JP2601140B2 - Independent mountain retaining wall method - Google Patents

Independent mountain retaining wall method

Info

Publication number
JP2601140B2
JP2601140B2 JP15004493A JP15004493A JP2601140B2 JP 2601140 B2 JP2601140 B2 JP 2601140B2 JP 15004493 A JP15004493 A JP 15004493A JP 15004493 A JP15004493 A JP 15004493A JP 2601140 B2 JP2601140 B2 JP 2601140B2
Authority
JP
Japan
Prior art keywords
retaining wall
pile
formation
excavation
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP15004493A
Other languages
Japanese (ja)
Other versions
JPH073796A (en
Inventor
耕喜 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP15004493A priority Critical patent/JP2601140B2/en
Publication of JPH073796A publication Critical patent/JPH073796A/en
Application granted granted Critical
Publication of JP2601140B2 publication Critical patent/JP2601140B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】地盤を掘削する場合、周囲地盤の
崩壊を防ぐために行う山留め壁工事に関する。
BACKGROUND OF THE INVENTION The present invention relates to a retaining wall construction for excavating a ground to prevent collapse of a surrounding ground.

【0002】[0002]

【従来の技術】軟弱地盤で、掘削平面が大きく、例えば
一辺が100mを超える場合とか、河川、海等に近接し
た地域、または傾斜地等で片側に土圧を受けるような場
合、従来から水平切梁工法、地盤アンカー工法、アイラ
ンド工法が用いられている。
2. Description of the Related Art Conventionally, when excavation plane is large on a soft ground, for example, when one side exceeds 100 m, or when earth pressure is applied to one side in an area close to a river, the sea, or a slope, etc., a horizontal cutting has been conventionally performed. The beam method, the ground anchor method, and the island method are used.

【0003】[0003]

【発明が解決しようとする課題】従来から用いられてい
る水平切梁工法は、一辺100m程度の掘削面積の場合
とか、河川、海等に近接した地域又は傾斜地等で片側か
ら土圧をうけるような場合、最早水平切梁によって軸力
を支承することが困難となり、軸力のバラツキも多く山
留め壁の品質保証が出来なくなる。また、このような条
件の下で採用される斜め地盤アンカー工法は、敷地条件
に制約を受け採用困難な場合が多い。
Conventionally, the horizontal beam cutting method is used in a case where the excavation area is about 100 m on a side, or in a region close to a river, the sea, or an inclined land, or the like, in which earth pressure is applied from one side. In such a case, it is no longer possible to support the axial force by the horizontal beam, and the axial force varies so much that the quality of the retaining wall cannot be guaranteed. In addition, the diagonal ground anchor method adopted under such conditions is often difficult to adopt due to restrictions on site conditions.

【0004】そこでこのような場合は、アイランド工法
が採用されるが、この工法は分割工事になることから工
期が長期にわたり、建設コストも嵩み好まれないのが現
状である。
[0004] In such a case, the island construction method is adopted. However, since this construction method is a division work, the construction period is long, the construction cost is high, and it is not preferred at present.

【0005】そこで泥水処理が不要で、排出泥土も他の
場所打ちRC山留め工法に比べて少なく、工期も短く経
済性の高いソイルセメント柱列山留め壁が考えられる
が、ソイルセメント柱列山留め壁単独では、土圧に対し
て自立山留め壁としての強度及び剛性の不足により、安
定した山留め壁の品質が期待できない。
[0005] Therefore, a soil cement pillar retaining wall which requires no muddy water treatment, discharges less mud than the other cast-in-place RC retaining method, has a shorter construction period, and is more economical can be considered. In this case, stable strength of the retaining wall cannot be expected due to insufficient strength and rigidity of the self-standing retaining wall against earth pressure.

【0006】これらの問題を解決するため、切梁を使用
せずソイルセメント柱列山留め壁の長所を利用した自立
山留め壁工法を提供するのが本発明の目的である。
[0006] In order to solve these problems, it is an object of the present invention to provide a self-standing mountain retaining wall construction method that utilizes the advantages of a soil cement pillar row retaining wall without using a beam.

【0007】[0007]

【課題を解決するための手段】ソイルセメント柱列山留
め壁を造成し、地盤掘削側に現場造成杭を造成し、一次
掘削し、前記造成杭毎に該造成杭とソイルセメント柱列
山留め壁の間隙に1ケの直方形箱状部材と2ケの台形箱
状部材を充当し、造成杭との間隙に充填材を注入し、部
材同志をボルト締結して造成杭と一体化し、該造成杭と
造成杭の間のソイルセメント柱列山留め壁に沿わせて、
H形鋼の腹起しを充当し、前記直方形箱状部材とボルト
締結し、地盤の最終掘削を行い、掘削深さに応じて順次
直方形箱状部材と台形箱状部材とH形鋼の腹起しを施工
する。なお、現場造成杭には、偏芯してアンカー用スリ
ーブを設け、地盤にアンカーとなるPC鋼線を配線し隙
間をグラウトしPC鋼線を杭頂部で緊張して、造成杭に
所期圧縮応力を与え土圧に有効に抗力を発揮せしめる。
[MEANS FOR SOLVING THE PROBLEMS] A soil cement pillar row retaining wall is formed, an on-site construction pile is formed on the ground excavation side, and primary excavation is performed. The gap is filled with one rectangular box-shaped member and two trapezoidal box-shaped members, a filler is injected into the gap between the formation pile, the members are bolted together, and integrated with the formation pile. Along the soil cement pillar row retaining wall between
Applied the bulge of the H-shaped steel, bolted to the rectangular box-shaped member, performed the final excavation of the ground, and sequentially performed the rectangular box-shaped member, the trapezoidal box-shaped member, and the H-shaped steel according to the excavation depth. Construct the stomach. An off-center anchor sleeve is provided on the on-site development pile, a PC steel wire as an anchor is laid on the ground, the gap is grouted, and the PC steel wire is tensioned at the pile top, and the desired compression is applied to the development pile. Gives stress and effectively exerts resistance to earth pressure.

【0008】[0008]

【実施例】図1に本発明の実施例の平面図を示す。図に
向かって右側が掘削地盤である。
FIG. 1 is a plan view showing an embodiment of the present invention. The right side of the figure is the excavated ground.

【0009】以下本発明の工法を順を追って詳説する。Hereinafter, the method of the present invention will be described in detail step by step.

【0010】(イ)山留めを行おうとする位置にソイル
セメント柱列山留め壁1を造成する。
(A) A soil cement pillar row retaining wall 1 is formed at a position where the retaining is to be performed.

【0011】ソイルセメント柱列山留め壁1は、注入液
となるセメント系混濁液を原位置土と混合・撹拌し、オ
ーバーラップボーリングした掘削孔に、芯材を適切な間
隔で挿入することにより、柱列状に施工した山留め壁で
ある。芯材としてはH形鋼、I形鋼、鋼矢板等が用いら
れる。図1は連続的にH形鋼を挿入した例である。
[0011] The soil cement pillar-column retaining wall 1 is obtained by mixing and stirring a cement-based turbid liquid, which is an injection liquid, with the in-situ soil, and inserting a core material at appropriate intervals into an overlap bored excavation hole. It is a retaining wall constructed in a column shape. H-shaped steel, I-shaped steel, steel sheet pile and the like are used as the core material. FIG. 1 shows an example in which H-shaped steel is continuously inserted.

【0012】(ロ)次に地盤掘削側に前記ソイルセメン
ト柱列山留め壁1に近く現場造成杭用の孔2’を掘削す
る。
(B) Next, a hole 2 ′ for an on-site formation pile is excavated near the soil cement pillar row retaining wall 1 on the ground excavation side.

【0013】(ハ)造成杭2の補強のため鉄芯篭2”
を、前記掘削孔2’に挿入する。この場合、鉄芯篭2”
には、予めソイルセメント柱列山留め壁1側に偏芯した
位置に地盤アンカー用のスリーブ8を設定しておく。
(C) Iron core basket 2 ″ for reinforcing the formation pile 2
Into the borehole 2 ′. In this case, iron core basket 2 "
, A ground anchor sleeve 8 is set in advance at a position eccentric to the soil cement pillar row retaining wall 1 side.

