KR100582563B1 - Construction method for bridges and bridges production it - Google Patents

Construction method for bridges and bridges production it Download PDF

Info

Publication number
KR100582563B1
KR100582563B1 KR1020040066731A KR20040066731A KR100582563B1 KR 100582563 B1 KR100582563 B1 KR 100582563B1 KR 1020040066731 A KR1020040066731 A KR 1020040066731A KR 20040066731 A KR20040066731 A KR 20040066731A KR 100582563 B1 KR100582563 B1 KR 100582563B1
Authority
KR
South Korea
Prior art keywords
girder
bottom plate
steel wire
precast bottom
installing
Prior art date
Application number
KR1020040066731A
Other languages
Korean (ko)
Other versions
KR20060018381A (en
Inventor
김근택
Original Assignee
한국시설안전기술공단
주식회사 비엔지컨설턴트
(주)대우건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국시설안전기술공단, 주식회사 비엔지컨설턴트, (주)대우건설 filed Critical 한국시설안전기술공단
Priority to KR1020040066731A priority Critical patent/KR100582563B1/en
Publication of KR20060018381A publication Critical patent/KR20060018381A/en
Application granted granted Critical
Publication of KR100582563B1 publication Critical patent/KR100582563B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

본 발명은 가설 교량의 시공방법 및 이 방법으로 제작된 교량에 관한 것으로, 그 목적은 미리 제작된 거더 측면에 외부강선을 설치하여 현장에 설치하고, 상기 거더의 상면에 프리캐스트(precast) 바닥판을 설치하며, 상기 외부강선을 인장함과 아울러 상기 거더의 상면에 설치된 프리캐스트 바닥판을 연결하도록 하여 시공이 간단히 이루어지는 가설교량의 시공방법 및 이 방법으로 제작된 교량을 제공함에 있다. 이는 (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계; (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계; (c)상기 외부강선(50)을 인장하는 단계; (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계; (e)상기 프리캐스트 바닥판(40)과 거더(30)를 합성하는 단계; 를 포함하는 것이다. 또한, (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계; (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계; (c)상기 외부강선(50)을 인장하는 단계; (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계; (e)상기 프리캐스트 바닥판(40)과 거더(30)를 비합성하는 단계; 를 포함하는 것이다.The present invention relates to a method for constructing a temporary bridge and a bridge manufactured by the method, and an object thereof is to install an external steel wire on a side of a girder prepared in advance, and to install it on a site, and to precast a bottom plate on an upper surface of the girder. To provide a construction method of the construction bridge and the bridge made by this method to simplify the construction by connecting the precast bottom plate installed on the upper surface of the girder as well as tension the outer steel wire. This includes the steps of: (a) installing an external steel wire 50 on the side of the girder 30 prepared in advance, and installing the girder 30 on-site; (b) installing a precast bottom plate 40 on an upper surface of the girder 30; (c) tensioning the outer steel wire 50; (d) connecting the precast bottom plate 40 installed in step (b); (e) synthesizing the precast bottom plate 40 and the girder 30; It will include. In addition, (a) installing the external steel wire 50 on the side of the girder 30 made in advance, the step of installing the girder 30 in the field; (b) installing a precast bottom plate 40 on an upper surface of the girder 30; (c) tensioning the outer steel wire 50; (d) connecting the precast bottom plate 40 installed in step (b); (e) non-synthesizing the precast bottom plate 40 and the girder 30; It will include.

거더, 바닥판, 외부강선Girder, Bottom Plate, Outer Steel Wire

Description

가설 교량의 시공방법 및 이 방법으로 제작된 교량{Construction method for bridges and bridges production it}Construction method for bridges and bridges production it}

도 1은 본 발명에 따른 시공방법을 설명하기 위한 도면으로서, 거더의 측면에 외부강선을 설치한 상태를 나타낸 도면.1 is a view for explaining the construction method according to the present invention, a view showing a state in which the external steel wire is installed on the side of the girder.

도 2는 도 1의 상태에서 바닥판을 안착시키는 단계를 설명하기 위한 도면.2 is a view for explaining a step of seating the bottom plate in the state of FIG.

도 3은 는 도 2에서 설치된 외부강선을 인장하는 단계를 설명하기 위한 도면.3 is a view for explaining the step of tensioning the outer steel wire installed in FIG.

도 4는 도 3에서 바닥판을 연결하는 단계를 설명하기 위한 도면으로 바닥판에 강선을 연결하는 상태를 나타낸 도면.Figure 4 is a view for explaining the step of connecting the bottom plate in Figure 3 showing a state of connecting the steel wire to the bottom plate.

도 5는 도 3에서 바닥판을 연결하는 단계를 설명하기 위한 도면으로 바닥판 사이에 콘크리트를 타설하는 상태를 나타낸 도면.Figure 5 is a view for explaining the step of connecting the bottom plate in Figure 3 showing a state of pouring concrete between the bottom plate.

도 6은 본 발명에 따른 바닥판과 거더를 합성하는 단계를 설명하기 위한 도면.6 is a view for explaining the step of synthesizing the bottom plate and the girder according to the present invention.

(도면중 주요 부분에 대한 부호의 설명)(Explanation of symbols for the main parts of the drawing)

10: 교각 20: 교좌장치10: pier 20: bridge system

30: 거더 40: 바닥판30: girder 40: bottom plate

41: 관통공 42: 내부강선41: through hole 42: inner steel wire

43: 철근 44: 고정수단43: reinforcing bar 44: fixing means

45: 포켓 50: 외부강선45: pocket 50: outer steel wire

51: 정착부 52: 디비에이터51: fixing unit 52: divider

본 발명은 가설 교량의 시공방법 및 이 방법으로 제작된 교량에 관한 것으로, 더욱 상세하게는 미리 제작된 거더 측면에 외부강선을 설치하여 현장에 설치하고, 상기 거더의 상면에 프리캐스트(precast) 바닥판을 설치하며, 상기 외부강선을 인장함과 아울러 상기 거더의 상면에 설치된 프리캐스트 바닥판을 연결하도록 하여 시공이 간단히 이루어지는 가설교량의 시공방법 및 이 방법으로 제작된 교량에 관한 것이다.The present invention relates to a method for constructing a temporary bridge and to a bridge manufactured by the method, and more particularly, to install the external steel wire on the side of a girder prepared in advance, and to install it on a site, and to a precast floor on an upper surface of the girder. The present invention relates to a construction method of a temporary bridge and a bridge manufactured by this method, in which a plate is installed and the external steel wire is tensioned and a precast bottom plate installed on the upper surface of the girder is connected to the construction.

일반적으로 교량은 여러종류가 있으며, 그 중에서 거더교는 교각 교각 사이에 거더를 길이방향으로 설치하고, 상기 거더의 상면에 바닥판(슬래브 이라고도 함)을 설치하고, 상기 바닥판에 콘크리트 등을 타설하게 된다.In general, there are several types of bridges, among which girder bridges are installed in the longitudinal direction between the bridge piers, a bottom plate (also called slab) is installed on the upper surface of the girder, and concrete is placed on the bottom plate. do.

또한, 교각과 교각 사이를 지간(span)이라고 하는데 각 지간의 주형이 분리된 교량을 단순교라 하고, 지간의 주형이 연속된 것을 연속교라 하며, 연속된 지간수에 따라 3지간, 4지간, 5지간 연속교라 부른다.The bridge between the bridge and the bridge is called span, and the bridge where the mold is separated between each bridge is called the simple bridge, and the bridge between the bridges is called the continuous bridge. It is called intercontinental bridge.

상기와 같은 거더교를 시공하기 위한 다양한 방법이 알려져 있다.Various methods for constructing such a girder bridge are known.

그러나, 종래에는 거더의 긴장력을 향상시키기 위해서는 거더의 내부에 쉬스 관을 설치하고, 상기 쉬스관의 내부에 강선을 통과시키고, 상기 강선의 양단부를 인장하도록 하여 작업성 및 시공성이 저하되는 문제점이 있다.However, in the related art, in order to improve the tension force of the girder, a sheath tube is installed inside the girder, a steel wire passes through the sheath tube, and both ends of the steel wire are tensioned so that workability and workability are deteriorated. .

본 발명은 이러한 종래의 문제점을 해결하기 위하여 이루어진 것으로, 그 목적은 미리 제작된 거더 측면에 외부강선을 설치하여 현장에 설치하고, 상기 거더의 상면에 프리캐스트(precast) 바닥판을 설치하며, 상기 외부강선을 인장함과 아울러 상기 거더의 상면에 설치된 프리캐스트 바닥판을 연결하도록 하여 시공이 간단히 이루어지는 가설교량의 시공방법 및 이 방법으로 제작된 교량을 제공함에 있다.The present invention has been made to solve such a conventional problem, the object is to install in the field by installing an external steel wire on the side of the girder made in advance, and install a precast bottom plate on the upper surface of the girder, The present invention provides a method of constructing a temporary bridge in which the construction is simple by tensioning an external steel wire and connecting a precast bottom plate installed on an upper surface of the girder, and a bridge manufactured by the method.

이러한 목적을 달성하기 위한 본 발명은 (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계; (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계; (c)상기 외부강선(50)을 인장하는 단계; (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계; (e)상기 프리캐스트 바닥판(40)과 거더(30)를 합성하는 단계; 를 포함하는 것이다.The present invention for achieving this object is (a) installing the external steel wire 50 on the side of the girder 30 made in advance, the step of installing the girder 30 in the field; (b) installing a precast bottom plate 40 on an upper surface of the girder 30; (c) tensioning the outer steel wire 50; (d) connecting the precast bottom plate 40 installed in step (b); (e) synthesizing the precast bottom plate 40 and the girder 30; It will include.

또한, 상기 보강용 외부강선(50)은 일측면 또는 양측면에 설치하여 시공하는 것이다.In addition, the reinforcing external steel wire 50 is installed on one side or both sides to be constructed.

또한, 상기 프리캐스트 바닥판(40)을 연결시 내부강선(42)을 이용하여 일체로 시공하는 것이다.In addition, the precast bottom plate 40 is to be integrally constructed using the inner steel wire 42 when connecting.

또한, 상기 프리캐스트 바닥판(40) 연결시 바닥판(40) 사이에 철근(43)을 배 치하고 이 프리캐스트 바닥판(40) 사이에는 콘크리트를 타설하여 연결하는 것이다.In addition, the reinforcing bar 43 is disposed between the bottom plate 40 when the precast bottom plate 40 is connected, and the concrete is placed between the precast bottom plate 40 by connecting.

또한, 상기 거더(30)의 양단부에 보강용 외부강선(50)의 정착부(51)를 설치하여 상기 외부강선(50)을 인장하는 것이다.In addition, the fixing portion 51 of the reinforcing outer steel wire 50 is provided at both ends of the girder 30 to tension the outer steel wire 50.

또한, 상기 거더(30)의 하중이 집중되는 위치에 복수개의 디비에이터(52)를 설치하여 인장하는 것이다.In addition, a plurality of dividers 52 are provided at the position where the load of the girder 30 is concentrated and tensioned.

또한, 상기 거더(30)의 상면에 프리캐스트 바닥판(40)과의 고정을 위한 장치로서 복수개의 고정수단(44)을 설치하고, 상기 고정수단(44)과 결합되도록 프리캐스트 바닥판(40)에 형성된 적어도 하나 이상의 포켓(45)에 모르타르 바람직하게는 무수축 모르타르를 충진 타설하여 상기 거더(30)와 프리캐스트 바닥판(40)이 합성단면이 되도록 하는 것이다.In addition, a plurality of fixing means 44 is installed on the upper surface of the girder 30 as a device for fixing with the precast bottom plate 40, and the precast bottom plate 40 is coupled to the fixing means 44. At least one pocket (45) formed in the present invention is filled with mortar, preferably non-shrink mortar so that the girder 30 and the precast bottom plate 40 is a composite cross section.

또한, (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계; (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계; (c)상기 외부강선(50)을 인장하는 단계; (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계; (e)상기 프리캐스트 바닥판(40)과 거더(30)를 비합성하는 단계; 를 포함하는 것이다.In addition, (a) installing the external steel wire 50 on the side of the girder 30 made in advance, the step of installing the girder 30 in the field; (b) installing a precast bottom plate 40 on an upper surface of the girder 30; (c) tensioning the outer steel wire 50; (d) connecting the precast bottom plate 40 installed in step (b); (e) non-synthesizing the precast bottom plate 40 and the girder 30; It will include.

또한, 상기 프리캐스트 바닥판(40)에 형성된 포켓(45)에 모르타르 바람직하게는 무수축 모르타르를 충전 타설하여 비합성 단면으로 형성하는 것이다.In addition, the mortar, preferably the non-contraction mortar, is filled and poured into the pocket 45 formed on the precast bottom plate 40 to form a non-synthetic cross section.

또한, 상기 시공방법으로 제작된 가설교량을 포함하는 것이다.In addition, it includes a temporary bridge produced by the construction method.

또한, 상기 교량의 거더(30) 타입이 피에스씨(PSC)거더, 스틸박스 거더, 스틸플레이트 거더 중 어느 하나인 것이다.In addition, the type of girder 30 of the bridge is any one of the PSC (PSC) girder, steel box girder, steel plate girder.

이하 본 발명의 바람직한 실시예를 첨부된 도면에 의거하여 상세하게 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 6은 본 발명에 따른 가설 교량의 시공방법을 설명하기 위한 도면이다. 이하에서 부호 10은 교각, 20은 교좌장치, 30은 거더, 40은 바닥판을 나타내고 있다.1 to 6 are views for explaining the construction method of the temporary bridge according to the present invention. Hereinafter, reference numeral 10 denotes a pier, 20 denotes a bridge arrangement, 30 denotes a girder, and 40 denotes a bottom plate.

도시한 바와 같이 본 발명에 따른 가설 교량의 시공방법은 (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계와, (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계와, (c)상기 외부강선(50)을 인장하는 단계와, (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계와, (e)상기 프리캐스트 바닥판(40)과 거더(30)를 합성하는 단계로 구성되어진다.As shown, the construction method of the temporary bridge according to the present invention comprises the steps of (a) installing the external steel wire 50 on the side of the girder 30 prepared in advance, and installing the girder 30 in the field, (b Installing a precast bottom plate 40 on the upper surface of the girder 30, (c) tensioning the outer steel wire 50, and (d) installed in the step (b) Connecting the precast bottom plate 40 and (e) synthesizing the precast bottom plate 40 and the girder 30.

상기 외부강선(50)을 설치하기 위해서는 상기 거더(30)의 양단부에 보강용 외부강선(50)의 정착부(51)을 설치하고, 상기 정착부(51)의 사이 거더(30)의 하중이 집중되는 위치에 복수개의 디비에이터(52)를 설치하여 외부강선(50)을 인장하게 된다.In order to install the external steel wire 50, the fixing unit 51 of the reinforcing external steel wire 50 is installed at both ends of the girder 30, the load of the girder 30 between the fixing unit 51 The plurality of dividers 52 are installed in the concentrated position to tension the outer steel wire 50.

상기에서 정착부(51)와 디비에이터(52)는 일반적인 것임으로 상세한 설명은 생략한다.Since the fixing unit 51 and the divider 52 are general, detailed description thereof will be omitted.

또한, 상기 프리캐스트 바닥판(40)은 미리 공장에서 제작하여 거더(30)의 상면에 순차적으로 안착시키게 된다.In addition, the precast bottom plate 40 is manufactured in advance in the factory to be sequentially seated on the upper surface of the girder 30.

또한, 상기 프리캐스트 바닥판(40)을 연결하여 일체화시키는 방법에는 두가 지가 있으며, 그 중 하나는 프리캐스트 바닥판(40)의 종방향으로 형성된 관통공(41)에 내부강선(42)을 설치하여 프리캐스트 바닥판(40)을 연결하는 방법이다.In addition, there are two methods of integrating the precast bottom plate 40 and integrating the precast bottom plate 40. One of them includes the inner steel wire 42 in the through hole 41 formed in the longitudinal direction of the precast bottom plate 40. It is a method of connecting the precast bottom plate 40 by installing.

그리고, 또 다른 방법은 바닥판(40)과 바닥판(40) 사이에 철근(43)을 배치하고, 이 사이에 콘크리트를 타설하는 방법이 있다.Another method is to arrange reinforcing bars 43 between the bottom plate 40 and the bottom plate 40, and to pour concrete therebetween.

또한, 상기 거더(30)의 상면에 프리캐스트 바닥판(40)과의 고정을 위한 장치로서 복수개의 고정수단(44)을 설치하고, 상기 고정수단(44)과 결합되도록 프리캐스트 바닥판(40)에 형성된 적어도 하나 이상의 포켓에 모르타르 바람직하게는 무수축 모르타르를 충진 타설하여 상기 거더(30)와 프리캐스트 바닥판(40)이 합성단면이 되도록 하는 것이 바람직하다.In addition, a plurality of fixing means 44 is installed on the upper surface of the girder 30 as a device for fixing with the precast bottom plate 40, and the precast bottom plate 40 is coupled to the fixing means 44. It is preferable to fill the mortar, preferably the non-shrink mortar in at least one pocket formed in the) so that the girder 30 and the precast bottom plate 40 is a composite cross section.

상기 고정수단(44)은 철근 등이 돌출되도록 하는 것이다.The fixing means 44 is to protrude the rebar, and the like.

한편, 본 발명의 시공방법은 합성단면 뿐만 아니라 비합성단면도 시공이 가능하고, 동일한 단계로 진행할 수 있다.On the other hand, the construction method of the present invention can be carried out not only the synthetic cross section but also the non-synthetic cross section, and proceed to the same step.

즉, (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계와, (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계와, (c)상기 외부강선(50)을 인장하는 단계와, (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계와, (e)상기 프리캐스트 바닥판(40)과 거더(30)를 비합성하는 단계로 이루어지게 된다.That is, (a) installing the external steel wire 50 on the side of the girder 30 prepared in advance, and installing the girder 30 in the field, and (b) precast (top) on the upper surface of the girder 30 precast) installing the bottom plate 40, (c) tensioning the outer steel wire 50, (d) connecting the precast bottom plate 40 installed in the step (b) and , (e) non-synthesizing the precast bottom plate 40 and the girder 30.

또한, 상기의 프리캐스트 바닥판(40)에 형성된 포켓(45)에 모르타르 바람직하게는 무수축 모르타르를 충전 타설하여 비합성 단면으로 형성할 수 도 있을 것이다.In addition, the mortar, preferably the non-condensed mortar, may be filled and poured into the pocket 45 formed on the precast bottom plate 40 to form a non-synthetic cross section.

또한, 상기 같은 시공방법으로 성형된 교량에 적용되는 거더(30) 타입은 피에스씨(PSC)거더, 스틸박스 거더, 스틸플레이트 거더 중 어느 것이라도 가능하지만 스틸플레이트가 보다 바람직하다.In addition, the girder 30 type applied to the bridge formed by the above construction method may be any one of PSC girder, steel box girder, and steel plate girder, but steel plate is more preferable.

그리고, 상기와 같은 시공방법으로 제작된 교량은 거더(30)의 측면에 외부강선(50)을 설치하고, 미리 제작된 프리캐스트 바닥판(40)을 안착시키며, 거더(30)의 외측에 외부강선(50)을 설치하여 인장하도록 하고, 상기 바닥판(40)을 연결하도록 하여 시공이 간단이 이루어지게 된다.In addition, the bridge manufactured by the construction method as described above is installed on the side of the girder 30, the outer steel wire 50, the precast bottom plate 40 is seated in advance, the outside of the girder 30 Install the steel wire 50 to tension, and connecting the bottom plate 40, the construction is made simple.

또한, 본 발명의 시공방법은 연속교를 예를 들어 설명하였지만 단순교도 시공할 수 있는 것은 당연하다.In addition, although the construction method of the present invention has been described using a continuous bridge as an example, it is natural that a simple bridge can also be constructed.

이상 상세히 설명한 바와 같은 본 발명의 미리 제작된 거더 측면에 외부강선을 설치하여 현장에 설치하고, 상기 거더의 상면에 프리캐스트(precast) 바닥판을 설치하며, 상기 외부강선을 인장함과 아울러 상기 거더의 상면에 설치된 프리캐스트 바닥판을 연결하도록 하여 시공이 간단히 이루어지는 것이다.Install the external steel wire on the site of the pre-fabricated girders of the present invention as described in detail above, install in the field, install a precast bottom plate on the upper surface of the girder, and tension the external steel wire as well as the girder Installation is made simply by connecting the precast bottom plate installed on the upper surface.

Claims (12)

(a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계; (a) installing the external steel wire 50 on the side of the girder 30 prepared in advance, and installing the girder 30 in the field; (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계; (b) installing a precast bottom plate 40 on an upper surface of the girder 30; (c)상기 외부강선(50)을 인장하는 단계;(c) tensioning the outer steel wire 50; (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계; (d) connecting the precast bottom plate 40 installed in step (b); (e)상기 프리캐스트 바닥판(40)과 거더(30)를 합성하는 단계; 를 포함하는 것을 특징으로 하는 가설교량 시공방법.(e) synthesizing the precast bottom plate 40 and the girder 30; Temporary bridge construction method comprising a. 제1항에 있어서,The method of claim 1, 상기 보강용 외부강선(50)은 일측면 또는 양측면에 설치하여 시공하는 것을 특징으로 하는 가설교량 시공방법.Temporary bridge construction method characterized in that the reinforcing external steel wire 50 is installed on one side or both sides. 제1항에 있어서, The method of claim 1, 상기 프리캐스트 바닥판(40)을 연결시 내부강선(42)을 이용하여 일체로 시공하는 것을 특징으로 하는 가설교량 시공방법.Temporary bridge construction method, characterized in that the pre-cast floor plate 40 is integrally constructed using an internal steel wire (42) when connecting. 제1항에 있어서, The method of claim 1, 상기 프리캐스트 바닥판(40) 연결시 바닥판(40) 사이에 철근(43)을 배치하고 이 프리캐스트 바닥판(40) 사이에는 콘크리트를 타설하여 연결하는 것을 특징으로 하는 가설교량 시공방법.Reinforcement 43 is disposed between the bottom plate 40 when the precast bottom plate 40 is connected between the precast bottom plate 40, the construction of the temporary bridge construction method, characterized in that by connecting concrete. 제1항에 있어서, The method of claim 1, 상기 거더(30)의 양단부에 보강용 외부강선(50)의 정착부(51)를 설치하여 상기 외부강선(50)을 인장하는 것을 특징으로 하는 가설교량 시공방법.Temporary bridge construction method characterized in that the fixing of the fixing portion 51 of the reinforcing outer steel wire (50) on both ends of the girder 30 to tension the outer steel wire (50). 제1항에 있어서, The method of claim 1, 상기 거더(30)의 하중이 집중되는 위치에 복수개의 디비에이터(52)를 설치하여 인장하는 것을 특징으로 하는 가설교량 시공방법.Temporary bridge construction method characterized in that the tension is provided by installing a plurality of dividers (52) in the position where the load of the girder (30) is concentrated. 제1항에 있어서, The method of claim 1, 상기 거더(30)의 상면에 프리캐스트 바닥판(40)과의 고정을 위한 장치로서 복수개의 고정수단(44)을 설치하고, 상기 고정수단(44)과 결합되도록 프리캐스트 바닥판(40)에 형성된 적어도 하나 이상의 포켓(45)에 모르타르 바람직하게는 무수축 모르타르를 충진 타설하여 상기 거더(30)와 프리캐스트 바닥판(40)이 합성단면이 되도록 하는 것을 특징으로 하는 가설교량 시공방법.As a device for fixing with the precast bottom plate 40 on the upper surface of the girder 30, a plurality of fixing means 44 are installed, and the precast bottom plate 40 is coupled to the fixing means 44. Method of constructing a temporary bridge construction, characterized in that the girder 30 and the precast bottom plate (40) is filled with a mortar, preferably a non-shrink mortar in the formed at least one pocket (45). (a)미리 제작된 거더(30) 측면에 외부강선(50)을 설치하고, 상기 거더(30)를 현장에 설치하는 단계; (a) installing the external steel wire 50 on the side of the girder 30 prepared in advance, and installing the girder 30 in the field; (b)상기 거더(30)의 상면에 프리캐스트(precast) 바닥판(40)을 설치하는 단계; (b) installing a precast bottom plate 40 on an upper surface of the girder 30; (c)상기 외부강선(50)을 인장하는 단계;(c) tensioning the outer steel wire 50; (d)상기 (b)단계에 설치된 프리캐스트 바닥판(40)을 연결하는 단계; (d) connecting the precast bottom plate 40 installed in step (b); (e)상기 프리캐스트 바닥판(40)과 거더(30)를 비합성하는 단계; 를 포함하는 것을 특징으로 하는 가설교량 시공방법.(e) non-synthesizing the precast bottom plate 40 and the girder 30; Temporary bridge construction method comprising a. 제8항에 있어서, The method of claim 8, 상기 프리캐스트 바닥판(40)에 형성된 포켓(45)에 모르타르 바람직하게는 무수축 모르타르를 충전 타설하여 비합성 단면으로 형성하는 것을 특징으로 하는 가설교량 시공방법.Temporary bridge construction method characterized in that the pocket 45 formed in the precast bottom plate 40 is filled with mortar, preferably non-contraction mortar to form a non-synthetic cross section. 상기 제1항 기재의 시공방법으로 제작된 가설교량.Temporary bridge produced by the construction method described in claim 1. 상기 제8항 기재의 시공방법으로 제작된 가설교량.Temporary bridge produced by the construction method of claim 8. 제10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 교량의 거더(30) 타입이 피에스씨(PSC)거더, 스틸박스 거더, 스틸플레이트 거더 중 어느 하나인 것을 특징으로 하는 가설교량.The bridge girder (30) type is a temporary bridge, characterized in that any one of the PSC (PSC) girder, steel box girder, steel plate girder.
KR1020040066731A 2004-08-24 2004-08-24 Construction method for bridges and bridges production it KR100582563B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040066731A KR100582563B1 (en) 2004-08-24 2004-08-24 Construction method for bridges and bridges production it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040066731A KR100582563B1 (en) 2004-08-24 2004-08-24 Construction method for bridges and bridges production it

Publications (2)

Publication Number Publication Date
KR20060018381A KR20060018381A (en) 2006-03-02
KR100582563B1 true KR100582563B1 (en) 2006-05-23

Family

ID=37126016

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040066731A KR100582563B1 (en) 2004-08-24 2004-08-24 Construction method for bridges and bridges production it

Country Status (1)

Country Link
KR (1) KR100582563B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100963488B1 (en) 2009-07-29 2010-06-17 노윤근 Negative moment floor slab prestress introduction method for which precast concrete pc wire anchorage block and this were used
KR100989586B1 (en) 2010-06-07 2010-10-25 주식회사 하이드로코리아 Girder for rahmen structure, the making method and bridge construction method using girder for rahmen structure
KR101074868B1 (en) 2008-10-30 2011-10-19 주식회사 교량과 고속철도 A multi-storied continuous rahmen bridge for additional longitudinal forces control of continuous welded rail and construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100793158B1 (en) * 2006-12-21 2008-01-10 주식회사 포스코 Construction method of girder bridge with later-tension precast plate
KR101637249B1 (en) * 2015-11-13 2016-07-07 대림산업 주식회사 Composite Girder with Steel Box Beam and Precast Concrete Slabs, and Constructing Method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197420A (en) * 1994-01-07 1995-08-01 Mitsubishi Heavy Ind Ltd Construction method of continuous composite girder bridge of concrete floor slab and steel girder
JPH07233509A (en) * 1994-02-24 1995-09-05 Mitsubishi Heavy Ind Ltd Building method for composite girder bridge to be formed by successively joining reinforced precast concrete floor slab to beam
KR19990068518A (en) * 1999-05-29 1999-09-06 정희용 The Structural Continuity Method for Prestreseed Concrete Bridge of Composite I-Beam
KR200167418Y1 (en) 1999-08-05 2000-02-15 정규성 Apparatus to reinforce structur member
KR20010000430A (en) * 2000-09-28 2001-01-05 한만엽 Open-type steel wire holding device and Metod for construction of continuous bridge using of prestressed concret beam having it
KR100323825B1 (en) 1998-10-19 2002-06-20 남상국 Bridge deck system using precast concrete deck with internal tension
KR200278126Y1 (en) 2002-02-19 2002-06-21 동양종합건업 주식회사 Multi-span continuous P.S.C. - I beam bridge
KR100362993B1 (en) 1999-11-05 2002-11-29 장승필 Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof
KR20040098995A (en) * 2003-05-16 2004-11-26 주식회사 비엔지컨설턴트 Construction Method for PSC Girder Bridges

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197420A (en) * 1994-01-07 1995-08-01 Mitsubishi Heavy Ind Ltd Construction method of continuous composite girder bridge of concrete floor slab and steel girder
JPH07233509A (en) * 1994-02-24 1995-09-05 Mitsubishi Heavy Ind Ltd Building method for composite girder bridge to be formed by successively joining reinforced precast concrete floor slab to beam
KR100323825B1 (en) 1998-10-19 2002-06-20 남상국 Bridge deck system using precast concrete deck with internal tension
KR19990068518A (en) * 1999-05-29 1999-09-06 정희용 The Structural Continuity Method for Prestreseed Concrete Bridge of Composite I-Beam
KR200167418Y1 (en) 1999-08-05 2000-02-15 정규성 Apparatus to reinforce structur member
KR100362993B1 (en) 1999-11-05 2002-11-29 장승필 Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof
KR20010000430A (en) * 2000-09-28 2001-01-05 한만엽 Open-type steel wire holding device and Metod for construction of continuous bridge using of prestressed concret beam having it
KR200278126Y1 (en) 2002-02-19 2002-06-21 동양종합건업 주식회사 Multi-span continuous P.S.C. - I beam bridge
KR20040098995A (en) * 2003-05-16 2004-11-26 주식회사 비엔지컨설턴트 Construction Method for PSC Girder Bridges

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101074868B1 (en) 2008-10-30 2011-10-19 주식회사 교량과 고속철도 A multi-storied continuous rahmen bridge for additional longitudinal forces control of continuous welded rail and construction method
KR100963488B1 (en) 2009-07-29 2010-06-17 노윤근 Negative moment floor slab prestress introduction method for which precast concrete pc wire anchorage block and this were used
KR100989586B1 (en) 2010-06-07 2010-10-25 주식회사 하이드로코리아 Girder for rahmen structure, the making method and bridge construction method using girder for rahmen structure

Also Published As

Publication number Publication date
KR20060018381A (en) 2006-03-02

Similar Documents

Publication Publication Date Title
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR100681849B1 (en) Fabricated Hollow Precast Concrete Slab
KR20160150155A (en) Fcm construction method using divided pouring light weight concrete for segment
KR20110126866A (en) Method for constructing united joint of tube filled concrete block
KR20180049518A (en) Construction methods inducing compressive stress in slab of negative moment area for type of rahmen bridge using precast girder
KR100936944B1 (en) Continuity Girder, Continuity Structure of Girder and Construction Method of the Same
KR102142633B1 (en) Accelerated construction method of integral abutment bridge and chambered precast segment wall applied to the same
KR100727114B1 (en) Precast segment for constructing through bridges and the constructing method using it
KR101034973B1 (en) Bridge and its construction method using tide arch hybrid girders by connecting precast blocks
KR101117497B1 (en) Bridge having continuous arch hybrid girders and the bridge construction method using the same
KR20160150154A (en) Fcm construction method using divided pouring of segment concrete
KR101582599B1 (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR20090050508A (en) Bridge having deck slab concrete structure on plural beams, constructing method thereof and precast partial-depth deck slab concrete structure used in constructing same
KR100582563B1 (en) Construction method for bridges and bridges production it
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
KR101664997B1 (en) Constructing method of precast T type modular composite rahmen bridge and composite rahmen bridge constructed by the same, and construction thing therefor
KR102139132B1 (en) Steel form structure capable of adjusting the angle of end, and prestressed concrete beam manufactured thereby and construction method of bridge using the same
KR101038714B1 (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
KR100616533B1 (en) Construction method for p.s.c. girder bridges and bridges production it
JP2006169730A (en) Concrete bridge girder and method of forming the same
KR100629905B1 (en) Reinforcement method for existing bridges and bridges production it
KR20100137749A (en) Precast concrete girder unified with slab
JP2008274567A (en) Circular steel pipe prefabricated bridge and its construction method
KR20150083446A (en) Construction methods for bridges of rahmen types by using precast P.S girder and steel box girder

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130305

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140305

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150504

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20160516

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20170608

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20180620

Year of fee payment: 13