JP7172916B2 - Bridge superstructure removal method - Google Patents

Bridge superstructure removal method Download PDF

Info

Publication number
JP7172916B2
JP7172916B2 JP2019150491A JP2019150491A JP7172916B2 JP 7172916 B2 JP7172916 B2 JP 7172916B2 JP 2019150491 A JP2019150491 A JP 2019150491A JP 2019150491 A JP2019150491 A JP 2019150491A JP 7172916 B2 JP7172916 B2 JP 7172916B2
Authority
JP
Japan
Prior art keywords
superstructure
bridge
span
reinforcing member
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019150491A
Other languages
Japanese (ja)
Other versions
JP2021031884A (en
Inventor
裕明 田中
信秀 中村
和人 伊佐
智美 木本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
JFE Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Engineering Corp filed Critical JFE Engineering Corp
Priority to JP2019150491A priority Critical patent/JP7172916B2/en
Publication of JP2021031884A publication Critical patent/JP2021031884A/en
Application granted granted Critical
Publication of JP7172916B2 publication Critical patent/JP7172916B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、橋梁上部工撤去工法に関し、詳細には、橋梁の上部工を撤去する際の桁下空間の利用制限を大きく緩和させることができる橋梁上部工撤去工法に関する。ここで、本願において、上部工とは、当該橋梁の主桁および床版のうち、少なくとも主桁を含む当該橋梁の上部構造のことである。 TECHNICAL FIELD The present invention relates to a bridge superstructure removal method, and more particularly, to a bridge superstructure removal method capable of greatly relaxing restrictions on the use of space under girder when removing a bridge superstructure. Here, in the present application, the superstructure means the superstructure of the bridge including at least the main girder, out of the main girder and floor slab of the bridge.

橋梁の上部工を撤去する場合、撤去する橋梁の上部工の下方の空間を使用して撤去を行う工法が一般的に用いられている。 When removing a superstructure of a bridge, a construction method of using the space below the superstructure of the bridge to be removed is generally used.

例えば、特許文献1に記載の橋梁の撤去方法では、2対のベントを使用して、それぞれ支持と降下を繰り返すことで、撤去する橋梁の上部工を降下させて撤去する。 For example, in the method of removing a bridge described in Patent Literature 1, two pairs of vents are used to repeatedly support and lower each of the bents, thereby lowering and removing the superstructure of the bridge to be removed.

しかしながら、上記のようなベントを用いて橋梁の上部工を撤去する方法では、大型のクレーンを用いる必要はなくても、ベントを立設する作業、及び当該ベントを用いて上部工を撤去する作業の間は、比較的長い時間、桁下に通っている道路や鉄道を通行止めする必要がある。つまり、撤去する上部工の下方の空間を使用することが大きく制限される。 However, in the above-described method of removing a bridge superstructure using a vent, the work of erecting the vent and the work of removing the superstructure using the vent do not require the use of a large crane. During this period, roads and railroads running under the girder must be closed to traffic for a relatively long period of time. In other words, the use of the space below the superstructure to be removed is greatly restricted.

特開2006-144282号公報JP 2006-144282 A

本発明は、かかる点に鑑みてなされたものであり、橋梁の上部工を撤去する際の桁下空間の利用の制限を大きく緩和させることができる橋梁上部工撤去工法を提供することを課題とする。 SUMMARY OF THE INVENTION It is an object of the present invention to provide a bridge superstructure removal method that can greatly relax restrictions on the use of the space under the girder when removing the superstructure of a bridge. do.

本発明は、以下の橋梁上部工撤去工法により、前記課題を解決したものである。 The present invention solves the above problems by the bridge superstructure removal method described below.

即ち、本発明に係る橋梁上部工撤去工法は、橋梁の上部工を撤去する橋梁上部工撤去工法であって、撤去対象径間およびその撤去対象径間に隣接する径間の前記上部工を補強する補強部材を前記橋梁の橋軸方向に延びる方向に設置する補強部材設置工程と、前記上部工の上方にクレーンを設置するクレーン設置工程と、前記補強部材設置工程の後、前記撤去対象径間の前記上部工の所定位置を切断する切断工程と、前記切断工程により切り離された前記上部工の所定部位を、前記クレーンで撤去する撤去工程と、を有することを特徴とする橋梁上部工撤去工法である。 That is, a bridge superstructure removal method according to the present invention is a bridge superstructure removal method for removing a superstructure of a bridge, wherein the superstructure of the span to be removed and the span adjacent to the target span to be removed is reinforced. A reinforcing member installation step of installing a reinforcing member to extend in the direction of the bridge axis of the bridge, a crane installation step of installing a crane above the superstructure, and after the reinforcing member installation step, the span to be removed and a removal step of removing the predetermined portion of the superstructure separated by the cutting step with the crane. is.

前記補強部材設置工程の後に、前記クレーン設置工程を行うようにしてもよい。 The crane installation step may be performed after the reinforcing member installation step.

前記補強部材設置工程では、撤去対象径間およびその撤去対象径間に隣接する径間の前記上部工の上方に、前記補強部材を前記橋梁の橋軸方向に延びる方向に設置してもよい。 In the reinforcing member installation step, the reinforcing member may be installed in a direction extending in the axial direction of the bridge above the superstructure of the span to be removed and the span adjacent to the target span to be removed.

前記上部工が鋼主桁を備える場合、前記補強部材設置工程では、撤去対象径間およびその撤去対象径間に隣接する径間の前記上部工の前記鋼主桁のウェブに、前記補強部材を前記橋梁の橋軸方向に延びる方向に設置してもよい。 When the superstructure includes a steel main girder, in the reinforcing member installation step, the reinforcing member is installed on the web of the steel main girder of the superstructure in the span to be removed and the span adjacent to the span to be removed. You may install in the direction extended to the bridge axis direction of the said bridge.

前記補強部材設置工程で設置した前記補強部材の上方に軌条設備を設置する軌条設備設置工程をさらに備えさせ、前記クレーン設置工程では、前記軌条設備設置工程で設置した前記軌条設備に、前記クレーンを前記軌条設備に沿って移動可能に設置するようにしてもよい。 A rail equipment installation step of installing rail equipment above the reinforcing member installed in the reinforcing member installing step is further provided, and in the crane installing step, the crane is installed on the rail equipment installed in the rail equipment installing step. You may make it install so that it can move along the said rail installation.

前記補強部材設置工程で設置した前記補強部材は、前記橋梁の橋軸方向に前記クレーンが移動できるようにする軌条設備も備えているように構成してもよい。 The reinforcing member installed in the reinforcing member installation step may be configured to also include a rail facility that allows the crane to move in the direction of the bridge axis of the bridge.

前記クレーン設置工程で設置した前記クレーンを、前記撤去対象径間の中央寄りの、前記補強部材の端部付近に移動させるクレーン移動工程をさらに備えさせ、前記撤去工程では、前記切断工程により切り離された前記上部工の前記所定部位を、前記クレーン移動工程で移動させた前記クレーンで撤去するようにしてもよい。 A crane moving step of moving the crane installed in the crane installing step to the vicinity of an end portion of the reinforcing member near the center of the removal target span, and in the removing step, the crane separated by the cutting step is provided. The predetermined portion of the superstructure may be removed by the crane moved in the crane moving step.

前記切断工程により切り離される前記上部工の前記所定部位の上方に位置する前記補強部材の部位を、前記補強部材の他の部位から切り離して撤去した後、前記上部工の前記所定部位を前記切断工程で切り離すようにしてもよい。 After the portion of the reinforcing member located above the predetermined portion of the superstructure cut off in the cutting step is separated from the other portion of the reinforcing member and removed, the predetermined portion of the superstructure is removed in the cutting step. You can separate it with .

前記撤去工程では、前記切断工程により切り離される前記上部工の前記所定部位だけでなく、該所定部位の上方に位置する前記補強部材の部位も同時に撤去するようにしてもよい。 In the removing step, not only the predetermined portion of the superstructure separated by the cutting step, but also the portion of the reinforcing member located above the predetermined portion may be removed at the same time.

前記切断工程では、前記上部工の切断位置における曲げモーメントを減少させてから、前記上部工を切断するようにしてもよい。 In the cutting step, the superstructure may be cut after reducing a bending moment at the cutting position of the superstructure.

前記切断工程では、前記上部工の前記切断位置における曲げモーメントを減少させる際にジャッキを用いてもよい。 The cutting step may employ a jack in reducing the bending moment of the superstructure at the cut location.

本発明に係る橋梁上部工撤去工法によれば、橋梁の上部工を撤去する際の桁下空間の利用の制限を大きく緩和させることができる橋梁上部工撤去工法を提供することができる。 INDUSTRIAL APPLICABILITY According to the bridge superstructure removal method according to the present invention, it is possible to provide a bridge superstructure removal method that can greatly relax restrictions on the use of the space under the girder when removing the bridge superstructure.

上部工撤去対象の橋梁60を模式的に示す側面図(橋軸直角方向から見た側面図)Side view schematically showing the bridge 60 to be removed from the superstructure (side view seen from the direction perpendicular to the bridge axis) 第1実施形態に係る橋梁上部工撤去工法を用いて橋梁60の上部工62の撤去を行うときの代表的な工程を模式的に示す側面図(橋軸直角方向から見た側面図)FIG. 2 is a side view schematically showing a representative process when removing a superstructure 62 of a bridge 60 using the bridge superstructure removal method according to the first embodiment (a side view seen from a direction perpendicular to the bridge axis). 第1実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材10および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)FIG. 2 is a front view schematically showing a state in which the installation of the reinforcing member 10 and the mobile crane 20 required for the bridge superstructure removal method according to the first embodiment is completed (front view seen from the bridge axis direction). 上部工62の既設床版66の部位のうち、既設主桁64の上方に位置する部位に孔66Aを離散的に設けた状態を示す正面図(橋軸方向から見た正面図)A front view showing a state in which holes 66A are discretely provided in a portion of the existing floor slab 66 of the superstructure 62 located above the existing main girder 64 (front view viewed from the bridge axis direction). 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 本発明の第1実施形態に係る橋梁上部工撤去工法の一工程を模式的に示す側面図FIG. 2 is a side view schematically showing one step of the bridge superstructure removal method according to the first embodiment of the present invention. 上部工62の切断位置62Xにおける曲げモーメントを減少させる一方法を模式的に示す側面図FIG. 4 is a side view schematically showing one method of reducing the bending moment at the cutting position 62X of the superstructure 62; 上部工62の切断位置62Xにおける曲げモーメントを減少させる一方法を模式的に示す側面図FIG. 4 is a side view schematically showing one method of reducing the bending moment at the cutting position 62X of the superstructure 62; 切断位置62Xで上部工62を切断した後、補強部材10の撤去対象径間68の中央寄りの部位にも接合部材12を設け、センターホールジャッキ96を撤去した状態を模式的に示す側面図FIG. 11 is a side view schematically showing a state in which, after the superstructure 62 is cut at the cutting position 62X, the joining member 12 is also provided at a portion near the center of the removal target span 68 of the reinforcing member 10, and the center hole jack 96 is removed; 第2実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材10および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)FIG. 3 is a front view schematically showing a state in which installation of a reinforcing member 10 and a mobile crane 20, which are necessary when carrying out the bridge superstructure removal method according to the second embodiment, is completed (front view seen from the direction of the bridge axis). 第3実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材30および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)FIG. 11 is a front view schematically showing a state in which the installation of the reinforcing member 30 and the mobile crane 20 required for the method of removing the bridge superstructure according to the third embodiment is completed (front view seen from the direction of the bridge axis). 補強部材30(断面T形の鋼部材30A)をボルト及びナット32で既設主桁64のウェブ64Cに機械的に連結した態様を示す正面図(橋軸方向から見た正面図)Front view (front view seen from the bridge axis direction) showing a mode in which the reinforcement member 30 (steel member 30A having a T-shaped cross section) is mechanically connected to the web 64C of the existing main girder 64 with bolts and nuts 32. 補強部材30(フラットバー30B)を溶接により既設主桁64のウェブ64Cに機械的に連結した態様を示す正面図(橋軸方向から見た正面図)Front view (front view seen from the bridge axis direction) showing a mode in which the reinforcing member 30 (flat bar 30B) is mechanically connected to the web 64C of the existing main girder 64 by welding. 第4実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材30および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)FIG. 11 is a front view (front view seen from the direction of the bridge axis) schematically showing a state in which the installation of the reinforcing member 30 and the mobile crane 20 required for the method of removing the bridge superstructure according to the fourth embodiment is completed;

以下、図面を参照して、本発明の実施形態に係る橋梁上部工撤去工法について詳細に説明する。 Hereinafter, a method for removing a bridge superstructure according to an embodiment of the present invention will be described in detail with reference to the drawings.

(1)第1実施形態
本発明に係る橋梁上部工撤去工法の第1実施形態は、撤去対象径間の上部工の既設主桁および既設床版を同時に撤去する実施形態である。
(1) First Embodiment The first embodiment of the bridge superstructure removal method according to the present invention is an embodiment in which the existing main girders and existing floor slabs of the superstructure of the span to be removed are removed simultaneously.

(1-1)概要の説明
図1は、上部工撤去対象の橋梁60を模式的に示す側面図(橋軸直角方向から見た側面図)である。上部工撤去対象の橋梁60は、その上部工62が下部工74、76、78、80に架設された3径間連続橋であり、以下の説明では、下部工76、78に架設されている上部工62の部位で、下部工76、78の間の撤去対象径間68に位置する部位(以下、撤去対象上部工部位62Aと記すことがある。)を撤去するものとして説明する。ただし、本発明の適用対象の橋梁が連続橋に限定されるわけではない。また、撤去対象径間の両端に位置する下部工については、橋脚であっても橋台であっても本発明は適用可能であり、本発明に係る橋梁上部工撤去工法は、下部工の種類によらず、適用することができる。なお、図1においては、上部工62の既設床版66(図3参照)の記載は省略している。
(1-1) Outline Description FIG. 1 is a side view (side view seen from the direction perpendicular to the bridge axis) schematically showing a bridge 60 from which the superstructure is to be removed. A bridge 60 whose superstructure is to be removed is a three-span continuous bridge in which a superstructure 62 is constructed on substructures 74, 76, 78, and 80. In the following description, it is constructed on substructures 76 and 78. It is assumed that the part of the superstructure 62 located in the removal target span 68 between the substructures 76 and 78 (hereinafter sometimes referred to as the removal target superstructure part 62A) is to be removed. However, the bridges to which the present invention is applied are not limited to continuous bridges. In addition, the present invention can be applied to the substructures located at both ends of the span to be removed, whether they are piers or abutments. can be applied regardless of 1, the description of the existing floor slab 66 (see FIG. 3) of the superstructure 62 is omitted.

また、図1において、隣接径間70は撤去対象径間68の左隣に位置する径間(下部工74、76の間の径間)であり、隣接径間72は撤去対象径間68の右隣に位置する径間(下部工78、80の間の径間)である。 In FIG. 1, the adjacent span 70 is the span located to the left of the target span 68 to be removed (the span between the substructures 74 and 76), and the adjacent span 72 is the span 68 to be removed. This is the span located on the right side (the span between the substructures 78 and 80).

また、橋梁60は跨道橋であり、橋梁60の撤去対象径間68の下方においては、橋梁60の橋軸方向と略直交する方向に道路82が延びているが、後の説明で明らかになるように、本第1実施形態に係る橋梁上部工撤去工法においては橋面上からの作業のみで撤去対象上部工部位62Aを撤去することができ、道路82を含む桁下空間に与える影響を極力抑制した状態で、本第1実施形態に係る橋梁上部工撤去工法は実施可能である。なお、本発明の適用対象の橋梁が跨道橋に限定されるわけではなく、本発明は跨線橋等に対しても好適に適用可能である。 In addition, the bridge 60 is an overpass, and below the removal target span 68 of the bridge 60, the road 82 extends in a direction substantially orthogonal to the bridge axis direction of the bridge 60, which will be clarified later. As described above, in the bridge superstructure removal method according to the first embodiment, the superstructure part 62A to be removed can be removed only by working from above the bridge surface, and the influence on the space under the girder including the road 82 is reduced. The bridge superstructure removal construction method according to the first embodiment can be carried out in a state of being suppressed as much as possible. Note that the bridges to which the present invention is applied are not limited to overpasses, and the present invention can be suitably applied to overpasses and the like.

なお、以下の説明では、上部工を撤去する対象の橋梁60は鋼橋であり、撤去対象の上部工62の既設主桁64(図3参照)は鋼桁であるものとして説明するが、本発明の適用対象の橋梁が鋼橋に限定されるわけではない。 In the following explanation, the bridge 60 from which the superstructure is to be removed is a steel bridge, and the existing main girder 64 (see FIG. 3) of the superstructure 62 to be removed is a steel girder. The bridges to which the invention is applied are not limited to steel bridges.

図2は、本第1実施形態に係る橋梁上部工撤去工法を用いて橋梁60の上部工62の撤去を行うときの代表的な工程を模式的に示す側面図(橋軸直角方向から見た側面図)である。図2においては、上部工62の既設床版66(図3参照)の記載は省略している。図3は、本第1実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材10および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)である。 FIG. 2 is a side view (viewed from a direction perpendicular to the bridge axis) schematically showing a typical process of removing the superstructure 62 of the bridge 60 using the bridge superstructure removal method according to the first embodiment. side view). 2, the description of the existing floor slab 66 (see FIG. 3) of the superstructure 62 is omitted. FIG. 3 is a front view (viewed from the direction of the bridge axis) schematically showing a state in which installation of the reinforcing member 10 and the mobile crane 20 required for the bridge superstructure removal method according to the first embodiment is completed. front view).

本第1実施形態に係る橋梁上部工撤去工法を実施するに際しては、図2および図3に示すように、補強部材10を、橋梁60の橋軸方向に延びるように上部工62の上方に配置し、接合部材12で補強部材10を上部工62の既設主桁64の上フランジ64A上面に取り付けて上部工62を補強する。撤去対象上部工部位62Aを撤去していく際には、撤去対象上部工部位62Aを橋軸直角方向に切断するが、切断後には撤去対象上部工部位62Aは片持ちとなるため、切断前と比較して上部工62の作用断面力の分布が変わり、上部工62上に設置するクレーン等の撤去用に用いる機材・資材等の重量によっては、上部工62に耐荷力が不足する部位が生じる。即ち、補強部材10は、上部工62の切断によって生ずる、上部工62自体の耐荷力不足を、安全性が確保できるレベルまで補うために上部工62に取り付けられる部材であり、そのような補強部材10の材質や構造等は特には限定されず、具体的には例えば、トラス構造の鋼製部材、鈑桁、鋼製箱桁も、上記目的を達成できるものであれば補強部材10として用いることができる。 When carrying out the bridge superstructure removal method according to the first embodiment, as shown in FIGS. 2 and 3, the reinforcing member 10 is arranged above the superstructure 62 so as to extend in the axial direction of the bridge 60. Then, the reinforcing member 10 is attached to the upper surface of the upper flange 64A of the existing main girder 64 of the superstructure 62 with the joining member 12 to reinforce the superstructure 62 . When removing the superstructure part 62A to be removed, the superstructure part 62A to be removed is cut in the direction perpendicular to the bridge axis. In comparison, the distribution of the acting cross-sectional force of the superstructure 62 changes, and depending on the weight of the equipment and materials used for removing the crane or the like installed on the superstructure 62, the superstructure 62 may have insufficient load bearing capacity. . That is, the reinforcing member 10 is a member attached to the superstructure 62 in order to compensate for the lack of load bearing capacity of the superstructure 62 itself caused by cutting the superstructure 62 to a level at which safety can be ensured. The material and structure of 10 are not particularly limited, and specifically, for example, steel members of truss structure, plate girders, and steel box girders can be used as reinforcing member 10 as long as they can achieve the above purpose. can.

補強部材10の配置位置は、図2に示すように、撤去対象径間68の両端部(下部工76、78の上方の位置)を中心として、撤去対象径間68と隣接径間70、72とをそれぞれ跨ぐような位置である。 As shown in FIG. 2, the reinforcing member 10 is arranged in the span 68 to be removed and the adjacent spans 70, 72 centering on both ends of the span 68 to be removed (positions above the substructures 76, 78). It is a position that straddles each.

また、補強部材10を上部工62に取り付ける接合部材12は、上部工62の既設床版66の部位のうち、既設主桁64の上方に位置する部位に離散的に設けた孔66A(図4参照)内に設置し、接合部材12によって、補強部材10の下面と既設主桁64の上フランジ64Aとを連結する。接合部材12としては、具体的には例えば、断面H形の鋼材をリブ鋼板で補強した鋼材等を用いることができる。補強部材10と接合部材12との連結態様および既設主桁64と接合部材12との連結態様は、十分な接合耐力が得られるのであれば特には限定されず、具体的には例えば、ボルト及びナット等を用いた機械的な連結等を採用することができる。 The joint members 12 for attaching the reinforcing member 10 to the superstructure 62 are provided with holes 66A (Fig. 4 ), and the lower surface of the reinforcement member 10 and the upper flange 64A of the existing main girder 64 are connected by the joint member 12. As shown in FIG. Specifically, as the joining member 12, for example, a steel material obtained by reinforcing a steel material having an H-shaped cross section with a rib steel plate can be used. The manner of connection between the reinforcing member 10 and the joint member 12 and the manner of connection between the existing main girder 64 and the joint member 12 are not particularly limited as long as sufficient joint strength can be obtained. A mechanical connection or the like using a nut or the like can be employed.

補強部材10の上面には、橋軸方向に延びる軌条設備14を設けており、軌条設備14には、軌条設備14上を橋軸方向に移動できる移動式クレーン20を設けている。軌条設備14と補強部材10との連結態様は、十分な接合耐力が得られるのであれば特には限定されず、具体的には例えば、ボルト及びナット等を用いた機械的な連結等を採用することができる。本第1実施形態では、補強部材10と軌条設備14とは、別々の部材としているが、補強部材10に軌条設備としての機能も備えさせ、補強部材10が軌条設備を兼ねるようにしてもよく、具体的には例えば、補強部材10に軌条設備14を予め取り付けておき、補強部材10の設置と同時に軌条設備14が設置されるようにしてもよい。 A rail facility 14 extending in the direction of the bridge axis is provided on the upper surface of the reinforcing member 10, and the rail facility 14 is provided with a mobile crane 20 capable of moving on the rail facility 14 in the direction of the bridge axis. The form of connection between the rail equipment 14 and the reinforcing member 10 is not particularly limited as long as a sufficient joint strength can be obtained. Specifically, for example, a mechanical connection using bolts and nuts, etc., is adopted. be able to. In the first embodiment, the reinforcing member 10 and the rail equipment 14 are separate members, but the reinforcing member 10 may also function as the rail equipment so that the reinforcing member 10 also serves as the rail equipment. Specifically, for example, the rail equipment 14 may be attached to the reinforcing member 10 in advance, and the rail equipment 14 may be installed simultaneously with the installation of the reinforcing member 10 .

撤去対象上部工部位62Aの所定撤去部位62A1(撤去対象上部工部位62Aのうち、撤去対象径間68の中央寄りの端部部位)を撤去する際には、移動式クレーン20を補強部材10の撤去対象径間68の中央寄りの端部付近に移動させて、その位置において、移動式クレーン20で、撤去対象上部工部位62Aの所定撤去部位62A1を支持した状態(図2の右側の移動式クレーン20参照)で、所定撤去部位62A1を切り離し、切り離した所定撤去部位62A1を移動式クレーン20で吊り上げて撤去する(図2の左側の移動式クレーン20参照)。 When removing the predetermined removal portion 62A1 of the removal target superstructure portion 62A (the end portion near the center of the removal target span 68 of the removal target superstructure portion 62A), the mobile crane 20 is placed on the reinforcing member 10. It is moved to the vicinity of the central end of the span 68 to be removed, and at that position, the mobile crane 20 supports the predetermined removal portion 62A1 of the superstructure portion 62A to be removed (the mobile crane on the right side of FIG. 2). crane 20), the predetermined removal portion 62A1 is separated, and the separated predetermined removal portion 62A1 is lifted and removed by the mobile crane 20 (see the mobile crane 20 on the left side of FIG. 2).

撤去対象上部工部位62Aの所定撤去部位62A1の撤去を終えた後、移動式クレーン20を撤去対象径間68の端部方向(下部工76、78に近づく方向)に引き戻し、撤去対象上部工部位62Aの次の撤去対象部位62A2を切り離して撤去する。次の撤去対象部位62A2を切り離して撤去する際には、次の撤去対象部位62A2の上方に位置する補強部材10の端部部位10Aを同時に撤去してもよく、あるいは次の撤去対象部位62A2の上方に位置する補強部材10の端部部位10Aを撤去した後に次の撤去対象部位62A2の撤去を行ってもよい。 After completing the removal of the predetermined removal portion 62A1 of the removal target superstructure portion 62A, the mobile crane 20 is pulled back in the direction of the end of the removal target span 68 (direction approaching the substructures 76, 78) to remove the superstructure portion to be removed. A part to be removed 62A2 next to 62A is separated and removed. When separating and removing the next part to be removed 62A2, the end part 10A of the reinforcing member 10 located above the next part to be removed 62A2 may be removed at the same time, or the next part to be removed 62A2 may be removed. After removing the end portion 10A of the reinforcing member 10 located above, the next removal target portion 62A2 may be removed.

(1-2)各工程についての説明
図5~図11は、本発明の第1実施形態に係る橋梁上部工撤去工法の各工程を模式的に示す側面図(上部工撤去対象の橋梁60を側方(橋軸直角方向)から見た側面図)である。なお、図5~図11においては、上部工62の既設床版66(図3参照)の記載は省略している。
(1-2) Description of Each Process FIGS. 5 to 11 are side views schematically showing each process of the bridge superstructure removal method according to the first embodiment of the present invention. is a side view seen from the side (perpendicular to the bridge axis). 5 to 11, the description of the existing floor slab 66 (see FIG. 3) of the superstructure 62 is omitted.

図5~図11を参照しつつ、本実施形態に係る橋梁架け替え工法の各工程(ステップS1~S6)について説明する。 Each step (steps S1 to S6) of the bridge replacement construction method according to the present embodiment will be described with reference to FIGS. 5 to 11. FIG.

<ステップS1>
図5に示すように、上部工62の所定の範囲(下部工76、78の上方の位置を中心とする所定の範囲)の上方に、補強部材10を橋梁60の橋軸方向に延びるように配置し、接合部材12(図2、3参照)で上部工62の既設主桁64に取り付けて上部工62を補強するとともに、図5に示すように、隣接径間70、72の端部近傍の上部工62の部位(下部工74、80近傍の部位)の上方に、橋梁60の上部工62の転倒を防ぐための重しとしての役割であるカウンターウェイト50を設ける。ただし、カウンターウェイト50は、他の構成により上部工62の転倒が既に防止されている場合には設ける必要がない。また、カウンターウェイト50を設けることに替えて、上部工62と隣り合う上部工84、86の端部に、上部工62の端部をそれぞれ連結して、橋梁60の上部工の連続化を行ってもよい。
<Step S1>
As shown in FIG. 5, the reinforcing member 10 extends in the longitudinal direction of the bridge 60 above a predetermined range of the superstructure 62 (a predetermined range centered on positions above the substructures 76 and 78). and attached to the existing main girder 64 of the superstructure 62 with the joint members 12 (see FIGS. 2 and 3) to reinforce the superstructure 62, and as shown in FIG. A counterweight 50 is provided above the portion of the superstructure 62 of the bridge 60 (the portion near the substructures 74 and 80) as a weight for preventing the superstructure 62 of the bridge 60 from overturning. However, the counterweight 50 need not be provided if the superstructure 62 is already prevented from tipping over by another configuration. Further, instead of providing the counterweight 50, the ends of the superstructure 62 are connected to the ends of the superstructures 84 and 86 adjacent to the superstructure 62, respectively, thereby making the superstructure of the bridge 60 continuous. may

<ステップS2>
ステップS1で補強部材10を上部工62の所定の範囲に取り付けるとともに、必要に応じてカウンターウェイト50を設けた後、図6に示すように、撤去対象径間68の中心位置(切断位置62X)で上部工62を橋軸直角方向に切断する。上部工62の切断には、ワイヤーソー、ウォールソー、ガス切断等を用いてもよい。なお、上部工62の「切断」には、ボルト継手を有する鋼主桁の場合、ボルト継手を取り外して、橋軸方向に連結されていた鋼主桁同士を切り離すことも含まれる。
<Step S2>
After attaching the reinforcing member 10 to a predetermined range of the superstructure 62 in step S1 and providing the counterweight 50 as necessary, as shown in FIG. , the superstructure 62 is cut in the direction perpendicular to the bridge axis. A wire saw, wall saw, gas cutting, or the like may be used to cut the superstructure 62 . In the case of steel main girders having bolted joints, "cutting" the superstructure 62 also includes removing the bolted joints to separate the steel main girders that have been connected in the bridge axis direction.

上部工62を切断する際には、切断位置62Xにおける曲げモーメントを減少させた状態で切断することが安全面で好ましい。切断位置62Xにおける曲げモーメントを減少させる際には、具体的には例えば、図12に示すように、上部工62の既設主桁64の上フランジ64A上面に、切断位置62Xを挟むようにブラケット88を取り付け、取り付けたブラケット88の間にジャッキ90を配置して、既設主桁64の上フランジ64A(切断位置62X近傍の上フランジ64A)に引張力を加えるとともに、上部工62の既設主桁64の下フランジ64B下面に、切断位置62Xを挟むようにブラケット92を取り付け、取り付けたブラケット92の橋軸方向外側の面にセンターホールジャッキ94を定着させて、既設主桁64の下フランジ64B(切断位置62X近傍の下フランジ64B)に圧縮力を加えるようにしてもよい。ただし、前記引張力および前記圧縮力を加える前に、ブラケット88、92の間に補剛材64Dを上下方向に配置して、補剛材64Dの側部を既設主桁64のウェブ64Cに取り付け、補剛材64Dの上端部を既設主桁64の上フランジ64Aの下面に取り付け、補剛材64Dの下端部を既設主桁64の下フランジ64Bの上面に取り付けておく。図12において、符号94Aはセンターホールジャッキ94のテンションロッドであり、符号94Bはセンターホールジャッキ94の定着体である。 When cutting the superstructure 62, it is preferable from the standpoint of safety to cut in a state in which the bending moment at the cutting position 62X is reduced. Specifically, when reducing the bending moment at the cutting position 62X, for example, as shown in FIG. , a jack 90 is placed between the attached brackets 88 to apply tensile force to the upper flange 64A of the existing main girder 64 (upper flange 64A near the cutting position 62X), and the existing main girder 64 of the superstructure 62 A bracket 92 is attached to the lower surface of the lower flange 64B so as to sandwich the cut position 62X, a center hole jack 94 is fixed to the outer surface of the attached bracket 92 in the bridge axis direction, and the lower flange 64B of the existing main girder 64 (cut A compressive force may be applied to the lower flange 64B) near location 62X. However, before applying the tensile force and the compressive force, the stiffener 64D is placed vertically between the brackets 88 and 92, and the side of the stiffener 64D is attached to the web 64C of the existing main girder 64. , the upper end of the stiffener 64D is attached to the lower surface of the upper flange 64A of the existing main girder 64, and the lower end of the stiffener 64D is attached to the upper surface of the lower flange 64B of the existing main girder 64. In FIG. 12, reference numeral 94A denotes a tension rod of the center hole jack 94, and reference numeral 94B denotes a fixing member of the center hole jack 94. As shown in FIG.

また、図13に示すように、補強部材10の撤去対象径間68の中央寄りの部位において接合部材12を設けないようにするとともに、補強部材10の撤去対象径間68の中央寄りの端部とその下方の上部工62の部位との間に、それらをお互いに近づける方向に力を加えるセンターホールジャッキ96を上下方向に設けて、上部工62の中央部に上向きの力を加えて、切断位置62Xにおける曲げモーメントを減少させた状態にして、切断位置62Xで上部工62を橋軸直角方向に切断してもよい。このようにした場合には、切断位置62Xで上部工62を橋軸直角方向に切断した後に、図14に示すように、補強部材10の撤去対象径間68の中央寄りの部位にも、接合部材12を設け、センターホールジャッキ96を撤去する。 In addition, as shown in FIG. 13, the joining member 12 is not provided at a portion near the center of the removal target span 68 of the reinforcing member 10, and the end portion near the center of the removal target span 68 of the reinforcing member 10 is removed. and the part of the superstructure 62 below it, a center hole jack 96 is provided in the vertical direction to apply force in a direction to bring them closer together, and an upward force is applied to the central part of the superstructure 62 to cut. The superstructure 62 may be cut in the direction perpendicular to the bridge axis at the cutting position 62X with the bending moment at the position 62X reduced. In this case, after cutting the superstructure 62 in the direction perpendicular to the bridge axis at the cutting position 62X, as shown in FIG. The member 12 is provided and the center hole jack 96 is removed.

<ステップS3>
補強部材10の上に設けた軌条設備14(図2参照)に移動式クレーン20を取り付け、移動式クレーン20を補強部材10の撤去対象径間68の中央寄りの端部付近に移動させて、その位置において、移動式クレーン20で、撤去対象上部工部位62Aの所定撤去部位62A1を支持した状態(図7の右側の移動式クレーン20参照)で、所定撤去部位62A1を切り離し、切り離した所定撤去部位62A1を移動式クレーン20で吊り上げて撤去する(図7の左側の移動式クレーン20参照)。
<Step S3>
A mobile crane 20 is attached to the rail equipment 14 (see FIG. 2) provided on the reinforcing member 10, and the mobile crane 20 is moved near the center end of the removal target span 68 of the reinforcing member 10, At that position, with the mobile crane 20 supporting the predetermined removal portion 62A1 of the superstructure portion 62A to be removed (see the mobile crane 20 on the right side of FIG. 7), the predetermined removal portion 62A1 is separated, and the separated predetermined removal is performed. The portion 62A1 is lifted by the mobile crane 20 and removed (see the left mobile crane 20 in FIG. 7).

撤去対象上部工部位62Aの所定撤去部位62A1を撤去する際には、図8に模式的に示すように、移動式クレーン20で吊り上げた所定撤去部位62A1を台車22上に吊り降ろし、台車22を軌条設備14に沿って隣接径間70、72の中央寄りの位置に移動させ、隣接径間70、72の上部工62の上に設けたクレーン24で、台車22上の所定撤去部位62A1をトレーラー26に積み込み、撤去する。 When removing the predetermined removal portion 62A1 of the superstructure portion 62A to be removed, as schematically shown in FIG. It is moved to a position near the center of the adjacent spans 70 and 72 along the rail equipment 14, and the predetermined removal portion 62A1 on the truck 22 is moved to a trailer by the crane 24 provided on the superstructure 62 of the adjacent spans 70 and 72. 26 to be loaded and removed.

<ステップS4>
撤去対象上部工部位62Aの所定撤去部位62A1の撤去を終えた後、移動式クレーン20を撤去対象径間68の端部方向(下部工76、78に近づく方向)に引き戻し、撤去対象上部工部位62Aの次の撤去対象部位62A2を切り離して撤去するが、次の撤去対象部位62A2を切り離す前に、図9に示すように、次の撤去対象部位62A2の上方に位置する補強部材10の端部部位10Aを撤去する。そして、その後に上部工62の次の撤去対象部位62A2の撤去を行う。
<Step S4>
After completing the removal of the predetermined removal portion 62A1 of the removal target superstructure portion 62A, the mobile crane 20 is pulled back in the direction of the end of the removal target span 68 (direction approaching the substructures 76, 78) to remove the superstructure portion to be removed. The next part to be removed 62A2 of 62A is separated and removed, but before separating the next part to be removed 62A2, as shown in FIG. Remove portion 10A. After that, the next part to be removed 62A2 of the superstructure 62 is removed.

なお、次の撤去対象部位62A2を切り離して撤去する際に、次の撤去対象部位62A2の上方に位置する補強部材10の端部部位10Aを同時に撤去してもよい。 When cutting off and removing the next part to be removed 62A2, the end part 10A of the reinforcing member 10 located above the next part to be removed 62A2 may be removed at the same time.

<ステップS5>
ステップS4を繰り返して、撤去対象径間68に位置する撤去対象上部工部位62Aの全ての撤去を行う。図10は、撤去対象径間68に位置する撤去対象上部工部位62Aの全ての撤去を終えた後の状態を模式的に示す側面図である。
<Step S5>
Step S4 is repeated to remove all of the superstructure parts 62A to be removed located in the span 68 to be removed. FIG. 10 is a side view schematically showing a state after removal of all of the superstructure part 62A to be removed located in the span 68 to be removed is finished.

<ステップS6>
ステップS5で撤去対象径間68に位置する撤去対象上部工部位62Aの全ての撤去を終えた後、隣接径間70、72の上部工62の上に残った補強部材10と移動式クレーン20を撤去して、本第1実施形態に係る橋梁上部工撤去工法の実施が完了する。図11は、本第1実施形態に係る橋梁上部工撤去工法の橋梁60に対する実施が完了した後の状態を模式的に示す側面図である。
<Step S6>
After removing all of the superstructure part 62A to be removed located in the span 68 to be removed in step S5, the reinforcing member 10 and the mobile crane 20 remaining on the superstructure 62 in the adjacent spans 70 and 72 are removed. After removal, the bridge superstructure removal method according to the first embodiment is completed. FIG. 11 is a side view schematically showing a state after the bridge superstructure removal method according to the first embodiment has been applied to the bridge 60. As shown in FIG.

(1-3)作用効果
以上説明したように、本第1実施形態に係る橋梁上部工撤去工法で用いる機材である補強部材10、接合部材12、軌条設備14、および移動式クレーン20、ならびに台車22、クレーン24、トレーラー26は、いずれも、上部工62の既設主桁64の上方に位置しており、本第1実施形態に係る橋梁上部工撤去工法では、橋面上からの作業のみで橋梁60の撤去対象上部工部位62Aを撤去することができる。
(1-3) Effects As described above, the reinforcing member 10, the joint member 12, the rail equipment 14, the mobile crane 20, and the truck, which are the equipment used in the bridge superstructure removal method according to the first embodiment. 22, crane 24, and trailer 26 are all located above the existing main girder 64 of the superstructure 62, and the method for removing the superstructure of the bridge according to the first embodiment requires only work from above the bridge surface. The removal target superstructure part 62A of the bridge 60 can be removed.

また、本第1実施形態では、ステップS1で補強部材10を上部工62の所定の範囲に取り付けた後、ステップS3で移動式クレーン20を設置しており、補強部材10は、移動式クレーン20の重量に対しても耐荷力を確保できるように設けられる。 In addition, in the first embodiment, after the reinforcing member 10 is attached to the predetermined range of the superstructure 62 in step S1, the mobile crane 20 is installed in step S3, and the reinforcing member 10 is attached to the mobile crane 20 It is provided so that the load-bearing capacity can be secured even for the weight of

(2)第2実施形態
先に説明した第1実施形態は、撤去対象径間68の上部工62(撤去対象上部工部位62A)の既設主桁64および既設床版66を同時に撤去する実施形態であったが、本発明に係る橋梁上部工撤去工法の第2実施形態は、撤去対象上部工部位62Aの既設床版66の撤去を先に行った後、既設主桁64の撤去を行う実施形態であり、既設床版66の撤去後に残った既設主桁64の撤去を行う際に実施する実施形態である。
(2) Second Embodiment The first embodiment described above is an embodiment in which the existing main girder 64 and the existing floor slab 66 of the superstructure 62 (removal target superstructure portion 62A) of the removal target span 68 are removed at the same time. However, in the second embodiment of the bridge superstructure removal method according to the present invention, the existing main girder 64 is removed after removing the existing floor slab 66 of the superstructure part 62A to be removed. This embodiment is carried out when removing the existing main girder 64 remaining after the removal of the existing floor slab 66 .

第1実施形態の撤去対象は既設主桁64および既設床版66の両方であって、第1実施形態はその両方を同時に撤去する実施形態であるのに対し、本第2実施形態に係る橋梁上部工撤去工法の撤去対象は、既設床版66の撤去後に残った既設主桁64であり、この点が第1実施形態に係る橋梁上部工撤去工法と異なり、それ以外の点は本第2実施形態に係る橋梁上部工撤去工法は第1実施形態に係る橋梁上部工撤去工法と同様である。 In the first embodiment, both the existing main girder 64 and the existing floor slab 66 are removed. The object to be removed by the superstructure removal method is the existing main girder 64 remaining after the removal of the existing floor slab 66, which is different from the bridge superstructure removal method according to the first embodiment. The bridge superstructure removal method according to the embodiment is the same as the bridge superstructure removal method according to the first embodiment.

本第2実施形態に係る橋梁上部工撤去工法においては、既設床版66の撤去をまず行った後、既設主桁64の補強を行う補強部材10を既設主桁64の上フランジ64Aの上に取り付けるが、撤去対象上部工部位62Aの既設床版66の撤去は、現状で行われている一般的な床版撤去工法で撤去すればよく、橋面上からの作業のみで撤去を行うことができる。 In the bridge superstructure removal method according to the second embodiment, the existing floor slab 66 is first removed, and then the reinforcing member 10 for reinforcing the existing main girder 64 is placed on the upper flange 64A of the existing main girder 64. However, the existing floor slab 66 of the superstructure part 62A to be removed can be removed by a general floor slab removal method that is currently used, and can be removed only from the bridge surface. can.

図15は、本第2実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材10および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)である。補強部材10および移動式クレーン20は、撤去対象上部工部位62Aの既設床版66の撤去を行った後に設置を行うので、図15に示すように、本第2実施形態に係る橋梁上部工撤去工法においては、その実施をする前に、既設床版66はすでに撤去している。 FIG. 15 is a front view (from the direction of the bridge axis) schematically showing a state in which the installation of the reinforcing member 10 and the mobile crane 20 required for the bridge superstructure removal method according to the second embodiment is completed. front view). Since the reinforcing member 10 and the mobile crane 20 are installed after removing the existing floor slab 66 of the superstructure part 62A to be removed, as shown in FIG. In the construction method, the existing floor slab 66 has already been removed before the implementation.

(3)第3実施形態
先に説明した第1および第2実施形態は、上部工62の既設主桁64の上フランジ64Aに接合部材12を介して補強部材10を取り付けて補強を行った上で、撤去対象上部工部位62Aの撤去を行う実施形態であったが、本発明に係る橋梁上部工撤去工法の第3実施形態は、図16に示すように、撤去対象上部工部位62Aの既設主桁64のウェブ64Cに補強部材30を、橋梁60の橋軸方向に延びる方向に取り付けて既設主桁64の補強を行った上で、撤去対象上部工部位62Aの撤去を行う実施形態である。このため、軌条設備14は、図16に示すように、上部工62の既設床版66の上に配置することになる。
(3) Third Embodiment In the first and second embodiments described above, the upper flange 64A of the existing main girder 64 of the superstructure 62 is reinforced by attaching the reinforcing member 10 to the upper flange 64A via the joint member 12. In the third embodiment of the bridge superstructure removal method according to the present invention, as shown in FIG. In this embodiment, the existing main girder 64 is reinforced by attaching the reinforcing member 30 to the web 64C of the main girder 64 in the direction extending in the bridge axis direction of the bridge 60, and then the superstructure part 62A to be removed is removed. . Therefore, the rail equipment 14 is arranged on the existing floor slab 66 of the superstructure 62, as shown in FIG.

それら以外の点は、本第3実施形態は第1実施形態と同様であり、本第3実施形態は、第1実施形態と同様に、既設主桁64および既設床版66を同時に撤去する実施形態である。 Except for these points, the third embodiment is the same as the first embodiment, and in the third embodiment, the existing main girder 64 and the existing floor slab 66 are simultaneously removed as in the first embodiment. form.

補強部材30は、撤去対象上部工部位62Aの既設主桁64のウェブ64Cに取り付けるが、その取り付け位置は、図16に示すように、既設主桁64の上フランジ64Aの近傍下方の位置および下フランジ64Bの近傍上方の位置である。 The reinforcing member 30 is attached to the web 64C of the existing main girder 64 of the superstructure part 62A to be removed. This is the position near and above the flange 64B.

既設主桁64のウェブ64Cに補強部材30を取り付ける態様は、十分な接合耐力が得られるのであれば特には限定されず、具体的には例えば、図17に示すように、補強部材30を断面T形の鋼部材30Aにして、ボルト及びナット32を用いて既設主桁64のウェブ64Cに機械的に連結する態様や、図18に示すように、補強部材30をフラットバー30Bにして、既設主桁64のウェブ64Cに溶接により連結する態様等を採用することができる。 The manner in which the reinforcing member 30 is attached to the web 64C of the existing main girder 64 is not particularly limited as long as sufficient joint strength can be obtained. Specifically, for example, as shown in FIG. A T-shaped steel member 30A is mechanically connected to the web 64C of the existing main girder 64 using bolts and nuts 32, and as shown in FIG. A mode of connecting to the web 64C of the main girder 64 by welding or the like can be adopted.

補強部材30は、上部工62の上を運搬するとともに、既設床版66の一部に補強部材30が通過できる開口を設けることで、桁下空間を使用せずに取り付け対象の既設主桁64の位置に運び込むことができ、吊り足場等を利用して既設主桁64の所定の位置に設置することが可能である。また、補強部材30は、隣接径間70や隣接径間72の桁下空間を使用して上部工62の上に搬入し、吊り足場等を利用して既設主桁64の所定の位置に設置することも可能である。 The reinforcing member 30 is transported on the superstructure 62, and by providing an opening through which the reinforcing member 30 can pass in a part of the existing floor slab 66, the existing main girder 64 to be attached without using the space under the girder. , and can be installed at a predetermined position on the existing main girder 64 using a suspended scaffold or the like. In addition, the reinforcing member 30 is carried onto the superstructure 62 using the space under the girder of the adjacent span 70 and the adjacent span 72, and installed at a predetermined position of the existing main girder 64 using a suspended scaffold or the like. It is also possible to

(4)第4実施形態
先に説明した第3実施形態は、撤去対象径間68の上部工62(撤去対象上部工部位62A)の既設主桁64および既設床版66を同時に撤去する実施形態であったが、本発明に係る橋梁上部工撤去工法の第4実施形態は、撤去対象上部工部位62Aの既設床版66の撤去を先に行った後、既設主桁64の撤去を行う実施形態であり、既設床版66の撤去後に残った既設主桁64の撤去を行う際に実施する実施形態である。
(4) Fourth Embodiment The third embodiment described above is an embodiment in which the existing main girder 64 and the existing floor slab 66 of the superstructure 62 (removal target superstructure portion 62A) of the removal target span 68 are removed at the same time. However, in the fourth embodiment of the bridge superstructure removal method according to the present invention, the existing main girder 64 is removed after removing the existing floor slab 66 of the superstructure part 62A to be removed. This embodiment is carried out when removing the existing main girder 64 remaining after the removal of the existing floor slab 66 .

第3実施形態の撤去対象は既設主桁64および既設床版66の両方であって、第3実施形態はその両方を同時に撤去する実施形態であるのに対し、本第4実施形態に係る橋梁上部工撤去工法の撤去対象は、既設床版66の撤去後に残った既設主桁64であり、この点が第3実施形態に係る橋梁上部工撤去工法と異なり、それ以外の点は本第4実施形態に係る橋梁上部工撤去工法は第3実施形態に係る橋梁上部工撤去工法と同様であり、本第4実施形態も、第3実施形態と同様、撤去対象上部工部位62Aの既設主桁64のウェブ64Cに補強部材30を取り付けて既設主桁64の補強を行った上で、撤去対象上部工部位62Aの既設主桁64の撤去を行う実施形態である。 In the third embodiment, both the existing main girder 64 and the existing floor slab 66 are removed. The object to be removed by the superstructure removal method is the existing main girder 64 remaining after the removal of the existing floor slab 66, which is different from the bridge superstructure removal method according to the third embodiment. The bridge superstructure removal method according to the embodiment is the same as the bridge superstructure removal method according to the third embodiment. In this embodiment, the reinforcing member 30 is attached to the web 64C of 64 to reinforce the existing main girder 64, and then the existing main girder 64 of the superstructure part 62A to be removed is removed.

本第4実施形態に係る橋梁上部工撤去工法においては、既設床版66の撤去を行った後、または既設床版66の撤去と並行して、既設主桁64のウェブ64Cに補強部材30を取り付けて既設主桁64の補強を行うが、撤去対象上部工部位62Aの既設床版66の撤去は、現状で行われている一般的な床版撤去工法で撤去すればよく、橋面上からの作業のみで撤去を行うことができる。 In the bridge superstructure removal method according to the fourth embodiment, after the existing floor slab 66 is removed or in parallel with the removal of the existing floor slab 66, the reinforcing member 30 is attached to the web 64C of the existing main girder 64. The existing main girder 64 is reinforced by installing it, but the existing floor slab 66 of the superstructure part 62A to be removed can be removed by the general floor slab removal method currently used. Removal can be done only by the work of

図19は、本第4実施形態に係る橋梁上部工撤去工法の実施の際に必要となる補強部材30および移動式クレーン20の設置が完了した状態を模式的に示す正面図(橋軸方向から見た正面図)である。移動式クレーン20は、撤去対象上部工部位62Aの既設床版66の撤去を行った後に設置を行うので、図19に示すように、本第4実施形態に係る橋梁上部工撤去工法においては、その実施をする前に、既設床版66はすでに撤去している。 FIG. 19 is a front view (viewed from the direction of the bridge axis) schematically showing a state in which installation of the reinforcing member 30 and the mobile crane 20, which are necessary for the bridge superstructure removal method according to the fourth embodiment, has been completed. front view). Since the mobile crane 20 is installed after removing the existing floor slab 66 of the superstructure part 62A to be removed, as shown in FIG. The existing floor slab 66 has already been removed before the implementation.

なお、本第4実施形態において、既設主桁64のウェブ64Cに補強部材30を取り付ける態様は、第3実施形態と同様である。 In addition, in the fourth embodiment, the aspect of attaching the reinforcing member 30 to the web 64C of the existing main girder 64 is the same as in the third embodiment.

10、30…補強部材
10A…端部部位
12…接合部材
14…軌条設備
20…移動式クレーン
22…台車
24…クレーン
26…トレーラー
30A…断面T形の鋼部材
30B…フラットバー
32…ボルト及びナット
50…カウンターウェイト
60…橋梁
62、84、86…上部工
62A…撤去対象上部工部位
62A1…所定撤去部位
62A2…次の撤去対象部位
62X…切断位置
64…既設主桁
64A…上フランジ
64B…下フランジ
64C…ウェブ
64D…補剛材
66…既設床版
66A…孔
68…撤去対象径間
70、72…隣接径間
74、76、78、80…下部工
82…道路
88、92…ブラケット
90…ジャッキ
94、96…センターホールジャッキ
94A…テンションロッド
94B…定着体
DESCRIPTION OF SYMBOLS 10, 30... Reinforcement member 10A... End part 12... Joint member 14... Rail installation 20... Mobile crane 22... Carriage 24... Crane 26... Trailer 30A... Steel member of T-shaped cross section 30B... Flat bar 32... Bolt and nut 50... Counterweight 60... Bridge 62, 84, 86... Superstructure 62A... Superstructure part to be removed 62A1... Predetermined removal part 62A2... Next part to be removed 62X... Cutting position 64... Existing main girder 64A... Upper flange 64B... Lower Flange 64C Web 64D Stiffener 66 Existing floor slab 66A Hole 68 Spans to be removed 70, 72 Adjacent spans 74, 76, 78, 80 Substructure 82 Roads 88, 92 Brackets 90 Jacks 94, 96 Center hole jack 94A Tension rod 94B Fixing body

Claims (9)

既設主桁を有する橋梁の上部工の所定位置を切断して前記上部工を撤去する橋梁上部工撤去工法であって、
撤去対象径間およびその撤去対象径間に隣接する隣接径間の前記上部工を補強する補強部材を、前記撤去対象径間と前記隣接径間とを跨ぐように前記橋梁の橋軸方向に延びる方向に設置する補強部材設置工程と、
前記上部工の上方にクレーンを設置するクレーン設置工程と、
前記クレーン設置工程で設置されたクレーンで、前記撤去対象径間の撤去対象である前記上部工の所定部位を支持した状態で、前記撤去対象径間の前記上部工の前記所定位置を切断する切断工程と、
前記切断工程により切り離された前記上部工の前記所定部位を、前記クレーンで撤去する撤去工程と、
を有することを特徴とする橋梁上部工撤去工法。
A bridge superstructure removal method for removing a superstructure of a bridge having an existing main girder by cutting a predetermined position of the superstructure,
A reinforcing member for reinforcing the superstructure of the span to be removed and the adjacent span adjacent to the span to be removed extends in the axial direction of the bridge so as to straddle the span to be removed and the adjacent span. A step of installing a reinforcing member installed in a direction;
a crane installation step of installing a crane above the superstructure;
The crane installed in the crane installation step cuts the predetermined position of the superstructure in the removal target span while supporting the predetermined portion of the superstructure to be removed in the removal target span. process and
a removing step of removing the predetermined portion of the superstructure separated by the cutting step with the crane;
A bridge superstructure removal method characterized by having
既設主桁を有する橋梁の上部工の所定位置を切断して前記上部工を撤去する橋梁上部工撤去工法であって、A bridge superstructure removal method for removing a superstructure of a bridge having an existing main girder by cutting a predetermined position of the superstructure,
撤去対象径間およびその撤去対象径間に隣接する隣接径間の前記上部工を補強する補強部材を、前記撤去対象径間と前記隣接径間とを跨ぐように前記橋梁の橋軸方向に延びる方向に設置する補強部材設置工程と、 A reinforcing member for reinforcing the superstructure of the span to be removed and the adjacent span adjacent to the span to be removed extends in the axial direction of the bridge so as to straddle the span to be removed and the adjacent span. A step of installing a reinforcing member installed in a direction;
前記上部工の上方にクレーンを設置するクレーン設置工程と、 a crane installation step of installing a crane above the superstructure;
前記撤去対象径間の前記既設主桁の上フランジに、前記上部工の前記所定位置を間に挟む異なる位置に第1のブラケットをそれぞれ取り付け、取り付けた前記第1のブラケット同士の間にジャッキを配置するとともに、前記撤去対象径間の前記既設主桁の下フランジに、前記上部工の前記所定位置を間に挟む異なる位置に第2のブラケットをそれぞれ取り付け、取り付けた前記第2のブラケット同士の間にジャッキを配置し、上下に位置する前記第1のブラケットと前記第2のブラケットとの間に、側部を前記既設主桁のウェブに取り付けた補剛材を上下方向にそれぞれ配置し、前記補剛材を配置した後に、前記第1のブラケット同士の間に配置した前記ジャッキを伸長させて引張力を前記既設主桁の上フランジに付与し、前記第2のブラケット同士の間に配置した前記ジャッキを収縮させて圧縮力を前記既設主桁の下フランジに付与して、前記上部工の前記所定位置での曲げモーメントを減少させる曲げモーメント減少工程と、 First brackets are attached to the upper flange of the existing main girder of the span to be removed at different positions sandwiching the predetermined position of the superstructure, and a jack is placed between the attached first brackets. In addition, second brackets are attached to the lower flange of the existing main girder in the span to be removed at different positions sandwiching the predetermined position of the superstructure, and the attached second brackets are attached to each other. a jack is arranged between them, stiffeners having side portions attached to the web of the existing main girder are arranged vertically between the first bracket and the second bracket positioned vertically, respectively; After placing the stiffeners, the jacks placed between the first brackets are extended to apply tensile force to the upper flanges of the existing main girder and placed between the second brackets. a bending moment reduction step of contracting the jack to apply a compressive force to the lower flange of the existing main girder to reduce the bending moment of the superstructure at the predetermined position;
前記曲げモーメント減少工程で曲げモーメントを減少させた状態で、前記上部工の前記所定位置を切断する切断工程と、 a cutting step of cutting the predetermined position of the superstructure with the bending moment reduced in the bending moment reducing step;
前記切断工程により切り離された前記上部工の所定部位を、前記クレーンで撤去する撤去工程と、 a removal step of removing a predetermined portion of the superstructure separated by the cutting step with the crane;
を有することを特徴とする橋梁上部工撤去工法。 A bridge superstructure removal method characterized by having
前記補強部材設置工程では、前記補強部材を、前記撤去対象径間および前記隣接径間の前記上部工の上方に、前記既設主桁の上フランジ上面に前記橋梁の橋軸方向に延びる方向に離散的に配置された接合部材を介して設置することを特徴とする請求項1または2に記載の橋梁上部工撤去工法。 In the reinforcing member installation step, the reinforcing members are dispersed above the superstructure between the span to be removed and the adjacent span in a direction extending in the axial direction of the bridge on the upper surface of the upper flange of the existing main girder. 3. The method for removing a bridge superstructure according to claim 1 or 2, wherein the bridge superstructure is installed through joint members that are arranged at intervals . 記補強部材設置工程では、前記撤去対象径間および前記隣接径間の前記上部工の前記既設主桁のウェブに、前記補強部材を前記橋梁の橋軸方向に延びる方向に設置することを特徴とする請求項1または2に記載の橋梁上部工撤去工法。 In the reinforcing member installing step, the reinforcing member is installed on the web of the existing main girder of the superstructure between the span to be removed and the adjacent span in a direction extending in the axial direction of the bridge. The bridge superstructure removal construction method according to claim 1 or 2. 前記補強部材設置工程で設置した前記補強部材の上方に軌条設備を設置する軌条設備設置工程をさらに有し、
前記クレーン設置工程では、前記軌条設備設置工程で設置した前記軌条設備に、前記クレーンを前記軌条設備に沿って移動可能に設置することを特徴とする請求項1~のいずれかに記載の橋梁上部工撤去工法。
further comprising a rail facility installation step of installing a rail facility above the reinforcing member installed in the reinforcing member installing step;
4. The bridge according to any one of claims 1 to 3 , wherein in the crane installation step, the crane is installed on the rail equipment installed in the rail equipment installation step so as to be movable along the rail equipment. Superstructure removal method.
前記補強部材設置工程で設置した前記補強部材は、前記橋梁の橋軸方向に前記クレーンが移動できるようにする軌条設備も備えていることを特徴とする請求項3に記載の橋梁上部工撤去工法。 4. The method for removing a bridge superstructure according to claim 3, wherein the reinforcing member installed in the reinforcing member installing step also includes a rail facility that enables the crane to move in the direction of the bridge axis of the bridge. . 前記クレーン設置工程で設置した前記クレーンを、前記撤去対象径間の中央寄りの、前記補強部材の端部付近に移動させるクレーン移動工程をさらに有し、
前記撤去工程では、前記切断工程により切り離された前記上部工の前記所定部位を、前記クレーン移動工程で移動させた前記クレーンで撤去することを特徴とする請求項5または6に記載の橋梁上部工撤去工法。
further comprising a crane moving step of moving the crane installed in the crane installing step to the vicinity of the end of the reinforcing member near the center of the removal target span;
7. The bridge superstructure according to claim 5 or 6, wherein in the removing step, the predetermined portion of the superstructure separated in the cutting step is removed by the crane moved in the crane moving step. Removal method.
前記切断工程により切り離される前記上部工の前記所定部位の上方に位置する前記補強部材の部位を、前記補強部材の他の部位から切り離して撤去した後、前記上部工の前記所定部位を前記切断工程で切り離すことを特徴とする請求項に記載の橋梁上部工撤去工法。 After the portion of the reinforcing member located above the predetermined portion of the superstructure cut off in the cutting step is separated from the other portion of the reinforcing member and removed, the predetermined portion of the superstructure is removed in the cutting step. 4. The bridge superstructure removal construction method according to claim 3 , wherein the bridge superstructure is separated by . 前記撤去工程では、前記切断工程により切り離される前記上部工の前記所定部位だけでなく、該所定部位の上方に位置する前記補強部材の部位も同時に撤去することを特徴とする請求項に記載の橋梁上部工撤去工法。 4. The method according to claim 3 , wherein in the removing step, not only the predetermined portion of the superstructure separated by the cutting step but also the portion of the reinforcing member located above the predetermined portion is removed at the same time. Bridge superstructure removal method.
JP2019150491A 2019-08-20 2019-08-20 Bridge superstructure removal method Active JP7172916B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019150491A JP7172916B2 (en) 2019-08-20 2019-08-20 Bridge superstructure removal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019150491A JP7172916B2 (en) 2019-08-20 2019-08-20 Bridge superstructure removal method

Publications (2)

Publication Number Publication Date
JP2021031884A JP2021031884A (en) 2021-03-01
JP7172916B2 true JP7172916B2 (en) 2022-11-16

Family

ID=74676758

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019150491A Active JP7172916B2 (en) 2019-08-20 2019-08-20 Bridge superstructure removal method

Country Status (1)

Country Link
JP (1) JP7172916B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110629677B (en) * 2019-09-29 2021-01-26 中铁大桥局集团有限公司 Method for erecting section steel beam on pier top short slideway beam
CN112921841B (en) * 2021-04-26 2023-04-07 河南省交通规划设计研究院股份有限公司 Method for quickly dismantling upper structure of deck through type arch bridge
CN113944115B (en) * 2021-11-15 2023-03-31 上海市基础工程集团有限公司 Full-automatic integrated bridge dismantling machine for dismantling concrete main beam of large-span cable-stayed bridge
CN114541286B (en) * 2021-12-31 2023-09-05 宁波市政工程建设集团股份有限公司 Sectional block dismantling construction method for cast-in-situ prestressed box girder
CN114263129B (en) * 2021-12-31 2023-09-05 宁波市政工程建设集团股份有限公司 Bridge superstructure dismantling construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006144282A (en) 2004-11-17 2006-06-08 Mitsubishi Heavy Ind Ltd Bridge removing method
JP2007113376A (en) 2005-10-19 2007-05-10 Matsuoka Chiteki Shoyuken Jimusho:Kk Method of dismantling bridge girder
JP2007191893A (en) 2006-01-18 2007-08-02 Shidagumi:Kk Bridge removing method
JP2013174075A (en) 2012-02-24 2013-09-05 Nippon Steel Topy Bridge Co Ltd Reconstruction technique for bridge girder
JP2016008406A (en) 2014-06-23 2016-01-18 首都高速道路株式会社 Temporary bearing method for main girder in floor slab replacement work with composite girder, floor slab replacement method with composite girder, and temporary bearing structure for main girder in floor slab replacement work with composite girder
JP2018009371A (en) 2016-07-14 2018-01-18 オリエンタル白石株式会社 Deck slab replacement method for steel composite girder
JP2018059311A (en) 2016-10-04 2018-04-12 Jfeエンジニアリング株式会社 Floor slab replacement method
JP2019132008A (en) 2018-01-30 2019-08-08 Jfeエンジニアリング株式会社 Carry-in/out method and carry-in/out facility

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006144282A (en) 2004-11-17 2006-06-08 Mitsubishi Heavy Ind Ltd Bridge removing method
JP2007113376A (en) 2005-10-19 2007-05-10 Matsuoka Chiteki Shoyuken Jimusho:Kk Method of dismantling bridge girder
JP2007191893A (en) 2006-01-18 2007-08-02 Shidagumi:Kk Bridge removing method
JP2013174075A (en) 2012-02-24 2013-09-05 Nippon Steel Topy Bridge Co Ltd Reconstruction technique for bridge girder
JP2016008406A (en) 2014-06-23 2016-01-18 首都高速道路株式会社 Temporary bearing method for main girder in floor slab replacement work with composite girder, floor slab replacement method with composite girder, and temporary bearing structure for main girder in floor slab replacement work with composite girder
JP2018009371A (en) 2016-07-14 2018-01-18 オリエンタル白石株式会社 Deck slab replacement method for steel composite girder
JP2018059311A (en) 2016-10-04 2018-04-12 Jfeエンジニアリング株式会社 Floor slab replacement method
JP2019132008A (en) 2018-01-30 2019-08-08 Jfeエンジニアリング株式会社 Carry-in/out method and carry-in/out facility

Also Published As

Publication number Publication date
JP2021031884A (en) 2021-03-01

Similar Documents

Publication Publication Date Title
JP7172916B2 (en) Bridge superstructure removal method
US20220333320A1 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
JP7346246B2 (en) Heavy object moving method using heavy object moving device and heavy object moving device
JP5319216B2 (en) Bridge girder erection device and bridge girder erection method
JP6180376B2 (en) Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
JP6793542B2 (en) Floor slab erection method and floor slab erection equipment
JP4033870B2 (en) How to build a bridge girder
JP5890060B1 (en) Bridge dismantling method using erection girder
JP2018059311A (en) Floor slab replacement method
CN108824199A (en) The Arch Bridge Construction method of underneath type Hanging Basket
JP2006077521A (en) Bridge constructing apparatus
JP6493322B2 (en) Floor slab replacement device and floor slab replacement method
JP7185567B2 (en) Bridge pier repair method
JP2008050811A (en) Movable suspended scaffolding apparatus
JP4033871B2 (en) How to build a bridge girder
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
JPH04228710A (en) Road slab for bridge
JP6969909B2 (en) How to reinforce steel synthetic girders
JP2021021252A (en) Viaduct replacing method
JP6672545B2 (en) Removal member removal method and member replacement method
JP2003027404A (en) Method for constructing under-track structure
JP6873435B2 (en) Suspended scaffolding and its erection method
CN114000429A (en) Longitudinal wet joint pouring deformation control method for eccentric half-width steel-concrete combined box girder
JP6740846B2 (en) Floor slab replacement structure and floor slab replacement construction method
JP4755998B2 (en) Cutting and rehabilitating connecting bridges with different distances between buildings

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210909

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220428

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220510

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220630

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20221004

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20221017

R150 Certificate of patent or registration of utility model

Ref document number: 7172916

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150