JP6046984B2 - Seismic isolation construction method and precast concrete footing - Google Patents

Seismic isolation construction method and precast concrete footing Download PDF

Info

Publication number
JP6046984B2
JP6046984B2 JP2012246340A JP2012246340A JP6046984B2 JP 6046984 B2 JP6046984 B2 JP 6046984B2 JP 2012246340 A JP2012246340 A JP 2012246340A JP 2012246340 A JP2012246340 A JP 2012246340A JP 6046984 B2 JP6046984 B2 JP 6046984B2
Authority
JP
Japan
Prior art keywords
footing
column
foundation
concrete
seismic isolation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012246340A
Other languages
Japanese (ja)
Other versions
JP2014095201A (en
Inventor
今井 敬
敬 今井
渡辺 隆
隆 渡辺
昌志 ▲高▼田
昌志 ▲高▼田
壮一郎 九嶋
壮一郎 九嶋
亨司 川田
亨司 川田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2012246340A priority Critical patent/JP6046984B2/en
Publication of JP2014095201A publication Critical patent/JP2014095201A/en
Application granted granted Critical
Publication of JP6046984B2 publication Critical patent/JP6046984B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Description

本発明は、免震基礎の施工方法及びプレキャストコンクリートフーチングに関する。   The present invention relates to a base isolation construction method and a precast concrete footing.

積層ゴムの上部フランジに、上面から複数のアンカー部材が突出したプレキャスト製のPCa盤を載置して連結した後、PCa盤の上にコンクリートを打設して上部基礎を構築する免震基礎の施工方法が知られている(例えば、特許文献1参照)。   A precast PCa board with a plurality of anchor members projecting from the top surface is connected to the upper flange of the laminated rubber, and then the concrete is placed on the PCa board to construct the upper foundation. A construction method is known (see, for example, Patent Document 1).

特開2012−067524号公報JP 2012-067524 A

しかしながら、特許文献1に開示された技術では、免震装置上に柱を立てる場合、上部基礎に後施工アンカー等を打ち込んだり、上部基礎の施工時に柱用のアンカー等を組み込んだりする必要があるため、柱の施工に手間がかかる。   However, in the technique disclosed in Patent Document 1, when a column is set up on a seismic isolation device, it is necessary to drive a post-construction anchor or the like into the upper foundation, or to incorporate a column anchor or the like when constructing the upper foundation. Therefore, it takes time to construct the pillar.

本発明は、上記の事実を考慮し、免震装置上に立てる柱の施工性を向上させることを目的とする。   In view of the above facts, an object of the present invention is to improve the workability of a column standing on a seismic isolation device.

第1態様に係る免震基礎の施工方法は、下部基礎に設置された免震装置の上に、柱と連結されるアンカー部材、又は前記柱を構成する柱部材が設けられたプレキャストコンクリート製のフーチングを設置するフーチング設置工程と、前記フーチングの上に、上端から前記アンカー部材又は前記柱部材が露出するようにコンクリートを打設して上部基礎を構築する上部基礎構築工程と、を含んでいる。 The construction method of the seismic isolation foundation according to the first aspect is made of precast concrete in which an anchor member connected to a column or a column member constituting the column is provided on a seismic isolation device installed on a lower foundation. A footing installation step of installing a footing; and an upper foundation construction step of constructing an upper foundation by placing concrete on the footing so that the anchor member or the column member is exposed from the upper end. .

第1態様に係る免震基礎の施工方法によれば、先ず、フーチング設置工程において、下部基礎に設置された免震装置の上に、柱と連結されるアンカー部材、又は柱を構成する柱部材が設けられたプレキャストコンクリート製のフーチングを設置する。次に、上部基礎構築工程において、フーチングの上にコンクリートを打設し、上端からアンカー部材又は柱部材が露出するように上部基礎を構築する。 According to the construction method of the seismic isolation foundation according to the first aspect , first, in the footing installation process, the anchor member connected to the column on the seismic isolation device installed on the lower foundation, or the column member constituting the column A precast concrete footing is installed. Next, in the upper foundation construction step, concrete is placed on the footing, and the upper foundation is constructed so that the anchor member or the column member is exposed from the upper end.

これにより、免震装置上に柱を立てる場合に、上部基礎の上端から露出したアンカー部材に柱を連結し、又は柱部材に他の柱部材を連結することにより、免震装置上に柱を立てることができる。したがって、施工性が向上する。   Thus, when a column is erected on the seismic isolation device, the column is connected to the anchor member exposed from the upper end of the upper foundation, or another column member is connected to the column member, so that the column is mounted on the seismic isolation device. Can stand. Therefore, the workability is improved.

また、アンカー部材又は柱部材が設けられたプレキャストコンクリート製のフーチングを用いたことにより、免震装置上でのフーチング用のコンクリート打設や、アンカー部材又は柱部材の組み込み作業等が不要になる。したがって、施工性がさらに向上する。   Further, by using the precast concrete footing provided with the anchor member or the column member, the concrete placement for footing on the seismic isolation device, the assembling work of the anchor member or the column member, or the like becomes unnecessary. Therefore, the workability is further improved.

第2態様に係る免震基礎の施工方法は、第1態様に係る免震基礎の施工方法において、前記フーチング設置工程の前に、前記アンカー部材又は前記柱部材の周囲に、前記上部基礎としての基礎梁の梁主筋を配筋する梁主筋配筋工程を含んでいる。 The base-isolation foundation construction method according to the second aspect is the base-isolation base construction method according to the first aspect, before the footing installation step, around the anchor member or the column member as the upper foundation. It includes a beam bar reinforcement process that arranges the beam reinforcement of the foundation beam.

第2態様に係る免震基礎の施工方法によれば、フーチング設置工程の前の梁主筋配筋工程において、フーチングに設けられたアンカー部材又は柱部材の周囲に、上部基礎としての基礎梁の梁主筋を配筋する。 According to the construction method of the seismic isolation foundation according to the second aspect , the beam of the foundation beam as the upper foundation is arranged around the anchor member or the column member provided in the footing in the beam reinforcement arrangement process before the footing installation process. Arrange the main bars.

これにより、免震装置上での梁主筋の配筋作業が不要になるため、施工性がさらに向上する。また、例えば、広い作業台等の上で、基礎梁の梁主筋を配筋することにより、梁主筋の配筋精度が向上する。   As a result, the work of arranging the main bar of the beam on the seismic isolation device becomes unnecessary, so that the workability is further improved. Further, for example, by arranging the beam main reinforcement of the foundation beam on a wide work table or the like, the accuracy of the arrangement of the beam main reinforcement is improved.

第3態様に係る免震基礎の施工方法は、第1態様又は第2態様に係る免震基礎の施工方法において、前記フーチング設置工程の前に、前記フーチングを製作するフーチング製作工程を含み、前記フーチング製作工程では、前記アンカー部材又は前記柱部材の周囲に、上方が開口した複数のU字状補強筋を平面視にて格子状に配筋すると共に前記U字状補強筋が上面から突出するように前記フーチング用のコンクリートを打設した後に、前記U字状補強筋における開口側端部間に上部補強筋を渡す。 The base isolation construction method according to the third aspect includes the footing manufacturing step of manufacturing the footing before the footing installation step in the base isolation base construction method according to the first aspect or the second aspect, In the footing manufacturing process, a plurality of U-shaped reinforcing bars opened upward are arranged in a lattice pattern around the anchor member or the column member, and the U-shaped reinforcing bars protrude from the upper surface. After placing the footing concrete in this manner, the upper reinforcing bar is passed between the opening-side end portions of the U-shaped reinforcing bar.

第3態様に係る免震基礎の施工方法によれば、フーチング設置工程の前のフーチング製作工程において、アンカー部材又は柱部材の周囲に、上方が開口した複数のU字状補強筋を平面視にて格子状に配筋すると共にこれらのU字状補強筋が上面から突出するようにフーチング用のコンクリートを打設する。その後、フーチングの上面から突出するU字状補強筋における開口側端部間に上部補強筋を渡す。 According to the construction method of the seismic isolation foundation according to the third aspect , in the footing manufacturing process before the footing installation process, a plurality of U-shaped reinforcing bars opened upwards around the anchor member or the column member in a plan view The concrete for footing is placed so that the bars are arranged in a lattice pattern and these U-shaped reinforcing bars protrude from the upper surface. Thereafter, the upper reinforcing bar is passed between the opening-side end portions of the U-shaped reinforcing bar protruding from the upper surface of the footing.

このように上方が開口したU字状補強筋を用いたことにより、開口から作業者が手を入れ易くなる。したがって、下方が開口したU字状補強筋を用いた場合と比較して、U字状補強筋の配筋作業が容易となる。   By using the U-shaped reinforcing bar having an opening at the top in this way, the operator can easily put his hand through the opening. Therefore, compared with the case where the U-shaped reinforcing bar which the lower part opened is used, the reinforcement work of a U-shaped reinforcing bar becomes easy.

また、U字状補強筋における開口側端部間に上部補強筋を渡して枠状にすることにより、フーチング及び上部基礎に対する補強効果が向上する。   Moreover, the reinforcement effect with respect to a footing and an upper foundation improves by passing an upper reinforcement bar between opening side edge parts in a U-shaped reinforcement bar, and making it frame shape.

さらに、フーチング用のコンクリートを打設した後に、U字状補強筋における開口側端部間に上部補強筋を渡すことにより、フーチング用のコンクリートを打設した後でも、U字状補強筋の開口側端部の位置調整等を容易に行うことができる。   Further, after placing the footing concrete, the upper reinforcing bar is passed between the opening-side end portions of the U-shaped reinforcing bar, so that the U-shaped reinforcing bar can be opened even after the footing concrete is cast. The position of the side end can be easily adjusted.

第4態様に係るプレキャストコンクリートフーチングは、免震装置の上部フランジに固定される固定面が形成されたコンクリート部と、前記コンクリート部に設けられ、柱が連結されるアンカー部材、又は前記柱を構成する柱部材と、前記アンカー部材又は前記柱部材の周囲に配筋された基礎梁の梁主筋と、を備えている。 The precast concrete footing which concerns on a 4th aspect comprises the concrete part in which the fixed surface fixed to the upper flange of a seismic isolation apparatus was formed, the anchor member provided in the said concrete part, and a pillar connected, or the said pillar And a main beam of the foundation beam arranged around the anchor member or the column member.

第4態様に係るプレキャストコンクリートフーチングによれば、コンクリート部に、柱が連結されるアンカー部材、又は柱を構成する柱部材を設けると共に、アンカー部材又は柱部材の周囲に基礎梁の梁主筋を配筋しておくことにより、免震装置上でのアンカー部材又は柱部材の組み込み作業や基礎梁の梁主筋の配筋作業が不要になる。したがって、施工性が向上する。 According to the precast concrete footing according to the fourth aspect , an anchor member to which a column is connected or a column member constituting the column is provided in the concrete part, and the main beam of the foundation beam is arranged around the anchor member or the column member. By arranging the lines, the work of assembling the anchor member or the column member on the seismic isolation device and the work of arranging the beam main bars of the foundation beam become unnecessary. Therefore, the workability is improved.

本発明は、上記の構成としたので、免震装置上に立てる柱の施工性を向上させることができる。   Since this invention was set as said structure, it can improve the workability of the pillar standing on a seismic isolation apparatus.

本発明の一実施形態における作業台、ベースプレート、架台、アンカーボルトを示す分解立面図である。It is a disassembled elevation view which shows the work bench | platform, the base plate, the mount frame, and the anchor bolt in one Embodiment of this invention. 図1に示されるベースプレートを示す平面図である。It is a top view which shows the baseplate shown by FIG. 本発明の一実施形態におけるU字状補強筋及び上部補強筋を示す分解立面図である。It is a decomposition | disassembly elevational view which shows the U-shaped reinforcement bar and upper reinforcement bar in one Embodiment of this invention. 本発明の一実施形態における基礎梁の上下の梁主筋及びせん断補強筋を示す立面図である。It is an elevational view showing upper and lower beam main bars and shear reinforcement bars of a foundation beam in an embodiment of the present invention. 本発明の一実施形態に係るフーチングを免震装置の上に設置する前の状態を示す立面図である。It is an elevation view which shows the state before installing the footing which concerns on one Embodiment of this invention on a seismic isolation apparatus. 本発明の一実施形態に係るフーチングを免震装置の上に設置した後の状態、及び基礎梁の仕口部の上に柱を立てた状態を示す立面図である。It is an elevation view which shows the state after installing the footing which concerns on one Embodiment of this invention on a seismic isolation apparatus, and the state which stood the pillar on the joint part of a foundation beam. 本発明の一実施形態に係るフーチングの変形例を示す縦断面図である。It is a longitudinal cross-sectional view which shows the modification of the footing which concerns on one Embodiment of this invention.

以下、図面を参照しながら、本発明の一実施形態に係る免震基礎の施工方法及びプレキャストコンクリートフーチングについて説明する。   Hereinafter, a construction method and a precast concrete footing according to an embodiment of the present invention will be described with reference to the drawings.

本実施形態に係る免震基礎の施工方法は、フーチング製作工程と、梁主筋配筋工程と、フーチング設置工程と、上部基礎構築工程とを含んでいる。   The base isolation construction method according to the present embodiment includes a footing manufacturing process, a beam main bar arranging process, a footing installation process, and an upper foundation construction process.

先ず、フーチング製作工程について説明する。フーチング製作工程では、プレキャストコンクリート製のプレキャストコンクリートフーチング(以下、単に「フーチング」という)10を製作する。本実施形態に係るフーチング10は、図6に示されるように、基礎梁80の下面から突出するコンクリート部12と、コンクリート部12の下面に設けられたベースプレート30と、コンクリート部12の上面に設けられた複数のアンカー部材としての複数のアンカーボルト60と、複数のアンカーボルト60の周囲に配筋された上下の梁主筋82A,82B(図5参照)とを備えている。このフーチング10は、例えば、敷地内に確保した作業スペース(サイトヤード)において製作する。なお、フーチング10は、工場等で製作することも可能である。   First, the footing manufacturing process will be described. In the footing manufacturing process, a precast concrete footing (hereinafter simply referred to as “footing”) 10 made of precast concrete is manufactured. As shown in FIG. 6, the footing 10 according to the present embodiment is provided on the concrete portion 12 protruding from the lower surface of the foundation beam 80, the base plate 30 provided on the lower surface of the concrete portion 12, and the upper surface of the concrete portion 12. A plurality of anchor bolts 60 as a plurality of anchor members and upper and lower beam main bars 82A and 82B (see FIG. 5) arranged around the plurality of anchor bolts 60 are provided. The footing 10 is manufactured, for example, in a work space (site yard) secured in the site. The footing 10 can be manufactured at a factory or the like.

具体的には、先ず、図1に示されるように、作業スペースに、足場を構成する作業台20を略水平に設置する。作業台20は、水平レベルを確保すると共に、型枠としても機能するものである。この作業台20は3枚のベニア板を積層して構成されており、その上面にベースプレート30を収容する凹部22が形成されている。凹部22は、ベースプレート30の形状及び大きさに応じて平面視にて略矩形に形成されると共に、その深さがベースプレート30の板厚と略同じに設定されている。これにより、凹部22にベースプレート30を収容した状態で、ベースプレート30の上面が作業台20の上面と略面一になるようになっている。   Specifically, first, as shown in FIG. 1, a work table 20 constituting a scaffold is installed in a substantially horizontal position in a work space. The work table 20 secures a horizontal level and also functions as a formwork. The work table 20 is configured by laminating three veneer plates, and a recess 22 for accommodating the base plate 30 is formed on the upper surface thereof. The recess 22 is formed in a substantially rectangular shape in plan view according to the shape and size of the base plate 30, and the depth thereof is set to be substantially the same as the plate thickness of the base plate 30. Thereby, the upper surface of the base plate 30 is substantially flush with the upper surface of the work table 20 in a state where the base plate 30 is accommodated in the recess 22.

次に、作業台20の凹部22内に、ベースプレート30を嵌め込む。これにより、ベースプレート30が略水平に配置されると共に、作業台20に対してベースプレート30が位置決められる。   Next, the base plate 30 is fitted into the recess 22 of the work table 20. Thereby, the base plate 30 is arranged substantially horizontally and the base plate 30 is positioned with respect to the work table 20.

なお、ベースプレート30の大きさが異なる複数のフーチング10を製作する場合は、最大のベースプレート30の大きさに応じた凹部22を作業台20に形成し、小さいベースプレート30を凹部22に設置する場合には、ベースプレート30と凹部22との隙間を板状のスペーサ等で埋めても良い。また、作業台20に複数の凹部22を形成し、複数のフーチング10を並行して製作することも可能である。   When manufacturing a plurality of footings 10 having different base plate 30 sizes, a recess 22 corresponding to the maximum size of the base plate 30 is formed in the work table 20 and a small base plate 30 is installed in the recess 22. The gap between the base plate 30 and the recess 22 may be filled with a plate-like spacer or the like. It is also possible to form a plurality of recesses 22 in the work table 20 and to manufacture a plurality of footings 10 in parallel.

ベースプレート30は、後述する免震装置18の上部フランジ18Aに固定されるフーチング10の固定面を形成するものであり、図2に示されるように、平面視にて矩形の鋼板で形成されている。このベースプレート30の上面には、工場等において、中心位置が墨出し(芯出し)されると共に、吊り治具用ナット32、免震装置用袋ナット34、スタッド36、及び架台用ブラケット(アングルピース)38が溶接等により取り付けられている。これらの吊り治具用ナット32、免震装置用袋ナット34、スタッド36、及び架台用ブラケット38は、コンクリート部12に下端部に埋設される。   The base plate 30 forms a fixing surface of the footing 10 that is fixed to the upper flange 18A of the seismic isolation device 18 to be described later, and is formed of a rectangular steel plate in plan view as shown in FIG. . On the upper surface of the base plate 30, the center position is marked (centered) in a factory or the like, and a lifting jig nut 32, a seismic isolation device cap nut 34, a stud 36, and a mounting bracket (angle piece) 38) is attached by welding or the like. The suspension jig nut 32, the seismic isolation device cap nut 34, the stud 36, and the gantry bracket 38 are embedded in the concrete portion 12 at the lower end.

複数の吊り治具用ナット32は、図示しない揚重機等のワイヤーが連結される吊り治具40(図1参照)が取り付けられる取付具であり、ベースプレート30の四隅にそれぞれ取り付けられている。複数の免震装置用袋ナット34は、ベースプレート30を後述する免震装置18の上部フランジ18Aに固定するボルト24(図5参照)が締結される締結具であり、ベースプレート30及び上部フランジ18Aに形成された図示しない複数のボルト孔に応じて円形に配列されている。複数のスタッド36は、コンクリート部12とベースプレート30との一体性を高める定着具であり、円形に配列された複数の免震装置用袋ナット34の内側に適宜配置されている。複数(本実施形態では、4つ)の架台用ブラケット38は、後述する架台50が取り付けられる取付具であり、円形に配列された免震装置用袋ナット34の内側に配置されている。   The plurality of suspension jig nuts 32 are attachments to which suspension jigs 40 (see FIG. 1) to which a wire such as a lifting machine (not shown) is connected are attached, and are attached to the four corners of the base plate 30, respectively. The plurality of seismic isolation device cap nuts 34 are fasteners to which bolts 24 (see FIG. 5) for fixing the base plate 30 to the upper flange 18A of the seismic isolation device 18 described later are fastened, and are attached to the base plate 30 and the upper flange 18A. They are arranged in a circle according to a plurality of bolt holes (not shown) formed. The plurality of studs 36 are fixing tools that enhance the integrity of the concrete portion 12 and the base plate 30 and are appropriately arranged inside the plurality of seismic isolation device cap nuts 34 arranged in a circle. A plurality (four in this embodiment) of the gantry brackets 38 are attachments to which the gantry 50 to be described later is attached, and are arranged inside the seismic isolation device cap nuts 34 arranged in a circle.

次に、図1に示されるように、ベースプレート30上の架台用ブラケット38に、架台50を取り付ける。支持部材としての架台50は、アンカーボルト60の取付高さを調整するものであり、平面視にて矩形の枠部50Aと、枠部50Aの角部をそれぞれ支持する4本の脚部50Bとを有している。これらの脚部50Bを架台用ブラケット38に溶接等でそれぞれ取り付けることにより、ベースプレート30に対して架台50が位置決められる。   Next, as shown in FIG. 1, the gantry 50 is attached to the gantry bracket 38 on the base plate 30. The mount 50 as a support member adjusts the mounting height of the anchor bolt 60, and includes a rectangular frame portion 50A in plan view and four leg portions 50B that respectively support corner portions of the frame portion 50A. have. The base 50 is positioned with respect to the base plate 30 by attaching these leg portions 50B to the base bracket 38 by welding or the like.

次に、架台50に、複数(本実施形態では、8本)のアンカーボルト60を立てた状態で取り付ける。複数のアンカーボルト60は、後述する柱90を基礎梁80に固定するものであり、その上端部に柱用ベース62がナット64により取り付けられている。連結部材としての柱用ベース62は平面視にて矩形の鋼板で形成されており、柱90の柱脚部(下端部)が溶接等により接合されるようになっている。   Next, a plurality (eight in this embodiment) of anchor bolts 60 are attached to the gantry 50 in an upright state. The plurality of anchor bolts 60 are for fixing a pillar 90 to be described later to the foundation beam 80, and a pillar base 62 is attached to the upper end of the pillar bolt 62 by a nut 64. The column base 62 as the connecting member is formed of a rectangular steel plate in plan view, and the column base (lower end) of the column 90 is joined by welding or the like.

また、複数のアンカーボルト60の下端部には、平面にて矩形の下部枠体66がナット68により取り付けられている。この下部枠体66を架台50の枠部50Aの上に載置し、溶接や図示しないボルト等で接合することにより、複数のアンカーボルト60が架台50に取り付けられ、所定の高さで保持される。なお、アンカーボルト60には、定着板等の定着具を適宜設けても良い。   In addition, a lower frame body 66 that is rectangular in plan is attached to the lower ends of the plurality of anchor bolts 60 by nuts 68. A plurality of anchor bolts 60 are attached to the gantry 50 and held at a predetermined height by placing the lower frame body 66 on the frame portion 50A of the gantry 50 and joining them by welding or bolts (not shown). The The anchor bolt 60 may be appropriately provided with a fixing tool such as a fixing plate.

次に、図3に示されるように、架台50及びアンカーボルト60の周囲に、上方が開口した複数のU字状補強筋70を配筋する。複数のU字状補強筋70は、鉄筋をU字形状に屈曲して形成されている。また、各U字状補強筋70の開口側端部70Aには、内側へ折り返された折返し部70Bが設けられている。この折返し部70Bには、後述する上部補強筋72の折返し部72Bが連結される。これらのU字状補強筋70を、開口を上に向けた状態で平面視にて格子状に配筋する。つまり、複数のU字状補強筋70を上方が開口した籠状に配筋する。   Next, as shown in FIG. 3, a plurality of U-shaped reinforcing bars 70 whose tops are opened are arranged around the gantry 50 and the anchor bolt 60. The plurality of U-shaped reinforcing bars 70 are formed by bending reinforcing bars into a U-shape. Further, an opening-side end portion 70 </ b> A of each U-shaped reinforcing bar 70 is provided with a folded portion 70 </ b> B that is folded back inward. A folded portion 72B of an upper reinforcing bar 72 described later is connected to the folded portion 70B. These U-shaped reinforcing bars 70 are arranged in a lattice shape in plan view with the opening facing upward. That is, the plurality of U-shaped reinforcing bars 70 are arranged in a hook shape with an upper opening.

次に、ベースプレート30、架台50、U字状補強筋70を囲むように図示しない型枠を仮設すると共に、当該型枠内にフーチング10用のコンクリートを打設し、コンクリート部12を形成する。この際、フーチング10用のコンクリートは、コンクリート部12の上面から各U字状補強筋70の上部が上方へ突出するように型枠内に打設する。そして、フーチング10用のコンクリートを養生させ、コンクリート部12を形成した後、図示しない型枠を撤去する。   Next, a mold frame (not shown) is temporarily installed so as to surround the base plate 30, the mount 50, and the U-shaped reinforcing bar 70, and concrete for the footing 10 is placed in the mold frame to form the concrete portion 12. At this time, the concrete for the footing 10 is placed in the mold so that the upper portion of each U-shaped reinforcing bar 70 protrudes upward from the upper surface of the concrete portion 12. Then, the concrete for the footing 10 is cured and the concrete portion 12 is formed, and then the formwork (not shown) is removed.

次に、各U字状補強筋70における開口側端部70A間に、上部補強筋72をそれぞれ渡す。上部補強筋72は、横方向に延びると共に、その両端部72Aが下方へ向けてそれぞれ屈曲されている。これらの両端部72Aの下端部には、内側へ折り返された折返し部72Bが設けられている。この折返し部72BをU字状補強筋70の折返し部70Bに重ねた状態で図示しない結束線等で結束することにより、上部補強筋72をU字状補強筋70に連結する。これにより、上部補強筋72及びU字状補強筋70によって枠状の基礎補強筋74(図4参照)が形成される。   Next, the upper reinforcing bars 72 are respectively passed between the opening-side end portions 70 </ b> A of the U-shaped reinforcing bars 70. The upper reinforcing bars 72 extend in the lateral direction, and both end portions 72A are bent downward. At the lower end portions of these both end portions 72A, a folded portion 72B that is folded inward is provided. The upper reinforcing bar 72 is connected to the U-shaped reinforcing bar 70 by binding the folded part 72B with a binding line or the like (not shown) in a state of being overlapped with the folded part 70B of the U-shaped reinforcing bar 70. As a result, a frame-shaped basic reinforcing bar 74 (see FIG. 4) is formed by the upper reinforcing bar 72 and the U-shaped reinforcing bar 70.

次に、梁主筋配筋工程について説明する。梁主筋配筋工程では、図4に示されるように、複数のアンカーボルト60の周囲に、基礎梁80(図6参照)の上下の梁主筋82A,82Bの一部を配筋する。具体的には、アンカーボルト60に対して左右両側から上下の梁主筋82A,82Bをそれぞれ配筋し、フーチング10の中央部で溶接等により接合すると共に、上下の梁主筋82A,82Bの周囲にせん断補強筋84を適宜配筋する。この際、上側の梁主筋82Aの端部を基礎補強筋74の上に載置し、当該基礎補強筋74によって上側の梁主筋82Aを支持する。つまり、本実施形態では、上側の梁主筋82Aの端部を支持する梁主筋用架台として基礎補強筋74を利用している。なお、基礎補強筋74とは別の梁主筋用架台を利用することも可能である。   Next, the beam main bar arrangement process will be described. In the beam main bar arrangement process, as shown in FIG. 4, a part of the upper and lower beam main bars 82A and 82B of the foundation beam 80 (see FIG. 6) is arranged around the plurality of anchor bolts 60. Specifically, upper and lower beam main bars 82A and 82B are arranged from both the left and right sides of the anchor bolt 60, and are joined by welding or the like at the center of the footing 10 and around the upper and lower beam main bars 82A and 82B. Shear reinforcement bars 84 are appropriately arranged. At this time, the end portion of the upper beam reinforcing bar 82 </ b> A is placed on the foundation reinforcing bar 74, and the upper beam reinforcing bar 82 </ b> A is supported by the foundation reinforcing bar 74. That is, in this embodiment, the foundation reinforcing bar 74 is used as a beam main bar gantry that supports the end of the upper beam main bar 82A. It is also possible to use a beam main bar stand different from the foundation reinforcing bar 74.

次に、フーチング載置工程について説明する。フーチング載置工程では、図5に示されるように、図示しない揚重機等によってフーチング10を吊り上げて移動し、基礎スラブ14の上面から突出する下側フーチング16上に設置された免震装置18の上部フランジ18Aの上に設置する。この際、フーチング10のベースプレート30を免震装置18の上部フランジ18Aの上に載置し、上部フランジ18A及びベースプレート30を貫通するボルト24を免震装置用袋ナット34に締結する。これにより、フーチング10の固定面を形成するベースプレート30が免震装置18の上部フランジ18Aに固定される。   Next, the footing placement process will be described. In the footing placement step, as shown in FIG. 5, the footing 10 is lifted and moved by a lifting machine (not shown) and the seismic isolation device 18 installed on the lower footing 16 protruding from the upper surface of the foundation slab 14. It is installed on the upper flange 18A. At this time, the base plate 30 of the footing 10 is placed on the upper flange 18A of the seismic isolation device 18, and the bolt 24 penetrating the upper flange 18A and the base plate 30 is fastened to the cap nut 34 for the seismic isolation device. As a result, the base plate 30 that forms the fixing surface of the footing 10 is fixed to the upper flange 18 </ b> A of the seismic isolation device 18.

なお、本実施形態では、基礎スラブ14及び下側フーチング16は、鉄筋コンクリート造とされている。また、免震装置18は積層ゴム支承で構成されており、その下部フランジ18Bが複数のボルト26によって下部基礎としての下側フーチング16の上面に固定されている。なお、免震装置18は、積層ゴム支承に限らず、滑り支承、転がり支承等でも良い。   In this embodiment, the foundation slab 14 and the lower footing 16 are reinforced concrete. The seismic isolation device 18 is formed of a laminated rubber bearing, and a lower flange 18B thereof is fixed to the upper surface of the lower footing 16 as a lower foundation by a plurality of bolts 26. The seismic isolation device 18 is not limited to a laminated rubber bearing, and may be a sliding bearing, a rolling bearing, or the like.

次に、上部基礎構築工程について説明する。上部基礎構築工程では、図6に示されるように、アンカーボルト60及び上下の梁主筋82A,82Bの周囲に図示しない型枠を仮設し、当該型枠内に基礎梁80用のコンクリートを打設する。この際、基礎梁80における柱90との仕口部80Aの上端からアンカーボルト60の上端部及び柱用ベース62が露出するように、型枠内に基礎梁80用のコンクリートを打設する。そして、基礎梁80用のコンクリートを養生させ、基礎梁80を構築した後、図示しない型枠を撤去する。   Next, the upper foundation construction process will be described. In the upper foundation construction process, as shown in FIG. 6, a formwork (not shown) is temporarily installed around the anchor bolt 60 and the upper and lower beam main bars 82A and 82B, and concrete for the foundation beam 80 is placed in the formwork. To do. At this time, the concrete for the foundation beam 80 is placed in the mold so that the upper end portion of the anchor bolt 60 and the column base 62 are exposed from the upper end of the joint portion 80A of the foundation beam 80 with the column 90. Then, after the concrete for the foundation beam 80 is cured and the foundation beam 80 is constructed, a formwork (not shown) is removed.

なお、本実施形態では、基礎梁80における仕口部80Aの上面に凹部86を形成し、当該凹部86にアンカーボルト60の上端部及び柱用ベース62を露出させているが、凹部86を省略し、基礎梁80における仕口部80Aの上面からアンカーボルト60を突出させることも可能である。なお、基礎梁80における仕口部80Aに凹部86を形成した場合は、当該凹部86の底壁が基礎梁80の上端となる。   In this embodiment, the recess 86 is formed on the upper surface of the joint 80A of the foundation beam 80, and the upper end of the anchor bolt 60 and the column base 62 are exposed in the recess 86, but the recess 86 is omitted. In addition, the anchor bolt 60 can be protruded from the upper surface of the joint portion 80A in the foundation beam 80. When the recess 86 is formed in the joint portion 80 </ b> A of the foundation beam 80, the bottom wall of the recess 86 becomes the upper end of the foundation beam 80.

次に、柱建込み工程について説明する。柱建込み工程では、図6に示されるように、基礎梁80の上端から露出した柱用ベース62の上に露出柱脚型の鉄骨造の柱90を立て、当該柱90の柱脚部を柱用ベース62に溶接や図示しないボルト等で接合する。これにより、柱90の柱脚部が柱用ベース62を介してアンカーボルト60に連結され、柱90の柱脚部が基礎梁80の仕口部80Aに固定される。その後、柱用ベース62と凹部86の底壁との隙間にモルタルやグラウト等を充填する。   Next, the column building process will be described. In the column erection process, as shown in FIG. 6, an exposed column base type steel column 90 is erected on the column base 62 exposed from the upper end of the foundation beam 80, and the column base portion of the column 90 is mounted. The column base 62 is joined by welding or a bolt (not shown). As a result, the column base of the column 90 is connected to the anchor bolt 60 via the column base 62, and the column base of the column 90 is fixed to the joint 80 </ b> A of the foundation beam 80. Thereafter, the gap between the column base 62 and the bottom wall of the recess 86 is filled with mortar, grout or the like.

以上説明したように、本実施形態に係る免震基礎の施工方法によれば、フーチング製作工程において、アンカーボルト60が設けられたプレキャストコンクリート製のフーチング10を予め製作しておくことにより、免震装置18上でのフーチング10用のコンクリート打設や、アンカーボルト60の組み込み作業等が不要になる。したがって、施工性が向上する。   As described above, according to the base isolation construction method according to the present embodiment, the precast concrete footing 10 provided with the anchor bolts 60 is manufactured in advance in the footing manufacturing process, so that the base isolation is achieved. It is not necessary to place concrete for the footing 10 on the device 18 or to install the anchor bolt 60. Therefore, the workability is improved.

また、上部基礎構築工程において、基礎梁80における仕口部80Aの上面に形成した凹部86からアンカーボルト60の上端部及び柱用ベース62が露出するように、型枠内に基礎梁80用のコンクリートを打設して基礎梁80を構築する。したがって、凹部86に露出した柱用ベース62に柱90の柱脚部を連結することにより、柱90を基礎梁80における仕口部80Aに固定することができる。   In the upper foundation construction process, the upper end portion of the anchor bolt 60 and the column base 62 are exposed in the formwork so that the upper end portion of the anchor bolt 60 and the column base 62 are exposed from the recess 86 formed on the upper surface of the joint portion 80A of the foundation beam 80. The foundation beam 80 is constructed by placing concrete. Therefore, the column 90 can be fixed to the joint portion 80 </ b> A in the foundation beam 80 by connecting the column base portion of the column 90 to the column base 62 exposed in the recess 86.

さらに、本実施形態では、梁主筋配筋工程において、複数のアンカーボルト60の周囲に基礎梁80の上下の梁主筋82A,82Bの一部及びせん断補強筋84を予め配筋(先組み)しておくことにより、免震装置18上での上下の梁主筋82A,82B及びせん断補強筋84の配筋作業が不要になる。したがって、施工性がさらに向上する。また、本実施形態では、安定した広い作業台20の上で、基礎梁80の上下の梁主筋82A,82B及びせん断補強筋84を配筋するため、上下の梁主筋82A,82Bの配筋効率及び配筋精度が向上すると共に、配筋された上下の梁主筋82A,82Bの検査作業が容易となる。   Further, in the present embodiment, in the beam main bar arrangement process, a part of the upper and lower beam main bars 82A and 82B of the foundation beam 80 and the shear reinforcement bar 84 are arranged in advance around the plurality of anchor bolts 60. This arrangement eliminates the work of arranging the upper and lower beam main bars 82A and 82B and the shear reinforcement bar 84 on the seismic isolation device 18. Therefore, the workability is further improved. Further, in this embodiment, the upper and lower beam main bars 82A and 82B and the shear reinforcement bars 84 of the foundation beam 80 are arranged on the stable and wide work table 20, so that the upper and lower beam main bars 82A and 82B are arranged efficiently. In addition, the bar arrangement accuracy is improved, and the inspection work of the upper and lower beam main bars 82A and 82B is easier.

しかも、本実施形態では、上下の梁主筋82A,82Bを配筋する際に、上側の梁主筋82Aを支持する架台として基礎補強筋74を利用している。これにより、上側の梁主筋82Aを支持するための専用架台が不要になる。したがって、コスト削減を図ることができる。   Moreover, in the present embodiment, when the upper and lower beam main bars 82A and 82B are arranged, the base reinforcing bar 74 is used as a gantry for supporting the upper beam main bar 82A. This eliminates the need for a dedicated stand for supporting the upper beam main reinforcement 82A. Therefore, cost reduction can be achieved.

また、フーチング製作工程では、架台50及びアンカーボルト60の周囲に、上方が開口した複数のU字状補強筋70を平面視にて格子状に配筋すると共に、これらのU字状補強筋70がコンクリート部12の上面から突出するように、フーチング10用のコンクリートを打設してコンクリート部12を形成する。その後、コンクリート部12の上面から突出したU字状補強筋70における開口側端部70A間に上部補強筋72を渡して、枠状の基礎補強筋74を形成する。   Further, in the footing manufacturing process, a plurality of U-shaped reinforcing bars 70 opened upward are arranged around the mount 50 and the anchor bolt 60 in a lattice shape in plan view, and these U-shaped reinforcing bars 70 are arranged. The concrete part 12 is formed by placing concrete for the footing 10 so as to protrude from the upper surface of the concrete part 12. Thereafter, the upper reinforcing bars 72 are passed between the opening-side end portions 70 </ b> A of the U-shaped reinforcing bars 70 protruding from the upper surface of the concrete portion 12 to form the frame-shaped basic reinforcing bars 74.

このように、上方が開口したU字状補強筋70を用いたことにより、作業者が上方の開口からU字状補強筋70の内側に手を入れ易くなる。したがって、下方が開口したU字状補強筋を用いた場合と比較して、複数のU字状補強筋70の配筋作業が容易となる。   As described above, by using the U-shaped reinforcing bar 70 having an upper opening, an operator can easily put his hand inside the U-shaped reinforcing bar 70 from the upper opening. Therefore, compared with the case where the U-shaped reinforcement bar which the lower part opened is used, the arrangement | positioning work of the several U-shaped reinforcement bar 70 becomes easy.

また、フーチング10用のコンクリートを打設した後に、各U字状補強筋70における開口側端部70A間に上部補強筋72を渡すことにより、フーチング10用のコンクリートを打設した後でも、U字状補強筋70の開口側端部70Aの位置調整等を容易に行うことができる。したがって、U字状補強筋70の折返し部70Bと上部補強筋72の折返し部72Bとの連結作業が容易となる。   In addition, after placing the concrete for the footing 10, the U-shaped reinforcement bars 70 are passed through the upper reinforcing bars 72 between the opening-side end portions 70 </ b> A. The position adjustment of the opening side end portion 70A of the character-shaped reinforcing bar 70 can be easily performed. Therefore, the connection work between the folded portion 70B of the U-shaped reinforcing bar 70 and the folded portion 72B of the upper reinforcing bar 72 is facilitated.

さらに、U字状補強筋70及び上部補強筋72によって枠状の基礎補強筋74を形成することにより、フーチング10及び基礎梁80の仕口部80Aに対する補強効果が向上する。   Furthermore, by forming the frame-shaped basic reinforcing bar 74 by the U-shaped reinforcing bar 70 and the upper reinforcing bar 72, the reinforcing effect on the joint 80A of the footing 10 and the basic beam 80 is improved.

さらにまた、基礎スラブ14等の施工と並行してフーチング10を製作することにより、免震装置18上でフーチング10を施工する場合と比較して、工期の短縮化及び作業工数の平準化を図ることができる。   Furthermore, by producing the footing 10 in parallel with the construction of the foundation slab 14 and the like, compared with the case of constructing the footing 10 on the seismic isolation device 18, the work period is shortened and the work man-hours are leveled. be able to.

次に、上記実施形態の変形例について説明する。   Next, a modification of the above embodiment will be described.

上記実施形態では、フーチング製作工程において、フーチング10のコンクリート部12の上面に、架台50を介してアンカーボルト60を設けた例を示したが、これに限らない。例えば、アンカーボルト60の一部(下部や下端部)をコンクリート部12に埋設することにより、コンクリート部12にアンカーボルト60を一体化させても良い。つまり、上記実施形態におけるフーチング10に設けられたアンカーボルト60とは、コンクリート部12に埋設された架台50等の支持部材に支持されたアンカーボルト60や、コンクリート部12の上面から突出するようにその一部がコンクリート部12に埋設されたアンカーボルト60等を含む概念である。   In the said embodiment, although the example which provided the anchor bolt 60 via the mount frame 50 was shown in the upper surface of the concrete part 12 of the footing 10 in the footing manufacturing process, it is not restricted to this. For example, the anchor bolt 60 may be integrated with the concrete portion 12 by embedding a part of the anchor bolt 60 (lower portion or lower end portion) in the concrete portion 12. That is, the anchor bolt 60 provided on the footing 10 in the above embodiment is protruded from the anchor bolt 60 supported by a support member such as the gantry 50 embedded in the concrete portion 12 or the upper surface of the concrete portion 12. The concept includes an anchor bolt 60 or the like partially embedded in the concrete portion 12.

また、フーチング製作工程では、必ずしもコンクリート部12の全体(全部)を形成する必要はなく、例えば、フーチング設置工程の後にコンクリート部12の一部を形成しても良いし、上部基礎構築工程において基礎梁80の施工と同時にコンクリート部12の一部を形成しても良い。   Further, in the footing manufacturing process, it is not always necessary to form the entire concrete part 12 (all). For example, a part of the concrete part 12 may be formed after the footing installation process, or the foundation in the upper foundation construction process. A part of the concrete portion 12 may be formed simultaneously with the construction of the beam 80.

また、上記実施形態では、柱用ベース62を介して柱90をアンカーボルト60に連結した例を示したが、これに限らない。柱用ベース62とは別の連結部材を介して柱90をアンカーボルト60に連結しても良いし、柱90をアンカーボルト60に直接連結しても良い。   Moreover, in the said embodiment, although the example which connected the pillar 90 to the anchor bolt 60 via the pillar base 62 was shown, it is not restricted to this. The pillar 90 may be connected to the anchor bolt 60 via a connecting member different from the pillar base 62, or the pillar 90 may be directly connected to the anchor bolt 60.

また、上記実施形態では、アンカー部材として、アンカーボルト60を例に説明したが、これに限らない。アンカー部材は、基礎梁80の仕口部80Aに一部が埋設され、当該仕口部80Aに柱90を固定(連結)可能な部材であれば良く、例えば、L型やJ型等の一般的なコンクリート用アンカーでも良い。また、基礎梁80の仕口部80Aから根巻きコンクリート部を立ち上げ、当該根巻きコンクリート部に柱90の柱脚部を埋設する場合は、根巻きコンクリート部と仕口部80Aとに亘って配筋される補強筋等をアンカー部材としても良い。さらに、後述するように、基礎梁80の仕口部80Aの上に鉄筋コンクリート造等の柱を立てる場合は、柱の柱主筋の一部をアンカー部材としても良い。   Moreover, in the said embodiment, although the anchor bolt 60 was demonstrated to the example as an anchor member, it is not restricted to this. The anchor member may be any member that is partially embedded in the joint portion 80A of the foundation beam 80 and that can fix (connect) the column 90 to the joint portion 80A. A concrete anchor may be used. Further, when a root-wrapped concrete portion is raised from the joint portion 80A of the foundation beam 80 and the column base portion of the column 90 is embedded in the root-wrap concrete portion, the root-wrap concrete portion and the joint portion 80A are spanned. A reinforcing bar or the like to be arranged may be used as the anchor member. Furthermore, as will be described later, when a column such as a reinforced concrete structure is erected on the joint portion 80A of the foundation beam 80, a part of the column main reinforcement of the column may be used as an anchor member.

また、上記実施形態では、フーチング設置工程の前に、梁主筋配筋工程を実施したが、フーチング設置工程と上部基礎構築工程との間で梁主筋配筋工程を実施しても良い。   Moreover, in the said embodiment, although the beam main bar reinforcement process was implemented before the footing installation process, you may implement a beam main reinforcement arrangement process between a footing installation process and an upper foundation construction process.

また、上記実施形態では、フーチング製作工程において、アンカーボルト60の周囲に基礎補強筋74を配筋した例を示したが、基礎補強筋74の配筋方法は適宜変更可能である。例えば、コンクリート部12を形成する前に、U字状補強筋70の開口側端部70Aに上部補強筋72を渡しても良いし、アンカーボルト60の周囲に下方が開口したU字状補強筋を配筋しても良い。また、基礎補強筋74は、必要に応じてアンカーボルト60の周囲に配筋すれば良く、適宜省略可能である。さらに、基礎補強筋74に替えて、一般的な補強筋を配筋することも可能である。   In the above embodiment, the example in which the base reinforcing bars 74 are arranged around the anchor bolt 60 in the footing manufacturing process is shown, but the method of arranging the basic reinforcing bars 74 can be changed as appropriate. For example, before forming the concrete portion 12, the upper reinforcing bar 72 may be passed to the opening-side end portion 70 </ b> A of the U-shaped reinforcing bar 70, or a U-shaped reinforcing bar having a lower opening around the anchor bolt 60. May be arranged. Further, the basic reinforcing bars 74 may be arranged around the anchor bolt 60 as necessary, and can be omitted as appropriate. Furthermore, it is possible to arrange a general reinforcing bar in place of the basic reinforcing bar 74.

また、上記実施形態では、上部基礎構築工程において、フーチング10の上に鉄筋コンクリート造の基礎梁80を構築した例に説明したが、これに限らない。基礎梁80は、鉄筋コンクリート造に限らず、コンクリート造、鉄骨コンクリート造、プレストレスコンクリート造等であっても良い。また、上部基礎としては、例えば、コンクリート造、鉄筋コンクリート造等の基礎スラブであっても良い。   Moreover, although the said embodiment demonstrated to the example which constructed | assembled the reinforced concrete foundation beam 80 on the footing 10 in the upper foundation construction process, it is not restricted to this. The foundation beam 80 is not limited to a reinforced concrete structure, and may be a concrete structure, a steel frame concrete structure, a prestressed concrete structure, or the like. Moreover, as an upper foundation, foundation slabs, such as concrete structure and a reinforced concrete structure, may be sufficient, for example.

また、上記実施形態では、柱建込み工程において、基礎梁80の仕口部80Aの上に鉄骨造の柱90を立てた例を示したが、これに限らない。柱は、鉄骨造に限らず、コンクリート造、鉄筋コンクリート造、鉄骨コンクリート造、プレストレスコンクリート造、CFT(Concrete Filled Steel Tube)造等であっても良い。また、鉄筋コンクリート造等の柱の場合は、例えば、基礎梁80の仕口部80Aから上方へ突出するアンカーボルト60の上部を柱に埋設することにより、アンカーボルト60と柱とを連結すれば良い。   Moreover, in the said embodiment, although the example in which the steel-structured pillar 90 was stood on the joint part 80A of the foundation beam 80 was shown in the pillar construction process, it is not restricted to this. The pillar is not limited to steel structure, but may be concrete structure, reinforced concrete structure, steel concrete structure, prestressed concrete structure, CFT (Concrete Filled Steel Tube) structure, or the like. In the case of a column such as a reinforced concrete structure, for example, the anchor bolt 60 and the column may be connected by embedding the upper portion of the anchor bolt 60 protruding upward from the joint 80A of the foundation beam 80 in the column. .

さらに、上記実施形態では、フーチング100にアンカー部材としてのアンカーボルト60を設けた例を示したが、これに限らない。フーチング100には、免震装置18上に立てられる柱を構成する柱部材を設けることも可能である。   Furthermore, although the example which provided the anchor bolt 60 as an anchor member in the footing 100 was shown in the said embodiment, it is not restricted to this. The footing 100 can be provided with a column member that constitutes a column that stands on the seismic isolation device 18.

具体的には、図7に示されるように、フーチング100のコンクリート部12の上面には、架台50を介して柱部材102が設けられている。柱部材102は、基礎梁80の仕口部80Aに柱脚部が埋設される柱脚埋め込み型の柱92の下部を構成するものであり、その上端部に柱92の上部を構成する他の柱部材(図示省略)が連結される。   Specifically, as shown in FIG. 7, a column member 102 is provided on the upper surface of the concrete portion 12 of the footing 100 via a mount 50. The column member 102 constitutes a lower portion of a column base embedded column 92 in which the column base portion is embedded in the joint portion 80A of the foundation beam 80, and the other upper end of the column 92 is formed at the upper end portion thereof. Column members (not shown) are connected.

この柱部材102は、角形鋼管で形成された本体部104と、本体部104の下端に設けられたベースプレート106とを有している。本体部104の外面には、応力伝達手段としての複数のスタッド108が設けられている。これらのスタッド108により、柱部材102と基礎梁80の仕口部80Aとの一体性が高められている。   The column member 102 has a main body portion 104 formed of a square steel pipe and a base plate 106 provided at the lower end of the main body portion 104. A plurality of studs 108 as stress transmission means are provided on the outer surface of the main body 104. These studs 108 enhance the integrity of the column member 102 and the joint 80A of the foundation beam 80.

このように構成された柱部材102は、前述したフーチング製作工程において、アンカーボルト60に替えて架台50に立てた状態で取り付けられる。なお、図7では、U字状補強筋70の図示が省略されている。そして、柱部材102の周囲に前述した上部補強筋72及び梁主筋82A,82B(図4参照)を配筋した後、フーチング設置工程においてフーチング100を免震装置18の上に設置し、上部基礎構築工程において基礎梁80を構築する。   The column member 102 configured in this manner is attached in a state where the column member 102 stands on the mount 50 in place of the anchor bolt 60 in the above-described footing manufacturing process. In FIG. 7, illustration of the U-shaped reinforcing bar 70 is omitted. Then, after arranging the upper reinforcing bars 72 and beam main bars 82A and 82B (see FIG. 4) around the column member 102, the footing 100 is installed on the seismic isolation device 18 in the footing installation process, and the upper foundation The foundation beam 80 is constructed in the construction process.

上部基礎構築工程では、フーチング100の上に、仕口部80Aの上端から柱部材102の上端部が露出するようにコンクリートを打設して基礎梁80を構築する。これにより、仕口部80Aの上端から露出した柱部材102の上端部に他の柱部材を連結することができる。したがって、柱脚埋め込み型の柱92の施工性を向上させることができる。   In the upper foundation construction step, the foundation beam 80 is constructed by placing concrete on the footing 100 so that the upper end of the column member 102 is exposed from the upper end of the joint 80A. Thereby, another column member can be connected to the upper end portion of the column member 102 exposed from the upper end of the joint portion 80A. Therefore, the workability of the column base embedded column 92 can be improved.

なお、柱部材102は、上記実施形態におけるアンカーボルト60と同様に、その一部(下部や下端部)をコンクリート部12に埋設することにより、コンクリート部12と一体化させても良い。つまり、フーチング100に設けられた柱部材102とは、コンクリート部12に埋設された架台50等の支持部材に支持された柱部材102や、コンクリート部12の上面から突出するようにその一部がコンクリート部12に埋設された柱部材102等を含む概念である。また、上記各種の変形例は、柱部材102が設けられたフーチング100にも適宜適用可能である。   The column member 102 may be integrated with the concrete portion 12 by embedding a part (lower portion or lower end portion) of the pillar member 102 in the concrete portion 12 in the same manner as the anchor bolt 60 in the above embodiment. That is, the pillar member 102 provided in the footing 100 is a part of the pillar member 102 supported by a support member such as the gantry 50 embedded in the concrete portion 12 or a part of the pillar member 102 so as to protrude from the upper surface of the concrete portion 12. This is a concept including a column member 102 and the like embedded in the concrete portion 12. Further, the various modifications described above can be applied as appropriate to the footing 100 provided with the column member 102.

以上、本発明の一実施形態について説明したが、本発明はこうした実施形態に限定されるものでなく、一実施形態及び各種の変形例を適宜組み合わせて用いても良いし、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。   As mentioned above, although one embodiment of the present invention was described, the present invention is not limited to such an embodiment, and one embodiment and various modifications may be used in combination as appropriate, and the gist of the present invention will be described. Of course, various embodiments can be implemented without departing from the scope.

10 プレキャストコンクリートフーチング(フーチング)
12 コンクリート部
14 基礎スラブ(下部基礎)
16 下側フーチング(下部基礎)
18 免震装置
18A 上部フランジ
30 ベースプレート(固定面)
50 架台
60 アンカーボルト(アンカー部材)
70 U字状補強筋
70A 開口側端部
72 上部補強筋
80 基礎梁(上部基礎)
82A 梁主筋
82B 梁主筋
90 柱
92 柱
100 フーチング
102 柱部材
10 Precast concrete footing (footing)
12 Concrete part 14 Foundation slab (lower foundation)
16 Lower footing (lower base)
18 Base isolation device 18A Upper flange 30 Base plate (fixed surface)
50 Mount 60 Anchor bolt (anchor member)
70 U-shaped reinforcing bar 70A Open side end 72 Upper reinforcing bar 80 Foundation beam (upper foundation)
82A Beam main bar 82B Beam main bar 90 Column 92 Column 100 Footing 102 Column member

Claims (4)

