JP6541520B2 - Renewed construction method of existing road and rebuilt road - Google Patents

Renewed construction method of existing road and rebuilt road Download PDF

Info

Publication number
JP6541520B2
JP6541520B2 JP2015176730A JP2015176730A JP6541520B2 JP 6541520 B2 JP6541520 B2 JP 6541520B2 JP 2015176730 A JP2015176730 A JP 2015176730A JP 2015176730 A JP2015176730 A JP 2015176730A JP 6541520 B2 JP6541520 B2 JP 6541520B2
Authority
JP
Japan
Prior art keywords
main girder
road
floor slab
main
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015176730A
Other languages
Japanese (ja)
Other versions
JP2017053117A (en
Inventor
櫻井 信彰
信彰 櫻井
敦郎 大嶽
敦郎 大嶽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Engineering Co Ltd
Original Assignee
Nippon Steel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Engineering Co Ltd filed Critical Nippon Steel Engineering Co Ltd
Priority to JP2015176730A priority Critical patent/JP6541520B2/en
Publication of JP2017053117A publication Critical patent/JP2017053117A/en
Application granted granted Critical
Publication of JP6541520B2 publication Critical patent/JP6541520B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、既設道路の更新施工方法と更新施工された道路に関するものである。   TECHNICAL FIELD The present invention relates to a method of renewing an existing road and a renewed road.

昭和40年代〜50年代にかけて施工された高速道路等の老朽化が顕在化しており、クラック等が入って老朽化した道路の床版を取り換える工事が今後2〜3年ほどで増加することが予測されている。   Deterioration of expressways constructed in the 1940s and 1950s has become apparent, and it is predicted that construction work to replace the floor slabs of roads that are cracked and cracked will increase in the next few years or so It is done.

床版の取り換え工事では少なからず通行止め等の交通規制が余儀なくされ、全国の多くの箇所で交通規制が発生することの社会的影響は計り知れず、工事発注者は通行止め等の交通規制期間を可及的に短縮したいとの思いが強いことは容易に想定される。   In the replacement work of the floor version, traffic regulation such as traffic closure is forced not a little, and the social impact of traffic regulation occurring in many parts of the country is immeasurable, and the contractor of the construction allowed traffic regulation period such as traffic closure It is easily assumed that the desire to shorten as much as possible is strong.

高速道路等の既設道路の構造の代表例を挙げると、二以上の鋼製の主桁上に鉄筋コンクリート製の床版が設置されてその全体が大略構成されている。ここで、主桁の上面にはスタッドジベル等のずれ止めが一般に取り付けられており、鉄筋コンクリート製の床版がずれ止めを埋設した状態で施工され、主桁と床版の一体化が図られている。より具体的には、二以上の主桁を設置後、ずれ止めを巻き込むようにして床版用の鉄筋を配筋し、現場にてコンクリートを打設して鉄筋コンクリート製の床版を施工するものである。   As a representative example of the structure of existing roads such as expressways, reinforced concrete floor slabs are installed on two or more steel main girders, and the whole is roughly configured. Here, a slip stopper such as a stud dowel is generally attached to the upper surface of the main girder, and a reinforced concrete floor slab is constructed in a state where the slip stopper is embedded, and integration of the main girder and the floor slab is achieved There is. More specifically, after installing two or more main girders, rebars for floor slabs are arranged so as to incorporate slip stoppers, concrete is cast at the site, and reinforced concrete floor slabs are constructed. It is.

従来一般の既設道路の更新方法として、床版から上方に突出するずれ止めを露出させるようにして主桁上のコンクリートを斫り、ずれ止めを含む主桁上方を清掃し、新規にずれ止めを設置し、ずれ止めが挿入される孔を下面に備えた新設の床版ブロック(プレキャストブロック)を主桁上に設置し、これを主桁の長手方向に繰り返しおこなうことで所定延長の既設道路を更新する方法が挙げられる。この従来一般の更新方法では、床版の斫り作業に多大な時間を要しており、これが更新施工に要する工期の長期化に繋がっていた。このように工期が長期化する更新施工方法では、上記するように今後増大するであろう更新施工において、工期が可及的に短縮された施工を実現することはできない。   Conventionally, as a general method of updating existing roads, the concrete on the main girder is rolled up to expose the slip stopper protruding upward from the floor slab, the upper side of the main girder including the slip stopper is cleaned, and a new slip stopper is Install a new floor block (precast block) with a hole on the lower surface, into which the slip stopper is inserted, and install it on the main girder, repeating this in the longitudinal direction of the main girder for an existing road with a predetermined extension There is a way to update. In this conventional general renewal method, it takes a lot of time to work on the floor slab, which has led to the extension of the construction period required for renewal construction. As described above, in the renewal construction method in which the construction period is prolonged, in the renewal construction which will increase in the future as described above, the construction in which the construction period is shortened as much as possible can not be realized.

一方、他の更新施工方法として、主桁の上フランジを切断し、床版と上フランジをまとめて撤去する方法があるが、この施工方法では、更新施工に際して主桁の上フランジを溶接やボルト等で接続して主桁の復旧をおこなう必要があり、この復旧施工に時間を要してしまい、交通規制は軽減できても、やはり更新施工に要する工期の長期化に繋がってしまう。   On the other hand, there is a method of cutting the upper flange of the main girder and removing the floor plate and the upper flange together as another renewal construction method. In this construction method, the upper flange of the main girder is welded or bolted at the time of renewal construction. It is necessary to connect by etc. and perform restoration of the main girder, and it takes time for this restoration and construction, and even if traffic regulation can be alleviated, it will also lead to prolongation of the construction period required for renewal construction.

ここで、特許文献1には、床版解体装置の反力を主桁の下フランジで取り、床版解体装置で床版を支持しながら床版の解体をおこなう方法が開示されているが、上記する課題、すなわち、更新施工に要する工期の長期化を抑制できる技術ではない。   Here, Patent Document 1 discloses a method of taking the reaction force of the floor slab disassembling apparatus with the lower flange of the main girder and disassembling the floor slab while supporting the floor slab with the floor slab disassembling apparatus. It is not a technology that can suppress the above-mentioned problem, that is, prolongation of the construction period required for renewal construction.

特開2007−100415号公報Japanese Patent Application Publication No. 2007-100415

本発明は上記する問題に鑑みてなされたものであり、既設道路の更新施工に要する工期の短縮を図ることのできる既設道路の更新施工方法と、この更新施工方法で更新施工された道路を提供することを目的としている。   The present invention has been made in view of the above problems, and provides an existing road renewal construction method capable of shortening the construction period required for renewal construction of the existing road, and a road renewed and constructed by this renewal construction method. The purpose is to

前記目的を達成すべく、本発明による既設道路の更新施工方法は、二以上の鋼製の主桁上に鉄筋コンクリート製の床版が設置されてなる既設道路の更新方法であって、床版のうち、主桁上の部分のみを残置し、他の部分を撤去する第一のステップ、下面に二以上の凹部を備えた新設の床版ブロックを、それぞれの凹部が前記二以上の主桁上の部分に嵌るようにして設置し、この床版ブロックの設置を道路の延伸方向に繰り返す第二のステップからなるものである。   In order to achieve the above object, the method of updating an existing road according to the present invention is a method of updating an existing road in which reinforced concrete floor slabs are installed on two or more steel main girders. Among them, the first step of leaving only the part on the main girder and removing the other part, a new floor slab block provided with two or more recesses on the lower surface, each recess on the two or more main girder And installing the floor slab block in the extending direction of the road.

本発明の既設道路の更新施工方法は、主桁を残し、主桁上にある鉄筋コンクリート製の床版を撤去するに当たり、床版の中で主桁上の部分のみを撤去せずに残し、その他の床版を撤去することに特徴を有する施工方法である。   According to the method of the present invention, the existing road is rebuilt without leaving the main girder and removing the reinforced concrete floor slab above the main girder without removing only the portion on the main girder of the floor slab, and so on. It is a construction method characterized by removing the floor plate of

主桁上の床版を撤去しないことから、主桁の上面から突出して床版内に埋設されているずれ止めを露出させるようにして床版を撤去し、主桁の上面を清掃する際に要する多大な斫り時間を解消することができ、従来の更新施工方法に比して施工時間を大幅に短縮することができる。   Since the floor plate on the main girder is not removed, the floor plate is removed by exposing the slip stopper embedded in the floor plate from the upper surface of the main girder, and when cleaning the upper surface of the main girder It is possible to eliminate a large amount of rolling time that is required, and it is possible to significantly reduce the construction time as compared with the conventional renewal construction method.

本発明の更新施工方法では、二以上の主桁において、床版の主桁上の部分のみを残してそれ以外の床版を撤去した後、プレキャスト製の床版ブロックを各主桁に架け渡すようにして設置する。たとえば、主桁が二本の場合は二本の主桁に床版ブロックが架け渡され、主桁が五本の場合は五本の主桁に床版ブロックが架け渡される。この際、前者の形態では床版ブロックの下面の二箇所に凹部が設けてあり、後者の形態では床版ブロックの下面の五箇所に凹部が設けてある。   In the renewal construction method of the present invention, in two or more main girders, after removing the other decks while leaving only the portion on the main girders of the deck, the precast floor slab block is bridged to each of the main girders To install. For example, in the case of two main girders, a floor slab block is bridged over two main girders, and in the case of five main girders, a floor plank block is bridged over five main girders. Under the present circumstances, the recessed part is provided in two places of the lower surface of a floor slab block in the former form, and the concave part is provided in five places of the lower surface of a floor slab block in the latter form.

ここで、床版ブロックはその下面において各主桁上の部分が嵌り込む凹部を備えており、各主桁上の部分をそれぞれ対応する凹部に嵌め込みながら、二以上の主桁への床版ブロックの設置がおこなわれる。   Here, the floor slab block is provided with a recess on the lower surface thereof into which the portion on each main girder fits, and while the portion on each main girder is fitted into the corresponding recess respectively, the floor slab block to two or more main girder Installation will take place.

このように、二以上の主桁に対し、それぞれの主桁上の部分を対応する凹部に嵌め込みながら床版ブロックが設置されることから、床版ブロックが主桁の側方へずれる惧れはない。   As described above, since the floor slab block is installed while inserting the portions on the respective main girders into the corresponding recesses for two or more main girders, there is a risk that the floor slab blocks will be displaced to the side of the main girders. Absent.

第二のステップでは、この床版ブロックの設置を道路の延伸方向に繰り返しおこなうことにより、多数の床版ブロックからなる新設道路が施工され、既設道路の更新施工が完了する。   In the second step, by repeatedly performing the installation of the floor slab in the extending direction of the road, a new road composed of a number of floor slabs is constructed, and the renewal construction of the existing road is completed.

上記するように、主桁上の部分が凹部に嵌り込むことで床版ブロックが主桁の側方にずれる惧れがないことに加えて、道路の延伸方向に多数の床版ブロックが設置されていることから、床版ブロックが道路の延伸方向へずれる惧れもない。   As described above, in addition to the fact that the floor slab block is not displaced to the side of the main girder by the portion on the main girder being fitted into the recess, a number of floor slab blocks are installed in the extending direction of the road As a result, there is no fear that the floor block will shift in the road extension direction.

また、本発明による既設道路の更新施工方法の好ましい実施の形態において、前記主桁の上面にずれ止めが取り付けてあり、床版がずれ止めを埋設して既設道路が構成されており、第一のステップで残置される前記主桁上の部分が、主桁上の鉄筋コンクリートのうち、ずれ止めを埋設する中立軸よりも下方の主桁側の部分のみである方法を挙げることができる。   Further, in a preferred embodiment of the method for updating an existing road according to the present invention, a slip stopper is attached to the upper surface of the main girder, and a floor slab is embedded in the slip stopper to constitute an existing road. The method in which the portion on the main girder left behind in the step is only the portion of the reinforced concrete on the main girder side on the main girder side below the neutral axis in which the slip stopper is embedded can be mentioned.

既設床版の主桁上の部分のうち、中立軸よりも上の部分は曲げモーメントによる引張領域(負の曲げモーメントの領域)となっており、この領域ではクラックが生じている。   Of the portion on the main girder of the existing floor slab, the portion above the neutral axis is a tensile area (area of negative bending moment) due to bending moment, and a crack is generated in this area.

中立軸よりも下側の領域には、主桁と床版を繋ぐずれ止めが埋設されており、この領域は主桁上の部分の中でも圧縮領域となることから、クラックの発生がなく、健全な領域となっている。そこで、本発明の更新施工方法では、主桁上の部分を残置するものの、主桁上の部分でもクラックが含まれる中立軸よりも上の部分は撤去し、中立軸よりも下の健全な部分を本明細書における「主桁上の部分」として採用し、残置するものである。   In the area below the neutral axis, there is embedded a slip stopper that connects the main girder and the floor slab, and since this area becomes a compression area even in the part on the main girder, there is no occurrence of cracks, and soundness Area. Therefore, in the renewal construction method of the present invention, although the portion on the main girder is left, the portion on the main girder above the neutral axis including the crack is removed, and the sound portion below the neutral axis is removed. Is adopted as "the part on the main girder" in the present specification and is left behind.

このように主桁上の部分の中でも健全な領域のみを残してこの領域と床版ブロックとの一体化を図ることにより、接続構造の構成要素の一方が古い鉄筋コンクリートからなる主桁上の部分であっても、高い接続強度を期待することができる。   By integrating the area with the floor slab block while leaving only the sound area among the parts on the main girder in this way, one of the components of the connection structure is the part on the main girder made of old reinforced concrete. Even if there is, high connection strength can be expected.

また、本発明による既設道路の更新施工方法の好ましい実施の形態において、第二のステップでは、前記主桁上の部分の上に充填材を充填した後に床版ブロックの凹部を該主桁上の部分に嵌めるものである。   Further, in a preferred embodiment of the existing road renewal construction method according to the present invention, in the second step, after filling the filler on the portion on the main girder, the recess of the floor slab block is placed on the main girder. It fits on the part.

充填材を介して主桁上の部分と床版ブロックを接続することにより、既設の主桁上の部分と新設の床版ブロックの接続界面が所定のせん断付着強度を有することとなり、主桁と床版ブロック全体の有効高さを備えた合成梁を形成することができる。より具体的には、このせん断付着強度が接続界面に生じる水平せん断力以上の強度を有していることで、主桁上の部分と床版ブロックが同じ挙動を示す一体化(上記する合成梁の形成)を図ることができる。したがって、たとえば主桁上のずれ止めの有する水平せん断強度と同程度のせん断付着強度を備えた充填材を適用することで、上記する合成梁を形成することができる。   By connecting the portion on the main girder to the floor slab block through the filler, the connection interface between the portion on the existing main girder and the new floor slab block has a predetermined shear adhesion strength. Composite beams can be formed with the effective height of the entire deck block. More specifically, since the shear adhesion strength has a strength equal to or higher than the horizontal shear force generated at the connection interface, the portion on the main girder and the floor slab block exhibit the same behavior (the integrated beam described above) Formation of the Therefore, the composite beam described above can be formed, for example, by applying a filler having a shear adhesion strength similar to the horizontal shear strength possessed by the slip stopper on the main girder.

ここで、適用する充填材としては、普通モルタルなどのセメント系充填材、エポキシ樹脂やエポキシ樹脂モルタルなどのエポキシ系充填材、アクリル樹脂やアクリル樹脂モルタルなどのアクリル系充填材、ポリマー系充填材などを挙げることができる。   Here, as the filler to be applied, cement-based fillers such as ordinary mortar, epoxy-based fillers such as epoxy resin and epoxy resin mortar, acrylic-based fillers such as acrylic resin and acrylic resin mortar, polymer-based fillers, etc. Can be mentioned.

また、本発明による既設道路の更新施工方法の好ましい実施の形態は、第二のステップの実施に当たり、前記新設の床版ブロックの上面において、該床版ブロックの長手方向に延びて二以上の凹部に跨る長さの補強材を取り付けておくものである。   Further, in a preferred embodiment of the method for renovating an existing road according to the present invention, in carrying out the second step, at the upper surface of the newly installed floor slab block, two or more recesses extending in the longitudinal direction of the floor slab block The reinforcement of the length which straddles is attached.

床版ブロックがその下面に複数の凹部を備えていることで、床版ブロックの設置に際して該床版ブロックがクレーン等で吊り上げられた際に、凹部を有する箇所が構造弱部となり、床版ブロックが過度に撓んだり、床版ブロックの凹部周辺を起点としたクラックが発生する可能性がある。   Since the floor slab block is provided with a plurality of recesses on its lower surface, when the floor slab block is lifted by a crane or the like at the time of installation of the floor slab block, the location having the recess becomes a structural weak portion, and the floor slab block However, there is a possibility that a crack originating from the periphery of the recess of the floor slab block may occur.

そこで、本実施の形態の更新施工方法では、新設の床版ブロックの上面において、該床版ブロックの長手方向(道路の延伸方向に直交する方向)に延びて二以上の凹部に跨る長さの補強材を取り付けておくものである。   Therefore, in the renewal construction method of the present embodiment, on the upper surface of the new floor slab block, the floor slab block extends in the longitudinal direction (direction orthogonal to the extending direction of the road) and extends over two or more recesses. Reinforcement is attached.

この補強材は、H型鋼やI型鋼、棒状のコンクリートブロックなど、所定の剛性を備えたものから形成できる。   This reinforcing material can be formed of an H-type steel, an I-type steel, a rod-like concrete block, or the like having a predetermined rigidity.

また、本発明は更新施工された道路にも及ぶものであり、この道路は、二以上の鋼製の主桁と、主桁上にあって更新されずに残置された鉄筋コンクリート製の部分と、下面に二以上の凹部を備え、凹部が鉄筋コンクリート製の部分に嵌って設置されている新設の床版ブロックと、からなり、複数の前記床版ブロックが道路の延伸方向に併設されているものである。   In addition, the present invention extends to a rebuilt road, which includes two or more steel main girders, and a reinforced concrete part which is on the main girder and left unrenewed, It consists of a new floor slab block that has two or more recesses on the lower surface, and the recess is installed by fitting it in a part made of reinforced concrete, and a plurality of the above-mentioned floor slab blocks are juxtaposed in the road extension direction is there.

本発明の更新施工された道路は、既述する本発明の既設道路の更新施工方法にて施工されたものである。   The renewed construction road of the present invention is constructed by the renewal construction method of the existing road of the present invention described above.

主桁上に更新されずに鉄筋コンクリート製の部分を残置し、ここに床版ブロックの下面の凹部を嵌め込んで双方を一体化することにより、短工期にて更新施工された道路を施工することができる。   By installing a reinforced concrete part without being renewed on the main girder, inserting the recess on the lower surface of the floor slab into it and integrating the two into one, construction of a road rebuilt in a short construction period Can.

また、この更新施工された道路においても、前記主桁の上面にずれ止めが取り付けてあり、残置された鉄筋コンクリート製の部分が、更新前の主桁上の鉄筋コンクリートのうち、ずれ止めを埋設する中立軸よりも下方の主桁側の部分であるのが好ましい。   In addition, also on this renewed construction road, a slip stopper is attached to the upper surface of the main girder, and the remaining reinforced concrete part is embedded in the shear resist of the reinforced concrete on the main girder before the renewal. It is preferable that it is a portion on the main girder side below the vertical axis.

中立軸よりも下方の主桁側の部分は、クラックのない健全な部分であることより、新旧の鉄筋コンクリート同士の接続部に関し、高い接続強度を期待することができる。   Since the part on the main girder side below the neutral axis is a sound part free of cracks, high connection strength can be expected with respect to the connection between old and new reinforced concrete.

さらに、鉄筋コンクリート製の部分と床版ブロックの凹部の間に充填材が介在しているのが好ましい。   Furthermore, it is preferable that a filler be interposed between the reinforced concrete part and the recess of the floor block.

充填材を介して主桁上の鉄筋コンクリート製の部分と床版ブロックを接続することにより、既設の鉄筋コンクリート製の部分と新設の床版ブロックの接続界面が所定のせん断付着強度を有することとなり、主桁と床版ブロック全体の有効高さを備えた合成梁を形成することができ、作用する活荷重に起因する鉛直変位を可及的に小さくすることができる。   By connecting the reinforced concrete section on the main girder with the floor slab block through the filler, the connection interface between the existing reinforced concrete section and the new floor slab block has a predetermined shear adhesion strength, It is possible to form a composite beam with the effective height of the girder and the whole floor block, and to reduce the vertical displacement due to the live load acting as much as possible.

以上の説明から理解できるように、本発明の既設道路の更新施工方法と更新施工された道路によれば、主桁上にある鉄筋コンクリート製の床版を撤去するに当たり、床版の中で主桁上の部分のみを撤去せずに残し、その他の床版を撤去し、主桁上の部分に床版ブロックの下面の凹部を嵌め込みながら双方の一体化を図って更新施工された道路を施工することにより、更新施工に要する工期を格段に短縮することができる。   As can be understood from the above description, according to the method of reworking an existing road of the present invention and the rebuilt road, when removing a reinforced concrete floor slab on the main girder, the main girder in the floor slab is used. Leave only the upper part without removing it, remove the other floor slabs, and construct a rebuilt road in an attempt to unify both while fitting the recess on the lower face of the floor slab block to the part on the main girder As a result, it is possible to dramatically shorten the construction period required for renewal construction.

本発明の既設道路の更新施工方法の第一のステップを説明した模式図である。It is a schematic diagram explaining the 1st step of the update construction method of the existing road of this invention. 図1に続いて第一のステップを説明した模式図である。It is a schematic diagram explaining the 1st step following FIG. 残置する主桁上の部分を設定する根拠を説明した図である。It is a figure explaining the ground which sets the portion on the main girder left behind. 既設道路の更新施工方法の第二のステップを説明した模式図である。It is a schematic diagram explaining the 2nd step of the renewal construction method of the existing road. 更新施工された道路を示した模式図である。It is a schematic diagram showing a renewed road. 残置された主桁上の部分と床版ブロックの間の界面状態を複数パターンでモデル化し、各モデルにおける活荷重載荷時の鉛直変位を求める解析において使用した、三次元モデルを示した図である。It is the figure which showed the three-dimensional model used in the analysis which models the interface state between the part on the left main girder and the floor slab block with a plurality of patterns, and calculates the vertical displacement at the time of live load loading in each model. . 残置された主桁上の部分と床版ブロックの間の界面状態に関し、複数の界面パターンモデルを説明した図である。It is a figure explaining a plurality of interface pattern models about the interface state between the part on the main girder left behind, and a floor slab block. 各界面パターンモデルにおいて活荷重載荷時の主桁間の床版の最大変位に関する解析結果を示した図である。It is a figure showing the analysis result about the maximum displacement of the floor slab between the main girder at the time of live load loading in each interface pattern model. 各界面パターンモデルにおける最大変位を比較した図である。It is the figure which compared the largest displacement in each interface pattern model.

以下、図面を参照して、本発明の既設道路の更新施工方法と更新施工された道路の実施の形態を説明する。なお、図示例は、二つの主桁からなる既設道路および更新施工された道路を示しているが、三以上の主桁を備えた既設道路が更新施工の対象であってもよいことは勿論のことである。   Hereinafter, with reference to the drawings, embodiments of the method for updating an existing road of the present invention and a road on which the method for updating is constructed will be described. In addition, although the example of illustration has shown the existing road which consists of two main girders, and the rebuilt road, it is needless to say that the existing road provided with three or more main girders may be the object of renewal construction. It is.

(既設道路の更新施工方法と更新施工された道路の実施の形態)
図1,2は本発明の既設道路の更新施工方法の第一のステップを説明した模式図であり、図3は残置する主桁上の部分を設定する根拠を説明した図であり、図4は第二のステップを説明した模式図である。また、図5は更新施工された道路を示した模式図である。
(Renewal construction method of existing road and embodiment of road which was renewed construction)
1 and 2 are schematic diagrams illustrating the first step of the method of updating an existing road according to the present invention, and FIG. 3 is a diagram illustrating the basis for setting the remaining portion on the main girder. These are schematic diagrams explaining the second step. Moreover, FIG. 5 is a schematic diagram which showed the road by which renewal construction was carried out.

図1で示す既設道路10は、道路の延伸方向Lに延びる二本の主桁1と、各主桁1に対して一体に施工された鉄筋コンクリート製の既設床版2とから大略構成されている。なお、図1で示す既設道路10は、その延伸方向に延びる道路全体の一部を取り出して図示している。   The existing road 10 shown in FIG. 1 is roughly composed of two main girder 1 extending in the extending direction L of the road and an existing reinforced concrete floor slab 2 integrally constructed to each main girder 1 . In addition, the existing road 10 shown in FIG. 1 takes out and is showing the part of the whole road extended in the extension direction.

この既設床版2には、供用期間中に繰り返し受けた活荷重等に起因した曲げモーメント等により、特に主桁1間の床板には多数のクラックや陥没などの損傷が生じている。   The floor plate between the main girder 1 is damaged particularly by a large number of cracks, depressions and the like due to bending moment or the like caused by the active load repeatedly received during the service period.

損傷した既設床版2を更新施工するに当たり、既設床版2のうち、主桁上の一部の鉄筋コンクリートを残し、他の部分を撤去することにより、図2で示すように主桁1の上に主桁上の部分4のみが残置した状態とする(第一のステップ)。   When the damaged existing floor slab 2 is to be rebuilt, the reinforced concrete part of the existing floor slab 2 is left on the main girder, and the other part is removed, as shown in FIG. In this state, only the part 4 on the main girder is left (first step).

具体的には、作業員がチェーンソー等の切断機にて主桁上の部分4のみが残るように既設床版2を鉛直斜め方向や水平方向に切断し、切断された既設床版2を撤去することにより、図2の状態を形成する。   Specifically, the worker cuts the existing floor slab 2 obliquely in the vertical or horizontal direction so as to leave only the part 4 on the main girder with a cutting machine such as a chain saw, and removes the cut existing floor slab 2 As a result, the state of FIG. 2 is formed.

ここで、主桁1の上面には多数のずれ止め3が取り付けられており、既設道路10は、このずれ止め3を取り囲むようにして鉄筋が配筋され、コンクリートが現場打設されることでずれ止め3を埋設するようにしてコンクリート製の既設床版2が施工されている。   Here, a large number of slip stoppers 3 are attached to the upper surface of the main girder 1, and in the existing road 10, reinforcing bars are arranged so as to surround the slip stoppers 3, and concrete is cast on the spot The existing floor slab 2 made of concrete is constructed so as to embed the slip stopper 3.

図2で示すように、第一のステップにて形成された主桁上の部分4には、そのずれ止め3が埋設されている。   As shown in FIG. 2, in the portion 4 on the main girder formed in the first step, the slip stopper 3 is embedded.

すなわち、従来の更新施工方法では、ずれ止めが露出するまで主桁上の部分を斫り、主桁の上方を清掃した後にプレキャスト製の床版ブロックを主桁上に設置する方法が一般的であったが、この方法ではこのずれ止めの斫り出しに多大な時間を要していた。   That is, in the conventional renewal construction method, a general method is to install the precast floor block block on the main girder after sweeping the portion on the main girder until the slip stopper is exposed and cleaning the upper side of the main girder. However, this method required a great deal of time for this anti-slip effect.

図示する更新施工方法では、第一のステップにおいて、ずれ止め3を露出するまで斫り出すことなく、鉄筋コンクリート製の主桁上の部分4の内部にずれ止め3が埋設された状態で既設床版2の撤去作業を終了する。このことにより、従来の更新施工方法におけるずれ止めの斫り出しに要していた多大な時間を解消することができる。   In the renewal construction method to illustrate, in the first step, the existing floor plate in a state in which the slip stopper 3 is embedded inside the portion 4 on the main girder made of reinforced concrete, without protruding until the slip stopper 3 is exposed. Finish the removal of 2. As a result, it is possible to eliminate the great amount of time required for the slippage prevention in the conventional renewable construction method.

ここで、図3を参照して、主桁上の部分4をどの範囲とするか、すなわち主桁上の部分4の範囲の設定方法について説明する。   Here, with reference to FIG. 3, the range of the portion 4 on the main digit will be described, that is, a method of setting the range of the portion 4 on the main digit will be described.

活荷重を受けた際に、既設道路10には主桁1の上方で負の曲げモーメント(−M)、主桁1間で正の曲げモーメント(+M)が生じており、既設床版2のうち、主桁上の部分4においては、その断面内の中立軸の上方が引張領域となり、下方が圧縮領域となっている。   When live load is received, a negative bending moment (−M) is generated above the main girder 1 and a positive bending moment (+ M) is generated between the main girder 1 on the existing road 10. Among them, in the portion 4 on the main girder, the upper side of the neutral axis in the cross section is a tensile area and the lower side is a compression area.

引張領域においては文字通りコンクリートに引張りが作用することでクラックが生じており、したがってこの引張領域は不健全な領域となっている。   In the tensioned area, the concrete literally has a crack due to the effect of the tension acting on the concrete, and therefore this tensioned area is an unhealthy area.

一方、圧縮領域は、コンクリートにクラックが生じていないことから健全な領域と言える。そこで、この健全な領域である中立軸よりも下方の範囲で、かつずれ止め3を包囲する範囲を床版ブロック6と接続する主桁上の部分4として規定し、残置領域とするものである。   On the other hand, the compressed area is said to be a sound area because no cracks occur in the concrete. Therefore, the area below the neutral axis, which is the sound area, and the area surrounding the shift stopper 3 is defined as the portion 4 on the main girder connected to the floor slab block 6, and is used as the remaining area .

図4で示すように、主桁上の部分4の全面に接着性の充填材5を塗布する。ここで、充填材5としては、普通モルタル、無収縮モルタル、繊維入りモルタルなどのセメント系充填材、エポキシ樹脂、エポキシ樹脂モルタル、エポキシ樹脂グラウトなどのエポキシ系充填材、アクリル樹脂、アクリル樹脂モルタル、アクリル樹脂グラウトなどのアクリル系充填材、ゴムラテックスモルタルなどのポリマー系充填材などが適用できる。   As shown in FIG. 4, an adhesive filler 5 is applied to the entire surface of the portion 4 on the main girder. Here, as the filler 5, cement-based filler such as ordinary mortar, non-shrink mortar, fiber-containing mortar, epoxy resin, epoxy resin mortar, epoxy-based filler such as epoxy resin grout, acrylic resin, acrylic resin mortar, Acrylic based fillers such as acrylic resin grout, polymer based fillers such as rubber latex mortar, etc. can be applied.

主桁上の部分4の全面に接着性の充填材5を塗布したら、プレキャスト製で下面に凹部6aを備えた床版ブロック6を不図示のクレーンで吊り下げられたワイヤ8で吊り下し、各凹部6aを対応する主桁上の部分4に嵌め込むようにして床版ブロック6を二本の主桁1に架け渡して設置する。   After the adhesive filler 5 is applied to the entire surface of the portion 4 on the main girder, the floor block 6 made of precast and provided with a recess 6a on the lower surface is suspended by a wire 8 suspended by a crane (not shown) The floor block 6 is placed over the two main girders 1 so that each recess 6a is fitted into the corresponding part 4 on the main girder.

ここで、床版ブロック6は下面に二条の凹部6aを有していることから、この凹部6aの付近の強度が弱く、ワイヤ8にて直接吊り下げられた際に構造弱部である凹部6aの周辺でクラックが発生することが危惧される。   Here, since the floor slab block 6 has the two recessed portions 6a on the lower surface, the strength in the vicinity of the recessed portion 6a is weak, and the recessed portion 6a which is a structural weak portion when directly suspended by the wire 8. It is feared that cracks may occur around the area.

そこで、床版ブロック6の上面には、予めその長手方向に延びて二本の凹部6aに跨る長さの補強材7を取り付けておき、補強材7に取り付けられている留め具7aにワイヤ8を取り付け、床版ブロック6を吊り上げるようにしておく。   Therefore, a reinforcing material 7 having a length extending in the longitudinal direction and straddling the two concave portions 6a is attached in advance to the upper surface of the floor block 6, and the wire 8 is attached to the fastener 7a attached to the reinforcing material 7. , And lift the floor block 6 up.

なお、補強材7としては、H型鋼やI型鋼、C型鋼、角鋼管等の鋼材、長尺のコンクリートブロックなどを適用できる。   In addition, as the reinforcing material 7, steel materials, such as H type steel, I type steel, C type steel, a square steel pipe, a long concrete block, etc. are applicable.

図4で示す床版ブロック6の設置を道路の延伸方向に繰り返して実施することにより、図5で示すように二本の主桁1の上に道路の延伸方向に多数の床版ブロック6が設置されてなる更新施工された道路20が施工され、既設道路の更新施工が完了する(第二のステップ)。   By repeating the installation of the floor slab block 6 shown in FIG. 4 in the extending direction of the road, as shown in FIG. 5, a large number of floor slab blocks 6 in the extending direction of the road are placed on the two main girder 1. The renewal construction road 20 which is installed is constructed, renewal construction of the existing road is completed (the 2nd step).

なお、充填材5を介して主桁上の部分4と床版ブロック6を接続することにより、既設の主桁上の部分4と新設の床版ブロック6の接続界面が所定のせん断付着強度を有することとなり、主桁1と床版ブロック6全体の有効高さを備えた合成梁をこの接続箇所に形成することができる。   In addition, by connecting the portion 4 on the main girder with the floor slab block 6 via the filler 5, the connection interface between the portion 4 on the existing main girder and the new floor slab block 6 has a predetermined shear adhesion strength. As a result, it is possible to form a composite beam having the effective height of the main girder 1 and the entire floor slab block 6 at this connection point.

より具体的には、このせん断付着強度が接続界面に生じる水平せん断力以上の強度を有していることで、主桁上の部分4と床版ブロック6が同じ挙動を示す一体化(上記する合成梁の形成)を図ることができる。   More specifically, since the shear adhesion strength is equal to or higher than the horizontal shear force generated at the connection interface, the portion 4 on the main girder and the floor block 6 exhibit the same behavior (the above-mentioned integration (described above) Formation of composite beams).

したがって、たとえば主桁1上のずれ止め3の有する水平せん断強度と同程度のせん断付着強度を備えた充填材5を適用することで、上記する合成梁を形成することが可能になる。   Therefore, it becomes possible to form the above-mentioned synthetic beam by applying filler 5 provided with the same shear adhesion strength as horizontal shear strength which slip stopper 3 on main girder 1 has, for example.

また、図示例のように、主桁上の部分4の断面形状を下底に対して上底が短い台形状とし、床版ブロック6の凹部6aをこれに相補的な形状のものとしておくことで、主桁上の部分4に対して凹部6aを嵌め込み易くできる。   Also, as shown in the illustrated example, the cross-sectional shape of the portion 4 on the main girder should be trapezoidal with the upper base short with respect to the lower base, and the recess 6a of the floor block 6 should be a shape complementary thereto. Thus, the recess 6a can be easily fitted into the portion 4 on the main girder.

(残置された主桁上の部分と床版ブロックの間の界面状態を複数パターンでモデル化し、各モデルにおける活荷重載荷時の鉛直変位を求めた解析とその結果)
本発明者等は、残置された主桁上の部分と床版ブロックの間の界面状態を複数パターンでモデル化し、各モデルにおける活荷重載荷時の鉛直変位を求める解析をおこなった。ここで、図6は解析において使用した三次元モデルを示した図であり、図7は複数の界面パターンモデルを説明した図である。
(Modeling the interface state between the left main girder part and the floor slab block with multiple patterns, and determining the vertical displacement during live load loading in each model and its results)
The inventors of the present invention modeled the interface state between the remaining portion on the main girder and the floor slab block with a plurality of patterns, and performed an analysis to obtain the vertical displacement at the time of live load loading in each model. Here, FIG. 6 is a view showing a three-dimensional model used in analysis, and FIG. 7 is a view explaining a plurality of interface pattern models.

本解析では、昭和50年2月の道路橋示方書で設計された3径間連続非合成鈑桁橋を解析対象とし、載荷荷重は道路橋示方書で規定されている自動車荷重(L荷重)とした。また、図6で示すように、コンピュータ内において、RC床版はソリッド要素でモデル化し、主桁や垂直補剛材は板要素でモデル化し、対傾構は棒要素でモデル化した。さらに、図7で示すように、充填材を介して接続された主桁上の部分と床版ブロックの界面状態は、完全剛結モデル、引張無視モデル、および界面剥離モデルの3種とした。そして、各界面モデルを形成するための条件設定として、x方向、y方向およびz方向の各バネ定数を適宜に設定し、必要に応じてある方向のばね定数を無限大(∞)としたり、引張方向のバネ定数をゼロとしたりする等の設定をおこなった。   In this analysis, the three span continuous non-synthetic girder bridge designed by the road bridge specification in February 1959 is analyzed, and the loading load is the vehicle load (L load) specified by the road bridge specification. did. Further, as shown in FIG. 6, in the computer, RC floor slabs were modeled by solid elements, the main girder and vertical stiffeners were modeled by plate elements, and the anti-tilting structure was modeled by rod elements. Furthermore, as shown in FIG. 7, the interface state between the portion on the main girder connected via the filler and the floor slab block was of three types: a completely rigid model, a tensile neglect model, and an interfacial peeling model. Then, as condition settings for forming each interface model, each spring constant in the x direction, y direction and z direction is appropriately set, and if necessary, the spring constant in a certain direction is infinite (∞), or Settings such as setting the spring constant in the tension direction to zero were performed.

充填材の物性値:EG=2.0×103N/mm2の際の、従来例のケース、界面状態が完全剛結モデルのケース、界面状態が引張無視モデルのケース、および界面状態が界面剥離モデルのケースの4ケースで解析をおこなった。なお、従来例のケースとは、主桁上のずれ止めを巻き込むようにして現場打設コンクリートにて床版が施工されてなる既設道路をモデル化したものである。ここで、図8は各界面パターンモデルにおいて活荷重載荷時の主桁間の床版の最大変位に関する解析結果を示した図であり、図9は各界面パターンモデルにおける最大変位を比較した図である。 Physical properties of filler: Case of the conventional example at the time of E G = 2.0 × 10 3 N / mm 2 , the case of the interface state being a completely rigid model, the case of the interface state being a tension neglect model, and the interface state being an interface The analysis was performed in four cases of the exfoliation model case. The case of the conventional example is a model of an existing road on which a floor slab is constructed with cast-in-place concrete in such a manner as to incorporate slip stoppers on the main girder. Here, FIG. 8 is a diagram showing an analysis result on the maximum displacement of the floor slab between the main girder during live load loading in each interface pattern model, and FIG. 9 is a diagram comparing the maximum displacement in each interface pattern model. is there.

図8より、従来例、完全剛結モデル、引張無視モデルの主桁間の最大鉛直変位は同程度であるのに対して、界面剥離モデルの最大鉛直変位は2〜3割程度も増加する結果となっている。   According to FIG. 8, while the maximum vertical displacement between the main girder of the conventional example, the completely rigid model and the tension neglect model is almost the same, the maximum vertical displacement of the interface peeling model is increased by about 30 to 30%. It has become.

図9は、従来例の最大鉛直変位を基準とし、この基準値で3種の解析結果を正規化して示している。さらに、充填材の物性値:EGが2.0×103N/mm2以外にも、2.0×101N/mm2のケース、2.0×102N/mm2のケース、および2.0×104N/mm2のケースでも解析をおこない、EGが2.0×103N/mm2のケースと同様に、従来例の最大鉛直変位を基準値として他の3種の解析結果を正規化して示している。 FIG. 9 shows three types of analysis results normalized with this reference value based on the maximum vertical displacement of the conventional example. Furthermore, physical properties of filler: E G is 2.0 × besides 10 3 N / mm 2, 2.0 × 10 1 N / mm 2 cases, 2.0 × 10 2 N / mm 2 of the case, and 2.0 × 10 4 Analysis is also performed in the case of N / mm 2, and in the same way as in the case of E G of 2.0 × 10 3 N / mm 2 , the other three types of analysis results are normalized with the maximum vertical displacement of the conventional example as a reference value. ing.

図9より、充填材の物性値に関わらず、界面状態が界面剥離モデルのケースにおいて、最大変位は8割程度も大きくなることが分かる。   From FIG. 9, regardless of the physical property value of the filler, it can be seen that the maximum displacement is increased by about 80% in the case of the interfacial separation model in the interfacial state.

この解析結果より、主桁上の部分と床版ブロックの間の界面状態において、界面剥離が生じることでこの領域に主桁と床版ブロックの一体化が図られず、このことに起因して合成梁が形成されず、いわゆる重ね梁となっていることで鉛直変位が大きくなることが分かる。   From this analysis result, in the interface state between the portion on the main girder and the floor slab block, interface separation occurs and integration of the main girder and floor slab block can not be achieved in this region, which is attributed to this. It can be seen that the vertical displacement is increased by forming a composite beam and forming a so-called overlapping beam.

したがって、適用される充填材には、主桁上の部分と新設の床版ブロックの接続界面に界面剥離が生じないようなせん断付着強度を有するものが望ましいことが分かる。   Therefore, it is understood that it is desirable for the applied filler to have a shear adhesion strength such that interfacial peeling does not occur at the connection interface between the portion on the main girder and the new floor slab block.

以上、本発明の実施の形態を図面を用いて詳述してきたが、具体的な構成はこの実施形態に限定されるものではなく、本発明の要旨を逸脱しない範囲における設計変更等があっても、それらは本発明に含まれるものである。   As mentioned above, although the embodiment of the present invention has been described in detail with reference to the drawings, the specific configuration is not limited to this embodiment, and there are design changes and the like within the scope of the present invention. Also, they are included in the present invention.

1…主桁、2…既設床版、3…ずれ止め、4…主桁上の部分(鉄筋コンクリート製の部分)、5…充填材、6…床版ブロック、6a…凹部、7…補強材、8…ワイヤ、10…既設道路、20…更新施工された道路   DESCRIPTION OF SYMBOLS 1 ... Main girder, 2 ... Existing floor version, 3 ... Slack stop, 4 ... Part (The reinforced concrete part) on the main girder, 5 ... Filler, 6 ... floor block, 6a .. 8 ... wire, 10 ... existing road, 20 ... updated construction road

Claims (5)

二以上の鋼製の主桁上に鉄筋コンクリート製の床版が設置されてなる既設道路の更新方法であって、
床版のうち、主桁上の部分のみを残置し、他の部分を撤去する第一のステップ、
下面に二以上の凹部を備えた新設の床版ブロックを、それぞれの凹部が前記二以上の主桁上の部分に嵌るようにして設置し、この床版ブロックの設置を道路の延伸方向に繰り返す第二のステップからなり、
前記主桁の上面にずれ止めが取り付けてあり、床版がずれ止めを埋設して既設道路が構成されており、
第一のステップで残置される前記主桁上の部分が、該主桁上の鉄筋コンクリートのうち、ずれ止めを埋設する中立軸よりも下方の主桁側の部分のみである、既設道路の更新施工方法。
A method of updating an existing road where reinforced concrete floor slabs are installed on two or more steel main girders,
The first step of leaving only the part on the main girder and removing the other parts of the floor slab,
A new floor slab block having two or more recesses on the lower surface is installed in such a way that each recess fits in the portion on the two or more main girders, and this floor slab block is repeated in the road extension direction Ri Do from the second step,
A slip stopper is attached to the upper surface of the main girder, and a floor plate is embedded in the slip stopper to constitute an existing road,
Renewal construction of the existing road where the part on the main girder left behind in the first step is only the part on the main girder side below the neutral axis which embeds the slip stopper among the reinforced concrete on the main girder Method.
第二のステップでは、前記主桁上の部分の上に充填材を充填した後に床版ブロックの凹部を該主桁上の部分に嵌める、請求項に記載の既設道路の更新施工方法。 In a second step, fitting the recess of the slab blocks after filling the filling material on the portion on the main beam to the portion of the main digits, existing update method of constructing roads according to claim 1. 第二のステップの実施に当たり、前記新設の床版ブロックの上面において、該床版ブロックの長手方向に延びて二以上の凹部に跨る長さの補強材を取り付けておく、請求項1または2に記載の既設道路の更新施工方法。 In implementing the second step, the upper surface of the slab blocks in the new, permanently installing longitudinally extending stiffener length spanning two or more recesses of the floor plate blocks, to claim 1 or 2 Renewal construction method of the existing road of statement. 二以上の鋼製の主桁と、
主桁上にあって更新されずに残置された鉄筋コンクリート製の部分と、
下面に二以上の凹部を備え、凹部が鉄筋コンクリート製の部分に嵌って設置されている新設の床版ブロックと、からなり、
複数の前記床版ブロックが道路の延伸方向に併設されており、更新施工された道路。
前記主桁の上面にずれ止めが取り付けてあり、
残置された鉄筋コンクリート製の部分が、更新前の主桁上の鉄筋コンクリートのうち、ずれ止めを埋設する中立軸よりも下方の主桁側の部分である、更新施工された道路。
With two or more steel main girders,
A reinforced concrete part that was left on the main girder without being updated,
A new floor slab block that has two or more recesses on the lower surface, and the recesses fit into a reinforced concrete part,
A plurality of said slab blocks are parallel in the extending direction of the road, the update construction road.
A slip stopper is attached to the upper surface of the main girder,
A rebuilt road on which the left reinforced concrete part is the part of the reinforced concrete on the main girder before updating, which is the part on the main girder side below the neutral axis on which the slip stopper is embedded.
鉄筋コンクリート製の部分と床版ブロックの凹部の間に充填材が介在している、請求項に記載の更新施工された道路。 The renewed construction road according to claim 4 , wherein a filler is interposed between the reinforced concrete part and the recess of the floor block.
JP2015176730A 2015-09-08 2015-09-08 Renewed construction method of existing road and rebuilt road Active JP6541520B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015176730A JP6541520B2 (en) 2015-09-08 2015-09-08 Renewed construction method of existing road and rebuilt road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015176730A JP6541520B2 (en) 2015-09-08 2015-09-08 Renewed construction method of existing road and rebuilt road

Publications (2)

Publication Number Publication Date
JP2017053117A JP2017053117A (en) 2017-03-16
JP6541520B2 true JP6541520B2 (en) 2019-07-10

Family

ID=58320443

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015176730A Active JP6541520B2 (en) 2015-09-08 2015-09-08 Renewed construction method of existing road and rebuilt road

Country Status (1)

Country Link
JP (1) JP6541520B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7290461B2 (en) * 2019-05-17 2023-06-13 中日本高速道路株式会社 Connection structure of girders and precast floor slabs
JP7012062B2 (en) * 2019-12-05 2022-01-27 テクノス株式会社 How to handle the floor slab separated from the girder

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6059209A (en) * 1983-09-08 1985-04-05 石川島播磨重工業株式会社 Replacing method of bridge reinforced concrete floor panel
JP4627383B2 (en) * 2001-05-10 2011-02-09 株式会社Ihiインフラシステム Replaced steel deck bridge
JP5051591B2 (en) * 2008-07-31 2012-10-17 株式会社ピーエス三菱 Precast PC plate erection device for floor slab and its erection method
JP5346676B2 (en) * 2009-05-08 2013-11-20 大成建設株式会社 Floor slab unit, floor slab joining structure and floor slab construction method

Also Published As

Publication number Publication date
JP2017053117A (en) 2017-03-16

Similar Documents

Publication Publication Date Title
JP6316665B2 (en) Composite structure of steel girder and precast slab and its construction method
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
KR101761476B1 (en) Change construction method of bridge expansion joint for quick construction
JP6837343B2 (en) Floor slab replacement method for synthetic girders
KR101817968B1 (en) Repair reinforcement method of bridge with a expansion joint
JP6541520B2 (en) Renewed construction method of existing road and rebuilt road
JP6771987B2 (en) Floor slab replacement method for steel synthetic girders and PC floor slab
KR20160115602A (en) Method of replacing bridge deck slab and prestressed concrete girder assembly used therein
JP5716117B1 (en) Hinge reinforcement method and reinforcement structure for existing girder bridge
JP5958907B2 (en) Partial restoration method for existing concrete slabs
JP2012184575A (en) Method for repairing steel structure
KR20200043293A (en) Reinforcing method and reinforced structure of hinge portion in prestressed concrete girder bridge
JP5848716B2 (en) Floor slab replacement method
JP7186670B2 (en) Concrete floor slab repair method
KR101693767B1 (en) Method for constructing precast floor plate with expansion joint
KR101060103B1 (en) Prestressed concrete paving method for road repair and its structure
JP2011149244A (en) Construction method for thickening upper surface of floor slab
JP5041481B2 (en) Updating method and structure of existing bearing device
KR100758878B1 (en) Method for repairing bridge using integrated girder-concrete slab assembly
JP6053087B1 (en) Steel composite girder floor slab replacement method
KR101381974B1 (en) Concrete deck slab assembly, Method for making the same and Temporary bridge using the same
JP2021070955A (en) Concrete structure repairing method
JP2019132070A (en) Precast floor slab for replacing pc composite girder and replacing method for pc composite girder precast floor slab
JP7452284B2 (en) Floor slab replacement method
KR101244403B1 (en) Prestressed Concrete Beam, connecting structure of the same and method of connecting the same.

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20170724

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20170824

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180606

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190129

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190304

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190521

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190611

R150 Certificate of patent or registration of utility model

Ref document number: 6541520

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250