JP3940735B2 - Earth retaining method - Google Patents

Earth retaining method Download PDF

Info

Publication number
JP3940735B2
JP3940735B2 JP2004167868A JP2004167868A JP3940735B2 JP 3940735 B2 JP3940735 B2 JP 3940735B2 JP 2004167868 A JP2004167868 A JP 2004167868A JP 2004167868 A JP2004167868 A JP 2004167868A JP 3940735 B2 JP3940735 B2 JP 3940735B2
Authority
JP
Japan
Prior art keywords
curing agent
sheet pile
hardener
ground
injection tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2004167868A
Other languages
Japanese (ja)
Other versions
JP2005290963A (en
Inventor
伸一 山下
大地 山下
Original Assignee
伸一 山下
山下 小夜子
大地 山下
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 伸一 山下, 山下 小夜子, 大地 山下 filed Critical 伸一 山下
Priority to JP2004167868A priority Critical patent/JP3940735B2/en
Publication of JP2005290963A publication Critical patent/JP2005290963A/en
Application granted granted Critical
Publication of JP3940735B2 publication Critical patent/JP3940735B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

この発明は、地中に水道管、ガス管、側溝、カルバートボックス等を埋設する土留め工事の施工に関するものである。 The present invention relates to construction of earth retaining work in which a water pipe, a gas pipe, a gutter, a culvert box, etc. are buried in the ground.

地中で比較的浅いところに水道管、ガス管、カルバートボックス等を埋設する工事においては、まず溝の両壁を構成すべき位置に簡易矢板、鉄板、シートパイル等の土留め部材を設置して溝壁が崩れるのを防止した上で、地面を掘削して溝を形成し、溝内での水道管等の敷設作業が行われる。この工事について図5に基づいて説明する。 When burying water pipes, gas pipes, culvert boxes, etc. in relatively shallow places in the ground, first install earth retaining members such as simple sheet piles, iron plates, sheet piles, etc. at the positions where both walls of the groove should be constructed. After preventing the wall from collapsing, the ground is excavated to form a groove, and a water pipe or the like is laid in the groove. This construction will be described with reference to FIG.

舗装21をカッターで切って取り除き、溝の両壁を構成すべき位置に簡易矢板、鉄板、シートパイル等の土留め部材23を設置して溝壁が崩れるのを防止した上で、掘削を開始する。(図5a)。シートパイル23の転倒を防止するための横梁28を設置しながら所定の深さまで掘り進めて溝22を形成する(図5b)。水道管等の埋設の場合は1.2〜1.7m程度の深さに掘る場合が多い。このシートパイル23によって溝22の壁が崩れるのを防止し、その後の作業を溝内で安全に支障なく行えるようにする。溝22の底盤部を整地し、グリ24とよばれる小石を所定の厚さだけ敷き点圧を行う(図5c)。このグリ24の層の上に砂26と埋設物25を入れる(図5d)。砂26は埋設物25の上をある程度の厚さで覆う程度に入れる。さらに砂26の層の上に土27を盛って溝22を完全に埋める(図5e)。ここで、砂26および土27は十分な強度に固められるように25cm程度の厚さずつ入れては点圧器で点圧しながら盛っていく。溝22が完全に埋まったらシートパイル23を引き抜く。そして、舗装を行う(図5f)。 Cut pavement 21 with a cutter and install earth retaining members 23 such as simple sheet piles, iron plates, sheet piles, etc. at positions where both walls of the groove should be constructed, and start excavating after preventing the groove wall from collapsing To do. (Figure 5a). The groove 22 is formed by digging to a predetermined depth while installing the cross beam 28 for preventing the sheet pile 23 from toppling (FIG. 5b). In the case of burying water pipes, etc., they are often dug to a depth of about 1.2 to 1.7 m. This sheet pile 23 prevents the wall of the groove 22 from collapsing, and the subsequent work can be safely performed without any trouble in the groove. The bottom plate portion of the groove 22 is leveled, and a pebble called the grits 24 is spread by a predetermined thickness to perform point pressure (FIG. 5c). Sand 26 and buried object 25 are put on the layer of the glue 24 (FIG. 5d). The sand 26 is put so as to cover the buried object 25 with a certain thickness. Further, the soil 27 is placed on the layer of sand 26 to completely fill the groove 22 (FIG. 5e). Here, the sand 26 and the soil 27 are put in a thickness of about 25 cm so as to be hardened to a sufficient strength, and are piled up while applying a point pressure with a point pressure device. When the groove 22 is completely filled, the sheet pile 23 is pulled out. Then, paving is performed (FIG. 5f).

上記のようなシートパイルを用いた工事に関連して、特許文献1には、シートパイルを整然と真直に押込み、建設公害を生じない土留めユニットが記載されている。
特開平4−200481号
In relation to the construction using the sheet pile as described above, Patent Document 1 describes a soil retaining unit that pushes the sheet pile in an orderly manner and does not cause construction pollution.
Japanese Patent Laid-Open No. 4-200481

上述の通り、シートパイルを用いた従来の工法において、工事の後半においてシートパイルの引き抜きが行われる。こうして回収されたシートパイルは次の工事で再利用されることになる。しかし、溝内に砂や土を盛った後にシートパイルを引く抜くことにより、地中にはシートパイルの体積分の空隙が生じることになる。この空隙の問題はこれまでほとんど検討されていない。この空隙を埋めるために周囲の土砂が移動し、さまざまな問題が生じうる。例えば、時間とともに溝内に充填した砂や土砂が空隙を埋めるために移動し、溝の上に敷かれた舗装面が沈下して、道路表面にくぼみを生じる。また、溝の外の土砂が移動することにより、溝の両側の地盤状態に変動をきたし、近くの建造物に影響を与えうる。さらに、周囲の地下水の状態が変われば、広範囲での影響も発生する。地下水は最も通りやすいところに水路を形成するので、シートパイルの引き抜きによって生じた空隙や、それを埋めるために移動した土砂によってできた水の通りやすい場所に新たな水路を形成し、周囲の地下水の流れが大きく変動する。この地下水の状態の変動によってそれまで保たれていた周囲の地盤の地圧のバランスがくずれ、地盤沈下等の地盤変動が生じ、そこに建造されている塀や建物等を変形させることになる。 As described above, in the conventional method using a sheet pile, the sheet pile is pulled out in the latter half of the work. The collected sheet pile will be reused in the next construction. However, when the sheet pile is pulled out after sand or earth is piled up in the groove, a void corresponding to the volume of the sheet pile is generated in the ground. Until now, the problem of this void has been hardly studied. The surrounding earth and sand moves to fill this gap, and various problems can occur. For example, as time passes, sand or earth and sand filled in the groove move to fill the gap, and the pavement surface laid on the groove sinks, resulting in a depression on the road surface. Moreover, when the earth and sand outside the groove move, the ground condition on both sides of the groove changes, and nearby buildings can be affected. Furthermore, if the surrounding groundwater conditions change, a wide range of effects will also occur. Since the groundwater forms a waterway where it can pass most easily, a new waterway is formed in the space where the water created by the removal of the sheet pile and the earth and sand moved to fill it, and the surrounding groundwater The flow of fluctuates greatly. Due to the change in the state of the groundwater, the ground pressure balance of the surrounding ground that has been maintained until then is lost, and ground changes such as ground subsidence occur, which deforms the walls and buildings built there.

そこで、シートパイルによる空隙を生じさせないために、シートパイルを引き抜かず、施工後も地中へ残すことが考えられる。しかし、地中に残されたシートパイルは時間とともに酸化・腐食により消失し、いずれは上述のような問題が生じることに変わりがない。また、シートパイルの素材である金属が土壌や地下水等を汚染することになる。シートパイルを使い捨てにすることは資源としても無駄な消費である。 Therefore, in order not to generate a gap due to the sheet pile, it is conceivable that the sheet pile is not pulled out and remains in the ground after construction. However, the sheet pile left in the ground disappears due to oxidation / corrosion with time, and the above-mentioned problems still occur. Moreover, the metal which is the material of a sheet pile will contaminate soil, groundwater, etc. Disposing sheet piles is a wasteful use of resources.

この発明は、施工後にも周囲の地盤や地下水の流れに変動を与えることがなく、環境問題を生させない施工方法、そのための土留め部材および土留め工事プラントを提供することを目的とする。 An object of the present invention is to provide a construction method that does not give rise to environmental problems without causing fluctuations in the surrounding ground and groundwater flow even after construction, and a soil retaining member and a soil retaining construction plant therefor.

上述の課題を解決するため、この発明の土留め工法は、既に設置された土留め部材に隣接させながら硬化剤注入管を所定間隔で設置し、土留め部材と硬化剤注入管を相互に固定し、土留め部材と硬化剤注入管を引き抜きながら硬化剤を地中に注入して土留め部材が引き抜かれた後の空隙を埋めるものである。In order to solve the above-mentioned problems, the earth retaining method of the present invention is to fix the earth retaining member and the curing agent injection pipe to each other by installing the curing agent injection pipes at predetermined intervals while being adjacent to the already-installed earth retaining members. Then, while pulling out the earth retaining member and the curing agent injection tube, the curing agent is injected into the ground to fill the gap after the earth retaining member is pulled out.

さらに、この発明の別の土留め工法は、溝を掘削し、長さ方向に沿って異なる位置に概ね等間隔で噴射口を有する硬化剤注入管が取り付けられた土留め部材で溝の両壁を土留めしながら溝内で作業をする土留め工法であって、溝を埋めた後に土留め部材を引き抜くとともに土留め部材に設けられた長さ方向に沿って異なる位置に概ね等間隔で噴射口を有する硬化剤注入管より複数の深さにおいて同時に硬化剤を地中に注入して土留め部材が引き抜かれた後の空隙を埋めるものである。Furthermore, another earth retaining method according to the present invention is a method of excavating a groove and retaining both walls of the groove with a retaining member to which a hardener injection pipe having injection holes at substantially equal intervals is attached at different positions along the length direction. The earth retaining method works in the groove while retaining the earth, and after filling the groove, pulls out the earth retaining member and injects at substantially equal intervals along the length direction provided in the earth retaining member. A hardening agent is simultaneously injected into the ground at a plurality of depths from a hardening agent injection tube having a mouth to fill the gap after the earth retaining member is pulled out.

この発明は、施工後にもシートパイル等の土留め部材の引き抜きによる地中の空隙を作らず、周囲の地盤や地下水の流れに変動を与えることがなく、環境問題を生じない施工方法、そのための土留め部材および土留め工事プラントを実現できるという効果がある。 The present invention does not create a void in the ground by pulling out a retaining member such as a sheet pile after construction, does not cause fluctuations in the surrounding ground and groundwater flow, and does not cause environmental problems, and therefore There is an effect that the earth retaining member and the earth retaining work plant can be realized.

この発明を実施するための最良の形態について、図面に基づいて説明する。図1はシートパイルを示す斜視図で、図2は硬化剤注入管の詳細を示す断面図、図3は土留め工事プラントを示す説明図、図4は硬化剤注入管の別の例の詳細を示す断面図、図5はシートパイルによる土留め工事の手順の手順を示す説明図である。 The best mode for carrying out the present invention will be described with reference to the drawings. FIG. 1 is a perspective view showing a sheet pile, FIG. 2 is a cross-sectional view showing details of a hardener injection pipe, FIG. 3 is an explanatory view showing a earth retaining work plant, and FIG. 4 is a detail of another example of the hardener injection pipe. FIG. 5 is an explanatory view showing the procedure of the earth retaining work by the sheet pile.

図1に示す例においては土留め部材として、シートパイル1を使用する。シートパイル1は、シートパイル本体部2(土留め部材本体部)と、硬化剤注入管3とを有する。シートパイル本体部2に取り付け孔等の取り付け手段4を設け、留金5等によって硬化剤注入管3を着脱自由な状態で取り付けている。取り付け孔や取り付け板などの取り付け手段は、硬化剤注入管3に設けてもよく、さらにシートパイル本体部2と硬化剤注入管3の双方に設けてもよい。これ以外に、硬化剤注入管3をシートパイル本体2に溶接して、一体に形成してもよい。シートパイル本体2は、シートパイルとして通常使用されているものでよい。硬化剤注入管3は、その先端部がシートパイル本体部2の下端より下に出るように取り付けられる。 In the example shown in FIG. 1, the sheet pile 1 is used as the earth retaining member. The sheet pile 1 includes a sheet pile main body portion 2 (a retaining member main body portion) and a curing agent injection tube 3. The sheet pile main body 2 is provided with attachment means 4 such as attachment holes, and the curing agent injection tube 3 is attached in a detachable state by a clasp 5 or the like. Attachment means such as attachment holes and attachment plates may be provided in the hardener injection tube 3, and may be provided in both the sheet pile main body 2 and the hardener injection tube 3. In addition to this, the curing agent injection pipe 3 may be welded to the sheet pile body 2 and integrally formed. The sheet pile main body 2 may be one normally used as a sheet pile. The curing agent injection tube 3 is attached so that the tip end thereof is below the lower end of the sheet pile main body 2.

硬化剤注入管3の先端部は様々な形状に成形することができる。図9は硬化剤注入管の先端部形状の例を示す説明図である。図9(a−1)は第1の先端部の例を示す正面図、図9(a−2)は同右側面図である。円柱を斜めに切断したような形状をしており、先端部には硬化剤注入管3の長さ方向に対して傾斜した面3aが形成されている。この先端部で最も突き出た部分がシートイル1に接するように配置し、留金5などの取り付け手段によって固定する。先端部に傾斜した面3aを設け、このような向きでシートイル1に取り付けることにより、硬化剤注入管3を地中へ打ち込むときに、先端部はシートパル1に対して押し付けられるような力が生じ、シートイル1と硬化剤注入管3は強く接合された状態で地中に設置される。 The tip of the hardener injection tube 3 can be formed into various shapes. FIG. 9 is an explanatory view showing an example of the shape of the tip of the curing agent injection tube. FIG. 9A-1 is a front view showing an example of the first tip, and FIG. 9A-2 is a right side view thereof. It has a shape that is obtained by obliquely cutting a cylinder, and a surface 3 a that is inclined with respect to the length direction of the hardener injection tube 3 is formed at the tip. The most protruding part in the distal end portion is arranged in contact with the sheet pile 1, it is secured by attachment means such as a clasp 5. A surface 3a inclined at the tip is provided, by attaching in such a direction to the sheet pile 1, when driving a curing agent injection tube 3 into the ground, so that the tip is pressed against Shitopa Lee le 1 a force is generated, the sheet pile 1 and the curing agent injection pipe 3 is installed in the ground in a state of being strongly bonded.

図9(b−1)は第2の先端部の例を示す正面図、図9(b−2)は同右側面図である。先端部には硬化剤注入管3の長さ方向に対して傾斜した面3aが形成されており、さらに側面でシートパイル1と接する側は平面状に形成されている。このように硬化剤注入管3の先端部の側面に平面を設けることにより、先端部においてシートイル1と硬化剤注入管3は隙間なく密着させることができるので、打ち込む際にシートイル1と硬化剤注入管3の間に土砂が入り込まなくなる。 FIG. 9B-1 is a front view showing an example of the second tip, and FIG. 9B-2 is a right side view thereof. A surface 3a that is inclined with respect to the length direction of the curing agent injection tube 3 is formed at the tip, and the side that contacts the sheet pile 1 on the side surface is formed in a flat shape. By providing such plane to the side surface of the distal end portion of the curing agent injection pipe 3, since the sheet pile 1 and the curing agent injection tube 3 at the distal end can be brought into close contact without a gap, the sheet when implanted pile 1 And no sand or sand enters between the hardener injection tube 3.

図9(c−1)は第3の先端部の例を示す正面図、図9(c−2)は同右側面図である。第2の先端部の例と同様に、先端部には硬化剤注入管3の長さ方向に対して傾斜した面3aが形成されており、さらに側面でシートパイル1と接する側は平面状に形成されている。そして、最先端の部分が尖った形に形成されており、第2の先端部の例のをさらに左右から切り取ったような形状になっている。このように先端を尖った形にすることにより、地中へ打ち込みやすくなる。 FIG. 9C-1 is a front view showing an example of the third tip, and FIG. 9C-2 is a right side view thereof. Similar to the example of the second tip portion, a surface 3a inclined with respect to the length direction of the hardener injection tube 3 is formed at the tip portion, and the side contacting the sheet pile 1 on the side surface is flat. Is formed. And the most advanced part is formed in the pointed shape, and it has become the shape which further cut off the example of the 2nd tip part from right and left. By making the tip pointed like this, it becomes easier to drive into the ground.

図9(d−1)は第4の先端部の例を示す正面図、図9(d−2)は同右側面図である。側面でシートパイル1と接する側は平面状に形成されている。シートパイル1と接する側の先端部には硬化剤注入管3の長さ方向に対して傾斜した面3aが形成されており、その逆側の先端部は概ね円錐状に形成されている。 FIG. 9D-1 is a front view showing an example of the fourth tip, and FIG. 9D-2 is a right side view thereof. The side in contact with the sheet pile 1 is formed in a planar shape. A surface 3a that is inclined with respect to the length direction of the hardener injection tube 3 is formed at the tip of the side in contact with the sheet pile 1, and the tip of the opposite side is formed in a substantially conical shape.

図9(e−1)は第5の先端部の例を示す正面図、図9(e−2)は同右側面図である。第4の先端部の例と同様に、側面でシートパイル1と接する側は平面状に形成されていて、シートパイル1と接する側の先端部には硬化剤注入管3の長さ方向に対して傾斜した面3aが形成されており、その逆側の先端部は概ね円錐状に形成されている。そして、傾斜した面3aがさらに左右から切り取られて尖った先端が形成されている。
Fig. 9 (e-1) is a front view showing an example of the fifth tip portion, and Fig. 9 (e-2) is a right side view thereof. As in the fourth tip portion, the side that contacts the sheet pile 1 on the side surface is formed in a flat shape, and the tip portion on the side that contacts the sheet pile 1 is in the length direction of the hardener injection tube 3. An inclined surface 3a is formed, and the tip on the opposite side is formed in a substantially conical shape. The inclined surface 3a is further cut off from the left and right to form a sharp tip.

図A(f−1)は第6の先端部の例を示す正面図、図9(f−2)は同右側面図である。先端部は円錐状に形成されており、鉛筆を削ったような形状になっている。硬化剤注入管3は打ち込む際にまっすぐ進行し、硬化剤注入管3を曲げるような力がかからない。 Fig. A (f-1) is a front view showing an example of the sixth tip portion, and Fig. 9 (f-2) is a right side view thereof. The tip portion is formed in a conical shape and is shaped like a sharpened pencil. The hardener injection tube 3 advances straight when driven, and no force is applied to bend the hardener injection tube 3.

図9(g−1)は第7の先端部の例を示す正面図、図9(g−2)は同右側面図である。先端は、軸方向に垂直な円形の面に形成されている。なお、図9に示されているの先端部の形状は例に過ぎず、これ以外の形状に加工してもよい。 FIG. 9G-1 is a front view showing an example of the seventh tip, and FIG. 9G-2 is a right side view thereof. The tip is formed in a circular surface perpendicular to the axial direction. In addition, the shape of the front-end | tip part shown by FIG. 9 is only an example, You may process it in shapes other than this.

硬化剤注入管3は、中空となっている管本体部6を有し、上端部には注入口7が設けられており、先端部には噴出口8が複数設けられている。また、管本体部6の内部で先端部付近には円柱状の栓9が設けられ、この栓9は付勢手段10によって上向きに付勢されている。この付勢手段10の付勢力によって栓9は噴出口8をふさぐ位置に保持されている(図2a)。しかし、注入口7より管本体部6に硬化剤が注入されるとその圧力によって栓9は下へ押し下げられ、噴射口8を塞がない位置に移動する(図2a)。なお、栓9は上部の外周部が斜めに切り取られている。この傾斜した切り取り面に沿って硬化剤は横向きに導かれ、噴射口8から横に向いて地中に噴射される。 The hardener injection tube 3 has a hollow tube main body 6, an injection port 7 is provided at the upper end, and a plurality of ejection ports 8 are provided at the tip. Further, a cylindrical plug 9 is provided in the vicinity of the tip inside the tube main body 6, and the plug 9 is biased upward by a biasing means 10. The stopper 9 is held in a position to close the spout 8 by the urging force of the urging means 10 (FIG. 2a). However, when the curing agent is injected into the tube body 6 from the injection port 7, the stopper 9 is pushed down by the pressure and moves to a position where the injection port 8 is not blocked (FIG. 2a). Note that the upper peripheral portion of the plug 9 is cut obliquely. The curing agent is guided laterally along the inclined cut surface, and is ejected from the ejection port 8 into the ground.

硬化剤注入管3は、先端に切削用の噴出口を有するものでもよい。図10は切削用の噴出口を有する硬化剤注入管を示す断面図である。先端部には下方向に空気や水を噴出するための切削用の噴出口5cが設けられている。また、栓9にも穴9aが貫通している。硬化剤注入管3を打ち込むときは、図10(a)に示すように栓9の穴9aが塞がれていない状態である。上部から空気、水、または空気と水の双方を供給すると、これらの流体は穴9aを通過し、切削用の噴出口5cから下向きに地中に噴出される。このようにして、空気や水を噴出して土砂や切削しながら硬化剤注入管3を進行させることができる。 The curing agent injection tube 3 may have a cutting outlet at the tip. FIG. 10 is a cross-sectional view showing a hardener injection tube having a cutting outlet. A cutting outlet 5c for ejecting air or water downward is provided at the tip. Moreover, the hole 9a also penetrates the stopper 9. When the hardener injection tube 3 is driven, the hole 9a of the plug 9 is not blocked as shown in FIG. When air, water, or both air and water are supplied from above, these fluids pass through the hole 9a and are ejected downward from the cutting outlet 5c into the ground. In this way, it is possible to advance the curing agent injection tube 3 while blowing air or water and removing earth or sand.

硬化剤を注入するときには図10(b)に示すように穴9aの径より少し大きいスティールボールXを上部より硬化剤注入管3の中に投入する。スティールボールXは穴9aを塞ぐ。ついで、上部より硬化剤を注入すると、栓9は下へ押し下げられ、噴射口8が開放される。この噴射口8より、硬化剤が地中へ注入される。この例の硬化剤注入管3の先端もさまざまな形状に形成することができ、図9に示された形状やそれ以外の形状を自由に選択できる。 When injecting the curing agent, as shown in FIG. 10B, a steel ball X slightly larger than the diameter of the hole 9a is introduced into the curing agent injection tube 3 from above. Steel ball X closes hole 9a. Next, when the curing agent is injected from the upper part, the stopper 9 is pushed down and the injection port 8 is opened. The curing agent is injected into the ground through the injection port 8. The tip of the hardener injection tube 3 of this example can also be formed in various shapes, and the shape shown in FIG. 9 and other shapes can be freely selected.

次に、比較的浅い場所でこのシートパイル1を使用した埋設工事の施工方法について図5に基づいて説明する。舗装21をカッターで切って取り除き、溝の両壁を構成すべき位置にシートパイル1を設置して溝壁が崩れるのを防止した上で、掘削を開始する。(図5a)。左右のシートパイル1間に横梁28を設置しながら所定の深さまで掘り進めて溝22を形成する(図5b)。左右のシートパイル1間に設けられた突っ張りのための横梁によりシートパイルの転倒を防止し、シートパイルが溝の両壁を確実に押さえるようにする。 Next, the construction method of the burying construction using this sheet pile 1 in a relatively shallow place will be described based on FIG. The pavement 21 is cut and removed by a cutter, and the sheet pile 1 is installed at a position where both walls of the groove should be formed to prevent the groove wall from collapsing, and then excavation is started. (Figure 5a). The groove 22 is formed by digging to a predetermined depth while installing the cross beam 28 between the left and right sheet piles 1 (FIG. 5b). The lateral piles provided between the left and right sheet piles 1 prevent the sheet piles from overturning, so that the sheet piles securely press both walls of the groove.

ここで、シートパイルの配置について説明する。土留めとして設置するシートパイルの全てを硬化剤注入管が取り付けられたシートパイル1にすることは必ずしも必要ではなく、硬化剤注入管付きシートパイル1と硬化剤注入管が取り付けられていない通常のシートパイル23を併用してもよい。この実施の形態においては、図4に示すように硬化剤注入管が取り付けられたシートパイル1に続いて硬化剤注入管が取り付けられていない通常のシートパイル23が2基又は3基設置され、また硬化剤注入管が取り付けられたシートパイル1が設置されるという繰り返しで配置される。シートパイル1の硬化剤注入管3から注入された硬化剤が到達する距離の範囲内で次の硬化剤注入管付きシートパイル1が設置されるように配置すればよい。 Here, the arrangement of the sheet pile will be described. It is not always necessary to make all the sheet piles to be installed as earth retaining plates into the sheet pile 1 to which the hardener injection pipe is attached, and the sheet pile 1 with the hardener injection pipe and the normal hardener injection pipe are not attached. The sheet pile 23 may be used in combination. In this embodiment, as shown in FIG. 4, two or three normal sheet piles 23 to which no curing agent injection tube is attached are installed following the sheet pile 1 to which the curing agent injection tube is attached, Moreover, it arrange | positions by repeating that the sheet pile 1 to which the hardening | curing agent injection | pouring pipe | tube was attached is installed. What is necessary is just to arrange | position so that the following sheet pile 1 with a hardening | curing agent injection tube may be installed within the range of the distance which the hardening | curing agent inject | poured from the hardening | curing agent injection tube 3 of the sheet pile 1 arrives.

このシートパイル1によって溝22の壁が崩れるのを防止し、その後の作業を溝内で安全に支障なく行えるようにする。溝22の底盤部を整地し、グリ24とよばれる小石を所定の厚さだけ敷き点圧を行う(図5c)。このグリ24の層の上に砂26と埋設物25を入れる(図5d)。砂26は埋設物25の上をある程度の厚さで覆う程度に入れる。さらに砂26の層の上に土27を盛って溝22を完全に埋める(図5e)。ここで、砂26および土27は十分な強度に固められるように25cm程度の厚さずつ入れては点圧器で点圧しながら盛っていく。 The sheet pile 1 prevents the wall of the groove 22 from collapsing, and the subsequent work can be safely performed without any trouble in the groove. The bottom plate portion of the groove 22 is leveled, and a pebble called the grits 24 is spread by a predetermined thickness to perform point pressure (FIG. 5c). Sand 26 and buried object 25 are put on the layer of the glue 24 (FIG. 5d). The sand 26 is put so as to cover the buried object 25 with a certain thickness. Further, the soil 27 is placed on the layer of sand 26 to completely fill the groove 22 (FIG. 5e). Here, the sand 26 and the soil 27 are put in a thickness of about 25 cm so as to be hardened to a sufficient strength, and are piled up while applying a point pressure with a point pressure device.

溝22が全て埋まるまで土27を盛ったら、シートパイルの引抜きを行う。シートパイルは端から順次引き抜くが、硬化剤注入管付きシートパイル1の引き抜きは硬化剤注入管3より地中に硬化剤を注入しながら行う。 When the soil 27 is piled up until all the grooves 22 are filled, the sheet pile is pulled out. The sheet pile is sequentially pulled out from the end, but the sheet pile 1 with the curing agent injection tube is pulled out while injecting the curing agent into the ground from the curing agent injection tube 3.

ここで、硬化剤の注入について説明する。土留め工事プラント11には水タンク12(給水手段)と材料貯留部13が設けられている。材料貯留部13にはセメント、ベントナイト、ケイ酸などの硬化剤の原材料が貯留されている。ミキサー14はホース15によって水タンク12および材料貯留部13と結ばれている。ミキサー14に送られた硬化剤の原料と水は混ぜ合わされ、硬化剤が調製される。注入ポンプ16から続いているホース15を硬化剤注入を行うべき位置のシートパイル1の硬化剤注入管3の注入口7に接続し、注入ポンプ16を作動させて、ミキサー14で混ぜ合わされた硬化剤を硬化剤注入管3へ送り、地中へ硬化剤を注入する。 Here, injection | pouring of a hardening | curing agent is demonstrated. The earth retaining work plant 11 is provided with a water tank 12 (water supply means) and a material storage unit 13. The material reservoir 13 stores a raw material of a curing agent such as cement, bentonite, and silicic acid. The mixer 14 is connected to the water tank 12 and the material reservoir 13 by a hose 15. The raw material of the hardener sent to the mixer 14 and water are mixed together to prepare the hardener. The hose 15 continuing from the injection pump 16 is connected to the injection port 7 of the curing agent injection tube 3 of the sheet pile 1 where the curing agent is to be injected, the injection pump 16 is operated, and the mixing mixed by the mixer 14 is performed. The agent is sent to the curing agent injection tube 3 to inject the curing agent into the ground.

注入する硬化剤は、施工場所の土質に合わせて適宜選択すればよいが、比較的ゲルタイムが長く強度の高い材料を選定することが好ましい。本例ではゲルタイムが10〜20分程度のセメント系の硬化剤を使用している。この硬化剤は地中に均一に行き渡り、一時的な体積膨張を起こさないので、周辺の地面を持ち上げるようなことが起こらない。一方、地下水が通っている場所の近くや土圧がかかっている場所などでは、ゲルタイムの短い硬化剤を使うこともできる。 The curing agent to be injected may be appropriately selected according to the soil quality at the construction site, but it is preferable to select a material having a relatively long gel time and high strength. In this example, a cement-type curing agent having a gel time of about 10 to 20 minutes is used. This hardener spreads uniformly in the ground and does not cause temporary volume expansion, so that it does not lift the surrounding ground. On the other hand, hardeners with short gel times can be used near places where groundwater passes or where earth pressure is applied.

硬化剤注入管3より地中に注入された硬化剤は、先に引き抜かれたシートパイル23および硬化剤注入管付きシートパイル1自体によってできる空隙を埋める。したがって、空隙に起因する地中の土壌の移動や地下水の水路の変化に伴う地盤状態の変動が発生しない。また、硬化剤は溝22内のグリ・砂・土にも浸透し、粒子間にある小さな空隙を埋めるとともに、溝内の強度を高める。 The curing agent injected into the ground through the curing agent injection tube 3 fills the gap formed by the sheet pile 23 drawn out earlier and the sheet pile 1 with the curing agent injection tube itself. Therefore, there is no change in the ground condition due to the movement of soil in the ground and the change of the groundwater channel due to the gap. Further, the curing agent penetrates into the grits, sand, and soil in the grooves 22 to fill small gaps between the particles and increase the strength in the grooves.

硬化剤を供給するプラント11内には流量計17が設けられており、注入した硬化剤の量が把握できるようになっている。必要量の硬化剤を注入したら注入をやめ、その硬化剤注入管付きシートパイル1とそれに続く通常のシートパイル23を引く抜く。ついで、次の硬化剤注入管付きシートパイル1により硬化剤を注入する。以上、この作業を繰り返し、全てのシートパイル1,23を引き抜いたら、溝22の上に舗装21を敷き、工事を終了する。 A flow meter 17 is provided in the plant 11 for supplying the curing agent so that the amount of the injected curing agent can be grasped. When the required amount of the curing agent is injected, the injection is stopped, and the sheet pile 1 with the curing agent injection tube and the subsequent normal sheet pile 23 are pulled out. Next, a curing agent is injected by the next sheet pile 1 with a curing agent injection tube. As described above, when this operation is repeated and all the sheet piles 1 and 23 are pulled out, the pavement 21 is laid on the groove 22 and the construction is completed.

なお、硬化剤注入管としては、図4に示す二重管を使うこともできる。管本体部が外管6aと内管6bの二重構造になっており、例えば2種類の薬液(A液、B液)を注入し、ゲルタイムを10秒以下にすることもできる。この例の硬化剤注入管は下方向に噴出口8を有する。したがって、地中に打ち込む際に、下方向に空気を噴出しながら掘り進むことができ、後述の簡易矢板等を用いた方法などに適用して、土留め部材の設置と独立して別途設置するような使用もできる。これ以外にも硬化剤注入管としては、二重管や三重管などの多重管を含め、さまざまなものを使用することができる。図6に硬化剤注入管の変形例を示す。図6a〜cは硬化剤を横方向に噴出するタイプのものであり、主にシートパイルやH鋼に取り付けた状態で地中に挿入する方法に適したものである。図6d〜fは硬化剤を下方向に噴出するタイプのものである。図6b、eの二重管や図6c、fの三重管などを使用すると、多種類の薬液を使用することができる。 In addition, as a hardening | curing agent injection | pouring pipe | tube, the double pipe | tube shown in FIG. 4 can also be used. The tube body has a double structure of an outer tube 6a and an inner tube 6b. For example, two types of chemical solutions (A solution and B solution) can be injected to reduce the gel time to 10 seconds or less. The hardener injection tube of this example has a jet 8 in the downward direction. Therefore, when driving into the ground, it can be dug while blowing air downward, and it is applied separately to the method using a simple sheet pile etc., which will be described later, and installed separately from the installation of the earth retaining member. Can also be used. In addition to this, various types of hardener injection tubes can be used including multiple tubes such as double tubes and triple tubes. FIG. 6 shows a modification of the hardener injection tube. FIGS. 6a to 6c are of the type in which the curing agent is ejected in the lateral direction, and are suitable for a method of inserting into the ground mainly in a state of being attached to a sheet pile or H steel. 6d to 6f are of the type in which the curing agent is jetted downward. When the double tube shown in FIGS. 6b and 6e and the triple tube shown in FIGS. 6c and 6f are used, various kinds of chemical solutions can be used.

以上、溝内に水道管を埋設する工事の例で説明をしたが、本発明の適用はこれにとどまらない。シートパイルにより土留めを行いながら行う工事について広く適用できることは明らかである。これらの場合も、工事の終盤において土留めに使用したシートパイルを引き抜くことに変わりがないので、硬化剤注入管付きシートパイルを適宜配置しておき、上述の通り硬化剤注入管付きより硬化剤を注入して先のシートパイルによって生じた空隙を埋めながら、シートパイルを引き抜いていけば、地中に空隙を残すことなく施工ができる。硬化剤注入により周囲の地盤の強化が合わせて行われることはいうまでもない。 As mentioned above, although the example of the construction which embeds a water pipe in a ditch was explained, application of the present invention is not restricted to this. It is clear that it can be widely applied to the work to be done while retaining the soil with a sheet pile. In these cases as well, there is no change in pulling out the sheet pile used for the earth retaining in the final stage of the construction. Therefore, the sheet pile with the curing agent injection tube is appropriately arranged, and the curing agent is more than the one with the curing agent injection tube as described above. If the sheet pile is pulled out while filling the gap generated by the previous sheet pile, the construction can be performed without leaving a gap in the ground. It goes without saying that the surrounding ground is strengthened by injecting the hardener.

次に本発明の別の実施形態について説明する。図7は、簡易矢板による土留め工事の手順を示す説明図である。舗装21をカッターで切って取り除き、溝の両壁となる位置に簡易矢板29を押し込みながら溝を掘削する(図7a)。溝の掘削を進めながら途中で簡易矢板29の転倒防止のため、横梁28を左右両壁の簡易矢板29間に設けながら、所定の深さまで溝を掘り進める(図7b)。掘削が完了したならば、簡易矢板29の側部に隣接するように硬化剤注入管3を所定間隔で設置する(図7c)。ここでは、1m程度の間隔で硬化剤注入管3を設置しているが、各硬化剤注入管3から硬化剤が到達する距離によってこの間隔を適宜決めればよい。 Next, another embodiment of the present invention will be described. FIG. 7 is an explanatory diagram showing a procedure of earth retaining work using a simple sheet pile. The pavement 21 is cut and removed with a cutter, and the groove is excavated while the simple sheet pile 29 is pushed into the position to be both walls of the groove (FIG. 7a). In order to prevent the simple sheet pile 29 from overturning while the groove is being excavated, the groove is advanced to a predetermined depth while the cross beam 28 is provided between the simple sheet piles 29 on the left and right walls (FIG. 7b). When excavation is completed, the hardener injection pipes 3 are installed at predetermined intervals so as to be adjacent to the side portion of the simple sheet pile 29 (FIG. 7c). Here, the curing agent injection pipes 3 are installed at intervals of about 1 m, but this interval may be appropriately determined depending on the distances that the curing agents reach from the respective curing agent injection pipes 3.

ついで、底部を整地し、所定の厚さまでグリ24を敷き、点圧を行う(図7d)。溝内に埋設物25を設置し、砂26の充填・点圧を繰り返しながら、埋設物25を固定する(図7e)。砂26の充填および横梁28の除去を行ったら、上層部に土27を充填し、さらに点圧を行う(図7f)。溝22が完全に埋まるまで土27を充填したら、簡易矢板29を引き抜く(図7g)。簡易矢板29を引き抜いた後に、硬化剤注入管3を引き上げながら硬化剤を地中に注入する。ここでは硬化剤注入管3を25cmずつ引き上げながら硬化剤を注入していった。簡易矢板29の引き上げによってできた空隙は、注入された硬化剤によって埋められるので、その後に地盤変動が生じることはない。なお、簡易矢板の変わりに鉄板等の土留め部材を使用しても同様である。 Next, the bottom is leveled, the grits 24 are laid down to a predetermined thickness, and point pressure is applied (FIG. 7d). The embedded object 25 is installed in the groove, and the embedded object 25 is fixed while repeating the filling and the point pressure of the sand 26 (FIG. 7e). When the sand 26 is filled and the cross beam 28 is removed, the upper layer is filled with the soil 27 and further subjected to point pressure (FIG. 7f). When the soil 27 is filled until the groove 22 is completely filled, the simple sheet pile 29 is pulled out (FIG. 7g). After pulling out the simple sheet pile 29, the curing agent is injected into the ground while pulling up the curing agent injection tube 3. Here, the curing agent was injected while pulling up the curing agent injection tube 3 by 25 cm. Since the gap formed by pulling up the simple sheet pile 29 is filled with the injected curing agent, ground fluctuation does not occur thereafter. In addition, it is the same even if it uses earth retaining members, such as an iron plate, instead of a simple sheet pile.

さらに別の実施形態について図8に基づいて説明する。図8は、親杭30と横矢板31による土留め工事の手順を示す説明図である。溝22の両壁となる位置に沿ってH鋼等の親杭30を所定間隔で打設する(図8a)。あわせて、硬化剤注入管3を親杭30に隣接して設置する。硬化剤注入管3は予め親杭30に取り付けられた状態で設置してもよく、親杭30とは独立して設置してもよい。舗装21を取り除き、親杭30の間に溝の両壁となる横矢板31を設置しながら、溝を掘り進める(図8b)。溝の掘削を進めながら途中で横矢板31の転倒防止のため、横梁28を左右の横矢板31間に設けながら、所定の深さまで溝を掘り進める(図8c)。ついで、底部を整地し、所定の厚さまでグリ24を敷き、点圧を行う(図8d)。溝内に埋設物25を設置し、横矢板31を撤去しながら砂26の充填・点圧を繰り返して行い、埋設物25を固定する(図8e)。砂25の充填・点圧および横梁28・横矢板31の撤去を行ったら、上層部に土27を充填し、さらに点圧を行う(図8f)。溝22が完全に埋まるまで土27を充填したら、硬化剤注入管3で硬化剤を注入しながら親杭30を引き抜く。親杭30の引き上げによってできる空隙は、注入された硬化剤によって埋められる。親杭30の撤去が終了したら、溝22の上面に舗装の復旧を行う(図8g)。 Still another embodiment will be described with reference to FIG. FIG. 8 is an explanatory diagram showing a procedure of earth retaining work using the main pile 30 and the lateral sheet pile 31. A main pile 30 made of H steel or the like is driven at predetermined intervals along the positions of both walls of the groove 22 (FIG. 8a). In addition, the curing agent injection pipe 3 is installed adjacent to the parent pile 30. The curing agent injection pipe 3 may be installed in a state of being attached to the parent pile 30 in advance, or may be installed independently of the parent pile 30. The pavement 21 is removed, and the groove is dug while installing the cross sheet piles 31 serving as both walls of the groove between the parent piles 30 (FIG. 8b). In order to prevent the horizontal sheet pile 31 from falling over the course of excavating the groove, the groove is advanced to a predetermined depth while the horizontal beam 28 is provided between the left and right horizontal sheet piles 31 (FIG. 8c). Next, the bottom is leveled, the grits 24 are laid down to a predetermined thickness, and point pressure is applied (FIG. 8d). The buried object 25 is placed in the groove, and the sand 26 is removed and the filling of the sand 26 is repeated and the point pressure is repeated while fixing the buried object 25 (FIG. 8e). When the sand 25 is filled and the point pressure is removed and the cross beam 28 and the cross sheet pile 31 are removed, the upper layer is filled with the soil 27 and further subjected to the point pressure (FIG. 8f). When the soil 27 is filled until the groove 22 is completely filled, the parent pile 30 is pulled out while injecting the hardener with the hardener injection tube 3. A void formed by pulling up the parent pile 30 is filled with the injected curing agent. When the removal of the parent pile 30 is completed, the pavement is restored on the upper surface of the groove 22 (FIG. 8g).

ここまでの例においては、硬化剤注入管の設置は土留め部材の設置時に行うものであった。しかし、既に埋設工事などのために設置された土留め部材であって、地中に残されたものもある。これらの土留め部材も単に引き抜けば地中に空隙を生じ、周囲に地盤沈下などの問題を発生させることに変わりがない。そこで、既に設置された土留め部材に隣接させながら硬化剤注入管3を所定間隔で設置し、土留め部材と硬化剤注入管をネジ止めや溶接などによって相互に固定して、土留め部材と硬化剤注入管を引き抜きながら硬化剤を地中に注入することもできる。このように硬化剤を地中に注入することによって土留め部材が引き抜かれた後の空隙を埋める。この場合、図9のa〜eの例のような先端部に軸方向に対して傾斜した面3bを有するものを使用すると、硬化剤注入管3を地中へ打ち込むときに、先端部はシートパイル1に対して押し付けられながら進行していく。このようにシートパイルの表面を滑りながら進行するほうが、土砂の抵抗を受けながら進行するよりも抵抗が少ないので、地中への設置が容易になる。 In the examples so far, the hardener injection tube is installed when the earth retaining member is installed. However, there are earth retaining members that have already been installed for burial work, etc., and remain in the ground. Even if these earth retaining members are simply pulled out, a void is formed in the ground, and there is no change in generating problems such as land subsidence. Therefore, the hardener injection pipe 3 is installed at a predetermined interval while being adjacent to the already installed earth retaining member, and the earth retaining member and the hardener injection pipe are fixed to each other by screwing or welding, It is also possible to inject the curing agent into the ground while pulling out the curing agent injection tube. In this way, the space after the earth retaining member is pulled out is filled by injecting the curing agent into the ground. In this case, when the tip portion having a surface 3b inclined with respect to the axial direction is used as in the example of FIGS. 9a to 9e, when the hardener injection tube 3 is driven into the ground, the tip portion is a sheet. It progresses while being pressed against pile 1. In this way, the traveling while sliding on the surface of the sheet pile has less resistance than the traveling while receiving the resistance of earth and sand, so that the installation in the ground becomes easy.

硬化材の注入は先端部からだけでなく、硬化剤注入管3の途中からも注入することができる。図11は注入の方法を示す説明図である。図11(a)に示すように、噴出口を先端部のみに設け、硬化剤注入管がほぼ完全に引き抜かれるまで注入を行うこともできる。また、図11(b)に示すように、先端部のほか、地表から先端部までの約2分の1の深さに当たる位置にも噴出口を設け、2箇所の深さで同時に注入を行うこともできる。この場合、硬化剤注入管3を半分引き抜くまでの間だけ注入することにより、先端部から地表部付近までの全ての深さにおいて硬化剤を注入することができるので、注入時間を約半分に短縮することができる。 The curing material can be injected not only from the tip portion but also from the middle of the curing agent injection tube 3. FIG. 11 is an explanatory view showing an injection method. As shown in FIG. 11 (a), it is possible to provide the injection port only at the tip portion and inject until the hardener injection tube is almost completely pulled out. As shown in FIG. 11 (b), in addition to the tip portion, a jet outlet is provided at a position corresponding to about half the depth from the ground surface to the tip portion, and injection is simultaneously performed at two depths. You can also. In this case, since the curing agent can be injected at all depths from the front end portion to the vicinity of the ground surface by injecting only until the curing agent injection tube 3 is pulled out by half, the injection time is reduced to about half. can do.

図11(c)に示す例では、地表から先端部までの深さを約3等分し、それぞれの深さにほぼ等間隔で噴出口を設け、これらの噴出口から同時に硬化剤を注入する。注入する時間は、約3分の1に短縮することができる。 In the example shown in FIG. 11 (c), the depth from the ground surface to the tip is divided into approximately three equal parts, and jets are provided at almost equal intervals, and the curing agent is simultaneously injected from these jets. . The injection time can be reduced to about one third.

図11(b)、(c)に示す多段式注入の例では、硬化剤注入管3は2重管または3重管になっており、2または3の通路が同心円状に形成されている。そして、各通路を通る硬化材の噴出口がそれぞれ異なる深さに設けられている。図11(b)、(c)の例では、上部から先端部まで外径は一定になっている。 In the example of the multistage injection shown in FIGS. 11B and 11C, the hardener injection tube 3 is a double tube or a triple tube, and two or three passages are formed concentrically. And the spout of the hardening material which passes through each channel | path is each provided in the different depth. In the examples of FIGS. 11B and 11C, the outer diameter is constant from the top to the tip.

図12も多段式の硬化剤注入管の例を示す断面図であるが、変形例を示している。3重管構造になっているが、最も外の管は、地表から約3分の1の深さで終わっている。この約3分の1の深さの位置に噴出口が設けられており、最も外の通路を通る硬化剤が噴出される。その内側の管は地表から約3分の2の深さまで伸びでおり、その深さに噴出口が設けられいる。最も内側の管は最先端の深さ、すなわちシートパイルの下端の深さまで伸びでおり、やはり噴出口が設けられている。なお上部には専用のスイベル18が設けられており、それぞれの噴出口へつながる注入口が項けられている。 FIG. 12 is also a cross-sectional view showing an example of a multistage curing agent injection tube, but shows a modification. Although it has a triple pipe structure, the outermost pipe ends at a depth of about one third from the ground surface. A jet outlet is provided at a position having a depth of about one third, and the curing agent passing through the outermost passage is jetted. The inner pipe extends from the surface to a depth of about two-thirds, and a spout is provided at that depth. The innermost tube extends to the most advanced depth, i.e. the depth of the lower end of the sheet pile, and is also provided with a spout. In addition, a dedicated swivel 18 is provided in the upper part, and an injection port connected to each jet port is mentioned.

図13はスイベルの例を示す断面図である。図13(a)は2重管用、図13(b)は3重管用を示す。たとえば、2重管の硬化剤注入管用の場合、スイベルも2重管構造を有する。上部には、注入ホース取り付け部19が2つ設けられており、それぞれ、内側の硬化剤通路および外側の硬化剤通路に硬化剤を供給することができる。先端部にはネジ部18aが設けられていて、硬化剤注入管3の上端部に接続できるようになっていて、スイベル18と硬化剤注入管3の内側の硬化剤通路同士および外側の硬化剤通路同士がつながる。3重管の場合も同様であり、3つの注入ホース取り付け部19が設けられており、スイベル18の3つの通路を介して硬化剤注入管3の通路へ硬化剤を供給できるようになっている。 FIG. 13 is a cross-sectional view showing an example of a swivel. FIG. 13A shows a case for a double pipe, and FIG. 13B shows a case for a triple pipe. For example, in the case of a double tube hardener injection tube, the swivel also has a double tube structure. Two injection hose attachment portions 19 are provided on the upper portion, and the curing agent can be supplied to the inner curing agent passage and the outer curing agent passage, respectively. A screw portion 18a is provided at the distal end portion so that it can be connected to the upper end portion of the hardener injection tube 3, and the hardener passages inside the swivel 18 and the hardener injection tube 3 and the external hardener. The passages are connected. The same applies to the case of a triple pipe, and three injection hose attachment portions 19 are provided so that the curing agent can be supplied to the passage of the curing agent injection pipe 3 through the three passages of the swivel 18. .

図14は、硬化剤注入管の接続部材の例を示す断面図である。深いところへ硬化剤を注入する場合、硬化剤注入管を複数のロッドに分割し、接続部材20で接続することができる。図14は、2重管の場合を示している。接続部材20は硬化剤注入管3の内側の硬化剤通路同士をつなぐ中心部の通路20aと外側の硬化剤通路同士をつなぐ外側の通路20bを有する。図14(a)に示すように、接続部材20の上下にネジ部を設けてロッド同士をネジ部によって接続してもよく、一方をOリングを介した差込式の接続にしてもよい。 FIG. 14 is a cross-sectional view showing an example of a connection member of a hardener injection tube. When injecting the curing agent into a deep place, the curing agent injection tube can be divided into a plurality of rods and connected by the connecting member 20. FIG. 14 shows the case of a double pipe. The connecting member 20 has a central passage 20 a that connects the inner hardener passages of the hardener injection pipe 3 and an outer passage 20 b that connects the outer hardener passages. As shown to Fig.14 (a), a thread part may be provided in the upper and lower sides of the connection member 20, and rods may be connected by a thread part, and one side may be made into the insertion type connection via an O-ring.

また、硬化剤に空気を混合して注入し、砂質土など注入しにくい土質でも均一に硬化剤を行き渡せることができる。図17に示すようなエジェクト装置により空気を薬液に混入して硬化剤注入管3に送り込む。 Also, air can be mixed and injected into the hardener, and the hardener can be evenly distributed even in soils that are difficult to inject, such as sandy soil. Air is mixed into the chemical solution by an ejecting apparatus as shown in FIG.

図12、図14、図15に示すような多段式硬化剤注入管は、複数の異なる深さにおいて同時に硬化剤を注入できるので、土留め部材が設けられた全深さについて短時間で注入作業を行うことができる。したがって、多段式硬化剤注入管は土留め部材の引き抜きの際に使用すると、特に効果的である。しかし、この多段式硬化剤注入管は、これ以外にも広い用途で地中への硬化剤注入に適用することができる。図16はエアランナー工法の例を示す説明図である。この例においては、ボーリングマシン41によって硬化剤注入管3を設置している。ここでは、A液・B液の2種類の薬剤をグラウトポンプ42によってエジェクト装置43へ送り込む。エジェクト装置43にはエアコンプレッサー44も接続されている。図17はエジェクト装置43の詳細を示す断面図である。エジェクト装置43によってA液・B液の混合液と空気が混ぜ合わされ、硬化剤注入ホース45とスイベルを介して硬化剤注入管3へ供給される。 Since the multi-stage type hardener injection tube as shown in FIGS. 12, 14, and 15 can inject the hardener simultaneously at a plurality of different depths, the injection work can be performed in a short time for the entire depth where the retaining members are provided. It can be performed. Therefore, the multi-stage type hardener injection tube is particularly effective when used when the retaining member is pulled out. However, this multistage curing agent injection tube can be applied to the injection of a curing agent into the ground for a wide range of uses other than this. FIG. 16 is an explanatory view showing an example of the air runner method. In this example, the hardening agent injection pipe 3 is installed by a boring machine 41. Here, two types of drugs, liquid A and liquid B, are sent to the ejecting device 43 by the grout pump 42. An air compressor 44 is also connected to the ejecting device 43. FIG. 17 is a cross-sectional view showing details of the ejecting device 43. The ejector 43 mixes the liquid mixture of the A liquid and the B liquid and air, and supplies them to the hardener injection pipe 3 through the hardener injection hose 45 and the swivel.

硬化剤に空気を混合して地中に注入するので、硬化剤は広範囲に均一に行き渡るが、この発明の多段式硬化剤注入管を使用することによって、最深部から地表までの深さの範囲を一回の注入作業で効率的に行うことができる。したがって、作業時管を短縮でき、深さ方向にも均一な注入作業が行える。 Since the hardener is mixed with air and injected into the ground, the hardener spreads uniformly over a wide range, but by using the multi-stage hardener injection tube of this invention, the depth range from the deepest part to the ground surface Can be efficiently performed by a single injection operation. Therefore, the working tube can be shortened and uniform injection work can be performed in the depth direction.

エアランナー工法においては、硬化剤注入管をケーシングに入れ、予め掘られた孔に硬化剤注入管をケーシングとともに設置することもできる。設置後、ケーシングを取り出し、硬化剤を注入する。 In the air runner method, the curing agent injection tube can be placed in the casing, and the curing agent injection tube can be installed together with the casing in a hole dug in advance. After installation, remove the casing and inject the curing agent.

この発明のシートパイルは、地中に水道管やガス管等を埋設する工事の施工等シートパイル等の土留め部材により土留めを行いながら行う工事について広く利用できるものである。土留め部材の跡に生じる空隙を残さないので、空隙に起因する地中の土壌の移動や地下水の水路の変化に伴う地盤状態の変動を発生させなることがなく、安全で環境への影響が少ない土留め工事が実現できる。 The sheet pile according to the present invention can be widely used for constructions that are carried out with earth retaining members such as sheet piles, such as construction for embedding water pipes and gas pipes in the ground. Since there are no gaps left in the traces of the earth retaining members, there will be no changes in the ground conditions due to the movement of soil in the ground due to the gaps and changes in the groundwater channels, which has a safe and environmental impact. Less earth retaining work can be realized.

シートパイルを示す斜視図である。It is a perspective view which shows a sheet pile. 硬化剤注入管の詳細を示す断面図である。It is sectional drawing which shows the detail of a hardening | curing agent injection pipe. 埋設工事ための現場プラントを示す説明図である。It is explanatory drawing which shows the site plant for burial construction. 硬化剤注入管の別の例を示す断面図である。It is sectional drawing which shows another example of a hardening | curing agent injection pipe. シートパイルによる土留め工事の手順を示す説明図である。It is explanatory drawing which shows the procedure of the earth retaining work by a sheet pile. 硬化剤注入管の変形例を示す断面図である。It is sectional drawing which shows the modification of a hardening | curing agent injection pipe. 簡易矢板による土留め工事の手順を示す説明図である。It is explanatory drawing which shows the procedure of the earth retaining work by a simple sheet pile. 親杭と横矢板による土留め工事の手順を示す説明図である。It is explanatory drawing which shows the procedure of the earth retaining work by a main pile and a horizontal sheet pile. 硬化剤注入管の先端部を示す説明図である。It is explanatory drawing which shows the front-end | tip part of a hardening | curing agent injection pipe. 硬化剤注入管の別の例を示す断面図である。It is sectional drawing which shows another example of a hardening | curing agent injection pipe. 硬化剤の注入を示す説明図である。It is explanatory drawing which shows injection | pouring of a hardening | curing agent. 多段式硬化剤注入管の例を示す説明図である。It is explanatory drawing which shows the example of a multistage hardener injection pipe. スイベルの例を示す断面図である。It is sectional drawing which shows the example of a swivel. 硬化剤注入管の接続部材の例を示す断面図である。It is sectional drawing which shows the example of the connection member of a hardening | curing agent injection pipe. 多段式硬化剤注入管の別の例を示す説明図である。It is explanatory drawing which shows another example of a multistage hardener injection tube. エアランナー工法の例を示す説明図である。It is explanatory drawing which shows the example of an air runner construction method. エジェクト装置の詳細を示す断面図である。It is sectional drawing which shows the detail of an eject apparatus.

符号の説明Explanation of symbols

1.シートパイル(土止め部材)
2.シートパイル本体部(土止め部材本体部)
3.硬化剤注入管
4.硬化剤注入管取り付け手段
5.留め金
6.管本体部
7.注入口
8.噴出口
9.栓
10.付勢手段
11.土留め工事プラント
12.水タンク
13.材料貯留部
14.ミキサー
15.ホース
16.注入ポンプ
17.流量計
18.スイベル
19.注入ホース取り付け部
20.接続部材
21.舗装
22.溝
23.シートパイル
24.グリ(小石)
25.埋設物
26.砂
27.土
28.横梁
29.簡易矢板
30.親杭
31.横矢板
41.ボーリングマシン
42.グラウトポンプ
43.エジェクト装置
44.エアコンプレッサー
45.硬化剤注入ホース


1. Sheet pile
2. Sheet pile body (earth retaining member body)
3. Hardener injection tube 4. 4. Hardener injection tube attachment means Clasp 6. 6. Pipe body part Inlet 8. Spout 9 Stopper 10. Biasing means 11. Earth retaining work plant 12. Water tank 13. Material reservoir 14. Mixer 15. Hose 16. Infusion pump 17. Flow meter 18. Swivel 19. Injection hose attachment part 20. Connecting member 21. Pavement 22. Groove 23. Sheet pile 24. Chestnut (pebbles)
25. Buried object 26. Sand 27. Sat 28. Cross beam 29. Simple sheet pile 30. Parent pile 31. Horizontal sheet pile 41. Boring machine 42. Grout pump 43. Ejecting device 44. Air compressor 45. Hardener injection hose


Claims (1)

既に設置された土留め部材に隣接させながら硬化剤注入管を所定間隔で設置し、土留め部材と硬化剤注入管を相互に固定し、土留め部材と硬化剤注入管を引き抜きながら硬化剤を地中に注入して土留め部材が引き抜かれた後の空隙を埋める土留め工法。 The hardener injection pipes are installed at predetermined intervals while being adjacent to the already-installed earth retaining member, the earth retaining member and the hardener injection pipe are fixed to each other, and the hardener is removed while pulling out the earth retaining member and the hardener injection pipe. Earth retaining method that fills the gap after the earth retaining member is pulled out by pouring into the ground.
JP2004167868A 2004-03-09 2004-06-07 Earth retaining method Active JP3940735B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004167868A JP3940735B2 (en) 2004-03-09 2004-06-07 Earth retaining method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2004066417 2004-03-09
JP2004167868A JP3940735B2 (en) 2004-03-09 2004-06-07 Earth retaining method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2006173512A Division JP2006291701A (en) 2004-03-09 2006-06-23 Earth retaining construction method

Publications (2)

Publication Number Publication Date
JP2005290963A JP2005290963A (en) 2005-10-20
JP3940735B2 true JP3940735B2 (en) 2007-07-04

Family

ID=35324203

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004167868A Active JP3940735B2 (en) 2004-03-09 2004-06-07 Earth retaining method

Country Status (1)

Country Link
JP (1) JP3940735B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009185494A (en) * 2008-02-05 2009-08-20 Shinichi Yamashita Earth retaining method and excavating member for earth retaining member vertical installation used for the method
JP2011236637A (en) * 2010-05-10 2011-11-24 Shinichi Yamashita Removal method of earth retaining member and slope strengthening block installation method using the same
CN101922148B (en) * 2009-06-15 2012-07-18 王顺华 Bridge and culvert type sheet-pile structure
JP2020125613A (en) * 2019-02-04 2020-08-20 大地 山下 Earth retention member removal method and, encapsulation method of contaminated soil

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4897985B2 (en) * 2006-10-18 2012-03-14 伸一 山下 Hardener injection pipe for earth retaining work and earth retaining method
JP5572469B2 (en) * 2010-07-27 2014-08-13 清水建設株式会社 Hardener injection mechanism
JP2016148137A (en) * 2015-02-10 2016-08-18 大成建設株式会社 Method for removing earth retaining member
JP6615494B2 (en) * 2015-05-29 2019-12-04 大地 山下 Removal method of retaining members

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57108311A (en) * 1980-12-25 1982-07-06 Giken Seisakusho:Kk Steel sheet pile
JPS57108312A (en) * 1980-12-25 1982-07-06 Giken Seisakusho:Kk Steel sheet pile
JPS6458713A (en) * 1987-08-27 1989-03-06 Kyowa Seisakusho Kk Cavitation-preventing sheet pile and construction using same
JP2680291B2 (en) * 1995-09-22 1997-11-19 三井不動産建設株式会社 Underground buffer wall and buffer plate
JP2003176531A (en) * 1999-08-24 2003-06-24 Nippon Sogo Bosui Kk High pressure injection stirring and mixing construction method and high pressure injection stirring and mixing device
JP3550392B2 (en) * 2001-09-20 2004-08-04 有限会社 ニューテック研究▲しゃ▼ Ground improvement method and ground improvement equipment
JP2003286717A (en) * 2002-01-28 2003-10-10 Raito Kogyo Co Ltd High-pressure injection grouting soil-improvement method
JP3697429B2 (en) * 2002-07-25 2005-09-21 株式会社上肥 Sheet pile embedding auxiliary device and method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009185494A (en) * 2008-02-05 2009-08-20 Shinichi Yamashita Earth retaining method and excavating member for earth retaining member vertical installation used for the method
CN101922148B (en) * 2009-06-15 2012-07-18 王顺华 Bridge and culvert type sheet-pile structure
JP2011236637A (en) * 2010-05-10 2011-11-24 Shinichi Yamashita Removal method of earth retaining member and slope strengthening block installation method using the same
JP2020125613A (en) * 2019-02-04 2020-08-20 大地 山下 Earth retention member removal method and, encapsulation method of contaminated soil
JP7277157B2 (en) 2019-02-04 2023-05-18 大地 山下 Method for removing earth retaining members and method for containing contaminated soil

Also Published As

Publication number Publication date
JP2005290963A (en) 2005-10-20

Similar Documents

Publication Publication Date Title
JP6679757B2 (en) Micropile corrugated grout bulb and method of forming the same
JP3940735B2 (en) Earth retaining method
JP2011236637A (en) Removal method of earth retaining member and slope strengthening block installation method using the same
KR100627642B1 (en) Apparatus for pressing steel pipe and method for pressing steel pipe using the same
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP4867861B2 (en) Method for preventing fluidization inhibition of groundwater, method for constructing retaining wall to prevent inhibition of groundwater flow, retaining wall constructed by the method, and method for constructing water passage
JP4294691B2 (en) Injection tube and grout injection method
JP5631371B2 (en) Equipment for extracting buried piles
JP4897985B2 (en) Hardener injection pipe for earth retaining work and earth retaining method
KR101442822B1 (en) Apparatus for inserting steel pipe and simultaneous horizontal high pressure jet-grouting in a tunnel supporting, and Method for inserting steel pipe and high pressure jet grouting with it
JP2009287326A (en) Pulling out method of existing pile
JP6730121B2 (en) Underground wall construction method
JP3363099B2 (en) Supporting ground improvement method for existing structures
JP4992769B2 (en) Method for preventing fluidization inhibition of groundwater, Construction method of water flow section preventing inhibition of groundwater flow
KR102297853B1 (en) Mortar pile formation method that can reduce the occurrence of floating soil
JP5284168B2 (en) Excavation member for earth retaining member construction and earth retaining member construction method
JP2006291701A (en) Earth retaining construction method
JP2005120622A (en) Construction method of underground structure
JPH02120410A (en) Concrete sheet pile
JP2011252319A (en) Reinforcement material for natural ground reinforcement earth method and natural ground reinforcement earth method
JP4633273B2 (en) Earth retaining method and equipment
JP6361045B2 (en) Removal method of earth retaining members
JP6340248B2 (en) Mountain retaining wall, how to construct a mountain retaining wall
JP5277925B2 (en) Method for preventing fluidization inhibition of groundwater and structure for preventing inhibition of flow of mountain retaining wall constructed by the method
JP5068678B2 (en) Earth retaining method and excavation member for earth retaining member standing construction used therefor

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060427

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060623

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060817

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060914

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20061228

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070119

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20070226

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070315

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070402

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3940735

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100406

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130406

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130406

Year of fee payment: 6

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130406

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140406

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250