JP2018197486A - Construction method for forming underground structure, and underground structure completed by the same - Google Patents

Construction method for forming underground structure, and underground structure completed by the same Download PDF

Info

Publication number
JP2018197486A
JP2018197486A JP2017121874A JP2017121874A JP2018197486A JP 2018197486 A JP2018197486 A JP 2018197486A JP 2017121874 A JP2017121874 A JP 2017121874A JP 2017121874 A JP2017121874 A JP 2017121874A JP 2018197486 A JP2018197486 A JP 2018197486A
Authority
JP
Japan
Prior art keywords
underground
forming
construction method
wall structure
permanent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017121874A
Other languages
Japanese (ja)
Other versions
JP6514739B2 (en
Inventor
シェン ツァオ チェン
Chang-Sheng Tsao
シェン ツァオ チェン
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RUNHORN PRETECH ENG CO Ltd
RUNHORN PRETECH ENGINEERING CO Ltd
Original Assignee
RUNHORN PRETECH ENG CO Ltd
RUNHORN PRETECH ENGINEERING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by RUNHORN PRETECH ENG CO Ltd, RUNHORN PRETECH ENGINEERING CO Ltd filed Critical RUNHORN PRETECH ENG CO Ltd
Publication of JP2018197486A publication Critical patent/JP2018197486A/en
Application granted granted Critical
Publication of JP6514739B2 publication Critical patent/JP6514739B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To provide a construction method for forming an underground structure, and an underground structure completed by the method.SOLUTION: The construction method comprises a step to form a first wall structure including a plurality of first walls that are parallel to each other and define a construction region, a step to form a first underground sub-structure by providing a plurality of first permanent underground beams for supporting the plurality of first walls between the insides of the plurality of first walls, a step to excavate earth within the construction region up to a first depth, and a step to press the first underground sub-structure into a ground up to substantially the first depth using a tensile material with a guide function.SELECTED DRAWING: Figure 2A

Description

本発明は、建築施工方法に関し、特に、地下構造の建築施工方法に関する。 The present invention relates to a building construction method, and more particularly to a building construction method for an underground structure.

建築物を建築する場合、先ずは敷地を掘削して地下構造を形成する必要がある。敷地を掘削する前に、通常、先ず敷地の掘削場所の周囲に擁壁構造を建てる必要がある。連続壁は、剛性と水密性が高く、且つ掘削可能な深さが大きい等の利点を有するので、近年、敷地掘削の擁壁工法に広く応用されている。一般的には、連続壁の製作手順として、先ず、敷地を掘削する予定の施工領域の周囲の地面に案内溝を掘り、そして、グラブ掘削機によって溝を掘り、溝を形成した後に、鉄筋籠を溝に設け、そして、セメント注入を行って連続壁の施工を完成する。 When building a building, it is necessary to first excavate the site to form an underground structure. Before excavating a site, it is usually necessary to first build a retaining wall structure around the site excavation site. Since the continuous wall has advantages such as high rigidity and water tightness and a large excavation depth, it has been widely applied to the retaining wall construction method for site excavation in recent years. In general, as a procedure for producing a continuous wall, first, a guide groove is dug in the ground around the construction area where the site is to be excavated, and then a groove is dug by a grab excavator to form the groove. Is installed in the groove and cement is poured to complete the construction of the continuous wall.

図1を参照し、従来、地下構造9を形成する施工工法では、先ず、地面11から土砂を掘削することによって、連続壁91を形成するための溝を形成し、そして、溝内にセメントを注入して連続壁91を形成する。連続壁91の形成に必要な溝がかなり深いため、溝を掘削すると同時に溝を支持する仮支持体(例えば、鋼板、仮支持梁及び柱)を設ける必要がある。しかし、従来の施工工法では、非常に手間が掛かるだけでなく、溝の両側の土砂が崩れる虞もある。 Referring to FIG. 1, in the conventional construction method for forming an underground structure 9, first, a groove for forming a continuous wall 91 is formed by excavating earth and sand from the ground 11, and cement is then placed in the groove. The continuous wall 91 is formed by pouring. Since the groove required for forming the continuous wall 91 is considerably deep, it is necessary to provide a temporary support body (for example, a steel plate, a temporary support beam, and a column) that supports the groove while excavating the groove. However, in the conventional construction method, not only is it time-consuming, but there is a possibility that the earth and sand on both sides of the groove may collapse.

図1に示すように、連続壁91を形成した後に、施工者は、建設領域10内において、地下構造9に必要な深さになるまで地面から土砂を下へ掘削する。この掘削ステップにおいて、地下構造9に必要な深さになるまで、何回も繰返して土砂を一層ずつ掘削し、且つ、土砂を一層掘削するたびに仮支持体(例えば、鋼板、仮支持梁及び柱)を設ける必要がある。この掘削及び仮支持体を設けるステップも、非常に手間が掛かり、建設領域10の両側の土砂が崩れる虞もある。上記ステップが完成するまでに、施工者は土砂の掘削によって形成される空間内において下から上へ地下サブ構造93を順に一層ずつ構築することによって地下構造9を形成することができない。 As shown in FIG. 1, after forming the continuous wall 91, the builder excavates the earth and sand from the ground down to the depth required for the underground structure 9 in the construction area 10. In this excavation step, the earth and sand are excavated one layer at a time until the depth required for the underground structure 9 is reached, and a temporary support (e.g., steel plate, temporary support beam and It is necessary to provide pillars. The step of providing the excavation and the temporary support is also very laborious and the earth and sand on both sides of the construction area 10 may be destroyed. By the time the above steps are completed, the contractor cannot form the underground structure 9 by building the underground substructure 93 one by one from the bottom up in the space formed by the excavation of earth and sand.

上記をまとめると、上記した従来の地下構造9の施工工法では、施工者は、連続壁91の施工が完成するまで待ってから、施工領域の内側を掘削し、地下サブ構造93を一層ずつ建築することによって地下構造9を形成しなければならないので、コストが高く、工期が長い欠点がある。 In summary, in the conventional construction method of the underground structure 9 described above, the builder waits until the construction of the continuous wall 91 is completed, and then excavates the inside of the construction area to build the underground substructure 93 one by one. By doing so, the underground structure 9 must be formed, and therefore there are disadvantages that the cost is high and the construction period is long.

本発明の一実施例は、地下構造を形成する施工方法を提供することにある。前記施工方法は、互いに連なって建設領域を画定する複数の第1壁を含む第1壁構造を形成するステップと、前記複数の第1壁の内側の間に、前記複数の第1壁を支持するための複数の第1永久地中梁を設けることによって、第1地下サブ構造を形成するステップと、前記建設領域内の土砂を第1深さまで掘削するステップと、及び前記第1地下サブ構造を、略前記第1深さまで地面から押し込むステップとを備える。 An embodiment of the present invention is to provide a construction method for forming an underground structure. The construction method supports the plurality of first walls between a step of forming a first wall structure including a plurality of first walls that are connected to each other to define a construction area, and the inside of the plurality of first walls. Providing a plurality of first permanent underground beams to form a first subsurface substructure, excavating earth and sand in the construction area to a first depth, and the first subsurface substructure Pushing from the ground to approximately the first depth.

本発明の他の一実施例は、上記施工方法によって形成される地下構造を提供することにある。 Another embodiment of the present invention is to provide an underground structure formed by the above construction method.

図1は従来の地下構造の断面模式図である。FIG. 1 is a schematic cross-sectional view of a conventional underground structure. 本発明の施工方法の一実施例のステップのフローチャートである。It is a flowchart of the step of one Example of the construction method of this invention. 図2AにおけるステップS2の詳細ステップのフローチャートである。It is a flowchart of the detailed step of step S2 in FIG. 2A. 図2AにおけるステップS3の詳細ステップのフローチャートである。It is a flowchart of the detailed step of step S3 in FIG. 2A. 図2AにおけるステップS7の詳細ステップのフローチャートである。It is a flowchart of the detailed step of step S7 in FIG. 2A. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method. 本発明施工方法の一実施例の各ステップに基づいて形成される構造の模式図である。It is a schematic diagram of the structure formed based on each step of one Example of this invention construction method.

図2A〜2D及び図3A〜3Lを参照する。本発明の地下構造1を形成する施工方法の一実施例は、主に、地面11に複数の互いに連なる案内溝12を形成するステップ(ステップS1、詳細が図3Aに示される)と、案内部材16を設けるステップ(ステップS2、詳細が図3B〜3Eに示される)と、互いに連なって建設領域10を画定する複数の第1壁を含む第1壁構造32を形成するステップ(ステップS3、図3F〜3H参照)と、複数の第1壁の内側の間に、複数の第1壁を支持するための複数の第1永久地中梁36を設けることによって、第1地下サブ構造3を形成するステップ(ステップS4、図3I参照)と、建設領域10内の土砂を第1深さH1まで掘削し、複数の第1永久柱43を形成するステップ(ステップS5、図3I参照)と、第1地下サブ構造3を、略第1深さH1になるまで地面11から押し込むステップ(ステップS6、図3I参照)とを備える。引き続き、多層の地下構造1を形成するために、本発明の地下構造1を形成する施工方法の他の一実施例は、上記ステップの実施後に、第2壁構造40を形成するステップ(ステップS7、図3J〜3K参照)と、第2永久地中梁42を設ける(図3Lp)ことによって、第2地下サブ構造4を形成し(図3L参照)、第1永久地中梁36と第2永久地中梁42との間に第2永久柱45を形成するステップ(ステップS8、図3L参照)と、建設領域10内の土砂を第2深さH2まで掘削するステップ(ステップS9、図3L参照)と、第1地下サブ構造3、第2地下サブ構造4、第1永久柱43、及び第2永久柱45を、第2深さH2まで地面11から押し込むステップ(ステップS10)とをさらに備える。以下に、施工手順に従って、上記他の一実施例のステップの詳細を説明する。 Please refer to FIGS. 2A to 2D and FIGS. 3A to 3L. One embodiment of the construction method for forming the underground structure 1 of the present invention is mainly composed of a step (step S1, details are shown in FIG. 3A) of forming a plurality of continuous guide grooves 12 on the ground 11, and a guide member. 16 (step S2, details are shown in FIGS. 3B-3E) and forming a first wall structure 32 that includes a plurality of first walls that are connected to each other to define the construction area 10 (step S3, FIG. 3F to 3H) and a plurality of first permanent underground beams 36 for supporting the plurality of first walls are formed between the inside of the plurality of first walls, thereby forming the first underground substructure 3 Step (see step S4, FIG. 3I), excavating the earth and sand in the construction area 10 to the first depth H1, and forming a plurality of first permanent pillars 43 (see step S5, FIG. 3I), 1 Sub-structure 3 is abbreviated Step pushing from the ground 11 to a depth of one H1 (step S6, see FIG. 3I) and a. Subsequently, in order to form the multi-layered underground structure 1, another embodiment of the construction method for forming the underground structure 1 of the present invention is the step of forming the second wall structure 40 after the above steps (step S7). 3J to 3K) and the second permanent underground beam 42 (see FIG. 3Lp) to form the second underground substructure 4 (see FIG. 3L), the first permanent underground beam 36 and the second A step of forming a second permanent column 45 between the permanent underground beam 42 (step S8, see FIG. 3L) and a step of excavating the earth and sand in the construction area 10 to the second depth H2 (step S9, FIG. 3L). And a step of pushing the first underground substructure 3, the second underground substructure 4, the first permanent pillar 43, and the second permanent pillar 45 from the ground 11 to the second depth H2 (step S10). Prepare. Below, the detail of the step of said another one Example is demonstrated according to a construction procedure.

図3Aに示すように、上記ステップS1は、建設領域10内の地面11に複数の互いに連なる案内溝12を形成する(例えば、深さ略1メートルの案内溝12)ことを含む。案内溝12は、建設領域10の外周縁に形成されることが好ましく、例えば、掘削機によって、建設領域10の外周縁の地面11に、案内溝12を掘る。 As shown in FIG. 3A, step S1 includes forming a plurality of guide grooves 12 connected to the ground surface 11 in the construction area 10 (for example, guide grooves 12 having a depth of about 1 meter). The guide groove 12 is preferably formed on the outer peripheral edge of the construction area 10. For example, the guide groove 12 is dug in the ground 11 on the outer peripheral edge of the construction area 10 by an excavator.

図2Bは、案内部材16を設けるステップS2を示す詳細ステップS21、S22、S23及びS24である。図3Bに示すように、ステップS21は、地面11から下へ延伸し、所定の深さDを有する複数の穴14を形成することを含む。穴14は、案内溝12において当該所定の深さDまで下へ延伸している。穴14は、例えば、削孔機によって案内溝12内において垂直で下向きにドリルすることによって形成されることができる。所定の深さDは、実際の建築設計の要求に応じて決められる。特定の実施例において、所定の深さDは、地面11から約24メートルであるが、これに限定されない。 FIG. 2B shows detailed steps S21, S22, S23 and S24 showing step S2 for providing the guide member 16. As shown in FIG. 3B, step S21 includes forming a plurality of holes 14 extending downward from the ground 11 and having a predetermined depth D. The hole 14 extends downward to the predetermined depth D in the guide groove 12. The hole 14 can be formed, for example, by drilling vertically downward in the guide groove 12 with a drilling machine. The predetermined depth D is determined in accordance with actual architectural design requirements. In a particular embodiment, the predetermined depth D is about 24 meters from the ground 11 but is not limited thereto.

