JPH03271408A - Steel floor bed for repairing bridge and method of attaching thereof - Google Patents
Steel floor bed for repairing bridge and method of attaching thereofInfo
- Publication number
- JPH03271408A JPH03271408A JP2071054A JP7105490A JPH03271408A JP H03271408 A JPH03271408 A JP H03271408A JP 2071054 A JP2071054 A JP 2071054A JP 7105490 A JP7105490 A JP 7105490A JP H03271408 A JPH03271408 A JP H03271408A
- Authority
- JP
- Japan
- Prior art keywords
- plate
- road
- road surface
- rib
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims description 27
- 239000010959 steel Substances 0.000 title claims description 27
- 238000000034 method Methods 0.000 title description 3
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 34
- 238000003780 insertion Methods 0.000 description 5
- 230000037431 insertion Effects 0.000 description 5
- 238000003466 welding Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は、高速道路等の橋梁において、路面に使用して
いるコンクリート床版が老朽化したため、鋼床版に張替
えるために使用する橋梁補修用鋼床版と、その取付方法
に関するものである。[Detailed Description of the Invention] [Industrial Application Field] The present invention is applied to bridges such as expressways, which are used to replace concrete deck slabs used for road surfaces with steel deck slabs because they have become obsolete. This article relates to repair steel deck slabs and how to install them.
[従来の技術]
従来の橋梁には、第3図に示すように主桁lの上に、鉄
筋を入れてコンクリートを打設したコンクリート床版2
を設けて路面としているものかある。[Conventional technology] As shown in Figure 3, conventional bridges have a concrete deck slab 2 in which reinforcing bars are inserted and concrete is cast on top of the main girder l.
There are some that have been installed as road surfaces.
このようなコンリート床版2が長年の使用によって老朽
化したため、路面を張替える必要か生じた場合、老朽化
したコンクリート床版2を撤去した後、新しく鉄筋を組
んでコンクリートを打設し、新しいコンクリート床版2
に張替えると、鉄筋の組立、コンクリートの打設、コン
クリートの硬化に日数がかかり、橋梁の補修作業として
は通行に支障を与える期間が長くなって好ましくない。If it becomes necessary to replace the road surface because such a concrete slab 2 has become obsolete due to long-term use, the aged concrete slab 2 is removed, new reinforcing bars are erected and concrete is poured, and a new one is constructed. concrete floor slab 2
If the bridge is replaced, it will take several days to assemble the reinforcing bars, place the concrete, and harden the concrete, which is not desirable for bridge repair work because it will lengthen the period of disruption to traffic.
一方、橋梁の路面として使用されるものに、鋼板を溶接
等によって組立てた第5図に示す鋼床版3がある。鋼床
版3は路面板4の下面に横リブ5が溶接され、横リブ5
と直交する方向に縦リブ6と補助主桁7が溶接されてい
る。On the other hand, a steel deck slab 3 shown in FIG. 5, which is assembled from steel plates by welding or the like, is used as the deck surface of a bridge. The steel deck slab 3 has horizontal ribs 5 welded to the lower surface of the road plate 4.
The vertical rib 6 and the auxiliary main girder 7 are welded in a direction perpendicular to the vertical rib 6 and the auxiliary main girder 7.
このような鋼床版3の強度をコンクリート床版2と同じ
強度にするためには、鋼床版の高さ8をコンクリート床
版の高さ9 (第3図参照)に比して大きくする必要が
ある。In order to make the strength of the steel deck slab 3 the same as that of the concrete deck slab 2, the height 8 of the steel deck slab should be made larger than the height 9 of the concrete deck slab (see Figure 3). There is a need.
[発明が解決しようとする課題]
第4図に示すようにコンクリート床版2を撤去したあと
の主桁1上に従来の鋼床版3をそのまま取付けると、鋼
床版の高さ8がコンクリート床版の高さ9よりも大きい
ため、鋼床版3の路面板4の位置が、それまで使用して
いたコンクリート床版2の上面よりも高くなり、取付道
路との間に段差ができてしまう問題かあった。[Problems to be Solved by the Invention] As shown in Fig. 4, when the conventional steel deck slab 3 is installed as is on the main girder 1 after the concrete deck slab 2 has been removed, the height 8 of the steel deck slab is Since the height of the steel deck slab 3 is greater than the height 9, the position of the road surface plate 4 of the steel deck slab 3 is higher than the top surface of the concrete slab 2 that had been used up until then, creating a step between it and the access road. There was a problem with it.
本発明はこのような問題を解決し、コンクリート床版を
鋼床版に替えても、取付道路との間に段差が生じないよ
うにした橋梁補修用鋼床版および橋梁補修用鋼床版の取
付方法を提供することを目的とするものである。The present invention solves these problems and provides a steel deck slab for bridge repair and a steel deck slab for bridge repair that does not create a level difference between the concrete deck and the access road even if the concrete deck is replaced with a steel deck. The purpose is to provide a mounting method.
[課題を解決するための手段]
本発明は、路面板と横リブとを別体に構成し、前記路面
板の下面には主桁の上にのせた状態で前記路面板の上面
か撤去前のコンクリート床版の場合と同一高さになるよ
うにした高さの低い補助主桁を固着し、前記路面板の下
面にはさらに多数の縦リブを互に平行にして固着し、該
縦リブと前記路面板の下面とにわたって路面板側補強リ
ブを鉛直に固着し、前記横リブの上面には横リブ側補強
リブを前記路面板側補強リブの位置に対応させて鉛直に
固着したことを特徴とする橋梁補修用鋼床版、および横
リブ側補強リブを上面に鉛直に固着した横リブの両端を
主桁の側面に固着し、コンクリート床版を撤去した主桁
上には路面板の下面に固着した補助主桁をのせて固定し
、路面板下面の縦リブと路面板下面とにわたって鉛直に
固着した路面板側補強リブと前記横リブ側補強リブとの
面を当接させて結合することを特徴とする橋梁補修用鋼
床版の取付方法である。[Means for Solving the Problems] The present invention configures a road board and a horizontal rib separately, and the bottom surface of the road board is placed on the main girder while the top surface of the road board is placed on the main girder. A low-height auxiliary main girder is fixed to the same height as that of the concrete deck slab, and a large number of vertical ribs are fixed to the lower surface of the road slab in parallel with each other. and the lower surface of the road surface plate, and a lateral rib side reinforcing rib is vertically fixed to the upper surface of the lateral rib in a manner corresponding to the position of the road surface plate side reinforcing rib. Steel deck slabs for bridge repair are featured, and horizontal rib side reinforcing ribs are fixed vertically to the upper surface.Both ends of the horizontal ribs are fixed to the sides of the main girder.The concrete deck slab is removed and the road plate is placed on the main girder. The auxiliary main girder fixed on the lower surface is placed and fixed, and the surfaces of the reinforcing rib on the road plate side fixed vertically across the vertical rib on the lower surface of the road plate and the lower surface of the road plate and the reinforcing rib on the horizontal rib side are brought into contact and connected. This is a method for installing steel deck slabs for bridge repair, which is characterized by:
[作 用コ
別体とした路面板と横リブは、後で連結することにより
一体の鋼床版を形成する。[Function] The separate road surface plate and horizontal ribs will be connected later to form an integrated steel deck.
主桁の側面に両端を固着した横リブ上面の横リブ側補強
リブに、補助主桁を主桁上に固定するようにした路面板
の路面板側補強リブを当接させて結合することにより、
鋼床版の路面板は、撤去したコンクリート床版の上面と
同じ高さになる。By connecting the auxiliary main girder to the reinforcing rib on the side of the road plate of the road plate, which fixes the auxiliary main girder on the main girder, to the reinforcing rib on the side of the transverse rib on the upper surface of the transverse rib, which has both ends fixed to the side surface of the main girder. ,
The steel deck deck will be at the same height as the top of the removed concrete deck.
[実 施 例] 以下、本発明の実施例を図面を参照して説明する。[Example] Embodiments of the present invention will be described below with reference to the drawings.
第1図において10は路面板、l!は横リブであって、
従来は第5図において説明したように一体にしていたも
のを、本発明では別体に構成したものである。In Fig. 1, 10 is a road board, l! is a horizontal rib,
Conventionally, the parts were integrated as explained in FIG. 5, but in the present invention, they are constructed separately.
路面板lOの下面には補助主桁12と互に平行な多数の
縦リブ13とが固着されている。補助主桁12の路面板
10の上面までの高さ14は、第5図に示した従来の鋼
床版の高さ8よりも低い高さになっていて、補助主桁1
2を第2図に示すように主桁l上にのせた状態で路面板
IOの上面の高さが、コンクリート床版の高さ9 (第
3図参照)と同一高さになる寸法にされている。路面板
10の下面に平行に多数固着されている縦リブ13の各
1対の組と路面板10の下面とにわたって路面板側補強
リブ15が鉛直に固着してあって、路面板側補強リブ1
5には多数のボルト挿通孔I6が穿設されている。An auxiliary main girder 12 and a large number of mutually parallel vertical ribs 13 are fixed to the lower surface of the road surface board IO. The height 14 of the auxiliary main girder 12 to the top surface of the road plate 10 is lower than the height 8 of the conventional steel deck shown in FIG.
2 is placed on the main girder L as shown in Figure 2, the height of the top surface of the road slab IO is the same as the height 9 of the concrete slab (see Figure 3). ing. A road plate side reinforcing rib 15 is fixed vertically across each pair of vertical ribs 13, which are fixed in parallel to the lower surface of the road plate 10, and the lower surface of the road plate 10. 1
5 has a large number of bolt insertion holes I6 bored therein.
横リブ11の上面には、前述した路面板側補強リブ15
の位置に対応するように横リブ側補強リブ17が鉛直に
固着してあって、横リブ側補強リブ17には、路面板側
補強リブ15のボルト挿通孔l6の配列と一致するよう
に、ボルト挿通孔18が穿設されている。On the upper surface of the horizontal rib 11, the aforementioned road plate side reinforcing rib 15 is provided.
The horizontal rib side reinforcing ribs 17 are fixed vertically so as to correspond to the positions of the horizontal rib side reinforcing ribs 17, and the horizontal rib side reinforcing ribs 17 are arranged so as to match the arrangement of the bolt insertion holes l6 of the road plate side reinforcing ribs 15. A bolt insertion hole 18 is bored.
コンクリート床版2を撤去した主桁1の側面には、第1
図、第2図に示すように副板19を固着し、この副板1
9を介して横リブ11の両端を主桁1の側面に固着する
。横リブ11の両端の副板19に対する固着は、ボルト
締めまたは溶接によって行なう。On the side of the main girder 1 from which the concrete slab 2 has been removed, the first
As shown in FIG. 2, the sub-plate 19 is fixed, and this
Both ends of the horizontal ribs 11 are fixed to the side surfaces of the main girder 1 via bolts 9. Both ends of the horizontal rib 11 are fixed to the sub-plate 19 by bolting or welding.
主桁l上には路面板10の補助主桁12を第2図に示す
ようにのせて、路面板側補強リブ15の面を横リブ側補
強リブ17の面に当接させた状態で補助主桁12の下端
を主桁1に固定する。The auxiliary main girder 12 of the road plate 10 is placed on the main girder l as shown in FIG. The lower end of the main girder 12 is fixed to the main girder 1.
次に互に面が当接している路面板側補強リブ15と横リ
ブ側補強リブ17とのボルト挿通孔113゜18にボル
トを挿通して路面板側補強リブ15と横リブ側補強リブ
17とを結合する。これによって別体に構成した路面板
10と横リブ11とは路面板側補強リブ15および横リ
ブ側補強リブ17を介して一体的に結合され、十分な強
度を保つことになる。Next, a bolt is inserted into the bolt insertion hole 113° 18 of the road plate side reinforcing rib 15 and the horizontal rib side reinforcing rib 17 whose surfaces are in contact with each other, and the road plate side reinforcing rib 15 and the horizontal rib side reinforcing rib 17 are inserted. Combine with. As a result, the road surface board 10 and the horizontal ribs 11, which are constructed separately, are integrally coupled via the road surface board side reinforcing ribs 15 and the horizontal rib side reinforcing ribs 17, thereby maintaining sufficient strength.
なお、路面板側補強リブ15と横リブ側補強リブ17と
の結合は、ボルトによらず溶接によってもよい。この場
合には、ボルト挿通孔16,18は穿設する必要がない
。Note that the road plate side reinforcing ribs 15 and the horizontal rib side reinforcing ribs 17 may be connected by welding instead of bolts. In this case, there is no need to drill the bolt insertion holes 16, 18.
[発明の効果]
本発明は、橋梁のコンクリート床版を鋼床版に張替える
場合に、鋼床版を別体の路面板と横リブにて構成し、横
リブを主桁側部間に固定し、路面板を主桁上および横リ
ブ上に固定するようにしたので、鋼床版の路面の高さを
コンクリート床版の場合と同じ高さにすることができる
ため、取付道路との間に段差を生ずることがなく、しか
も路面高さを押えながら十分な強度を保持することがで
きる。[Effects of the Invention] When replacing the concrete deck slab of a bridge with a steel deck slab, the present invention comprises the steel deck slab with a separate road plate and horizontal ribs, and connects the horizontal ribs between the main girder side parts. Since the road slab is fixed on the main girders and horizontal ribs, the height of the road surface of the steel deck slab can be made the same as that of the concrete deck slab, making it easier to maintain the same height as the access road. There is no difference in level between the two, and sufficient strength can be maintained while keeping the height of the road surface low.
第1図は本発明の一実施例の縦断面図、第2図は路面板
と横リブとを結合した状態を示す縦断面図、第3図はコ
ンクリート床版の縦断面図、第4図はコンクリート床版
と従来の鋼床版との高さの差を示す縦断面図、第5図は
従来の鋼床版の縦断面図である。
図中、1は主桁、2はコンクリート床版、IOは路面板
、11は横リブ、■2は補助主桁、13は縦リブ、14
は高さ、15は路面板側補強リブ、17は横リブ側補強
リブを示す。
第1図Fig. 1 is a longitudinal cross-sectional view of an embodiment of the present invention, Fig. 2 is a longitudinal cross-sectional view showing a state in which a road plate and horizontal ribs are combined, Fig. 3 is a longitudinal cross-sectional view of a concrete slab, and Fig. 4 FIG. 5 is a vertical cross-sectional view showing the difference in height between a concrete deck slab and a conventional steel deck slab, and FIG. 5 is a vertical cross-sectional view of a conventional steel deck slab. In the figure, 1 is the main girder, 2 is the concrete slab, IO is the road plate, 11 is the horizontal rib, ■2 is the auxiliary main girder, 13 is the vertical rib, 14
15 is the height, 15 is the reinforcing rib on the road board side, and 17 is the reinforcing rib on the side rib side. Figure 1
Claims (1)
面には主桁の上にのせた状態で前記路面板の上面が撤去
前のコンクリート床板の場合と同一高さになるようにし
た高さの低い補助主桁を固着し、前記路面板の下面には
さらに多数の縦リブを互に平行にして固着し、該縦リブ
と前記路面板の下面とにわたって路面板側補強リブを鉛
直に固着し、前記横リブの上面には横リブ側補強リブを
前記路面板側補強リブの位置に対応させて鉛直に固着し
たことを特徴とする橋梁補修用鋼床版。 2)横リブ側補強リブを上面に鉛直に固着した横リブの
両端を主桁の側面に固着し、コンクリート床板を撤去し
た主桁上には路面板の下面に固着した補助主桁をのせて
固定し、路面板下面の縦リブと路面板下面とにわたって
鉛直に固着した路面板側補強リブと前記横リブ側補強リ
ブとの面を当接させて結合することを特徴とする請求項
1記載の橋梁補修用鋼床版の取付方法。[Scope of Claims] 1) In the case where the road surface plate and the horizontal ribs are configured separately, the lower surface of the road surface plate is placed on the main girder, and the upper surface of the road surface plate is a concrete floor plate before removal. A low-height auxiliary main girder is fixed to the lower surface of the road surface plate, and a large number of vertical ribs are further fixed in parallel to each other on the lower surface of the road surface plate. For bridge repair, characterized in that a reinforcing rib on the road plate side is vertically fixed to the upper surface of the horizontal rib, and a reinforcing rib on the side rib is fixed vertically to the upper surface of the horizontal rib in a manner corresponding to the position of the reinforcing rib on the road plate side. Steel floor version. 2) Both ends of the horizontal rib, with the horizontal rib side reinforcing rib fixed vertically to the upper surface, are fixed to the side of the main girder, and the auxiliary main girder fixed to the lower surface of the road plate is placed on the main girder from which the concrete floor plate has been removed. 2. The reinforcing rib on the road surface board and the reinforcing rib on the lateral rib side, which are fixed and fixed vertically across the vertical rib on the lower surface of the road surface board and the lower surface of the road surface board, are joined by bringing their surfaces into contact with each other. How to install steel deck slabs for bridge repair.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7105490A JP2861219B2 (en) | 1990-03-20 | 1990-03-20 | Bridge deck repair steel slab and its mounting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7105490A JP2861219B2 (en) | 1990-03-20 | 1990-03-20 | Bridge deck repair steel slab and its mounting method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH03271408A true JPH03271408A (en) | 1991-12-03 |
JP2861219B2 JP2861219B2 (en) | 1999-02-24 |
Family
ID=13449424
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7105490A Expired - Lifetime JP2861219B2 (en) | 1990-03-20 | 1990-03-20 | Bridge deck repair steel slab and its mounting method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2861219B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002332612A (en) * | 2001-05-10 | 2002-11-22 | Ishikawajima Harima Heavy Ind Co Ltd | Re-covering steel-plate floor deck bridge |
JP2007107185A (en) * | 2005-10-11 | 2007-04-26 | Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd | Structure and method for repairing and reinforcing steel bridge |
JP2007327256A (en) * | 2006-06-08 | 2007-12-20 | Nippon Steel Corp | Fatigue-resistant steel floor slab |
KR100899166B1 (en) * | 2009-01-30 | 2009-05-26 | 노윤근 | Lengthwise slope upward control method of steel bridge |
CN113216017A (en) * | 2021-05-12 | 2021-08-06 | 山西省交通科技研发有限公司 | Steel-encased ultrahigh-performance concrete reinforcing method for box girder |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5858308A (en) * | 1981-10-02 | 1983-04-06 | 日本鋼管株式会社 | Repairing of bridge beam floor plate by steel floor panel |
-
1990
- 1990-03-20 JP JP7105490A patent/JP2861219B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5858308A (en) * | 1981-10-02 | 1983-04-06 | 日本鋼管株式会社 | Repairing of bridge beam floor plate by steel floor panel |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002332612A (en) * | 2001-05-10 | 2002-11-22 | Ishikawajima Harima Heavy Ind Co Ltd | Re-covering steel-plate floor deck bridge |
JP4627383B2 (en) * | 2001-05-10 | 2011-02-09 | 株式会社Ihiインフラシステム | Replaced steel deck bridge |
JP2007107185A (en) * | 2005-10-11 | 2007-04-26 | Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd | Structure and method for repairing and reinforcing steel bridge |
JP2007327256A (en) * | 2006-06-08 | 2007-12-20 | Nippon Steel Corp | Fatigue-resistant steel floor slab |
KR100899166B1 (en) * | 2009-01-30 | 2009-05-26 | 노윤근 | Lengthwise slope upward control method of steel bridge |
CN113216017A (en) * | 2021-05-12 | 2021-08-06 | 山西省交通科技研发有限公司 | Steel-encased ultrahigh-performance concrete reinforcing method for box girder |
Also Published As
Publication number | Publication date |
---|---|
JP2861219B2 (en) | 1999-02-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4985540B2 (en) | Vertical beam system for mobile work vehicles for cantilever installation | |
KR101962853B1 (en) | Joint for Precast Beam and Columns | |
JP2003253620A (en) | Cable stayed bridge and its construction method | |
JPH03271408A (en) | Steel floor bed for repairing bridge and method of attaching thereof | |
JP3450054B2 (en) | Installation method of floor slab on bridge girder and slab cradle | |
JP2006112086A (en) | Structure of bridge and method for rebuilding bridge | |
JP2000008304A (en) | Pedestal for rail road work beam and execution method of pedestal for rail road work beam | |
JP4627383B2 (en) | Replaced steel deck bridge | |
JPS6059210A (en) | Replacing method of bridge reinforced concrete floor panel | |
KR100334257B1 (en) | Formwork method using no prop for the floor concrete of the bridge | |
JP2001081726A (en) | Method and structure for re-laying steel floor slab of concrete floor slab bridge | |
JP2571810Y2 (en) | Stone stairs | |
JPH0820915A (en) | Precast floor slab | |
JP2003041516A (en) | Integral structure of upper and lower parts of continuous girder bridge and method of constructing it | |
JPS6157732A (en) | Construction of multilayered building skeletal by precast reinforced concrete unit | |
JP2002227131A (en) | End section widening method for existing bridge | |
KR100395590B1 (en) | The Method of Lane Extension by Beam Support to Wayside and Structure Thereof | |
JP2002173911A (en) | Re-covering execution method for steel floorslab and concrete floorslab | |
JP2004293113A (en) | Latticed point structure of floor slab and coupler in bridge | |
KR200241339Y1 (en) | Delay joint construction of reforced concrete structure | |
JPH01151603A (en) | Method of installing expansion joint device | |
JP2713085B2 (en) | Wall formwork mounting structure | |
JPH035442B2 (en) | ||
KR200333777Y1 (en) | Structure of continuous PSC beam with connection member and steel cross beam | |
JPS6025590B2 (en) | Method for joining old and new concrete using studded plates |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071211 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071211 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071211 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081211 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091211 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091211 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101211 Year of fee payment: 12 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101211 Year of fee payment: 12 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101211 Year of fee payment: 12 |