JP2017190607A - Erection method of simple temporary bridge - Google Patents

Erection method of simple temporary bridge Download PDF

Info

Publication number
JP2017190607A
JP2017190607A JP2016080277A JP2016080277A JP2017190607A JP 2017190607 A JP2017190607 A JP 2017190607A JP 2016080277 A JP2016080277 A JP 2016080277A JP 2016080277 A JP2016080277 A JP 2016080277A JP 2017190607 A JP2017190607 A JP 2017190607A
Authority
JP
Japan
Prior art keywords
girder
temporary
hand
support
superstructure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016080277A
Other languages
Japanese (ja)
Other versions
JP5977904B1 (en
Inventor
田中 雅人
Masahito Tanaka
雅人 田中
誠 石黒
Makoto Ishiguro
誠 石黒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hirose and Co Ltd
Original Assignee
Hirose and Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hirose and Co Ltd filed Critical Hirose and Co Ltd
Priority to JP2016080277A priority Critical patent/JP5977904B1/en
Application granted granted Critical
Publication of JP5977904B1 publication Critical patent/JP5977904B1/en
Publication of JP2017190607A publication Critical patent/JP2017190607A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide an erection method of a simple temporary bridge capable of largely reducing construction cost by using general-purpose materials, and capable of simplifying the materials for constituting a superstructure of the simple temporary bridge.SOLUTION: A process of extending a manual-extending temporary girder 30 toward the bridge axial direction by connecting to an existing superstructure, a process of removing a side girth 32 while leaving a girder bearer 31 erected between head parts of a plurality of erected support piles 20 as it is and a process of assembling the superstructure by mounting a plurality of main girders 40 between the girder bearers 31 separated at an interval, are repeatedly executed by a span unit by using the manual-extending temporary girder 30 presenting a plane U shape having the girder bearer 31 with a pile guide cylinder 33 and a pair of detachably connected side girths 32.SELECTED DRAWING: Figure 1

Description

本発明は簡易仮橋の架設方法に関するものである。   The present invention relates to a method for constructing a simple temporary bridge.

特許文献1には、ユニット化した桟橋パネルを用い、仮橋、仮桟橋工を斜張設備により上部工架設を先行して施工する簡易仮橋の架設方法が開示されている。
図8,9を参照して説明すると、従来はつぎの工程1〜工程4を1スパン単位で反復して施工している。
(1)桟橋パネルの平場地組工程
図8に示すように、縦横方向に配置した複数の主桁81と受桁82等を連結して格子状に組み立てると共に、受桁82の一部に複数の杭ガイド筒83を付設した剛性構造の桟橋パネル80を平場で地組みする。
(2)桟橋パネルの架設工程
図9に示すように、クレーンで懸吊した桟橋パネル80の一端を、既設の桟橋パネル80aの前部に連結して延設する。
この際、既設の上部工に反力支柱85を立設し、反力支柱85の頂部と延設した桟橋パネル80の間、及びに反力支柱85の頂部と既設の桟橋パネル80aの間に夫々斜張材84,86を接続して桟橋パネル80を水平に支持する。
(3)支持杭の打込み工程
手延べした桟橋パネル80の前端の各杭ガイド筒83に内挿して支持杭87を打ち込み、支持杭87の頭部と杭ガイド筒83を連結する。桟橋パネル80の上面に床板89を敷設する。
(4)補強材の取り付け工程
横繋ぎ材や垂直ブレス材等の補強材88をクレーンで懸吊し、隣り合う支持杭87間に補強材88を架け渡し、補強材88の側端部を溶接して支持杭87に固定する。
Patent Document 1 discloses a simple temporary bridge erection method in which a unitary pier panel is used and a temporary bridge and a temporary pier are preliminarily constructed by a cable-stretching facility before an upper work is erected.
Referring to FIGS. 8 and 9, conventionally, the following steps 1 to 4 are repeated for each span.
(1) Jetty panel flat ground laying process As shown in FIG. 8, a plurality of main girders 81 and receiving girders 82, etc. arranged in the vertical and horizontal directions are connected and assembled into a lattice shape, and a plurality of girder 82 are arranged in part A pier panel 80 having a rigid structure provided with a pile guide tube 83 is grounded on a flat surface.
(2) Pier Panel Installation Step As shown in FIG. 9, one end of a pier panel 80 suspended by a crane is connected to the front part of an existing pier panel 80a and extended.
At this time, the reaction strut 85 is erected on the existing superstructure, between the top of the reaction strut 85 and the extended pier panel 80, and between the top of the reaction strut 85 and the existing pier panel 80a. The cable stays 84 and 86 are connected to support the pier panel 80 horizontally.
(3) Support pile driving process The support pile 87 is driven by being inserted into each pile guide tube 83 at the front end of the pier panel 80 that has been handed over, and the head of the support pile 87 and the pile guide tube 83 are connected. A floor board 89 is laid on the upper surface of the jetty panel 80.
(4) Reinforcing material attachment process Reinforcing material 88 such as a horizontal connecting material or vertical brace material is suspended by a crane, the reinforcing material 88 is bridged between adjacent support piles 87, and the side ends of the reinforcing material 88 are welded. And fixed to the support pile 87.

特開平10−46523号公報Japanese Patent Laid-Open No. 10-46523

既述した従来の簡易仮橋の架設技術はつぎのような問題点を有する。
<1>ユニット化された桟橋パネル80には、上部工だけでなくクレーン等の重機類の重量も直接負荷することから、桟橋パネル80は載荷重に耐え得る強度に製作した専用品となる。
そのために一枚当たりの桟橋パネル80のコストが非常に高いものとなる。
<2>上記したように桟橋パネル80の主桁81には大きな上載荷重が負荷することから、主桁81の基端の端面と既設の受桁82の前面との間を強固に連結する必要があり、主桁81と既設の受桁82の連結部の増強コストが高くなる。
<3>上部工を構成する桟橋パネル80は、簡易仮橋の全長に亘って連設しなければならず、大量の桟橋パネル80を使用することが工費高騰の一因となっている。
<4>桟橋パネル80が標準化されていることに伴い、橋軸方向の長さを現場で変更することができない。
橋軸方向の長さを標準化されていない寸法に変更する場合は、桟橋パネル80を別途に製作すればよいが、桟橋パネル80の製作コストが更に増すために、橋軸方向の長さ変更に伴うコストが非常に高くつく。
The conventional simple temporary bridge construction technique described above has the following problems.
<1> Since the unitized jetty panel 80 is directly loaded with the weight of heavy machinery such as a crane as well as the superstructure, the jetty panel 80 is a dedicated product manufactured with a strength that can withstand the load.
Therefore, the cost of the pier panel 80 per sheet becomes very high.
<2> As described above, the main girder 81 of the pier panel 80 is subjected to a large overload, and therefore it is necessary to firmly connect the end face of the base end of the main girder 81 and the front surface of the existing receiving girder 82. Therefore, the reinforcement cost of the connecting portion between the main beam 81 and the existing receiving beam 82 is increased.
<3> The pier panel 80 constituting the superstructure has to be continuously provided over the entire length of the simple temporary bridge, and the use of a large amount of the pier panel 80 is a cause of the increase in the construction cost.
<4> With the pier panel 80 being standardized, the length in the bridge axis direction cannot be changed on site.
When the length in the bridge axis direction is changed to a non-standard dimension, the pier panel 80 may be manufactured separately. However, since the manufacturing cost of the pier panel 80 is further increased, the length in the bridge axis direction is changed. The costs involved are very high.

本発明は以上の点に鑑みて成されたもので、その目的とするところはつぎの簡易仮橋の架設方法を提供することにある。
<1>汎用資材を使用できて工費の大幅削減が可能であること。
<2>簡易仮橋の上部工を構成する資材を簡略化できること。
<3>橋軸方向の長さ変更の経済性と対応性に優れていること。
The present invention has been made in view of the above points, and an object thereof is to provide the following method for constructing a simple temporary bridge.
<1> General-purpose materials can be used, and construction costs can be significantly reduced.
<2> Materials that make up the superstructure of a simple temporary bridge can be simplified.
<3> Excellent economy and responsiveness in changing the length in the bridge axis direction.

本発明は、複数の支持杭で支持する既設の上部工の前方に上部工を延設し、延設した上部工を水平支持手段により支持しつつ該上部工に付設した杭ガイド筒に支持杭を内挿して立設して行う簡易仮橋の架設方法であって、
複数の杭ガイド筒を具備した桁受材と、該桁受材の直交方向に配置され、杭ガイド筒を介して桁受材の両端部に着脱可能に連結した一対の側方つなぎ材とを具備した平面コ字形を呈する複数組の手延仮桁を使用し、
橋軸方向に向けて配置した前記一対の側方つなぎ材の基端を既設の上部工に連結して手延仮桁を橋軸方向へ向けて延設する工程と、
前記杭ガイド筒に内挿して支持杭を立設した後に複数の支持杭の頭部間に橋軸横断方向に向けて架設した桁受材を残置しつつ前記一対の側方つなぎ材を撤去する工程と、
既設の手延仮桁と前記延設した手延仮桁の桁受材の間に複数の主桁を搭載して上部工を組み立てる工程とを含み、
前記した複数の工程をスパン単位で繰り返して行うことを特徴とする。
さらに本発明は、複数の支持杭で支持する既設の上部工の前方に上部工を延設し、延設した上部工を水平支持手段により支持しつつ該上部工に付設した杭ガイド筒に支持杭を内挿して立設して行う簡易仮橋の架設方法であって、
複数の杭ガイド筒を具備した桁受材と、該桁受材の直交方向に配置され、杭ガイド筒を介して桁受材の両端部に着脱可能に連結した一対の側方つなぎ材とを具備した平面コ字形を呈する手延仮桁を組み立てる工程と、
既設上部工の前方に前記手延仮桁を連結して延設した後に、水平支持手段を介して延設した手延仮桁を支持する工程と、
前記手延仮桁の杭ガイド筒に内挿して支持杭を立設する工程と、
前記杭ガイド筒を介して延設した手延仮桁の桁受材を橋軸横断方向に向けて支持杭の頭部間に架設する工程と、
既設の手延仮桁と前記延設した手延仮桁の桁受材間に主桁を搭載して上部工を組み立てる工程と、
前記延設した手延仮桁の桁受材から分離した一対の側方つなぎ材を撤去する工程とを含み、
前記した複数の工程をスパン単位で繰り返して行うことを特徴とする。
本発明の他の形態において、撤去した前記一対の側方つなぎ材を転用して次スパンの手延仮桁を組み立てる。
本発明の他の形態において、前記杭ガイド筒が支持杭を挿通可能な筒部と、筒部の外周面に橋軸方向に沿って突設した複数の連結リブとを有していて、前記連結リブを介して一対の側方つなぎ材が着脱可能である。
本発明の他の形態において、前記手延仮桁の水平支持手段が、既設上部工に立設した反力支柱と、反力支柱の頂部を中心に既設上部工と延設した手延仮桁との間に張設した複数の斜張材との組み合わせからなり、前記水平支持手段をスパン単位で移設して使用する。
The present invention extends a superstructure ahead of an existing superstructure that is supported by a plurality of support piles, and supports piles on a pile guide tube attached to the superstructure while supporting the superstructure that has been extended by horizontal support means. Is a simple temporary bridge construction method,
A girder support member having a plurality of pile guide tubes, and a pair of side connecting members that are arranged in the orthogonal direction of the girder support members and are detachably connected to both ends of the girder support members via the pile guide tubes. Using multiple sets of hand-drawn temporary girders with a flat U-shape,
Connecting the base ends of the pair of side connecting members arranged in the direction of the bridge axis to the existing superstructure, and extending the hand-drawn temporary girder in the direction of the bridge axis;
After the support pile is erected by interpolating in the pile guide tube, the pair of side connecting materials are removed while leaving the girder support material erected in the crossing direction of the bridge axis between the heads of the plurality of support piles. Process,
A step of assembling an upper work by mounting a plurality of main girders between an existing hand-drawn temporary girder and a girder receiving material of the extended hand-drawn temporary girder,
The above-described plurality of steps are repeated for each span.
Further, according to the present invention, an upper work is extended in front of an existing super work supported by a plurality of support piles, and the extended super work is supported by a pile guide tube attached to the super work while being supported by a horizontal support means. It is a method of erection of a simple temporary bridge that is done by inserting a pile and standing up,
A girder support member having a plurality of pile guide tubes, and a pair of side connecting members that are arranged in the orthogonal direction of the girder support members and are detachably connected to both ends of the girder support members via the pile guide tubes. Assembling a hand-drawn temporary girder having a flat U-shaped shape,
After connecting and extending the hand-drawn temporary girder in front of the existing superstructure, supporting the hand-drawn temporary girder extended through the horizontal support means; and
Inserting the support pile by interpolating the pile guide cylinder of the hand-drawn temporary girder; and
A step of laying the girder support material of the hand-drawn temporary girder extended through the pile guide tube between the heads of the support piles in the bridge axis crossing direction;
A step of assembling an upper work by mounting a main girder between the existing hand-drawn temporary girder and the girder receiving material of the extended hand-drawn temporary girder;
Removing a pair of side tie members separated from the girder support material of the extended manual temporary girder,
The above-described plurality of steps are repeated for each span.
In another embodiment of the present invention, the pair of lateral connecting members removed are used to assemble a hand span temporary girder for the next span.
In another aspect of the present invention, the pile guide tube has a tube portion through which the support pile can be inserted, and a plurality of connecting ribs projecting along the bridge axis direction on the outer peripheral surface of the tube portion, A pair of side ties can be attached and detached via the connecting ribs.
In another aspect of the present invention, the horizontal support means of the hand-drawn temporary girder includes a reaction force column that is erected on the existing upper work, and a hand-drawn temporary beam that is extended with the existing upper work around the top of the reaction force support. The horizontal support means is used by being transferred in units of spans.

本発明は少なくともつぎのひとつの効果を奏する。
<1>複数組(少数組)の手延仮桁を使用することで簡易仮橋を施工できるので、従来工法で使用していた大量の専用の桟橋パネルの使用を省略することができる。
<2>手延仮桁を使用することで、主桁に汎用の鋼材を使用できるので、手延仮桁を低廉に組み立てることができる。
<3>手延仮桁が桁受材の両端に一対の側方つなぎ材を連結しただけの簡単な構造であることと、着脱可能な側方つなぎ材を手延仮桁の構成材として繰り返し使用できることに伴い、ユニット化した大量の専用の桟橋パネルを使用する従来工法と比べて工費を大幅に削減できる。
<4>桁受材に対して長さの異なる側方つなぎ材を簡単に付け替えできるので、従来工法で使用するユニット化した専用品の桟橋パネルと比べて、橋軸方向の長さの変更に対する経済性および対応性が格段によくなる。
<5>主桁は一対の桁受材の上面に載置して掛け渡すことができるので、従来工法のように主桁の側端面に連結リブを突設したり、多数の連結ピンや高強度ボルト等で連結したりして連結部を増強する必要がなくなる。
さらに桁受材は鋼材の端部に杭ガイド筒を付設しただけの簡単な構造である。
したがって、簡易仮橋の上部工を構成する桁受材や主桁の構造を簡略化できる。
The present invention has at least one of the following effects.
<1> Since a simple temporary bridge can be constructed by using a plurality of sets (minor sets) of hand-drawn temporary girders, the use of a large number of dedicated jetty panels used in the conventional construction method can be omitted.
<2> Since a general-purpose steel material can be used for the main girder by using the hand-drawn temporary girder, the hand-drawn temporary girder can be assembled at a low cost.
<3> The hand-drawn temporary girder has a simple structure in which a pair of side connecting materials are connected to both ends of the girder support material, and the detachable side connecting material is repeatedly used as a constituent material of the hand-drawn temporary girder. As it can be used, the construction cost can be greatly reduced compared to the conventional method that uses a large number of unitized jetty panels.
<4> Since the side tie materials with different lengths can be easily replaced with the girder support material, the length of the bridge axis direction can be changed compared to the unitized dedicated pier panel used in the conventional construction method. Economical and responsiveness will be much better.
<5> Since the main girder can be placed and hung on the upper surface of a pair of girder support members, a connecting rib is projected on the side end surface of the main girder as in the conventional construction method, or many connecting pins and There is no need to reinforce the connecting part by connecting with a strength bolt or the like.
Furthermore, the girder is a simple structure with a pile guide tube attached to the end of the steel material.
Therefore, the structure of the girder receiving material and the main girder constituting the superstructure of the simple temporary bridge can be simplified.

本発明に係る簡易仮橋の架設方法の説明図Explanatory drawing of the construction method of the simple temporary bridge concerning the present invention 施工に使用する手延仮桁の斜視図Perspective view of hand-drawn temporary girder used for construction 簡易仮橋の架設方法の説明図で、手延仮桁の水平架設工程を示した簡易仮橋の側面Side view of the simplified temporary bridge showing the horizontal installation process of the hand-drawn temporary girder in the explanatory diagram of the method of installing the simplified temporary bridge 簡易仮橋の架設方法の説明図で、支持杭の立設工程を示した簡易仮橋の側面Side view of the simple temporary bridge, showing the process of erecting the support pile in the explanatory diagram of the method of erection of the simple temporary bridge 簡易仮橋の架設方法の説明図で、主桁と床板の敷設工程を示した簡易仮橋の側面Side view of the simplified temporary bridge, showing the construction process of the main girder and floorboard, with an explanatory diagram of the method for constructing the simplified temporary bridge 一部を省略した図5の平面図Plan view of FIG. 5 with a part omitted 簡易仮橋の架設方法の説明図で、水平支持手段の移設工程と側方つなぎ材の撤去工程を示した簡易仮橋の側面Side view of the simplified temporary bridge showing the process of moving the horizontal support means and the process of removing the side ties in the explanatory diagram of the method of erection of the simplified temporary bridge 桟橋パネルの斜視図Perspective view of pier panel 桟橋パネルを用いた従来の簡易仮橋の架設方法の説明図Explanatory drawing of a conventional simple temporary bridge construction method using pier panels

以下に図面を参照しながら本発明を詳細に説明する。   Hereinafter, the present invention will be described in detail with reference to the drawings.

<1>簡易仮橋の使用資材
図1を参照して簡易仮橋の施工に用いる架設資材について説明する。
簡易仮橋10は下部工を構成する複数の支持杭20と、支持杭20の頭部間に架設した上部工とを具備する。
上部工は複数の支持杭20の頭部間を橋軸横断方向に横架した桁受材31と、桁受材31に支持され、橋軸方向に配置する複数の主桁40と、主桁40の上面に敷設した覆工板等の床板41とを具備する。
本発明では、既設上部工の前端に橋軸方向に張り出した平面形状がコ字形を呈する手延仮桁30と、手延仮桁30を支持する水平支持手段とを使用して上部工を施工する。
<1> Materials Used for Simple Temporary Bridge Construction materials used for the construction of the simple temporary bridge will be described with reference to FIG.
The simple temporary bridge 10 includes a plurality of support piles 20 constituting a substructure and an upper work constructed between the heads of the support piles 20.
The superstructure includes a girder support member 31 that is horizontally mounted between the heads of the plurality of support piles 20, a plurality of main girders 40 that are supported by the girder support member 31 and arranged in the bridge shaft direction, and a main girder. 40 and a floor plate 41 such as a lining plate laid on the upper surface of 40.
In the present invention, the superstructure is constructed using a hand-drawn temporary girder 30 whose planar shape extending in the direction of the bridge axis at the front end of the existing superstructure has a U-shape and horizontal support means for supporting the hand-drawn temporary girder 30. To do.

<2>手延仮桁
図2を参照して説明すると、手延仮桁30は杭ガイド筒33(連結機構)を具備した桁受材31と、杭ガイド筒33を介して桁受材31と着脱可能に設けた左右一対の側方つなぎ材32,32とを有する。
従来工法で使用する桟橋パネルのように、手延仮桁30には主桁が組み込まれておらず、主桁40は手延仮桁30と別部材として使用する。
桁受材31だけでなく側方つなぎ材32についても、安価な汎用鋼材(H型鋼等)を使用して簡単に組み立てたものを使用できるので、手延仮桁30の組み立てコストを低廉に抑えることができる。
公知のリース材を用いて手延仮桁30を組み立てる場合も同様にリース料を大幅に低減できる。
<2> Hand-drawn temporary girder Referring to FIG. 2, the hand-drawn temporary girder 30 includes a girder receiving material 31 having a pile guide tube 33 (connection mechanism) and a girder receiving material 31 via the pile guide tube 33. And a pair of left and right side connecting members 32, 32 detachably provided.
Unlike the jetty panel used in the conventional construction method, the main girder 30 is not incorporated with the main girder 30, and the main girder 40 is used as a separate member from the manual girder 30.
Since not only the girder 31 but also the side tie 32 can be easily assembled using inexpensive general-purpose steel (such as H-shaped steel), the assembly cost of the hand-drawn temporary girder 30 can be kept low. be able to.
Similarly, when assembling the temporary provisional girder 30 using a known leasing material, the lease fee can be greatly reduced.

<2.1>桁受材
桁受材31は上部工の構成材を兼ねていて、支持杭20の頭部間に橋軸横断方向に向けて架設される。
桁受材31は複数の杭ガイド筒33を具備している。
本例では、桁受材31の両端部に2つの杭ガイド筒33を設けた形態を示すが、桁受材31は3つ以上の杭ガイド筒33を具備していてもよい。
桁受材31と杭ガイド筒33の間は、溶接またはボルト止め等により一体構造となっている。
<2.1> Girder receiving material The girder receiving material 31 also serves as a structural material for the upper work, and is laid between the heads of the support piles 20 in the crossing direction of the bridge shaft.
The girder member 31 includes a plurality of pile guide tubes 33.
In this example, a mode in which two pile guide cylinders 33 are provided at both ends of the girder support member 31 is shown, but the girder support member 31 may include three or more pile guide tube 33.
Between the girder receiving member 31 and the pile guide tube 33, an integrated structure is formed by welding or bolting.

<2.2>杭ガイド筒
杭ガイド筒33は、支持杭20の立設ガイド機能と、桁受材31及び側方つなぎ材32の間を連結する機能を併有した縦向きの筒体である。
図2に例示した杭ガイド筒33について説明すると、杭ガイド筒33は支持杭20を挿通可能な筒部33aと、筒部33aの上下に設けた環状のフランジ33b,33cと、筒部33aの外周面に橋軸方向に沿って突設した複数の連結リブ33dとを有している。
上位のフランジ33bに固定蓋33eを取り付けて筒部33aの上口を閉鎖することで、打ち込みを終えた支持杭20の頭部と杭ガイド筒33の間を固定することが可能である。
<2.2> Pile guide tube Pile guide tube 33 is a vertically oriented tube body that has both a standing guide function of support pile 20 and a function of connecting between beam receiving member 31 and side connecting member 32. is there.
The pile guide cylinder 33 illustrated in FIG. 2 will be described. The pile guide cylinder 33 includes a cylindrical portion 33a through which the support pile 20 can be inserted, annular flanges 33b and 33c provided above and below the cylindrical portion 33a, and a cylindrical portion 33a. And a plurality of connecting ribs 33d projecting along the bridge axis direction on the outer peripheral surface.
By attaching the fixing lid 33e to the upper flange 33b and closing the upper opening of the cylinder portion 33a, it is possible to fix the space between the head of the support pile 20 that has been driven and the pile guide cylinder 33.

<2.3>側方つなぎ材
側方つなぎ材32は上部工の構成材ではなく、桁受材31を既設上部工の最前から離隔して位置させるための間隔保持部材であり、支持杭20の頭部間に橋軸方向に向けて架設される。
側方つなぎ材32の両端面には橋軸方向に沿って連結リブ32aが突設してあり、図外の複数の連結用のボルト又はピンを介して杭ガイド筒33の連結リブ33dと連結及び分離可能である。
<2.3> Side tie material The side tie material 32 is not a constituent material of the superstructure, but is a spacing member for positioning the girder 31 away from the forefront of the existing superstructure. It is installed between the heads in the direction of the bridge axis.
Connection ribs 32a project from the both end faces of the side connecting members 32 along the bridge axis direction, and are connected to the connection ribs 33d of the pile guide cylinder 33 via a plurality of connection bolts or pins not shown. And separable.

<2.3.1>側方つなぎ材を着脱式にした理由
側方つなぎ材32を桁受材31に対して着脱可能に構成したのは、同一の側方つなぎ材32を転用して使用するためと、手延仮桁30の水平張出長さを簡単に変更するためである。
<2.3.1> Reason why the side tie material is made detachable The side tie material 32 is configured to be detachable from the girder support material 31 by using the same side tie material 32. This is for the purpose of easily changing the horizontal overhang length of the provisional temporary girder 30.

<2.3.2>側方つなぎ材の資材例
側方つなぎ材32には、低廉な既存の形鋼単体や鈑桁を使用できるだけでなく、複数の鋼材を組み合せたトラス構造体等を使用することもできる。
上部工を構成しない側方つなぎ材32には大きな載荷重が負荷しないので、側方つなぎ材32の強度は桁受材31や主桁40と比較して格段に小さくてよく、自重を支えられるだけの強度で十分である。
<2.3.2> Examples of side tie materials In addition to using low-priced existing structural steel and girder, the side tie material 32 uses a truss structure that combines multiple steel materials. You can also.
Since a large loading load is not applied to the side connecting material 32 that does not constitute the superstructure, the strength of the side connecting material 32 may be much smaller than that of the girder material 31 and the main girder 40 and can support its own weight. Only the strength is sufficient.

<2.4>手延仮桁の使用数
従来工法では簡易架橋の全長に亘って多数の桟橋パネルを連設する必要があった。
これに対し本発明では、手延仮桁30を簡易架橋の全長に亘って連接する必要はなく、最低2組の手延仮桁30を使用するだけで施工が可能である。
<2.4> Number of hand-drawn temporary girders In the conventional method, it was necessary to connect a number of jetty panels over the entire length of the simple bridge.
On the other hand, in the present invention, it is not necessary to connect the hand-drawn temporary girders 30 over the entire length of the simple bridge, and the construction can be performed only by using at least two sets of the hand-drawn temporary girders 30.

<3>水平支持手段
手延仮桁30の水平支持手段は、既設上部工に立設した反力支柱43と、反力支柱43の頂部と既設上部工の間に張設した第1斜張材44と、反力支柱43の頂部と手延べした手延仮桁30の間に張設した第2斜張材45とを具備する。
第1又は第2斜張材44,45には引張耐力に優れた鋼材、鎖、ロープ材の何れか一つ、又はこれらを組み合せて適用可能であり、チェーンブロック等の長さ調整機器を介装する場合もある。
本例では、既設の支持杭20の真上に反力支柱43を立設した形態を示すが、既設の支持杭20の近傍の既設上部工に立設してもよい。
<3> Horizontal Support Means The horizontal support means of the hand-drawn temporary girder 30 includes a reaction force column 43 erected on the existing superstructure, and a first slant stretched between the top of the reaction force column 43 and the existing superstructure. A material 44 and a second cable-stretching material 45 stretched between the top of the reaction force column 43 and the hand-drawn temporary girder 30 are provided.
The first or second cable-stretching member 44, 45 can be applied with any one of steel materials, chains, rope materials excellent in tensile strength, or a combination thereof, via a length adjusting device such as a chain block. There is also a case.
In this example, the reaction force column 43 is erected directly above the existing support pile 20, but it may be erected on an existing superstructure near the existing support pile 20.

尚、水平支持機構は本例に例示した機構に限定されず、既設上部工から反力を得て、既設上部工の前端に張り出した手延仮桁30を水平に支持できる公知の支持機構を適用できる。   The horizontal support mechanism is not limited to the mechanism illustrated in this example, and a known support mechanism that can obtain a reaction force from the existing superstructure and can horizontally support the hand-drawn temporary girder 30 protruding from the front end of the existing superstructure. Applicable.

[簡易仮橋の架設方法]
つぎに簡易仮橋10の架設方法について説明する。
[How to install a simple temporary bridge]
Next, the construction method of the simple temporary bridge 10 will be described.

<1>反力支柱の立設
図3は施工途中の簡易仮橋10を示していて、簡易仮橋10の上部工を構成する複数の主桁40と床板41は、複数の支持杭20a,20bと、これら各支持杭20a,20bの横架した第1手延仮桁30Aによって支持されている。
床板41の上面には移動式クレーン等の重機50が搭載されている。
<1> Standing up of reaction force column FIG. 3 shows a simple temporary bridge 10 in the middle of construction, and a plurality of main girders 40 and a floor plate 41 constituting the superstructure of the simple temporary bridge 10 include a plurality of support piles 20a, It is supported by 20b and the first hand-drawn temporary girder 30A horizontally mounted by these support piles 20a and 20b.
A heavy machine 50 such as a mobile crane is mounted on the upper surface of the floor plate 41.

簡易仮橋10を延長するには、最前の支持杭20bの真上に反力支柱43を立設すると共に、反力支柱43の頂部と既設上部工の間に第1斜張材44を張設する。   In order to extend the simple temporary bridge 10, a reaction strut 43 is erected directly above the foremost support pile 20 b and a first cable-stretching member 44 is stretched between the top of the reaction strut 43 and the existing superstructure. Set up.

<2>手延仮桁の組み立て
地上、又は既設上部工の上面でコ字形の第2手延仮桁30Bを組み立てる。
第1及び第2手延仮桁30A,30Bには、図2に示した同一構造の手延仮桁30を使用する。
<2> Assembling the hand-drawn temporary girder The U-shaped second hand-drawn temporary girder 30B is assembled on the ground or the upper surface of the existing superstructure.
As the first and second hand-drawn temporary girders 30A and 30B, the hand-drawn temporary girders 30 having the same structure shown in FIG. 2 are used.

<3>手延仮桁の水平架設
図3を参照して説明すると、重機50を使用して第2手延仮桁30Bを既設の第1手延仮桁30Aの延長位置に吊り込み、連結機構である杭ガイド筒33を介して連結する。
すなわち、第2手延仮桁30Bを構成する各側方つなぎ材32,32の自由端の連結リブ32aと杭ガイド筒33の連結リブ33dを重合させ、その重合部にボルト又はピンを挿通して連結する。
<3> Horizontal construction of the hand-drawn temporary girder Referring to FIG. 3, the heavy-duty machine 50 is used to suspend the second hand-drawn temporary girder 30B at the extension position of the existing first hand-drawn temporary girder 30A and connect it. It connects via the pile guide cylinder 33 which is a mechanism.
That is, the connecting ribs 32a at the free ends of the side connecting members 32 and 32 constituting the second hand-drawn temporary girder 30B and the connecting ribs 33d of the pile guide tube 33 are overlapped, and a bolt or a pin is inserted into the overlapping portion. Connect.

第2手延仮桁30Bの左端を既設の第1手延仮桁30Aの右端に連結しただけでは、第2手延仮桁30Bの水平性を保持できない。
そこで、図4に示すように、反力支柱43の頂部と第2手延仮桁30Bの間に第2斜張材45を張設し、反力支柱43と第1及び第2斜張材44,45が協働して第2手延仮桁30Bを水平に支持する。
By simply connecting the left end of the second hand-drawn temporary girder 30B to the right end of the existing first hand-drawn temporary girder 30A, the horizontality of the second hand-drawn temporary girder 30B cannot be maintained.
Therefore, as shown in FIG. 4, a second cable-stretching material 45 is stretched between the top of the reaction force strut 43 and the second hand-drawn temporary girder 30 </ b> B so that the reaction force strut 43 and the first and second cable-stretching materials 44 and 45 cooperate to support the second hand-drawn temporary girder 30B horizontally.

<4>支持杭の立設
図4を参照して説明すると、重機50に吊り下げた立設予定の支持杭20cを吊り上げ、第2手延仮桁30Bの最前の杭ガイド筒33に内挿しながら鉛直に建て込む。
地盤が硬質である場合には、支持杭20cに公知の削孔機を内挿して削孔しながら支持杭20cを所定の深さまで打ち込む。
そして、各支持杭20cの頭部を第2手延仮桁30Bの杭ガイド筒33に固定し、第2手延仮桁30Bの自重を複数の支持杭20b,20cに支持させる。
支持杭20cの頭部が杭ガイド筒33の上方へ突出している場合は、支持杭20cの突出部をガス切断した後に第2手延仮桁30Bと固定する。
<4> Standing up the support pile When it demonstrates with reference to FIG. 4, the support pile 20c scheduled to be set up suspended from the heavy machine 50 is lifted and inserted into the foremost pile guide cylinder 33 of the second hand-drawn temporary girder 30B. While building vertically.
When the ground is hard, a known drilling machine is inserted into the support pile 20c, and the support pile 20c is driven to a predetermined depth while drilling.
And the head of each support pile 20c is fixed to the pile guide pipe | tube 33 of the 2nd extension temporary girder 30B, and the self weight of the 2nd extension temporary girder 30B is made to support the some support pile 20b, 20c.
When the head of the support pile 20c protrudes above the pile guide tube 33, the protruding portion of the support pile 20c is gas cut and then fixed to the second hand-drawn temporary girder 30B.

<5>主桁と床板の敷設
図5,6を参照して説明すると、第1及び第2手延仮桁30A,30Bの橋軸横断方向に沿って並設した一対の桁受材31,31の間に主桁40を載置するとともに、複数の主桁40上に床板41を敷設する。主桁40や床板41の重量は一対の桁受材31,31を介して複数の支持杭20b,20cが支持する
一対の側方つなぎ材32,32は主桁40や床板41の外方に位置するので、側方つなぎ材32に主桁40や床板41の重量は作用しない。
<5> Laying of main girder and floor board Referring to FIGS. 5 and 6, a pair of girder support members 31 arranged side by side along the bridge axis crossing direction of the first and second hand-drawn temporary girders 30A, 30B, The main girder 40 is placed between 31 and a floor plate 41 is laid on the plurality of main girders 40. The weight of the main girder 40 and the floor board 41 is supported by the plurality of support piles 20b and 20c via the pair of girder support members 31 and 31. The pair of side connecting members 32 and 32 are located outside the main girder 40 and the floor board 41. Therefore, the weight of the main beam 40 and the floor board 41 does not act on the side connecting material 32.

主桁40は一対の桁受材31,31の上面に載置して掛け渡すことができるので、従来工法のように主桁40の側端面に連結リブを突設したり、高強度ボルトで連結したりして連結部を増強する必要がなくなる。
さらに主桁40には、既存の形鋼単体、鈑桁、トラス構造体等を使用できるので、従来工法で使用する主桁を一体に組み込んだ多数の桟橋パネルを使用する場合と比べて極めて経済的である。
Since the main girder 40 can be placed on the upper surface of the pair of girder members 31 and 31 and hung over, a connecting rib is projected on the side end surface of the main girder 40 as in the conventional method, or a high strength bolt is used. There is no need to reinforce the connecting part.
Furthermore, because the main girder 40 can use existing structural steel, steel beams, truss structures, etc., it is extremely economical compared to the case of using many jetty panels that are integrated with the main girder used in the conventional method. It is.

<6>水平支持手段の撤去と移設
水平支持手段を構成する反力支柱43、第1、第2斜張材44,45を撤去する。
撤去した反力支柱43は最前の支持杭20cの真上に移設し、第1斜張材44も同様に移設する。
この水平支持手段の移設作業は、主桁40と床板41の敷設作業の直前に行ってもよい。
<6> Removal and transfer of horizontal support means The reaction force support 43 and the first and second cable stay members 44 and 45 constituting the horizontal support means are removed.
The removed reaction force column 43 is moved directly above the foremost support pile 20c, and the first cable-stretching material 44 is also transferred in the same manner.
The horizontal support means may be moved immediately before the main girder 40 and the floor plate 41 are laid.

<7>側方つなぎ材の撤去
第1手延仮桁30Aを構成する一対の側方つなぎ材32の両端を杭ガイド筒33から分離して撤去する。第1手延仮桁30Aを構成する桁受材31は上部工としてそのまま残置する。
撤去した側方つなぎ材32は次スパンの手延仮桁30の組み立て用資材として用いる。
尚、側方つなぎ材32の撤去作業は、主桁40と床板41の敷設作業の直前に行ってもよい。
<7> Removal of side connecting material The both ends of the pair of side connecting materials 32 constituting the first hand-drawn temporary girder 30A are separated from the pile guide tube 33 and removed. The girder receiving material 31 constituting the first hand-drawn temporary girder 30A is left as it is as an upper work.
The removed side connecting material 32 is used as a material for assembling the hand-drawn temporary girder 30 of the next span.
The removal work of the side connecting material 32 may be performed immediately before the laying work of the main beam 40 and the floor board 41.

<8>作業の繰り返し
以上説明したように、手延仮桁30の組み立て、手延仮桁30の水平架設、支持杭20の立設、主桁40と床板41の敷設、水平支持手段の移設、側方つなぎ材32の撤去の一連の作業を、スパン単位で反復して行う。
<8> Repeating the operation As described above, assembling the hand-drawn temporary girder 30, horizontally laying the hand-drawn temporary girder 30, standing the support pile 20, laying the main girder 40 and the floor board 41, and moving the horizontal support means A series of operations for removing the side connecting material 32 is repeated for each span.

なお、簡易架橋10の上部工は、水平に架設する以外に上下方向に勾配を付与したり、左右方向に蛇行させたりして施工することも可能である。
例えば、手延仮桁30を構成する杭ガイド筒33と側方つなぎ材32との連結部の角度を変更するだけで、上部工に上下方向の勾配をつけるとことが可能である。
また2本の側方つなぎ材32,32の何れか一方の長さを変更する等して上部工を左右方向に振ることが可能となる。
In addition, the superstructure of the simple bridge | bridging 10 can also be constructed by giving a gradient in the up-down direction or meandering in the left-right direction, in addition to laying horizontally.
For example, it is possible to give a vertical gradient to the superstructure only by changing the angle of the connecting portion between the pile guide cylinder 33 and the side connecting material 32 constituting the hand-drawn temporary girder 30.
In addition, it is possible to swing the superstructure in the left-right direction by changing the length of one of the two side connecting members 32, 32 or the like.

<9>橋軸方向長さの変更対応性について
簡易架橋10の施工に使用する手延仮桁30は、桁受材31の両端に連結する2本の側方つなぎ材32,32の長さを選択して簡単に付け替え可能である。
換言すれば、2本の側方つなぎ材32,32の付け替えを行うだけで、手延仮桁30の橋軸方向の長さを自由に調整できる。
そのため、従来工法で使用するユニット化した専用品の桟橋パネルと比べて、橋軸方向の長さの変更に対する対応性が格段に優れる。
<9> Correspondence of change in length in bridge axis direction The hand-drawn temporary girder 30 used for the construction of the simple bridge 10 is the length of the two side connecting members 32 and 32 connected to both ends of the girder support 31. It can be easily replaced by selecting.
In other words, it is possible to freely adjust the length of the hand-drawn temporary girder 30 in the bridge axis direction by simply replacing the two side connecting members 32 and 32.
Therefore, compared with the unitized exclusive jetty panel used in the conventional construction method, the adaptability to changes in the length in the bridge axis direction is remarkably superior.

10・・・簡易仮橋
20・・・支持杭
20a〜20c・・支持杭
30・・・手延仮桁
30A・・第1手延仮桁
30B・・第2手延仮桁
31・・・桁受材
32・・・側方つなぎ材
32a・・連結リブ
33・・・杭ガイド筒
33a・・筒部
33b・・上位のフランジ
33c・・下位のフランジ
33d・・連結リブ
34・・・足場板の高欄
40・・・主桁
41・・・床板
43・・・反力支柱
44・・・第1斜張材
45・・・第2斜張材
50・・・重機
DESCRIPTION OF SYMBOLS 10 ... Simple temporary bridge 20 ... Support piles 20a-20c ... Support pile 30 ... Manual provisional temporary girder 30A ... First manual temporary provisional girder 30B ... Second manual provisional temporary girder 31 ... Girder support member 32... Side linking member 32 a .. Connecting rib 33... Pile guide tube 33 a .. Tube portion 33 b .. Upper flange 33 c .. Lower flange 33 d. Board rail 40 ... main girder 41 ... floor board 43 ... reaction force column 44 ... first cable stay 45 ... second cable stay 50 ... heavy machinery

本発明は、複数の支持杭で支持する既設の上部工の前方に上部工を延設し、延設した上部工を水平支持手段により支持しつつ該上部工に付設した杭ガイド筒に支持杭を内挿して立設して行う簡易仮橋の架設工法であって、複数の杭ガイド筒を具備した桁受材と、該桁受材の直交方向に配置され、杭ガイド筒を介して桁受材の両端部に着脱可能に連結した一対の側方つなぎ材とを具備した平面コ字形を呈する手延仮桁を組み立てる第1工程と、既設上部工の前方に前記手延仮桁を連結して延設した後に、水平支持手段を介して延設した手延仮桁を支持する第2工程と、前記手延仮桁の杭ガイド筒に内挿して支持杭を立設する第3工程と前記杭ガイド筒を介して延設した手延仮桁の桁受材を橋軸横断方向に向けて支持杭の頭部間に架設する第4工程と、既設の手延仮桁と前記延設した手延仮桁の桁受材間に主桁を搭載して上部工を組み立てる第5工程と、前記既設の手延仮桁の桁受材から分離した一対の側方つなぎ材を撤去する第6工程とを含み、前記した工1〜6をスパン単位で繰り返して行うことを特徴とする。
本発明の他の形態において、撤去した前記一対の側方つなぎ材を転用して次スパンの手延仮桁を組み立てる。
本発明の他の形態において、前記杭ガイド筒が支持杭を挿通可能な筒部と、筒部の外周面に橋軸方向に沿って突設した複数の連結リブとを有していて、前記連結リブを介して一対の側方つなぎ材が着脱可能である。
本発明の他の形態において、前記手延仮桁の水平支持手段が、既設上部工に立設した反力支柱と、反力支柱の頂部を中心に既設上部工と延設した手延仮桁との間に張設した複数の斜張材との組み合わせからなり、前記水平支持手段をスパン単位で移設して使用する。
The present invention extends a superstructure ahead of an existing superstructure that is supported by a plurality of support piles, and supports piles on a pile guide tube attached to the superstructure while supporting the superstructure that has been extended by horizontal support means. A construction method of a simple temporary bridge that is erected by interpolating a girder with a plurality of pile guide tubes and a girder arranged in a direction orthogonal to the girder support members, A first step of assembling a hand-drawn temporary girder having a planar U-shape having a pair of side connecting members removably connected to both ends of the receiving material, and connecting the hand-drawn temporary girder in front of the existing superstructure The second step of supporting the hand-drawn temporary girder extended through the horizontal support means, and the third step of standing the support pile by interpolating the pile guide tube of the hand-drawn temporary girder. If a fourth to extended between the head of the support piles toward the Tenobe provisional digit digit receiving material that extends through the pile guide tube to the bridge axis transversely Degree and a fifth step for assembling the superstructure equipped with a main girder between the the existing Tenobe temporary digits extending the Tenobe provisionally digit digit receiving material, Tenobe of the existing temporary digit of the digit receiving material and a sixth step of removing the pair of side ties separated from, and performs engineering as 1-6 described above is repeated in the span units.
In another embodiment of the present invention, the pair of lateral connecting members removed are used to assemble a hand span temporary girder for the next span.
In another aspect of the present invention, the pile guide tube has a tube portion through which the support pile can be inserted, and a plurality of connecting ribs projecting along the bridge axis direction on the outer peripheral surface of the tube portion, A pair of side ties can be attached and detached via the connecting ribs.
In another aspect of the present invention, the horizontal support means of the hand-drawn temporary girder includes a reaction force column that is erected on the existing upper work, and a hand-drawn temporary beam that is extended with the existing upper work around the top of the reaction force support. The horizontal support means is used by being transferred in units of spans.

Claims (5)

複数の支持杭で支持する既設の上部工の前方に上部工を延設し、延設した上部工を水平支持手段により支持しつつ該上部工に付設した杭ガイド筒に支持杭を内挿して立設して行う簡易仮橋の架設方法であって、
複数の杭ガイド筒を具備した桁受材と、該桁受材の直交方向に配置され、杭ガイド筒を介して桁受材の両端部に着脱可能に連結した一対の側方つなぎ材とを具備した平面コ字形を呈する複数組の手延仮桁を使用し、
橋軸方向に向けて配置した前記一対の側方つなぎ材の基端を既設の上部工に連結して手延仮桁を橋軸方向へ向けて延設する工程と、
前記杭ガイド筒に内挿して支持杭を立設した後に複数の支持杭の頭部間に橋軸横断方向に向けて架設した桁受材を残置しつつ前記一対の側方つなぎ材を撤去する工程と、
既設の手延仮桁と前記延設した手延仮桁の桁受材の間に複数の主桁を搭載して上部工を組み立てる工程とを含み、
前記した複数の工程をスパン単位で繰り返して行うことを特徴とする、
簡易仮橋の架設方法。
Extend the superstructure ahead of the existing superstructure supported by multiple support piles, and insert the support pile into the pile guide tube attached to the superstructure while supporting the extended superstructure with the horizontal support means. It is a method of erection of a simple temporary bridge
A girder support member having a plurality of pile guide tubes, and a pair of side connecting members that are arranged in the orthogonal direction of the girder support members and are detachably connected to both ends of the girder support members via the pile guide tubes. Using multiple sets of hand-drawn temporary girders with a flat U-shape,
Connecting the base ends of the pair of side connecting members arranged in the direction of the bridge axis to the existing superstructure, and extending the hand-drawn temporary girder in the direction of the bridge axis;
After the support pile is erected by interpolating in the pile guide tube, the pair of side connecting materials are removed while leaving the girder support material erected in the crossing direction of the bridge axis between the heads of the plurality of support piles. Process,
A step of assembling an upper work by mounting a plurality of main girders between an existing hand-drawn temporary girder and a girder receiving material of the extended hand-drawn temporary girder,
It is characterized by repeatedly performing the plurality of steps described above in units of spans.
Simple temporary bridge construction method.
複数の支持杭で支持する既設の上部工の前方に上部工を延設し、延設した上部工を水平支持手段により支持しつつ該上部工に付設した杭ガイド筒に支持杭を内挿して立設して行う簡易仮橋の架設方法であって、
複数の杭ガイド筒を具備した桁受材と、該桁受材の直交方向に配置され、杭ガイド筒を介して桁受材の両端部に着脱可能に連結した一対の側方つなぎ材とを具備した平面コ字形を呈する手延仮桁を組み立てる工程と、
既設上部工の前方に前記手延仮桁を連結して延設した後に、水平支持手段を介して延設した手延仮桁を支持する工程と、
前記手延仮桁の杭ガイド筒に内挿して支持杭を立設する工程と、
前記杭ガイド筒を介して延設した手延仮桁の桁受材を橋軸横断方向に向けて支持杭の頭部間に架設する工程と、
既設の手延仮桁と前記延設した手延仮桁の桁受材間に主桁を搭載して上部工を組み立てる工程と、
前記延設した手延仮桁の桁受材から分離した一対の側方つなぎ材を撤去する工程とを含み、
前記した複数の工程をスパン単位で繰り返して行うことを特徴とする、
簡易仮橋の架設方法。
Extend the superstructure ahead of the existing superstructure supported by multiple support piles, and insert the support pile into the pile guide tube attached to the superstructure while supporting the extended superstructure with the horizontal support means. It is a method of erection of a simple temporary bridge
A girder support member having a plurality of pile guide tubes, and a pair of side connecting members that are arranged in the orthogonal direction of the girder support members and are detachably connected to both ends of the girder support members via the pile guide tubes. Assembling a hand-drawn temporary girder having a flat U-shaped shape,
After connecting and extending the hand-drawn temporary girder in front of the existing superstructure, supporting the hand-drawn temporary girder extended through the horizontal support means; and
Inserting the support pile by interpolating the pile guide cylinder of the hand-drawn temporary girder; and
A step of laying the girder support material of the hand-drawn temporary girder extended through the pile guide tube between the heads of the support piles in the bridge axis crossing direction;
A step of assembling an upper work by mounting a main girder between the existing hand-drawn temporary girder and the girder receiving material of the extended hand-drawn temporary girder;
Removing a pair of side tie members separated from the girder support material of the extended manual temporary girder,
It is characterized by repeatedly performing the plurality of steps described above in units of spans.
Simple temporary bridge construction method.
撤去した前記一対の側方つなぎ材を転用して次スパンの手延仮桁を組み立てることを特徴とする、請求項1または2に記載の簡易仮橋の架設方法。   3. The method for constructing a simple temporary bridge according to claim 1 or 2, wherein the pair of lateral connecting members removed are used to assemble a hand span temporary girder for the next span. 前記杭ガイド筒が支持杭を挿通可能な筒部と、筒部の外周面に橋軸方向に沿って突設した複数の連結リブとを有していて、前記連結リブを介して一対の側方つなぎ材が着脱可能であることを特徴とする、請求項1または2に記載の簡易仮橋の架設方法。   The pile guide tube has a tube portion through which the support pile can be inserted, and a plurality of connecting ribs projecting along the bridge axis direction on the outer peripheral surface of the tube portion, and a pair of sides via the connecting rib 3. The method for constructing a simple temporary bridge according to claim 1, wherein the connecting material is detachable. 前記手延仮桁の水平支持手段が、既設上部工に立設した反力支柱と、反力支柱の頂部を中心に既設上部工と延設した手延仮桁との間に張設した複数の斜張材との組み合わせからなり、前記水平支持手段をスパン単位で移設して使用することを特徴とする、請求項1または2に記載の簡易仮橋の架設方法。   A plurality of horizontal support means for the hand-drawn temporary girder are stretched between a reaction force column erected on the existing superstructure and a hand-drawn temporary girder extended around the top of the reaction force strut. The method for erection of a simple temporary bridge according to claim 1 or 2, wherein the horizontal support means is used by being transferred in units of spans.
JP2016080277A 2016-04-13 2016-04-13 Construction method of simple temporary bridge Active JP5977904B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016080277A JP5977904B1 (en) 2016-04-13 2016-04-13 Construction method of simple temporary bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016080277A JP5977904B1 (en) 2016-04-13 2016-04-13 Construction method of simple temporary bridge

Publications (2)

Publication Number Publication Date
JP5977904B1 JP5977904B1 (en) 2016-08-24
JP2017190607A true JP2017190607A (en) 2017-10-19

Family

ID=56760024

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016080277A Active JP5977904B1 (en) 2016-04-13 2016-04-13 Construction method of simple temporary bridge

Country Status (1)

Country Link
JP (1) JP5977904B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7437270B2 (en) 2020-08-31 2024-02-22 鹿島建設株式会社 Bridge construction method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6034531B1 (en) * 2016-08-03 2016-11-30 ヒロセ株式会社 Construction method of simple temporary bridge
CN109162205B (en) * 2018-10-25 2023-12-12 中交武汉港湾工程设计研究院有限公司 Arch rib folding section mounting structure and mounting method
JP7011613B2 (en) * 2019-02-12 2022-02-10 ヒロセ株式会社 How to build a simple temporary bridge
CN113969540B (en) * 2020-07-24 2024-02-20 天津电力工程监理有限公司 Construction temporary trestle and construction method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3043320B2 (en) * 1998-09-17 2000-05-22 株式会社高知丸高 Piling pier construction method and pile pier structure
JP4219067B2 (en) * 1999-10-18 2009-02-04 ヒロセ株式会社 Construction method of temporary bridge temporary pier
JP4190112B2 (en) * 1999-11-01 2008-12-03 大成建設株式会社 Construction method of hand-drawn pier
JP4567080B2 (en) * 2008-09-05 2010-10-20 Jfeシビル株式会社 How to build a jetty road
JP5661011B2 (en) * 2011-09-20 2015-01-28 株式会社高知丸高 Manufacturing method of superstructure for bridge, bridge and superstructure for bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7437270B2 (en) 2020-08-31 2024-02-22 鹿島建設株式会社 Bridge construction method

Also Published As

Publication number Publication date
JP5977904B1 (en) 2016-08-24

Similar Documents

Publication Publication Date Title
JP5977904B1 (en) Construction method of simple temporary bridge
JP5053589B2 (en) How to build a bridge girder
KR101391637B1 (en) Constrution methoed for Prestressed Composite Truss girder using steel truss member
KR101687495B1 (en) Partial top-down construction method for building underground structures
JP5033726B2 (en) Formwork support and horizontal force processing member for formwork support
KR200417438Y1 (en) Bracket structure for girder and slab construction
KR20120097702A (en) Connection of concrete filled steel tube column and h-shaped steel beam and constructing method of the same
JP6034531B1 (en) Construction method of simple temporary bridge
JP2011157720A (en) Method for constructing railway reinforced concrete rigid-frame structure viaduct
CN111119070A (en) Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
JP5277106B2 (en) Lining structure and lining method
JP4033871B2 (en) How to build a bridge girder
CN102155095B (en) Arranging method of concrete reinforcements of steel rib of large-scale metallurgical workshop
JP2005188102A (en) Structure of building and construction method
JP2018115514A (en) Method for constructing pile bearing structure, and reinforcement member used in the pile bearing structure
JP7093714B2 (en) Pit structure and how to build it
JP7219529B2 (en) Combination structure of steel materials, shoring structure and construction method
JP4814019B2 (en) Joint structure and method of pile and superstructure
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
JP7301248B1 (en) Structure of floor girder unit and temporary pier
JP2021001453A (en) Top plate construction method of vertical shaft and top plate structure
KR102641926B1 (en) Segmental Steel Box Girder, Bridge Upper Structure Using It and Its Construction Method
KR102567830B1 (en) Assembly of steel beam with easy construction
CN216892835U (en) Bolt-up and down-welding type steel concrete beam column joint structure for spliced beam section
CN212452315U (en) Assembly module and modular construction platform

Legal Events

Date Code Title Description
A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20160615

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160621

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160701

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160719

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160722

R150 Certificate of patent or registration of utility model

Ref document number: 5977904

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250