JP2018009371A - Deck slab replacement method for steel composite girder - Google Patents
Deck slab replacement method for steel composite girder Download PDFInfo
- Publication number
- JP2018009371A JP2018009371A JP2016139117A JP2016139117A JP2018009371A JP 2018009371 A JP2018009371 A JP 2018009371A JP 2016139117 A JP2016139117 A JP 2016139117A JP 2016139117 A JP2016139117 A JP 2016139117A JP 2018009371 A JP2018009371 A JP 2018009371A
- Authority
- JP
- Japan
- Prior art keywords
- floor slab
- steel
- girder
- slab
- deck slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 103
- 239000010959 steel Substances 0.000 title claims abstract description 103
- 238000000034 method Methods 0.000 title claims abstract description 86
- 239000002131 composite material Substances 0.000 title claims abstract description 32
- 239000004567 concrete Substances 0.000 claims abstract description 62
- 230000002787 reinforcement Effects 0.000 claims abstract description 16
- 230000003014 reinforcing effect Effects 0.000 claims description 60
- 238000005304 joining Methods 0.000 claims description 14
- 230000015572 biosynthetic process Effects 0.000 claims description 7
- 238000003786 synthesis reaction Methods 0.000 claims description 7
- 239000000203 mixture Substances 0.000 abstract 3
- 238000009434 installation Methods 0.000 abstract 2
- 238000010276 construction Methods 0.000 description 6
- 238000011900 installation process Methods 0.000 description 5
- 230000002265 prevention Effects 0.000 description 5
- 238000005452 bending Methods 0.000 description 3
- 239000000945 filler Substances 0.000 description 3
- 230000002194 synthesizing effect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 239000010426 asphalt Substances 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 229910003460 diamond Inorganic materials 0.000 description 1
- 239000010432 diamond Substances 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 102220042703 rs147727753 Human genes 0.000 description 1
- 238000007790 scraping Methods 0.000 description 1
- 239000010935 stainless steel Substances 0.000 description 1
- 239000003351 stiffener Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Abstract
Description
本発明は、鋼合成桁の床版取替工法に関し、詳しくは、鋼合成桁の床版をプレキャストPC床版に取り替える鋼合成桁の床版取替工法に関する。 The present invention relates to a steel composite girder floor slab replacement method, and more particularly to a steel composite girder floor slab replacement method in which a steel composite girder floor slab is replaced with a precast PC floor slab.
従来、このような鋼合成桁の床版取替工法において、鋼合成桁の床版をプレキャストPC床版等に取り替えることが行われている。例えば、特許文献1には、合成桁の床版をプレキャスト床版で取り替える場合、既設の合成桁の床版を撤去し、プレキャスト床版を架設する際の桁とプレキャスト床版を合成する前に生じる主桁の横倒れを防止するとともに既存の防止対策における欠点を除去することを目的として、プレキャスト床版に形成した箱抜き部を主桁の上フランジ上に位置させて載置し、主桁方向の箱抜き部間を固定点間距離とし、箱抜き部でプレキャスト床版と主桁とを仮固定し、プレキャスト床版の架設完了後に固定を解除して箱抜き部にコンクリートを打設する主桁横倒れ座屈の防止工法が開示されている(特許文献1の請求項1、明細書の段落[0008]〜[0010]、図面の図1、図9等参照)。 Conventionally, in such a steel composite girder floor slab replacement method, a steel composite girder floor slab is replaced with a precast PC floor slab or the like. For example, in Patent Document 1, when replacing a composite slab floor slab with a precast floor slab, remove the existing composite girder floor slab and synthesize the precast floor slab before synthesizing the precast floor slab. The main girder is placed with the box opening formed on the precast floor slab positioned on the upper flange of the main girder in order to prevent the main girder from falling down and to eliminate the disadvantages of existing prevention measures. Set the distance between the boxed parts in the direction to the distance between the fixed points, temporarily fix the precast floor slab and main girder at the boxed part, and release the fixation after the precast floor slab is installed and place concrete in the boxed part The main girder lateral buckling prevention construction method is disclosed (see claim 1 of Patent Document 1, paragraphs [0008] to [0010] of the specification, FIG. 1 of FIG. 1, FIG. 9 and the like).
しかし、特許文献1に記載された主桁横倒れ座屈の防止工法のように、鋼合成桁の床版取替工法において、鋼合成桁の床版をプレキャストPC床版に取り替える場合、鋼桁とプレキャストPC床版とを一体化して合成する必要があるため、鋼桁とPC床版を繋ぐスタッドジベル(以下、単にスタッドという。)が多数必要となっていた。このため、結果的に、そのスタッド用のPC床版の孔が多くなり、図10に示すように、プレストレスを付与するPC鋼材の配置が困難となるという問題があった。 However, when the steel composite girder floor slab is replaced with the precast PC floor slab in the steel composite girder floor slab replacement method, as in the main girder lateral buckling prevention method described in Patent Document 1, the steel girder And a precast PC floor slab need to be integrated and synthesized, so a large number of stud gibels (hereinafter simply referred to as studs) connecting the steel girder and the PC floor slab are required. For this reason, as a result, the hole of the PC floor slab for the stud increases, and as shown in FIG. 10, there is a problem that it is difficult to arrange the PC steel material to which prestress is applied.
そこで、鋼桁に補強部材(鋼部材)を追加することで、鋼桁とPC床版の非合成化を行って、スタッド本数を少なくし、前記問題を解決することも行われている。しかし、非合成化を床版撤去前に行うと、非合成化のために鋼桁に追加する補強部材に、床版が撤去されて軽くなる分撓んだ鋼桁が元に戻ろうとして鋼桁に応力が作用する(図6参照)。この応力は、本来取替作業完了時に有利な応力であるが、床版撤去前に補強部材を追加すると、追加する補強部材にもこの応力が作用して阻害されるだけでなく、その応力にも対抗できるようにするため必要以上に補強部材の寸法が大きくなってしまうという問題があった。 Therefore, by adding a reinforcing member (steel member) to the steel girder, the steel girder and the PC slab are not synthesized to reduce the number of studs and solve the above problem. However, if non-synthesizing is performed before the floor slab is removed, the steel girder will be returned to the reinforcing member added to the steel girder for non-synthesizing. Stress acts on the girders (see FIG. 6). This stress is inherently advantageous when the replacement work is completed, but if a reinforcing member is added before the floor slab is removed, this stress acts on the additional reinforcing member and is not only obstructed, but the stress is also reduced. However, there is a problem that the size of the reinforcing member becomes larger than necessary in order to be able to compete.
そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、鋼合成桁の床版取替の際に非合成化のために追加する補強部材の寸法を極力小さくすることができ、且つ、床版の撤去時の揚重作業にも支障のない鋼合成桁の床版取替工法を提供することにある。 Therefore, the present invention has been devised in view of the above-mentioned problems, and the object of the present invention is to measure the size of a reinforcing member to be added for non-synthesis when replacing a steel slab floor slab. It is an object of the present invention to provide a method of replacing a steel slab floor slab that can be made as small as possible and that does not interfere with the lifting work when the slab is removed.
第1発明に係る鋼合成桁の床版取替工法は、鋼桁とコンクート床版とが一体となった鋼合成桁の既設コンクート床版をプレキャスト床版に取り替える鋼合成桁の床版取替工法であって、前記既設コンクリート床版を撤去する前に、非合成化するために追加して補強する補強部材を前記鋼桁に取り付ける補強部材取付工程と、前記既設コンクリート床版を解体撤去する床版撤去工程と、前記床版撤去工程後に、前記補強部材を締め付けるボルトなどの接合部材の全部又は一部を、緩めるか又は一旦撤去する緊結緩和工程と、を有し、一旦緩め又は撤去した前記接合部材を再度締め付けた後、前記プレキャスト床版を前記鋼桁に載置することを特徴とする。 The steel composite girder floor slab replacement method according to the first aspect of the present invention is a steel composite girder floor slab replacement in which an existing concrete floor slab of a steel composite girder integrated with a steel girder and a concrete floor slab is replaced with a precast floor slab. Before removing the existing concrete slab, it is a construction method, a reinforcing member attaching step for attaching a reinforcing member to be added and reinforced for non-synthesis to the steel girder, and dismantling and removing the existing concrete slab A floor slab removing step, and after the floor slab removing step, all or a part of a joining member such as a bolt for tightening the reinforcing member is loosened or once loosened, and once loosened or removed. After the joint member is tightened again, the precast slab is placed on the steel beam.
第2発明に係る床版取替工法は、第1発明において、前記床版撤去工程では、前記補強部材取付工程で前記補強部材を取り付けた前記鋼桁上にクレーンなどの揚重機を載置して前記既設コンクリート床版を撤去することを特徴とする。 In the floor slab replacement method according to the second invention, in the first invention, in the floor slab removal step, a lifting machine such as a crane is placed on the steel girder to which the reinforcing member is attached in the reinforcing member attaching step. And removing the existing concrete slab.
第3発明に係る床版取替工法は、第1発明又は第2発明において、前記プレキャスト床版は、予めプレストレスが付与されたプレテンション方式のプレキャストPC床版であることを特徴とする。 The floor slab replacement method according to a third aspect of the present invention is characterized in that, in the first aspect or the second aspect, the precast floor slab is a pre-tensioned precast PC floor slab pre-stressed.
第1発明〜第3発明によれば、補強部材を締め付ける接合部材の全部又は一部を、緩めるか又は一旦撤去する緊結緩和工程を有するので、鋼合成桁の床版取替の際に非合成化のために追加する補強部材の寸法を極力小さくすることができ、床版の取替コストを低減することができる。また、既設コンクリート床版を撤去する前に、補強部材を鋼桁に取り付ける補強部材取付工程を行うので、床版の撤去時の揚重作業にも支障がない。 According to the first to third inventions, since there is a tightening relaxation process in which all or a part of the joining member for tightening the reinforcing member is loosened or temporarily removed, the non-synthetic process is performed when the steel composite girder is replaced. Therefore, the size of the reinforcing member to be added for the purpose of reduction can be reduced as much as possible, and the replacement cost of the floor slab can be reduced. Moreover, since the reinforcement member attachment process which attaches a reinforcement member to a steel girder is performed before removing an existing concrete floor slab, there is no problem also in the lifting work at the time of removal of a floor slab.
特に、第2発明によれば、補強部材を取り付けた鋼桁上に揚重機を設置して床版撤去工程を行うことができる。このため、安全に短時間で床版の撤去作業を行うことができるとともに、床版撤去作業に用いる揚重機のサイズを小さいものとすることができ、床版撤去作業のコストダウンを図ることができる。また、橋梁下に揚重機を設置できない環境下の橋梁でも床版の撤去作業を行うことができる。 In particular, according to the second invention, it is possible to perform a floor slab removal step by installing a lifting machine on a steel beam to which a reinforcing member is attached. For this reason, it is possible to safely remove the slab in a short time and to reduce the size of the lifting machine used for the slab removal work, thereby reducing the cost of the slab removal work. it can. In addition, the floor slab can be removed even in an environment where a lifting machine cannot be installed under the bridge.
特に、第3発明によれば、取り替える新設床版を大型のものとすることができ、床版の取替作業を短時間で行うことができ、さらに、床版撤去作業のコストダウンを図ることができる。 In particular, according to the third invention, the new floor slab to be replaced can be made large, the replacement work of the floor slab can be performed in a short time, and the cost of the floor slab removal work can be reduced. Can do.
以下、本発明に係る床版取替工法を実施するための一実施形態について、図面を参照しながら詳細に説明する。 Hereinafter, an embodiment for carrying out a floor slab replacement method according to the present invention will be described in detail with reference to the drawings.
図1〜図9を用いて、本発明の実施形態に係る床版取替工法について説明する。図1は、本発明の実施形態に係る床版取替工法の各工程を示すフローチャートである。図1に示すように、本実施形態に係る床版取替工法は、(1)〜(6)の各工程を行って、鋼桁とコンクート床版とが一体となった鋼合成桁の既設コンクート床版をプレキャスト床版に取り替える工法である。次に、実施形態に係る床版取替工法の各工程について説明する。 The floor slab replacement method according to the embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a flowchart showing each step of a floor slab replacement method according to an embodiment of the present invention. As shown in FIG. 1, the floor slab replacement method according to the present embodiment is an existing steel composite girder in which a steel girder and a concrete floor slab are integrated by performing the steps (1) to (6). This method replaces the concrete slab with a precast slab. Next, each process of the floor slab replacement method according to the embodiment will be described.
先ず、取替作業を行う前の既存の鋼合成桁について簡単に説明する。図2は、本実施形態に係る床版取替工法で取替作業を行う前の既存の鋼合成桁を橋軸方向に直交する鉛直断面で切断した状態を示す鉛直断面図である。図示する鋼合成桁1は、主桁である鋼桁G1と、鉄筋コンクリート製の既設コンクリート床版CSと、から主に構成され、鋼桁G1の上面に溶植されたスタッド(スタッドジベル)SJで鋼桁G1とコンクート床版CSとが一体となった鋼合成桁である。 First, an existing steel composite girder before replacement work will be briefly described. FIG. 2 is a vertical cross-sectional view showing a state in which an existing steel composite girder before being replaced by the floor slab replacement method according to the present embodiment is cut along a vertical cross section perpendicular to the bridge axis direction. The steel composite girder 1 shown in the figure is a stud (stud gibber) SJ mainly composed of a steel girder G1 which is a main girder and an existing concrete floor slab CS made of reinforced concrete, and is implanted on the upper surface of the steel girder G1. A steel composite girder in which a steel girder G1 and a concrete floor slab CS are integrated.
この鋼桁G1は、所定寸法の厚板鋼板同士を溶接して組み立てたI形断面鋼板であり、上フランジG10と、下フランジG11と、これらを繋ぐウェブG12など、から構成されている。この上フランジG10は、既設コンクリート床版CSと一体として算定されるため、一般的には、下フランジG11より幅が小さいものとなっている。 This steel girder G1 is an I-shaped cross-section steel plate assembled by welding thick steel plates having predetermined dimensions, and includes an upper flange G10, a lower flange G11, and a web G12 connecting these. Since this upper flange G10 is calculated as an integral part of the existing concrete floor slab CS, it is generally smaller in width than the lower flange G11.
また、鋼桁G1と既設コンクリート床版CSとを非合成化を図る際には、鋼桁G1は、上フランジG10が既設コンクリート床版CSと別体として算定されても鋼桁G1の撓みが所定値以下となるようにしなければならない。このため、鋼桁G1の上部には、剛性を上げる補剛材として追加・補強する後述の補強部材L1が取り付けられる。 Further, when the steel girder G1 and the existing concrete floor slab CS are not synthesized, the steel girder G1 is bent even if the upper flange G10 is calculated as a separate body from the existing concrete floor slab CS. Must be less than or equal to a predetermined value. For this reason, the below-mentioned reinforcement member L1 added and reinforced as a stiffener which raises rigidity is attached to the upper part of the steel beam G1.
(1)補強部材取付工程
図3は、本実施形態に係る床版取替工法の(1)補強部材取付工程を示す工程説明図であり、図2と同様の鉛直断面で示している。図3に示すように、本実施形態に係る床版取替工法では、先ず、非合成化するために追加・補強する補強部材L1,L1を鋼桁G1に取り付ける補強部材取付工程を行う。
(1) Reinforcing member attaching step FIG. 3 is a process explanatory view showing the (1) reinforcing member attaching step of the floor slab replacement method according to this embodiment, and shows a vertical section similar to FIG. As shown in FIG. 3, in the floor slab replacement method according to the present embodiment, first, a reinforcing member attaching step for attaching the reinforcing members L1 and L1 to be added and reinforced for non-synthesis to the steel beam G1 is performed.
具体的には、既存の鋼桁G1のウェブG12の上部に、ボルト挿通用のボルト孔(例えば、直径24mm)を穿孔する。その後、補強部材L1をウェブG12の上部の取付位置にあてがって、上フランジG10の下面と補強部材L1の上面とが所定距離離間した状態で、接合部材である図示しない高力ボルト(例えば、トルシア形高力ボルトTCB M22(S10T))で補強部材L1をウェブG12にボルト接合(摩擦接合)する。 Specifically, a bolt hole (for example, a diameter of 24 mm) for inserting a bolt is drilled in the upper part of the web G12 of the existing steel girder G1. Thereafter, the reinforcing member L1 is applied to the mounting position of the upper portion of the web G12, and a high-strength bolt (not shown) which is a joining member (for example, torcia) in a state where the lower surface of the upper flange G10 and the upper surface of the reinforcing member L1 are separated by a predetermined distance The reinforcing member L1 is bolted (friction bonded) to the web G12 with a high-strength bolt TCB M22 (S10T).
上フランジG10の下面と補強部材L1の上面とを所定距離離間させているのは、防錆塗装等を施すためである。このため、耐食性鋼板から補強部材を作成するなど、防錆処理上、間隔を空けておく必要がない場合は、上フランジG10の下面と補強部材L1の上面とを接触させて設置しても何ら問題はない。 The reason why the lower surface of the upper flange G10 and the upper surface of the reinforcing member L1 are separated from each other by a predetermined distance is to apply rust prevention coating or the like. For this reason, when it is not necessary to keep a space | interval on rust prevention processing, such as creating a reinforcement member from a corrosion-resistant steel plate, even if it installs by making the lower surface of upper flange G10 and the upper surface of the reinforcement member L1 contact, No problem.
また、補強する補強部材L1の寸法等は、構造計算により算出、決定されるものであるが、図示形態は、ウェブG12の左右両側に2条のL−250×250×25の等辺山形鋼を取り付ける場合を例示している。 In addition, the dimensions and the like of the reinforcing member L1 to be reinforced are calculated and determined by structural calculation. In the illustrated embodiment, two L-250 × 250 × 25 equilateral angle steels are provided on the left and right sides of the web G12. The case where it attaches is illustrated.
なお、構造計算の結果によっては、補強部材は、ウェブG12の上部の左右両側に設ける補強部材L1に加え、図4に示すように、鋼桁G1のウェブG12の下部の両側に補強部材L2,L2を設けても構わない。 Depending on the result of the structural calculation, in addition to the reinforcing members L1 provided on the left and right sides of the upper portion of the web G12, the reinforcing members may be provided on both sides of the lower portion of the web G12 of the steel girder G1 as shown in FIG. L2 may be provided.
(2)床版撤去工程
次に、本実施形態に係る床版取替工法では、既設コンクリート床版を解体撤去する床版撤去工程を行う。図5は、本実施形態に係る床版取替工法の(2)床版撤去工程を示す工程説明図であり、図2と同様の鉛直断面で示している。
(2) Floor slab removal process Next, in the floor slab replacement method according to this embodiment, a floor slab removal process for dismantling and removing an existing concrete floor slab is performed. FIG. 5 is a process explanatory view showing the (2) floor slab removal process of the floor slab replacement method according to the present embodiment, and shows a vertical section similar to FIG.
具体的には、コールピックハンマーや油圧ブレーカーなどの斫り機等でスタッドSJの周りのコンクリートを斫り取ったり、スタッドSJを根本から切断したりして、鋼桁G1と既設コンクリート床版CSとを切り離す。そして、ダイヤモンドカッターや斫り機等を用いて、既設コンクリート床版CSを揚重可能な大きさに切断・分割して、撤去する搬出する。 Specifically, the steel girder G1 and the existing concrete floor slab CS are removed by scraping the concrete around the stud SJ with a drilling machine such as a call pick hammer or a hydraulic breaker, or by cutting the stud SJ from the root. And disconnect. Then, the existing concrete floor slab CS is cut / divided into a size capable of being lifted using a diamond cutter, a punching machine, or the like, and removed.
このとき、本実施形態に係る床版取替工法では、本工程前に補強部材取付工程を実行して、既設コンクリート床版CSと切り離した鋼桁G1を既に補強しているので、ラフタークレーン等の既設コンクリート床版CS上を自走可能な揚重装置により、既設コンクリート床版CSの揚重・撤去作業を行うことができる。このため、既設コンクリート床版CSの撤去時の揚重作業が容易で短時間に行うことができる。 At this time, in the floor slab replacement method according to the present embodiment, the reinforcing member attaching step is executed before this step, and the steel girder G1 separated from the existing concrete floor slab CS has already been reinforced. The existing concrete slab CS can be lifted and removed by a lifting device capable of self-propelling on the existing concrete slab CS. For this reason, the lifting work at the time of removal of the existing concrete slab CS is easy and can be performed in a short time.
これに対して、鋼桁G1を補強しないで、既設コンクリート床版CSの撤去作業を行う場合、既設コンクリート床版CS上をクレーンなどの重機が走行すると、床版と切り離して非合成化した鋼桁G1の撓みが大きくなり過ぎて危険であるという問題がある。また、危険であるだけでなく、鋼桁G1の下に支保工を設置する作業を行うなど、鋼桁G1の撓み等の管理をしなければならず、床版の解体・撤去作業に手間が掛かり、費用が嵩むという問題も生じる。 On the other hand, when the existing concrete floor slab CS is removed without reinforcing the steel girder G1, when a heavy machine such as a crane runs on the existing concrete floor slab CS, the steel is separated from the floor slab and made unsynthetic. There is a problem that the bending of the girder G1 becomes too dangerous. Moreover, it is not only dangerous, but it is necessary to manage the bending of the steel girder G1, such as by installing a support under the steel girder G1, and it takes time to dismantle and remove the floor slab. This also raises the problem of increased costs.
図6は、鋼桁G1の橋軸方向に沿った鉛直断面で本工程により既設コンクリート床版CSを撤去した際に発生する応力を示す応力説明図である。図6に示すように、本工程により既設コンクリート床版CSを撤去すると、既設コンクリート床版CSの荷重分下方に撓んでいた鋼桁G1が元の状態に戻ろうとする。このとき、鋼桁G1の上フランジG10には、引張力が作用し、下フランジG11には、圧縮力が作用することとなる。 FIG. 6 is a stress explanatory diagram showing the stress generated when the existing concrete floor slab CS is removed by this process in the vertical cross section along the bridge axis direction of the steel girder G1. As shown in FIG. 6, when the existing concrete slab CS is removed by this process, the steel girder G1 bent downward by the load of the existing concrete slab CS tends to return to the original state. At this time, a tensile force acts on the upper flange G10 of the steel girder G1, and a compressive force acts on the lower flange G11.
本実施形態に係る床版取替工法では、床版撤去工程前に、前述の補強部材取付工程を行う。このため、補強部材L1にも図6に示す応力が作用することとなる。これらの応力は、新設の床版に取り替えた際には、本来、床版を支える上で有利な応力である。しかし、床版撤去工程前に補強部材取付工程を行った場合は、この有利な応力が補強部材L1により阻害されるだけでなく、補強部材L1は、この応力にも対抗し得る設計としなければならない。 In the floor slab replacement method according to this embodiment, the above-described reinforcing member attaching step is performed before the floor slab removing step. For this reason, the stress shown in FIG. 6 also acts on the reinforcing member L1. These stresses are inherently advantageous in supporting the floor slab when it is replaced with a new floor slab. However, when the reinforcing member attaching step is performed before the floor slab removing step, this advantageous stress is not only hindered by the reinforcing member L1, but the reinforcing member L1 must be designed to resist this stress. Don't be.
したがって、床版撤去工程前に取り付ける補強部材L1は、床版撤去工程後に補強部材を取り付ける場合の設計よりかなり大きな寸法としなければならないという問題があった。図7は、床版撤去前後で補強を行った場合の補強部材の寸法の違いを比較して示す図である。勿論、補強部材は、橋梁の大きさや条件等で適宜定められるものであり、単純に比較することはできない。しかし、一例として、図7のa)に示すように、床版撤去工程前に補強を行った場合は、補強部材は、500×50の組立鋼板である必要があるが、床版撤去工程後に補強を行った場合は、b)に示すように、L−250×250×25の等辺山形鋼で済むという計算結果もある。 Therefore, the reinforcing member L1 to be attached before the floor slab removing process has a problem that it must have a size considerably larger than the design when the reinforcing member is attached after the floor slab removing process. FIG. 7 is a diagram showing a comparison of the difference in dimensions of the reinforcing members when the reinforcement is performed before and after the floor slab removal. Of course, the reinforcing member is appropriately determined depending on the size and conditions of the bridge, and cannot simply be compared. However, as an example, as shown in FIG. 7 a), when reinforcement is performed before the floor slab removal step, the reinforcing member needs to be a 500 × 50 assembled steel plate, In the case of reinforcement, there is a calculation result that, as shown in b), an L-250 × 250 × 25 equilateral mountain steel is sufficient.
このように、クレーン等の揚重装置を行うには、床版撤去工程前に補強を行うことが好ましいが、床版撤去工程前に補強を行うか否かで補強部材の必要寸法が大きく違うという二律背反の問題があった。しかし、本願の発明者らは、この問題を次の締付緩和工程を行うことにより解決した。 Thus, in order to perform a lifting device such as a crane, it is preferable to reinforce before the floor slab removal process, but the required size of the reinforcing member varies greatly depending on whether to reinforce before the floor slab removal process. There was a contradiction problem. However, the inventors of the present application solved this problem by performing the following tightening relaxation process.
(3)締付緩和工程
次に、図1に示すように、本実施形態に係る床版取替工法では、補強部材L1を締め付ける接合部材の全部又は一部を緩めるか又は一旦撤去する緊結緩和工程を行う。具体的には、既設コンクリート床版CSが全て撤去され、鋼桁G1に自重以外の荷重が掛かっていない状態で、鋼桁G1に補強部材L1を止め付けている接合部材の全部又は一部を緩める。
(3) Tightening relaxation process Next, as shown in FIG. 1, in the floor slab replacement method according to the present embodiment, all or part of the joining member that tightens the reinforcing member L1 is loosened or temporarily removed. Perform the process. Specifically, all or a part of the joining members that fasten the reinforcing member L1 to the steel girder G1 in a state where the existing concrete floor slab CS is all removed and no load other than its own weight is applied to the steel girder G1. loosen.
前述のように、本実施形態に係る床版取替工法では、接合部材としてトルシア形高力ボルトを使用しているため、緩めたものは再度使用できず廃棄することとなるが、本工程では、補強部材L1が離脱しないように緩めるか、若しくは、一旦、補強部材L1を撤去する。なお、緩めるか撤去する接合部材の範囲は、床版撤去の範囲や補強部材L1や鋼桁G1の長さなど、状況に応じて適宜定めるとよい。 As described above, in the floor slab replacement method according to the present embodiment, the torcia-type high-strength bolt is used as the joining member, so that the loosened bolt cannot be reused and discarded, but in this step Then, the reinforcing member L1 is loosened so as not to be detached, or the reinforcing member L1 is temporarily removed. In addition, the range of the joining member to be loosened or removed may be appropriately determined according to the situation such as the range of floor slab removal and the length of the reinforcing member L1 or the steel beam G1.
本工程を行うことにより、図6に示す応力の作用を補強部材L1で阻害することなく、既設コンクリート床版CSの荷重による鋼桁G1の撓みが解消され、新設床版載荷により鋼桁G1に発生する応力分布の際に有利に働く(図9参照)。 By performing this process, the bending of the steel girder G1 due to the load of the existing concrete floor slab CS is eliminated without hindering the action of the stress shown in FIG. 6 with the reinforcing member L1, and the steel girder G1 is loaded by loading the new floor slab. It works favorably during the stress distribution that occurs (see FIG. 9).
(4)再締付工程
次に、図1に示すように、本実施形態に係る床版取替工法では、前工程で緩めた接合部材を再度、締め付け直す再締付工程を行う。勿論、補強部材L1を撤去した場合や、接合部材としてトルシア形高力ボルトを使用して締め付け直すことができない場合は、新しい接合部材で補強部材L1をウェブG12にボルト接合する。要するに、再締付とは、補強部材L1をウェブG12にボルト接合するのに必要な所定の摩擦接合力を発生させるのに必要な締付力を再度発生させることを意味している。
(4) Re-clamping step Next, as shown in FIG. 1, in the floor slab replacement method according to the present embodiment, a re-clamping step of re-tightening the joint member loosened in the previous step is performed. Of course, when the reinforcing member L1 is removed, or when it is not possible to retighten using the Torcia type high strength bolt as the joining member, the reinforcing member L1 is bolted to the web G12 with a new joining member. In short, the retightening means that the tightening force necessary to generate the predetermined frictional joining force necessary for bolting the reinforcing member L1 to the web G12 is generated again.
(5)PC床版設置工程
次に、図8、図1に示すように、本実施形態に係る床版取替工法では、新設のコンクリート床版CS’を鋼桁G1に載置して所定の位置に据え付けるPC床版設置工程を行う。図8は、本実施形態に係る床版取替工法のPC床版設置工程を示す工程説明図であり、図2と同様の鉛直断面で示している。具体的には、ラフタークレーン等の揚重装置を用いて鋼桁G1の所定の位置に新設のコンクリート床版CS’を架け渡して設置する。
(5) PC floor slab installation process Next, as shown in FIG. 8 and FIG. 1, in the floor slab replacement method according to the present embodiment, a newly installed concrete floor slab CS ′ is placed on a steel girder G1 and predetermined. PC floor slab installation process to be installed at the position. FIG. 8 is a process explanatory view showing a PC floor slab installation process of the floor slab replacement method according to the present embodiment, and is shown by a vertical cross section similar to FIG. Specifically, a new concrete floor slab CS ′ is installed over a predetermined position of the steel beam G1 using a lifting device such as a rough terrain crane.
また、本工程で設置するコンクリート床版CS’は、予めプレストレスが付与されたプレテンション方式のプレキャストPC床版である。よって、コンクリート床版CS’は、プレストレスの作用により、PC鋼材に沿った長手方向に大きなスパンをとった大判のプレキャスト床版とすることができる。このため、本工程で載置するコンクリート床版CS’の吊上げ吊り降ろし回数を削減して本工程の作業時間を短縮することができる。 The concrete floor slab CS 'installed in this step is a pre-tensioned precast PC floor slab pre-stressed. Therefore, the concrete floor slab CS 'can be a large-sized precast floor slab having a large span in the longitudinal direction along the PC steel material due to the action of prestress. For this reason, the working time of this process can be shortened by reducing the number of times the concrete floor slab CS 'placed in this process is lifted and suspended.
勿論、新たに設置するコンクリート床版は、プレテンション、ポストテンション併用のプレキャストPC床版やポストテンション方式のプレキャストPC床版であってもよいことは云うまでもない。要するに、新たに設置するコンクリート床版は、予め工場等で打設されてプレストレスが付与されたプレキャストPC床版であればよい。 Of course, the concrete floor slab to be newly installed may be a precast PC floor slab that uses pre-tension and post-tension, or a post-tension precast PC floor slab. In short, the concrete floor slab to be newly installed may be a precast PC floor slab that has been previously placed in a factory or the like and prestressed.
但し、プレストレスの有無は必須ではなく、設計に応じて、新設するコンクリート床版をプレキャストコンクリート製のPCa床版とすることも可能である。 However, the presence or absence of prestress is not essential, and it is possible to replace the newly installed concrete floor slab with a precast concrete PCa floor slab.
(6)充填材充填工程
次に、図1に示すように、本実施形態に係る床版取替工法では、コンクリート床版CS’のスタッド用の孔であるコッター(図示せず)内に新たなスタッドSJ’を溶植するとともに、その周りをコンクリートや無収縮モルタルなどの充填材を充填する充填材充填工程を行う。
(6) Filler Filling Step Next, as shown in FIG. 1, in the floor slab replacement method according to this embodiment, a new cotter (not shown), which is a hole for a stud of the concrete floor slab CS ′, is newly added. A stud filling step is performed in which a stud SJ ′ is melt-planted and a filler such as concrete or non-shrink mortar is filled therearound.
但し、鋼桁G1とコンクリート床版CS’とは、非合成の設計であるため、コッター及びスタッドの数は、既設コンクリート床版CSと比べて極めて少ないものである。 However, since the steel girder G1 and the concrete floor slab CS 'are non-synthetic designs, the number of cotters and studs is extremely small compared to the existing concrete floor slab CS.
その後、図1に示すように、充填材が硬化するまでの養生期間をとって、コンクリート床版CS’上にアスファルト舗装を施すなど、その他の必要な作業を行って本実施形態に係る床版取替工法の床版取替作業が終了する。 Thereafter, as shown in FIG. 1, a curing period until the filler is hardened is taken, and other necessary operations such as asphalt pavement are performed on the concrete floor slab CS ′ to perform the floor slab according to the present embodiment. The slab replacement work for the replacement method is completed.
以上説明した本実施形態に係る床版取替工法によれば、補強部材L1を締め付ける接合部材の全部又は一部を緩めるか又は一旦撤去する緊結緩和工程を有するので、補強部材L1の寸法を極力小さくすることができ、補強部材L1の製造コストを削減して床版の取替コストを低減することができる。 According to the floor slab replacement method according to the present embodiment described above, since the whole or part of the joining member for fastening the reinforcing member L1 is loosened or temporarily removed, the size of the reinforcing member L1 is reduced as much as possible. The manufacturing cost of the reinforcing member L1 can be reduced, and the replacement cost of the floor slab can be reduced.
また、本実施形態に係る床版取替工法によれば、既設コンクリート床版CSを撤去する前に、補強部材L1を鋼桁G1に取り付けるので、床版の撤去時の揚重作業にも支障がない。つまり、本実施形態に係る床版取替工法によれば、既設コンクリート床版CS上を自走可能なラフタークレーン等の揚重装置で既設コンクリート床版CSの撤去作業を行うことができる。このため、既設コンクリート床版CSの撤去時の揚重作業が安全且つ容易に短時間で行うことができ、この点でも、床版取替のコストを低減することができる。 Moreover, according to the floor slab replacement method according to the present embodiment, the reinforcing member L1 is attached to the steel girder G1 before the existing concrete floor slab CS is removed, which hinders lifting work when the floor slab is removed. There is no. That is, according to the floor slab replacement method according to the present embodiment, the existing concrete floor slab CS can be removed with a lifting device such as a rough terrain crane that can self-propell on the existing concrete floor slab CS. For this reason, the lifting work at the time of removal of the existing concrete floor slab CS can be performed safely and easily in a short time, and in this respect also, the cost of replacing the floor slab can be reduced.
その上、本実施形態に係る床版取替工法によれば、撤去する既設コンクリート床版CS上を走行して撤去する床版の至近距離まで接近できるので、床版撤去作業に用いる揚重機のサイズを小さいものとすることができ、床版撤去作業のコストダウンを図ることができる。また、橋梁下に揚重機を設置できない環境下の橋梁でも床版の撤去作業を行うことができる。 Moreover, according to the floor slab replacement method according to the present embodiment, it is possible to approach the nearest distance of the floor slab to be removed by running on the existing concrete floor slab CS to be removed. The size can be reduced, and the cost for removing the slab can be reduced. In addition, the floor slab can be removed even in an environment where a lifting machine cannot be installed under the bridge.
それに加え、本実施形態に係る床版取替工法によれば、プレテンション方式のプレキャストPC床版を用いることにより、取り替える新設床版を大型のものとすることができ、床版の取替作業を短時間で行うことができる。これにより、さらに、床版撤去作業のコストダウンを図ることができる。 In addition, according to the floor slab replacement method according to this embodiment, by using a pre-tension type precast PC floor slab, the new floor slab to be replaced can be made large, and the floor slab replacement work Can be performed in a short time. Thereby, the cost reduction of the floor slab removal work can be further achieved.
以上、本実施形態に係る床版取替工法について詳細に説明したが、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ぎず、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。 As mentioned above, although the floor slab replacement method according to the present embodiment has been described in detail, the above-described or illustrated embodiment is merely an embodiment embodied in carrying out the present invention, Therefore, the technical scope of the present invention should not be construed in a limited manner.
G1 :鋼桁(主桁)
G10 :上フランジ
G11 :下フランジ
G12 :ウェブ
CS :既設コンクリート床版
CS’ :新設コンクリート床版
SJ,SJ’ :スタッド
L1,L2 :補強部材
G1: Steel girders (main girders)
G10: Upper flange G11: Lower flange G12: Web CS: Existing concrete floor slab CS ': New concrete floor slab SJ, SJ': Stud L1, L2: Reinforcing member
第1発明に係る鋼合成桁の床版取替工法は、鋼桁とコンクリート床版とが一体となった鋼合成桁の既設コンクリート床版をプレキャスト床版に取り替える鋼合成桁の床版取替工法であって、前記既設コンクリート床版を撤去する前に、非合成化するために追加して補強する補強部材を前記鋼桁に取り付ける補強部材取付工程と、前記既設コンクリート床版を解体撤去する床版撤去工程と、前記床版撤去工程後に、前記補強部材を締め付ける接合部材の全部又は一部を、緩めるか又は一旦撤去する緊結緩和工程と、を有し、一旦緩め又は撤去した前記接合部材を再度締め付けた後、前記プレキャスト床版を前記鋼桁に載置することを特徴とする。 Deck replacement method of steel synthetic girder according to the first invention, the steel synthetic replacing steel girder and concentrated rie preparative slab and has an existing Conc rie preparative slab of steel synthesis digits together in precast slab A slab replacement method for a girder, wherein before the existing concrete slab is removed, a reinforcing member attaching step for attaching a reinforcing member to be added to the steel girder for non-synthesis, and the existing concrete A floor slab removal step of dismantling and removing the floor slab, and a binding relaxation step of loosening or temporarily removing all or part of the joining member that tightens the reinforcing member after the floor slab removal step. Or after fastening the removed said joining member again, the said precast floor slab is mounted in the said steel beam.
図1〜図9を用いて、本発明の実施形態に係る床版取替工法について説明する。図1は、本発明の実施形態に係る床版取替工法の各工程を示すフローチャートである。図1に示すように、本実施形態に係る床版取替工法は、(1)〜(6)の各工程を行って、鋼桁とコンクリート床版とが一体となった鋼合成桁の既設コンクリート床版をプレキャスト床版に取り替える工法である。次に、実施形態に係る床版取替工法の各工程について説明する。 The floor slab replacement method according to the embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a flowchart showing each step of a floor slab replacement method according to an embodiment of the present invention. As shown in FIG. 1, the floor plate replacement method according to the present embodiment, (1) performing the steps of - (6), steel synthesis and steel girder and concentrated rie preparative slab are integrated the existing Conch rie door floor version of the digit is a method to replace the precast slab. Next, each process of the floor slab replacement method according to the embodiment will be described.
先ず、取替作業を行う前の既存の鋼合成桁について簡単に説明する。図2は、本実施形態に係る床版取替工法で取替作業を行う前の既存の鋼合成桁を橋軸方向に直交する鉛直断面で切断した状態を示す鉛直断面図である。図示する鋼合成桁1は、主桁である鋼桁G1と、鉄筋コンクリート製の既設コンクリート床版CSと、から主に構成され、鋼桁G1の上面に溶植されたスタッド(スタッドジベル)SJで鋼桁G1とコンクリート床版CSとが一体となった鋼合成桁である。 First, an existing steel composite girder before replacement work will be briefly described. FIG. 2 is a vertical cross-sectional view showing a state in which an existing steel composite girder before being replaced by the floor slab replacement method according to the present embodiment is cut along a vertical cross section perpendicular to the bridge axis direction. The steel composite girder 1 shown in the figure is a stud (stud gibber) SJ mainly composed of a steel girder G1 which is a main girder and an existing concrete floor slab CS made of reinforced concrete, and is implanted on the upper surface of the steel girder G1. and a steel girder G1 and the Conch rie door deck CS is a steel synthetic digits together.
Claims (3)
前記既設コンクリート床版を撤去する前に、非合成化するために追加して補強する補強部材を前記鋼桁に取り付ける補強部材取付工程と、
前記既設コンクリート床版を解体撤去する床版撤去工程と、
前記床版撤去工程後に、前記補強部材を締め付けるボルトなどの接合部材の全部又は一部を、緩めるか又は一旦撤去する緊結緩和工程と、を有し、
一旦緩め又は撤去した前記接合部材を再度締め付けた後、前記プレキャスト床版を前記鋼桁に載置すること
を特徴とする鋼合成桁の床版取替工法。 A steel composite girder slab replacement method that replaces an existing concrete slab of a steel composite girder in which a steel girder and a concrete floor slab are integrated with a precast floor slab,
Before removing the existing concrete floor slab, a reinforcing member attaching step for attaching a reinforcing member to be added and reinforced for non-synthesis to the steel girder,
A floor slab removal step of dismantling and removing the existing concrete floor slab;
After the floor slab removal step, all or part of a joining member such as a bolt that tightens the reinforcing member is loosened or a binding relaxation step of temporarily removing the bonding member,
A steel composite girder slab replacement method, wherein the joint member once loosened or removed is tightened again, and then the precast slab is placed on the steel girder.
を特徴とする請求項1に記載の鋼合成桁の床版取替工法。 2. The floor slab removal step includes placing a lifting machine such as a crane on the steel girder to which the reinforcement member is attached in the reinforcement member attachment step, and removing the existing concrete floor slab. The steel composite girder floor slab replacement method described in 1.
を特徴とする請求項1又は2に記載の鋼合成桁の床版取替工法。 The method of replacing a steel composite girder slab according to claim 1 or 2, wherein the precast slab is a pre-tensioned precast PC slab pre-stressed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2016139117A JP6053087B1 (en) | 2016-07-14 | 2016-07-14 | Steel composite girder floor slab replacement method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2016139117A JP6053087B1 (en) | 2016-07-14 | 2016-07-14 | Steel composite girder floor slab replacement method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP6053087B1 JP6053087B1 (en) | 2016-12-27 |
JP2018009371A true JP2018009371A (en) | 2018-01-18 |
Family
ID=57582116
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2016139117A Active JP6053087B1 (en) | 2016-07-14 | 2016-07-14 | Steel composite girder floor slab replacement method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6053087B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2021031884A (en) * | 2019-08-20 | 2021-03-01 | Jfeエンジニアリング株式会社 | Bridge upper structure removal method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09256322A (en) * | 1996-03-22 | 1997-09-30 | P S Co Ltd | Reinforcing method of existing steel girder |
JP2003082617A (en) * | 2001-09-13 | 2003-03-19 | Nkk Corp | Reinforcing structure of bridge structure and method for repairing bridge structure |
JP2005273392A (en) * | 2004-03-26 | 2005-10-06 | Oriental Construction Co Ltd | Method of reinforcing bridge using prestressed concrete steel |
JP6180376B2 (en) * | 2014-06-23 | 2017-08-16 | 首都高速道路株式会社 | Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method |
-
2016
- 2016-07-14 JP JP2016139117A patent/JP6053087B1/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2021031884A (en) * | 2019-08-20 | 2021-03-01 | Jfeエンジニアリング株式会社 | Bridge upper structure removal method |
JP7172916B2 (en) | 2019-08-20 | 2022-11-16 | Jfeエンジニアリング株式会社 | Bridge superstructure removal method |
Also Published As
Publication number | Publication date |
---|---|
JP6053087B1 (en) | 2016-12-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6316665B2 (en) | Composite structure of steel girder and precast slab and its construction method | |
US6904636B2 (en) | Deck-to-girder connections for precast or prefabricated bridge decks | |
JP6097965B2 (en) | Construction method of concrete precast slab for bridge | |
JP2014177766A (en) | Method for constructing concrete precast floor slab for bridge | |
JP2012077471A (en) | Joint structure of precast members and concrete precast members | |
JP6771987B2 (en) | Floor slab replacement method for steel synthetic girders and PC floor slab | |
JP6053087B1 (en) | Steel composite girder floor slab replacement method | |
JP2004183232A (en) | Reinforcing method and reinforcement structure of steel structural material of construction structure | |
JP5716117B1 (en) | Hinge reinforcement method and reinforcement structure for existing girder bridge | |
JP6444912B2 (en) | Steel structure reinforcement and repair structure and method | |
JP6642884B2 (en) | Bridge steel deck slab reinforcement structure and bridge steel deck slab reinforcement method | |
JP6969909B2 (en) | How to reinforce steel synthetic girders | |
JP6541520B2 (en) | Renewed construction method of existing road and rebuilt road | |
JP2020063598A (en) | Hinge part reinforcement method and reinforcement structure in hinged girder bridge with pc | |
JP2002266503A (en) | Method for repairing and reinforcing steel structural material for existing building structure and structure | |
JP2010159568A (en) | Structure and method for reinforcing existing simple girder bridge | |
JP7080648B2 (en) | How to erection the bridge girder | |
JP7186670B2 (en) | Concrete floor slab repair method | |
JP4293696B2 (en) | Construction method of composite floor slab bridge | |
JP7010709B2 (en) | How to build prefabricated and concrete structures | |
JP2002332645A (en) | Foundation structure of rail for ground-traveling crane and laying method for foundation | |
JP6845457B1 (en) | How to replace concrete bridges with precast floor slabs | |
KR20210001147U (en) | Shear connector for steel frame structure and bridge structure with the same | |
JP6845456B1 (en) | How to replace concrete bridges with precast floor slabs | |
KR100691847B1 (en) | Prefabricated beams reinforced with connecting steel boxes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20161027 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20161122 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20161125 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6053087 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |