JP5620344B2 - Construction method of pier - Google Patents

Construction method of pier Download PDF

Info

Publication number
JP5620344B2
JP5620344B2 JP2011137345A JP2011137345A JP5620344B2 JP 5620344 B2 JP5620344 B2 JP 5620344B2 JP 2011137345 A JP2011137345 A JP 2011137345A JP 2011137345 A JP2011137345 A JP 2011137345A JP 5620344 B2 JP5620344 B2 JP 5620344B2
Authority
JP
Japan
Prior art keywords
precast
formwork
mold
reinforcing bar
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011137345A
Other languages
Japanese (ja)
Other versions
JP2013002238A (en
Inventor
光則 村尾
光則 村尾
喜彦 平
喜彦 平
春日 昭夫
昭夫 春日
柴田敏雄
敏雄 柴田
茂樹 富山
茂樹 富山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2011137345A priority Critical patent/JP5620344B2/en
Publication of JP2013002238A publication Critical patent/JP2013002238A/en
Application granted granted Critical
Publication of JP5620344B2 publication Critical patent/JP5620344B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)

Description

本願発明は、プレキャストコンクリートからなる板状部材を型枠として用い、構築現場においてこれらのプレキャストコンクリートからなる型枠と一体となるようにコンクリートを打設して橋脚を構築する方法に関するものである。   The present invention relates to a method for constructing a pier by using a plate-like member made of precast concrete as a mold, and placing the concrete so as to be integrated with the mold made of precast concrete at a construction site.

橋脚を構築する方法としては、形成された基礎上で鉄筋を組み立てるとともに、これらを囲むように設けられた型枠内にコンクリートを打設して構築する方法が広く採用されている。この方法では、基礎から上下方向に配置される主鉄筋を立ち上げ、主鉄筋を囲むように水平に配置されて主鉄筋を拘束する帯鉄筋、及び帯鉄筋を水平方向に連結する中間帯鉄筋等を組み立てる。そして、これらの鉄筋を囲むように型枠を設けて、この型枠内へコンクリートを打設する。   As a method for constructing a pier, a method is widely employed in which reinforcing bars are assembled on a formed foundation and concrete is placed in a formwork provided so as to surround them. In this method, the main reinforcing bars arranged up and down from the foundation are raised, the horizontal reinforcing bars that are placed horizontally around the main reinforcing bars to restrain the main reinforcing bars, the intermediate reinforcing bars that connect the reinforcing bars in the horizontal direction, etc. Assemble. Then, a mold is provided so as to surround these reinforcing bars, and concrete is placed in the mold.

また、プレキャストコンクリート板を型枠として使用し、これらのプレキャストコンクリート板と一体となるように構築現場でコンクリートを打設する橋脚の構築方法が、例えば特許文献1に記載されている。
この橋脚の構築方法は、断面が中空となった橋脚を構築するものであり、プレキャストコンクリートからなる内型枠及び外型枠を使用して、所定の高さごとにこれらの間にコンクリートを打設するものである。上記内型枠及び外型枠は橋脚の周方向に複数に分割されており、それぞれには主鉄筋を拘束する帯鉄筋を埋め込むとともに主鉄筋が仮支持されている。そして、これら内型枠及び外型枠を橋脚の基礎上又は橋脚の既に形成された部分の上で、周方向にほぼ連続するように配列する。隣接した内型枠又は外型枠に取り付けられた帯鉄筋は、隣接する内型枠間又は外型枠間で接続するとともに、仮支持された主鉄筋を下方の施工済みの橋脚又は基礎から突き出した主鉄筋に接合する。その後、内型枠及び外型枠で囲まれた空間内にコンクリートを打設し、内型枠、外型枠、主鉄筋、帯鉄筋を一体とする。コンクリートの硬化後、この硬化した橋脚の上部に、同様に内型枠及び外型枠を配列し、帯鉄筋及び主鉄筋を接合する工程、コンクリートを打設する工程を繰り返し、橋脚を上方に立ち上げて構築するものとなっている。
Moreover, Patent Document 1 describes a method for building a pier that uses a precast concrete plate as a formwork and casts concrete at a construction site so as to be integrated with these precast concrete plates.
This pier construction method is to construct a pier with a hollow cross-section, using an inner mold frame and an outer mold frame made of precast concrete, and placing concrete between them at a predetermined height. It is to be established. The inner mold frame and the outer mold frame are divided into a plurality of portions in the circumferential direction of the bridge pier, and each of them embeds a band rebar for restraining the main rebar and temporarily supports the main rebar. Then, the inner mold frame and the outer mold frame are arranged so as to be substantially continuous in the circumferential direction on the foundation of the pier or on the already formed portion of the pier. Reinforcing bars attached to adjacent inner formwork or outer formwork connect between adjacent inner formwork or outer formwork, and project the temporarily supported main rebar from the installed pier or foundation below. Join the main rebar. Thereafter, concrete is placed in a space surrounded by the inner mold frame and the outer mold frame, and the inner mold frame, the outer mold frame, the main reinforcing bar, and the belt reinforcing bar are integrated. After the concrete is hardened, the inner and outer formwork are similarly arranged on the top of the hardened pier, and the process of joining the strip reinforcement and main reinforcement and the process of placing concrete are repeated, with the pier standing upwards. It is meant to be built up.

特開平8−232212号公報JP-A-8-232212

しかし、構築現場において主鉄筋や帯鉄筋の組立て及び接合、型枠の組み立て、脱型及び撤去等を行う構築方法では、構築現場で行う作業が多く、構築に要する期間が長くなってしまう。また、このような作業を行うために大掛かりな足場等の組立てが必要となり、作業効率が悪く、コストも高くなる。   However, in the construction method for assembling and joining main reinforcing bars and strip reinforcing bars, assembling the formwork, demolding and removing at the construction site, many operations are performed at the construction site, and the time required for construction becomes long. Further, in order to perform such work, it is necessary to assemble a large scaffold or the like, resulting in poor work efficiency and high cost.

一方、特許文献1に記載の技術では、橋脚の外周面を形成するための外型枠と中空となった内周面を形成するための内型枠とを、所定の間隔で対向するように支持するとともに、これらに埋め込まれている帯鉄筋の双方に両端が係止された中間帯鉄筋を配置しなければない。帯鉄筋は、図16に示すようにプレキャストコンクリートからなる内型枠101と外型枠102に埋め込んでおくのが作業の効率化のために望ましく、このように帯鉄筋103がプレキャストコンクリートに埋め込まれていると、中間帯鉄筋104は両端部を分離して、それぞれ内型枠101と外型枠102の製作時にコンクリート中に埋め込んでおく必要がある。そして、構築現場においては内型枠101と外型枠102とを別個に吊り上げ、対向するように配置した後に、これらの間で中間帯鉄筋104を接続しなければならない。このとき分割された中間帯鉄筋104を一ヶ所で接続するためには端面を正確に突き合わせる必要があり、接続が難しくなる。このため、図16に示すように、長さを調整した短い鉄筋106を介在させ、二ヶ所に継ぎ手105を設けて接続することになる。したがって、中間帯鉄筋を接続するための作業量が多くなってしまう。   On the other hand, in the technique described in Patent Document 1, the outer mold frame for forming the outer peripheral surface of the pier and the inner mold frame for forming the hollow inner peripheral surface are opposed to each other at a predetermined interval. In addition to supporting, an intermediate band reinforcing bar having both ends locked to both of the band reinforcing bars embedded therein must be arranged. As shown in FIG. 16, it is desirable to embed the band reinforcement in the inner mold frame 101 and the outer mold frame 102 made of precast concrete in order to improve work efficiency. In this way, the band reinforcement 103 is embedded in the precast concrete. If this is the case, it is necessary to separate the both ends of the intermediate rebars 104 and embed them in the concrete when manufacturing the inner mold 101 and the outer mold 102, respectively. At the construction site, the inner mold frame 101 and the outer mold frame 102 are separately lifted and arranged so as to face each other, and then the intermediate strip reinforcing bar 104 must be connected therebetween. At this time, in order to connect the divided intermediate strip reinforcing bars 104 at one place, it is necessary to accurately match the end faces, which makes the connection difficult. For this reason, as shown in FIG. 16, a short reinforcing bar 106 whose length is adjusted is interposed, and joints 105 are provided at two locations for connection. Therefore, the work amount for connecting the intermediate strip reinforcing bars increases.

また、プレキャストコンクリートからなる内型枠及び外型枠を現場に配列した後に、隣接して配置された内型枠又は外型枠に埋め込まれた帯鉄筋を接合するときにも、機械継ぎ手で全ての帯鉄筋を連結するために双方の内型枠又は外型枠から突き出した帯鉄筋の端面を正確に突き合わせることは難しい。さらに、上下に複数が配置された帯鉄筋のそれぞれの接続位置が、帯鉄筋の軸線方向において同じ位置となる。つまり、接続位置が上下に並ぶことになって、欠陥のないコンクリート部材を形成するために望ましくない。   In addition, when the inner and outer molds made of precast concrete are arranged on the site, and when joining the reinforcing bars embedded in the adjacent inner or outer molds, all the mechanical joints are used. It is difficult to accurately match the end faces of the band reinforcing bars protruding from both the inner mold frame and the outer mold frame in order to connect the band reinforcing bars. Furthermore, the connection positions of the strip reinforcing bars arranged in the top and bottom are the same in the axial direction of the strip reinforcing bars. In other words, the connection positions are arranged vertically, which is not desirable for forming a concrete member having no defect.

本願発明は、このような事情に鑑みてなされたものであり、その目的は、プレキャストコンクリートにより形成された型枠を用い、断面形状が矩形で内部に空間を有する橋脚を効率よく構築する橋脚の構築方法を提供することである。   The present invention has been made in view of such circumstances, and its purpose is to use a formwork formed of precast concrete, and to efficiently construct a bridge pier having a rectangular cross-sectional shape and having a space inside. It is to provide a construction method.

上記課題を解決するために、請求項1に係る発明は、 プレキャストコンクリートにより形成された型枠を用い、現場で打設されたコンクリートと前記型枠とを一体として、断面形状が矩形で内部に空間を有する橋脚を構築する方法であって、 所定の高さを有し、橋脚の周方向に複数が配列されて前記橋脚の外周面を形成するプレキャストコンクリートからなるプレキャスト外型枠と、該プレキャスト外型枠と所定の間隔をあけて該プレキャスト外型枠と連結され、前記橋脚の中空となった内周面を形成するプレキャストコンクリートからなるプレキャスト内型枠と、前記プレキャスト外型枠及びプレキャスト内型枠のそれぞれに水平方向に埋設される複数の帯鉄筋と、前記プレキャスト外型枠に埋め込まれた帯鉄筋とプレキャスト内型枠に埋め込まれた帯鉄筋とを水平方向に連結する中間帯鉄筋と、を備えた型枠ユニットを製作しておき、 前記橋脚の基礎又は前記橋脚の既に形成された部分の上に、立設された主鉄筋を前記プレキャスト外型枠と前記プレキャスト内型枠との間に挿通して前記型枠ユニットを載置し、該橋脚の隅角部を除外して周方向に複数の前記型枠ユニットを配列する工程と、 前記隅角部に水平方向の鉄筋を配置するとともに、該隅角部の型枠を現場で組み立てて、前記隅角部の前記型枠内及び前記プレキャスト外型枠とプレキャスト内型枠との間にコンクリートを打設する工程とを含み、 前記型枠ユニットを配列する工程と、前記隅角部の前記鉄筋を配置し、前記型枠を組み立てる工程と、前記コンクリートを打設する工程と、を繰り返して順次に上方に立ち上げることを特徴とする橋脚の構築方法を提供する。   In order to solve the above-mentioned problem, the invention according to claim 1 uses a formwork formed of precast concrete, and the concrete placed on site and the formwork are integrated, and the cross-sectional shape is rectangular and inside. A method for constructing a pier having a space, comprising: a precast outer mold frame made of precast concrete having a predetermined height and a plurality of which are arranged in a circumferential direction of the pier to form an outer peripheral surface of the pier; A precast inner mold made of precast concrete which is connected to the precast outer mold at a predetermined interval from the outer mold and forms a hollow inner peripheral surface of the pier, and the precast outer mold and the precast inner A plurality of rebars embedded horizontally in each of the molds, and a rebar and precast inner molds embedded in the precast outer mold A formwork unit having an intermediate rebar that connects the embedded rebar in a horizontal direction is manufactured, and is installed on the foundation of the pier or the already formed part of the pier. A main rebar is inserted between the precast outer formwork and the precast inner formwork to place the formwork unit, and a plurality of formwork units are arranged in the circumferential direction excluding the corners of the pier. Arranging the horizontal reinforcing bars at the corners, and assembling the corner formwork in the field, and in the formwork of the corner and the precast outer formwork and the precast Placing concrete between the formwork, arranging the formwork units, placing the reinforcing bars at the corners, assembling the formwork, and placing the concrete And repeating the process It provides a method for constructing a pier, characterized by launch.

この橋脚の構築方法では、予め製造される型枠ユニットには、帯鉄筋及びこの帯鉄筋を水平方向に連結する中間帯鉄筋が支持されているので、構築現場における配筋作業が低減される。そして、互いに対向して配置されるプレキャスト内型枠とプレキャスト外型枠が一体に連結されており、橋脚の構築現場で中間帯鉄筋を接続する必要がなく、コンクリートを打設する位置に型枠ユニットを効率よく設置することができる。また、隅角部ではプレキャストコンクリートの型枠を用いることなく、他の部分に型枠ユニットを配置した後においても開放された領域が設けられる。そして、隅角部において橋脚の隣り合う2つの側面が開放され、多くの主鉄筋が既に立ち上げられていても隅角部に水平方向の鉄筋を効率よく配置することができる。さらに、型枠ユニットは隅角部の両側で離れて設置されるので、上下方向に複数が配置された帯鉄筋を接続するときは、型枠ユニット間で接続する位置を交互にずらして設けることができる。   In this pier construction method, the formwork unit manufactured in advance supports the band reinforcing bar and the intermediate band reinforcing bar that connects the band reinforcing bar in the horizontal direction, so that the bar arrangement work at the construction site is reduced. And the precast inner formwork and the precast outer formwork, which are arranged opposite to each other, are integrally connected, so there is no need to connect the intermediate strip reinforcement at the construction site of the pier, and the formwork is placed at the position where concrete is to be placed. Units can be installed efficiently. Further, in the corner portion, a precast concrete mold is not used, and an open area is provided even after the mold unit is arranged in another part. Then, two adjacent side surfaces of the pier are opened at the corner, and a horizontal reinforcing bar can be efficiently arranged at the corner even if many main reinforcing bars have already been raised. In addition, since the formwork units are installed separately on both sides of the corner, when connecting a plurality of strip reinforcing bars arranged in the vertical direction, the connection positions between the formwork units should be alternately shifted. Can do.

請求項2に係る発明は、請求項1に記載の橋脚の構築方法において、 前記隅角部を除外し、該隅角部の両側で隣り合うように配置された前記型枠ユニットの一方は、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に帯鉄筋の端部を突出させておき、 他方の型枠ユニットは、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に突き出し、前記隅角部でU字状に連続した帯鉄筋を有するものとし、 前記型枠ユニットの配列後に前記隅角部に配置する水平方向の鉄筋として、後端部がフック状に曲げ加工された2本の所定長のフック付き鉄筋を用い、前記一方の型枠ユニットの端面から突出した前記帯鉄筋の延長線に沿って該突出した帯鉄筋の端面に向かって前記フック付き鉄筋を先端から差し入れ、該フック付き鉄筋と前記一方の型枠ユニットから突出した前記帯鉄筋の端部とを接続し、 前記フック付き鉄筋のフック状に曲げ加工された部分を、前記隅角部に埋め込んで定着するものとする。   The invention according to claim 2 is the construction method of a pier according to claim 1, wherein one of the formwork units arranged so as to be adjacent to both sides of the corner portion is excluded from the corner portion. The end of the rebar is protruded horizontally from the substantially vertical end faces of the precast outer mold and the precast inner mold toward the corner, and the other mold unit is The formwork unit and the precast inner formwork have horizontal reinforcing bars projecting horizontally from the substantially vertical end faces toward the corner portion and continuous in a U shape at the corner portion, and the formwork unit. As the horizontal reinforcing bars to be arranged in the corners after the arrangement of the two, two reinforcing bars with hooks having a predetermined length bent at the rear end are hooked and protruded from the end surface of the one mold unit. The band iron Inserting the rebar with the hook from the tip toward the end surface of the protruding rebar along the extension line of the hook, and connecting the rebar with the hook and the end of the rebar protruding from the one formwork unit, A portion bent into a hook shape of the hooked reinforcing bar is embedded and fixed in the corner portion.

この構築方法では、一方の型枠ユニットから端部が突き出した帯鉄筋に対して、フック付き鉄筋を開放された隅角部から差し入れて効率よく接続することができる。そして、このフック付き鉄筋は隅角部で定着され、他方の型枠ユニットから突き出してU字状に曲げ加工された帯鉄筋とともに主鉄筋の変位を有効に拘束するものとなる。また、帯鉄筋を構築現場で接続する継ぎ手の数を少なくすることができる。   In this construction method, the hooked reinforcing bar can be inserted from the opened corner portion and efficiently connected to the band reinforcing rod whose end protrudes from one mold unit. The hooked reinforcing bars are fixed at the corners, and effectively restrain the displacement of the main reinforcing bars together with the belt reinforcing bars protruding from the other mold unit and bent into a U shape. In addition, the number of joints that connect the reinforcing bars at the construction site can be reduced.

請求項3に係る発明は、請求項1に記載の橋脚の構築方法において、 前記隅角部を除外し、該隅角部の両側で隣り合うように配置された前記型枠ユニットの一方は、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に帯鉄筋の端部を突出させておき、 他方の型枠ユニットは、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に突き出し、前記隅角部でU字状に連続した帯鉄筋を有するものとし、 前記型枠ユニットの配列後に前記隅角部に配置する水平方向の鉄筋として、U字状に曲げ加工されたU字鉄筋を用い、該U字鉄筋の曲げ加工された部分の両側のほぼ平行となった部分を、前記一方の型枠ユニットの端面から突出した前記帯鉄筋の該延長線に沿って該突出した帯鉄筋の端面に向かって差し入れ、該U字鉄筋と前記一方の型枠ユニットから突出した前記帯鉄筋の端部とを接続し、 前記他方の型枠ユニットから突き出した前記帯鉄筋のU字状となるように曲げ回された部分と前記U字鉄筋の曲げ回された部分とで、前記隅角部に配置された前記主鉄筋を囲むものとする。   The invention according to claim 3 is the construction method of the pier according to claim 1, wherein one of the formwork units arranged so as to be adjacent to both sides of the corner portion is excluded from the corner portion. The end of the rebar is protruded horizontally from the substantially vertical end faces of the precast outer mold and the precast inner mold toward the corner, and the other mold unit is The formwork unit and the precast inner formwork have horizontal reinforcing bars projecting horizontally from the substantially vertical end faces toward the corner portion and continuous in a U shape at the corner portion, and the formwork unit. As the horizontal reinforcing bars to be arranged at the corners after the arrangement of the U-shaped reinforcing bars, U-shaped reinforcing bars bent in a U-shape are used, and substantially parallel portions on both sides of the bent portions of the U-shaped reinforcing bars are used. , Said one formwork Inserted toward the end surface of the protruding band reinforcing bar along the extension line of the band reinforcing bar protruding from the end surface of the steel plate, the U-shaped reinforcing bar and the end of the band reinforcing bar protruding from the one formwork unit Are connected to the other formwork unit, and the bent portion of the rebar that protrudes from the other formwork unit and the bent portion of the U-shaped rebar are arranged at the corner portion. The main reinforcing bar should be enclosed.

この構築方法では、隅角部において橋脚の外周面付近に配置された帯鉄筋と内周面付近に配置された帯鉄筋とが連続し、主鉄筋を有効に拘束することができる。そして、一方の型枠ユニットから端部が突き出した帯鉄筋に対して、U字鉄筋を効率よく接続することができ、継ぎ手を設ける位置も少なくすることができる。   In this construction method, the belt reinforcing bars arranged near the outer peripheral surface of the pier at the corner and the belt reinforcing bars arranged near the inner peripheral surface are continuous, and the main reinforcing bars can be effectively restrained. And the U-shaped reinforcing bar can be efficiently connected to the band reinforcing bar whose end protrudes from one of the formwork units, and the position where the joint is provided can be reduced.

請求項4に係る発明は、請求項1から請求項3までのいずれかに記載の橋脚の構築方法において、 前記プレキャスト外型枠と前記プレキャスト内型枠とは、鋼製のトラス部材によって所定の間隔で連結したものとし、 該トラス部材は、前記プレキャスト外型枠と前記プレキャスト内型枠とに密接し、鉛直方向に軸線を有する二つの弦材と、これらを斜め方向に連結する斜材と、前記二つの弦材のそれぞれに固着されるとともにプレキャスト外型枠又はプレキャスト内型枠のコンクリート中に埋め込まれる複数のアンカーを有し、 該アンカーは、上下方向に所定の間隔をおいて水平方向に配置される前記帯鉄筋の上下方向の間隔に合わせて設け、 前記型枠ユニットの製作時において、前記帯鉄筋は前記アンカーに支持させて配置するものとする。   The invention according to claim 4 is the pier construction method according to any one of claims 1 to 3, wherein the precast outer mold frame and the precast inner mold frame are predetermined by a steel truss member. The truss members are in close contact with the precast outer mold frame and the precast inner mold frame, and two string members having an axis in the vertical direction, and a diagonal member for connecting these in an oblique direction. A plurality of anchors fixed to each of the two chord members and embedded in the concrete of the precast outer formwork or the precast inner formwork, the anchors being horizontally arranged at predetermined intervals in the vertical direction Provided in accordance with the vertical spacing of the band reinforcing bars arranged in the frame, and when the mold unit is manufactured, the band reinforcing bars are arranged to be supported by the anchors. To.

この橋脚の構築方法では、型枠ユニットの製作時においては、帯鉄筋をトラス部材に支持させた状態で配置することができるので、帯鉄筋を正確かつ迅速に配置して型枠ユニットを効率よく製造することが可能となる。また、トラス部材によってプレキャスト内型枠とプレキャスト外型枠とを連結して、構築される橋脚の所定位置に配置するために吊り支持したときの相対的な変位を抑制することが可能となる。   In this pier construction method, when the formwork unit is manufactured, the rebar can be placed with the truss member supported on the truss member, so the rebar can be placed accurately and quickly to efficiently place the formwork unit. It can be manufactured. In addition, it is possible to suppress relative displacement when the precast inner mold frame and the precast outer mold frame are connected by the truss member and are suspended and supported to be arranged at a predetermined position of the constructed pier.

請求項5に係る発明は、請求項1から請求項4までのいずれかに記載の橋脚の構築方法において、 前記中間帯鉄筋は、水平方向に所定の間隔で設けるとともに、それぞれの帯鉄筋に対して上下方向に配列して設け、両端部を前記プレキャスト外型枠及びプレキャスト内型枠に埋め込むものとし、 上下方向に配列した前記帯鉄筋の側面に、斜め方向に軸線を有する斜め部材を当接し、複数の前記中間帯鉄筋に対して結合し、 該斜め部材によって前記プレキャスト外型枠とプレキャスト内型枠との相対的な変位を拘束するものとする。   The invention according to claim 5 is the pier construction method according to any one of claims 1 to 4, wherein the intermediate strip reinforcing bars are provided at predetermined intervals in the horizontal direction, and Are arranged in the vertical direction, and both end portions are embedded in the precast outer mold frame and the precast inner mold frame, and an oblique member having an axis in an oblique direction is brought into contact with the side surface of the band reinforcing bar arranged in the vertical direction. , It is coupled to the plurality of intermediate strip reinforcing bars, and the slanting member restrains the relative displacement between the precast outer mold and the precast inner mold.

この方法では、中間帯鉄筋によってプレキャスト内型枠とプレキャスト外型枠とを連結するとともに、斜め部材と中間帯鉄筋とプレキャスト内型枠とプレキャスト外型枠とよってトラス構造が形成される。したがって、簡単な構造でプレキャスト内型枠とプレキャスト外型枠とを相対的な変位が抑制された状態で支持することができる。   In this method, the precast inner mold frame and the precast outer mold frame are connected by the intermediate band reinforcing bar, and the truss structure is formed by the oblique member, the intermediate band reinforcing bar, the precast inner mold frame, and the precast outer mold frame. Therefore, the precast inner mold frame and the precast outer mold frame can be supported with a simple structure in a state in which relative displacement is suppressed.

以上説明したように、本願発明の橋脚の構築方法では、対向して配置される2枚のプレキャストコンクリートの板状部材に帯鉄筋及び中間帯鉄筋を一体として所定の位置に配置することができるので、構築現場における鉄筋の配置や連結等の配筋作業、型枠の設置や脱型等の作業が低減され、橋脚を効率よく構築することができる。
また、隅角部を開放した状態に型枠ユニットを配列し、この開放された位置から隅角部の帯鉄筋をほぼ水平に差し入れて型枠ユニット中の帯鉄筋に接続することができる。したがって、帯鉄筋の配置を効率よく行うことができるとともに、帯鉄筋の接合箇所を低減することが可能となる。
As described above, in the method for constructing a pier according to the present invention, it is possible to arrange the reinforcing bar and the intermediate reinforcing bar integrally at a predetermined position on the two plate-like members of the precast concrete arranged opposite to each other. In addition, the work of bar arrangement such as placement and connection of rebars at the construction site, work such as installation and demolding of formwork is reduced, and the pier can be constructed efficiently.
Further, the formwork units can be arranged in a state where the corner portions are opened, and the band reinforcing bars at the corner portions can be inserted almost horizontally from the opened positions to be connected to the band reinforcing bars in the formwork unit. Accordingly, it is possible to efficiently arrange the reinforcing bars and reduce the number of joining points of the reinforcing bars.

本願発明に係る方法により構築された橋脚を備える橋梁の一例を示す概略側面図及び立断面図である。It is the schematic side view and elevation sectional view which show an example of the bridge provided with the pier constructed | assembled by the method which concerns on this invention. 図1に示す橋脚の平断面図である。It is a plane sectional view of the pier shown in FIG. 図1及び図2に示す橋脚を構築するために用いる型枠ユニットの概略配置図である。FIG. 3 is a schematic layout diagram of a formwork unit used to construct the pier shown in FIGS. 1 and 2. 図3に示す型枠ユニットの立断面図である。FIG. 4 is a sectional elevation view of the mold unit shown in FIG. 3. 図3に示す型枠ユニットの平断面図である。It is a plane sectional view of the formwork unit shown in FIG. 型枠ユニットを拡大して示す立断面図及び平断面図である。It is the elevation sectional view and plane sectional view which expand and show a formwork unit. 型枠ユニットを製作する方法を説明するための概略立断面図及び概略平断面図である。It is a schematic elevation sectional view and a schematic plane sectional view for explaining a method of manufacturing a mold unit. 橋脚の隅角部に帯鉄筋を配置する方法を示す概略平断面図である。It is a schematic plane sectional view which shows the method of arrange | positioning a band reinforcement in the corner part of a bridge pier. ほぼ長方形となった橋脚断面の長辺部分と隔壁との接合部に帯鉄筋を配置する方法を示す概略平面図である。It is a schematic plan view which shows the method of arrange | positioning a strip reinforcement in the junction part of the long side part of the bridge pier cross-section which became substantially rectangular, and a partition. 型枠ユニットに用いるトラス部材の他の例及びその機能を示す概略立断面図である。It is a schematic elevation sectional drawing which shows the other example of the truss member used for a formwork unit, and its function. 型枠ユニットのプレキャスト型枠が相対的に変位するのを抑制する手段の他の例を示す概略立断面図である。It is a schematic sectional elevation showing another example of means for suppressing relative displacement of the precast formwork of the formwork unit. 橋脚の隅角部に帯鉄筋を配置する方法の他の例を示す概略平断面図である。It is a general | schematic plane sectional view which shows the other example of the method of arrange | positioning a band reinforcement in the corner part of a bridge pier. 橋脚の隅角部に帯鉄筋を配置する方法の他の例を示す概略平断面図である。It is a general | schematic plane sectional view which shows the other example of the method of arrange | positioning a band reinforcement in the corner part of a bridge pier. ほぼ長方形となった橋脚断面の長辺部分と隔壁との接合部に帯鉄筋を配置する方法の他の例を示す概略平面図である。It is a schematic plan view which shows the other example of the method of arrange | positioning a band reinforcement in the junction part of the long side part of the bridge pier cross-section which became substantially rectangular shape, and a partition. ほぼ長方形となった橋脚断面の長辺部分と隔壁との接合部に帯鉄筋を配置する方法の他の例を示す概略平面図である。It is a schematic plan view which shows the other example of the method of arrange | positioning a band reinforcement in the junction part of the long side part of the bridge pier cross-section which became substantially rectangular shape, and a partition. 本発明が解決しようとする課題の一つを説明するために示すプレキャストコンクリートの型枠の概略立断面図である。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic sectional elevation view of a precast concrete formwork shown to explain one of the problems to be solved by the present invention.

以下、本願発明の実施の形態を図に基づいて説明する。
図1は、本願発明に係る方法により構築された橋脚を備える橋梁の一例を示す概略側面図及び立断面図であり、図2は、図1に示す橋脚の平断面図である。
この橋梁は、コンクリートの橋桁1を2つの橋脚2及び2つの橋台3によって支持する3径間のラーメン橋である。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 is a schematic side view and an elevational sectional view showing an example of a bridge provided with a pier constructed by the method according to the present invention, and FIG. 2 is a plan sectional view of the pier shown in FIG.
This bridge is a three-diameter ramen bridge in which a concrete bridge girder 1 is supported by two piers 2 and two abutments 3.

橋脚2は、鉄筋コンクリートからなり、基礎として形成されたケーソン4又は直接基礎として形成されたフーチング5上に立ち上げられている。この橋脚の断面形状は、図2に示すようにほぼ長方形で、内部に空間が設けられた中空断面となっており、中空部を2分割する隔壁が設けられている。
この橋脚2の断面内の外周面に沿った位置及び内周面に沿った位置には上下方向に主鉄筋11,12が配列され、外周面に沿った位置に配列された主鉄筋11の外側つまり外周面側には、水平方向の帯鉄筋13が上下方向に所定の間隔を設けて配置されている。また、内周面に沿った位置に配置された主鉄筋12の内周面側にも帯鉄筋14が配置されている。これらの帯鉄筋13,14は、橋脚2に大きな曲げモーメントが発生し、主鉄筋11,12に降伏点応力に近い引張応力又は降伏点応力を超える引張応力が生じた後に圧縮応力が作用したときに、主鉄筋11,12が座屈してコンクリート部材の表面から膨らみ出すのを拘束するものとして配置されている。そして、外周面に沿って配置された帯鉄筋13と内周面に沿って配置された帯鉄筋14とに両端部が係止され、帯鉄筋がコンクリート部材の表面側に押し出されるのを拘束する中間帯鉄筋15が、水平方向に所定の間隔で、上下方向に配列された帯鉄筋13,14の全てに対して配置されている。
The pier 2 is made of reinforced concrete and is raised on a caisson 4 formed as a foundation or a footing 5 formed as a direct foundation. The cross-sectional shape of the pier is substantially rectangular as shown in FIG. 2 and has a hollow cross section with a space inside, and a partition wall that divides the hollow portion into two is provided.
Main rebars 11 and 12 are arranged in a vertical direction at a position along the outer peripheral surface and a position along the inner peripheral surface in the cross section of the pier 2, and outside the main rebar 11 arranged at a position along the outer peripheral surface. That is, on the outer peripheral surface side, the horizontal reinforcing bars 13 are arranged at a predetermined interval in the vertical direction. Moreover, the belt reinforcement 14 is arrange | positioned also at the internal peripheral surface side of the main reinforcement 12 arrange | positioned in the position along an internal peripheral surface. When these strip reinforcing bars 13 and 14 generate a large bending moment in the pier 2 and a compressive stress is applied to the main reinforcing bars 11 and 12 after a tensile stress close to the yield point stress or a tensile stress exceeding the yield point stress is generated. The main reinforcing bars 11 and 12 are arranged to restrain the buckling and swelling from the surface of the concrete member. And both ends are latched by the band reinforcement 13 arrange | positioned along an outer peripheral surface, and the band reinforcement 14 arrange | positioned along an inner peripheral surface, and restrains that a band reinforcement is extruded to the surface side of a concrete member. The intermediate rebars 15 are arranged with respect to all of the rebars 13 and 14 arranged in the vertical direction at a predetermined interval in the horizontal direction.

橋脚2は、予め設定された施工区分ごとに型枠の設置、鉄筋の配置及びコンクリートの打設を繰り返し行い、上方に所定の高さまで構築するものである。そして、型枠にはプレキャストコンクリートで形成された板状部材を外型枠及び内型枠として用い、これらを構築現場で組み立てるメタルフォーム又は合板製の型枠と組み合わせて用いる。プレキャストコンクリートの型枠は、現場で打設されるコンクリートと一体となり、橋脚の一部となるものである。   The pier 2 is constructed by repeating the installation of the formwork, the arrangement of the reinforcing bars, and the placement of the concrete for each construction section set in advance to a predetermined height. And the plate-shaped member formed with precast concrete is used for a formwork as an outer formwork and an inner formwork, and these are used in combination with a metal form or a plywood formwork assembled at a construction site. The precast concrete formwork is integrated with the concrete cast on site and becomes part of the pier.

プレキャストコンクリートで形成された型枠は、図3に示すように矩形となった断面の隅角部2aを除外し、隅角部間の外周面部分と内周面部分及び隔壁の両側面部分に用いている。
ほぼ長方形となった断面の長辺部分に用いられるプレキャストコンクリートの型枠及び短辺部分に用いられるプレキャストコンクリートの型枠は、外周面を形成するプレキャスト外型枠16,18と内周面を形成するプレキャスト内型枠17,19とが、鋼製のトラス部材21によって連結され、それぞれAタイプの型枠ユニットUA又はBタイプの型枠ユニットUBとなっている。これらの型枠ユニットは吊り上げたときにも鋼製のトラス部材21によってプレキャスト外型枠とプレキャスト内型枠との相対的な変位が抑制されるものとなっており、一体にした状態で吊り上げて所定の位置に設置することができるものである。
As shown in FIG. 3, the formwork formed of precast concrete excludes the corner portion 2a of the cross section which is rectangular, and is provided on the outer peripheral surface portion and inner peripheral surface portion between the corner portions and both side surface portions of the partition wall. Used.
The precast concrete formwork used for the long side portion of the cross section which has become almost rectangular and the precast concrete formwork used for the short side portion form the inner peripheral surface with the precast outer mold frames 16 and 18 forming the outer peripheral surface. a precast inner die frame 17, 19 which is connected by a steel truss members 21, respectively a mold unit U B formwork units U a or B type a type. Even when these formwork units are lifted, the relative displacement between the precast outer formwork and the precast inner formwork is suppressed by the steel truss member 21, and they are lifted in an integrated state. It can be installed at a predetermined position.

上記トラス部材21は鋼からなり、図4に示すように、プレキャスト外型枠16,18のコンクリートと接触する第1の弦材21aとプレキャスト内型枠17,19のコンクリートと接触する第2の弦材21bとを有し、これらがほぼ平行となるように斜材21cによって連結したものである。上記第1の弦材21a及び第2の弦材21bには、H形鋼、L型鋼等の型鋼を用いることができ、斜材にはL型鋼又は鋼プレート等を用いることができる。また、第1の弦材21a及び第2の弦材21bにはプレキャスト外型枠16,18及びプレキャスト内型枠17,19のコンクリートと接触する面に、複数のアンカー21dが突出するように取り付けられており、プレキャスト外型枠16,18又はプレキャスト内型枠17,19となるコンクリートに埋め込まれるものとなっている。   The truss member 21 is made of steel, and as shown in FIG. 4, the first chord material 21a that comes into contact with the concrete of the precast outer molds 16 and 18 and the second chord that comes into contact with the concrete of the precast inner molds 17 and 19 are used. It has a string material 21b and is connected by an oblique material 21c so that they are substantially parallel to each other. For the first chord member 21a and the second chord member 21b, a steel plate such as H-shaped steel or L-shaped steel can be used, and for the diagonal member, L-shaped steel or steel plate can be used. Further, the first chord member 21a and the second chord member 21b are attached so that a plurality of anchors 21d protrude from the surfaces of the precast outer mold frames 16 and 18 and the precast inner mold frames 17 and 19 in contact with the concrete. The precast outer molds 16 and 18 or the precast inner molds 17 and 19 are embedded in the concrete.

一方、図3に示すように、隔壁部分に用いられるプレキャストコンクリートのプレキャスト型枠20も同様に、一方の立面を形成する第1のプレキャスト型枠20aと他方の立面を形成する第2のプレキャスト型枠20bとがトラス部材21によって連結され、一体として設置することができるCタイプの型枠ユニットUCとなっている。 On the other hand, as shown in FIG. 3, the precast concrete precast mold 20 used for the partition wall portion similarly has a first precast mold 20a that forms one elevation surface and a second precast mold frame 20a that forms the other elevation surface. The precast mold 20b is connected by a truss member 21 to form a C type mold unit U C that can be installed as a unit.

ほぼ長方形となった断面の長辺部分に用いられるAタイプの型枠ユニットUAは、図3に示すように、プレキャスト外型枠16が隣り合う一方の隅角部付近から他方の隅角部付近まで一枚のプレキャストコンクリート板となっており、これと対向するプレキャスト内型枠17は2つに分割され、分割されたプレキャスト内型枠17は相互間に所定の間隔を開けてほぼ同一仮想面上に配置されている。これら2枚のプレキャスト内型枠17の間の開放された部分に隔壁が設けられる。 As shown in FIG. 3, the A-type mold unit U A used for the long side portion of the cross-section that is substantially rectangular is, as shown in FIG. 3, from one corner portion adjacent to the precast outer mold frame 16 to the other corner portion. One precast concrete plate is formed in the vicinity, and the precast inner mold 17 facing the same is divided into two, and the divided precast inner mold 17 is substantially the same virtual space with a predetermined interval between each other. It is arranged on the surface. A partition wall is provided in an open portion between the two precast inner molds 17.

プレキャスト外型枠16とプレキャス内型枠17とには、図5(a)に示すようにそれぞれ帯鉄筋13,14が外周面又は内周面に沿って水平に埋め込まれ、上下に所定の間隔を開けて高さ方向の全領域に配置されている。プレキャスト外型枠16に埋め込まれた帯鉄筋13は、プレキャスト外型枠16の水平方向における一方の端面16aから露出し、U字状に曲げ回されて、プレキャスト内型枠17の一方の端面17aから突き出した帯鉄筋14と連続している。プレキャスト外型枠16及びプレキャスト内型枠17の他方の端面16b,17bからは、帯鉄筋13,14がそれぞれ所定の長さで突き出している。また、2枚に分割されたプレキャスト内型枠17の間の開放された部分からは、プレキャスト外型枠16の帯鉄筋13に先端が係止された鉄筋22が、プレキャスト内型枠17の表面とほぼ垂直に突き出している。   In the precast outer mold 16 and the precast inner mold 17, as shown in FIG. 5 (a), band reinforcing bars 13 and 14 are embedded horizontally along the outer peripheral surface or the inner peripheral surface, respectively, and at predetermined intervals in the vertical direction. Is opened and placed in the entire area in the height direction. The rebar 13 embedded in the precast outer mold 16 is exposed from one end surface 16a in the horizontal direction of the precast outer mold 16, is bent in a U shape, and is one end surface 17a of the precast inner mold 17. It is continuous with the belt rebar 14 protruding from. From the other end surfaces 16b and 17b of the precast outer mold 16 and the precast inner mold 17, band reinforcing bars 13 and 14 respectively protrude with a predetermined length. Further, from the open part between the precast inner mold 17 divided into two sheets, a reinforcing bar 22 whose tip is locked to the band reinforcing bar 13 of the precast outer mold 16 is the surface of the precast inner mold 17. And protruding almost vertically.

また、中間帯鉄筋15は、図6に示すようにプレキャスト外型枠16に埋め込まれた帯鉄筋13とプレキャスト内型枠17に埋め込まれた帯鉄筋14とに、それぞれ両端が係止される。中間帯鉄筋15の両端には鋼からなるプレート15aが溶接又は加熱及び加圧して圧接されており、このプレート15aを帯鉄筋13,14の上側から側面に当接し、中間帯鉄筋15とプレート15aによって帯鉄筋13,14に掛け回して係止する。そして、コンクリートの打設により中間帯鉄筋15の両端部は帯鉄筋13,14とともにプレキャスト外型枠16又はプレキャスト内型枠17となるコンクリート中に埋め込まれ、両端部の間は2つのプレキャスト型枠間で露出している。   Further, as shown in FIG. 6, both ends of the intermediate rebar 15 are locked to the rebar 13 embedded in the precast outer mold 16 and the rebar 14 embedded in the precast inner mold 17, respectively. Plates 15a made of steel are welded or heated and pressurized and pressed against both sides of the intermediate rebar 15 and the plate 15a is brought into contact with the side surfaces of the rebars 13 and 14 so as to contact the intermediate rebar 15 and the plate 15a. Is hung around the steel bars 13 and 14 and locked. Then, both ends of the intermediate rebar 15 are embedded in the concrete to be the precast outer mold 16 or the precast inner mold 17 together with the rebars 13 and 14 by placing concrete, and the two precast molds are between the two ends. It is exposed between.

ほぼ長方形となった断面の短辺部分に用いられるBタイプの型枠ユニットUBは、図5(b)に示すように、プレキャスト外型枠18とプレキャスト内型枠19とが対向し、トラス部材21によって連結されている。そして、プレキャスト外型枠18とプレキャスト内型枠19とのそれぞれに帯鉄筋13,14が配置され、中間帯鉄筋15がこれらを連結するように配置される。また、Aタイプの型枠ユニットUAと同様に、水平方向における一方の端部ではプレキャスト外型枠18の端面18aから突き出した帯鉄筋13がU字状に曲げ回されてプレキャスト内型枠19の端面19aから突き出した帯鉄筋14と連続している。他方の端部ではプレキャスト外型枠の端面18bとプレキャスト内型枠の端面19bとのそれぞれから所定長さの帯鉄筋13,14が突き出している。 Substantially rectangular and become formwork units U B of B type used in the shorter side portion of the cross-section, as shown in FIG. 5 (b), and precast outer frame 18 and the precast inner die frame 19 are opposed, truss The members 21 are connected. And the band rebars 13 and 14 are arrange | positioned at each of the precast outer formwork 18 and the precast inner formwork 19, and the intermediate | middle belt reinforcement 15 is arrange | positioned so that these may be connected. Similarly to the A- type formwork unit U A , the band rebar 13 protruding from the end surface 18a of the precast outer formwork 18 is bent into a U shape at one end in the horizontal direction, and the precast inner formwork 19 It is continuous with the belt reinforcing bar 14 protruding from the end face 19a. At the other end, strip reinforcing bars 13 and 14 of a predetermined length protrude from the end face 18b of the precast outer mold and the end face 19b of the precast inner mold, respectively.

隔壁となる部分に用いられるCタイプの型枠ユニットUCは、図5(c)に示すように、2枚のプレキャスト型枠20a,20bが所定間隔をあけて対向し、これらがトラス部材21によって互いに連結されている。また、それぞれのプレキャスト型枠20a,20bに帯鉄筋23及び中間帯鉄筋15が配置され、水平方向における端面からは第1のプレキャスト型枠20a及び第2のプレキャスト型枠20bのそれぞれから帯鉄筋23が突き出している。 As shown in FIG. 5 (c), the C type mold unit U C used for the partition wall portion has two precast molds 20a, 20b facing each other with a predetermined interval, and these are the truss members 21. Are connected to each other. Moreover, the band reinforcement 23 and the intermediate band reinforcement 15 are arrange | positioned at each precast formwork 20a, 20b, and the band reinforcement 23 from each of the 1st precast formwork 20a and the 2nd precast formwork 20b from the end surface in a horizontal direction. Is sticking out.

上記のような型枠ユニットは、工場又は製作ヤードにおいて次のように製作することができる。なお、図7は、型枠ユニットを製作するために鉄筋を配置し、型枠を設置した状態を示す概略立断面図及び概略平断面図である。
まず、トラス部材21を型枠ユニットUA,UBの製作台31上に設置する。そして、プレキャスト外型枠16,18及びプレキャスト内型枠17,19に埋め込む帯鉄筋13,14を配置する。帯鉄筋13,14は水平方向に配置し、上下方向に複数の帯鉄筋を所定の間隔で型枠ユニットUA,UBの高さ方向のほぼ全域に配列する。これらの帯鉄筋13,14はほぼ鉛直方向に組み立て筋を適切な間隔で設け、これらに支持させる。また、トラス部材21に支持させても良い。
帯鉄筋13,14が配置されると、プレキャスト外型枠16,18に埋め込む帯鉄筋13とプレキャスト内型枠17,19に埋め込む帯鉄筋14とに両端を係止し、中間帯鉄筋15を水平に配置する。この中間帯鉄筋15は、軸線がプレキャスト外型枠16,18及びプレキャスト内型枠17,19とほぼ垂直となるように対向する位置間で帯鉄筋13,14に係止する。そして、上下方向に配列した帯鉄筋13,14の全てについて同じ位置に設けて上下に複数を配列する。また、これらの中間帯鉄筋15を水平方向に所定の間隔で複数の位置に設け、橋脚の完成時には帯鉄筋13,14がコンクリート部材の表面側に押し出されるのを拘束できるものとする。
The above-mentioned formwork unit can be manufactured as follows in a factory or a manufacturing yard. FIG. 7 is a schematic elevational sectional view and a schematic plan sectional view showing a state in which reinforcing bars are arranged in order to manufacture a formwork unit and the formwork is installed.
First, the truss member 21 is installed on the production base 31 of the formwork units U A and U B. Then, the reinforcing bars 13 and 14 embedded in the precast outer molds 16 and 18 and the precast inner molds 17 and 19 are arranged. Hoop reinforcement 13 is placed horizontally, vertically formwork unit a plurality of hoop reinforcement at predetermined intervals in U A, arranged in substantially the entire height direction of the U B. These band reinforcing bars 13 and 14 are provided with an assembly bar at an appropriate interval in a substantially vertical direction, and are supported by these. Further, the truss member 21 may be supported.
When the band reinforcing bars 13 and 14 are arranged, both ends are locked to the band reinforcing bar 13 embedded in the precast outer mold frames 16 and 18 and the band reinforcing bar 14 embedded in the precast inner mold frames 17 and 19, and the intermediate band reinforcing bar 15 is horizontally disposed. To place. The intermediate rebar 15 is locked to the rebars 13 and 14 between the opposing positions so that the axis is substantially perpendicular to the precast outer molds 16 and 18 and the precast inner molds 17 and 19. And all the strip reinforcing bars 13 and 14 arranged in the up-and-down direction are provided in the same position, and a plurality is arranged up and down. Further, these intermediate strip reinforcing bars 15 are provided at a plurality of positions in the horizontal direction at predetermined intervals, and when the pier is completed, the strip reinforcing bars 13 and 14 can be restrained from being pushed out to the surface side of the concrete member.

帯鉄筋13,14及び中間帯鉄筋15が配置されると、帯鉄筋13,14の両側にこのプレキャスト外型枠16,18及びプレキャスト内型枠17,19のコンクリートを打設するための型枠を設ける。橋脚の構築現場で打設されるコンクリートと接触する面を形成する内側の型枠32は、トラス部材21の第1の弦材21aおよび第2の弦材21bと突き合わせるとともに、中間帯鉄筋15が貫通するように設ける。また、この内側の型枠32と対向し、橋脚となるコンクリート部材の外周面又は内周面を形成する外側の型枠33を設ける。そして、上記外側の型枠33と内側の型枠32との間にコンクリートを打設し、帯鉄筋13,14及び中間帯鉄筋15の両端部を埋め込むとともに、トラス部材21の2つの弦材21a,21bから突き出したアンカー21dを埋め込む。これにより、中間帯鉄筋15及びトラス部材21で連結されたプレキャスト外型枠16,18及びプレキャスト内型枠17,19を備えた型枠ユニットUA,UBが完成する。
なお、Cタイプの型枠ユニットUCについては、第1のプレキャスト型枠20aと第2のプレキャスト型枠20bに埋め込む帯鉄筋23の配置、中間帯鉄筋15の配置、内側及び外側の型枠の形成及びコンクリートの打設を同様に行って、Cタイプの型枠ユニットUCを製作することができる。
When the band reinforcing bars 13 and 14 and the intermediate band reinforcing bar 15 are arranged, the formwork for placing the concrete of the precast outer molds 16 and 18 and the precast inner molds 17 and 19 on both sides of the band reinforcing bars 13 and 14 is provided. Is provided. The inner formwork 32 that forms a surface that comes into contact with the concrete placed at the construction site of the pier is abutted against the first chord member 21a and the second chord member 21b of the truss member 21, and the intermediate band reinforcing bar 15 Is provided so as to penetrate. In addition, an outer mold 33 is provided which faces the inner mold 32 and forms an outer peripheral surface or an inner peripheral surface of a concrete member serving as a pier. Then, concrete is placed between the outer mold frame 33 and the inner mold frame 32 to embed both ends of the band reinforcing bars 13 and 14 and the intermediate band reinforcing bar 15, and the two string members 21 a of the truss member 21. , 21b protruding from the anchor 21d. Thereby, the formwork units U A and U B provided with the precast outer molds 16 and 18 and the precast inner molds 17 and 19 connected by the intermediate band reinforcing bar 15 and the truss member 21 are completed.
Note that the mold unit U C C-type arrangement of the first precast mold 20a and hoop reinforcement 23 embedded in the second precast mold 20b, the arrangement of the intermediate band rebar 15, the inner and outer mold the pouring of the formation and concrete similarly performed on, it is possible to manufacture the mold unit U C of C type.

次に上記型枠ユニットUA,UB,UCを用いた橋脚2の構築方法について説明する。
基礎となるケーソン4又はフーチング5を形成し、橋脚2の主鉄筋11,12の下端部を上記ケーソン4又はフーチング5に埋め込んで上方に突き出しておく。この主鉄筋11,12が立ち上げられた部分に橋脚2の下端部の第1の施工区分を構築する。図1(b)に示す橋脚2の下部のコンクリート部材厚が拡大された部分2bつまり内周面にテーパが設けられた部分は、構築現場において鉄筋の組み立て及び型枠の組み立てを行って、コンクリートを打設する。つまり、主鉄筋11,12の周囲を囲む帯鉄筋13及び内周面に沿った帯鉄筋14を配置するとともに中間帯鉄筋15を配置する。そして、外周面を形成するための外型枠、内周面を形成するための内型枠及び隔壁を形成するための型枠を設置して、これらの型枠に囲まれた範囲にコンクリートを打設する。
Next, a method for constructing the pier 2 using the above-mentioned formwork units U A , U B , U C will be described.
The base caisson 4 or footing 5 is formed, and the lower ends of the main reinforcing bars 11 and 12 of the pier 2 are embedded in the caisson 4 or footing 5 and protrude upward. The 1st construction division of the lower end part of the pier 2 is built in the part where these main reinforcing bars 11 and 12 were started. The portion 2b in which the concrete member thickness at the lower part of the pier 2 shown in FIG. 1B is enlarged, that is, the portion where the inner peripheral surface is tapered is assembled at the construction site by rebar assembly and formwork assembly. To cast. That is, the band reinforcing bar 13 surrounding the main reinforcing bars 11 and 12 and the band reinforcing bar 14 along the inner peripheral surface are arranged, and the intermediate band reinforcing bar 15 is arranged. Then, an outer mold frame for forming the outer peripheral surface, an inner mold frame for forming the inner peripheral surface, and a mold frame for forming the partition wall are installed, and the concrete is placed in a range surrounded by these mold frames. To cast.

橋脚の下端部における第1の施工区分が構築されると、図6に示すように、橋脚の既に形成された部分2e上に予め形成されている型枠ユニットUA,UB,UCを配置する。型枠ユニットUA,UB,UCはクレーン等によって吊り上げ、トラス部材21及び中間帯鉄筋15によってほぼ平行に連結された2つのプレキャストコンクリートの型枠の間に、既に立ち上げられている主鉄筋11,12を挿通させて設置する。一つの施工区分について型枠ユニットは、Aタイプの型枠ユニットUAを2つ、Bタイプの型枠ユニットUBを2つ、及び一つのCタイプの型枠ユニットUCを、図3に示すように配置する。これらの型枠ユニットUA,UB,UCはほぼ同じ高さで一施工区分の高さとなっており、ほぼ長方形となった断面形状の長辺部分にAタイプ、短辺部分にBタイプ及び隔壁の部分にCタイプを配置し、断面の隅角部2a及び長辺部分と隔壁部分との接合部2fでは、型枠ユニット間に間隔を開けて開放された領域を設けておく。 When the first construction section at the lower end of the pier is constructed, as shown in FIG. 6, the formwork units U A , U B , U C formed in advance on the already formed part 2e of the pier are replaced. Deploy. The formwork units U A , U B , and U C are lifted by a crane or the like, and are already set up between two precast concrete formwork connected almost in parallel by the truss member 21 and the intermediate strip rebar 15. Reinforcing bars 11 and 12 are installed. Mold units for one construction segment, two mold units U A A type, two mold units U B of B type, and one C-type formwork unit U C, Figure 3 Arrange as shown. These formwork units U A , U B , and U C have almost the same height and the height of one construction section. The A type is on the long side of the cross-sectional shape that is almost rectangular, and the B type is on the short side. In addition, the C type is disposed in the partition wall portion, and an open region is provided with a space between the mold unit at the corner 2a of the cross section and the joint portion 2f between the long side portion and the partition wall portion.

上記断面の隅角部2aつまり図2中に示すA部分では、図8に示すように、隣り合うAタイプの型枠ユニットUAとBタイプの型枠ユニットUBとのいずれか一方(図8の例ではUB)は、プレキャスト外型枠18とプレキャスト内型枠19とから帯鉄筋13,14が突き出し、これらがU字状に連続している。そして、U字状に曲げ回された部分13bが隅角部2aの外周面に沿った位置となるように配置する。また、他方の型枠ユニット(図8の例ではUA)は、プレキャスト外型枠16とプレキャスト内型枠17とからそれぞれ帯鉄筋13,14の端部の所定長さが水平に該隅角部2aに向かって突き出すように配置する。 In the A portion shown in corners 2a of clogging Figure 2 above section, as shown in FIG. 8, either one (Figure of mold units of adjacent A-type U A and B type mold unit U B U B) is an 8 example, the hoop 13 from precast outer frame 18 and the precast within mold 19. protrude, they are continuous in a U-shape. And it arrange | positions so that the part 13b bent in the U-shape may become a position along the outer peripheral surface of the corner part 2a. Further, (U A in the example of FIG. 8) the other mold units, predetermined length horizontally該隅angle end of the precast outer frame 16 and the precast inner mold frame 17, respectively zone from the Metropolitan rebar 13 It arrange | positions so that it may protrude toward the part 2a.

水平に所定長が突き出した上記帯鉄筋13a,14aには、図8に示すようにU字状に曲げ加工がなされたU字鉄筋24を接続する。U字鉄筋24は、U字状の曲げ加工がされてほぼ平行となった直線部分24a,24bを、水平に突き出した上記帯鉄筋13a,14aの延長線上に支持し、この延長線に沿って隅角部から上記帯鉄筋13a,14aの端面に向かって差し入れる。このようにU字鉄筋24を差し入れることにより、隅角部2aに複数の主鉄筋11,12が立設されていても、これらに阻害されることなく、端面を型枠ユニットから突き出した帯鉄筋13a,14aの端面に突き合わせることができる。そして、このときU字鉄筋24の曲げ回された部分は橋脚断面の隅角部2aで外周面に沿って配置されるものとし、上記U字鉄筋24と水平に突き出した帯鉄筋13a,14aとを接続する。この接続作業は、隣り合う型枠ユニット間の開放された領域で行うことができる。   A U-shaped reinforcing bar 24 bent in a U-shape as shown in FIG. 8 is connected to the band reinforcing bars 13a and 14a that protrude horizontally by a predetermined length. The U-shaped reinforcing bar 24 supports the straight portions 24a and 24b which are U-shaped bent and substantially parallel to each other on the extension line of the band reinforcing bars 13a and 14a protruding horizontally, and along the extension line. It is inserted from the corner portion toward the end faces of the band reinforcing bars 13a and 14a. By inserting the U-shaped reinforcing bar 24 in this way, even if a plurality of main reinforcing bars 11 and 12 are erected at the corner 2a, the end face is projected from the formwork unit without being obstructed by them. It can face | match with the end surface of the reinforcing bars 13a and 14a. At this time, the bent part of the U-shaped reinforcing bar 24 is arranged along the outer peripheral surface at the corner 2a of the pier cross section, and the band reinforcing bars 13a and 14a protruding horizontally from the U-shaped reinforcing bar 24, Connect. This connection work can be performed in an open area between adjacent formwork units.

上記U字鉄筋24と型枠ユニットUAから水平に突き出した帯鉄筋13a,14aとは、いずれもいわゆる異形鉄筋であって、これらの接続にはグラウト式の継ぎ手を用いるのが望ましい。つまり、鋼製の筒状部材の内側に両端から接続する鉄筋の端部を挿入し、この筒状部材内にモルタル又は合成樹脂のグラウトを注入して硬化させるものである。また、異形鉄筋の外周面の凸状部がねじ山となった全ねじ棒鋼を用い、このねじ山にねじり合わされた長いナット状の機械継ぎ手25によって上記U字鉄筋24と型枠ユニットUAから突き出した帯鉄筋13a,14aとを接続することもできる。さらに、帯鉄筋の機能を失わないものであれば他の態様の継ぎ手を用いることもできる。 The U-shaped reinforcing bars 24 and mold unit U A hoop projecting horizontally from 13a, the 14a, both a so-called deformed bars, that in these connections using joint grout expression desired. That is, the end part of the reinforcing bar connected from both ends is inserted inside the tubular member made of steel, and a mortar or synthetic resin grout is injected into the tubular member and cured. Further, a full threaded steel bar having a thread on the outer peripheral surface of the deformed reinforcing bar is used, and the U-shaped reinforcing bar 24 and the formwork unit U A are connected to each other by a long nut-like mechanical joint 25 screwed onto the thread. The protruding band reinforcing bars 13a and 14a can also be connected. Furthermore, the joint of another aspect can also be used as long as it does not lose the function of the rebar.

このように一方の型枠ユニットから突き出してU字状に曲げ回されている帯鉄筋13bと、他方の型枠ユニットから水平に突き出した帯鉄筋13a,14aと接続されたU字鉄筋24とが、隅角部2aにおいて重ね合わされ、これらが隅角部2aに配置された主鉄筋11,12を取り囲むものとなっており、これらの鉄筋は帯鉄筋として主鉄筋11,12が隅角部2aのコンクリートから外周面側に押し出されるのを拘束することができる。   Thus, the rebar 13b protruding from one mold unit and bent in a U shape, and the U rebar 24 connected to the rebars 13a and 14a protruding horizontally from the other mold unit are provided. The corner bars 2a are overlapped with each other and surround the main reinforcing bars 11 and 12 disposed in the corner section 2a. These reinforcing bars are band reinforcing bars, and the main reinforcing bars 11 and 12 are the corner bars 2a. Extrusion from the concrete to the outer peripheral surface side can be restrained.

なお、本実施の形態では、上記型枠ユニットUAの帯鉄筋13a,14aの所定長さが水平に突き出した端面の位置は、橋脚断面の辺に沿った方向でずれた位置に設定されている。つまりプレキャスト外型枠16の端面はプレキャスト内型枠17より隅角部2aから離れた位置に設定されている。そして、プレキャスト外型枠16の端面から突き出した複数の帯鉄筋13aの長さが、長いものと短いものとが上下に交互となるように配列されている。これらの水平に突き出した帯鉄筋13aに接続するU字鉄筋の直線部分24aの長さは、上記帯鉄筋13aの突き出し長と対応するように交互に調整されており、帯鉄筋13aの継ぎ手位置が上下に配列された帯鉄筋13の全てで水平方向に同じ位置となるのを回避することができる。つまり帯鉄筋13aの継ぎ手位置が交互に水平にずれた位置となり、鉄筋の信頼性を向上するとともに、均質なコンクリートの打設が可能となる。一方、橋脚断面の内周面に沿った位置における帯鉄筋14aの継ぎ手は隅角部2aに近い位置に設けられ、水平方向の同じ位置となっているが、外周面に沿った帯鉄筋の継ぎ手と同様に、プレキャスト内型枠17の端面の位置を隅角部2aから離れた位置とし、交互に継ぎ手の位置をずらすように設定することもできる。
また、プレキャスト外型枠16及びプレキャスト内型枠17の双方について端面の位置を隅角部2aと近い位置に設定し、上下に複数が配置された帯鉄筋13,14の全てについて継ぎ手が同じ位置となるようにすることもできる。このようにプレキャスト外型枠16及びプレキャスト内型枠17の端面の位置を隅角部2aと近い位置に設定することにより、橋脚の構築現場で組み立てる型枠の面積を少なくすることができる。
In this embodiment, the position of the end face of hoop 13a, a predetermined length of 14a projecting horizontally above form unit U A is set to a position shifted in a direction along the sides of the piers section Yes. That is, the end face of the precast outer mold 16 is set at a position farther from the corner 2 a than the precast inner mold 17. And the length of the some rebar 13a protruded from the end surface of the precast outer formwork 16 is arranged so that a long thing and a short thing may alternate up and down. The lengths of the straight portions 24a of the U-shaped reinforcing bars connected to the horizontally protruding band reinforcing bars 13a are alternately adjusted so as to correspond to the protruding lengths of the band reinforcing bars 13a, and the joint positions of the band reinforcing bars 13a are adjusted. It is possible to avoid having the same position in the horizontal direction in all of the strip reinforcing bars 13 arranged vertically. In other words, the joint positions of the band reinforcing bars 13a are alternately shifted horizontally, so that the reliability of the reinforcing bars is improved and uniform concrete can be placed. On the other hand, the joint of the band rebar 14a at the position along the inner peripheral surface of the pier cross section is provided at a position close to the corner 2a and is the same position in the horizontal direction, but the joint of the band rebar along the outer peripheral surface. Similarly to the above, the position of the end face of the precast inner mold 17 can be set to a position away from the corner 2a, and the position of the joint can be alternately shifted.
Further, the positions of the end faces of both the precast outer mold 16 and the precast inner mold 17 are set close to the corners 2a, and the joints are the same for all of the strip reinforcing bars 13 and 14 arranged in the upper and lower directions. It can also be made to be. Thus, by setting the positions of the end faces of the precast outer mold 16 and the precast inner mold 17 close to the corner 2a, the area of the mold assembled at the construction site of the pier can be reduced.

図2に示すB部分、つまりほぼ長方形となった橋脚断面の長辺部分と隔壁とが接合される部分は、図9に示すように、Aタイプの型枠ユニットUAのプレキャスト内型枠17が途切れた部分にCタイプの型枠ユニットUCが備えるプレキャスト型枠20の端面が間隔を開けて対向するように配置する。このとき、Cタイプの型枠ユニットUCが備えるプレキャスト型枠20の端面からは水平に帯鉄筋23の所定の長さが突き出している。この帯鉄筋23の端面を、Aタイプの型枠ユニットUAのプレキャスト内型枠17が途切れた部分から突き出している鉄筋22の端面と間隔を開けて対向させる。これらの鉄筋22,23の端面間には、図9に示すようにこれらの間隔に合わせて切断された鉄筋26を介在させ、これらの両端をAタイプの型枠ユニットUAから突き出した鉄筋22とCタイプの型枠ユニットUCから突き出した帯鉄筋23とに継ぎ手25によって連結する。その後、この連結部分に中間帯鉄筋15を配置する。この中間帯鉄筋15も端部にプレー15aが固着されたプレート定着型の中間帯鉄筋を使用し、上下方向に複数が配列された帯鉄筋23の全てについて配置する。 The portion B shown in FIG. 2, that is, the portion where the long side portion of the cross section of the pier that is substantially rectangular and the partition wall is joined, as shown in FIG. 9, is the precast inner formwork 17 of the A type formwork unit UA. The end face of the precast mold 20 provided in the C-type mold unit U C is arranged at a portion where the gap is interrupted so as to face each other with a gap. At this time, a predetermined length of the band rebar 23 protrudes horizontally from the end surface of the precast formwork 20 included in the C type formwork unit UC. The end face of the rebar 23 is opposed to the end face of the reinforcing bar 22 protruding from the portion where the precast inner form 17 of the A type formwork unit UA is interrupted. As shown in FIG. 9, reinforcing bars 26 cut in accordance with these intervals are interposed between the end faces of these reinforcing bars 22 and 23, and both ends of the reinforcing bars 22 protrude from the A type formwork unit UA. And a band rebar 23 protruding from the C- type formwork unit U C by a joint 25. After that, the intermediate band reinforcing bar 15 is arranged at this connecting portion. This intermediate band reinforcing bar 15 is also a plate fixing type intermediate band reinforcing bar with a plate 15a fixed to the end thereof, and is arranged for all of the band reinforcing bars 23 arranged in a plurality in the vertical direction.

このように、配列された型枠ユニット間の開放された部分を利用して、各隅角部2a並びにAタイプの型枠ユニットUAとCタイプの型枠ユニットUCの接合部2fへの配筋が終了すると、これらの開放された部分のそれぞれに型枠(図示しない)を設置する。
その後、これらの型枠内、プレキャスト外型枠16,18とプレキャスト内型枠17,19の間、及び隔壁の2つのプレキャスト型枠20a,20b間にコンクリートを打設し、露出している帯鉄筋13,14、中間帯鉄筋15、主鉄筋11,12及びトラス部材21等を埋め込むとともにプレキャスト型枠16,17,18,19,20と密着させる。このコンクリートが硬化することにより、必要な鉄筋が埋め込まれるとともにプレキャストコンクリートの型枠と一体となった橋脚の一施工区分が形成される。これを順次に繰り返し、上方に施工区分毎に橋脚を立ち上げる。橋脚の最上部のコンクリート部材厚が拡大された部分及び中実部分2cは下端部と同様に橋脚の構築現場で鉄筋及び型枠を組み立て、コンクリートを打設して形成する。このようにして完成した橋脚上に橋桁が構築される。
Thus, by utilizing the open portion between arrayed mold unit, to the junction 2f of mold units U C formwork units U A and C type of each corner portion 2a and A-type When the bar arrangement is completed, a mold (not shown) is installed in each of these open portions.
After that, concrete is cast in these molds, between the precast outer molds 16 and 18 and the precast inner molds 17 and 19, and between the two precast molds 20a and 20b of the partition wall, and the exposed band. The reinforcing bars 13, 14, the intermediate band reinforcing bars 15, the main reinforcing bars 11, 12, the truss member 21, etc. are embedded and brought into close contact with the precast molds 16, 17, 18, 19, 20. As the concrete hardens, the necessary reinforcing bars are embedded and one construction section of the pier that is integrated with the precast concrete formwork is formed. This is repeated sequentially, and the pier is set up for each construction section above. The part where the concrete member thickness of the uppermost part of the pier is enlarged and the solid part 2c are formed by assembling the reinforcing bars and the formwork at the construction site of the pier and placing the concrete in the same manner as the lower end part. A bridge girder is built on the completed pier.

本願発明の橋脚の構築方法は、以上に説明した実施の形態に限定されるものではなく、本願発明の範囲内で他の形態として実施することもできる。
例えば、プレキャスト外型枠16とプレキャスト内型枠17とを連結するためのトラス部材21に設けるアンカーは、図10に示すように帯鉄筋13,14の上下方向のピッチに合わせて設けておき、型枠ユニットを形成するときに帯鉄筋13,14をこれらのアンカー21eに支持させて配置することができる。また、これらのアンカー21eの先端部は上方に曲折したものを用いることもできる。これにより帯鉄筋13,14の配置を効率よく行うことができる。
The construction method of the pier of the present invention is not limited to the embodiment described above, and can be implemented as other forms within the scope of the present invention.
For example, the anchor provided on the truss member 21 for connecting the precast outer mold 16 and the precast inner mold 17 is provided in accordance with the vertical pitch of the strip reinforcing bars 13 and 14 as shown in FIG. When forming the form unit, the rebars 13 and 14 can be arranged to be supported by these anchors 21e. Further, the tip portions of these anchors 21e can be bent upward. Thereby, arrangement | positioning of the band reinforcement 13 and 14 can be performed efficiently.

また、トラス部材21を用いることなく、又はトラス部材21とともに中間帯鉄筋15を用いて対向するプレキャスト外型枠16とプレキャスト内型枠17を、相対的な変位を抑制して連結することができる。例えば、図11に示すように上下方向に配列された中間帯鉄筋15に斜め方向に軸線を有する鉄筋つまり斜め部材27を複数の中間帯鉄筋15にわたって固定する。これらの斜め部材27と帯鉄筋15と2つのプレキャストコンクリート板16,17とがトラス構造を形成し、これらで形成される型枠ユニットを吊り上げたときに、2つのプレキャストコンクリート板の相互間の変位を小さく抑制することが可能となる。   Further, the precast outer mold frame 16 and the precast inner mold frame 17 which are opposed to each other without using the truss member 21 or together with the truss member 21 using the intermediate band reinforcing bar 15 can be connected while suppressing relative displacement. . For example, as shown in FIG. 11, a reinforcing bar having an axis in an oblique direction, that is, an oblique member 27, is fixed over a plurality of intermediate band reinforcing bars 15 in the intermediate band reinforcing bars 15 arranged in the vertical direction. When the slanted member 27, the strip reinforcing bar 15, and the two precast concrete plates 16 and 17 form a truss structure, and the formwork unit formed by these members is lifted, the displacement between the two precast concrete plates Can be kept small.

一方、隅角部に配置する水平方向の鉄筋は、上記実施の形態のようにU字鉄筋24に限定されるものではなく、図12又は図13に示すように鉄筋を水平に配置することもできる。
図12に示す例では、L字状に曲げ加工がなされたL字鉄筋28と、一端がフック状に曲げ加工されたフック付き鉄筋29を用いるものである。また、隅角部2aで隣り合う一方の型枠ユニットUAが有するプレキャスト外型枠16の帯鉄筋13とプレキャスト内型枠17の帯鉄筋14とは、図8に示す実施の形態と同様に、水平方向に所定長を付き出しておく。他方の型枠ユニットUBが有するプレキャスト外型枠18の帯鉄筋13は、端面から所定長を突き出しておき、プレキャスト内型枠19の帯鉄筋14は、橋脚の隣り合う側面2d付近まで伸長して先端にフック状の曲げ加工を施しておく。
On the other hand, the horizontal reinforcing bars arranged at the corners are not limited to the U-shaped reinforcing bars 24 as in the above embodiment, and the reinforcing bars may be arranged horizontally as shown in FIG. 12 or FIG. it can.
In the example shown in FIG. 12, an L-shaped reinforcing bar 28 bent in an L shape and a hooked reinforcing bar 29 whose one end is bent in a hook shape are used. Further, the band reinforcing bar 13 of the precast outer mold 16 and the band reinforcing bar 14 of the precast inner mold 17 included in one mold unit U A adjacent to each other at the corner 2a are the same as in the embodiment shown in FIG. A predetermined length is added in the horizontal direction. Hoop 13 of precast outer frame 18 having the other mold units U B is previously protrude a predetermined length from the end face, hoop 14 precast inner die frame 19, extends to the vicinity of the side surface 2d adjacent piers The hook is bent at the tip.

上記L字状鉄筋28は、一方の型枠ユニットUAのプレキャスト外型枠16から突き出した帯鉄筋13aの延長線に沿って先端を上記帯鉄筋13aの端面に向かって差し入れる。そして、他方の型枠ユニットUBのプレキャスト内型枠19から突き出した帯鉄筋14bの先端部に設けられたフック部分が係止されるものとし、先端が突き合わされた上記帯鉄筋13aに継ぎ手25によって接続する。一方、L字状に曲げ加工された後端部28aは他方の型枠ユニットUBのプレキャスト外型枠18から突き出した帯鉄筋13cに接続する。また、フック付き鉄筋29は、一方の型枠ユニットUAのプレキャスト内型枠17から突き出した帯鉄筋14aの延長線に沿って差し入れ、先端を該帯鉄筋14aに接続するとともに、後端部のフック部分を他方の型枠ユニットUBのプレキャスト外型枠18から突き出した帯鉄筋13cに係止する。 The L-shaped reinforcing bar 28, along the extension of the hoop 13a projecting from precast outer frame 16 of one of the mold units U A insert the tip toward the end face of the strip reinforcing bars 13a. Then, it is assumed that distal end hook portion provided in the other mold units U hoop 14b projecting from precast inner die frame 19 of B is locked, the joint 25 to the band reinforcement 13a whose tip butted Connect by. On the other hand, processed rear portion 28a bent into an L-shape is connected to the hoop 13c projecting from the other mold units U B precast outer frame 18. Further, hooked rebar 29, pledged along an extension line of the hoop 14a projecting from precast inner die frame 17 of one of the mold units U A, with connecting tip belt-reinforcing bar 14a, the rear end portion locking the hook portion to the hoop 13c projecting from the other mold units U B precast outer frame 18.

図13に示す例は、後端部がフック状に曲げ加工された2本のフック付き鉄筋41,42を用いるものである。
隅角部2aで隣り合う一方の型枠ユニットUAが有するプレキャスト外型枠16の帯鉄筋13とプレキャスト内型枠17の帯鉄筋14とは、図8に示す実施の形態と同様に、水平方向に所定長を付き出しておく。ただし、この例では型枠ユニットUAのプレキャスト外型枠16とプレキャスト内型枠17の端面16b,17bの位置が帯鉄筋13,14を配置する方向において揃えられた位置になっている。一方、型枠ユニットUBが有するプレキャスト外型枠18及びプレキャスト内型19から突き出した帯鉄筋13bは、図8に示す例と同様にU字状に曲げ加工されて連続するものとなっている。
The example shown in FIG. 13 uses two hooked reinforcing bars 41 and 42 whose rear end portions are bent into a hook shape.
The hoop 14 of hoop 13 and precast inner die frame 17 of the precast outer frame 16 having the one of the mold units U A, which are adjacent in the corners 2a, similarly to the embodiment shown in FIG. 8, the horizontal A predetermined length is given in the direction. However, the end face 16b of the precast outer frame 16 and the precast inner die frame 17 of the mold unit U A in this example, has become a position where the position of 17b are aligned in the direction of placing the hoop 13,14. On the other hand, hoop 13b projecting from precast outer frame 18 and pre-cast in the mold 19 having the mold unit U B has a successive ones are bent to the U-shaped as in the example shown in FIG. 8 .

上記フック付き鉄筋41は、一方の型枠ユニットUAのプレキャスト外型枠16から突き出した帯鉄筋13aの延長線に沿って先端を上記帯鉄筋13aの端面に向かって差し入れる。そして、他方の型枠ユニットUBのプレキャスト外型枠18及びプレキャスト内型枠19から突き出してU字状に曲げ回された帯鉄筋13bの一部と重ね合わせ、先端が突き合わされた上記帯鉄筋13aに継ぎ手25によって接続する。もう一本のフック付き鉄筋42は、プレキャスト内型枠17から突き出した帯鉄筋14aの延長線に沿って先端を上記帯鉄筋14aの端面に向かって差し入れ、上記帯鉄筋14aと接続する。これらのフック付き鉄筋41,42の後端部に設けられたフック状に曲げ加工した部分は、他方の型枠ユニットUBから突き出したU字状の帯鉄筋13bの一部と重ね合わせ、隅角部のコンクリート中に定着する。
なお、上記L字状鉄筋28及びフック付き鉄筋29,41,42と帯鉄筋との接続には機械継ぎ手を用いるのが、作業効率を向上させるために望ましい。
このように水平方向の鉄筋を配置しても、作業量を低減することができるともに、鉄筋の継ぎ手の箇所を少なくすることが可能となる。
It said hooked rebar 41, insert the tip along the extension line of the hoop 13a projecting from precast outer frame 16 of one of the mold units U A towards the end surface of the band reinforcement 13a. Then, it protrudes from the other mold units U precast outer frame 18 and precast within mold 19 B superimposed with part of the bending around the hoop 13b in a U shape, the belt reinforcing bar tip is abutted 13a is connected by a joint 25. Another hooked reinforcing bar 42 is inserted into the end of the band reinforcing bar 14a along the extension line of the band reinforcing bar 14a protruding from the precast inner mold 17, and is connected to the band reinforcing bar 14a. Processing portion bent in a hook shape which is provided at the rear end of these hooked rebar 41, superimposed with a portion of the U-shaped hoop 13b protruding from the other mold units U B, corner It settles in the corner concrete.
In order to improve working efficiency, it is preferable to use a mechanical joint for connecting the L-shaped reinforcing bar 28 and hooked reinforcing bars 29, 41, and 42 to the band reinforcing bar.
Thus, even when horizontal reinforcing bars are arranged, the amount of work can be reduced and the number of joints of reinforcing bars can be reduced.

一方、ほぼ長方形となった橋脚断面の長辺部分と隔壁とが接合される部分についても、図9に示すように水平方向の鉄筋を配置する方法の他に、例えば図14又は図15に示すように水平方向の鉄筋を配置することもできる。
図14に示す例は、図9に示す例と同様にAタイプの型枠ユニットUA’のプレキャスト内型枠17が途切れた部分に、隔壁の帯鉄筋と接続する鉄筋51を突き出しておく。ただし、この例ではAタイプの型枠ユニットUA’のプレキャスト内型枠17は、途切れた部分で隔壁の側面に沿った方向に曲折し、隔壁に沿った方向に所定長が突き出している。そしてこの突き出した端面から上記鉄筋51が突き出している。
一方、隔壁を形成するためのCタイプの型枠ユニットUCは、対向するように配置された2つのプレキャスト型枠20,20からそれぞれ帯鉄筋23が突き出し、これらがU字状に曲げ回されて連続している。このU字状となって突き出した帯鉄筋の先端部23aは、Aタイプの型枠ユニットUA’から突き出した上記鉄筋51の先端と重ならない位置に設定しておく。そして、Aタイプの型枠ユニットUA’から突き出した上記鉄筋51には、図14に示すように側方からフック付き鉄筋52を継ぎ手53によって接続する。このフック付き鉄筋52がU字状となった帯鉄筋と重ね合わされるとともにフック状に曲げ加工された部分が橋脚の構築現場で打設されたコンクリート内に埋め込まれることによって帯鉄筋23の引張力が伝達されるとともに鉛直方向の鉄筋の変位を拘束することができる。
On the other hand, in addition to the method of arranging the horizontal reinforcing bars as shown in FIG. 9, for example, as shown in FIG. 14 or FIG. In this way, horizontal reinforcing bars can be arranged.
In the example shown in FIG. 14, similarly to the example shown in FIG. 9, a reinforcing bar 51 connected to the band reinforcing bar of the partition wall is protruded in a portion where the precast inner mold 17 of the A type mold unit U A ′ is interrupted. However, in this example, the precast inner mold 17 of the A type mold unit U A ′ is bent in the direction along the side face of the partition wall at the interrupted portion, and a predetermined length protrudes in the direction along the partition wall. The rebar 51 protrudes from the protruding end surface.
On the other hand, the mold units U C C-type for forming the partition wall protrudes each band reinforcement 23 two precast mold 20, 20 disposed so as to face, it turned bent into a U-shape Are continuous. The tip end portion 23a of the band reinforcing bar protruding in the U shape is set at a position where it does not overlap the tip of the reinforcing bar 51 protruding from the A type formwork unit U A '. Further, as shown in FIG. 14, a hooked reinforcing bar 52 is connected to the reinforcing bar 51 protruding from the A type formwork unit U A ′ from the side by a joint 53. The rebar 52 with the hook is overlapped with the U-shaped band rebar and the portion bent into the hook shape is embedded in the concrete placed at the construction site of the bridge pier, whereby the tensile force of the band rebar 23 is obtained. Is transmitted and the displacement of the reinforcing bars in the vertical direction can be restricted.

図15に示す例は、橋脚断面の長辺部分に用いる型枠ユニットUA”が隔壁と接合される部分で2つに分割されており、分割された型枠ユニットUA”のそれぞれを所定の位置に配置した後にプレキャスト外型枠16とプレキャスト内型枠17に埋め込んである帯鉄筋13,14を継ぎ手54によって接続するものとなっている。なお、この継ぎ手54には管状部材の両端から接続する鉄筋の端部を挿入してグラウトを管状部材内に注入するグラウト式の継ぎ手を用いるのが望ましい。 In the example shown in FIG. 15, the mold unit U A ″ used for the long side portion of the pier cross section is divided into two at the portion joined to the partition wall, and each of the divided mold units U A ″ is predetermined. After being arranged at the position, the band rebars 13 and 14 embedded in the precast outer mold 16 and the precast inner mold 17 are connected by a joint 54. In addition, it is desirable to use the grout type joint which inserts the edge part of the reinforcing bar connected from the both ends of a tubular member and injects grout into a tubular member for this joint 54.

一方、隔壁部分に用いられる型枠ユニットUCは、図9に示す例と同様に2つのプレキャスト型枠20から帯鉄筋23の端部を突き出しておく。そして、型枠ユニットUA”及び型枠ユニットUCを配置した後、2つのプレキャスト型枠20の端面からそれぞれ突き出した帯鉄筋23bの延長線に沿って、橋脚の外周面の外側から2本のフック付き鉄筋55の先端を差し入れる。このフック付き鉄筋55は、図15に示すように後端部にフック状の曲げ加工が施されたものである。このフック付き鉄筋55の先端をプレキャスト型枠20の端面から突き出した帯鉄筋23bと継ぎ手56によって接続し、後端部のフック状に曲げ加工された部分を橋脚の構築現場で打設されるコンクリート中に埋め込んで定着する。
このような構成で、ほぼ長方形となった橋脚断面の長辺部分と隔壁とが接合される部分に水平方向の鉄筋を配置しても、効率の良い作業を実現することができる。
On the other hand, the mold unit U C used for the partition wall portion projects the end of the band reinforcing bar 23 from the two precast molds 20 in the same manner as the example shown in FIG. Then, after the formwork unit U A ″ and the formwork unit U C are arranged, two from the outside of the outer peripheral surface of the pier along the extension lines of the band reinforcing bars 23b respectively protruding from the end faces of the two precast formwork 20 The hooked reinforcing bar 55 is inserted into the hooked reinforcing bar 55. The hooked reinforcing bar 55 has a hook-like bent at its rear end as shown in Fig. 15. The tip of the hooked reinforcing bar 55 is precast. The band reinforcing bar 23b protruding from the end face of the formwork 20 is connected by the joint 56, and the portion bent into a hook shape at the rear end is embedded and fixed in the concrete cast at the construction site of the pier.
With such a configuration, even if a horizontal reinforcing bar is arranged at a portion where the long side portion of the cross section of the pier that is substantially rectangular and the partition wall are joined, efficient work can be realized.

1:橋桁、 2:橋脚、 2a:橋脚断面の隅角部、 3:橋台、 4:ケーソン、 5:フーチング、
11:外周面に沿った位置の主鉄筋、 12:内周面に沿った位置の主鉄筋、 13:外周面に沿った位置の帯鉄筋、 14:内周面に沿った位置の帯鉄筋、 15:中間帯鉄筋、 16:プレキャスト外型枠、 17:プレキャスト内型枠、 18プレキャスト外型枠、 19:プレキャスト内型枠、 20:隔壁部分のプレキャスト型枠、 21:トラス部材、 22:Aタイプの型枠ユニットから突き出した鉄筋、 23:隔壁部分に配置される帯鉄筋、 24:U字鉄筋、 25:継ぎ手、 26:連結鉄筋、 27:斜め部材、 28:L字鉄筋、 29:フック付き鉄筋、
31:製作台、 32:内側の型枠、 33:外側の型枠、
41,42:フック付き鉄筋、
51:隔壁の帯鉄筋と接続する鉄筋、 52:フック付き鉄筋、 53:継ぎ手、 54:継ぎ手、 55:フック付き鉄筋、 56:継ぎ手、
A:Aタイプの型枠ユニット、 UB:Bタイプの型枠ユニット、 UC:Cタイプの型枠ユニット






1: bridge girder, 2: pier, 2a: corner section of pier cross section, 3: abutment, 4: caisson, 5: footing,
11: Main reinforcing bar at a position along the outer peripheral surface, 12: Main reinforcing bar at a position along the inner peripheral surface, 13: A reinforcing bar at a position along the outer peripheral surface, 14: A reinforcing bar at a position along the inner peripheral surface, 15: Intermediate rebar, 16: Precast outer formwork, 17: Precast inner formwork, 18 Precast outer formwork, 19: Precast inner formwork, 20: Precast formwork of partition wall part, 21: Truss member, 22: A Reinforcing bars protruding from a type of formwork unit, 23: Band reinforcing bars arranged in the partition wall part, 24: U-shaped reinforcing bars, 25: Joints, 26: Connecting reinforcing bars, 27: Diagonal members, 28: L-shaped reinforcing bars, 29: Hooks Rebar,
31: Production stand, 32: Inner formwork, 33: Outer formwork,
41, 42: Rebar with hook,
51: Reinforcing bars connected to the reinforcing bars of the bulkhead 52: Reinforcing bars with hooks 53: Fittings 54: Fittings 55: Reinforcing hooks 56: Fittings
U A : A type formwork unit, U B : B type formwork unit, U C : C type formwork unit






Claims (5)

プレキャストコンクリートにより形成された型枠を用い、現場で打設されたコンクリートと前記型枠とを一体として、断面形状が矩形で内部に空間を有する橋脚を構築する方法であって、
所定の高さを有し、橋脚の周方向に複数が配列されて前記橋脚の外周面を形成するプレキャストコンクリートからなるプレキャスト外型枠と、該プレキャスト外型枠と所定の間隔をあけて該プレキャスト外型枠と連結され、前記橋脚の中空となった内周面を形成するプレキャストコンクリートからなるプレキャスト内型枠と、前記プレキャスト外型枠及びプレキャスト内型枠のそれぞれに水平方向に埋設される複数の帯鉄筋と、前記プレキャスト外型枠に埋め込まれた帯鉄筋とプレキャスト内型枠に埋め込まれた帯鉄筋とを水平方向に連結する中間帯鉄筋と、を備えた型枠ユニットを製作しておき、
前記橋脚の基礎又は前記橋脚の既に形成された部分の上に、立設された主鉄筋を前記プレキャスト外型枠と前記プレキャスト内型枠との間に挿通して前記型枠ユニットを載置し、該橋脚の隅角部を除外して周方向に複数の前記型枠ユニットを配列する工程と、
前記隅角部に水平方向の鉄筋を配置するとともに、該隅角部の型枠を現場で組み立てて、前記隅角部の前記型枠内及び前記プレキャスト外型枠とプレキャスト内型枠との間にコンクリートを打設する工程とを含み、
前記型枠ユニットを配列する工程と、前記隅角部の前記鉄筋を配置し、前記型枠を組み立てる工程と、前記コンクリートを打設する工程と、を繰り返して順次に上方に立ち上げることを特徴とする橋脚の構築方法。
A method of constructing a pier having a rectangular cross-sectional shape and having a space inside by using a formwork formed of precast concrete and integrating the concrete placed on site with the formwork,
A precast outer mold made of precast concrete having a predetermined height and arranged in the circumferential direction of the pier to form an outer peripheral surface of the pier, and the precast at a predetermined interval from the precast outer mold A precast inner mold made of precast concrete that is connected to the outer mold and forms a hollow inner peripheral surface of the bridge pier, and a plurality of embedded in the horizontal direction in each of the precast outer mold and the precast inner mold A formwork unit comprising: a steel bar reinforcing bar; and a steel bar reinforcing member embedded in the precast outer formwork and an intermediate belt reinforcing member that horizontally connects the steel bar reinforcing member embedded in the precast inner formwork. ,
On the foundation of the pier or the already formed part of the pier, the main reinforcing bar erected is inserted between the precast outer formwork and the precast inner formwork to place the formwork unit. A step of arranging a plurality of the formwork units in the circumferential direction excluding the corners of the piers;
A horizontal rebar is arranged at the corner, and a mold at the corner is assembled on-site, in the mold at the corner and between the precast outer mold and the precast inner mold. And placing concrete into
The step of arranging the mold units, the step of arranging the reinforcing bars at the corners, assembling the mold, and the step of placing the concrete are sequentially started upward. How to build a pier.
前記隅角部を除外し、該隅角部の両側で隣り合うように配置された前記型枠ユニットの一方は、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に帯鉄筋の端部を突出させておき、
他方の型枠ユニットは、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に突き出し、前記隅角部でU字状に連続した帯鉄筋を有するものとし、
前記型枠ユニットの配列後に前記隅角部に配置する水平方向の鉄筋として、後端部がフック状に曲げ加工された2本の所定長のフック付き鉄筋を用い、前記一方の型枠ユニットの端面から突出した前記帯鉄筋の延長線に沿って該突出した帯鉄筋の端面に向かって前記フック付き鉄筋を先端から差し入れ、該フック付き鉄筋と前記一方の型枠ユニットから突出した前記帯鉄筋の端部とを接続し、
前記フック付き鉄筋のフック状に曲げ加工された部分を、前記隅角部に埋め込んで定着することを特徴とする請求項1に記載の橋脚の構築方法。
One of the mold units arranged so as to be adjacent to both sides of the corner portion excluding the corner portion is formed from the substantially vertical end surfaces of the precast outer mold frame and the precast inner mold frame. Project the end of the band rebar horizontally toward each corner,
The other mold unit protrudes horizontally from the substantially vertical end faces of the precast outer mold frame and the precast inner mold frame toward the corner portion, and is a U-shaped continuous band at the corner portion. Have rebars,
As the horizontal reinforcing bars to be arranged at the corners after the mold unit is arranged, two reinforcing bars with hooks having a rear end bent into a hook shape are used. The rebar with the hook is inserted from the tip toward the end surface of the protruding band reinforcing bar along the extension line of the band reinforcing bar protruding from the end face, and the band reinforcing bar protruding from the hooked reinforcing bar and the one formwork unit Connect the end,
The method of building a pier according to claim 1, wherein a portion of the hooked reinforcing bar bent into a hook shape is embedded and fixed in the corner portion.
前記隅角部を除外し、該隅角部の両側で隣り合うように配置された前記型枠ユニットの一方は、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に帯鉄筋の端部を突出させておき、
他方の型枠ユニットは、前記プレキャスト外型枠及び前記プレキャスト内型枠のほぼ鉛直となった端面から前記隅角部に向かってそれぞれ水平に突き出し、前記隅角部でU字状に連続した帯鉄筋を有するものとし、
前記型枠ユニットの配列後に前記隅角部に配置する水平方向の鉄筋として、U字状に曲げ加工されたU字鉄筋を用い、該U字鉄筋の曲げ加工された部分の両側のほぼ平行となった部分を、前記一方の型枠ユニットの端面から突出した前記帯鉄筋の延長線に沿って該突出した帯鉄筋の端面に向かって差し入れ、該U字鉄筋と前記一方の型枠ユニットから突出した前記帯鉄筋の端部とを接続し、
前記他方の型枠ユニットから突き出した前記帯鉄筋のU字状となるように曲げ回された部分と前記U字鉄筋の曲げ回された部分とで、前記隅角部に配置された前記主鉄筋を囲むことを特徴とする請求項1に記載の橋脚の構築方法。
One of the mold units arranged so as to be adjacent to both sides of the corner portion excluding the corner portion is formed from the substantially vertical end surfaces of the precast outer mold frame and the precast inner mold frame. Project the end of the band rebar horizontally toward each corner,
The other mold unit protrudes horizontally from the substantially vertical end faces of the precast outer mold frame and the precast inner mold frame toward the corner portion, and is a U-shaped continuous band at the corner portion. Have rebars,
A U-shaped reinforcing bar bent in a U-shape is used as a horizontal reinforcing bar arranged in the corner portion after the formwork unit is arranged, and substantially parallel to both sides of the bent portion of the U-shaped reinforcing bar. The inserted portion is inserted along the extension line of the band reinforcing bar protruding from the end surface of the one formwork unit toward the end surface of the protruding band reinforcing bar, and protrudes from the U-shaped reinforcing bar and the one formwork unit. Connected to the end of the rebar
The main reinforcing bar disposed at the corner portion by a portion bent so as to form a U-shape of the band reinforcing bar protruding from the other formwork unit and a bent portion of the U-shaped reinforcing bar The method for constructing a pier according to claim 1, wherein:
前記プレキャスト外型枠と前記プレキャスト内型枠とは、鋼製のトラス部材によって所定の間隔で連結したものとし、
該トラス部材は、前記プレキャスト外型枠と前記プレキャスト内型枠とに密接し、鉛直方向に軸線を有する二つの弦材と、これらを斜め方向に連結する斜材と、前記二つの弦材のそれぞれに固着されるとともにプレキャスト外型枠又はプレキャスト内型枠のコンクリート中に埋め込まれる複数のアンカーを有し、
該アンカーは、上下方向に所定の間隔をおいて水平方向に配置される前記帯鉄筋の上下方向の間隔に合わせて設け、
前記型枠ユニットの製作時において、前記帯鉄筋は前記アンカーに支持させて配置することを特徴とする請求項1から請求項3までのいずれかに記載の橋脚の構築方法。
The precast outer formwork and the precast inner formwork are connected at predetermined intervals by a steel truss member,
The truss member is in close contact with the precast outer formwork and the precast inner formwork, and has two chords having an axis in the vertical direction, an oblique member connecting them in an oblique direction, and the two chord members Having a plurality of anchors fixed to each and embedded in the concrete of the precast outer formwork or the precast inner formwork,
The anchor is provided in accordance with the vertical interval of the rebars arranged in the horizontal direction at a predetermined interval in the vertical direction,
The method for constructing a pier according to any one of claims 1 to 3, wherein at the time of manufacturing the formwork unit, the band reinforcing bar is arranged to be supported by the anchor.
前記中間帯鉄筋は、水平方向に所定の間隔で設けるとともに、それぞれの帯鉄筋に対して上下方向に配列して設け、両端部を前記プレキャスト外型枠及びプレキャスト内型枠に埋め込むものとし、
上下方向に配列した前記帯鉄筋の側面に、斜め方向に軸線を有する斜め部材を当接し、複数の前記中間帯鉄筋に対して結合し、
該斜め部材によって前記プレキャスト外型枠とプレキャスト内型枠との相対的な変位を拘束することを特徴とする請求項1から請求項4までのいずれかに記載の橋脚の構築方法。



The intermediate rebars are provided at predetermined intervals in the horizontal direction, and arranged in the vertical direction with respect to the respective rebars, and both ends are embedded in the precast outer mold frame and the precast inner mold frame,
Abutting an oblique member having an axis line in an oblique direction on the side surface of the band reinforcing bar arranged in the vertical direction, coupled to a plurality of the intermediate band reinforcing bar,
The method for constructing a pier according to any one of claims 1 to 4, wherein a relative displacement between the precast outer mold and the precast inner mold is constrained by the oblique member.



JP2011137345A 2011-06-21 2011-06-21 Construction method of pier Active JP5620344B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011137345A JP5620344B2 (en) 2011-06-21 2011-06-21 Construction method of pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011137345A JP5620344B2 (en) 2011-06-21 2011-06-21 Construction method of pier

Publications (2)

Publication Number Publication Date
JP2013002238A JP2013002238A (en) 2013-01-07
JP5620344B2 true JP5620344B2 (en) 2014-11-05

Family

ID=47671096

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011137345A Active JP5620344B2 (en) 2011-06-21 2011-06-21 Construction method of pier

Country Status (1)

Country Link
JP (1) JP5620344B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612038A (en) * 2015-01-22 2015-05-13 宁波大学 Flange-connecting concrete-filled double-wall steel pipe prefabricated assembly piers with additional dampers

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643638B (en) * 2013-12-23 2015-09-23 中铁大桥局集团有限公司 The system and method for flexible pier reassembling type lateral locking
DE102016205907A1 (en) * 2016-04-08 2017-10-12 Db Bahnbau Gruppe Gmbh Method and apparatus for producing a bridge construction using precast elements
JP6742932B2 (en) * 2017-02-22 2020-08-19 三井住友建設株式会社 Pier and its construction method
CN107841948B (en) * 2017-11-24 2023-10-31 中交路桥华南工程有限公司 Avoidance adjustment structure and method for main reinforcement
JP6960870B2 (en) * 2018-02-27 2021-11-05 三井住友建設株式会社 How to build a pier
CN109056510A (en) * 2018-09-26 2018-12-21 中铁二院工程集团有限责任公司 The queen post superelevation frame pier of multiple steel member connection
CN113417213A (en) * 2021-06-28 2021-09-21 中交路桥建设有限公司 Integral truss type pull-rod-free turnover formwork system and turnover construction method
CN114197314B (en) * 2021-12-14 2024-05-14 中铁大桥局武汉桥梁特种技术有限公司 Construction method of steel bar close-fitting type thin-wall pier

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3137448B2 (en) * 1992-08-05 2001-02-19 前田建設工業株式会社 Construction method of concrete main tower
JP3322701B2 (en) * 1992-10-08 2002-09-09 ケイコン株式会社 Prefabricated piers and concrete blocks for piers
JP3835716B2 (en) * 1997-07-17 2006-10-18 株式会社フジタ Reinforced concrete pier construction method
JP4136049B2 (en) * 1998-02-23 2008-08-20 前田建設工業株式会社 Concrete pier construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612038A (en) * 2015-01-22 2015-05-13 宁波大学 Flange-connecting concrete-filled double-wall steel pipe prefabricated assembly piers with additional dampers

Also Published As

Publication number Publication date
JP2013002238A (en) 2013-01-07

Similar Documents

Publication Publication Date Title
JP5620344B2 (en) Construction method of pier
US20160340855A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
JP6855296B2 (en) Building foundation structure and its construction method
KR100894650B1 (en) Rahmen bridge with preflexion load and manufacturing method the same
KR101186053B1 (en) Method of Constructing Insitu Concrete Beam Using Preinstalled Precast Concrete Slab
KR101375382B1 (en) Precast formless composite beam and manufacturing method thereof
JP2016205051A (en) Construction method for structure
KR100653283B1 (en) Method for connecting reinforced concrete structures
JP5932455B2 (en) Reinforcement joint structure and pier reinforcement method
KR102197994B1 (en) Construction method using beam-reinforced deck plate
JP5033645B2 (en) How to build a synthetic slab
KR102327700B1 (en) Girder structure and construction method for continuity of supporting portion of girder using the same
JP2016044494A (en) Construction method of foundation
KR101576865B1 (en) Construction method of slab for bridge without support bar using converse T-type beams
KR100860592B1 (en) Temporary system for vertical structure using precast concreat block
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JPH10102423A (en) Pca form and construction method of pier using the same pca form
JP6089096B2 (en) Method for suppressing twist of precast girder and method for joining precast girder
KR101078292B1 (en) Concrete slab mold assembly and method for constructing slab
JPH1136229A (en) Construction method for reinforced concrete bridge pier
KR20140140954A (en) Steel concrete composite girder bridge and construction method thereof
KR101426392B1 (en) Reinforcement member and girder using the same
KR102625479B1 (en) Construction method using precast module with prestressing force
KR200407184Y1 (en) Precasted concrete plate

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140116

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140813

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140916

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140918

R150 Certificate of patent or registration of utility model

Ref document number: 5620344

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250