下部基礎に設置された免震装置の上に、柱と連結されるアンカー部材、又は前記柱を構成する柱部材が上方へ突出するように設けられたプレキャストコンクリート製のフーチングを設置するフーチング設置工程と、
前記フーチングの上に、上端から前記アンカー部材又は前記柱部材が露出するようにコンクリートを打設して上部基礎を構築する上部基礎構築工程と、
を含む免震基礎の施工方法。
A footing installation process in which an anchor member connected to a column or a precast concrete footing provided so that the column member constituting the column protrudes upward on the seismic isolation device installed on the lower foundation When,
An upper foundation construction step of constructing an upper foundation by placing concrete so that the anchor member or the column member is exposed from the upper end on the footing,
Construction method of seismic isolation foundation including
前記フーチング設置工程の前に、前記アンカー部材又は前記柱部材の周囲に、前記上部基礎としての基礎梁の梁主筋を配筋する梁主筋配筋工程を含む、
請求項1に記載の免震基礎の施工方法。
Before the footing installation step, including a beam main bar reinforcement step of arranging the beam main reinforcement of the foundation beam as the upper foundation around the anchor member or the column member,
The construction method of the seismic isolation foundation of Claim 1.
前記フーチング設置工程の前に、前記フーチングを製作するフーチング製作工程を含み、
前記フーチング製作工程では、前記アンカー部材又は前記柱部材の周囲に、上方が開口した複数のU字状補強筋を平面視にて格子状に配筋すると共に前記U字状補強筋が上面から突出するように前記フーチング用のコンクリートを打設した後に、前記U字状補強筋における開口側端部間に上部補強筋を渡す、
請求項1又は請求項2に記載の免震基礎の施工方法。
Before the footing installation step, including a footing production step for producing the footing,
In the footing manufacturing step, a plurality of U-shaped reinforcing bars opened upward are arranged in a lattice pattern around the anchor member or the column member, and the U-shaped reinforcing bars protrude from the upper surface. After placing the footing concrete so as to pass the upper reinforcing bar between the opening side end portions of the U-shaped reinforcing bar,
The construction method of the seismic isolation foundation of Claim 1 or Claim 2.
免震装置の上部フランジに固定される固定面が形成されたコンクリート部と、
前記コンクリート部に設けられ、柱が連結されるアンカー部材、又は前記柱を構成する柱部材と、
前記コンクリート部の上に配置され、前記アンカー部材又は前記柱部材の周囲に配筋された基礎梁の梁主筋と、
を備えたプレキャストコンクリートフーチング。
A concrete part formed with a fixed surface to be fixed to the upper flange of the seismic isolation device;
An anchor member provided in the concrete part and connected to a column, or a column member constituting the column,
A beam main reinforcement of a foundation beam arranged on the concrete portion and arranged around the anchor member or the column member;
Precast concrete footing with
JP2012246340A 2012-11-08 2012-11-08 Seismic isolation construction method and precast concrete footing Active JP6046984B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012246340A JP6046984B2 (en) 2012-11-08 2012-11-08 Seismic isolation construction method and precast concrete footing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012246340A JP6046984B2 (en) 2012-11-08 2012-11-08 Seismic isolation construction method and precast concrete footing

Publications (2)

Publication Number Publication Date
JP2014095201A JP2014095201A (en) 2014-05-22
JP6046984B2 true JP6046984B2 (en) 2016-12-21

Family

ID=50938495

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012246340A Active JP6046984B2 (en) 2012-11-08 2012-11-08 Seismic isolation construction method and precast concrete footing

Country Status (1)

Country Link
JP (1) JP6046984B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6882860B2 (en) * 2016-07-06 2021-06-02 大成建設株式会社 How to build a seismic isolation foundation structure
JP6953723B2 (en) * 2017-01-18 2021-10-27 株式会社大林組 Construction method of seismic isolation structure
JP7186003B2 (en) * 2017-12-21 2022-12-08 株式会社竹中工務店 Construction method of foundation structure
CN108678416B (en) * 2018-07-04 2023-09-15 浙江理工大学 Assembled underground storey-adding vibration-isolating structure and storey-adding vibration-isolating construction process
RU193791U1 (en) * 2019-07-15 2019-11-15 Федеральное государственное автономное образовательное учреждение высшего образования "Крымский федеральный университет имени В.И. Вернадского" Pipe-concrete seismic-insulating support on a monolithic reinforced concrete foundation

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6351529A (en) * 1986-08-22 1988-03-04 Kajima Corp Construction of reinforced concrete underground beam and slab
JPH0874265A (en) * 1994-09-07 1996-03-19 Fujita Corp Precast concrete foundation pole and manufacture thereof
JP3002107B2 (en) * 1994-12-19 2000-01-24 勤伍 内藤 Column base structure and column base construction method
JPH08218390A (en) * 1995-02-13 1996-08-27 Taisei Corp Method for constructing underground beam
JPH11270182A (en) * 1998-03-19 1999-10-05 Taisei Corp Base isolation structure
JP2000273951A (en) * 1999-03-26 2000-10-03 Atsuhide Hashimoto Exposed type fixed column base having high earthquake- resistant performance
JP3760304B2 (en) * 2000-10-30 2006-03-29 清水建設株式会社 Building foundation construction method
JP3850776B2 (en) * 2002-09-12 2006-11-29 五洋建設株式会社 Column-to-beam joint structure in the top layer of reinforced concrete structures
JP4568101B2 (en) * 2004-12-06 2010-10-27 株式会社竹中工務店 Pile-column connection structure
JP4625692B2 (en) * 2004-12-27 2011-02-02 株式会社竹中工務店 Building construction method of base-isolated structure with laminated rubber bearing
JP4612422B2 (en) * 2005-01-05 2011-01-12 大成建設株式会社 Construction method of structure and foundation structure used for it
JP2008240329A (en) * 2007-03-27 2008-10-09 Taisei Corp Joining structure
JP5190035B2 (en) * 2009-07-14 2013-04-24 大成建設株式会社 Construction method of seismic isolation structure
JP5232106B2 (en) * 2009-08-27 2013-07-10 大成建設株式会社 Construction method of seismic isolation structure
JP5737554B2 (en) * 2010-09-24 2015-06-17 清水建設株式会社 Seismic isolation foundation construction method
JP5656538B2 (en) * 2010-10-04 2015-01-21 章 福田 Reinforcement structure of upper steel column base

Also Published As

Publication number Publication date
JP2014095201A (en) 2014-05-22

Similar Documents

Publication Publication Date Title
JP5594987B2 (en) Method for manufacturing concrete mount, concrete mount, and connecting material
JP4732915B2 (en) Foundation construction method and device, and anchor bolt support device for construction
KR101131679B1 (en) Splicing Method of Embedded type Baseplate with Steel Column
JP6046984B2 (en) Seismic isolation construction method and precast concrete footing
JP2018115489A (en) Anchor frame and method of building steel frame structure using the same
JP5574328B2 (en) Tokai seismic wall and its construction method
JP5713710B2 (en) Seismic isolation structure and its construction method
JP2011012464A (en) Method of constructing base isolating structure, and temporary supporting structure for base isolating device
JP5176786B2 (en) Construction method of column beam frame
JP2018123537A (en) Method of constructing mat foundation, tubular formwork and mat foundation structure
JP5183606B2 (en) Unit structure of anchor bolt used for foundation construction of equipment and foundation construction method of equipment using it
JP6255220B2 (en) Positioning member and construction method
JP2008285952A (en) Base-isolated building structure
JP6632290B2 (en) Steel column leg structure and steel column leg construction method
JP6083655B2 (en) Hanging frame and method of constructing structure using the same
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP4625692B2 (en) Building construction method of base-isolated structure with laminated rubber bearing
JP5912194B1 (en) Construction method of wooden building and basic member used in the construction method
JP2015081467A (en) Base isolation structure
JP2016172982A (en) Fixing method for joint part steel of composite structure, joint part construction method and joint part structure, anchor bolt fixing jig
JP2009299419A (en) Construction method for preventing displacement of form, and installment tool
JP6738535B2 (en) Steel plate concrete structure and construction method of steel plate concrete structure
JP6381096B2 (en) Construction structure, gantry and turbine generator facility, and method for manufacturing construction structure
JP2018115473A (en) Method of constructing seismic isolation structure and base isolation structure
JP7165548B2 (en) Seismic isolation foundation structure and its construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20160629

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160705

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160901

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20161101

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20161118

R150 Certificate of patent or registration of utility model

Ref document number: 6046984

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150