JP2708698B2 - Construction method of combined joint of friction joint high strength bolt joint and weld joint - Google Patents
Construction method of combined joint of friction joint high strength bolt joint and weld jointInfo
- Publication number
- JP2708698B2 JP2708698B2 JP18224493A JP18224493A JP2708698B2 JP 2708698 B2 JP2708698 B2 JP 2708698B2 JP 18224493 A JP18224493 A JP 18224493A JP 18224493 A JP18224493 A JP 18224493A JP 2708698 B2 JP2708698 B2 JP 2708698B2
- Authority
- JP
- Japan
- Prior art keywords
- joint
- strength
- strength bolt
- friction
- tightening force
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bridges Or Land Bridges (AREA)
- Joining Of Building Structures In Genera (AREA)
- Connection Of Plates (AREA)
Description
【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION
【0001】[0001]
【産業上の利用分野】本発明は、橋梁や建築物等の鋼構
造物の鋼部材の継手部に用いられる摩擦接合高力ボルト
継手と溶接継手との併用継手に係り、特に、溶接継手部
の残留応力を減少するとともに高力ボルトのすべり耐力
の低減を防止する摩擦接合高力ボルト継手と溶接継手と
の併用継手の施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a joint using a friction-joined high-strength bolted joint and a welded joint used for a joint of a steel member of a steel structure such as a bridge or a building. The present invention relates to a method for constructing a joint using a friction-joined high-strength bolted joint and a welded joint to reduce the residual stress of the high-strength bolt and to prevent the reduction of the slip strength of the high-strength bolt.
【0002】[0002]
【従来の技術】橋梁や建築物等の鋼構造物の鋼部材に用
いられる現場継手は、一般に溶接継手でなく摩擦接合高
力ボルト継手が用いられる。溶接継手とした場合、一般
に溶接は作業時間が長いため、溶接作業中架設機械や作
業員を拘束する必要があり、不経済となる。また、交通
を遮断して鉄骨の架設工事を行う場合には、作業時間が
長くなると社会生活の上でも与える影響が大きい。さら
に、溶接を現場で行う場合は、工場での溶接の場合と異
なり施工環境を整えることが難しいため、品質管理上の
問題も生じる。2. Description of the Related Art In-situ joints used for steel members of steel structures such as bridges and buildings generally use friction-joined high-strength bolt joints instead of welded joints. In the case of using a welded joint, welding generally requires a long working time, so it is necessary to restrain the erection machine and workers during the welding work, which is uneconomical. In the case of constructing a steel frame while blocking traffic, a long working time has a large effect on social life. Furthermore, when welding is performed on site, it is difficult to prepare a construction environment unlike the case of welding at a factory, and thus there is a problem in quality control.
【0003】一方、摩擦接合高力ボルト継手を単独で用
いた場合には前述した欠点はないが、荷重に対する変形
量の線形性、すなわち弾性変形性能が劣り、継手部にお
いて部材耐力が減少するという問題がある。図6に、摩
擦接合高力ボルト継手と溶接継手との比較を示すが、溶
接継手の場合には、直線aのように荷重と変形量とは比
例関係にあるが、摩擦接合高力ボルト継手の場合には、
曲線cのように荷重が大きくなると変形量は極端に大き
くなり、同一の変形量で比べると、摩擦接合高力ボルト
継手は溶接継手より荷重が小さく、したがって耐力も小
さいことがわかる。[0003] On the other hand, when the friction-joined high-strength bolt joint is used alone, the above-mentioned drawbacks are not present, but the linearity of the amount of deformation with respect to the load, that is, the elastic deformation performance is inferior, and the member strength at the joint decreases. There's a problem. FIG. 6 shows a comparison between a friction-joined high-strength bolt joint and a welded joint. In the case of a welded joint, the load and the deformation amount are in a proportional relationship as indicated by a straight line a. In Case of,
As shown by the curve c, when the load becomes large, the deformation becomes extremely large, and it can be seen that the friction-bonded high-strength bolted joint has a smaller load than the welded joint, and therefore has a lower proof stress, when compared with the same deformation.
【0004】そこで、従来、摩擦接合高力ボルト継手と
溶接継手とを併用して用い、鉄骨を現場で架設する時に
は、架設時の荷重を支えることができる程度に摩擦接合
高力ボルト継手で接合し、架設機械や作業員を短時間で
解放し、その後、該継手部に溶接継手を施して摩擦接合
高力ボルト継手の耐力を補強し、架設後の本体構造物に
作用する荷重に対抗させている。その場合には、継手全
体の弾性変形性能は摩擦接合高力ボルト継手のみの場合
より向上し、継手部における部材耐力の減少を抑えるこ
とができる。図6に、摩擦接合高力ボルト継手と溶接継
手との併用継手と、摩擦接合高力ボルト継手との比較を
示すが、併用継手の場合には、前記溶接継手の場合と同
じように、直線bのように荷重と変形量は比例関係にあ
るが、摩擦接合高力ボルト継手の場合よりは耐力が大き
いことがわかる。Therefore, conventionally, when a steel frame is erected on site by using a friction-joined high-strength bolt joint and a weld joint together, the joint is made with a friction-joined high-strength bolt joint enough to support the load at the time of erection. Release the erection machine and workers in a short time, and then apply a welded joint to the joint to reinforce the strength of the friction-joined high-strength bolted joint and counteract the load acting on the main body structure after erection. ing. In this case, the elastic deformation performance of the entire joint is improved as compared with the case of only the friction-joined high-strength bolt joint, and a decrease in the member strength at the joint can be suppressed. FIG. 6 shows a comparison between a joint using a friction-joined high-strength bolted joint and a welded joint and a friction-joined high-strength bolted joint. Although the load and the amount of deformation are proportional to each other as shown by b, it can be seen that the proof stress is larger than in the case of the friction-joined high-strength bolted joint.
【0005】ところが、摩擦接合高力ボルト継手と溶接
継手との併用継手を用いた場合には、解決すべき問題が
存在している。すなわち、 (1)溶接熱による母材の収縮変形を摩擦接合高力ボル
ト継手で拘束すると、該摩擦接合高力ボルト継手の摩擦
接合面には拘束による応力が生じ、該摩擦接合高力ボル
ト継手部に作用させることのできる許容摩擦力との余裕
がなくなり、高力ボルトとしての実質的なすべり耐力が
低下する。 (2)また、溶接熱による母材の収縮変形
を摩擦接合高力ボルト継手で拘束すると、鋼部材の内部
には残留応力が生じ、母材に作用させることのできる許
容応力との余裕がなくなり、本体構造物として使用する
ときの荷重を負担できない。[0005] However, there is a problem to be solved when a combined joint of a friction joint high strength bolt joint and a weld joint is used. That is, (1) when the contraction deformation of the base material due to welding heat is restrained by the friction-bonded high-strength bolt joint, stress is generated on the friction-bonded surface of the friction-bonded high-strength bolt joint, and the friction-bonded high-strength bolt joint is generated. There is no allowance for the allowable frictional force that can be applied to the part, and the substantial slip resistance as a high-strength bolt is reduced. (2) Further, when the contraction deformation of the base material due to welding heat is restrained by the friction-joined high-strength bolted joint, residual stress is generated inside the steel member, and there is no room for the allowable stress that can be applied to the base material. In addition, it cannot bear the load when used as a main body structure.
【0006】そこで、前記の問題のうち特に(1)を解
決するために、従来、溶接熱の影響が大きい溶接継手部
付近では高力ボルトの締め付けを行わず、溶接熱の影響
のない部分の高力ボルトを設計締め付け力で締め付けて
おき、溶接熱が冷めた後に残りの高力ボルトを設計締め
付け力で締め付ける方法が用いられている。この方法に
関する研究論文としては、「鋼床版現場溶接にともなう
腹板高力ボルト拘束力に関する調査」片山技報、昭和5
9年8月20日発行、著者 小島鉄也・由佐禎男・夏秋
義広、発行所 株式会社片山鉄工所を挙げることができ
る。Therefore, in order to solve the above problem (1) in particular, conventionally, high-strength bolts are not tightened in the vicinity of a welded joint where the influence of welding heat is large, and a portion of the joint not affected by welding heat is conventionally not tightened. A method is used in which high-strength bolts are tightened with a design tightening force, and after the welding heat is cooled, the remaining high-strength bolts are tightened with the design tightening force. As a research paper on this method, "Investigation on the binding strength of high-strength web plate bolts associated with on-site welding of steel deck" Katayama Technical Report, Showa 5
Published on August 20, 2009, authors Tetsuya Kojima, Yoshio Yoshida, Yoshihiro Natsuaki, Katayama Iron Works Co., Ltd.
【0007】また、前記の問題のうち特に(1)を解決
するために、摩擦接合高力ボルト継手部のうち、熱影響
を受けない部分の摩擦接合用高力ボルトについては全て
を設計締め付け力で締め付け、熱影響を受ける部分の摩
擦接合用高力ボルトについては一部を設計締め付け力で
締め付け、溶接熱が冷めた後に、溶接熱の影響を受けた
部分の高力ボルトを取り外し、新しい高力ボルトと交換
して設計締め付け力で締め付けする方法も用いられてい
る。この方法に関する研究論文としては、「溶接・ボル
ト併用継手における影響調査」首都高技報、昭和58年
3月1日発行、著者 高野晴夫・熊谷糺・佐野浩一、発
行所 首都高速道路公団を挙げることができる。Further, in order to solve the above problem (1) in particular, all of the high-strength bolts for friction joining, which are not affected by heat, in the friction-joining high-strength bolt joints are all designed with a tightening force. Part of the high-strength bolts for friction joining of the heat-affected parts are tightened with the design tightening force.After the welding heat has cooled, the high-strength bolts in the parts affected by the welding heat are removed, and the new high-strength bolts are removed. A method of replacing with a force bolt and tightening with a design tightening force is also used. As a research paper on this method, "Investigation of Impact on Welding and Bolt Joints" published by Tokyo Metropolitan Technical Report, March 1, 1983, author Haruo Takano, Tadashi Kumagai, Koichi Sano, published by Metropolitan Expressway Public Corporation be able to.
【0008】次に、前記の問題のうち特に(2)を解決
するために、従来、摩擦接合高力ボルト継手部の高力ボ
ルトを設計締め付け力の6割程度で締め付け、溶接熱が
冷めた後に全ての高力ボルトを設計締め付け力で締め付
ける方法も研究されている。この方法に関する研究論文
としては、「高力ボルトと溶接の併用継手に関する実験
的研究」横河橋梁技報、昭和52年11月1日発行、著
者 夏目光尋、発行所、株式会社横河橋梁制作所を挙げ
ることができる。Next, in order to solve the above problem (2) in particular, conventionally, the high-strength bolt of the friction-joint high-strength bolt joint is tightened at about 60% of the design tightening force, and the welding heat is cooled. Later, a method of tightening all high-strength bolts with a design tightening force has also been studied. A research paper on this method includes "Experimental Research on Joints Using High-Strength Bolts and Welds", Yokogawa Bridge Technical Report, published on November 1, 1977, author Mitsuhiro Natsume, issuance office, Yokogawa Bridge Co., Ltd. You can name a production place.
【0009】[0009]
【発明が解決しようとする課題】しかしながら、前記の
方法のうち、溶接熱の影響が大きい溶接継手部付近では
高力ボルトの締め付けを行わず、溶接熱の影響のない部
分の高力ボルトを設計締め付け力で締め付けておき、溶
接熱が冷めた後に残りの高力ボルトを設計締め付け力で
締め付けする方法では、摩擦接合高力ボルト継手部の高
力ボルトのうち、設計締め付け力で締め付ける範囲が小
さいため、架設時の継手の耐力が小さくなり、架設時に
大きな荷重を支える必要がある場合には継手構造を大き
くしなければならないこと、また、溶接後の高力ボルト
の締め付け本数が多くなり、施工が煩雑になるという問
題がある。However, of the above-mentioned methods, high-strength bolts are not tightened in the vicinity of a welded joint where the influence of welding heat is large, and a high-strength bolt which is not affected by welding heat is designed. In the method of tightening the remaining high-strength bolts with the design tightening force after the welding heat cools down, the range of tightening with the design tightening force is small among the high-strength bolts of the friction joining high-strength bolt joint As a result, the joint's proof strength during erection is reduced, and if it is necessary to support a large load during erection, the joint structure must be enlarged.In addition, the number of high-strength bolts after welding increases, and Is complicated.
【0010】また、前記の方法のうち、摩擦接合高力ボ
ルト継手部の中で、熱影響を受けない部分の高力ボルト
については全てを設計締め付け力で締め付け、熱影響を
受ける部分の高力ボルトについては一部を設計締め付け
力で締め付け、溶接熱が冷めた後に、溶接熱の影響を受
けた部分の高力ボルトを取り外し、新しい高力ボルトと
交換して設計締め付け力で締め付けする方法では、架設
時に大きな荷重を支える必要がある場合には継手構造を
小さくすることができるが、一般に一旦設計締め付け力
で締め付けした高力ボルトは再使用ができないため、交
換した高力ボルトは廃棄しなければならず不経済とな
る。In the above-mentioned method, all the high-strength bolts of the friction-joined high-strength bolt joint that are not affected by heat are all tightened by the design tightening force. For the bolts, the method of tightening a part with the design tightening force, after the welding heat has cooled, removing the high-strength bolt affected by the welding heat, replacing it with a new high-strength bolt, and tightening with the design tightening force However, if it is necessary to support a large load during installation, the joint structure can be made smaller.However, since high-strength bolts once tightened with the design tightening force cannot be reused, replaced high-strength bolts must be discarded. Must be uneconomical.
【0011】さらに、前記の方法のうち、摩擦接合高力
ボルト継手部の高力ボルトを設計締め付け力の6割程度
で締め付けておき、溶接熱が冷めた後に全ての高力ボル
トを設計締め付け力で締め付ける方法では、母材内部に
残留応力が発生せず、高力ボルト継手部にも拘束による
応力が生じることはないが、高力ボルトを設計締め付け
力の6割程度で締め付けの状態として架設時の荷重を支
えた場合には高力ボルトの軸部にせん断力が作用し、架
設完了後に設計締め付け力で締め付けを行っても高力ボ
ルトに所定の軸力を導入できないという問題がある。本
発明は、橋梁や建築物等の鋼構造物の鋼部材に用いられ
る摩擦接合高力ボルト継手と溶接継手との併用継手にお
いて、前記の母材の残留応力の集中をなくすとともに、
高力ボルトのすべり耐力を低下させない摩擦接合高力ボ
ルト継手と溶接継手との併用継手を提供することを目的
とする。Further, in the above method, the high-strength bolts of the friction-joint high-strength bolt joints are tightened to about 60% of the design tightening force, and after the welding heat is cooled, all the high-strength bolts are tightened to the design tightening force. With the method of tightening, no residual stress is generated inside the base material and no stress is generated at the high-strength bolted joints, but the high-strength bolt is installed in a tightened state with about 60% of the design tightening force. When the load at the time is supported, a shear force acts on the shaft portion of the high-strength bolt, and there is a problem that a predetermined axial force cannot be introduced into the high-strength bolt even if the bolt is tightened with the design tightening force after the completion of the erection. The present invention eliminates the concentration of the residual stress of the base material in a joint joint of a friction joint high strength bolt joint and a weld joint used for steel members of steel structures such as bridges and buildings,
An object of the present invention is to provide a combined joint of a friction-joined high-strength bolt joint and a welded joint that does not reduce the slip strength of the high-strength bolt.
【0012】[0012]
【課題を解決するための手段】本発明は、前記目的を達
成するために、橋梁や建築物等の鋼構造物の鋼部材に用
いられる摩擦接合高力ボルト継手と溶接継手との併用継
手において、溶接部に最も近い列の高力ボルト群のみを
設計締め付け力の2/3から1/4で締め付け、溶接熱
が冷めた後、該高力ボルト群を設計締め付け力で締め付
けることにより、残留応力の集中をなくすとともに、高
力ボルトのすべり耐力の低下を防ぐことができる。SUMMARY OF THE INVENTION In order to achieve the above object, the present invention provides a joint joint of a friction joint high strength bolt joint and a weld joint used for steel members of steel structures such as bridges and buildings. Only the high-strength bolt group in the row closest to the welded portion is tightened with 2/3 to 1/4 of the design tightening force, and after the welding heat is cooled, the high-strength bolt group is tightened with the design tightening force, so that the residual strength is reduced. The stress concentration can be eliminated, and a decrease in the sliding strength of the high-strength bolt can be prevented.
【0013】[0013]
【作用】本発明によれば、橋梁や建築物等の鋼構造物の
鋼部材に用いられる摩擦接合高力ボルト継手と溶接継手
との併用継手において、高力ボルトを施した後に溶接す
ることによって発生する溶接熱による残留応力の集中を
なくし、高力ボルトのすべり耐力の低下を防ぐことがで
きる。According to the present invention, in a joint joint of a friction joint high strength bolt joint and a weld joint used for a steel member of a steel structure such as a bridge or a building, welding is performed after applying a high strength bolt. Concentration of residual stress due to the generated welding heat can be eliminated, and a decrease in slip strength of the high-strength bolt can be prevented.
【0014】[0014]
【実施例】以下、本発明の実施例について図面を参照し
ながら詳細に説明する。図1は、本発明を、H形断面の
鋼部材のウェブに高力ボルトを、該H形断面の鋼部材の
フランジに溶接を用いた摩擦接合高力ボルト継手と溶接
継手との併用継手の図である。この図に示すように、H
形断面の鋼部材のウェブ12を添接鋼板13で挟み、溶
接部から最も近い列の高力ボルト群15bを除いた高力
ボルト群15aを設計締め付け力で締め付け、溶接部に
最も近い列の高力ボルト群15bを設計締め付け力の2
/3から1/4で締め付けた後、H形断面の鋼部材のフ
ランジ11、11’の溶接14、14’を行い、溶接熱
が冷めた後、溶接部に近い列の該高力ボルト群15bを
設計締め付け力で締め付ける。Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 shows the present invention using a high-strength bolt joint on a web of a steel member having an H-shaped cross section and a joint joint of a friction jointed high-strength bolt joint and a welded joint using welding on a flange of the steel member having an H-shaped cross section. FIG. As shown in FIG.
The web 12 of a steel member having a cross section is sandwiched between the attached steel plates 13, and the high-strength bolt group 15a excluding the high-strength bolt group 15b in the row closest to the weld is tightened with the design tightening force. The high-strength bolt group 15b has a design tightening force of 2
After tightening by 3 to 4, the flanges 11 and 11 ′ of the H-shaped steel member are welded 14 and 14 ′, and after the welding heat is cooled, the high-strength bolt group in a row near the welded portion 15b is tightened with a design tightening force.
【0015】図2は、本発明を、H形断面の鋼部材のウ
ェブと片側のフランジに高力ボルトを、該H形断面の鋼
部材の他方のフランジに溶接を用いた摩擦接合高力ボル
ト継手と溶接継手との併用継手の断面図である。この図
に示すように、H形断面の鋼部材のウェブ22を添接鋼
板23で挟み、さらに、H形断面の鋼部材の片方のフラ
ンジ(下フランジ)21’を添接鋼板24、24’で挟
んで、溶接部から最も近い列の高力ボルト群26bを除
いた高力ボルト群26a、26cを設計締め付け力で締
め付け、溶接部に最も近い列の高力ボルト群26bを設
計締め付け力の2/3から1/4で締め付け、H形断面
の鋼部材の他方のフランジ(下フランジ)21の溶接2
5を行い、溶接熱が冷めた後、溶接部に最も近い列の該
高力ボルト群26bを設計締め付け力で締め付ける。FIG. 2 shows a high-strength bolt formed by welding a high-strength bolt to the web and one side flange of a steel member having an H-shaped section and welding to the other flange of the steel member having the H-shaped section. It is sectional drawing of the joint joint of a joint and a welding joint. As shown in this drawing, a web 22 of a steel member having an H-shaped cross section is sandwiched between attached steel plates 23, and one flange (lower flange) 21 'of the steel member having an H-shaped cross section is further connected to attached steel plates 24, 24'. The high-strength bolt groups 26a, 26c except for the high-strength bolt group 26b in the row closest to the weld are tightened with the design tightening force, and the high-strength bolt group 26b in the row closest to the weld is tightened with the design tightening force. Welding 2/3 to 1/4, welding the other flange (lower flange) 21 of the steel member with H-shaped cross section 2
After the welding heat is cooled down, the group of high-strength bolts 26b in the row closest to the welded portion is tightened by the design tightening force.
【0016】図3は、本発明を、鋼管の継手部リブプレ
ートに高力ボルトを、該鋼管に溶接を用いた摩擦接合高
力ボルト継手と溶接継手との併用継手である。この図に
示すように、鋼管の継手部リブプレート31を添接鋼板
32で挟み、溶接部から最も近い列の高力ボルト群33
bを除いた高力ボルト群33aを設計締め付け力で締め
付け、溶接部に最も近い列の高力ボルト群33bを設計
締め付け力の2/3から1/4で締め付けた後、鋼管3
4の溶接35を行い、溶接熱が冷めた後、溶接部に最も
近い列の該高力ボルト群33bを設計締め付け力で締め
付ける。FIG. 3 shows a joint according to the present invention, which is a combination of a high-strength bolted joint and a welded joint using a high-strength bolt for a joint rib plate of a steel pipe and welding to the steel pipe. As shown in this drawing, a steel pipe joint rib plate 31 is sandwiched between attached steel plates 32, and a high-strength bolt group 33 in the row closest to the welded portion.
After tightening the high-strength bolt group 33a excluding the b, with the design tightening force, and tightening the high-strength bolt group 33b in the row closest to the welded portion with 2/3 to 1/4 of the design tightening force, the steel pipe 3
After the welding heat of No. 4 is performed and the welding heat is cooled, the high-strength bolt group 33b in the row closest to the welded portion is tightened by the design tightening force.
【0017】なお、図には示さないが、鋼管と梁の交差
部において鋼管に取り付けられる梁のH形断面の鋼部材
のウェブに高力ボルトを、該鋼管に溶接を用いた摩擦接
合高力ボルト継手と溶接継手との併用継手の場合にも適
用することができる。Although not shown in the figure, a high-strength bolt is applied to the web of the steel member having the H-shaped cross section of the beam attached to the steel pipe at the intersection of the steel pipe and the beam, and the steel pipe is welded to the high-strength joint by welding. The present invention can also be applied to a joint joint of a bolt joint and a weld joint.
【0018】(具体例)図4に示すような形状の摩擦接
合高力ボルト継手と溶接継手との併用継手について、弾
性変形状態から、弾性変形と局部的な微小すべりが混在
している状態を経て、主すべり状態に至るまでのすべり
挙動の解析を行った。なお、この解析方法に関する研究
論文としては、「摩擦接合継手のすべり問題および設計
への適用」都立大学博士号論文、平成3年発行、著者
長嶋文雄を挙げることができる。この図に示すように、
H形鋼(H588×300×12×20)41のウェブ
を添接鋼板(PL470×16×370)42で挟ん
で、 (a)すべての高力ボルト群43a、43bを設計締め
付け力(ボルト軸力19.6tf)で締め付けた後、溶
接を下フランジの溶接44、上フランジの溶接45の順
に行う場合 (b)溶接部に最も近い列の高力ボルト群43bを除く
高力ボルト群43aを設計締め付け力(ボルト軸力1
9.6tf)で締め付け、溶接部に最も近い列の高力ボ
ルト群43bを設計締め付け力の2/3(ボルト軸力1
3.1tf)で締め付け、フランジの溶接44、45を
行う場合 (c)溶接部に最も近い列の高力ボルト群を
除く高力ボルト群43aを設計締め付け力(ボルト軸力
19.6tf)で締め付け、溶接部に最も近い列の高力
ボルト群43bを設計締め付け力の1/4(ボルト軸力
4.9tf)で締め付け、フランジの溶接44、45を
行う場合の3ケースについて前記の解析手法で解析を行
った。それぞれのケースの解析結果を図5に示すが、こ
の図からわかるように(a)のケースでは母材の残留応
力は溶接部の近くで集中しており、その値は鋼材の許容
応力150MPaより大きい。また、高力ボルトの摩擦
力も、溶接部に最も近い高力ボルト群に集中して生じる
ために摩擦面ですべりを生じる(図5では、すべりが生
じた後の状態を示している)。したがって、(a)のケ
ースでは溶接部に最も近い列の高力ボルトを新しい高力
ボルトに交換する必要がある。一方、(b)及び(c)
のケースでは前述の残留応力の集中や高力ボルトの摩擦
力の集中がなく、溶接熱が冷めた後に溶接部に最も近い
高力ボルト群を設計締め付け力で締め付ければよいこと
がわかる。(Specific Example) In a joint joint of a friction-joined high-strength bolt joint and a welded joint having a shape as shown in FIG. 4, a state in which elastic deformation and local minute slip are mixed from an elastic deformation state. After that, the slip behavior up to the main slip condition was analyzed. In addition, as a research paper on this analysis method, "Slip Problem of Friction Welded Joint and Application to Design", Doctoral Dissertation of Tokyo Metropolitan University, published in 1991, author
Fumio Nagashima can be mentioned. As shown in this figure,
A web of an H-section steel (H588 × 300 × 12 × 20) 41 is sandwiched by an attached steel plate (PL470 × 16 × 370) 42. (a) All the high-strength bolt groups 43a and 43b are designed with a design tightening force (bolt shaft). When welding is performed in the order of the lower flange weld 44 and the upper flange weld 45 after tightening with a force of 19.6 tf) (b) The high-strength bolt group 43a except for the high-strength bolt group 43b in the row closest to the welded portion is removed. Design tightening force (bolt axial force 1
9.6tf), and tighten the high-strength bolt group 43b in the row closest to the welded portion to の of the design tightening force (bolt axial force 1).
3.1. Tf) Tightening and Flange Welding 44, 45 (c) The high-strength bolt group 43a excluding the high-strength bolt group in the row closest to the welded part is designed with the designed tightening force (bolt axial force 19.6tf). The above-mentioned analysis method is used for three cases in which the high-strength bolt group 43b in the row closest to the welded portion is tightened with 1 / of the designed tightening force (bolt axial force 4.9 tf) and the flanges 44 and 45 are welded. Was analyzed. The analysis results of each case are shown in FIG. 5. As can be seen from FIG. 5, in case (a), the residual stress of the base metal is concentrated near the welded portion, and the value is higher than the allowable stress of steel material of 150 MPa. large. Further, the frictional force of the high-strength bolt is also concentrated on the high-strength bolt group closest to the welded portion, so that a slip occurs on the friction surface (FIG. 5 shows a state after the slip has occurred). Therefore, in the case of (a), it is necessary to replace the high-strength bolt in the row closest to the weld with a new high-strength bolt. On the other hand, (b) and (c)
In the case (1), there is no concentration of the residual stress and no concentration of the frictional force of the high-strength bolt, and it is understood that the high-strength bolt group closest to the welded portion may be tightened with the designed tightening force after the welding heat is cooled.
【0019】本発明は、前記実施例のほか、 (1)添接鋼板を1枚として摩擦接合面を1面とした1
面添接継手の場合 (2)また、図では示さないが、H形、I形、Π形及び
箱形等の断面を持つ主桁に、別の断面を持つ横桁やブラ
ケット等を取り付ける場合 (3)さらに、添接鋼板を用いないで母材同士を直接摩
擦接合継手で結合する場合にも本発明を適用することが
できる。According to the present invention, in addition to the above-described embodiment, (1) one friction-bonded surface having one contacted steel sheet and
In the case of a surface-attached joint (2) Although not shown in the figure, when attaching a horizontal girder or bracket with another cross section to a main girder having a cross section such as H type, I type, Π type or box type (3) Further, the present invention can be applied to a case where base materials are directly connected to each other by a friction welding joint without using an impregnated steel plate.
【0020】なお、本発明は前記実施例に限定されるも
のではなく、本発明の趣旨に基づき種々の変形が可能で
あり、それらを本発明の範囲から排除するものではな
い。It should be noted that the present invention is not limited to the above-described embodiment, and various modifications are possible based on the gist of the present invention, and they are not excluded from the scope of the present invention.
【0021】[0021]
【発明の効果】以上、説明したように、本発明によれ
ば、橋梁や建築物等の鋼構造物の鋼部材に用いる摩擦接
合高力ボルト継手と溶接継手との併用継手において、継
手の一部に摩擦接合高力ボルト継手を施した後に、残り
の部分に溶接継手を施し、摩擦接合高力ボルト継手部の
耐力と溶接継手部の耐力とを合成させた耐力で継手全体
に作用する力に対抗させる構造の継手において、高力ボ
ルトのうち溶接部に最も近い高力ボルト群の締め付け力
を設計締め付け力の2/3から1/4としたので、溶接
の熱による母材の変形を拘束するために生じる部材内部
の残留応力を減少することができた。As described above, according to the present invention, in a joint joint of a friction joint high strength bolt joint and a weld joint used for steel members of a steel structure such as a bridge or a building, one of the joints is provided. After applying a friction-joined high-strength bolted joint to the joint, the remaining joints are welded, and the force acting on the entire joint with the combined strength of the strength of the friction-jointed high-strength bolted joint and the strength of the welded joint In the joint with a structure that is opposed to the above, the tightening force of the high-strength bolt group closest to the welded portion among the high-strength bolts is set to 2/3 to 1/4 of the design tightening force, so that the deformation of the base material due to the heat of welding is reduced. The residual stress inside the member caused by the restraint was reduced.
【図1】本発明を、H形断面の鋼部材のウェブに摩擦接
合高力ボルト接合を、該H形断面の鋼部材のフランジに
溶接継手を用いた摩擦接合高力ボルト継手と溶接継手と
の併用継手の図である。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a diagram showing a friction-joined high-strength bolted joint and a welded joint using a welded joint on a flange of a steel member having an H-shaped section, FIG.
【図2】本発明を、H形断面の鋼部材のウェブと下フラ
ンジに摩擦接合高力ボルト接合を、該H形断面の鋼部材
の上フランジに溶接継手を用いた摩擦接合高力ボルト継
手と溶接継手との併用継手の図である。FIG. 2 shows a friction-joined high-strength bolted joint using a friction-joined high-strength bolt joint to a web and a lower flange of a steel member having an H-shaped section, and a welded joint to an upper flange of the steel member having an H-shaped section. It is a figure of a joint used together with a welding joint.
【図3】本発明を、鋼管の継手部リブプレートに摩擦接
合高力ボルト接合を、該鋼管に溶接継手を用いた摩擦接
合高力ボルト継手と溶接継手との併用継手の図である。FIG. 3 is a view showing a joint joint of a friction-joined high-strength bolted joint and a welded joint using the present invention by friction-joining high-strength bolt joints to a joint rib plate of a steel pipe and using a welded joint to the steel pipe;
【図4】本発明の具体例を示す、H形断面の鋼部材のウ
ェブに摩擦接合高力ボルト接合を、該H形断面の鋼部材
のフランジに溶接継手を用いた摩擦接合高力ボルト継手
と溶接継手との併用継手の解析モデルの形状を示す図で
ある。FIG. 4 shows a concrete example of the present invention, wherein a high-strength bolted joint is formed by friction welding a high-strength bolted joint to a web of a steel member having an H-shaped cross section and a welded joint is formed to a flange of the steel member having the H-shaped cross section. FIG. 4 is a view showing a shape of an analysis model of a joint used in combination with a welding joint.
【図5】前記の本発明の具体例について、本発明の効果
を示した説明図である。FIG. 5 is an explanatory diagram showing the effect of the present invention with respect to the specific example of the present invention.
【図6】摩擦接合高力ボルト継手、溶接継手および摩擦
接合高力ボルト継手と溶接継手との併用継手の弾性変形
性能を示した説明図である。FIG. 6 is an explanatory diagram showing the elastic deformation performance of a friction-joined high-strength bolt joint, a welded joint, and a joint joint of a friction-joined high-strength bolt joint and a welded joint.
