JPH02266091A - Vertical shaft mechanism for shield machine starting section, its constructing method, and starting and reaching method of shield machine using its mechanism - Google Patents

Vertical shaft mechanism for shield machine starting section, its constructing method, and starting and reaching method of shield machine using its mechanism

Info

Publication number
JPH02266091A
JPH02266091A JP8590089A JP8590089A JPH02266091A JP H02266091 A JPH02266091 A JP H02266091A JP 8590089 A JP8590089 A JP 8590089A JP 8590089 A JP8590089 A JP 8590089A JP H02266091 A JPH02266091 A JP H02266091A
Authority
JP
Japan
Prior art keywords
shaft
core material
shield machine
starting
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8590089A
Other languages
Japanese (ja)
Other versions
JP2681511B2 (en
Inventor
Tetsushi Sonoda
園田 徹士
Yasuaki Takenouchi
康昭 竹之内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP8590089A priority Critical patent/JP2681511B2/en
Publication of JPH02266091A publication Critical patent/JPH02266091A/en
Application granted granted Critical
Publication of JP2681511B2 publication Critical patent/JP2681511B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To enable a shield machine to start and reach without requiring the improvement of ground by setting vertical shaft retaining core material for surrounding a vertical shaft continuously, and by erecting the core material in an underground continuous wall, to form a shield machine starting notched-section. CONSTITUTION:Vertical shaft retaining core material 2 for surrounding a vertical shaft for setting a shield machine 20, continuously is set, and is erected in an underground continuous wall 1 for starting the shield machine 20, and a notched section 12 for starting the shield machine 20 is formed. After that, on the periphery of the notched section 12, a protective internal wall for starting the shield machine 20 is constructed, and in the underground continuous wall 1 outside the vertical shaft retaining core material 2, starting retaining core material 3 with the surface processed for drawing is erected to cover the notched section 12. Besides, the reaching vertical shaft of the same mechanism is constructed, and from the underground continuous wall 1, the reaching retaining core material is drawn onto the notched section 12, and the shield machine 20 can be taken in.

Description

【発明の詳細な説明】 〈産業」二の利用分野〉 この発明は、シールドトンネル工事におけるシールド機
発進部の立坑構造とその施工法、及びその構造を利用し
たシールド機の発進・到達方法に関する。
[Detailed Description of the Invention] <Industry> 2 Field of Application The present invention relates to a vertical shaft structure of a shield machine launch section in shield tunnel construction, a construction method thereof, and a method for launching and reaching a shield machine using the structure.

〈従来の技術〉 今までに知られているシールド機発進部の立坑構造とし
ては、土留壁を鋼矢板、地中壁等で構築し、シールド発
進(到達)部を地上からボーリングして薬液注入などに
より、地盤改良を行ない、立坑を掘削して、シールド機
発進用のエントランスを設置し、発進部の土留壁を撤去
してシール1く機を発進し、到達は地盤改良された到達
部にシールド機を到達させ土留壁を撤去し貫通させる地
盤改良工法がある。
<Prior art> The shaft structure of the shield machine launch section known so far consists of constructing earth retaining walls with steel sheet piles, underground walls, etc., and boring the shield launch (arrival) section from the ground and injecting chemical liquid. By doing so, we improved the ground, excavated a shaft, installed an entrance for launching the shield machine, removed the earth retaining wall at the launch area, launched the seal machine, and reached the area where the ground had been improved. There is a ground improvement method that involves using a shield machine to remove and penetrate the retaining wall.

また、土留壁を鋼矢板、地中壁等で構築し、シールド発
進(到達)部に地上および立坑内より凍結管を設置し冷
媒を送ることにより地盤を凍結させ、シールド発進部土
留壁にエン[〜ランスを設置し土留壁を撤去してシール
ド機を発進(到達)させる凍結工法がある。
In addition, the earth retaining wall is constructed with steel sheet piles, underground walls, etc., and freezing pipes are installed from the ground and inside the shaft at the shield launch (arrival) part and the ground is frozen by sending refrigerant. [~There is a freezing method in which a lance is installed, the retaining wall is removed, and the shield machine is launched (reached).

さらに、鋼矢板、地中壁等で土留壁を構築して立坑を掘
削し、立坑内にシールド機を搬入してから、立坑上部に
圧気床板を設置し、土留壁にエントランスを設置してか
ら発進部の土圧・水圧と同等の圧気を立坑内に加えて、
土留壁を撤去し、シールド機を発進させる立坑圧気工法
が用いられている。
Furthermore, a retaining wall is constructed using steel sheet piles, underground walls, etc., a shaft is excavated, a shield machine is brought into the shaft, a pressure plate is installed at the top of the shaft, and an entrance is installed on the retaining wall. Adding pressure equal to the earth pressure and water pressure in the starting area into the shaft,
The vertical shaft pressurized construction method is used, which involves removing the earth retaining wall and launching a shield machine.

〈発明が解決しようとする課題〉 しかしながら、上記従来工法は、工区の地盤の状況に応
じてそれぞれ使い分けされ、それぞれの利点はあるもの
の、都市部などにおける工域が狭隘な場所での立坑の構
築に限度がある場合、及び工期が短期間に限られている
場合には必ずしも十分なものとは云えない。
<Problem to be solved by the invention> However, the above conventional construction methods are used depending on the ground condition of the construction area, and although each has its advantages, it is difficult to construct a shaft in a place where the construction area is narrow, such as in an urban area. This may not necessarily be sufficient if there is a limit to the amount of time available or if the construction period is limited to a short period of time.

特に、上記地盤改良工法は以下の問題点がある。In particular, the above ground improvement method has the following problems.

1、立坑掘削前に地盤改良を行なう期間が必要。1. A period of ground improvement is required before shaft excavation.

2、地盤改良後の掘削に伴ない土留壁が変形し、土留壁
と地盤改良地山が分離して、シールド発進時の出水等の
事故が多い。
2. Due to the excavation after ground improvement, the earth retaining wall becomes deformed, and the earth retaining wall and the soil improved ground become separated, resulting in many accidents such as water leakage during shield launch.

3゜地盤改良に場所と多額の費用を要する。3゜ Ground improvement requires space and a large amount of money.

また、上記凍結工法の問題点としては、1、凍結管の設
置や、地盤の凍結に長期間を要する。
In addition, the problems with the above-mentioned freezing method include: 1. It takes a long time to install freezing pipes and freeze the ground.

2、地盤の凍結(溶解)により大きな地盤沈下が発生す
る。
2. Large ground subsidence occurs due to freezing (melting) of the ground.

3、地盤改良に多額の費用を要する。3. Ground improvement requires a large amount of money.

ことがある。Sometimes.

さらに、圧気工法の問題点には、 1、高圧下の作業となり安全性が悪い。Furthermore, the problems with the pressure method include: 1. Work is under high pressure, which is unsafe.

2、圧気設備に多額の費用を要する。2. A large amount of money is required for pressurized air equipment.

3、圧気設備など発進段取りに長期間を要する。3. It takes a long time to set up the start-up, such as using pressurized air equipment.

等が考えられる。etc. are possible.

ト なお、上記従来工法の他に二重鋼矢板工法が知られてい
るが、この工法は、鋼矢板を利用してシールド機の発進
時に鋼矢板を引抜いて掘削を開始し、軟弱地盤など地盤
条件や施工深さおよび被圧水などの条件下においてその
効果が発揮でき、適応範囲が限定されるというものの他
に、立坑の内壁全てを強固な連壁にし、かつシールド機
の発進部の地盤を改良する点において、基本的には先述
した地盤改良工法と変りなく、いぜん地盤改良のための
工期の長期化やある程度の場所的な制約が必要であると
いう問題点があった。
In addition to the conventional method mentioned above, the double steel sheet pile method is also known, but this method uses steel sheet piles and starts excavation by pulling out the steel sheet piles when the shield machine starts, and is used to dig into soft ground or other ground. In addition to being effective under certain conditions, construction depth, and pressurized water conditions, and having a limited scope of application, all the inner walls of the shaft should be made into solid continuous walls, and the ground of the shield machine launch area should be In terms of improving the ground, it is basically the same as the ground improvement method described above, but there are still problems in that the construction period for ground improvement is prolonged and a certain degree of location restrictions are required.

この発明は、上記問題点を解消すべくなされたものであ
り、その第1の目的は地盤が弱く地下水か侵入し易いシ
ールド機発進部において地盤改良を行なうことなく今ま
でより強固な地下連続壁を、まだ発進部以外は簡易な立
坑の土留を構築して、限られた立坑の平面積内で短期間
でシールド発進部の立坑構造を得んとしたものである。
This invention was made to solve the above-mentioned problems, and its first purpose is to create a stronger underground continuous wall than before without the need for ground improvement in the shield machine launch area where the ground is weak and underground water easily invades. The aim was to construct a simple earth retaining shaft for the shaft except for the starting part, and to obtain the shaft structure of the shield starting part in a short period of time within the limited planar area of the shaft.

この発明の他の目的は、場合によって、立坑の埋戻しを
容易にした立坑の施工法を得んとするものである。
Another object of the present invention is to provide a method for constructing a shaft that facilitates the backfilling of the shaft in some cases.

この発明におけるさらに別の目的は、立坑の構造を簡単
にしてシール1く機の発進と到達が容易なシールド機の
発進・到達方法を提供せんとする。
Still another object of the present invention is to provide a method for starting and reaching a shield machine by simplifying the structure of a shaft and making it easy for the seal machine to start and reach.

〈課題を解決するための手段〉 この発明は、」二記問題点に鑑みてなされたものであり
、その要旨はシールド機を設置する立坑と、この立坑を
連続して囲繞する立坑土留芯材とから成り、この立坑土
留芯材をシールド機発進側の地下連続壁中に建込むと共
に、シールド機発進用切欠部を形成し、切欠部の周囲に
はシールド機発進用保護内壁を構築し、前記立坑土留芯
材の外側の地下連続壁中には表面に引抜き加工を施した
発進土類留芯材を前記切欠部を覆うように建込んでなる
シールド機発進部の立坑構造にある。ここで上記立坑土
留芯材は柱列式地下連続工法や壁式地下連続工法などに
よる地下連続壁中に建込めた鋼矢板、■杭、鉄筋コンク
リートなどを示し、また上記発進土類留芯材としては、
例えば鋼矢板やH杭などが考えられる。
<Means for Solving the Problems> This invention has been made in view of the problems mentioned in 2.The gist of the invention is to provide a shaft in which a shield machine is installed, and a shaft earth retaining core that continuously surrounds the shaft. This shaft retaining core material is built into the underground continuous wall on the shield machine launch side, and a notch for shield machine launch is formed, and a protective inner wall for shield machine launch is constructed around the notch. In the shaft structure of the shield machine starting part, a starting earth retaining core material whose surface has been subjected to drawing processing is installed in the underground continuous wall outside the shaft earth retaining core material so as to cover the notch. Here, the above-mentioned shaft earth retaining core material refers to steel sheet piles, piles, reinforced concrete, etc. built into the underground continuous wall by column-type underground continuous construction method or wall-type underground continuous construction method, etc. Also, the above-mentioned starting earth retaining core material teeth,
For example, steel sheet piles and H piles can be considered.

また、他の発明の要旨は立坑構造を発進側と到達側に用
い、それぞれの立坑内にシールド機の反力壁と発進用保
護内壁の内周に沿って設けたシール材付き筒状チャンバ
を設け、立坑の発進側に地山を掘削していくシールド機
を設置し、発進土類留芯材を地下連続壁がら立坑芯材の
切欠部上に引抜き、シールド前面の芯材のない地下連続
壁の一部を掘削しながら発進して目標地盤を掘進じ、到
達側の発進土類留芯材に相当する到達土留芯材を地下連
続壁から立坑土留芯材の切欠部上に引抜いてシールド機
を所定圧の人工地盤を形成した到達側の立坑内に取込み
到達するようにしたシールIく機の発進・到達方法にあ
る。
Another gist of the invention is that a shaft structure is used on the starting side and the reaching side, and a cylindrical chamber with a sealing material is provided in each shaft along the inner periphery of the reaction wall of the shield machine and the protective inner wall for starting. A shield machine is installed to excavate the ground on the starting side of the shaft, and the starting earth retaining core material is pulled out from the underground continuous wall onto the notch of the shaft core material, and the underground continuity without core material is installed in front of the shield. Start while excavating a part of the wall, dig into the target ground, pull out the reaching earth retaining core material corresponding to the starting earth retaining core material from the underground continuous wall onto the notch of the shaft earth retaining core material, and shield it. This is a method of starting and reaching a Seal I machine, in which the machine is taken into a shaft on the reaching side where an artificial ground with a predetermined pressure is formed.

さらに、その他の発明は予定した立坑区域のシールド機
発進側に、地下連続壁工法により1表面づ1抜き加工し
た立坑土留芯材と発進土類留芯材との二重芯材を建込ん
で地下連続壁を構築する工程と、この地下連続壁中の立
坑土留芯材と連続して他の立坑内面となる立坑土留芯材
としての立坑土留矢板を打込むと共に、囲繞した立坑土
留矢板内部を掘削する工程と、前記地下連続壁のシール
ド機の発進坑口周囲に保護内壁を打設すると共に、保護
内壁の内側にあたる前記立坑土留芯材に切欠部を形成す
る工程とからなる立坑発進側の地盤改良を行なわないシ
ールド発進部の立坑構造の施工法を要旨とする。
Furthermore, another invention is to erect a double core material of a shaft earth retaining core material and a starting earth retainer core material, which are punched one by one on each surface using the underground continuous wall construction method, on the shield machine launch side of the planned shaft area. The process of constructing an underground continuous wall, and driving the shaft earth retaining sheet pile as a shaft earth retaining core material that is continuous with the shaft earth retaining core material in this underground continuous wall and forming the inner surface of another shaft, and the inside of the enclosed shaft earth retaining sheet pile. The ground on the shaft starting side, which consists of the step of excavating, and the step of driving a protective inner wall around the starting shaft entrance of the shield machine of the underground continuous wall, and forming a notch in the shaft earth retaining core material that is inside the protective inner wall. The gist is the construction method for the vertical shaft structure of the shield launch section without any modification.

〈作用〉 この発明の立坑構造によれば、シールド機の発進部以外
は、通常の地下土留芯材を囲繞して、土留めをし、発進
部ば連壁中の発進土類留芯材を一体に建込んでシールl
く発進前における発進部とそれ外の土留を十分にすると
同時に、発進時において発進土類留芯材を引抜いてもシ
ールド切羽が地下連続壁に圧接することによって土庄を
支えることができ、しかもシールド機を掘進しても立坑
土留芯材の切欠部において、掘削するのでスムーズに発
進できるようにしている。
<Function> According to the shaft structure of the present invention, except for the starting part of the shield machine, a normal underground earth retaining core is surrounded and earth-retained, and in the starting part, the starting earth retaining core in the continuous wall is Built in one piece and sealed
At the same time, the shield face can be pressed against the underground continuous wall to support the tonosho even if the starting earth retaining core material is pulled out at the time of starting. Even when the machine excavates, it excavates at the notch in the shaft retaining core material, so it can start smoothly.

また、立坑構造の発進・到達方法は、発進側と到達側と
の地下連続壁中に立坑土留芯材と発進土類留芯材とを二
重に建込んだ立坑を用い、シールド機を発進用保護内壁
の筒状チャンバにセラ1〜してから発進土類留芯材を引
抜いてシールド切羽と発進部地盤の圧力とを均衡させ、
シールド機を掘進して予定のトンネルを覆工し、到達側
の到達土留芯材を引抜き立坑に土庄や水圧など所定圧を
掛けた人口地盤中に取込むようにしている。
In addition, the method for starting and reaching the shaft structure is to use a shaft in which the shaft earth retaining core material and the starting earth retaining core material are built double in the underground continuous wall between the starting side and the reaching side, and the shield machine is launched. After filling the cylindrical chamber of the protective inner wall, the starting earth anchoring material is pulled out to balance the pressure of the shield face and the starting part ground,
A shield machine is used to excavate and line the planned tunnel, and the earth retaining core material on the reaching side is pulled out and taken into the vertical shaft into the artificial ground where a predetermined pressure, such as water pressure, is applied.

さらに、立坑の施工は発進部以外は立坑土留矢板を予定
立坑の面積に沿って地中に打ち込み、矢板内を腹おこし
や切梁などの公知の手段によって立坑を掘削し、前記発
進側には発進部以外の立坑土留矢板と、発進土留矢板と
を同時に地下連壁中に建込んで二重芯材を簡単に仕上げ
る。また、前記土留矢板の発進部のシールド機の発進坑
口(エントランス)周囲には保護内壁を打設すると共に
、内壁内の土留矢板を切欠いてシールドの発進を容易に
する。このようにして、通常の立坑の構造の他に、地盤
を強固にしなければならない発進側を地下連続壁中に発
進土類留芯材を建込んで補強し、シールド発進時には掘
進に邪魔にならないように引抜くことができる。
Furthermore, in the construction of the shaft, except for the starting part, the shaft retaining sheet piles are driven into the ground along the area of the planned shaft, and the shaft is excavated inside the sheet piles by known means such as raising the belly or cutting beams. The shaft retaining sheet pile other than the starting part and the starting retaining sheet pile are simultaneously built in an underground continuous wall to easily finish a double core material. In addition, a protective inner wall is installed around the shield machine launch portal (entrance) of the starting portion of the earth retaining sheet pile, and the earth retaining sheet pile is cut out in the inner wall to facilitate the shield's launch. In this way, in addition to the normal shaft structure, the starting side, where the ground must be strengthened, is reinforced by erecting starting earth retaining materials in the underground continuous wall, so that it does not get in the way of excavation during shield starting. It can be pulled out like this.

〈実施例〉 以下にこの発明の一実施例を説明する。<Example> An embodiment of the present invention will be described below.

第1図はこの発明のシールド機発進時の立坑構造の要部
を示すものであり、これを図に従って説明すると、1は
シールド発進側のソイルモルタルルを使用した柱列式又
は泥水固化した型式などの地下連続壁であり、この連続
壁中には立坑土留芯材としての内側土留矢板2とこれか
ら所定間隔を置いた発進土類留芯材としての外側土留矢
板3が建込んでいる。そしてこの地下連続壁1の外部は
地盤改良がされていない地盤4であって、図示していな
いが前記内側土留矢板2に継手等で接続した発進側以外
の3壁面にも土留矢板2があり、これらが腹おこしや切
梁によって立坑を構築している。
Figure 1 shows the main part of the shaft structure when the shield machine of this invention is launched.This will be explained according to the diagram.1 shows the column type using soil mortar on the shield launch side or the type with solidified mud water. This continuous wall is an underground continuous wall, and in this continuous wall, there are built an inner earth retaining sheet pile 2 as a shaft earth retaining core material and an outer earth retaining sheet pile 3 as a starting earth retaining core material placed at a predetermined interval from the inner earth retaining sheet pile 2. The outside of this underground continuous wall 1 is ground 4 that has not been improved, and although not shown, there are retaining sheet piles 2 on three wall surfaces other than the starting side that are connected to the inner retaining sheet piles 2 with joints, etc. , These are used to construct vertical shafts using sills and struts.

5は上記のように形成した立坑の一部壁面に接するよう
に設けられた前後にフランジ部5a、5bを有する円筒
チャンバで、全体として筒状の鋼材からなり、この円筒
チャンバの設置後に、これの外周に、地中壁1に内接す
るように内壁6が打設される。なお、上記円筒チャンバ
5の中央付近と後端部付近の内側には、所定幅のリング
状弾性の第1−のシール材6と第2のシール材7とが固
着され、第2のシール材7はヒンジ式のシール押えなど
でその内端部が前方に傾斜するようになっている。8は
泥水タンク9からの圧力調整パイプであり、バルブ10
を介して泥水・グラウト供給パイプ11に接続し、これ
の出水端が円筒チャンバ5の上下から内部に開口して、
シールド機20の前面と内側土留矢板2にシールド機発
進用として円形に切欠いた切欠部12間に泥水が圧入さ
れるように配設している。この泥水・グラウI・供給パ
イプ11は、バルブ13を介して途中から、グラウト注
入パイプ14を接続し、後述するように、シールド機2
0により地下連続壁1を貫通後にセグメント背面の空隙
部にグラウトを注入するパイプとして利用するものであ
る。また、15は裏込注入用パイプで、これの出口がバ
ルブ16を介して円筒チャンバ2とシール1−機20の
スキンプレート17間において90°ごとの間隔で室内
にそれぞれ開口するように設けられている。20はこの
ような円筒チャンバ2内に設置されるシールド機であり
、これの発進に当っては、カッタービット18の先端を
圧接するとともに、シールド機20のスキンプレート]
7と円筒チャンバ5ならびにシール材6および7で囲ま
れる空間19に裏込材などによるシールを行なう。さら
に、必要に応じてシールド機20の前面に前記泥水タン
ク9からの泥水を満たす。この場合圧力調整パイプ8側
のバルブ10を開いて泥水タンク9の水位を設定泥水圧
に保持して地山の圧力に対抗させることができる。シー
ルド機20に対向する部位の地下連続壁1中の内側土留
矢板2を、シールド機20の掘削と貫入を可能にするだ
けの大きさで切欠いて切欠部12を形成し、続いて表面
を引抜き容易にワックス加工した内側土留矢板2を上向
き(矢印)に引抜いてシールド機20で掘削しながら発
進させる。
Reference numeral 5 denotes a cylindrical chamber having front and rear flanges 5a and 5b, which is provided so as to be in contact with a part of the wall surface of the shaft formed as described above, and is made of a cylindrical steel material as a whole. An inner wall 6 is cast around the outer periphery of the underground wall 1 so as to be inscribed in the underground wall 1. Note that a ring-shaped elastic first sealing material 6 and a second sealing material 7 having a predetermined width are fixed to the inside of the cylindrical chamber 5 near the center and near the rear end. Reference numeral 7 is a hinge type seal holder or the like, and the inner end thereof is inclined forward. 8 is a pressure adjustment pipe from the muddy water tank 9, and a valve 10
It is connected to the muddy water/grout supply pipe 11 through the pipe, and the water outlet end thereof opens into the inside from the top and bottom of the cylindrical chamber 5.
The front face of the shield machine 20 and the inner earth retaining sheet pile 2 are arranged so that muddy water is press-fitted between circular notches 12 for starting the shield machine. This muddy water/grau I/supply pipe 11 is connected to a grout injection pipe 14 from the middle via a valve 13, and as described later, the shield machine 2
This pipe is used as a pipe for injecting grout into the gap at the back of the segment after penetrating the underground continuous wall 1. Reference numeral 15 denotes a backfilling injection pipe, the outlet of which opens into the chamber at intervals of 90 degrees between the cylindrical chamber 2 and the skin plate 17 of the seal 1-machine 20 through valves 16. ing. 20 is a shield machine installed in such a cylindrical chamber 2, and when starting this, the tip of the cutter bit 18 is pressed and the skin plate of the shield machine 20 is pressed.]
A space 19 surrounded by the cylindrical chamber 7 and the sealing materials 6 and 7 is sealed with a backing material or the like. Furthermore, if necessary, the front surface of the shield machine 20 is filled with muddy water from the muddy water tank 9. In this case, by opening the valve 10 on the pressure regulating pipe 8 side, the water level in the muddy water tank 9 can be maintained at the set muddy water pressure to counteract the pressure of the ground. The inner earth retaining sheet pile 2 in the underground continuous wall 1 at the part facing the shielding machine 20 is cut out to a size that allows the shielding machine 20 to excavate and penetrate, forming a notch 12, and then the surface is pulled out. The inner earth retaining sheet pile 2 which has been easily waxed is pulled out upward (indicated by an arrow) and started while being excavated by a shield machine 20.

なお、芯材の引抜きに際しては、あらかじめ芯材に配設
した注入パイプ(図示せず)により、芯材先端に発生す
るボイド部に必要に応じてグラウト材の注入を行う。シ
ールド機20が地下連続壁1を掘削・開口して円筒チャ
ンバ5内をI−ンネル覆工用のセグメントで置き換えら
れた時点で泥水・グラウI・供給パイプ〕−1からグラ
ウト注入を行い、確実な止水を行う。
In addition, when pulling out the core material, grout material is injected into the void portion generated at the tip of the core material as necessary using an injection pipe (not shown) provided in the core material in advance. When the shielding machine 20 excavates and opens the underground continuous wall 1 and replaces the inside of the cylindrical chamber 5 with the segment for I-channel lining, it injects grout from the muddy water, grout I, and supply pipe]-1 to ensure a reliable flow. Make sure to turn off the water.

つぎに、この発明である上記第1図におけるシールド機
を立坑に設置するまでのシールド機発進部の立坑構造と
その施工法を第2図乃至第7図により説明し、この立坑
構造を用いたシールド機の発進・到達方法を第7図乃至
第1−2図により順を追って説明する。
Next, the shaft structure of the shield machine starting part and its construction method until the shield machine of the present invention shown in Fig. 1 is installed in the shaft will be explained with reference to Figs. The method of starting and arriving at the shield machine will be explained step by step with reference to FIGS. 7 to 1-2.

↓征隻林建込皿 まず、初めに、予定した立坑区域21のうちシールド機
20の発進側を地盤の性状に応じて、型式地下連続壁工
法により、後述する立坑土留芯材と発進土類留芯材であ
る土留矢板を例えば40印の間隔を置いて二重芯材とし
て建込めるように仮設土留構築ラインに沿って地下連続
壁22を構築する(第2図a、b)。掘削は、泥水によ
り立坑壁を保護するようにする。
↓Seisenbayashi construction plate First, in the planned shaft area 21, the starting side of the shield machine 20 is constructed using the type underground continuous wall construction method to construct the shaft retaining core material and starting earth, which will be described later. The underground continuous wall 22 is constructed along the temporary earth retaining construction line so that the retaining sheet piles, which are retaining core materials, can be built as double core materials at intervals of, for example, 40 marks (FIGS. 2a and 2b). During excavation, the shaft walls will be protected by muddy water.

なお、芯材としてH鋼を用いることもできる。Note that H steel can also be used as the core material.

土留芯材体 み び 水 ついで、泥水の充填した連続壁22に、以下に述べるよ
うに事前加工された立坑土留芯材23と発進土類留芯材
2/Uとをそれぞれ内外二重に精度良く建込む。精度良
く建込む理由は、立坑の土留めや矢板の打撃による精度
劣化を防止し、発進土類留芯材24に表面加工したワッ
クスを保護するためである。泥水は、壁式地下連続工法
のためセメン1〜により自然固化するが、泥水同化の代
わりにソイルモルタルの打込み又は薬液注入を行なって
もよい(第3図a、b)。
Next, the shaft earth retaining core material 23 and the starting earth retaining core material 2/U, which have been pre-processed as described below, are placed on the continuous wall 22 filled with muddy water with double precision inside and outside. Build well. The reason for building with high precision is to prevent precision deterioration due to the impact of the earth retaining of the shaft and the sheet pile, and to protect the wax surface-treated on the starting earth retaining material 24. Mud water is naturally solidified with cement 1 because of the continuous wall-type underground construction method, but soil mortar or chemical injection may be performed instead of mud assimilation (Fig. 3 a, b).

上記の芯材の事前加工とは、外側の矢板である発進土類
留芯材24には後に述べる引抜きを容易にするため全表
面をワックス加工し、内側の立坑土留矢板23には上記
発進土留矢板24を引抜く際に矢板同志の接触による引
抜き抵抗を小さくし、外部から後述する立坑土留矢板2
3の切欠部からの補水防止のために、建込み方向にパイ
プスペーサー25を溶接することである。
The above-mentioned pre-processing of the core material means that the entire surface of the starting earth retaining core material 24, which is the outer sheet pile, is waxed to facilitate the pulling out described later, and the inner shaft retaining sheet pile 23 is waxed. When pulling out the sheet pile 24, the pulling resistance due to contact between the sheet piles is reduced, and the shaft retaining sheet pile 2, which will be described later, is removed from the outside.
In order to prevent water replenishment from the notch 3, a pipe spacer 25 is welded in the construction direction.

土    工6了 び立 地下連続壁22を構築した後に、前記立坑予定区域に立
坑内面となる立坑土留矢板25を打込んで、土留壁を設
置し、囲繞された内部を支保工26を架設しながら最終
掘削予定面31まで掘削して立坑を構築する。上記立坑
土留矢板25と前記立坑土留芯材23とは、継手等によ
り連続することで浸水を防止する(第4図a、b)。
After completing the earthworks 6 and constructing the vertical continuous underground wall 22, the shaft retaining sheet pile 25, which will become the inner surface of the shaft, is driven into the shaft planned area, the retaining wall is installed, and shoring 26 is erected inside the enclosed area. The vertical shaft is constructed by excavating up to the final planned excavation surface 31. The shaft retaining sheet pile 25 and the shaft retaining core material 23 are connected by a joint or the like to prevent water intrusion (FIGS. 4a and 4b).

見皿尻旦工 ついで、シールド発進部(シールド発進予定位N)の周
囲(坑口)を鋼材又はコンクリ−1・により補強して保
護内壁27を設置する。この保護内壁27の内側には、
第1のシール月28と第2のシール材29を備えてシー
ルド機20を密封状態に設置する筒状チャンバ30をセ
ットする(第5図a、 b)。
After completing the construction, the area around the shield starting part (planned shield starting position N) (the mine entrance) is reinforced with steel or concrete, and a protective inner wall 27 is installed. Inside this protective inner wall 27,
A cylindrical chamber 30 is set, which is provided with a first sealing member 28 and a second sealing material 29 and in which the shielding machine 20 is installed in a sealed state (FIGS. 5a and 5b).

立′土 芯材坑口部の切断 立坑内にシールド発進に必要な反力壁、架台、仮組セグ
メン1−などの仮設を投入、据付けなどを行なって発進
準備を終了し、つぎに立坑土留芯材である内側土留矢板
23のうち保護内壁27の内側を切断して切欠部32を
設けて坑口部の鏡開きを行なう。なお、立坑土留芯材2
3には矢板、H鋼の他に鉄筋の場合も考えられる。
The preparation for launch is completed by installing and installing temporary structures such as reaction walls, frames, and temporary assembly segment 1- required for shield launch into the cutting shaft at the entrance of the core material shaft. A notch 32 is provided by cutting the inside of the protective inner wall 27 of the inner retaining sheet pile 23, which is a material, to open the opening of the mine opening. In addition, the shaft earth retaining core material 2
For 3, in addition to sheet piles and H steel, reinforcing bars may also be used.

立坑土留芯材に切欠部32を設けても地山の安定を確保
する理由は、a・・・地下連続壁22中に発進土類留芯
材24が存在すること。b・・内外の芯材23.24間
に地下連続壁22の一部同化体が存在し、これらがあた
かも段ボール状に一体結合していること。C・・・パイ
プスペーサ25によって発進土類留芯材24から内側へ
の出水を防水する。この場合地下連続壁22の同化体を
不透水性のものにすればより効果が生じる。
The reason why the stability of the ground is ensured even if the notch 32 is provided in the shaft earth retaining core material is that a... the starting earth retaining core material 24 is present in the underground continuous wall 22. b. A partial assimilation of the underground continuous wall 22 exists between the inner and outer core materials 23 and 24, and these are integrally connected like cardboard. C: The pipe spacer 25 prevents water from flowing inward from the starting earth anchoring material 24. In this case, it will be more effective if the assimilated body of the underground continuous wall 22 is made of a water-impermeable material.

以上述べたことにより、この発明の立坑構造が出来上が
るが、これらは従来行なった地盤改良工程を省き、シー
ルド発進部のみを補強して他を一般の土留壁と同程度に
簡易構造としたので、工期が短縮されるだけでなく、立
坑構築用の平面積が最少で済むために都心部での利用に
有効である。
As described above, the vertical shaft structure of the present invention is completed, but the conventional ground improvement process is omitted, only the shield starting part is reinforced, and the rest is made as simple as a general earth retaining wall. It is effective for use in urban areas because it not only shortens the construction period, but also requires the minimum floor area for constructing a vertical shaft.

また、立坑をマンホールとして使用する場合、又は埋め
戻す場合にも地盤を現状復帰させることが容易である。
Furthermore, when using a shaft as a manhole or backfilling, it is easy to restore the ground to its current state.

シールド発進 シールド機を設置するには、筒状チェンバ30中にシー
ルド機の先端を押付ける。ついでバルブ10を開にして
泥水タンク9からシール1〜機20の前面と地下連続壁
22との間に泥水を注入し、シールド機先部のカッター
に掘削運転時と同程度の地山に対抗できる圧力を保持す
る。このようにしてシールド機20と地盤4側の圧力を
保持しておき、発進土類留芯材24をワックス効果によ
ってスムーズに引抜く。この場合芯材24を全て引き抜
いてもよいが、シールド機の発進に必要な中央部を所定
の高さまで引抜く方がシール1く発進部の土留めを確実
にする」二で有利である(第7図a。
Shield Launch To install the shield machine, press the tip of the shield machine into the cylindrical chamber 30. Next, the valve 10 is opened to inject muddy water from the muddy water tank 9 between the front of the seals 1 to 20 and the underground continuous wall 22, and the cutter at the tip of the shield machine is exposed to the same level of ground as during excavation operation. Hold as much pressure as possible. In this way, the pressure between the shield machine 20 and the ground 4 is maintained, and the starting earth anchoring material 24 is smoothly pulled out by the wax effect. In this case, it is possible to pull out the entire core material 24, but it is more advantageous to pull out the center part to a predetermined height, which is necessary for starting the shield machine, in order to ensure that the seal 1 and the starting part are grounded (2). Figure 7a.

b)。b).

発進土類留芯材24の引抜きと同時にシールド機を前進
させて行くが、発進坑口である切欠部32の止水にはセ
グメン1へ組立て後に裏込め注入を行なって坑口の隙間
の止水を行うと共に、必要によリパルプ16を開にして
裏込注入用パイプ15がら第1と第2のシール材6,7
間に止水グラウトを行うこともできる。
The shield machine is moved forward at the same time as the starting earth anchoring material 24 is pulled out, but in order to stop the water in the notch 32 which is the starting well mouth, backfilling is performed after assembly into segment 1 to stop the water in the gap at the well mouth. At the same time, if necessary, the repulp 16 is opened and the first and second sealing materials 6, 7 are removed from the backfilling injection pipe 15.
Water stop grouting can also be done in between.

到達側立坑の準備工 到達側も発進側と対称構造の立坑を構築しておく。Preparation work for the reaching side shaft Construct a vertical shaft on the arrival side that is symmetrical to the starting side.

この他に、到達側の立坑内にはシールド機が内部に侵入
する大きさで筒状仮組セグメン1へ33を保護内壁27
′内にセラI・する。この仮組セグメント33中には、
土砂を詰め込み人工地盤34を造成する(第8図a、b
)。
In addition, inside the shaft on the reaching side, there is a protective inner wall 27 that is large enough to allow the shield machine to enter the cylindrical temporary assembly segment 1.
'Cera I.'. In this temporary assembly segment 33,
Fill the earth and sand to create artificial ground 34 (Fig. 8 a, b)
).

人工地盤への加圧 仮組セグメント33内に人工地盤34が構築されると、
予め仮組セグメン1−33にセットシている注入パイプ
35で給水槽36から泥水を注入して、(到達)土留芯
材24を引抜いてシールド機20を導き入れる際の地山
作用圧に人工地盤34が充分に抵抗できるようにする。
Pressure on the artificial ground When the artificial ground 34 is constructed within the temporary assembly segment 33,
Mud water is injected from the water tank 36 using the injection pipe 35 that has been set in the temporary assembly segment 1-33 in advance, and the earth acting pressure is applied to the artificial ground when the earth retaining core material 24 is pulled out and the shielding machine 20 is introduced. 34 to provide sufficient resistance.

なお、注入時には注入が容易になるようにエア抜きパイ
プ37を数カ所設け、これを利用して内部圧力を確認す
るようにすることもできる(第9図a、b)。
Note that during injection, air vent pipes 37 may be provided at several locations to facilitate injection, and these may be used to check the internal pressure (FIGS. 9a and 9b).

シールド機到達と土留芯 弓 き シールド機が暗渠を掘削しながら立坑に到達した時点で
到達土留芯材としての土留矢板24を無理なく引抜く(
第]O図a、b)。無理なく引抜ける理由は、表面のワ
ックス加工と、強制打込みによらない精度良い建込み及
びパイプスペーザーによる内側土留矢板23との接触抵
抗を軽減したことによる。なお、外側の土留矢板の引抜
きによる鏡の安定は、人工地盤の加圧調整により作用圧
とバランスさせて行ない、人工地盤の加圧調整は仮組セ
グメント33に予め設けた圧力ゲージ38により給水量
を調整して行なう。
Reach of the shield machine and earth retaining core When the shield machine reaches the shaft while excavating the culvert, it effortlessly pulls out the earth retaining sheet pile 24 as the earth retaining core material (
] Figure O a, b). The reason why it can be pulled out easily is because of the waxing on the surface, the highly accurate erection without forced driving, and the reduction of contact resistance with the inner retaining sheet pile 23 by the pipe spacer. The stabilization of the mirror by pulling out the outer retaining sheet pile is done by adjusting the pressure of the artificial ground to balance it with the working pressure. Adjust and do this.

シールド の立 内への導入 び止水 シールド機20は、仮組セフメン1〜33内を掘削しな
がら前進して全体を立坑内に導入する。ここで、仮組セ
グメント33の後方外周に仮11ユめしでおいた止水板
38をくさび状に打込みセグメント全周を密閉する。ま
た、止水板38の外側には、予め設けておいたグラウト
パイプを使用して地山側の空隙部にグラウトに注入して
止水を完全なものにする(第11図a、b)。
Introduction of the shield into the shaft The water-stopping shield machine 20 moves forward while excavating the inside of the temporarily assembled safety men 1 to 33, and introduces the whole into the shaft. Here, a water stop plate 38 temporarily placed on the rear outer periphery of the temporarily assembled segment 33 is driven into a wedge shape to seal the entire periphery of the segment. Further, on the outside of the water stop plate 38, a grout pipe provided in advance is used to inject grout into the void on the ground side to complete the water stop (FIGS. 11a and 11b).

仮組セグメン1−の取 しとシード の  し最後に、
仮組セグメン1へを取外すには、排水パイプを開いてセ
グメント全周の圧力水を抜き開口の後、シール1く機を
立坑外に引き上げ、立坑内を片付けて作業を終了する(
第12図a、b)。
Kari group segment 1- selection and seeding.Finally,
To remove the temporarily assembled segment 1, open the drain pipe and drain the pressure water around the segment, then pull the seal 1 machine out of the shaft, clean up the inside of the shaft, and finish the work (
Figure 12 a, b).

〈発明の効果〉 以上述べてきたように、この発明の立坑構造はシールド
機発進側のみ立坑と発進の土留芯材を二重にして地下連
続壁中に建込み、他の立坑側壁を通常の立坑土留芯材と
しているので、構造が極めて簡単で工期が短かくてすむ
。また、立坑外の地盤改良をしないので小さなスペース
でシールド発進部を構築できる。さらに、立坑周囲にお
ける通常の土留芯材はもちろん地下連続壁も簡単に撤去
できるので土地の現状復帰のための工事が簡単である。
<Effects of the Invention> As described above, in the shaft structure of the present invention, the earth retaining core material for the shaft and the start are doubled only on the shield machine starting side, and are built into the underground continuous wall, and the other shaft side walls are built in the same way as usual. Since it is used as a shaft retaining core material, the structure is extremely simple and the construction period is short. Additionally, since there is no need to improve the ground outside the shaft, the shield launching section can be constructed in a small space. Furthermore, since not only the usual earth retaining core material around the shaft but also the underground continuous wall can be easily removed, the work to restore the land to its current state is easy.

また、上記立坑構造を発進側と到達側に配する=20 ことにより、シールドの発進も到達も発進(到達)土留
芯材の引抜きと、到達側の人工地盤の形成によって1−
ンネルの覆工を容易に行うことができる。
In addition, by placing the above-mentioned shaft structure on the starting side and the reaching side = 20, the starting and reaching of the shield can be done by pulling out the earth retaining core material and forming the artificial ground on the reaching side.
The tunnel can be lined easily.

さらに、この立坑構造の施工は1通常の地下連続壁工法
と同じか、それ以下の作業で出来、しかも連続壁内の二
重の芯材をそれぞれの作用に応じて使い分けることによ
り、シールド機の発進前はもちろん、発進後においても
十分に地山の崩壊を防止することができる。
Furthermore, the construction of this shaft structure can be done with the same or less work than the normal underground continuous wall construction method, and by using the double core materials in the continuous wall according to their functions, the shield machine can be constructed. It is possible to sufficiently prevent the collapse of the ground not only before starting, but also after starting.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明にかかるシールド機の発進部施工構造
を示す断面図、第2図乃至第1−2図まではこの発明で
ある立坑構造の施工法とシールド機−の発進・到達方法
を順に記載したものであり、各図の(a)は平面図、(
b)は側面図である。 1 (22)  ・・地下連続壁、2(23) ・・立
坑土留芯材、3 (24) ・・発進土類留芯材、4・
・地盤、5・・筒状チャンバ、1.2(32)  ・・
切欠部、20・・シール1く機。
Fig. 1 is a sectional view showing the construction structure of the starting part of the shield machine according to the present invention, and Figs. They are described in order, and (a) of each figure is a plan view, (
b) is a side view. 1 (22) ... Underground continuous wall, 2 (23) ... Vertical earth retaining core material, 3 (24) ... Starting earth retaining core material, 4.
・Ground, 5...Cylindrical chamber, 1.2 (32)...
Notch, 20...Seal 1 machine.

Claims (1)

【特許請求の範囲】 1)シールド機を設置する立坑と、この立坑を連続して
囲繞する立坑土留芯材とから成り、 この立坑土留芯材をシールド機発進側の地下連続壁中に
建込むと共に、シールド機発進用切欠部を形成し、 切欠部の周囲にはシールド機発進用保護内壁を構築し、 前記立坑土留芯材の外側の地下連続壁中には表面に引抜
き加工を施した発進土類留芯材を前記切欠部を覆うよう
に建込んでなる、 シールド機発進部の立坑構造。 2)請求項1の立坑構造を発進側と到達側に用い、それ
ぞれの立坑内にシールド機の反力壁と発進用保護内壁の
内周に沿って設けたシール材付き筒状チャンバを設け、 立坑の発進側に地山を掘削していくシールド機を設置し
、発進土留芯材を地下連続壁から立坑土留芯材の切欠部
上に引抜き、シールド前面の芯材のない地下連続壁の一
部を掘削しながら発進して目標地盤を掘進し、 到達側の発進土留芯材に相当する到達土留芯材を地下連
続壁から立坑土留芯材の切欠部上に引抜いてシールド機
を所定圧の人工地盤を形成した到達側の立坑内に取込み
到達するようにした、 シールド機の発進・到達方法。 3)予定した立坑区域のシールド機発進側に、地下連続
壁工法により、表面引抜き加工した立坑土留芯材と発進
土留芯材との二重芯材を建込んで地下連続壁を構築する
工程と、 この地下連続壁中の立坑土留芯材と連続して他の立坑内
面となる立坑土留芯材としての立坑土留矢板を打込むと
共に、囲繞した立坑土留矢板内部を掘削する工程と、 前記地下連続壁のシールド機の発進坑口周囲に保護内壁
を設けると共に、保護内壁の内側にあたる前記立坑土留
芯材に切欠部を形成する工程と、 からなる立坑発進側の地盤改良を行なわないシールド発
進部の立坑構造の施工法。
[Scope of Claims] 1) Consisting of a shaft in which the shield machine is installed and a shaft earth retaining core material that continuously surrounds this shaft, this shaft earth retainer core material is built into an underground continuous wall on the shield machine launch side. At the same time, a notch for launching the shield machine is formed, a protective inner wall for launching the shield machine is constructed around the notch, and a launching plate with a drawing process applied to the surface is provided in the underground continuous wall outside the shaft earth retaining core material. A vertical shaft structure of a shield machine starting part, in which earth anchoring material is built so as to cover the notch. 2) The shaft structure according to claim 1 is used on the starting side and the reaching side, and a cylindrical chamber with a sealing material is provided in each shaft along the inner periphery of the reaction wall of the shield machine and the protective inner wall for starting. A shield machine that excavates the ground is installed on the starting side of the shaft, and the starting earth retaining core material is pulled out from the underground continuous wall onto the notch of the shaft earth retaining core material, and the part of the underground continuous wall without core material in front of the shield is pulled out. Start while excavating the target ground, pull out the reaching earth retaining core material corresponding to the starting earth retaining core material on the reaching side from the underground continuous wall onto the notch of the shaft earth retaining core material, and apply the shield machine to the specified pressure. A method for launching and reaching a shield machine that takes in and reaches a shaft on the reaching side where artificial ground has been formed. 3) The step of constructing an underground continuous wall on the shield machine starting side of the planned shaft area by using the underground continuous wall construction method to construct a double core material consisting of a vertical shaft earth retaining core material whose surface has been drawn and a starting earth retaining core material. , a step of driving a shaft retaining sheet pile as a shaft retaining core material to become the inner surface of another shaft continuously with the shaft retaining core material in this underground continuous wall, and excavating the inside of the enclosed shaft retaining sheet pile; A step of providing a protective inner wall around the starting shaft entrance of the shield machine in the wall, and forming a notch in the shaft earth retaining core material inside the protective inner wall. Construction method of structure.
JP8590089A 1989-04-05 1989-04-05 Vertical shaft structure of shield machine starting part, its construction method, and start / arrival method of shield machine using the structure Expired - Fee Related JP2681511B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8590089A JP2681511B2 (en) 1989-04-05 1989-04-05 Vertical shaft structure of shield machine starting part, its construction method, and start / arrival method of shield machine using the structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8590089A JP2681511B2 (en) 1989-04-05 1989-04-05 Vertical shaft structure of shield machine starting part, its construction method, and start / arrival method of shield machine using the structure

Publications (2)

Publication Number Publication Date
JPH02266091A true JPH02266091A (en) 1990-10-30
JP2681511B2 JP2681511B2 (en) 1997-11-26

Family

ID=13871737

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8590089A Expired - Fee Related JP2681511B2 (en) 1989-04-05 1989-04-05 Vertical shaft structure of shield machine starting part, its construction method, and start / arrival method of shield machine using the structure

Country Status (1)

Country Link
JP (1) JP2681511B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006257806A (en) * 2005-03-18 2006-09-28 Sumitomo Metal Ind Ltd Earth retaining steel material

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2987501B2 (en) 1998-04-16 1999-12-06 有限会社タム・テック Tunnel entrance sealing device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006257806A (en) * 2005-03-18 2006-09-28 Sumitomo Metal Ind Ltd Earth retaining steel material
JP4604779B2 (en) * 2005-03-18 2011-01-05 住友金属工業株式会社 Earth retaining steel

Also Published As

Publication number Publication date
JP2681511B2 (en) 1997-11-26

Similar Documents

Publication Publication Date Title
JPH02266091A (en) Vertical shaft mechanism for shield machine starting section, its constructing method, and starting and reaching method of shield machine using its mechanism
JPH04357293A (en) Flexible pipe and executing method thereof
JPH0424398A (en) Construction of underground space with arched member
JP2697558B2 (en) Independent mountain retaining wall method
JP2874906B2 (en) Shaft construction method
JPS6117696A (en) Construction of underground head
JP3803753B2 (en) Tunnel construction method
JPS6065825A (en) Method of constructing landslide protection wall having newel pile
JPH0437916B2 (en)
JPH04115024A (en) Sheathing method
JPH0470422A (en) Open caisson method
JPS5664028A (en) Sheathing construction work by antecedent support framework
JP4180347B2 (en) Construction method of underground continuous wall and underground continuous wall
JPS6027358B2 (en) Cofferdam construction method for vertical shafts for muddy water shield construction
JP2987093B2 (en) Tunnel construction method
JPH01315588A (en) Advancing method for shield machine and advance section construction structure
JPS6357566B2 (en)
JP3065228B2 (en) How to build a building foundation
JPH11181806A (en) Heaving preventing method and construction of underground building
JP2601140B2 (en) Independent mountain retaining wall method
JPH07259078A (en) Steel material for shield opening, constructing method for underground continuous wall, and boring method for pit
JPH04336117A (en) Landslide protection stabilizing construction method
JPS63176530A (en) Construction of foundation of underground continuous wall
JPH10159074A (en) Execution method of underground structure in cut and cover tunneling method
JPH08218770A (en) Underground curved member and its construction method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees