JPS5858308A - Repairing of bridge beam floor plate by steel floor panel - Google Patents

Repairing of bridge beam floor plate by steel floor panel

Info

Publication number
JPS5858308A
JPS5858308A JP15609081A JP15609081A JPS5858308A JP S5858308 A JPS5858308 A JP S5858308A JP 15609081 A JP15609081 A JP 15609081A JP 15609081 A JP15609081 A JP 15609081A JP S5858308 A JPS5858308 A JP S5858308A
Authority
JP
Japan
Prior art keywords
deck
flange
bridge
steel
main girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15609081A
Other languages
Japanese (ja)
Inventor
森 国夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Kokan Ltd filed Critical Nippon Kokan Ltd
Priority to JP15609081A priority Critical patent/JPS5858308A/en
Publication of JPS5858308A publication Critical patent/JPS5858308A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は、橋梁の老朽化した鉄筋コンクリート版を除去
し、短朗間でパネル式鋼床版に取替えて復旧すると共に
、橋梁の耐荷力を増大させるようにした橋梁床版の復旧
方法に関するものである。
[Detailed Description of the Invention] The present invention is a bridge deck in which the aged reinforced concrete slab of a bridge is removed and restored by replacing it with a panel-type steel deck slab in a short period of time, and the load-bearing capacity of the bridge is increased. This is related to how to restore the version.

従来、第1図に示すような通常の鋼製主桁1を有する橋
梁において、老朽化して例えばひソ割れなどが生じたコ
ンクリート床版2を補修又は復旧する方法としては、次
のようなものがある。
Conventionally, in a bridge having an ordinary steel main girder 1 as shown in Fig. 1, the following methods have been used to repair or restore the aged concrete slab 2 that has developed cracks, for example. There is.

(1)  コンクIJ −トのひび割れ部に樹脂等を1
’4E人したり、床版下面に鋼販を貼って補修する方法
があるが、この方法はあく葦で一時的なもので、恒久的
なものではない。
(1) Apply resin, etc. to the cracked part of the concrete IJ-to.
There are methods of repairing the problem, such as by using a 4E person or by pasting steel tape on the bottom of the floor slab, but this method is only temporary and is not permanent.

(2)主桁1間に縦桁などを追加する方法もあるが、こ
の方法ではコンクリートのひソ割れなどに対する根本的
な対策にはならない。
(2) There is a method of adding vertical girders between each main girder, but this method does not provide a fundamental countermeasure against cracks in concrete.

(3)  また、老朽化したコンクIJ−1・を除去し
て、新らしいコンクリートを打設する方法があるが、こ
の方法によると、一般にコンクリートの宋版厚が増大す
る傾向にあり、死荷重が増大するので好ましくない。
(3) There is also a method of removing old concrete IJ-1 and pouring new concrete, but this method generally tends to increase the thickness of the concrete, and the dead load is undesirable because it increases

このように、従来の補修、復旧方法には種々欠点がある
ので、最近では老朽化したコンクリートを除去して、鋼
床版パネルに替えるケースが増加している。
As described above, conventional repair and restoration methods have various drawbacks, so recently there has been an increase in the number of cases in which aged concrete is removed and replaced with steel deck panels.

このような場合、一般に、第1図に示すような橋梁のア
スファルト舗装3及びコンクリート床版2を除去し、第
2図に示すように、鋼床版を構成するデツキプレート4
の表面の主桁1に対向する位置に例えばT型鋼からなる
連結部材5を、また各連結部材5の間l/ζ複数個のT
型鋼、Lm鋼等からなる縦リブ6をそれぞれ溶接1〜、
これを主桁1に装着した横桁7ヒに載置して、連結部材
5及び縦リブ6のフランジ上それぞれ主桁1のフランジ
及び横桁7にボルトで固定している。
In such cases, generally, the asphalt pavement 3 and concrete deck slab 2 of the bridge as shown in Fig. 1 are removed, and the deck plate 4 constituting the steel deck slab is removed as shown in Fig. 2.
A connecting member 5 made of, for example, T-shaped steel is placed at a position facing the main girder 1 on the surface of the
The vertical ribs 6 made of type steel, Lm steel, etc. are welded 1 to 1, respectively.
This is placed on a cross beam 7 attached to the main girder 1 and fixed to the flanges of the connecting member 5 and the vertical rib 6 by bolts to the flanges of the main girder 1 and the cross beam 7, respectively.

ところで、このような従来の鋼床版パネルによる橋梁の
復旧方法においては、次のような多くの問題があり、早
期解決が望まれていた。
By the way, in such a conventional bridge restoration method using steel deck panels, there are many problems as described below, and an early solution has been desired.

(1)橋梁の復旧にあたっては、一般に復旧前後の路面
高を同一にしなければならないという制約があるため、
連結部材5の烏さを充分にとることができない。このた
め、主桁1のフランジとデツキプレート4との間が特に
狭くなり、連結部材5のフランジを主桁1のフランジに
ボルトで固定する作業がきわめて困難である。
(1) When restoring a bridge, there is generally a constraint that the road surface height must be the same before and after restoration.
The roughness of the connecting member 5 cannot be sufficiently removed. Therefore, the space between the flange of the main girder 1 and the deck plate 4 becomes particularly narrow, making it extremely difficult to fix the flange of the connecting member 5 to the flange of the main girder 1 with bolts.

(2)連結部材5のフランジと縦リブ6のフランジのボ
ルト穴は通常工場で加工されるため、現場で加工した主
桁1の7ランジのボルト穴との穴合せがきわめて面倒で
あり、時間がか\るばか如でなく18度−ヒも問題があ
る。。
(2) Since the bolt holes of the flange of the connecting member 5 and the flange of the vertical rib 6 are usually machined at the factory, it is extremely troublesome and time-consuming to match the bolt holes of the 7 langes of the main girder 1 machined on site. There is also a problem with 18 degrees - Hi, not just Gaka\ru Bakayo. .

(3)第3図に示すように、主桁1のフランジの一ヒ面
に現場添接部1aがあるときは、既設のボルトが邪魔に
なって連結部材5の取・f=lIが困兼である0 (4)  横桁7tこは前記した高さの佃]約から、主
桁1との連結部に切欠きを設けなければならないので、
作業が面倒なばかりでなく、強度北も問題があるっ 本発明は、上記のような問題点を1fイ決するためにな
されたもので、鋼床版パネルの取付が容易でその上上桁
の剛性が旧が沙、橋梁全体の耐荷力を増大させることの
できる橋梁床版の複11」か法を提供することを目的と
するものである。
(3) As shown in Fig. 3, when there is an on-site attachment part 1a on one side of the flange of the main girder 1, it is difficult to remove the connecting member 5 due to the existing bolts getting in the way. (4) Since the crossbeam 7t has the above-mentioned height, a notch must be provided at the connection with the main girder 1.
Not only is the work troublesome, but there is also a problem with strength.The present invention was made to solve the above-mentioned problems.It is easy to install steel deck panels, and the upper girder The purpose of this invention is to provide a method for constructing bridge decks that can increase the load-bearing capacity of the entire bridge, even though its rigidity is low.

本発明は、橋梁の老朽化した鉄筋コンクリート床版を補
修又は複11」するに際し、前記鉄筋コンクリート床版
を除去したのち各主1イiのフランジに1桁のウェブを
溶接し、該’、1” 4(rのフランジにデツキプレー
トを載置してその側端部を前@[!T桁のフランジに溶
接することを特徴とする鋼床版パネルによる橋梁床版の
復旧方法に関するものである。以下図面を用いて本発明
を説明する。
In the present invention, when repairing or replacing an aging reinforced concrete deck of a bridge, after removing the reinforced concrete deck, a single digit web is welded to the flange of each main 1i, This relates to a method for restoring a bridge deck using a steel deck panel, which is characterized by placing a deck plate on the flange of 4(r) and welding its side end to the flange of the front @[!T girder. The present invention will be explained below using the drawings.

