JP3065228B2 - How to build a building foundation - Google Patents

How to build a building foundation

Info

Publication number
JP3065228B2
JP3065228B2 JP7080309A JP8030995A JP3065228B2 JP 3065228 B2 JP3065228 B2 JP 3065228B2 JP 7080309 A JP7080309 A JP 7080309A JP 8030995 A JP8030995 A JP 8030995A JP 3065228 B2 JP3065228 B2 JP 3065228B2
Authority
JP
Japan
Prior art keywords
building
slime
ground
building foundation
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7080309A
Other languages
Japanese (ja)
Other versions
JPH08277520A (en
Inventor
博 藤村
侑弘 五十殿
正至 長田
弘明 久保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Chemical Grouting Co Ltd
Original Assignee
Kajima Corp
Chemical Grouting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Chemical Grouting Co Ltd filed Critical Kajima Corp
Priority to JP7080309A priority Critical patent/JP3065228B2/en
Publication of JPH08277520A publication Critical patent/JPH08277520A/en
Application granted granted Critical
Publication of JP3065228B2 publication Critical patent/JP3065228B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は軟弱地盤上に建物を構
築する際の建物基礎の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a building foundation for constructing a building on soft ground.

【0002】[0002]

【従来の技術】軟弱な地盤上に建物を構築する場合、建
物重量を支持するために、地盤内に固化材を注入し、堅
固な支持層に達する基礎杭を造成するなどして軟弱地盤
を改良していた。また、地盤を掘削して建物基礎部分を
構築するには、掘削面に作用する土圧、水圧に耐える山
留壁を必要とした。
2. Description of the Related Art When constructing a building on soft ground, in order to support the weight of the building, a solidified material is injected into the ground, and a foundation pile reaching a solid support layer is formed. Had improved. In addition, excavating the ground to build the foundation of the building required a retaining wall that could withstand the earth pressure and water pressure acting on the excavated surface.

【0003】従って、このような従来の建物基礎の構築
には、地盤の改良とともに大掛りで堅固な山留壁を仮設
材として設置しなければならず、少なからぬ負担となっ
ていた。
[0003] Therefore, in the construction of such a conventional building foundation, it is necessary to install a large-scale and solid retaining wall as a temporary material together with the improvement of the ground, which is a considerable burden.

【0004】[0004]

【発明の目的】この発明は上記問題点の解消を図ったも
のである。その目的は、軟弱地盤に固化材を注入し地盤
を改良し、建物基礎を構築する際に、固化材の注入によ
り排出スライムを有効利用し、山留壁として機能せし
め、大掛りな仮設山留を不要となし、同時に施工の省力
化、コストの低減を図り得る建物基礎の構築方法を提案
するにある。
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems. The purpose is to improve the ground by injecting the solidified material into the soft ground and use the discharged slime effectively by injecting the solidified material when constructing the building foundation, function as a retaining wall, and make a large temporary temporary It is an object of the present invention to propose a method of constructing a building foundation that can eliminate the need for construction, and at the same time can save labor and cost.

【0005】[0005]

【発明の構成】この建物基礎の構築方法は、軟弱地盤に
固化材を注入し地盤を改良し、その上に建物を建造する
建物基礎の構築方法において、地盤改良の際に排出する
スライムを建物基礎部分の周囲に埋戻し、スライム固結
体を形成することを特徴とする。
According to the method of constructing a building foundation, in a method of constructing a building foundation in which a solidified material is injected into soft ground to improve the ground, and a building is constructed thereon, slime discharged at the time of ground improvement is used. It is characterized by being buried around the base part to form a slime compact.

【0006】[0006]

【作用】この発明は上記構成からなり、排出したスライ
ムを埋め戻し、建物基礎部分の周囲に形成したスライム
固結体は周囲の土圧と拮抗し、建物基礎部分の掘削面に
作用する土圧を低減せしめることができる。従って切梁
を設置したり、大掛り堅固に山留壁を設置することなく
掘削などの工事を進めることができる。
The present invention has the above-mentioned structure, and backfills the discharged slime. The slime consolidated body formed around the building foundation opposes the surrounding earth pressure and acts on the excavated surface of the building foundation. Can be reduced. Accordingly, construction work such as excavation can be performed without installing a girder or installing a large retaining wall.

【0007】また、スライムを発生した現場で有効利用
するので廃棄費用の節減、環境保全に効果がある。
Further, since the slime is effectively used at the site where the slime is generated, the disposal cost is reduced and the environment is effectively protected.

【0008】[0008]

【実施例】以下、この建物基礎の構築方法を実施例をあ
げ、工程順に図面を用い説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The method of constructing a building foundation will be described below in the order of steps with reference to the drawings.

【0009】建物を構築すべき軟弱地盤1に建物周囲を
とり囲み山留壁2を施設する(図1参照)。
[0009] A mountain retaining wall 2 is provided around the building on the soft ground 1 on which the building is to be constructed (see FIG. 1).

【0010】山留壁2の外側、すなわち構築すべき建物
の回りを土質に応じた安定した斜面角を保った法面を形
成しながら掘削する(図2参照)。この際に、地下水位
が高い場合は、法面部分にウエルポイント3を設けて地
下水位を下げ、掘削を進める。
Excavation is performed on the outside of the retaining wall 2, that is, around the building to be constructed while forming a slope with a stable slope angle according to the soil quality (see FIG. 2). At this time, if the groundwater level is high, a well point 3 is provided on the slope to lower the groundwater level, and excavation proceeds.

【0011】所定の深さまで掘削した後、山留壁の変形
と応力を小さくするために、山留壁2頂部と根切底とを
斜めに結ぶ線上に土圧を受ける切梁4を架設する。ま
た、隣接する切梁4相互間に山留壁2の面外方向の剛性
を高めるための腹起材5を取付ける。山留壁2近くの残
りの土を掘削する。
After excavation to a predetermined depth, in order to reduce deformation and stress of the retaining wall, a cutting beam 4 receiving earth pressure is erected on a line diagonally connecting the top of the retaining wall 2 and the root bottom. . In addition, a belly material 5 for increasing the rigidity of the retaining wall 2 in the out-of-plane direction is attached between the adjacent cutting beams 4. Excavate the remaining soil near the mountain retaining wall 2.

【0012】次に、図3に示すように、構築すべき建物
下側全面にわたり、噴射式攪拌工法により、固化材を注
入し、地盤土砂と混合し、地盤改良体6を造成する。こ
の地盤改良に際し排出する土砂と固化材との混合物から
なるスラリー状をなすスライム7を前記掘削した建物の
回りの掘削空間に埋め戻す。
Next, as shown in FIG. 3, a solidification material is injected by a jet-type stirring method over the entire lower surface of the building to be constructed, mixed with the soil and soil, and a ground improvement body 6 is formed. The slime 7 in the form of a slurry made of a mixture of the earth and sand and the solidified material discharged during the ground improvement is buried in the excavation space around the excavated building.

【0013】その後、図4のごとく、排出するスライム
7の埋め戻しを継続し、スライム7上面位置が地下水位
より上になった時点でウエルポイント3を除去し、地盤
面まで到達したら埋め戻しを止め、固化するまで放置す
る。
Thereafter, as shown in FIG. 4, backfilling of the slime 7 to be discharged is continued, and the well point 3 is removed when the upper surface position of the slime 7 becomes higher than the groundwater level. Stop and allow to solidify.

【0014】埋め戻したスライム7が固化しスライム固
結体8となり所定の強度に達した後、図5に示すごと
く、地上から固化材を注入し、土留壁2の外側に沿っ
て、建物の根切底以深に達する所定の幅をもった地盤改
良部9を造成する。
After the backfilled slime 7 solidifies to form a slime consolidated body 8 and reaches a predetermined strength, a solidified material is injected from the ground as shown in FIG. The ground improvement part 9 having a predetermined width reaching the depth below the root cut is created.

【0015】スライム固結体8の下の地盤改良部9の強
度が発現した後、図6に示すごとく、建物基礎部分すな
わち、土留壁2の内側の掘削を開始する。
After the strength of the ground improvement part 9 below the slime consolidated body 8 has developed, as shown in FIG. 6, excavation of the building foundation, that is, the inside of the retaining wall 2 is started.

【0016】掘削を継続し、図7のごとく、地盤改良体
6に達する根切底まで掘削し建物基礎を構築する。図8
は建物基礎上に建造した建物10である。建物基礎部分
は地盤改良体6、スライム固結体8および地盤改良部9
で遮蔽され地下水の浸入が防止されている。
Excavation is continued, and as shown in FIG. 7, excavation is performed up to the root bottom reaching the ground improvement body 6 to construct a building foundation. FIG.
Is a building 10 built on the building foundation. The foundation of the building is ground improvement body 6, slime consolidated body 8, and ground improvement section 9.
And the groundwater is prevented from entering.

【0017】上記実施例ではスライム固結体8の下側に
地盤改良部9を設けたが、必ずしも設ける必要はない。
しかし、実施例のごとく地盤改良部9を設けると、内部
の掘削が進行してもスライム固結体8と地盤改良部9が
一体となり、土圧と釣合を保ち、土留壁に土圧が作用し
なくなり、そのまま工事を進行でき好適である。
In the above embodiment, the ground improvement part 9 is provided below the slime consolidated body 8, but it is not always necessary to provide the ground improvement part 9.
However, when the ground improvement part 9 is provided as in the embodiment, the slime solidified body 8 and the ground improvement part 9 are united even when the excavation proceeds, and the earth pressure is balanced with the earth pressure, and the earth pressure is applied to the retaining wall. It does not work, and construction can proceed as it is.

【0018】[0018]

【発明の効果】この発明は以上の通りであり、軟弱地盤
に固化材を注入し、地盤改良体を造成し、その上に建物
を構築する際に地盤改良に伴い排出するスライムを埋め
戻し、建物周囲にスライム固結体をつくることにより、
大掛りな仮設山留が不要となり、建物基礎の地盤の掘
削、基礎施工の能率化および施工コストの低減を図るこ
とができる。
The present invention is as described above. A solidified material is injected into soft ground, a ground improvement body is formed, and slime discharged with the ground improvement when a building is constructed thereon is backfilled. By making a slime compact around the building,
Extensive temporary stakes are not required, and excavation of the ground of a building foundation, efficiency of foundation construction, and reduction of construction costs can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】山留壁を地中に施設した状態の断面図である。FIG. 1 is a cross-sectional view of a state where a retaining wall is installed underground.

【図2】山留壁の外周部を掘削する状態の断面図であ
る。
FIG. 2 is a cross-sectional view of a state where an outer peripheral portion of a retaining wall is excavated.

【図3】山留壁の内部に固化材を注入し地盤改良体を造
成した状態の断面図である。
FIG. 3 is a cross-sectional view showing a state where a solidification material is injected into the inside of the retaining wall to form a ground improvement body.

【図4】排出スライムを山留壁外周部に埋め戻し、スラ
イム固結体を形成した状態の断面図である。
FIG. 4 is a cross-sectional view showing a state in which the discharged slime is backfilled to the outer peripheral portion of the retaining wall to form a slime compact.

【図5】スライム固結体の下側に地盤改良部を造成した
状態の断面図である。
FIG. 5 is a cross-sectional view showing a state in which a ground improvement part is formed below the slime compact.

【図6】山留壁内側の建物基礎部分を掘削する状態の断
面図である。
FIG. 6 is a cross-sectional view of a state where a building base portion inside a retaining wall is excavated.

【図7】根切底まで掘削した建物基礎部分の断面図であ
る。
FIG. 7 is a sectional view of a building foundation portion excavated to a root incision.

【図8】掘削した建物基礎部分に建物を建造した状態の
概念図である。
FIG. 8 is a conceptual diagram of a state in which a building has been built on an excavated building base.

【符号の説明】[Explanation of symbols]

1……軟弱地盤、2……土留壁、3……ウエルポイン
ト、4……切梁、5……腹起材、6……地盤改良体、7
……スライム、8……スライム固結体、9……地盤改良
部、10……建物。
1 ... soft ground, 2 ... earth retaining wall, 3 ... well point, 4 ... cut beam, 5 ... belly material, 6 ... ground improvement body, 7
… Slime, 8… slime solidification, 9… ground improvement section, 10… building.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 長田 正至 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 久保 弘明 東京都練馬区中村南3丁目16番4号 (56)参考文献 特開 昭63−233115(JP,A) 特開 昭53−87511(JP,A) 特開 平5−287722(JP,A) (58)調査した分野(Int.Cl.7,DB名) E02D 3/00 E02D 3/12 E02D 27/00 - 27/52 E02D 17/04 ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Masayoshi Nagata 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Hiroaki Kubo 3-164 Nakamura Minami, Nerima-ku, Tokyo (56) References JP-A-63-233115 (JP, A) JP-A-53-87511 (JP, A) JP-A-5-287722 (JP, A) (58) Fields investigated (Int. 7 , DB name) E02D 3/00 E02D 3/12 E02D 27/00-27/52 E02D 17/04

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 軟弱地盤に固化材を注入し地盤を改良
し、その上に建物を建造する建物基礎の構築方法におい
て、地盤改良の際に排出するスライムを建物基礎部分の
周囲に埋め戻し、スライム固結体を形成することを特徴
とする建物基礎の構築方法。
1. A method of constructing a building foundation in which a solidified material is injected into soft ground to improve the ground, and a building is constructed thereon, wherein slime discharged at the time of ground improvement is backfilled around the building foundation. A method for constructing a building foundation, comprising forming a slime compact.
JP7080309A 1995-04-05 1995-04-05 How to build a building foundation Expired - Lifetime JP3065228B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7080309A JP3065228B2 (en) 1995-04-05 1995-04-05 How to build a building foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7080309A JP3065228B2 (en) 1995-04-05 1995-04-05 How to build a building foundation

Publications (2)

Publication Number Publication Date
JPH08277520A JPH08277520A (en) 1996-10-22
JP3065228B2 true JP3065228B2 (en) 2000-07-17

Family

ID=13714678

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7080309A Expired - Lifetime JP3065228B2 (en) 1995-04-05 1995-04-05 How to build a building foundation

Country Status (1)

Country Link
JP (1) JP3065228B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6186267B2 (en) * 2013-12-19 2017-08-23 鹿島建設株式会社 How to build an underground tunnel

Also Published As

Publication number Publication date
JPH08277520A (en) 1996-10-22

Similar Documents

Publication Publication Date Title
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP3065228B2 (en) How to build a building foundation
JP3967473B2 (en) Construction method of underground structure
JP4485006B2 (en) Construction method for underground structures
JP3185190B2 (en) Construction method of PC hollow pile and underground structure
JP2868651B2 (en) Earth retaining method above existing underground structure
JPS6115209B2 (en)
JPH0796776B2 (en) Yamadome method
JP2874906B2 (en) Shaft construction method
JPH0415878B2 (en)
JP2554507B2 (en) Underground space construction method
JP3091859B2 (en) Piling method for shafts with openings at the top
JP2000178966A (en) Structure of diaphragm wall
JP2001011849A (en) Liquefaction prevention structure of ground, its construction method, and ground improving method
JP3099040B2 (en) Embankment culvert
JP4279818B2 (en) Open shield method
JP2657731B2 (en) Open shield method and open shield machine
JPS6357566B2 (en)
JP3116253B2 (en) How to build a continuous underground wall
JP2536108B2 (en) Foundation construction method for offshore structures
JPH0493430A (en) Floating prevention method for underground structure
JP2810957B2 (en) Pile foundation method
JPH08226126A (en) Construction method for earth retaining wall and construction material therefor
JPH10159074A (en) Execution method of underground structure in cut and cover tunneling method
JP2000178983A (en) Foundation construction method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20000425