JP4897985B2 - Hardener injection pipe for earth retaining work and earth retaining method - Google Patents

Hardener injection pipe for earth retaining work and earth retaining method Download PDF

Info

Publication number
JP4897985B2
JP4897985B2 JP2006283721A JP2006283721A JP4897985B2 JP 4897985 B2 JP4897985 B2 JP 4897985B2 JP 2006283721 A JP2006283721 A JP 2006283721A JP 2006283721 A JP2006283721 A JP 2006283721A JP 4897985 B2 JP4897985 B2 JP 4897985B2
Authority
JP
Japan
Prior art keywords
earth retaining
curing agent
injection pipe
steel sheet
sheet pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2006283721A
Other languages
Japanese (ja)
Other versions
JP2008101373A (en
Inventor
伸一 山下
大地 山下
Original Assignee
伸一 山下
山下 小夜子
大地 山下
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 伸一 山下, 山下 小夜子, 大地 山下 filed Critical 伸一 山下
Priority to JP2006283721A priority Critical patent/JP4897985B2/en
Publication of JP2008101373A publication Critical patent/JP2008101373A/en
Application granted granted Critical
Publication of JP4897985B2 publication Critical patent/JP4897985B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

この発明は、鋼矢板などで土留めを行いながら地中に水道管、ガス管、側溝、カルバートボックス等を埋設する土留め工事の施工に関するものである。 The present invention relates to construction of earth retaining work in which a water pipe, a gas pipe, a gutter, a culvert box and the like are buried in the ground while earth retaining with a steel sheet pile or the like.

地中に水道管、ガス管、カルバートボックス、下水管、側溝等を埋設する工事においては、まず溝の両壁を構成すべき位置に簡易矢板、鉄板、シートパイル等の土留め部材を設置して溝壁が崩れるのを防止した上で、地面を掘削して溝を形成し、溝内での水道管等の敷設作業が行われる。敷設作業が終了し溝を埋めなおした後に、土留め部材は地中から引き抜かれる。しかし、地中には土留め部材の体積分の空隙が生じることになる。この空隙の問題はこれまでほとんど検討されていない。この空隙を埋めるために周囲の土砂が移動し、さまざまな問題が生じうる。例えば、時間とともに溝内に充填した砂や土砂が空隙を埋めるために移動し、溝の上に敷かれた舗装面が沈下して、道路表面にくぼみを生じる。また、溝の外の土砂が移動することにより、溝の両側の地盤状態に変動をきたし、近くの建造物に影響を与えうる。さらに、周囲の地下水の状態が変われば、広範囲での影響も発生する。地下水は最も通りやすいところに水路を形成するので、土留め部材の引き抜きによって生じた空隙や、それを埋めるために移動した土砂によってできた水の通りやすい場所に新たな水路を形成し、周囲の地下水の流れが大きく変動する。この地下水の状態の変動によってそれまで保たれていた周囲の地盤の地圧のバランスがくずれ、地盤沈下等の地盤変動が生じ、そこに建造されている塀や建物等を変形させることになる。 When constructing underground pipes such as water pipes, gas pipes, culvert boxes, sewer pipes, gutters, etc., first install earth retaining members such as simple sheet piles, iron plates, and sheet piles at the positions where both walls of the groove should be constructed. After preventing the wall from collapsing, the ground is excavated to form a groove, and a water pipe or the like is laid in the groove. After the laying operation is completed and the groove is refilled, the earth retaining member is pulled out from the ground. However, a void corresponding to the volume of the earth retaining member is generated in the ground. Until now, the problem of this void has been hardly studied. The surrounding earth and sand moves to fill this gap, and various problems can occur. For example, as time passes, sand or earth and sand filled in the groove move to fill the gap, and the pavement surface laid on the groove sinks, resulting in a depression on the road surface. Moreover, when the earth and sand outside the groove move, the ground condition on both sides of the groove changes, and nearby buildings can be affected. Furthermore, if the surrounding groundwater conditions change, a wide range of effects will also occur. Since the groundwater forms a waterway where it is most likely to pass, a new waterway is formed in a space where the water created by the removal of the earth retaining member and the water created by the earth and sand moved to fill it can be Groundwater flow fluctuates greatly. Due to the change in the state of the groundwater, the ground pressure balance of the surrounding ground that has been maintained until then is lost, and ground changes such as ground subsidence occur, which deforms the walls and buildings built there.

そこで、シートパイルによる空隙を生じさせないために、シートパイルを引き抜かず、施工後も地中へ残すことが考えられる。しかし、地中に残されたシートパイルは時間とともに酸化・腐食により消失し、いずれは上述のような問題が生じることに変わりがない。また、シートパイルの素材である金属が土壌や地下水等を汚染することになる。シートパイルを使い捨てにすることは資源としても無駄な消費である。 Therefore, in order not to generate a gap due to the sheet pile, it is conceivable that the sheet pile is not pulled out and remains in the ground after construction. However, the sheet pile left in the ground disappears due to oxidation / corrosion with time, and the above-mentioned problems still occur. Moreover, the metal which is the material of a sheet pile will contaminate soil, groundwater, etc. Disposing sheet piles is a wasteful use of resources.

引用文献1(特開昭64−58713)には、鋼矢板の引抜き時に土砂を落下させて空隙を埋めることが記載されている。引用文献2(特開昭57−108311)および引用文献3(特開昭57−108312)には「地盤圧密剤」を注して空洞を埋めることが、引用文献4(特開昭49−49404)には、「充填材」を注入することが記載されている。さらに、引用文献5(特開2005−290963)には、硬化剤を注入することが記載されている。
特開昭64−58713 特開昭57−108311 特開昭57−108312 特開昭49−49404 特開2005−290963
Cited Document 1 (Japanese Patent Laid-Open No. 64-58713) describes that earth and sand are dropped to fill a gap when a steel sheet pile is pulled out. In Cited Document 2 (Japanese Patent Laid-Open No. 57-108311) and Cited Document 3 (Japanese Patent Laid-Open No. 57-108312), it is possible to fill a cavity with a “ground compaction agent”. ) Describes that a “filler” is injected. Furthermore, cited document 5 (Japanese Patent Laid-Open No. 2005-290963) describes injecting a curing agent.
JP-A 64-58713 JP-A-57-108311 JP-A-57-108312 JP 49-49404 JP-A-2005-290963

特許文献1に記載の方法は実施が不可能なものである。土砂を地中に埋め戻すにあたっては、約25cmごとに点圧器で点圧を行い、さらに水をかけてしめ固めなければならない。しかし、鋼矢板の引抜き跡に入れられた土砂に対して点圧を行うことはできない。また、鋼矢板の引抜き中や引抜き直後に地中に水を供給すれば、かえって地盤沈下を加速させることになる。点圧も水しめも行われない土砂は空隙が多く、地盤変動を防止することができない。 The method described in Patent Document 1 cannot be performed. When refilling the earth and sand into the ground, it is necessary to apply point pressure with a point pressure device about every 25 cm, and then apply water to consolidate. However, point pressure cannot be applied to the earth and sand put in the drawing sheet of the steel sheet pile. Moreover, if water is supplied into the ground during or immediately after the steel sheet piles are pulled out, ground subsidence is accelerated. Sediment that is not subjected to point pressure or squeezing has many voids and cannot prevent ground deformation.

特許文献2および特許文献3には「地盤圧密剤」が記載されているが、これらの文献には「地盤圧密剤」についての具体的な説明は一切なく、結局、どのように実施すべきかは不明である。特許文献4の「充填材」についても同文献中に記載はなく、どのように実施すべきかは不明である。 Patent Document 2 and Patent Document 3 describe “ground compaction agent”, but these documents do not have any specific explanation about “ground compaction agent”. It is unknown. The “filler” of Patent Document 4 is not described in the same document, and it is unclear how it should be implemented.

特許文献5には、土留め部材、硬化剤注入管、作業手順、硬化剤の種類などが具体的に示されており、初めて、実施可能な技術が提示されている。しかし、同文献に記載されている硬化剤注入管は円柱状のものである。特許文献1から特許文献4に記載された管もすべて円柱状である。 Patent Document 5 specifically shows a soil retaining member, a curing agent injection tube, a work procedure, a type of a curing agent, and the like, and a technique that can be implemented is presented for the first time. However, the curing agent injection tube described in the document is cylindrical. The pipes described in Patent Documents 1 to 4 are all cylindrical.

しかし、円柱状の形状の土硬化剤注入管を留め部材への取付けを行うことには困難を伴う。図13は円柱状の硬化剤注入管の取り付け作業を示す斜視図である。鋼矢板などの土留め部材を施工業者自身が所有している場合は少なく、通常は、施工時にレンタル業者より借り受け、施工終了後に返却する。したがって、硬化剤注入管の土留め部材への取り付けも施工現場で行われる。鋼矢板を地面に置き、その上に硬化剤注入管をのせてから固定する。しかし、円柱状の硬化剤注入管は転がりやすい。鋼矢板は20mもの長さを有するものあり、これを完全に水平な状態で保持できる場所が施工現場に常にあるわけではない。したがって、硬化剤注入管の取付けが完了するまで、作業者が硬化剤注入管を手で押さえていなくてはならない。また、建て込みや引抜きをおこなう機械のチャックが鋼矢板の中央部の面をつかむために使用されるので、硬化剤注入管は鋼矢板の側面に取り付けることが好ましいが、側面は傾斜しているので、円柱状の硬化剤注入管の取り付け作業はより困難となる。 However, it is difficult to attach the columnar earth hardening agent injection pipe to the fastening member. FIG. 13 is a perspective view showing the mounting operation of the cylindrical curing agent injection tube. There are few cases where the construction contractor owns a steel retaining member such as a steel sheet pile, and it is usually borrowed from a rental contractor at the time of construction and returned after the construction is completed. Therefore, the hardener injection pipe is attached to the earth retaining member at the construction site. Place the steel sheet pile on the ground, place the hardener injection tube on it and fix it. However, the cylindrical hardener injection tube is easy to roll. Steel sheet piles have a length of 20 m, and there is not always a place on the construction site where they can be held in a completely horizontal state. Therefore, the operator must hold the hardener injection tube by hand until the installation of the hardener injection tube is completed. Also, since the chuck of the machine that builds and pulls out is used to grab the central surface of the steel sheet pile, the hardener injection tube is preferably attached to the side of the steel sheet pile, but the side is inclined Therefore, it becomes more difficult to attach the columnar curing agent injection tube.

また、長い硬化剤注入管であれば複数のロッドに分割し、鋼矢板の上で各ロッドを接続した後に取り付けることになる。通常の硬化剤注入管で用いられるネジ式の接続方式であると、6以上のネジ山を係合させる必要がある。ロッドをパイレーン等の工具でつかんで回転させる必要があるが、そのためには、ロッドと鋼矢板の間に当て板をおいてパイレーンを回転させるための空間を確保することになる。全部のロッドを接続したら、当て板を取り除き、硬化剤注入管を鋼矢板に押し当て、溶接によって固定する。この作業の全期間中、硬化剤注入管が転がらないように、複数の作業者が手で硬化剤注入管を手で押さえていなくてはならない。 Moreover, if it is a long hardening | curing agent injection | pouring pipe | tube, it will divide | segment into a some rod and will attach after connecting each rod on a steel sheet pile. In the case of the screw-type connection method used in a normal curing agent injection tube, it is necessary to engage six or more threads. It is necessary to hold the rod with a tool such as a pyrene and rotate it. To do so, a space for rotating the pyrene is secured by placing a contact plate between the rod and the steel sheet pile. When all the rods are connected, the caulking plate is removed, and the hardener injection tube is pressed against the steel sheet pile and fixed by welding. During the entire period of this work, a plurality of workers must hold the hardener injection tube by hand so that the hardener injection tube does not roll.

この発明は、硬化剤注入管の土留め部材への取付けを短時間で実施でき、簡易でコストのかからない土留め工法を提供することを目的とする。 An object of the present invention is to provide a simple and inexpensive earth retaining method in which the hardener injection pipe can be attached to the earth retaining member in a short time.

上述の課題を解決するため、この発明の土留め工事用硬化剤注入管は、硬化剤を送り込む流路を有し、複数の部分に長さ方向に分割されている硬化剤注入管であり、分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続する接続部材を有するものである。さらに、硬化剤注入管には、土留め部材に当接する平面状の土留め部材取り付け面が備えられていることが好ましく、外形が概ね多角柱状であり、特に四角柱状であることが好ましい。 In order to solve the above-mentioned problem, the hardener injection pipe for earth retaining work of the present invention is a hardener injection pipe having a flow path for feeding the hardener and divided in a length direction into a plurality of portions, By connecting the divided curing agent injection pipes in the axial direction, the connecting members are connected so as to connect the flow paths. Further, the hardener injection tube is preferably provided with a planar retaining member mounting surface that abuts against the retaining member, and the outer shape is generally a polygonal column shape, particularly preferably a rectangular column shape.

この発明の土留め工法は、硬化剤を送り込む流路を有し、複数の部分に長さ方向に分割されている硬化剤注入管であり、分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続する接続部材を有する土留め工事用硬化剤注入管を土留め部材に取り付けて地中に建て込んで土留めを行う工法であって、分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続して土留め工事用硬化剤注入管を土留め部材に取り付け、土留め部材の引抜き時には硬化剤を硬化剤注入管の流路を介して地中に注入しながら引抜を行い、土留め部材の引抜き跡の空隙を硬化剤で充填するものである。これに加えて、土留め工事用硬化剤注入管が土留め部材に当接する平面状の土留め部材取り付け面を有するものであり、土留め部材取り付け面を土留め部材に当接させて土留め工事用硬化剤注入管を土留め部材に取り付けるものであることが好ましい。さらに、土留め部材が中央面とその中央面の両端につながった側面とを有する鋼矢板であり、側面に土留め工事用硬化剤注入管を取り付けることが好ましい。また、土留め部材が長さ方向に複数の部分部材に分割されており、部分部材に分割ロッドを取り付けてから地中に建て込み、直前に建て込まれた部分部材の上部に次の部分部材を溶接により接続するとともに直前に建て込まれた部分部材の分割ロッドに次の分割ロッドを軸方向に挿し込んで接続した上で次の部分部材に取り付けてさらに地中に建て込んでいくようにしてもよい。 The earth retaining method of the present invention is a curing agent injection pipe having a flow path for feeding a curing agent and divided in a length direction into a plurality of portions, and the divided curing agent injection pipes are inserted in the axial direction. It is a method of attaching a hardening agent injection pipe for earth retaining work having a connecting member to connect each flow path so as to connect each flow path and installing it in the earth retaining member to perform earth retaining and divided. The hardener injection pipes are inserted in the axial direction to connect the flow paths to each other, and the hardener injection pipe for earthing work is attached to the earth retaining member. When the earth retaining member is pulled out, the curing agent is used as the hardener. It pulls out while injecting into the ground through the flow path of the injection pipe, and fills the voids of the pull-out trace of the earth retaining member with a curing agent. In addition to this, the hardener injection pipe for earth retaining work has a flat earth retaining member attaching surface that abuts against the earth retaining member, and the earth retaining member is brought into contact with the earth retaining member. It is preferable that the construction hardener injection pipe is attached to the earth retaining member. Furthermore, it is preferable that the earth retaining member is a steel sheet pile having a central surface and side surfaces connected to both ends of the central surface, and a hardener injection pipe for earth retaining work is attached to the side surface. In addition, the earth retaining member is divided into a plurality of partial members in the length direction, and after mounting the dividing rod on the partial member, it is built into the ground, and the next partial member is placed on the upper part of the partial member that was built immediately before Are connected by welding, and the next split rod is inserted in the axial direction into the split rod of the partial member that was built immediately before, and then attached to the next partial member to be further built into the ground. May be.

この発明は、硬化剤注入管の土留め部材への取付けを短時間で実施できるという効果を有する。地面が傾斜した場所や狭い場所でも実施できるという効果を有する。 The present invention has an effect that the hardener injection tube can be attached to the earth retaining member in a short time. It has the effect that it can be implemented even in places where the ground is inclined or narrow.

この発明を実施するための最良の形態について、図面に基づいて説明する。図1は土留め工事用硬化剤注入管の概略を示す正面図である。土留め工事用硬化剤注入管1はその長さ方向について分割されている。この例においては1基の先端部材2と、それに続く3基の中間ロッド3と、最上段に位置するスイベル4に分割されている。そして、その間には接続部材5が設けられている。 The best mode for carrying out the present invention will be described with reference to the drawings. FIG. 1 is a front view showing an outline of a hardener injection pipe for earth retaining work. The hardener injection pipe 1 for earth retaining work is divided in the length direction. In this example, it is divided into one tip member 2, followed by three intermediate rods 3, and a swivel 4 located at the uppermost stage. And the connection member 5 is provided in the meantime.

図2は土留め工事用硬化剤注入管の先端部材を示す断面図である。先端部材2および中間ロッド3は土留め部材に当接する平面状の土留め部材取り付け面6を有する。他の面は曲面上に形成することも可能であるが、外形を多角柱状にするのが好ましい。本例では、四角柱状の外形を有する。 FIG. 2 is a cross-sectional view showing a tip member of a hardener injection pipe for earth retaining work. The tip member 2 and the intermediate rod 3 have a planar retaining member attachment surface 6 that abuts against the retaining member. The other surface can be formed on a curved surface, but the outer shape is preferably a polygonal column. In this example, it has a quadrangular prism shape.

また、先端部材2および中間ロッド3は内部に複数の独立した流路を有する。本例では、2種類の薬液を独立して送り込めるように2つの流路7,8を備えた二重管構造になっているが、さらに三重管以上にしてもよい。先端部材2は、その側面に吐出口9を備えており、硬化剤を横方向に吐出できるようになっている。本例では、平面状の土留め部材取り付け面6を除く面にそれぞれ一つずつ直径8〜10mmの吐出口9が設けられている。 The tip member 2 and the intermediate rod 3 have a plurality of independent flow paths inside. In this example, the double pipe structure is provided with two flow paths 7 and 8 so that two kinds of chemical solutions can be sent independently, but a triple pipe or more may be used. The tip member 2 has a discharge port 9 on its side surface, and can discharge the curing agent in the lateral direction. In this example, one discharge port 9 having a diameter of 8 to 10 mm is provided on each surface except the flat earth retaining member mounting surface 6.

吐出口9の近くには栓10と、栓10を上方向に付勢する付勢部材11が設けられている。栓10は硬度の高いプラスチックを素材としている。付勢手段11も長期間土中にあっても劣化しないようにプラスチック製であり、0.5kg程度の加重で下がるようになっている。栓10の上面に大気圧がかかっている状態で、栓10は吐出口9を塞ぐ位置にある(図2a)。 A stopper 10 and a biasing member 11 that biases the stopper 10 upward are provided near the discharge port 9. The stopper 10 is made of high-hardness plastic. The biasing means 11 is also made of plastic so that it does not deteriorate even in the soil for a long period of time, and is lowered with a weight of about 0.5 kg. In a state where atmospheric pressure is applied to the upper surface of the stopper 10, the stopper 10 is in a position for closing the discharge port 9 (FIG. 2a).

図3は土留め工事用硬化剤注入管の中間ロッド3を示す断面図である。先端部材2と同様に四角柱状の形状であり、土留め部材に当接する平面状の土留め部材取り付け面6を有する。また、内部は二重管構造であり、独立した二つの流路7,8を有する。 中間ロッド3およびスイベル4は土留め部材に当接する平面状の土留め部材取り付け面6を有する。他の面は曲面上に形成することも可能であるが、外形を多角柱状にするのが好ましい。本例では、四角柱状の外形を有する。 FIG. 3 is a cross-sectional view showing the intermediate rod 3 of the hardener injection pipe for earth retaining work. Like the tip member 2, it has a quadrangular prism shape and has a flat earth retaining member attachment surface 6 that abuts against the earth retaining member. Further, the inside has a double tube structure and has two independent flow paths 7 and 8. The intermediate rod 3 and the swivel 4 have a planar retaining member attachment surface 6 that abuts against the retaining member. The other surface can be formed on a curved surface, but the outer shape is preferably a polygonal column. In this example, it has a quadrangular prism shape.

図4は土留め工事用硬化剤注入管の硬化剤導入部4を示す断面図である。硬化剤導入部5はスイベル形式のものではなく、中間ロッド3に対して回転しないものとしている。二つの硬化剤導入口12,13が設けられており、ホースを取り付けることができるようになっている。 FIG. 4 is a cross-sectional view showing the hardener introduction part 4 of the hardener injection pipe for earth retaining work. The curing agent introducing section 5 is not of a swivel type and is not rotated with respect to the intermediate rod 3. Two curing agent inlets 12 and 13 are provided so that a hose can be attached.

先端部材2の上端部、中間ロッド3の両端部および硬化剤導入部4の下端部にはそれぞれ接続部材挿入口14が形成されている。この接続部材挿入口14は、径が大きい第1の円孔15と、その奥の径の小さい第2の円孔16よりなる。第1の円孔15の内周面にはOリング17が設けられている。 Connection member insertion ports 14 are formed at the upper end portion of the tip member 2, both end portions of the intermediate rod 3, and the lower end portion of the hardener introduction portion 4. The connection member insertion port 14 includes a first circular hole 15 having a large diameter and a second circular hole 16 having a small diameter at the back thereof. An O-ring 17 is provided on the inner peripheral surface of the first circular hole 15.

図5は、接続部材5を示す断面図である。接続部材5は太い円柱状の基部18と、基部18の両側より突出する細い円柱状の突起部19よりなる。基部18の外径は接続部材挿入口14の第1の円孔15の内径とほぼ同じであり、突起部19の外径は接続部材挿入口14の第2の円孔16の内径とほぼ同じである。また、突起部19の長さは第2の円孔16の深さとほぼ同じである。したがって、接続部材5を接続部材挿入口14に軸方向に挿し込むことによって、接続部材5の片側と接続部材挿入口14ははめ込むことができる。 FIG. 5 is a cross-sectional view showing the connection member 5. The connecting member 5 includes a thick columnar base 18 and a thin columnar projection 19 projecting from both sides of the base 18. The outer diameter of the base 18 is substantially the same as the inner diameter of the first circular hole 15 of the connection member insertion port 14, and the outer diameter of the protrusion 19 is substantially the same as the inner diameter of the second circular hole 16 of the connection member insertion port 14. It is. Further, the length of the projection 19 is substantially the same as the depth of the second circular hole 16. Therefore, one side of the connection member 5 and the connection member insertion port 14 can be fitted by inserting the connection member 5 into the connection member insertion port 14 in the axial direction.

接続部材5の中心には、基部18と突起部19を通した第1の孔20が貫通している。また、基部18の 外辺付近にも複数の第2の孔21が通っている。また、突起部19の外周にはOリング22が設けられている。 In the center of the connecting member 5, a first hole 20 that passes through the base 18 and the protrusion 19 penetrates. Further, a plurality of second holes 21 are also passed near the outer side of the base 18. An O-ring 22 is provided on the outer periphery of the protrusion 19.

ついで、この土留め工事用硬化剤注入管1を使用した土留め工法について説明する。図6は土留め工事用硬化剤注入管の取付け作業を示す斜視図である。土留め部材として鋼矢板30を使用する。鋼矢板30は、広い中央面31と、その中央面31の両側の側面32を有するが、ここでは、土留め工事用硬化剤注入管1を中央面31に取り付ける場合について説明する。 Next, the earth retaining method using the curing agent injection pipe 1 for earth retaining work will be described. FIG. 6 is a perspective view showing the work of attaching the hardener injection pipe for earth retaining work. A steel sheet pile 30 is used as the earth retaining member. Although the steel sheet pile 30 has the wide center surface 31 and the side surfaces 32 of the both sides of the center surface 31, the case where the hardening agent injection pipe | tube 1 for earth retaining work is attached to the center surface 31 is demonstrated here.

鋼矢板30を施工現場の地面に置く。地面は完全に水平である必要はなく、多少の凹凸や傾斜があってもよい。中央面31の上で先端部材2および中間ロッド3を接続する。接続作業は、先端部材2から行ってもよく、また、最上段の中間ロッド3から行っても良い。たとえば、まず、鋼矢板30の先端部に先端部材2を置き、この先端部材2の上端の接続部材挿入口14に接続部材5の片側を挿入する。ついで接続部材5の反対側と中間ロッド3の接続部材挿入口14を係合させる。このようにして、先端部材2および中間ロッド3を回転させることなく、長さ方向での挿し込みだけで簡単に接続することができる。2本目以降の中間ロッド3も同様にして接続していく。最上段の中間ロッド3まで接続する。ただし、鋼矢板の建て込みの際、機械のチャックは中央面31の上端部を保持するので、中央面31に硬化剤注入管1を取り付ける場合、中最上段の間ロッド3は鋼矢板30の上端よりやや下側までしか取り付けることはできない。 The steel sheet pile 30 is placed on the ground of the construction site. The ground need not be completely horizontal and may have some irregularities and slopes. The tip member 2 and the intermediate rod 3 are connected on the central surface 31. The connection work may be performed from the tip member 2 or from the uppermost intermediate rod 3. For example, first, the tip member 2 is placed at the tip of the steel sheet pile 30, and one side of the connection member 5 is inserted into the connection member insertion port 14 at the upper end of the tip member 2. Next, the opposite side of the connection member 5 and the connection member insertion port 14 of the intermediate rod 3 are engaged. In this way, it is possible to simply connect by inserting in the length direction without rotating the tip member 2 and the intermediate rod 3. The second and subsequent intermediate rods 3 are similarly connected. Connect to the uppermost intermediate rod 3. However, since the chuck of the machine holds the upper end portion of the central surface 31 when the steel sheet pile is installed, when the hardener injection tube 1 is attached to the central surface 31, the rod 3 is attached to the steel sheet pile 30. It can be attached only to the lower side from the upper end.

最上段の中間ロッド3まで接続したら、各接続箇所の両側に固定金具23を取り付けて溶接を行う。図7は接続箇所を示す断面図である。固定金具23はL字状の断面を有する金具であり、相互に垂直な二つの面を有する。一方の面が鋼矢板30に当接し、他の面が工事用硬化剤注入管1の側面に当接することによって、鋼矢板30と工事用硬化剤注入管1を安定した状態で固定する。固定金具23を鋼矢板30および工事用硬化剤注入管1に溶接することによって、工事用硬化剤注入管1は鋼矢板30に取り付けられる。 After the connection up to the uppermost intermediate rod 3, the fixing brackets 23 are attached to both sides of each connection portion and welding is performed. FIG. 7 is a cross-sectional view showing a connection location. The fixing bracket 23 is a bracket having an L-shaped cross section, and has two surfaces perpendicular to each other. One surface is in contact with the steel sheet pile 30 and the other surface is in contact with the side surface of the work hardener injection pipe 1, thereby fixing the steel sheet pile 30 and the work hardener injection pipe 1 in a stable state. The work hardener injection pipe 1 is attached to the steel sheet pile 30 by welding the fixing bracket 23 to the steel sheet pile 30 and the work hardener injection pipe 1.

以上、先端部材2および中間ロッド3は接続部材によって、簡単に接続される。接続部材5の第1の孔21は中心部の流路7同士を連絡し、第2の孔22は外周部の流路8同士を連絡する。したがって、この接続によって、先端部材2から最上段の中間ロッド3まで、2本の連続した流路が形成される。先端部材2および中間ロッド3は平面状の土留め部材取り付け面6によって鋼矢板30と接しているので取付け作業中に転がることはなく、作業者が押さえている必要がない。また、十分に広い当接面があるので接続作業中も安定しており、鋼矢板30の長さ方向に沿って真直ぐに接続していくことができる。 As described above, the tip member 2 and the intermediate rod 3 are simply connected by the connecting member. The first hole 21 of the connecting member 5 communicates with the flow paths 7 in the central portion, and the second hole 22 communicates with the flow paths 8 in the outer peripheral portion. Therefore, by this connection, two continuous flow paths are formed from the tip member 2 to the uppermost intermediate rod 3. Since the tip member 2 and the intermediate rod 3 are in contact with the steel sheet pile 30 by the flat retaining member attachment surface 6, the tip member 2 and the intermediate rod 3 do not roll during the attachment work and do not need to be pressed by the operator. In addition, since there is a sufficiently wide contact surface, it is stable during the connection work, and the connection can be made straight along the length direction of the steel sheet pile 30.

硬化剤注入管1の鋼矢板30への取り付けが完了したら、鋼矢板30を埋設工事を行う場所の両側に建て込んでいく。建て込み作業は、たとえば鋼矢板を地中に圧入する通常の装置を使用して行うことができる。 When the attachment of the hardener injection pipe 1 to the steel sheet pile 30 is completed, the steel sheet pile 30 is built on both sides of the place where the burial work is performed. The erection operation can be performed using, for example, a normal device that press-fits a steel sheet pile into the ground.

ここで、鋼矢板の配置について説明する。土留めとして設置する鋼矢板の全てに硬化剤注入管を取り付けることは必ずしも必要ではなく、硬化剤注入管付き鋼矢板と硬化剤注入管が取り付けられていない通常の鋼矢板を併用してもよい。たとえば、硬化剤注入管が取り付けられた鋼矢板に続いて硬化剤注入管が取り付けられていない鋼矢板が2基又は3基設置され、また硬化剤注入管が取り付けられた鋼矢板が設置されるという繰り返しで配置してもよい。硬化剤注入管1から注入された硬化剤が到達する距離の範囲内であれば硬化剤注入管が取り付けられた鋼矢板を設置することができる。 Here, arrangement | positioning of a steel sheet pile is demonstrated. It is not always necessary to attach a hardener injection pipe to all steel sheet piles installed as earth retaining, and a steel sheet pile with a hardener injection pipe and a normal steel sheet pile without a hardener injection pipe may be used in combination. . For example, two or three steel sheet piles without a hardener injection pipe are installed following a steel sheet pile with a hardener injection pipe attached, and a steel sheet pile with a hardener injection pipe attached. You may arrange by repeating. A steel sheet pile to which the curing agent injection tube is attached can be installed as long as the curing agent injected from the curing agent injection tube 1 is within a distance range.

鋼矢板30の建て込み時において、先端部材2内の付勢部材11は栓10を上方向に押しており、栓10によって吐出口9は閉じられている。したがって、土砂が硬化剤注入管1の中に入り込むことはない。 When the steel sheet pile 30 is installed, the urging member 11 in the tip member 2 pushes the stopper 10 upward, and the outlet 9 is closed by the stopper 10. Therefore, earth and sand do not enter the hardener injection tube 1.

次に、鋼矢板30の撤去方法について説明する。引抜きを行う鋼矢板30の硬化剤注入管1の上端に硬化剤導入部4を取り付ける。硬化剤導入部4の硬化剤導入口12,13に硬化剤ホースを接続する。鋼矢板30は端から順次引き抜くが、硬化剤注入管1により地中に硬化剤を注入しながら行う。 Next, a method for removing the steel sheet pile 30 will be described. The hardener introduction part 4 is attached to the upper end of the hardener injection pipe 1 of the steel sheet pile 30 to be pulled out. A hardener hose is connected to the hardener inlets 12 and 13 of the hardener inlet 4. The steel sheet pile 30 is sequentially pulled out from the end, and is performed while injecting the curing agent into the ground by the curing agent injection tube 1.

鋼矢板30の引抜き跡を迅速に充填するためには、硬化剤としては2液を混合するゲルタイムの短いものが好ましい。
瞬結性の硬化剤の例について説明する。A液として水ガラス(JIS3号ケイ酸ナトリウム)80リットルに水120リットルを加えたものを用意する。B液としては、高炉セメントB種に無機系懸濁型水ガラス系グラウト用硬化剤を加えたものを用意する。例えば、高炉セメントB種50Kg、YMS45(三興コロイド化学株式会社)10Kgおよび178.7リットルを混合してB液とする。YMS45は硫酸カルシウムと水酸化カルシウムを主成分とする薬剤である。このA液とB液を1対1で使用することにより、また、高炉セメントB種50Kg、YMS90(三興コロイド化学株式会社)5Kgおよび181.4リットルを混合してB液とすると、20℃でのゲルタイムが1〜2分、4週強度0.5〜1N/mm2となる。これらの硬化剤は、毒物や劇物を含まない安全性の高い無公害薬剤である。
ついで、緩結性の硬化剤の例について説明する。高炉セメントB種50Kg、ベントナイト10Kg、セメントミルク凝結硬化促進剤であるYMS2000(三興コロイド化学株式会社)4Kgおよび177.8リットルを混合する。これによって、流動性消失時間が30〜40分、4週強度0.71N/mm2となる。
In order to quickly fill the traces of the steel sheet pile 30, the hardener is preferably a gel having a short gel time in which two liquids are mixed.
An example of the instantaneous curing agent will be described. A liquid A is prepared by adding 80 liters of water to 80 liters of water glass (JIS No. 3 sodium silicate). As B liquid, the thing which added the hardening | curing agent for inorganic suspension water glass grout to blast furnace cement B type is prepared. For example, 50 kg of blast furnace cement type B, 10 kg of YMS45 (Sanko Colloid Chemical Co., Ltd.) and 178.7 liters are mixed to make a B liquid. YMS45 is a drug mainly composed of calcium sulfate and calcium hydroxide. By using this A liquid and B liquid on a one-to-one basis, and mixing B blast furnace cement type B 50 kg, YMS90 (Sanko Colloid Chemical Co., Ltd.) 5 kg and 181.4 liters into B liquid, The gel time at 1 to 2 minutes and 4 weeks strength 0.5 to 1 N / mm 2 . These hardeners are highly safe and non-polluting drugs that do not contain poisonous or deleterious substances.
Next, an example of a slow-curing curing agent will be described. Blast furnace cement type B 50 kg, bentonite 10 kg, cement milk setting hardening accelerator YMS2000 (Sanko Colloid Chemical Co., Ltd.) 4 kg and 177.8 liters are mixed. Thus, the fluidity disappearance time is 30 to 40 minutes, and the 4-week strength is 0.71 N / mm 2 .

ホースより硬化剤が硬化剤注入管1に注入されると、硬化剤の圧力によって栓10が下方向に押し下げられ、吐出口9が開放される。本例においては、栓10の位置よりも下方の側壁に小さなエア抜き穴25が設けられている。したがって、栓10はスムーズに下方へ移動し、先端部材2の側壁に横向きに設けられた吐出口9は確実に開放される。二つの流路7,8を通ってきた2種類の薬液(A液、B液)は先端部材2内で混合され、吐出口9より横向きに地中に注入される。 When the curing agent is injected from the hose into the curing agent injection tube 1, the stopper 10 is pushed downward by the pressure of the curing agent, and the discharge port 9 is opened. In this example, a small air vent hole 25 is provided on the side wall below the position of the stopper 10. Therefore, the stopper 10 moves smoothly downward, and the discharge port 9 provided laterally on the side wall of the tip member 2 is reliably opened. Two types of chemical solutions (A solution and B solution) that have passed through the two flow paths 7 and 8 are mixed in the tip member 2 and injected laterally from the discharge port 9 into the ground.

硬化剤注入管1より地中に注入された硬化剤は、先に引き抜かれた鋼矢板および硬化剤注入管付き鋼矢板自体によってできる空隙を埋める。したがって、空隙に起因する地中の土壌の移動や地下水の水路の変化に伴う地盤状態の変動が発生しない。 The hardener injected into the ground from the hardener injection tube 1 fills the gap formed by the steel sheet pile previously drawn out and the steel sheet pile with the hardener injection tube itself. Therefore, there is no change in the ground condition due to the movement of soil in the ground and the change of the groundwater channel due to the gap.

引き抜きが完了したら、硬化剤導入部4とホースを取り外し、次に引き抜く鋼矢板に取り付ける。以下、同様の作業を繰り返して、全ての鋼矢板を撤去する。なお、工事用硬化剤注入管1は全ての鋼矢板に取り付けておいてもよく、また、工事用硬化剤注入管の付いた鋼矢板と工事用硬化剤注入管の付いていない鋼矢板を一つおきに交互に使用してもよい。 When the drawing is completed, the curing agent introducing portion 4 and the hose are removed and then attached to the steel sheet pile to be drawn out. Thereafter, the same operation is repeated to remove all the steel sheet piles. The hardener injection pipe 1 for construction may be attached to all the steel sheet piles, and the steel sheet pile with the construction hardener injection pipe and the steel sheet pile without the construction hardener injection pipe are combined. You may use it alternately.

ついで、硬化剤注入管1を鋼矢板30の側面32に取り付ける例について説明する。図8は硬化剤注入管の側面への取付け作業を示す斜視図である。まず、地面に置かれた鋼矢板30の側面32で、硬化剤注入管1の接続部材5が取り付けられる位置の下側に、固定金具23を溶接していく。固定金具23が一列に取り付けられたら、この固定金具23の上で硬化剤注入管1を組み立てていく。まず、先端部材2と中間ロッド3を接続部材5によって接続する。接続は、長さ方向への挿し込みによって簡単に行える。以下、中間ロッド3を同様の手順で接続していく。最上段の中間ロッド3まで接続したら、硬化剤注入管1の接続箇所と固定金具23を溶接により固定する。さらに、接続箇所の上側にも固定金具23を取り付けて溶接する。このようにして、硬化剤注入管1は鋼矢板30の側面32に取り付けられる。 Next, an example in which the hardener injection tube 1 is attached to the side surface 32 of the steel sheet pile 30 will be described. FIG. 8 is a perspective view showing the attaching operation to the side surface of the hardener injection tube. First, on the side surface 32 of the steel sheet pile 30 placed on the ground, the fixing bracket 23 is welded to the lower side of the position where the connecting member 5 of the hardener injection tube 1 is attached. When the fixtures 23 are attached in a row, the curing agent injection tube 1 is assembled on the fixtures 23. First, the tip member 2 and the intermediate rod 3 are connected by the connecting member 5. Connection can be easily performed by inserting in the length direction. Thereafter, the intermediate rod 3 is connected in the same procedure. After the connection to the uppermost intermediate rod 3, the connection location of the hardener injection tube 1 and the fixing bracket 23 are fixed by welding. Further, the fixing bracket 23 is attached to the upper side of the connection portion and welded. In this way, the hardener injection tube 1 is attached to the side surface 32 of the steel sheet pile 30.

鋼矢板30の側面32は傾斜しているので、円柱状の硬化剤注入管では取付けが極めて困難である。また、パイレーンを使用するための当て板を置く事もできないので、ネジ式の接続方法は使用できない。本例では、四角柱状の硬化剤注入管1を使用しているので、作業は容易であり、しかも強固に固定することができる。 Since the side surface 32 of the steel sheet pile 30 is inclined, it is extremely difficult to mount it with a cylindrical hardener injection tube. In addition, a screw-type connection method cannot be used because a patch plate for using the pyrene cannot be placed. In this example, since the square columnar curing agent injection tube 1 is used, the operation is easy and can be firmly fixed.

鋼矢板の建て込みの際、機械のチャックは中央面31の上端部を保持するので、中央面31に硬化剤注入管1を取り付ける場合、中間ロッド3は鋼矢板の上端よりやや下側までしか取り付けることはできない。したがって、中間ロッド3の上端が地上に出るように鋼矢板30を建て込むと、上端部がある程度地上に突出することとなる。しかし、側面32は機械のチャックに使用されないので、中間ロッド3は鋼矢板30上端まで、あるいはある程度上部に突出させた状態でも、取り付けることができる。鋼矢板30のほとんど全てを地中に挿入することができる。 When the steel sheet pile is installed, the chuck of the machine holds the upper end portion of the central surface 31. Therefore, when the hardener injection tube 1 is attached to the central surface 31, the intermediate rod 3 is only slightly below the upper end of the steel sheet pile. It cannot be installed. Therefore, when the steel sheet pile 30 is built such that the upper end of the intermediate rod 3 comes out on the ground, the upper end portion protrudes to the ground to some extent. However, since the side surface 32 is not used for the chuck of the machine, the intermediate rod 3 can be attached to the upper end of the steel sheet pile 30 or even in a state where it protrudes to some extent. Almost all of the steel sheet pile 30 can be inserted into the ground.

ついで、複数の異なる深さで硬化剤を注入する方法について説明する。図9は複数の異なる深さで硬化剤を注入する方法を示す斜視図である。ここでは、長い硬化剤注入管1aと短い硬化剤注入管1bの2本が取り付けられている。長い硬化剤注入管1aはこれまでの例で説明ものと同様に鋼矢板30の下端まで伸びており、吐出口9aはその下端部に位置する。一方、短い硬化剤注入管1bは長い硬化剤注入管1aの半分程度の本数の中間ロッド3を有しており、鋼矢板の長さの約半分である。吐出口9bは鋼矢板の長さの約半分の位置にある。 Next, a method for injecting the curing agent at a plurality of different depths will be described. FIG. 9 is a perspective view showing a method of injecting a curing agent at a plurality of different depths. Here, two long hardener injection pipes 1a and a short hardener injection pipe 1b are attached. The long hardening | curing agent injection | pouring pipe | tube 1a is extended to the lower end of the steel sheet pile 30 similarly to what was demonstrated by the example so far, and the discharge outlet 9a is located in the lower end part. On the other hand, the short hardening | curing agent injection | pouring pipe | tube 1b has about half the number of intermediate rods 3 of the long hardening | curing agent injection | pouring pipe | tube 1a, and is about half the length of a steel sheet pile. The discharge port 9b is at a position about half the length of the steel sheet pile.

これによって、吐出口9aへ続く流路と吐出口9bへ続く流路はそれぞれ独立したものとなる。この鋼矢板を引抜くとき、長い硬化剤注入管1aと短い硬化剤注入管1bのそれぞれ上部に硬化剤導入部4とホースを接続する。そして、吐出口9aと吐出口9bの両方から同時に硬化剤を注入しながら鋼矢板を引き抜く。これによって、硬化剤の注入時間を約1/2に短縮することができる。 Thereby, the flow path leading to the discharge port 9a and the flow path leading to the discharge port 9b are independent of each other. When this steel sheet pile is pulled out, the hardener introduction part 4 and the hose are connected to the upper parts of the long hardener injection pipe 1a and the short hardener injection pipe 1b, respectively. Then, the steel sheet pile is pulled out while simultaneously injecting the curing agent from both the discharge port 9a and the discharge port 9b. Thereby, the injection time of the curing agent can be shortened to about ½.

以上、2箇所の深さに吐出口9を設けた例を説明したが、3箇所でもよい。この場合、3系統の流路を設けた硬化剤注入管を用いる。鋼矢板の長さをLとすると、吐出口9は鋼矢板の最下端、最下端からL/3の位置、および最下端から2・L/3の位置、に設ける。これによって注入時間を約1/3に短縮することができる。 As described above, the example in which the discharge ports 9 are provided at two depths has been described. In this case, a curing agent injection tube provided with three channels is used. When the length of the steel sheet pile is L, the discharge ports 9 are provided at the lowest end of the steel sheet pile, at the position L / 3 from the lowest end, and at the position 2 · L / 3 from the lowest end. This can reduce the injection time to about 1/3.

複数の異なる深さで硬化剤を注入するためには、2箇所以上の深さに吐出口9を設けた多段式の硬化剤注入管を使用しても良い。図10および図11は多段式硬化剤注入管の例を示す断面図である。図10aの例では、長さ方向に渡って同一の太さの四角柱となっている。内部には2本の独立した硬化剤の流路7a,7bが設けられている。中心部の流路7aは先端部まで延びており、先端部に設けられた吐出口9aにつながっている。外周部の流路7bは先端部から約L/2の位置(Lは鋼矢板の長さ)にある吐出口9bにつながっている。図10bの例では、3系統の流路が同一の硬化剤注入管内に設けられており、それぞれは鋼矢板の最下端の吐出口9a、最下端からL/3の位置(最上端から2L/3の位置)の吐出口9b、および最下端から2L/3の位置(最上端からL/3の位置)の吐出口9cにつながっている。なお、図示は省略しているが、図1に示す硬化剤注入管と同様に、複数の部分に長さ方向に分割されており、分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続する接続部材を有する。また、接続箇所に固定金具を当てて、硬化剤注入管を鋼矢板に取り付けるもの同様である。各吐出口9には1本の流路7がつながっているので、セメントミルクなど1液の硬化剤を使用する。たとえばセメントミルク凝結硬化促進剤であるYMS2000を加えた硬化剤が使用できる。 In order to inject the curing agent at a plurality of different depths, a multistage curing agent injection tube provided with discharge ports 9 at two or more depths may be used. 10 and 11 are cross-sectional views showing an example of a multistage curing agent injection tube. In the example of FIG. 10a, the prisms have the same thickness over the length direction. Two independent curing agent channels 7a and 7b are provided inside. The central channel 7a extends to the tip and is connected to a discharge port 9a provided at the tip. The outer peripheral flow path 7b is connected to the discharge port 9b at a position of about L / 2 from the tip (L is the length of the steel sheet pile). In the example of FIG. 10b, three flow paths are provided in the same hardener injection pipe, and each of them is a discharge port 9a at the lowermost end of the steel sheet pile, a position L / 3 from the lowermost end (2L / second from the uppermost end). 3) and the discharge port 9c at a position 2L / 3 from the lowermost end (position at L / 3 from the uppermost end). In addition, although illustration is abbreviate | omitted, like the hardening | curing agent injection | pouring pipe | tube shown in FIG. 1, it is divided | segmented into the length direction at several parts, and inserts the divided | segmented hardening | curing agent injection | pouring pipes in an axial direction. The connection member which connects so that each flow path may be connected by. Moreover, it is the same as that which attaches a fixing metal fitting to a connection location and attaches a hardening | curing agent injection pipe | tube to a steel sheet pile. Since one flow path 7 is connected to each discharge port 9, one liquid curing agent such as cement milk is used. For example, a hardener to which YMS2000, which is a cement milk setting hardening accelerator, is added can be used.

図11の例も、内部は3本の独立した硬化剤の流路7a,7b,7cが設けられていて、それぞれが、最下端の吐出口9a、最下端からL/3の位置(最上端から2L/3の位置)の吐出口9b、および最下端から2L/3の位置(最上端からL/3の位置)の吐出口9cにつながっている。この硬化剤注入管の外形は、上部3分の1の部分が太くなっており、これに続く中間部ではやや細くなり、下部3分の1の部分では最も細くなっている。 In the example of FIG. 11 as well, the inside is provided with three independent curing agent channels 7a, 7b and 7c, each of which has a discharge port 9a at the lowest end, and a position L / 3 from the lowest end (the highest end). To a discharge port 9b at a position 2L / 3 from the bottom and a discharge port 9c at a position 2L / 3 from the bottom (position L / 3 from the top). The outer shape of the hardening agent injection tube is thicker at the upper third portion, slightly thinner at the intermediate portion following the outer portion, and thinnest at the lower third portion.

さらに、鋼矢板を分割して設置する方法について説明する。図12は鋼矢板を分割して設置する方法を示す概略図である。施工場所によって上部に橋などの障害物24が存在し、長い鋼矢板をそのまま打ち込めない場合がある。そこで、障害物24の下の限られたスペースでも建て込みができる程度の短い断片に鋼矢板を分割する。まず、最初の鋼矢板の断片に先端部材2と中間ロッド3を取り付け、この断片を建て込む。 Furthermore, the method of dividing | segmenting and installing a steel sheet pile is demonstrated. FIG. 12 is a schematic view showing a method of dividing and installing a steel sheet pile. Depending on the construction site, there may be an obstacle 24 such as a bridge in the upper part, and a long steel sheet pile may not be driven as it is. Therefore, the steel sheet pile is divided into short pieces that can be built even in a limited space under the obstacle 24. First, the tip member 2 and the intermediate rod 3 are attached to the first piece of steel sheet pile, and this piece is built.

ついで、先に建て込んだ断片の上に、次の断片を置き、溶接によって接続する。また、先の断片に取り付けられた中間ロッド3の上端に、新たな中間ロッド3を軸方向に挿し込んで接続する。そして、この新たな中間ロッド3を固定金具23と溶接によって鋼矢板の断片に取り付ける。このとき、鋼矢板は垂直に立った状態であるが、中間ロッド3は接続部材5を介した挿し込みによって簡単に接続することができる。また、中間ロッド3は四角柱状の外形であるために、鋼矢板へ押し当て位置決めするのが容易であり、取り付けにもさほど困難はない。中間ロッド3を取り付けたら、この新たな鋼矢板も地中へ挿入する。以上、同様の作業を繰り返し、必要な深さまで鋼矢板を建て込んでいく。 Next, the next piece is placed on the previously built piece and connected by welding. Further, a new intermediate rod 3 is inserted and connected to the upper end of the intermediate rod 3 attached to the previous piece in the axial direction. Then, the new intermediate rod 3 is attached to the steel sheet pile piece by welding with the fixing bracket 23. At this time, although the steel sheet pile is standing vertically, the intermediate rod 3 can be easily connected by insertion through the connecting member 5. Moreover, since the intermediate rod 3 has a quadrangular prism shape, it is easy to press and position the steel rod against the steel sheet pile, and there is no difficulty in mounting. When the intermediate rod 3 is attached, this new steel sheet pile is also inserted into the ground. The same work is repeated until the steel sheet pile is built to the required depth.

鋼矢板の引き抜きは、硬化剤注入管1より地中に硬化剤を注入しながら行う。鋼矢板の断片1個分が地上に出たら、硬化剤注入および引き抜きを中断する。断片間の溶接箇所を切り離すとともに、中間ロッド3間の接続箇所も切り離す。残った中間ロッド3に硬化剤導入部4とホースを取り付けて、再度、硬化剤注入および引き抜きを行う。このように、各断片について引き抜きと切断を繰り返しながら、全ての鋼矢板を撤去する。 The steel sheet pile is pulled out while injecting the hardener into the ground from the hardener injection tube 1. When one piece of steel sheet pile comes out on the ground, the hardener injection and withdrawal are interrupted. While disconnecting the welding location between fragments, the connection location between the intermediate rods 3 is also disconnected. The curing agent introduction part 4 and the hose are attached to the remaining intermediate rod 3, and the curing agent is injected and pulled out again. In this way, all the steel sheet piles are removed while repeating drawing and cutting for each piece.

以上、簡易な装置および作業で、土留め工事を行うことができる。鋼矢板の引き抜きによる空隙が残らないので、地番変動が生じることが防止される。建て込みに水を使用しないので、施工場所を水浸しにすることがない。硬化剤注入管の設置においてボーリングマシン等を必要としないので、これらの設備を使用するためのレンタル料も不要になる。発電機も小型のもので済むので、エネルギーの消費も小さく、排気ガスも少なくなる。回収した鋼矢板は再利用されるので、資源の無駄な消費も生じない。 As described above, the earth retaining work can be performed with a simple device and work. Since there are no gaps left by pulling out the steel sheet piles, it is prevented that the lot number fluctuates. Since no water is used for installation, the construction site is not flooded. Since a boring machine or the like is not required for installing the hardener injection pipe, a rental fee for using these facilities is also unnecessary. Since the generator is small, energy consumption is small and exhaust gas is reduced. Since the collected steel sheet pile is reused, there is no wasteful consumption of resources.

この発明の第1の実施例について説明する。図14はこの実施例の硬化剤注入管を示す概念図である。中間ロッド3a、3bは平行に設けられた2本の円柱状のパイプである。それぞれのパイプ3a、3bが独立した硬化剤の流路を形成する。この中間ロッド3a、3bは長さ方向に分割されている。そして、長さ方向に差し込むことによって接続する接続部材によって接続される。この接続部材は、図5に示すものとほぼ同じであるが、各接続箇所においてそれぞれのパイプ3a、3bに対して1つずつ使用され、流路は1つのみである A first embodiment of the present invention will be described. FIG. 14 is a conceptual diagram showing a hardener injection tube of this embodiment. The intermediate rods 3a and 3b are two cylindrical pipes provided in parallel. Each pipe 3a, 3b forms an independent hardener flow path. The intermediate rods 3a and 3b are divided in the length direction. And it connects by the connection member connected by inserting in a length direction. This connection member is substantially the same as that shown in FIG. 5, but one for each of the pipes 3a and 3b at each connection location, and only one flow path .

そして、接続箇所にはブレ止め部材5aが取り付けられる。ブレ止め部材5aは略直方体状の外形を有し、パイプ3a、3bを収容するための2本の孔5bが貫通している。このブレ止め部材5aによってパイプ3a、3bの相互の位置関係が固定され、鋼矢板の建て込み時などにおけるパイプ3a、3bのブレを防止する。 And the anti-blur member 5a is attached to a connection location. The anti-blur member 5a has a substantially rectangular parallelepiped outer shape, and two holes 5b for receiving the pipes 3a and 3b pass therethrough. The mutual positional relationship between the pipes 3a and 3b is fixed by the anti-blur member 5a, thereby preventing the pipes 3a and 3b from blurring when a steel sheet pile is installed.

先端部材2は略直方体状の外形を有し、特に最先端部の面は斜めに切り取られた形状に形成されており、建て込み時に土中を進行しやすくなっている。先端部材2において二つの流路は合流し、それぞれのパイプ3a、3bを通ってきた液体が混合されるようになっている。側面に3つの吐出口を横方向に有する。 The tip member 2 has a substantially rectangular parallelepiped outer shape, and in particular, the surface of the most distal portion is formed in an obliquely cut shape so that the tip member 2 can easily travel through the soil when built. In the tip member 2, the two flow paths merge to mix the liquid that has passed through the pipes 3a and 3b. There are three outlets in the lateral direction on the side.

図15は第1の実施例における中央面への硬化剤注入管の取り付け作業を示す斜視図、図16は硬化剤注入管の溶接方法を示す概念図である。まず、先端部材2と中間ロッド3a、3bを接続部材を介して長さ方向に差し込むことによって、ワンタッチで接続する。そして、中間ロッド3a、3bの他端部にブレ止め部材5aを取り付ける。ブレ止め部材5aも、パイプ3a、3bを孔5bに通すようにして取り付けることができる。そして、先端部材2およびブレ止め部材5aを鋼矢板30に溶接する。先端部材2およびブレ止め部材5aは略直方体状であり、平面状の土留め部材取り付け面を有するので、簡単かつ確実に取り付けることができる。 FIG. 15 is a perspective view showing an attaching operation of the hardener injection pipe to the center surface in the first embodiment, and FIG. 16 is a conceptual view showing a welding method of the hardener injection pipe. First, the tip member 2 and the intermediate rods 3a and 3b are connected in one-touch by inserting them in the length direction via the connecting member. Then, the anti-blur member 5a is attached to the other end of the intermediate rods 3a and 3b. The anti-blur member 5a can also be attached by passing the pipes 3a and 3b through the hole 5b. Then, the tip member 2 and the anti-blur member 5 a are welded to the steel sheet pile 30. Since the tip member 2 and the anti-blur member 5a are substantially rectangular parallelepiped and have a planar earth retaining member attachment surface, they can be easily and reliably attached.

ついで、次の中間ロッド3a、3bを接続する。また、追加した中間ロッド3の上部にブレ止め部材5aを取り付ける。中間ロッド3同士の接続も、接続部材を介して長さ方向に差し込むことによって、ワンタッチで行える。ネジ式でないので中間ロッド3同士を回転する必要がないので、このように先端部から順次接続することができる。レンチなどの工具も特に要しない。 Next, the next intermediate rods 3a and 3b are connected. Further, the anti-blur member 5a is attached to the upper part of the added intermediate rod 3. The intermediate rods 3 can also be connected to each other by one touch by inserting them in the length direction via a connecting member. Since it is not a screw type, it is not necessary to rotate the intermediate rods 3, and thus it is possible to sequentially connect from the tip portion in this way. No special tools such as a wrench are required.

図17は第1の実施例における側面への硬化剤注入管の取り付け作業を示す斜視図である。まず、先端部材2と中間ロッド3a、3bを接続部材を介して長さ方向に差し込むことによって、ワンタッチで接続する。そして、中間ロッド3a、3bの他端部にブレ止め部材5aを取り付ける。先端部材2およびブレ止め部材5aを鋼矢板30の側面32に溶接する。さらに、次の中間ロッド3を継ぎ足しながら、順次溶接して、鋼矢板30の側面32に取り付けて行く。鋼矢板30の側面32は傾斜しているが、中間ロッド3同士の接続も、接続部材を介して長さ方向に差し込むことによって、ワンタッチで行える。ネジ式でないので中間ロッド3同士を回転する必要がないので、このように先端部から順次接続することができる。図17のように鋼矢板30の側面32に取り付けると、建て込み時に機械のチャック部に干渉しないので、鋼矢板30の最上部まで中間ロッド3を取り付けることができる。したがって、鋼矢板30のほとんど全部を地中に打ち込むことができ、地上に突き出る部分がほとんどない。 FIG. 17 is a perspective view showing an operation of attaching the curing agent injection pipe to the side surface in the first embodiment. First, the tip member 2 and the intermediate rods 3a and 3b are connected in one-touch by inserting them in the length direction via the connecting member. Then, the anti-blur member 5a is attached to the other end of the intermediate rods 3a and 3b. The tip member 2 and the anti-blur member 5 a are welded to the side surface 32 of the steel sheet pile 30. Further, the next intermediate rod 3 is welded in succession while being attached to the side face 32 of the steel sheet pile 30. Although the side surface 32 of the steel sheet pile 30 is inclined, the connection between the intermediate rods 3 can also be performed with one touch by inserting it in the length direction via the connecting member. Since it is not a screw type, it is not necessary to rotate the intermediate rods 3, and thus it is possible to sequentially connect from the tip portion in this way. When attached to the side surface 32 of the steel sheet pile 30 as shown in FIG. 17, the intermediate rod 3 can be attached up to the top of the steel sheet pile 30 because it does not interfere with the chuck portion of the machine at the time of installation. Therefore, almost all of the steel sheet pile 30 can be driven into the ground, and there is almost no portion protruding to the ground.

鋼矢板30に硬化剤注入管1を取り付けたら、地中に建て込む。そして、埋設工事が終了したら、鋼矢板30の引く抜きを行う。中間ロッド3a、3bの最上部に硬化剤導入部4を取り付け、硬化剤導入口12,13に硬化剤ホースを接続する鋼矢板30は端から順次引き抜くが、硬化剤注入管1により地中に硬化剤を注入しながら行う。この実施例では2本の独立したパイプ3a、3bにより独立した流路を有するので、2液性の硬化剤を使用することができる。たとえば、A液として水ガラス(JIS3号ケイ酸ナトリウム)80リットルに水120リットルを加えたものを用意し、B液としては、高炉セメントB種50Kg、YMS45(三興コロイド化学株式会社)10Kgおよび178.7リットルを混合したものを用意する。このA液とB液を1対1で注入する。また、高炉セメントB種50Kg、YMS90(三興コロイド化学株式会社)5Kgおよび181.4リットルを混合してB液としてもよい。これらの硬化剤は、毒物や劇物を含まない安全性の高い無公害薬剤である。 When the hardener injection pipe 1 is attached to the steel sheet pile 30, it is built into the ground. When the burying work is completed, the steel sheet pile 30 is pulled out. The steel sheet pile 30 that attaches the hardener introduction part 4 to the uppermost part of the intermediate rods 3a and 3b and connects the hardener hose to the hardener inlets 12 and 13 is sequentially pulled out from the end. Perform while injecting curing agent. In this embodiment, since two independent pipes 3a and 3b have independent flow paths, a two-component curing agent can be used. For example, 80 parts of water glass (JIS No. 3 sodium silicate) added to 120 liters of water is prepared as liquid A, and as liquid B, blast furnace cement type B 50 kg, YMS45 (Sanko Colloid Chemical Co., Ltd.) 10 kg and Prepare a mixture of 178.7 liters. This A liquid and B liquid are inject | poured 1: 1. Alternatively, 50 kg of Blast Furnace Cement B, 5 kg of YMS90 (Sanko Colloid Chemical Co., Ltd.) and 181.4 liters may be mixed to obtain B liquid. These hardeners are highly safe and non-polluting drugs that do not contain poisonous or deleterious substances.

この発明の第2の実施例について説明する。図18はこの実施例の硬化剤注入管を示す概念図である。中間ロッド3は円柱状の外形を有する。内部は、二重管構造になっており、独立した2つの流路7,8が設けられている。 A second embodiment of the present invention will be described. FIG. 18 is a conceptual diagram showing a curing agent injection tube of this embodiment. The intermediate rod 3 has a cylindrical outer shape. The inside has a double pipe structure, and two independent flow paths 7 and 8 are provided.

先端部材2は略直方体状の外形を有し、特に最先端部の面は斜めに切り取られた形状に形成されており、建て込み時に土中を進行しやすくなっている。先端部材2において二つの流路は合流し、それぞれ中間ロッド3の独立した2つの流路7,8液体が混合されるようになっている。側面に3つの吐出口を横方向に有する。 The tip member 2 has a substantially rectangular parallelepiped outer shape, and in particular, the surface of the most distal portion is formed in an obliquely cut shape so that the tip member 2 can easily travel through the soil when built. In the tip member 2, the two flow paths merge so that the two independent flow paths 7 and 8 of the intermediate rod 3 are mixed. There are three outlets in the lateral direction on the side.

先端部材2と中間ロッド3の間の接続、および中間ロッド3同士の間の接続は、図5に示す接続部材4を介して行う。したがって、中間ロッド3を回転させる必要はなく、長さ方向に挿し込むことによってワンタッチで接続することができる。 The connection between the tip member 2 and the intermediate rod 3 and the connection between the intermediate rods 3 are performed via a connection member 4 shown in FIG. Therefore, it is not necessary to rotate the intermediate rod 3, and it can be connected with one touch by inserting in the length direction.

鋼矢板30の中央面31に対しても、側面に対しても、硬化剤注入管を取り付けることができる。先端部材2と中間ロッド3の間の接続、および中間ロッド3同士の間の接続は、図5に示す接続部材4を介して行う。まず、先端部材2と中間ロッド3を接続部材を介して長さ方向に差し込むことによって、ワンタッチで接続する。そして、先端部材2を鋼矢板30に溶接する。 A hardener injection tube can be attached to both the central surface 31 and the side surface of the steel sheet pile 30. The connection between the tip member 2 and the intermediate rod 3 and the connection between the intermediate rods 3 are performed via a connection member 4 shown in FIG. First, the tip member 2 and the intermediate rod 3 are connected in one-touch by inserting them in the length direction via a connecting member. Then, the tip member 2 is welded to the steel sheet pile 30.

ついで、次の中間ロッド3を接続する。そして、L字アングルなどの固定金具23を介して接続箇所を溶接し、中間ロッド3を鋼矢板30に固定する。同様の手順で、鋼矢板30の上端まで中間ロッド3を継ぎ足しながら鋼矢板30に取り付けていく。中間ロッド3同士の接続も、接続部材を介して長さ方向に差し込むことによって、ワンタッチで行える。ネジ式でないので中間ロッド3同士を回転する必要がないので、このように先端部から順次接続することができる。レンチなどの工具も特に要しない。 Next, the next intermediate rod 3 is connected. And a connection location is welded via fixing brackets 23, such as an L-shaped angle, and the intermediate rod 3 is fixed to the steel sheet pile 30. FIG. The intermediate rod 3 is attached to the steel sheet pile 30 while adding the intermediate rod 3 to the upper end of the steel sheet pile 30 in the same procedure. The intermediate rods 3 can also be connected to each other by one touch by inserting them in the length direction via a connecting member. Since it is not a screw type, it is not necessary to rotate the intermediate rods 3, and thus it is possible to sequentially connect from the tip portion in this way. No special tools such as a wrench are required.

このようにして、硬化剤注入管を取り付けた鋼矢板は、第1の実施例と同様に、地中に建て込む。引き抜き時には、最上段の中間ロッド3に硬化剤導入部4を取り付ける。この実施例の硬化剤導入部4は、鋼矢板30の引き抜きに使用されるパイラーと呼ばれる機械のチャック部に取り付けられている。そして、硬化剤注入管1により地中に硬化剤を注入しながら、鋼矢板の引き抜きを行う。この硬化剤注入管1は、2つの独立した流路7,8を有するので、2液性の硬化剤を使用することができ、第1の実施例に記載した例の硬化剤を使用することができる。 Thus, the steel sheet pile to which the hardener injection pipe is attached is built in the ground as in the first embodiment. At the time of drawing, the curing agent introduction part 4 is attached to the uppermost intermediate rod 3. The hardening | curing agent introducing | transducing part 4 of this Example is attached to the chuck | zipper part of the machine called a pillar used for extraction of the steel sheet pile 30. FIG. Then, the steel sheet pile is pulled out while injecting the curing agent into the ground by the curing agent injection tube 1. Since this curing agent injection tube 1 has two independent flow paths 7 and 8, a two-component curing agent can be used, and the curing agent of the example described in the first embodiment should be used. Can do.

この発明の第3の実施例について説明する。図19はこの実施例を示す概念図、図20はこの実施例における鋼矢板の建て込み方法を示す概念図である。この実施例においては、硬化剤注入管1に加えて高圧水注入管40も土留め部材に取り付けて土留めを行う。鋼矢板が入りにくい土質のときには、高圧水注入管40より200kg/cm2程度の高圧水を真下に噴出することによって、鋼矢板の建て込みを迅速に行うことができる。 A third embodiment of the present invention will be described. FIG. 19 is a conceptual diagram showing this embodiment, and FIG. 20 is a conceptual diagram showing a steel sheet pile installation method in this embodiment. In this embodiment, in addition to the hardener injection tube 1, the high-pressure water injection tube 40 is also attached to the earth retaining member for earth retaining. When the steel sheet pile is difficult to enter, the steel sheet pile can be built quickly by ejecting about 200 kg / cm 2 of high-pressure water directly from the high-pressure water injection pipe 40.

鋼矢板30の引き抜き時には、硬化剤注入管1により地中に硬化剤を注入し、引き抜き跡の空隙を埋めていく。ここで注入する硬化剤は1液のものである。たとえば、高炉セメントB種50Kg、ベントナイト10Kg、セメントミルク凝結硬化促進剤であるYMS2000(三興コロイド化学株式会社)4Kgおよび177.8リットルを混合したものを使用することができる。これは、流動性消失時間が30〜40分程度の硬化剤である。 When the steel sheet pile 30 is pulled out, the hardener is injected into the ground by the hardener injection tube 1 to fill the voids in the extraction trace. The hardening | curing agent inject | poured here is a thing of 1 liquid. For example, it is possible to use a mixture of 50 kg of blast furnace cement B, 10 kg of bentonite, 4 kg of cement milk setting accelerator, 4 kg of Sanko Colloid Chemical Co., Ltd., and 177.8 liters. This is a curing agent having a fluidity disappearance time of about 30 to 40 minutes.

この実施例の場合、全ての鋼矢板30に硬化剤注入管1と高圧水注入管40を取り付ける。鋼矢板30の建て込み方法として、振動式杭打ち機で強制振動を加えながら建て込むバイブロハンマー工法と呼ばれるものと、既に建て込まれた鋼矢板を機械がつかみながら反力で鋼矢板30を地中に圧入するサイレントパイラー工法と呼ばれるものがある。 In the case of this embodiment, the hardener injection pipe 1 and the high-pressure water injection pipe 40 are attached to all the steel sheet piles 30. The steel sheet pile 30 can be built using the vibro-hammer method, which is built while applying forced vibration with a vibration pile driver, and the steel sheet pile 30 is grounded by the reaction force while the machine holds the already built steel sheet pile. There is a so-called Silent Piler method that press fits inside.

図21はバイブロハンマー工法における硬化剤注入管1と高圧水注入管40の取り付け位置を示す平面図、図22は同斜視図である。鋼矢板30の中央面の内側と外側の中央部(図21における場所1と場所2)に硬化剤注入管1と高圧水注入管40を取り付ける。建て込み時には、高圧水注入管40で高圧水を噴出する。特に鋼矢板が入りにくい場合には、この場所1と場所2に加え、左右の側面(図21における場所3と場所4)に硬化剤注入管1と高圧水注入管40を取り付けてもよい。引き抜き時には、各鋼矢板30ごとに硬化剤を注入する。 FIG. 21 is a plan view showing attachment positions of the curing agent injection pipe 1 and the high-pressure water injection pipe 40 in the vibro hammer method, and FIG. 22 is a perspective view thereof. The hardener injection tube 1 and the high-pressure water injection tube 40 are attached to the inner and outer central portions (location 1 and location 2 in FIG. 21) of the central surface of the steel sheet pile 30. At the time of installation, high-pressure water is ejected through the high-pressure water injection pipe 40. In particular, when the steel sheet pile is difficult to enter, the hardener injection tube 1 and the high-pressure water injection tube 40 may be attached to the left and right side surfaces (location 3 and location 4 in FIG. 21) in addition to the location 1 and location 2. At the time of drawing, a hardening agent is injected for each steel sheet pile 30.

図23はサイレントパイラー工法における硬化剤注入管1と高圧水注入管40の取り付け位置を示す平面図、図24は同斜視図である。鋼矢板30の中央面で内側を向いた面の中央部(図23における場所1)に硬化剤注入管1と高圧水注入管40を取り付ける。建て込み時には、高圧水注入管40で高圧水を噴出する。特に鋼矢板が入りにくい場合には、この場所1に加え、左右の側面(図21における場所3と場所4)に硬化剤注入管1と高圧水注入管40を取り付けてもよい。引き抜き時には、各鋼矢板30ごとに硬化剤を注入する。 FIG. 23 is a plan view showing attachment positions of the curing agent injection pipe 1 and the high-pressure water injection pipe 40 in the silent pillar method, and FIG. 24 is a perspective view thereof. The hardener injection pipe 1 and the high-pressure water injection pipe 40 are attached to the central portion (place 1 in FIG. 23) of the surface facing the inside on the central surface of the steel sheet pile 30. At the time of installation, high-pressure water is ejected through the high-pressure water injection pipe 40. In particular, when the steel sheet pile is difficult to enter, the hardener injection tube 1 and the high-pressure water injection tube 40 may be attached to the left and right side surfaces (location 3 and location 4 in FIG. 21) in addition to the location 1. At the time of drawing, a hardening agent is injected for each steel sheet pile 30.

この発明のシートパイルは、地中に水道管やガス管等を埋設する工事の施工等シートパイル等の土留め部材により土留めを行いながら行う工事について広く利用できるものである。土留め部材の跡に生じる空隙を残さないので、空隙に起因する地中の土壌の移動や地下水の水路の変化に伴う地盤状態の変動を発生させなることがなく、安全で環境への影響が少ない土留め工事が実現できる。 The sheet pile according to the present invention can be widely used for constructions that are carried out with earth retaining members such as sheet piles, such as construction for embedding water pipes and gas pipes in the ground. Since there are no gaps left in the traces of the earth retaining members, there will be no changes in the ground conditions due to the movement of soil in the ground due to the gaps and changes in the groundwater channels, which has a safe and environmental impact. Less earth retaining work can be realized.

土留め工事用硬化剤注入管の概略を示す正面図である。It is a front view which shows the outline of the hardening | curing agent injection pipe | tube for earth retaining work. 先端部材を示す断面図である。It is sectional drawing which shows a front-end | tip member. 中間ロッドを示す断面図である。It is sectional drawing which shows an intermediate | middle rod. 硬化剤導入部を示す断面図である。It is sectional drawing which shows a hardening | curing agent introduction part. 接続部材を示す断面図である。It is sectional drawing which shows a connection member. 中央面への硬化剤注入管の取り付け作業を示す斜視図である。It is a perspective view which shows the attachment operation | work of the hardening | curing agent injection pipe | tube to a center surface. 接続箇所を示す断面図である。It is sectional drawing which shows a connection location. 側面への硬化剤注入管の取り付け作業を示す斜視図である。It is a perspective view which shows the attachment operation | work of the hardening | curing agent injection pipe | tube to a side surface. 複数の異なる深さで硬化剤を注入する方法を示す斜視図である。It is a perspective view which shows the method of inject | pouring a hardening | curing agent in several different depth. 多段式硬化剤注入管の例を示す断面図である。It is sectional drawing which shows the example of a multistage type hardener injection tube. 多段式硬化剤注入管の別の例を示す断面図である。It is sectional drawing which shows another example of a multistage hardener injection tube. 鋼矢板を分割して設置する方法を示す概略図である。It is the schematic which shows the method of dividing | segmenting and installing a steel sheet pile. 円柱状の硬化剤注入管の取り付け作業を示す斜視図である。It is a perspective view which shows the attachment operation | work of a column-shaped hardening | curing agent injection pipe. 第1の実施例の硬化剤注入管を示す概念図である。It is a conceptual diagram which shows the hardening | curing agent injection pipe | tube of a 1st Example. 第1の実施例における中央面への硬化剤注入管の取り付け作業を示す斜視図である。It is a perspective view which shows the attachment operation | work of the hardening | curing agent injection pipe to the center surface in a 1st Example. 硬化剤注入管の溶接方法を示す概念図である。It is a conceptual diagram which shows the welding method of a hardening | curing agent injection pipe. 第1の実施例における側面への硬化剤注入管の取り付け作業を示す斜視図である。It is a perspective view which shows the attachment operation | work of the hardening | curing agent injection | pouring pipe | tube to the side surface in a 1st Example. 第2の実施例の硬化剤注入管を示す概念図である。It is a conceptual diagram which shows the hardening | curing agent injection pipe | tube of a 2nd Example. 第3の実施例を示す概念図である。It is a conceptual diagram which shows a 3rd Example. 第3の実施例における鋼矢板の建て込み方法を示す概念図である。It is a conceptual diagram which shows the construction method of the steel sheet pile in a 3rd Example. バイブロハンマー工法における硬化剤注入管と高圧水注入管の取り付け位置を示す平面図である。It is a top view which shows the attachment position of the hardening | curing agent injection pipe in a vibro hammer construction method, and a high pressure water injection pipe. 同斜視図である。It is the same perspective view. サイレントパイラー工法における硬化剤注入管と高圧水注入管の取り付け位置を示す平面図である。It is a top view which shows the attachment position of the hardening | curing agent injection pipe and high-pressure water injection pipe in a silent pillar construction method. 同斜視図である。It is the same perspective view.

符号の説明Explanation of symbols

1.土留め工事用硬化剤注入管
2.先端部材
3.中間ロッド
4.硬化剤導入部
5.接続部材
6.土留め部材取り付け面
7,8 流路
9.吐出口
10.栓
11.付勢手段
23.固定金具
30.鋼矢板
31.中央面
32.側面
1. Hardener injection pipe for earth retaining work2. 2. Tip member Intermediate rod 4. 4. Curing agent introduction part Connecting member 6. Earth retaining member mounting surface 7, 8 Channel 9. Discharge port 10. Stopper 11. Biasing means 23. Fixing bracket 30. Steel sheet pile 31. Central surface 32. side

Claims (8)

硬化剤を送り込む流路を有し、複数の部分に長さ方向に分割されている硬化剤注入管であり、分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続する接続部材と、土留め部材に当接する平面状の土留め部材取り付け面を有する土留め工事用硬化剤注入管。 It is a curing agent injection pipe having a flow path for feeding a curing agent and divided in a length direction into a plurality of portions, and each flow path is inserted by inserting the divided curing agent injection pipes in the axial direction. A hardening agent injection pipe for earth retaining work , comprising a connecting member connected so as to be connected, and a planar earth retaining member mounting surface abutting against the earth retaining member . 複数の中間ロッドに分割されており、中間ロッドは平行に設けられた2本の円柱状のパイプを有し、ブレ止め部材により2本の円柱状のパイプの相互の位置関係が固定され、ブレ止め部材には平面状の土留め部材取り付け面が設けられている請求項1に記載の土留め工事用硬化剤注入管。The intermediate rod is divided into a plurality of intermediate rods, and the intermediate rod has two cylindrical pipes provided in parallel, and the positional relationship between the two cylindrical pipes is fixed by the anti-blur member, and the The hardener injection pipe for earth retaining work according to claim 1, wherein the retaining member is provided with a planar earth retaining member mounting surface. 外形が概ね多角柱状である請求項に記載の土留め工事用硬化剤注入管。 Retaining construction curing agent injection tube according to claim 1 is the outer shape is generally polygonal shape. 外形が概ね四角柱状である請求項に記載の土留め工事用硬化剤注入管。 The hardener injection pipe for earth retaining work according to claim 3 , wherein the outer shape is substantially a quadrangular prism shape. 硬化剤を送り込む流路を有し、複数の部分に長さ方向に分割されていて、土留め部材に当接する平面状の土留め部材取り付け面を有し、分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続する接続部材を有する土留め工事用硬化剤注入管を、土留め部材取り付け面にて溶接することにより土留め部材に取り付けて地中に建て込んで土留めを行う工法であって、
分割された硬化剤注入管同士を軸方向に挿し込むことによって各流路同士をつなぐように接続して土留め工事用硬化剤注入管を土留め部材に取り付け、
土留め部材の引抜き時には硬化剤を硬化剤注入管の流路を介して地中に注入しながら引抜を行い、土留め部材の引抜き跡の空隙を硬化剤で充填する土留め工法。
It has a flow path for feeding the curing agent, is divided into a plurality of portions in the length direction, has a flat earth retaining member mounting surface that comes into contact with the earth retaining member, and the divided curing agent injection pipes are connected to each other. By attaching the hardening agent injection pipe for earth retaining work having a connecting member to connect each flow path by inserting in the axial direction, it is attached to the earth retaining member by welding on the earth retaining member attaching surface. It is a construction method that builds in and holds earth retaining,
Attaching the hardener injection pipe for earthing work to the earth retaining member by connecting the flow paths to each other by inserting the divided hardener injection pipes in the axial direction,
A soil retaining method in which when the earth retaining member is pulled out, the curing agent is extracted while being injected into the ground through the flow path of the curing agent injecting pipe, and the void of the withdrawal trace of the earth retaining member is filled with the curing agent.
施工現場にて土留め工事用硬化剤注入管を土留め部材に取り付けるものである請求項5に記載の土留め工法。 6. The earth retaining method according to claim 5, wherein the earth retaining work hardener injection pipe is attached to the earth retaining member at a construction site . 土留め部材が中央面とその中央面の両端につながった側面とを有する鋼矢板であり、側面に土留め工事用硬化剤注入管を取り付ける請求項5または請求項6に記載の土留め工法。 The earth retaining method according to claim 5 or 6, wherein the earth retaining member is a steel sheet pile having a central surface and side surfaces connected to both ends of the central surface, and a hardener injection pipe for earth retaining work is attached to the side surface. 土留め部材が長さ方向に複数の部分部材に分割されており、部分部材に分割された硬化剤注入管を取り付けてから地中に建て込み、直前に建て込まれた部分部材の上部に次の部分部材を溶接により接続するとともに直前に建て込まれた部分部材の硬化剤注入管に次の分割された硬化剤注入管を軸方向に挿し込んで接続した上で次の部分部材に取り付けてからさらに地中に建て込んでいく請求項5ないし請求項7のいずれかに記載の土留め工法。 The earth retaining member is divided into a plurality of partial members in the length direction, and after installing the divided hardener injection pipe into the partial members, it is built in the ground, and next to the upper part of the partial member that was built immediately before After connecting the partial member of this part by welding and inserting the next divided hardener injection pipe into the hardener injection pipe of the partial member built immediately before and connecting it to the next partial member The earth retaining method according to any one of claims 5 to 7, wherein the earth retaining method is further built into the ground.
JP2006283721A 2006-10-18 2006-10-18 Hardener injection pipe for earth retaining work and earth retaining method Active JP4897985B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006283721A JP4897985B2 (en) 2006-10-18 2006-10-18 Hardener injection pipe for earth retaining work and earth retaining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006283721A JP4897985B2 (en) 2006-10-18 2006-10-18 Hardener injection pipe for earth retaining work and earth retaining method

Publications (2)

Publication Number Publication Date
JP2008101373A JP2008101373A (en) 2008-05-01
JP4897985B2 true JP4897985B2 (en) 2012-03-14

Family

ID=39435908

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006283721A Active JP4897985B2 (en) 2006-10-18 2006-10-18 Hardener injection pipe for earth retaining work and earth retaining method

Country Status (1)

Country Link
JP (1) JP4897985B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5635804B2 (en) * 2010-05-10 2014-12-03 山下 伸一 Method for removing earth retaining member and method for installing slope reinforcing block using the same
JP6273603B2 (en) * 2013-12-19 2018-02-07 大地 山下 Earth retaining method
JP7073326B2 (en) 2019-12-20 2022-05-23 大地 山下 How to remove buried objects
JP6917099B1 (en) * 2021-03-18 2021-08-11 株式会社遠藤工業 Steel sheet pile drawing void filling method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH079095B2 (en) * 1989-04-21 1995-02-01 栄興産業株式会社 Jet stirring device
JP3940735B2 (en) * 2004-03-09 2007-07-04 伸一 山下 Earth retaining method

Also Published As

Publication number Publication date
JP2008101373A (en) 2008-05-01

Similar Documents

Publication Publication Date Title
KR101067707B1 (en) The earth retaining wall and waterproof construction technique for which cast in place concrete pile and grouting column was used
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
JP4897985B2 (en) Hardener injection pipe for earth retaining work and earth retaining method
KR100832490B1 (en) A foundation method of continuous and cut off wall by overlap casing
KR100652558B1 (en) Guide pipe for sheet pile and construction method using the same
JP2015124478A (en) Construction method of earth retaining wall
KR20000006650A (en) a pole for mud wall and constrution method of fence for mud
JP3940735B2 (en) Earth retaining method
JP6273603B2 (en) Earth retaining method
KR20200133548A (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
JP2005273376A (en) Working face stabilizing method applicable to underground structure construction method
JP7280602B2 (en) Concrete wall forming method for earth retaining
KR200403694Y1 (en) Guide pipe for sheet pile
JP6361045B2 (en) Removal method of earth retaining members
JP5648850B2 (en) Groundwater collection structure and groundwater flow structure
JP2009068203A (en) Earth retaining wall composed of horizontal sheathing with soldier beam, and cut-off structure, construction method and cut-off method for the earth retaining wall
JP4905296B2 (en) Method for constructing retaining wall and retaining wall
KR100968431B1 (en) Jacket Installing process of jacket facility structure using R.C.D. reamming bit for excavating enlarged hole in the earth
KR101736117B1 (en) Construction equipment and construction method of underground watertight wall
KR100446586B1 (en) Soil-Nail able to Withdraw Itself by Blasting
JPH0813495A (en) Earth retaining wall and method thereof
KR101327172B1 (en) Water-proof and retaining method
KR102184081B1 (en) Construction method for perforating goround bore using inverse casing
JP6206899B2 (en) Earth retaining pipe for reaching mine and underground pipe construction method using the same
KR20030091836A (en) A Continuous and Cut Off wall And Foundation Method By Overlap Casing

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091003

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101126

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110420

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110425

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110622

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20110622

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111206

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111224

R150 Certificate of patent or registration of utility model

Ref document number: 4897985

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150106

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250