ステップS22において、複数の穴14内に、それぞれ細長く可撓性を有する複数の案内部材16を設ける。図3Cに示すように、複数の案内部材16は、所定の深さDまで延伸するように設けられることによって、図3Iに示す第1地下サブ構造3を、地面11に押し込むように案内する。 In step S22, a plurality of elongated and flexible guide members 16 are provided in the plurality of holes 14, respectively. As shown in FIG. 3C, the plurality of guide members 16 are provided so as to extend to a predetermined depth D, thereby guiding the first underground substructure 3 shown in FIG.

図3Dに示すように、図2BのステップS23は、複数の穴14からセメントスラリーを注入することによって、複数の穴14の複数の底部に、複数の案内部材16の一端を固定するための複数の固結領域18を形成することを含む。固結領域18とは、セメントスラリーによって固化される土砂である。特定の実施例において、固結領域18は、地面11から約14〜24メートルに位置するが、これに限定されない。 As shown in FIG. 3D, step S23 of FIG. 2B is performed by injecting cement slurry from the plurality of holes 14 to fix one end of the plurality of guide members 16 to the plurality of bottom portions of the plurality of holes 14. Forming the consolidated region 18. The consolidated region 18 is earth and sand solidified by cement slurry. In certain embodiments, consolidation area 18 is located approximately 14-24 meters from ground 11 but is not limited to such.

図3Eに示すように、図2BのステップS24は、複数の管状物20を、それぞれ複数の案内部材16に覆設することを含む。複数の管状物20は、一実施例において、接続されている複数のプラスチックパイプであり、複数の穴14の略長手方向に沿って延伸している。ステップS24において、後のセメント注入作業において案内部材16がスラリーに接触することによって腐食されることを回避するために、複数の管状物20の一端が固結領域18に接触することが好ましい。 As shown in FIG. 3E, step S24 of FIG. 2B includes covering the plurality of tubular objects 20 on the plurality of guide members 16, respectively. In one embodiment, the plurality of tubular objects 20 are connected to a plurality of plastic pipes, and extend along the substantially longitudinal direction of the plurality of holes 14. In step S <b> 24, it is preferable that one end of the plurality of tubular objects 20 is in contact with the consolidated region 18 in order to prevent the guide member 16 from being corroded by contact with the slurry in a subsequent cement injection operation.

図2Cは、第1壁構造32を形成するステップS3を示す詳細ステップS31、S32及びS33である。図3Fに示すように、ステップS31は、複数の剛性挿入スリーブ22を用意することを含む。剛性挿入スリーブ22のそれぞれは、漸縮端221と、漸縮端221に対応する接続端222とを有する。この好ましい実施例において、ステップS31において、剛性挿入スリーブ22の漸縮端221のそれぞれを、連なっている複数の案内溝12に設け、複数の剛性挿入スリーブ22の接続端222を地面11の上に露出させる。上記複数の剛性挿入スリーブ22の漸縮端221は、好ましくは建設領域10に対して、建設領域10の外側からその内側へ上向きに傾斜する尖端24であり、これによって、後の第1地下サブ構造3を地面11に押し込むステップにおいて、建設領域10の内側の掘削された空間に土砂を排除する。複数の剛性挿入スリーブ22は、鋼、合金又は類似する剛性を有する他の材質で作製されることが好ましい。 FIG. 2C shows detailed steps S31, S32 and S33 showing step S3 of forming the first wall structure 32. As shown in FIG. 3F, step S31 includes preparing a plurality of rigid insertion sleeves 22. Each of the rigid insertion sleeves 22 has a gradually reducing end 221 and a connecting end 222 corresponding to the gradually reducing end 221. In this preferred embodiment, in step S31, each of the gradually reducing ends 221 of the rigid insertion sleeve 22 is provided in the plurality of continuous guide grooves 12, and the connection ends 222 of the plurality of rigid insertion sleeves 22 are placed on the ground 11. Expose. The gradually reducing ends 221 of the plurality of rigid insertion sleeves 22 are preferably sharp tips 24 inclined upwardly from the outside of the construction area 10 to the inside thereof with respect to the construction area 10, whereby the rear first underground sub In the step of pushing the structure 3 into the ground 11, the earth and sand are removed in the excavated space inside the construction area 10. The plurality of rigid insertion sleeves 22 are preferably made of steel, an alloy or other material with similar rigidity.

図3Gに示すように、ステップS32は、複数の堰板構造26をそれぞれ複数の剛性挿入スリーブ22の接続端222に接続することを含む。好ましくは、ステップS32は、図3Gに示すように、複数の剛性挿入スリーブ22及び複数の堰板構造26で画定された複数の空間28内において、複数の堰板261によって複数の加力領域Pを仕切ることによって、第1壁構造32の内側に、図3Hに示すような、力を加えるための複数の窪み30を形成する。具体的には、複数の堰板261の仕切りによって、加力領域Pに、鉄筋を設けることもコンクリートを注入することもなく、これによって、第1壁構造32の内側に力を加えるための複数の窪み30を形成し、つまり、上記した加力領域Pは第1壁構造32内の複数の窪み30に対応して位置する。 As shown in FIG. 3G, step S32 includes connecting the plurality of barrier plate structures 26 to the connection ends 222 of the plurality of rigid insertion sleeves 22, respectively. Preferably, in step S32, as shown in FIG. 3G, in the plurality of spaces 28 defined by the plurality of rigid insertion sleeves 22 and the plurality of dam plate structures 26, the plurality of force regions P by the plurality of dam plates 261. As shown in FIG. 3H, a plurality of depressions 30 for applying a force are formed inside the first wall structure 32. Specifically, the partition of the plurality of barrier plates 261 does not provide reinforcing bars or inject concrete into the applied region P, and thereby a plurality of members for applying a force to the inside of the first wall structure 32. In other words, the above-described force region P is positioned corresponding to the plurality of recesses 30 in the first wall structure 32.

図3Hに示すように、ステップS33は、複数の剛性挿入スリーブ22及び複数の堰板構造26で画定された複数の空間28において、第1壁構造32を形成することを含む。ステップS33は、複数の空間28内に、それぞれ複数の鉄筋籠(図示せず)を設け、セメント注入を行うことによって、鉄筋コンクリートで構成される第1壁構造32を形成するをさらに含む。特定の実施例において、第1壁構造32は、プレキャスト鉄筋コンクリートで構成されるものである。他の特定実施例において、第1壁構造32は、地面11から約1階の高さであることが好ましい。他の特定実施例において、第1壁構造32において、横向きに5〜10メートルごとに図3Hに示すような窪み30を設けることができ、第1壁構造32の複数の第1壁で画定された建設領域10は閉塞した建設領域10である。 As shown in FIG. 3H, step S33 includes forming a first wall structure 32 in a plurality of spaces 28 defined by the plurality of rigid insertion sleeves 22 and the plurality of barrier plate structures 26. Step S33 further includes forming a first wall structure 32 made of reinforced concrete by providing a plurality of reinforcing rods (not shown) in the plurality of spaces 28 and performing cement injection. In a particular embodiment, the first wall structure 32 is composed of precast reinforced concrete. In another particular embodiment, the first wall structure 32 is preferably about one floor above the ground 11. In another particular embodiment, the first wall structure 32 can be provided with indentations 30 as shown in FIG. 3H every 5-10 meters laterally, defined by a plurality of first walls of the first wall structure 32. The construction area 10 is a closed construction area 10.

図3Gに示す一実施例において、複数の案内部材16は、複数の金属ケーブルであり、ステップS32において堰板構造26を設けるときに、予め複数の金属ケーブルで形成された複数の案内部材16を、それぞれ複数の堰板261で仕切られた加力領域Pから抜き出しておく。これによって、図3Hに示すように、ステップS33において第1壁構造32を形成するときに、複数の金属ケーブルで形成された複数の案内部材16は、複数の窪み30から抜き出されるように配置される。 In one embodiment shown in FIG. 3G, the plurality of guide members 16 are a plurality of metal cables, and when the barrier plate structure 26 is provided in step S32, the plurality of guide members 16 formed in advance by the plurality of metal cables. These are extracted from the applied region P partitioned by a plurality of barrier plates 261. Accordingly, as shown in FIG. 3H, when the first wall structure 32 is formed in step S33, the plurality of guide members 16 formed of the plurality of metal cables are arranged so as to be extracted from the plurality of depressions 30. Is done.

図3Iに示すように、ステップS4は、第1壁構造32の複数の第1壁の内側の間に、複数の第1壁を支持するための複数の第1永久地中梁36(地下室の基礎梁又は格子梁とも呼ばれる)を設けることによって、第1地下サブ構造3を形成することを含む。永久地中梁36とは、複数の第1壁を一時に支持する仮支持体ではなく、第1壁構造32と固接され、完成後の地下構造1の永久的な一部とされるものである。永久地中梁36は、現場でキャスティングされるものであっても、プレキャスト鉄筋コンクリートであってもよく、或いは、コンクリート被覆鋼構造物であってもよい。 As shown in FIG. 3I, step S4 includes a plurality of first permanent underground beams 36 (basement chambers) for supporting the plurality of first walls between the insides of the plurality of first walls of the first wall structure 32. Forming the first subsurface substructure 3 by providing (also referred to as foundation beams or lattice beams). The permanent underground beam 36 is not a temporary support body that supports a plurality of first walls at a time, but is fixed to the first wall structure 32 and becomes a permanent part of the completed underground structure 1. It is. The permanent underground beam 36 may be cast on site, may be precast reinforced concrete, or may be a concrete-coated steel structure.

図3Iに示すように、ステップS5は、建設領域10内の土砂を第1深さH1まで掘削することを含む。ステップS6は、第1地下サブ構造3を、略第1深さH1まで地面11に押し込むことを含む。複数の管状物20が複数の案内部材16上に覆設されているので、複数の管状物20は、対応する複数の案内部材16との間で相対摺動可能である。したがって、管状物20と結合される第1壁構造32は、複数の案内部材16に固定されていない。複数の管状物20と対応の複数の案内部材16との間の覆設関係によって、第1壁構造32は、複数の案内部材16を摺動可能になる。本実施例のステップS6において、施工者は、複数の窪み30においてジャッキ34によって下へ推力を加えることによって、第1地下サブ構造3を地面11から押し込む。ステップS6は、複数の剛性挿入スリーブ22の尖端24を、元の例えば1メートルの深さから、例えば4メートルの第1深さH1、好ましくは1階の高さの深さまで押し込む。この押し込みステップが完成する後に、第1壁構造32は、地下構造(地下室)の外壁とされることができる。 As shown in FIG. 3I, step S5 includes excavating the earth and sand in the construction area 10 to the first depth H1. Step S6 includes pushing the first underground substructure 3 into the ground 11 to approximately the first depth H1. Since the plurality of tubular objects 20 are covered on the plurality of guide members 16, the plurality of tubular objects 20 can slide relative to the corresponding plurality of guide members 16. Therefore, the first wall structure 32 coupled to the tubular object 20 is not fixed to the plurality of guide members 16. Due to the covering relationship between the plurality of tubular objects 20 and the corresponding plurality of guide members 16, the first wall structure 32 can slide the plurality of guide members 16. In step S <b> 6 of this embodiment, the installer pushes the first underground substructure 3 from the ground 11 by applying a thrust downward by the jacks 34 in the plurality of depressions 30. Step S6 pushes the tips 24 of the plurality of rigid insertion sleeves 22 from the original depth of 1 meter, for example, to a first depth H1 of 4 meters, for example, preferably a depth of the first floor. After this pushing step is completed, the first wall structure 32 can be an outer wall of an underground structure (basement).

図3Hに示す実施例において、施工者は、複数の窪み30において、それぞれ複数のジャッキ34を設けるとともに、それぞれ複数のジャッキ34を、対応する複数の金属ケーブルで形成された複数の案内部材16に接続する。これによって、ステップS6に使用される複数のジャッキ34は、それぞれ複数の金属ケーブルで形成された複数の案内部材16に力を加えるとともに、複数の金属ケーブルで形成された複数の案内部材16がそれぞれに複数の固結領域18に接続される固結関係による反力によって、第1地下サブ構造3を地面11から押し込む。本実施例において、複数の剛性挿入スリーブ22の漸縮端221は、建設領域10に対して建設領域10の外側からその内側へ上向きに傾斜する尖端24を有するので、第1地下サブ構造3を下へ押し込むと同時に、漸縮端221によって、ステップS5で掘削されて空間を有する建設領域10の内側へ土砂を排除することができる。 In the embodiment shown in FIG. 3H, the installer provides a plurality of jacks 34 in the plurality of depressions 30, and each of the plurality of jacks 34 to a plurality of guide members 16 formed of a plurality of corresponding metal cables. Connecting. As a result, the plurality of jacks 34 used in step S6 apply force to the plurality of guide members 16 each formed of a plurality of metal cables, and the plurality of guide members 16 formed of the plurality of metal cables respectively. The first underground substructure 3 is pushed in from the ground 11 by the reaction force due to the consolidation relationship connected to the plurality of consolidation regions 18. In the present embodiment, the gradually reducing ends 221 of the plurality of rigid insertion sleeves 22 have a tip 24 that is inclined upward from the outside of the construction area 10 to the inside thereof with respect to the construction area 10. Simultaneously with the downward pressing, the gradually reducing end 221 can remove earth and sand to the inside of the construction area 10 excavated in step S5 and having a space.

他の実施例において、複数の複数の金属ケーブルで形成された案内部材16は、第1壁構造32の上方から抜き出され、第1壁構造32上から下向きの推力を加える。このとき、第1壁構造32は、それに固接される複数の管状物20と対応する複数の案内部材16との間の覆設関係によって、複数の案内部材16を摺動可能になり、これによって、第1地下サブ構造3を地面11から押し込む。この実施例において、施工者は、第1壁構造32に複数のジャッキ34を設け、複数のジャッキ34によって、複数の金属ケーブルで形成された複数の案内部材16のそれぞれに力を加え、複数の金属ケーブルで形成された複数の案内部材16が複数の固結領域18にそれぞれ接続される固結関係による反力によって、第1地下サブ構造3を地面11に押し込む。 In another embodiment, the guide member 16 formed of a plurality of metal cables is extracted from above the first wall structure 32 and applies a downward thrust from above the first wall structure 32. At this time, the first wall structure 32 can slide the plurality of guide members 16 by the covering relationship between the plurality of tubular objects 20 fixedly contacted thereto and the corresponding guide members 16. The first underground substructure 3 is pushed in from the ground 11. In this embodiment, the installer provides a plurality of jacks 34 on the first wall structure 32, and applies a force to each of the plurality of guide members 16 formed of a plurality of metal cables by the plurality of jacks 34. The first underground substructure 3 is pushed into the ground 11 by a reaction force due to a consolidation relationship in which a plurality of guide members 16 formed of metal cables are respectively connected to a plurality of consolidation regions 18.

複数の案内部材16は、一実施例のいて、グラウンドアンカー工法でいうテンドンであり、抗張材で作製される。抗張材は、鋼製品及び/又は他の材料であってもよく、鋼製品は、鋼棒(例えば、CNS9272 G3192の規定に従う剛棒)、鋼線又は鋼撚り線(例えば、CNS 3332 G3073の規定に従う鋼撚り線)、他の材料は、ガラス繊維等の材料を含む。 The plurality of guide members 16 are tendons referred to in the ground anchor method in one embodiment, and are made of a tensile material. The tensile material may be a steel product and / or other material, the steel product being a steel bar (eg a rigid bar according to the provisions of CNS9272 G3192), a steel wire or a steel strand (eg CNS 3332 G3073). Steel stranded wire according to regulations), other materials include materials such as glass fiber.

ステップS6において、第1地下サブ構造3を、地面11に押し込んだ後に、第1壁構造32上に後の壁構造を形成して所望の高さを有する多層地下構造1を構築するために、以下のステップS7〜S10をさらに備える。 In step S6, after the first underground substructure 3 is pushed into the ground 11, in order to form the rear wall structure on the first wall structure 32 and to construct the multilayer underground structure 1 having a desired height, The following steps S7 to S10 are further provided.

図2Dは、図2Aに示す第2壁構造40を形成するステップS7を示す詳細ステップS71及びS72である。図3Jに示すように、ステップS71は、複数の堰板構造38をそれぞれ第1壁構造32の上端に接続することを含む。図3Kに示すように、ステップS72は、堰板構造38において、第1壁構造32の上方に、複数の第2壁を含む第2壁構造40を形成することを含む。第1壁構造32と第2壁構造40との間を、予め設けた鉄筋によって互いに重ねてから、コンクリートを注入することで接続し、或いは他の接続手段によって第1壁構造32及び第2壁構造40を接続する。 FIG. 2D shows detailed steps S71 and S72 showing step S7 for forming the second wall structure 40 shown in FIG. 2A. As shown in FIG. 3J, step S71 includes connecting a plurality of barrier plate structures 38 to the upper ends of the first wall structures 32, respectively. As shown in FIG. 3K, step S <b> 72 includes forming a second wall structure 40 including a plurality of second walls above the first wall structure 32 in the barrier plate structure 38. The first wall structure 32 and the second wall structure 40 are connected to each other by injecting concrete after being overlapped with each other by a reinforcing bar provided in advance, or by other connecting means. The structure 40 is connected.

図3Lに示すように、図2AのステップS8は、第2壁構造40の複数の第2壁の内側の間に、第2壁構造40の複数の第2壁を支持するための複数の第2永久地中梁42を設けることによって、第2地下サブ構造4を形成し、そして、複数の第1永久地中梁36と複数の第2永久地中梁42との間に複数の第2永久柱45を形成することを含む。図2AのステップS9は、前記建設領域10内の土砂を、第1深さH1よりも深い第2深さH2まで掘削することを含む。図2AのステップS10は、第1地下サブ構造3、第2地下サブ構造4、複数の第1永久柱43及び複数の第2永久柱45を、複数の窪み30に位置する複数のジャッキ34によって、略第2深さH2まで下へ押し込むことを含む。 As shown in FIG. 3L, step S8 of FIG. 2A includes a plurality of second walls for supporting the plurality of second walls of the second wall structure 40 between the insides of the plurality of second walls of the second wall structure 40. By providing two permanent underground beams 42, a second underground substructure 4 is formed, and a plurality of second underground substructures 36 and a plurality of second permanent underground beams 42 are provided between the plurality of second permanent underground beams 42. Forming the permanent pillar 45. Step S9 in FIG. 2A includes excavating the earth and sand in the construction area 10 to a second depth H2 deeper than the first depth H1. Step S10 in FIG. 2A includes a plurality of jacks 34 in which the first underground substructure 3, the second underground substructure 4, the plurality of first permanent columns 43, and the plurality of second permanent columns 45 are positioned in the plurality of depressions 30. , And pushing down to approximately the second depth H2.

本発明の地下構造1の施工方法は、複数の第1永久地中梁36の上方に、第1地下フロア床層F1を敷設することと、第1永久柱43の下方に、前記第1永久柱43を支持するための地下構造床層F0を形成することとをさらに含むことが好ましい。 In the construction method of the underground structure 1 according to the present invention, the first underground floor layer F1 is laid above the plurality of first permanent underground beams 36, and the first permanent pillar 43 is below the first permanent pillar 43. It is preferable to further include forming an underground structure floor layer F0 for supporting the pillar 43.

所望の深さの壁及び地下構造が完成されるまで、上記ステップS7〜ステップS10のステップを繰返して行い、完成された壁構造に多層の第2壁構造40を形成し、第2永久地中梁42を構築し、第2壁構造40を押し込む等のステップを順に行う。 The steps S7 to S10 are repeated until the desired depth of the wall and the underground structure is completed, and the multilayered second wall structure 40 is formed on the completed wall structure, and the second permanent underground Steps such as building the beam 42 and pushing in the second wall structure 40 are performed in order.

以上によると、図3Lは、第1地下サブ構造3と、地面11から下へ延伸し、所定の深さDを有する複数の穴14と、複数の穴14内に設けられ、細長く可撓性を有する複数の案内部材16と、複数の穴14の複数の底部に形成され、複数の案内部材16の一端を固定する複数の固結領域18とを備える、本発明の地下構造の施工方法によって完成される地下構造1を示す。また、複数の管状物20は、複数の穴14の略長手方向に沿って延伸する。第1地下サブ構造3は、第1壁構造32と、第1壁構造32の複数の第1壁の内側の間に設けられ、複数の第1壁を支持するための複数の第1永久地中梁36と、第1永久柱43とを備える。 According to the above, FIG. 3L shows the first underground substructure 3, a plurality of holes 14 extending downward from the ground 11 and having a predetermined depth D, and provided in the plurality of holes 14. And a plurality of consolidated regions 18 formed at a plurality of bottom portions of the plurality of holes 14 and fixing one end of the plurality of guide members 16. The completed underground structure 1 is shown. Further, the plurality of tubular objects 20 extend along the substantially longitudinal direction of the plurality of holes 14. The first underground substructure 3 is provided between the first wall structure 32 and the plurality of first walls of the first wall structure 32, and a plurality of first permanent lands for supporting the plurality of first walls. An intermediate beam 36 and a first permanent pillar 43 are provided.

地下構造1は、複数の案内部材16に覆設される複数の管状物20と、複数の剛性挿入スリーブ22とをさらに備える。複数の剛性挿入スリーブ22の漸縮端221は、建設領域10に対して、建設領域10の外側からその内側へ上向きに傾斜する尖端24であることが好ましい。好ましくは、複数の剛性挿入スリーブ22は鋼又は合金で作製される。好ましい実施例において、複数の案内部材16は複数の金属ケーブルであり、それぞれに対応する複数の窪み30から抜き出される。 The underground structure 1 further includes a plurality of tubular objects 20 covered by the plurality of guide members 16 and a plurality of rigid insertion sleeves 22. The gradually reducing ends 221 of the plurality of rigid insertion sleeves 22 are preferably sharp edges 24 inclined upward from the outside of the construction area 10 to the inside thereof with respect to the construction area 10. Preferably, the plurality of rigid insertion sleeves 22 are made of steel or an alloy. In a preferred embodiment, the plurality of guide members 16 are a plurality of metal cables, which are extracted from a plurality of recesses 30 corresponding thereto.

本発明の地下構造1は、第1壁構造32上に形成される第2壁構造40と、第2壁構造40の複数の第2壁の内側の間に設けられ、複数の第2壁を支持して第2地下サブ構造4を形成するための複数の第2永久地中梁42とをさらに備える。複数の第1永久地中梁36と複数の第2永久地中梁42との間に、複数の第2永久柱45がさらに形成されている。 The underground structure 1 of the present invention is provided between the second wall structure 40 formed on the first wall structure 32 and the plurality of second walls of the second wall structure 40, and the plurality of second walls are A plurality of second permanent underground beams 42 for supporting and forming the second underground substructure 4 are further provided. A plurality of second permanent columns 45 are further formed between the plurality of first permanent underground beams 36 and the plurality of second permanent underground beams 42.

本発明の地下構造1は、複数の第1永久地中梁36の上方に敷設される第1地下フロア床層F1と、地下構造床層F0とをさらに備えることが好ましい。 The underground structure 1 of the present invention preferably further includes a first underground floor layer F1 and an underground structure floor layer F0 laid above the plurality of first permanent underground beams 36.

以上をまとめると、本発明の地下構造1の施工方法によれば、地下構造1を形成すると同時に、建設領域10の内側を掘削し、また、永久地中梁及び永久柱を同時に設けることができるので、品質が良く、コストが低く、工期が短い利点を有する。 In summary, according to the construction method of the underground structure 1 of the present invention, the underground structure 1 can be formed, the inside of the construction region 10 can be excavated, and permanent underground beams and permanent columns can be provided simultaneously. Therefore, it has the advantages of good quality, low cost and short construction period.

本発明は、既に上記した関連実施例によって説明され、しかし、上記実施例は本発明を実施するための例に過ぎない。開示された実施例は本発明の範囲を制限する意図はないことを説明しておくべきである。逆に、特許請求の範囲の主旨及び範囲に含まれる修正及び均等な設置はいずれも本発明の範囲内に含まれる。 The present invention has been explained by the related embodiments already described above, but the above embodiments are merely examples for carrying out the present invention. It should be noted that the disclosed embodiments are not intended to limit the scope of the invention. On the contrary, all modifications and equivalent installations included in the spirit and scope of the claims are included in the scope of the present invention.

1 : 地下構造 10 : 建設領域
11 : 地面 12 : 案内溝
14 : 穴 16 : 案内部材
18 : 固結領域 20 : 管状物
22 : 挿入スリーブ 221 : 漸縮端
222 : 接続端 24 : 尖端
26 : 堰板構造 261 : 堰板
28 : 空間 30 : 窪み
3 : 第1地下サブ構造 32 : 第1壁構造
34 : ジャッキ 36 : 第1永久地中梁
38 : 堰板構造 4 : 第2地下サブ構造
40 : 第2壁構造 42 : 第2永久地中梁
43 : 第1永久柱 45 : 第2永久柱
9 : 地下構造 91 : 連続壁
93 : 地下サブ構造
D : 所定の深さ H1 : 第1深さ
H2 : 第2深さ F1 : 第1地下フロア床層
F0 : 地下構造床層 P : 加力領域
S1〜S10 : ステップ
S21〜S24 : ステップ
S31〜S33 : ステップ
S71〜S72 : ステップ
DESCRIPTION OF SYMBOLS 1: Underground structure 10: Construction area 11: Ground 12: Guide groove 14: Hole 16: Guide member 18: Consolidation area 20: Tubular object 22: Insertion sleeve 221: Reducing end 222: Connection end 24: Pointed end 26: Weir Plate structure 261: Dam plate 28: Space 30: Indent 3: First underground substructure 32: First wall structure 34: Jack 36: First permanent underground beam 38: Dam plate structure 4: Second underground substructure 40: Second wall structure 42: Second permanent underground beam 43: First permanent column 45: Second permanent column 9: Underground structure 91: Continuous wall 93: Underground substructure D: Predetermined depth H1: First depth H2 : Second depth F1: First underground floor layer F0: Underground structure floor layer P: Applied area S1 to S10: Steps S21 to S24: Steps S31 to S33: Steps S71 to S72: Step

Claims (14)

地下構造を形成するための施工方法であって、
互いに連なって建設領域を画定する複数の第1壁を含む第1壁構造を形成するステップと、
前記複数の第1壁の内側の間に、前記複数の第1壁を支持するための複数の第1永久地中梁を設けることによって、第1地下サブ構造を形成するステップと、
前記建設領域内の土砂を第1深さまで掘削するステップと、
前記第1地下サブ構造を、略前記第1深さまで地面に押し込むステップと、を備える施工方法。
A construction method for forming an underground structure,
Forming a first wall structure that includes a plurality of first walls that are connected together to define a construction area;
Forming a first underground substructure by providing a plurality of first permanent underground beams for supporting the plurality of first walls between the inside of the plurality of first walls;
Excavating the earth and sand in the construction area to a first depth;
Pushing the first underground substructure into the ground substantially to the first depth.
当該前記第1壁構造を形成する当該前記ステップの前に、
前記地面から下へ延伸し、所定の深さを有する複数の穴を形成するステップと、
前記第1地下サブ構造の前記地面への押し込みを案内するように、所定の深さまで延伸し、細長く可撓性を有する複数の案内部材を、前記複数の穴内に設けるステップと、
前記複数の穴から、セメントスラリーを注入することによって、前記複数の穴の複数の底部に、複数の固結領域を形成して前記案内部材の一端を固定するステップと、
をさらに備える請求項1に記載の施工方法。
Before the step of forming the first wall structure,
Extending downward from the ground to form a plurality of holes having a predetermined depth;
Providing a plurality of elongated and flexible guide members in the plurality of holes, extending to a predetermined depth so as to guide the pushing of the first underground substructure into the ground;
Fixing a first end of the guide member by forming cemented slurry from the plurality of holes to form a plurality of consolidated regions at a plurality of bottoms of the plurality of holes;
The construction method according to claim 1, further comprising:
前記第1壁構造を形成する前記ステップの前に、前記複数の穴の略長手方向に沿って延伸する複数の管状物を、前記複数の案内部材に覆設するステップをさらに備える請求項2に記載の施工方法。 The step of covering the plurality of guide members with a plurality of tubular objects extending along substantially the longitudinal direction of the plurality of holes before the step of forming the first wall structure is provided. The construction method described. 前記第1壁構造を形成する前記ステップは、
前記空間内において、複数の堰板によって複数の加力領域を仕切ることによって、前記第1壁構造の内側に、力を加えるための複数の窪みを形成することをさらに含み、
前記第1地下サブ構造を前記地面に押し込むステップは、前記複数の窪みにおいて複数の下向きの推力を加える請求項3に記載の施工方法。
The step of forming the first wall structure comprises:
Forming a plurality of depressions for applying a force inside the first wall structure by partitioning a plurality of force application regions by a plurality of barrier plates in the space;
The construction method according to claim 3, wherein the step of pushing the first underground substructure into the ground applies a plurality of downward thrusts in the plurality of depressions.
前記複数の案内部材は、複数の金属ケーブルであり、
前記施工方法は、前記複数の金属ケーブルを前記複数の窪みから抜き出し、前記複数の窪みにそれぞれ複数のジャッキを設け、前記複数のジャッキのそれぞれによって、前記複数の金属ケーブルに力を加え、前記複数の金属ケーブルがそれぞれ前記複数の固結領域に接続されることによる反力によって、前記第1地下サブ構造を前記地面に押し込むことをさらに含む請求項4に記載の施工方法。
The plurality of guide members are a plurality of metal cables,
In the construction method, the plurality of metal cables are extracted from the plurality of depressions, a plurality of jacks are provided in the plurality of depressions, and a force is applied to the plurality of metal cables by each of the plurality of jacks. The construction method according to claim 4, further comprising pressing the first underground substructure into the ground by a reaction force caused by each of the metal cables connected to the plurality of consolidated regions.
前記複数の案内部材は、複数の金属ケーブルであり、前記施工方法は、前記複数の金属ケーブルを、前記第1壁構造の上端から抜き出しすることと、前記第1壁構造の上端に、複数のジャッキを設け、前記複数のジャッキによって、前記複数の金属ケーブルに力を加え、前記複数の金属ケーブルが前記複数の固結領域に接続されることによる反力によって、前記第1地下サブ構造を前記地面に押し込むこととをさらに含む請求項3に記載の施工方法。 The plurality of guide members are a plurality of metal cables, and the construction method includes extracting the plurality of metal cables from an upper end of the first wall structure and a plurality of metal cables at an upper end of the first wall structure. Providing a jack, applying a force to the plurality of metal cables by the plurality of jacks, and reacting the plurality of metal cables to the plurality of consolidated regions, thereby causing the first underground substructure to be The construction method according to claim 3, further comprising pushing into the ground. 前記建設領域内の土砂を第1深さまで掘削するステップの後に、前記複数の第1永久地中梁の下方に第1永久柱を形成することをさらに含み、且つ前記複数の第1壁により画定された前記建設領域は、閉塞した建設領域である請求項3に記載の施工方法。 After the step of excavating the earth and sand in the construction area to a first depth, further comprising forming a first permanent column below the plurality of first permanent underground beams and defined by the plurality of first walls. The construction method according to claim 3, wherein the constructed construction area is a closed construction area. 前記第1壁構造を形成する前記ステップは、
それぞれ漸縮端及び前記漸縮端と対応する接続端とを有する複数の剛性挿入スリーブを用意するステップと、
複数の堰板構造を、それぞれ前記複数の剛性挿入スリーブの前記接続端に接続するステップと、
前記複数の剛性挿入スリーブ及び前記複数の堰板構造によってそれぞれ画定された複数の空間において、前記第1壁構造を形成するステップとをさらに備える請求項7に記載の施工方法。
The step of forming the first wall structure comprises:
Providing a plurality of rigid insertion sleeves each having a gradually reducing end and a connecting end corresponding to the gradually reducing end;
Connecting a plurality of barrier plate structures to the connection ends of the plurality of rigid insertion sleeves, respectively;
The construction method according to claim 7, further comprising: forming the first wall structure in a plurality of spaces respectively defined by the plurality of rigid insertion sleeves and the plurality of barrier plate structures.
前記第1壁構造を形成する前記ステップの前に、
前記地面に、複数の連なる案内溝を形成するステップと、
前記複数の剛性挿入スリーブの前記漸縮端を、それぞれ前記複数の連なる案内溝に設けるステップとをさらに備える請求項8に記載の施工方法。
Before the step of forming the first wall structure,
Forming a plurality of continuous guide grooves in the ground;
The construction method according to claim 8, further comprising the step of providing the gradually reducing ends of the plurality of rigid insertion sleeves in the plurality of continuous guide grooves, respectively.
前記漸縮端が建設領域に対して、前記建設領域の外側からその内側へ上向きに傾斜する尖端であり、前記第1地下サブ構造を前記地面に押し込むステップにおいて、前記漸縮端によって、前記建設領域の内側へ土砂を排除する請求項8に記載の施工方法。 The gradually reducing edge is a sharp tip inclined upward from the outside of the construction area to the inside thereof with respect to the construction area, and in the step of pushing the first underground substructure into the ground, The construction method according to claim 8, wherein earth and sand are excluded to the inside of the region. 前記第1壁構造を形成する前記ステップは、前記複数の空間内に、それぞれ複数の鉄筋籠を設けるとともにセメント注入を行うことを含む請求項8に記載の施工方法。 The construction method according to claim 8, wherein the step of forming the first wall structure includes providing a plurality of reinforcing bar rods in each of the plurality of spaces and injecting cement. 複数の堰板構造を前記第1壁構造の上端に接続することと、
複数の第2壁を含む第2壁構造を形成することと、
前記複数の第2壁の内側の間に、前記複数の第2壁を支持するための複数の第2永久地中梁を設けることによって、第2地下サブ構造を形成することと、
前記複数の第1永久地中梁と前記複数の第2永久地中梁との間に、複数の第2永久柱を形成することと、
前記建設領域内の土砂を、前記第1深さよりも深い第2深さまで掘削することと、
前記第1地下サブ構造、前記第2地下サブ構造、前記複数の第1永久柱、及び前記複数の第2永久柱を、略前記第2深さまで下へ押し込むことと、
をさらに含む請求項8に記載の施工方法。
Connecting a plurality of barrier plate structures to an upper end of the first wall structure;
Forming a second wall structure including a plurality of second walls;
Forming a second subsurface substructure by providing a plurality of second permanent underground beams for supporting the plurality of second walls between the inside of the plurality of second walls;
Forming a plurality of second permanent columns between the plurality of first permanent underground beams and the plurality of second permanent underground beams;
Excavating the earth and sand in the construction area to a second depth deeper than the first depth;
Pushing the first subsurface substructure, the second subsurface substructure, the plurality of first permanent columns, and the plurality of second permanent columns substantially to the second depth;
The construction method according to claim 8, further comprising:
前記複数の第1永久地中梁の上方に、第1地下フロア床層を敷設することと、第1永久柱の下方に、地下構造フロア床層を形成することとをさらに含む請求項12に記載の施工方法。 13. The method according to claim 12, further comprising: laying a first underground floor floor layer above the plurality of first permanent underground beams; and forming an underground structure floor floor layer below the first permanent pillar. The construction method described. 請求項2〜13のいずれか1項に記載の施工方法により形成される地下構造。 The underground structure formed by the construction method of any one of Claims 2-13.
JP2017121874A 2017-05-24 2017-06-22 Construction method for forming underground structure and underground structure completed thereby Active JP6514739B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
TW106117089A TWI634249B (en) 2017-05-24 2017-05-24 Method for forming underground construction and underground construction formed thereby
TW106117089 2017-05-24

Publications (2)

Publication Number Publication Date
JP2018197486A true JP2018197486A (en) 2018-12-13
JP6514739B2 JP6514739B2 (en) 2019-05-15

Family

ID=64452746

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017121874A Active JP6514739B2 (en) 2017-05-24 2017-06-22 Construction method for forming underground structure and underground structure completed thereby

Country Status (2)

Country Link
JP (1) JP6514739B2 (en)
TW (1) TWI634249B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI753415B (en) * 2020-04-29 2022-01-21 聖陸營造工程股份有限公司 Construction Method of Constructing Continuous Wall Guide Ditch of New Building on the Old Underground Floor Structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62268423A (en) * 1986-05-16 1987-11-21 Kajima Corp Construction work of underground pile used in common for earth anchor
JPS6410854A (en) * 1987-07-01 1989-01-13 Sumitomo Electric Industries Double-coated unbond pc steel material
JPH08193333A (en) * 1995-01-13 1996-07-30 Taisei Corp Caisson press in method
JPH1113287A (en) * 1997-06-26 1999-01-19 Takenaka Komuten Co Ltd Large space constructing method applying diagonal tension system
JP2000257060A (en) * 1999-03-11 2000-09-19 Topy Ind Ltd Earth anchor

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW428060B (en) * 1998-02-23 2001-04-01 Jang Jr Jia Descending shoring method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62268423A (en) * 1986-05-16 1987-11-21 Kajima Corp Construction work of underground pile used in common for earth anchor
JPS6410854A (en) * 1987-07-01 1989-01-13 Sumitomo Electric Industries Double-coated unbond pc steel material
JPH08193333A (en) * 1995-01-13 1996-07-30 Taisei Corp Caisson press in method
JPH1113287A (en) * 1997-06-26 1999-01-19 Takenaka Komuten Co Ltd Large space constructing method applying diagonal tension system
JP2000257060A (en) * 1999-03-11 2000-09-19 Topy Ind Ltd Earth anchor

Also Published As

Publication number Publication date
TW201900987A (en) 2019-01-01
JP6514739B2 (en) 2019-05-15
TWI634249B (en) 2018-09-01

Similar Documents

Publication Publication Date Title
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
CH615236A5 (en)
KR101777176B1 (en) Construction method of cast-in-placed-pile using steel pipes having different shapes to each other
KR20090094555A (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR102009077B1 (en) Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type
KR101901392B1 (en) A Micropile and Retaining Wall Method by using Micropile
KR20140055639A (en) A execution method of architecture beam
CN108316670B (en) Steel pipe underpinning construction method under existing building foundation
JP2015124587A (en) Construction method for new underground skeleton, accompanied by demolition of existing underground skeleton
KR20070076553A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR101187170B1 (en) Application of under pinning method in remodeling
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JP6460712B2 (en) Construction method of underground continuous wall
KR100898969B1 (en) Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof
JP2000352296A (en) Method o constructing passage just under underground structure
JP6514739B2 (en) Construction method for forming underground structure and underground structure completed thereby
JP5681039B2 (en) Mountain fastening method
CN111042104A (en) Method for constructing diaphragm wall at existing underground structure
KR102072889B1 (en) Construction method of smallcaliber composite pile wall using small drilling rig at adjacent building proximity section
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
JP2012087561A (en) Construction method of outer peripheral column in inverted construction
JP6947477B2 (en) How to advance the open shield machine
JP2018053466A (en) Open shield method

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190205

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190306

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190402

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190412

R150 Certificate of patent or registration of utility model

Ref document number: 6514739

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250