 In recent years, with the aim of shortening the construction period and traffic control time, after removing the existing floorboards, a method of laying precast floorboards with a width of about 2m in the direction of the bridge axis manufactured at the factory has been adopted. . Wall balustrades are generally constructed after laying precast floor slabs, but even when constructing wall balustrades, there is a method of constructing precast wall balustrades made at the factory on precast slabs for the purpose of shortening the construction period. Adopted. According to this method, there is no need to spend time on concrete placement and curing, so it is possible to shorten the overall construction period or shorten the traffic control time.

しかし、プレキャスト床版とプレキャスト壁高欄との接続に関しては、例えばプレキャスト床版にアンカー鉄筋を突出状態で設置するとともに、プレキャスト壁高欄にアンカー鉄筋を挿入するアンカー孔を設置し、このアンカー孔にプレキャスト床版から突出させたアンカー鉄筋を挿入し、互いの隙間に例えばモルタルを充填することによって一体化する方法が知られる(例えば引用文献1)。 However, regarding the connection between the precast floor slab and the precast wall balustrade, for example, anchor rebars are installed in the precast floor slab in a protruding state, and anchor holes for inserting the anchor rebars are installed in the precast wall balustrade. There is known a method of inserting anchor reinforcing bars that protrude from the floor slab and filling the mutual gaps with, for example, mortar for integration (for example, Cited Document 1).

また、アンカー鉄筋の代わりに、アンカーボルトをプレキャスト床版に埋め込み、プレキャスト壁高欄に設けられたアンカー孔にアンカーボルトを挿入し、ナットで固定する方法もある(例えば引用文献2)。 There is also a method of embedding anchor bolts in precast floor slabs instead of anchor reinforcing bars, inserting the anchor bolts into anchor holes provided in precast wall balustrades, and fixing them with nuts (for example, Cited Document 2).

さらに、壁高欄のみを更新する工事に関して、既設の壁高欄を撤去した後、既設の張り出し床版上の鉄筋を研り出し、予め工場等で製作した下端部に床版と接続する鉄筋を突出させたプレキャスト壁高欄を張り出し床版上面とプレキャスト壁高欄下端部との間に隙間を開けて設置し、その隙間に無収縮モルタルを充填して壁高欄を構築する方法が知られている(例えば引用文献3)。 In addition, regarding the construction to renew only the wall balustrade, after removing the existing wall balustrade, the reinforcing bars on the existing overhanging floor slabs were ground, and the reinforcing bars that connect to the floor slabs were protruding from the lower ends that had been manufactured in advance at the factory, etc. There is a known method of constructing a wall balustrade by installing a precast balustrade with a gap between the upper surface of the overhanging floor slab and the lower end of the precast balustrade, and filling the gap with non-shrinking mortar (for example, Reference 3).

さらに、コンクリート製のプレキャスト橋桁や現場打コンクリートで構築された床版橋における張り出し床版上の橋梁防護柵の更新工事がある。この更新工事において鋼製防護柵からコンクリート製の壁高欄へと更新する場合は、鋼製防護柵とコンクリート製壁高欄の自重の差が大きく、張り出し床版の付け根の耐力不足が生じる場合があるため、張り出し床版上の橋梁防護柵とともに張り出し床版を更新する場合がある。一般的に張り出し床版はコンクリート構造であるため、張り出し床版をプレキャスト橋桁や床版橋本体との境界で切断撤去し、 現場打コンクリートにより新しい張り出し床版を構築する。その際、既設の壁高欄は既設張り出し床版と一体となって撤去されるため、新しい壁高欄を構築する必要がある。新しい壁高欄は、新しい張り出し床版から突出した鉄筋に新しい壁高欄の鉄筋を接続して鉄筋を組み立て、現場打コンクリートにより構築される。 In addition, there is renewal work of bridge protection fences on overhanging slabs of concrete precast bridge girders and floor slab bridges constructed with cast-in-place concrete. In this renewal work, when replacing steel protective fences with concrete wall balustrades, the weight difference between steel protective fences and concrete wall balustrades is large, and there may be cases where the bearing capacity at the base of the overhanging floor slabs is insufficient. Therefore, the overhanging slab may be renewed along with the bridge protection fence on the overhanging slab. Since the overhanging slab is generally a concrete structure, the overhanging slab is cut and removed at the boundary between the precast bridge girder and the slab bridge body, and a new overhanging slab is constructed using cast-in-place concrete. At that time, since the existing wall balustrade will be removed together with the existing overhanging floor slab, it will be necessary to construct a new wall balustrade. The new wall balustrade is constructed by connecting the reinforcing bars of the new wall balustrade to the reinforcing bars protruding from the new overhanging floor slabs, assembling the reinforcing bars, and constructing the cast-in-place concrete.

特開2017-115485号公報JP 2017-115485 A 特開平09-29641号公報JP-A-09-29641 特開2013-36205号公報JP 2013-36205 A

鋼橋に敷設されたコンクリート床版の更新は、工期の短縮のため、工場で製作した新しいプレキャスト床版を敷設後、工場で製作したプレキャスト壁高欄を敷設しプレキャスト床版と接続することで行われることが多い。
しかしながら、プレキャスト部材どうしの接続となるため、プレキャスト床版にはアンカー鉄筋やアンカーボルトの設置、プレキャスト壁高欄にはアンカーの設置が必要であり、特にプレキャスト壁高欄の製作は煩雑になりやすい。
In order to shorten the construction period, the concrete floor slabs laid on the steel bridge were renewed by laying new precast floor slabs manufactured at the factory and then installing precast wall balustrades manufactured at the factory and connecting them to the precast floor slabs. often
However, since precast members are connected to each other, it is necessary to install anchor reinforcing bars and anchor bolts on precast floor slabs and anchors on precast wall balustrades.

壁高欄のみの更新工事においては、既設の壁高欄を切断撤去し、既設の張り出し床版はそのまま再利用することから、新たなプレキャスト壁高欄を構築する場合は、プレキャスト壁高欄下端部に床版接続鉄筋を突出させ、張り出し床版上面とプレキャスト壁高欄下端に隙間を開けてプレキャスト壁高欄を設置し、その隙間に無収縮モルタルを充填する、という方法を採っている。 In the renewal work of only the wall balustrade, the existing wall balustrade will be cut and removed, and the existing overhanging floor slab will be reused as it is. A method is adopted in which connecting reinforcing bars are protruded, a gap is opened between the upper surface of the overhanging floor slab and the lower end of the precast wall balustrade, a precast wall balustrade is installed, and the gap is filled with non-shrinkage mortar.

しかし、張り出し床版とプレキャスト壁高欄との鉄筋を接続するため、特殊な鉄筋継手の使用や張り出し床版上面に後施工アンカーを施工するなど張り出し床版とプレキャスト壁高欄の鉄筋の接続は複雑である。また、張り出し床版とプレキャスト壁高欄との隙間に無収縮モルタルを充填するため、プレキャスト壁高欄の車道側および外側に型枠を設置する必要がある。
さらに、プレキャスト・コンクリート橋桁やコンクリート床版橋の張り出し床版の更新を伴う壁高欄の更新では、新しく構築される張り出し床版や壁高欄は現場打コンクリートで製作することが一般的であるため、コンクリート打設や養生に費やす時間が必要となり、交通規制の制限を受ける更新工事においては作業時間の制約が厳しい。
However, in order to connect the reinforcing bars between the overhanging floor slab and the precast wall balustrade, the connection between the overhanging floor slab and the precast wall balustrade is complicated, such as the use of special reinforcing bar joints and the construction of post-installed anchors on the upper surface of the overhanging floor slab. be. In addition, in order to fill the gap between the overhanging floor slab and the precast wall balustrade with non-shrink mortar, it is necessary to install forms on the road side and outside of the precast wall balustrade.
Furthermore, when updating precast concrete bridge girders and overhanging deck slabs of concrete slab bridges, it is common to manufacture newly constructed overhanging slabs and overhanging balustrades with cast-in-place concrete. Concrete placement and curing require time, and work hours are severely restricted in renewal work subject to traffic restrictions.

本発明は、上記の事情に鑑み、橋梁上部工のコンクリート製壁高欄の構築に要する作業時間を短縮することのできるコンクリート製壁高欄の構築方法を提供することを目的とするものである。 In view of the above circumstances, it is an object of the present invention to provide a concrete wall balustrade construction method capable of shortening the work time required to construct a concrete balustrade of a bridge superstructure.

上記目的を達成するために、本発明に係るコンクリート製壁高欄の構築方法は、コンクリート床版用の底枠を配置し、コンクリート製のプレキャスト壁高欄部材を前記コンクリート床版用の底枠上の先端に仮置きするとともに、前記型枠内にコンクリート床版用の鉄筋を組み立て、前記コンクリート床版のコンクリートを打設する、ことによって行われる。 In order to achieve the above object, a method for constructing a concrete wall balustrade according to the present invention comprises placing a bottom frame for a concrete floor slab, and placing precast concrete wall balustrade members on the concrete floor slab bottom frame. This is done by temporarily placing the concrete floor slab at the tip, assembling reinforcing bars for the concrete floor slab in the formwork, and pouring the concrete for the concrete floor slab.

前記プレキャスト壁高欄部材には、コンクリート床版への定着部材が突出され、前記型枠内に打設されたコンクリート床版のコンクリートに定着するようにしてもよい。 The precast wall balustrade member may have a fixing member to the concrete floor slab protrude so that the precast wall balustrade member is fixed to the concrete of the concrete floor slab cast in the mold.

本発明によれば、現場打コンクリートで構築する壁高欄をプレキャスト壁高欄に変更したことで、壁高欄更新工事の作業時間を低減することができる。
また、プレキャスト壁高欄の突出した鉄筋が新設張り出し床版部のコンクリート内に埋め込まれて定着されるので、新設張り出し床版部とプレキャスト壁高欄が一体の構造物として得られる。このため、張り出し床版とプレキャスト壁高欄との隙間を無収縮モルタルなどで埋める作業が不要になる。
ADVANTAGE OF THE INVENTION According to this invention, the work time of wall balustrade renewal construction can be reduced by changing the wall balustrade constructed with the cast-in-place concrete to the precast wall balustrade.
In addition, since the protruding reinforcing bars of the precast wall balustrade are embedded and fixed in the concrete of the newly overhanging floor slab, the newly overhanging floor slab and the precast wall balustrade are obtained as an integrated structure. This eliminates the need to fill the gap between the overhanging floor slab and the precast wall balustrade with non-shrinkage mortar or the like.

本実施形態のコンクリート製壁高欄の構築方法の手順を示す流れ図である。It is a flowchart which shows the procedure of the construction method of the concrete balustrade of this embodiment. 同構築方法における既設コンクリート床版1のコンクリート張り出し床版部2を示す断面図である。FIG. 3 is a cross-sectional view showing a concrete overhanging floor slab portion 2 of an existing concrete floor slab 1 in the same construction method. 同構築方法における図2の既設コンクリート床版1から鋼製橋梁防護柵3を含む既設張り出し床版部2を切断・撤去した状態を示す断面図である。3 is a cross-sectional view showing a state in which an existing overhanging floor slab 2 including a steel bridge protection fence 3 is cut and removed from the existing concrete floor slab 1 of FIG. 2 in the same construction method. FIG. 同構築方法における支保工の構築および底枠の組立てを示す断面図である。FIG. 4 is a cross-sectional view showing construction of the shoring and assembly of the bottom frame in the same construction method; 同構築方法における下側鉄筋7の組立てを示す断面図である。It is sectional drawing which shows the assembly of the lower side reinforcing-bar 7 in the same construction method. 同構築方法におけるプレキャスト壁高欄3Aの仮置きを示す断面図である。It is sectional drawing which shows temporary placement of 3 A of precast wall balustrades in the same construction method. 同構築方法における新設張り出し床版部の上側鉄筋12の組み立てを示す断面図である。It is sectional drawing which shows the assembly of the upper side reinforcing-bar 12 of the new overhang floor slab part in the same construction method. 同構築方法におけるコンクリート打設を示す断面図である。It is sectional drawing which shows concrete placing in the same construction method. プレキャスト壁高欄の構築完了の状態を示す断面図である。It is sectional drawing which shows the state of the completion of construction of a precast wall balustrade. プレキャスト壁高欄3Aの車線方向端部に荷重伝達機能を備えた目地構造を示す斜視図である。It is a perspective view which shows the joint structure provided with the load transmission function in the lane direction edge part of 3 A of precast wall balustrades.

以下、本発明に係るコンクリート製壁高欄の構築方法の実施形態を図面に基づき詳細に説明する。
本実施形態は、既設コンクリート床版橋の張り出し床版先端部に敷設された鋼製橋梁防護柵をコンクリート製壁高欄に更新する方法に関する。鋼製橋梁防護柵からコンクリート製壁高欄への更新に伴い、既設コンクリート床版においてコンクリート製壁高欄を支持する張り出し床版先端部の必要な耐力を満足するために、その張り出し床版先端部の更新を同時に行う必要がある。
Hereinafter, an embodiment of a method for constructing a concrete balustrade according to the present invention will be described in detail based on the drawings.
This embodiment relates to a method of replacing a steel bridge protection fence laid at the tip of an overhanging deck slab of an existing concrete deck bridge with a concrete wall balustrade. Along with the renewal of the steel bridge protection fence to the concrete wall balustrade, in order to satisfy the required strength of the tip of the overhanging floor slab that supports the concrete wall balustrade in the existing concrete slab, the tip of the overhanging slab tip The updates should be done at the same time.

図1は本実施形態の更新作業の手順を示す流れ図である。
本更新作業は、以下の作業手順S1-S8からなる。
S1.既設鋼製橋梁防護柵及び既設張り出し床版先端部の切断・撤去。
S2.支保工の構築。
S3.新設張り出し床版の底枠の組み立て。
S4.新設張り出し床版部の下側鉄筋の組み立て。
S5.プレキャスト壁高欄の仮置き及び高さ・鉛直調整。
S6.新設張り出し床版部の上側鉄筋の組み立て。
S7.床版先端等必要箇所に型枠を設置。
S8.新設張り出し床版部のコンクリート打設、型枠解体。
FIG. 1 is a flowchart showing the procedure of update work according to this embodiment.
This update work consists of the following work procedures S1-S8.
S1. Cut and remove the existing steel bridge protection fence and the tip of the existing overhang floor slab.
S2. Construction of shoring.
S3. Assembling the bottom frame of the newly installed overhanging floor slab.
S4. Assembling the lower reinforcing bars of the new overhang floor slab.
S5. Temporary placement and height/vertical adjustment of precast wall balustrades.
S6. Assembly of the upper reinforcing bars of the newly installed overhanging floor slab.
S7. Formwork is installed where necessary, such as the tip of floor slabs.
S8. Concrete placement and formwork dismantling for newly installed overhanging floor slabs.

以下、それぞれの作業の詳細を説明する。
(S1.既設鋼製橋梁防護柵及び既設張り出し床版先端部の切断・撤去)
図2は既設橋梁1のコンクリート張り出し床版部2(以下「既設張り出し床版部2」と呼ぶ。)を示す断面図である。既設張り出し床版部2の先端部には、例えば鋼製橋梁防護柵等の撤去対象防護柵3が設けられている。
Details of each work are described below.
(S1. Cutting and removing the existing steel bridge protection fence and the tip of the existing overhang floor slab)
FIG. 2 is a sectional view showing the concrete overhanging floor slab 2 of the existing bridge 1 (hereinafter referred to as the "existing overhanging floor slab 2"). A protective fence 3 to be removed, such as a steel bridge protective fence, is provided at the tip of the existing overhanging floor slab 2 .

まず、図3に示すように、既設橋梁1から、鋼製橋梁防護柵3を含む既設張り出し床版部2を切断・撤去する。このとき、残った既設橋梁1の切断面より、新設張り出し床版(図示せず)の鉄筋との継手用の張り出し床版上縁側の既存鉄筋4を突出させておく。本実施形態では、新設張り出し床版付け根の耐力確保のため、新設張り出し床版付け根の断面寸法を大きくする必要があり、張り出し床版下縁側の鉄筋は、後施工アンカー4′を既設橋梁側に設置し、後施工アンカー4′に鉄筋4″を接続して構築する。 First, as shown in FIG. 3, from the existing bridge 1, the existing overhanging floor slab 2 including the steel bridge protection fence 3 is cut and removed. At this time, from the remaining cut surface of the existing bridge 1, the existing reinforcing bars 4 on the upper edge side of the overhanging floor slab for joint with the reinforcing bars of the newly overhanging floor slab (not shown) are made to protrude. In this embodiment, in order to ensure the strength of the base of the new overhanging floor slabs, it is necessary to increase the cross-sectional dimension of the base of the newly overhanging floor slabs. It is constructed by connecting the rebar 4″ to the post-installed anchor 4′.

(S2.支保工の構築とS3.新設張り出し床版の底枠の組み立て)
次に、図4に示すように、新設張り出し床版を構築するための支保工5の構築と、新設張り出し床版部の底枠6の組み立てを行う。支保工5の強度は、新設張り出し床版部のコンクリート重量とプレキャスト壁高欄部の重量を考慮したものとする。
(S2. Construction of shoring and S3. Assembly of bottom frame of new overhanging floor slab)
Next, as shown in FIG. 4, construction of the shoring 5 for constructing the new overhanging floor slab and assembly of the bottom frame 6 of the newly overhanging floor slab are carried out. The strength of the shoring 5 shall take into account the weight of the concrete of the newly installed overhanging floor slab and the weight of the precast wall balustrade.

(S4.新設張り出し床版部の下側鉄筋の組み立て)
次いで、図5に示すように、新設張り出し床版部の下側鉄筋7を組立てる。この際、下側鉄筋7と、既設橋梁1の切断面に後施工アンカーに接続した鉄筋4″とを機械式継手7′等で接続する。本実施形態では、既設コンクリート床版1に設置した後施工アンカーに新設張り出し床版下縁側の鉄筋を機械式継手により接続しているが、鉄筋の接続は重ね継手でもよく、鉄筋に作用する力を伝達できる構造であれば、鉄筋継手構造は問わない。
(S4. Assembling the lower reinforcing bars of the newly installed overhang floor slab)
Next, as shown in FIG. 5, the lower reinforcing bars 7 of the new overhanging floor slab are assembled. At this time, the lower reinforcing bar 7 and the reinforcing bar 4″ connected to the post-installed anchor on the cut surface of the existing bridge 1 are connected with a mechanical joint 7′ or the like. The rebar on the lower edge of the newly installed overhanging floor slab is connected to the post-installed anchor by a mechanical joint, but the rebar connection may be a lap joint. do not have.

(S5.プレキャスト壁高欄の仮置き及び高さ・鉛直調整)
新設張り出し床版部の下側鉄筋7の組立後、図6に示すように、既設張り出し床版2の撤去前に張り出し床版付け根より車道中心側に設定された、道路上の有効幅員を確認する基準線を利用して有効幅員調整材8を設置する。有効幅員調整材8の設置後、プレキャスト壁高欄部材3Aを油圧クレーンで吊り上げ、有効幅員調整材8に合わせてプレキャスト壁高欄部材3Aを底枠6上に仮置きする。これにより容易に道路線形の基準値以内にプレキャスト壁高欄部材3Aを設置することができる。
(S5. Temporary placement and height/vertical adjustment of precast wall balustrades)
After assembling the lower reinforcing bars 7 of the new overhanging floor slab, as shown in Fig. 6, before removing the existing overhanging floor slab 2, the effective width on the road, which was set toward the center of the roadway from the base of the overhanging floor slab, was confirmed. The effective width adjusting material 8 is installed using the reference line to be used. After installing the effective width adjusting member 8, the precast wall balustrade member 3A is lifted by a hydraulic crane, and the precast wall balustrade member 3A is temporarily placed on the bottom frame 6 in accordance with the effective width adjusting member 8. - 特許庁Thereby, the precast wall balustrade member 3A can be easily installed within the reference value of the road alignment.

なお、図6に示すように、プレキャスト壁高欄部材3Aの底部には高さ調整材設置用の全ねじボルト9が突出させてあり、プレキャスト壁高欄部材3Aの仮置きの際、高さ調整材10を全ねじボルト9に設置する。プレキャスト壁高欄部材3Aの仮置き後、プレキャスト壁高欄部材3Aの高さを高さ測定器等で確認し、必要により高さ調整10で高さを調整すると同時にプレキャスト壁高欄部材3Aの鉛直性を確保する目的で、プレキャス ト壁高欄部材3Aの車道側側面と、既設コンクリート床版1の切断部より道路中心側の路面との間を支持材11で互いに支持し合う。支持材11は、プレキャスト壁高欄部材3A の鉛直性を調整できるように、長さを調節できるものがよく、プレキャスト壁高欄部材3Aの1体につき2か所以上設置することが望ましい。なお、支持材11は、プレキャスト 壁高欄部材3Aの鉛直性の確保のみならず、転倒防止用として機能し得るものである。 In addition, as shown in FIG. 6, the bottom of the precast wall balustrade member 3A is protruded with a fully threaded bolt 9 for installing the height adjustment member. 10 is installed on the fully threaded bolt 9. After temporarily placing the precast wall balustrade member 3A, the height of the precast wall balustrade member 3A is checked with a height measuring instrument or the like, and the height is adjusted with the height adjustment member 10 if necessary, and at the same time, the verticality of the precast wall balustrade member 3A. For the purpose of securing, the side of the precast wall balustrade member 3A on the side of the roadway and the road surface on the center side of the road from the cut portion of the existing concrete floor slab 1 are mutually supported by supporting members 11. The support members 11 are preferably adjustable in length so as to adjust the verticality of the precast wall balustrade member 3A, and are preferably installed at two or more locations per precast wall balustrade member 3A. In addition, the supporting member 11 can function not only to ensure the verticality of the precast wall balustrade member 3A but also to prevent overturning.

(S6.新設張り出し床版部の上側鉄筋の組み立て)
プレキャスト壁高欄部材3Aを固定した後、図7に示すように新設張り出し床版部の上側鉄筋12の組み立てを行う。下側鉄筋7の組立てと同様に、既設コンクリート床版1の切断面に突出させた既存鉄筋と、新設張り出し床版部の上側鉄筋12とを機械式継手7′等で接続する、あるいは、既設コンクリート床版1の切断面に突出させた既存鉄筋4の突出長を重ね継手長以上に突出させ、新設張り出し床版側の鉄筋7と重ね継手で接続してもよく、鉄筋継手構造は問わない。
(S6. Assembling the upper reinforcing bars of the new overhang floor slab)
After fixing the precast wall balustrade members 3A, the upper reinforcing bars 12 of the newly overhanging floor slab are assembled as shown in FIG. Similar to the assembly of the lower reinforcing bars 7, the existing reinforcing bars protruding from the cut surface of the existing concrete floor slab 1 and the upper reinforcing bars 12 of the newly overhanging floor slab are connected by mechanical joints 7' or the like, or The protruding length of the existing reinforcing bars 4 protruding from the cut surface of the concrete floor slab 1 may be made to protrude beyond the length of the lap joint, and may be connected to the reinforcing bars 7 on the side of the newly overhanging floor slab by lap joints, regardless of the reinforcing bar joint structure. .

なお、プレキャスト壁高欄部材3Aの車線方向両端部はフラットな面であり構造的に接合されていないが、図10に示すように荷重伝達機能を備えた目地構造を採用してもよい。図10に示す荷重伝達機能は、プレキャスト壁高欄部材3Aの車線方向で互いに突き合わされる何れか一方の接合端面に他方側に突出させた接合凸部16を一体に備え、何れか他方のプレキャスト壁高欄3Aの接合端面に、接合凸部16が嵌め込まれる凹溝状の接合凹部17を一体に形成してもよい。
プレキャスト壁高欄部材3Aの設置固定は1橋梁分あるいは径間ごとに連続して行うことで、橋軸方向における並びの線形の良否を確認しやすくなる。
Although both ends of the precast wall balustrade member 3A in the lane direction are flat surfaces and are not structurally joined, a joint structure having a load transmission function may be employed as shown in FIG. The load transmission function shown in FIG. 10 is provided integrally with a joint convex portion 16 projecting to the other side on one of the joint end surfaces of the precast wall balustrade member 3A that are butted against each other in the lane direction. A groove-shaped joint recess 17 into which the joint protrusion 16 is fitted may be integrally formed on the joint end face of the balustrade 3A.
By installing and fixing the precast wall balustrade members 3A continuously for one bridge or for each span, it becomes easy to check the quality of alignment in the direction of the bridge axis.

(S7.床版先端等必要箇所に型枠を設置とS8.新設張り出し床版部のコンクリート打設、型枠解体)
プレキャスト壁高欄部材3Aの設置固定後、図8に示すように、プレキャスト壁高欄外側の新設張り出し床版先端の側枠6′や車線方向の端部などの必要な部位に側枠(図示せず)を設置し、底枠6、既設コンクリート床版1の切断面および前記の側枠との間の空間にコンクリート15を流し込むことで新設張り出し床版部の構築を行う。所定の養生期間経過後、底枠、側枠などの型枠を解体する。これにより、図9に示すように、張り出し床版先端部の更新(新設張り出し床版先端部2Aの構築)と同時にコンクリート製壁高欄の構築が完了する。
(S7. Install formwork at required locations such as the tip of the floor slab, and S8. Concrete placement for the newly overhanging floor slab, dismantling the formwork.)
After installing and fixing the precast wall balustrade members 3A, as shown in Fig. 8, side frames (not shown) are attached to necessary parts such as the side frame 6' at the tip of the new overhanging floor slab on the outside of the precast wall balustrade and the end in the lane direction. ) is installed, and concrete 15 is poured into the space between the bottom frame 6, the cut surface of the existing concrete floor slab 1, and the side frame, thereby constructing a new overhanging floor slab. After the specified curing period has passed, the forms such as the bottom frame and side frames are dismantled. As a result, as shown in FIG. 9, the construction of the concrete wall balustrade is completed at the same time as the renewal of the tip of the overhanging floor slab (construction of the top end of the overhanging floor slab 2A).

図7に示したように、プレキャスト壁高欄部材3Aの底部には鉄筋13が突出している。プレキャスト壁高欄部材3Aの底部に突出した鉄筋13は新設張り出し床版部2Aのコンクリート内に埋め込まれて定着される。これにより、新設張り出し床版部2Aとプレキャスト壁高欄3Aは一体の構造物として構築される。 As shown in FIG. 7, a reinforcing bar 13 protrudes from the bottom of the precast wall balustrade member 3A. The reinforcing bars 13 projecting from the bottom of the precast wall balustrade member 3A are embedded and fixed in the concrete of the newly overhanging floor slab portion 2A. As a result, the new overhanging floor slab 2A and the precast wall balustrade 3A are constructed as an integral structure.

本実施形態では、橋軸方向の長さが例えば4.0m程度のプレキャスト壁高欄部材3Aが橋軸方向に並べられる。プレキャスト壁高欄部材3Aから突出させる鉄筋の径、長さ、ピッチ、本数などの配筋設計は、現場打ちコンクリートで壁高欄を構築する場合と同一とすることができるため、特別な設計検討を必要としないことも本構築方法のメリットといえる。 In this embodiment, precast wall balustrade members 3A having a length in the bridge axis direction of, for example, about 4.0 m are arranged in the bridge axis direction. Reinforcement design such as diameter, length, pitch and number of rebar protruding from the precast wall balustrade members 3A can be the same as when constructing the wall balustrade with cast-in-place concrete, so a special design study is required. It can be said that it is an advantage of this construction method that it does not.

以上、本実施形態のコンクリート製壁高欄の構築方法によれば、現場打コンクリートで構築する壁高欄をプレキャスト壁高欄に変更したことで、壁高欄更新工事の作業時間を低減することができる。特に、コンクリート張り出し床版部の更新を伴う壁高欄更新工事の作業時間の大幅な短縮が可能である。
また、プレキャスト壁高欄3Aから突出した鉄筋13が新設張り出し床版部2Aのコンクリート内に埋め込まれて定着されるので、新設張り出し床版部2Aとプレキャスト壁高欄3Aが一体の構造物として得られる。このため、壁高欄のみを更新する工事において必要な、張り出し床版とプレキャスト壁高欄との隙間を無収縮モルタルなどで埋める作業が不要になる。
ここで、本実施形態においては、プレキャスト壁高欄から鉄筋を突出させているが、新設張り出し床版と構造的に一体化されるものであれば、アンカーボルトの先端に定着プレートを設置した構造としてもよい。新設張り出し床版と一体化可能であれば、プレキャスト壁高欄の定着構造にこだわるものではない。
そして、本実施形態のコンクリート製壁高欄の構築方法によれば、張り出し床版と壁高欄の構築が同時に完了するので、早期の交通規制解除が可能となる。
As described above, according to the concrete wall balustrade construction method of the present embodiment, by changing the wall balustrade constructed with cast-in-place concrete to the precast wall balustrade, the work time for the wall balustrade renewal work can be reduced. In particular, it is possible to significantly reduce the work time for wall balustrade renewal work that involves the renewal of concrete overhanging floor slabs.
Further, since the reinforcing bars 13 projecting from the precast wall balustrade 3A are embedded and fixed in the concrete of the newly overhanging floor slab part 2A, the newly overhanging floor slab part 2A and the precast wall balustrade 3A are obtained as an integral structure. For this reason, the work of filling the gap between the overhanging floor slab and the precast wall balustrade with non-shrinkable mortar or the like, which is required in the construction work for renewing only the wall balustrade, becomes unnecessary.
Here, in this embodiment, the reinforcing bars are protruding from the precast wall balustrade. good too. As long as it can be integrated with the newly installed overhanging floor slabs, there is no need to stick to the fixed structure of the precast wall balustrade.
According to the construction method of the concrete wall balustrade of the present embodiment, the construction of the overhanging floor slab and the wall balustrade is completed at the same time, so early traffic restrictions can be lifted.

上記実施形態では、新設張り出し床版の底枠9の組み立て後、新設張り出し床版部の下側鉄筋7を組立てからプレキャスト壁高欄部材3Aを底枠6上に仮置きしたが、新設張り出し床版部の下側鉄筋7および上側鉄筋12を組立てからプレキャスト壁高欄部材3Aを底枠6上に仮置きしてもよい。すなわち、プレキャスト壁高欄部材3Aの仮置きと新設張り出し床版部の下側鉄筋7および上側鉄筋12の組立ては並行が可能である。 In the above embodiment, after assembling the bottom frame 9 of the new overhanging floor slab, the lower reinforcing bars 7 of the newly overhanging floor slab are assembled, and then the precast wall balustrade members 3A are temporarily placed on the bottom frame 6. The precast wall balustrade member 3A may be temporarily placed on the bottom frame 6 after assembling the lower reinforcing bars 7 and the upper reinforcing bars 12. That is, the temporary placement of the precast wall balustrade member 3A and the assembly of the lower reinforcing bars 7 and the upper reinforcing bars 12 of the newly overhanging floor slab can be performed in parallel.

なお、ここまで既設橋梁のコンクリート床版の張り出し床版先端部の更新に伴うプレキャスト壁高欄を使用したコンクリート製壁高欄の構築方法を説明したが、本願発明は、本実施形態に限定されるものではなく、新設橋梁のコンクリート床版へのコンクリート製の壁高欄の構築に採用することができる。 Although the construction method of the concrete wall balustrade using the precast wall balustrade accompanying the renewal of the overhanging floor slab end portion of the concrete floor slab of the existing bridge has been described so far, the present invention is limited to this embodiment. Instead, it can be used to construct concrete balustrades on the concrete floor slabs of new bridges.

3A…プレキャスト壁高欄部材
6…底枠
7…新設張り出し床版部の下側鉄筋
12…新設張り出し床版部の上側鉄筋
15…コンクリート
3A... Precast wall balustrade member 6... Bottom frame 7... Lower reinforcing bar of new overhanging floor slab part 12... Upper reinforcing bar of newly overhanging floor slab part 15... Concrete

Claims (2)

コンクリート床版用の底枠を配置し、
壁高欄を構成するコンクリート製のプレキャスト壁高欄部材を前記底枠上に、高さ調整材を挟んで前記底枠と前記プレキャスト壁高欄部材の下面との間に隙間を形成した状態で仮置きするとともに、前記コンクリート床版用の前記底枠以外の型枠および鉄筋を組み立て、
前記隙間を含む、前記コンクリート床版用のコンクリート打設空間にコンクリートを打設する
コンクリート製壁高欄の構築方法。
Placing the bottom frame for the concrete floor slab,
A precast wall balustrade member made of concrete constituting the wall balustrade is temporarily placed on the bottom frame with a height adjusting member interposed therebetween to form a gap between the bottom frame and the lower surface of the precast wall balustrade member. At the same time, assembling forms and reinforcing bars other than the bottom frame for the concrete floor slab ,
A method for constructing a concrete wall balustrade, wherein concrete is placed in the concrete placement space for the concrete floor slab, including the gap .
前記プレキャスト壁高欄部材には、前記コンクリート床版への定着部材が突出され、前記コンクリート打設空間内に打設されたコンクリートに定着する、請求項1に記載のコンクリート製壁高欄の構築方法。 2. The method for constructing a concrete wall balustrade according to claim 1, wherein the precast wall balustrade member has a fixed member for fixing to the concrete floor slab protruding, and is fixed to the concrete placed in the concrete placing space. .
JP2021202573A 2021-12-14 2021-12-14 Concrete balustrade construction method Active JP7242821B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021202573A JP7242821B1 (en) 2021-12-14 2021-12-14 Concrete balustrade construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021202573A JP7242821B1 (en) 2021-12-14 2021-12-14 Concrete balustrade construction method

Publications (2)

Publication Number Publication Date
JP7242821B1 true JP7242821B1 (en) 2023-03-20
JP2023087983A JP2023087983A (en) 2023-06-26

Family

ID=85641203

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021202573A Active JP7242821B1 (en) 2021-12-14 2021-12-14 Concrete balustrade construction method

Country Status (1)

Country Link
JP (1) JP7242821B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013036205A (en) 2011-08-05 2013-02-21 Dc Co Ltd Construction method for joining wall balustrade of bridge
JP5171099B2 (en) 2007-04-27 2013-03-27 株式会社フジタ Overhang railing structure and overhang railing method
JP2017115485A (en) 2015-12-25 2017-06-29 株式会社ピーエス三菱 Road bridge guard fence and installation method thereof
JP6845501B2 (en) 2017-01-12 2021-03-17 インフラテック株式会社 Vertical member installation structure, vertical member installation method, and precast vertical member

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5171099B2 (en) 2007-04-27 2013-03-27 株式会社フジタ Overhang railing structure and overhang railing method
JP2013036205A (en) 2011-08-05 2013-02-21 Dc Co Ltd Construction method for joining wall balustrade of bridge
JP2017115485A (en) 2015-12-25 2017-06-29 株式会社ピーエス三菱 Road bridge guard fence and installation method thereof
JP6845501B2 (en) 2017-01-12 2021-03-17 インフラテック株式会社 Vertical member installation structure, vertical member installation method, and precast vertical member

Also Published As

Publication number Publication date
JP2023087983A (en) 2023-06-26

Similar Documents

Publication Publication Date Title
KR100958014B1 (en) Construction method of steel composite girder bridge
KR100703134B1 (en) Prefabricated prestressed concrete beam bridge and its construction method
JP5045214B2 (en) Column head construction method
KR101107826B1 (en) Slab-type box girder made by precast concrete and method constructing the bridge therewith
KR100788275B1 (en) Bridge deck with stay-in-place precast concrete panel
KR20100083260A (en) The upper and lower one body type multi span precast parts which has a construction improvement function
JP3844743B2 (en) Box girder bridge structure and its construction method
KR101263370B1 (en) Precast end-block with girder connection member and bridge construction method using ths same
US20180282993A1 (en) Precast concrete building elements and assemblies thereof, and related methods
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
KR100876388B1 (en) Stay in place deck precast panel
KR100631029B1 (en) Precasted concrete plate assembly and the construction method using thereof
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
JP7242821B1 (en) Concrete balustrade construction method
KR100963488B1 (en) Negative moment floor slab prestress introduction method for which precast concrete pc wire anchorage block and this were used
KR102477955B1 (en) Bridge pier and the construction method using maintained concrete mold
KR100631030B1 (en) Precasted concrete plate and bridge slab construction method using that
JP7134133B2 (en) Bridge railing construction method
JP4359731B2 (en) Method of replacing concrete floor slab bridge with steel slab and structure of replacing concrete floor slab bridge with steel slab
JP2980567B2 (en) How to replace the bearing device
KR101127427B1 (en) Rahmen bridge and construction method thereof
KR20120022285A (en) Composite steel continuous bridge using concrete cross beams and its construction method
KR20100074741A (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR200397849Y1 (en) Prefabricated prestressed concrete beam bridge
KR200395629Y1 (en) Bridge deck with stay-in-place precast concrete panel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220412

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20221220

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230215

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230307

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230308

R150 Certificate of patent or registration of utility model

Ref document number: 7242821

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350