KR200436478Y1 - Continuous prestressed concrete structure without baseplate concrete - Google Patents

Continuous prestressed concrete structure without baseplate concrete Download PDF

Info

Publication number
KR200436478Y1
KR200436478Y1 KR2020060004208U KR20060004208U KR200436478Y1 KR 200436478 Y1 KR200436478 Y1 KR 200436478Y1 KR 2020060004208 U KR2020060004208 U KR 2020060004208U KR 20060004208 U KR20060004208 U KR 20060004208U KR 200436478 Y1 KR200436478 Y1 KR 200436478Y1
Authority
KR
South Korea
Prior art keywords
prestressed concrete
concrete
bridge
bottom plate
girder
Prior art date
Application number
KR2020060004208U
Other languages
Korean (ko)
Inventor
박영희
Original Assignee
박영희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박영희 filed Critical 박영희
Priority to KR2020060004208U priority Critical patent/KR200436478Y1/en
Application granted granted Critical
Publication of KR200436478Y1 publication Critical patent/KR200436478Y1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Abstract

본 고안은 상부플랜지 및 하부플랜지 측면에 전단키가 형성되어 있는 프리스트레스트 콘크리트 거더가 횡방향으로 플랜지와 플랜지 측면이 맞대어 형성되어 있고 종방향으로는 2경간 이상의 연속구조물에 있어 내측지점부에 상부플랜지 및 하부플랜지에 설치한 연결강판에 의해 연결되어 있으며 상기 전단키 내부에는 몰타르 또는 에폭시가 충전되어 있으며 교량의 종방향으로 횡방향 PC 강선이 설치, 프리스트레스를 도입시킨 것을 특징으로 하는 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물에 관한 것이다.The present invention is a prestressed concrete girder with shear keys formed on the upper flange and the lower flange side, the flange and the side of the flange is formed in the transverse direction, and in the longitudinal direction in the continuous structure of two or more spans, the upper flange and It is connected by connecting steel plate installed on the lower flange, and the inside of the shear key is filled with mortar or epoxy, and the horizontal plate steel wire is installed in the longitudinal direction of the bridge and the prestress is introduced. A prestressed concrete structure.

본 고안에서 제시한 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물은 교량 구조물에서 바닥판 콘크리트가 없는 구조이기에 그만큼 교량 구조물 전체의 형고를 낮출 수가 있으며 연결부에도 프리스트레스를 도입시킬 수 있어 연속교로의 거동도 가능케 할 수 있다. 또한 현장에서 각각 제작된 I형의 프리스트레스트 콘크리트 거더를 횡방향으로 일체화시켜 전체 구조물이 큰 비틀림 강성을 가졌기에 기존의 강상자형교를 대체할 수 있는 교량 구조물로도 충분히 가능할 수 있다.The continuous prestressed concrete structure without the bottom plate concrete presented in the present invention is the structure without the bottom plate concrete in the bridge structure, so that the overall height of the bridge structure can be lowered, and the prestress can be introduced in the connection part. It can be possible. In addition, I-shaped prestressed concrete girder fabricated on the site can be integrated as a bridge structure that can replace the existing steel box bridge because the entire structure has great torsional rigidity.

횡방향 PC 강선 Transverse PC Liner

Description

바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물{.}Continuous Prestressed Concrete Structure without Bottom Plate Concrete {.}

[도 1]은 종래기술의 구조물을 나타낸 사시도로서 [도 1a]는 박스거더 구조물을, [도 1b]는 프리스트레스트 콘크리트 거더 구조물을 나타낸 것이다.FIG. 1 is a perspective view showing a structure of the prior art, FIG. 1A shows a box girder structure, and FIG. 1B shows a prestressed concrete girder structure.

[도 2]는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물에서 [도 2a]는 구조물의 형성을 위해 제작되는 각각의 프리스트레스트 콘크리트 거더의 횡단면도를, [도 2b]는 형성된 구조물의 횡단면도를 나타낸 것이다.FIG. 2 is a cross-sectional view of each prestressed concrete girder fabricated for the formation of the structure in the continuous prestressed concrete structure in which the bottom plate concrete of the present invention is omitted, and FIG. The cross section is shown.

[도 3]는 본 고안 중 제 1 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물의 정면도 및 사시도를 나타낸 것으로 [도 3a]는 정면도를, [도 3b]는 횡방향 프리스트레스를 도입한 후 구조물의 사시도를 [도 3c]는 완공된 구조물의 사시도를 나타낸 것이다.FIG. 3 is a front view and a perspective view of a continuous prestressed concrete structure in which the bottom plate concrete of the first design is omitted, and FIG. 3A is a front view, and FIG. 3B is a transverse prestress. Figure 3c shows a perspective view of the structure after the completed structure.

[도 4]는 본 고안 중 제 2 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물의 정면도 및 사시도를 나타낸 것으로 [도 4a]는 정면도를, [도 4b]는 횡방향 프리스트레스를 도입한 후 구조물의 사시도를 [도 4c]는 완공된 구조물의 사시도를 나타낸 것이다.FIG. 4 is a front view and a perspective view of a continuous prestressed concrete structure in which the bottom plate concrete of the second design is omitted. FIG. 4A is a front view, and FIG. 4B is a transverse prestress. Figure 4c shows a perspective view of the structure after the completed structure.

[도 5]는 본 고안 중 제 1 고안에 의한 바닥판 콘크리트가 생략된 연속 프리 스트레스트 콘크리트 구조물의 연속화 방법에 대한 것으로 [도 5a]는 연결방법에 대한 연결부 정면도 상세도이며 [도 5b]는 상기 [도 5a]의 평면도를, [도 5c]는 본 발명의 연속화 방법에 대한 이론적 설명을 나타내기 위한 상세도이다.5 is a sequential method of the continuous prestressed concrete structure in which the bottom plate concrete is omitted according to the first design of the present invention [FIG. 5A] is a front view of the connection part for the connection method detailed view [FIG. 5B] 5A is a plan view of FIG. 5A, and FIG. 5C is a detailed diagram for illustrating a theoretical explanation of the sequencing method of the present invention.

[도 6]은 본 고안 중 제 2 고안에 의한 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물의 연속화 방법에 대한 것으로 [도 6a]는 연결방법에 대한 연결부 정면도 상세도이며 [도 6b]는 상기 [도 6a]의 평면도를, [도 6c]는 본 발명의 연속화 방법에 대한 이론적 설명을 나타내기 위한 상세도이다.[FIG. 6] is a sequential method of the continuous prestressed concrete structure in which the bottom plate concrete according to the second design of the present invention is omitted. [FIG. 6A] is a detailed view of the connection part for the connection method. 6A is a plan view of FIG. 6A, and FIG. 6C is a detailed diagram for illustrating a theoretical explanation of the sequencing method of the present invention.

< 도면의 주요부분에 대한 설명>    <Description of Main Parts of Drawing>

10:강상자 20:바닥판 콘크리트 30:PC 강선 정착구 40:프리스트레스트 콘크리트 거더 70:종방향 PC 강선 90:전단키 100:횡방향 PC 강선 110:바닥판 콘크리트가 생략된 프리스트레스트 콘크리트 거더 130:외측거더용 상부 및 하부플랜지의 측면에 전단키가 설치된 프리스트레스트 콘크리트 거더 140:내측거더용 상부 및 하부플랜지의 측면에 전단키가 설치된 프리스트레스트 콘크리트 거더 150:몰타르 또는 에폭시 160:연결부DESCRIPTION OF SYMBOLS 10 Steel plate 20 Bottom plate concrete 30 PC steel wire anchorage 40 Prestressed concrete girder 70 Longitudinal PC steel wire 90 Shear key 100 Lateral PC steel wire 110 Freestress concrete girder 130 without bottom plate concrete 130 Outside Prestressed concrete girder 140 with shear keys installed on the sides of the upper and lower flanges for the girder Prestressed concrete girder 150: mortar or epoxy 160 with shear keys installed on the sides of the upper and lower flanges for the inner girder

본 고안은 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물에 관한 것으로써 종래기술로는 박스거더 구조물과 일반 프리스트레스트 콘크리트 거더 구조물이 있다.The present invention relates to a continuous prestressed concrete structure in which the bottom plate concrete is omitted, and the prior art includes a box girder structure and a general prestressed concrete girder structure.

먼저 도 1에 나타낸 종래기술의 구조물을 설명하면 다음과 같다.Referring to the structure of the prior art shown in Figure 1 as follows.

도 1a는 통상의 박스거더(10) 구조물을 도시한 것이다. 박스거더 구조물은 슬래브 하면에 거더를 설치하는 방식이 아닌, 거더와 슬래브가 일체로 제작되어 교량하부 구조물에 설치되고, 슬래브 상면 즉, 거더의 상부플랜지 상면에 포장층을 시공하는 방식으로 교량 시공이 완료된다. 도 1b는 아주 일반적인 슬래브(20) 하면에 설치되는 I형 형태를 가지는 프리스트레스트 콘크리트 거더(40) 구조물을 도시한 것이다. 통상 I형 단면의 프리스트레스트 콘크리트 거더의 간격은 2.5m 정도인데 제작이 간단하여 경제성 측면에서는 유리하나, 설치되는 거더의 개수 및 장지간 설치를 위하여 통상 형고를 높이거나 PC 강선을 내부 또는 외부에 설치하는 단면설계방식을 따르게 되지만 이에는 한계가 있고, 횡방향으로의 거더 설치 개수를 줄이기 위하여 거더 간격은 크게 하고, 형고를 높이는 경우 슬래브의 두께를 증가시켜야 하며, 슬래브용 거푸집 지지용 동바리가 항상 필요하게 되어 그 시공성 및 작업성이 매우 떨어진다는 문제점을 가지고 있다. 또한 비틀림에 대한 저항 능력이 적어 장지간의 교량 구조물에는 그 적용성이 현저히 떨어진다.1A shows a conventional box girder 10 structure. The box girder structure is not installed on the bottom of the slab, but the girder and the slab are manufactured integrally and installed on the lower structure of the bridge, and the bridge construction is performed by installing a paving layer on the upper surface of the slab, that is, the upper flange of the girder. Is done. Figure 1b shows a prestressed concrete girder 40 structure having an I-shape installed on the bottom surface of a very common slab 20. Normally, the length of prestressed concrete girders of type I cross section is about 2.5m, but it is simple to manufacture, which is advantageous in terms of economical efficiency, but in order to install the number of girders to be installed and the long distance between them, usually increase the height of the mold or install PC steel wire inside or outside. However, there is a limit to this, but there is a limit. To reduce the number of girders installed in the transverse direction, the girder spacing should be increased, and the slab thickness should be increased when the mold height is increased, and the slab formwork supporting club is always needed. There is a problem that the workability and workability is very poor. In addition, its resistance to torsion is low, and its applicability is significantly lowered for bridge structures between long legs.

본 고안은 이상에서 설명한 종래기술의 단점들을 보완할 수 있는 새로운 구조물을 개발하고 이를 이용하여 교량을 시공하는 방법을 찾아 그의 적용성을 극대화시키고자 한다.The present invention seeks to maximize the applicability of the method by developing a new structure that can compensate for the disadvantages of the prior art described above and constructing a bridge using the same.

본 고안은 위와 같은 종래 기술의 단점을 해결하고자 하는 목적으로 안출되었으며, 종래의 기술은 바닥판 콘크리트가 추가로 교량에 생성되어 있기에 전체 구조물의 형고가 높을 뿐만 아니라 바닥판 콘크리트를 생략한 구조물을 제작한다고 해도 이를 연속교로의 시도는 전혀 전무하였다.The present invention has been devised for the purpose of solving the above-mentioned disadvantages of the prior art, the prior art is because the bottom plate concrete is additionally generated in the bridge, not only the height of the overall structure is high but also manufactures the structure without the bottom plate concrete Nevertheless, no attempt was made to continue teaching.

도 2에서 도 6는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물에 대한 것이다.2 to 6 is for the continuous prestressed concrete structure without the bottom plate concrete of the present invention.

이를 도면을 이용하여 설명하면 다음과 같다. This will be described with reference to the drawings.

