JP7293568B2 - Construction method of structures - Google Patents

Construction method of structures Download PDF

Info

Publication number
JP7293568B2
JP7293568B2 JP2022110399A JP2022110399A JP7293568B2 JP 7293568 B2 JP7293568 B2 JP 7293568B2 JP 2022110399 A JP2022110399 A JP 2022110399A JP 2022110399 A JP2022110399 A JP 2022110399A JP 7293568 B2 JP7293568 B2 JP 7293568B2
Authority
JP
Japan
Prior art keywords
underground structure
new
service
constructed
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2022110399A
Other languages
Japanese (ja)
Other versions
JP2022132363A (en
Inventor
雅路 青木
貴穂 河野
博人 熊谷
公章 方田
昭次 山川
稔 岡橋
俊介 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP2018009802A external-priority patent/JP7173460B2/en
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2022110399A priority Critical patent/JP7293568B2/en
Publication of JP2022132363A publication Critical patent/JP2022132363A/en
Application granted granted Critical
Publication of JP7293568B2 publication Critical patent/JP7293568B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

本発明は、構造物の施工方法に関する。 The present invention relates to a construction method for structures.

地下構造体の外周部を先行施工し、当該地下構造体の外周部を山留め壁として利用するトレンチカット工法が知られている(例えば、特許文献1参照)。 A trench cut method is known in which the outer periphery of an underground structure is constructed in advance and the outer periphery of the underground structure is used as a retaining wall (for example, see Patent Document 1).

特開平5-133108号公報JP-A-5-133108

ところで、平面視にて供用中地下構造物の隣に、新設地下構造体を備える構造物を施工する場合がある。この場合、平面視にて供用中地下構造物と隣り合う地盤を掘削すると、掘削領域、及びその周辺の地盤が浮き上がる可能性がある。この結果、供用中地下構造物も浮き上がり、当該供用中地下構造物が影響を受ける可能性がある。 By the way, there is a case where a structure including a new underground structure is constructed next to an in-service underground structure in plan view. In this case, when the ground adjacent to the in-service underground structure is excavated in plan view, the excavated area and the surrounding ground may rise. As a result, the in-service underground structure may also be lifted up, and the in-service underground structure may be affected.

これと同様に、平面視にて供用中地下構造物の隣にある既設地下構造体を解体し、新設地下構造体を備える構造物を施工する場合がある。この場合、既設地下構造体を解体すると、解体領域、及びその周辺の地盤が浮き上がる可能性がある。この結果、供用中地下構造物も浮き上がり、当該供用中地下構造物が影響を受ける可能性がある。 Similarly, there is a case where an existing underground structure next to an in-service underground structure in plan view is demolished and a structure equipped with a new underground structure is constructed. In this case, when the existing underground structure is demolished, there is a possibility that the demolished area and the surrounding ground will rise. As a result, the in-service underground structure may also be lifted up, and the in-service underground structure may be affected.

本発明は、上記の事実を考慮し、供用中地下構造物の浮き上がりを抑制することを目的とする。 SUMMARY OF THE INVENTION In view of the above facts, it is an object of the present invention to suppress the uplift of an underground structure during service.

第1態様に係る構造物の施工方法は、平面視にて供用中地下構造物と隣り合う新設地下構造体を有する構造物を施工する構造物の施工方法であって、前記新設地下構造体における前記供用中地下構造物側を、逆打ち工法によって施工する供用中地下構造物側施工工程と、施工された前記新設地下構造体の前記供用中地下構造物側に隣接して、該新設地下構造体の残部を施工する残部施工工程と、を備える。 A structure construction method according to a first aspect is a structure construction method for constructing a structure having a new underground structure adjacent to an in-service underground structure in a plan view, wherein the new underground structure an in-service underground structure side construction step of constructing the in-service underground structure side by a reverse construction method; and a remainder construction step for constructing the remainder of the body.

第1態様に係る構造物の施工方法によれば、先ず、供用中地下構造物側施工工程において、新設地下構造体における供用中地下構造物側を、逆打ち工法によって施工する。次に、残部施工工程において、施工された新設地下構造体の供用中地下構造物側に隣接して、新設地下構造体の残部を施工する。 According to the structure construction method according to the first aspect, first, in the in-service underground structure side construction step, the in-service underground structure side of the new underground structure is constructed by the reverse casting method. Next, in the remainder construction step, the remainder of the new underground structure is constructed adjacent to the in-service underground structure side of the constructed new underground structure.

このように本発明では、新設地下構造体における供用中地下構造物側を先行して施工する。これにより、新設地下構造体の掘削領域全体を同時に掘削する場合と比較して、掘削領域、及びその周辺の地盤の浮き上がりが抑制される。したがって、供用中地下構造物の浮き上がりが抑制される。 As described above, in the present invention, construction is performed first on the side of the underground structure that is in service in the new underground structure. As a result, lifting of the excavated area and the surrounding ground is suppressed compared to the case where the entire excavated area of the new underground structure is excavated at the same time. Therefore, the lifting of the underground structure during service is suppressed.

また、新設地下構造体における供用中地下構造物側を逆打ち工法によって施工することにより、新設地下構造体における供用中地下構造物側を順打ち工法によって施工する場合と比較して、掘削領域、及びその周辺の地盤の浮き上がりがさらに抑制される。したがって、供用中地下構造物の浮き上がりもさらに抑制される。 In addition, by constructing the in-service underground structure side of the new underground structure by the reverse construction method, compared with the case of constructing the in-service underground structure side of the new underground structure by the forward construction method, and the uplift of the ground around them is further suppressed. Therefore, the lifting of the underground structure during service is further suppressed.

第2態様に係る構造物の施工方法は、第1態様に係る構造物の施工方法において、前記供用中地下構造物側施工工程において、前記新設地下構造体が施工される掘削領域を、前記新設地下構造体における前記供用中地下構造物側が施工される第一領域と前記残部が施工される第二領域とに仮設山留め壁で仕切った状態で、前記第一領域を掘削する。 A structure construction method according to a second aspect is the structure construction method according to the first aspect, wherein in the in-service underground structure side construction step, an excavation area in which the new underground structure is to be constructed is The first region of the underground structure is excavated while being partitioned into a first region where the in-service underground structure side is constructed and a second region where the remainder is constructed by a temporary retaining wall.

第2態様に係る構造物の施工方法によれば、供用中地下構造物側施工工程において、新設地下構造体が施工される掘削領域を、新設地下構造体における供用中地下構造物側が施工される第一領域と、新設地下構造体の残部が施工される第二領域とに仮設山留め壁で仕切り、この状態で、掘削領域の第一領域を掘削する。これにより、掘削領域の第二領域に先行して、第一領域を容易に掘削することができる。 According to the structure construction method according to the second aspect, in the in-service underground structure side construction process, the in-service underground structure side of the new underground structure is constructed in the excavation area where the new underground structure is to be constructed. The first area and the second area where the remainder of the new underground structure will be constructed are partitioned by a temporary retaining wall, and the first area of the excavation area is excavated in this state. As a result, the first area can be easily excavated prior to the second area of the excavation area.

