JP4755998B2 - Cutting and rehabilitating connecting bridges with different distances between buildings - Google Patents

Cutting and rehabilitating connecting bridges with different distances between buildings Download PDF

Info

Publication number
JP4755998B2
JP4755998B2 JP2007001262A JP2007001262A JP4755998B2 JP 4755998 B2 JP4755998 B2 JP 4755998B2 JP 2007001262 A JP2007001262 A JP 2007001262A JP 2007001262 A JP2007001262 A JP 2007001262A JP 4755998 B2 JP4755998 B2 JP 4755998B2
Authority
JP
Japan
Prior art keywords
connecting bridge
cutting
sides
cut
concrete floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2007001262A
Other languages
Japanese (ja)
Other versions
JP2008169552A (en
Inventor
将史 森田
直樹 宮本
英史 奥本
健 山中
弘 杉原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2007001262A priority Critical patent/JP4755998B2/en
Publication of JP2008169552A publication Critical patent/JP2008169552A/en
Application granted granted Critical
Publication of JP4755998B2 publication Critical patent/JP4755998B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、不同沈下等によって建造物間の距離が変化した連絡橋の切断改修方法に関する。   The present invention relates to a method for cutting and repairing a connecting bridge in which the distance between buildings has changed due to uneven settlement or the like.

例えば、埋立による人工島に建設された空港等においては、地盤の不同沈下が発生することを想定し、建造物は、特許文献1,2等に見られるように、ジャッキアップによって沈下修正ができる構造となっている。しかし、互いに離れた場所に建設されている二つの建造物の不同沈下の状況によっては、建造物のジャッキアップによる沈下修正を行っても、建造物間の距離が短くなったり、逆に長くなったりすることがある。   For example, in an airport constructed on an artificial island by landfill, assuming that uneven settlement of the ground occurs, the building can be corrected by jacking up as seen in Patent Documents 1 and 2 etc. It has a structure. However, depending on the situation of uneven settlement of two buildings that are constructed at a distance from each other, even if the settlement of the building is corrected by jacking up the building, the distance between the buildings is shortened or conversely increased. Sometimes.

そのため、このような建造物間に建設される連絡橋には、その一端側にエキスパンションジョイントが設けられているが、建造物間の距離の変化がエキスパンションジョイントによるクリアランスの許容範囲を超えると、連絡橋としての健全な状態を保てないので、何らかの改修工事が必要となる。   Therefore, an expansion joint is provided on one end side of such a connecting bridge constructed between buildings. If the change in the distance between the buildings exceeds the allowable clearance of the expansion joint, the connection bridge will be connected. Since it cannot maintain a sound state as a bridge, some kind of renovation work is required.

この改修工事の方法としては、橋桁を切断し、切り離された橋桁を引き寄せ、切断面を再接続して、連絡橋の長さを縮めるたり、あるいは、逆に、切り離された橋桁を引き離した後、切断面の間に橋桁部材を追加して、連絡橋の長さを伸ばす連絡橋の切断改修方法が考えられる。   The repair work can be done by cutting the bridge girder, pulling the separated bridge girder, reconnecting the cut surfaces, reducing the length of the connecting bridge, or conversely pulling the separated bridge girder apart. A method of cutting and refurbishing a connecting bridge in which a bridge girder member is added between the cut surfaces to increase the length of the connecting bridge can be considered.

この連絡橋の切断改修方法は、連絡橋全体を架け替える場合に比して、工期、工費の両面で極めて有利である。しかしながら、連絡橋の切断改修方法においては、橋桁の大梁を切断した状態で、地震が発生した場合の安全確保が考慮されなければならない。また、切断した橋桁の引寄せ、あるいは、引離しを行うにあたっては、切断面が相互に垂直方向にも水平方向にもずれないように引き寄せる、あるいは、引き離す必要がある。   This method of cutting and refurbishing the connecting bridge is extremely advantageous in terms of construction period and construction cost, compared to the case of replacing the entire connecting bridge. However, in the method of cutting and refurbishing connecting bridges, safety must be considered in the event of an earthquake with the bridge beam girder cut. Further, when pulling or separating the cut bridge girder, it is necessary to draw or separate the cut surfaces so that they do not deviate from each other in the vertical direction or the horizontal direction.

特開平07−324347号公報Japanese Patent Application Laid-Open No. 07-324347 特開2005−146585号公報JP 2005-146585 A

本発明は、上記の点に留意してなされたものであって、その目的とするところは、工事中に地震が発生しても安全を確保できる連絡橋の切断改修方法を提供することにある。   The present invention has been made in consideration of the above points, and an object of the present invention is to provide a method for cutting and repairing a connecting bridge that can ensure safety even if an earthquake occurs during construction. .

上記の目的を達成するために本発明が講じた技術的手段は、次のとおりである。即ち、請求項1に記載の発明は、建造物間に架設された連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを修正する連絡橋の切断改修方法であって、切断された状態においても切断前と略同等な強度を維持できるように、連絡橋の切断予定位置の近くを支持しつつ切断から再接続までの工程を行うことを特徴としている。   The technical means taken by the present invention in order to achieve the above object are as follows. In other words, the invention according to claim 1 cuts the connecting bridge erected between the buildings, moves the cut connecting bridge in the length direction, and then reconnects it to increase the length of the connecting bridge. A method of cutting and rehabilitating a connecting bridge to be corrected, and a process from cutting to reconnection while supporting the vicinity of the planned cutting position of the connecting bridge so that it can maintain substantially the same strength as before cutting even in a disconnected state. It is characterized by performing.

請求項2に記載の発明は、請求項1に記載の建造物間の距離が変化した連絡橋の切断改修方法であって、切断予定位置の近くに、切断前から再接続終了までの間、切断部位相互の垂直方向及び水平方向へのずれを防止するための支持装置を設けて、切断時、切断された連絡橋の移動時、再接続時の何れにおいても、切断部位相互の垂直方向及び水平方向へのずれを防止できるようにしたことを特徴としている。   The invention according to claim 2 is a method for cutting and refurbishing a connecting bridge in which the distance between buildings according to claim 1 is changed, near the planned cutting position and before the end of reconnection, Provide a support device for preventing the vertical and horizontal shifts between the cutting sites, and when cutting, moving the disconnected connecting bridge, and reconnecting, It is characterized by preventing horizontal displacement.

尚、請求項1、2に記載の発明において、連絡橋としては、鉄骨造、鉄骨鉄筋コンクリート造、鉄筋コンクリート造の何れであってもよい。   In the first and second aspects of the invention, the connecting bridge may be any of a steel structure, a steel reinforced concrete structure, and a reinforced concrete structure.

請求項3、4に記載の発明は、何れも、鉄骨鉄筋コンクリート造の連絡橋を対象としており、請求項3に記載の発明は、建造物間に架設された複数本の橋桁用大梁鉄骨と、これらの大梁鉄骨に支持された通路用のコンクリート床とを備えた連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを短縮する連絡橋の切断改修方法であって、切断予定位置のコンクリート床を通路の幅方向中央部側コンクリート床が残された状態にはつり取って、大梁鉄骨の上フランジを露出させ、各々の大梁鉄骨における切断予定位置の両側に位置する上フランジ間にわたって振れ止めを取り付け、且つ、各々の大梁鉄骨における切断予定位置の両側部を連絡橋の下方に設置した仮受構台に仮受ジャッキを介して支持させ、この状態で大梁鉄骨を所定幅にわたって切断除去する一方、切断位置の両側に位置する大梁鉄骨のウエブ間にわたってガイドプレートを取り付け、且つ、切断位置の両側に位置する大梁鉄骨同士を横力保持用の水平ジャッキで連結した状態で、残しておいた前記中央部側コンクリート床をはつり取り、水平ジャッキの除荷後、水平ジャッキの盛り替えを行って、切断された大梁鉄骨同士の引寄せを行い、ガイドプレートの撤去後、切断位置の両側に位置する大梁鉄骨のウエブ同士をスプライスプレートを介してボルト連結すると共に、水平ジャッキを撤去し、切断位置の両側に位置する大梁鉄骨の上,下フランジの溶接後、前記振れ止めを撤去し、しかる後、配筋、コンクリート打設を行って、コンクリート床の切断部位の復旧を行うことを特徴としている。   Each of the inventions according to claims 3 and 4 is directed to a steel-framed reinforced concrete connecting bridge, and the invention according to claim 3 includes a plurality of girder steel beams for bridge girder constructed between buildings, Cut the connecting bridge with the concrete floor for the passage supported by these girder steel frames, move the cut connecting bridge in the length direction, and then reconnect it to shorten the length of the connecting bridge In this method, the concrete floor at the planned cutting position is suspended in a state where the concrete floor at the center in the width direction of the passage is left, and the upper flange of the large beam steel frame is exposed. A steady rest is attached between the upper flanges located on both sides of the planned cutting position of the steel plate, and both sides of the planned cutting position of each girder steel frame are supported via a temporary jack on a temporary support base installed below the connecting bridge. Let In this state, the girder steel frame is cut and removed over a predetermined width, while a guide plate is attached between the webs of the girder steel frame located on both sides of the cutting position, and the girder steel frames located on both sides of the cutting position are used for holding a lateral force. In the state where it is connected with a horizontal jack, the center part side concrete floor that has been left is removed, after unloading the horizontal jack, the horizontal jack is refilled, and the cut large beam steel frames are drawn together, After the guide plate is removed, the large beam steel webs located on both sides of the cutting position are bolted together via the splice plate, the horizontal jack is removed, and the upper and lower flanges of the large beam steel frames located on both sides of the cutting position are removed. After welding, remove the steady rest, and then perform reinforcement and concrete placement to restore the cut section of the concrete floor. It is a symptom.

請求項4に記載の発明は、建造物間に架設された複数本の橋桁用大梁鉄骨と、これらの大梁鉄骨に支持された通路用のコンクリート床とを備えた連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを伸長する連絡橋の切断改修方法であって、切断予定位置のコンクリート床を通路の幅方向中央部側コンクリート床が残された状態にはつり取って、大梁鉄骨の上フランジを露出させ、各々の大梁鉄骨における切断予定位置の両側に位置する上フランジ間にわたって振れ止めを取り付け、且つ、各々の大梁鉄骨における切断予定位置の両側部を連絡橋の下方に設置した仮受構台に仮受ジャッキを介して支持させ、この状態で大梁鉄骨を切断する一方、切断位置の両側に位置する大梁鉄骨のウエブ間にわたってガイドプレートを取り付け、且つ、切断位置の両側に位置する大梁鉄骨同士を引き離し用の水平ジャッキで連結した状態で、残しておいた前記中央部側コンクリート床をはつり取り、水平ジャッキの除荷後、水平ジャッキの盛り替えを行って、切断された大梁鉄骨同士の引離しを行い、引き離された大梁鉄骨間に断面T字状の継足し用大梁材を挿入した後、ガイドプレートを撤去し、継足し用大梁材のウエブとその両側に位置する大梁鉄骨のウエブとをスプライスプレートを介してボルト連結した後、水平ジャッキを撤去し、継足し用大梁材の上フランジとその両側に位置する大梁鉄骨の上フランジとを溶接すると共に、継足し用大梁材のウエブ下端に溶接した下フランジとその両側に位置する大梁鉄骨の下フランジとを溶接した後、前記振れ止めを撤去し、しかる後、配筋、コンクリート打設を行って、コンクリート床の切断部位の復旧を行うことを特徴としている。   The invention according to claim 4 cuts and cuts a connecting bridge including a plurality of bridge girder steel beams installed between buildings and a concrete floor for a passage supported by these girder steel frames. The connecting bridge is cut and repaired by moving the connecting bridge in the length direction and then reconnecting it to extend the length of the connecting bridge. In the state where the concrete floor is left behind, the upper flanges of the steel beams are exposed, and a steady rest is attached between the upper flanges located on both sides of the planned cutting positions of the steel beams. Both sides of the planned cutting position are supported by a temporary receiving frame installed under the connecting bridge via a temporary jack, and in this state the large beam steel frame is cut, while between the large beam steel webs located on both sides of the cutting position. Watt After attaching the guide plate and connecting the large beam steel frames located on both sides of the cutting position with a horizontal jack for separation, the left-side central floor concrete floor is removed, and after unloading the horizontal jack, After changing the horizontal jacks, the separated large beam steel frames are pulled apart, and after inserting the large beam material for the T-shaped cross section between the separated large beam steel frames, the guide plate is removed, After connecting the web of the extra beam material and the web of the big beam steel frame located on both sides of the web via the splice plate, the horizontal jack is removed, and the upper flange of the extra beam material for the extra beam and the large beam steel frame located on both sides thereof are removed. And welding the lower flange welded to the lower end of the web of the extension beam material and the lower flanges of the large beam steel frame located on both sides thereof, Re and removing the stopper, and thereafter, reinforcement, performs concreting, is characterized by performing the recovery of the cleavage site of the concrete floor.

請求項1に記載の発明によれば、切断された状態においても切断前と略同等な強度を維持できるように、の切断予定位置の近くを支持しつつ切断から再接続までの工程を行うので、工事中に地震が発生しても安全を確保できる。   According to the first aspect of the present invention, the steps from cutting to reconnection are performed while supporting the vicinity of the planned cutting position so that substantially the same strength as before cutting can be maintained even in the cut state. Even if an earthquake occurs during construction, safety can be ensured.

請求項2に記載の発明によれば、切断予定位置の近くに、切断前から再接続終了までの間、切断部位相互の垂直方向及び水平方向へのずれを防止するための支持装置を設けたので、切断した連絡橋の引寄せ、あるいは、引離しを行うにあたって、切断面が相互に垂直
方向にも水平方向にもずれないように引き寄せる、あるいは、引き離すことができ、切断部の再接続を容易かつ高精度に行うことができる。
According to the second aspect of the present invention, the support device is provided near the scheduled cutting position to prevent the vertical and horizontal shifts between the cutting parts from before the cutting until the end of the reconnection. Therefore, when pulling or pulling the disconnected bridge, it can be pulled or separated so that the cut surfaces do not deviate vertically or horizontally from each other. It can be performed easily and with high accuracy.

請求項3に記載の発明による連絡橋の切断改修方法によれば、不同沈下等によって建造物間の距離が短くなり、建造物間に架設された連絡橋の長さを短縮する必要が生じた場合、また、請求項4に記載の発明による連絡橋の切断改修方法によれば、不同沈下等によって建造物間の距離が長くなり、建造物間に架設された連絡橋の長さを伸長する必要が生じた場合、夫々、橋桁用大梁鉄骨の切断や通路用コンクリート床の切断に際し、仮設の振れ止め、ガイドプレート、水平ジャッキ等を取り付けることによって、想定する地震の範囲で水平力に対して常に連結された状態で工事を進めることができ、工事中に地震が発生しても安全を確保できるという効果がある。   According to the method for cutting and refurbishing a connecting bridge according to the invention described in claim 3, the distance between the buildings is shortened due to unsettled settlement or the like, and it is necessary to shorten the length of the connecting bridge constructed between the buildings. In this case, according to the cutting and refurbishing method of the connecting bridge according to the invention described in claim 4, the distance between the buildings becomes long due to the unsettled settlement or the like, and the length of the connecting bridge built between the buildings is extended. If necessary, install a temporary steady rest, guide plate, horizontal jack, etc. when cutting the girder steel beams for bridge girders or the concrete floor for passages, and against horizontal forces within the assumed earthquake range. The construction can be carried out in a state of being always connected, and there is an effect that safety can be secured even if an earthquake occurs during the construction.

即ち、請求項3に記載の発明による連絡橋の切断改修方法によれば、橋桁用大梁鉄骨における切断予定位置の両側部を連絡橋の下方に設置した仮受構台に仮受ジャッキを介して支持させるだけでなく、各大梁鉄骨における切断予定位置の両側に位置する上フランジ間にわたって振れ止めを取り付け、しかも、通路の幅方向中央部側コンクリート床を残した状態で、大梁鉄骨を切断するので、大梁鉄骨が所定幅にわたって切断除去されても、連絡橋は、中央部側コンクリート床と振れ止めとで水平方向に連結されていることになる。また、切断した大梁鉄骨の垂直方向のずれについては、仮受ジャッキでレベル調整することができる。   That is, according to the method for cutting and refurbishing a connecting bridge according to the invention described in claim 3, both sides of the planned cutting position of the bridge beam girder steel frame are supported via a temporary receiving jack on a temporary receiving base installed below the connecting bridge. As well as letting the braids cut across the upper flanges located on both sides of the planned cutting position in each girder steel frame, and in addition to cutting the girder steel frame with the concrete floor in the width direction center side left, Even if the girder steel frame is cut and removed over a predetermined width, the connecting bridge is connected in the horizontal direction by the center side concrete floor and the steady rest. Further, the level of the vertical displacement of the cut large beam steel frame can be adjusted with a temporary jack.

そして、前記中央部側コンクリート床をはつり取る前に、切断位置の両側に位置する大梁鉄骨のウエブ間にわたってガイドプレートを取り付け、且つ、切断位置の両側に位置する大梁鉄骨同士を横力保持用の水平ジャッキで連結するので、前記中央部側コンクリート床をはつり取っても、連絡橋は、振れ止めとガイドプレートと水平ジャッキで連結されていることになり、切断前の変形状態からの弾性復元による横力を水平ジャッキで受け止めることができ、切断した大梁鉄骨の水平方向(幅方向)のずれは、振れ止めとガイドプレートとによって防止することができる。   Before the center-side concrete floor is lifted, a guide plate is attached between the webs of the large beam steel frames positioned on both sides of the cutting position, and the large beam steel frames positioned on both sides of the cutting position are used for holding the lateral force. Since it is connected with a horizontal jack, even if the concrete floor on the center side is removed, the connecting bridge will be connected with the steady rest and the guide plate with the horizontal jack, and due to elastic recovery from the deformed state before cutting Lateral force can be received by a horizontal jack, and the horizontal deviation (width direction) of the cut large beam steel frame can be prevented by the steady rest and the guide plate.

水平ジャッキの除荷後は、当該水平ジャッキを切断された大梁鉄骨同士の引寄せに用いる方向に盛り替えて、振れ止めとガイドプレートで連結された状態にある大梁鉄骨同士を引き寄せることになり、ガイドプレートの撤去後は、切断位置の両側に位置する大梁鉄骨のウエブ同士をスプライスプレートを介してボルト連結した後、水平ジャッキを撤去し、切断位置の両側に位置する大梁鉄骨の上,下フランジの溶接後、振れ止めを撤去するので、常に連結された状態で工事が進められることになる。従って、工事中に地震が発生しても安全を確保でき、しかも、切断した大梁鉄骨の引寄せを行うにあたって、切断面が相互に垂直方向にも水平方向にもずれないように引き寄せることができ、切断部の再接続を容易かつ高精度に行うことができる。   After unloading the horizontal jacks, the horizontal jacks are rearranged in the direction used for pulling the cut large beam steels together, and the large beam steels in a state connected by the steady rest and the guide plate are drawn together. After removing the guide plate, after connecting the webs of the large beam steel frames located on both sides of the cutting position with bolts via the splice plate, the horizontal jack is removed, and the upper and lower flanges of the large beam steel frames located on both sides of the cutting position Since the steady rest is removed after welding, the construction is always carried out in a connected state. Therefore, even if an earthquake occurs during construction, safety can be ensured, and when drawing the cut steel beams, the cut surfaces can be drawn so that they do not deviate in the vertical or horizontal direction. The reconnection of the cutting part can be performed easily and with high accuracy.

請求項2に記載の発明による連絡橋の切断改修方法によれば、橋桁用大梁鉄骨における切断予定位置の両側部を連絡橋の下方に設置した仮受構台に仮受ジャッキを介して支持させるだけでなく、各大梁鉄骨における切断予定位置の両側に位置する上フランジ間にわたって振れ止めを取り付け、しかも、通路の幅方向中央部側コンクリート床を残した状態で、大梁鉄骨を切断するので、大梁鉄骨が切断されても、連絡橋は、中央部側コンクリート床と振れ止めとで水平方向に連結されていることになる。また、切断した大梁鉄骨の垂直方向のずれについては、仮受ジャッキでレベル調整することができる。   According to the method for cutting and refurbishing a connecting bridge according to the second aspect of the present invention, only the both sides of the planned cutting position of the bridge beam girder steel frame are supported by the temporary receiving frame installed below the connecting bridge via the temporary receiving jack. Rather than attaching a steady rest between the upper flanges located on both sides of the planned cutting position of each girder steel frame, and cutting the girder steel frame with the concrete floor in the width direction center side left, the girder steel frame is cut. Even if is cut, the connecting bridge is connected in the horizontal direction by the center side concrete floor and the steady rest. Further, the level of the vertical displacement of the cut large beam steel frame can be adjusted with a temporary jack.

そして、前記中央部側コンクリート床をはつり取る前に、切断位置の両側に位置する大梁鉄骨のウエブにガイドプレートを取り付け、且つ、切断位置の両側に位置する大梁鉄骨同士を引き離し用の水平ジャッキで連結するので、前記中央部側コンクリート床をはつり
取っても、連絡橋は、振れ止めとガイドプレートと水平ジャッキで連結されていることになり、切断前の変形状態からの弾性復元による引張力を水平ジャッキで受け止めることができ、切断した大梁鉄骨の水平方向(幅方向)のずれは、振れ止めとガイドプレートとによって防止することができる。
Then, before removing the central concrete floor, a guide plate is attached to the web of the large beam steel frame located on both sides of the cutting position, and the large beam steel frames located on both sides of the cutting position are separated with a horizontal jack for separating them. Because it is connected, the connecting bridge is connected to the steady rest and the guide plate with a horizontal jack even if the concrete floor on the center side is removed, and the tensile force due to elastic recovery from the deformed state before cutting is obtained. The horizontal jack can be received by the horizontal jack, and the horizontal deviation (width direction) of the cut large beam steel frame can be prevented by the steady rest and the guide plate.

水平ジャッキの除荷後は、当該水平ジャッキを切断された大梁鉄骨同士の引離しに用いる方向に盛り替えて、振れ止めとガイドプレートで連結された状態にある大梁鉄骨同士を引き離すことになり、引き離された大梁鉄骨間に断面T字状の継足し用大梁材を挿入した後、ガイドプレートを撤去し、継足し用大梁材のウエブとその両側に位置する大梁鉄骨のウエブとをスプライスプレートを介してボルト連結した後、水平ジャッキを撤去し、継足し用大梁材の上フランジとその両側に位置する大梁鉄骨の上フランジとを溶接すると共に、継足し用大梁材のウエブ下端に溶接した下フランジとその両側に位置する大梁鉄骨の下フランジとを溶接した後、振れ止めを撤去するので、常に連結された状態で工事が進められることになる。従って、工事中に地震が発生しても安全を確保でき、しかも、切断した大梁鉄骨の引離しを行うにあたって、切断面が相互に垂直方向にも水平方向にもずれないように引き離すことができ、切断部の再接続を容易かつ高精度に行うことができる。   After unloading the horizontal jacks, the horizontal jacks are rearranged in the direction used to separate the cut large beam steel frames, and the large beam steel frames that are connected by the steady rest and the guide plate are separated from each other. After inserting the extension beam material with T-shaped cross section between the separated beam beams, remove the guide plate, and connect the extension beam material web and the beam beam beams on both sides to the splice plate. After the bolts are connected, the horizontal jack is removed, and the upper flange of the extension beam is welded to the upper flange of the upper beam steel frame located on both sides of the upper beam, and the lower beam is welded to the lower end of the extension beam. After welding the flange and the lower flange of the large beam steel frame located on both sides of the flange, the steady rest is removed, so that the construction is always performed in a connected state. Therefore, safety can be ensured even if an earthquake occurs during the construction, and when the cut steel beams are pulled apart, they can be separated so that the cut surfaces do not deviate in the vertical and horizontal directions. The reconnection of the cutting part can be performed easily and with high accuracy.

以下、本発明の実施形態を図面に基づいて説明する。図1のAは、埋立による人工島に建設された二つの建造物B,C間に架設された連絡橋を示す。不同沈下によって建造物Bの位置が建造物C側にずれて、建造物B,C間の距離が短くなり、その結果、連絡橋Aの中間部を支持する中柱Dが建造物C側にやや傾いている。Pは切断予定位置を示す。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1A shows a connecting bridge constructed between two buildings B and C constructed on an artificial island by landfill. Due to the unsettled settlement, the position of the building B is shifted to the building C side, and the distance between the buildings B and C is shortened. As a result, the middle column D supporting the intermediate part of the connecting bridge A is moved to the building C side. Slightly inclined. P indicates a scheduled cutting position.

連絡橋Aは、SRC造であり、図2(A),(B)に示すように、建造物B,C間に架設された2本の橋桁用大梁鉄骨1と、これらの大梁鉄骨1に小梁鉄骨2を介して支持された通路用のコンクリート床3と、大梁鉄骨1に立設した柱4で支持された屋根5とを備えている。また、通路用のコンクリート床3の両側には、大梁鉄骨1から外側へ片持ち状に跳ね出したコンクリート溝6が設けられており、各コンクリート溝6にはムービングウォーク(動く歩道)7が設置されている。8は手摺である。   The connecting bridge A is an SRC structure, and as shown in FIGS. 2 (A) and 2 (B), two bridge girder steel frames 1 constructed between the buildings B and C, and these girder steel frames 1 A passage concrete floor 3 supported via a small beam steel frame 2 and a roof 5 supported by a column 4 standing on the large beam steel frame 1 are provided. Further, on both sides of the concrete floor 3 for the passage, there are provided concrete grooves 6 that cantilevered outwardly from the steel beam 1, and a moving walk (moving sidewalk) 7 is installed in each concrete groove 6. Has been. 8 is a handrail.

上記の連絡橋AをPの位置で所定幅だけ切断除去し、切断された橋桁用大梁鉄骨1を引き寄せて、切断面を再接続することにより、連絡橋Aの長さを縮めるにあたって、切断された状態においても切断前と略同等な強度を維持できるように、連絡橋Aの切断予定位置Pの近くを、後述する仮受ジャッキ16、振れ止め14、ガイドプレート18、水平ジャッキ19等からなる支持装置で支持しつつ切断から再接続までの工程を行う切断改修方法が採用されている。以下に、その切断改修方法を具体的に説明する。   The above-mentioned connecting bridge A is cut and removed by a predetermined width at the position P, and the cut bridge girder steel frame 1 is drawn and reconnected to cut the length of the connecting bridge A. In order to maintain substantially the same strength as before cutting, the connection bridge A includes a temporary jack 16, a steady rest 14, a guide plate 18, a horizontal jack 19, and the like, which are described later, near the planned cutting position P. A cutting and repairing method is employed in which steps from cutting to reconnection are performed while being supported by a support device. Below, the cutting and repairing method will be specifically described.

先ず、図2(A),(B)に示すように、コンクリート床3の仕上材とムービングウォーク7を撤去すると共に、高所作業車(図示せず)を用いて、軒天パネル9を必要範囲だけ撤去する。   First, as shown in FIGS. 2A and 2B, the finishing material of the concrete floor 3 and the moving walk 7 are removed, and an eaves panel 9 is required using an aerial work vehicle (not shown). Remove only the range.

次に、図3(A),(B)に示すように、切断予定位置P近くの大梁鉄骨1間に補強用の小梁鉄骨2aを新設する。10は小梁鉄骨2a取付け用のガセットプレート、11は高所作業車上に搬入された小梁鉄骨2aを吊り上げて仮支持する電動チェーンブロックであり、コンクリート床3の所定位置には、予め適当な時点で電動チェーンブロックによる吊り金具を挿通するための貫通孔を穿設しておくものとする。12は電動チェーンブロック11を支持する枠組足場である。   Next, as shown in FIGS. 3A and 3B, a reinforcing small beam steel frame 2a is newly provided between the large beam steel frames 1 near the planned cutting position P. Reference numeral 10 denotes a gusset plate for attaching the small beam steel frame 2a, and 11 denotes an electric chain block for lifting and temporarily supporting the small beam steel frame 2a carried on the aerial work vehicle. It is assumed that a through-hole for inserting a hanging metal fitting by an electric chain block is made at a certain point. A frame scaffold 12 supports the electric chain block 11.

次いで、図4(A),(B)に示すように、連絡橋Aの下方に仮受構台Eを設置した後、図5(A),(B)に示すように、仮受構台Eの周囲に枠組足場Fを組み立てる一方、
切断予定位置Pの上方の屋根及び壁面仕上材を撤去し、切断予定位置Pの上方の屋根鉄骨を切断する。Gは跳出し梁受支保工である。
Next, as shown in FIGS. 4 (A) and 4 (B), after installing the temporary receiving gantry E below the connecting bridge A, as shown in FIGS. 5 (A) and 5 (B), While assembling the frame scaffolding F around,
The roof and wall finishing material above the planned cutting position P are removed, and the roof steel frame above the planned cutting position P is cut. G is a jump beam support work.

しかる後、図6(A),(B)に示すように、切断予定位置Pを含む小範囲の大梁鉄骨1直上のコンクリート床3とコンクリート溝6をはつり取って、大梁鉄骨1の上フランジ及びウエブを露出させ、通路の幅方向中央部側コンクリート床3aははつらずに残しておく。この状態で、各大梁鉄骨1のウエブに対するボルト孔の加工、水平ジャッキ用ブラケット13の取付けを行い、各大梁鉄骨1における切断予定位置Pの両側に位置する上フランジにわたって振れ止め14を取り付ける。また、大梁鉄骨1にはムービングウォーク床受梁(復旧した後のコンクリート溝を支持する梁鉄骨)15を取り付け、仮受構台Eには4台の仮受ジャッキ16を据え付けて、各々の大梁鉄骨1における切断予定位置Pの両側部を支持させる。仮受ジャッキ16の上部と大梁鉄骨1の下フランジ1cとの間には、テフロン(登録商標)、ナイロン等の滑り材16aを介在させてある。   Thereafter, as shown in FIGS. 6 (A) and 6 (B), the concrete floor 3 and the concrete groove 6 just above the small beam steel frame 1 including the scheduled cutting position P are suspended, and the upper flange and The web is exposed and the concrete floor 3a in the width direction center side of the passage is left without being left. In this state, the bolt holes are formed in the web of each steel beam steel frame 1 and the horizontal jack bracket 13 is attached, and the steady rests 14 are attached to the upper flanges located on both sides of the planned cutting position P in each steel beam steel frame 1. Further, a moving walk floor receiving beam (beam steel frame that supports the restored concrete groove) 15 is attached to the large beam steel frame 1, and four temporary receiving jacks 16 are installed on the temporary receiving frame E, and each large beam steel frame is installed. 1 is supported on both sides of the scheduled cutting position P. A sliding material 16a such as Teflon (registered trademark) or nylon is interposed between the upper portion of the temporary jack 16 and the lower flange 1c of the steel beam 1.

前記振れ止め14は、図11、図12に示すように、切断予定位置Pの片側に位置する上フランジ1aの外側部に第一の水平鋼板14aを溶接し、切断予定位置Pの反対側に位置する上フランジ1aの外側部には、切断予定位置Pを越えて第一の水平鋼板14aに重なり合う位置まで達する第二の水平鋼板14bを溶接し、これらの水平鋼板14a,14b同士を一定範囲内で橋桁長手方向にのみスライド自在にボルト連結して構成したものである。第一の水平鋼板14aには円形のボルト孔が形成されているが、第二の水平鋼板14bには、大梁鉄骨1の切除幅に対応する長さの長孔17が形成されている。図示しないが、前記両水平鋼板14a,14b間、第二の水平鋼板14bとナットの座金との間には、夫々、テフロン(登録商標)、ナイロン等の滑り材を介在させてある。   As shown in FIGS. 11 and 12, the steady rest 14 is welded with a first horizontal steel plate 14a on the outer side of the upper flange 1a located on one side of the planned cutting position P, and on the opposite side of the planned cutting position P. A second horizontal steel plate 14b that reaches the position overlapping the first horizontal steel plate 14a beyond the planned cutting position P is welded to the outer portion of the upper flange 1a that is positioned, and the horizontal steel plates 14a and 14b are within a certain range. It is constructed by bolts slidably only in the longitudinal direction of the bridge girder. Although the circular bolt hole is formed in the 1st horizontal steel plate 14a, the long hole 17 of the length corresponding to the cutting width of the girder steel frame 1 is formed in the 2nd horizontal steel plate 14b. Although not shown, sliding materials such as Teflon (registered trademark) and nylon are interposed between the horizontal steel plates 14a and 14b and between the second horizontal steel plate 14b and the washer of the nut, respectively.

しかる後、図7(A),(B)に示すように、通路の幅方向中央部側コンクリート床3aを残したまま、大梁鉄骨1を所定幅(これは中柱Dを垂直姿勢に復元するに必要な距離でもあり、例えば、150mm程度である。)にわたって切断除去する一方、切断位置の両側に位置する大梁鉄骨1のウエブ1bの両面にウエブ接続用ボルト孔を利用してガイドプレート18を取り付け、切断位置の両側に位置する水平ジャッキ用ブラケット13間に、横力保持用の水平ジャッキ19を取り付ける。   Thereafter, as shown in FIGS. 7A and 7B, the girder steel frame 1 is restored to a predetermined width (this restores the middle column D to a vertical posture while leaving the concrete floor 3a in the width direction center side of the passage. The guide plate 18 is cut using a web connection bolt hole on both sides of the web 1b of the large beam steel frame 1 located on both sides of the cutting position. A horizontal jack 19 for holding a lateral force is attached between the horizontal jack brackets 13 located on both sides of the attachment and cutting positions.

尚、水平ジャッキ19としては、図13〜図16に示すように、軸芯部にねじ軸19aを貫通したセンターホールジャッキ用いられている。19bはねじ軸19a用のジョイントカプラーである。水平ジャッキ用ブラケット13には、ねじ軸19a挿通用の切欠部か形成され、ガセットプレート10には、上下二箇所にジョイントカプラー19b挿通用の貫通孔10aが形成されている。   As shown in FIGS. 13 to 16, the horizontal jack 19 is a center hole jack having a shaft portion penetrating a screw shaft 19a. 19b is a joint coupler for the screw shaft 19a. The horizontal jack bracket 13 is formed with a notch for inserting the screw shaft 19a, and the gusset plate 10 is formed with through holes 10a for inserting the joint coupler 19b at two upper and lower positions.

前記ガイドプレート18は、図11、図12に示すように、ウエブ1bの両面を橋桁長手方向にのみスライド自在に挟持する一対の溝型鋼によって構成され、各溝型鋼の切断位置の片側に位置するウエブ1bとボルト連結する部分には、円形のボルト孔が形成され、切断位置の反対側に位置するウエブ1bと連結する部分には、大梁鉄骨1の切除幅に対応する長さの長孔20が形成されている。図示しないが、座金と溝型鋼との間や溝型鋼とウエブ1bとの間には、夫々、テフロン(登録商標)、ナイロン等の滑り材を介在させてある。   As shown in FIGS. 11 and 12, the guide plate 18 is composed of a pair of groove steels that slidably hold both surfaces of the web 1b only in the longitudinal direction of the bridge beam, and is located on one side of the cutting position of each groove steel. A circular bolt hole is formed in a portion connected to the web 1b and the bolt, and a long hole 20 having a length corresponding to the excision width of the girder steel frame 1 is formed in a portion connected to the web 1b located on the opposite side of the cutting position. Is formed. Although not shown, sliding materials such as Teflon (registered trademark) and nylon are interposed between the washer and the grooved steel and between the grooved steel and the web 1b.

図8(A),(B)、図13に示すように、切断位置の両側に位置する大梁鉄骨1同士を横力保持用の水平ジャッキ19で連結した状態で、残しておいた前記中央部側コンクリート床3aをはつり取る。中央部側コンクリート床3aが無くなることによって、図14に示すように、切断された大梁鉄骨1が切断前の変形状態から小距離(例えば、50mm程度)弾性復元するので、この切断前の変形状態からの弾性復元による横力を水平ジャッ
キ19で受け止める。
As shown in FIGS. 8 (A), (B), and FIG. 13, the central portion left in the state where the large beam steel frames 1 located on both sides of the cutting position are connected to each other by a horizontal jack 19 for holding a lateral force. Scrape the side concrete floor 3a. By eliminating the central concrete floor 3a, as shown in FIG. 14, the cut large beam steel frame 1 is elastically restored from a deformed state before cutting by a small distance (for example, about 50 mm). Lateral force due to elastic recovery from the horizontal jack 19 is received.

次に、水平ジャッキ19の除荷後、図9(A),(B)、図15に示すように、水平ジャッキ19を切断された大梁鉄骨1同士の引寄せに用いる方向に盛り替えて、水平ジャッキ19を伸長動作させることにより、切断された大梁鉄骨1同士を引き寄せる。   Next, after unloading the horizontal jack 19, as shown in FIGS. 9 (A), (B) and FIG. 15, the horizontal jack 19 is changed to the direction used for pulling the crossed large beam steel frames 1, By operating the horizontal jack 19 to extend, the cut large beam steel frames 1 are drawn together.

そして、図10(A),(B)、図16に示すように、ガイドプレート18の撤去後、切断位置の両側に位置する大梁鉄骨1のウエブ1b同士をスプライスプレート21を介してボルト連結すると共に、水平ジャッキ19を撤去し、切断位置の両側に位置する大梁鉄骨1の上,下フランジ1a,1cの溶接後、前記振れ止め14を撤去する。   Then, as shown in FIGS. 10A, 10B, and 16, after the guide plate 18 is removed, the webs 1b of the large beam steel frames 1 positioned on both sides of the cutting position are bolted together via the splice plate 21. At the same time, the horizontal jack 19 is removed, and after the upper and lower flanges 1a, 1c are welded on the large beam steel frame 1 located on both sides of the cutting position, the steady rest 14 is removed.

しかる後、仮受ジャッキ16を撤去すると共に、図17に示すように、はつり取った範囲の配筋(図示せず)、コンクリート3b打設を行って、コンクリート床3やコンクリート溝の切断部位の復旧を行い、且つ、屋根・壁面復旧を行った後、枠組足場Fの解体、仮受構台Eの解体を行い、ムービングウォーク7等の設備の復旧、軒天パネル9の復旧を行うことになる。   Thereafter, the temporary jack 16 is removed, and, as shown in FIG. 17, a bar arrangement (not shown) in the range where it is picked up, concrete 3b is placed, and the concrete floor 3 and the concrete groove are cut. After the restoration and roof / wall restoration, the frame scaffold F will be dismantled, the temporary receiving base E will be dismantled, the equipment such as the moving walk 7 will be restored, and the eaves panel 9 will be restored. .

上記の構成によれば、不同沈下等によって建造物B,C間の距離が短くなり、建造物B,C間に架設された連絡橋Aの長さを短縮する必要が生じた場合、橋桁用大梁鉄骨1の切断や通路用コンクリート床3の切断に際し、仮設の振れ止め14、ガイドプレート18、水平ジャッキ19等を取り付けることによって、想定する地震の範囲で水平力に対して常に連結された状態で工事を進めることができ、工事中に地震が発生しても安全を確保できる。   According to the above configuration, when the distance between the buildings B and C is shortened due to uneven settlement, etc., and it becomes necessary to shorten the length of the connecting bridge A erected between the buildings B and C, the bridge girder is used. When cutting the girder steel frame 1 or the concrete floor 3 for the passage, the temporary steady rest 14, the guide plate 18, the horizontal jack 19, etc. are attached so that they are always connected to the horizontal force within the assumed earthquake range. It is possible to proceed with the construction and secure safety even if an earthquake occurs during the construction.

即ち、橋桁用大梁鉄骨1における切断予定位置Pの両側部を連絡橋Aの下方に設置した仮受構台Eに仮受ジャッキ16を介して支持させるだけでなく、各大梁鉄骨1における切断予定位置Pの両側に位置する上フランジ1a,1a間にわたって振れ止め14を取り付け、しかも、通路の幅方向中央部側コンクリート床3aを残した状態で、大梁鉄骨1を切断するので、大梁鉄骨1が所定幅にわたって切断除去されても、連絡橋Aは、中央部側コンクリート床3aと振れ止め14とで水平方向に連結されていることになる。また、切断した大梁鉄骨1の垂直方向のずれについては、仮受ジャッキ15でレベル調整することができる。   In other words, not only the both sides of the planned cutting position P in the bridge girder steel beam 1 are supported by the temporary receiving base E installed below the connecting bridge A via the temporary receiving jacks 16 but also the planned cutting positions in the respective large beam steel frames 1. Since the steady rest 14 is attached between the upper flanges 1a, 1a located on both sides of the P, and the concrete beam 3a in the width direction of the passage is left, the large beam steel frame 1 is cut. Even if it is cut and removed over the width, the connecting bridge A is connected in the horizontal direction by the center side concrete floor 3a and the steady rest 14. Further, the level of the vertical displacement of the cut large beam steel frame 1 can be adjusted by the provisional jack 15.

そして、前記中央部側コンクリート床3aをはつり取る前に、切断位置の両側に位置する大梁鉄骨1のウエブ1b間にわたってガイドプレート18を取り付け、且つ、切断位置の両側に位置する大梁鉄骨1同士を横力保持用の水平ジャッキ19で連結するので、前記中央部側コンクリート床3aをはつり取っても、連絡橋Aは、振れ止め14とガイドプレート18と水平ジャッキ19で連結されていることになり、切断前の変形状態からの弾性復元による横力を水平ジャッキ19で受け止めることができ、切断した大梁鉄骨1の水平方向(幅方向)のずれは、振れ止め14とガイドプレート18とによって防止することができる。   And before picking up the said center side concrete floor 3a, the guide plate 18 is attached over the web 1b of the large beam steel frame 1 located in the both sides of a cutting position, and the large beam steel frames 1 located in the both sides of a cutting position are attached. Since the horizontal jacks 19 for holding the lateral force are connected, the connecting bridge A is connected to the steady rest 14, the guide plate 18, and the horizontal jacks 19 even if the central concrete floor 3 a is removed. Lateral force due to elastic recovery from the deformed state before cutting can be received by the horizontal jack 19, and horizontal deviation (width direction) of the cut large beam steel frame 1 is prevented by the steady rest 14 and the guide plate 18. be able to.

水平ジャッキ19の除荷後は、当該水平ジャッキ19を切断された大梁鉄骨1同士の引寄せに用いる方向に盛り替えて、振れ止め14とガイドプレート18で連結された状態にある大梁鉄骨1同士を引き寄せることになり、ガイドプレート18の撤去後は、切断位置の両側に位置する大梁鉄骨1のウエブ1b同士を一対のスプライスプレート21を介してボルト連結した後、水平ジャッキ19を撤去し、切断位置の両側に位置する大梁鉄骨1の上,下フランジ1a,1cの溶接後、振れ止め14を撤去するので、常に連結された状態で工事が進められることになる。   After unloading the horizontal jacks 19, the horizontal jacks 19 are rearranged in the direction used to draw the cut large beam steels 1, and the large beam steels 1 in a state where they are connected by the steady rest 14 and the guide plate 18. After the guide plate 18 is removed, the webs 1b of the large beam steel frames 1 located on both sides of the cutting position are bolted together via a pair of splice plates 21, and then the horizontal jack 19 is removed and cut. Since the steady rest 14 is removed after welding the upper and lower flanges 1a and 1c of the large beam steel frame 1 located on both sides of the position, the construction is always continued in a connected state.

従って、工事中に地震が発生しても安全を確保でき、しかも、切断した大梁鉄骨1の引寄せを行うにあたって、切断面が相互に垂直方向にも水平方向にもずれないように引き寄せることができ、切断部の再接続を容易かつ高精度に行うことができる。   Therefore, even if an earthquake occurs during construction, safety can be ensured, and when the cut beam 1 is drawn, the cut surfaces can be drawn so that they do not deviate in the vertical and horizontal directions. It is possible to reconnect the cutting part easily and with high accuracy.

以上の実施形態では、不同沈下によって建造物B,C間の距離が短くなった場合を例に挙げて本発明を説明したが、本発明は、上記とは逆に、不同沈下によって建造物B,C間の距離が長くなり、建造物B,C間に架設された連絡橋Aの長さを伸長する必要が生じた場合にも、適用可能である。   In the above embodiment, the present invention has been described by taking as an example the case where the distance between the buildings B and C is shortened due to the unsettled settlement. However, the present invention, contrary to the above, the building B due to the unsettled settlement. , C becomes longer, and the connection bridge A erected between the buildings B and C needs to be extended in length.

以下は、その場合の実施形態を示す。尚、図2(A),(B)〜図6(A),(B)までの施工手順は、建造物B,C間の距離が短くなった場合の施工手順と同じであるから、図示説明を省略する。また、図18〜図22に示すように、この実施形態において用いられる振れ止め14やガイドプレート18は、図11〜図15で示した振れ止め14やガイドプレート18と実質的に同じ構成であるが、図11〜図15の例では、長孔17、20が切断された大梁鉄骨1同士を引き寄せる際の大梁鉄骨1の移動を可能にするためのものであるのに対し、図18〜図22の例では、長孔17、20が切断された大梁鉄骨1同士を引き離す際の大梁鉄骨1の移動を可能にするためのものである点でのみ相違している。   The following shows an embodiment in that case. In addition, since the construction procedure to FIG. 2 (A), (B)-FIG. 6 (A), (B) is the same as the construction procedure when the distance between the buildings B and C becomes short, it is illustrated. Description is omitted. Also, as shown in FIGS. 18 to 22, the steady rest 14 and the guide plate 18 used in this embodiment have substantially the same configuration as the steady rest 14 and the guide plate 18 shown in FIGS. However, in the example of FIGS. 11 to 15, it is intended to enable the movement of the large beam steel frames 1 when drawing the large beam steel frames 1 from which the long holes 17 and 20 are cut, whereas FIGS. The example of 22 is different only in that it is intended to enable movement of the girder steel frames 1 when the girder steel frames 1 having the long holes 17 and 20 cut are separated.

図6(A),(B)の工程の後、図20に示すように、通路の幅方向中央部側コンクリート床3aを残したまま、大梁鉄骨1を切断予定位置Pで切断する一方、切断位置の両側に位置する大梁鉄骨1のウエブ1bの両面にウエブ接続用ボルト孔を利用してガイドプレート18を取り付け、切断位置の両側に位置する水平ジャッキ用ブラケット13間にわたって、引き離し用の水平ジャッキ(センターホールジャッキ)19を取り付ける。具体的には、切断位置の片側のブラケット13に水平ジャッキ19を取り付け、水平ジャッキ19の軸芯を貫通するねじ軸の一端部を切断位置の反対側のブラケット13に固定して、切断された大梁鉄骨1同士が離れる方向に移動するのを阻止するように水平ジャッキ19を据え付ける。   After the steps of FIGS. 6 (A) and 6 (B), as shown in FIG. 20, the large beam steel frame 1 is cut at the planned cutting position P while leaving the widthwise central portion side concrete floor 3a. Guide plates 18 are attached to both sides of the web 1b of the large beam steel frame 1 located on both sides of the position using web connecting bolt holes, and the horizontal jacks for pulling apart are disposed between the horizontal jack brackets 13 located on both sides of the cutting position. (Center hole jack) 19 is attached. Specifically, the horizontal jack 19 is attached to the bracket 13 on one side of the cutting position, and one end portion of the screw shaft that passes through the shaft core of the horizontal jack 19 is fixed to the bracket 13 on the opposite side of the cutting position. A horizontal jack 19 is installed so as to prevent the girder steel frames 1 from moving in a direction away from each other.

しかる後、図21に示すように、切断位置の両側に位置する大梁鉄骨1同士を引き離し用の水平ジャッキ19で連結した状態で、残しておいた前記中央部側コンクリート床3aをはつり取る。中央部側コンクリート床3aが無くなることによって、切断された大梁鉄骨1が切断前の変形状態から小距離(例えば、50mm程度)弾性復元するので、この切断前の変形状態からの弾性復元による引張力を水平ジャッキ19で受け止めることができ、切断した大梁鉄骨1の水平方向(幅方向)のずれは、振れ止め14とガイドプレート18とによって防止することができる。   Thereafter, as shown in FIG. 21, the central concrete side floor 3a that has been left is suspended while the large beam steel frames 1 located on both sides of the cutting position are connected to each other by a horizontal jack 19 for separation. Since the center-side concrete floor 3a is eliminated, the cut large beam steel frame 1 is elastically restored from a deformed state before cutting by a short distance (for example, about 50 mm). Therefore, a tensile force due to elastic restoration from the deformed state before cutting. Can be received by the horizontal jack 19, and the horizontal displacement (width direction) of the cut large beam steel frame 1 can be prevented by the steady rest 14 and the guide plate 18.

次に、水平ジャッキ19の除荷後、図22に示すように、水平ジャッキ19を切断された大梁鉄骨1同士の引き離しに用いる方向に盛り替えて、水平ジャッキ19を伸長動作させることにより、切断された大梁鉄骨1同士の引き離しを行う。そして、引き離された大梁鉄骨1間に断面T字状の継足し用大梁材1Aを挿入した後、ガイドプレート18を撤去する。   Next, after the unloading of the horizontal jack 19, as shown in FIG. 22, the horizontal jack 19 is changed in the direction used for pulling the cut-off large steel frames 1, and the horizontal jack 19 is extended to perform the cutting operation. The separated large beam steel frames 1 are separated. Then, after inserting the extension beam material 1A having a T-shaped cross section between the separated steel beam steel frames 1, the guide plate 18 is removed.

この状態で、図23に示すように、継足し用大梁材1Aのウエブ1Abとその両側に位置する大梁鉄骨1のウエブ1bとを二対のスプライスプレート21を介してボルト連結した後、水平ジャッキ19を撤去し、継足し用大梁材1Aの上フランジ1Aaとその両側に位置する大梁鉄骨1の上フランジ1aとを溶接すると共に、継足し用大梁材1Aのウエブ1Ab下端に現場溶接した下フランジ1Acとその両側に位置する大梁鉄骨1の下フランジ1cとを溶接した後、前記振れ止め14を撤去する。   In this state, as shown in FIG. 23, the web 1Ab of the extension beam 1A and the web 1b of the beam 1 positioned on both sides of the web 1b are bolted together via two pairs of splice plates 21, and then the horizontal jack 19 is removed, and the upper flange 1Aa of the extension beam 1A and the upper flange 1a of the upper beam 1 positioned on both sides thereof are welded, and the lower flange is welded in situ to the lower end of the web 1Ab of the extension beam 1A. After welding 1Ac and the lower flange 1c of the girder steel frame 1 located on both sides thereof, the steady rest 14 is removed.

しかる後、仮受ジャッキ16を撤去すると共に、図24に示すように、はつり取った範
囲の配筋(図示せず)、コンクリート3b打設を行って、コンクリート床3やコンクリート溝の切断部位の復旧を行い、且つ、屋根・壁面復旧を行った後、枠組足場Fの解体、仮受構台Eの解体を行い、ムービングウォーク7等の設備の復旧、軒天パネル9の復旧を行うことになる。
After that, the temporary jack 16 is removed, and as shown in FIG. 24, the arrangement of the barbed area (not shown) and the concrete 3b are placed, and the concrete floor 3 and the concrete groove are cut. After the restoration and roof / wall restoration, the frame scaffold F will be dismantled, the temporary receiving base E will be dismantled, the equipment such as the moving walk 7 will be restored, and the eaves panel 9 will be restored. .

上記の構成によれば、不同沈下等によって建造物B,C間の距離が長くなり、建造物B,C間に架設された連絡橋Aの長さを伸長する必要が生じた場合、橋桁用大梁鉄骨1の切断や通路用コンクリート床3の切断に際し、仮設の振れ止め14、ガイドプレート18、水平ジャッキ19等を取り付けることによって、想定する地震の範囲で水平力に対して常に連結された状態で工事を進めることができ、工事中に地震が発生しても安全を確保できる。   According to the above configuration, when the distance between the buildings B and C becomes long due to uneven settlement, etc., and it becomes necessary to extend the length of the connecting bridge A erected between the buildings B and C, the bridge girder is used. When cutting the girder steel frame 1 or the concrete floor 3 for the passage, the temporary steady rest 14, the guide plate 18, the horizontal jack 19, etc. are attached so that they are always connected to the horizontal force within the assumed earthquake range. It is possible to proceed with the construction and secure safety even if an earthquake occurs during the construction.

即ち、橋桁用大梁鉄骨1における切断予定位置Pの両側部を連絡橋Aの下方に設置した仮受構台Eに仮受ジャッキ16を介して支持させるだけでなく、各大梁鉄骨1における切断予定位置の両側に位置する上フランジ1a,1a間にわたって振れ止め14を取り付け、しかも、通路の幅方向中央部側コンクリート床3aを残した状態で、大梁鉄骨1を切断するので、大梁鉄骨1が切断されても、連絡橋Aは、中央部側コンクリート床3aと振れ止め14とで水平方向に連結されていることになる。また、切断した大梁鉄骨1の垂直方向のずれについては、仮受ジャッキ15でレベル調整することができる。   In other words, not only the both sides of the planned cutting position P in the bridge girder steel beam 1 are supported by the temporary receiving base E installed below the connecting bridge A via the temporary receiving jacks 16 but also the planned cutting positions in the respective large beam steel frames 1. The brace 14 is cut between the upper flanges 1a, 1a located on both sides of the steel plate, and the steel beam 1 is cut with the concrete floor 3a in the width direction of the passage remaining, so that the steel beam 1 is cut. However, the connecting bridge A is connected in the horizontal direction by the center side concrete floor 3a and the steady rest 14. Further, the level of the vertical displacement of the cut large beam steel frame 1 can be adjusted by the provisional jack 15.

そして、前記中央部側コンクリート床3aをはつり取る前に、切断位置の両側に位置する大梁鉄骨1のウエブ1b間にわたってガイドプレート18を取り付け、且つ、切断位置の両側に位置する大梁鉄骨1同士を引き離し用の水平ジャッキ19で連結するので、前記中央部側コンクリート床3aをはつり取っても、連絡橋Aは、振れ止め14とガイドプレート18と水平ジャッキ19で連結されていることになり、切断前の変形状態からの弾性復元による引張力を水平ジャッキ19で受け止めることができる。   And before picking up the said center side concrete floor 3a, the guide plate 18 is attached over the web 1b of the large beam steel frame 1 located in the both sides of a cutting position, and the large beam steel frames 1 located in the both sides of a cutting position are attached. Since it is connected by the horizontal jack 19 for separation, the connecting bridge A is connected by the steady rest 14, the guide plate 18, and the horizontal jack 19 even if the center side concrete floor 3 a is picked up. A tensile force due to elastic recovery from the previous deformation state can be received by the horizontal jack 19.

水平ジャッキ19の除荷後は、当該水平ジャッキ19を切断された大梁鉄骨1同士の引き離しに用いる方向に盛り替えて、振れ止め14とガイドプレート18で連結された状態にある大梁鉄骨1同士を引き離すことになり、引き離された大梁鉄骨1間に断面T字状の継足し用大梁材1Aを挿入した後、ガイドプレート18を撤去し、継足し用大梁材1Aのウエブ1Abとその両側に位置する大梁鉄骨1のウエブ1bとをスプライスプレート21を介してボルト連結した後、水平ジャッキ19を撤去し、継足し用大梁材1Aの上フランジ1Aaとその両側に位置する大梁鉄骨1の上フランジ1aとを溶接すると共に、継足し用大梁材1Aのウエブ1Ab下端に溶接した下フランジ1Acとその両側に位置する大梁鉄骨1の下フランジ1cとを溶接した後、振れ止め14を撤去するので、常に連結された状態で工事が進められることになる。   After unloading the horizontal jacks 19, the horizontal jacks 19 are rearranged in the direction used to separate the cut large beam steels 1, and the large beam steels 1 connected by the steady rest 14 and the guide plate 18 are exchanged. After inserting the extension beam material 1A having a T-shaped cross section between the separated beam beams 1, the guide plate 18 is removed, and the web 1Ab of the extension beam material 1A is positioned on both sides thereof. After connecting the web 1b of the large beam steel frame 1 to the bolt 1 via the splice plate 21, the horizontal jack 19 is removed, and the upper flange 1Aa of the large beam material 1A for extension and the upper flange 1a of the large beam steel frame 1 positioned on both sides thereof Are welded to the lower flange 1Ac welded to the lower end of the web 1Ab of the extension beam material 1A and the lower flange 1c of the steel beam frame 1 positioned on both sides thereof. After you, because it removed the bracing 14, always will be construction work on a consolidated state is advanced.

従って、工事中に地震が発生しても安全を確保でき、しかも、切断した大梁鉄骨1の引離しを行うにあたって、切断面が相互に垂直方向にも水平方向にもずれないように引き離すことができ、切断部の再接続を容易かつ高精度に行うことができる。   Therefore, safety can be ensured even if an earthquake occurs during construction, and when the cut steel beam 1 is separated, the cut surfaces can be separated so that they do not deviate in the vertical and horizontal directions. It is possible to reconnect the cutting part easily and with high accuracy.

以上、本発明の実施形態について説明したが、本発明は上記の実施形態のみに限定されるものではなく、例えば、RC造の連絡橋を施工対象とするなど、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。   As mentioned above, although embodiment of this invention was described, this invention is not limited only to said embodiment, For example, the range which does not deviate from the summary of this invention, such as making RC connection bridge into construction object Of course, the present invention can be implemented in various modes.

本発明の実施形態を示す連絡橋の概略側面図である。It is a schematic side view of a connecting bridge showing an embodiment of the present invention. 本発明に係る連絡橋の切断改修方法の施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure of the cutting and repairing method of the connecting bridge according to the present invention is shown, (A) is a longitudinal front view, (B) is a longitudinal side view. 図2に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 2 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図3に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 3 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図4に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 4 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図5に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 5 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図6に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 6 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図7に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 7 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図8に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 8 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 図9に続く施工手順を示し、(A)は縦断正面図、(B)は縦断側面図である。The construction procedure following FIG. 9 is shown, (A) is a longitudinal front view, and (B) is a longitudinal side view. 振れ止めとガイドプレートの構成を説明する要部の平面図である。It is a top view of the principal part explaining the structure of a steady rest and a guide plate. 振れ止めとガイドプレートの構成を説明する要部の縦断正面図である。It is a vertical front view of the principal part explaining the structure of a steady rest and a guide plate. 中央部側コンクリート床をはつり取る直前における要部の側面図である。It is a side view of the principal part just before picking up a center part side concrete floor. 中央部側コンクリート床のはつり取り直後における要部の側面図である。It is a side view of the principal part just after suspending of the center part side concrete floor. 水平引き寄せを行った状態における要部の側面図である。It is a side view of the principal part in the state which performed horizontal drawing. 引き寄せられた大梁鉄骨のウエブをボルト連結した状態における要部の側面図である。It is a side view of the principal part in the state which carried out the bolt connection of the web of the drawn large beam steel frame. 再接続を完了した状態における要部の側面図である。It is a side view of the principal part in the state which completed reconnection. 本発明の他の実施形態を示し、振れ止めとガイドプレートの構成を説明する要部の平面図である。It is a top view of the principal part which shows other embodiment of this invention and demonstrates the structure of a steady rest and a guide plate. 振れ止めとガイドプレートの構成を説明する要部の縦断正面図である。It is a vertical front view of the principal part explaining the structure of a steady rest and a guide plate. 中央部側コンクリート床をはつり取る直前における要部の側面図である。It is a side view of the principal part just before picking up a center part side concrete floor. 水平引き離しを行った状態における要部の側面図である。It is a side view of the principal part in the state which performed horizontal separation. 引き離された大梁鉄骨間に継足し用大梁材を挿入する状態における要部の側面図である。It is a side view of the principal part in the state which inserts the large beam material for extension between the separated large beam steel frames. 引き離された大梁鉄骨と継足し用大梁材をボルト連結及び溶接した状態における要部の側面図である。It is a side view of the principal part in the state which carried out the bolt connection and the welded large beam steel material and the large beam material for an extension. 再接続を完了した状態における要部の側面図である。It is a side view of the principal part in the state which completed reconnection.

符号の説明Explanation of symbols

A 連絡橋
B,C 建造物
E 仮受構台
1 橋桁用大梁鉄骨
3 コンクリート床
3a 中央部側コンクリート床
14 振れ止め
16 仮受ジャッキ
18 ガイドプレート
19 水平ジャッキ(センターホールジャッキ)
A Connecting bridge B, C Building E Temporary receiving frame 1 Large beam steel frame for bridge girder 3 Concrete floor 3a Center side concrete floor 14 Stabilization 16 Temporary receiving jack 18 Guide plate 19 Horizontal jack (center hole jack)

Claims (4)

建造物間に架設された連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを修正する連絡橋の切断改修方法であって、切断された状態においても切断前と略同等な強度を維持できるように、連絡橋の切断予定位置の近くを支持しつつ切断から再接続までの工程を行うことを特徴とする建造物間の距離が変化した連絡橋の切断改修方法。   A method of cutting and refurbishing a connecting bridge that corrects the length of the connecting bridge by cutting the connecting bridge erected between the buildings, moving the disconnected connecting bridge in the length direction, and then reconnecting it. In order to maintain approximately the same strength as before cutting even in a disconnected state, the steps from cutting to reconnection are performed while supporting the vicinity of the planned cutting position of the connecting bridge. How to cut and repair a connecting bridge whose distance has changed. 建造物間に架設された連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを修正する連絡橋の切断改修方法であって、切断予定位置の近くに、切断前から再接続終了までの間、切断部位相互の垂直方向及び水平方向へのずれを防止するための支持装置を設けて、切断時、切断された連絡橋の移動時、再接続時の何れにおいても、切断部位相互の垂直方向及び水平方向へのずれを防止できるようにしたことを特徴とする請求項1に記載の建造物間の距離が変化した連絡橋の切断改修方法。   A method of cutting and refurbishing a connecting bridge that corrects the length of the connecting bridge by cutting the connecting bridge erected between the buildings, moving the disconnected connecting bridge in the length direction, and then reconnecting it. In the vicinity of the planned cutting position, a support device is provided to prevent vertical and horizontal shifts between the cutting sites from before cutting until the end of reconnection. The connecting bridge according to claim 1, wherein the distance between buildings can be prevented from shifting in a vertical direction and a horizontal direction between cutting parts in both cases of movement and reconnection. Cutting repair method. 建造物間に架設された複数本の橋桁用大梁鉄骨と、これらの大梁鉄骨に支持された通路用のコンクリート床とを備えた連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを短縮する連絡橋の切断改修方法であって、切断予定位置のコンクリート床を通路の幅方向中央部側コンクリート床が残された状態にはつり取って、大梁鉄骨の上フランジを露出させ、各々の大梁鉄骨における切断予定位置の両側に位置する上フランジ間にわたって振れ止めを取り付け、且つ、各々の大梁鉄骨における切断予定位置の両側部を連絡橋の下方に設置した仮受構台に仮受ジャッキを介して支持させ、この状態で大梁鉄骨を所定幅にわたって切断除去する一方、切断位置の両側に位置する大梁鉄骨のウエブ間にわたってガイドプレートを取り付け、且つ、切断位置の両側に位置する大梁鉄骨同士を横力保持用の水平ジャッキで連結した状態で、前記中央部側コンクリート床をはつり取り、水平ジャッキの除荷後、水平ジャッキの盛り替えを行って、切断された大梁鉄骨同士の引寄せを行い、ガイドプレートの撤去後、切断位置の両側に位置する大梁鉄骨のウエブ同士をスプライスプレートを介してボルト連結すると共に、水平ジャッキを撤去し、切断位置の両側に位置する大梁鉄骨の上,下フランジの溶接後、前記振れ止めを撤去し、しかる後、配筋、コンクリート打設を行って、コンクリート床の切断部位の復旧を行うことを特徴とする建造物間の距離が変化した連絡橋の切断改修方法。   Cut the connecting bridge with multiple girder steel beams for bridge girders erected between the buildings and the concrete floor for the passage supported by these girder steel frames, and move the cut connecting bridge in the length direction And then reconnecting to shorten the length of the connecting bridge. The connecting bridge is cut and refurbished, and the concrete floor at the planned cutting position is suspended in the state where the concrete floor on the center side in the width direction of the passage is left. The upper flanges of the steel beams are exposed, the steady rests are attached between the upper flanges located on both sides of the planned cutting positions in each steel beam, and both sides of the planned cutting positions in each steel beam are connected to the bridge In this state, the girder steel frame is cut and removed over a predetermined width, while the girder steel frame is positioned between the webs of the girder steel frames located on both sides of the cutting position. In the state where large beam steel frames located on both sides of the cutting position are connected to each other with a horizontal jack for holding lateral force, the center side concrete floor is suspended, and after unloading the horizontal jack, the horizontal jack After the guide plate is removed, the webs of the large beam steel frames located on both sides of the cutting position are bolted together via the splice plate and the horizontal jack is pulled. After welding the upper and lower flanges of the girder steel frames located on both sides of the cutting position, remove the steady rest, and then perform reinforcement and concrete placement to restore the cut section of the concrete floor. A cutting and repairing method for connecting bridges with different distances between buildings. 建造物間に架設された複数本の橋桁用大梁鉄骨と、これらの大梁鉄骨に支持された通路用のコンクリート床とを備えた連絡橋を切断し、切断された連絡橋を長さ方向に移動させた後、再接続して、連絡橋の長さを伸長する連絡橋の切断改修方法であって、切断予定位置のコンクリート床を通路の幅方向中央部側コンクリート床が残された状態にはつり取って、大梁鉄骨の上フランジを露出させ、各々の大梁鉄骨における切断予定位置の両側に位置する上フランジ間にわたって振れ止めを取り付け、且つ、各々の大梁鉄骨における切断予定位置の両側部を連絡橋の下方に設置した仮受構台に仮受ジャッキを介して支持させ、この状態で大梁鉄骨を切断する一方、切断位置の両側に位置する大梁鉄骨のウエブ間にわたってガイドプレートを取り付け、且つ、切断位置の両側に位置する大梁鉄骨同士を引き離し用の水平ジャッキで連結した状態で、前記中央部側コンクリート床をはつり取り、水平ジャッキの除荷後、水平ジャッキの盛り替えを行って、切断された大梁鉄骨同士の引離しを行い、引き離された大梁鉄骨間に断面T字状の継足し用大梁材を挿入した後、ガイドプレートを撤去し、継足し用大梁材のウエブとその両側に位置する大梁鉄骨のウエブとをスプライスプレートを介してボルト連結した後、水平ジャッキを撤去し、継足し用大梁材の上フランジとその両側に位置する大梁鉄骨の上フランジとを溶接すると共に、継足し用大梁材のウエブ下端に溶接した下フランジとその両側に位置する大梁鉄骨の下フランジとを溶接した後、前記振れ止めを撤去し、しかる後、配筋、コンクリート打設を行って、コンクリート床の切断部位の復旧を行うことを特徴とする建造物間の距離が変化した連絡橋
の切断改修方法。
Cut the connecting bridge with multiple girder steel beams for bridge girders erected between the buildings and the concrete floor for the passage supported by these girder steel frames, and move the cut connecting bridge in the length direction And then reconnecting and extending the length of the connecting bridge. The connecting bridge is cut and refurbished, and the concrete floor at the planned cutting position is suspended in the state where the concrete floor at the center in the width direction of the passage is left. The upper flanges of the steel beams are exposed, the steady rests are attached between the upper flanges located on both sides of the planned cutting positions in each steel beam, and both sides of the planned cutting positions in each steel beam are connected to the bridge Is supported by a temporary support jack installed underneath, and in this state the large beam steel frame is cut, while the guide plates are mounted between the large beam steel webs located on both sides of the cutting position. In the state where the large beam steel frames located on both sides of the cutting position are connected with a horizontal jack for separating, the center side concrete floor is suspended, and after unloading the horizontal jack, the horizontal jack is refilled. After separating the beamed steel beams, insert a beam for extension with a T-shaped cross section between the separated beam beams, remove the guide plate, and the web of the beam for extension beam and its After bolting the web of steel beams on both sides via splice plates, remove the horizontal jack and weld the upper flange of the extension beam and the upper flanges of the beam on both sides After welding the lower flange welded to the lower end of the web of the extension beam and the lower flanges of the large beam steel frame located on both sides of the lower beam, the steady rest is removed, and then the reinforcement, Performing cleat striking setting, cutting repair method of connecting bridge the distance between buildings has changed, characterized by performing the recovery of the cleavage site of the concrete floor.
JP2007001262A 2007-01-09 2007-01-09 Cutting and rehabilitating connecting bridges with different distances between buildings Active JP4755998B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007001262A JP4755998B2 (en) 2007-01-09 2007-01-09 Cutting and rehabilitating connecting bridges with different distances between buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007001262A JP4755998B2 (en) 2007-01-09 2007-01-09 Cutting and rehabilitating connecting bridges with different distances between buildings

Publications (2)

Publication Number Publication Date
JP2008169552A JP2008169552A (en) 2008-07-24
JP4755998B2 true JP4755998B2 (en) 2011-08-24

Family

ID=39697898

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007001262A Active JP4755998B2 (en) 2007-01-09 2007-01-09 Cutting and rehabilitating connecting bridges with different distances between buildings

Country Status (1)

Country Link
JP (1) JP4755998B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103726449A (en) * 2013-12-19 2014-04-16 柳州欧维姆机械股份有限公司 Automatic beam placement platform device and construction method of replacing railway beams thereby

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114263204B (en) * 2021-12-22 2022-12-13 中铁三局集团建筑安装工程有限公司 Large-thickness continuous seamless casting concrete bottom plate and construction method thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5289882A (en) * 1976-06-14 1977-07-28 Hidetaka Chiba Method of cutting lower angle of every kind of stone
JPS5726738Y2 (en) * 1978-06-30 1982-06-10
JPH047214Y2 (en) * 1988-08-19 1992-02-26
JPH0756032Y2 (en) * 1991-05-30 1995-12-25 ドーエイ外装有限会社 Crossing passage
JP2541903B2 (en) * 1993-03-20 1996-10-09 ドーエイ外装有限会社 Crossing passage
JP4348108B2 (en) * 2003-04-30 2009-10-21 三菱重工鉄構エンジニアリング株式会社 Bridge replacement method and bridge
JP2005273178A (en) * 2004-03-23 2005-10-06 Shimizu Corp Construction method for demolishing and removing viaduct

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103726449A (en) * 2013-12-19 2014-04-16 柳州欧维姆机械股份有限公司 Automatic beam placement platform device and construction method of replacing railway beams thereby

Also Published As

Publication number Publication date
JP2008169552A (en) 2008-07-24

Similar Documents

Publication Publication Date Title
JP5097313B2 (en) Suspended scaffold and its installation method
AU2013212529B2 (en) Automated formwork climbing system
CN103967277A (en) Construction method of super-high-rise core tube inclined shear wall
JP6180376B2 (en) Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
JP7172916B2 (en) Bridge superstructure removal method
CN110847169B (en) Construction method of steel pipe pile steel trestle
JP5563961B2 (en) H steel support system and method of dismantling building using the same
JP2003221875A (en) Rail-less slide method
KR101941942B1 (en) Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same
JP4755998B2 (en) Cutting and rehabilitating connecting bridges with different distances between buildings
JP6143070B2 (en) Building demolition method
JP2007218029A (en) Girder lifting erection method and girder erection joint structure
KR102085928B1 (en) Temporary bridge with end corner member and construction method therefor
JP7136309B2 (en) Superstructure material transportation equipment and superstructure material transportation method
JP7461855B2 (en) Superstructure support structure, step prevention structure and bearing replacement method
JP6969646B2 (en) Superstructure material transportation equipment and superstructure material transportation method
CN211691535U (en) Assembled platform of unloading of encorbelmenting
CN212743307U (en) Steel construction work platform of assembled
CN209907886U (en) Adjustable assembled stair construction platform
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
JP4375788B2 (en) Construction method of upper-floor type suspension floor slab bridge
CN115162823B (en) Assembling method of pinnacle steel member
KR102416758B1 (en) Cantilever structure for bridge and construction method of cantilever structure for bridge
CN115075530B (en) Cantilever structure and construction method thereof
JP3922952B2 (en) Bridge floor slab and replacement method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091224

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110427

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110517

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110530

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140603

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4755998

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150