도 2는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물(110)을 나타낸 것으로 도 2a는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물의 구성을 위해 현장의 제작장에서 제작되는 외측거더용 및 내측거더용 상부 및 하부플랜지의 측면에 전단키(90)가 설치된 프리스트레스트 콘크리트 거더(130, 140)의 횡단면도를 나타낸 것으로 1개의 교량 내에 4개의 프리스트레스트 거더가 사용된 일례를 나타낸 것이다. 도 2b는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물(110)의 횡단면을 나타낸 것이다. 바닥판 콘크리트를 생략한 본 고안은 도 2a와 같이 각각 제작한 프리스트레스트 콘크리트 거더의 상부플랜지 위에 포장층을 직접 형성시키고 활하중이 직접 작용하도록 한 것으로 이를 위해서는 제작한 프리스트레스트 콘크리트 거더를 횡으로 플랜지와 플랜지가 직접 맞닿도록 완성하고자하는 교량의 폭만큼 거치시키 고 활하중 작용시 거더가 제각각 처짐이 발생하지 않도록 전단키(90)에는 몰타르 또는 에폭시(150)를 충전한 후 교량의 종방향으로 횡방향 PC 강선(100)을 설치하고 횡방향 프리스트레스를 도입시킨다(도 2b 참조). 이의 사시도를 나타낸 것이 도 3b, 도 3c 및 도 4b, 도 4c이다.Figure 2 shows a continuous prestressed concrete structure 110, the bottom plate concrete of the present invention is omitted, Figure 2a is manufactured in the production site of the site for the configuration of the continuous prestressed concrete structure is omitted the bottom plate concrete of the present invention The cross sectional view of the prestressed concrete girders 130 and 140 having shear keys 90 installed on the side surfaces of the upper and lower flanges for the outer girder and the inner girder, showing an example in which four prestressed girders are used in one bridge. will be. Figure 2b shows a cross section of the continuous prestressed concrete structure 110, the bottom plate concrete of the present invention is omitted. The present invention omitting the bottom plate concrete is to form a pavement layer directly on the upper flange of the prestressed concrete girder, respectively, as shown in Figure 2a and to allow the live load to act directly. Mount the width of the bridge to be in direct contact with the flange, and the shear key 90 is filled with mortar or epoxy 150 so that the girder does not sag when the live load is applied, and then transverse PC steel wire in the longitudinal direction of the bridge Install 100 and introduce transverse prestress (see FIG. 2B). 3B, 3C, 4B, and 4C show perspective views thereof.

도 3 및 도 4는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물을 도시한 것으로 도 3은 그 중 제 1 고안의 실시예를, 도 4는 제 2 고안의 실시예를 나타낸 것이다.3 and 4 illustrate a continuous prestressed concrete structure in which the bottom plate concrete of the present invention is omitted. FIG. 3 shows an embodiment of the first design and FIG. 4 shows an embodiment of the second design.

도 3a는 본 고안의 구조물을 제 1 고안에 대하여 2경간 연속교에 적용시킨 정면도를 보인 것이다. 현장의 제작장에서 한 경간의 길이만큼으로 제작된 프리스트레스트 콘크리트 거더(130, 140)를 교대 및 교각에 거치하고 횡방향 PC 강선(100)에 의해서 각각의 거더를 횡으로 엮은 후 선 발명인 공개특허공보 제 10-2004-0072147호를 이용하여 서로의 거더를 또 종방향으로 연결한다. 다음 공정으로는 거더와 거더 사이의 연결부(160) 공간을 몰타르 또는 에폭시로 충전시키고 이곳에도 추가로 횡방향 PC 강선(100)을 설치하여 프리스트레스를 도입시킨다. 이의 사시도를 나타낸 것이 도 3b이며, 연결된 거더의 상부플랜지 위에 포장층을 포설하여 완성된 구조물을 도 3c에 나타내었다.Figure 3a shows a front view of the structure of the present invention applied to the two-span continuous bridge for the first design. After mounting the prestressed concrete girders 130 and 140 to the alternating and pier at the production site of the field in the alternating and pier, and after weaving each girder laterally by the transverse PC steel wire 100, the inventors Publication 10-2004-0072147 is also used to connect the girders to each other longitudinally. In the next process, the space between the girder and the girder 160 is filled with mortar or epoxy, and additionally, a transverse PC steel wire 100 is installed to introduce prestress. 3B shows a perspective view of the structure, and a structure completed by installing a packaging layer on the upper flange of the connected girder is shown in FIG. 3C.

도 4a는 본 고안의 구조물을 제 2 고안에 대하여 2경간 연속교에 적용시킨 정면도를 보인 것이다. 현장의 제작장에서 한 경간의 길이만큼으로 제작된 프리스트레스트 콘크리트 거더(130, 140)를 교대 및 교각에 거치하고 횡방향 PC 강선(100)에 의해서 각각의 거더를 횡으로 엮은 후 선 발명인 공개특허공보 제 10- 2004-0072147호를 이용하여 서로의 거더를 또 종방향으로 연결한다. 다음 공정으로는 거더와 거더 사이의 연결부(160) 공간을 팽창시멘트로 충전시키며 제 2 고안의 경우는 이곳에 횡방향 PC 강선을 설치하지 않는다. 즉, 팽창시멘트의 팽창만을 이용하여 프리스트레스를 도입시키는 것이다. 이의 사시도를 나타낸 것이 도 4b이며, 연결된 거더의 상부플랜지 위에 포장층을 포설하여 완성된 구조물을 도 4c에 나타내었다.Figure 4a shows a front view of the structure of the present invention applied to the two-span continuous bridge for the second design. After mounting the prestressed concrete girders 130 and 140 to the alternating and pier at the production site of the field in the alternating and pier, and after weaving each girder laterally by the transverse PC steel wire 100, the inventors The girder of each other is also longitudinally connected using the publication 10-2004-0072147. In the next process, the space of the connecting portion 160 between the girder and the girder is filled with expansion cement, and in the case of the second design, no transverse PC steel wire is installed there. That is, the prestress is introduced using only expansion of the expansion cement. 4B is a perspective view illustrating the structure completed by installing a packaging layer on the upper flange of the connected girder.

다음은 본 고안의 핵심이라 할 수 있는 연속화의 이론적 구성에 대하여 자세히 설명한다.The following describes in detail the theoretical construction of sequencing, which is the core of the present invention.

도 5는 본 고안의 제 1 고안인 연속화를 이루기 위한 연결부도 횡방향 PC 강선을 설치하여 프리스트레스를 가할 경우의 이론적 원리에 대한 설명도이다.5 is an explanatory view of a theoretical principle in the case of applying a prestress by installing a transverse PC steel wire to the connection part for continuity which is the first design of the present invention.

도 5a는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물의 연속화를 이루기 위한 연결부(160)를 나타낸 상세도이다. 그림에 나타낸 연결부의 연결방법은 대한민국 공개특허공보 제10-2004-0072147호의 기술을 그대로 사용하였으며 이에 대한 자세한 연결 방법은 생략한다. 단, 프리스트레스트 콘크리트 거더(130, 140) 사이의 에폭시 주입부는 1개의 정착구가 횡방향으로 설치될 수 있도록 그 폭을 크게 하며 충전은 총 2회에 걸쳐서 실시하는데 먼저 1차 충전은 인장력이 발생하는 단면의 중립축 상단까지만 실시하며 나머지 충전은 횡방향 PC 강선의 인장 후에 실시한다. 도 5b는 상기 도 5a의 연결부를 1개 거더에 해당하는 부분만을 나타낸 평면도이다. 1개 거더의 연결부 및 부모멘트 구간에 횡방향 프리스트레스력 P가 작용할 경우 본 발명의 이론적 구성을 설명하기 위해 도 5c는 일례로 연결부만을 나타내었다. 도 5c의 ①에 보인바와 같이 연결부에 충전한 몰타르 또는 에폭시는 횡방향으로의 강선력에 의하여 횡방향으로

Figure 112006010999233-utm00001
만큼의 변형률이 발생한다. 이렇게 발생한 횡방향 변형률은 종방향으로 횡방향의 변형률
Figure 112006010999233-utm00002
에 포아송비(
Figure 112006010999233-utm00003
)를 곱한 수치인
Figure 112006010999233-utm00004
만큼의 변형률을 유발시킨다. 도 5c의 ②는 도 5a의 연결부 상세도에서 "A"부분만을 확대한 그림이며 도 5c의 ①에서 발생한 종방향 변형률은 도 5c의 ②에서 나타낸 바와 같이 몰타르 또는 에폭시의 변형률
Figure 112006010999233-utm00005
와 같다. 이때에 상부 연결 강판도 변형을 하는데 강판은 몰타르 또는 에폭시의 재질과 다르기 때문에 강판은
Figure 112006010999233-utm00006
의 변형률을 가진다. 이로서 강판과 몰타르 또는 에폭시는 그 변형률 차이 (
Figure 112006010999233-utm00007
)에 몰타르 또는 에폭시의 탄성계수
Figure 112006010999233-utm00008
을 곱한 수치만큼 응력(
Figure 112006010999233-utm00009
)이 발생하여 결국 종방향으로 부모멘트에 대응하는 프리스트레스를 가할 수 있는 것이다. Figure 5a is a detailed view showing a connection portion 160 for continuity of the continuous prestressed concrete structure in which the bottom plate concrete of the present invention is omitted. The connection method of the connection part shown in the figure used the technology of the Republic of Korea Patent Publication No. 10-2004-0072147 as it is, and detailed connection method thereof will be omitted. However, the epoxy injection portion between the prestressed concrete girders 130 and 140 increases the width so that one anchorage can be installed in the transverse direction, and the filling is performed twice in total. Only the top of the neutral shaft of the section is carried out, and the rest of the filling is carried out after tensioning the transverse PC steel wire. 5B is a plan view illustrating only a part corresponding to one girder of the connection part of FIG. 5A. When the lateral prestressing force P acts on the connecting portion and the parent section of one girder, FIG. 5C shows only the connecting portion as an example to explain the theoretical configuration of the present invention. As shown in ① of FIG. 5C, the mortar or epoxy filled in the connecting portion is in the transverse direction by the stiffness in the transverse direction.
Figure 112006010999233-utm00001
As much strain occurs. The transverse strain thus generated is the transverse strain in the longitudinal direction.
Figure 112006010999233-utm00002
Poisson's ratio to
Figure 112006010999233-utm00003
) Multiplied by
Figure 112006010999233-utm00004
Cause as much strain. ② of FIG. 5C is an enlarged view of part “A” in the detailed view of the connecting part of FIG. 5A, and the longitudinal strain generated in ① of FIG. 5C is a strain of mortar or epoxy as shown in ② of FIG. 5C.
Figure 112006010999233-utm00005
Same as At this time, the upper connection steel sheet is also deformed. The steel plate is different from the material of mortar or epoxy.
Figure 112006010999233-utm00006
Has a strain of. This allows the steel plate and the mortar or epoxy to differ in its strain rate (
Figure 112006010999233-utm00007
Modulus of elasticity of mortar or epoxy
Figure 112006010999233-utm00008
Stress by the product of
Figure 112006010999233-utm00009
) And eventually prestress corresponding to the parent in the longitudinal direction.

다음 도 6은 본 고안의 제 2 고안인 연속화를 이루기 위한 설명도로서 연결부에 횡방향 PC 강선을 설치하지 않고 팽창시멘트만의 충전으로 종방향으로 프리스트레스를 도입시킬 경우의 이론적 원리에 대한 설명도이다.6 is an explanatory diagram for achieving continuity, which is the second design of the present invention, and is an explanatory diagram for explaining the theoretical principle when the prestress is introduced in the longitudinal direction by filling only the expansion cement without installing the transverse PC steel wire in the connecting portion. .

도 6a는 본 고안의 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물의 연속화를 이루기 위한 연결부(160)를 나타낸 상세도이다. 그림에 나타낸 연결부의 연결방법은 대한민국 공개특허공보 제10-2004-0072147호의 기술을 그대로 사용하였으며 이에 대한 자세한 연결 방법은 생략한다. 단, 상기 연결부에의 충전은 총 2회에 걸쳐서 실시하는데 먼저 1차 충전은 인장력이 발생하는 단면의 중립축 상단까지만 실시하며 나머지 충전은 팽창시멘트의 팽창이 충분히 이루어진 후에 실시한다. 도 6b는 상기 도 6a의 연결부에 팽창시멘트를 충전시킬 경우 본 발명의 이론적 구성을 설명하기 위해 도 6c는 일례로 연결부만을 나타내었다. 도 6c에 보인바와 같이 연결부에 충전한 팽창시멘트는 횡방향 및 종방향으로 모두 팽창이 발생하며 본 발명의 논점 방향인 종방향만으로의 팽창을 고려하면

Figure 112006010999233-utm00010
만큼의 변형률이 발생한다. 도 6c는 도 6a의 연결부 상세도에서 "A"부분만을 확대한 그림이다. 이때에 상부 연결 강판은 변형이 발생하지 않고 팽창시멘트의 종방향 팽창을 억제하기 때문에 자연스럽게 종방향으로 압축응력 (
Figure 112006010999233-utm00011
)이 발생하여 부모멘트에 대응하는 프리스트레스를 가할 수 있는 것이다. Figure 6a is a detailed view showing a connection portion 160 for continuity of the continuous prestressed concrete structure in which the bottom plate concrete of the present invention is omitted. The connection method of the connection part shown in the figure used the technology of the Republic of Korea Patent Publication No. 10-2004-0072147 as it is, and detailed connection method thereof will be omitted. However, the filling of the connecting portion is performed twice in total. First, the first filling is performed only to the upper end of the neutral axis of the cross section in which the tensile force is generated, and the remaining filling is performed after the expansion cement is sufficiently expanded. FIG. 6B illustrates only the connection part as an example to explain the theoretical configuration of the present invention when the expansion cement is filled in the connection part of FIG. 6A. As shown in FIG. 6C, the expansion cement filled in the connecting portion expands both in the transverse direction and in the longitudinal direction, and considering expansion in only the longitudinal direction, which is the point of issue of the present invention.
Figure 112006010999233-utm00010
As much strain occurs. FIG. 6C is an enlarged view of part "A" in the detailed view of the connecting part of FIG. 6A. At this time, the upper connecting steel plate naturally suppresses the compressive stress in the longitudinal direction because it suppresses the longitudinal expansion of the expanded cement without deformation.
Figure 112006010999233-utm00011
) Can be applied to prestress corresponding to the parent.

프리스트레스의 효과를 극대화시키기 위해 상기의 2가지 방법을 혼용해서 사용할 수도 있다.In order to maximize the effect of prestress, the above two methods may be used in combination.

본 고안에서 제시한 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물은 교량 구조물에서 바닥판 콘크리트가 없는 구조이기에 그만큼 교량 구조물 전체의 형고를 낮출 수가 있으며 연결부에도 프리스트레스를 도입시킬 수 있 어 연속교로의 거동도 가능케 할 수 있다. 또한 현장에서 각각 제작된 I형의 프리스트레스트 콘크리트 거더를 횡방향으로 일체화시켜 전체 구조물이 큰 비틀림 강성을 가졌기에 기존의 강상자형교를 대체할 수 있는 교량 구조물로도 충분히 가능할 수 있다.The continuous prestressed concrete structure without the bottom plate concrete presented in the present invention is the structure without the bottom plate concrete in the bridge structure, so the overall height of the bridge structure can be lowered, and the prestress can be introduced to the connection, so the behavior of the continuous bridge It can also be possible. In addition, I-shaped prestressed concrete girder fabricated on the site can be integrated as a bridge structure that can replace the existing steel box bridge because the entire structure has great torsional rigidity.

Claims (4)

상부플랜지 및 하부플랜지 측면에 전단키가 형성되어 있는 프리스트레스트 콘크리트 거더가 횡방향으로 플랜지와 플랜지 측면이 맞대어 형성되어 있고 종방향으로는 2경간 이상의 연속구조물에 있어 내측지점부에 상부플랜지 및 하부플랜지에 설치한 연결강판에 의해 연결되어 있으며 상기 전단키 내부에는 몰타르 또는 에폭시가 충전되어 있으며 교량의 종방향으로 횡방향 PC 강선이 설치, 프리스트레스를 도입시킨 것을 특징으로 하는 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물Prestressed concrete girders with shear keys formed on the upper and lower flange sides are formed with the flange and the flange side facing each other in the transverse direction. Continuous prestressed concrete without bottom plate concrete, which is connected by installed connecting steel plate, and inside the shear key is filled with mortar or epoxy, and a transverse PC steel wire is installed in the longitudinal direction of the bridge to introduce prestress. structure 청구항 1항에 있어According to claim 1 연결강판에 의해 종방향으로 연결된 프리스트레스트 콘크리트 구조물의 틈새에는 몰타르 또는 에폭시 또는 팽창시멘트가 충전되어 있으며 해당 충전부에도 횡방향 PC 강선이 설치되어 프리스트레스가 도입된 것을 특징으로 하는 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물The gap of the prestressed concrete structure connected in the longitudinal direction by the connecting steel plate is filled with mortar or epoxy or expansion cement, and the bottom part concrete is omitted, characterized in that the prestress is introduced by the transverse PC steel wire is also installed in the filling part. Prestressed concrete structures 청구항 1에 있어In claim 1 연결강판에 의해 종방향으로 연결된 프리스트레스트 콘크리트 구조물의 틈새단면의 중립축 상단에는 팽창시멘트가 충전되어 있으며 중립축 하단에는 몰타르 또는 에폭시가 충전되어 있는 것을 특징으로 하는 바닥판 콘크리트가 생략된 연속 프리스트 레스트 콘크리트 구조물Continuous prestressed concrete structure without bottom plate concrete, characterized in that expansion cement is filled at the upper end of the neutral shaft of the gap section of the prestressed concrete structure connected by the connecting steel plate, and mortar or epoxy is filled at the lower end of the neutral shaft. 청구항 1에 있어In claim 1 교량의 종방향으로 형성되어 부모멘트 구간에 설치한 PC 강선은 정모멘트 구간에 설치한 PC 강선보다 좁은 간격으로 형성된 것을 특징으로 하는 바닥판 콘크리트가 생략된 연속 프리스트레스트 콘크리트 구조물PC steel wire formed in the longitudinal direction of the bridge and installed in the parent moment section is a continuous prestressed concrete structure with the bottom plate concrete omitted, characterized in that formed at a narrower interval than the PC steel wire installed in the constant moment section
KR2020060004208U 2006-02-15 2006-02-15 Continuous prestressed concrete structure without baseplate concrete KR200436478Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020060004208U KR200436478Y1 (en) 2006-02-15 2006-02-15 Continuous prestressed concrete structure without baseplate concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020060004208U KR200436478Y1 (en) 2006-02-15 2006-02-15 Continuous prestressed concrete structure without baseplate concrete

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020060014495 Division 2006-02-15 2006-02-15

Publications (1)

Publication Number Publication Date
KR200436478Y1 true KR200436478Y1 (en) 2007-08-28

Family

ID=41632482

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020060004208U KR200436478Y1 (en) 2006-02-15 2006-02-15 Continuous prestressed concrete structure without baseplate concrete

Country Status (1)

Country Link
KR (1) KR200436478Y1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100893322B1 (en) 2008-10-09 2009-04-27 (주) 케이 이엔씨 A girder bridge for slabless
KR101078827B1 (en) * 2008-11-20 2011-11-02 이소라 Structure using pre-cast panel
KR101082126B1 (en) 2009-12-23 2011-11-10 재단법인 포항산업과학연구원 Continuous girder bridge having composite non-uniform section structure and construction method the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100893322B1 (en) 2008-10-09 2009-04-27 (주) 케이 이엔씨 A girder bridge for slabless
KR101078827B1 (en) * 2008-11-20 2011-11-02 이소라 Structure using pre-cast panel
KR101082126B1 (en) 2009-12-23 2011-11-10 재단법인 포항산업과학연구원 Continuous girder bridge having composite non-uniform section structure and construction method the same

Similar Documents

Publication Publication Date Title
JP5945418B2 (en) How to build a box girder bridge
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
US11136733B2 (en) Method for producing an integral bridge, and integral bridge
KR101112195B1 (en) Steel-concrete composite crossbeam having wire mesh and construction method using the same
KR101208231B1 (en) Method for constructing continuous supporting structure of corrugated steel web PSC beam
KR101077090B1 (en) Bridge structure of continuous PSC girder
KR200407182Y1 (en) Precasted concrete plate
KR100318565B1 (en) Reinforcing Method Of PC Beam Bridge With Box Structure And PC Beam Bridge Having Box Reinforced Structure
KR200436478Y1 (en) Continuous prestressed concrete structure without baseplate concrete
KR101300296B1 (en) Rapid cnstruction method of semi-integral abutment bridge using prestressed concrete girder having end diaphragm
KR100767145B1 (en) Construction method of prestressed concrete temporary bridge that can be assembled and dismantled using lateral steel wire
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR100712622B1 (en) Continuous Preflex Girder Structure Using Prestress in Parent Section Using Expanded Concrete and Its Construction Method
KR101075756B1 (en) A manufacturing process for the Truss Half Precast Prestressed Concrete Panel
JP4562631B2 (en) Repair structure of hinge part in concrete structure
KR101397131B1 (en) Prestress concrete bridge and building method thereof
KR102327700B1 (en) Girder structure and construction method for continuity of supporting portion of girder using the same
JP5528217B2 (en) Abutment reinforcement method
KR100631030B1 (en) Precasted concrete plate and bridge slab construction method using that
KR200420640Y1 (en) Continuous prestressed concrete structure without baseplate concrete
KR100582563B1 (en) Construction method for bridges and bridges production it
JP6089096B2 (en) Method for suppressing twist of precast girder and method for joining precast girder
KR20100137749A (en) Precast concrete girder unified with slab
KR20070081812A (en) Hpc
KR101004221B1 (en) One Way Waffle Slab System Continued by Post-tensioning and Post-tensioning method of the same

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20110616

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee