KR102009077B1 - Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type - Google Patents

Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type Download PDF

Info

Publication number
KR102009077B1
KR102009077B1 KR1020170070994A KR20170070994A KR102009077B1 KR 102009077 B1 KR102009077 B1 KR 102009077B1 KR 1020170070994 A KR1020170070994 A KR 1020170070994A KR 20170070994 A KR20170070994 A KR 20170070994A KR 102009077 B1 KR102009077 B1 KR 102009077B1
Authority
KR
South Korea
Prior art keywords
primary
casing
order
hole
guide member
Prior art date
Application number
KR1020170070994A
Other languages
Korean (ko)
Other versions
KR20180133748A (en
Inventor
신승혜
Original Assignee
신승혜
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 신승혜 filed Critical 신승혜
Priority to KR1020170070994A priority Critical patent/KR102009077B1/en
Publication of KR20180133748A publication Critical patent/KR20180133748A/en
Application granted granted Critical
Publication of KR102009077B1 publication Critical patent/KR102009077B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 발명은 1차 현장 말뚝에 차수용 중공부를 둔 후 2차 현장 말뚝에 차수용 중공부를 포함하여 콘크리트가 타설되도록 함으로써 차수가 완성되도록 한 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법을 제공한다.
본 발명의 적절한 실시 형태에 따른 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법은, (a) 흙막이 벽체가 시공될 지반에 일정 간격마다 소정의 직경을 갖는 1차 케이싱을 근입하고 천공을 실시하여 1차 천공홀을 시공하는 단계와; (b) 한 쌍의 중첩경계용 가이드부재가 각기 부착된 철근망이나 H빔을 인양하여 1차 천공홀에 인입시켜 놓는 단계와; (c) 1차 천공홀에 콘크리트를 타설하여 중첩경계용 가이드부재의 외측으로 콘크리트가 타설되지 않은 차수용 중공부를 형성시킨 후, 1차 케이싱을 인발하는 단계와; (d) 이웃한 1차 천공홀의 사이에 존재하는 중첩경계용 가이드부재에 의해 형성된 차수용 중공부가 겹침되도록 하여 동일한 직경을 갖는 2차 케이싱을 근입하고 천공을 실시하여 2차 천공홀을 시공하는 단계와; (e) 중첩경계용 가이드부재가 설치되지 않은 철근망이나 H빔을 인양하여 2차 천공홀에 인입시켜 놓는 단계와; (f) 차수용 중공부를 포함시킨 2차 천공홀에 콘크리트를 타설한 후, 2차 케이싱을 인발하는 단계;를 포함하여 시공되는 것을 특징으로 한다.
The present invention provides a construction method of the earth wall using the order-type column-type cast-in-placement piles to ensure the order is completed by placing the hollows for the order in the primary site piles, including the hollows for the secondary site piles to provide.
According to a preferred embodiment of the present invention, a method of constructing a retaining wall using an ordered column-type cast-in-placement pile includes: (a) incorporating a primary casing having a predetermined diameter at a predetermined interval in the ground on which the retaining wall is to be constructed; Constructing a primary drilling hole; (b) lifting a rebar net or H beam to which a pair of superimposed boundary guide members are attached, respectively, and introducing the reinforcing bar into the primary drilling hole; (c) placing concrete in the primary perforation hole to form a hollow portion for the non-pouring concrete on the outside of the guide member for overlapping boundary, and then drawing the primary casing; (d) constructing secondary drilling holes by incorporating secondary casings having the same diameter so as to allow the hollow portions for order formed by the overlapping boundary guide members existing between neighboring primary drilling holes to overlap; Wow; (e) lifting the reinforcing bar or H beam which is not provided with the guide member for overlapping boundary, and introducing the reinforcing hole into the secondary drilling hole; (f) after pouring concrete into the secondary perforation hole including the hollow portion for drawing, drawing a secondary casing; characterized in that the construction including.

Description

차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법{Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type}Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type}

본 발명은 흙막이 벽체의 시공방법에 관한 것으로, 특히 1차 현장 말뚝에 차수용 중공부를 둔 후 2차 현장 말뚝에 차수용 중공부를 포함하여 콘크리트가 타설되도록 함으로써 차수가 완성되도록 한 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법에 관한 것이다.The present invention relates to a construction method of the retaining wall, in particular, after placing the hollow portion for the primary site piles and the secondary site piles including the hollow portion for the degree of order to complete the order by placing concrete It relates to a construction method of the retaining wall using the pouring pile.

흙막이 공법은 지하구조물 설치를 위한 작업공간 확보 수단으로 토압, 수압에 저항하여 굴착면의 붕괴나 토사유입 방지를 위하여 설치하는 가설구조물로서, 현장여건 및 주변사항(토지조건, 지하수위 분포 여부, 지하매설물, 인접시설물 등)을 고려하여 안정성 및 시공성, 경제성을 충족할 수 있는 공법을 선택하여 적용한다.As the construction method for the construction of the underground structure, it is a temporary structure installed to prevent the collapse of the excavation surface or the inflow of soil by resisting earth pressure and water pressure as a means of securing the working space for the installation of underground structures, and the site conditions and surroundings (land conditions, groundwater level distribution, underground) Considering buried items, adjacent facilities, etc.), select and apply a method that can satisfy stability, constructability, and economic feasibility.

흙막이 벽체로는 엄지말뚝+토류판, 강널말뚝 벽체, 현장타설 콘크리트 말뚝(C.I.P) 주열식 벽, 소일 시멘트 벽체(S.C.W), 지하연속벽(Slurry Wall) 등의 공법이 알려져 있다.As the clam wall, construction methods such as thumb pile + earth plate, sheet pile wall, cast-in-place concrete pile (C.I.P) casting type wall, soil cement wall (S.C.W), and underground continuous wall (Slurry Wall) are known.

주열식 벽(C.I.P) 공법은 오거나 T4 장비를 이용하여 소정의 직경으로 개별 천공 후 H-파일과 철근을 삽입하고 콘크리트를 타설하여 흙막이 벽을 형성시키는 공법으로, 강성 벽체로서 인접구조물에 피해를 최소화할 수 있는 장점을 갖는데 반해, 깊은 심도에서는 수직도가 떨어지고, 공과 공 사이의 이음부가 취약하고, 차수를 위한 별도의 차수 공법이 적용되어야 하므로 경제성에서 취약한 문제를 가지고 있다. 예를 들어, 후 공정으로 차수기능을 위해 이중관 로드를 사용한 특수 첨단장치를 결합시켜 대상지반에 유도공간을 형성시켜 순결에 가까운 겔타임을 가진 약액 또는 약액과 초미립 시멘트 혼합제를 사용하여 지반을 개량하는 차수공법이 별도로 추가된다. 따라서 주열식 벽(C.I.P) 공법이 가지는 이러한 단점을 해결할 수 있는 방안이 요구된다.The CIP method is a method of inserting H-pile and reinforcing bars and placing concrete walls to form a retaining wall after individual drilling with a predetermined diameter by using T4 equipment, and minimizing damage to adjacent structures as a rigid wall. On the other hand, there is a weak point in economics because the vertical depth is poor, the joints between the balls and the joints are weak at deep depths, and a separate order method for the order must be applied. For example, the advanced process using double pipe rods is combined to form an induction space in the target ground by the post process to improve the ground by using the chemical liquid or the chemical and ultra fine cement mixture with gel time close to purity. The order method is added separately. Therefore, there is a need for a solution that can solve these disadvantages of the C.I.P process.

본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-0927186호로서, '흙막이 및 차수용 연속 벽체 시공방법'이 제안되어 있다. 이는 파일이 근입될 위치의 지반에 파일공을 천공하기 위하여 지반 터파기를 한 후에 케이싱 가이드를 설치하고, 상기 케이싱 가이드에 케이싱을 삽입한 후에 이 케이싱을 이용하여 일정 깊이까지 천공한 다음 토사 및 암편을 배토시키고, 상기 케이싱의 내부에 사전에 제작된 파일을 근입시키면서 선형을 유지시킨 후에 케이싱을 인발한 후, 파일과 파일 사이를 천공하여 연결공을 형성한 후에 레미콘이나 몰탈을 연결공에 주입하여 파일 간을 연결하고 케이싱 가이드를 해체함으로써 하나의 연속 벽체 구조물을 구축하는 것을 특징으로 한다. 그러나 이 배경기술은 파일 선형 작업 시공 후 연결공을 천공하고, 이에 몰탈을 타설하는 후공정의 차수작업이 요구된다.As a background technology of the present invention, Korean Patent Registration No. 10-0927186 has been proposed, 'a continuous wall construction method for the wall and the order'. This is to install the casing guide after drilling the ground in order to drill the pile hole in the ground where the pile will be located, insert the casing into the casing guide and drill it to a certain depth using this casing, After discharging, maintaining the linear shape while injecting the pre-fabricated pile inside the casing, drawing the casing, and drilling the pile between the pile and the pile to form a connection hole, and then injecting the ready-mixed concrete or mortar into the connecting hole. It is characterized by building one continuous wall structure by connecting the liver and dismantling the casing guide. However, this background art requires the post-processing work of drilling the connection hole after constructing the pile linear work and placing mortar on it.

본 발명의 배경이 되는 다른 기술로는 한국 등록특허 등록번호 제10-1590032호로서, '지중 매입 파일을 이용한 주열식 벽체 및 이를 이용한 구조물 시공방법'이 제안되어 있다. 이는 파일을 이용하여 종방향으로 파일을 연결하면서 벽체를 시공하되 굽힘보강부를 파일에 형성시켜 효과적인 토압지지가 가능하며, 이러한 파일을 이용한 주열식 벽체를 이용하여 다양한 구조물을 시공할 수 있도록 한 것이다. 그러나 이 배경기술은 지반을 일부 터파기 한 후, 터파기된 지표면에 지중매입 파일과 접하는 부위가 닫힌 공간이 형성되도록 제작된 엑스자형을 포함하는 연결금구; 및 상기 닫힌 공간으로 주입되어 연결금구와 지중매입 파일과 지중매입 파일이 서로 일체화되도록 하는 그라우팅재를 포함하는 파일연결재의 설치 등으로 차수를 위한 구성수가 증가되고 공수가 늘어나 시공이 복잡해지는 단점이 있다.As another technology that is the background of the present invention, Korean Patent Registration No. 10-1590032 has been proposed, 'stage heating wall using underground embedded pile and structure construction method using the same'. This allows the construction of walls while connecting piles in the longitudinal direction using piles, but the formation of bending reinforcement parts on piles for effective earth pressure support, and the construction of various structures using pile walls using such piles. However, the background art is a connection bracket including an X-shaped fabricated to form a closed space in contact with the landfill pile on the surface of the trench after the partial destruction of the ground; And the construction of a pile connecting material including a grouting material which is injected into the closed space and a grouting material for integrating the connecting bracket, the underground buying file and the underground buying file, increases the number of components for the order and increases the number of works. .