【0014】(ニ)現場造成杭用削孔2’にコンクリー
トを打設する。
(D) Concrete is poured into the drilling hole 2 'for the on-site formation pile.

【0015】(ホ)地盤アンカー用スリーブ8を通して
アンカー用孔を支持層地盤まで削孔しPC鋼線9を配線
し隙間をグラウトして固化する。その後PC鋼線9を緊
張し、杭頂部で緊結し、造成杭2のソイルセメント柱列
山留め壁1側に初期圧縮応力を発生させる。
(E) An anchor hole is drilled through the ground anchor sleeve 8 to the support layer ground, a PC steel wire 9 is wired, and the gap is grouted and solidified. Thereafter, the PC steel wire 9 is tightened and tied at the top of the pile, and an initial compressive stress is generated on the soil cement pillar row retaining wall 1 side of the formed pile 2.

【0016】(へ)掘削地盤側を一次掘削する。(F) Primary excavation is performed on the excavation ground side.

【0017】(ト)造成杭2とソイルセメント柱列山留
め壁1前面に直方体箱状の補材3を充当する。更に該直
方体箱状の補材3と円柱系の造成杭2に、沿わせた2ケ
の台形箱状補材4を充当し、前記直方体箱状の補材3と
該台形箱状補材4をボルト締結5し造成杭2との間隙に
充填材を充填して、前記直方体箱状の補材3、前記台形
箱状補材4、造成杭2を一体化する。
(G) A rectangular parallelepiped box-shaped auxiliary material 3 is applied to the front surface of the formation pile 2 and the soil cement pillar row retaining wall 1. Further, two rectangular trapezoidal box-like supplements 4 are applied to the rectangular parallelepiped box-like supplementary materials 3 and the columnar forming piles 2, and the rectangular parallelepiped box-like supplementary materials 3 and the trapezoidal box-like supplementary materials 4 are applied. And filling the gap with the formation pile 2 with a filler to integrate the rectangular box-shaped supplement 3, the trapezoidal box-shaped supplement 4, and the formation pile 2.

【0018】(チ)造成杭2の直方体箱状の補材3と造
成杭2の直方体箱状の補材3間に、ソイルセメント柱列
山留め壁に沿ってH形鋼の腹起し7を充当して、前記直
方体箱状の補材3とボルト締結6する。
(H) Between the rectangular parallelepiped box-shaped supplementary material 3 of the formation pile 2 and the rectangular parallelepiped box-shaped supplementary material 3 of the formation pile 2, the bulging 7 of the H-shaped steel is formed along the soil cement pillar row retaining wall. Then, bolting 6 is performed with the rectangular parallelepiped box-shaped auxiliary member 3.

【0019】(リ)地盤の最終掘削を行い(ト)で行っ
たように地盤深さに応じて造成杭2の背面に直方体箱状
の補材3と台形箱状補材4を充当し、更にソイルセメン
ト柱列山留め壁1にそってH形鋼で腹起し7をボルト締
結する。
(I) The final excavation of the ground is performed, and the rectangular parallelepiped box-shaped supplementary material 3 and the trapezoidal box-shaped supplementary material 4 are applied to the back surface of the formation pile 2 according to the ground depth as performed in (g). Further, the swelling 7 is bolted with H-shaped steel along the soil cement pillar row retaining wall 1.

【0020】(ヌ)躯体を構築して腹起しを撤去する。(G) Construct a skeleton and remove the bulging.

【0021】図2は、図1のA視図であり図3は本発明
の工法を(a)〜(i)まで順を追って説明した図であ
る。
FIG. 2 is a view as viewed from A in FIG. 1, and FIG. 3 is a view for explaining the method of the present invention in order from (a) to (i).

【0022】(a) ソイルセメント柱列山留め壁を
施工 (b) 現場造成杭用孔掘削 (c) 地盤アンカー用スリーブ付鉄芯篭挿入 (d) 現場造成杭にコンクリート打設 (e) 地盤アンカー用孔掘削、PC鋼線配線、グラ
ウト、緊張 (f) 一次掘削 (g) 造成杭の背面の直方体箱状の補材、台形箱状
補材充当、H形鋼腹起し設定 (h) 最終掘削、必要に応じて造成杭背面の補材と
H形腹起し設定 (i) 躯体を構築して腹起し撤去
(A) Construction of pile retaining wall for soil cement columns (b) Drilling of holes for on-site construction piles (c) Insertion of iron core cage with sleeve for ground anchor (d) Concrete placement on on-site construction piles (e) Ground anchor Hole excavation, PC steel wire wiring, grout, tension (f) Primary excavation (g) Rectangular box-shaped supplementary material on the back of the created pile, trapezoidal box-shaped supplementary material application, H-shaped steel bulging setting (h) Final Excavation, if necessary, supplementary material on the back of the formation pile and setting of H-shape erection (i) Build the frame, erode and remove

【0023】[0023]

【発明の効果】本発明の効果は、ソイルセメント柱列山
留め壁と現場造成杭で山留めを行う。
The effect of the present invention is that the earth cement is carried out with the column cement pile retaining wall and the on-site formation pile.

【0024】ソイルセメント柱列山留め壁は浅い地盤の
掘削等特殊な場合を除き、強度及び剛性の不足のため切
梁が用いられていたが、現場造成杭とソイルセメント柱
列山留め壁を一体化する箱状及び台形補材の利用により
ソイルセメント柱列山留め壁の強度及び剛性を保持する
ことが出来る。
Except for special cases such as excavation of shallow ground, cut-off beams were used for the soil-cemented pillar pile retaining wall. The strength and rigidity of the soil cement pillar row retaining wall can be maintained by using the box-shaped and trapezoidal auxiliary materials.

【0025】又現場造成杭には、偏芯したアンカーが緊
張してあり初期圧縮応力を生じているので土圧を受ける
と有効に抗力を発揮する。従って掘削平面が大きい場合
とか、片側土圧を受ける場合などでも山留め壁の品質保
持が可能となる。さらに障害物のない地下空間での作業
が可能となり工事の省力化、プレファブ化、機械化など
えの展開が可能となり、工期短縮、労働条件の改善効果
を生む。
Further, the eccentric anchor is tensioned and generates initial compressive stress in the on-site formation pile, so that it effectively exerts resistance when subjected to earth pressure. Therefore, the quality of the retaining wall can be maintained even when the excavation plane is large or when one side receives earth pressure. In addition, it is possible to work in an underground space without obstacles, which makes it possible to save labor, prefab, and mechanize construction, shortening the construction period and improving working conditions.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の上面図である。FIG. 1 is a top view of the present invention.

【図2】図1のA視図である。FIG. 2 is a view as viewed from A in FIG. 1;

【図3】(a)〜(i)は施工手順を示す図である。FIGS. 3A to 3I are diagrams showing a construction procedure.

【符号の説明】[Explanation of symbols]

1・・・ソイルセメント柱列山留め壁、2・・・現場造
成杭、2’・・・現場造成杭用孔、2”・・・鉄芯篭、
3・・・直方体箱状の補材、4・・・台形箱状補材、5
・・・ボルト、6・・・ボルト、7・・・H形鋼腹起
し、8・・・地盤アンカー用スリーブ、9・・・PC鋼
線、10・・・躯体
1 ・ ・ ・ Soil cement pillar row retaining wall, 2 ・ ・ ・ Site creation pile, 2 ′ ・ ・ ・ Site hole for site creation pile, 2 ″ ・ ・ ・ Steel core cage,
3 ... rectangular box-shaped auxiliary material, 4 ... trapezoidal box-shaped auxiliary material, 5
··· Bolt, 6 ··· bolt, 7 ··· H-shaped steel protuberance, 8 ··· sleeve for ground anchor, 9 ··· PC steel wire, 10 ··· frame

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ソイルセメント柱列山留め壁を造成し、
地盤掘削側に現場造成杭を造成し、一次掘削し、前記造
成杭毎に該造成杭とソイルセメント柱列山留め壁の間隙
に1ケの直方形箱状部材と2ケの台形箱状部材を充当
し、造成杭との間隙に充填材を注入し、部材同志をボル
ト締結して造成杭と一体化し、該造成杭と造成杭の間の
ソイルセメント柱列山留め壁に沿わせて、H形鋼の腹起
しを充当し、前記直方形箱状部材とボルト締結し、地盤
の最終掘削を行い、掘削深さに応じて順次直方形箱状部
材と台形箱状部材とH形鋼の腹起しを施工することを特
徴とする自立山留め壁工法。
1. A soil cement pillar row retaining wall is formed,
On the ground excavation side, an on-site formation pile is created, primary excavation is performed, and one rectangular box-like member and two trapezoidal box-like members are provided in the gap between the formation pile and the soil cement column row retaining wall for each of the formation piles. Filling, injecting filler into the gap between the formation pile, fastening the members together with bolts and integrating them with the formation pile, and along the soil cement pillar row retaining wall between the formation pile and the formation pile, forming an H-shape Filling the steel belly, bolting to the rectangular box-shaped member, performing the final excavation of the ground, and sequentially according to the excavation depth, the rectangular box-shaped member, the trapezoidal box-shaped member, and the H-shaped steel Self-standing mountain retaining wall construction method characterized by erection.
【請求項2】 現場造成杭に偏芯してアンカー用スリー
ブを設け、地盤にアンカーとなるPC鋼線を配線し隙間
をグラウトしPC鋼線を杭頂部で緊張することを特徴と
する請求項1記載の自立山留め壁工法。
2. An anchor sleeve is provided eccentrically on an on-site formation pile, a PC steel wire serving as an anchor is laid on the ground, a gap is grouted, and the PC steel wire is tensioned at the top of the pile. The self-standing mountain retaining wall method according to 1.
JP15004493A 1993-06-22 1993-06-22 Independent mountain retaining wall method Expired - Lifetime JP2601140B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15004493A JP2601140B2 (en) 1993-06-22 1993-06-22 Independent mountain retaining wall method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15004493A JP2601140B2 (en) 1993-06-22 1993-06-22 Independent mountain retaining wall method

Publications (2)

Publication Number Publication Date
JPH073796A JPH073796A (en) 1995-01-06
JP2601140B2 true JP2601140B2 (en) 1997-04-16

Family

ID=15488283

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15004493A Expired - Lifetime JP2601140B2 (en) 1993-06-22 1993-06-22 Independent mountain retaining wall method

Country Status (1)

Country Link
JP (1) JP2601140B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001030704A1 (en) 1999-10-28 2001-05-03 Kazuto Hashizume Improved process for water treatment

Also Published As

Publication number Publication date
JPH073796A (en) 1995-01-06

Similar Documents

Publication Publication Date Title
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
CN103958780B (en) The method for forming cementing retaining wall
US3226933A (en) Sheeting wall system and method of constructing same
JP2007154413A (en) Soldier pile type earth retaining anchor type retaining wall and its construction method
KR102195504B1 (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
US3429126A (en) Method of producing a continuous bore pile wall
EP0070659A1 (en) Retaining wall and in situ method of construction
US20020071725A1 (en) Earth support and permanent structural foundation wall
JP2000352296A (en) Method o constructing passage just under underground structure
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
JP2601140B2 (en) Independent mountain retaining wall method
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
KR100477357B1 (en) Construction method for retaining of earth
US2007498A (en) Method of erecting an iron frame building having deep underground floors
JP2697558B2 (en) Independent mountain retaining wall method
JPH10131175A (en) Earth retaining wall and construction method thereof
JP2003301454A (en) Earth retaining wall and construction method for underground structure
JPH0734449A (en) Self standing type landslide protection wall construction method
JPS63280153A (en) Underground inverted lining method
JPS6018769B2 (en) Construction method of underground structure
JPH04115024A (en) Sheathing method
JP2657671B2 (en) Reconstruction method for existing structures
JPH03267493A (en) Auxiliary method in tunnel construction
JPH09111754A (en) Soldier pile cut-of wall construction method
JPH02266015A (en) Constructing underground continuous wall

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19961126