JP4537228B2 - Shallow buried method using fluidized soil - Google Patents

Shallow buried method using fluidized soil Download PDF

Info

Publication number
JP4537228B2
JP4537228B2 JP2005057741A JP2005057741A JP4537228B2 JP 4537228 B2 JP4537228 B2 JP 4537228B2 JP 2005057741 A JP2005057741 A JP 2005057741A JP 2005057741 A JP2005057741 A JP 2005057741A JP 4537228 B2 JP4537228 B2 JP 4537228B2
Authority
JP
Japan
Prior art keywords
buried pipe
buoyancy
pipe
soil
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005057741A
Other languages
Japanese (ja)
Other versions
JP2006241791A (en
Inventor
達也 三ツ井
知之 安田
常太郎 岩淵
Original Assignee
徳倉建設株式会社
常太郎 岩淵
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 徳倉建設株式会社, 常太郎 岩淵 filed Critical 徳倉建設株式会社
Priority to JP2005057741A priority Critical patent/JP4537228B2/en
Publication of JP2006241791A publication Critical patent/JP2006241791A/en
Application granted granted Critical
Publication of JP4537228B2 publication Critical patent/JP4537228B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Description

本発明は、流動化処理土による浅層埋設工法に関する。 The present invention relates to a shallow burial method using fluidized soil .

従来の流動化処理土・処理土等の充填材による浅層埋設工法は、埋設管の施工完了後に、地下水位等による浮力(浮力とする)を防止するために、浮力防止材を設置する。しかし、この従来工法では、施工後の浮力を上部に充填した(打設した)土かぶりで抑えていたため、埋設管の設置する位置(設置とする)が深いデメリットであった。上記に鑑み本発明は、この従来工法のデメリットを解決し、簡易的に浅層に埋設管を設置することができる工法を提供する。即ち、土中に打設した対の土留め壁の下部に板材を固定し、この板材に埋設管を設置し、また当該板材に浮力防止材を定着し、この板材全体で流動化処理土の重量を受け止め、この浮力防止材で埋設管を固定するとともに、この浮力防止材及び/又は板材・対の土留め壁と、この土留め壁にかかる土圧等で埋設管にかかる浮力に対抗可能とすることを意図する。   In the conventional underground burying method using a filler such as fluidized soil and treated soil, a buoyancy prevention material is installed to prevent buoyancy (buoyancy) due to the groundwater level after the construction of the buried pipe. However, in this conventional construction method, the buoyancy after construction was suppressed by a soil cover filled (placed) in the upper part, so the position (installed) of the buried pipe was a serious demerit. In view of the above, the present invention solves the disadvantages of this conventional construction method and provides a construction method capable of easily installing a buried pipe in a shallow layer. That is, a plate material is fixed to the lower part of a pair of retaining walls placed in the soil, a buried pipe is installed on the plate material, and a buoyancy prevention material is fixed on the plate material. Responds to the weight and fixes the buried pipe with this buoyancy prevention material, and can counter the buoyancy applied to the buried pipe with this buoyancy prevention material and / or plate / pair retaining wall and earth pressure on this retaining wall Is intended.

この本発明と関連がある先行文献を挙げると、次の文献(1)〜文献(3)がある。以下、その概要を説明する。   Prior art documents related to the present invention include the following documents (1) to (3). The outline will be described below.

文献(1)は、特開平6−249365号の「管路の浮上防止及び管路勾配設定工法」である。その内容は、近時、重量の重い埋設管(埋設用管材)、即ち、ダクタイル管に替り、比重の小さな軽量のFRP管、FRPM管が使用されてきたが、この種のFRP管、FRPM管は、軽量の利点を有する反面、単位長さ当たりの容積に比し自重が小さいので、管埋戻し時に、流動化処理土内での浮力で浮上してしまうという問題があった。この問題点を解決するために、当該文献(1)の発明は、管路を掘削した後、管路に打設した矢板に、予め管路勾配を設定して管路固定具を固定する工程と、この管路固定具上に管を敷設する工程と、この敷設された管の上方から鋏み管浮上防止具をこの管路固定具に固定し、この管を鋏み込み固定する工程と、流動化処理土を管路に投入し管を埋設する工程とからなる構成であって、予め管路勾配を設定して固定された管路固定具により、正確な管路勾配で管が管路に敷設される。またこの管路固定具に固定された管浮上防止具により、管の浮上が防止されること等の特徴がある。   Document (1) is “A method for preventing pipe levitation and setting a pipe slope” disclosed in JP-A-6-249365. Recently, instead of heavy buried pipes (embedded pipe materials), that is, ductile pipes, lightweight FRP pipes and FRPM pipes with small specific gravity have been used. This kind of FRP pipes and FRPM pipes have been used. Although it has the advantage of light weight, its own weight is smaller than the volume per unit length, so that there is a problem that it floats due to buoyancy in the fluidized soil during pipe backfilling. In order to solve this problem, the invention of the document (1) includes a step of fixing a pipe fixture by setting a pipe gradient in advance on a sheet pile placed in the pipe after excavating the pipe. And a step of laying a pipe on the pipe line fixing tool, a step of fixing a stagnation pipe levitation prevention tool to the pipe line fixing tool from above the laid pipe, a step of swallowing and fixing the pipe, and a flow The process comprises the step of introducing the liquefied soil into the pipe and burying the pipe, and the pipe is fixed to the pipe with an accurate pipe gradient by a pipe fixture that is set and fixed in advance. Laid. In addition, there is a feature that the pipe floating is prevented by the pipe floating prevention tool fixed to the pipe line fixing tool.

文献(2)は、特開平7−317959号の「管埋設工法」である。その内容は、管基床部上に敷設した管の周囲に流動化処理土を投入して管を埋設する流動化処理土による埋設工法である。しかし、この工法は、大量の流動化処理土が必要であり、大量の流動化処理土を作成するプラントも大型のものが必要となり、コスト高となるという問題があった。この問題点を解決するために、当該文献(2)の発明は、予め打設した管基床部上に管を敷設した後、管の周囲に砕石等の塊状物を投入し、塊状物相互間に連続した間隙を生じさせた後、この塊状物相互間の連続した間隙に流動化処理土を投入する構成であって、注入管から流動化処理土を投入しても管が浮上することはなく、注入管から流動化処理土の投入が円滑に行われること、また流動化処理土の使用量が少なくなること等の特徴がある。   Document (2) is a “pipe embedding method” disclosed in Japanese Patent Laid-Open No. 7-317959. The contents are a burying method using fluidized soil in which fluidized soil is introduced around a pipe laid on a pipe base floor to embed the pipe. However, this construction method requires a large amount of fluidized soil, and requires a large plant for producing a large amount of fluidized soil, resulting in high costs. In order to solve this problem, in the invention of the reference (2), after laying a pipe on a previously placed pipe base floor, a lump such as crushed stone is introduced around the pipe, After creating a continuous gap between them, the fluidized soil is introduced into the continuous gap between the blocks, and the pipe floats even if the fluidized soil is introduced from the injection pipe. However, the fluidized soil is smoothly introduced from the injection pipe, and the amount of the fluidized soil used is reduced.

文献(3)は、特開2004−125100の「管埋設工法」である。その内容は、従来の流動化処理土による埋設工法では、掘削溝を埋設する管の直径に対して少なくとも左右に30cm程度の余裕を持たせて掘削するので、掘削する土砂の量(残土の処分量)が大量になるとともに、埋戻し材料も大量に必要になること、また管と掘削溝の壁面との距離が30cm程度の余裕がある場合、管の周辺部に打設した流動化処理土が固化するまでに2〜4時間と時間がかかり、土砂を転圧するまで待機する必要があり、施工時間が長くなること等の問題があった。この問題点を解決するために、当該文献(3)の発明は、開削工法により地表面下に管を埋設する管埋設工法において、掘削溝を埋設する管の直径に対して左右に最大で10cmの余裕を持たせた極小幅で掘削した後、この掘削溝に管を配設し、この管の直径の1/2を越えない位置まで流動化処理土を充填し、この流動化処理土の上部に直ちに土砂を埋戻して転圧する構成であって、開削工法により地中に管を埋設するときの掘削する土砂量を低減できるとともに、施工時間を大幅に短縮できること、又は埋戻し後の地表面の沈下を確実に防止できること等の特徴がある。   Document (3) is a “pipe embedding method” disclosed in Japanese Patent Application Laid-Open No. 2004-125100. The contents of the conventional method of embedding with fluidized soil are excavated with a margin of about 30 cm at least to the left and right of the diameter of the pipe in which the excavation groove is embedded, so the amount of soil to be excavated (disposal of residual soil) If the amount of backfill material is large, and there is a margin of about 30 cm between the pipe and the wall of the excavation groove, the fluidized soil placed in the periphery of the pipe It took 2 to 4 hours to solidify, and it was necessary to wait until the earth and sand were compacted, resulting in problems such as a long construction time. In order to solve this problem, the invention of the document (3) is a pipe burying method in which a pipe is buried under the ground surface by an open-cut method, and a maximum of 10 cm to the left and right with respect to the diameter of the pipe burying the excavation groove After excavating with a minimum width with sufficient margin, a pipe is arranged in the excavation groove, and fluidized soil is filled to a position not exceeding 1/2 of the diameter of the tube. It is configured to immediately backfill and roll the earth and sand at the upper part, and it can reduce the amount of earth and sand to be excavated when pipes are buried in the ground by the open-cut method, and can significantly reduce the construction time, or the land after backfilling There are features such as the ability to reliably prevent surface settlement.

特開平6−249365号JP-A-6-249365 特開平7−317959号JP 7-317959 A 特開2004−125100JP 2004-125100 A

文献(1)は、矢板に管路勾配を設定して管路固定具を固定し、この管路固定具及び/又は鋏み管浮上防止具で管を固定し、流動化処理土を管路に投入し管を埋設する構成である。従って、小径の管の場合には適する反面、大径の管の場合には、不都合と考えられる。また板材の代替として管基床部を打設する従来の工法であり、現場作業の複雑化を招来し、また基材の提供と、その打設作業に手間を要する等の問題点が考えられる。また地盤によっては、その施工に困難性が考えられる。   In literature (1), a pipe slope is set on a sheet pile to fix a pipe fixing tool, the pipe is fixed with this pipe fixing tool and / or a stagnation pipe anti-floating tool, and the fluidized soil is used as the pipe. This is a configuration in which the charging pipe is buried. Therefore, it is suitable for a small-diameter pipe, but is inconvenient for a large-diameter pipe. In addition, it is a conventional method of placing the pipe base floor as an alternative to the plate material, which leads to complicated on-site work, and problems such as the provision of the base material and the time required for the placing work are considered. . Depending on the ground, it may be difficult to construct.

また文献(2)は、管基床部上に管を敷設し、砕石等の塊状物を投入し、塊状物相互間に連続して形成された間隙に流動化処理土を投入する構成である。従って、砕石等の塊状物を投入という作業が必要となり、現場作業の複雑化を招来し、また塊状物の提供と、その投入作業に手間を要する等の問題点が考えられる。また地盤よっては、その施工に困難性が考えられる。さらに流動化処理土(廃棄物処理)の拡充を意図する業界の流れに適しないことが考えられる。   Reference (2) is a configuration in which a pipe is laid on a pipe base floor, lump such as crushed stone is thrown in, and fluidized soil is thrown into a gap formed continuously between the lump. . Therefore, it is necessary to perform a lump work such as crushed stone, which leads to a complicated on-site work, and there are problems such as providing a lump object and requiring labor for the lapping work. Depending on the ground, it may be difficult to construct. Furthermore, it is considered that it is not suitable for the industry flow intended to expand fluidized soil (waste treatment).

さらに文献(3)は、開削工法により掘削溝を埋設する管の直径に対して左右に最大で10cmの余裕を持たせた極小幅で掘削し、この掘削溝に管を配設し、この管の直径の1/2を越えない位置まで流動化処理土を充填し後、土砂を埋戻して転圧する構成である。従って、ガス管等の如く、小径の管の場合には適する反面、大径の管の場合には、不都合と考えられる。またこの工法は、開削工法で穿孔した布堀部の両端に土のうを積み上げる構成であるので、小径の管を浅い土中(地中)に埋設するには適するが、大径の管を所定の土中に埋設するには問題がある。また板材、管基床部に浮上防止材で、地下水位及び/又は流動化処理土の充填等(地下水位等)で発生する浮力を抑制する構成でないので、前述と同様に小径の管を浅い土中に埋設する工事に限定されるものと考えられる。   Furthermore, the document (3) is excavated with a minimum width of 10 cm at the left and right with respect to the diameter of the pipe in which the excavation groove is embedded by the open-cut method, and a pipe is disposed in the excavation groove. After the fluidized soil is filled to a position that does not exceed 1/2 of the diameter, the soil is backfilled and rolled. Therefore, it is suitable for a small diameter pipe such as a gas pipe, but it is considered inconvenient for a large diameter pipe. In addition, this construction method has a structure in which sandbags are piled up at both ends of the cloth moat drilled by the open-cut method, so it is suitable for embedding small-diameter pipes in shallow soil (underground). There is a problem in burying inside. In addition, it is not a structure that suppresses the buoyancy generated by the groundwater level and / or fluidized soil filling (groundwater level, etc.) by using the antifloating material on the plate and pipe base floor, so that the small-diameter pipe is shallow as described above. It is thought that it is limited to construction that is buried in the soil.

請求項1の発明は、流動化処理土を利用した浅層埋設管の埋戻工法を提案することで、板材に固定した浮力防止材により埋設管と周辺の原料土(建設発生土)と固化材、水を混合した流動化処理土及び/又は地中の土砂との一体が図れ、埋設管に対する地下水位等で発生する浮力による持ち上がりを防止することを意図する。   The invention of claim 1 proposes a method for backfilling a shallow buried pipe using fluidized soil, so that the buried pipe and surrounding raw material soil (construction generated soil) are solidified by a buoyancy prevention material fixed to the plate. It is intended to be integrated with fluidized soil mixed with wood and water, and / or soil in the ground, and to prevent lifting due to buoyancy generated at the groundwater level with respect to the buried pipe.

また請求項1の発明では、次のようなことを達成することを意図する。(1) 建設発生土の有効利用が図れる。(2) 掘削及び/又は埋戻断面の縮小を図る。(3) 土留め壁(矢板等の土留め材)の長さが短くなる。(4) 施工完了後、地下水位等による浮力を防止するための浮力防止材を板材に設置する。(5) 管設置位置が深い従来工法に替り、簡易的に浅層に埋設管を設置する。(6) 埋設管下部に設置した板材に浮力防止材を定着させ、土の重量を板材全体で受け止め、浮力防止材にかかる浮力を抑制する。   The invention of claim 1 is intended to achieve the following. (1) Effective use of construction waste soil. (2) To reduce excavation and / or backfill sections. (3) The length of the earth retaining wall (earth retaining material such as a sheet pile) is shortened. (4) After the completion of construction, buoyancy prevention materials to prevent buoyancy due to groundwater level etc. will be installed on the plate material. (5) Instead of the conventional method with a deep pipe installation position, a buried pipe is simply installed in the shallow layer. (6) The buoyancy prevention material is fixed to the plate material installed at the lower part of the buried pipe, and the weight of the soil is received by the whole plate material to suppress the buoyancy applied to the buoyancy prevention material.

この請求項1では、次の工程でなる流動化処理土による浅層埋設工法であって、
第一の工程は、埋設対象地盤を掘削し壁を施工し、少なくとも埋設管両側面に200〜400mm程度の幅の施工スペースを確保する。
第二の工程は、前記壁の下方に埋設管据付の基礎となり得る蛇篭を設置する。
第三の工程は、この埋設管の略上部の1/2を捲装し、この埋設管にかかる地下水位等で発生する浮力を抑制する対の浮力防止材の下端を、この蛇篭に固定する。
第四の工程は、前記埋設管据付の基礎となり得る埋設管支持部材を、蛇篭の上に設置する。
第五の工程は、この蛇篭及び/又は埋設管支持部材に、埋設管を設置し、この埋設管と前記施工スペースとの間に流動化処理土の充填材を充填する充填スペースを形成する。
第六の工程は、この埋設管の略上部の1/2を捲装した前記対の浮力防止材で、この埋設管にかかる地下水位等で発生する浮力を抑制するとともに、この対の浮力防止材を利用して浮力を蛇篭に伝達する。
第七の工程は、充填材を、前記充填スペースに一気に充填し、現場発生土砂の埋戻しをする。
In this claim 1, it is a shallow layer embedding method using fluidized soil in the following steps,
In the first step, the ground to be buried is excavated and walls are constructed, and a construction space having a width of about 200 to 400 mm is secured at least on both sides of the buried pipe.
A 2nd process installs the gabion which can become a foundation of an underground pipe installation under the said wall.
In the third step, half of the upper part of the buried pipe is fitted, and the lower ends of the pair of buoyancy prevention materials for suppressing the buoyancy generated at the groundwater level applied to the buried pipe are fixed to the gabion . .
In the fourth step, a buried pipe support member that can serve as a foundation for the buried pipe installation is installed on the gabion .
In the fifth step, a buried pipe is installed in the gabion and / or buried pipe support member, and a filling space for filling the fluidized soil filler is formed between the buried pipe and the construction space.
The sixth step is a pair of buoyancy prevention materials equipped with approximately half of the upper part of the buried pipe, and suppresses the buoyancy generated at the groundwater level, etc. applied to the buried pipe, and prevents this pair of buoyancy. Using material, buoyancy is transmitted to gabion .
In the seventh step, the filling material is filled into the filling space at once, and the on-site generated soil is backfilled.

請求項2の発明は、請求項1と同じ意図であるが、より施工の簡易化、低コスト化と、工期の短縮化等を意図し、埋設管支持部材の付設を省略する。 The invention of claim 2 has the same intention as that of claim 1, but intends to simplify construction, reduce costs, shorten the construction period, and the like, and omits the installation of the buried pipe support member.

この請求項2では、次の工程でなる流動化処理土による浅層埋設工法であって、
第一の工程は、埋設対象地盤を掘削し壁を施工し、少なくとも埋設管両側面に200〜400mm程度の幅の施工スペースを確保する。
第二の工程は、前記壁の下方に埋設管据付の基礎となり得る蛇篭を設置する。
第三の工程は、この埋設管の略上部の1/2を捲装し、この埋設管にかかる地下水位等で発生する浮力を抑制する対の浮力防止材の下端を、この蛇篭に固定する。
第四の工程は、この蛇篭に、埋設管を設置し、この埋設管と前記施工スペースとの間に流動化処理土の充填材を充填する充填スペースを形成する。
第五の工程は、この埋設管の略上部の1/2を捲装した前記対の浮力防止材で、この埋設管にかかる地下水位等で発生する浮力を抑制するとともに、この対の浮力防止材を利用して浮力を蛇篭に伝達する。
第六の工程は、充填材を、前記充填スペースに一気に充填し、現場発生土砂の埋戻しをする。
In this claim 2, it is a shallow layer burying construction method by fluidized soil in the following steps,
In the first step, the ground to be buried is excavated and walls are constructed, and a construction space having a width of about 200 to 400 mm is secured at least on both sides of the buried pipe.
A 2nd process installs the gabion which can become a foundation of an underground pipe installation under the said wall.
In the third step, half of the upper part of the buried pipe is fitted, and the lower ends of the pair of buoyancy prevention materials for suppressing the buoyancy generated at the groundwater level applied to the buried pipe are fixed to the gabion . .
In the fourth step, a buried pipe is installed in the gabion , and a filling space for filling the fluidized soil filler is formed between the buried pipe and the construction space.
The fifth step is the pair of buoyancy prevention materials equipped with substantially the upper half of the buried pipe, and suppresses the buoyancy generated at the groundwater level applied to the buried pipe and prevents the buoyancy of the pair. Using material, buoyancy is transmitted to gabion .
In the sixth step, the filling material is filled into the filling space at once, and the on-site generated soil is backfilled.

請求項3の発明は、請求項1又は請求項2の目的を達成すること、この目的を達成するに最適な掘削周辺地盤への影響の軽減を意図して対の土留め壁を設置する浅層埋設工法を提供することを意図する。 The invention of claim 3 is a shallow method in which a pair of retaining walls is installed in order to achieve the object of claim 1 or claim 2 and to reduce the influence on the ground around the excavation optimum for achieving the object. It is intended to provide a layer embedding method.

請求項3では、請求項1又は請求項2に記載の埋設対象地盤を掘削するに際し、この掘削周辺地盤への影響の軽減を意図して対の土留め壁を設置した後に行う構成とした流動化処理土による浅層埋設工法である。 In claim 3, when excavating the ground to be buried according to claim 1 or claim 2, the flow is performed after installing a pair of retaining walls in order to reduce the influence on the ground around the excavation. It is a shallow burial method using chlorinated soil .

請求項4の発明は、請求項1又は請求項2の目的を達成すること、この目的を達成するに最適な対の浮力防止材の連結(結合)手段を提供することを意図する。 The invention of claim 4 is intended to achieve the object of claim 1 or claim 2 and to provide means for connecting (coupling) pairs of buoyancy prevention materials optimal for achieving the object.

この請求項4では、請求項1又は請求項2に記載の対の浮力防止材の上部端部を、ターンバックル、溶接、面ファスナー、接着等の物理的な手段で連結する構成とした流動化処理土による浅層埋設工法である。 In this fourth aspect, fluidization in which the upper ends of the pair of buoyancy preventive members according to the first or second aspect are connected by physical means such as a turnbuckle, welding, hook-and-loop fastener, or adhesion . It is a shallow burial method using treated soil .

請求項5の発明は、請求項1又は請求項2の目的を達成すること、この目的を達成するに最適な対の土留め壁を提供することを意図する。 The invention of claim 5 is intended to achieve the object of claim 1 or claim 2 and to provide an optimum pair of retaining walls for achieving this object.

この請求項5では、請求項1又は請求項2に記載の土留め壁を、建屋等の構造物、道路、鉄道等の公共構造物への影響を回避するために、安息角度を確保して設置する構成とした流動化処理土による浅層埋設工法である。 In this claim 5, the retentive wall according to claim 1 or claim 2 is secured with a repose angle in order to avoid the influence on structures such as buildings, public structures such as roads and railways. This is a shallow burial method using fluidized soil .

請求項6の発明は、請求項1又は請求項2の目的を達成すること、この目的を達成するに最適な埋設管の構造を提供することを意図する。 The invention of claim 6 is intended to achieve the object of claim 1 or claim 2 and to provide an optimum buried pipe structure for achieving the object.

この請求項6では、請求項1又は請求項2に記載の埋設管に、重量物を内蔵する構成とした流動化処理土による浅層埋設工法である。 The sixth aspect of the present invention is a shallow-layer embedding method using fluidized soil in which a heavy object is built in the buried pipe according to claim 1 or claim 2 .

請求項7の発明は、請求項1又は請求項2の目的を達成すること、この目的を達成するに最適な板材の構造を提供することを意図する。 The invention of claim 7 is intended to achieve the object of claim 1 or claim 2 and to provide an optimal plate structure for achieving the object.

この請求項7では、請求項1又は請求項2に記載の蛇篭を、壁間に隙間なく設置する構成とした流動化処理土による浅層埋設工法である。 The seventh aspect is a shallow burial method using fluidized soil in which the gabions according to the first or second aspect are installed without a gap between the walls.

請求項1の発明は、次の工程でなる流動化処理土による浅層埋設工法であって、
第一の工程は、埋設対象地盤を掘削し壁を施工し、少なくとも埋設管両側面に200〜400mm程度の幅の施工スペースを確保する。
第二の工程は、前記壁の下方に埋設管据付の基礎となり得る蛇篭を設置する。
第三の工程は、この埋設管の略上部の1/2を捲装し、この埋設管にかかる地下水位等で発生する浮力を抑制する対の浮力防止材の下端を、この蛇篭に固定する。
第四の工程は、前記埋設管据付の基礎となり得る埋設管支持部材を、蛇篭の上に設置する。
第五の工程は、この蛇篭及び/又は埋設管支持部材に、埋設管を設置し、この埋設管と前記施工スペースとの間に流動化処理土の充填材を充填する充填スペースを形成する。
第六の工程は、この埋設管の略上部の1/2を捲装した前記対の浮力防止材で、この埋設管にかかる地下水位等で発生する浮力を抑制するとともに、この対の浮力防止材を利用して浮力を蛇篭に伝達する。
第七の工程は、充填材を、前記充填スペースに一気に充填し、現場発生土砂の埋戻しをする。
The invention of claim 1 is a shallow layer embedding method using fluidized soil in the following process,
In the first step, the ground to be buried is excavated and walls are constructed, and a construction space having a width of about 200 to 400 mm is secured at least on both sides of the buried pipe.
A 2nd process installs the gabion which can become a foundation of an underground pipe installation under the said wall.
In the third step, half of the upper part of the buried pipe is fitted, and the lower ends of the pair of buoyancy prevention materials for suppressing the buoyancy generated at the groundwater level applied to the buried pipe are fixed to the gabion . .
In the fourth step, a buried pipe support member that can serve as a foundation for the buried pipe installation is installed on the gabion .
In the fifth step, a buried pipe is installed in the gabion and / or buried pipe support member, and a filling space for filling the fluidized soil filler is formed between the buried pipe and the construction space.
The sixth step is a pair of buoyancy prevention materials equipped with approximately half of the upper part of the buried pipe, and suppresses the buoyancy generated at the groundwater level, etc. applied to the buried pipe, and prevents this pair of buoyancy. Using material, buoyancy is transmitted to gabion .
In the seventh step, the filling material is filled into the filling space at once, and the on-site generated soil is backfilled.

従って、請求項1は、流動化処理土を利用した浅層埋設管の埋戻工法を提案することで、板材に固定した浮力防止材により埋設管と周辺の原料土(建設発生土)と固化材、水を混合した流動化処理土及び/又は地中の土砂との一体が図れ、埋設管に対する地下水位等で発生する浮力による持ち上がりを防止できる特徴がある。   Therefore, claim 1 proposes a method for backfilling a shallow buried pipe using fluidized soil, and solidifies the buried pipe and surrounding raw soil (construction generated soil) with a buoyancy prevention material fixed to the plate. It can be integrated with fluidized soil mixed with wood and water and / or soil in the ground, and can be prevented from lifting due to buoyancy generated at the groundwater level with respect to the buried pipe.

また請求項1の発明では、次のような内容を達成できる特徴がある。(1) 建設発生土の有効利用が図れる。(2) 掘削及び/又は埋戻断面の縮小が図れる。(3) 土留め壁(矢板等の土留め材)の長さが短くできる。(4) 施工完了後、地下水位等による浮力を防止するための浮力防止材を板材に設置できる。(5) 管設置位置が深い従来工法に替り、簡易的に浅層に埋設管を設置することができる。(6) 埋設管下部に設置した板材に浮力防止材を定着させ、土の重量を板材全体で受け止め、浮力防止材にかかる浮力を抑制できる。   Further, the invention of claim 1 is characterized in that the following contents can be achieved. (1) Effective use of construction waste soil. (2) Excavation and / or backfilling cross section can be reduced. (3) The length of the earth retaining wall (earth retaining material such as a sheet pile) can be shortened. (4) After the completion of construction, a buoyancy prevention material for preventing buoyancy due to groundwater level or the like can be installed on the plate material. (5) Instead of the conventional method with a deep pipe installation position, a buried pipe can be installed in a shallow layer easily. (6) The buoyancy prevention material is fixed to the plate material installed in the lower part of the buried pipe, and the weight of the soil is received by the whole plate material, and the buoyancy applied to the buoyancy prevention material can be suppressed.

請求項2の発明は、次の工程でなる流動化処理土による浅層埋設工法であって、
第一の工程は、埋設対象地盤を掘削し壁を施工し、少なくとも埋設管両側面に200〜400mm程度の幅の施工スペースを確保する。
第二の工程は、前記壁の下方に埋設管据付の基礎となり得る蛇篭を設置する。
第三の工程は、この埋設管の略上部の1/2を捲装し、この埋設管にかかる地下水位等で発生する浮力を抑制する対の浮力防止材の下端を、この蛇篭に固定する。
第四の工程は、この蛇篭に、埋設管を設置し、この埋設管と前記施工スペースとの間に流動化処理土の充填材を充填する充填スペースを形成する。
第五の工程は、この埋設管の略上部の1/2を捲装した前記対の浮力防止材で、この埋設管にかかる地下水位等で発生する浮力を抑制するとともに、この対の浮力防止材を利用して浮力を蛇篭に伝達する。
第六の工程は、充填材を、前記充填スペースに一気に充填し、現場発生土砂の埋戻しをする。
The invention of claim 2 is a shallow layer embedding method using fluidized soil in the following process,
In the first step, the ground to be buried is excavated and walls are constructed, and a construction space having a width of about 200 to 400 mm is secured at least on both sides of the buried pipe.
A 2nd process installs the gabion which can become a foundation of an underground pipe installation under the said wall.
In the third step, half of the upper part of the buried pipe is fitted, and the lower ends of the pair of buoyancy prevention materials for suppressing the buoyancy generated at the groundwater level applied to the buried pipe are fixed to the gabion . .
In the fourth step, a buried pipe is installed in the gabion , and a filling space for filling the fluidized soil filler is formed between the buried pipe and the construction space.
The fifth step is the pair of buoyancy prevention materials equipped with substantially the upper half of the buried pipe, and suppresses the buoyancy generated at the groundwater level applied to the buried pipe and prevents the buoyancy of the pair. Using material, buoyancy is transmitted to gabion .
In the sixth step, the filling material is filled into the filling space at once, and the on-site generated soil is backfilled.

従って、請求項2は、請求項1と同じ意図を達成できること、またより施工の簡易化、低コスト化と、工期の短縮化等が図れること、さらに埋設管支持部材の付設を省略できることなどの特徴がある。 Therefore, claim 2 can achieve the same intention as claim 1, can further simplify the construction, reduce costs, shorten the construction period, etc., and can omit the installation of the buried pipe support member. There are features.

請求項3の発明は、請求項1又は請求項2に記載の埋設対象地盤を掘削するに際し、この掘削周辺地盤への影響の軽減を意図して対の土留め壁を設置した後に行う構成とした流動化処理土による浅層埋設工法である。 The invention of claim 3 is a structure that is performed after excavating the ground to be buried according to claim 1 or claim 2 after installing a pair of retaining walls with the intention of reducing the influence on the ground around the excavation. This is a shallow burial method using fluidized soil .

従って、請求項3は、請求項1又は請求項2の目的を達成できること、この目的を達成するに最適な掘削周辺地盤への影響の軽減を意図して対の土留め壁を設置する浅層埋設工法を提供できること等の特徴がある。 Therefore, Claim 3 can achieve the object of Claim 1 or Claim 2, and is a shallow layer in which a pair of retaining walls is installed in order to reduce the influence on the ground around the excavation optimum to achieve this object. There is a feature such as being able to provide a buried construction method.

請求項4の発明は、請求項1又は請求項2に記載の対の浮力防止材の上部端部を、ターンバックル、溶接、面ファスナー、接着等の物理的な手段で連結する構成とした流動化処理土による浅層埋設工法である。 According to a fourth aspect of the present invention, there is provided a flow in which the upper ends of the pair of buoyancy prevention materials according to the first or second aspect are connected by physical means such as a turnbuckle, welding, a hook-and-loop fastener, or an adhesive. It is a shallow burial method using chlorinated soil .

従って、請求項4は、請求項1又は請求項2の目的を達成できること、この目的を達成するに最適な対の浮力防止材の連結(結合)手段を提供できること等の特徴がある。 Therefore, the fourth aspect is characterized in that the object of the first or second aspect can be achieved, and that a pair of buoyancy preventing material coupling (coupling) means optimal for achieving the object can be provided.

請求項5の発明は、請求項1又は請求項2に記載の土留め壁を、建屋等の構造物、道路、鉄道等の公共構造物への影響を回避するために、安息角度を確保して設置する構成とした流動化処理土による浅層埋設工法である。 The fifth aspect of the invention secures the angle of repose of the earth retaining wall according to the first or second aspect of the invention in order to avoid the influence on a structure such as a building or a public structure such as a road or a railway. This is a shallow burial method using fluidized soil .

従って、請求項5は、請求項1又は請求項2の目的を達成できること、この目的を達成するに最適な対の土留め壁を提供できること等の特徴がある。 Therefore, claim 5 has the characteristics that the object of claim 1 or claim 2 can be achieved, and that an optimal pair of retaining walls can be provided to achieve this object.

請求項6の発明は、請求項1又は請求項2に記載の埋設管に、重量物を内蔵する構成とした流動化処理土による浅層埋設工法である。 The invention of claim 6 is a shallow-layer embedding method using fluidized soil in which a heavy object is built in the embedding pipe according to claim 1 or claim 2 .

従って、請求項6は、請求項1又は請求項2の目的を達成できること、この目的を達成するに最適な埋設管を提供できること等の特徴がある。 Therefore, claim 6 has the characteristics that the object of claim 1 or claim 2 can be achieved, and an optimum buried pipe can be provided to achieve this object.

請求項7の発明は、請求項1又は請求項2に記載の蛇篭を、壁間に隙間なく設置する構成とした流動化処理土による浅層埋設工法である。 The invention of claim 7 is a shallow burial method using fluidized soil in which the gabion according to claim 1 or 2 is installed without a gap between the walls.

従って、請求項7は、請求項1又は請求項2の目的を達成できること、この目的を達成するに最適な板材の構造を提供できること等の特徴がある。 Accordingly, the seventh aspect is characterized in that the object of the first or second aspect can be achieved, and that an optimal plate material structure can be provided to achieve the object.

以下、本発明の好ましい一実施例を説明する。   Hereinafter, a preferred embodiment of the present invention will be described.

◎ 先ず土留め壁を打設する埋設工法に関し、「1」〜「8」と分説する。   ◎ First, the embedding method for placing earth retaining walls is described as “1” to “8”.

「1」 土留め壁設置と、掘削及び/又は床付けを行う工程を説明する。   “1” A process for installing a retaining wall and performing excavation and / or flooring will be described.

この工程の目的は、周辺地盤への影響を軽減するため、土留め壁1、1(対の時には単独の数字とする)を設置(圧入、打設等)する。この土留め壁1は、地盤に見合った材料を使用する。例えば、鋼矢板、H鋼+矢板、連続地中壁等とする。そして、この土留め壁1を構築する土木機械としては、クレーン、圧入機、バイブロ、連続壁を施工する機械、トレンチャー、パワーブレンド、TRD(商品名:商標)、SMW(商品名:商標)等が望ましい。   The purpose of this step is to install (press-fit, place, etc.) earth retaining walls 1, 1 (single numbers when paired) in order to reduce the influence on the surrounding ground. The earth retaining wall 1 uses a material suitable for the ground. For example, a steel sheet pile, H steel + sheet pile, continuous underground wall, etc. Civil engineering machines for constructing the retaining wall 1 include cranes, press-fitting machines, vibrators, continuous wall construction machines, trenchers, power blends, TRD (trade name: trademark), SMW (trade name: trademark), etc. Is desirable.

この土留め壁1を設置した後、掘削して施工スペース2を確保する。尚、地下水位が高い場合は仮締切り(止水性の壁)を施工する。この掘削の際に、従来工法であれば、埋設管3の両側面に施工スペースを500mm程度設けるが本工法は必要としないために、その分横方向の掘削土量が少なくなる。尚、土留め壁1の設置は、建屋等の構造物、道路、鉄道等の公共構造物Hへの影響を回避するために、安息角度Aを確保して設置する。   After the earth retaining wall 1 is installed, the construction space 2 is secured by excavation. If the groundwater level is high, a temporary cutoff (water blocking wall) will be constructed. In the case of this excavation, if it is a conventional construction method, construction space is provided about 500 mm on both sides of the buried pipe 3, but since this construction method is not required, the amount of excavated soil in the lateral direction is reduced accordingly. The earth retaining wall 1 is installed with a repose angle A secured in order to avoid the influence on structures such as buildings and public structures H such as roads and railways.

「2」 仮設材の設置(必要に応じて)及び/又は板材の設置の工程を説明する。   “2” A process of installing a temporary material (if necessary) and / or a plate material will be described.

この工程の目的は、土留め壁1の崩壊を防ぐためと、崩壊の危険性がある場合、又は安全管理、規則等を考慮し、その状況によって仮設材を順次及び/又は必要とする時に設置する。この例では、腹起し400及び/又は切梁4と、また覆工板401等を設置し、前記崩壊を防止、安全性の確保等を意図する。勿論、この仮設材は、周辺地盤や掘削深さ等を考慮して設計するが、必要としない場合もある。何れにしても、従来工法より掘削幅の縮小により切梁4の長さは短くて済み有効であること、設置の簡便化、低コスト化等が図れること等の特徴がある。   The purpose of this process is to prevent collapse of the earth retaining wall 1 and when there is a risk of collapse, or when considering the safety management, rules, etc., and when temporary materials are needed sequentially and / or depending on the situation To do. In this example, the upset 400 and / or the cut beam 4 and the lining plate 401 are installed to prevent the collapse and to ensure safety. Of course, this temporary material is designed in consideration of the surrounding ground, excavation depth, etc., but may not be necessary. In any case, the length of the cut beam 4 can be shortened by the reduction of the excavation width compared to the conventional method, and it is effective, the installation can be simplified, the cost can be reduced, and the like.

その後、前記施工スペース2の底面200にコンクリート板材、鋼板、複合板材等の板材5を設ける。この板材5には対の浮力防止材6を固着(定着)させる。この板材5は、施工スペース2と埋設管3とで形成される空間(充填スペース201)に打設される流動化処理土、処理土等の充填材7及び/又は埋戻し土砂8(現場発生土砂)の重量に耐え得る構造である。またこの板材5は埋設管3にかかる地下水位等で発生する浮力を抑制する対の浮力防止材6の支持体としての役割を備えており、埋設管3の浮力に耐え得る構造である。また板材5は埋設管3の設置(据付)の基礎になる。またこの板材5は、埋設管3の長さ方向に必要とする面積比を確保できる構造とするので、例えば、土留め壁1(掘削壁1a)の下方の支持及び/又は土圧対抗手段としての機能を備えること、板材5自身の浮上回避、土圧による破壊回避を図ること等を意図する。   Thereafter, a plate 5 such as a concrete plate, a steel plate, or a composite plate is provided on the bottom surface 200 of the construction space 2. A pair of buoyancy prevention materials 6 are fixed (fixed) to the plate material 5. This plate material 5 is composed of fluidized treated soil, treated soil and other filler 7 and / or backfilled soil 8 (generated on site) placed in a space (filling space 201) formed by the construction space 2 and the buried pipe 3. The structure can withstand the weight of earth and sand. Further, the plate member 5 has a role as a support body for the pair of buoyancy prevention members 6 that suppress buoyancy generated at the groundwater level or the like applied to the buried pipe 3, and has a structure that can withstand the buoyancy of the buried pipe 3. Further, the plate material 5 serves as a basis for installation (installation) of the buried pipe 3. Moreover, since this board | plate material 5 is set as the structure which can ensure the area ratio required in the length direction of the buried pipe 3, for example, as a support under the retaining wall 1 (excavation wall 1a) and / or earth pressure countermeasure means It is intended to provide the above functions, to avoid the floating of the plate material 5 itself, to avoid destruction by earth pressure, and the like.

尚、板材5を、土留め壁1(掘削壁1a)間に隙間なく設置することで、この土留め壁1(掘削壁1a)の補強に役立ち、例えば、当該土留め壁1(掘削壁1a)の転倒防止、崩壊防止と、その補強工事の簡略化等に役立つものと考えられる。   In addition, it is useful for reinforcement of this earth retaining wall 1 (excavation wall 1a) by installing the board | plate material 5 between the earth retaining walls 1 (excavation wall 1a), for example, the earth retaining wall 1 (excavation wall 1a). ) To prevent falls and collapse, and to simplify the reinforcement work.

この切梁4は、現場に応じ変化するがコンクリート、コンクリート2次製品、鋼製の製品等を使用する。そして、この切梁4の施工には、現場に応じ変化するがクレーン、コンクリート打設に必要な機械等を使用する。   Although this cut beam 4 changes according to the site, concrete, a concrete secondary product, steel products, etc. are used. For the construction of the beam 4, a crane, a machine necessary for placing concrete, or the like is used although it varies depending on the site.

「3」 浮力防止材及び/又は埋設管(FRPM管、鋼製管、ヒューム管)等の設置の工程を説明する。   “3” A process for installing a buoyancy prevention material and / or a buried pipe (FRPM pipe, steel pipe, fume pipe) will be described.

この工程の目的は、対の浮力防止材6を介して板材5に埋設管3を緊締して施工完了後において、この埋設管3にかかる浮力を下部の板材5に伝達する役割がある。この浮力とは、板材5に埋設管3を施工完了後において、地下水位等により埋設管3に発生する浮力である。また施工時の浮力対策にもなる。その他の工法としては、例えば、施工時には別途上部から押さえる工法、また管内部に重量物(図示せず)を挿入する等の浮力対策を講じる場合もある。そして、この浮力防止材6を板材5に固着する施工順序は、この板材5を土留め壁1に固着した後にするか、予め板材5に固着した後に、土留め壁1に固着するか、或いは埋設管3を板材5等に設置した後に固着するかは自由である。しかし、望ましい工法は、板材5を固着した後に、浮力防止材6を固着し、この浮力防止材6間に埋設管3を設置し、その後、浮力防止材6の上部端部を連結(結合)し、この埋設管3を緊結する施工順序である。この施工順序が、埋設管3を板材5に設けた浮力防止材6間に設置する容易性と、及び/又は施工スペース2等の狭隘な空間に設置された埋設管3の連結の容易性、確実性等において有益である。   The purpose of this step is to transmit the buoyancy applied to the buried pipe 3 to the lower plate 5 after the construction is completed by tightening the buried pipe 3 to the plate 5 via the pair of buoyancy prevention materials 6. The buoyancy is buoyancy generated in the buried pipe 3 due to the groundwater level after the construction of the buried pipe 3 on the plate material 5 is completed. It also serves as a measure for buoyancy during construction. As other construction methods, for example, a construction method in which the material is pressed from above at the time of construction, or a buoyancy measure such as inserting a heavy object (not shown) inside the pipe may be taken. And, the construction sequence for fixing the buoyancy prevention material 6 to the plate material 5 is performed after the plate material 5 is fixed to the retaining wall 1, or after being fixed to the plate material 5 in advance, or to the retaining wall 1. It is free to fix the buried pipe 3 after it is installed on the plate 5 or the like. However, a desirable method is to fix the buoyancy prevention material 6 after fixing the plate material 5, install the buried pipe 3 between the buoyancy prevention materials 6, and then connect (join) the upper end of the buoyancy prevention material 6. In this construction sequence, the buried pipe 3 is fastened. This construction order is easy to install the buried pipe 3 between the buoyancy prevention materials 6 provided on the plate material 5 and / or easy to connect the buried pipe 3 installed in a narrow space such as the construction space 2, This is beneficial in terms of certainty.

この浮力防止材6は、鋼製及び/又は合成樹脂等で加工されているバンド等、鉄筋、丸鋼などが考えられる。また浮力防止材6の緊締(結合)手段は、ターンバックル、溶接、面ファスナー、接着等の物理的な手段が簡便、かつ迅速に対応できて有益である。そして、埋設管3の取扱いは人力作業、荷降ろし機械等を採用して行う。   The buoyancy prevention material 6 may be a steel band and / or a band processed with a synthetic resin or the like, a reinforcing bar, a round steel bar, or the like. The buoyancy prevention material 6 is usefully tightened (bonded) by physical means such as turnbuckles, welding, hook-and-loop fasteners, and adhesion, which can be easily and quickly handled. And the handling of the buried pipe 3 is performed by employing a manual work, an unloading machine or the like.

「4」 埋設管支持部材を採用する埋設管の設置の工程を説明する。   “4” A process of installing a buried pipe that employs a buried pipe support member will be described.

この工程の目的は、埋設管支持部材10により埋設管3を設置する他の例を示しており、この例では埋設管支持部材10の上面を曲面とし、埋設管3との馴染みを図って安定設置を図る。また埋設管3の位置の修正として利用し、埋設管3を設計の位置に埋設すること、板材5の歪み解消と、板材5の他の問題の解消等に役立てる。この埋設管支持部材10は必要により設ける工程である。   The purpose of this step is to show another example in which the buried pipe support member 10 is installed by the buried pipe support member 10. In this example, the upper surface of the buried pipe support member 10 is made a curved surface so that the familiarity with the buried pipe 3 can be secured. Plan for installation. Further, it is used as a correction of the position of the buried pipe 3 and is used for burying the buried pipe 3 at the design position, eliminating distortion of the plate material 5, and solving other problems of the plate material 5. This buried pipe support member 10 is a process to be provided if necessary.

この埋設管支持部材10は、コンクリート、コンクリート2次製品、鋼製、木材、充填材等の材料である。またこの埋設管支持部材10に緩衝効果を付与し、施工の安全性と容易化を図ることも可能である(他の例も同じ)。さらにこの埋設管支持部材10は、埋設管3に着脱自在として、自由な使用と、高さの調整と、また埋設位置の調整及び/又は地盤等の変化に対応できる構造が理想である。   The buried pipe support member 10 is made of a material such as concrete, a concrete secondary product, steel, wood, or a filler. Moreover, it is also possible to give a buffering effect to the buried pipe support member 10 to achieve construction safety and simplification (the same applies to other examples). Further, the buried pipe support member 10 is ideally configured to be detachable from the buried pipe 3 so that it can be freely used, adjusted in height, adjusted in the buried position, and / or changed in the ground.

尚、板材5は板状形状で説明したが、図示しない蛇篭方式も可能であり、この蛇篭は、例えば、イ) 土留め壁1(掘削壁1a)間に略隙間なく設置する板状であって、かつ所定の長手方向(間隔方向に直交する方向)に所定の長さを備えた形状とする例、またロ) 土留め壁1(掘削壁1a)間に分割した二連の棒状であって、かつ所定の長手方向(間隔方向に直交する方向)に所定の長さを備えた形状とする例、等が考えられるが限定されない。そして、この蛇篭方式は、地下水の発生し易い地盤(地中)、軟弱地盤、変形地盤等に適する工法である。   Although the plate material 5 has been described as having a plate shape, a gabion method (not shown) is also possible. This gabion is, for example, a plate shape that is installed between the earth retaining wall 1 (excavation wall 1a) without a substantial gap. And an example of a shape having a predetermined length in a predetermined longitudinal direction (a direction orthogonal to the interval direction), and b) a double bar shape divided between the earth retaining wall 1 (excavation wall 1a). In addition, an example of a shape having a predetermined length in a predetermined longitudinal direction (a direction orthogonal to the interval direction) is conceivable, but is not limited. And this gabion method is a construction method suitable for ground (underground), soft ground, deformed ground, etc. where groundwater is likely to be generated.

「5」 浮力防止材の連結の工程を説明する。   “5” The step of connecting the buoyancy prevention material will be described.

この工程の目的は、埋設管3を板材5及び/又は埋設管支持部材10への設置を完了した後、所定の位置に設置された段階で、予め設置されている浮力防止材6を埋設管3の上方で連結する。尚、前述の如く、埋設管3を設置後に浮力防止材6を設置し、前述の作業をすることも場合により可能である。   The purpose of this step is to install the buoyancy prevention material 6 installed in advance at the stage where the embedded tube 3 is installed at a predetermined position after the installation of the embedded tube 3 on the plate material 5 and / or the embedded tube support member 10 is completed. Connect above 3. As described above, the buoyancy prevention material 6 may be installed after the buried pipe 3 is installed, and the above-described operation may be performed in some cases.

「6」 流動化処理土等による埋戻し工程を説明する。   “6” Explain the backfilling process using fluidized soil.

この工程の目的は、流動化処理土・処理土等の充填材7(流動化処理土7とする)は流動性に富んでいるので締固め及び/又は転圧等の作業を必要としない利点があって、例えば、現場作業スペースの省力化、汎用性の向上、又は交通、歩行の障害回避が図れて有益である。さらには埋設作業等において、施工スピードの向上と、施工工期の短縮化、低コスト化に役立つ利点がある。   The purpose of this process is the advantage that the filling material 7 (referred to as fluidized soil 7) such as fluidized soil and treated soil is rich in fluidity and therefore does not require operations such as compaction and / or rolling. Thus, for example, it is beneficial to save labor on the work site, improve versatility, or avoid obstacles to traffic and walking. Furthermore, there are advantages in improving the construction speed, shortening the construction period, and reducing the cost in burial work.

尚、流動化処理土7の他の例としては、これと同等な効果のある材料、又は流動化処理土7と砂や山砂、現場発生土、フライアッシュ等を組合わせて構成した材料(混練材料)の場合も可能である。そして、各種の廃棄物(廃材)を利用することで、産業廃材の有効利用と、その廃棄に基づく弊害の解消と、環境保護、また資源の有効利用が図れる。尚、この流動化処理土7の単独使用に限定されず、例えば、埋設管3の下半分は、流動化処理土7を、他を埋戻し土砂8(現場発生土砂)を使用する。この例では現場で発生する土砂の取扱い(処理)の容易化と、土砂の搬送による問題の解消等を意図する。尚、流動化処理土7の投入(打設)は、施工時のそれぞれの浮力に対応するために2回〜数回に分けて施工することも考えられる。   In addition, as another example of the fluidized soil 7, a material having an effect equivalent to this, or a material configured by combining the fluidized soil 7 with sand, mountain sand, on-site generated soil, fly ash, or the like ( It is also possible in the case of kneaded materials. By using various types of wastes (waste materials), it is possible to effectively use industrial waste materials, eliminate harmful effects caused by the disposal, protect the environment, and effectively use resources. The fluidized soil 7 is not limited to single use. For example, the lower half of the buried pipe 3 uses the fluidized soil 7 and the other backfill soil 8 (site-generated soil). In this example, it is intended to facilitate handling (processing) of earth and sand generated on site and to solve problems caused by earth and sand transport. In addition, in order to respond | correspond to each buoyancy at the time of construction, injection | throwing-in of the fluidization processing soil 7 may be divided into 2 to several times.

「7」 仮設材撤去及び/又は上部埋戻し工程を説明する。   “7” The temporary material removal and / or upper backfilling step will be described.

この工程の目的は、必要により設けられた仮設材(腹起し400及び/又は切梁4と、また覆工板401等)を順次従来と同様に撤去し復旧する。そして、周辺の地盤を考慮した場合、土留め壁1及び/又は仮設材を残置する場合も考えられる。この仮設材撤去後の表面付近は、流動化処理土7、砂、山砂、現地発生土等により現況復旧をする。   The purpose of this step is to remove and restore the temporary materials (the erection 400 and / or the beam 4 and the lining plate 401, etc.) provided as necessary in the same manner as before. And when the surrounding ground is considered, the earth retaining wall 1 and / or the temporary material may be left behind. The surface near the surface after removal of the temporary material will be restored with fluidized soil 7, sand, mountain sand, local soil, etc.

そして、本発明の適用箇所の一例を説明すると、: 管路新設・修理等による交換 : 既設管路(開水路等)の地下化・修理等による交換 : 水路、ガス管、電気等ライフラインの地下化・修理等による交換等が考えられる。   An example of the application of the present invention is as follows: Replacement by new pipe construction / repair, etc. Replacement by existing underground pipes (open waterways, etc.) / Repair: Lifelines such as waterways, gas pipes, and electricity It may be exchanged by undergrounding or repairing.

「8」 埋設管支持部材を採用しない流動化処理土等による埋戻し工程を説明する。   “8” A backfilling process using fluidized soil that does not employ a buried pipe support member will be described.

この例では、板材5に直接埋設管3を設置する。勿論、必要により回転防止手段及び/又は緩衝材等を設け、施工の安全性と容易化を図ることは可能である(他の例も同じ)。   In this example, the buried pipe 3 is installed directly on the plate material 5. Of course, if necessary, it is possible to provide rotation prevention means and / or cushioning material, etc., to make the construction safe and easy (other examples are the same).

前述した各施工手順は、好ましい一例であり、地盤、埋設環境、交通量等の状況で変更される。そして、この施工手順が異なっても、本発明の思想の範疇であれば、その実施態様となる。   Each construction procedure mentioned above is a preferable example, and it changes with conditions, such as the ground, a buried environment, and traffic volume. And even if this construction procedure is different, it is an embodiment as long as it is within the concept of the present invention.

◎ 次にオープンカット工法を説明する。   ◎ Next, the open cut method will be explained.

「9」はオープンカット工法であり、この例は、図9〜図11に示してある。この工法は、オープンカットにより掘削壁1aを崩壊しない角度(安息角度A)で掘削して施工スペース2を確保する。この施工スペース2の底面200に前述の例と同様に、板材5を設ける。この板材5には対の浮力防止材6を固着(定着)させる。この板材5は、施工スペース2と埋設管3とで形成される空間(充填スペース201)に打設される流動化処理土7及び/又は埋戻し土砂8(現場発生土砂)の重量に耐え得る構造である。そして、この例では、施工時の浮力対策として、流動化処理土7を一時的に停止(打ち止め)することも可能であり、その一例を矢印イとして示す。具体的には、図示の角度と打ち止め位置が理想である。その後、次の流動化処理土7及び/又は埋戻し土砂8を打設する。図11は流動化処理土7等を充填又は必要時に設けた各部材を撤去した模式図である。そして、その他の各工程、手順等は前述の例に準ずる。   “9” is an open cut method, and examples of this are shown in FIGS. In this method, the construction space 2 is secured by excavating the excavation wall 1a at an angle (rest angle A) that does not collapse by the open cut. The plate material 5 is provided on the bottom surface 200 of the construction space 2 in the same manner as in the above example. A pair of buoyancy prevention materials 6 are fixed (fixed) to the plate material 5. This plate material 5 can withstand the weight of fluidized soil 7 and / or backfill soil 8 (site-generated soil sand) placed in the space (filling space 201) formed by the construction space 2 and the buried pipe 3. It is a structure. In this example, it is possible to temporarily stop (stop) the fluidized soil 7 as a countermeasure for buoyancy at the time of construction, and an example thereof is indicated by an arrow a. Specifically, the illustrated angle and stop position are ideal. Thereafter, the next fluidized soil 7 and / or backfill soil 8 is placed. FIG. 11 is a schematic diagram in which each member provided with fluidized soil 7 or the like or provided when necessary is removed. And each other process, a procedure, etc. are based on the above-mentioned example.

土留め壁設置と、掘削及び/又は床付けを行う工程を説明する模式図Schematic diagram explaining the steps of earth retaining wall installation and excavation and / or flooring 仮設材の設置(必要に応じて)及び/又は板材の設置の工程を説明する模式図Schematic diagram explaining the steps of temporary material installation (if necessary) and / or plate material installation 浮力防止材の設置の工程を説明する模式図Schematic explaining the process of installing buoyancy prevention material 埋設管支持部材設置を採用する及び/又は埋設管(FRPM管、鋼製管、ヒューム管)等の設置の工程を説明する模式図Schematic diagram illustrating the process of installing buried pipe support members and / or installing buried pipes (FRPM pipes, steel pipes, fume pipes), etc. 浮力防止材の連結の工程を説明する模式図Schematic explaining the process of connecting buoyancy prevention materials 流動化処理土等による埋戻し工程を説明する模式図Schematic diagram explaining the backfilling process using fluidized soil 仮設材撤去及び/又は上部埋戻し工程を説明する模式図Schematic diagram explaining temporary material removal and / or upper backfilling process 埋設管支持部材設置を採用しない埋設管の設置の工程を説明する模式図Schematic diagram explaining the process of installing buried pipes that do not employ buried pipe support member installation オープンカット工法による掘削及び/又は板材・浮力防止材等の設置の工程を説明する模式図Schematic diagram explaining the process of excavation and / or installation of plate materials and buoyancy prevention materials by the open cut method 図9の例における流動化処理土7の打ち止め工程を説明する模式図FIG. 9 is a schematic diagram for explaining the stopping process of the fluidized soil 7 in the example of FIG. 図9の例の埋設管の設置の工程を説明する模式図FIG. 9 is a schematic diagram for explaining the process of installing the buried pipe of the example

1 土留め壁
1a 掘削壁
2 施工スペース
200 底面
201 充填スペース
3 埋設管
4 切梁
400 腹起し
401 覆工板
5 板材
6 浮力防止材
7 流動化処理土
8 土砂
10 埋設管支持部材
A 安息角度
H 公共構造物
イ 矢印
DESCRIPTION OF SYMBOLS 1 Earth retaining wall 1a Excavation wall 2 Construction space 200 Bottom surface 201 Filling space 3 Buried pipe 4 Cut beam 400 Raising 401 Backing board 5 Plate material 6 Buoyancy prevention material 7 Fluidization processing soil 8 Earth and sand 10 Buried pipe support member A Rest angle H Public structure b Arrow

Claims (7)

次の工程でなる流動化処理土による浅層埋設工法であって、
第一の工程は、埋設対象地盤を掘削し壁を施工し、少なくとも埋設管両側面に200〜400mm程度の幅の施工スペースを確保する。
第二の工程は、前記壁の下方に埋設管据付の基礎となり得る蛇篭を設置する。
第三の工程は、この埋設管の略上部の1/2を捲装し、この埋設管にかかる地下水位等で発生する浮力を抑制する対の浮力防止材の下端を、この蛇篭に固定する。
第四の工程は、前記埋設管据付の基礎となり得る埋設管支持部材を、蛇篭の上に設置する。
第五の工程は、この蛇篭及び/又は埋設管支持部材に、埋設管を設置し、この埋設管と前記施工スペースとの間に流動化処理土の充填材を充填する充填スペースを形成する。
第六の工程は、この埋設管の略上部の1/2を捲装した前記対の浮力防止材で、この埋設管にかかる地下水位等で発生する浮力を抑制するとともに、この対の浮力防止材を利用して浮力を蛇篭に伝達する。
第七の工程は、充填材を、前記充填スペースに一気に充填し、現場発生土砂の埋戻しをする。
It is a shallow burial method using fluidized soil in the next process,
In the first step, the ground to be buried is excavated and walls are constructed, and a construction space having a width of about 200 to 400 mm is secured at least on both sides of the buried pipe.
A 2nd process installs the gabion which can become a foundation of an underground pipe installation under the said wall.
In the third step, half of the upper part of the buried pipe is fitted, and the lower ends of the pair of buoyancy prevention materials for suppressing the buoyancy generated at the groundwater level applied to the buried pipe are fixed to the gabion . .
In the fourth step, a buried pipe support member that can serve as a foundation for the buried pipe installation is installed on the gabion .
In the fifth step, a buried pipe is installed in the gabion and / or buried pipe support member, and a filling space for filling the fluidized soil filler is formed between the buried pipe and the construction space.
The sixth step is a pair of buoyancy prevention materials equipped with approximately half of the upper part of the buried pipe, and suppresses the buoyancy generated at the groundwater level, etc. applied to the buried pipe, and prevents this pair of buoyancy. Using material, buoyancy is transmitted to gabion .
In the seventh step, the filling material is filled into the filling space at once, and the on-site generated soil is backfilled.
次の工程でなる流動化処理土による浅層埋設工法であって、
第一の工程は、埋設対象地盤を掘削し壁を施工し、少なくとも埋設管両側面に200〜400mm程度の幅の施工スペースを確保する。
第二の工程は、前記壁の下方に埋設管据付の基礎となり得る蛇篭を設置する。
第三の工程は、この埋設管の略上部の1/2を捲装し、この埋設管にかかる地下水位等で発生する浮力を抑制する対の浮力防止材の下端を、この蛇篭に固定する。
第四の工程は、この蛇篭に、埋設管を設置し、この埋設管と前記施工スペースとの間に流動化処理土の充填材を充填する充填スペースを形成する。
第五の工程は、この埋設管の略上部の1/2を捲装した前記対の浮力防止材で、この埋設管にかかる地下水位等で発生する浮力を抑制するとともに、この対の浮力防止材を利用して浮力を蛇篭に伝達する。
第六の工程は、充填材を、前記充填スペースに一気に充填し、現場発生土砂の埋戻しをする。
It is a shallow burial method using fluidized soil in the next process,
In the first step, the ground to be buried is excavated and walls are constructed, and a construction space having a width of about 200 to 400 mm is secured at least on both sides of the buried pipe.
A 2nd process installs the gabion which can become a foundation of an underground pipe installation under the said wall.
In the third step, half of the upper part of the buried pipe is fitted, and the lower ends of the pair of buoyancy prevention materials for suppressing the buoyancy generated at the groundwater level applied to the buried pipe are fixed to the gabion . .
In the fourth step, a buried pipe is installed in the gabion , and a filling space for filling the fluidized soil filler is formed between the buried pipe and the construction space.
The fifth step is the pair of buoyancy prevention materials equipped with substantially the upper half of the buried pipe, and suppresses the buoyancy generated at the groundwater level applied to the buried pipe and prevents the buoyancy of the pair. Using material, buoyancy is transmitted to gabion .
In the sixth step, the filling material is filled into the filling space at once, and the on-site generated soil is backfilled.
請求項1又は請求項2に記載の埋設対象地盤を掘削するに際し、この掘削周辺地盤への影響の軽減を意図して対の土留め壁を設置した後に行う構成とした流動化処理土による浅層埋設工法。 When excavating the ground to be buried according to claim 1 or claim 2, shallowing by the fluidized soil, which is performed after installing a pair of retaining walls in order to reduce the influence on the surrounding ground for excavation Layer burying method. 請求項1又は請求項2に記載の対の浮力防止材の上部端部を、ターンバックル、溶接、面ファスナー、接着等の物理的な手段で連結する構成とした流動化処理土による浅層埋設工法。 A shallow layer embedment by fluidized soil in which the upper ends of the pair of buoyancy prevention materials according to claim 1 or 2 are connected by physical means such as turnbuckle, welding, hook-and-loop fastener, adhesion, etc. Construction method. 請求項1又は請求項2に記載の土留め壁を、建屋等の構造物、道路、鉄道等の公共構造物への影響を回避するために、安息角度を確保して設置する構成とした流動化処理土による浅層埋設工法。 The Retaining wall according to claim 1 or claim 2, the structure of the building such as roads, in order to avoid affecting the public structures railways and configured to be installed to secure the repose angle flow Shallow burial method using chlorinated soil . 請求項1又は請求項2に記載の埋設管に、重量物を内蔵する構成とした流動化処理土による浅層埋設工法。 A shallow burial method using fluidized soil in which a heavy object is built in the burial pipe according to claim 1 or claim 2 . 請求項1又は請求項2に記載の蛇篭を、壁間に隙間なく設置する構成とした流動化処理土による浅層埋設工法。 A shallow burial method using fluidized soil in which the gabion according to claim 1 or 2 is installed without a gap between walls.
JP2005057741A 2005-03-02 2005-03-02 Shallow buried method using fluidized soil Active JP4537228B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005057741A JP4537228B2 (en) 2005-03-02 2005-03-02 Shallow buried method using fluidized soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005057741A JP4537228B2 (en) 2005-03-02 2005-03-02 Shallow buried method using fluidized soil

Publications (2)

Publication Number Publication Date
JP2006241791A JP2006241791A (en) 2006-09-14
JP4537228B2 true JP4537228B2 (en) 2010-09-01

Family

ID=37048472

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005057741A Active JP4537228B2 (en) 2005-03-02 2005-03-02 Shallow buried method using fluidized soil

Country Status (1)

Country Link
JP (1) JP4537228B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5041223B2 (en) * 2007-08-01 2012-10-03 清水建設株式会社 Reinforcement method and structure of existing structure foundation
JP5973213B2 (en) * 2012-04-20 2016-08-23 東急建設株式会社 Method of embedding pipes with fluidized soil
JP5571219B1 (en) * 2013-04-08 2014-08-13 中性固化土工事業協同組合 Shield excavation residual soil processing method and processing system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000283334A (en) * 1999-03-29 2000-10-13 Kurimoto Ltd Underground buried structure of multistage pipeline and burying method thereof
JP2002206668A (en) * 2001-01-09 2002-07-26 Sekisui Chem Co Ltd Floating preventive construction method for buried pipeline
JP2004125100A (en) * 2002-10-04 2004-04-22 Jfe Koken Corp Construction method for burying pipe

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5032004Y2 (en) * 1972-04-18 1975-09-18
JPS54164306A (en) * 1978-06-15 1979-12-27 Kubota Ltd Floating preventive structure of buried light pipe
JPH04157272A (en) * 1990-10-19 1992-05-29 Kubota Corp Pipe floating preventing method
JPH07310861A (en) * 1994-05-20 1995-11-28 Sekisui Chem Co Ltd Laying method for underground buried pipe
JPH07317959A (en) * 1994-05-27 1995-12-08 Sekisui Chem Co Ltd Pipe burying method
JP2979117B2 (en) * 1995-12-13 1999-11-15 鹿島建設株式会社 Building foundation method
JPH11182737A (en) * 1997-12-24 1999-07-06 Tokyo Gas Co Ltd Pipe burying construction method
JPH11217832A (en) * 1998-02-03 1999-08-10 Hitachi Constr Mach Co Ltd Liquefaction backfilling construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000283334A (en) * 1999-03-29 2000-10-13 Kurimoto Ltd Underground buried structure of multistage pipeline and burying method thereof
JP2002206668A (en) * 2001-01-09 2002-07-26 Sekisui Chem Co Ltd Floating preventive construction method for buried pipeline
JP2004125100A (en) * 2002-10-04 2004-04-22 Jfe Koken Corp Construction method for burying pipe

Also Published As

Publication number Publication date
JP2006241791A (en) 2006-09-14

Similar Documents

Publication Publication Date Title
WO2020173100A1 (en) Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN103958780B (en) The method for forming cementing retaining wall
CN104234056B (en) For preventing the liquefy construction method of regional underground pipe gallery distortion of high water level
KR101111594B1 (en) Method for constructing underground structure
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
JP2010090608A (en) Method for constructing underground space and structure of the underground space
JP4537228B2 (en) Shallow buried method using fluidized soil
CN210163910U (en) Pipeline pipe jacking receiving well foundation pit supporting structure
JP2011094443A (en) Method for constructing wall surface work by using bag body
JP7178243B2 (en) Tunnel lining construction method
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
WO2024042603A1 (en) Construction method for structure
JP6298255B2 (en) Method and jig for preventing floating of underground structure
JP2008202344A (en) Support structure and support method of tunnel
JP2023158429A (en) Buried structure of buried pipe and method for burying buried pipe
JP2006057242A (en) Construction method for earth retaining wall
JPH07300845A (en) Preventive method against liquefaction of underground linear structure
KR100926286B1 (en) Construction method for tunnel using perpendicular hall
CN111021270A (en) Construction method for permanently protecting existing pipeline during road reconstruction
JPH0881952A (en) H-steel pile
JP2021031915A (en) Underground buried object floating prevention method and underground buried object floating prevention structure
JP3352951B2 (en) Installation method of invert and underground drainage in mountain tunnel
CN115727195A (en) Municipal large-diameter pipe jacking pipeline slippage repairing method under complex terrain
JP4427456B2 (en) Mountain-crested parent pile construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080218

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100204

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100209

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100401

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100607

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100617

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130625

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4537228

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250