JP2009287326A - Pulling out method of existing pile - Google Patents

Pulling out method of existing pile Download PDF

Info

Publication number
JP2009287326A
JP2009287326A JP2008142690A JP2008142690A JP2009287326A JP 2009287326 A JP2009287326 A JP 2009287326A JP 2008142690 A JP2008142690 A JP 2008142690A JP 2008142690 A JP2008142690 A JP 2008142690A JP 2009287326 A JP2009287326 A JP 2009287326A
Authority
JP
Japan
Prior art keywords
existing pile
ground
cutting rod
cutting
pulling out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008142690A
Other languages
Japanese (ja)
Other versions
JP5100512B2 (en
Inventor
Mitsuo Kametani
光男 亀谷
Akira Hyogoya
明 兵庫谷
Shinichi Goto
信一 後藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fukuda Corp
Original Assignee
Fukuda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fukuda Corp filed Critical Fukuda Corp
Priority to JP2008142690A priority Critical patent/JP5100512B2/en
Publication of JP2009287326A publication Critical patent/JP2009287326A/en
Application granted granted Critical
Publication of JP5100512B2 publication Critical patent/JP5100512B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a pulling out method of an existing pile which makes possible pulling out of the existing pile with a simple facility at low cost and which is excellent in practicality. <P>SOLUTION: In the pulling out method of the existing pile, part of or the whole of the existing pile is buried in the ground 1. One or a plurality of bore holes 4 are bored in the existing pile 2 along its axial direction by a rod 3 for cutting while issuing a fluid from the rod 3 for cutting on the ground 1 surrounding the existing pile 2 and softening the ground 1 surrounding the rod 3 for cutting. After that, a filler is charged from the rod 3 for cutting while pulling the rod 3 for cutting out of the bore hole 4. The filler is used for controlling the tightening and hardening of the softened ground 8 surrounding the rod 3 for cutting. Then the soil pressure which the existing pile 2 receives from the ground 1 is reduced, and the existing pile 2 is pulled out of the ground 1 in this sate of reduced soil pressure. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、既存杭の引き抜き方法に関するものである。   The present invention relates to a method for extracting an existing pile.

地盤に一部若しくは全部が埋設された既存杭を引き抜く方法としては、例えば特許文献1に開示されるように、既存杭よりやや径大な管体を既存杭を囲うように打ち込み埋設し、既存杭と周囲の地盤とを縁切りして(既存杭の周面摩擦力をカットして)既存杭にかかる土圧を低減せしめた状態で、この既存杭をクレーンで引き上げる方法が知られている。   As a method of pulling out an existing pile partially or wholly embedded in the ground, for example, as disclosed in Patent Document 1, a pipe having a diameter slightly larger than that of an existing pile is driven and embedded so as to surround the existing pile. A method is known in which a pile is lifted with a crane while cutting the pile and the surrounding ground (cutting the peripheral frictional force of the existing pile) to reduce the earth pressure applied to the existing pile.

特開2001−303570号公報JP 2001-303570 A

しかしながら、上記方法を行う場合には、既存杭より径大な大型で重い管体を必要とし、これを運搬したり打ち込むためのクレーンや打ち込み装置も大型となり非常にコスト高となるのは勿論、管体を打ち込んだり引き上げる際に上方に広い作業空間を確保する必要があることから、例えば高架線が既存杭の上空に存在する場合には施工が厄介である。また、河川内など足場が悪く大型の装置の配置が困難な場所での施工も厄介である。   However, when performing the above method, it requires a large and heavy pipe having a diameter larger than that of the existing pile, and of course, the crane and driving device for transporting and driving this are also large and very expensive. Since it is necessary to secure a wide working space above when the pipe body is driven or pulled up, the construction is troublesome when, for example, an overhead wire exists above the existing pile. In addition, it is troublesome to construct in places such as rivers where the scaffolding is poor and it is difficult to place a large device.

また、管体を打ち込まずに切削装置によって既存杭の全周を囲うような環状の縁切り孔を切削形成する方法も考えられるが、このような縁切り孔を切削形成するのは極めて時間と手間がかかり厄介である。   In addition, a method of cutting and forming an annular edge hole that surrounds the entire circumference of an existing pile without using a pipe body can be considered, but cutting and forming such an edge hole is extremely time consuming and laborious. It is troublesome.

本発明は、上述のような現状に鑑みなされたもので、従来のように既存杭より径大な管体を用いる必要なく、また、既存杭の全周を囲うような縁切り孔を形成する必要もなく、簡易な設備でそれだけコスト安に既存杭の引き抜きを可能とする極めて実用性に秀れた既存杭の引き抜き方法を提供するものである。   The present invention has been made in view of the above situation, and it is not necessary to use a pipe having a diameter larger than that of an existing pile as in the prior art, and it is also necessary to form an edge cutting hole that surrounds the entire circumference of the existing pile. In addition, the present invention provides a method for pulling out an existing pile that is excellent in practicality, and can be used to pull out an existing pile at a low cost with simple equipment.

添付図面を参照して本発明の要旨を説明する。   The gist of the present invention will be described with reference to the accompanying drawings.

地盤1に一部若しくは全部が埋設された既存杭の引き抜き方法であって、前記既存杭2の周囲の地盤1に、切削用ロッド3から流体を噴出させて該切削用ロッド3の周囲の地盤1を軟化せしめながら該切削用ロッド3により一若しくは複数のボーリング孔4を該既存杭2の軸方向に沿って穿設した後、前記切削用ロッド3を前記ボーリング孔4から引き抜きながら該切削用ロッド3から該切削用ロッド3の周囲の軟化した地盤8の締め固まりを抑制する充填材を充填し前記既存杭2が地盤1から受ける土圧を軽減させ、この土圧が軽減した状態で前記既存杭2を前記地盤1から引き抜くことを特徴とする既存杭の引き抜き方法に係るものである。   A method for extracting an existing pile partially or wholly embedded in the ground 1, wherein a fluid is ejected from the cutting rod 3 to the ground 1 around the existing pile 2 and the ground around the cutting rod 3 1 or a plurality of boring holes 4 are drilled along the axial direction of the existing pile 2 while the cutting rod 3 is softened, and then the cutting rod 3 is pulled out of the boring hole 4 and cut. The rod 3 is filled with a filler that suppresses the compaction of the softened ground 8 around the cutting rod 3 to reduce the earth pressure that the existing pile 2 receives from the ground 1. The present invention relates to a method for extracting an existing pile, wherein the existing pile 2 is extracted from the ground 1.

また、請求項1記載の既存杭の引き抜き方法において、前記既存杭2の外周面に接する地盤1が軟化するように前記切削用ロッド3を前記地盤1に導入することを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, the drawing method of the existing pile of Claim 1 WHEREIN: The said rod 3 for cutting is introduce | transduced into the said ground 1 so that the ground 1 which contact | connects the outer peripheral surface of the said existing pile 2 may be softened. This relates to the drawing method.

また、請求項1,2いずれか1項に記載の既存杭の引き抜き方法において、前記充填材の種類若しくは量を調整して前記軟化した地盤8の締め固まり抑制時間を設定することを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, in the extraction method of the existing pile of any one of Claims 1, 2, the kind or quantity of the said filler is adjusted, and the compaction suppression time of the said softened ground 8 is set, It is characterized by the above-mentioned. This relates to the method of pulling out existing piles.

また、請求項3記載の既存杭の引き抜き方法において、前記充填材には増粘材が含まれていることを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, the extraction method of the existing pile of Claim 3 is based on the extraction method of the existing pile characterized by the said thickener being contained in the said filler.

また、請求項1〜4いずれか1項に記載の既存杭の引き抜き方法において、前記既存杭2を囲うように前記ボーリング孔4を該既存杭2から離れた位置に夫々独立に複数穿設することを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, in the extraction method of the existing pile according to any one of claims 1 to 4, a plurality of the boring holes 4 are independently drilled at positions away from the existing pile 2 so as to surround the existing pile 2. The present invention relates to a method for pulling out an existing pile.

また、請求項1〜5いずれか1項に記載の既存杭の引き抜き方法において、前記既存杭2は無底筒状であり、この既存杭2を引き抜く際、この既存杭2の内周側の前記地盤1に前記ボーリング孔4を穿設することを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, in the extraction method of the existing pile of any one of Claims 1-5, the said existing pile 2 is a bottomless cylindrical shape, and when this existing pile 2 is extracted, the inner peripheral side of this existing pile 2 is provided. The boring hole 4 is drilled in the ground 1 and relates to a method for pulling out an existing pile.

また、請求項1〜6いずれか1項に記載の既存杭の引き抜き方法において、複数の前記ボーリング孔4を穿設する際、同一の前記切削用ロッド3を用いて前記各ボーリング孔4を順次穿設することを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, in the extraction method of the existing pile of any one of Claims 1-6, when drilling the said several boring hole 4, each said boring hole 4 is sequentially used using the same said rod 3 for cutting. The present invention relates to a method for pulling out an existing pile characterized by drilling.

また、請求項1〜7いずれか1項に記載の既存杭の引き抜き方法において、前記既存杭2の前記地盤1から露出する露出部に下向きのジャッキ受け面5を有するジグ6を取り付け固定すると共に、このジャッキ受け面5と対向状態に押し上げジャッキ7を配設し、この押し上げジャッキ7により前記ジグ6のジャッキ受け面5を押し上げることで前記既存杭2を引き上げ引き抜くことを特徴とする既存杭の引き抜き方法に係るものである。   Moreover, in the extraction method of the existing pile of any one of Claims 1-7, while attaching and fixing the jig 6 which has the downward jack receiving surface 5 to the exposed part exposed from the said ground 1 of the said existing pile 2 A push-up jack 7 is arranged opposite to the jack receiving surface 5, and the existing pile 2 is lifted and pulled out by pushing up the jack receiving surface 5 of the jig 6 by the push-up jack 7. This relates to the drawing method.

本発明は上述のようにするから、従来のように既存杭より径大な管体を用いる必要なく、また、既存杭の全周を囲うような縁切り孔を形成する必要もなく、簡易な設備でそれだけコスト安に既存杭の引き抜きを可能とする極めて実用性に秀れた既存杭の引き抜き方法となる。   Since the present invention is as described above, it is not necessary to use a pipe having a diameter larger than that of an existing pile as in the prior art, and it is not necessary to form an edge cutting hole that surrounds the entire circumference of the existing pile. Therefore, the existing pile can be pulled out at a very low cost.

好適と考える本発明の実施形態を、図面に基づいて本発明の作用を示して簡単に説明する。   An embodiment of the present invention which is considered to be suitable will be briefly described with reference to the drawings showing the operation of the present invention.

既存杭2の周囲の地盤1にボーリング孔4を穿設することで、このボーリング孔4により既存杭2と周囲の地盤1とを縁切りして(既存杭2の周面摩擦力をカットして)既存杭2を締め付ける地盤1の土圧を解放(軽減)することができ、よって、既存杭2を良好に引き抜くことが可能となる。   By drilling a boring hole 4 in the ground 1 around the existing pile 2, the existing pile 2 and the surrounding ground 1 are cut by this boring hole 4 (cutting the peripheral frictional force of the existing pile 2 ) The earth pressure of the ground 1 for fastening the existing pile 2 can be released (reduced), and thus the existing pile 2 can be pulled out satisfactorily.

また、切削用ロッド3によりボーリング孔4を穿設することで縁切りを行うため、従来のように既存杭2を囲う径大な管体を打ち込む必要がなく、径大で重い管体を打ち込む大型の打ち込み装置等は不要となり、径小な切削用ロッド3の回転降下導入が可能な一般的なボーリング装置を用いるだけで済み、極めてコスト性に秀れる。   Further, since the edge cutting is performed by drilling the boring hole 4 with the cutting rod 3, it is not necessary to drive a large tube surrounding the existing pile 2 as in the prior art, and a large tube for driving a large and heavy tube. No need for a driving device or the like, and it is only necessary to use a general boring device capable of introducing a rotational drop of the small-diameter cutting rod 3, which is extremely cost-effective.

また、切削用ロッド3は1mおき等、短い間隔で継ぎ足して導入長さを調整できるため、上方に広い作業空間を確保する必要がなく、よって、上空に高架線が存在する場合であっても良好に施工可能となる。   Moreover, since the cutting rod 3 can be added at a short interval, such as every 1 m, and the introduction length can be adjusted, it is not necessary to secure a wide working space above, so even if there is an overhead wire in the sky Good construction is possible.

また、切削用ロッド3から水等の流体を噴射して切削用ロッド3の周囲の地盤1を軟化せしめながらボーリング孔4を穿設することで、より効率的に縁切りを行うことができ、一層効率的に土圧を軽減できる。   Further, by cutting the boring hole 4 while jetting a fluid such as water from the cutting rod 3 and softening the ground 1 around the cutting rod 3, the edge can be cut more efficiently. The earth pressure can be reduced efficiently.

また、切削用ロッド3をボーリング孔4から引き抜く際、軟化した地盤8の締め固まりを抑制する充填材を充填することで、切削用ロッド3をボーリング孔4から引き抜いた後も該ボーリング孔及び軟化した地盤8が締め固まることを阻止でき、複数のボーリング孔4を穿設する場合でも良好に土圧を軽減できる。   Further, when the cutting rod 3 is pulled out from the boring hole 4, a filling material that suppresses the compaction of the softened ground 8 is filled, so that the boring hole and the softening after the cutting rod 3 is pulled out from the boring hole 4 are filled. The ground 8 can be prevented from being compacted, and the earth pressure can be reduced well even when a plurality of boring holes 4 are formed.

更に、ボーリング孔4を既存杭2を囲うように該既存杭2から離れた位置に夫々独立に複数穿設することで、一層良好に土圧を軽減できる。また、この際、ボーリング孔4を夫々連設させず夫々独立に穿設するため、既存杭2の全周を囲うような環状の縁切り孔を形成する場合に比し、それだけ縁切り作業が簡易となる。   Furthermore, the earth pressure can be further reduced by perforating a plurality of boring holes 4 at positions apart from the existing pile 2 so as to surround the existing pile 2. Further, at this time, since the boring holes 4 are formed independently without being continuously provided, the edge cutting operation is simpler than that in the case of forming an annular edge cutting hole surrounding the entire circumference of the existing pile 2. Become.

本発明の具体的な実施例について図面に基づいて説明する。   Specific embodiments of the present invention will be described with reference to the drawings.

本実施例は、図1に図示したような地盤1に一部若しくは全部が埋設された既存杭の引き抜き方法であって、前記既存杭2の周囲の地盤1に、切削用ロッド3から流体を噴出させて該切削用ロッド3の周囲の地盤1を軟化せしめながら該切削用ロッド3により一若しくは複数のボーリング孔4を該既存杭2の軸方向に沿って穿設した後、前記切削用ロッド3を前記ボーリング孔4から引き抜きながら該切削用ロッド3から該切削用ロッド3の周囲の軟化した地盤8の締め固まりを抑制する充填材を充填し前記既存杭2が地盤1から受ける土圧を軽減させ、この土圧が軽減した状態で前記既存杭2を前記地盤1から引き抜くものである。   The present embodiment is a method for extracting an existing pile partially or entirely embedded in the ground 1 as shown in FIG. 1, and the fluid is applied to the ground 1 around the existing pile 2 from the cutting rod 3. One or a plurality of boring holes 4 are drilled along the axial direction of the existing pile 2 with the cutting rod 3 while softening the ground 1 around the cutting rod 3, and then the cutting rod The earth pressure that the existing pile 2 receives from the ground 1 is filled with a filler that suppresses the compaction of the softened ground 8 around the cutting rod 3 from the cutting rod 3 while pulling out the 3 from the boring hole 4. The existing pile 2 is pulled out from the ground 1 in a state where the earth pressure is reduced.

本実施例では、地盤1に先端部の一部(露出部)を残して残余の基端部側が埋設された無底筒状の既存杭2の周囲の地盤1に複数のボーリング孔4を穿設して該既存杭2を引き抜く場合について説明する。   In the present embodiment, a plurality of boring holes 4 are drilled in the ground 1 around the existing bottomless cylindrical pile 2 in which a part of the distal end portion (exposed portion) is left in the ground 1 and the remaining base end side is embedded. The case where it installs and pulls out this existing pile 2 is demonstrated.

本実施例においては、切削用ロッド3の先端から流体(水)を圧縮空気と共にジェット噴射せしめて切削用ロッド3の周囲の地盤1を軟化させながらボーリング孔4を穿設する。この際、既存杭2の外周面に接する地盤1が軟化するように水のジェット噴射範囲及びボーリング孔4の穿設位置を設定している。具体的には、既存杭2の全周位置の地山を軟化せしめ得るように、ボーリング数や地盤1の土質や既存杭2の径や流体の噴射量や噴射強さ等に応じて、噴射範囲及びボーリング孔4の穿設位置(既存杭2との距離)を適宜設定する。   In this embodiment, a boring hole 4 is drilled while softening the ground 1 around the cutting rod 3 by jetting a fluid (water) together with compressed air from the tip of the cutting rod 3. At this time, the water jet injection range and the drilling position of the boring hole 4 are set so that the ground 1 in contact with the outer peripheral surface of the existing pile 2 is softened. Specifically, in order to soften the ground around the existing pile 2 according to the number of bores, the soil quality of the ground 1, the diameter of the existing pile 2, the injection amount of the fluid, the injection strength, etc. The range and the drilling position of the boring hole 4 (distance from the existing pile 2) are set as appropriate.

尚、本実施例においては、上述のように既存杭2の外周面に接する地盤1が軟化するように水を噴射せしめながらボーリング孔4を穿設しているが、既存杭2の外周面に接する地盤1を軟化させずとも、その周囲の地盤1を軟化させることで土圧を解放することが可能であり、従って、既存杭2の外周面に接する地盤1を軟化させないように、前記水により軟化した地盤8と既存杭2の外周面とが接触しないように、流体の噴射範囲及びボーリング孔4の穿設位置を設定しても良い。   In the present embodiment, the boring hole 4 is drilled while spraying water so that the ground 1 in contact with the outer peripheral surface of the existing pile 2 is softened as described above. It is possible to release the earth pressure by softening the surrounding ground 1 without softening the ground 1 in contact therewith, and therefore the water 1 is not so softened that the ground 1 in contact with the outer peripheral surface of the existing pile 2 is softened. The injection range of the fluid and the drilling position of the boring hole 4 may be set so that the ground 8 softened by the above and the outer peripheral surface of the existing pile 2 do not contact each other.

また、本実施例は、砂質土、砂礫土、粘性土若しくはシルト質土等、どのような土質にも対応可能であるが、土質によっては、切削用ロッド3の先端から水若しくは空気のいずれかを噴射するようにしても良い。また、切削用ロッド3としては、先端から基端までが同径であるものを採用しても良いし、先端部(切削部)のみが径大となっているものを採用しても良い。   In addition, the present embodiment can cope with any soil quality such as sandy soil, gravel soil, viscous soil, or silty soil, but depending on the soil quality, either water or air is applied from the tip of the cutting rod 3. You may make it inject. Moreover, as the rod 3 for cutting, what has the same diameter from a front end to a base end may be employ | adopted, and what has a large diameter only a front-end | tip part (cutting part) may be employ | adopted.

また、ボーリング孔4を穿設した後は、このボーリング孔4(及び周囲の軟化した地盤8)に該ボーリング孔4及びボーリング孔4の周囲の軟化した地盤8がしばらく締め固まらないように(軟化・流動化した状態を保持するように)、この締め固まりを抑制(遅延)する増粘材を含む充填材(ベントナイトや泥土に増粘材を加えたもの。遅延材。)を充填する。具体的には、切削用ロッド3は地山に降下導入する際には先端部から水及び空気を噴射させながら導入し、ボーリング孔4穿設後、上昇導出する際には先端部から充填材を吐出させながら導出するように構成されている。尚、増粘材としては、孔壁の崩落を阻止でき且つ環境に悪影響を与え難いものであれば、カルボキシルメチルセルロースや高分子膠質有機物(商品名レスター)等を適宜採用できる。また、この充填材の種類及び充填材の注入量を調整して締め固まり抑制時間を調整できる。   Further, after the boring hole 4 is drilled, the boring hole 4 and the softened ground 8 around the boring hole 4 are not tightened for a while (softening). -Filling with a filler (thickener added to bentonite or mud) containing a thickener that suppresses (delays) this compaction so as to maintain a fluidized state. Specifically, the cutting rod 3 is introduced while jetting water and air from the tip when the descent is introduced into the natural ground, and the filler is inserted from the tip when the boring hole 4 is drilled and led out. It is comprised so that it may derive | lead-out, discharging. As the thickener, carboxymethyl cellulose, a polymeric colloidal organic substance (trade name Lester), or the like can be appropriately employed as long as it can prevent the pore wall from collapsing and hardly adversely affect the environment. Moreover, the compaction suppression time can be adjusted by adjusting the type of filler and the amount of filler injected.

充填材が注入されることで、ボーリング孔4及び軟化した地盤8が急速に締まることが抑制され、例えば複数のボーリング孔4を穿設する必要がある場合など、穿設から引き抜くまでに時間を要する場合であっても、良好に既存杭2を引き抜くことが可能となる。   By injecting the filler, it is possible to prevent the boring holes 4 and the softened ground 8 from being rapidly tightened. For example, when it is necessary to drill a plurality of boring holes 4, it takes time from drilling to pulling out. Even if necessary, the existing pile 2 can be pulled out satisfactorily.

また、内部に土砂が入り込む無底筒状の既存杭2を引き抜く際には、この既存杭2の内周側の地盤1に上記同様にボーリング孔4を穿設し内部の土砂を排除した後、この既存杭2を引き抜くと、既存杭2がより軽量となり抜き易くなる。この際、既存杭2の外側に穿設されるボーリング孔4と同様に、流体を噴射しながら切削用ロッド3により切削しても良いし、流体を噴射せずに切削しても良い。   Moreover, when pulling out the existing bottomless cylindrical pile 2 in which earth and sand enter, after drilling the bore hole 4 in the ground 1 on the inner peripheral side of the existing pile 2 and removing the inner earth and sand When this existing pile 2 is pulled out, the existing pile 2 becomes lighter and becomes easier to pull out. At this time, similarly to the boring hole 4 drilled on the outside of the existing pile 2, the cutting rod 3 may be cut while ejecting the fluid, or the fluid may be cut without being ejected.

本実施例の切削用ロッド3を導入するボーリング装置9は、図1に図示したように切削用ロッド3を回転自在且つ昇降自在に保持する保持部10を有する一般的なものである。尚、図中、符号11は切削用ロッド3の導入出をガイドするガイド部である。また、切削用ロッド3は既存杭2に比し径小であり、流体の噴射により既存杭2より径大な範囲の地盤1を軟化し得るように構成されている。   The boring device 9 for introducing the cutting rod 3 according to the present embodiment is a general one having a holding portion 10 for holding the cutting rod 3 so as to be rotatable and movable up and down as shown in FIG. In the figure, reference numeral 11 denotes a guide portion for guiding the introduction and removal of the cutting rod 3. Moreover, the cutting rod 3 has a smaller diameter than the existing pile 2 and is configured to soften the ground 1 in a larger diameter range than the existing pile 2 by jetting fluid.

また、本実施例のボーリング装置9の保持部10には、降下導入した切削用ロッド3の導入長さが表示される表示部が設けられており、切削用ロッド3を適宜継ぎ足して導入する際、ある程度正確な切削用ロッド3導入長を把握できる。従って、例えば既存杭2の埋設長さが不明である場合、この既存杭2の周囲や内部に上述のようにしてボーリング孔4を穿設することで、流体の吹き上がり具合等を確認して、ある程度既存杭2の埋設長さを把握することが可能となる。   In addition, the holding unit 10 of the boring device 9 of the present embodiment is provided with a display unit for displaying the introduction length of the cutting rod 3 that has been lowered and introduced. It is possible to grasp the introduction length of the cutting rod 3 that is somewhat accurate. Therefore, for example, when the burial length of the existing pile 2 is unknown, the boring hole 4 is drilled around the inside of the existing pile 2 as described above to check the fluid blow-up condition, etc. It becomes possible to grasp the burying length of the existing pile 2 to some extent.

切削用ロッド3には流体を噴射したり充填材を吐出したりするホースが内装され、このホースの基端側には、水及び充填材が夫々仕切られて貯留せしめられるタンク12が送出用のポンプ13を介して連設されると共に、圧縮空気を送出するエアポンプ14が連設されている。図中、符号16は切削用ロッド3に内装されるホースと水若しくは充填材が流通する流通部17と空気が流通する流通部18とを連設する連設部である。   The cutting rod 3 is internally provided with a hose for injecting fluid and discharging a filler, and a tank 12 in which water and filler are partitioned and stored at the base end side of the hose is for delivery. An air pump 14 is provided continuously through the pump 13 and sends compressed air. In the figure, reference numeral 16 denotes a continuous portion that connects a hose built in the cutting rod 3, a flow portion 17 through which water or filler flows and a flow portion 18 through which air flows.

従って、ホースに水及び圧縮空気を送出することで水を円錐状(断面視扇状)にジェット噴射しつつ切削用ロッド3を降下導入することで、ボーリング孔4の周囲(切削用ロッド3の周囲)の地盤1を軟化せしめつつ地盤1にボーリング孔4を形成した後、ホースに充填材を送出して該充填材を吐出しつつ切削用ロッド3を上昇導出することで、ボーリング孔4及び周囲の軟化した地盤8に充填材を注入することが可能となる。尚、タンクはバルブによって水若しくは充填材の切削用ロッド3への送出を切り換えられるように構成しているが、1つのタンクに切削用ロッド3の降下導入時には水のみを貯留し、上昇導出時には充填材のみを貯留するようにしても良い。   Accordingly, by feeding water and compressed air to the hose and jetting water in a conical shape (fan shape in cross section), the cutting rod 3 is lowered and introduced, so that the surroundings of the boring hole 4 (the surroundings of the cutting rod 3). ) While softening the ground 1, the boring hole 4 is formed in the ground 1, and then the cutting rod 3 is lifted and led out while feeding the filler to the hose and discharging the filler. It becomes possible to inject the filler into the softened ground 8. The tank is configured so that the delivery of water or filler to the cutting rod 3 can be switched by a valve, but only water is stored in one tank when the cutting rod 3 is lowered, and when the rise is derived. Only the filler may be stored.

本実施例においては、具体的には以下の手順で既存杭2の引き抜きを行う。   In the present embodiment, specifically, the existing pile 2 is pulled out by the following procedure.

既存杭2の上方にボーリング装置9を設置し、このボーリング装置9により切削用ロッド3を回転させつつ地盤1に降下導入して、既存杭2の外周面に接触する地盤1を軟化し得るように所定円形状範囲に水をジェット噴射しつつ、この既存杭2の近傍位置に既存杭2の軸方向に沿ってボーリング孔4を穿設する。   A boring device 9 is installed above the existing pile 2, and the ground rod 1 that is in contact with the outer peripheral surface of the existing pile 2 can be softened by introducing the descent into the ground 1 while rotating the cutting rod 3 by the boring device 9. In addition, the water is jetted into a predetermined circular range, and a boring hole 4 is drilled in the vicinity of the existing pile 2 along the axial direction of the existing pile 2.

続いて、所定深さ位置(既存杭2の下端位置と略同じ位置)まで切削用ロッド3を導入して既存杭2の埋設長さと略同じ深さのボーリング孔4を穿設した後、切削用ロッド3を引き抜きながら軟化した地盤8が締め固まり難くなるように該軟化した地盤8に充填材を充填する。   Subsequently, the cutting rod 3 is introduced to a predetermined depth position (substantially the same position as the lower end position of the existing pile 2), and a boring hole 4 having a depth substantially the same as the embedded length of the existing pile 2 is drilled, and then cutting is performed. The softened ground 8 is filled with a filler so that the softened ground 8 is hard to be compacted while the rod 3 is pulled out.

続いて、同様の手順で同一の切削用ロッド3を用いて既存杭2を挟んだ対向位置にもボーリング孔4を形成する。具体的には、図2に図示したように、既存杭2を挟んで180度間隔で対向する二ヶ所に切削用ロッド3により円形のボーリング孔4を穿設することで、既存杭2と周囲の地盤1とを縁切りして(既存杭2の周面摩擦力をカットして)既存杭2を締め付ける地盤1の土圧を解放(軽減)する。この際、軟化した地盤8の端部(水の噴射外縁部)が互いにラップするように水の噴射度合い及びボーリング位置を設定すると良い。   Then, the boring hole 4 is formed in the opposing position which pinched the existing pile 2 using the same cutting rod 3 in the same procedure. Specifically, as shown in FIG. 2, a circular boring hole 4 is drilled with two cutting rods 3 at two positions facing each other at an interval of 180 degrees across the existing pile 2, so that the existing pile 2 and the surrounding The ground pressure of the ground 1 that clamps the existing pile 2 is released (reduced) by cutting off the ground 1 (cutting the peripheral frictional force of the existing pile 2). At this time, it is preferable to set the water injection degree and the boring position so that the end portions (water injection outer edge portions) of the softened ground 8 overlap each other.

尚、ボーリング孔4を穿設する際には、1つ若しくは2つめで既存杭2が動くなどして十分周囲からの土圧を軽減できたと認められた場合には、後述する既存杭2の引き上げ作業を開始し、未だ土圧の軽減が不十分であると認められた場合には、他の位置にも同様にしてボーリング孔4を形成する。即ち、例えば、対抗する位置の2点にボーリング孔4を穿設するのみでは既存杭2が引き抜き難い場合には、例えば既存杭2の周囲に90度間隔で4点に上記同様にボーリング孔4を穿設したり、更には図3に図示したように既存杭2の全周をカバーするように60度間隔で6点に上記同様にボーリング孔4を穿設する。従って、本実施例は、現場で状況に応じて容易にボーリング孔4の数を可変できるため、非常に作業性に秀れる。即ち、本実施例は、ボーリング孔4を穿設しながら既存杭2の引き抜き易さを確認しつつ、現場で様子を見ながらボーリング孔4を追加穿設したり予定穿設数より少なくしたりして適宜調整できるため、極めて扱い易い技術となる。   In addition, when drilling the boring hole 4, if it is recognized that the earth pressure from the surroundings can be sufficiently reduced by moving the existing pile 2 by the first or second, When the lifting work is started and it is recognized that the earth pressure is still not sufficiently reduced, the bore holes 4 are formed in the other positions in the same manner. That is, for example, when it is difficult to pull out the existing pile 2 only by drilling the boring holes 4 at two points at the opposing positions, for example, the boring holes 4 are formed at four points around the existing pile 2 at intervals of 90 degrees. Further, as shown in FIG. 3, bore holes 4 are similarly drilled at six points at intervals of 60 degrees so as to cover the entire circumference of the existing pile 2. Therefore, in this embodiment, the number of the bore holes 4 can be easily changed according to the situation at the site, so that the workability is very excellent. That is, in this embodiment, while confirming the ease of pulling out the existing pile 2 while drilling the boring holes 4, additional drilling holes 4 can be drilled while watching the situation on the site or less than the planned number of drilling Therefore, it can be adjusted as appropriate, so that the technique is extremely easy to handle.

続いて、既存杭2の内側にも同一の切削用ロッド3を用いて同様にしてボーリング孔4を穿設することで、この既存杭2の内側の地盤1にもボーリング孔4を穿設する。尚、既存杭2の外側、内側にボーリング孔4を穿設する際の順序は、どちらを先としても良い。また、一つの同一の切削用ロッド3を用いて複数のボーリング孔4を順次穿設せず、複数の切削用ロッド3を用いて複数のボーリング孔4を同時に穿設しても良い。   Subsequently, a boring hole 4 is also drilled in the ground 1 inside the existing pile 2 by drilling a boring hole 4 in the same way using the same cutting rod 3 inside the existing pile 2. . In addition, the order at the time of drilling the boring hole 4 in the outer side and the inner side of the existing pile 2 may be first. Alternatively, the plurality of boring holes 4 may be simultaneously drilled using the plurality of cutting rods 3 without sequentially drilling the plurality of boring holes 4 using the same cutting rod 3.

続いて、既存杭2の露出する先端部(露出部)に下向きのジャッキ受け面5を有するジグ6をボルト等で取り付け固定すると共に、このジャッキ受け面5と対向状態に押し上げジャッキ7を配設し、ジャッキ受け面5を押し上げジャッキ7により押し上げることで既存杭2を地盤1から少しずつ引き上げて引き抜き、露出部分がある程度の長さに達したらジグ6を設ける部分を残して余剰部2’を適宜切断除去しながら、既存杭2を引き抜く。図中、符号15はジャッキ設置足場である。尚、既存杭2を引き抜く際、上空に高架線がない場合などには、クレーン、パイラーや三点式杭打ち機などを用いて引き抜くなど他の手段を採用しても良い。   Subsequently, a jig 6 having a downward jack receiving surface 5 is attached and fixed to the exposed end portion (exposed portion) of the existing pile 2 with a bolt or the like, and a push-up jack 7 is disposed opposite to the jack receiving surface 5. Then, by pushing up the jack receiving surface 5 and pushing it up by the jack 7, the existing pile 2 is pulled up and pulled out little by little from the ground 1, and when the exposed part reaches a certain length, the surplus part 2 ′ is left leaving the part where the jig 6 is provided. The existing pile 2 is pulled out while appropriately cutting and removing. In the figure, reference numeral 15 denotes a jack installation scaffold. When the existing pile 2 is pulled out, if there is no overhead wire in the sky, other means such as pulling out using a crane, a pillar, a three-point pile driving machine, etc. may be adopted.

続いて、既存杭2の引き抜きにより形成された空隙に土砂を埋め戻して作業終了となる。尚、埋め戻しに限らず、モルタル等の充填材を充填しても良い。   Subsequently, earth and sand are backfilled in the gap formed by pulling out the existing pile 2, and the operation is completed. In addition, you may fill not only with a backfill but fillers, such as mortar.

また、本実施例においては、既存杭2が径大であっても、切削用ロッド3として直径数cm〜10cm程度の径小・軽量のもので十分対応でき(ボーリング孔数や水の噴射量等を現場で調整して縁切り度合いを適宜調整でき)、従来のように既存杭2より径大な径大管を埋設する必要なく、一般的なボーリング装置によりボーリング孔4を穿設可能であり、極めてコスト安に既存杭2を引き抜くことが可能となる。   Further, in this embodiment, even if the existing pile 2 has a large diameter, a cutting rod 3 having a small diameter and a light weight of about several centimeters to 10 centimeters can sufficiently respond (the number of bore holes and the amount of water injection). It is possible to adjust the degree of edge cutting as needed by adjusting on-site, etc.), and it is not necessary to embed a large-diameter pipe larger than the existing pile 2 as in the past, and the boring hole 4 can be drilled with a general boring device. The existing pile 2 can be pulled out at a very low cost.

尚、本実施例においては、既存杭2として上述のように無底筒体の場合について説明しているが、例えば有底筒体や棒状体等、他の構成の既存杭2でも(既存杭2の内側にボーリング孔4を形成するか否かを除き)同様にして引き抜くことができる。   In addition, in the present Example, although the case of a bottomless cylindrical body is demonstrated as above-mentioned as the existing pile 2, for example, the existing pile 2 of other structures, such as a bottomed cylindrical body and a rod-shaped body, is also known (existing pile). 2) (except for whether or not the boring hole 4 is formed inside 2).

本実施例は上述のようにするから、既存杭2の周囲の地盤1にボーリング孔4を穿設することで、このボーリング孔4により既存杭2と周囲の地盤1とを縁切りして(既存杭2の周面摩擦力をカットして)既存杭2を締め付ける地盤1の土圧を解放(軽減)することができ、よって、既存杭2を良好に引き抜くことが可能となる。   Since the present embodiment is as described above, by drilling the borehole 4 in the ground 1 around the existing pile 2, the existing pile 2 and the surrounding ground 1 are cut off by this borehole 4 (existing It is possible to release (reduce) the earth pressure of the ground 1 that tightens the existing pile 2 by cutting the peripheral frictional force of the pile 2, and thus the existing pile 2 can be pulled out satisfactorily.

また、切削用ロッド3によりボーリング孔4を穿設することで縁切りを行うため、従来のように既存杭2を囲う径大な管体を打ち込む必要がなく、径大で重い管体を打ち込む大型の打ち込み装置等は不要となり、径小な切削用ロッド3の回転降下導入が可能な一般的なボーリング装置を用いるだけで済み、極めてコスト性に秀れる。   Further, since the edge cutting is performed by drilling the boring hole 4 with the cutting rod 3, it is not necessary to drive a large tube surrounding the existing pile 2 as in the prior art, and a large tube for driving a large and heavy tube. No need for a driving device or the like, and it is only necessary to use a general boring device capable of introducing a rotational drop of the small-diameter cutting rod 3, which is extremely cost-effective.

また、切削用ロッド3は1mおき等、短い間隔で継ぎ足して導入長さを調整できるため、上方に広い作業空間を確保する必要がなく、よって、上空に高架線が存在する場合であっても良好に施工可能となる。   Moreover, since the cutting rod 3 can be added at a short interval, such as every 1 m, and the introduction length can be adjusted, it is not necessary to secure a wide working space above, so even if there is an overhead wire in the sky Good construction is possible.

また、切削用ロッド3から水等の流体を噴射して切削用ロッド3の周囲の地盤1を軟化(流動化)せしめながらボーリング孔4を穿設することで、より効率的に縁切りを行うことができ、一層効率的に土圧を軽減できる。   Further, by cutting the boring hole 4 while jetting a fluid such as water from the cutting rod 3 and softening (fluidizing) the ground 1 around the cutting rod 3, the edging can be performed more efficiently. Can reduce the earth pressure more efficiently.

また、切削用ロッド3をボーリング孔4から引き抜く際、軟化した地盤8の締め固まりを抑制する充填材を充填することで、切削用ロッド3をボーリング孔4から引き抜いた後も該ボーリング孔が締め固まることを阻止でき、複数のボーリング孔4を穿設する場合でも良好に土圧を軽減できる。   Further, when the cutting rod 3 is pulled out from the boring hole 4, the boring hole is tightened even after the cutting rod 3 is pulled out from the boring hole 4 by filling with a filler that suppresses the compaction of the softened ground 8. Hardening can be prevented, and even when a plurality of boring holes 4 are formed, the earth pressure can be reduced well.

更に、ボーリング孔4を既存杭2を囲うように該既存杭2から離れた位置に夫々独立に複数穿設することで、一層良好に土圧を軽減できる。また、この際、ボーリング孔4を夫々連設させず夫々独立に穿設するため、既存杭2の全周を囲うような環状の縁切り孔を形成する場合に比し、それだけ縁切り作業が簡易となる。   Furthermore, the earth pressure can be further reduced by perforating a plurality of boring holes 4 at positions apart from the existing pile 2 so as to surround the existing pile 2. Further, at this time, since the boring holes 4 are formed independently without being continuously provided, the edge cutting operation is simpler than that in the case of forming an annular edge cutting hole surrounding the entire circumference of the existing pile 2. Become.

また、ボーリング孔4を穿設する際には、このボーリング孔4同士が接触するように穿設する必要はなく、間隔をおいて設けることで対応できるため、例えば既存杭2の全周に孔を形成する方法に比しても極めて容易に既存杭2にかかる土圧を軽減して引き抜きを容易化できることになる。   In addition, when drilling the boring holes 4, it is not necessary to drill the boring holes 4 so that they are in contact with each other. Even if compared with the method of forming, the earth pressure applied to the existing pile 2 can be reduced very easily and the drawing can be facilitated.

よって、本実施例は、従来のように既存杭2より径大な管体を用いる必要なく、また、既存杭2の全周を囲うような縁切り孔を形成する必要もなく、簡易な設備でそれだけコスト安に既存杭2の引き抜きを可能とする極めて実用性に秀れた既存杭の引き抜き方法となる。   Therefore, the present embodiment does not require the use of a pipe having a diameter larger than that of the existing pile 2 as in the prior art, and does not require the formation of edge cutting holes that surround the entire circumference of the existing pile 2. Therefore, the existing pile 2 can be pulled out at a low cost, and the existing pile can be pulled out with excellent practicality.

本実施例の概略説明図である。It is a schematic explanatory drawing of a present Example. 本実施例の概略説明平面図である。It is a schematic explanatory plan view of a present Example. 別例の概略説明平明図である。It is a schematic explanatory plan view of another example. 本実施例の概略説明側面図である。It is a schematic explanatory side view of a present Example. 本実施例の概略説明側面図である。It is a schematic explanatory side view of a present Example.

符号の説明Explanation of symbols

1 地盤
2 既存杭
3 切削用ロッド
4 ボーリング孔
5 ジャッキ受け面
6 ジグ
7 ジャッキ
8 軟化した地盤
DESCRIPTION OF SYMBOLS 1 Ground 2 Existing pile 3 Cutting rod 4 Boring hole 5 Jack receiving surface 6 Jig 7 Jack 8 Softened ground

Claims (8)

地盤に一部若しくは全部が埋設された既存杭の引き抜き方法であって、前記既存杭の周囲の地盤に、切削用ロッドから流体を噴出させて該切削用ロッドの周囲の地盤を軟化せしめながら該切削用ロッドにより一若しくは複数のボーリング孔を該既存杭の軸方向に沿って穿設した後、前記切削用ロッドを前記ボーリング孔から引き抜きながら該切削用ロッドから該切削用ロッドの周囲の軟化した地盤の締め固まりを抑制する充填材を充填し前記既存杭が地盤から受ける土圧を軽減させ、この土圧が軽減した状態で前記既存杭を前記地盤から引き抜くことを特徴とする既存杭の引き抜き方法。   A method for extracting an existing pile partially or wholly embedded in the ground, wherein the ground around the existing pile is ejected with fluid from the cutting rod to soften the ground around the cutting rod. After drilling one or more boring holes along the axial direction of the existing pile with a cutting rod, the cutting rod is pulled out from the boring hole and softened around the cutting rod from the cutting rod. Pulling out an existing pile filled with a filler that suppresses compaction of the ground, reducing the earth pressure that the existing pile receives from the ground, and pulling out the existing pile from the ground in a state in which the earth pressure is reduced Method. 請求項1記載の既存杭の引き抜き方法において、前記既存杭の外周面に接する地盤が軟化するように前記切削用ロッドを前記地盤に導入することを特徴とする既存杭の引き抜き方法。   2. The method for extracting an existing pile according to claim 1, wherein the cutting rod is introduced into the ground so that the ground in contact with the outer peripheral surface of the existing pile is softened. 請求項1,2いずれか1項に記載の既存杭の引き抜き方法において、前記充填材の種類若しくは量を調整して前記軟化した地盤の締め固まり抑制時間を設定することを特徴とする既存杭の引き抜き方法。   In the extraction method of the existing pile of any one of Claims 1 and 2, the kind or amount of the filler is adjusted, and the compaction suppression time of the softened ground is set. Drawing method. 請求項3記載の既存杭の引き抜き方法において、前記充填材には増粘材が含まれていることを特徴とする既存杭の引き抜き方法。   The extraction method of the existing pile of Claim 3 WHEREIN: The thickener is contained in the said filler, The extraction method of the existing pile characterized by the above-mentioned. 請求項1〜4いずれか1項に記載の既存杭の引き抜き方法において、前記既存杭を囲うように前記ボーリング孔を該既存杭から離れた位置に夫々独立に複数穿設することを特徴とする既存杭の引き抜き方法。   In the extraction method of the existing pile according to any one of claims 1 to 4, a plurality of the boring holes are independently drilled at positions apart from the existing pile so as to surround the existing pile. Pulling out existing piles. 請求項1〜5いずれか1項に記載の既存杭の引き抜き方法において、前記既存杭は無底筒状であり、この既存杭を引き抜く際、この既存杭の内周側の前記地盤に前記ボーリング孔を穿設することを特徴とする既存杭の引き抜き方法。   In the extraction method of the existing pile of any one of Claims 1-5, the said existing pile is a bottomless cylindrical shape, When pulling out this existing pile, the said boring is carried out to the said ground on the inner peripheral side of this existing pile. A method of pulling out an existing pile characterized by drilling a hole. 請求項1〜6いずれか1項に記載の既存杭の引き抜き方法において、複数の前記ボーリング孔を穿設する際、同一の前記切削用ロッドを用いて前記各ボーリング孔を順次穿設することを特徴とする既存杭の引き抜き方法。   In the extraction method of the existing pile of any one of Claims 1-6, when drilling a plurality of the boring holes, the boring holes are sequentially drilled using the same cutting rod. A method of pulling out an existing pile as a feature. 請求項1〜7いずれか1項に記載の既存杭の引き抜き方法において、前記既存杭の前記地盤から露出する露出部に下向きのジャッキ受け面を有するジグを取り付け固定すると共に、このジャッキ受け面と対向状態に押し上げジャッキを配設し、この押し上げジャッキにより前記ジグのジャッキ受け面を押し上げることで前記既存杭を引き上げ引き抜くことを特徴とする既存杭の引き抜き方法。   In the extraction method of the existing pile of any one of Claims 1-7, while attaching and fixing the jig which has a downward jack receiving surface to the exposed part exposed from the said ground of the said existing pile, this jack receiving surface and A method for pulling out an existing pile, wherein a push-up jack is arranged in an opposing state, and the jack is lifted and pulled out by pushing up the jack receiving surface of the jig.
JP2008142690A 2008-05-30 2008-05-30 Pulling out existing piles Active JP5100512B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008142690A JP5100512B2 (en) 2008-05-30 2008-05-30 Pulling out existing piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008142690A JP5100512B2 (en) 2008-05-30 2008-05-30 Pulling out existing piles

Publications (2)

Publication Number Publication Date
JP2009287326A true JP2009287326A (en) 2009-12-10
JP5100512B2 JP5100512B2 (en) 2012-12-19

Family

ID=41456803

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008142690A Active JP5100512B2 (en) 2008-05-30 2008-05-30 Pulling out existing piles

Country Status (1)

Country Link
JP (1) JP5100512B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493455A (en) * 2011-12-20 2012-06-13 中铁第四勘察设计院集团有限公司 Method for removing foundation piles
CN103485344A (en) * 2013-09-17 2014-01-01 常熟理工学院 Method for extracting construction engineering pile foundation
CN110984624A (en) * 2019-12-20 2020-04-10 中建一局集团建设发展有限公司 Ultralong vertical underground steel pipe pulling-out system and construction method thereof
JP2020193534A (en) * 2019-05-30 2020-12-03 株式会社設計室ソイル Removal method of steel pipe pile
JP7073326B2 (en) 2019-12-20 2022-05-23 大地 山下 How to remove buried objects

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06116955A (en) * 1992-10-09 1994-04-26 Daiken:Kk Pulling-out method for existing pile
JP2000352053A (en) * 1999-06-09 2000-12-19 Hazama Gumi Ltd Existing pile dismantling construction method
JP2004218378A (en) * 2003-01-17 2004-08-05 Sato Kogyo Co Ltd Removing method for existing pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06116955A (en) * 1992-10-09 1994-04-26 Daiken:Kk Pulling-out method for existing pile
JP2000352053A (en) * 1999-06-09 2000-12-19 Hazama Gumi Ltd Existing pile dismantling construction method
JP2004218378A (en) * 2003-01-17 2004-08-05 Sato Kogyo Co Ltd Removing method for existing pile

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493455A (en) * 2011-12-20 2012-06-13 中铁第四勘察设计院集团有限公司 Method for removing foundation piles
CN103485344A (en) * 2013-09-17 2014-01-01 常熟理工学院 Method for extracting construction engineering pile foundation
JP2020193534A (en) * 2019-05-30 2020-12-03 株式会社設計室ソイル Removal method of steel pipe pile
CN110984624A (en) * 2019-12-20 2020-04-10 中建一局集团建设发展有限公司 Ultralong vertical underground steel pipe pulling-out system and construction method thereof
JP7073326B2 (en) 2019-12-20 2022-05-23 大地 山下 How to remove buried objects
CN110984624B (en) * 2019-12-20 2024-04-05 中建一局集团建设发展有限公司 Ultra-long vertical underground steel pipe pulling-out system and construction method thereof

Also Published As

Publication number Publication date
JP5100512B2 (en) 2012-12-19

Similar Documents

Publication Publication Date Title
JP4282022B2 (en) Drain pipe burial method and structures, etc. to prevent tilting, sinking or floating
US6471445B2 (en) Rotary displacement piling equipment
JP5100512B2 (en) Pulling out existing piles
JP5718306B2 (en) Underground consolidated body construction method and underground solid body creation device for creating a solid body using the method
JP2015229860A (en) Method to control groundwater movement in excavated pit, grout filling method, and water storage means
JP5698316B2 (en) Construction method of foundation pile
JP2009263966A (en) Removal method of existing pile
JP5717148B2 (en) Underground consolidated body construction method
JP3940764B2 (en) Drain pipe method and ground drilling device
JP2019039140A (en) Method for constructing ground improvement body and method for constructing pile
JP5305573B2 (en) Underground solid body forming device and underground solid body forming method
JP6807285B2 (en) Construction method of ground improvement body and casing pipe
JP3363099B2 (en) Supporting ground improvement method for existing structures
JP2012021390A (en) Method of constructing steel pipe pile foundation, and head of drilling insertion apparatus
JP2005120622A (en) Construction method of underground structure
JP2009041301A (en) Curved boring method
JP2006016756A (en) Extraction method for existing pile
JP6872940B2 (en) High pressure injection device
KR101368999B1 (en) Pipe propulsion apparatus enabling reinforcement of laying hole of pipe and pipe constructing method using this
JP3905201B2 (en) Drilling rig
JP4515307B2 (en) Ground improvement method
JP5755298B2 (en) Chemical injection method
JPH0224419A (en) Simultaneous backfilling with pile drawing, and pile drawer
JP7191327B2 (en) How to remove steel pipe piles
JP3973401B2 (en) Ground compaction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100415

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120330

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120521

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120720

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120830

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120925

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151005

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5100512

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250