JP5514846B2 - Simple lining board - Google Patents

Simple lining board Download PDF

Info

Publication number
JP5514846B2
JP5514846B2 JP2012023918A JP2012023918A JP5514846B2 JP 5514846 B2 JP5514846 B2 JP 5514846B2 JP 2012023918 A JP2012023918 A JP 2012023918A JP 2012023918 A JP2012023918 A JP 2012023918A JP 5514846 B2 JP5514846 B2 JP 5514846B2
Authority
JP
Japan
Prior art keywords
lining
main body
lining board
lining plate
road surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012023918A
Other languages
Japanese (ja)
Other versions
JP2013159998A (en
Inventor
裕央 山口
智 河上
俊樹 高橋
Original Assignee
東信工業株式会社
Llアシスト株式会社
三倉工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 東信工業株式会社, Llアシスト株式会社, 三倉工業株式会社 filed Critical 東信工業株式会社
Priority to JP2012023918A priority Critical patent/JP5514846B2/en
Publication of JP2013159998A publication Critical patent/JP2013159998A/en
Application granted granted Critical
Publication of JP5514846B2 publication Critical patent/JP5514846B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Description

本発明は、掘削した路面などを仮復旧する際に用いられる構造物であって、掘削箇所の上部を覆うための簡易覆工板に関する。   The present invention relates to a simple lining plate for covering an upper portion of an excavation site, which is a structure used when temporarily recovering an excavated road surface and the like.

従来から、上下水道管、ガス管、電気ケーブル等を新たに埋設する場合や、これら埋設した管、ケーブル等を保守点検及び維持管理する場合には、必要な深さまで路面を掘削して水道管などの埋設工事等が行われている。
ところで、このような埋設工事等のために掘削された路面などの掘削箇所は、工事終了後に、路面から所定の深さまで砂、砕石等を投入して埋め戻されるとともに、敷き詰められた砂、砕石等の上にアスファルト合材等を施して仮復旧舗装が行われており、形成された掘削箇所が車両の路面走行や人の通行に支障を来たさないように、路面と面一となるような対策が施されている。そして後日、時間経過に伴って掘削箇所に敷き詰められた砂、砕石等が押し固められると、仮復旧舗装のアスファルト合材等を剥ぎ取り、その後、アスファルト合材等を使用して掘削箇所及び周辺箇所の本復旧舗装工事が行われるようになっている。
Conventionally, when newly burying water and sewage pipes, gas pipes, electric cables, etc., or when maintaining and checking these buried pipes and cables, water pipes are excavated to the required depth. Such as burial work is carried out.
By the way, excavation points such as road surfaces excavated for such burial work etc. are backfilled with sand, crushed stones, etc. from the road surface to a predetermined depth after the completion of construction, and the laid sand, crushed stones Temporary restoration pavement is carried out by applying asphalt compound material etc. on etc., so that the excavated place formed will be flush with the road surface so as not to hinder the road running of the vehicle and traffic of people Such measures are taken. And later, when sand, crushed stones, etc. spread over the excavation site with time elapses, the asphalt composite material of the temporary restoration pavement is peeled off, and then the asphalt composite material etc. The actual restoration paving work is being carried out at the location.

すなわち、路面の掘削箇所などを本復旧舗装する際には、仮復旧舗装のアスファルト合材等を剥ぎ取る面倒な作業が必要となるため、多くの作業時間が掛かるという問題があった。また、剥ぎ取られたアスファルト合材等の大部分は、再利用されずに廃棄されており、産業廃棄物として処理しなければならないので、経済的に不利であるとともに、地球環境に悪影響を与え、エコ性能の向上を図ることができないという問題があった。   That is, when this road is excavated on the road surface, there is a problem that it takes a lot of work time because it requires troublesome work to remove the asphalt composite material of the temporarily restored paving. In addition, most of the stripped asphalt mixture is discarded without being reused and must be disposed of as industrial waste, which is economically disadvantageous and adversely affecting the global environment. There was a problem that eco-performance could not be improved.

そこで従来においては、路面などの掘削箇所の埋め戻し面上に仮路盤材を敷き詰める仮復旧工法が提供されている(例えば、特許文献1参照)。
特許文献1の仮復旧工法では、掘削坑を路面高さから所定の深さまで埋め戻し、埋め戻し面上に仮路盤材を敷き詰め、敷き詰めた仮路盤材及びその周囲をマットで覆い、マット中の仮路盤材より外側の箇所にピンを打ち込むことによってマットを固定し、アスファルト合材等を使用せずに仮復旧工事を行っている。
Therefore, in the past, a temporary restoration method has been provided in which temporary roadbed material is laid down on a backfill surface of an excavation site such as a road surface (see, for example, Patent Document 1).
In the temporary restoration method of Patent Document 1, the excavation mine is backfilled from the road surface height to a predetermined depth, the temporary roadbed material is spread on the backfill surface, and the spread temporary roadbed material and its periphery are covered with a mat. The mat is fixed by driving a pin outside the temporary roadbed material, and temporary restoration work is performed without using asphalt mix.

特開2004−52410号公報JP 2004-52410 A

しかしながら、上述した従来の仮復旧工法においては、埋め戻し面上に仮路盤材を載置し、この仮路盤材の上をマットで覆うとともに、マットをピンで路面に固定しているに過ぎないので、通行する車両などによってマットが破損したり、あるいは、仮路盤材が所定の設置位置から移動したりすることが起こり、仮路盤材を介して掘削箇所の砂、砕石等の埋め戻し材を十分に押し固めることができない可能性があった。したがって、上述した従来の仮復旧工法では、仮復旧の機能を十分に発揮できず、使用回数も限られ、本復旧舗装工事に支障を来たすおそれがあった。そのため、上述した従来の仮復旧工法は、路肩等に設けられる比較的小さな掘削箇所に使用され、車両や人が多く通行する交通量の多い道路などに用いられておらず、使用できる範囲が狭いという問題があった。   However, in the conventional temporary restoration method described above, a temporary roadbed material is placed on the backfill surface, the temporary roadbed material is covered with a mat, and the mat is fixed to the road surface with pins. Therefore, the mat may be damaged by a passing vehicle or the like, or the temporary roadbed material may be moved from the predetermined installation position, and the backfill material such as sand, crushed stone, etc. at the excavation site is passed through the temporary roadbed material. There was a possibility that it could not be fully pressed. Therefore, in the conventional temporary restoration method described above, the function of temporary restoration cannot be fully exhibited, the number of times of use is limited, and this restoration pavement work may be hindered. Therefore, the conventional temporary restoration method described above is used for relatively small excavation points provided on the shoulders of the road, etc., and is not used for roads with a lot of traffic through which many vehicles and people pass, and the usable range is narrow. There was a problem.

本発明はこのような実状に鑑みてなされたものであって、その目的は、掘削した路面を仮復旧する際に、仮復旧舗装のアスファルト合材等を用いることなく繰り返し使用でき、産業廃棄物の量を減らしてエコ性能の向上と工事期間の短縮を図ることができるとともに、本復旧舗装するまで掘削箇所の埋め戻し材を十分に押し固めることができ、本復旧舗装工事を迅速かつ確実に行うことが可能な簡易覆工板を提供することにある。   The present invention has been made in view of such a situation, and the purpose of the present invention can be repeatedly used without temporarily using the asphalt mixture of temporarily restored pavement when temporarily recovering the excavated road surface. By reducing the amount of wastewater, the eco-performance can be improved and the construction period can be shortened, and the backfilling material at the excavation site can be sufficiently solidified until the restoration pavement is completed. It is in providing the simple lining board which can be performed.

上記従来技術の有する課題を解決するために、本発明は、路面を掘削することにより形成される掘削箇所を仮復旧する際に用いられ、前記路面から所定の深さまで埋め戻した埋め戻し面上に設置される簡易覆工板であって、前記埋め戻し面上で長手方向及び幅方向に並べて配置される複数の覆工板本体を備え、これら覆工板本体の中央部には、締結具を差し込む差込孔が設けられ、かつ、前記覆工板本体の側部には、本体凹凸部がそれぞれ設けられており、前記覆工板本体のそれぞれは、隣接する前記覆工板本体の対向する前記本体凹凸部を互いに嵌合させることによって前記路面の長手方向及び幅方向で連結されているとともに、前記締結具を前記差込孔に差し込むことによって前記埋め戻し面に固定されている。   In order to solve the above-described problems of the prior art, the present invention is used when temporarily recovering an excavation site formed by excavating a road surface, on a backfill surface backfilled from the road surface to a predetermined depth. A plurality of lining plate bodies arranged side by side in the longitudinal direction and the width direction on the backfill surface, and a fastener at the center of these lining plate bodies Insertion side holes are provided, and side portions of the main body of the lining plate are provided with main body uneven portions, and each of the lining plate main bodies is opposed to the adjacent lining plate main body. The main body uneven portions are connected to each other in the longitudinal direction and the width direction of the road surface by being fitted to each other, and are fixed to the backfill surface by inserting the fastener into the insertion hole.

また、本発明において、前記路面の長手方向及び幅方向の少なくとも一方には、前記掘削箇所の開口寸法に対応して端部覆工板が配置され、該端部覆工板の側部には、端部凹凸部が設けられており、前記端部覆工板は、前記端部凹凸部を前記覆工板本体の前記本体凹凸部に嵌合させることによって前記覆工板本体に連結されている。   Further, in the present invention, an end covering plate is disposed in at least one of the longitudinal direction and the width direction of the road surface corresponding to the opening size of the excavation site, and on the side portion of the end covering plate An end concavo-convex portion is provided, and the end lining plate is coupled to the lining plate main body by fitting the end concavo-convex portion to the main body concavo-convex portion of the covering plate main body. Yes.

さらに、本発明において、前記覆工板本体及び前記端部覆工板の連結される側部間には、シール材が配設されている。
そして、本発明において、前記覆工板本体及び前記端部覆工板の周囲には、補修材が敷き詰められている。
Furthermore, in this invention, the sealing material is arrange | positioned between the side parts to which the said lining board main body and the said edge part lining board are connected.
And in this invention, the repair material is spread | wrapped around the said lining board main body and the said edge part lining board.

上述の如く、本発明に係る簡易覆工板は、路面を掘削することにより形成される掘削箇所を仮復旧する際に用いられ、前記路面から所定の深さまで埋め戻した埋め戻し面上に設置されるものであって、前記埋め戻し面上で長手方向及び幅方向に並べて配置される複数の覆工板本体を備え、これら覆工板本体の中央部には、締結具を差し込む差込孔が設けられ、かつ、前記覆工板本体の側部には、本体凹凸部がそれぞれ設けられており、前記覆工板本体のそれぞれは、隣接する前記覆工板本体の対向する前記本体凹凸部を互いに嵌合させることによって前記路面の長手方向及び幅方向で連結されているとともに、前記締結具を前記差込孔に差し込むことによって前記埋め戻し面に固定されているので、アスファルト合材等を使用することなく、周囲の路面と面一となる厚さの覆工板本体を用いることで掘削箇所の路面を仮復旧することができる。また、後に行われる本復旧では、アスファルト合材等を剥がす必要がなく、掘削箇所の埋め戻し面上に設置した覆工板本体を撤去するだけで済むため、本復旧舗装工事を迅速に行うことができ、工事期間を短縮できる。しかも、本発明の簡易覆工板は、何回も繰り返して使用することが可能であるため、産業廃棄物の量を減らしてエコ性能を向上させることができる。   As described above, the simple lining board according to the present invention is used when temporarily recovering an excavation site formed by excavating a road surface, and is installed on a backfill surface backfilled from the road surface to a predetermined depth. A plurality of lining plate bodies arranged side by side in the longitudinal direction and the width direction on the backfill surface, and insertion holes for inserting fasteners in the center of these lining plate bodies And a main body uneven portion is provided on each side of the lining plate main body, and each of the lining plate main bodies is opposed to the adjacent main concavo-convex portion of the lining plate main body. Are connected to each other in the longitudinal and width directions of the road surface, and fixed to the backfill surface by inserting the fastener into the insertion hole. Without using The road surface drilling location could be temporarily restored by using a lining plate body of the road surface and flush become thick circumference. In the subsequent restoration, it is not necessary to peel off the asphalt mixture, and it is only necessary to remove the main body of the lining plate installed on the backfill surface of the excavation site. The construction period can be shortened. And since the simple lining board of this invention can be used repeatedly many times, the quantity of industrial waste can be reduced and eco-performance can be improved.

さらに、本発明の簡易覆工板は、掘削箇所の埋め戻し面上に位置決めされた状態でしっかり固定されているので、通行する車両などによって所定の設置位置から移動することが起こらず、覆工板本体を介して掘削箇所の砂、砕石等の埋め戻し材を十分に押し固めることができ、後に行われる本復旧舗装工事を確実に行うことができる。したがって、本発明の簡易覆工板は、車両や人が多く通行する交通量の多い道路、歩道などに適用することが可能であるので、使用範囲が広くて汎用性に優れており、仮復旧工事に適した構造物を提供することができる。   Furthermore, since the simple lining board of the present invention is firmly fixed in a state where it is positioned on the backfill surface of the excavation site, it does not move from a predetermined installation position by a passing vehicle, etc. The back-filling material such as sand and crushed stone at the excavation site can be sufficiently pressed through the plate main body, and the subsequent restoration paving work to be performed later can be performed reliably. Therefore, since the simple lining board of the present invention can be applied to roads, sidewalks and the like with a lot of traffic through which many vehicles and people pass, it has a wide range of use and excellent versatility. A structure suitable for construction can be provided.

また、本発明において、前記路面の長手方向及び幅方向の少なくとも一方には、前記掘削箇所の開口寸法に対応して端部覆工板が配置され、該端部覆工板の側部には、端部凹凸部が設けられており、前記端部覆工板は、前記端部凹凸部を前記覆工板本体の前記本体凹凸部に嵌合させることによって前記覆工板本体に連結されているので、仮復旧する掘削箇所の開口寸法に応じて必要な数の端部覆工板を路面の長手方向や幅方向に配置することにより、種々の大きさに形成された掘削箇所の埋め戻し面の全体を簡易覆工板で覆うことが可能となり、仮復旧期間中において埋め戻し材の全体を確実に押し固めることができる。   Further, in the present invention, an end covering plate is disposed in at least one of the longitudinal direction and the width direction of the road surface corresponding to the opening size of the excavation site, and on the side portion of the end covering plate An end concavo-convex portion is provided, and the end lining plate is coupled to the lining plate main body by fitting the end concavo-convex portion to the main body concavo-convex portion of the covering plate main body. Therefore, by placing the required number of end lining plates in the longitudinal direction and width direction of the road surface according to the opening size of the excavation site to be temporarily restored, the excavation sites formed in various sizes are backfilled. The entire surface can be covered with a simple lining plate, and the entire backfill material can be reliably pressed during the temporary restoration period.

さらに、本発明において、前記覆工板本体及び前記端部覆工板の連結される側部間には、シール材が配設されているので、連結される覆工板本体及び端部覆工板の間に隙間を生じることがなくなり、人や車両が覆工板本体や端部覆工板の上を通過する際につまずいたり、異音を発生させたりすることなくスムーズに通行することができる。しかも、覆工板本体及び端部覆工板の間から雨水などが必要以上に掘削箇所の埋め戻し材中に流れ込むことを防止することができる。
また、本発明において、前記覆工板本体及び前記端部覆工板の周囲には、補修材が敷き詰められているので、覆工板本体及び端部覆工板を所定の位置により一層確実に保持でき、通行する車両などによって覆工板本体及び端部覆工板を所定の設置位置から移動するのをより防ぐことができる。
Furthermore, in the present invention, since the sealing material is disposed between the side portions to which the lining plate main body and the end portion lining plate are connected, the lining plate main body and the end portion lining to be connected are arranged. A gap is not generated between the plates, and a person or a vehicle can pass smoothly without tripping or generating abnormal noise when passing over the lining plate main body or the end lining plate. Moreover, it is possible to prevent rainwater or the like from flowing between the lining plate body and the end lining plate more than necessary into the backfill material at the excavation site.
Further, in the present invention, since the repair material is laid around the lining plate body and the end lining plate, the lining plate body and the end lining plate are more reliably positioned in a predetermined position. It can hold | maintain and can prevent moving a lining board main body and an edge part lining board from a predetermined installation position more by the vehicle etc. which pass.

本発明の実施形態に係る簡易覆工板を示す平面図である。It is a top view which shows the simple lining board which concerns on embodiment of this invention. 図1のA−A線断面図である。It is the sectional view on the AA line of FIG. 本発明の実施形態の簡易覆工板を構成する覆工板本体及び端部覆工板の側部にシール材を取付けた状態を示す側面図である。It is a side view which shows the state which attached the sealing material to the side part of the lining board main body and end part lining board which comprise the simple lining board of embodiment of this invention. 仮復旧時において、掘削坑の埋め戻し面上に本発明の実施形態の簡易覆工板を設置した状態を示す縦断面図である。It is a longitudinal cross-sectional view which shows the state which installed the simple lining board of embodiment of this invention on the backfilling surface of an excavation mine at the time of temporary restoration. 掘削した掘削坑に路面から所定の深さまで埋め戻し材を埋め込んだ状態を示す縦断面図である。It is a longitudinal cross-sectional view which shows the state which buried the backfill material from the road surface to the predetermined depth in the excavated mine. 本復旧時において、本発明の実施形態の簡易覆工板を取り除き、アスファルト合材を施した状態を示す縦断面図である。It is a longitudinal cross-sectional view which shows the state which removed the simple lining board of embodiment of this invention, and gave the asphalt compound material at the time of this restoration | restoration.

以下、本発明を図示の実施の形態に基づいて詳細に説明する。
図1〜図4は、本発明の実施の形態に係る簡易覆工板を示すものであり、図1は簡易覆工板の平面図、図2は図1のA−A線断面図、図3はシール材を取付けた端部覆工板の側面図、図4は掘削坑の埋め戻し面上に設置した簡易覆工板の断面図である。
Hereinafter, the present invention will be described in detail based on illustrated embodiments.
1 to 4 show a simple lining board according to an embodiment of the present invention, FIG. 1 is a plan view of the simple lining board, and FIG. 2 is a cross-sectional view taken along line AA in FIG. 3 is a side view of the end cover plate to which the sealing material is attached, and FIG. 4 is a cross-sectional view of the simple cover plate installed on the backfill surface of the excavation mine.

本実施形態の簡易覆工板1は、路面の地盤中を立杭状に掘削することにより形成される掘削箇所の掘削坑を仮復旧する際に用いられる構造物である。すなわち、上下水道管、ガス管、電気ケーブル等を新たに埋設する場合や、これら埋設した管、ケーブル等を保守点検及び維持管理する場合には、必要な深さまで路面を掘削して水道管などの埋設工事等が行われるが、埋設工事等の終了後は、形成された掘削坑が車両の路面走行や人の通行に支障を来たさないように、路面と面一となるような仮復旧舗装が施されている。本実施形態の仮復旧舗装では、掘削された路面の掘削坑内に所定量の埋め戻し材である砂、砕石等を投入して路面から所定の深さまで埋め戻し、これら砂、砕石等の埋め戻し面上に砂、砕石等を押し固める機能を有する簡易覆工板1を設置して路面と面一にする工事が行われている。そして後日、時間経過に伴って掘削坑に敷き詰められた砂、砕石等が簡易覆工板1を介して押し固められて安定すると、簡易覆工板1を撤去し、その後、アスファルト合材等を使用して掘削坑及び周辺箇所の本復旧舗装が行われるようになっている。   The simple lining board 1 of this embodiment is a structure used when temporarily recovering an excavation pit at an excavation site formed by excavating the inside of a road surface in a vertical pile shape. That is, when newly burying water and sewage pipes, gas pipes, electric cables, etc., or when maintaining and inspecting such buried pipes, cables, etc., excavate the road surface to the required depth, etc. However, after the completion of the burial work, etc., the temporary excavation mine should be flush with the road surface so that it will not hinder the road running of the vehicle or traffic of people. Restoration pavement is given. In the temporary restoration pavement of this embodiment, a predetermined amount of sand, crushed stone, or the like as backfill material is put into the excavated mine of the excavated road surface to backfill to a predetermined depth from the road surface, and backfill of these sand, crushed stone, etc. There is a construction in which a simple lining board 1 having a function of pressing sand, crushed stones, and the like is installed on the surface so as to be flush with the road surface. And later, when sand, crushed stones, etc. laid down in the excavation mine are pressed and stabilized through the simple lining plate 1 over time, the simple lining plate 1 is removed, and then the asphalt mixture, etc. It is used to perform the main restoration pavement of the excavation mine and surrounding areas.

このため、本実施形態の簡易覆工板1は、図1〜図4に示すように、路面2の地盤中に形成した掘削坑3の上部全体を覆うため、開口面積に対応する大きさに設定されており、掘削坑3内に投入することにより路面2から所定の深さまで埋め戻された埋め戻し材4の埋め戻し面4a上で、路面2の長手方向L及び幅方向Wに並べて配置される複数個の覆工板本体11及び端部覆工板21を備えている。本実施形態の仮復旧舗装では、覆工板本体11は長手方向Lに3個配置され、かつ幅方向Wに2個配置されており、端部覆工板21は路面2の長手方向L及び幅方向Wの片側のみに覆工板本体11の設置数と対応して配置されている。また、本実施形態の簡易覆工板1を構成する覆工板本体11及び端部覆工板21の厚さは、埋め戻し材4の埋め戻し面4a上に設置された状態で、路面2とほぼ面一となる大きさに形成されている。   For this reason, since the simple lining board 1 of this embodiment covers the whole upper part of the excavation mine 3 formed in the ground of the road surface 2, as shown in FIGS. 1-4, it is the magnitude | size corresponding to an opening area. It is set and arranged side by side in the longitudinal direction L and the width direction W of the road surface 2 on the backfill surface 4a of the backfill material 4 backfilled from the road surface 2 to a predetermined depth by being put into the excavation mine 3. A plurality of lining plate main bodies 11 and end lining plates 21 are provided. In the temporary restoration pavement of the present embodiment, three lining board main bodies 11 are arranged in the longitudinal direction L and two are arranged in the width direction W, and the end lining boards 21 are arranged in the longitudinal direction L of the road surface 2 and It arrange | positions corresponding to the installation number of the lining board main bodies 11 only in the one side of the width direction W. FIG. Moreover, the thickness of the lining board main body 11 and the edge part lining board 21 which comprise the simple lining board 1 of this embodiment is the road surface 2 in the state installed on the backfilling surface 4a of the backfilling material 4. FIG. It is formed in the size which becomes almost flush.

本実施形態の覆工板本体11は、一例として、30cm角や40cm角の正方形板を用いて形成されている。各覆工板本体11の中央部には、図1〜図4に示すように、アンカーボルト(締結具)12を差し込む差込孔13が厚み方向に貫通して設けられている。これら差込孔13は、アンカーボルト12の軸部及び頭部を収納することが可能な大きさと形状に形成されており、差し込まれたアンカーボルト12の頭部が覆工板本体11の上面から突出しないように構成されている。一方、アンカーボルト12の軸部は、覆工板本体11の厚さよりも長く形成されており、差込孔13に差し込まれたアンカーボルト12の軸部先端が覆工板本体11の下面から突出して埋め戻し材4の埋め戻し面4aと係合するように構成されている。
また、各覆工板本体11の側部には、複数の本体凹凸部14,15が路面2の長手方向L及び幅方向Wに沿って櫛歯状にそれぞれ形成されており、これら本体凹凸部14,15は、一定の大きさで交互に設けられている。しかも、本体凹凸部14,15は、設置位置に応じて、覆工板本体11のすべての側部に設けられ、あるいは覆工板本体11の4つの側部のうち、2つもしくは3つの側部に設けられている。なお、本体凹凸部14,15は、矩形状に限られずに波形でも良く、さらに、1個の湾曲形状の突起部や陥没部であっても良い。
The lining board main body 11 of this embodiment is formed using a 30 cm square or a 40 cm square square board as an example. As shown in FIGS. 1 to 4, an insertion hole 13 into which an anchor bolt (fastener) 12 is inserted is provided in the center portion of each lining plate main body 11 in the thickness direction. These insertion holes 13 are formed in a size and shape that can accommodate the shaft portion and the head portion of the anchor bolt 12, and the head portion of the inserted anchor bolt 12 extends from the upper surface of the lining plate main body 11. It is configured not to protrude. On the other hand, the shaft portion of the anchor bolt 12 is formed to be longer than the thickness of the cover plate main body 11, and the tip end of the shaft portion of the anchor bolt 12 inserted into the insertion hole 13 protrudes from the lower surface of the cover plate main body 11. The back-filling surface 4a of the back-filling material 4 is engaged.
In addition, a plurality of main body uneven portions 14 and 15 are formed in a comb-tooth shape along the longitudinal direction L and the width direction W of the road surface 2 on the side portions of the respective lining plate main bodies 11. 14 and 15 are alternately provided with a fixed size. Moreover, the main body uneven portions 14 and 15 are provided on all sides of the lining plate main body 11 according to the installation position, or two or three sides of the four side portions of the lining plate main body 11. Provided in the department. The main body uneven portions 14 and 15 are not limited to a rectangular shape, and may be a corrugated shape, or may be a single curved protrusion or depression.

したがって、覆工板本体11のそれぞれは、隣接する覆工板本体11の対向する本体凹凸部14,15を互いに嵌合させることによって路面2の長手方向L及び幅方向Wで連結されて相互に移動しないように並んで配置されているとともに、アンカーボルト12を差込孔13に差し込むことによって埋め戻し面4a上の所定位置で一体的に固定されている。   Therefore, each of the lining board main bodies 11 is connected to each other in the longitudinal direction L and the width direction W of the road surface 2 by fitting the opposing main body concavo-convex parts 14 and 15 of the adjacent lining board main bodies 11 to each other. They are arranged side by side so as not to move, and are fixed integrally at a predetermined position on the backfill surface 4 a by inserting the anchor bolts 12 into the insertion holes 13.

一方、本実施形態の端部覆工板21は、図1〜図4に示すように、掘削坑3の開口寸法に対応して、路面2の長手方向L及び幅方向Wの片側(図1中で下側及び右側)にそれぞれ配置されている。この端部覆工板21は、一例として、30×10cm(30×20cm)や40×10cm(40×20cm)の幅狭の長方形板を用いて形成され、覆工板本体11の長さに対応している。また、各端部覆工板21の片側側部には、複数の端部凹凸部22,23が路面2の長手方向L及び幅方向Wに沿って櫛歯状にそれぞれ形成されており、これら端部凹凸部22,23は、本体凹凸部14,15と同様の大きさと間隔で交互に設けられている。なお、端部凹凸部22,23は、本体凹凸部14,15と対応して矩形状に限られずに波形でも良く、さらに、1個の湾曲形状の突起部や陥没部であっても良い。   On the other hand, as shown in FIGS. 1 to 4, the end cover plate 21 of the present embodiment corresponds to the opening size of the excavation pit 3, and the one side in the longitudinal direction L and the width direction W of the road surface 2 (FIG. 1). In the lower side and the right side). As an example, the end lining plate 21 is formed using a narrow rectangular plate of 30 × 10 cm (30 × 20 cm) or 40 × 10 cm (40 × 20 cm), and the length of the lining plate main body 11 is set. It corresponds. Further, on one side of each end covering plate 21, a plurality of end uneven portions 22 and 23 are formed in a comb shape along the longitudinal direction L and the width direction W of the road surface 2, respectively. The end uneven portions 22 and 23 are alternately provided with the same size and interval as the main body uneven portions 14 and 15. Note that the end uneven portions 22 and 23 are not limited to a rectangular shape corresponding to the main body uneven portions 14 and 15, but may be a corrugated shape, and may be a single curved protrusion or depression.

したがって、端部覆工板21のそれぞれは、端部凹凸部22,23を隣接する覆工板本体11の対向する本体凹凸部14,15と互いに嵌合させることによって路面2の長手方向L及び幅方向Wで連結されて相互に移動しないように、端部覆工板21と並んで配置されているとともに、埋め戻し面4a上の所定位置で端部覆工板21と一体的に固定されている。   Therefore, each of the end lining plates 21 is fitted with the opposing main body concavo-convex portions 14 and 15 of the adjacent lining plate main body 11 by fitting the end concavo-convex portions 22 and 23 with each other in the longitudinal direction L of the road surface 2 and It is arranged side by side with the end cover plate 21 so as not to be connected to each other in the width direction W, and is fixed integrally with the end cover plate 21 at a predetermined position on the backfill surface 4a. ing.

本実施形態の簡易覆工板1を構成する覆工板本体11及び端部覆工板21の材質としては、繊維強化プラスチック(FRP)、塩化ビニル、ゴム等の合成樹脂、コンクリート、鋳物、ステンレス鋼などが挙げられ、適用する道路及び歩道の交通量、環境などによって選択することが可能である。   The material of the lining plate body 11 and the end lining plate 21 constituting the simple lining plate 1 of the present embodiment is synthetic resin such as fiber reinforced plastic (FRP), vinyl chloride, rubber, concrete, casting, stainless steel. Steel can be used, and it can be selected depending on the traffic volume and environment of the road and sidewalk to be applied.

また、本実施形態の簡易覆工板1において、覆工板本体11及び端部覆工板21の連結される側部間には、図1及び図2に示すように、弾力性を有するゴム材や合成樹脂材などで形成したシール材5が配設されており、このシール材5によって、連結する2つの覆工板本体11の側部間や、連結する覆工板本体11と端部覆工板21との側部間に隙間が生じないように構成されている。シール材5は、図3に示すように、覆工板本体11及び端部覆工板21の側部において、凹凸部14,15及び端部凹凸部22,23に沿って接着材などで取付けられている。   Moreover, in the simple lining board 1 of this embodiment, as shown in FIG.1 and FIG.2, the rubber | gum which has elasticity between the side parts to which the lining board main body 11 and the edge part covering board 21 are connected. A sealing material 5 formed of a material, a synthetic resin material, or the like is disposed, and by this sealing material 5, between the side portions of the two lining plate main bodies 11 to be connected, or the lining plate main body 11 to be connected and the end portions. It is comprised so that a clearance gap may not arise between side parts with the lining board 21. FIG. As shown in FIG. 3, the sealing material 5 is attached with an adhesive or the like along the uneven portions 14 and 15 and the end uneven portions 22 and 23 on the side portions of the covering plate body 11 and the end covering plate 21. It has been.

さらに、本実施形態の簡易覆工板1を構成する覆工板本体11及び端部覆工板21の周囲には、図1に示すように、常温合材アスファルト等の補修材6が敷き詰められている。この補修材6は、掘削坑3内の埋め戻し面4a上に設置した簡易覆工板1と掘削坑3内の内周壁との間に生じた隙間を埋め、覆工板本体11及び端部覆工板21を所定の位置に、より一層確実に保持するために使用されるものである。したがって、補修材6は、簡易覆工板1と掘削坑3内の内周壁との間に隙間が生じない場合、使用する必要がない。   Further, as shown in FIG. 1, a repair material 6 such as a room temperature composite asphalt is spread around the lining plate body 11 and the end lining plate 21 constituting the simple lining plate 1 of the present embodiment. ing. The repair material 6 fills a gap formed between the simple lining plate 1 installed on the backfill surface 4a in the excavation mine 3 and the inner peripheral wall in the excavation mine 3, and the lining plate main body 11 and the end portion It is used to hold the lining plate 21 in a predetermined position more reliably. Therefore, the repair material 6 does not need to be used when no gap is generated between the simple lining plate 1 and the inner peripheral wall in the excavation pit 3.

次に、本発明の実施形態に係る簡易覆工板1を用いて仮復旧する方法を説明する。まず、上下水道管、ガス管などを埋設したり、あるいは、既設の上下水道管、ガス管などを点検したりする場合、これら管の設置箇所の路面2の舗装部分を切断し、既設の舗装部分を剥ぎ取って、必要な深さまで地盤を掘削して掘削坑3を形成する。そして、この掘削坑3を利用して上下水道管、ガス管などの埋設工事を行い、あるいは、既設の上下水道管、ガス管などの点検作業を行う。
次いで、工事等の終了後に、掘削した掘削坑3の上方から砂、砕石等の埋め戻し材4を投入して、路面2から舗装部分の厚みを除いた深さまで埋め戻すとともに、転圧することにより埋め戻し面4aを平らにする(図5参照)。続いて、掘削坑3まで搬送した簡易覆工板1の複数の覆工板本体11及び端部覆工板21を埋め戻し面4a上の所定位置に設置しながら、シール材5を介して本体凹凸部14,15及び端部凹凸部22,23を互いに嵌合させることにより、隣接する覆工板本体11同士、及び覆工板本体11と端部覆工板21とを連結する。その後、アンカーボルト12を各覆工板本体11の差込孔12に差し込んで埋め戻し材4と係合させれば、簡易覆工板1は、掘削坑3の周囲の路面2と面一の状態で埋め戻し面4aに固定され、仮復旧舗装が完了することになる(図4参照)。この際、必要に応じて簡易覆工板1の覆工板本体11及び端部覆工板21の周囲に補修材6を施すことにより、掘削坑3の内周壁との隙間を埋めることが可能である。なお、使用する覆工板本体11及び端部覆工板21の厚みは、本復旧舗装工事の際に規定されている舗装部分の厚さに相当している。
Next, a method for temporarily recovering using the simple lining plate 1 according to the embodiment of the present invention will be described. First, when embedding water and sewage pipes, gas pipes, etc., or inspecting existing water and sewage pipes and gas pipes, cut the pavement part of the road surface 2 at the installation location of these pipes, The part is peeled off and the ground is excavated to a necessary depth to form the excavation pit 3. Then, the excavation pit 3 is used to embed water and sewage pipes and gas pipes, or to inspect existing water and sewage and gas pipes.
Next, after completion of the construction, etc., a backfill material 4 such as sand and crushed stone is introduced from above the excavated excavation mine 3 to backfill the road surface 2 to a depth excluding the thickness of the pavement and by rolling. The backfill surface 4a is flattened (see FIG. 5). Subsequently, the main body through the sealing material 5 while the plurality of lining board main bodies 11 and the end lining board 21 of the simple lining board 1 conveyed to the excavation mine 3 are installed at predetermined positions on the backfill surface 4a. By fitting the concavo-convex portions 14 and 15 and the end concavo-convex portions 22 and 23 to each other, the adjacent lining plate main bodies 11, and the lining plate main body 11 and the end lining plate 21 are connected. After that, if the anchor bolt 12 is inserted into the insertion hole 12 of each lining plate main body 11 and engaged with the backfill material 4, the simple lining plate 1 is flush with the road surface 2 around the excavation mine 3. In this state, it is fixed to the backfill surface 4a, and the temporary restoration pavement is completed (see FIG. 4). At this time, it is possible to fill a gap with the inner peripheral wall of the excavation pit 3 by applying the repair material 6 around the lining plate main body 11 and the end lining plate 21 of the simple lining plate 1 as necessary. It is. In addition, the thickness of the lining board main body 11 and the edge part lining board 21 to be used is equivalent to the thickness of the pavement part prescribed | regulated in this restoration pavement construction.

また、上述した仮復旧舗装後で所定期間が経過したときに、本復旧舗装を行う場合には、すべてのアンカーボルト12を埋め戻し材4及び覆工板本体11の差込孔12から抜き取り、覆工板本体11の本体凹凸部14,15及び端部覆工板21の端部凹凸部22,23の嵌合をそれぞれ外して相互の連結を解除し、簡易覆工板1を掘削坑3より撤去して埋め戻し材4の埋め戻し面4aを露出する。本復旧舗装までの間、掘削坑3の埋め戻し材4は、通行する車両や人の重量により簡易覆工板1を介して押し固められている。
次いで、掘削坑3内に位置する埋め戻し材4の埋め戻し面4a上や、必要ならば掘削坑3の周囲箇所にアスファルト合材7を施して仕上げ舗装をすれば、復旧舗装が完了することになる(図6参照)。
In addition, when the predetermined period has elapsed after the temporary restoration paving described above, when performing the actual restoration paving, all the anchor bolts 12 are extracted from the backfilling material 4 and the insertion holes 12 of the lining board main body 11, The concavo-convex portions 14 and 15 of the lining plate main body 11 and the end concavo-convex portions 22 and 23 of the end lining plate 21 are respectively disconnected to release the mutual connection, and the simple lining plate 1 is removed from the excavation pit 3. It removes more and the backfill surface 4a of the backfilling material 4 is exposed. Until the actual restoration pavement, the backfilling material 4 of the excavation mine 3 is pressed and compacted through the simple lining plate 1 by the weight of the vehicle or person passing by.
Next, if the asphalt composite material 7 is applied to the backfill surface 4a of the backfill material 4 located in the excavation mine 3 or if necessary, the asphalt mixture 7 is applied to the surrounding area of the excavation mine 3 to complete the restoration paving (See FIG. 6).

このように構成された本実施形態の簡易覆工板1を用いて仮復旧すれば、従来の仮復旧工法において必要なアスファルト合材等を使用することなく、掘削坑3の上部を周囲の路面2と面一にかつ迅速に仮復旧舗装を行ことができる。また、後に行われる本復旧では、アスファルト合材等を剥がす必要がなくなり、掘削坑3の埋め戻し面4a上に設置した覆工板本体11や端部覆工板21を撤去するだけで本復旧舗装工事を行うことができ、工事期間を大幅に短縮できる。しかも、本実施形態の簡易覆工板1は何回も再利用可能であり、施工現場の作業コストや部材コストを低減できるとともに、産業廃棄物の排出量を減らしてエコ性能を向上させることができる。   If temporary restoration is performed using the simple lining plate 1 of the present embodiment configured in this way, the upper surface of the excavation pit 3 is surrounded by a road surface without using asphalt mixture or the like necessary in the conventional temporary restoration method. Temporary restoration pavement can be performed flush with 2 and quickly. Further, in the actual restoration to be performed later, it is not necessary to peel off the asphalt mixture or the like, and the restoration can be performed only by removing the lining board main body 11 and the end lining board 21 installed on the backfill surface 4a of the excavation mine 3. Pavement work can be performed and the construction period can be greatly shortened. Moreover, the simple lining board 1 of the present embodiment can be reused many times, so that the work cost and the material cost at the construction site can be reduced, and the eco-performance can be improved by reducing the discharge amount of industrial waste. it can.

また、本実施形態の簡易覆工板1は、本体凹凸部14,15及び端部凹凸部22,23の嵌合及びアンカーボルト12の使用によって覆工板本体11と端部覆工板21とが掘削坑3の埋め戻し面4a上に位置決めされた状態で固定されているので、通行する車両などによって埋め戻し面4aの所定位置から移動することなく、覆工板本体11及び端部覆工板21を介して掘削坑3内の埋め戻し材4を十分に押し固めることができ、本復旧舗装工事を確実に行うことができるとともに、車両や人が多く通行する交通量の多い道路、歩道などに適用することができる。   In addition, the simplified lining board 1 of the present embodiment includes the lining board main body 11 and the end lining board 21 by fitting the main body concavo-convex parts 14 and 15 and the end concavo-convex parts 22 and 23 and using the anchor bolts 12. Is fixed in a state of being positioned on the backfill surface 4a of the excavation mine 3, so that the lining plate main body 11 and the end cover are not moved from a predetermined position of the backfill surface 4a by a passing vehicle or the like. The backfill material 4 in the excavation mine 3 can be sufficiently pressed through the plate 21 and the restoration paving work can be surely performed, and the roads and sidewalks with a large amount of traffic through which many vehicles and people pass. Etc.

以上、本発明の実施の形態につき述べたが、本発明は既述の実施の形態に限定されるものではなく、本発明の技術的思想に基づいて各種の変形及び変更が可能である。
例えば、既述の実施の形態の簡易覆工板1では、端部覆工板21が路面2の長手方向L及び幅方向Wに配置されているが、掘削坑3の開口寸法によっては、長手方向L及び幅方向Wのいずれか一方、あるいは両方に端部覆工板21が配置されるような構成を採用しても良い。また、覆工板本体11及び端部覆工板21の設置数、大きさ及び形状は、掘削坑3の開口面積や形状に対応して適宜選択することができる。さらに、適用する道路や歩道の交通量などによっては、覆工板本体11及び端部覆工板21の周囲に補修材6を設けなくとも良い。
While the embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments, and various modifications and changes can be made based on the technical idea of the present invention.
For example, in the simple lining board 1 of the above-described embodiment, the end lining board 21 is arranged in the longitudinal direction L and the width direction W of the road surface 2. You may employ | adopt the structure that the edge part covering board 21 is arrange | positioned in any one of the direction L and the width direction W, or both. Further, the number, size, and shape of the lining plate main body 11 and the end lining plate 21 can be appropriately selected according to the opening area and shape of the excavation pit 3. Furthermore, the repair material 6 may not be provided around the lining board main body 11 and the end lining board 21 depending on the road and sidewalk traffic to be applied.

1 簡易覆工板
2 路面
3 掘削坑
4 埋め戻し材
4a 埋め戻し面
5 シール材
6 補修材
11 覆工板本体
12 アンカーボルト(締結具)
13 差込孔
14,15 本体凹凸部
21 端部覆工板
22,23 端部凹凸部
DESCRIPTION OF SYMBOLS 1 Simple lining board 2 Road surface 3 Excavation pit 4 Backfilling material 4a Backfilling surface 5 Sealing material 6 Repair material 11 Backing board main body 12 Anchor bolt (fastener)
13 Insertion holes 14 and 15 Main body uneven portion 21 End cover plates 22 and 23 End uneven portion

Claims (4)

路面を掘削することにより形成される掘削箇所を仮復旧する際に用いられ、前記路面から所定の深さまで埋め戻した埋め戻し面上に設置される簡易覆工板であって、
前記埋め戻し面上で長手方向及び幅方向に並べて配置される複数の覆工板本体を備え、これら覆工板本体の中央部には、締結具を差し込む差込孔が設けられ、かつ、前記覆工板本体の側部には、本体凹凸部がそれぞれ設けられており、
前記覆工板本体のそれぞれは、隣接する前記覆工板本体の対向する前記本体凹凸部を互いに嵌合させることによって前記路面の長手方向及び幅方向で連結されているとともに、前記締結具を前記差込孔に差し込むことによって前記埋め戻し面に固定されていることを特徴とする簡易覆工板。
It is used when temporarily recovering excavation points formed by excavating a road surface, and is a simple lining board installed on a backfill surface backfilled to a predetermined depth from the road surface,
Provided with a plurality of lining plate main bodies arranged side by side in the longitudinal direction and the width direction on the backfill surface, the center portion of these lining plate main bodies is provided with an insertion hole for inserting a fastener, and On the side of the lining plate main body, there are provided main body uneven parts,
Each of the lining board main bodies is connected in the longitudinal direction and the width direction of the road surface by fitting the opposing main body concavo-convex parts of the adjacent lining board main bodies together, and the fasteners are A simple lining board characterized by being fixed to the backfill surface by being inserted into an insertion hole.
前記路面の長手方向及び幅方向の少なくとも一方には、前記掘削箇所の開口寸法に対応して端部覆工板が配置され、該端部覆工板の側部には、端部凹凸部が設けられており、前記端部覆工板は、前記端部凹凸部を前記覆工板本体の前記本体凹凸部に嵌合させることによって前記覆工板本体に連結されていることを特徴とする請求項1に記載の簡易覆工板。   At least one of the longitudinal direction and the width direction of the road surface is provided with an end covering plate corresponding to the opening size of the excavation site, and an end uneven portion is provided on a side portion of the end covering plate. The end lining plate is connected to the lining plate body by fitting the end concavo-convex portion to the body concavo-convex portion of the lining plate main body. The simple lining board according to claim 1. 前記覆工板本体及び前記端部覆工板の連結される側部間には、シール材が配設されていることを特徴とする請求項2に記載の簡易覆工板。   The simple lining board according to claim 2, wherein a sealing material is disposed between side parts to which the lining board main body and the end part lining board are connected. 前記覆工板本体及び前記端部覆工板の周囲には、補修材が敷き詰められていることを特徴とする請求項2または3に記載の簡易覆工板。
The simple lining board according to claim 2 or 3, wherein a repair material is spread around the lining board main body and the end lining board.
JP2012023918A 2012-02-07 2012-02-07 Simple lining board Active JP5514846B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012023918A JP5514846B2 (en) 2012-02-07 2012-02-07 Simple lining board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012023918A JP5514846B2 (en) 2012-02-07 2012-02-07 Simple lining board

Publications (2)

Publication Number Publication Date
JP2013159998A JP2013159998A (en) 2013-08-19
JP5514846B2 true JP5514846B2 (en) 2014-06-04

Family

ID=49172496

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012023918A Active JP5514846B2 (en) 2012-02-07 2012-02-07 Simple lining board

Country Status (1)

Country Link
JP (1) JP5514846B2 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672091A (en) * 2016-01-27 2016-06-15 吕爱萍 Automobile road combination emergency blanket for ice and snow field
CN105672087A (en) * 2016-01-27 2016-06-15 林建凯 Airplane snowfield takeoff and landing abrasion-resistant blanket
CN105672093A (en) * 2016-01-27 2016-06-15 吕爱萍 Snowmobile road wear-resisting emergency blanket
CN105672088A (en) * 2016-01-27 2016-06-15 吕爱萍 Automobile road combination abrasion-resistant emergency layered blanket on ice and snow field
CN105672089A (en) * 2016-01-27 2016-06-15 林建凯 Airplane snowfield takeoff and landing abrasion-resistant layered blanket
CN105672081A (en) * 2016-01-27 2016-06-15 吕爱萍 Combination anti-skid emergency layered blanket for automobile roads in ice and snow field
CN105672083A (en) * 2016-01-27 2016-06-15 陈小燕 Airplane snowfield takeoff and landing blanket
KR20180056217A (en) * 2016-11-18 2018-05-28 황병호 Spherical bridge bearing
CN115029980A (en) * 2022-06-20 2022-09-09 交通运输部公路科学研究所 Road panel splicing assembly and temporary road system
CN115142314A (en) * 2022-06-28 2022-10-04 中国五冶集团有限公司 Turnover splicing type construction access road and construction process

Also Published As

Publication number Publication date
JP2013159998A (en) 2013-08-19

Similar Documents

Publication Publication Date Title
JP5514846B2 (en) Simple lining board
JP2012036720A (en) Open-cut excavation structure using lining panel, and open-cut excavation construction method
JPWO2010073538A1 (en) Steel sheet pile wall and its construction method
JP3893056B2 (en) Construction method of underground structure
KR20110070188A (en) Construction method for underground watertight wall
KR200443038Y1 (en) A removal type earth anchor
KR100362615B1 (en) A Repairing Method of Underground Voids of Approach Slab in Abutment Constructure
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
JP4537228B2 (en) Shallow buried method using fluidized soil
JP2007107316A (en) Method of temporarily recovering pavement surface in burying work of underground buried object
JP3856791B2 (en) How to lay an overhanging sidewalk
CN112282022A (en) Method for quickly constructing rain sewage inspection well on existing road
JP4761052B2 (en) Precast box culvert excavation method without margin
KR101685114B1 (en) Underground diaphragm wall using embedded plates and coupler and contructing method thereof
JP2006322284A (en) Backfilling material such as plasticizing processing soil and grade separated crossing construction method using the backfilling material
KR101605012B1 (en) Retaining wall construction method using backward tension
JP6871344B1 (en) Tunnel repair method and repair equipment for existing tunnels
JPH07300845A (en) Preventive method against liquefaction of underground linear structure
JP2006057406A (en) Rubber mat for temporary recovery
KR20050029332A (en) Basic bottom permanent drainage structure using trench and drainage member and it's construction method
JP3352951B2 (en) Installation method of invert and underground drainage in mountain tunnel
JP4182004B2 (en) Stripping prevention member, tunnel lining prevention structure, and tunnel lining construction method
JP4319122B2 (en) Branch and junction structure of branching tunnel and its construction method
JP4384148B2 (en) Lamp installation method and lamp installation structure
JP3786600B2 (en) How to build a culvert

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130628

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20130628

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130708

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140218

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140228

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140331

R150 Certificate of patent or registration of utility model

Ref document number: 5514846

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250