JP4348108B2 - Bridge replacement method and bridge - Google Patents

Bridge replacement method and bridge Download PDF

Info

Publication number
JP4348108B2
JP4348108B2 JP2003125177A JP2003125177A JP4348108B2 JP 4348108 B2 JP4348108 B2 JP 4348108B2 JP 2003125177 A JP2003125177 A JP 2003125177A JP 2003125177 A JP2003125177 A JP 2003125177A JP 4348108 B2 JP4348108 B2 JP 4348108B2
Authority
JP
Japan
Prior art keywords
upper structure
bridge
piers
existing
superstructure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003125177A
Other languages
Japanese (ja)
Other versions
JP2004332222A (en
Inventor
伊知郎 増田
眞二 中谷
茂 永谷
俊蔵 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MM Bridge Co Ltd
Original Assignee
Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd filed Critical Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd
Priority to JP2003125177A priority Critical patent/JP4348108B2/en
Publication of JP2004332222A publication Critical patent/JP2004332222A/en
Application granted granted Critical
Publication of JP4348108B2 publication Critical patent/JP4348108B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、橋梁の架替工法、およびその架替工法により構築された橋梁に関する。
【0002】
【従来の技術】
経年変化や交通量の増加等により耐用期間が満了に近づいた橋梁の架け替えを行う場合、その方法としては、隣り合う2つの橋脚間において新規橋桁を構築し、この新規橋桁を支保工昇降機構を用いて上方へ移動させ、新規橋桁に旧橋桁の荷重を支持させた状態で旧橋桁を橋体から切り離し、新たに新規橋桁を2つの橋脚に支承させ、新規橋桁上で旧橋桁を解体、撤去する例がある(下記の特許文献1)。
その他の方法としては、隣り合う2つの橋脚間にジャッキを配置し、このジャッキを用いて既設橋桁を下方から支持した状態で、既設橋桁上において新設橋桁を構築し、新設橋桁が完成したらジャッキにより既設、新設の両橋桁を降下させ、新設橋桁を2つの橋脚に支承させ、既設橋桁のみさらに降下させて撤去する例がある(下記の特許文献2)。
【0003】
【特許文献1】
特開平11−190008号公報
【特許文献2】
特開2003−34911号公報
【0004】
【発明が解決しようとする課題】
新規橋桁を上方に移動させ、旧橋桁と入れ替える先の例では、新規橋桁が両側の橋桁と同じ高さとなったところで、別個に用意した継ぎブロックを橋桁上に搬入し、この継ぎブロックを新規橋桁と両側の橋桁との間に挿入して新規橋桁を両側の橋桁と接合し、橋脚に新規橋桁を支承させている。この工法では、新規橋桁を構築する間は旧橋桁上の通行が可能であるが、継ぎブロックを用いた橋桁の接合作業に手間が掛かる。この作業の間は旧橋桁上の通行が不可能であり、長期に渡って橋梁の利用が不可能になるために周辺地域に社会的、経済的に大きな損失を与えることになる。
【0005】
新設橋桁を降下させ、既設橋桁と入れ替える後の例では、新設橋桁を当初から2つの橋脚間に架設できる長さに構築し、ジャッキにより既設、新設の両橋桁を降下させる際に既設橋桁の両端を切除し、2つの橋脚間に既設橋桁を落とし込ませている。この工法では、新設橋桁を既設橋桁上で構築するため、新設橋桁の構築を開始してから既設橋桁との入れ替えを終えるまで既設橋桁上の通行が不可能であり、先の例以上に周辺地域に社会的、経済的に大きな損失を与えることになる。
【0006】
本発明は上記の事情に鑑みてなされたものであり、橋桁の架け替えに要する期間を短縮することにより周辺地域が被る社会的、経済的な損失を軽減させることを目的としている。
【0007】
【課題を解決するための手段】
上記の課題を解決するための手段として、次のような構成の橋梁の架替工法、および橋梁を採用する。すなわち本発明に係る橋梁の架替工法は、隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向の長さが可変な構造を有する新設の分割された上部構造物を、前記橋軸方向に短縮した状態で配置し、前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の分割された上部構造物で押し上げて前記2つの橋脚から分離し、前記既存の上部構造物を撤去する前、または撤去した後に、前記新設の分割された上部構造物を前記橋軸方向に伸長し一体化して前記2つの橋脚間に架設することを特徴とする。
【0008】
本発明に係る橋梁の架替工法は、隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向に複数に分割された新設の上部構造物を、個々の分割体を積み重ねた状態で配置し、前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の上部構造物で押し上げて前記2つの橋脚から分離し、前記既存の上部構造物を利用して前記個々の分割体を前記橋軸方向に配列し、配列された前記個々の分割体を結合し前記新設の上部構造物として一体化して前記2つの橋脚間に架設することを特徴とする。
【0009】
本発明に係る橋梁は、隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向の長さが可変な構造を有する新設の上部構造物を、前記橋軸方向に短縮した状態で配置し、前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の上部構造物で押し上げて前記2つの橋脚から分離し、前記既存の上部構造物を撤去する前、または撤去した後に、前記新設の上部構造物を前記橋軸方向に伸長して前記2つの橋脚間に架設したことを特徴とする。
【0010】
本発明に係る橋梁は、隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向に複数に分割された新設の上部構造物を、個々の分割体を積み重ねた状態で配置し、前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の上部構造物で押し上げて前記2つの橋脚から分離し、前記既存の上部構造物を利用して前記個々の分割体を前記橋軸方向に配列し、配列された前記個々の分割体を結合し前記新設の上部構造物として一体化して前記2つの橋脚間に架設したことを特徴とする。
【0011】
本発明に係る橋梁の上部構造物は、隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、隣り合う前記2つの橋脚間に架設される橋梁の上部構造物であって、橋軸方向に複数に分割され、隣り合う分割体どうしが上面でヒンジ連結されて前記橋軸方向の長さが可変な構造を有する新設の分割された上部構造物を、前記橋軸方向に短縮した状態で配置し、前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された前記既存の上部構造物を前記新設の分割された上部構造物で押し上げて前記2つの橋脚から分離し、前記既存の上部構造物を撤去する前、または撤去した後に、前記新設の分割された上部構造物を前記橋軸方向に伸長し一体化して前記2つの橋脚間に架設したことを特徴とする。
【0012】
本発明においては、長さを短縮した新設の上部構造物を上方に移動させて既設の上部構造物と入れ替え、既存の上部構造物を撤去する前、または撤去した後に伸長し、隣り合う2つの橋脚間に架設する。本発明によれば、新設の上部構造物を橋軸方向の長さが可変な構造とすることにより、新設の上部構造物の架設作業が短期間のうちに行えるようになるので、橋梁を利用できなくなる期間が短くて済み、周辺地域が被る社会的、経済的な損失を軽減させることができる。
【0013】
本発明においては、新設の上部構造物を橋軸方向に複数に分割するとともに隣り合う分割体どうしをヒンジ連結することで橋軸方向に長さが可変な構造とし、既存の上部構造物を撤去した後に、新設の上部構造物を橋軸方向に伸長して2つの橋脚間に架設することが望ましい。新設の上部構造物を橋軸方向に複数に分割し、隣り合う分割体どうしをヒンジ連結することにより、新設の上部構造物を長さが可変な構造とすることが非常に簡易に、かつ安価に実現されるので、架設作業の効率化ならびに施工コストの削減が図れる。
【0014】
本発明においては、個々の分割体を積み重ねた状態で配置した新設の上部構造物を上方に移動させて既設の上部構造物と入れ替え、既存の上部構造物を利用して個々の分割体を前記橋軸方向に配列し、配列された個々の分割体を結合し新設の上部構造物として一体化して2つの橋脚間に架設する。本発明によれば、新設の上部構造物を個々の分割体に分け、個々の分割体を既存の上部構造物を利用して橋軸方向に配列することにより、新設の上部構造物の架設作業が短期間のうちに行えるようになるので、橋梁を利用できなくなる期間が短くて済み、周辺地域が被る社会的、経済的な損失を軽減させることができる。
【0015】
本発明においては、既存の上部構造物に軌道を取り付け、軌道に沿って個々の分割体を橋軸方向に移動させることが望ましい。既存の上部構造物に取り付けた軌道に沿って個々の分割体を移動させることにより、分割体の配列作業が行い易くなるので、架設作業の効率化ならびに施工コストの削減が図れる。
【0016】
本発明においては、橋脚を当初は高さ方向に複数に分割しておき、個々の分割体を、より上端近くに設置すべきものがひとつずつ上方に移動するように積み重ねて構築することが望ましい。このようにすれば橋脚をジャッキとして利用して上部構造物の架け替えと同時に橋脚の再構築も可能になるので、橋梁の全面的な架替工事に関して作業の効率化ならびに施工コストの削減が図れる。
【0017】
【発明の実施の形態】
本発明に係る第1の実施形態を図1ないし図3に示して説明する。
図1には、両端部を折り畳むことで橋軸方向の長さを変化させることができる上部構造物1を示している。上部構造物1は、橋桁2と床版3とが一体化されたもので、橋軸方向に3つに分割されており、各分割体のうち主体となる中間部4の橋軸方向の両側に、端部5,6がヒンジ部7を介してそれぞれ連結されている。端部5,6は、いずれもヒンジ部7を中心として中間部4の上面側にほぼ180°回動することができ、この状態では中間部4上に端部5,6が載置されることになる。
【0018】
上記のように構成された上部構造物を用いて行う橋梁の架替工法を図2、図3を参照して説明する。
まず、図2(a)に示すように、隣り合う2つの橋脚10,10間に、橋軸方向に離間させて複数の大型ジャッキ11を配置する。大型ジャッキ11はいずれも短縮させておく。短縮させた大型ジャッキ11上に、図1に示した新設の上部構造物1を、両端部5,6を中間部4上に折り畳んで橋軸方向の長さを短縮した状態で配置する。折り畳んだ新設の上部構造物1上には、シンクロジャッキ12およびローラ架台13を配置しておく。
【0019】
次に、図2(b)に示すように、大型ジャッキ11を伸長し、橋脚10,10間に架設された既設の上部構造物14を、シンクロジャッキ12およびローラ架台13を介して新設の上部構造物1上に支持する。続けて大型ジャッキ11を伸長し、既存の上部構造物14を新設の上部構造物1で押し上げて橋脚10から分離する。さらに大型ジャッキ11の伸長を続け、新設の上部構造物1を両側の上部構造物14’と同じ高さにまで上昇させる。なお、既設の上部構造物14を橋脚10や両側の上部構造物14’に固定していた連結ボルト等の締着手段(図示略)は事前に撤去しておく。
【0020】
新設の上部構造物1を両側の上部構造物14’と同じ高さにまで上昇させたら、図2(c)に示すように、新設の上部構造物1上でシンクロジャッキ12を駆動し、既設の上部構造物14を橋軸方向の一方に移動させる。新設の上部構造物1上で可能な限りシンクロジャッキ12を移動させたら、シンクロジャッキ12を短縮し、既設の上部構造物14をローラ架台13のみで支持した状態としたうえで、シンクロジャッキ12を橋軸方向の他方に移動させる。シンクロジャッキ12を伸長して既設の上部構造物14を支持し、再びシンクロジャッキ12を駆動し、既設の上部構造物14を橋軸方向の一方に移動させる。この作業を何度か繰り返し、必要になれば橋軸方向の一方に位置する上部構造物14’上にもシンクロジャッキ12を配置して撤去すべき既存の上部構造物14を支持する。
【0021】
次に、図3(a)に示すように、上部構造物14’上にトレーラ15を配置し、このトレーラ15上に既存の上部構造物14の一端を順次送り出す。トレーラ15上に架かった既存の上部構造物14が適当な長さになったら、この部分をカッターで切断してトレーラ15に載せ、橋梁上から撤去する。残った部分についても上記と同様の作業を繰り返して切断、撤去する。
【0022】
既設の上部構造物14をすべて撤去したら、図3(b)に示すように、大型ジャッキ11を伸長させて新設の上部構造物1をもう一段階上昇させたうえで、両側の上部構造物14’上にそれぞれトラッククレーン16を配置し、新設の上部構造物1の折り畳んでいた両端部5,6をトラッククレーン16で吊り上げるようにして展開させる。両端部5,6を展開させたら、大型ジャッキ11を短縮させて新設の上部構造物1を一段階降下させたうえで、連結ボルト等の締着手段(図示略)を用いて新設の上部構造物1と両側の上部構造物14’、さらにこれら構造物と橋脚10とを締着する。
【0023】
各部を締着して十分な強度が確保できたら、新設の上部構造物1からヒンジ部分(図示略)を撤去するとともに、図3(c)に示すように大型ジャッキ11を短縮、撤去して架替工事を完了する。これにより、橋脚10,10間に新設の上部構造物1が架設される。以降は隣接する既設の上部構造物14’についても続けて同様の架替作業を行う。
【0024】
本実施形態の架替工法によれば、新設の上部構造物1を橋軸方向の長さが可変な構造とすることにより、上部構造物1の架設作業が短期間のうちに行えるようになるので、橋梁を利用できなくなる期間が短くて済み、周辺地域が被る社会的、経済的な損失を軽減させることができる。
【0025】
また、新設の上部構造物1を橋軸方向に複数に分割し、隣り合う分割体(中間体4,端部5,6)どうしをヒンジ連結することにより、上部構造物1を長さが可変な構造とすることが非常に簡易に、かつ安価に実現されるので、架設作業の効率化ならびに施工コストの削減が可能である。
【0026】
なお、本実施形態においては既設の上部構造物14を撤去した後に新設の上部構造物1を展開しているが、既設の上部構造物14を撤去する前に新設の上部構造物1を展開するようにしてもよい。
【0027】
次に、本発明に係る第2の実施形態を図4から図6に示して説明する。なお、上記実施形態において既に説明した構成要素には同一符号を付して説明は省略する。
本実施形態において、新設する上部構造物1はヒンジ連結されておらず、単に橋軸方向に複数に分割されているだけである。このような上部構造物を用いて行う橋梁の架替工法を図4から図6を参照して説明する。
まず、図4(a)に示すように、隣り合う2つの橋脚10,10間に、橋軸方向に離間させて複数の大型ジャッキ11を配置する。大型ジャッキ11はいずれも短縮させておく。短縮させた大型ジャッキ11上に、新設の上部構造物1を、両端部5,6を中間部4上に積み重ねた状態で配置する。新設の上部構造物1上には、シンクロジャッキ12、ローラ架台13および小型ジャッキ19を配置し、さらにシンクロジャッキ12およびローラ架台13の上に複数本のガイドレール(軌道)20を橋軸方向に沿って並べて仮置きしておく。
【0028】
次に、図4(b)に示すように、大型ジャッキ11を伸長し、橋脚10,10間に架設された既設の上部構造物14の下面にガイドレール20を沿わせる。既設の上部構造物14の下面にガイドレール20を沿わせたら、シンクロジャッキ12を駆動し、2本のガイドレール20を橋軸方向の相反する方向にそれぞれ移動させる。新設の上部構造物1上で可能な限りシンクロジャッキ12を移動させ、2本のガイドレール20の端部を既存の上部構造物14の両端部に達するまで移動させたら、図4(c)に示すように、既設の上部構造物14の下面にガイドレール20を固定する。
【0029】
既設の上部構造物14の下面にガイドレール20を固定したら、再び大型ジャッキ11を伸長し、既存の上部構造物14を新設の上部構造物1で押し上げて橋脚10から分離する。さらに大型ジャッキ11の伸長を続け、図5(a)に示すように、新設の上部構造物1を両側の上部構造物14’と同じ高さにまで上昇させる。なお、既設の上部構造物14を橋脚10や両側の上部構造物14’に固定していた連結ボルト等の締着手段(図示略)は事前に撤去しておく。
【0030】
新設の上部構造物1を両側の上部構造物14’と同じ高さにまで上昇させたら、図5(b)に示すように、新設の上部構造物1の両端部5,6を、ガイドレール20に吊り下げ、橋脚10側に移動させる。なお、両端部5,6の移動は、シンクロジャッキ12に支持された既設の上部構造物14のバランスを崩さないように両方で同時進行させることが望ましい。
【0031】
新設の上部構造物1の両端部5,6を、中間部4と両側の上部構造物14’との間隙上にそれぞれ移動させたら、図5(c)に示すように、両端部を吊り降ろして間隙21に填め込み、連結ボルト等の締着手段(図示略)を用いて中間部や両側の上部構造物14’、さらに橋脚10に締着する。
【0032】
各部を締着して十分な強度が確保できたら、図6(a)に示すように、両側の上部構造物14’上から新設の上部構造物1上にトレーラ15をそれぞれ配置し、各トレーラ15上に既存の上部構造物14の端部を差し掛けるように配置する。シンクロジャッキ12および小型ジャッキ19を短縮し、既存の上部構造物14を各トレーラ15に支持させる。既存の上部構造物14のトレーラ15上に差し掛かった部分をカッターで切断してトレーラ15に載せ、トレーラ15を牽引して橋梁上から撤去する。残った部分については、図6(b)に示すように、シンクロジャッキ12および小型ジャッキ19を盛り代えて支持しておき、後に別のトレーラ15に載せて撤去する。
【0033】
既設の上部構造物14をすべて撤去したら、図6(c)に示すように大型ジャッキ11を短縮、撤去して架替工事を完了する。これにより、橋脚10,10間に新設の上部構造物1が架設される。以降は隣接する既設の上部構造物14’についても続けて同様の架替作業を行う。
【0034】
本実施形態の架替工法によれば、新設の上部構造物1を複数に分割し、両端部5,6を既存の上部構造物14を利用して橋軸方向に配列することにより、新設の上部構造物1の架設作業が短期間のうちに行えるようになるので、橋梁を利用できなくなる期間が短くて済み、周辺地域が被る社会的、経済的な損失を軽減させることができる。
【0035】
また、既存の上部構造物14に取り付けたガイドレール20に沿って両端部5,6を移動させることにより、両端部5,6の配列作業が行い易くなるので、架設作業の効率化ならびに施工コストの削減が可能である。
【0036】
次に、本発明に係る第3の実施形態を図7から図9に示して説明する。なお、上記実施形態において既に説明した構成要素には同一符号を付して説明は省略する。
本実施形態においては、両端部5,6を折り畳むことができる上部構造物1Aと、一方の端部6のみ折り畳むことができる上部構造物1Bの2つを用いる。また、ジャッキアップ式の橋脚30を用いる。ジャッキアップ式の橋脚30は、図7に示すように、高さ方向にほぼ等しい長さで複数に分割されており、個々の分割体31が、より上端近くに設置すべきものをひとつずつ上方に移動させるように下端側から積み重ねられて構築される。橋脚30を支持する基礎32上には、積み上げた分割体31を分割体31ひとつ分持ち上げるための支保工33が設置され、個々の分割体31には、支保工33に沿って自らを上方に押し上げるスライドジャッキ34が設けられている。
このような上部構造物1A,1B、およびジャッキアップ式の橋脚30を用いて行う橋梁の架替工法を図8、図9を参照して説明する。
【0037】
まず、図8(a)に示すように、橋軸方向に並ぶ3つの橋脚10A,10B,10Cのうち、隣り合う橋脚10A,10Bのそれぞれに隣接させて基礎32を構築し、この基礎32にジャッキアップ式の橋脚30を構築するとともに、隣り合う橋脚10B,10Cのそれぞれに隣接させて大型ジャッキ11を配置する。ジャッキアップ式の橋脚30は最も短い分割体31ひとつ分の高さとし、大型ジャッキ11はいずれも短縮させておく。ジャッキアップ式の橋脚30および大型ジャッキ11上に、新設の上部構造物1A,1Bを、各端部5,6を折り畳んで橋軸方向の長さを短縮した状態で配置する。折り畳んだ新設の上部構造物1A,1B上には、シンクロジャッキ12およびローラ架台13を配置しておく。
【0038】
次に、図8(b)に示すように、ジャッキアップ式の橋脚30および大型ジャッキ11を伸長し、橋脚10A〜10C間に架設された既設の上部構造物14を、シンクロジャッキ12およびローラ架台13を介して新設の上部構造物1A,1B上に支持する。続けてジャッキアップ式の橋脚30および大型ジャッキ11を伸長し、既存の上部構造物14を新設の上部構造物1A,1Bで押し上げて橋脚10から分離する。さらにジャッキアップ式の橋脚30および大型ジャッキ11の伸長を続け、新設の上部構造物1A,1Bを両側の上部構造物14’と同じ高さにまで上昇させる。なお、既設の上部構造物14を橋脚10A,10B,10Cや両側の上部構造物14’に固定していた連結ボルト等の締着手段(図示略)は事前に撤去しておく。
【0039】
新設の上部構造物1を両側の上部構造物14’と同じ高さにまで上昇させたら、図8(c)に示すように、新設の上部構造物1A,1B上でシンクロジャッキ12を駆動し、既設の上部構造物14を橋軸方向の一方に移動させる。新設の上部構造物1A,1B上で可能な限りシンクロジャッキ12を移動させたら、シンクロジャッキ12を短縮し、既設の上部構造物14をローラ架台13のみで支持した状態としたうえで、シンクロジャッキ12を橋軸方向の他方に移動させる。シンクロジャッキ12を伸長して既設の上部構造物14を支持し、再びシンクロジャッキ12を駆動し、既設の上部構造物14を橋軸方向の一方に移動させる。
【0040】
次に、図9(a)に示すように、上部構造物14’上にトレーラ15を配置し、このトレーラ15上に既存の上部構造物14の一端を順次送り出す。トレーラ15上に架かった既存の上部構造物14が適当な長さになったら、この部分をカッターで切断してトレーラ15に載せ、橋梁上から撤去する。残った部分についても上記と同様の作業を繰り返して切断、撤去する。
【0041】
既設の上部構造物14をすべて撤去したら、図9(b)に示すように、ジャッキアップ式の橋脚30および大型ジャッキ11を伸長させて新設の上部構造物1をもう一段階上昇させたうえで、両側の上部構造物14’上にそれぞれトラッククレーン16を配置し、新設の上部構造物1A,1Bの折り畳んでいた各端部5,6をトラッククレーン16で吊り上げるようにして展開させる。各端部5,6を展開させたら、ジャッキアップ式の橋脚30および大型ジャッキ11を短縮させて新設の上部構造物1A,1Bを一段階降下させる。
【0042】
新設の上部構造物1A,1Bの各部を連結ボルトで締着して十分な強度が確保できたら、新設の上部構造物1A,1Bからヒンジ部分(図示略)を撤去するとともに、図9(c)に示すように、大型ジャッキ11および既設の橋脚10A,10Bを撤去して架替工事を完了する。これにより、橋軸方向に並ぶ3つの橋脚30,30,10C間に新設の上部構造物1A,1Bが架設される。以降は隣接する既設の上部構造物14’についても続けて同様の架替作業を行う。
【0043】
本実施形態の架替工法によれば、橋脚をジャッキとして利用して上部構造物の架け替えと同時に橋脚の再構築も可能になるので、橋梁の全面的な架替工事に関して作業の効率化ならびに施工コストの削減が可能である。
【0044】
なお、本実施形態においては、上部構造物に上記第1の実施形態のようなヒンジ連結による長さの可変構造を与えたが、これに代えて上部構造物に上記第2の実施形態のようなガイドレールによる長さの可変構造を与えてもよい。
また、本実施形態においては、上部構造物の架け替えに併せて橋脚の再構築を行ったが、上部構造物はそのまま使用し、橋脚だけを再構築する場合もある。
【0045】
【発明の効果】
以上説明したように、本発明によれば、新設の上部構造物を橋軸方向に長さの可変な構造とすることにより、新設の上部構造物の架設作業が短期間のうちに行えるようになるので、橋梁を利用できなくなる期間が短くて済み、周辺地域が被る社会的、経済的な損失を軽減させることができる。
【0046】
本発明によれば、新設の上部構造物を橋軸方向に複数に分割し、隣り合う分割体どうしをヒンジ連結することにより、新設の上部構造物を長さの可変な構造とすることが非常に簡易に、かつ安価に実現されるので、架設作業の効率化ならびに施工コストの削減が可能である。
【0047】
本発明によれば、新設の上部構造物を個々の分割体に分け、個々の分割体を既存の上部構造物を利用して橋軸方向に配列することにより、新設の上部構造物の架設作業が短期間のうちに行えるようになるので、橋梁を利用できなくなる期間が短くて済み、周辺地域が被る社会的、経済的な損失を軽減させることができる。
【0048】
本発明によれば、既存の上部構造物に取り付けた軌道に沿って個々の分割体を移動させることにより、分割体の配列作業が行い易くなるので、架設作業の効率化ならびに施工コストの削減が可能である。
【0049】
本発明によれば、橋脚をジャッキとして利用して上部構造物の架け替えと同時に橋脚の再構築も可能になるので、橋梁の全面的な架替工事に関して作業の効率化ならびに施工コストの削減が可能である。
【図面の簡単な説明】
【図1】 本発明に係る第1の実施形態を示す図であって、橋軸方向の長さが可変な構造を与えられた上部構造物を示す側面図である。
【図2】 第1の実施形態における橋梁の架替工法を説明するための段階的な状態図である。
【図3】 同じく、第1の実施形態における橋梁の架替工法を説明するための段階的な状態図である。
【図4】 本発明に係る第2の実施形態を示す図であって、橋梁の架替工法を説明するための段階的な状態図である。
【図5】 同じく、第2の実施形態における橋梁の架替工法を説明するための段階的な状態図である。
【図6】 同じく、第2の実施形態における橋梁の架替工法を説明するための段階的な状態図である。
【図7】 本発明に係る第3の実施形態を示す図であって、ジャッキアップ式の橋脚の構造を示す側面図である。
【図8】 第3の実施形態における橋梁の架替工法を説明するための段階的な状態図である。
【図9】 同じく、第3の実施形態における橋梁の架替工法を説明するための段階的な状態図である。
【符号の説明】
1 新設の上部構造物
2 橋桁
3 床版
4 中間部
5,6 端部
7 ヒンジ部
10 橋脚
11 大型ジャッキ
12 シンクロジャッキ
13 ローラ架台
14 既設の上部構造物
15 トレーラ
19 小型ジャッキ
20 ガイドレール(軌道)
21 間隙
30 ジャッキアップ式の橋脚
31 個々の分割体
32 基礎
33 支保工
34 スライドジャッキ
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a bridge replacement method and a bridge constructed by the replacement method.
[0002]
[Prior art]
When replacing a bridge that has reached the end of its useful life due to secular change or increased traffic, a new bridge girder is constructed between two adjacent piers, and this new bridge girder is supported by a lifting mechanism. The old bridge girder is detached from the bridge body with the new bridge girder supporting the load of the old bridge girder, the new bridge girder is supported on the two piers, and the old bridge girder is disassembled on the new bridge girder, There is an example of removal (Patent Document 1 below).
As another method, a jack is placed between two adjacent piers, and the existing bridge girder is supported from below using this jack, and a new bridge girder is constructed on the existing bridge girder. There is an example in which both existing and new bridge girders are lowered, the new bridge girders are supported on two piers, and only the existing bridge girders are further lowered and removed (Patent Document 2 below).
[0003]
[Patent Document 1]
Japanese Patent Laid-Open No. 11-190008
[Patent Document 2]
JP 2003-34911 A
[0004]
[Problems to be solved by the invention]
In the previous example where the new bridge girder is moved upward and replaced with the old bridge girder, when the new bridge girder is at the same height as the bridge girder on both sides, a separately prepared joint block is carried onto the bridge girder, and this joint block is moved to the new bridge girder. Is inserted between the bridge girder on both sides and the new bridge girder is joined to the bridge girder on both sides, and the new bridge girder is supported on the pier. In this method, while the new bridge girder is constructed, it is possible to pass on the old bridge girder, but it takes time to join the bridge girder using the joint block. During this work, traffic on the old bridge girder is impossible, and the use of the bridge over a long period of time becomes impossible, resulting in a large social and economic loss in the surrounding area.
[0005]
In the example after the new bridge girder is lowered and replaced with the existing bridge girder, the new bridge girder is constructed to a length that can be installed between the two piers from the beginning, and both ends of the existing bridge girder are lowered when the existing and new bridge girder are lowered with a jack. The existing bridge girder is dropped between the two piers. In this construction method, since the new bridge girder is built on the existing bridge girder, it is impossible to pass on the existing bridge girder from the start of construction of the new bridge girder until the replacement with the existing bridge girder. Will cause great social and economic losses.
[0006]
This invention is made | formed in view of said situation, and it aims at reducing the social and economical loss which a surrounding area suffers by shortening the period required for bridge girder replacement.
[0007]
[Means for Solving the Problems]
As means for solving the above-mentioned problems, a bridge replacement method and a bridge having the following configuration are adopted. That is, the bridge replacement method according to the present invention is a new construction having a structure in which the length in the bridge axis direction is variable on a jack located between two adjacent piers and below an existing superstructure. Divided The upper structure is arranged in a state shortened in the bridge axis direction, and the jack is extended upward, so that the existing upper structure constructed between the two bridge piers is installed in the newly installed structure. Divided It is pushed up by the superstructure and separated from the two piers, and the new superstructure is installed before or after the existing superstructure is removed. Divided Extend the superstructure in the direction of the bridge axis Integrated It is constructed between the two bridge piers.
[0008]
In the bridge replacement method according to the present invention, a new upper structure divided into a plurality of pieces in the bridge axis direction is individually placed on a jack located between two adjacent piers and below the existing upper structure. Are arranged in a stacked state, and by extending the jack upward, the existing upper structure constructed between the two piers is pushed up by the new upper structure, and the two piers are Separating, using the existing upper structure, arranging the individual divided bodies in the bridge axis direction, combining the arranged individual divided bodies, and integrating them as the new upper structure; It is constructed between two piers.
[0009]
In the bridge according to the present invention, a new upper structure having a structure in which the length in the bridge axis direction is variable is placed on a jack located between two adjacent piers and below the existing upper structure. Arranged in a shortened state in the axial direction and extending the jack upward, the existing upper structure built between the two piers is pushed up by the new upper structure and separated from the two piers. Then, before or after the existing upper structure is removed, the new upper structure is extended in the direction of the bridge axis and installed between the two piers.
[0010]
In the bridge according to the present invention, a new upper structure divided into a plurality of parts in the bridge axis direction is placed on a jack disposed between two adjacent piers and below an existing upper structure. Arranged in a stacked state and extending the jack upward, the existing upper structure constructed between the two piers is pushed up by the new upper structure and separated from the two piers, Using the existing superstructure, the individual divisions are arranged in the direction of the bridge axis, and the arranged individual divisions are combined and integrated as the new superstructure, between the two piers. Characterized by erection.
[0011]
The superstructure of the bridge according to the present invention is On the jack placed between two adjacent piers and below the existing superstructure, An upper structure of a bridge constructed between the two adjacent piers, which is divided into a plurality of pieces in the bridge axis direction, and the adjacent divided bodies are hinged on the upper surface so that the length in the bridge axis direction is variable. The existing divided upper structure having a simple structure is arranged in a state of being shortened in the bridge axis direction, and the jack is extended upward, whereby the existing upper structure constructed between the two bridge piers. The new divided upper structure is pushed up by the new divided upper structure and separated from the two piers, and the new divided upper structure is moved to the bridge before or after the existing upper structure is removed. Along the two piers, extending in the axial direction and integrated. It is characterized by that.
[0012]
In the present invention, the new upper structure whose length is shortened is moved upward to replace the existing upper structure, and is extended before or after the existing upper structure is removed. Build between the piers. According to the present invention, the construction of the newly constructed superstructure can be carried out in a short period of time by making the construction of the newly constructed superstructure variable in the bridge axis direction. The period during which it cannot be done can be shortened, and the social and economic losses incurred by the surrounding area can be reduced.
[0013]
In the present invention, the newly constructed upper structure is divided into a plurality of pieces in the bridge axis direction and the adjacent divided bodies are hinged to each other so that the length is variable in the bridge axis direction, and the existing upper structure is removed. After that, it is desirable to extend the newly constructed superstructure in the direction of the bridge axis and install it between the two piers. It is very easy and inexpensive to divide the new upper structure into multiple parts in the bridge axis direction and to connect the adjacent divided bodies with hinges to make the new upper structure variable in length. Therefore, the construction work can be made more efficient and the construction cost can be reduced.
[0014]
In the present invention, the new upper structure arranged in a state where the individual divided bodies are stacked is moved upward to replace the existing upper structure, and the individual divided bodies are replaced with the existing upper structure using the existing upper structure. They are arranged in the direction of the bridge axis, and the individual divided bodies arranged are combined and integrated as a new superstructure and installed between two piers. According to the present invention, the newly constructed upper structure is divided into individual divided bodies, and the individual divided bodies are arranged in the direction of the bridge axis using the existing upper structures. Can be done in a short period of time, the period during which the bridge cannot be used can be shortened, and the social and economic losses incurred by the surrounding area can be reduced.
[0015]
In the present invention, it is desirable to attach a track to an existing superstructure and to move the individual divided bodies along the track in the direction of the bridge axis. By moving the individual divided bodies along the track attached to the existing superstructure, the arrangement work of the divided bodies can be easily performed, so that the construction work can be made more efficient and the construction cost can be reduced.
[0016]
In the present invention, it is desirable to divide the pier into a plurality of parts in the height direction at the beginning, and to build each divided body so that those to be installed closer to the upper end move upward one by one. In this way, the bridge pier can be used as a jack and the pier can be reconstructed at the same time as the replacement of the superstructure. Therefore, the work efficiency and the construction cost can be reduced for the entire bridge replacement work. .
[0017]
DETAILED DESCRIPTION OF THE INVENTION
A first embodiment according to the present invention will be described with reference to FIGS.
FIG. 1 shows an upper structure 1 that can change the length in the bridge axis direction by folding both ends. The superstructure 1 is composed of a bridge girder 2 and a floor slab 3 that are integrated into three parts in the bridge axis direction, and both sides in the bridge axis direction of the intermediate part 4 that is the main part of each divided body. The end portions 5 and 6 are connected to each other via the hinge portion 7. Each of the end portions 5 and 6 can be rotated by approximately 180 ° on the upper surface side of the intermediate portion 4 around the hinge portion 7. In this state, the end portions 5 and 6 are placed on the intermediate portion 4. It will be.
[0018]
A bridge replacement method using the superstructure configured as described above will be described with reference to FIGS.
First, as shown in FIG. 2A, a plurality of large jacks 11 are disposed between two adjacent bridge piers 10 and 10 so as to be separated in the bridge axis direction. Both large jacks 11 are shortened. The newly installed upper structure 1 shown in FIG. 1 is placed on the shortened large jack 11 in a state in which both end portions 5 and 6 are folded on the intermediate portion 4 and the length in the bridge axis direction is shortened. A sync jack 12 and a roller mount 13 are arranged on the newly-folded upper structure 1.
[0019]
Next, as shown in FIG. 2 (b), the large jack 11 is extended, and the existing upper structure 14 installed between the piers 10, 10 is replaced with the newly installed upper part via the sync jack 12 and the roller mount 13. It is supported on the structure 1. Subsequently, the large jack 11 is extended, and the existing upper structure 14 is pushed up by the new upper structure 1 and separated from the pier 10. Further, the large jack 11 is continuously extended, and the newly installed upper structure 1 is raised to the same height as the upper structures 14 'on both sides. It should be noted that fastening means (not shown) such as connecting bolts that have fixed the existing upper structure 14 to the pier 10 or the upper structure 14 'on both sides are removed in advance.
[0020]
When the new upper structure 1 is raised to the same height as the upper structures 14 'on both sides, the sync jack 12 is driven on the new upper structure 1 as shown in FIG. The upper structure 14 is moved to one side in the bridge axis direction. After the sync jack 12 is moved as much as possible on the new upper structure 1, the sync jack 12 is shortened so that the existing upper structure 14 is supported only by the roller mount 13, and the sync jack 12 is Move to the other in the direction of the bridge axis. The sync jack 12 is extended to support the existing upper structure 14, the sync jack 12 is driven again, and the existing upper structure 14 is moved to one side in the bridge axis direction. This operation is repeated several times. If necessary, the existing jack 14 to be removed is supported by disposing the sync jack 12 on the upper structure 14 'located on one side in the bridge axis direction.
[0021]
Next, as shown in FIG. 3A, the trailer 15 is disposed on the upper structure 14 ′, and one end of the existing upper structure 14 is sequentially delivered onto the trailer 15. When the existing superstructure 14 on the trailer 15 has an appropriate length, this portion is cut with a cutter, placed on the trailer 15, and removed from the bridge. The remaining part is cut and removed by repeating the same operation as above.
[0022]
When all the existing upper structures 14 are removed, as shown in FIG. 3 (b), the large jack 11 is extended to raise the new upper structure 1 one more stage, and then the upper structures 14 on both sides are removed. The truck cranes 16 are respectively arranged on the upper side, and the folded ends 5 and 6 of the newly installed superstructure 1 are lifted by the truck crane 16 and deployed. When both ends 5 and 6 are deployed, the large jack 11 is shortened to lower the newly installed upper structure 1 by one step, and then the newly installed upper structure is used using fastening means (not shown) such as a connecting bolt. The object 1 and the upper structures 14 ′ on both sides, and these structures and the pier 10 are fastened.
[0023]
When each part is fastened and sufficient strength is secured, the hinge portion (not shown) is removed from the newly constructed upper structure 1, and the large jack 11 is shortened and removed as shown in FIG. 3 (c). Complete the replacement work. Thereby, the newly installed upper structure 1 is installed between the piers 10 and 10. Thereafter, the same replacement work is continuously performed on the adjacent existing upper structure 14 '.
[0024]
According to the replacement construction method of the present embodiment, the construction work of the upper structure 1 can be performed in a short period of time by making the newly constructed upper structure 1 a structure whose length in the bridge axis direction is variable. Therefore, the period during which the bridge cannot be used can be shortened, and the social and economic losses incurred by the surrounding area can be reduced.
[0025]
Further, the length of the upper structure 1 can be varied by dividing the newly formed upper structure 1 into a plurality of pieces in the bridge axis direction and hinge-connecting the adjacent divided bodies (intermediate bodies 4, ends 5, 6). Since a simple structure can be realized very simply and inexpensively, it is possible to improve the efficiency of construction work and reduce the construction cost.
[0026]
In the present embodiment, the new upper structure 1 is deployed after the existing upper structure 14 is removed, but the new upper structure 1 is deployed before the existing upper structure 14 is removed. You may do it.
[0027]
Next, a second embodiment according to the present invention will be described with reference to FIGS. In addition, the same code | symbol is attached | subjected to the component already demonstrated in the said embodiment, and description is abbreviate | omitted.
In the present embodiment, the newly constructed upper structure 1 is not hinged, but is simply divided into a plurality of pieces in the bridge axis direction. A bridge replacement method performed using such an upper structure will be described with reference to FIGS.
First, as shown in FIG. 4A, a plurality of large jacks 11 are arranged between two adjacent piers 10 and 10 so as to be separated in the bridge axis direction. Both large jacks 11 are shortened. On the shortened large jack 11, the new upper structure 1 is arranged in a state where both end portions 5 and 6 are stacked on the intermediate portion 4. A sync jack 12, a roller mount 13, and a small jack 19 are arranged on the newly constructed upper structure 1, and a plurality of guide rails (tracks) 20 are arranged on the sync jack 12 and the roller mount 13 in the direction of the bridge axis. Place them side by side temporarily.
[0028]
Next, as shown in FIG. 4B, the large jack 11 is extended, and the guide rail 20 is placed along the lower surface of the existing upper structure 14 installed between the piers 10 and 10. When the guide rail 20 is placed along the lower surface of the existing upper structure 14, the sync jack 12 is driven to move the two guide rails 20 in opposite directions in the bridge axis direction. When the sync jack 12 is moved as much as possible on the new upper structure 1 and the ends of the two guide rails 20 are moved to reach both ends of the existing upper structure 14, FIG. As shown, the guide rail 20 is fixed to the lower surface of the existing upper structure 14.
[0029]
When the guide rail 20 is fixed to the lower surface of the existing upper structure 14, the large jack 11 is extended again, and the existing upper structure 14 is pushed up by the new upper structure 1 and separated from the pier 10. Further, the extension of the large jack 11 is continued, and the new upper structure 1 is raised to the same height as the upper structures 14 ′ on both sides as shown in FIG. It should be noted that fastening means (not shown) such as connecting bolts that have fixed the existing upper structure 14 to the pier 10 or the upper structure 14 'on both sides are removed in advance.
[0030]
When the new upper structure 1 is raised to the same height as the upper structures 14 'on both sides, as shown in FIG. 5 (b), both ends 5 and 6 of the new upper structure 1 are connected to the guide rails. It is suspended at 20 and moved to the pier 10 side. In addition, it is desirable that the movements of both end portions 5 and 6 proceed simultaneously in both directions so as not to break the balance of the existing upper structure 14 supported by the sync jack 12.
[0031]
When the both end portions 5 and 6 of the new upper structure 1 are respectively moved onto the gap between the intermediate portion 4 and the upper structure 14 'on both sides, the both end portions are suspended as shown in FIG. 5 (c). Then, it is inserted into the gap 21 and fastened to the intermediate structure and the upper structure 14 ′ on both sides and further to the pier 10 using fastening means (not shown) such as a connecting bolt.
[0032]
When each part is fastened and sufficient strength is secured, as shown in FIG. 6 (a), trailers 15 are arranged on the new upper structure 1 from the upper structure 14 'on both sides, and each trailer is arranged. 15 is arranged so that the end portion of the existing superstructure 14 is put on it. The sync jack 12 and the small jack 19 are shortened, and the existing upper structure 14 is supported by each trailer 15. A portion of the existing superstructure 14 that has reached the trailer 15 is cut with a cutter and placed on the trailer 15, and the trailer 15 is pulled to be removed from the bridge. As for the remaining portion, as shown in FIG. 6B, the sync jack 12 and the small jack 19 are replaced and supported, and then placed on another trailer 15 and removed.
[0033]
When all the existing upper structures 14 are removed, the large jack 11 is shortened and removed as shown in FIG. 6C to complete the replacement work. Thereby, the newly installed upper structure 1 is installed between the piers 10 and 10. Thereafter, the same replacement work is continuously performed on the adjacent existing upper structure 14 '.
[0034]
According to the replacement method of the present embodiment, the newly constructed upper structure 1 is divided into a plurality of parts, and both end portions 5 and 6 are arranged in the bridge axis direction using the existing upper structure 14, thereby Since the construction work of the superstructure 1 can be performed in a short period of time, the period during which the bridge cannot be used can be shortened, and the social and economic losses incurred by the surrounding area can be reduced.
[0035]
Further, by moving the both end portions 5 and 6 along the guide rail 20 attached to the existing upper structure 14, the arrangement work of the both end portions 5 and 6 is facilitated. Can be reduced.
[0036]
Next, a third embodiment according to the present invention will be described with reference to FIGS. In addition, the same code | symbol is attached | subjected to the component already demonstrated in the said embodiment, and description is abbreviate | omitted.
In the present embodiment, two structures are used: an upper structure 1A that can fold both end portions 5 and 6, and an upper structure 1B that can fold only one end portion 6. A jack-up pier 30 is used. As shown in FIG. 7, the jack-up pier 30 is divided into a plurality of pieces having substantially the same length in the height direction. It is built by stacking from the lower end side so as to move. On the foundation 32 that supports the pier 30 is installed a support 33 for lifting the stacked divided bodies 31 by one divided body 31, and each divided body 31 is moved upward along the support 33. A slide jack 34 to be pushed up is provided.
A bridge replacement method performed using such superstructures 1A and 1B and the jack-up pier 30 will be described with reference to FIGS.
[0037]
First, as shown in FIG. 8A, a foundation 32 is constructed adjacent to each of the adjacent piers 10A, 10B among the three piers 10A, 10B, 10C arranged in the bridge axis direction. The jack-up pier 30 is constructed, and the large jack 11 is disposed adjacent to each of the adjacent piers 10B and 10C. The jack-up pier 30 is as high as one shortest divided body 31, and the large jacks 11 are all shortened. On the jack-up pier 30 and the large jack 11, the newly installed upper structures 1A and 1B are arranged in a state where the end portions 5 and 6 are folded and the length in the bridge axis direction is shortened. A sync jack 12 and a roller mount 13 are arranged on the newly folded upper structures 1A and 1B.
[0038]
Next, as shown in FIG. 8 (b), the jackup-type pier 30 and the large jack 11 are extended, and the existing upper structure 14 installed between the piers 10A to 10C is replaced with the sync jack 12 and the roller mount. 13 is supported on the newly installed superstructures 1A and 1B. Subsequently, the jack-up pier 30 and the large jack 11 are extended, and the existing upper structure 14 is pushed up by the new upper structures 1A and 1B to be separated from the pier 10. Further, the jack-up pier 30 and the large jack 11 are continuously extended, and the newly installed upper structures 1A and 1B are raised to the same height as the upper structures 14 'on both sides. It should be noted that fastening means (not shown) such as connecting bolts that fix the existing upper structure 14 to the piers 10A, 10B, 10C and the upper structures 14 'on both sides are removed in advance.
[0039]
When the new upper structure 1 is raised to the same height as the upper structures 14 'on both sides, the sync jack 12 is driven on the new upper structures 1A and 1B as shown in FIG. 8 (c). Then, the existing upper structure 14 is moved to one side in the bridge axis direction. When the sync jack 12 is moved as much as possible on the newly installed upper structures 1A and 1B, the sync jack 12 is shortened and the existing upper structure 14 is supported only by the roller mount 13, and then the sync jack 12 is moved to the other side of the bridge axis direction. The sync jack 12 is extended to support the existing upper structure 14, the sync jack 12 is driven again, and the existing upper structure 14 is moved to one side in the bridge axis direction.
[0040]
Next, as shown in FIG. 9A, the trailer 15 is disposed on the upper structure 14 ′, and one end of the existing upper structure 14 is sequentially sent onto the trailer 15. When the existing superstructure 14 hung on the trailer 15 has an appropriate length, this portion is cut with a cutter, placed on the trailer 15, and removed from the bridge. The remaining part is cut and removed by repeating the same operation as above.
[0041]
After all the existing upper structure 14 is removed, as shown in FIG. 9B, the jackup-type bridge pier 30 and the large jack 11 are extended to raise the new upper structure 1 one step further. The truck crane 16 is arranged on the upper structures 14 ′ on both sides, and the folded end portions 5 and 6 of the newly installed upper structures 1 A and 1 B are lifted by the truck crane 16 and deployed. When the end portions 5 and 6 are deployed, the jack-up pier 30 and the large jack 11 are shortened to lower the newly installed upper structures 1A and 1B by one step.
[0042]
When each part of the newly installed upper structure 1A, 1B is fastened with a connecting bolt and sufficient strength is secured, the hinge portion (not shown) is removed from the newly installed upper structure 1A, 1B, and FIG. ), The large jack 11 and the existing piers 10A and 10B are removed to complete the replacement work. Thereby, the newly installed upper structures 1A and 1B are installed between the three piers 30, 30, and 10C arranged in the bridge axis direction. Thereafter, the same replacement work is performed on the adjacent existing upper structure 14 '.
[0043]
According to the replacement method of the present embodiment, it is possible to rebuild the bridge pier at the same time as the replacement of the superstructure using the pier as a jack. Construction costs can be reduced.
[0044]
In this embodiment, the upper structure is provided with a variable length structure by hinge connection as in the first embodiment. Instead, the upper structure is provided in the upper structure as in the second embodiment. A variable length structure may be provided by a simple guide rail.
In the present embodiment, the pier is reconstructed in conjunction with the replacement of the upper structure. However, the upper structure may be used as it is and only the pier is reconstructed.
[0045]
【The invention's effect】
As described above, according to the present invention, the construction of the new upper structure can be performed in a short period of time by adopting a structure in which the length of the new upper structure is variable in the bridge axis direction. Therefore, the period during which the bridge cannot be used can be shortened, and the social and economic losses incurred by the surrounding area can be reduced.
[0046]
According to the present invention, the new upper structure is divided into a plurality of parts in the bridge axis direction, and adjacent divided bodies are hinged to each other, so that the new upper structure has a variable length structure. Therefore, the construction work can be made more efficient and the construction cost can be reduced.
[0047]
According to the present invention, the newly constructed upper structure is divided into individual divided bodies, and the individual divided bodies are arranged in the direction of the bridge axis using the existing upper structures. Can be done in a short period of time, the period during which the bridge cannot be used can be shortened, and the social and economic losses incurred by the surrounding area can be reduced.
[0048]
According to the present invention, by moving the individual divided bodies along the track attached to the existing superstructure, it becomes easier to arrange the divided bodies, so that the construction work can be made more efficient and the construction cost can be reduced. Is possible.
[0049]
According to the present invention, the bridge pier can be used as a jack, and the pier can be reconstructed at the same time as the replacement of the superstructure. Is possible.
[Brief description of the drawings]
FIG. 1 is a diagram showing a first embodiment according to the present invention, and is a side view showing an upper structure provided with a structure having a variable length in a bridge axis direction.
FIG. 2 is a stepwise state diagram for explaining a bridge replacement method in the first embodiment.
FIG. 3 is a stepwise state diagram for explaining the bridge replacement method according to the first embodiment.
FIG. 4 is a diagram showing a second embodiment according to the present invention, and is a stepwise state diagram for explaining a bridge replacement method.
FIG. 5 is also a stepwise state diagram for explaining a bridge replacement method in the second embodiment.
FIG. 6 is also a stepwise state diagram for explaining the bridge replacement method in the second embodiment.
FIG. 7 is a side view showing a structure of a jack-up type pier according to a third embodiment of the present invention.
FIG. 8 is a staged state diagram for explaining a bridge replacement method in the third embodiment.
FIG. 9 is a stepwise state diagram for explaining a bridge replacement method according to the third embodiment.
[Explanation of symbols]
1 New superstructure
2 Bridge girder
3 Floor slab
4 middle part
5,6 end
7 Hinge part
10 Pier
11 Large jack
12 Sync jack
13 Roller mount
14 Existing superstructure
15 trailer
19 Small jack
20 Guide rail (track)
21 gap
30 Jack-up pier
31 Individual divisions
32 Basics
33 Supporting work
34 Slide jack

Claims (8)

隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向の長さが可変な構造を有する新設の分割された上部構造物を、前記橋軸方向に短縮した状態で配置し、
前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の分割された上部構造物で押し上げて前記2つの橋脚から分離し、
前記既存の上部構造物を撤去する前、または撤去した後に、前記新設の分割された上部構造物を前記橋軸方向に伸長し一体化して前記2つの橋脚間に架設する
ことを特徴とする橋梁の架替工法。
A new divided upper structure with a variable length in the bridge axis direction is shortened in the bridge axis direction on a jack located between two adjacent piers and below the existing upper structure. Placed in the
By extending the jack upward, the existing upper structure constructed between the two piers is pushed up by the newly divided upper structure and separated from the two piers,
Before or after removing the existing superstructure, the newly divided superstructure is extended in the direction of the bridge axis and integrated between the two bridge piers. Replacement method.
前記新設の上部構造物を、前記橋軸方向に複数に分割するとともに隣り合う分割体どうしをヒンジ連結することで長さが可変な構造とし、
前記既存の上部構造物を撤去した後に、前記新設の上部構造物を前記橋軸方向に伸長して前記2つの橋脚間に架設する
ことを特徴とする請求項1記載の橋梁の架替工法。
The newly constructed upper structure is divided into a plurality of pieces in the direction of the bridge axis and the adjacent divided bodies are hinge-connected to form a variable length structure.
2. The method of replacing a bridge according to claim 1, wherein after the existing upper structure is removed, the newly installed upper structure is extended in the direction of the bridge axis and installed between the two piers.
隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向に複数に分割された新設の上部構造物を、個々の分割体を積み重ねた状態で配置し、
前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の上部構造物で押し上げて前記2つの橋脚から分離し、
前記既存の上部構造物を利用して前記個々の分割体を前記橋軸方向に配列し、
配列された前記個々の分割体を結合し前記新設の上部構造物として一体化して前記2つの橋脚間に架設する
ことを特徴とする橋梁の架替工法。
On the jack placed between two adjacent piers and below the existing superstructure, the new superstructure divided into multiple pieces in the direction of the bridge axis is arranged in a state in which individual divisions are stacked,
By extending the jack upward, the existing superstructure constructed between the two piers is pushed up by the new superstructure and separated from the two piers,
Using the existing superstructure, the individual divided bodies are arranged in the bridge axis direction,
A bridge replacement method characterized in that the individual divided bodies arranged are combined and integrated as the new superstructure and installed between the two bridge piers.
前記既存の上部構造物に軌道を取り付け、前記軌道に沿って前記個々の分割体を前記橋軸方向に移動させる
ことを特徴とする請求項3記載の橋梁の架替工法。
The bridge replacement method according to claim 3, wherein a track is attached to the existing superstructure, and the individual divided bodies are moved along the track in the bridge axis direction.
前記橋脚を当初は高さ方向に複数に分割しておき、個々の分割体を、より上端近くに設置すべきものがひとつずつ上方に移動するように積み重ねて構築する
ことを特徴とする請求項3または4記載の橋梁の架替工法。
The pier is divided into a plurality of parts in the height direction at the beginning, and each divided body is constructed by stacking so that ones to be installed near the upper end move upward one by one. Or the bridge replacement method described in 4.
隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向の長さが可変な構造を有する新設の分割された上部構造物を、前記橋軸方向に短縮した状態で配置し、
前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の分割された上部構造物で押し上げて前記2つの橋脚から分離し、
前記既存の上部構造物を撤去する前、または撤去した後に、前記新設の分割された上部構造物を前記橋軸方向に伸長し一体化して前記2つの橋脚間に架設した
ことを特徴とする橋梁。
A new divided upper structure with a variable length in the bridge axis direction is shortened in the bridge axis direction on a jack located between two adjacent piers and below the existing upper structure. Placed in the
By extending the jack upward, the existing upper structure constructed between the two piers is pushed up by the newly divided upper structure and separated from the two piers,
Before or after removing the existing superstructure, the newly divided superstructure is extended and integrated in the direction of the bridge axis, and bridged between the two piers. .
隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、橋軸方向に複数に分割された新設の上部構造物を、個々の分割体を積み重ねた状態で配置し、
前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された既存の上部構造物を前記新設の上部構造物で押し上げて前記2つの橋脚から分離し、
前記既存の上部構造物を利用して前記個々の分割体を前記橋軸方向に配列し、
配列された前記個々の分割体を結合し前記新設の上部構造物として一体化して前記2つの橋脚間に架設した
ことを特徴とする橋梁。
On the jack placed between two adjacent piers and below the existing superstructure, the new superstructure divided into multiple pieces in the direction of the bridge axis is arranged in a state in which individual divisions are stacked,
By extending the jack upward, the existing superstructure constructed between the two piers is pushed up by the new superstructure and separated from the two piers,
Using the existing superstructure, the individual divided bodies are arranged in the bridge axis direction,
A bridge characterized in that the individual divided bodies arranged are combined and integrated as the newly installed superstructure and installed between the two piers.
隣り合う2つの橋脚間にあってかつ既存の上部構造物の下方に配置したジャッキ上に、隣り合う前記2つの橋脚間に架設される橋梁の上部構造物であって、橋軸方向に複数に分割され、隣り合う分割体どうしが上面でヒンジ連結されて前記橋軸方向の長さが可変な構造を有する新設の分割された上部構造物を、前記橋軸方向に短縮した状態で配置し、
前記ジャッキを上方に伸長することで、前記2つの橋脚間に架設された前記既存の上部構造物を前記新設の分割された上部構造物で押し上げて前記2つの橋脚から分離し、
前記既存の上部構造物を撤去する前、または撤去した後に、前記新設の分割された上部構造物を前記橋軸方向に伸長し一体化して前記2つの橋脚間に架設したことを特徴とする橋梁の上部構造物。
An upper structure of a bridge constructed between two adjacent piers on a jack disposed between two adjacent piers and below the existing upper structure, and is divided into a plurality of parts in the direction of the bridge axis. The newly divided upper structure having a structure in which adjacent divided bodies are hinged on the upper surface and the length in the bridge axis direction is variable is arranged in a state shortened in the bridge axis direction,
By extending the jack upward, the existing upper structure constructed between the two piers is pushed up by the newly divided upper structure and separated from the two piers,
Before or after removing the existing superstructure, the newly divided superstructure is extended and integrated in the direction of the bridge axis, and bridged between the two piers. Superstructure.
JP2003125177A 2003-04-30 2003-04-30 Bridge replacement method and bridge Expired - Fee Related JP4348108B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003125177A JP4348108B2 (en) 2003-04-30 2003-04-30 Bridge replacement method and bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003125177A JP4348108B2 (en) 2003-04-30 2003-04-30 Bridge replacement method and bridge

Publications (2)

Publication Number Publication Date
JP2004332222A JP2004332222A (en) 2004-11-25
JP4348108B2 true JP4348108B2 (en) 2009-10-21

Family

ID=33502521

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003125177A Expired - Fee Related JP4348108B2 (en) 2003-04-30 2003-04-30 Bridge replacement method and bridge

Country Status (1)

Country Link
JP (1) JP4348108B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101149972B1 (en) 2010-04-07 2012-06-01 조희진 construction a method
CN105350462A (en) * 2015-11-25 2016-02-24 中铁第五勘察设计院集团有限公司 Bridge overall transversely-moving beam replacing system and method

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007077656A (en) * 2005-09-14 2007-03-29 Yokogawa Bridge Corp Construction method of bridge girder, and bridge girder
JP4727504B2 (en) * 2006-06-01 2011-07-20 三菱重工鉄構エンジニアリング株式会社 Bridge removal method
JP4755998B2 (en) * 2007-01-09 2011-08-24 株式会社竹中工務店 Cutting and rehabilitating connecting bridges with different distances between buildings
KR101572563B1 (en) * 2014-10-20 2015-11-27 코벡(주) Method for carrying out replacement of an upperstructure of a bridge
JP6551467B2 (en) * 2017-07-13 2019-07-31 Jfeエンジニアリング株式会社 Bridge replacement method
JP6950549B2 (en) * 2018-01-30 2021-10-13 Jfeエンジニアリング株式会社 Carry-in / out method and carry-in / out equipment
JP7124794B2 (en) * 2019-06-18 2022-08-24 Jfeエンジニアリング株式会社 Bridge replacement method
JP2021070916A (en) * 2019-10-29 2021-05-06 株式会社Ihiインフラシステム Carrying-in method of bridge article, carrying-out method of bridge article, removing method of bridge article, installation method thereof and lifting device for bridge article
CN112900290A (en) * 2021-01-20 2021-06-04 中铁大桥局武汉桥梁特种技术有限公司 Bridge beam replacing method and system
CN112921718B (en) * 2021-01-28 2022-11-01 柳州煜乾机械装备股份公司 Continuous jacking and mounting device for light rail track beam and using method thereof
CN113818365A (en) * 2021-10-14 2021-12-21 上海公路桥梁(集团)有限公司 Method for replacing viaduct body
CN114263125B (en) * 2021-12-23 2023-08-08 中铁第五勘察设计院集团有限公司 Bridge deck supporting system of beam changing machine and beam changing machine
CN114575270B (en) * 2022-02-25 2024-03-22 济南城建集团有限公司 Bridge jacking and reinforcing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101149972B1 (en) 2010-04-07 2012-06-01 조희진 construction a method
CN105350462A (en) * 2015-11-25 2016-02-24 中铁第五勘察设计院集团有限公司 Bridge overall transversely-moving beam replacing system and method

Also Published As

Publication number Publication date
JP2004332222A (en) 2004-11-25

Similar Documents

Publication Publication Date Title
JP4348108B2 (en) Bridge replacement method and bridge
US5511268A (en) Construction of large structures by robotic crane placement of modular bridge sections
JP4563413B2 (en) Bridge girder construction method
JP7346246B2 (en) Heavy object moving method using heavy object moving device and heavy object moving device
JP6702835B2 (en) Bridge girder erection method for multi span span bridge
JP2007321389A (en) Bridge construction method
WO1996005375A9 (en) Construction of large structures by robotic crane placement of modular bridge sections
KR101632922B1 (en) Bridge construction method using non-self launching beam launcher
WO2023168902A1 (en) Dual-mode bridge girder erection machine and variable-span girder erection method
KR20130040409A (en) System and method for launching upper structure of bridege
JP5032787B2 (en) Heavy equipment installation equipment
RU2304656C1 (en) Method for lattice span structure disassembling by span structure division into three-dimensional blocks
CN114657884A (en) Descending type movable formwork construction method for abutment assembling and segmented propelling
JP5653835B2 (en) Bridge pier reconstruction method and rebuild pier structure
JP4704279B2 (en) Bridge construction method
EP0165712B1 (en) Bridge construction
CN215925692U (en) Overlength multispan assembly type integrated multifunctional bridge girder erection machine
JPH10237823A (en) Method for replacing overhead bridge
JPH04353105A (en) Erecting method for bridge girder
KR200363059Y1 (en) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
KR100907141B1 (en) Mobile crane installation structure and method for replacing an upper structure of a railway bridge using the same
CN210395113U (en) Bridge erecting machine
CN113882286A (en) Bridge dismantling and building all-in-one machine and spanning method thereof, bridge dismantling method and new building method
KR20100078371A (en) Rapid replacement method and apparatus using pulling-up facility and scaffold truss with wheels under the bottom of existing and replacing bridges
CN113957812B (en) Expandable railway emergency repair beam and erection method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060202

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20060809

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20060829

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080828

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080902

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081104

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090519

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090616

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090714

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090717

R150 Certificate of patent or registration of utility model

Ref document number: 4348108

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120724

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130724

Year of fee payment: 4

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees