KR20100100193A - Form system for constructing rc-girder in rc top down method and the rc top down method using the same - Google Patents

Form system for constructing rc-girder in rc top down method and the rc top down method using the same Download PDF

Info

Publication number
KR20100100193A
KR20100100193A KR1020090018937A KR20090018937A KR20100100193A KR 20100100193 A KR20100100193 A KR 20100100193A KR 1020090018937 A KR1020090018937 A KR 1020090018937A KR 20090018937 A KR20090018937 A KR 20090018937A KR 20100100193 A KR20100100193 A KR 20100100193A
Authority
KR
South Korea
Prior art keywords
formwork
construction
junction
center portion
pillar
Prior art date
Application number
KR1020090018937A
Other languages
Korean (ko)
Inventor
유광준
서정호
Original Assignee
(주)씨엠파트너스건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)씨엠파트너스건축사사무소 filed Critical (주)씨엠파트너스건축사사무소
Priority to KR1020090018937A priority Critical patent/KR20100100193A/en
Publication of KR20100100193A publication Critical patent/KR20100100193A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/30Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor

Abstract

PURPOSE: A form system for an RC beam construction in an RC top-down construction manner and an RC top-down construction method are provided to mount a slab form and facilitate installation and dismantlement. CONSTITUTION: A form system for an RC beam construction in an RC top-down construction manner comprises a joint form(200) and a connection form(300). The joint form is for forming a joint part of an RC beam and a center part(111) of a composite column. The joint form is attached to and detached from the center part of the composite column. The connection form is for forming the RC beam. The connection form is installed in order to connect the joint forms.

Description

RC역타공법에서의 RC보 시공용 거푸집시스템 및 이를 이용한 RC역타공법{Form system for constructing RC-girder in RC top down method and the RC top down method using the same}Form system for constructing RC-girder in Rc reinforcement method and Rc reversal method using same {form system for constructing RC-girder in RC top down method and the RC top down method using the same}

본 발명은 RC역타공법과 관련한 기술에 관한 것으로, 더욱 상세하게는 거푸집이면서도 안정적인 지지틀이 되도록 구성함과 동시에 슬래브거푸집의 거치가 가능하면서도 설치와 해체가 용이하도록 간단하게 구성한 RC보 시공용 거푸집시스템과, 이 거푸집시스템을 바람직하게 이용한 RC역타공법에 관한 것이다.The present invention relates to a technology related to the RC reverse drilling method, and more specifically, to form a stable and support frame, and at the same time can be mounted slab formwork, but simply configured to easily install and dismantle the RC beam construction formwork system And it is related with the RC reverse drilling method which used this formwork system preferably.

역타공법(Top Down method)은 건물의 지하부분을 하향식으로 공사하는 방법으로서, 지하공사와 지상공사의 병행으로 공기단축이 가능하고 소음과 진동이 적어 주로 도심지 지하공사로 각광받는 공법이다.Top down method is the method of constructing the underground part of the building from top to bottom. It is possible to shorten the air by the underground work and the ground work in parallel, and it is a method that is mainly spotlighted as the underground work in the city because of the low noise and vibration.

역타공법에서 건물 지하부분의 층간구조체(보와 슬래브)를 철근콘크리트구조로 시공한 것이 RC역타공법인데, RC역타공법에서 동바리와 거푸집 설치 등의 가설작업은 필수적이다. 다시 말해, RC역타공법은 통상 지반을 굴토한 후 굴토바닥을 고른 상태에서 동바리와 보거푸집 내지 슬래브거푸집을 설치한 다음 콘크리트를 타설하는 방법으로 진행된다. 그러나 이 방식은 동바리의 안정적인 설치를 위해 바닥 고르기 작업을 수행하야 하고 아울러 매층마다 동바리 설치와 해체작업을 반복적으로 수행해야 하기 때문에 가설작업량이 많을 수밖에 없다. 이를 개선하고자 현수식 RC역타공법이 개발되었다.In the reverse drilling method, the construction of interlayer structures (beams and slabs) in the basement of the building with reinforced concrete structures is the RC reverse drilling method. In the RC reverse drilling method, construction work such as installation of shells and formwork is essential. In other words, the RC reverse drilling method is usually performed after the ground is excavated, and the concrete is installed after installing the clubbing and the formwork or the slab formwork in the state of selecting the pit. However, this method requires a lot of construction work because it is necessary to perform floor leveling work for stable installation of the club, and it is necessary to repeatedly install and dismantle the club for each floor. To improve this, a suspension RC reverse drilling method was developed.

현수식 RC역타공법은 동바리를 세우는 것 대신에 보거푸집 내지 슬래브거푸집을 현수재에 매단 지지틀이 지지하도록 한 방식으로, 거푸집을 지지틀과 함께 아래로 이동시키면서 반복적인 층간구조체를 시공하도록 한 방법이다. 이와 같은 현수식 RC역타공법은 현수재를 매달기 위한 기시공 상태의 층간구조체가 반드시 있어야 하기 때문에 1층의 층간구조체 시공에는 이용될 수 없다는 단점이 있다. 이를 개선하고자 브라켓 지지방식의 RC역타공법이 개발되었다.Suspended RC reversal method is a method of constructing a repetitive interlayer structure by moving the formwork or slab formwork to the suspension material instead of building the bridge, moving the formwork down with the support frame. to be. Such suspension RC reverse drilling method has a disadvantage that it cannot be used for the construction of the interlayer structure of the first floor because the interlayer structure of the construction state must be used for hanging the suspension material. In order to improve this, RC reverse drilling method with bracket support method was developed.

브라켓 지지방식의 RC역타공법은 기둥에 브라켓을 고정 설치함과 아울러 브라켓에 지지틀을 설치함으로써 보거푸집을 지지틀 및 브라켓을 통해 기둥이 지지하도록 한 방식으로, 브라켓을 현수재로 매달아 거푸집을 지지틀 및 브라켓과 함께 아래로 이동시키면서 반복적인 층간구조체를 시공하도록 한 방법이다. 이와 같은 브라켓 지지방식의 RC역타공법은 시공하중은 기둥이 지지하도록 하는 한편 하강시의 지지틀 하중은 현수재가 지지하도록 한 방식이다. RC reverse drilling method of bracket support method is to fix the bracket to the pillar and to install the support frame on the bracket so that the pillar is supported by the support frame and the bracket. It is a method to construct a repetitive interlayer structure while moving down with the frame and bracket. The RC reverse boring method of the bracket supporting method is such that the construction load is supported by the column while the supporting frame load during the descent is supported by the suspension material.

도 1은 브라켓 지지방식의 RC역타공법에서 이용되는 지지틀시스템(지지틀+브라켓)을 보여준다. 보는 바와 같이 브라켓 지지방식의 RC역타공법에는 보거푸집과는 별도의 가설자재로 복잡한 구조의 브라켓과 지지틀이 필요하다. 더군다나 브라 켓 지지방식의 RC역타공법에서는 거푸집패널, 장선, 멍에 등의 복잡한 구조를 가지는 보거푸집을 이용해왔다. 이와 같이 브라켓 지지방식의 RC역타공법은 보거푸집, 브라켓, 지지틀을 각각 따로 복잡하게 준비하여 설치해야 하기 때문에 설치 자재의 개수가 많고 작업량이 많다는 단점이 있다.Figure 1 shows a support frame system (support frame + bracket) used in the RC reverse drilling method of the bracket support method. As you can see, the RC reversing method of bracket support type requires a bracket and support frame with a complicated structure as a temporary material separate from the formwork. In addition, bracket-supported RC reverse drilling has used complex formwork such as formwork panels, joists, and yokes. As described above, the RC reverse boring method of the bracket supporting method has a disadvantage in that a large number of installation materials and a large amount of work materials are required because the boring die, bracket, and support frame must be prepared and installed separately.

본 발명은 상기와 같은 종래 RC역타공법에서의 RC보 시공 문제를 개선하고자 개발된 것으로서, 거푸집이면서도 동시에 안정적인 지지틀이 되는 한편 설치와 해체가 용이하고 나아가 슬래브거푸집의 거치가 가능한 RC보 시공용 거푸집시스템을 제공하는데 기술적 과제가 있다.The present invention was developed in order to improve the RC beam construction problem in the conventional RC reverse drilling method as described above, it is a formwork for the RC beam construction formwork at the same time a stable support frame and easy to install and dismantle and further mount the slab formwork There is a technical challenge in providing a system.

또한, 본 발명은 전용률을 향상시킨 RC보 시공용 거푸집시스템을 제공하는데 기술적 과제가 있다.In addition, the present invention has a technical problem to provide a formwork system for RC beam construction with improved rate of utilization.

또한, 본 발명은 가설작업을 최소화하면서 시공성과 경제성을 향상시킨 RC역타공법을 제공하는데 기술적 과제가 있다.In addition, the present invention has a technical problem to provide an RC reverse drilling method that improved construction and economical efficiency while minimizing the construction work.

상기한 기술적 과제를 해결하기 위해 본 발명은 다음과 같은 기술적 특징을 가지는 RC역타공법에서의 RC보 시공용 거푸집시스템과 RC역타공법을 제공한다.In order to solve the above technical problem, the present invention provides a formwork system and RC reverse drilling method for RC beam construction in the RC reverse drilling method having the following technical features.

본 발명에 따른 RC역타공법에서의 RC보 시공용 거푸집시스템은, 철골·CFT· PC에 의한 센터부분 주변에 RC부분이 형성되는 합성기둥과 RC보로 설계된 지하구조물을 역타공법으로 시공함에 있어 합성기둥의 센터부분을 시공한 후 합성기둥의 RC부분을 시공하기에 앞서 RC보를 시공하기 위한 거푸집시스템으로, 합성기둥의 RC부분과 RC보의 접합부를 형성시키기 위한 거푸집으로 접합부바닥판과 지지브라켓 및 접합부측면판으로 구성된 접합부거푸집;과, RC보를 형성시키기 위한 거푸집으로 연결바닥판과 연결측면판 및 수평날개로 구성된 연결거푸집;을 포함하여 구성되는 것을 특징으로 한다.The RC beam construction formwork system in the RC reverse drilling method according to the present invention, the composite pillar in which the RC portion is formed around the center portion by steel frame, CFT, PC and the underground structure designed by RC beam by the reverse drilling method Formwork system for constructing RC beams before constructing RC part of composite column after constructing the center part of composite column. Formwork for forming joints of RC part and RC beam of composite column. Joining formwork consisting of side plates; and Formwork for forming RC beams, connecting formwork consisting of a connecting bottom plate and a connecting side plate and a horizontal wing; characterized in that comprises a.

본 발명에 따른 RC역타공법은, 상기한 RC보 시공용 거푸집시스템을 이용하면서 RC역타공법으로 건물의 지하부분을 구축하는 방법으로서, (a)흙막이벽을 시공하는 단계; (b)내부기둥으로 철골, CFT 또는 PC에 의한 센터부분 주변에 RC부분이 형성되는 합성기둥을 계획하고 흙막이벽 내부에 합성기둥의 센터부분을 시공하는 단계; (c)흙막이벽 내부 지반을 굴토하는 단계; (d)접합부거푸집의 지지브라켓을 합성기둥의 센터부분에 장착시키면서 RC보 시공용 거푸집시스템을 RC보 시공위치에 설치하는 단계; (e)RC보 시공용 거푸집시스템 내부에 보철근을 배근하고 보콘크리트를 타설하면서 RC보를 시공하는 한편, RC보 시공용 거푸집시스템의 수평날개에 슬래브거푸집을 거치하여 설치하고 슬래브콘크리트를 타설하면서 슬래브를 시공하는 단계; (f)상기 (c)단계 내지 (e)단계를 반복 실시하는 단계; (g)합성기둥의 센터부분 주변으로 기둥철근을 배근하고 기둥콘크리트를 타설하면서 합성기둥의 RC부분을 시공하여 합성기둥을 완성하는 단계;를 포함하여 이루어지되, 상기 (f)단계 속에서 (d)단계는 접합부거푸집의 지지브라켓을 합성기둥의 센터부분에서 탈락시켜 RC보 시공용 거푸집시스템을 아래층 RC보 시공위치로 하강시키면서 이루어지는 것을 특징으로 한다.RC reverse drilling method according to the present invention, a method for constructing the underground portion of the building by the RC reverse drilling method using the above-described RC beam construction formwork system, comprising the steps of: (a) constructing a wall; (b) planning a synthetic column in which the RC portion is formed around the center portion by steel frame, CFT or PC as an inner pillar and constructing the center portion of the synthetic pillar in the earth wall; (c) excavating the ground within the retaining wall; (d) installing the formwork system for RC beam construction at the RC beam construction position while mounting the support bracket of the joining formwork to the center portion of the composite column; (e) RC beams are installed by placing reinforcement reinforcement inside the RC beam construction formwork and placing bocon concrete, while installing slab formwork on the horizontal wing of RC beam construction formwork, and placing slab concrete. Constructing; (f) repeating steps (c) to (e); (g) constructing the RC column of the composite pillar while placing the pillar reinforcement around the center portion of the composite pillar and placing the pillar concrete to complete the composite pillar; but in the step (f), (d) The step is characterized in that the support bracket of the joint formwork is removed from the center of the composite column while lowering the formwork system for RC beam construction to the construction position of the RC beam construction downstairs.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

첫째, 본 발명에 따른 거푸집시스템은 거푸집과 지지틀을 통합한 것이기 때문에 전체적으로 자재의 개수가 적어 설치 및 관리가 용이하며, 이에 따라 RC역타공법을 수행함에 있어 전반적으로 시공성과 경제성을 동시에 향상시킬 수 있다.First, since the formwork system according to the present invention integrates the formwork and the support frame, it is easy to install and manage due to the small number of materials as a whole. Accordingly, the overall construction and economic efficiency can be simultaneously improved in performing the RC reverse boring method. have.

둘째, 본 발명에 따른 거푸집시스템은 1방향 내지 2방향 골조 각각의 구조형식에 부합하는 접합부거푸집과 1방향 내지 2방향 골조 구조형식에 무관하는 연결거푸집으로 분리 구성되기 것이기 때문에, 접합부거푸집을 변경하기만 하면 연결거푸집을 그대로 이용하면서도 1,2방향 골조 구조형식에 적절하게 대응하면서 적용할 수 있어 거푸집 전용률을 향상시킬 수 있다.Secondly, since the formwork system according to the present invention will be composed of a joint formwork corresponding to each structural form of the one-way or two-way frame and a connecting formwork irrelevant to the structural form of the one-way or two-way frame, to change the junction formwork If only the connection formwork is used as it is, it can be applied while appropriately responding to the 1,2-way frame structure type, thereby improving the formwork rate.

셋째, 본 발명에 따른 거푸집시스템은 거푸집이 곧 지지틀이 되기 때문에 콘크리트 측압을 안정적으로 견딜 수 있으며, 이에 따라 콘크리트 타설과정에서 형틀이 터지거나 배가 부르는 등의 현상을 최소화시킬 수 있어 전반적으로 균일하고도 우수한 시공품질을 확보할 수 있다.Third, the formwork system according to the present invention can withstand the concrete side pressure stably because the formwork soon becomes a support frame, thereby minimizing the phenomenon such as the mold bursting or hungry in the process of placing concrete, it is overall uniform and Also excellent construction quality can be secured.

이하, 본 발명을 첨부한 도면 및 바람직한 실시예에 따라 상세히 설명한다. 다만, 본 발명은 RC보 시공용 거푸집시스템과 이 거푸집시스템을 RC역타공법에 관하여 제안하므로 이들을 구분하여 살펴본다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments. However, the present invention proposes the formwork system for RC beam construction and this formwork system with respect to the RC reverse drilling method, and looks at them separately.

1. RC보 시공용 거푸집시스템1. Formwork system for RC beam construction

본 발명에 따른 거푸집시스템은, 철골 또는 CFT 또는 PC에 의한 센터부분(111) 주변에 RC부분(112)이 형성되는 합성기둥(110)과 RC보(120)로 설계된 지하구조물을 역타공법으로 시공함에 있어 합성기둥의 센터부분(111)을 시공한 후 합성기둥의 RC부분(112)을 시공하기에 앞서 RC보(120)를 시공하기 위한 거푸집시스템으로서, 거푸집이면서도 동시에 안정적인 지지틀이 되도록 구성되는 한편 설치와 해체가 용이하도록 간단하게 구성되고 나아가 슬래브거푸집의 거치가 가능하게 구성된다는데 기술적 특징이 있다.Formwork system according to the present invention, the construction of the underground structure designed by the composite column 110 and RC beam 120 is formed by the RC section 112 around the center portion 111 by the steel frame or CFT or PC by reverse drilling method As a formwork system for constructing the RC beam 120 prior to the construction of the RC part 112 of the composite pillar after the construction of the center portion 111 of the synthetic pillar in the ship, it is configured to be a formwork and at the same time stable support frame On the other hand there is a technical feature that it is simply configured to facilitate installation and disassembly, and furthermore it is possible to mount the slab formwork.

본 발명에 따른 거푸집시스템은 접합부거푸집(200)과 연결거푸집(300)으로 구성된다. 접합부거푸집(200)은 합성기둥의 센터부분(111)과 RC보(120)의 접합부를 형성시키기 위한 거푸집으로, 합성기둥의 센터부분(111)에 탈착 가능하게 설치되는 구성이다. 연결거푸집(300)은 RC보(120)를 형성시키기 위한 거푸집으로, 접합부거푸집(200) 상호 간을 연결하도록 설치되는 구성이다. 접합부거푸집(200)이 합성기둥의 센터부분(111)에 설치되고 연결거푸집(300)에 의해 접합부거푸집(200)이 연결됨에 따라, RC보(120)의 시공하중은 연결거푸집(300)과 접합부거푸집(200)의 자체 내력으로 지지되는 한편 합성기둥의 센터부분(111)으로 전달되어 지지된다. 나아가 상기 연결거푸집(200)은 슬래브거푸집의 거치가 가능하도록 구성되며, 더불어 접합부거푸집(100)도 슬래브거푸집의 거치가 가능하게 구성될 수 있다.Formwork system according to the present invention is composed of a junction formwork 200 and the connection formwork (300). Joining formwork 200 is a formwork for forming a joining portion of the center portion 111 and the RC beam 120 of the composite pillar, is a configuration that is detachably installed in the center portion 111 of the composite pillar. The connection formwork 300 is a formwork for forming the RC beam 120, the junction formwork 200 is configured to be connected to each other. As the joint formwork 200 is installed in the center portion 111 of the composite pillar and the junction formwork 200 is connected by the connection formwork 300, the construction load of the RC beam 120 is connected to the connection formwork 300 and the junction part. While being supported by the internal strength of the formwork 200 is transferred to and supported by the center portion 111 of the composite pillar. Furthermore, the connection die 200 is configured to be mounted on the slab formwork, and the junction die 100 may also be configured to be mounted on the slab formwork.

도 2와 도 3은 본 발명에 따른 거푸집시스템에 대한 실시예들을 보여주는데, 구조형식에 따라 구분하여 보여준다. 도 2는 RC보(120)를 1방향으로 시공하기 위해 제안된 1방향 골조용의 거푸집시스템으로 연결거푸집(300)이 1방향으로 설치된 예이고, 도 3은 RC보(120)를 2방향으로 시공하기 위해 제안된 2방향 골조용의 거푸집시스템으로 연결거푸집(300)이 2방향으로 설치된 예이다. 보는 바와 같이 1방향 골조용과 2방향 골조용은 연결거푸집(300)의 설치방향에서 차이가 있음에 따라 연결거푸집(300)이 거치되는 접합부거푸집(200)에서 차이가 있을 뿐, 전체적으로 동일하다.2 and 3 show embodiments of the formwork system according to the present invention, shown separately according to the structure type. Figure 2 is an example of the formwork system for the one-way frame for the construction of the RC beam 120 in one direction, the connection formwork 300 is installed in one direction, Figure 3 is the RC beam 120 in two directions The linkage formwork 300 is installed in two directions as a formwork system for a two-way frame proposed for construction. As shown, the one-way frame and the two-way frame is the same in the installation form of the connection formwork 300, there is a difference in the junction formwork 200, where the connection formwork 300 is mounted, is the same as a whole.

도 4는 1방향 골조용 거푸집시스템에서의 접합부거푸집(200)을 보여주며, 도 5는 2방향 골조용 거푸집시스템에서의 접합부거푸집(200)을 보여준다. 어떠한 구조형식을 위한 것이든 본 발명에 따른 거푸집시스템에서 접합부거푸집(200)은, 접합부바닥판(210), 지지브라켓(220) 및 접합부측면판(230)을 포함하여 구성되며, 다만 구조형식에 따라 접합부측면판(230)의 구체적인 형태가 달라질 뿐이다. 접합부거푸집(200)은 그 자체가 시공하중을 충분히 견딜 수 있도록 충분한 내력을 발휘하는 구조용 강재로 구성함이 바람직하다. Figure 4 shows the junction formwork 200 in a one-way frame formwork system, Figure 5 shows the junction formwork 200 in a two-way frame formwork system. The joint formwork 200 in the formwork system according to the present invention, which is for any structural form comprises a junction bottom plate 210, a support bracket 220 and a junction side plate 230, but only in the structural form Accordingly, the specific shape of the junction side plate 230 is only changed. Joining formwork 200 is preferably composed of structural steel that exhibits sufficient strength to withstand the construction load itself.

접합부거푸집(200)에서 접합부바닥판(210)은, 합성기둥의 센터부분(111) 단면보다 넓은 판면을 가지는 판형 부재로서, 가운데에 합성기둥의 센터부분(111)을 통과시키는 개구부(211)가 형성되도록 마련된 구성이다. 접합부바닥판(210)은 개 구부(211)에 의해 합성기둥의 센터부분(111)을 둘러쌀 수 있게 된다. 이러한 접합부바닥판(210)은 RC보(120)의 단부(합성기둥의 센터부분과의 접합부를 구성하는 단부) 바닥면을 형성하는 거푸집판으로 역할하게 되고, 아울러 후술하는 연결거푸집의 연결바닥판(310)을 거치하기 위한 거치대로서 역할하게 되며, 나아가 4개가 +자형으로 분리 배치되는 지지브라켓(220)을 서로 연결 구속하는 매개로서 역할하게 된다.In the junction die 200, the junction bottom plate 210 is a plate-shaped member having a plate surface wider than the cross section of the center portion 111 of the composite pillar, and an opening 211 through which the center portion 111 of the composite pillar passes through the center portion is formed. It is a structure provided to be formed. The junction bottom plate 210 may be surrounded by the center portion 111 of the composite pillar by the opening 211. The joint bottom plate 210 serves as a form plate forming the bottom surface of the end of the RC beam 120 (the end constituting the joint portion with the center portion of the composite pillar), and also the connection bottom plate of the connection form to be described later It serves as a cradle for mounting (310), and further serves as a medium for constraining and connecting the support brackets 220, which are separated from each other in four shapes.

한편, 접합부바닥판의 개구부(211)는 합성기둥의 센터부분(111) 단면과 동일해야 접합부바닥판(210)이 합성기둥의 센터부분(111)을 둘러싸면서 거푸집판으로 역할할 수 있게 될 것이다. 하지만 접합부바닥판의 개구부(211)를 합성기둥의 센터부분(111) 단면과 동일하게 하면 다양한 상황변화에 유연하게 대등하기 어렵다. 이에 본 발명에서는 접합부바닥판의 개구부(211)를 합성기둥의 센터부분(111)보다 크게 형성시킬 것을 제안하며, 다만 이러한 접합부바닥판(210)은 합성기둥의 센터부분(111)에 설치될 때 개구부(211)가 일부 오픈되어 콘크리트 타설이 곤란할 수 있기 때문에 철망바닥판(250)을 함께 사용할 것을 제안한다. 즉, 접합부바닥판의 개구부(211)에서 일부 오픈되는 부분을 철망바닥판(250)으로 덮어 콘크리트 타설을 가능케 한 것이다. 철망바닥판(250)은 콘크리트 타설면을 거칠게 하므로, 나중에 합성기둥의 RC부분(112)을 시공할 때 일체성 강화에 유리한 역할을 한다. On the other hand, the opening portion 211 of the junction bottom plate should be the same as the cross section of the center portion 111 of the composite column will be able to serve as a form plate while the junction bottom plate 210 surrounds the center portion 111 of the composite pillar. . However, if the opening 211 of the joint bottom plate is the same as the cross section of the center portion 111 of the composite column, it is difficult to flexibly cope with various situational changes. Accordingly, the present invention proposes to form the opening 211 of the junction bottom plate larger than the center portion 111 of the composite pillar, but when the junction bottom plate 210 is installed at the center portion 111 of the composite pillar. Since the opening part 211 may be partially opened and concrete pouring may be difficult, it is proposed to use the wire mesh base plate 250 together. That is, the part that is partially opened in the opening 211 of the joint bottom plate is covered with the wire mesh bottom plate 250 to enable concrete pouring. Since the wire mesh base plate 250 makes the concrete pour surface rough, it plays an advantageous role in strengthening the integrity when constructing the RC portion 112 of the composite column later.

접합부거푸집(200)에서 지지브라켓(220)은, 가운데에 합성기둥의 센터부분(111)을 통과시키는 빈 공간을 남겨둔 채 4개가 +자형으로 배치되어 접합부바닥판(210) 아래에 접합부바닥판(210)을 지지하도록 설치되는 구성인데, +자형으로 배 치된 4개 중 전부가 또는 마주보는 한 쌍만이 합성기둥의 센터부분(111)에 탈착 가능하게 설치되게 된다. 지지브라켓(220)이 합성기둥의 센터부분(111)에 장착되면 본 발명에 따른 거푸집시스템은 거푸집을 겸한 지지틀로서 안정적으로 자리 잡게 되고, 지지브라켓(220)이 합성기둥의 센터부분(111)에서 탈락되면 본 발명에 따른 거푸집시스템은 이동성을 가지게 된다. 지지브라켓(220)의 탈착은 볼트 조립방식으로 처리할 수 있다. 특히, 지지브라켓(220)은 합성기둥의 센터부분(111)에 장착된 상태에서 시공하중을 합성기둥의 센터부분(111)으로 전달하는 역할을 하게 된다. 도 4와 도 5 및 도 15에서는 지지브라켓(220)으로 H형강을 채택한 예를 도시하고 있으나, H형강 대신 플레이트 등을 채택하는 것도 가능하다. In the joint formwork 200, the support brackets 220 are arranged in a + -shape, leaving four empty spaces for passing the center portion 111 of the composite pillar in the center to form a junction bottom plate (below the junction bottom plate 210). 210 is installed to support, all of the four arranged in a + -shaped or only a pair facing each other will be detachably installed in the center portion 111 of the synthetic column. When the support bracket 220 is mounted on the center portion 111 of the synthetic pillar, the formwork system according to the present invention is stably positioned as a support frame serving as a formwork, and the support bracket 220 is the center portion 111 of the synthetic pillar. When dropped from the formwork system according to the invention will have mobility. Desorption of the support bracket 220 may be treated by bolt assembly method. In particular, the support bracket 220 serves to transfer the construction load to the center portion 111 of the synthetic pillar in a state mounted on the center portion 111 of the synthetic pillar. 4, 5, and 15 illustrate an example in which H-shaped steel is adopted as the support bracket 220, but a plate or the like may be adopted instead of H-shaped steel.

접합부거푸집(200)에서 접합부측면판(230)은, 접합부바닥판(210) 위에 수직 입설된 판형 부재로서, RC보(120)의 시공 방향에 대응하게 마련된 구성이다. 접합부측면판(230)은 RC보(120)의 시공 방향에 대응하므로, RC보(120)가 1방향으로 시공되는 경우라면 접합부측면판(230)은 도 4에서와 같이 양 측에서 평행하게 마련되며, RC보(120)가 2방향으로 시공되는 경우라면 접합부측면판(230)은 도 5에서와 같이 네 코너에서 인코너를 형성하면서 마련된다. 나아가 도 4에서는 접합부측면판(230)에서 외향하게 수평으로 수평날개(240)가 더 마련되고 있는데, 접합부거푸집의 수평날개(240)에는 후술하는 연결거푸집의 수평날개(340)가 안착되게 되며, 아울러 접합부거푸집의 수평날개(240)는 연결거푸집의 수평날개(340)와 동일하게 슬래브거푸집이 거치되는 거치대가 되기도 한다. In the junction part die 200, the junction part side plate 230 is a plate-shaped member vertically mounted on the junction part bottom plate 210, and is a structure provided corresponding to the construction direction of the RC beam 120. As shown in FIG. Since the junction side plate 230 corresponds to the construction direction of the RC beam 120, when the RC beam 120 is constructed in one direction, the junction side plate 230 is provided in parallel on both sides as shown in FIG. If the RC beam 120 is constructed in two directions, the junction side plate 230 is provided while forming an inconor at four corners as shown in FIG. 5. Furthermore, in Figure 4, the horizontal blade 240 is further provided horizontally outward from the junction side plate 230, the horizontal blade 240 of the junction die will be seated horizontal blade 340 of the connecting die to be described later, In addition, the horizontal wing 240 of the joint formwork may be a cradle in which the slab formwork is mounted in the same manner as the horizontal wing 340 of the connection formwork.

도시하지 않았지만 상기와 같은 접합부거푸집(200)은 좌측 세그먼트와 우측 세그먼트의 조립으로 마련된 것이 바람직한데(도 12에서의 연결거푸집의 조립과 유사한 방식임), 이는 접합부거푸집(200)을 합성기둥의 센터부분(111)에서 용이하게 분리 제거하기 위함이다. Although not shown, the junction die 200 as described above is preferably provided by the assembly of the left segment and the right segment (similar to the assembly of the connection die in Figure 12), which is the junction die 200 to the center of the composite pillar This is for easily separating and removing the portion 111.

도 6 내지 도 13은 본 발명에 따른 거푸집시스템에서의 연결거푸집(300)의 다양한 실시예를 보여주는데, 연결거푸집(300)은 접합부거푸집(200)과 달리 구조형식에 무관하게 1방향 골조용이든 2방향 골조용이든 동일한 것을 적용할 수 있다. 본 발명에 따른 거푸집시스템에서 연결거푸집(300)은, 연결바닥판(310), 연결측면판(330) 및 수평날개(340)를 포함하여 구성되며, 이들 구성들은 일체형으로 마련되는 것은 물론 적절한 조립형으로 마련될 수도 있다. 연결거푸집(300)은 그 자체가 시공하중을 충분히 견딜 수 있도록 충분한 내력을 발휘하는 구조용 강재로 구성함이 바람직하다.6 to 13 show various embodiments of the connecting formwork 300 in the formwork system according to the present invention, the connecting formwork 300 is a two-way frame for two-way regardless of the structure type, unlike the junction formwork 200 The same applies to directional framing. In the formwork system according to the present invention, the connection formwork 300 is configured to include a connection bottom plate 310, a connection side plate 330 and a horizontal wing 340, these components are integrally provided as well as appropriate assembly It may be provided in a form. The connection formwork 300 is preferably composed of structural steel exhibiting sufficient strength to withstand the construction load itself.

연결거푸집(300)에서 연결바닥판(310)은, RC보(120)의 바닥면을 형성하도록 마련된 판형 부재로서, 접합부거푸집의 접합부바닥판(210) 위에 거치되어 접합부바닥판(210) 상호 간을 연결하게 되는 구성이다. 연결거푸집(300)에서 연결측면판(330)은, RC보(120)의 측면을 형성하도록 상기 연결바닥판(310) 양 측 위에 입설된 판형 부재로서, 상기 접합부거푸집의 접합부측면판(230)에 내접하게 배치되어 접합부측면판(230) 상호 간을 연결하게 되는 구성이다. 연결거푸집(300)에서 수평날개(340)는, 연결측면판(330)에서 외향하게 수평으로 마련된 구성으로, 이러한 수평날개(340)는 슬래브바닥판을 거치하기 위한 거치대가 된다. In the connection formwork 300, the connection bottom plate 310 is a plate-shaped member provided to form the bottom surface of the RC beam 120, mounted on the junction bottom plate 210 of the junction formwork, the junction bottom plate 210 mutually This is the configuration to connect. The connection side plate 330 in the connection die 300 is a plate-shaped member placed on both sides of the connection bottom plate 310 to form a side of the RC beam 120, the junction side plate 230 of the junction die It is arranged to be in contact with the junction side plate 230 is a configuration that connects each other. In the connecting die 300, the horizontal wing 340 is configured to be provided horizontally outward from the connecting side plate 330, the horizontal wing 340 is a cradle for mounting the slab bottom plate.

도 6은 기본형의 연결거푸집(300)으로 수평날개(340)가 연결측면판(330) 상단에서 연장된 예를 보여주며, 도 7과 도 8은 RC보(120)를 낮은 춤으로 시공할 경우에 대비하여 기본형의 연결거푸집(300)에서 각각 연결바닥판(310)과 수평날개(340)의 위치를 변경한 예를 보여준다.6 shows an example in which the horizontal blade 340 extends from the upper side of the connecting side plate 330 to the connection die 300 of the basic type, and FIGS. 7 and 8 show the construction of the RC beam 120 in low dance. In contrast, in the connection form 300 of the basic type shows an example of changing the position of the connecting bottom plate 310 and the horizontal wing 340, respectively.

도 9 내지 도 11은 기본형의 연결거푸집을 변형한 예로서 보강수단을 더 마련한 예를 보여주는데, 보강수단은 시공하중에 의한 처짐을 제어하기 위해 내력을 키우는 방식으로 마련된다. 도 9는 연결바닥판(310) 하부면에 연결바닥판(310)의 길이방향을 따라 ⊥자형 보강대(351)를 설치하여 보강한 예이고, 도 10은 수평날개(340)와 연결측면판(330)을 연결하도록 보강리브(352)를 설치하여 보강한 예이고, 도 11은 연결측면판(330)에서 연결바닥판(310)으로 이어지게 하면서 연결측면판(330)과 연결바닥판(310)의 외둘레에 보강띠(353)를 덧대어지게 설치하여 보강한 예이다. 보강수단으로 ⊥자형 보강대(351), 보강리브(352), 보강띠(353)는 서로 조합하여 마련할 수 있는 것은 물론이다.9 to 11 show an example in which a reinforcing means is further provided as an example of a modification of the connection die of the basic type, and the reinforcing means is provided in such a manner as to increase the strength to control the deflection due to the construction load. 9 is an example in which the U-shaped reinforcement 351 is installed in the lower surface of the connection bottom plate 310 along the longitudinal direction of the connection bottom plate 310, and FIG. 10 is a horizontal wing 340 and a connection side plate ( The reinforcing rib 352 is installed to reinforce the 330 to be connected, and FIG. 11 is a connecting side plate 330 and a connecting bottom plate 310 while leading from the connecting side plate 330 to the connecting bottom plate 310. It is an example of reinforcing by installing the reinforcing band (353) padded on the outer circumference of the. As the reinforcing means, the U-shaped reinforcing table 351, the reinforcing rib 352, and the reinforcing band 353 may be provided in combination with each other.

도 12는 조립식의 연결거푸집(300)을 보여주는데, 조립식의 연결거푸집(300)은

Figure 112009013613579-PAT00001
자 단면을 가지는 좌측 세그먼트(300a)와
Figure 112009013613579-PAT00002
자 단면을 가지는 우측 세그먼트(300b) 및
Figure 112009013613579-PAT00003
자 단면을 가지는 가운데 세그먼트(300c)를 적절히 조합하여 완성할 수 있다. 즉, 좌·우측 세그먼트(300a, 300b)만으로 조립하거나, 좌·우측 세그먼트(300a, 300b)와 적절한 개수의 가운데 세그먼트(300c)를 조립하는 것이다. 각 세그먼트(300a, 300b, 300c)의 조립은 서로 맞닿는 하부 수직부분에서 이루어지 게 되며, 이 조립부분은 일종의 보강대가 될 것이다. 특히, 도 12에서와 같이 각 세그먼트(300a, 300b ,300c)가 하부에서 내향하게 수평 연장된 수평리프(L)가 더 마련된 것이라면, 각 세그먼트의 조립으로 연결바닥판(310) 하부에 ⊥자형 보강대(351)가 자연스럽게 마련된다. Figure 12 shows a prefabricated connecting formwork 300, the prefabricated connecting formwork 300
Figure 112009013613579-PAT00001
The left segment 300a having a ruler cross section
Figure 112009013613579-PAT00002
Right segment
300b having a child cross section and
Figure 112009013613579-PAT00003
The center segment 300c having a ruler cross section can be appropriately combined and completed. That is, the left and right segments 300a and 300b are assembled only, or the left and right segments 300a and 300b and an appropriate number of center segments 300c are assembled. The assembly of each segment (300a, 300b, 300c) will be made in the lower vertical portion in contact with each other, this assembly will be a kind of reinforcement. In particular, as shown in Figure 12, if each segment (300a, 300b, 300c) is further provided with a horizontal leaf (L) extending horizontally inwardly from the bottom, the U-shaped reinforcement on the bottom of the connecting bottom plate 310 by the assembly of each segment 351 is naturally provided.

도 13은 수평날개(340)의 단부가 절삭된 연결거푸집(300)을 보여주는데, 이는 2방향 골조용의 거푸집시스템에 바람직하게 적용하기 위해 제안된 형태이다. 다시 말해, 2방향 골조용의 거푸집시스템은 연결거푸집(300)이 2방향으로 인코너를 형성하면서 설치되기 때문에(도 3 참조) 인코너에서 연결거푸집의 수평날개(340)끼리 간섭될 수 있으며, 이에 간섭문제를 미연에 차단하기 위해 수평날개(340)의 단부를 절삭시킨 것이다. Figure 13 shows the connection formwork 300 cut off the end of the horizontal blade 340, which is a form proposed for application to the formwork system for two-way framework. In other words, since the formwork system for the two-way frame is installed while forming the connecting die 300 in two directions (see Fig. 3), the horizontal blades 340 of the connecting formwork at the corner may interfere with each other, and thus interfere with this. In order to block the problem in advance, the end of the horizontal blade 340 is cut.

2. 무지주 역타공법2. Unsupported reverse punching method

도 14와 도 15는 본 발명에 따른 RC역타공법에서 각각 RC보(120) 시공단계와 RC보 시공용 거푸집시스템의 하강단계를 도시하며, 이하 이들 도면을 참고하여 본 발명에 따른 RC역타공법을 단계적으로 설명한다. 14 and 15 illustrate the RC beam 120 construction step and the descending step of the RC beam construction formwork system, respectively, in the RC reverse drilling method according to the present invention. Hereinafter, the RC reverse drilling method according to the present invention will be described with reference to these drawings. Explain step by step.

(a)단계: 흙막이벽 시공Step (a): construct the wall

건축선에 맞춰 흙막이벽을 시공한다. 흙막이벽은 H말뚝과 토류판, CIP, SCW, 시트파일 등은 물론 지하연속벽(슬러리월)으로 시공 가능하다. Construct a wall of mud walls in line with the construction line. The retaining wall can be constructed with H pile, earth plate, CIP, SCW, sheet pile, etc. as well as underground continuous wall (slurry wall).

(b)단계: 합성기둥의 센터부분 시공Step (b): construction of the center part of the composite column

지하구조물의 일부가 되는 내부기둥으로 철골, CFT 또는 PC에 의한 센터부분(111) 주변에 RC부분(112)이 형성되는 합성기둥(110)을 계획하고, 흙막이벽 내부에 합성기둥의 센터부분(111)을 시공한다. 합성기둥의 센터부분(111) 시공은 통상 역타공법에서와 동일하다. 도 14에서는 합성기둥의 센터부분(111)을 H형강으로 시공한 예를 보여준다.As the inner pillar to be a part of the underground structure, the composite pillar 110 is formed around the center portion 111 by the steel frame, CFT or PC, and the composite pillar 110 is formed. 111) Install. The construction of the center portion 111 of the composite column is the same as in the reverse drilling method. 14 shows an example in which the center portion 111 of the composite pillar is constructed of H-beams.

(c)단계; 굴토(c) step; Gulto

흙막이벽 내부 지반을 굴토한다. 굴토깊이는 흙막이벽의 안정적인 지지상태를 고려하면서 실시한다. Excavate the ground inside the retaining wall. The pit depth is carried out considering the stable support of the retaining wall.

(d)단계: RC보 시공용 거푸집시스템 설치Step (d): Formwork System for RC Beam Construction

접합부거푸집의 지지브라켓(220)을 합성기둥의 센터부분(111)에 장착시키면서 RC보 시공용 거푸집시스템을 RC보(120)의 시공 위치에 설치한다. RC보 시공용 거푸집시스템의 설치는, 접합부거푸집(200)이 준비된 상태에서 접합부바닥판의 개구부(211)를 통해 합성기둥의 센터부분(111)에 끼운 후 지지브라켓(220)을 합성기둥의 센터부분(111)에 장착시켜 접합부거푸집(200)을 설치하고, 이어 연결거푸집(300)을 접합부거푸집(200) 위에 거치하여 설치하는 과정으로 진행하면 된다.While mounting the support bracket 220 of the joint formwork to the center portion 111 of the composite column to install the formwork system for RC beam construction at the construction position of the RC beam 120. Installation of the formwork system for RC beam construction, the support bracket 220 is inserted into the center portion 111 of the composite pillar through the opening 211 of the joint bottom plate in the state in which the joint formwork 200 is prepared, and then the support bracket 220 is centered on the composite pillar. Attached to the portion 111 to install the junction die 200, and then proceed to the process of mounting the connection die 300 mounted on the junction die (200).

(e)단계: RC보 및 슬래브 시공Step (e): Construction of RC Beams and Slabs

RC보 시공용 거푸집시스템을 설치하고 나면, RC보 시공용 거푸집시스템 내부에 보철근을 배근하고 보콘크리트를 타설하면서 RC보(120)를 시공한다. RC보 시공용 거푸집시스템이 받는 시공하중은 지지브라켓(220)을 통해 합성기둥의 센터부분(111)으로 전달되어 지지된다. 본 단계를 실시함에 따라 RC보(120)는 합성기둥의 센터부분(111)을 둘러쌈과 동시에 합성기둥의 센터부분(111)을 서로 연결하면서 완성되며, 이로써 RC보(120)는 흙막이벽과 합성기둥의 센터부분(111)을 연결하여 흙막이벽을 지지하는 버팀대가 된다. 상기와 같은 RC보(120)의 흙막이 버팀대로서의 역할을 감안하면 합성기둥의 센터부분(111)에 스터드(142)를 마련하여 합성기둥의 센터부분(111)과 RC보(120)의 일체성을 강화하는 것이 바람직하다. 도 14와 도 15에서는 합성기둥의 센터부분(111)으로 시공한 H형강의 양 플랜지와 양 플랜지를 연결한 보강판(141)에 각각 스터드(142)를 접합한 상태를 확인할 수 있다.After the RC beam construction formwork system is installed, the RC beams 120 are constructed while reinforcing the reinforcement in the RC beam construction formwork system and placing the bocon concrete. The construction load received by the RC beam formwork system is transferred to and supported by the center portion 111 of the composite pillar through the support bracket 220. By performing this step, the RC beam 120 is completed while surrounding the center portion 111 of the composite pillar and connecting the center portion 111 of the composite pillar to each other, whereby the RC beam 120 and the earth wall By connecting the center portion 111 of the synthetic pillar is a brace for supporting the earth wall. Considering the role of the soil barrier of the RC beam 120 as described above, by providing a stud 142 in the center portion 111 of the composite pillar, the integrity of the center portion 111 and the RC beam 120 of the composite pillar It is desirable to strengthen. In FIG. 14 and FIG. 15, it is possible to confirm a state in which the studs 142 are bonded to the reinforcing plates 141 connecting the two flanges and the two flanges of the H-shaped steel constructed by the center portion 111 of the composite column.

아울러 본 단계에서는 RC보(120) 시공과 더불어 슬래브(130)를 시공하도록 하며, 슬래브(130)는 RC보(120)와 일체화되어 흙막이벽을 지지하게 된다. 슬래브시공은 RC보 시공용 거푸집시스템의 수평날개(240, 340)에 슬래브거푸집을 거치하여 설치하고 슬래브콘크리트를 타설하는 과정으로 진행하면 되며, 경우에 따라 슬래브철근을 배근한다. 슬래브시공에서 슬래브거푸집은 슬래브콘크리트 타설 후 탈형하여 제거하는 제거식 거푸집은 물론 철판데크와 같이 영구적으로 존치시키는 영구존치식 거푸집도 채택할 수 있으며, 나아가 슬래브철근이 조립된 상태의 것도 채택할 수 있다. 물론 슬래브시공은 RC보 시공과 더불어 철근 배근과 콘크리트 타설이 한꺼번에 진행할 수 있다.In addition, in this step, the construction of the slab 130 in addition to the construction of the RC beam 120, the slab 130 is integrated with the RC beam 120 to support the retaining wall. Slab construction is installed by mounting the slab formwork on the horizontal wings (240, 340) of the formwork system for RC beam construction, and proceed with the process of placing the slab concrete, if necessary reinforce the slab reinforcement. In slab construction, the slab formwork can adopt not only the removable formwork that demolds and removes after slab concrete casting, but also the permanently positioned formwork that permanently retains, such as iron plate decks, and also the state in which the slab reinforcement is assembled. . Of course, slab construction can be carried out at the same time with RC beam construction and reinforcement and concrete placement.

(f)단계: 반복 실시Step (f): Repeat

상기 (c)단계 내지 (e)단계를 반복 실시한다. 즉, 굴토과정과 RC보(120) 및 슬래브(130) 시공과정을 반복하여 지하구조물의 층간구조체를 완성하는 것이다. 다만, 본 단계 속에서 (d)단계는 접합부거푸집의 지지브라켓(220)을 합성기둥의 센터부분(111)에서 탈락시켜 RC보 시공용 거푸집시스템을 아래층 RC보(120)의 시공 위치로 하강시키면서 실시하도록 한다. 그래야 RC보 시공용 거푸집시스템을 반복적으로 전용할 수 있다. 한편 슬래브거푸집으로 제거식 거푸집을 채택한 경우라면 슬래브거푸집도 탈형하여 RC보 시공용 거푸집시스템과 같이 하강시키도록 하며, 슬래브거푸집으로 영구존치식 거푸집을 채택한 경우라면 RC보 시공용 거푸집시스템을 하강함과 동시에 하강 위치에서 새로운 슬래브거푸집을 설치하도록 한다.Steps (c) to (e) are repeated. In other words, by repeating the construction process of the gulto and RC beam 120 and the slab 130 to complete the interlayer structure of the underground structure. However, step (d) in this step is dropping the support bracket 220 of the joint formwork from the center portion 111 of the composite pillar while lowering the formwork system for RC beam construction to the construction position of the lower beam RC beam 120 Do it. Only then can the RC beam formwork system be repeatedly converted. On the other hand, if the slab formwork adopts the removable formwork, the slab formwork is demoulded and lowered like the RC beam construction formwork. If the slab formwork adopts the permanent zone type formwork, the slab formwork lowers the formwork for the RC beam construction. At the same time, a new slab formwork is installed at the lowered position.

본 단계에서 RC보 시공용 거푸집시스템의 하강은 현수방식을 적용할 수 있는데, 구체적으로 접합부거푸집의 지지브라켓(220)을 현수재(150)로 매단 상태에서 합성기둥의 센터부분(111)에서 탈락시키고 현수재(150)를 내리면서 접합부거푸집의 지지브라켓(220)을 하강시킴에 따라 RC보 시공용 거푸집시스템을 아래층 RC보(120)의 시공 위치로 하강시키는 것이다. 다만 이 경우에 RC보(120) 시공과정은 현수재(150)가 RC보(120)에 구속되지 않게 계획한다. 가령 합성기둥의 센터부분(111)을 H형강으로 시공한다면, 도 15에서와 같이 H형강의 양 플랜지를 보강판(141)으로 연결한 후 현수재(150)가 H형강의 웨브와 보강판(141) 사이의 공간을 통과하도록 계획한다. 도시하지는 않았지만 슬리브(sleeve) 등을 적절히 이용하는 것도 가능 하다. The descent of the formwork system for RC beam construction in this step can be applied to the suspension method, specifically, the support bracket 220 of the joint formwork is suspended from the center portion 111 of the composite column in the suspended state with the suspension member 150. And lowering the suspension bracket 150 while lowering the support bracket 220 of the joint formwork to lower the formwork system for RC beam construction to the construction position of the RC beam 120 downstairs. In this case, however, the construction of the RC beams 120 is planned so that the suspension material 150 is not bound to the RC beams 120. For example, if the center portion 111 of the composite column is constructed of H-shaped steel, as shown in Figure 15, after connecting both flanges of the H-shaped steel to the reinforcement plate 141, the suspension member 150 is the web and the reinforcement plate (H-shaped steel ( Plan to pass through the space between them. Although not shown, a sleeve or the like may be appropriately used.

본 단계를 통해 지하구조물의 층간구조체를 전부 완성한 후에는 RC보 시공용 거푸집시스템을 제거한다.After completing the interlayer structure of the underground structure through this step, the formwork system for RC beam construction is removed.

(g)단계: 합성기둥 완성Step (g): complete the composite column

상기 (f)단계와 동시에 또는 순차적으로 합성기둥의 RC부분(112)을 시공한다. 즉, 합성기둥의 센터부분(111) 주변으로 기둥철근을 배근하고 기둥콘크리트를 타설하면서 합성기둥의 RC부분(112)을 시공하여 합성기둥(110)을 완성하는 것이다.Simultaneously or sequentially with step (f), the RC portion 112 of the synthetic column is constructed. In other words, while constructing the RC column 112 of the synthetic pillar while placing the column reinforcement around the center portion 111 of the synthetic pillar and placing the pillar concrete, the synthetic pillar 110 is completed.

합성기둥의 센터부분(111) 주변으로 이미 RC보(120) 내지 슬래브(130)가 시공되었기 때문에 합성기둥의 RC부분(112)은 층간 분리 시공되는 바, RC보(120) 시공단계에서는 미리 합성기둥의 RC부분(112)의 층간 일체 거동을 위한 대책을 마련하도록 한다. 가령 기둥철근을 연속화하기 위해 이음용 철근을 미리 배근해 놓거나 철근커플러(coupler) 등을 미리 매입하도록 한다. Since the RC beam 120 to the slab 130 have already been constructed around the center portion 111 of the composite pillar, the RC portion 112 of the composite pillar is separated from each other by the bar, and the RC beam 120 is constructed in advance. The countermeasure for interlayer integration of the RC part 112 of the pillar is prepared. For example, in order to continually reinforce column reinforcing bars, the reinforcing bars are pre-arranged or rebar couplers are purchased in advance.

이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.The present invention has been described in detail above with reference to specific embodiments, but the embodiments are only for illustrating the present invention, and thus the embodiments substituted, added, and modified within the scope without departing from the spirit of the present invention are also described below. It will be said to belong to the protection scope of the present invention as defined by the claims appended hereto.

도 1은 종래의 RC역타공법에서 많이 이용되는 거푸집지지틀을 보여준다.Figure 1 shows a formwork supporting frame commonly used in the conventional RC reverse drilling method.

도 2는 본 발명에 따른 'RC역타공법에서의 RC보 시공용 거푸집시스템'의 일 실시예로서 1방향 골조용이 설치된 상태를 도시한다.Figure 2 shows a state in which one-way frame is installed as an embodiment of the 'RC beam construction formwork system in RC reverse drilling method' according to the present invention.

도 3은 본 발명에 따른 'RC역타공법에서의 RC보 시공용 거푸집시스템'의 다른 실시예로서 2방향 골조용을 도시한다.Figure 3 illustrates a two-way frame as another embodiment of the 'RC beam construction formwork system in RC reverse drilling method' according to the present invention.

도 4는 도 2에 따른 RC보 시공용 거푸집시스템에 적용되는 1방향 골조용의 접합부거푸집과 그 설치상태를 도시한다. Figure 4 shows the joint formwork and the installation state of the one-way frame applied to the RC beam construction formwork according to FIG.

도 5는 도 3에 따른 RC보 시공용 거푸집시스템에 적용되는 2방향 골조용의 접합부거푸집을 도시한다. Figure 5 shows the joint formwork for two-way framework applied to the RC beam construction formwork according to FIG.

도 6 내지 도 13은 도 2와 도 3에 따른 RC보 시공용 거푸집시스템에 적용되는 연결거푸집의 다양한 실시예를 도시한다.6 to 13 show various embodiments of the connection formwork applied to the formwork system for RC beam construction according to FIGS. 2 and 3.

도 14는 본 발명에 따른 RC역타공법에서 RC보 시공단계를 도시한다.Figure 14 shows an RC beam construction step in the RC reverse drilling method according to the present invention.

도 15는 본 발명에 따른 RC역타공법에서 RC보 시공용 거푸집시스템의 하강단계를 도시한다.Figure 15 shows the descending stage of the formwork system for RC beam construction in the RC reverse drilling method according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

110: 합성기둥110: composite column

111: 센터부분111: center part

112: RC부분112: RC part

120: RC보120: RC beam

130: 슬래브130: slab

141: 보강판141: gusset

142: 스터드142: stud

150: 현수재150: Suspension

200: 접합부거푸집200: junction die

210: 접합부바닥판210: junction bottom plate

220: 지지브라켓220: support bracket

230: 접합부측면판230: junction side plate

300: 연결거푸집300: connecting die

310: 연결바닥판310: connecting bottom plate

330: 연결측면판330: connecting side plate

340: 수평날개340: horizontal wing

Claims (10)

철골, CFT 또는 PC에 의한 센터부분(111) 주변에 RC부분(112)이 형성되는 합성기둥(110)과 RC보(120)로 설계된 지하구조물을 역타공법으로 시공함에 있어 합성기둥의 센터부분(111)을 시공한 후 합성기둥의 RC부분(112)을 시공하기에 앞서 RC보(120)를 시공하기 위한 거푸집시스템으로,The center part of the composite column in the construction of the underground structure designed by the composite pillar 110 and RC beam 120 formed with the RC section 112 around the center section 111 by steel, CFT or PC by reverse drilling method ( As a formwork system for the construction of the RC beam 120 before the construction of the RC section 112 of the composite pillar after the construction of 111), 합성기둥의 센터부분(111)과 RC보(120)의 접합부를 형성시키기 위한 거푸집으로, 합성기둥의 센터부분(111)에 설치되는 접합부거푸집(200);과,Formwork for forming the junction of the center portion 111 and the RC beam 120 of the composite column, the junction formwork 200 is installed in the center portion 111 of the synthetic column; And, RC보(120)를 형성시키기 위한 거푸집으로, 상기 접합부거푸집(200) 상호 간을 연결하도록 설치되는 연결거푸집(300);을 포함하여 구성되되,Formed to form RC beams 120, the connection dies 200, the connection formwork 300 is installed to connect with each other; configured to include, 상기 접합부거푸집(200)은,The junction die 200, 합성기둥의 센터부분(111) 단면보다 넓은 판면을 가지는 판형 부재로, 가운데에 합성기둥의 센터부분(111)을 통과시키는 개구부(211)가 형성된 접합부바닥판(210);A plate-shaped member having a plate surface wider than a cross section of the center portion 111 of the composite pillar, the junction part bottom plate 210 having an opening 211 through which the center portion 111 of the composite pillar passes; 가운데에 합성기둥의 센터부분(111)을 통과시키는 빈 공간을 남겨둔 채 4개가 +자형으로 배치되어 상기 접합부바닥판(210) 아래에 접합부바닥판(210)을 지지하도록 설치되며, 전부 또는 마주보는 한 쌍만이 합성기둥의 센터부분(111)에 탈착 가능하게 설치되게 되는 지지브라켓(220);The four are arranged in a + shape while leaving an empty space for passing the center portion 111 of the composite pillar in the center, and are installed to support the junction bottom plate 210 under the junction bottom plate 210, and face or face each other. Only one pair of support brackets 220 to be detachably installed in the center portion 111 of the synthetic pillar; 상기 접합부바닥판(210)에서 수직 입설된 판형 부재로, RC보(120)의 시공 방향에 대응하게 마련된 접합부측면판(230);을 포함하여 구성된 것이며,The plate-shaped member vertically placed in the junction bottom plate 210, junction side plate 230 provided corresponding to the construction direction of the RC beam 120; configured to include, 상기 연결거푸집(300)은,The connecting die 300, RC보(120)의 바닥면을 형성하도록 마련된 판형 부재로, 상기 접합부거푸집의 접합부바닥판(210) 위에 거치되어 접합부바닥판(210) 상호 간을 연결하게 되는 연결바닥판(310);A plate-shaped member provided to form a bottom surface of the RC beam 120, the connection bottom plate 310 mounted on the junction bottom plate 210 of the junction part die to connect the junction bottom plate 210 to each other; RC보(120)의 측면을 형성하도록 상기 연결바닥판(310) 양 측에서 수직 입설된 판형 부재로, 상기 접합부거푸집의 접합부측면판(230)에 내접하게 배치되어 접합부측면판(230) 상호 간을 연결하게 되는 연결측면판(330);A plate-shaped member vertically installed at both sides of the connecting bottom plate 310 to form a side surface of the RC beam 120, and is disposed in an indirect contact with the junction side plate 230 of the joint formwork, the junction side plate 230 mutually Connection side plate 330 to be connected; 상기 연결측면판(330)에서 외향하게 수평으로 마련된 수평날개(340);를 포함하여 구성된 것임을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.The formwork system for RC beam construction in the RC reverse drilling method, characterized in that consisting of; comprising; horizontal wing (340) provided horizontally outwardly from the connecting side plate (330). 제1항에서,In claim 1, 상기 접합부거푸집의 접합부바닥판(210)은 개구부(211)가 합성기둥의 센터부분(111)보다 크게 형성된 것이어서 상기 접합부거푸집(200)은 합성기둥의 센터부분(111)에 설치될 때 접합부바닥판의 개구부(211)가 일부 오픈되게 되며,The junction bottom plate 210 of the junction die is an opening 211 is formed larger than the center portion 111 of the composite pillar, so that the junction die 200 is installed in the center portion 111 of the composite pillar Part of the opening 211 will be partially opened, 상기 접합부거푸집(200)은, The junction die 200, 상기 접합부바닥판의 개구부(211)의 일부 오픈된 부분을 덮는 철망바닥판(250);을 더 포함하여 구성된 것임을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.Formwork system for RC beam construction in the RC reverse drilling method, characterized in that it further comprises; wire mesh bottom plate 250 covering a part of the opening portion 211 of the junction bottom plate. 제1항에서,In claim 1, 상기 접합부거푸집의 접합부측면판(230)은,The junction side plate 230 of the junction die, 양 측에서 평행하게 마련되거나,Are parallel to both sides, 네 코너에서 인코너를 형성하면서 마련된 것임을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.Formwork system for RC beam construction in RC reverse drilling method, characterized in that it is prepared by forming the in-corner at four corners. 제1항에서,In claim 1, 상기 접합부거푸집(200)은 좌측 세그먼트와 우측 세그먼트의 조립으로 마련된 것임을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.The joining formwork 200 is a formwork system for RC beam construction in the RC reverse drilling method, characterized in that provided by the assembly of the left segment and the right segment. 제1항에서,In claim 1, 상기 연결거푸집(300)은,The connecting die 300, 연결바닥판(310) 하부면에 연결바닥판(310)의 길이방향을 따라 설치된 ⊥자형 보강대(351);A U-shaped reinforcement 351 installed along the longitudinal direction of the connection bottom plate 310 on the bottom surface of the connection bottom plate 310; 수평날개(340)와 연결측면판(330)을 연결하도록 설치된 보강리브(352);Reinforcing rib 352 is installed to connect the horizontal blade 340 and the connecting side plate 330; 연결측면판(330)에서 연결바닥판(310)으로 이어지게 하면서 연결측면판(330)과 연결바닥판(310)의 외둘레에 덧대어지게 설치된 보강띠(353);A reinforcing band 353 padded on the outer circumference of the connection side plate 330 and the connection bottom plate 310 while leading from the connection side plate 330 to the connection bottom plate 310; 중에서 하나 이상을 더 포함하여 구성된 것임을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.Formwork system for RC beam construction in RC reverse drilling method, characterized in that it comprises one or more of more. 제1항에서,In claim 1, 상기 연결거푸집(300)은,The connecting die 300,
Figure 112009013613579-PAT00004
자 단면을 가지는 좌측 세그먼트(300a)와
Figure 112009013613579-PAT00005
자 단면을 가지는 우측 세그먼트(300b)의 조립으로 마련되거나,
Figure 112009013613579-PAT00004
The left segment 300a having a ruler cross section
Figure 112009013613579-PAT00005
It is provided by the assembly of the right segment 300b having a ruler cross section,
Figure 112009013613579-PAT00006
자 단면을 가지는 좌측 세그먼트(300a)와
Figure 112009013613579-PAT00007
자 단면을 가지는 가운데 세그먼트(300c) 및
Figure 112009013613579-PAT00008
자 단면을 가지는 우측 세그먼트(300b)의 조립으로 마련된 것임을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.
Figure 112009013613579-PAT00006
The left segment 300a having a ruler cross section
Figure 112009013613579-PAT00007
Middle segment 300c having a child cross section and
Figure 112009013613579-PAT00008
Formwork system for RC beam construction in the RC reverse drilling method, characterized in that provided by the assembly of the right segment 300b having a ruler cross section.
제6항에서,In claim 6, 상기 연결거푸집(300)을 구성하는 각 세그먼트(300a, 300b, 300c)는 하부에서 내향하게 수평 연장된 수평리프(L)가 더 마련된 것이어서 상기 연결거푸집의 연결바닥판(310)은 각 세그먼트(300a, 300b, 300c)의 조립으로 하부에 ⊥자형 보강대(351)가 마련되게 되는 것을 특징으로 하는 RC역타공법에서의 RC보 시공용 거푸집시스템.Each segment (300a, 300b, 300c) constituting the connecting die 300 is further provided with a horizontal leaf (L) extending horizontally inwardly from the bottom so that the connecting bottom plate 310 of the connecting die 300 each segment (300a) , 300b, 300c) formwork system for RC beam construction in the RC reverse drilling method, characterized in that the U-shaped reinforcement 351 is provided in the lower portion. 상기 제1항 내지 제7항 중 어느 한 항에 따른 RC보 시공용 거푸집시스템을 이용하면서 RC역타공법으로 건물의 지하부분을 구축하는 방법으로서,As a method of constructing the underground part of the building by RC reverse drilling method using the formwork system for RC beam construction according to any one of claims 1 to 7, (a)흙막이벽을 시공하는 단계;(a) constructing a retaining wall; (b)내부기둥으로 철골, CFT 또는 PC에 의한 센터부분(111) 주변에 RC부분(112)이 형성되는 합성기둥(110)을 계획하고, 흙막이벽 내부에 합성기둥의 센터부분(111)을 시공하는 단계;(b) planning the synthetic column 110, the RC portion 112 is formed around the center portion 111 by the steel frame, CFT or PC as an inner pillar, and the center portion 111 of the synthetic pillar inside the retaining wall Construction step; (c)흙막이벽 내부 지반을 굴토하는 단계;(c) excavating the ground within the retaining wall; (d)접합부거푸집의 지지브라켓(220)을 합성기둥의 센터부분(111)에 장착시키면서 RC보 시공용 거푸집시스템을 RC보(120) 시공위치에 설치하는 단계;(d) installing the formwork system for RC beam construction at the construction site of the RC beam 120 while mounting the support bracket 220 of the bonded formwork to the center portion 111 of the composite pillar; (e)RC보 시공용 거푸집시스템 내부에 보철근을 배근하고 보콘크리트를 타설하면서 RC보(120)를 시공하는 한편, RC보 시공용 거푸집시스템의 수평날개(340)에 슬래브거푸집을 거치하여 설치하고 슬래브콘크리트를 타설하면서 슬래브(130)를 시공하는 단계;(e) Installing the RC beam 120 while placing the reinforcement bar inside the RC beam construction formwork and placing the bore concrete, while installing the slab formwork on the horizontal wing 340 of the RC beam construction formwork system. Constructing the slab 130 while pouring slab concrete; (f)상기 (c)단계 내지 (e)단계를 반복 실시하는 단계;(f) repeating steps (c) to (e); (g)합성기둥의 센터부분(111) 주변으로 기둥철근을 배근하고 기둥콘크리트를 타설하면서 합성기둥의 RC부분(112)을 시공하여 합성기둥(110)을 완성하는 단계;를 포함하여 이루어지되,(g) constructing the RC column 112 of the synthetic pillar while placing the pillar reinforcement around the center portion 111 of the synthetic pillar and placing the pillar concrete to complete the synthetic pillar 110; 상기 (f)단계 속에서 (d)단계는 접합부거푸집의 지지브라켓(220)을 합성기둥 의 센터부분(111)에서 탈락시켜 RC보 시공용 거푸집시스템을 아래층 RC보(120) 시공위치로 하강시키면서 이루어지는 것을 특징으로 하는 RC보 시공용 거푸집시스템을 이용한 RC역타공법.Step (d) in the step (f) dropping the support bracket 220 of the joint formwork from the center portion 111 of the composite column while lowering the formwork system for RC beam construction to the construction site of the lower beam RC beam 120 RC reverse drilling method using the formwork system for RC beam construction, characterized in that made. 제8항에서,In claim 8, 상기 (f)단계 속에서 (d)단계는, 접합부거푸집의 지지브라켓(220)을 현수재(150)로 매단 상태에서 합성기둥의 센터부분(111)에서 탈락시키고 현수재(150)를 내리면서 접합부거푸집의 지지브라켓(220)을 하강시킴에 따라 RC보 시공용 거푸집시스템이 아래층 RC보 시공위치로 하강되도록 이루어지는 것을 특징으로 하는 RC보 시공용 거푸집시스템을 이용한 RC역타공법.Step (d) in the step (f), while the support bracket 220 of the joint formwork suspended from the suspension member 150 in the center portion 111 of the synthetic column while lowering the suspension member 150 RC reverse drilling method using the formwork system for RC beam construction, characterized in that the formwork system for RC beam construction is lowered to the construction site of the RC beam construction as the support bracket 220 of the joint formwork is lowered. 제9항에서,The method of claim 9, 상기 (b)단계는 합성기둥의 센터부분(111)을 H형강으로 시공하면서 이루어지고,The step (b) is made while constructing the center portion 111 of the synthetic column in H-beam, 상기 (e)단계는 RC보(120) 시공위치의 H형강 양 플랜지가 보강판(141)으로 연결된 상태에서 이루어지며,Step (e) is made in a state in which both flanges of the H-beams at the construction position of the RC beam 120 are connected to the reinforcing plate 141, 상기 (f)단계 속에서 (d)단계는 현수재(150)가 H형강의 웨브와 보강판(141) 사이의 공간을 통해 접합부거푸집의 지지브라켓(220)을 매단 상태에서 이루어지는 것을 특징으로 하는 RC보 시공용 거푸집시스템을 이용한 RC역타공법.Step (d) in the step (f) is characterized in that the suspension member 150 is made in the state of hanging the support bracket 220 of the joint formwork through the space between the web and the reinforcement plate 141 of the H-shaped steel RC reverse drilling method using formwork system for RC beam construction.
KR1020090018937A 2009-03-05 2009-03-05 Form system for constructing rc-girder in rc top down method and the rc top down method using the same KR20100100193A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090018937A KR20100100193A (en) 2009-03-05 2009-03-05 Form system for constructing rc-girder in rc top down method and the rc top down method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090018937A KR20100100193A (en) 2009-03-05 2009-03-05 Form system for constructing rc-girder in rc top down method and the rc top down method using the same

Publications (1)

Publication Number Publication Date
KR20100100193A true KR20100100193A (en) 2010-09-15

Family

ID=43006295

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090018937A KR20100100193A (en) 2009-03-05 2009-03-05 Form system for constructing rc-girder in rc top down method and the rc top down method using the same

Country Status (1)

Country Link
KR (1) KR20100100193A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101101182B1 (en) * 2011-08-31 2012-01-03 (주)동하이엔지 Top-down method of underground structure
KR101107567B1 (en) * 2011-01-04 2012-01-25 주식회사 씨엠파트너스건축사사무소 For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
WO2012044091A2 (en) * 2010-09-30 2012-04-05 (주)바로건설기술 Device and method for constructing underground structure
KR101707376B1 (en) * 2016-05-20 2017-02-16 (주)대우건설 Structure for constructing underground structure using composite beams and the construction method thereof
KR20180070813A (en) * 2016-12-19 2018-06-27 주식회사 하이브릭스이앤씨 Wide composite structure for reinforcing the connecting part of girders and column
KR20180112750A (en) * 2018-10-03 2018-10-12 주식회사 하이브릭스이앤씨 Wide composite structure for reinforcing the connecting part of girders and column
KR102158021B1 (en) * 2020-04-07 2020-09-21 주식회사 액트파트너 Joint structure between the steel column with square cross section and the composite girder

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012044091A2 (en) * 2010-09-30 2012-04-05 (주)바로건설기술 Device and method for constructing underground structure
WO2012044091A3 (en) * 2010-09-30 2012-06-21 (주)바로건설기술 Device and method for constructing underground structure
KR101107567B1 (en) * 2011-01-04 2012-01-25 주식회사 씨엠파트너스건축사사무소 For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
KR101101182B1 (en) * 2011-08-31 2012-01-03 (주)동하이엔지 Top-down method of underground structure
KR101707376B1 (en) * 2016-05-20 2017-02-16 (주)대우건설 Structure for constructing underground structure using composite beams and the construction method thereof
KR20180070813A (en) * 2016-12-19 2018-06-27 주식회사 하이브릭스이앤씨 Wide composite structure for reinforcing the connecting part of girders and column
KR20180112750A (en) * 2018-10-03 2018-10-12 주식회사 하이브릭스이앤씨 Wide composite structure for reinforcing the connecting part of girders and column
KR102158021B1 (en) * 2020-04-07 2020-09-21 주식회사 액트파트너 Joint structure between the steel column with square cross section and the composite girder

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR100694503B1 (en) Downward construction system and method for 1-way girder and slab of underground structure
KR20100100193A (en) Form system for constructing rc-girder in rc top down method and the rc top down method using the same
KR20090094555A (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR20090094971A (en) Under ground top-down method
KR20120096605A (en) Bracket support type downward construction system and method
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR101107567B1 (en) For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
KR200417438Y1 (en) Bracket structure for girder and slab construction
JPH08253946A (en) Reverse placing method for concrete of underground structure under road
KR20110004541A (en) Downward construction method of basement applying scf(sliding channel form)
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101187170B1 (en) Application of under pinning method in remodeling
KR100605514B1 (en) Bracket support type downward construction system and construction method using the same
KR20060096706A (en) Deck suspension top-down method of sub-structure
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
KR200398231Y1 (en) 1way-supporting bracket for girder and slab construction
KR101071245B1 (en) Non support downward method using Steel-PC composite girder and the Steel-PC composite girder
KR101008552B1 (en) Tubing system whit wire-rope and tunnelling method thereof
JP2004027609A (en) Construction method for subterranean structure and subterranean structure
KR20100043161A (en) Pillar construction method by layer-built and frame construction method adapting the same
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
KR200390421Y1 (en) Top-down substructure by deck suspension
KR101701495B1 (en) Top-down construction method using steel tube column with horizontal and vertical reinforcement

Legal Events

Date Code Title Description
N231 Notification of change of applicant
WITN Withdrawal due to no request for examination