JPH04336117A - Landslide protection stabilizing construction method - Google Patents

Landslide protection stabilizing construction method

Info

Publication number
JPH04336117A
JPH04336117A JP13583091A JP13583091A JPH04336117A JP H04336117 A JPH04336117 A JP H04336117A JP 13583091 A JP13583091 A JP 13583091A JP 13583091 A JP13583091 A JP 13583091A JP H04336117 A JPH04336117 A JP H04336117A
Authority
JP
Japan
Prior art keywords
retaining wall
ground layer
anchor
hard ground
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13583091A
Other languages
Japanese (ja)
Inventor
Sakae Nakamura
栄 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP13583091A priority Critical patent/JPH04336117A/en
Publication of JPH04336117A publication Critical patent/JPH04336117A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To certainly reinforce a landslide protection wall without extending an anchor longer. CONSTITUTION:A curing agent is poured into a soil in an area behind a landslide protection wall 3 deposited along the planning line of an excavating area 2 to form a hard ground layer 4. The landslide protection wall 3 and the hard ground layer 4 are mutually connected through anchors 6(6a-6c) at every time when ground soil inside the landslide protection wall 3 is excavated as much as a fixed depth.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、立穴の掘削に際して山
留壁を安定させるための山留め安定工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for stabilizing a retaining wall during excavation of a vertical hole.

【0002】0002

【従来の技術】ビル工事、トンネル工事等(以下、単に
ビル工事等という)において立穴を掘削するには、通常
、掘削区域の計画線に沿ってシートパイル、セメント系
連続壁等から成る山留壁を打設した後、この山留壁の内
側を掘削し、該山留壁により地盤土が崩れ落ちるのを防
止するようにしている。
[Prior Art] In order to excavate a vertical hole in building construction, tunnel construction, etc. (hereinafter simply referred to as building construction, etc.), a pile of sheet piles, continuous cement walls, etc. is usually constructed along the planned line of the excavation area. After the retaining wall is cast, the inside of the retaining wall is excavated to prevent the ground soil from collapsing due to the retaining wall.

【0003】ところで近年、ビル工事等の大規模化に伴
って立穴の深度は益々大きくなる傾向にあり、これに応
じて山留壁にかかる土圧も益々高まるようになってきて
いる。そこで従来、かゝる大深度の立穴を掘削する場合
は、所定深さだけ掘削するごとに山留壁からアンカーを
延ばし、該アンカーの先端部を掘削区域の周りの地盤に
定着させて山留壁を補強するようにしていた。
[0003] In recent years, with the increasing scale of building construction work, the depth of vertical holes has tended to become larger and larger, and the earth pressure applied to retaining walls has also increased accordingly. Conventionally, when excavating a vertical hole of such great depth, an anchor is extended from the retaining wall every time a predetermined depth is excavated, and the tip of the anchor is anchored in the ground around the excavated area. The retaining walls were to be reinforced.

【0004】0004

【発明が解決しようとする課題】しかしながら、上記ア
ンカーにより山留壁を補強する工法によれば、アンカー
の先端部を定着させる地盤が軟弱であると補強効果が失
われるため、強固な地盤を求めてアンカーを延ばさなけ
ればならず、場合によってば数十メートルもアンカーを
延長しなければならないこととなって、施工に多大の工
数と時間とを要するという問題があった。また、最近は
限られたスペース内でビル工事等を行うことが多いため
、アンカーの延長にもおのずから限界があり、アンカー
補強を断念せざるを得ない状況が往々に発生していた。
[Problem to be solved by the invention] However, according to the method of reinforcing mountain retaining walls using anchors, the reinforcing effect is lost if the ground on which the tip of the anchor is anchored is soft, so it is necessary to find a strong ground. In some cases, the anchor must be extended by several tens of meters, which poses a problem in that construction requires a large amount of man-hours and time. Furthermore, as building construction work is often carried out in limited spaces these days, there is a natural limit to the extension of anchors, and situations often arise where anchor reinforcement has to be abandoned.

【0005】なお、アンカー補強に代わるものとして、
対向する山留壁間に補強用の横けたを橋架する方法もあ
るが、この場合には横けたによって立穴内の作業スペー
スが狭ばめられるため、作業性が著しく阻害され、工期
の大幅な延長を来すばかりか、作業安全性の面でも問題
の多いところなっている。
[0005] As an alternative to anchor reinforcement,
There is also a method of building reinforcing horizontal beams between opposing retaining walls, but in this case, the working space in the vertical hole is narrowed by the horizontal beams, which significantly impedes work efficiency and significantly shortens the construction period. Not only is the work being extended, but it is also causing many problems in terms of work safety.