第4図は本発明実施例を説明するだめの橋梁の斜視図、
第5図はその要部の正面図である。なお、第2図と同じ
部分には同じ符号を付し、説明を省略する。8はT型鋼
からなる主桁1の両側に溶接されたステイフナプレート
、7aはデツキプレート4の縦リブ6を支持する横桁で
、■型鋼、T型鋼等からなり、スプライスプレート9に
より主桁1に設けたステイフナプレート8に装着されて
いる。5aはT型・鋼からなる1桁で、第5図に示すよ
うにそのウェブを主桁1のフランジに現場ですみ肉溶接
したものである。なお、10はデツキプレート4を橋軸
方向に連結するカバーブ1/−トである。
FIG. 4 is a perspective view of a temporary bridge for explaining an embodiment of the present invention;
FIG. 5 is a front view of the main parts. Note that the same parts as in FIG. 2 are denoted by the same reference numerals, and explanations thereof will be omitted. 8 is a stiffener plate welded to both sides of the main girder 1 made of T-shaped steel, 7a is a cross beam that supports the vertical rib 6 of the deck plate 4, and is made of ■-shaped steel, T-shaped steel, etc. It is attached to the stiffener plate 8 provided in 1. 5a is a single girder made of T-shaped steel, and its web is fillet welded to the flange of the main girder 1 on site as shown in FIG. Note that 10 is a cover plate 1/-t that connects the deck plate 4 in the bridge axis direction.

上記のような各部材により本発明の復旧方法を説明すれ
ば次の通りである。先ず、各主桁1の両側面にステイフ
ナプレート8を溶接し、スプライスプレート9により横
桁7aを主桁1のステイフナプレート8に装着する。横
桁7aは、コンクリート床版2を除去してから主桁1に
装着してもよいが、除去前に装着した方が作業時間を短
縮できる。ついで、第5図に示すように各主桁1のフラ
ンジに1桁5aのウェブをすみ肉溶接する。
The restoration method of the present invention will be explained using the above-mentioned members as follows. First, the stiffener plates 8 are welded to both sides of each main girder 1, and the cross beams 7a are attached to the stiffener plates 8 of the main girder 1 using the splice plates 9. The cross beam 7a may be attached to the main girder 1 after removing the concrete slab 2, but the work time can be shortened if it is attached before removal. Then, as shown in FIG. 5, the web of one girder 5a is fillet welded to the flange of each main girder 1.

一方、工場で表面にT型鋼)L型鋼等からなる縦リブ6
のウェブを溶接したデツキプレート4を現場に運搬し、
主桁1と横桁7a上に載置して各デツキプレート4の側
端部を1桁5aのフランジ上に所定の間隔をおいて載せ
、第5図に示すようにデツキプレート4の橋軸方向の側
端部を主桁1のフランジにすみ肉溶接する。次に各縦リ
ブ6のフランジを横桁7&のフランジにボルトで固定し
、最後にデツキプレート4の橋軸方向の継目にカバープ
レート10を装着する。
On the other hand, vertical ribs 6 made of T-shaped steel) L-shaped steel etc. are attached to the surface at the factory.
Transport the deck plate 4 with the web welded to the site,
The deck plates 4 are placed on the main girder 1 and the cross beam 7a, and the side ends of each deck plate 4 are placed on the flange of the first girder 5a at a predetermined interval, and the bridge axis of the deck plate 4 is placed on the main girder 1 and the cross beam 7a. Fillet weld the side end of the direction to the flange of the main girder 1. Next, the flange of each vertical rib 6 is fixed to the flange of the cross beam 7& with bolts, and finally, the cover plate 10 is attached to the joint of the deck plate 4 in the bridge axis direction.

上記のような本発明の復旧方法によれば、デツキプレー
ト4は1桁のフランジ上にすみ肉溶接で装着するので、
多少の誤差かめってもとりつけが容易である。また主桁
1のフランジ上に添接部1a(第6図)があっても、1
桁5aを溶接するウェブ上にはボルトがないのでとりつ
けが可能でありしたがってデツキプレート4を橋軸方向
に連続シ2て装着することができる。さらに、縦リブ6
は横桁7a上でのみボルトで固定されるので、ボルトの
数が少なくてすみ、作業空間も充分あるためとりつけが
容易である。
According to the restoration method of the present invention as described above, the deck plate 4 is attached to the 1-digit flange by fillet welding.
It is easy to install even if there are some errors. Also, even if there is a joint part 1a (Fig. 6) on the flange of the main girder 1, 1
Since there are no bolts on the web to which the girder 5a is welded, attachment is possible, and therefore the deck plate 4 can be attached continuously in the bridge axis direction. Furthermore, the vertical rib 6
Since it is fixed with bolts only on the crossbeam 7a, the number of bolts is small and there is sufficient work space, making installation easy.

以上詳述したように、本発明によれば鋼床版パネルのと
りつけがきわめて容易になるばかりでなく、既設の主桁
は新設の1桁と一体構造になるので上フランジが補強さ
れたことに々す、剛性が上り主桁即ち橋梁全体の耐荷力
が増大する等、実施による効果大である。
As detailed above, according to the present invention, not only is it extremely easy to install steel deck panels, but the existing main girder is integrated with the newly constructed single girder, so the upper flange is reinforced. The effects of implementation are significant, such as increased rigidity and load-bearing capacity of the main girder, that is, the entire bridge.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は鉄筋コンクリート床版の橋梁を説明する為の側
面図、第2図は従来の鋼床版パネルによる吹出方法を説
明するための斜視図、第6図はその主桁のフランジ部分
を示す斜視図、第4図は本発明実施例を説明するだめの
斜視図、第5図はその要部の正面図である。 1゛主桁、2:鉄筋コンクリート床版、4;デツキプレ
ート、5a :’p桁、6;縦リブ、7a:横桁。 代理人 弁理士  佐 ノm 正 年 第1図 第2図 第3図 鍔〆 第4図 第5図 手続袖市書(自発) 特許庁長官殿        昭和565+= 111
ビ(On   1、事件の表示 %願昭 56 − 156090号 2、発明の名称 鋼床版パネルによる橋梁床版の復旧方法3、袖1Fをす
る者 4、代理人 6°補、+Ti (7) 対象  明細書の「発明の名
称」、「特許請求の範囲」、「発明の詳細な説明」、「
図面7、補正の内容      の簡単な説明」の欄及
び図面別紙の通シ (1)  明細書の発明の名称の[鋼床版パネルによる
橋梁床版の復旧方法]とあるのを「鋼床版パネルによる
橋梁床板の復旧方法」と補正−する。 (2、特許請求の範囲全別紙の通り補止する。 (3)  明細書中次の通り補正する。 (4)  明細書第1頁第13行〜第14行の[鉄筋コ
ンクリート版]とあるのを「鉄筋コンクリート床版」と
補正する。 (5)  明細書第6頁第3行〜第6行の[らなる縦リ
ブ6・・・・・ボルトで固定している。」とあるのを次
の通り補正する。 [らなる縦リブ6をそれぞれ沁接し、この連結部材5の
7ランジ金主桁1のフランジにボルトで固定している。 」 (6)明細’4F第5頁第11行目のr5aはT型鋼か
らなる1桁で、」とあるのをr5aは1桁で、」と補正
する。 (7)明細書第5頁第18行〜第20行の[側面にステ
インナプレート8を溶接し、・・・・・・ステイフナプ
レート8に装着する。」とあるのを次の通り補正する。 の [側−ffli Kステイフナプレー1・8に、スプラ
イスプレート9により横桁7aを装庸する。」(8) 
 明細書第6頁第10行目の「主桁1」とあるのを[゛
T桁5aJと補正する。 (9)  明細書第6頁第19行〜m20行の[1桁5
aを溶接するウェブ上にはボルトがないので」とあるの
を[1桁5aと主桁1のフランジ上面にとりつけた添接
部1aとの交差部にけ添接ボルトがないので」ど補正−
「る。 αQ 図面の第6図及び第4図を別紙の通り補正する。 補正後の11′81=d1:請求の範囲「橋梁の老朽化
した鉄筋コンクリ−1・床版を補修又は復旧するに除し
、前記鉄筋コンクリート床版を除去したのち各主桁のフ
ランジに1桁のウェブを溶接し、該1桁のフランジにデ
ツキプレートに載置してその側端部を前記1桁のフラン
ジに溶接することを特徴とする鋼床版パネルによる橋梁
床版の復旧方法。」 第3図 第4図
Figure 1 is a side view to explain a reinforced concrete deck bridge, Figure 2 is a perspective view to explain the blowing method using conventional steel deck panels, and Figure 6 shows the flange part of the main girder. FIG. 4 is a perspective view for explaining an embodiment of the present invention, and FIG. 5 is a front view of the main parts thereof. 1. Main girder, 2. Reinforced concrete deck slab, 4. Deck plate, 5a. 'p girder, 6. Vertical rib, 7a. Cross beam. Agent Patent Attorney Masaru San Figure 1 Figure 2 Figure 3 Tsuba〆 Figure 4 Figure 5 Procedures Sodeichi (self-motivated) Mr. Commissioner of the Japan Patent Office 1985+= 111
Bi (On 1, Incident Display Percent Request No. 56-156090 No. 2, Title of Invention Method for Restoring Bridge Slabs Using Steel Deck Panels 3, Person Performing Sleeve 1F 4, Agent 6° Supplement, +Ti (7) Target: "Title of the invention", "Claims", "Detailed description of the invention", "
Drawing 7, "Brief explanation of the contents of the amendment" column and the appendix to the drawing (1) In the title of the invention in the specification, "Method for restoring bridge deck slabs using steel deck panels" is replaced with "Steel deck slab". Revised as ``Method for restoring bridge decks using panels.'' (2. The entire scope of the claims is amended as per the appendix. (3) The specification is amended as follows. (4) The phrase [reinforced concrete version] in lines 13 to 14 of page 1 of the specification is amended. (5) On page 6 of the specification, lines 3 to 6, the statement [consisting of vertical ribs 6... fixed with bolts] should be corrected as follows: [The vertical ribs 6 are in contact with each other and are fixed to the flange of the 7-lung metal main girder 1 of this connecting member 5 with bolts.'' (6) Specification '4F, page 5, line 11. ``R5a is a single digit made of T-shaped steel,'' is corrected to ``R5a is a single digit.'' (7) In the specification, page 5, lines 18 to 20, [stainer plate on the side] 8, and attach it to the stiffener plate 8.'' is corrected as follows. Wear 7a.” (8)
``Main digit 1'' on page 6, line 10 of the specification is corrected to [゛T digit 5aJ. (9) [1st digit 5] on page 6, line 19 to line m20 of the specification
The statement "There are no bolts on the web to be welded a" was corrected to "There are no bolts at the intersection of the first girder 5a and the splice part 1a attached to the top surface of the flange of the main girder 1." −
αQ Figures 6 and 4 of the drawings are amended as shown in the attached sheet. 11'81=d1 after amendment: Claim ``Repair or restoration of aged reinforced concrete 1/deck of bridge. After removing the reinforced concrete slab, weld one web to the flange of each main girder, place it on a deck plate on the flange of said one girder, and attach the side end to the flange of said one girder. A method for restoring bridge decks using steel deck panels characterized by welding." Figure 3 Figure 4

Claims (1)

【特許請求の範囲】[Claims] 橋梁の老朽化した鉄筋コンク’J −ト床版を補修又は
復旧するに際し、前記鉄筋コンクリート床版を除去した
のち各主桁のフランジにTmのウェブを溶接し、該1桁
のフランジにデツキプレートを載置してその側端部を前
記1桁のフランジに溶接することを特徴とする鋼床版パ
ネルによる橋梁床版の復旧方法。
When repairing or restoring the aged reinforced concrete deck of a bridge, after removing the reinforced concrete deck, a web of Tm is welded to the flange of each main girder, and a deck plate is attached to the flange of that one girder. A method for restoring a bridge deck using a steel deck panel, the method comprising placing the steel deck panel on top and welding its side end to the flange of the single digit.
JP15609081A 1981-10-02 1981-10-02 Repairing of bridge beam floor plate by steel floor panel Pending JPS5858308A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15609081A JPS5858308A (en) 1981-10-02 1981-10-02 Repairing of bridge beam floor plate by steel floor panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15609081A JPS5858308A (en) 1981-10-02 1981-10-02 Repairing of bridge beam floor plate by steel floor panel

Publications (1)

Publication Number Publication Date
JPS5858308A true JPS5858308A (en) 1983-04-06

Family

ID=15620082

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15609081A Pending JPS5858308A (en) 1981-10-02 1981-10-02 Repairing of bridge beam floor plate by steel floor panel

Country Status (1)

Country Link
JP (1) JPS5858308A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03271408A (en) * 1990-03-20 1991-12-03 Ishikawajima Harima Heavy Ind Co Ltd Steel floor bed for repairing bridge and method of attaching thereof
JP2002173911A (en) * 2000-12-07 2002-06-21 Ishikawajima Harima Heavy Ind Co Ltd Re-covering execution method for steel floorslab and concrete floorslab
JP2006077523A (en) * 2004-09-13 2006-03-23 Jfe Engineering Kk Reinforcing construction method of steel plate floor
JP2008169572A (en) * 2007-01-10 2008-07-24 Mitsui Eng & Shipbuild Co Ltd Bridge with a small number of main girders
JP6845301B1 (en) * 2019-12-04 2021-03-17 日本製鉄株式会社 Floor slab replacement structure and floor slab replacement method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03271408A (en) * 1990-03-20 1991-12-03 Ishikawajima Harima Heavy Ind Co Ltd Steel floor bed for repairing bridge and method of attaching thereof
JP2002173911A (en) * 2000-12-07 2002-06-21 Ishikawajima Harima Heavy Ind Co Ltd Re-covering execution method for steel floorslab and concrete floorslab
JP2006077523A (en) * 2004-09-13 2006-03-23 Jfe Engineering Kk Reinforcing construction method of steel plate floor
JP2008169572A (en) * 2007-01-10 2008-07-24 Mitsui Eng & Shipbuild Co Ltd Bridge with a small number of main girders
JP6845301B1 (en) * 2019-12-04 2021-03-17 日本製鉄株式会社 Floor slab replacement structure and floor slab replacement method
JP2021088873A (en) * 2019-12-04 2021-06-10 日本製鉄株式会社 Floor slab replacement structure and floor slab replacement method

Similar Documents

Publication Publication Date Title
JPS5858308A (en) Repairing of bridge beam floor plate by steel floor panel
JPS6059209A (en) Replacing method of bridge reinforced concrete floor panel
JP2000288726A (en) Structure for repairing and/or reinforcing crack from welded filet part of sole plate in steel bridge
JPS6282147A (en) Novel prestressed synthetic beam and its construction
JP2508677B2 (en) Reinforcement method of bridge reinforced concrete slab
CN110284716B (en) Construction method of lifting plate node structure of steel bar truss floor bearing plate
JPS6364565B2 (en)
JPS6059210A (en) Replacing method of bridge reinforced concrete floor panel
JPS6033962A (en) Pillar and beam connecting apparatus
JP2861219B2 (en) Bridge deck repair steel slab and its mounting method
JP2708698B2 (en) Construction method of combined joint of friction joint high strength bolt joint and weld joint
JPS6340586Y2 (en)
JPH09177031A (en) Provisionally receiving facility for jack in repair work of main girder constituting elevated bridge, etc.
JPH0320325Y2 (en)
JPS5925931Y2 (en) Composite girder using π-shaped steel
JPH0312803Y2 (en)
JPS63315714A (en) Method for mounting steel floor panel to existing cross beam
Putkey Common steel erection problems and suggested solutions
CN116289667A (en) Prestressed concrete continuous beam dismantling method
KODA Research and Development Trends in Restoration Technologies for Railway Bridges and Viaducts Developed by the Railway Technical Research Institute
Barton Carbon fibre “plate bonding”
JP2574644Y2 (en) Frame structure combining steel beams with reinforced concrete girders
JPH036282B2 (en)
Fisher et al. An ounce of prevention
KR20230034003A (en) Hollow insert fastening type steel cross beam structure and its construction method