JP6089096B2 - Method for suppressing twist of precast girder and method for joining precast girder - Google Patents

Method for suppressing twist of precast girder and method for joining precast girder Download PDF

Info

Publication number
JP6089096B2
JP6089096B2 JP2015251356A JP2015251356A JP6089096B2 JP 6089096 B2 JP6089096 B2 JP 6089096B2 JP 2015251356 A JP2015251356 A JP 2015251356A JP 2015251356 A JP2015251356 A JP 2015251356A JP 6089096 B2 JP6089096 B2 JP 6089096B2
Authority
JP
Japan
Prior art keywords
precast
girder
precast girder
floor slab
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2015251356A
Other languages
Japanese (ja)
Other versions
JP2016040447A (en
Inventor
春日 昭夫
昭夫 春日
喜彦 平
喜彦 平
飯島 基裕
基裕 飯島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2015251356A priority Critical patent/JP6089096B2/en
Publication of JP2016040447A publication Critical patent/JP2016040447A/en
Application granted granted Critical
Publication of JP6089096B2 publication Critical patent/JP6089096B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、コンクリートで形成され、断面形状が箱形となった橋桁を構築する工程でプレキャスト桁のねじれを抑制する方法及びプレキャスト桁を接合する方法に関するものである。   The present invention relates to a method for suppressing twisting of a precast girder and a method for joining precast girders in a step of constructing a bridge girder formed of concrete and having a box-shaped cross section.

コンクリートの箱桁橋を構築する方法としては、所定の間隔で形成された橋台又は橋脚間に地上から支保工を組み立て、この支保工に支持させて型枠の形成、鉄筋の組立て及びコンクリートの打設を行う、いわゆる全支保工施工方法が広く採用されている。
上記全支保工施工方法では、橋の構築現場で行う作業の量が多く、工期が長くなるという問題があり、コンクリートの橋桁の一部にプレキャストコンクリートからなるプレキャストセグメント又はプレキャスト桁を用いる方法が提案されている。
As a method of constructing a concrete box girder bridge, a support work is assembled from the ground between abutments or piers formed at a predetermined interval, and supported by this support work, forming a formwork, assembling reinforcing bars, and placing concrete. A so-called all-supporting construction method is widely used.
In the above all support construction methods, there is a problem that the amount of work to be done at the construction site of the bridge is large and the construction period is long, and a method using a precast segment made of precast concrete or a precast girder as a part of the concrete bridge girder is proposed Has been.

例えば、特許文献1に記載されている方法は、製作ヤード等でプレキャストコンクリートからなるプレキャスト桁を予め製作しておき、これらのプレキャスト桁を橋脚間で吊り上げて架設するものである。この方法で用いるプレキャスト桁は、下床版となる部分と2つのウェブとなる部分から構成されて断面形状がほぼU字状となっている。そして、橋脚上部分の橋桁を最初に形成しておき、上記プレキャスト桁(上床版が形成されていない桁)を橋脚間で吊り上げて橋脚上部分の橋桁と接合し、橋軸方向に緊張力を導入する。一径間毎にこのような架設を順次繰り返してすべての径間にプレキャスト桁を架設するとともに、このプレキャスト桁上に上床版を構築するものとなっている。   For example, in the method described in Patent Document 1, precast girders made of precast concrete are produced in advance in a production yard or the like, and these precast girders are suspended between bridge piers and installed. The precast girder used in this method is composed of a lower floor slab part and two web part parts, and has a substantially U-shaped cross section. First, the bridge girder on the upper part of the pier is formed first, and the precast girder (girder without the upper floor slab) is lifted between the piers and joined with the bridge girder on the upper part of the pier, and tension is applied in the direction of the bridge axis Introduce. Such a construction is sequentially repeated for each span to construct a precast girder between all the spans, and an upper floor slab is constructed on the precast girder.

特開2009−68249号公報JP 2009-68249 A

上記特許文献1に記載されているように、U字状となったプレキャスト桁を径間毎に順次吊り上げて架設する方法では、プレキャスト桁上に現場で上床版を形成しなければならず、型枠の形成、配筋、コンクリートの打設、脱型等を現場で行う必要がある。これに対し、プレキャスト桁として上床版も一体に形成されているものを吊り上げようとすると、重量が著しく大きくなり、吊り上げるためのガーダや吊り上げるための揚重装置等が大型化して効率が悪くなってしまう。   As described in the above-mentioned Patent Document 1, in the method in which the U-shaped precast girders are sequentially lifted and installed for each span, an upper floor slab must be formed on the precast girders, It is necessary to perform frame formation, reinforcement, concrete placement, demolding, etc. on site. On the other hand, if the upper floor slab is integrally formed as a precast girder, the weight increases significantly, and the girder for lifting, the lifting device for lifting, etc. become larger and the efficiency becomes worse. End up.

本発明は、このような事情に鑑みてなされたものであり、その目的は、橋の構築現場における作業量を低減し、施工期間を短縮するとともに、橋桁を分割した形状のプレキャスト桁のねじれが抑制された状態で接合することを可能とするものである。 The present invention has been made in view of such circumstances, the purpose of which is to reduce the amount of work at the construction site of the bridge, shorten the construction period, and torsion of the precast girder of the shape obtained by dividing the bridge girder. It is possible to join in a suppressed state .

上記課題を解決するために、請求項1に係る発明は、 断面の一部が箱形となった橋桁の断面を分割した形状にプレキャストコンクリートで形成されたプレキャスト桁を両端部で支持したときのねじれ抑制方法であって、 前記プレキャスト桁は、一つのウェブと、該ウェブの上部から両側方に張り出した上床版と、該ウェブの下部から片側方へ張り出した下床版とを有するものとし、 該プレキャスト桁の、前記上床版と前記下床版との双方が張り出した側縁付近に、該プレキャスト桁の軸線方向に緊張材を配置し、 該緊張材は、前記プレキャスト桁を両端で支持して吊り上げる前に緊張力を導入して、該プレキャスト桁の両端付近で該プレキャスト桁の上縁付近に定着するとともに、該プレキャスト桁の軸線方向における中央付近では、該プレキャスト桁の下縁付近で該緊張材の軸線が曲折し、該緊張材に導入された緊張力によって上向きの力が該プレキャスト桁に作用するように配置するプレキャスト桁のねじれ抑制方法を提供する。   In order to solve the above-mentioned problem, the invention according to claim 1 is provided when a precast girder formed of precast concrete is supported at both ends in a shape obtained by dividing a cross-section of a bridge girder having a box-shaped cross section. A method for suppressing twisting, wherein the precast girder has one web, an upper floor slab protruding from the upper part of the web to both sides, and a lower floor slab protruding from the lower part of the web to one side, A tension material is arranged in the axial direction of the precast girder near the side edge of the precast girder where both the upper floor slab and the lower floor slab project, and the tension material supports the precast girder at both ends. Introducing tension before lifting and fixing near the upper edge of the precast girder near both ends of the precast girder, and near the center in the axial direction of the precast girder, Near the lower edge of the precast girder bent axis of the tendons, upward force by tension introduced into the tension member to provide a precast girder method twist suppression arranged to act on the precast girder.

請求項2に係る発明は、 断面の一部が箱形となった橋桁の断面を分割した形状にプレキャストコンクリートで形成された第1のプレキャスト桁と第2のプレキャスト桁とを両端部で支持した状態で接合するプレキャスト桁の接合方法であって、 前記第1のプレキャスト桁は、一つのウェブと、該ウェブの上部から両側方に張り出した上床版と、該ウェブの下部から片側方へ張り出した下床版とを有するものとし、 前記第2のプレキャスト桁は、一つのウェブと、該ウェブの上部から前記第1のプレキャスト桁から張り出した上床版と対向するように張り出した上床版と、下部から前記第1のプレキャスト桁から張り出した下床版と対向するように張り出した下床版とを有するものとし、 前記第1のプレキャスト桁と前記第2のプレキャスト桁とを軸線方向の両端部を支持して吊り上げ、所定の位置に支持する工程と、 前記第1のプレキャスト桁と前記第2のプレキャスト桁との双方から張り出した上床版の間及び双方から張り出した下床版の間にコンクリートを打設して前記第1のプレキャスト桁と前記第2のプレキャスト桁とを一体に接合する工程と、を含み、 該第1のプレキャスト桁の、前記コンクリートの打設によって前記第2のプレキャスト桁と接合される側縁付近に、該第1のプレキャスト桁の軸線方向に緊張材を配置し、 該緊張材は、前記第1のプレキャスト桁を両端部を支持して吊り上げる前に緊張力を導入して、前記第1のプレキャスト桁の両端付近で該第1のプレキャスト桁の上縁付近に定着するとともに、該第1のプレキャスト桁の軸線方向における中央付近では、該第1のプレキャスト桁の下縁付近で該緊張材の軸線が曲折し、該緊張材に導入された緊張力によって上向きの力が該第1のプレキャスト桁に作用するように配置するプレキャスト桁の接合方法を提供するものである。   In the invention according to claim 2, the first precast girder and the second precast girder, which are formed of precast concrete in a shape obtained by dividing the cross section of the bridge girder having a box-shaped part, are supported at both ends. A precast girder joining method for joining in a state, wherein the first precast girder is one web, an upper floor slab projecting from the upper part of the web to both sides, and projecting from the lower part of the web to one side. The second precast girder has one web, an upper floor slab protruding from the upper part of the web so as to face the upper floor slab, and a lower part. A lower floor slab projecting from the first precast girder and a lower floor slab projecting so as to face the first precast girder, and the first precast girder and the second precast girder A step of supporting the girder by supporting both ends in the axial direction, and supporting the girder in a predetermined position, and between and between the upper floor slabs protruding from both the first precast girder and the second precast girder Placing concrete between the overhanging lower floor slabs and integrally joining the first precast girder and the second precast girder, the first precast girder of the concrete A tension material is arranged in the axial direction of the first precast girder in the vicinity of a side edge to be joined to the second precast girder by placing, and the tension material supports the first precast girder at both ends. Then, tension is introduced before lifting and fixing near the upper edge of the first precast girder near both ends of the first precast girder, and in the axial direction of the first precast girder Near the center, the axis of the tendon is bent near the lower edge of the first precast girder, and an upward force is applied to the first precast girder by the tension introduced into the tendon. A precast girder joining method is provided.

断面形状が箱形となった橋桁をウェブ間のほぼ中央で分割した形状のプレキャスト桁を吊り上げて橋脚間に架け渡すので、吊り上げるプレキャスト桁の重量は、完成したときの橋桁の重量の1/2以下とすることができる。したがって、吊り揚げるための機構、例えばガーダや巻き上げ機等を小型化することが可能となる。また、プレキャスト桁は、上床版部分と下床版部分とを接合することにより箱桁とすることができ、橋の構築現場で組み立てる型枠の量、配置する鉄筋の量及びコンクリートの打設量が低減される。したがって、橋の構築現場で行う作業量が低減され、施工期間の短縮を実現することができる。   A precast girder with a box-shaped cross-section is split at approximately the center between the webs. The precast girder is suspended between the piers, so the weight of the precast girder is half the weight of the completed bridge girder. It can be as follows. Therefore, it is possible to reduce the size of a mechanism for lifting such as a girder or a hoisting machine. Precast girders can be made into box girders by joining the upper and lower floor slab parts, the amount of formwork assembled at the construction site of the bridge, the amount of reinforcing bars to be placed, and the amount of concrete cast Is reduced. Therefore, the amount of work performed at the construction site of the bridge is reduced, and the construction period can be shortened.

上記プレキャスト桁は、箱形部のウェブ間のほぼ中央で橋桁の軸線に沿って分割されたものであり、分割されたプレキャスト桁の断面形状が非対称であるとともに箱形部を構成する部分が側方に開放された形状となっている。このような断面形状を有したプレキャスト桁では断面の重心位置とせん断中心の位置とが異なっている。このため、両端部で吊り支持すると、自重が作用することによって支持している位置間でねじり変形が生じる。これに対し、軸線方向の中央付近で上向きの反力成分が作用するように緊張材を配置し、自重によるねじる変形とは逆方向のねじり変形を生じさせている。これにより、吊り上げたときのねじれに起因した変形が低減され、架け渡された2つのプレキャスト桁をねじれが抑制された状態で互いに接合することができる。 The precast girder is divided along the axis of the bridge girder at approximately the center between the webs of the box-shaped portion, and the cross-sectional shape of the divided precast girder is asymmetric and the portion constituting the box-shaped portion is the side. The shape is open to the direction. In the precast girder having such a cross-sectional shape, the position of the center of gravity of the cross-section and the position of the shear center are different. For this reason, if it is supported by suspension at both ends, torsional deformation occurs between the positions supported by its own weight. On the other hand, a tension material is arranged so that an upward reaction force component acts near the center in the axial direction, and a torsional deformation in the direction opposite to the torsional deformation due to its own weight is generated. Thereby, the deformation | transformation resulting from the twist when it lifts is reduced, and the two precast girders spanned can be joined to each other in a state where the twist is suppressed.

以上説明したように、本発明のプレキャスト桁のねじれ抑制方法及びプレキャスト桁の接合方法では、箱桁を軸線方向に分割して一度に吊り上げる重量を低減すること、及び橋の構築現場における作業量を低減して施工期間を短縮して橋桁を構築することが可能になるとともに、橋桁を分割した形状のプレキャスト桁のねじれが抑制された状態で接合することが可能となる。 As described above, in the precast girder twist suppressing method and the precast girder joining method of the present invention, the weight of the box girder divided in the axial direction and suspended at one time is reduced, and the work amount at the construction site of the bridge is reduced. As a result, the construction period can be shortened and the bridge girder can be constructed, and the precast girder having a shape obtained by dividing the bridge girder can be joined in a state where twisting is suppressed .

本発明に係る方法を適用して構築することができる箱桁橋の一例を示す概略断面図及び概略側面図である。It is the schematic sectional drawing and schematic side view which show an example of the box girder bridge which can be constructed | assembled by applying the method which concerns on this invention. 図1に示す箱桁橋を構成するプレキャスト桁を配置する位置及び形状を示す概略側面図及び断面図である。It is the schematic side view and sectional drawing which show the position and shape which arrange | position the precast girder which comprises the box girder bridge shown in FIG. 図2に示すプレキャスト桁の概略斜視図である。It is a schematic perspective view of the precast girder shown in FIG. 図2及び図3に示すプレキャスト桁に配置する緊張材を示す概略側面図、端面図及び断面図である。FIG. 4 is a schematic side view, an end view, and a cross-sectional view showing a tendon disposed in the precast girder shown in FIGS. 2 and 3. 図2、図3及び図4に示すプレキャスト桁を両端部で支持したときの変形状態を示す概略断面図である。It is a schematic sectional drawing which shows a deformation | transformation state when the precast girder shown in FIG.2, FIG3 and FIG.4 is supported by both ends. 図2、図3及び図4に示すプレキャスト桁の断面の主軸を示す概略断面図である。It is a schematic sectional drawing which shows the principal axis of the cross section of the precast girder shown in FIG.2, FIG3 and FIG.4. 図1に示す箱桁橋を構築する工程を説明する断面図及び側面図である。It is sectional drawing and a side view explaining the process of constructing the box girder bridge shown in FIG. 図1に示す箱桁橋を構築する工程を説明する断面図及び側面図である。It is sectional drawing and a side view explaining the process of constructing the box girder bridge shown in FIG. 図1に示す箱桁橋を構築する工程を説明する断面図及び側面図である。It is sectional drawing and a side view explaining the process of constructing the box girder bridge shown in FIG. 本発明の特徴を利用して構築することができる箱桁橋の概略断面図及びこの箱桁橋を構築するために形成するプレキャスト桁の断面図である。1 is a schematic cross-sectional view of a box girder bridge that can be constructed using the features of the present invention and a cross-sectional view of a precast girder that is formed to construct the box girder bridge.