【0006】本発明は、上記従来の問題に鑑みてなされ
たもので、その目的とするところは、アンカーを長く延
ばさなくも山留壁を確実に補強し得る山留め安定工法を
提供することにある。
The present invention has been made in view of the above-mentioned conventional problems, and its purpose is to provide a stabilizing construction method for retaining a retaining wall that can reliably reinforce the retaining wall without extending the anchor for a long time. .

【0007】[0007]

【課題を解決するための手段】本発明は、上記目的を達
成するため、掘削区域に近接してその周りに硬化剤で固
めた硬質地盤層を形成し、前記掘削区域の計画線に沿っ
て打設した山留壁の内側を所定深さだけ掘削するごとに
、該山留壁と前記硬質地盤層とをアンカーにて連結する
ようにしたことを特徴とする。
[Means for Solving the Problems] In order to achieve the above object, the present invention forms a hard ground layer hardened with a hardening agent near and around an excavation area, and forms a hard ground layer around the excavation area along a planned line of the excavation area. The present invention is characterized in that each time the inside of the cast mountain retaining wall is excavated to a predetermined depth, the mountain retaining wall and the hard ground layer are connected by an anchor.

【0008】本発明において、上記硬化剤の種類は特に
問うものでなく、例えばセメントスラリー、石灰、水ガ
ラス系や高分子系の薬液などを用いることができる。ま
た、この硬質地盤層を形成する方法は任意であり、例え
ば単に注入管を土中に挿入して硬化剤を圧力注入する方
法、中空ケーシングを土中に打込み、ケーシング内部に
硬化剤を供給してケーシングの引上げ跡に硬化剤を充填
する方法、あるいは撹拌翼を持つ中空ケーシングを土中
に挿入し、該ケーシングを回転させてながらこの中を通
して供給した硬化剤と地盤土とを撹拌する方法などを選
択することができる。さらに、上記アンカーの数も任意
であり、掘削区域の広さおよび掘削しようとする立穴の
深さに応じて適宜の数を選択し得る。
In the present invention, the type of the hardening agent is not particularly limited, and for example, cement slurry, lime, water glass-based or polymer-based chemicals can be used. In addition, any method can be used to form this hard ground layer, such as simply inserting an injection pipe into the soil and injecting the hardening agent under pressure, or driving a hollow casing into the soil and supplying the hardening agent inside the casing. A method of filling the hardening agent into the area where the casing was pulled up, or a method of inserting a hollow casing with stirring blades into the soil and stirring the hardening agent supplied through the casing and the ground soil while rotating the casing. can be selected. Furthermore, the number of anchors is also arbitrary, and can be selected appropriately depending on the width of the excavated area and the depth of the vertical hole to be excavated.

【0009】また本発明において、上記山留壁を打設す
る方法も任意であり、例えばシートパイルを連続に打込
んで山留壁としても、あるいはセメント系材料を現場打
ちして山留壁としても良い。さらに、本発明において硬
化剤で固めて硬質地盤層を形成する工程と山留壁を打設
する工程とは、どちらを優先して行っても良いものであ
る。
Further, in the present invention, the method for pouring the mountain retaining wall is arbitrary; for example, sheet piles may be continuously driven to form a mountain retaining wall, or cement-based materials may be cast on-site to form a mountain retaining wall. Also good. Furthermore, in the present invention, either the step of hardening with a hardening agent to form a hard ground layer or the step of pouring a retaining wall may be performed with priority.

【0010】0010

【作用】上記のように構成した山留め安定工法において
は、硬質地盤層にアンカーの先端部を定着させることに
よりアンカーの引抜き抵抗が著しく増大し、山留壁の補
強は確実となる。しかも、硬質地盤層を掘削区域に近接
してその周りに形成したので、アンカーを長く延ばすこ
となく山留壁を補強できる。
[Function] In the mountain retaining stabilization method constructed as described above, by fixing the tip of the anchor to the hard ground layer, the pull-out resistance of the anchor increases significantly, and the reinforcement of the mountain retaining wall becomes reliable. Moreover, since the hard ground layer is formed close to and around the excavated area, the retaining wall can be reinforced without extending the anchor for a long time.

【0011】[0011]

【実施例】以下、本発明の実施例を添付図面にもとづい
て説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Examples of the present invention will be described below with reference to the accompanying drawings.

【0012】図1および図2において、1は地盤、2は
掘削区域であり、本実施例においては、先ず、掘削区域
2の計画線に沿ってシートパイルを打込んで山留壁3を
形成し、次に、この山留壁3から所定距離だけ後方へ離
間した箇所の土中に硬化剤を注入して硬質地盤層4を形
成する。硬質地盤層4は、掘削区域2のほヾ全域を囲む
ようにかつ掘削しようとする立穴5の深さよりわずか深
く形成する。
In FIGS. 1 and 2, 1 is the ground, and 2 is an excavation area. In this embodiment, sheet piles are first driven along the planned line of the excavation area 2 to form a retaining wall 3. Next, a hardening agent is injected into the soil at a location spaced a predetermined distance rearward from this retaining wall 3 to form a hard ground layer 4. The hard ground layer 4 is formed to surround almost the entire excavation area 2 and to be slightly deeper than the depth of the vertical hole 5 to be excavated.

【0013】その後、山留壁3の内側の地盤土を適宜の
掘削機械を用いて掘削する。そして、所定深さだけ掘削
したところで一旦掘削を停止し(この時の地盤表面を図
1に二点鎖線で示す)、山留壁3から硬質地盤層4まで
達する細径の穴を掘削区域2の周方向に所定のピッチで
複数穿設し、各穴にアンカー6aを挿入して、該アンカ
ー6aの先端部を硬質地盤層4内に定着させる一方、そ
の基端部を山留壁3に締め具7を用いて締付け固定する
。次に、再び掘削区域2内の地盤土の掘削を開始し、所
定深さだけ掘削が進んだところで、再び前記したと同様
の手順により山留壁3と硬質地盤層4とをアンカー6b
により連結し、その後、さらに掘削を進めてアンカー6
cにより山留壁3と硬質地盤層4を連結する。なお、図
2においてはアンカーを統括的に符号6で示している。
[0013] Thereafter, the ground soil inside the retaining wall 3 is excavated using a suitable excavation machine. Then, once the excavation has been excavated to a predetermined depth, the excavation is temporarily stopped (the ground surface at this time is shown by the two-dot chain line in Figure 1), and a small diameter hole is excavated from the retaining wall 3 to the hard ground layer 4 in the excavation area 2. A plurality of anchors 6a are inserted into each hole at a predetermined pitch in the circumferential direction, and the tip of the anchor 6a is fixed in the hard ground layer 4, while the base end is fixed in the retaining wall 3. Tighten and fix using the fastener 7. Next, excavation of the ground within the excavation area 2 is started again, and when the excavation has progressed to a predetermined depth, the retaining wall 3 and the hard ground layer 4 are attached to the anchor 6b again by the same procedure as described above.
After that, further excavation is carried out and anchor 6 is connected.
c connects the mountain retaining wall 3 and the hard ground layer 4. In addition, in FIG. 2, the anchor is generally indicated by the reference numeral 6.

【0014】このようにして、所定の深さの立穴5が形
成されるが、アンカー6の先端部が硬質地盤層4に定着
されているため、その引抜き抵抗が著しく増大し、この
結果、山留壁3の補強は十分となって土砂崩れを起こす
心配はなくなる。しかも、硬質地盤層4を掘削区域に近
接して設けることにより、強固な地盤を求めてアンカー
6を長く延ばす必要もなくなり、施工能率は向上する。 さらに山留壁3と硬質地盤層4との間の部分D(図1)
がアンカー6を介して一体となって土圧に抵抗するので
、立穴5の周囲の地盤はきわめて安定する。
In this way, the vertical hole 5 of a predetermined depth is formed, but since the tip of the anchor 6 is fixed to the hard ground layer 4, its pull-out resistance increases significantly, and as a result, The mountain retaining wall 3 is sufficiently reinforced and there is no need to worry about landslides. Moreover, by providing the hard ground layer 4 close to the excavated area, there is no need to extend the anchor 6 long in search of strong ground, and construction efficiency is improved. Furthermore, the part D between the mountain retaining wall 3 and the hard ground layer 4 (Fig. 1)
The ground around the vertical hole 5 is extremely stable because they work together through the anchor 6 to resist earth pressure.

【0015】[0015]

【発明の効果】以上、詳細に説明したように、本発明に
かゝる山留め安定工法によれば、掘削区域に近接してそ
の周りに硬質地盤層を形成して、この硬質地盤層にアン
カーの先端部を定着させるようにしたので、アンカーを
長く延ばさなくても山留壁を確実に補強できるようにな
り、工期の大幅な短縮はもとより、施工費用の大幅な低
減を達成できる。また、山留壁と硬質地盤層との間の部
分が一体化してきわめて安定となるので、工事の安全性
はより一層高まるようになる。しかも、工事範囲の隣地
への拡大を規制できるので、スペース的な制約の多いビ
ル工事、トンネル工事等に用いて好適となる。
Effects of the Invention As explained above in detail, according to the mountain retaining stabilization method according to the present invention, a hard ground layer is formed near and around the excavation area, and anchors are attached to this hard ground layer. Since the tip of the anchor is anchored, the retaining wall can be reliably reinforced without having to extend the anchor for a long time, which not only significantly shortens the construction period, but also significantly reduces construction costs. Additionally, the area between the retaining wall and the hard ground layer is integrated and becomes extremely stable, further increasing the safety of the construction work. Moreover, since it is possible to restrict the expansion of the construction area to adjacent land, it is suitable for use in building construction, tunnel construction, etc. where there are many space constraints.

【図面の簡単な説明】[Brief explanation of drawings]

【図1】本発明にかゝる山留め安定工法による施工態様
を示す断面図である。
FIG. 1 is a sectional view showing a construction mode using the stabilizing construction method for retaining mountains according to the present invention.

【図2】本山留め安定工法による施工態様を示す平面図
である。
FIG. 2 is a plan view showing a construction mode using the Motoyama-dome stable construction method.

【符号の説明】[Explanation of symbols]

1  地盤 2  掘削区域 3  山留壁 4  硬質地盤層 5  立穴 6  アンカー 6a アンカー 6b アンカー 6c アンカー 1. Ground 2. Excavation area 3 Mountain retaining wall 4 Hard ground layer 5 Standing hole 6 Anchor 6a Anchor 6b Anchor 6c anchor

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  掘削区域に近接してその周りに硬化剤
で固めた硬質地盤層を形成し、前記掘削区域の計画線に
沿って打設した山留壁の内側を所定深さだけ掘削するご
とに、該山留壁と前記硬質地盤層とをアンカーにて連結
することを特徴とする山留め安定工法
[Claim 1] A hard ground layer hardened with a hardening agent is formed near and around the excavated area, and the inside of a retaining wall cast along the planned line of the excavated area is excavated to a predetermined depth. A method for stabilizing mountain retaining construction, characterized in that the mountain retaining wall and the hard ground layer are connected by anchors.
JP13583091A 1991-05-10 1991-05-10 Landslide protection stabilizing construction method Pending JPH04336117A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13583091A JPH04336117A (en) 1991-05-10 1991-05-10 Landslide protection stabilizing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13583091A JPH04336117A (en) 1991-05-10 1991-05-10 Landslide protection stabilizing construction method

Publications (1)

Publication Number Publication Date
JPH04336117A true JPH04336117A (en) 1992-11-24

Family

ID=15160782

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13583091A Pending JPH04336117A (en) 1991-05-10 1991-05-10 Landslide protection stabilizing construction method

Country Status (1)

Country Link
JP (1) JPH04336117A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8898996B2 (en) 2011-09-27 2014-12-02 Maurice Garzon Method for forming a retaining wall, and corresponding retaining wall
JP2017031727A (en) * 2015-08-04 2017-02-09 株式会社大林組 Deformation suppressing structure for earth retaining wall and deformation suppressing method for earth retaining wall
JP2017197910A (en) * 2016-04-25 2017-11-02 鹿島建設株式会社 Construction method of earth retaining wall structure, and earth retaining wall structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0387416A (en) * 1989-08-30 1991-04-12 Taisei Corp Land slide protection works for weak ground

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0387416A (en) * 1989-08-30 1991-04-12 Taisei Corp Land slide protection works for weak ground

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8898996B2 (en) 2011-09-27 2014-12-02 Maurice Garzon Method for forming a retaining wall, and corresponding retaining wall
JP2017031727A (en) * 2015-08-04 2017-02-09 株式会社大林組 Deformation suppressing structure for earth retaining wall and deformation suppressing method for earth retaining wall
JP2017197910A (en) * 2016-04-25 2017-11-02 鹿島建設株式会社 Construction method of earth retaining wall structure, and earth retaining wall structure

Similar Documents

Publication Publication Date Title
JP3824114B2 (en) Whale bone method for large section tunnel
CN107060803A (en) A kind of method for tunnel construction of utilization pipe curtain slip casting
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JP7053402B2 (en) Rectangular shaft and its construction method
JP4485006B2 (en) Construction method for underground structures
JPH04336117A (en) Landslide protection stabilizing construction method
KR100432782B1 (en) Supporting structure for tunnel and underground tunnel construction method using the same
JPH086318B2 (en) How to bury wooden piles
JP3200240B2 (en) Filling method of self-hardening material in ground reinforcement method
JP2874906B2 (en) Shaft construction method
KR200354672Y1 (en) Wall Structure by Steel-column Pile Recovery Process
JP2000178966A (en) Structure of diaphragm wall
JPH04115024A (en) Sheathing method
JPH073777A (en) Method for constructing self-supporting land slide protection wall
JP2675858B2 (en) Vertical shaft excavation method
JPS61134496A (en) Departure of shield excavator
JP2002147164A (en) Tunnel construction method and tunnel
KR200279246Y1 (en) Supporting structure for tunnel
JP2022100109A (en) Subsidence prevention structure for adjacent building and method thereof
JPH11336466A (en) Construction method of tunnel
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
JP2002021063A (en) Method for constructing earth retaining wall
JP2004238981A (en) Method for constructing tunnel
JPS60233226A (en) Sealing structure for landslide protection wall anchor insertion hole