11、11’、21、21’ H形断面の鋼部材のフ
ランジ 12、22 H形断面の鋼部材のウェブ 13、23、24、24’、32、42 添接鋼板 15a、15b、26a、26b、26c、33a、3
3b、43a、43b高力ボルト群 14、14’、2
5、35、44、45 溶接 31 鋼管の継手部リブプレート 34 鋼管 41 H形鋼11, 11 ', 21, 21' Flange of steel member having H-shaped section 12, 22 Web of steel member having H-shaped section 13, 23, 24, 24 ', 32, 42 Spliced steel plate 15a, 15b, 26a, 26b , 26c, 33a, 3
3b, 43a, 43b high-strength bolt group 14, 14 ', 2
5, 35, 44, 45 Welding 31 Steel pipe joint rib plate 34 Steel pipe 41 H-section steel
Claims (1)
合高力ボルト継手を施した後に、継手の残りの部分に溶
接継手を施す構造の併用継手において、 (1)該摩擦接合高力ボルト継手部のうち該溶接継手部
に最も近い列の高力ボルト群を設計締め付け力の2/3
から1/4で締め付けて、 (2)他の箇所の高力ボルトは設計締め付け力で締め付
けて、 (3)該溶接継手部を溶接して、 (4)該溶接継手部の溶接熱が冷めた後に、該溶接継手
部に最も近い列の高力ボルト群を設計締め付け力で締め
付けることを特徴とする摩擦接合高力ボルト継手と溶接
継手との併用継手の施工方法。1. A combined joint having a structure in which a high strength bolt joint is applied to a part of a joint between a steel structure and a steel member and then a weld joint is applied to the remaining part of the joint. Among the high-strength bolted joints, the high-strength bolt group in the row closest to the welded joint is 部 of the design tightening force.
(2) Tighten the high-strength bolts at other locations with the design tightening force. (3) Weld the weld joint. (4) Cool the welding heat of the weld joint. And then tightening a group of high-strength bolts in the row closest to the welded joint with a designed tightening force.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18224493A JP2708698B2 (en) | 1993-06-29 | 1993-06-29 | Construction method of combined joint of friction joint high strength bolt joint and weld joint |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18224493A JP2708698B2 (en) | 1993-06-29 | 1993-06-29 | Construction method of combined joint of friction joint high strength bolt joint and weld joint |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0782800A JPH0782800A (en) | 1995-03-28 |
JP2708698B2 true JP2708698B2 (en) | 1998-02-04 |
Family
ID=16114871
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18224493A Expired - Lifetime JP2708698B2 (en) | 1993-06-29 | 1993-06-29 | Construction method of combined joint of friction joint high strength bolt joint and weld joint |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2708698B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006231338A (en) * | 2005-02-22 | 2006-09-07 | Ishikawajima Harima Heavy Ind Co Ltd | Repairing method and repairing structure of rivet joint |
JP5230085B2 (en) * | 2006-08-21 | 2013-07-10 | 株式会社Ihiインフラシステム | Assembling method of structure |
CN106193622B (en) * | 2016-07-29 | 2018-04-10 | 中国一冶集团有限公司 | H profile steel beam docks node locating installation method |
-
1993
- 1993-06-29 JP JP18224493A patent/JP2708698B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH0782800A (en) | 1995-03-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Tamboli | Handbook of structural steel connection design and details | |
JP3858480B2 (en) | Splice plate and beam joint structure | |
Fisher et al. | Distortion-induced fatigue cracking of bridge details with web gaps | |
JP2003020618A (en) | Existing bridge reinforcing method, and reinforced existing bridge | |
KR20040020444A (en) | Column-Beam Connection Detail and Construction Method for the Steel Structure | |
JP2708698B2 (en) | Construction method of combined joint of friction joint high strength bolt joint and weld joint | |
JP4978444B2 (en) | Method for adjusting gaps in steel plates for seismic reinforcement | |
JPH06146405A (en) | Beam member connecting method | |
JP6512564B1 (en) | Sliding seismic isolation bearing structure | |
JP5298774B2 (en) | Seismic structure of viaduct | |
JP3951793B2 (en) | Steel tube column connection structure | |
JP2000288726A (en) | Structure for repairing and/or reinforcing crack from welded filet part of sole plate in steel bridge | |
Feier et al. | Deflection and precambering study of VFT beams in the welded joints | |
JPH08302619A (en) | Joint structure for composite members | |
JPH08144368A (en) | Structure and method for connecting end plate type steel frame structure | |
JPH11280023A (en) | Earthquake resistant beam of rigid frame bridge | |
RU2132433C1 (en) | Method for strengthening of supporting unit in girder structure | |
CN219711027U (en) | Truss assembly jig frame | |
JPH10131131A (en) | Method for reinforcing rivet connection beam | |
Tsai | Design of steel beam-to-box column connections for seismic load | |
JP3883659B2 (en) | Box girder support | |
JPH11280022A (en) | Earthquake resistant beam of rigid frame bridge | |
JP2007100383A (en) | Divided structure of large steel h beam, and method of assembling the same | |
JPH09184303A (en) | Lining steel plate and reinforcing method for existing columnar body | |
Thatcher | Horizontally Curved Steel Girders; Fabrication and Design |