以下、本発明の実施の形態を図に基づいて説明する。
図1は、本発明に係る方法を適用して構築することができる箱桁橋の一例を示す概略断面図及び概略側面図である。また、図2は、図1に示す箱桁橋を構築するために用いられるプレキャスト桁の配置を示す側面図及び断面図であり、図3はプレキャスト桁の概略斜視図である。
この箱桁橋1は、所定の間隔で構築された橋脚2又は橋台(図示せず)に支持された多径間の連続桁を有する橋梁であり、橋桁3はプレキャストコンクリートにより形成された箱桁となっている。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 is a schematic sectional view and a schematic side view showing an example of a box girder bridge that can be constructed by applying the method according to the present invention. 2 is a side view and a cross-sectional view showing the arrangement of precast girders used for constructing the box girder bridge shown in FIG. 1, and FIG. 3 is a schematic perspective view of the precast girders.
The box girder bridge 1 is a bridge having multi-girder continuous girders supported by piers 2 or abutments (not shown) constructed at predetermined intervals, and the bridge girder 3 is a box girder formed of precast concrete. It has become.

上記橋桁3は、図2(b)に示すように、中空となった箱形部4を有し、この箱形部4の上部を構成するとともに該箱形部の両側方への張り出し部5aを有する上床版5と、前記箱形部の下部を構成する下床版7と、該下床版7と前記上床版5とを連結する2つのウェブ6と、で主要部が構成されている。そして、図2(a)に示すように、この橋桁3は橋脚上部分31と2つの橋脚間に架け渡されて両端が上記橋脚上部分31に接続される径間部32とに分けて形成されるものである。径間部32は、上記箱形部4の幅方向のほぼ中央で左右に分割された右側のプレキャスト桁11及び左側のプレキャスト桁12が予め形成され、これらを吊り上げて橋脚2上に支持されている橋脚上部分31と接合して形成されたものとなっている。   As shown in FIG. 2 (b), the bridge girder 3 has a hollow box-shaped portion 4, which constitutes an upper portion of the box-shaped portion 4 and extends over both sides of the box-shaped portion 5a. The main part is comprised by the upper floor slab 5 which has this, the lower floor slab 7 which comprises the lower part of the said box-shaped part, and the two webs 6 which connect this lower floor slab 7 and the said upper floor slab 5 . As shown in FIG. 2 (a), the bridge girder 3 is divided into a bridge pier upper part 31 and a span part 32 spanned between the two piers and connected at both ends to the bridge pier upper part 31. It is what is done. The span portion 32 is formed in advance with a right precast girder 11 and a left precast girder 12 which are divided into left and right at substantially the center in the width direction of the box-shaped portion 4, and these are lifted and supported on the pier 2. It is formed by being joined to the upper pier upper portion 31.

次に、本発明の一実施形態であって、上記のような箱桁橋を構築するにあたって適用することができるプレキャスト桁のねじれ抑制方法及びプレキャスト桁の接合方法について説明する。
まず、箱桁橋を構築する現場において所定の位置に橋脚2を構築する。これとともに構築現場に近い位置にプレキャスト桁の製作ヤードを設けて、2つのプレキャスト桁11,12を形成する。
Next, a precast girder twist suppressing method and a precast girder joining method, which are one embodiment of the present invention and can be applied to construct the above box girder bridge, will be described.
First, the pier 2 is constructed at a predetermined position on the site where the box girder bridge is constructed. At the same time, a precast girder production yard is provided near the construction site to form two precast girders 11 and 12.

径間部32を構成する2つのプレキャスト桁11,12は、図2(b)、図3及び図4に示すように、断面が箱形となった部分を有する橋桁のほぼ右半分及びほぼ左半分を構成するものである。そして、それぞれは一つのウェブ6を備え、その上部から上床版の張り出し部5aと箱形部を構成する部分5bとが両側に張り出したものとなる。また、ウェブ6の下端部からは、互いに接合される他方のプレキャスト桁側に向かって分割された下床版7aが張り出している。したがって、それぞれのプレキャスト桁11,12の断面は、ウェブ6の上部からは両側に上床版5が張り出し、下端部からは片側に下床版7aが張り出して非対称な形状となる。   The two precast girders 11 and 12 constituting the span portion 32 are, as shown in FIGS. 2 (b), 3 and 4, substantially right half and almost left of a bridge girder having a box-shaped section. It constitutes half. And each is provided with the one web 6, and the overhanging part 5a of the upper floor slab and the part 5b which comprises a box-shaped part overhang on both sides from the upper part. Further, a lower floor slab 7a divided from the lower end portion of the web 6 is projected toward the other precast girder side to be joined. Therefore, the cross sections of the respective precast girders 11 and 12 have an asymmetric shape with the upper floor slab 5 projecting on both sides from the top of the web 6 and the lower floor slab 7a projecting on one side from the lower end.

2つのプレキャスト桁11,12は、2つの隣り合う橋脚2上に支持された橋脚上部分31間に支持し、これらの橋脚上部分31の橋桁と接続することができる長さに形成する。つまり一径間の長さから橋脚上部分の長さとこれらの接合部10の長さを差し引いた長さとする。そして、これらのプレキャスト桁11,12の軸線方向における両端部付近と中央部とには、これらのプレキャスト桁11,12の断面が変形するのを抑制するための横桁13a,13b,13cを設ける。つまり、これらのプレキャスト桁11,12の軸線とは直角方向の壁体を、箱形部を構成する上床版5aと下床版7aとウェブ6とに連続するように形成する。また、これらの横桁13a,13b,13cは、二つのプレキャスト桁11,12が相互間の接合部9にコンクリートを打設することによって接合されたときには、これらの横桁13もそれぞれ接合され、箱形部4で連続する1つの横桁が形成されるようになっている。   The two precast girders 11 and 12 are formed between the upper pier support portions 31 supported on the two adjacent piers 2 so as to be connected to the bridge piers of the upper pier portions 31. That is, it is set as the length which deducted the length of the pier upper part and the length of these junction parts 10 from the length between one diameter. Further, lateral girders 13a, 13b, and 13c are provided in the vicinity of the both ends in the axial direction of these precast girders 11 and 12 and in the central portion for suppressing deformation of the cross section of these precast girders 11 and 12. . That is, a wall body perpendicular to the axes of the precast girders 11 and 12 is formed so as to be continuous with the upper floor slab 5a, the lower floor slab 7a and the web 6 constituting the box-shaped portion. These cross beams 13a, 13b, 13c are also joined when the two precast beams 11, 12 are joined by placing concrete in the joint 9 between them, One continuous girder is formed in the box-shaped portion 4.

上記プレキャスト桁11,12は、製作ヤードにおいて通常のコンクリート部材と同様にして形成することができる。つまり、型枠を形成して、この型枠内に鉄筋を組み立てる。また、必要な緊張材又は緊張材を挿通するためシース等を配置する。そして、コンクリートを打設し、コンクリートの硬化後に脱型する。   The precast girders 11 and 12 can be formed in the production yard in the same manner as a normal concrete member. That is, a formwork is formed, and a reinforcing bar is assembled in this formwork. In addition, a sheath or the like is disposed to insert the necessary tendon or the tendon. Then, concrete is cast and demolded after the concrete is hardened.

上記プレキャスト桁11,12には、緊張材を次のように配置する。
図4(a)はプレキャスト桁11,12の互いに接合される側からの側面図、図4(b)はプレキャスト桁の端面図、図4(c)はプレキャスト桁の軸線方向の中央部付近の断面図である。
これらの図に示すように、プレキャスト桁11,12には、箱形部4の内側となる領域で、互いに接合される側縁付近に緊張材14を張架する。この緊張材14は、コンクリート部材外に張架し、緊張力を導入した状態で端部付近の横桁13a,13cの上部に定着する。そして、中央部の横桁13bの下部に設けた貫通孔に挿通し、緊張力が導入された緊張材14をこの横桁部分で曲折させる。これにより、緊張力が導入された緊張材14が曲げ上げられることによる上方への力を横桁13bに作用させるものとする。
In the precast girders 11 and 12, a tension material is arranged as follows.
4A is a side view from the side where the precast girders 11 and 12 are joined to each other, FIG. 4B is an end view of the precast girder, and FIG. 4C is a view in the vicinity of the central portion in the axial direction of the precast girders. It is sectional drawing.
As shown in these drawings, a tension member 14 is stretched around the side edges of the precast girders 11 and 12 that are joined to each other in the region inside the box-shaped portion 4. The tension member 14 is stretched outside the concrete member, and is fixed on the upper portions of the cross beams 13a and 13c near the ends in a state where the tension force is introduced. And it inserts in the through-hole provided in the lower part of the cross beam 13b of a center part, and makes the tension | tensile_strength material 14 into which tension | tensile_strength was introduced bend in this cross beam part. Thereby, the upward force by bending the tension material 14 introduced with the tension force is applied to the cross beam 13b.

一方、上床版の張り出し部5aの先端部、及びウェブ6と下床版7との連結部のコンクリート中には、プレキャスト桁11,12の軸線方向にシースを埋め込み、この中に緊張材15,16を挿通して緊張力を導入する。これにより、上床版の張り出し部5aの先端部、及びウェブ6と下床版7との連結部にプレストレスを導入する。   On the other hand, a sheath is embedded in the axial direction of the precast girders 11 and 12 in the concrete of the tip portion of the overhanging portion 5a of the upper floor slab and the connecting portion between the web 6 and the lower floor slab 7, and the tension members 15 and 16 is inserted and tension is introduced. As a result, prestress is introduced into the tip portion of the overhanging portion 5 a of the upper floor slab and the connecting portion between the web 6 and the lower floor slab 7.

図5は、プレキャスト桁11を他方のプレキャスト桁12と接合する側縁11a付近に上記緊張材14を配置し、緊張力を導入することによる効果を説明する概略図であり、図5(a)は、上記プレキャスト桁を両端部で支持したときの自重による中央部のたわみを、端部の位置と中央部断面の位置とを対比して示すものである。また、図5(b)は上記緊張材に緊張力を導入することによる中央部のたわみを示す図であり、図5(c)は図5(a)に示すプレキャスト桁の自重が作用したときのたわみと、図5(b)に示す緊張材の緊張力が作用したときのたわみと、の双方が作用した状態を示す図である。
これらの図において、プレキャスト桁11の中央部断面の位置を実線で示し、端部の位置を仮想線で示している。
FIG. 5 is a schematic diagram for explaining the effect of arranging the tension material 14 in the vicinity of the side edge 11a that joins the precast girder 11 to the other precast girder 12 and introducing a tension force. Shows the deflection of the central part due to its own weight when the precast girder is supported at both ends, comparing the position of the end part and the position of the cross section of the central part. FIG. 5 (b) is a diagram showing the deflection of the central part by introducing a tension force to the tension material, and FIG. 5 (c) is when the weight of the precast girder shown in FIG. 5 (a) is applied. It is a figure which shows the state which both the bending | flexion and the bending | flexion when the tension | tensile_strength of the tendon shown in FIG.5 (b) acted were acted.
In these drawings, the position of the cross section of the central portion of the precast beam 11 is indicated by a solid line, and the position of the end portion is indicated by an imaginary line.

プレキャスト桁11の断面形状は、左右非対称であるとともに一方の側面では上床版5bと下床版7aとが突き出しているがこれらの間が開放された、いわゆる開断面となっている。このため、上記プレキャスト桁11は、図5(a)に示すように、重心位置とせん断中心の位置とが水平方向にずれており、プレキャスト桁11の軸線方向に分布する自重が作用すると、他のプレキャスト桁12と接合する側縁11aが他方の側縁11bより大きく下方にたわむようにねじり変形が生じる。一方、緊張材14の緊張力によってプレキャスト桁11の中央部付近に上方の力が作用すると、図5(b)に示すように、互いに接合する側縁11aが他方の側縁11bより大きく上方へ持ち上げられるようにねじり変形が生じる。そして、両端でプレキャスト桁11を吊り支持したときにはこれらの双方が作用し、中央部のたわみは図5(c)に示すように、2つのプレキャスト桁11,12を互いに接合する側縁11aと上床版の張り出し部5aの先端となる側縁11bとで、下方へのたわみ量に大きな差が生じない。このような状態で並列した2つのプレキャスト桁11,12を接合することが可能となる。   The cross-sectional shape of the precast girder 11 is a so-called open cross-section in which the upper floor slab 5b and the lower floor slab 7a protrude from one side surface but are opened between them. For this reason, as shown in FIG. 5A, the precast girder 11 is shifted in the horizontal direction from the position of the center of gravity and the position of the shear center, and when the self-weight distributed in the axial direction of the precast girder 11 acts, The torsional deformation occurs so that the side edge 11a joined to the precast girder 12 bends downward more largely than the other side edge 11b. On the other hand, when an upward force acts near the center of the precast girder 11 due to the tension of the tension member 14, as shown in FIG. 5 (b), the side edges 11a joined to each other are larger than the other side edge 11b. Torsional deformation occurs so that it can be lifted. When the precast girder 11 is suspended and supported at both ends, both of these act, and the deflection at the center is as shown in FIG. 5 (c), with the side edge 11a and the upper floor joining the two precast girders 11 and 12 together. There is no significant difference in the amount of downward deflection between the side edge 11b at the tip of the plate overhanging portion 5a. In this state, the two precast girders 11 and 12 arranged in parallel can be joined.

一方、図6に示すようにプレキャスト桁11の断面が左右非対称となっていることにより、断面の主軸が水平方向又は鉛直方向に対して傾斜する。つまり、このプレキャスト桁11の曲げ剛性が最も小さくなる方向(図6中に示すX軸回りに曲げモーメントが作用する方向)と曲げ剛性がもっとも大きくなる方向(Y軸回りに曲げモーメントが作用する方向)とが傾斜することになる。これにより、プレキャスト桁11を両端で吊り支持すると中央部は、最も曲げ変形が生じやすい方向つまり曲げ剛性が小さい方向に大きな曲げ変形が生じ、上床版の張り出し部5aの先端付近、及びウェブ6と下床版7との連結部付近に引張応力度が生じ易くなる。これに対して、予めこれらの部分にプレストレスを導入しておくことにより、プレキャスト桁11のたわみを抑制するとともに、プレキャスト桁11のコンクリートに引張力が発生するのが抑制される。   On the other hand, as shown in FIG. 6, the cross section of the precast girder 11 is asymmetrical, so that the main axis of the cross section is inclined with respect to the horizontal direction or the vertical direction. That is, the direction in which the bending rigidity of the precast girder 11 becomes the smallest (the direction in which the bending moment acts around the X axis shown in FIG. 6) and the direction in which the bending rigidity becomes the largest (the direction in which the bending moment acts around the Y axis). ) And will be inclined. Thus, when the precast girder 11 is suspended and supported at both ends, the central portion is greatly bent in the direction in which bending deformation is most likely to occur, that is, in the direction in which bending rigidity is small. Tensile stress is likely to occur in the vicinity of the connecting portion with the lower floor slab 7. On the other hand, by prestressing these portions in advance, the deflection of the precast girder 11 is suppressed, and the generation of tensile force in the concrete of the precast girder 11 is suppressed.