第3態様に係る構造物の施工方法は、平面視にて供用中地下構造物と隣り合う既設地下構造体を解体し、新設地下構造体を有する構造物を施工する構造物の施工方法であって、前記既設地下構造体における前記供用中地下構造物側を解体し、逆打ち工法によって前記新設地下構造体における供用中地下構造物側を施工する供用中地下構造物側施工工程と、残存する前記既設地下構造体の残存部を解体し、前記新設地下構造体における前記供用中地下構造物側に隣接して、該新設地下構造体の残部を施工する残部施工工程と、を備える。 A structure construction method according to the third aspect is a structure construction method in which an existing underground structure adjacent to an in-service underground structure in plan view is dismantled and a structure having a new underground structure is constructed. an in-service underground structure side construction step of dismantling the in-service underground structure side of the existing underground structure and constructing the in-service underground structure side of the new underground structure by a reverse construction method; and a remaining portion construction step of dismantling the remaining portion of the existing underground structure and constructing the remaining portion of the new underground structure adjacent to the in-service underground structure side of the new underground structure.

第3態様に係る構造物の施工方法によれば、先ず、供用中地下構造物側施工工程において、既設地下構造体における供用中地下構造物側を解体し、逆打ち工法によって新設地下構造体における供用中地下構造物側を施工する。次に、残部施工工程において、残存する既設地下構造体の残存部を解体し、新設地下構造体における供用中地下構造物側に隣接して、新設地下構造体の残部を施工する。 According to the structure construction method according to the third aspect, first, in the in-service underground structure side construction process, the in-service underground structure side of the existing underground structure is dismantled, and the new underground structure is constructed by the reverse construction method. During service, the underground structure side will be constructed. Next, in the remainder construction process, the remaining portion of the existing underground structure is dismantled, and the remainder of the new underground structure is constructed adjacent to the in-service underground structure side of the new underground structure.

このように本発明では、新設地下構造体における供用中地下構造物側を先行して施工する。つまり、本発明では、既設地下構造体における供用中地下構造物側を先行して解体する。これにより、既設地下構造体全体を同時に解体する場合と比較して、既設地下構造体の解体領域、及びその周辺の地盤の浮き上がりが抑制される。したがって、供用中地下構造物の浮き上がりが抑制される。 As described above, in the present invention, construction is performed first on the side of the underground structure that is in service in the new underground structure. That is, in the present invention, the in-service underground structure side of the existing underground structure is dismantled first. As a result, compared to the case where the entire existing underground structure is demolished at the same time, the uplift of the ground around the demolished region of the existing underground structure is suppressed. Therefore, the lifting of the underground structure during service is suppressed.

第4態様に係る構造物の施工方法は、第3態様に係る構造物の施工方法において、前記供用中地下構造物側施工工程において、前記既設地下構造体を前記供用中地下構造物側と前記残存部とを仕切壁で仕切った状態で、前記既設地下構造体の前記供用中地下構造物側を解体する。 A structure construction method according to a fourth aspect is the structure construction method according to the third aspect, wherein in the in-service underground structure side construction step, the existing underground structure is placed on the in-service underground structure side and the The existing underground structure is demolished on the side of the in-service underground structure while being separated from the remaining part by a partition wall.

第4態様に係る構造物の施工方法によれば、供用中地下構造物側施工工程において、既設地下構造体を供用中地下構造物側と残存部とに仕切壁で仕切り、この状態で、既設地下構造体の供用中地下構造物側を解体する。これにより、既設地下構造体の残存部に先行して、既設地下構造体の供用中地下構造物側を容易に解体することができる。 According to the structure construction method according to the fourth aspect, in the in-service underground structure side construction process, the existing underground structure is partitioned into the in-service underground structure side and the remaining part by the partition wall, and in this state, the existing underground structure The underground structure side will be dismantled while the underground structure is in service. As a result, the in-service underground structure side of the existing underground structure can be easily dismantled prior to the remaining portion of the existing underground structure.

以上説明したように、本発明によれば、供用中地下構造物の浮き上がりを抑制することができる。 As described above, according to the present invention, it is possible to suppress the lifting of an underground structure during service.

第一実施形態に係る構造物の施工方法が適用される地盤を示す縦断面図である。1 is a vertical cross-sectional view showing ground to which a structure construction method according to a first embodiment is applied; FIG. 第一実施形態に係る構造物の施工方法によって施工された新設構造物を示す縦断面図である。1 is a vertical cross-sectional view showing a new structure constructed by a construction method for a structure according to the first embodiment; FIG. 第一実施形態に係る構造物の施工方法の施工過程を示す縦断面図である。It is a longitudinal cross-sectional view which shows the construction process of the construction method of the structure which concerns on 1st embodiment. 第一実施形態に係る構造物の施工方法の施工過程を示す縦断面図である。It is a longitudinal cross-sectional view which shows the construction process of the construction method of the structure which concerns on 1st embodiment. 第二実施形態に係る構造物の施工方法が適用される既設構造物を示す縦断面図である。FIG. 4 is a vertical cross-sectional view showing an existing structure to which the method for constructing a structure according to the second embodiment is applied; 第二実施形態に係る構造物の施工方法の施工過程を示す縦断面図である。It is a longitudinal cross-sectional view which shows the construction process of the construction method of the structure which concerns on 2nd embodiment. 第二実施形態に係る構造物の施工方法の施工過程を示す縦断面図である。It is a longitudinal cross-sectional view which shows the construction process of the construction method of the structure which concerns on 2nd embodiment. 第二実施形態に係る構造物の施工方法の施工過程を示す縦断面図である。It is a longitudinal cross-sectional view which shows the construction process of the construction method of the structure which concerns on 2nd embodiment. 第二実施形態に係る構造物の施工方法の変形例を示す縦断面図である。It is a longitudinal cross-sectional view which shows the modification of the construction method of the structure which concerns on 2nd embodiment. 第一実施形態に係る構造物の施工方法の変形例を示す縦断面図である。It is a longitudinal cross-sectional view which shows the modification of the construction method of the structure which concerns on 1st embodiment.

(第一実施形態)
先ず、第一実施形態について説明する。
(First embodiment)
First, the first embodiment will be explained.

図1に示されるように、本実施形態に係る構造物の施工方法は、供用中地下構造物16が設けられた地盤12に適用される。供用中地下構造物16は、例えば、営業中の鉄道(地下鉄)や道路とされており、地盤12(地中)に埋設されている。 As shown in FIG. 1, the structure construction method according to the present embodiment is applied to the ground 12 on which an underground structure 16 is provided during service. The in-service underground structure 16 is, for example, a railroad (subway) or a road in service, and is buried in the ground 12 (underground).

なお、供用中地下構造物16は、少なくとも一部が地盤12に埋設されていれば良い。 At least a part of the in-service underground structure 16 may be buried in the ground 12 .

(構造物)
図2に示されるように、本実施形態では、供用中地下構造物16の隣の地盤12(掘削領域R)を掘削して、新設構造物20を施工(構築)する。新設構造物20は、複数層からなり、平面視にて、供用中地下構造物16と隣り合って配置される。
(Structure)
As shown in FIG. 2, in this embodiment, the ground 12 (excavation area R) next to the in-service underground structure 16 is excavated to construct (construct) the new structure 20 . The new structure 20 consists of multiple layers, and is arranged adjacent to the in-service underground structure 16 in a plan view.

新設構造物20は、複数の柱22と、隣り合う柱22に架設される複数の梁24と、梁24に支持される床スラブ26とを有して構成される。なお、新設構造物20の内部の柱22は、構真柱用杭21に支持され、新設構造物20の外周の柱22は、後述する山留め壁30に支持される。なお、外周の柱22の下に構真柱用杭を施工し、当該構真柱用杭に外周の柱22を支持させても良い。 The new structure 20 is constructed by having a plurality of columns 22 , a plurality of beams 24 constructed between adjacent columns 22 , and a floor slab 26 supported by the beams 24 . The pillars 22 inside the new structure 20 are supported by the structural column piles 21, and the pillars 22 on the outer periphery of the new structure 20 are supported by the retaining wall 30 described later. In addition, it is also possible to construct a structure column pile under the outer peripheral column 22 and support the outer peripheral column 22 on the structure column pile.

新設構造物20は、地盤12中に設けられる新設地下構造体20Aと、地上に設けられる新設地上構造体20Bとを有している。新設地下構造体20Aは、地盤12の掘削領域Rに設けられる。また、新設地下構造体20Aの上には、新設地上構造体20Bが設けられる。 The new structure 20 has a new underground structure 20A provided in the ground 12 and a new aboveground structure 20B provided on the ground. A new underground structure 20A is provided in an excavation area R of the ground 12 . A new above ground structure 20B is provided on the new underground structure 20A.

なお、新設地下構造体20A及び新設地上構造体20Bは、単一層であっても良い。また、新設構造物20は、少なくとも新設地下構造体20Aを有していれば良く、新設地上構造体20Bは省略されても良い。また、新設構造物20は、構造物の一例である。 In addition, the new underground structure 20A and the new aboveground structure 20B may be of a single layer. Also, the new structure 20 may have at least the new underground structure 20A, and the new aboveground structure 20B may be omitted. Also, the new structure 20 is an example of a structure.

(構造物の施工方法)
次に、構造物の施工方法の一例について説明する。
(Construction method for structures)
Next, an example of a construction method for a structure will be described.

本実施形態に係る構造物の施工方法では、先ず、新設構造物20の供用中地下構造物16側の外周部20Yを逆打ち工法によって施工する。次に、新設構造物20の外周部20Y以外の本体部20Xを施工する。以下、本実施形態に係る構造物の施工方法を具体的に説明する。 In the structure construction method according to the present embodiment, first, the outer peripheral portion 20Y of the new structure 20 on the side of the in-service underground structure 16 is constructed by the reverse hammering method. Next, the body portion 20X of the new structure 20 other than the outer peripheral portion 20Y is constructed. Hereinafter, the construction method of the structure according to this embodiment will be specifically described.

なお、ここでいう新設構造物20の外周部20Yとは、供用中地下構造物16及び新設構造物20を含む縦断面において、新設構造物20の供用中地下構造物16側の1スパン以上の部分(1つの柱梁架構部分)を意味する。また、新設構造物20の外周部20Yは、新設構造物における供用中地下構造物側(の部位)の一例である。また、新設構造物20の本体部20Xは、新設構造物の残部の一例である。 In addition, the outer peripheral portion 20Y of the new structure 20 referred to here refers to one span or more of the new structure 20 on the side of the underground structure 16 in service in a longitudinal section including the underground structure 16 in service and the new structure 20. means a part (one column-beam frame part). In addition, the outer peripheral portion 20Y of the new structure 20 is an example of (part of) the in-service underground structure side of the new structure. Also, the body portion 20X of the new structure 20 is an example of the remainder of the new structure.

(山留め壁施工工程)
先ず、山留め壁施工工程について説明する。図1に示されるように、山留め壁施工工程では、地盤12の掘削領域Rの外周部に、山留め壁30を施工する。山留め壁30は、掘削領域Rを囲むように、例えば、平面視にて枠状に形成する。この山留め壁30のうち、供用中地下構造物16側の山留め壁30Aは、供用中地下構造物16と対向して配置されている。
(Earth retaining wall construction process)
First, the retaining wall construction process will be described. As shown in FIG. 1 , in the mountain retaining wall construction process, an earth retaining wall 30 is constructed on the outer periphery of the excavation region R of the ground 12 . The retaining wall 30 is formed, for example, in a frame shape in plan view so as to surround the excavation region R. As shown in FIG. Of the earth retaining walls 30, the earth retaining wall 30A on the side of the underground structure 16 in service is arranged to face the underground structure 16 in service.

なお、山留め壁30は、例えば、地中連続壁(コンクリート壁)や、地盤改良壁(ソイルセメント壁)、親杭横矢板等の鋼製壁によって形成されている。 The earth retaining wall 30 is formed of, for example, a diaphragm wall (concrete wall), a soil improvement wall (soil cement wall), or a steel wall such as a main pile horizontal sheet pile.

(供用中地下構造物側施工工程)
次に、供用中地下構造物側施工工程について説明する。図1に示されるように、供用中地下構造物側施工工程では、新設構造物20の外周部20Yを逆打ち工法によって施工する。具体的には、先ず、地盤12の掘削領域Rに、山留め壁30Aと対向する仮設山留め壁34を施工する。仮設山留め壁34は、例えば、親杭横矢板等の鋼製壁とされる。この仮設山留め壁34によって、掘削領域Rを供用中地下構造物16側の第一領域RYと、第一領域RY以外の第二領域RXとに仕切る。
(Construction process on the underground structure side during service)
Next, the construction process on the side of the underground structure that is in service will be described. As shown in FIG. 1, in the in-service underground structure side construction process, the outer peripheral portion 20Y of the new structure 20 is constructed by the reverse construction method. Specifically, first, in the excavated region R of the ground 12, a temporary earth retaining wall 34 is constructed so as to face the earth retaining wall 30A. The temporary retaining wall 34 is, for example, a steel wall such as a parent pile lateral sheet pile. The temporary retaining wall 34 divides the excavation area R into a first area RY on the side of the in-service underground structure 16 and a second area RX other than the first area RY.

なお、第一領域RYは、新設構造物20の本体部20Xが施工される領域とされ、第二領域RXは、新設構造物20の外周部20Yが施工される領域とされる。また、仮設山留め壁34は、親杭横矢板等の鋼製壁に限らず、地中連続壁(コンクリート壁)や、地盤改良壁(ソイルセメント壁)であっても良い。 The first region RY is the region where the main body portion 20X of the new structure 20 is constructed, and the second region RX is the region where the outer peripheral portion 20Y of the new structure 20 is constructed. Moreover, the temporary retaining wall 34 is not limited to a steel wall such as a parent pile horizontal sheet pile, but may be a diaphragm wall (concrete wall) or a soil improvement wall (soil cement wall).

次に、図3に示されるように、掘削領域Rのうち、第二領域RXを残して第一領域RYを図示しない重機等によって掘削し、新設構造物20の外周部20Yを逆打ち工法によって施工する。具体的には、先ず、第一領域RYの根切り底R1よりも下に、構真柱用杭21を施工するとともに、構真柱用杭21上に構真柱22を打設する。 Next, as shown in FIG. 3, the first region RY of the excavation region R is excavated by a heavy machine or the like (not shown) while leaving the second region RX, and the outer peripheral portion 20Y of the new structure 20 is formed by the reverse construction method. to construct. Specifically, first, below the root cut bottom R1 of the first region RY, the piles 21 for the structural columns are constructed, and the structural columns 22 are driven on the piles 21 for the structural columns.

次に、第一領域RYを所定深さまで掘削(一次掘削)し、新設構造物20(新設地上構造体20B)の外周部20Yの一階の梁24及び床スラブ26を施工する。なお、この段階で新設構造物20の本体部20Xの一階の梁24及び床スラブ26は、構真柱22で支持しても良い。この場合、これらの梁24及び床スラブ26は、山留め壁30A及び仮設山留め壁34を支持する山留め支保工として機能する。 Next, the first region RY is excavated (primary excavation) to a predetermined depth, and the first-floor beams 24 and floor slabs 26 of the outer peripheral portion 20Y of the new structure 20 (new ground structure 20B) are constructed. At this stage, the beams 24 and the floor slabs 26 of the main body 20X of the new structure 20 may be supported by the structural columns 22. In this case, these beams 24 and floor slabs 26 function as earth retaining shoring to support earth retaining wall 30A and temporary earth retaining wall 34 .

次に、第一領域RYを所定深さ(40L)まで掘削(二次掘削、三次掘削、四次掘削、、、)し、新設地下構造体20Aの外周部20Yを順次施工する。また、新設地下構造体20Aの外周部20Yの施工と並行して、新設地上構造体20Bの外周部20Yを順次施工する。具体的には、複数の構真柱22上に、新設地上構造体20Bの外周部20Yの一階の柱22を施工するとともに、新設地上構造体20Bの二階の梁24及び床スラブ26を施工する。この手順を繰り返すことにより、新設構造物20の外周部20Yを施工する。 Next, the first region RY is excavated (secondary excavation, tertiary excavation, quaternary excavation, etc.) to a predetermined depth (40L), and the outer peripheral portion 20Y of the new underground structure 20A is sequentially constructed. In parallel with construction of the outer peripheral portion 20Y of the new underground structure 20A, the outer peripheral portion 20Y of the new aboveground structure 20B is sequentially constructed. Specifically, on the plurality of structure columns 22, the first floor pillars 22 of the outer peripheral portion 20Y of the new ground structure 20B are constructed, and the second floor beams 24 and floor slabs 26 of the new ground structure 20B are constructed. do. By repeating this procedure, the outer peripheral portion 20Y of the new structure 20 is constructed.

(残部施工工程)
次に、残部施工工程について説明する。図4に示されるように、残部施工工程では、新設構造物20の外周部20Yに隣接して、新設構造物20の本体部20Xを逆打ち工法によって施工する。具体的には、先ず、第二領域RXの根切り底R1よりも下に、複数の構真柱用杭21を施工するとともに、各構真柱用杭21上に構真柱22を打設する。
(Remainder construction process)
Next, the remainder construction process will be described. As shown in FIG. 4, in the remaining construction process, the body portion 20X of the new structure 20 is constructed adjacent to the outer peripheral portion 20Y of the new structure 20 by the reverse hammering method. Specifically, first, a plurality of structure column piles 21 are constructed below the root cut bottom R1 of the second region RX, and a structure structure column 22 is driven on each structure column pile 21. do.

次に、第二領域RXを所定深さまで掘削(一次掘削)し、新設構造物20(新設地上構造体20B)の本体部20Xの一階の梁24及び床スラブ26を施工する。なお、新設構造物20の本体部20Xの一階の梁24及び床スラブ26は、構真柱22で支持する。また、これらの梁24及び床スラブ26は、山留め壁30及び仮設山留め壁34を支持する山留め支保工として機能する。 Next, the second region RX is excavated (primary excavation) to a predetermined depth, and the first floor beams 24 and floor slabs 26 of the main body portion 20X of the new structure 20 (new ground structure 20B) are constructed. The first floor beam 24 and the floor slab 26 of the main body 20X of the new structure 20 are supported by the structural column 22 . These beams 24 and floor slabs 26 also function as earth retaining shoring to support earth retaining walls 30 and temporary earth retaining walls 34 .

次に、第二領域RXを所定深さまで掘削(二次掘削、三次掘削、四次掘削、、、)し、新設地下構造体20Aの本体部20Xを順次施工する。また、新設地下構造体20Aの本体部20Xの施工と並行して、新設地上構造体20Bの本体部20Xを順次施工する。具体的には、複数の構真柱22上に、新設地上構造体20Bの本体部20Xの一階の柱22を施工するとともに、新設地上構造体20Bの二階の梁24及び床スラブ26を施工する。この手順を繰り返すことにより、新設構造物20の本体部20Xを施工する。その後、仮設山留め壁34を撤去する。なお、仮設山留め壁34は、新設地下構造体20Aの本体部20Xと外周部20Yとが、構造的に繋がれば撤去しても良い。 Next, the second region RX is excavated to a predetermined depth (secondary excavation, tertiary excavation, quaternary excavation, . Also, in parallel with the construction of the main body portion 20X of the new underground structure 20A, the main body portion 20X of the new aboveground structure 20B is sequentially constructed. Specifically, the first floor pillars 22 of the main body 20X of the new ground structure 20B are constructed on the plurality of structure columns 22, and the second floor beams 24 and floor slabs 26 of the new ground structure 20B are constructed. do. By repeating this procedure, the main body part 20X of the new structure 20 is constructed. After that, the temporary retaining wall 34 is removed. Note that the temporary retaining wall 34 may be removed if the body portion 20X and the outer peripheral portion 20Y of the new underground structure 20A are structurally connected.

なお、残部施工工程は、施工中の新設構造物20の外周部20Yの重量によって供用中地下構造物16の浮き上りを所定値以内に制限可能になった段階で実施可能であり、必ずしも新設構造物20の外周部20Yの完成を待つ必要はない。また、図示を省略するが、山留め壁30の内側には、コンクリート地下外壁を適宜施工しても良い。 It should be noted that the rest of the construction process can be carried out at a stage when the weight of the outer peripheral portion 20Y of the new structure 20 under construction can limit the uplift of the underground structure 16 in service to within a predetermined value, and the new structure does not necessarily need to be carried out. There is no need to wait for the completion of the outer peripheral portion 20Y of the object 20; Also, although not shown, a concrete underground outer wall may be appropriately constructed inside the retaining wall 30 .

(作用及び効果)
次に、本実施形態の作用及び効果について説明する。
(Action and effect)
Next, the operation and effects of this embodiment will be described.

例えば、図3に二点鎖線L1で示されるように、地盤12の掘削領域Rの全領域(第一領域RY及び第二領域RX)を一度に掘削すると、掘削領域Rの根切り底R1及びその周辺の地盤12が浮き上がる可能性がある。そして、掘削領域Rの周辺の地盤12が浮き上がると、供用中地下構造物16が浮き上がる可能性がある。 For example, as indicated by a two-dot chain line L1 in FIG. The surrounding ground 12 may rise. If the ground 12 around the excavation area R rises, the underground structure 16 may rise during use.

この対策として、本実施形態では、先ず、供用中地下構造物側施工工程において、新設構造物20の本体部20Xに先行して、新設構造物20の外周部20Yを逆打ち工法に施工する。つまり、掘削領域Rの第二領域RXに先行して、第一領域RYを掘削する。 As a countermeasure, in this embodiment, first, in the in-service underground structure side construction process, the outer peripheral portion 20Y of the new structure 20 is constructed by the reverse construction method prior to the main body portion 20X of the new structure 20. That is, prior to the second region RX of the excavation region R, the first region RY is excavated.

これにより、図3に二点鎖線L2で示されるように、掘削領域Rに残された第二領域RXの地盤12の重量によって、掘削領域R、及びその周辺の地盤12の浮き上がりが抑制される。さらに、掘削領域Rの第一領域RYに施工された新設構造物20の外周部20Yの重量によっても、掘削領域R、及びその周辺の地盤12の浮き上がりが抑制される。したがって、供用中地下構造物16の浮き上がりが抑制される。 As a result, as indicated by the two-dot chain line L2 in FIG. 3, the weight of the ground 12 in the second region RX left in the excavation region R suppresses the uplift of the excavation region R and the ground 12 in the vicinity thereof. . Furthermore, the weight of the outer peripheral portion 20Y of the new structure 20 constructed in the first region RY of the excavation region R also suppresses the uplift of the excavation region R and the ground 12 therearound. Therefore, the floating of the underground structure 16 during service is suppressed.

また、供用中地下構造物側施工工程では、新設構造物20の外周部20Yを逆打ち工法によって施工する。これにより、掘削領域Rの第一領域RYを根切り底R1まで掘削してから、新設構造物20の外周部20Yを施工する場合(順打ち工法)と比較して、供用中地下構造物16の浮き上がりがさらに抑制される。 In addition, in the in-service underground structure side construction process, the outer peripheral portion 20Y of the new structure 20 is constructed by the reverse construction method. As a result, after excavating the first region RY of the excavation region R to the excavation bottom R1, compared with the case of constructing the outer peripheral portion 20Y of the new structure 20 (sequential construction method), the underground structure 16 is further suppressed.

さらに、供用中地下構造物側施工工程において、掘削領域Rに仮設山留め壁34を仮設し、掘削領域Rを新設構造物20の外周部20Y用の第一領域RYと、新設構造物20の本体部20X用の第二領域RXとに仮設山留め壁34で仕切った状態で、掘削領域Rの第一領域RYを掘削する。これにより、掘削領域Rの第二領域RXに先行して、第一領域RYを容易に掘削することができる。 Furthermore, in the construction process on the side of the underground structure during use, a temporary retaining wall 34 is temporarily installed in the excavation area R, and the excavation area R is divided into the first area RY for the outer peripheral portion 20Y of the new structure 20 and the main body of the new structure 20. The first region RY of the excavation region R is excavated while being separated from the second region RX for the portion 20X by the temporary retaining wall 34 . As a result, the first region RY can be easily excavated prior to the second region RX of the excavation region R.

次に、残部施工工程では、掘削領域Rに残された第二領域RXの地盤12を掘削し、新設構造物20の本体部20Xを施工する。この残部施工工程では、新設構造物20の本体部20Xが施工されるまでは、新設構造物20の外周部20Yの重量によって、掘削領域R、及びその周辺の地盤12の浮き上がりが抑制される。したがって、供用中地下構造物16の浮き上がりが抑制される。 Next, in the remaining portion construction step, the ground 12 of the second region RX remaining in the excavation region R is excavated, and the main body portion 20X of the new structure 20 is constructed. In this rest construction process, the weight of the outer peripheral portion 20Y of the new structure 20 prevents the excavation region R and the surrounding ground 12 from lifting until the main body portion 20X of the new structure 20 is constructed. Therefore, the floating of the underground structure 16 during service is suppressed.

さらに、供用中地下構造物側施工工程では、新設構造物20の本体部20Xを逆打ち工法によって施工する。これにより、掘削領域Rの第二領域RXを根切り底R1(図2参照)まで掘削してから、新設構造物20の本体部20Xを施工する場合(順打ち工法)と比較して、供用中地下構造物16の浮き上がりがさらに抑制される。 Furthermore, in the in-service underground structure side construction process, the main body portion 20X of the new structure 20 is constructed by the reverse construction method. As a result, after excavating the second region RX of the excavation region R to the root cutting bottom R1 (see FIG. 2), compared to the case of constructing the main body portion 20X of the new structure 20 (sequence construction method), Uplift of the semi-underground structure 16 is further suppressed.

(第二実施形態)
次に、第二実施形態について説明する。なお、第二実施形態において、第一実施形態と同じ構成の部材等には、同符号を付して説明を適宜省略する。
(Second embodiment)
Next, a second embodiment will be described. In addition, in the second embodiment, members having the same configuration as those in the first embodiment are denoted by the same reference numerals, and description thereof is omitted as appropriate.

図5に示されるように、本実施形態に係る構造物の施工方法は、供用中地下構造物16及び既設構造物40が設けられた地盤12に適用される。既設構造物40は、既設地下構造体40A及び既設地上構造体40Bを有している。また、既設構造物40は、複数の柱42と、隣り合う柱42に架設される梁44と、梁44に支持される床スラブ46とを有して構成される。 As shown in FIG. 5, the structure construction method according to the present embodiment is applied to the ground 12 on which the underground structure 16 in service and the existing structure 40 are provided. The existing structure 40 has an existing underground structure 40A and an existing aboveground structure 40B. Also, the existing structure 40 includes a plurality of pillars 42 , beams 44 that span adjacent pillars 42 , and floor slabs 46 that are supported by the beams 44 .

既設地下構造体40Aは、平面視にて供用中地下構造物16と隣り合って配置されている。この既設地下構造体40Aの上には、既設地上構造体40Bが設けられている。なお、既設構造物40は、少なくとも既設地下構造体40Aを有していれば良く、既設地上構造体40Bは省略されても良い。 The existing underground structure 40A is arranged adjacent to the in-service underground structure 16 in plan view. An existing ground structure 40B is provided on the existing underground structure 40A. The existing structure 40 may have at least the existing underground structure 40A, and the existing aboveground structure 40B may be omitted.

(構造物の施工方法)
次に、本実施形態に係る構造物の施工方法の一例について説明する。
(Construction method for structures)
Next, an example of a construction method for a structure according to this embodiment will be described.

本実施形態に係る構造物の施工方法では、既設構造物40を解体して新設構造物20を構築する。つまり、本実施形態に係る構造物の施工方法は、既設構造物40の建て替え時に使用される。この際、本実施形態では、先ず、既設構造物40の本体部40Xを残して、既設構造物40の供用中地下構造物16側の外周部40Yを建て替える。その後、既設構造物40の本体部40Xを建て替える。これにより、供用中地下構造物16の浮き上がりを抑制する。 In the structure construction method according to the present embodiment, the existing structure 40 is dismantled and the new structure 20 is constructed. In other words, the method for constructing a structure according to this embodiment is used when the existing structure 40 is reconstructed. At this time, in this embodiment, first, the main body portion 40X of the existing structure 40 is left, and the outer peripheral portion 40Y of the existing structure 40 on the side of the in-service underground structure 16 is reconstructed. After that, the body part 40X of the existing structure 40 is rebuilt. As a result, floating of the underground structure 16 during service is suppressed.

また、本実施形態では、新設地下構造体20Aの深さが、既設地下構造体40Aの深さよりも浅い。そのため、新設地下構造体20Aよりも深い既設地下構造体40Aの部位(下部40L)は解体せず、新設地下構造体20Aの基礎として使用する。以下、本実施形態に係る構造物の施工方法を具体的に説明する。 Further, in this embodiment, the depth of the new underground structure 20A is shallower than the depth of the existing underground structure 40A. Therefore, the portion (lower portion 40L) of the existing underground structure 40A that is deeper than the new underground structure 20A is not dismantled and is used as the foundation of the new underground structure 20A. Hereinafter, the construction method of the structure according to this embodiment will be specifically described.

(供用中地下構造物側施工工程)
先ず、供用中地下構造物側施工工程について説明する。図6に示されるように、供用中地下構造物側施工工程では、先ず、既設地下構造体40Aの外周に山留め壁30を施工する。次に、解体される(解体予定の)既設地下構造体40Aの各階に、仮設仕切壁48を施工する。
(Construction process on the underground structure side during service)
First, the construction process on the side of the underground structure that is in service will be described. As shown in FIG. 6, in the in-service underground structure side construction process, first, the retaining wall 30 is constructed around the outer circumference of the existing underground structure 40A. Next, a temporary partition wall 48 is constructed on each floor of the existing underground structure 40A to be demolished (to be demolished).

なお、山留め壁30は省略し、既設地下構造体40Aの地下外壁40Wを山留め壁として利用することも可能である。 It is also possible to omit the retaining wall 30 and use the underground outer wall 40W of the existing underground structure 40A as the retaining wall.

仮設仕切壁48は、例えば、コンクリート壁や鋼製壁とされており、既設地下構造体40Aの供用中地下構造物16側に配置される。この仮設仕切壁48によって、既設地下構造体40Aを、供用中地下構造物16側の外周部40Yと、外周部40Y以外の本体部40Xとに仕切る。既設地下構造体40Aの外周部40Yは、新設地下構造体20Aの外周部20Yが施工される領域とされ、既設地下構造体40Aの本体部40Xは、新設地下構造体20Aの本体部20Xが施工される領域とされる。 The temporary partition wall 48 is, for example, a concrete wall or a steel wall, and is arranged on the in-service underground structure 16 side of the existing underground structure 40A. The temporary partition wall 48 partitions the existing underground structure 40A into an outer peripheral portion 40Y on the side of the in-service underground structure 16 and a main body portion 40X other than the outer peripheral portion 40Y. The outer peripheral portion 40Y of the existing underground structure 40A is an area where the outer peripheral portion 20Y of the new underground structure 20A is constructed, and the main body portion 40X of the existing underground structure 40A is constructed by the main body portion 20X of the new underground structure 20A. area.

次に、図7に示されるように、既設構造物40のうち、本体部40Xを残して外周部40Yを図示しない重機等によって解体し、新設構造物20の外周部(本体部)20Yを逆打ち工法によって施工する。 Next, as shown in FIG. 7, the outer peripheral portion 40Y of the existing structure 40 is dismantled with a heavy machine (not shown) while leaving the main body portion 40X. Constructed by hammering method.

具体的には、先ず、既設地下構造体40Aの外周部40Yの下部40L上に、構真柱22を施工する。次に、既設地下構造体40Aを図示しない重機等によって所定深さまで解体(一次解体)し、新設構造物20の外周部20Yの一階の梁24及び床スラブ26を施工する。 Specifically, first, the structural column 22 is constructed on the lower portion 40L of the outer peripheral portion 40Y of the existing underground structure 40A. Next, the existing underground structure 40A is dismantled (primary dismantling) to a predetermined depth by a heavy machine or the like (not shown), and the first-floor beams 24 and floor slabs 26 of the outer periphery 20Y of the new structure 20 are constructed.

なお、新設構造物20の本体部20Xの一階の梁24及び床スラブ26は、構真柱22で支持する。また、これらの梁24及び床スラブ26は、既設地下構造体40A(地下外壁40W)を支持する山留め支保工として機能する。 The first floor beam 24 and the floor slab 26 of the main body 20X of the new structure 20 are supported by the structural column 22 . Also, these beams 24 and floor slab 26 function as earth retaining shoring for supporting the existing underground structure 40A (underground outer wall 40W).

次に、第一領域RYを所定深さまで解体(二次解体、三次解体、、、)し、新設地下構造体20Aの外周部20Yを順次施工する。また、新設地下構造体20Aの外周部20Yの施工と並行して、新設地上構造体20Bの外周部20Yを順次施工する。具体的には、山留め壁30A及び構真柱22上に、新設地上構造体20Bの外周部20Yの一階の柱22を施工するとともに、当該外周部20Yの二階の梁24及び床スラブ26を施工する。この手順を繰り返すことにより、新設構造物20の外周部20Yを施工する。 Next, the first region RY is dismantled (secondary dismantling, tertiary dismantling, etc.) to a predetermined depth, and the outer peripheral portion 20Y of the new underground structure 20A is sequentially constructed. In parallel with construction of the outer peripheral portion 20Y of the new underground structure 20A, the outer peripheral portion 20Y of the new aboveground structure 20B is sequentially constructed. Specifically, on the retaining wall 30A and the structure column 22, the first floor column 22 of the outer peripheral portion 20Y of the new ground structure 20B is constructed, and the second floor beam 24 and the floor slab 26 of the outer peripheral portion 20Y are constructed. to construct. By repeating this procedure, the outer peripheral portion 20Y of the new structure 20 is constructed.

なお、既設地下構造体40Aの外周部40Yは、既設地下構造体における供用中地下構造物側の一例である。 It should be noted that the outer peripheral portion 40Y of the existing underground structure 40A is an example of the in-service underground structure side of the existing underground structure.

(残部施工工程)
次に、残部施工工程について説明する。図8に示されるように、残部施工工程では、既設構造物40の既設地下構造体40Aの本体部40Xを図示しない重機等によって解体し、新設構造物20の本体部20Xを施工する。その後、仮設仕切壁48を撤去する。
(Remainder construction process)
Next, the remainder construction process will be described. As shown in FIG. 8, in the remaining construction process, the main body portion 40X of the existing underground structure 40A of the existing structure 40 is dismantled by a heavy machine (not shown) or the like, and the main body portion 20X of the new structure 20 is constructed. After that, the temporary partition wall 48 is removed.

なお、残部施工工程は、施工中の新設構造物20の外周部20Yの重量によって供用中地下構造物16の浮き上りを所定値以内に制限可能になった段階で実施可能であり、必ずしも新設構造物20の外周部20Yの完成を待つ必要はない。 It should be noted that the rest of the construction process can be carried out at a stage when the weight of the outer peripheral portion 20Y of the new structure 20 under construction can limit the uplift of the underground structure 16 in service to within a predetermined value, and the new structure does not necessarily need to be carried out. There is no need to wait for the completion of the outer peripheral portion 20Y of the object 20;

また、図示を省略するが、山留め壁30の内側には、コンクリート地下外壁及び地下柱を適宜施工しても良い。また、既設地下構造体40Aの本体部40Xは、既設地下構造体の残存部の一例である。 Also, although not shown, concrete underground outer walls and underground pillars may be appropriately constructed inside the retaining wall 30 . Also, the body portion 40X of the existing underground structure 40A is an example of the remaining portion of the existing underground structure.

(作用及び効果)
次に、本実施形態の作用及び効果について説明する。
(Action and effect)
Next, the operation and effects of this embodiment will be described.

本実施形態に係る構造物の施工方法によれば、図7に示されるように、先ず、供用中地下構造物側施工工程において、既設構造物40の外周部40Yを解体し、新設構造物20の供用中地下構造物16側の外周部20Yを逆打ち工法によって施工する。 According to the structure construction method according to the present embodiment, as shown in FIG. The outer peripheral portion 20Y on the side of the underground structure 16 during use is constructed by the reverse hammering method.

これにより、残された既設構造物40の本体部40Xの重量によって、既設地下構造体40Aの解体領域、及びその周辺の地盤12の浮き上がりが抑制される。さらに、施工された新設構造物20の外周部20Yの重量によっても、既設地下構造体40Aの解体領域、及びその周辺の地盤12の浮き上がりが抑制される。したがって、供用中地下構造物16の浮き上がりが抑制される。 As a result, the weight of the remaining main body portion 40X of the existing structure 40 suppresses uplift of the demolished area of the existing underground structure 40A and the surrounding ground 12 . Furthermore, the weight of the outer peripheral portion 20Y of the constructed new structure 20 also suppresses uplift of the demolished area of the existing underground structure 40A and the surrounding ground 12 . Therefore, the floating of the underground structure 16 during service is suppressed.

また、供用中地下構造物側施工工程では、新設構造物20の外周部20Yを逆打ち工法によって施工する。これにより、既設構造物40の外周部40Yの下部40L以浅を解体してから、新設構造物20の外周部20Yを施工する場合(順打ち工法)と比較して、供用中地下構造物16の浮き上がりがさらに抑制される。 In addition, in the in-service underground structure side construction process, the outer peripheral portion 20Y of the new structure 20 is constructed by the reverse construction method. As a result, compared to the case where the outer peripheral portion 40Y of the existing structure 40 is dismantled from the lower portion 40L or shallower and then the outer peripheral portion 20Y of the new structure 20 is constructed (sequential construction method), the construction of the underground structure 16 during service is Floating is further suppressed.

さらに、供用中地下構造物側施工工程において、既設地下構造体40Aに仮設仕切壁48を仮設し、既設地下構造体40Aを外周部40Yと本体部40Xとに仕切った状態で、既設地下構造体40Aの外周部40Yを解体する。これにより、既設構造物40の本体部40Xに先行して、既設構造物40の外周部40Yを容易に解体することができる。 Furthermore, in the underground structure side construction process during service, a temporary partition wall 48 is temporarily installed in the existing underground structure 40A, and the existing underground structure 40A is partitioned into the outer peripheral portion 40Y and the main body portion 40X. The outer peripheral portion 40Y of 40A is dismantled. As a result, the outer peripheral portion 40Y of the existing structure 40 can be easily dismantled prior to the main body portion 40X of the existing structure 40. As shown in FIG.

次に、図8に示されるように、残部施工工程では、残された既設構造物40の本体部40Xを解体し、新設構造物20の本体部20Xを施工する。この供用中地下構造物側施工工程では、新設構造物20の本体部20Xが施工されるまでは、新設構造物20の外周部20Yによって、既設構造物40の本体部40Xの解体領域、及びその周辺の地盤12の浮き上がりが抑制される。したがって、供用中地下構造物16の浮き上がりが抑制される。 Next, as shown in FIG. 8, in the remainder construction process, the main body part 40X of the remaining existing structure 40 is dismantled, and the main body part 20X of the new structure 20 is constructed. In this in-service underground structure side construction process, until the main body part 20X of the new structure 20 is constructed, the outer peripheral part 20Y of the new structure 20 controls the dismantling area of the main body part 40X of the existing structure 40 and its demolition area. Uplift of the surrounding ground 12 is suppressed. Therefore, the floating of the underground structure 16 during service is suppressed.

また、残部施工工程において、新設構造物20の本体部20Xを逆打ち工法によって施工する。これにより、既設構造物40の本体部40Xの下部40L以浅を解体してから、新設構造物20の本体部20Xを施工する場合(順打ち工法)と比較して、供用中地下構造物16の浮き上がりがさらに抑制される。ただし、新設構造物20の本体部20Xは、順打ち工法及び逆打ち工法の何れの工法によっても施工可能である。 Also, in the remaining construction process, the main body portion 20X of the new structure 20 is constructed by the reverse construction method. As a result, compared to the case where the body portion 20X of the new structure 20 is constructed after demolishing the lower portion 40L or less of the body portion 40X of the existing structure 40 (sequential construction method), the construction of the underground structure 16 during service is reduced. Floating is further suppressed. However, the main body part 20X of the new structure 20 can be constructed by either the forward casting method or the reverse casting method.

(第二実施形態の変形例)
次に、第二実施形態の変形例について説明する。
(Modified example of the second embodiment)
Next, a modified example of the second embodiment will be described.

図9に示される変形例では、新設地下構造体20Aの深さが、既設地下構造体40Aの深さよりも深い。この場合は、既設地下構造体40Aに仮設仕切壁48を仮設し、既設地下構造体40Aを外周部40Yと本体部40Xとに仕切る。また、既設地下構造体40Aよりも深い地盤12に仮設山留め壁52を仮設し、第一領域RYと第二領域RXとに仕切る。これにより、新設地下構造体20Aの本体部20Xに先行して、新設地下構造体20Aの外周部20Yを容易に施工することができる。 In the modification shown in FIG. 9, the depth of the new underground structure 20A is deeper than the depth of the existing underground structure 40A. In this case, a temporary partition wall 48 is temporarily installed in the existing underground structure 40A to partition the existing underground structure 40A into the outer peripheral portion 40Y and the main body portion 40X. In addition, a temporary retaining wall 52 is temporarily installed in the ground 12 deeper than the existing underground structure 40A to divide it into a first area RY and a second area RX. This makes it possible to easily construct the outer peripheral portion 20Y of the new underground structure 20A prior to the main body portion 20X of the new underground structure 20A.

なお、仮設仕切壁48及び仮設山留め壁52は、例えば、地中連続壁(コンクリート壁)や、地盤改良壁(ソイルセメント壁)、親杭横矢板等の鋼製壁によって形成されても良い。 The temporary partition wall 48 and the temporary earth retaining wall 52 may be formed of, for example, a diaphragm wall (concrete wall), a ground improvement wall (soil cement wall), a steel wall such as a main pile lateral sheet.

(第一及び第二実施形態の変形例)
次に、上記第一実施形態及び第二実施形態の変形例について説明する。なお、以下では、上記第一実施形態を例に各種の変形例について説明するが、これらの変形例は、第二実施形態にも適宜適用可能である。
(Modified example of the first and second embodiments)
Next, modified examples of the first embodiment and the second embodiment will be described. Various modifications will be described below using the first embodiment as an example, but these modifications can also be applied to the second embodiment as appropriate.

図10に示される変形例のように、供用中地下構造物側施工工程において、新設地下構造体20Aの外周部20Yに、錘としての水槽60を仮設しても良い。これにより、供用中地下構造物16の浮上りをさらに抑制することができる。また、錘として水槽60を用いることにより、搬入及び撤去が容易となる。 As in the modification shown in FIG. 10, a water tank 60 as a weight may be temporarily installed on the outer peripheral portion 20Y of the new underground structure 20A in the in-service underground structure side construction process. As a result, uplift of the underground structure 16 that is in service can be further suppressed. Also, by using the water tank 60 as the weight, it becomes easier to carry in and remove.

なお、新設地下構造体20Aの外周部20Yには、少なくとも一つの水槽60を設置することができる。また、錘は、水槽60に限らず、他の部材を用いても良い。 At least one water tank 60 can be installed in the outer peripheral portion 20Y of the new underground structure 20A. Further, the weight is not limited to the water tank 60, and other members may be used.

また、上記第一実施形態では、新設構造物20の外周部20Yは、供用中地下構造物16及び新設構造物20を含む縦断面において、新設構造物20の供用中地下構造物16側の1スパン部分とされる。しかしながら、新設構造物20の外周部は、例えば、供用中地下構造物16及び新設構造物20を含む縦断面において、供用中地下構造物16側の1スパン部分以上(複数スパン部分)とされても良い。 In the first embodiment described above, the outer peripheral portion 20Y of the new structure 20 is located at the side of the in-service underground structure 16 of the new structure 20 in the longitudinal section including the in-service underground structure 16 and the new structure 20. It is considered as a span part. However, the outer peripheral portion of the new structure 20 is, for example, one span portion (multiple span portions) on the side of the in-service underground structure 16 in a longitudinal section including the in-service underground structure 16 and the new structure 20. Also good.

また、上記第一実施形態では、供用中地下構造物16が新設構造物20の片側にのみ配置されるが、上記第一実施形態はこれに限らない。供用中地下構造物は、例えば、新設構造物(構造物)の周囲に複数配置されていても良い。この場合、供用中地下構造物側施工工程では、例えば、新設地下構造体における複数の供用中地下構造物側をそれぞれ逆打ち工法によって施工する。 In addition, in the above-described first embodiment, the in-service underground structure 16 is arranged only on one side of the new structure 20, but the above-described first embodiment is not limited to this. A plurality of in-service underground structures may be arranged, for example, around a new structure (structure). In this case, in the in-service underground structure side construction process, for example, each of the plurality of in-service underground structure sides of the new underground structure is constructed by the reverse construction method.

以上、本発明の一実施形態について説明したが、本発明はこうした実施形態に限定されるものでなく、一実施形態及び各種の変形例を適宜組み合わせて用いても良いし、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。 Although one embodiment of the present invention has been described above, the present invention is not limited to such an embodiment, and one embodiment and various modifications may be used in combination as appropriate. It goes without saying that various aspects can be implemented without departing from the scope.

16 供用中地下構造物
20 新設構造物(構造物)
20A 新設地下構造体
20X 本体部(新設地下構造体の残部)
20Y 外周部(新設地下構造体における供用中地下構造物側)
40A 既設地下構造体
40X 本体部(既設地下構造体の残存部)
40Y 外周部(既設地下構造体における供用中地下構造物側)
48 仕切壁
16 Underground structure in service 20 New structure (structure)
20A new underground structure 20X main body (remainder of new underground structure)
20Y Periphery (underground structure side in service in new underground structure)
40A Existing underground structure 40X Main body (remaining part of existing underground structure)
40Y Peripheral part (underground structure side in service in the existing underground structure)
48 partition wall

Claims (2)

平面視にて供用中地下構造物と隣り合う既設地下構造体を解体し、新設地下構造体を有する構造物を施工する構造物の施工方法であって、
前記既設地下構造体における前記供用中地下構造物側のみを解体し、逆打ち工法によって前記新設地下構造体における前記供用中地下構造物側を施工する供用中地下構造物側施工工程と、
残存する前記既設地下構造体の残存部を解体し、前記新設地下構造体における前記供用中地下構造物側に隣接して、該新設地下構造体の残部を施工する残部施工工程と、
を備える構造物の施工方法。
A structure construction method for dismantling an existing underground structure adjacent to an in-service underground structure in plan view and constructing a structure having a new underground structure,
an in-service underground structure side construction step of dismantling only the in-service underground structure side of the existing underground structure and constructing the in-service underground structure side of the new underground structure by a reverse construction method;
a remainder construction step of dismantling the remaining part of the existing underground structure and constructing the remaining part of the new underground structure adjacent to the in-service underground structure side of the new underground structure;
Construction method of a structure comprising
前記供用中地下構造物側施工工程において、前記既設地下構造体を前記供用中地下構造物側と前記残存部とを仕切壁で仕切った状態で、前記既設地下構造体の前記供用中地下構造物側を解体する、In the in-service underground structure side construction step, the in-service underground structure side of the existing underground structure is separated from the remaining part by a partition wall. dismantle the side,
請求項1に記載の構造物の施工方法。A construction method for a structure according to claim 1 .
JP2022110399A 2018-01-24 2022-07-08 Construction method of structures Active JP7293568B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2022110399A JP7293568B2 (en) 2018-01-24 2022-07-08 Construction method of structures

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2018009802A JP7173460B2 (en) 2018-01-24 2018-01-24 Construction method of structures
JP2022110399A JP7293568B2 (en) 2018-01-24 2022-07-08 Construction method of structures

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2018009802A Division JP7173460B2 (en) 2018-01-24 2018-01-24 Construction method of structures

Publications (2)

Publication Number Publication Date
JP2022132363A JP2022132363A (en) 2022-09-08
JP7293568B2 true JP7293568B2 (en) 2023-06-20

Family

ID=86772615

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2022110399A Active JP7293568B2 (en) 2018-01-24 2022-07-08 Construction method of structures

Country Status (1)

Country Link
JP (1) JP7293568B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201809774U (en) 2010-09-16 2011-04-27 中建三局建设工程股份有限公司 Foundation ditch support replacement and inner support removal construction structure
JP2012082676A (en) 2011-04-11 2012-04-26 Takenaka Komuten Co Ltd Displacement controlling method
JP2012107430A (en) 2010-11-17 2012-06-07 Shimizu Corp Construction method of underground structure
JP2017166139A (en) 2016-03-14 2017-09-21 大成建設株式会社 Construction method of underground structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58173226A (en) * 1982-04-01 1983-10-12 Kawasaki Steel Corp Construction of underground structure using temporary underground cut beam
JP2571426B2 (en) * 1988-11-11 1997-01-16 株式会社竹中工務店 Construction method of retaining wall
JPH07119465B2 (en) * 1990-03-02 1995-12-20 清水建設株式会社 Underground excavation construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201809774U (en) 2010-09-16 2011-04-27 中建三局建设工程股份有限公司 Foundation ditch support replacement and inner support removal construction structure
JP2012107430A (en) 2010-11-17 2012-06-07 Shimizu Corp Construction method of underground structure
JP2012082676A (en) 2011-04-11 2012-04-26 Takenaka Komuten Co Ltd Displacement controlling method
JP2017166139A (en) 2016-03-14 2017-09-21 大成建設株式会社 Construction method of underground structure

Also Published As

Publication number Publication date
JP2022132363A (en) 2022-09-08

Similar Documents

Publication Publication Date Title
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
JP4722783B2 (en) Foundation reinforcement method for existing buildings
JP6274406B2 (en) Construction method of new underground structure with dismantling of existing underground structure
JP6543176B2 (en) Building method
CN102444130A (en) Support replacing construction method in deep foundation pit project
JP2017210787A (en) Aseismatic structure of cut-and-cover tunnel
JP5038170B2 (en) How to rebuild a structure
JP7173460B2 (en) Construction method of structures
JP7173459B2 (en) Construction method of structures
JP7293568B2 (en) Construction method of structures
JP6441030B2 (en) How to add underground facilities
JP7293567B2 (en) Construction method of structures
JP7338119B2 (en) Floating control structure and reversed construction method
JP6693115B2 (en) Underground construction method
KR20130021949A (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR101481073B1 (en) Method for removing underground structure
JP2005002671A (en) Underpinning method and viaduct
JP7230313B2 (en) Basement structure and construction method of basement
JP6827256B2 (en) How to rebuild the building
JP6710999B2 (en) Temporary receiving method for existing structures
JP2017119953A (en) Building method using reverse out method
JP6938198B2 (en) Construction method
JP2020125630A (en) Building construction method
JP6543177B2 (en) Building method
JP7193065B2 (en) Reverse construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220708

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230131

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230330

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230509

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230519

R150 Certificate of patent or registration of utility model

Ref document number: 7293568

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150