본 발명의 또 다른 배경이 되는 기술로는 한국 등록특허 등록번호 제10-0752397호로서, '지중 차수벽 시공방법 및 이에 사용되는 보조케이싱'이 제안되어 있다. 이는 주케이싱과의 결합을 위한 홈부가 양측에 형성된 복수의 보조케이싱을 지반에 설치하되, 그 복수의 보조케이싱 사이에 상기 주케이싱이 설치될 간격을 두고 설치하는 보조케이싱 설치단계와; 상기 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱 사이의 지반을 천공하여 복수의 상기 주케이싱을 설치하는 주케이싱 설치단계와; 상기 복수의 보조케이싱 및 주케이싱의 내부에 배근을 설치하는 배근단계와; 상기 복수의 보조케이싱 및 주케이싱 내부에 콘크리트를 타설하는 콘크리트 타설단계와; 상기 콘크리트 타설단계에 의해 타설된 콘크리트의 양생 전, 상기 보조케이싱 및 주케이싱을 제거하는 케이싱 제거단계를; 포함하는 지중 차수벽 시공방법을 제시한다. 그러나 이 배경기술은 보조케이싱에 홈부가 형성되어 있어 지반에 회전 관입시키기가 어렵고, 이를 해결하기 위해 주케이싱을 임시로 지반에 설치하여 천공한 후, 그 주케이싱 내부에 보조케이싱을 삽입 설치하고, 다시 주케이싱을 제거하는 번거로운 작업이 필요하다. 또한 보조케이싱을 주케이싱의 중앙부에 위치시키기 위해 스페이서를 설치하는 추가적인 작업 공정이 필요하여, 전체적으로 시공 공수가 늘어나는 문제가 있다.As a background technology of the present invention, Korean Patent Registration No. 10-0752397 has been proposed, 'underground order wall construction method and auxiliary casing used therein'. The auxiliary casing installation step of installing a plurality of auxiliary casings formed on both sides of the groove portion for coupling with the main casing on the ground, the auxiliary casing is installed at intervals between the plurality of auxiliary casing to be installed; A main casing installing step of drilling a ground between the plurality of auxiliary casings installed by the auxiliary casing installing step to install a plurality of the main casings; A step of installing a back muscle in the plurality of auxiliary casings and the main casing; A concrete placing step of placing concrete in the plurality of auxiliary casings and the main casing; A casing removing step of removing the auxiliary casing and the main casing before curing of the concrete poured by the concrete pouring step; We present the method of construction of underground containment wall. However, this background art has a groove formed in the auxiliary casing, so that it is difficult to intrude rotation into the ground. To solve this problem, the main casing is temporarily installed in the ground to be drilled, and then the auxiliary casing is inserted into the main casing. Again, cumbersome work is needed to remove the main casing. In addition, there is a need for an additional work process of installing a spacer to position the auxiliary casing in the center of the main casing, which increases the construction man-hour.

한국 등록특허 등록번호 제10-0927186호Korea Patent Registration No. 10-0927186 한국 등록특허 등록번호 제10-1590032호Korean Patent Registration No. 10-1590032 한국 등록특허 등록번호 제10-0752397호Korea Patent Registration No. 10-0752397

본 발명은 1차 현장 말뚝에 차수용 중공부를 둔 후 2차 현장 말뚝에 차수용 중공부를 포함하여 콘크리트가 타설되도록 함으로써 차수가 완성되도록 한 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법을 제공함에 그 목적이 있다.The present invention provides a construction method of the earth wall using the order-type column-type cast-in-placement piles to ensure the order is completed by placing the hollows for the order in the primary site piles, including the hollows for the secondary site piles The purpose is to provide.

본 발명의 적절한 실시 형태에 따른 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법은, (a) 흙막이 벽체가 시공될 지반에 일정 간격마다 소정의 직경을 갖는 1차 케이싱을 근입하고 천공을 실시하여 1차 천공홀을 시공하는 단계와; (b) 한 쌍의 중첩경계용 가이드부재가 각기 부착된 철근망이나 H빔을 인양하여 1차 천공홀에 인입시켜 놓는 단계와; (c) 1차 천공홀에 콘크리트를 타설하여 중첩경계용 가이드부재의 외측으로 콘크리트가 타설되지 않은 차수용 중공부를 형성시킨 후, 1차 케이싱을 인발하는 단계와; (d) 이웃한 1차 천공홀의 사이에 존재하는 중첩경계용 가이드부재에 의해 형성된 차수용 중공부가 겹침되도록 하여 동일한 직경을 갖는 2차 케이싱을 근입하고 천공을 실시하여 2차 천공홀을 시공하는 단계와; (e) 중첩경계용 가이드부재가 설치되지 않은 철근망이나 H빔을 인양하여 2차 천공홀에 인입시켜 놓는 단계와; (f) 차수용 중공부를 포함시킨 2차 천공홀에 콘크리트를 타설한 후, 2차 케이싱을 인발하는 단계;를 포함하여 시공되는 것을 특징으로 한다.According to a preferred embodiment of the present invention, a method of constructing a retaining wall using an ordered column-type cast-in-placement pile includes: (a) incorporating a primary casing having a predetermined diameter at a predetermined interval in the ground on which the retaining wall is to be constructed; Constructing a primary drilling hole; (b) lifting a rebar net or H beam to which a pair of superimposed boundary guide members are attached, respectively, and introducing the reinforcing bar into the primary drilling hole; (c) placing concrete in the primary perforation hole to form a hollow portion for the non-pouring concrete on the outside of the guide member for overlapping boundary, and then drawing the primary casing; (d) constructing secondary drilling holes by incorporating secondary casings having the same diameter so as to allow the hollow portions for order formed by the overlapping boundary guide members existing between neighboring primary drilling holes to overlap; Wow; (e) lifting the reinforcing bar or H beam which is not provided with the guide member for overlapping boundary, and introducing the reinforcing hole into the secondary drilling hole; (f) after pouring concrete into the secondary perforation hole including the hollow portion for drawing, drawing a secondary casing; characterized in that the construction including.

또한, 상기 (b)단계에서 중첩경계용 가이드부재는 그 길이방향으로 직경에 해당하는 반경을 갖는 원호형의 단면을 갖는 것을 특징으로 한다.In addition, in the step (b), the guide member for overlapping boundary is characterized in that it has an arc-shaped cross section having a radius corresponding to the diameter in the longitudinal direction.

또한, 상기 (b)단계에서 중첩경계용 가이드부재는 스페이서를 매개로 철근망 또는 H빔에 연결되어 있는 것을 특징으로 한다.In addition, in the step (b), the guide member for overlapping boundary is characterized in that connected to the rebar network or H beam via a spacer.

또한, 상기 (a)단계에서 1차 케이싱의 근입 수직도를 맞추기 위해 가이드 빔 유닛을 사용하되, 상기 가이드 빔 유닛은, 직경에 해당하는 이격거리를 갖고 서로 나란하게 수평 배치된 한 쌍의 수평 H빔과; 한 쌍의 수평 H빔의 각기 하면에 길이 방향으로 직경에 해당하는 이격거리를 갖고 일정 간격마다 접합되어 있는 수직 H빔과; 한 쌍의 수평 H빔의 사이에 일정 간격마다 수직방향으로 배치되어 수직 H빔에 접합되어 직경에 외접하는 사각영역을 형성시키는 가이드 격판;을 포함하여 제작된 것을 특징으로 한다.In addition, in step (a), a guide beam unit is used to adjust the incidence perpendicularity of the primary casing, wherein the guide beam unit has a distance H corresponding to a diameter and a pair of horizontal H arranged horizontally next to each other. Beams; Vertical H beams which are bonded at regular intervals on a lower surface of each of the pair of horizontal H beams with a distance corresponding to a diameter in a longitudinal direction; And a guide diaphragm disposed in a vertical direction at regular intervals between the pair of horizontal H beams to be joined to the vertical H beams to form a rectangular area circumscribed in diameter.

본 발명의 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법에 따르면, 1차 현장 말뚝에 중첩경계용 가이드부재를 적용하여 차수용 중공부를 둔 후 2차 현장 말뚝에 차수용 중공부를 포함하여 콘크리트가 타설되도록 함으로써 차수가 확실해질 뿐만 아니라 종래와 달리 별도의 차수 단계를 가질 필요가 없어지게 된다. 또한, 1차 말뚝과 2차 말뚝간의 간격이 좁아져 더 조밀해진 배열을 갖게 됨으로써 흙막이 벽체의 강성이 증대된다. 또한, 흙막이 벽체의 강성이 증대되므로 철근망의 철근량을 절감시킬 수 있다. 또한 1차 말뚝과 2차 말뚝에 사용하는 케이싱 굴착 장비를 모두 동일하게 사용할 수 있어 시공이 간편해진다.According to the construction method of the retaining wall using the order-type column-type cast-in-placement pile of the present invention, after applying the overlapping guide member to the primary field piles, the hollow portion for the order is placed, and then the secondary field piles include the hollow portion for the secondary field piles. By allowing concrete to be poured, not only the order is assured, but also unlike the prior art, there is no need to have a separate order step. In addition, the gap between the primary pile and the secondary pile is narrowed to have a denser arrangement, thereby increasing the rigidity of the retaining wall. In addition, since the rigidity of the retaining wall is increased, it is possible to reduce the amount of rebar in the rebar network. In addition, the casing excavation equipment used for the primary pile and the secondary pile can be used in the same way, thereby simplifying the construction.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1a의 (가),(나)는 본 공법에 사용되는 철근망에 중첩경계용 가이드부재가 설치된 상태에서의 사시도 및 평면도.
도 1b는 일반적인 철근망으로 일 형태의 사시도.
도 2의 (가),(나)는 본 공법에 사용되는 H빔에 중첩경계용 가이드부재가 설치된 상태에서의 사시도 및 평면도.
도 3 내지 도 8은 본 공법에 따른 순차적인 시공상태도.
도 9 및 도 10은 본 공법에 따른 다양한 실시 형태의 시공상태도.
도 11a 및 도 11b는 본 공법에 적용되는 가이드 빔 유닛의 사용상태도 및 평면도.
The following drawings, which are attached in this specification, illustrate the preferred embodiments of the present invention, and together with the detailed description thereof, serve to further understand the technical spirit of the present invention. It should not be construed as limited.
(A) and (b) of FIG. 1A are a perspective view and a plan view in a state where a superimposed boundary guide member is installed in a rebar network used in the present method.
1B is a perspective view of one form of a general rebar network;
Figure 2 (a), (b) is a perspective view and a plan view in a state where the guide member for overlapping boundary is installed on the H beam used in the present method.
3 to 8 is a sequential construction state diagram according to the present method.
9 and 10 are construction state diagrams of various embodiments according to the present method.
11A and 11B are a state diagram and a plan view of a guide beam unit applied to the present method.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.In the following the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings, but the embodiments presented are exemplary for a clear understanding of the present invention is not limited thereto.

1차 Primary 천공홀Drill hole 시공 Construction

먼저, 도 3과 같이 흙막이 벽체가 시공될 지반(10)에 일정 간격(P)마다 소정의 직경(D)을 갖는 1차 케이싱(101)을 근입하고 주지의 천공장비로 천공을 실시하여 1차 천공홀(11)을 시공한다. 천공장비는 예로 오거가 될 수 있다.First, as shown in FIG. 3, a primary casing 101 having a predetermined diameter D is inserted into the ground 10 on which the earth wall is to be constructed, and then drilled with a well-known drilling equipment. The drilling hole 11 is constructed. The drilling rig can be an auger, for example.

중첩경계용 Overlap boundary 가이드부재를Guide member 갖는  Having 철근망Rebar 설치 install

그 다음, 도 2와 같이 한 쌍의 중첩경계용 가이드부재(30)가 부착된 철근망(20)을 인양하여 1차 천공홀(11)에 인입시켜 놓는다. Next, as shown in FIG. 2, the reinforcing bar network 20 to which the pair of overlap boundary guide members 30 are attached is lifted and introduced into the primary drilling hole 11.

이때 중첩경계용 가이드부재(30)는 그 길이방향으로 직경(D)*1/2에 해당하는 반경(R)을 갖는 원호형의 단면을 갖는 것이 바람직하다. 이때 중첩경계용 가이드부재(30)는 스페이서(32)를 매개로 철근망(20)에 연결된다. 중첩경계용 가이드부재(30)는 합성수지 또는 강판이 될 수 있으나 이러한 재질에 한정되는 것은 아니다. 스페이서(32)는 철근망(20)에 길이 방향으로 일정 간격마다 설치되어 중첩경계용 가이드부재(30)를 철근망(20)에 연결시키는 것으로 특정한 형태나 재질에 한정되는 것은 아니다. At this time, the overlapping guide member 30 preferably has an arc-shaped cross section having a radius R corresponding to the diameter D * 1/2 in the longitudinal direction thereof. At this time, the guide member 30 for overlapping boundary is connected to the rebar network 20 via the spacer 32. The guide member 30 for overlapping boundary may be a synthetic resin or a steel sheet, but is not limited thereto. The spacer 32 is installed at regular intervals in the longitudinal direction in the rebar network 20 to connect the guide member 30 for overlapping boundary to the rebar network 20, but is not limited to a specific shape or material.

철근망(20)은 주철근과 띠철근을 포함하여 제작되며, 주철근은 도 4와 같이 사각으로 배열될 수 있으나 원형으로 배열될 수도 있다.The reinforcing bar 20 is manufactured including the main reinforcing bars and the strip reinforcing bars, and the main reinforcing bars may be arranged in a square as shown in FIG. 4, but may be arranged in a circular shape.

이때 철근망(20)에 대체하여 도 2와 같이 중첩경계용 가이드부재(30)가 부착된 H빔(21)을 사용할 수도 있다. 이때 H빔(21)은 도 10과 같이 흙막이 벽체가 받는 배압을 고려하여 강축방향으로 설치됨이 바람직하다. 이 경우 중첩경계용 가이드부재(30)는 스페이서(32)를 매개로 H빔(21)에 연결된다.At this time, instead of the reinforcing bar 20, as shown in FIG. 2, the H-beam 21 to which the guide member 30 for overlapping is attached may be used. At this time, the H beam 21 is preferably installed in the axial direction in consideration of the back pressure received by the earth wall as shown in FIG. In this case, the guide member 30 for overlapping boundary is connected to the H beam 21 through the spacer 32.

차수용Order 중공부Hollow part 형성 및 1차  Formation and primary 케이싱Casing 인발Drawing

그 다음, 도 5와 같이 1차 천공홀(11)에 콘크리트(100)를 타설한다. 이때 타설된 콘크리트(100)는 철근망(20)과 합성되며 중첩경계용 가이드부재(30)의 외측으로 콘크리트가 타설되지 않은 차수용 중공부(15)가 형성된다.Next, the concrete 100 is poured into the primary drilling hole 11 as shown in FIG. At this time, the poured concrete 100 is synthesized with the reinforcing bar 20 and the outer hollow portion 15 for forming the concrete is not formed on the outside of the guide member 30 for overlapping boundary.

이후, 타설된 콘크리트(100)가 양생되기 전에 1차 케이싱(101)을 인발하여 지반(10)의 외부로 인출해낸다.Thereafter, before the poured concrete 100 is cured, the primary casing 101 is drawn and drawn out of the ground 10.

이같이 하여 1열에 일정 간격마다 중첩경계용 가이드부재(30)가 부착된 철근망(20)이 콘크리트(100)와 합성되어 차수용 중공부(15)를 갖는 1차 말뚝(P1)이 1열로 일정 간격을 두고 시공된다.In this way, the reinforcing bar 20 having the overlapping guide member 30 attached to the overlapping boundary in one row is synthesized with the concrete 100 so that the primary pile P1 having the hollow portion 15 for the order is fixed in one row. Constructed at intervals.

차수용Order 중공부가Hollow section 겹침되는Overlapped 2차  Secondary 천공홀Drill hole 시공 Construction

그 다음, 도 6과 같이 이웃한 1차 천공홀(11과 11)의 사이에 동일한 직경(D)을 갖는 2차 케이싱(102)을 근입하고 주지의 천공장비로 천공을 실시하여 2차 천공홀(12)을 시공한다.Next, as shown in FIG. 6, the secondary casing 102 having the same diameter D is inserted between the adjacent primary drilling holes 11 and 11, and the second drilling hole is drilled with a known drilling equipment. Construct (12).

이때 2차 천공홀(12)은 이웃한 1차 천공홀(11과 11)의 사이에 존재하는 중첩경계용 가이드부재(30)에 의해 형성된 차수용 중공부(15)가 겹침되도록 하여 천공된다. 따라서 2차 천공홀(12)의 중심은 차수용 중공부(15)의 최대 폭만큼 1차 천공홀(11)의 중심에 더 가까이 위치하게 되어 1차 천공홀(11)과 2차 천공홀(12)간의 중심은 차수용 중공부(15)를 갖지 않을 때보다 더 줄어들어 조밀한 배열을 이루게 된다.At this time, the secondary drilling hole 12 is drilled so that the order hollow portion 15 formed by the overlapping guide member 30 existing between the neighboring primary drilling holes 11 and 11 overlaps. Therefore, the center of the secondary boring hole 12 is located closer to the center of the primary boring hole 11 by the maximum width of the hollow portion 15 for the order, so that the primary boring hole 11 and the secondary boring hole ( 12) the center of the liver is reduced more than when not having the hollow portion 15 for the order to achieve a dense arrangement.

일반적인 Normally 철근망Rebar 또는 H빔 설치 Or H beam installation

그 다음, 도 1b와 같이 중첩경계용 가이드부재(30)가 설치되지 않은 철근망(20)을 인양하여 2차 천공홀(12)에 인입시켜 놓는다.Next, as shown in FIG. 1B, the reinforcing bar 20 without the overlapping guide member 30 installed is lifted and drawn into the secondary boring hole 12.

이때 철근망(20)에 대채하여 도 9와 같이 H빔(21)을 사용할 수도 있고, 철근망(20)과 H빔(21)을 교대로 반복하여 설치될 수도 있다.At this time, the H beam 21 may be used as shown in FIG. 9 in relation to the rebar network 20, or the rebar network 20 and the H beam 21 may be alternately installed.

차수용Order 중공부Hollow part 차수 시공 Order construction

그 다음, 도 8과 같이 차수용 중공부(15)를 포함시킨 2차 천공홀(12)에 콘크리트(100)를 타설한 후, 2차 케이싱(102)을 인발하여 2차 말뚝(P2)을 시공한다.Subsequently, after pouring concrete 100 into the secondary drilling hole 12 including the hollow portion 15 for the order as shown in FIG. 8, the secondary casing 102 is pulled out to form the secondary pile P2. Construct

이때 차수용 중공부(15)에도 콘크리트(100)가 타설되어 1,2차 말뚝(P1,P2)간에 차수가 이루어지는 흙막이 벽체의 시공이 완성된다.At this time, the concrete 100 is poured into the hollow portion 15 for the order, so that the construction of the earthquake wall made of the order between the first and second piles P1 and P2 is completed.

이와 같이 시공되는 본 공법은 1차 말뚝(P1)과 2차 말뚝(P2)간의 간격이 좁아져 더 조밀해진 배열을 갖게 됨으로써 흙막이 벽체의 강성이 증대된다. 또한, 흙막이 벽체의 강성이 증대되므로 철근망의 철근량을 절감시킬 수 있다. 또한, 차수용 중공부(15)를 겹침시켜 콘크리트가 타설되어 차수가 확실해질 뿐만 아니라 별도의 차수 단계를 가질 필요가 없어지게 된다. 또한 1차 말뚝(P1)과 2차 말뚝(P2)에 사용하는 케이싱 굴착 장비를 모두 동일하게 사용할 수 있어 시공이 간편해진다.In this construction method constructed as described above, the gap between the primary pile P1 and the secondary pile P2 is narrowed to have a denser arrangement, thereby increasing the rigidity of the retaining wall. In addition, since the rigidity of the retaining wall is increased, it is possible to reduce the amount of rebar in the rebar network. In addition, by overlapping the hollow portion 15 for the order, the concrete is poured, so that the order is assured and there is no need to have a separate order step. In addition, since the casing excavation equipment used for the primary pile (P1) and the secondary pile (P2) can be used in the same way, the construction is simplified.

한편, 본 공법의 1차 천공홀 시공 단계에서 도 11에서와 같이 1차 케이싱(101)의 근입 수직도를 맞추기 위해 가이드 빔 유닛(200)이 사용될 수 있다.On the other hand, the guide beam unit 200 may be used to adjust the indentation perpendicularity of the primary casing 101 as shown in Figure 11 in the primary drilling hole construction step of the present method.

가이드 빔 유닛(200)은 직경(D)에 해당하는 이격거리(L)를 갖고 서로 나란하게 수평 배치된 한 쌍의 수평 H빔(201,201)과, 한 쌍의 수평 H빔(201,201)의 각기 하면에 길이 방향으로 직경(D)에 해당하는 이격거리를 갖고 일정 간격마다 접합되어 있는 수직 H빔(202)과, 한 쌍의 수평 H빔(201,201)의 사이에 일정 간격마다 수직방향으로 배치되어 수직 H빔(201,201)에 접합되어 직경(D)에 외접하는 사각영역을 형성시키는 가이드 격판(203)을 포함하여 제작된다. 이때 수직 H빔(202)은 수직도를 확보하기 위해 1.5m 이상의 깊이로 지반에 묻힐 수 있는 충분한 길이를 갖는 것이 바람직하다.The guide beam unit 200 has a pair of horizontal H beams 201 and 201 and a pair of horizontal H beams 201 and 201 arranged horizontally in parallel with each other with a separation distance L corresponding to the diameter D, respectively. Vertically disposed at regular intervals between the vertical H beam 202 and the pair of horizontal H beams 201 and 201 which are bonded at regular intervals with a separation distance corresponding to the diameter D in the longitudinal direction. It is manufactured by including a guide diaphragm 203 bonded to the H beams 201 and 201 to form a rectangular region circumscribed to the diameter D. At this time, the vertical H-beam 202 preferably has a length sufficient to be buried in the ground to a depth of 1.5m or more to ensure the verticality.

따라서 1차 케이싱(101)의 근입시 한 쌍의 수평 H빔(201,201)과 가이드 격판(203)에 의해 형성된 사각 영역의 둘레가 1차 케이싱(101)의 외주면에 외접하는 형태가 되어 1차 케이싱(101)의 근입시 수직도를 정확히 맞출 수 있다.Accordingly, when the primary casing 101 is moved in and out, the periphery of the rectangular area formed by the pair of horizontal H beams 201 and 201 and the guide diaphragm 203 is circumscribed to the outer circumferential surface of the primary casing 101 so that the primary casing At the time of approaching the 101, the verticality can be accurately adjusted.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. So far, the present invention has been described in detail with reference to the presented embodiments, but those skilled in the art may make various modifications and modifications without departing from the technical spirit of the present invention with reference to the presented embodiments. will be. The invention is not limited by the invention as such variations and modifications but only by the claims appended hereto.

11: 1차 천공홀
12: 2차 천공홀
20: 철근망
30: 중첩경계용 가이드부재
32: 스페이서
101: 1차 케이싱
102: 2차 케이싱
200: 가이드 빔 유닛
11: 1st drilling hole
12: secondary drilling hole
20: rebar
30: overlapping guide member
32: spacer
101: primary casing
102: secondary casing
200: guide beam unit

Claims (4)

(a) 흙막이 벽체가 시공될 지반(10)에 일정 간격(P)마다 소정의 직경(D)을 갖는 1차 케이싱(101)을 근입하고 천공을 실시하여 1차 천공홀(11)을 시공하는 단계와;
(b) 한 쌍의 합성수지재 원호형 단면의 중첩경계용 가이드부재(30)가 스페이서(32)를 매개로 각기 부착된 철근망(20)이나 H빔(21)을 인양하여 1차 천공홀(11)에 인입시켜 놓는 단계와;
(c) 1차 천공홀(11)에 콘크리트를 타설하여 중첩경계용 가이드부재(30)의 외측으로 콘크리트가 타설되지 않은 차수용 중공부(15)를 형성시킨 후, 1차 케이싱(101)을 인발하는 단계와;
(d) 이웃한 1차 천공홀(11과 11)의 사이에 존재하는 중첩경계용 가이드부재(30)에 의해 형성된 차수용 중공부(15)가 겹침되도록 하여 동일한 직경(D)을 갖는 2차 케이싱(102)을 근입하고 천공을 실시하여 2차 천공홀(12)을 시공하는 단계와;
(e) 중첩경계용 가이드부재(30)가 설치되지 않은 철근망(20)이나 H빔(21)을 인양하여 2차 천공홀(12)에 인입시켜 놓는 단계와;
(f) 차수용 중공부(15)를 포함시킨 2차 천공홀(12)에 콘크리트를 타설한 후, 2차 케이싱(102)을 인발하는 단계;를 포함하여 시공되는 것을 특징으로 하는 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법.
(a) The primary casing (101) having a predetermined diameter (D) at a predetermined interval (P) in the ground (10) where the earth wall is to be built in and drills to construct the primary drilling hole (11) Steps;
(b) A pair of synthetic resin guides 30 having an arc-shaped cross-section overlaps the reinforcing bar 20 or the H beam 21 attached to each other via a spacer 32 to form a primary hole. 11) introducing into;
(c) After the concrete is poured into the primary drilling hole 11 to form the hollow portion 15 for the non-concrete order on the outside of the guide member 30 for overlapping boundary, the primary casing 101 is opened. Drawing;
(d) the secondary having the same diameter (D) so that the order hollow portion 15 formed by the overlap boundary guide member 30 existing between the adjacent primary drilling holes 11 and 11 overlaps. Accessing the casing 102 and drilling to construct a secondary drilling hole 12;
(e) lifting the reinforcing bar 20 or H beam 21 in which the guide member 30 for overlapping boundary is not installed and drawing it into the secondary drilling hole 12;
(f) pouring concrete into the secondary drilling hole 12 including the hollow portion 15 for the order, and drawing the secondary casing 102; Construction method of retaining wall using thermal cast-in-placement pile.
제 1항에 있어서,
상기 (b)단계에서 중첩경계용 가이드부재(30)는 그 길이방향으로 직경(D)*1/2에 해당하는 반경(R)을 갖는 원호형의 단면을 갖는 것을 특징으로 하는 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법.
The method of claim 1,
In the step (b), the overlapping guide member 30 has a circular type cross section having an arc-shaped cross section having a radius (R) corresponding to the diameter (D) * 1/2 in the longitudinal direction Method of constructing the retaining wall using the cast-in-placement pile.
삭제delete 제 1항에 있어서,
상기 (a)단계에서 1차 케이싱(101)의 근입 수직도를 맞추기 위해 가이드 빔 유닛(200)을 사용하되,
상기 가이드 빔 유닛(200)은,
직경(D)에 해당하는 이격거리를 갖고 서로 나란하게 수평 배치된 한 쌍의 수평 H빔(201,201)과;
한 쌍의 수평 H빔(201,201)의 각기 하면에 길이 방향으로 직경(D)에 해당하는 이격거리를 갖고 일정 간격마다 접합되어 있는 수직 H빔(202)과;
한 쌍의 수평 H빔(201,201)의 사이에 일정 간격마다 수직방향으로 배치되어 수직 H빔(201,201)에 접합되어 직경(D)에 외접하는 사각영역을 형성시키는 가이드 격판(203);을 포함하여 제작된 것을 특징으로 하는 차수형 주열식 현장타설 말뚝을 이용한 흙막이 벽체의 시공방법.
The method of claim 1,
In the step (a) to use the guide beam unit 200 to adjust the vertical proximity of the primary casing 101,
The guide beam unit 200,
A pair of horizontal H beams 201 and 201 arranged horizontally parallel to each other with a separation distance corresponding to the diameter D;
Vertical H beams 202 joined to the lower surfaces of the pair of horizontal H beams 201 and 201 at regular intervals with a distance corresponding to the diameter D in the longitudinal direction;
A guide diaphragm 203 disposed in the vertical direction at regular intervals between the pair of horizontal H beams 201 and 201 and joined to the vertical H beams 201 and 201 to form a rectangular area circumscribed to the diameter D. Construction method of the retaining wall using the order-type column-type cast-in-placement pile, characterized in that produced.
KR1020170070994A 2017-06-07 2017-06-07 Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type KR102009077B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170070994A KR102009077B1 (en) 2017-06-07 2017-06-07 Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170070994A KR102009077B1 (en) 2017-06-07 2017-06-07 Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type

Publications (2)

Publication Number Publication Date
KR20180133748A KR20180133748A (en) 2018-12-17
KR102009077B1 true KR102009077B1 (en) 2019-08-08

Family

ID=65007522

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170070994A KR102009077B1 (en) 2017-06-07 2017-06-07 Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type

Country Status (1)

Country Link
KR (1) KR102009077B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102317138B1 (en) 2020-08-28 2021-10-25 주식회사 와이앤피기술 Construction method of cast in place concrete pile for retaining wall
KR102321410B1 (en) * 2020-10-08 2021-11-02 이창호 Method for constructing earth retaining wall

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109322313B (en) * 2018-11-12 2019-03-29 上海建工集团股份有限公司 Foundation pit enclosure structure system and its construction method
KR102325623B1 (en) * 2021-02-17 2021-11-15 (주)서아건설 Construction method of retaining wall
KR102640241B1 (en) * 2022-01-13 2024-02-22 오용환 Ground reinforcement and retaining wall construction method using the same
KR102551842B1 (en) * 2022-01-28 2023-07-05 (주)원준테크 Wall structure construction method with top-down construction using cast in place piles

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000319881A (en) * 1999-05-12 2000-11-21 Fumio Hoshi Method for continuous lap drilling by leader auger machine and device used therefor
KR101025179B1 (en) * 2008-12-19 2011-03-31 코오롱건설주식회사 Reinforcement assembly and c.i.p. construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100752397B1 (en) 2006-02-13 2007-08-28 홍지기술산업주식회사 Construction method for underground watertight wall and subsidiary casing used in the same
KR100927186B1 (en) 2009-03-24 2009-11-18 이규철 Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
KR20100124234A (en) * 2010-11-06 2010-11-26 정동욱 The construction method of continuous pile walls using guide wing in under ground
KR101481810B1 (en) * 2013-03-14 2015-01-12 김연태 Method for construction of constinuous overlap pile wall using the double casing for construction of constinuous overlap pile wall
KR101590032B1 (en) 2015-02-12 2016-01-29 주식회사 대산시빌테크날러지 Column wall using pile and structure construction method therewith

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000319881A (en) * 1999-05-12 2000-11-21 Fumio Hoshi Method for continuous lap drilling by leader auger machine and device used therefor
KR101025179B1 (en) * 2008-12-19 2011-03-31 코오롱건설주식회사 Reinforcement assembly and c.i.p. construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102317138B1 (en) 2020-08-28 2021-10-25 주식회사 와이앤피기술 Construction method of cast in place concrete pile for retaining wall
KR102321410B1 (en) * 2020-10-08 2021-11-02 이창호 Method for constructing earth retaining wall

Also Published As

Publication number Publication date
KR20180133748A (en) 2018-12-17

Similar Documents

Publication Publication Date Title
KR102009077B1 (en) Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
KR102159832B1 (en) Construction method of basic construction of buildings
KR20200098362A (en) tunnel shaft and Construction Method forstructures according to the excavation.
KR102248187B1 (en) Cast-in-place pile using reinforced grouting and construction method
KR20140055639A (en) A execution method of architecture beam
KR101901392B1 (en) A Micropile and Retaining Wall Method by using Micropile
KR101041274B1 (en) Retaining wall grouting structure and method for constructing thereof
KR20160088059A (en) CFT pile Construction Method and the Shoring Method using the same file
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR102097919B1 (en) Melioration wall and replacement wall mixed retaining wall construction method
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR100803921B1 (en) Pit working method forr undergrund floor railroad operation of elevator
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
KR102317138B1 (en) Construction method of cast in place concrete pile for retaining wall
KR101567422B1 (en) Vertical structure construction method for vertical and horizontal regid connection
KR100849226B1 (en) C.i.p temporary wall and method for constructing thereof
JP2000352296A (en) Method o constructing passage just under underground structure
KR101974826B1 (en) The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
JP7057726B2 (en) How to form underground space and how to use underground space

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right