次に、上記プレキャスト桁11,12を用いて橋脚2上に橋桁3を架設する方法について説明する。
まず、図7(a)に示すように、基礎地盤から立ち上げられた橋脚2の上部に、橋桁の橋脚上部分31を形成する。この橋脚上部分31は、上記2つのプレキャスト桁11,12とともに製作ヤード等であらかじめ製作したものを吊り上げ、橋脚2上に設置するものであっても良いし、橋脚2上に支保工を組み立て、型枠の設置、鉄筋の配置を行って、橋脚上でコンクリートを打設するものであっても良い。
橋桁の橋脚上部分31は断面の全部を一体として形成し、支承が設けられる位置には支点上横桁を有するものとする。そして、この橋脚上部分31の軸線方向における端面に2つのプレキャスト桁11,12を接続する。
Next, a method for installing the bridge girder 3 on the pier 2 using the precast girders 11 and 12 will be described.
First, as shown to Fig.7 (a), the pier upper part 31 of a bridge girder is formed in the upper part of the pier 2 raised from the foundation ground. The upper part 31 of the pier may be one that is pre-manufactured in a production yard or the like together with the two precast girders 11 and 12, and may be installed on the pier 2 or a support work is assembled on the pier 2; It is also possible to place concrete on the pier by installing the formwork and arranging the reinforcing bars.
The pier upper part 31 of the bridge girder is formed integrally with the entire cross section, and has a horizontal girder on the fulcrum at a position where the support is provided. Then, two precast girders 11 and 12 are connected to the end face in the axial direction of the pier upper portion 31.

上記橋脚上部分31は、橋脚2に支承18を介して支持され、橋桁3が完成したときには橋桁3の軸線と直角となる水平方向の軸線回りに回転変位を許容するか、又はこの回転変位とともに橋桁3の軸線方向の変位を許容するものとなる。しかし、上記プレキャスト桁11,12と一体に接合するまでは、上記橋脚上部分31は橋脚2に対して変位を拘束するように仮固定を行う。仮固定の方法は、例えば橋脚2と橋桁の橋脚上部分31との間にコンクリートブロックを介挿し、鉛直方向に配置した緊張材に緊張力を導入して橋桁の橋脚上部分31を橋脚2に締め付ける方法を採用することができる。   The upper part 31 of the pier is supported by the pier 2 via the support 18 and, when the bridge girder 3 is completed, allows rotational displacement around a horizontal axis perpendicular to the axis of the bridge girder 3, or together with this rotational displacement. The displacement of the bridge girder 3 in the axial direction is allowed. However, until the precast girders 11 and 12 are integrally joined, the pier upper part 31 is temporarily fixed so as to restrain displacement with respect to the pier 2. The temporary fixing method is, for example, by inserting a concrete block between the bridge pier 2 and the bridge pier upper portion 31 and introducing tension to the tension members arranged in the vertical direction so that the bridge pier upper portion 31 is connected to the pier 2. A tightening method can be employed.

次に、橋脚2に支持された上記橋桁の橋脚上部分31の上に支柱21を介して架設用ガーダ22を架け渡す。そして、図7(b)に示すように、予め製作した右側のプレキャスト桁11を上記架設ガーダ22から垂下した吊り材23によって橋脚2間に吊り上げる。このとき吊り材23はプレキャスト桁11の両端部にそれぞれ係止し、架設ガーダ22の両端の支柱21付近で巻き揚げる。   Next, the erection girder 22 is bridged over the pier upper part 31 of the bridge girder supported by the pier 2 through the support column 21. Then, as shown in FIG. 7 (b), the right precast girder 11 produced in advance is lifted between the piers 2 by a suspension member 23 suspended from the erection girder 22. At this time, the suspension members 23 are respectively engaged with both end portions of the precast girder 11 and are wound up in the vicinity of the columns 21 at both ends of the installation girder 22.

このようにして右側のプレキャスト桁11を、2つの橋脚上部分31間の所定の位置に吊り上げ、図8(a)に示すように、橋脚2に固定された橋脚上部分31によって仮支持する。このとき橋脚上部分31との間には、橋桁の構築現場でコンクリートを打設して橋脚上部分31とプレキャスト桁11とを接合するための間隔つまり接合部10となる空間が設けられている。
なお、プレキャスト桁11を橋脚上部分31に仮支持させる方法としては様々な方法を採用することができるが、橋脚上部分の上部にプレキャスト桁11側に張り出して仮固定用の鋼梁24を固定しておき、この鋼梁24を介してプレキャスト桁11を仮支持することができる。
In this way, the right precast girder 11 is lifted to a predetermined position between the two pier upper portions 31 and temporarily supported by the pier upper portion 31 fixed to the pier 2 as shown in FIG. At this time, a space is provided between the upper pier portion 31 and a space for forming the gap, that is, the joint portion 10 for joining the upper pier portion 31 and the precast girder 11 by placing concrete at the construction site of the bridge girder. .
Various methods can be adopted as a method for temporarily supporting the precast girder 11 on the pier upper portion 31. However, the steel beam 24 for temporary fixing is fixed by projecting to the precast girder 11 side above the upper portion of the pier. In addition, the precast girder 11 can be temporarily supported via the steel beam 24.

続いて、図8(b)に示すように架設用ガーダ22を横方向に移動して、もう一方のプレキャスト桁つまり左側のプレキャスト桁12を吊り上げる位置に設置する。そして、右側のプレキャスト桁11と同様にして左側のプレキャスト桁12を吊り上げ、図9(a)に示すように、左側のプレキャスト桁12を橋桁の橋脚上部分31に仮固定する。このとき、左側のプレキャスト桁12の箱形部を形成する上床版5bは右側のプレキャスト桁11が支持された側方に向かって突き出し、同様に右側のプレキャスト桁11から突き出した上床版5bと双方の端面が所定の間隔で対向している。また、下床版7も同様にウェブ6から突き出した部分7aの端面が所定の間隔で互いに対向している。   Subsequently, as shown in FIG. 8B, the erection girder 22 is moved in the lateral direction, and the other precast girder, that is, the left precast girder 12 is installed at a position to be lifted. Then, the left precast girder 12 is lifted in the same manner as the right precast girder 11, and the left precast girder 12 is temporarily fixed to the bridge pier upper portion 31 as shown in FIG. At this time, the upper floor slab 5b forming the box-shaped portion of the left precast girder 12 protrudes toward the side where the right precast girder 11 is supported, and similarly, both the upper floor slab 5b protruding from the right precast girder 11 Are opposed to each other at a predetermined interval. Similarly, the end surface of the portion 7a protruding from the web 6 also faces the lower floor slab 7 at a predetermined interval.

このように支持された2つのプレキャスト桁11,12のそれぞれは、断面形状が左右非対称で突き出した上床版5bと下床版7aとの間が開放されたものとなっている。このため、上記のように両端部で支持した時に、自重によって軸線方向の中央付近にねじり変形が生じるが、緊張材14に導入された緊張力が中央付近で上向きの成分として作用し、ねじり変形を抑制した状態で支持することができる。
また、張り出し部5aの先端部およびウェブ6と下床版7との接合部付近に、プレストレスを導入しており、これらの領域に引張応力度が生じるのが抑制される。
Each of the two precast girders 11 and 12 supported in this way has an open section between the upper floor slab 5b and the lower floor slab 7a protruding in a cross-sectionally asymmetric manner. For this reason, when supported at both ends as described above, torsional deformation occurs near the center in the axial direction due to its own weight, but the tension force introduced into the tension member 14 acts as an upward component near the center, and torsional deformation occurs. It can support in the state which suppressed.
Further, prestress is introduced in the vicinity of the front end portion of the overhang portion 5a and the joint portion between the web 6 and the lower floor slab 7, and the generation of tensile stress in these regions is suppressed.

上記右側のプレキャスト桁11と左側のプレキャスト桁12との間である接合部9、及び2つのプレキャスト桁11,12と橋桁の橋脚上部分31との間である接合部10にはコンクリートを打設し、これらを一体に接合する。
コンクリートの打設に先立ち、右側のプレキャスト桁11と左側のプレキャスト桁12とが備える上床版5bの互いに対向する端面からは、鉄筋が所定の間隔で突き出しており、これらの鉄筋を重ね合わせるか、又はこれらの鉄筋の双方と重ね合わせるように新たな鉄筋を配置する。また、双方から突き出した下床版7aの端面及び両端部付近と軸線方向の中央部付近に設けられた横桁13の対向する端面についても同様に鉄筋を突き出しておき、これらが接続されるように鉄筋を配置する。そして、端面が対向するように突き出した上床版5b及び下床版7aの間には、下側に型枠を設ける。
Concrete is cast in the joint 9 between the right precast girder 11 and the left precast girder 12 and the joint 10 between the two precast girders 11 and 12 and the bridge pier upper part 31. These are joined together.
Prior to placing concrete, reinforcing bars protrude at predetermined intervals from the mutually facing end surfaces of the upper floor slab 5b provided in the right precast girder 11 and the left precast girder 12, or these rebars are overlapped, Alternatively, a new reinforcing bar is arranged so as to overlap with both of these reinforcing bars. In addition, reinforcing bars are similarly protruded from the end surface of the lower floor slab 7a protruding from both sides, the vicinity of both ends, and the opposite end surface of the cross beam 13 provided in the vicinity of the central portion in the axial direction so that they are connected. Place the rebar in And a formwork is provided on the lower side between the upper floor slab 5b and the lower floor slab 7a protruding so that the end faces face each other.

一方、2つのプレキャスト桁11,12の軸線方向の端面と橋脚上部分31の端面とが対向する接続部10の空間には、双方から鉄筋を突き出しておいても良いが、端面を粗く仕上げておくか、せん断キーとして作用する凸部又は凹部を設けておくものでも良い。そして、これらの端面間に鉄筋を配置するともに型枠を設置する。その後、コンクリートを打設して硬化させる。   On the other hand, in the space of the connecting portion 10 where the end face in the axial direction of the two precast girders 11 and 12 and the end face of the pier upper part 31 face each other, reinforcing bars may be protruded from both sides, but the end face is roughened. Alternatively, a convex portion or a concave portion acting as a shear key may be provided. And a rebar is arranged between these end faces, and a formwork is installed. Then, concrete is cast and hardened.

コンクリートが硬化した後、上床版5内で橋桁3の軸線と直角方向に埋め込まれたシース内に緊張材(図示せず)を挿通し、緊張して横方向のプレストレスを導入する。これにより、上床版5が載荷される輪荷重等に抵抗できるものとする。また、橋桁3の軸線方向には、断面が箱形となった内側でコンクリート部材外に緊張材(図示しない)を追加配置し、緊張して橋桁3のコンクリートにプレストレスを導入する。緊張材は、プレキャスト桁11,12と橋脚上部分31との接合部の両側にわたって配置するとともに、橋桁3に大きな負の曲げモーメントが作用する橋脚上部分31及び正の曲げモーメントが作用する橋脚間の中央部付近に充分なプレストレスが導入されるように配置する。このとき、プレキャスト桁11,12の端面と接合部10に打設したコンクリートとの間、及び橋脚上部分31と接合部10に打設したコンクリートとの間では、常に圧縮応力度が作用するものとし、これらの境界面で鉄筋が連続していない場合においても強固に接続することができる。   After the concrete has hardened, a tension material (not shown) is inserted into a sheath embedded in the upper floor slab 5 in a direction perpendicular to the axis of the bridge girder 3 and is tensioned to introduce lateral prestress. Thereby, it shall resist the wheel load etc. with which the upper floor slab 5 is loaded. Further, in the axial direction of the bridge girder 3, a tension material (not shown) is additionally disposed outside the concrete member inside the box-shaped cross section, and the prestress is introduced into the concrete of the bridge girder 3 by tension. The tension members are arranged on both sides of the joint between the precast girders 11 and 12 and the pier upper part 31 and between the pier upper part 31 on which the large negative bending moment acts on the bridge girder 3 and the pier on which the positive bending moment acts. It is arranged so that a sufficient prestress is introduced near the center of the. At this time, the degree of compressive stress always acts between the end faces of the precast girders 11 and 12 and the concrete cast on the joint 10 and between the pier upper part 31 and the concrete cast on the joint 10. In addition, even when the reinforcing bars are not continuous at these boundary surfaces, a strong connection can be achieved.

上記のようにプレキャスト桁11,12と橋脚上部分31とが一体に接合され、橋脚2間に橋桁3が架け渡されると、図9(b)に示すように架設用ガーダ22を次の径間に移動し、既に架け渡した橋桁3と連続するように次の径間の橋桁を同様に構築する。また、既に橋桁3が架け渡された径間については、橋脚上部分31によるプレキャスト桁11,12の仮支持を解放するともに、橋脚上部分31の橋脚2に対する仮固定を解放することができる。
このようにして全ての径間について橋桁3が形成された後、上床版5上に地覆、高欄、舗装等を施して箱桁橋の構築を完成する。
When the precast girders 11 and 12 and the pier upper part 31 are integrally joined as described above, and the bridge girder 3 is bridged between the piers 2, as shown in FIG. The bridge girder between the next spans is constructed in the same way so as to be continuous with the bridge girder 3 that has already been bridged. Further, for the span where the bridge girder 3 has already been bridged, the temporary support of the precast girders 11 and 12 by the upper pier part 31 and the temporary fixing of the upper pier part 31 to the pier 2 can be released.
After the bridge girder 3 has been formed for all spans in this way, the construction of the box girder bridge is completed by applying ground cover, railing, pavement, etc. on the upper floor slab 5.

このように箱形の断面を有する橋桁3を形成することにより、箱形となった断面を左右に分割した形状の2つのプレキャスト桁11,12を、ねじり変形がほとんど生じていない状態で接合して箱形の断面を有する一つの橋桁3とすることができる。つまり、ねじりによるせん断力が作用した状態のまま2つのプレキャスト桁11,12が接合されるのを回避するとともに、2のプレキャスト桁11,12にねじり変形が生じて接合する側縁11a,12a付近が下方に大きくたわんだ状態で2つのプレキャスト桁11,12が接合されるのを回避し、正確な形状に橋桁3を形成することができる。   Thus, by forming the bridge girder 3 having a box-shaped cross section, the two precast girders 11 and 12 having a shape obtained by dividing the box-shaped cross section into left and right are joined in a state in which almost no torsional deformation occurs. One bridge girder 3 having a box-shaped cross section can be obtained. That is, while avoiding the joining of the two precast girders 11 and 12 while the shearing force due to the torsion is applied, the vicinity of the side edges 11a and 12a where the two precast girders 11 and 12 are torsionally deformed and joined. It is possible to prevent the two precast girders 11 and 12 from being joined in a state of being greatly bent downward, and to form the bridge girder 3 in an accurate shape.

なお、本発明は、上記に説明した実施の形態に限定されるものではなく、本発明の範囲内で様々な形態で実施することができる。
例えば、本実施の形態では、横桁13をプレキャスト桁11,12の軸線方向における両端部と中央部の3箇所に設けたがこれらの横桁に加えて他の位置にも設けることができる。
また、上記実施の形態では、プレキャスト桁11,12を橋脚2間で吊り上げるものであったが、橋台と橋脚との間又は橋台と橋台との間においても同様にしてプレキャスト桁を吊り上げることができる。このときには、橋台の上に橋桁の端部を端部ブロックとして先に形成し、橋台に仮固定しておく。そしてこの端部ブロックと橋脚上に仮固定された橋脚上部分との間、又は端部ブロックと端部ブロックとの間でプレキャスト桁を吊り上げることができる。
The present invention is not limited to the embodiment described above, and can be implemented in various forms within the scope of the present invention.
For example, in the present embodiment, the cross beams 13 are provided at the three positions of the both ends and the central portion in the axial direction of the precast beams 11 and 12, but can be provided at other positions in addition to these cross beams.
In the above-described embodiment, the precast girders 11 and 12 are lifted between the piers 2. However, the precast girders can be lifted in the same manner between the abutment and the pier or between the abutment and the abutment. . At this time, the end of the bridge girder is first formed as an end block on the abutment and temporarily fixed to the abutment. And a precast girder can be lifted between this end block and the pier upper part temporarily fixed on the pier, or between an end block and an end block.

橋桁3は、以上に説明した実施の形態において、支承18を介して橋脚2上に支持されるものであったが、橋桁が橋脚と連続したラーメン構造とすることもできる。この場合には、橋桁の橋脚上部分を橋脚と一体に形成しておくことができ、橋脚上部分の仮固定を行う工程及び仮固定の解除を行う工程を省略することができる。
また、上記実施の形態では、橋桁3が1つの箱形部分を有するものであったが、図10(a)に示すように、2つの箱形部分41,42が連続した断面を有する橋桁40も同様にして形成することができる。この橋桁40は、3つのウェブ43,44,45を有するものであり、これらのウェブ43,44,45の上部及び下部がそれぞれ上床版46と下床版47とによって連結されたものである。このような橋桁40を有する箱桁橋を構築するときには、図10(b)に示すように、橋桁40の径間部を軸線方向の分割線でウェブ毎に分割した3つのプレキャスト桁48,49,50を製作する。そして、これらを順次に橋脚51間で吊り上げる。このとき、断面の中央部にあるウェブ44を含むプレキャスト桁49は断面がほぼ左右対称となり、ねじれ変形はほとんど生じない。したがって、その両側の2つのプレキャスト桁48,50について、上記実施の形態と同様に、他のプレキャスト桁と接合される側縁付近に緊張材52を配置し、ねじり変形を抑制して吊り上げ、接合することができる。
The bridge girder 3 is supported on the pier 2 via the support 18 in the embodiment described above, but it may be a ramen structure in which the bridge girder is continuous with the pier. In this case, the upper part of the pier of the bridge girder can be formed integrally with the pier, and the process of temporarily fixing the pier upper part and the process of releasing the temporary fixation can be omitted.
Moreover, in the said embodiment, although the bridge girder 3 has one box-shaped part, as shown to Fig.10 (a), the bridge girder 40 in which the two box-shaped parts 41 and 42 have a continuous cross section. Can be formed in the same manner. The bridge girder 40 has three webs 43, 44, 45, and the upper and lower parts of these webs 43, 44, 45 are connected by an upper floor slab 46 and a lower floor slab 47, respectively. When constructing a box girder bridge having such a bridge girder 40, as shown in FIG. 10 (b), three precast girders 48, 49 in which the span portion of the bridge girder 40 is divided for each web by the dividing line in the axial direction. , 50. These are then sequentially lifted between the piers 51. At this time, the cross section of the precast girder 49 including the web 44 at the center of the cross section is substantially bilaterally symmetric, and almost no torsional deformation occurs. Therefore, the tension members 52 are arranged near the side edges to be joined to the other precast girders on the two precast girders 48 and 50 on both sides in the same manner as in the above-described embodiment, and they are lifted and joined while suppressing torsional deformation. can do.

1:箱桁橋、 2:橋脚、 3:橋桁、 4:箱形部、 5:上床版、 5a:上床版の張り出し部、 5b:上床版の箱形部を構成する部分、 6:ウェブ、 7:下床版、 9:2つのプレキャスト桁の接合部、 10:橋桁の橋脚上部分とプレキャスト桁との接合部、 11:右側のプレキャスト桁、 12:左側のプレキャスト桁、 13:横桁、 14:緊張材、 15,16:コンクリート部材内に配置した緊張材、 18:支承、 21:支柱、 22:架設用ガーダ、 23:吊り材、 24:鋼梁、 31:橋桁の橋脚上部分、 32:橋桁の径間部、 40:橋桁、 41,42:箱形部、 43,44,45:ウェブ、 46:上床版、 47:下床版、 48:左側のプレキャスト桁、 49:中央のプレキャスト桁、 50:右側のプレキャスト桁、 51:橋脚

1: box girder bridge, 2: bridge pier, 3: bridge girder, 4: box-shaped part, 5: upper floor slab, 5a: projecting part of upper floor slab, 5b: part constituting the box-shaped part of upper floor slab, 6: web, 7: Lower floor slab, 9: Joint between two precast girders, 10: Joint between the upper part of the pier and the precast girders, 11: Precast girders on the right side, 12: Precast girders on the left side, 13: Cross girders, 14: Tensile material, 15, 16: Tensile material arranged in concrete member, 18: Support, 21: Post, 22: Construction girder, 23: Suspension material, 24: Steel beam, 31: Upper part of bridge girder, 32: span part of bridge girder, 40: bridge girder, 41, 42: box-shaped part, 43, 44, 45: web, 46: upper floor slab, 47: lower floor slab, 48: left precast girder, 49: center Precast digits, 50: right precast digits, 51: Bridge pier

Claims (2)

断面の一部が箱形となった橋桁の断面を分割した形状にプレキャストコンクリートで形成されたプレキャスト桁を両端部で支持したときのねじれ抑制方法であって、
前記プレキャスト桁は、一つのウェブと、該ウェブの上部から両側方に張り出した上床版と、該ウェブの下部から片側方へ張り出した下床版とを有するものとし、
該プレキャスト桁の、前記上床版と前記下床版との双方が張り出した側縁付近に、該プレキャスト桁の軸線方向に緊張材を配置し、
該緊張材は、前記プレキャスト桁を両端で支持して吊り上げる前に緊張力を導入して、該プレキャスト桁の両端付近で該プレキャスト桁の上縁付近に定着するとともに、該プレキャスト桁の軸線方向における中央付近では、該プレキャスト桁の下縁付近で該緊張材の軸線が曲折し、該緊張材に導入された緊張力によって上向きの力が該プレキャスト桁に作用するように配置することを特徴とするプレキャスト桁のねじれ抑制方法
A method for suppressing torsion when supporting a precast girder formed of precast concrete into a shape obtained by dividing a cross section of a bridge girder in which a part of the cross section is a box shape,
The precast girder has one web, an upper floor slab protruding from the upper part of the web to both sides, and a lower floor slab protruding from the lower part of the web to one side,
A tension material is arranged in the axial direction of the precast girder near the side edge of the precast girder where both the upper floor slab and the lower floor slab project.
The tension material introduces a tension force before supporting and lifting the precast girder at both ends, and is fixed near the upper edge of the precast girder near both ends of the precast girder, and in the axial direction of the precast girder Near the center, the axis of the tendon is bent near the lower edge of the precast girder, and an upward force is applied to the precast girder by the tension introduced into the tendon. Precast girder twist control method
断面の一部が箱形となった橋桁の断面を分割した形状にプレキャストコンクリートで形成された第1のプレキャスト桁と第2のプレキャスト桁とを両端部で支持した状態で接合するプレキャスト桁の接合方法であって、
前記第1のプレキャスト桁は、一つのウェブと、該ウェブの上部から両側方に張り出した上床版と、該ウェブの下部から片側方へ張り出した下床版とを有するものとし、
前記第2のプレキャスト桁は、一つのウェブと、該ウェブの上部から前記第1のプレキャスト桁から張り出した上床版と対向するように張り出した上床版と、下部から前記第1のプレキャスト桁から張り出した下床版と対向するように張り出した下床版とを有するものとし、
前記第1のプレキャスト桁と前記第2のプレキャスト桁とを軸線方向の両端部を支持して吊り上げ、所定の位置に支持する工程と、
前記第1のプレキャスト桁と前記第2のプレキャスト桁との双方から張り出した上床版の間及び双方から張り出した下床版の間にコンクリートを打設して前記第1のプレキャスト桁と前記第2のプレキャスト桁とを一体に接合する工程と、を含み、
該第1のプレキャスト桁の、前記コンクリートの打設によって前記第2のプレキャスト桁と接合される側縁付近に、該第1のプレキャスト桁の軸線方向に緊張材を配置し、
該緊張材は、前記第1のプレキャスト桁を両端部を支持して吊り上げる前に緊張力を導入して、前記第1のプレキャスト桁の両端付近で該第1のプレキャスト桁の上縁付近に定着するとともに、該第1のプレキャスト桁の軸線方向における中央付近では、該第1のプレキャスト桁の下縁付近で該緊張材の軸線が曲折し、該緊張材に導入された緊張力によって上向きの力が該第1のプレキャスト桁に作用するように配置することを特徴とするプレキャスト桁の接合方法。
Joining of precast girders in which the first precast girders and the second precast girders made of precast concrete are joined to each other in a shape that divides the cross section of the bridge girder whose section is box-shaped. A method,
The first precast girder has one web, an upper floor slab protruding from the upper part of the web to both sides, and a lower floor slab protruding from the lower part of the web to one side,
The second precast girder has one web, an upper floor slab that projects from the upper part of the web so as to face the upper floor slab that projects from the first precast girder, and a projecting from the first precast girder from the lower part. A lower floor slab protruding so as to face the lower floor slab,
Supporting the first precast girder and the second precast girder by supporting both ends in the axial direction and supporting them at predetermined positions;
Concrete is laid between the upper floor slab projecting from both the first precast girder and the second precast girder and between the lower floor slab projecting from both, and the first precast girder and the second precast girder And a step of integrally joining the precast girder of
A tension material is arranged in the axial direction of the first precast girder in the vicinity of the side edge of the first precast girder joined to the second precast girder by placing the concrete.
The tension material introduces a tension force before lifting the first precast girder while supporting both ends, and is fixed near the upper edge of the first precast girder near both ends of the first precast girder. In addition, in the vicinity of the center in the axial direction of the first precast girder, the axis of the tendon is bent near the lower edge of the first precast girder, and an upward force is applied by the tension force introduced into the tendon. Is arranged so as to act on the first precast girder.
JP2015251356A 2015-12-24 2015-12-24 Method for suppressing twist of precast girder and method for joining precast girder Expired - Fee Related JP6089096B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015251356A JP6089096B2 (en) 2015-12-24 2015-12-24 Method for suppressing twist of precast girder and method for joining precast girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015251356A JP6089096B2 (en) 2015-12-24 2015-12-24 Method for suppressing twist of precast girder and method for joining precast girder

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2012001885A Division JP5945418B2 (en) 2012-01-10 2012-01-10 How to build a box girder bridge

Publications (2)

Publication Number Publication Date
JP2016040447A JP2016040447A (en) 2016-03-24
JP6089096B2 true JP6089096B2 (en) 2017-03-01

Family

ID=55540836

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015251356A Expired - Fee Related JP6089096B2 (en) 2015-12-24 2015-12-24 Method for suppressing twist of precast girder and method for joining precast girder

Country Status (1)

Country Link
JP (1) JP6089096B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7439332B1 (en) 2023-09-11 2024-02-27 エム・エムブリッジ株式会社 Girder construction method and girder erection method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3896032B2 (en) * 2002-05-15 2007-03-22 大成建設株式会社 Construction method of precast column head and pier column head
JP3737475B2 (en) * 2002-12-06 2006-01-18 オリエンタル建設株式会社 Box girder bridge structure and construction method

Also Published As

Publication number Publication date
JP2016040447A (en) 2016-03-24

Similar Documents

Publication Publication Date Title
JP5945418B2 (en) How to build a box girder bridge
KR100536489B1 (en) Manufacturing method for prestressed steel composite girder and prestressed steel composite girder thereby
KR101249285B1 (en) Bridge with prestressed concrete box girder of cantilever support structure by precast bracket, and it`s construction method
JP2008121288A (en) Continuous steel plate web bridge and method of constructing continuous steel plate web bridge
JP2006316580A (en) Corrugated steel plate web pc composite beam and construction method of bridge using corrugated steel plate web pc composite beam
KR101222620B1 (en) Prestressed concrete girder and it's manufacture and construction method which used pretensioning steel plate
KR101693256B1 (en) Construction method of prefabricated psc bridge
JP5620344B2 (en) Construction method of pier
KR101152444B1 (en) The pre-stress concrete bim and that making method using a pre-tensioning construction
JP5184836B2 (en) Construction method of synthetic steel slab girder bridge
KR20120136071A (en) Composite beam with partially filled concrete
JP3701250B2 (en) Cable stayed bridge and its construction method
JP3830767B2 (en) Continuous girder for bridge
JP6089096B2 (en) Method for suppressing twist of precast girder and method for joining precast girder
KR101075756B1 (en) A manufacturing process for the Truss Half Precast Prestressed Concrete Panel
KR100767145B1 (en) Construction method of prestressed concrete temporary bridge that can be assembled and dismantled using lateral steel wire
JP3877995B2 (en) How to build a string string bridge
KR101300490B1 (en) Hollow girder having upper flange of different materials, and method for constructing bridge using for the same
KR102325276B1 (en) Half Precast Concrete continuous slab and construction method of the same
JP4005774B2 (en) Bridge girder
KR200436478Y1 (en) Continuous prestressed concrete structure without baseplate concrete
KR200291793Y1 (en) Pssc complex girder
KR102033052B1 (en) Method for constructing truss bridge support with infilled tube using src girder
KR101023175B1 (en) Method for manufacturing preflex composite beam and continuous composite beam using the same
KR101057409B1 (en) Hollow prestressed concrete girder and method for manufacturing thereof

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160114

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160114

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170131

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170206

R150 Certificate of patent or registration of utility model

Ref document number: 6089096

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees