JP4190112B2 - Construction method of hand-drawn pier - Google Patents

Construction method of hand-drawn pier Download PDF

Info

Publication number
JP4190112B2
JP4190112B2 JP31100599A JP31100599A JP4190112B2 JP 4190112 B2 JP4190112 B2 JP 4190112B2 JP 31100599 A JP31100599 A JP 31100599A JP 31100599 A JP31100599 A JP 31100599A JP 4190112 B2 JP4190112 B2 JP 4190112B2
Authority
JP
Japan
Prior art keywords
girder
pile
pier
hand
guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP31100599A
Other languages
Japanese (ja)
Other versions
JP2001131938A (en
Inventor
正義 松木田
裕紀 深沢
雅喜 高久
裕史 武居
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP31100599A priority Critical patent/JP4190112B2/en
Publication of JP2001131938A publication Critical patent/JP2001131938A/en
Application granted granted Critical
Publication of JP4190112B2 publication Critical patent/JP4190112B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Revetment (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は桟橋の構築方法に関するものである。
【0002】
【従来の技術】
従来の水上に桟橋を構築する場合には、桟橋の基礎となる杭を杭打船で水底に打設した後、この杭に橋桁や床版を設置して桟橋を構築していた。
また陸上では、手延桁と称する桟橋の延長方向に配置した仮設の部材をガイドとして杭を打設した後、この杭に橋桁や床版を設置して桟橋を構築していた。
【0003】
【発明が解決しようとする課題】
前記したような従来の手延式桟橋の構築方法は次のような問題を備えていた。
<イ>水上に桟橋を構築する場合には、杭打船や自己昇降式足場を利用して杭を打設する。そのために波浪や潮位の状況によって施工が妨げられることが多く、工程が不安定であった。
また、水深の浅い所や、沖からの波浪が破砕する海域では杭打船などの作業船の停泊が不可能であるために船を使用した構築を行うことができない。
<ロ>また杭打船は波浪による船体の揺動を避けることができないから、精密な杭の打設位置の設定や、安全作業が困難である。
<ハ>地上に桟橋を構築する方法では、桟橋下部の結構作業に時間を要するとともに、下方での作業が多くなることから、高所作業、足場の設置などの点で安全面で問題があった。
<ニ>桟橋を設置する地盤が岩盤である場合には、事前に削孔を行い、その孔に杭を建て込んでグラウト注入による根固めを行う必要がある。
このような事前掘削のための特別なガイドや、ケーシングパイプの段取り、根固め作業などによって施工費用が上昇することになる。
【0004】
【本発明の目的】
本発明は上記のような問題を改善するためになされたもので、海上では波浪や潮位の影響を受けずに桟橋を構築することができる、手延式桟橋の構築方法を提供することを目的とする。
また本発明は、陸上では桟橋を支える下部の結構作業を簡略化して安全に構築することができる、手延式桟橋の構築方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
上記のような目的を達成するために本発明の手延式桟橋の構築方法は、桟橋の延長方向に配置したクレーン走行桁と、その両側に、桟橋の延長方向に、クレーン走行桁に沿って桟橋の延長方向にスライド可能な手延桁と、手延桁の延長方向の前方に鉛直方向に向けて、ネジ鋼棒によって取り付けたガイド用鋼管とより構成し、ガイド用鋼管内に挿入した杭を、クレーン走行桁上の杭打機によって打設し、杭の打設後にはガイド用鋼管を杭に沿って下降させ、杭とガイド用鋼管を一体化し、新たに打設した杭の頭部に、桟橋の延長方向を横断する方向に、新たな杭頭横断桁を設置し、新たな杭頭横断桁の上に、新たなクレーン走行桁を設置し、手延桁を前進させて、その先端を新たな杭頭横断桁よりも前方に突出させ、その手延桁の前方に新たなガイド用鋼管を取り付けて行う、手延式桟橋の構築方法である。
【0006】
【発明の実施の形態】
以下図面にもとづいて本発明の一実施例を説明する。
【0007】
<イ>クレーン走行桁。
まず桟橋を構築する装置の構成を説明すると、この装置は基本的にはクレーン走行桁1と手延桁2によって構成する。
クレーン走行桁1は、構築すべき桟橋の延長方向に配置する鋼材の桁であり、後述する基礎杭4の間隔との関係では、延長方向に打設した基礎杭4と基礎杭4の間隔に相当する長さを備えていればたりる。
このクレーン走行桁1を、桟橋の延長方向に向けて、2本平行に配置し、その上に杭打機6などを搭載して移動させる。
【0008】
<ロ>手延桁2。
平行に配置した2本のクレーン走行桁1の外側には各々、手延桁2と称する長い桁をスライド自在に取り付ける。
この手延桁2も鋼材の桁であり、後述する基礎杭4の間隔との関係では、延長方向に打設した複数本の基礎杭4の間隔にまたがる長さを備えている。
手延桁2を前方に向けてスライドさせるには、例えばクレーン走行桁1に搭載した杭打機6と手延桁2を連結する。そして杭打機6を前進させれば、手延桁2は桟橋の延長方向にクレーン走行桁1に沿ってスライド可能である。
【0009】
<ハ>ガイド用鋼管5。
各手延桁2の延長方向の前方にはガイド用鋼管5を鉛直方向に向けて取り付ける。
このガイド用鋼管5は長さが基礎杭4に比較して短い中空のパイプ体である。
そして両側のガイド用鋼管5は、桟橋の延長方向と横断する方向の枠体51によって一体に連結する。
ガイド用鋼管5は手延桁2に強固に取り付けるものではなく、ネジ鋼棒によって簡単に取り外しが可能な状態で取り付ける。
さらに手延桁2には、ガイド用鋼管5の取り付け位置とは別の位置に調整ジャッキ52の一端を取り付け、この調整ジャッキ52の他端をガイド用鋼管5に取り付ける。
こうすると調整ジャッキ52の伸縮によって、ガイド用鋼管5の鉛直性を確保することができる。
【0010】
<ニ>施工方法の説明。
次に施工方法について、以下の状態にある桟橋において説明する。
一定間隔で両側に平行に打設した基礎杭4の上には、桟橋の横断方向に杭頭横断桁3が固定してあり、横断桁3の上には桟橋の延長方向に向けて2本のクレーン走行桁1が平行に固定してある。クレーン走行桁1の上には杭打機6を配置してある。
クレーン走行桁1の外側には手延桁2が配置してある。
【0011】
<ホ>基礎杭4の打設。
クレーン走行桁1の上に配置した杭打機6で基礎杭4を吊り上げ、手延桁2の先端のガイド用鋼管5内に挿入する。
この基礎杭4を杭打機6のバイブロハンマーなど公知の手段によって打設する。
前記したように調整ジャッキ52の伸縮によってガイド用鋼管5の鉛直性、あるいは打設角度を確保することができるから、測量によって精度を確保しながらガイド用鋼管5をガイドとして正確な角度で基礎杭4を打設することができる。
なお、最終の打ち込みは油圧ハンマーによって行い、支持力を確認することもできる。
【0012】
<ヘ>岩盤への基礎杭4打ち。
岩盤では直接基礎杭4を打設できない場合がある。
その場合には基礎杭4打ち前に、杭打機6に取り付けたオーガーによって事前削孔しておく方法、あるいはウォータージェットを装備したダミー杭をバイブロハンマーで打設して事前削孔しておく方法を採用することもできる。
この事前削孔作業も、ガイド用鋼管5をガイドとして使用して行うことができるから、打設方向は正確である。
あるいは基礎杭4を盤面に立てておき、その基礎杭4の内部に削孔装置を挿入し、基礎杭4をガイドとして先行削孔することもできる。
あるいは先行削孔に際して、削孔する直径を基礎杭4の外径よりも小さい直径で行い、基礎杭4の外周の地盤を乱さないで行えば、基礎杭4の打設後の根固めグラウトが不要となる。
【0013】
<ト>鋼管の下降。
打設が終了したらガイド用鋼管5をいったん、杭打機6で吊っておく。
その状態で調節ジャッキ52を取り外し、ネジ鋼棒53で吊り直すことで手延桁2から分離する。
そしてネジ鋼棒53を延長することによって、両側の基礎杭4をガイドとして所定の位置までガイド用鋼管5を下降することができる。
所定の位置まで下降したガイド用鋼管5は基礎杭4に仮固定する。
鋼管を基礎杭4に仮固定するには例えば基礎杭4の側面から固定金物を突出させて行うことができる。
【0014】
<チ>鋼管と基礎杭4の一体化。
所定の位置に仮固定したガイド用鋼管5と基礎杭4の間にグラウトを注入して両者を一体化する。
グラウトが両者の間隔から流出しないように、ガイド用鋼管5の下部に鉄板を溶接したり、ゴムシールを取り付ける。
こうして両側の基礎杭4の下部の間を強固に連結して結構作業を完了することができる。
【0015】
<リ>横断桁の設置。
新たに打設し、下部を強固に連結した両側の基礎杭4の頭部に、杭頭横断桁3を設置して溶接する。
この杭頭横断桁3は、両側の基礎杭4の間隔よりも長く形成した鋼製の桁である。
両側の基礎杭4の頭部に設置することから、杭頭横断桁3は、桟橋の延長方向を横断する方向に設置することになる。
杭打機6を使用して、新たに設置した杭頭横断桁3の上に、直交方向に新たなクレーン走行桁1を設置する。
【0016】
<ヌ>手延桁2の前進。
横断桁3の設置が終わったら、手延桁2を連結器などを介してで杭打機6に連結する。
そして杭打機6を前進させれば、手延桁2を前進させることができる。
手延桁2はすでに配置してある横断桁3の上をスライドすることになるが、横断桁3には延長方向に平行なガイド板を複数個所に突設しておくことによって外側への転倒や外れを阻止することができる。
このガイド板はスライドが終了したら手延桁2にボルト止めして安定を図る。
手延桁2が前進することによってその先端は新たな杭頭横断桁3の上を乗り越え、その先端は新たな杭頭横断桁3よりも前方に突出させることができる。
こうして突出した手延桁2の前方に新たなガイド用鋼管5を取り付け、前記した作業を繰り返して桟橋を延長してゆく。
後方に荷役クレーンを設置しておき、このクレーンで鋼床板の敷設、あるいは鉄筋コンクリート、プレキャスト工を行う。
【0017】
<ル>他の実施例。
以上は2本のガイド用鋼管5を使用する構成であったが、2本以上の複数本のガイド用鋼管5を使用することもできる。
また杭頭横断桁3として、その両端に斜め方向のガイド用鋼管を取り付けた桁を使用し、この斜めガイド用鋼管をガイドとして斜基礎杭4を打設することができる。
すると両側に、外側に広がった斜杭を設置した構造の桟橋を構築することができる。
【0018】
【発明の効果】
本発明は上記したようになるから、次のような効果を達成することができる。
<イ>海上での工事の場合に、波浪や潮位の影響を受けることがない。そのために計画的、かつ短期間で桟橋を構築することができる。
<ロ>安定した桟橋上での作業となるので、精密な杭打ち作業を安全確実に実施することができる。
<ハ>先端に設けたガイド用鋼管5をガイドとして基礎杭4を打設するので、基礎杭4の打設角度を正確に維持することができ、精度が大きく向上する。
<ニ>杭打ちのガイドとして利用したガイド用鋼管5を、基礎杭4に沿って下降して固定するだけで下部の結構作業を完成できる。したがって迅速で安全な作業によって基礎杭4群を強固に支持することができる。
<ホ>基礎杭4を岩盤に打設する場合に、グラウト根固め工程が不要となり、コストの削減、工期の短縮を達成できる。
【図面の簡単な説明】
【図1】手延式桟橋の構築状態の正面図。
【図2】その側面図。
【図3】施行順序の説明図。
【図4】施行順序の説明図。
【図5】施行順序の説明図。
【図6】施行順序の説明図。
【図7】施行順序の説明図。
【図8】施行順序の説明図。
【図9】施行順序の説明図。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a pier construction method.
[0002]
[Prior art]
In the case of building a jetty on the conventional water, a pile that forms the foundation of the jetty was placed on the bottom of the water with a pile driving ship, and then a bridge girder and floor slab were installed on the pile to construct the jetty.
On land, a pier was constructed by placing piles and floor slabs on this pile after placing a pile using temporary members arranged in the extension direction of the pier called a manual girder as a guide.
[0003]
[Problems to be solved by the invention]
The conventional method for constructing a hand-drawn pier as described above has the following problems.
<I> When building a pier on the water, piles are laid using a pile driving ship or a self-lifting scaffold. For this reason, construction was often hindered by wave and tide conditions, and the process was unstable.
In addition, it is impossible to construct a ship using a ship because it is impossible to anchor a working ship such as a pile driving ship in a shallow water area or in a sea area where waves from offshore are crushed.
<B> In addition, since a pile driving ship cannot avoid the rocking of the hull due to waves, it is difficult to set a precise setting position of the pile and to perform safety work.
<C> The method of building a jetty on the ground requires time for the work at the bottom of the jetty and requires a lot of work at the bottom, so there are problems in terms of safety in terms of work at high places and installation of scaffolding. It was.
<D> If the ground on which the pier is installed is rock, it is necessary to drill holes in advance, build a pile in the hole, and solidify by grouting.
The construction cost increases due to such special guides for pre-digging, setup of casing pipes, and solidification work.
[0004]
[Object of the present invention]
The present invention was made to improve the above problems, and an object thereof is to provide a construction method of a hand-drawn pier that can build a pier without being affected by waves and tides at sea. And
Another object of the present invention is to provide a construction method of a hand-drawn pier that can be safely constructed by simplifying the construction work of the lower part that supports the pier on land.
[0005]
[Means for Solving the Problems]
In order to achieve the above-described object, the construction method of the hand-drawn pier according to the present invention includes a crane traveling girder arranged in the extending direction of the pier, and on both sides of the traveling girder in the extending direction of the pier along the crane traveling girder. A pile made up of a guide girder slidable in the extension direction of the pier and a guide steel pipe attached with a threaded steel rod in the vertical direction in front of the extension direction of the guide girder, and inserted into the guide steel pipe Is driven by a pile driving machine on a crane traveling girder, and after the pile is driven , the guide steel pipe is lowered along the pile, the pile and the guide steel pipe are integrated, and the head of the newly driven pile In addition, a new pile head crossing girder is installed in the direction crossing the extension direction of the pier, a new crane traveling girder is installed on the new pile head crossing girder, and the hand girder is advanced. The tip protrudes ahead of the new pile head crossing girder, and new in front of the hand girder Performing the guiding steel attached, a method of constructing Tenobeshiki pier.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
An embodiment of the present invention will be described below with reference to the drawings.
[0007]
<A> Crane traveling girder.
First, the structure of the apparatus for constructing the pier will be described. This apparatus is basically composed of a crane traveling girder 1 and a manual girder 2.
The crane traveling girder 1 is a steel girder arranged in the extending direction of the pier to be constructed. In relation to the interval between the foundation piles 4 to be described later, the distance between the foundation pile 4 and the foundation pile 4 placed in the extending direction is as follows. If you have a corresponding length.
Two crane traveling girders 1 are arranged in parallel in the extending direction of the jetty, and a pile driving machine 6 or the like is mounted thereon and moved.
[0008]
<B> Hand girder 2.
A long girder called a manual girder 2 is slidably attached to the outside of the two crane traveling girders 1 arranged in parallel.
The hand girders 2 are also steel girders, and have a length that spans the intervals of a plurality of foundation piles 4 placed in the extending direction in relation to the intervals of the foundation piles 4 described later.
In order to slide the hand girder 2 forward, for example, the pile driving machine 6 mounted on the crane traveling girder 1 and the hand girder 2 are connected. And if the pile driving machine 6 is advanced, the hand girder 2 can slide along the crane traveling girder 1 in the extension direction of the pier.
[0009]
<C> Guide steel pipe 5.
A guide steel pipe 5 is attached in the vertical direction in front of each extension girder 2 in the extending direction.
The guide steel pipe 5 is a hollow pipe body having a length shorter than that of the foundation pile 4.
The guide steel pipes 5 on both sides are integrally connected by a frame body 51 in a direction crossing the extending direction of the pier.
The guide steel pipe 5 is not firmly attached to the hand girders 2 but is attached in a state where it can be easily removed by a threaded steel bar.
Furthermore, one end of the adjustment jack 52 is attached to the manual girder 2 at a position different from the attachment position of the guide steel pipe 5, and the other end of the adjustment jack 52 is attached to the guide steel pipe 5.
In this way, the verticality of the guide steel pipe 5 can be ensured by the expansion and contraction of the adjustment jack 52.
[0010]
<D> Explanation of construction method.
Next, the construction method will be described in the pier in the following state.
A pile head crossing girder 3 is fixed in the crossing direction of the pier on the foundation pile 4 that is driven in parallel at both sides at regular intervals, and two pieces are placed on the crossing girder 3 in the extending direction of the pier. The crane traveling beam 1 is fixed in parallel. A pile driver 6 is arranged on the crane traveling beam 1.
On the outside of the crane traveling girder 1, a manual girder 2 is arranged.
[0011]
<E> Placement of foundation pile 4
The foundation pile 4 is lifted by a pile driving machine 6 disposed on the crane traveling girder 1 and inserted into the guide steel pipe 5 at the tip of the hand-grown girder 2.
The foundation pile 4 is driven by a known means such as a vibro hammer of the pile driving machine 6.
As described above, the verticality of the guide steel pipe 5 or the placement angle can be ensured by the expansion and contraction of the adjustment jack 52. Therefore, the foundation pile is formed at an accurate angle using the guide steel pipe 5 as a guide while ensuring accuracy by surveying. 4 can be placed.
The final driving can be performed with a hydraulic hammer to check the supporting force.
[0012]
<F> 4 piles of foundation piles to bedrock.
In some cases, the foundation pile 4 cannot be placed directly on the bedrock.
In that case, before the foundation pile 4 is driven, a method of pre-drilling with an auger attached to the pile driving machine 6 or a dummy pile equipped with a water jet is driven with a vibro hammer and pre-drilled. The method can also be adopted.
Since this pre-drilling operation can also be performed using the guide steel pipe 5 as a guide, the placing direction is accurate.
Alternatively, the foundation pile 4 can be erected on the board surface, a drilling device can be inserted into the foundation pile 4, and the foundation pile 4 can be used as a guide to make a previous drilling.
Alternatively, in the case of preceding drilling, if the diameter to be drilled is smaller than the outer diameter of the foundation pile 4 and the ground on the outer periphery of the foundation pile 4 is not disturbed, the rooting grout after placement of the foundation pile 4 can be obtained. It becomes unnecessary.
[0013]
<G> Lowering of the steel pipe.
When the placement is finished, the guide steel pipe 5 is once suspended by the pile driving machine 6.
In this state, the adjustment jack 52 is removed, and it is separated from the hand girder 2 by suspending it with the threaded steel rod 53.
By extending the threaded steel rod 53, the guide steel pipe 5 can be lowered to a predetermined position using the foundation piles 4 on both sides as guides.
The guide steel pipe 5 lowered to a predetermined position is temporarily fixed to the foundation pile 4.
In order to temporarily fix the steel pipe to the foundation pile 4, for example, a fixed hardware can be projected from the side surface of the foundation pile 4.
[0014]
<H> Integration of steel pipe and foundation pile 4.
A grout is injected between the guide steel pipe 5 and the foundation pile 4 temporarily fixed at a predetermined position to integrate both.
An iron plate is welded to the lower part of the guide steel pipe 5 or a rubber seal is attached so that the grout does not flow out from the gap between the two.
Thus, the lower part of the foundation piles 4 on both sides can be firmly connected to complete the work.
[0015]
<Re> Installation of crossing girders.
The pile head crossing girder 3 is installed and welded to the heads of the foundation piles 4 on both sides which are newly placed and firmly connected at the lower part.
This pile head crossing girder 3 is a steel girder formed longer than the interval between the foundation piles 4 on both sides.
Since it installs in the head of the foundation pile 4 of both sides, the pile head crossing girder 3 will be installed in the direction which crosses the extension direction of a pier.
A new crane traveling girder 1 is installed in the orthogonal direction on the newly installed pile head crossing girder 3 using the pile driving machine 6.
[0016]
<Nu> Advance the hand girder 2.
When the installation of the crossing girder 3 is finished, the manual girder 2 is connected to the pile driving machine 6 via a coupler or the like.
And if the pile driving machine 6 is advanced, the manual girder 2 can be advanced.
The hand girder 2 slides on the crossing girder 3 which has already been arranged, but the crossing girder 3 falls outward by projecting a plurality of guide plates parallel to the extending direction. Can be prevented.
When the slide is finished, this guide plate is bolted to the manual extension girder 2 for stability.
As the hand girder 2 moves forward, its tip can ride over the new pile head crossing girder 3, and its tip can protrude forward from the new pile head crossing girder 3.
A new guide steel pipe 5 is attached in front of the protruding girder 2 protruding in this manner, and the pier is extended by repeating the above-described operation.
A cargo handling crane is installed at the rear, and steel cranes are laid, or reinforced concrete and precast are used with this crane.
[0017]
<Le> Other embodiments.
The above is a configuration in which two guide steel pipes 5 are used, but two or more guide steel pipes 5 can also be used.
Further, as the pile head crossing girder 3, a girder having a steel pipe for oblique guide attached to both ends thereof can be used, and the diagonal foundation pile 4 can be driven using the steel pipe for oblique guide as a guide.
Then, on both sides, a pier with a structure with diagonal piles spreading outwards can be constructed.
[0018]
【The invention's effect】
Since the present invention is as described above, the following effects can be achieved.
<A> In the case of construction at sea, it is not affected by waves or tide levels. Therefore, the jetty can be constructed in a planned and short time.
<B> Since the work is performed on a stable pier, precise pile driving work can be carried out safely and reliably.
<C> Since the foundation pile 4 is driven using the guide steel pipe 5 provided at the tip as a guide, the setting angle of the foundation pile 4 can be accurately maintained, and the accuracy is greatly improved.
<D> Just by lowering and fixing the guide steel pipe 5 used as a guide for pile driving along the foundation pile 4, the lower part can be completed. Therefore, the foundation pile 4 group can be firmly supported by quick and safe work.
<E> When the foundation pile 4 is placed on the bedrock, the grout consolidation process is not required, and the cost can be reduced and the construction period can be shortened.
[Brief description of the drawings]
FIG. 1 is a front view of a hand-drawn pier constructed.
FIG. 2 is a side view thereof.
FIG. 3 is an explanatory diagram of an enforcement order.
FIG. 4 is an explanatory diagram of an enforcement order.
FIG. 5 is an explanatory diagram of an enforcement order.
FIG. 6 is an explanatory diagram of an enforcement order.
FIG. 7 is an explanatory diagram of an enforcement order.
FIG. 8 is an explanatory diagram of an enforcement order.
FIG. 9 is an explanatory diagram of an enforcement order.

Claims (3)

桟橋の延長方向に配置したクレーン走行桁と、
その両側に、桟橋の延長方向に、クレーン走行桁に沿って桟橋の延長方向にスライド可能な手延桁と、
手延桁の延長方向の前方に鉛直方向に向けて、ネジ鋼棒によって取り付けたガイド用鋼管とより構成し、
ガイド用鋼管内に挿入した杭を、クレーン走行桁上の杭打機によって打設し、
杭の打設後にはガイド用鋼管を杭に沿って下降させ、
杭とガイド用鋼管を一体化し、
新たに打設した杭の頭部に、桟橋の延長方向を横断する方向に、新たな杭頭横断桁を設置し、
新たな杭頭横断桁の上に、新たなクレーン走行桁を設置し、
手延桁を前進させて、その先端を新たな杭頭横断桁よりも前方に突出させ、
その手延桁の前方に新たなガイド用鋼管を取り付けて行う、
手延式桟橋の構築方法。
Crane traveling girder arranged in the extension direction of the pier,
On both sides, a hand girder that can slide in the extension direction of the pier, along the crane traveling girder in the extension direction of the pier,
It consists of a steel pipe for guides attached with a threaded steel rod in the vertical direction forward of the extension direction of the hand girder,
The pile inserted in the guide steel pipe is driven by a pile driver on the crane traveling beam,
After placing the pile, lower the guide steel pipe along the pile,
Integrate piles and guide steel pipes,
A new pile head crossing girder is installed in the direction of crossing the extension direction of the pier on the head of the newly piled pile,
Install a new crane traveling girder on the new pile head crossing girder,
Advance the hand girder and make its tip protrude more forward than the new pile head crossing girder,
Install a new guide steel pipe in front of the hand girder,
How to construct a hand-drawn pier.
ガイド用鋼管は、手延桁の前方に二本以上を取り付け、
かつ両ガイド用鋼管は、桟橋の延長方向と横断する方向の枠材によって接続する、
請求項1記載の手延式桟橋の構築方法。
At least two guide pipes are installed in front of the hand girders.
And the guide for the steel pipe is connected by the direction of the frame member to cross the extending direction of the pier,
The construction method of the hand-drawn pier according to claim 1.
ガイド用鋼管をガイドとして、ジェット装置を下降させて地盤に削孔し、
削孔後の孔内に杭を打設する、
請求項1、2記載の手延式桟橋の構築方法。
Using the guide steel pipe as a guide, lower the jet device to drill holes in the ground,
Pile a pile in the hole after drilling,
The construction method of the hand-drawn type jetty according to claim 1 or 2.
JP31100599A 1999-11-01 1999-11-01 Construction method of hand-drawn pier Expired - Fee Related JP4190112B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31100599A JP4190112B2 (en) 1999-11-01 1999-11-01 Construction method of hand-drawn pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31100599A JP4190112B2 (en) 1999-11-01 1999-11-01 Construction method of hand-drawn pier

Publications (2)

Publication Number Publication Date
JP2001131938A JP2001131938A (en) 2001-05-15
JP4190112B2 true JP4190112B2 (en) 2008-12-03

Family

ID=18011988

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31100599A Expired - Fee Related JP4190112B2 (en) 1999-11-01 1999-11-01 Construction method of hand-drawn pier

Country Status (1)

Country Link
JP (1) JP4190112B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101192052B1 (en) 2011-01-18 2012-10-17 주식회사 벤트코리아 Method for constructing temporary bridge using movable boxgirder
JP6387321B2 (en) * 2015-04-14 2018-09-05 新日鉄住金エンジニアリング株式会社 How to build a bridge
JP6007307B1 (en) * 2015-12-21 2016-10-12 株式会社横山基礎工事 How to build a bridge
KR101744437B1 (en) * 2016-02-23 2017-06-07 이종란 Construction method of temporary bridge using camber
JP5977904B1 (en) * 2016-04-13 2016-08-24 ヒロセ株式会社 Construction method of simple temporary bridge
JP6034531B1 (en) * 2016-08-03 2016-11-30 ヒロセ株式会社 Construction method of simple temporary bridge
JP7437270B2 (en) 2020-08-31 2024-02-22 鹿島建設株式会社 Bridge construction method
CN115262362A (en) * 2022-07-26 2022-11-01 中国港湾工程有限责任公司 Full-hall type steel trestle and construction method thereof
CN115387240A (en) * 2022-09-20 2022-11-25 中国铁建重工集团股份有限公司 High-efficient pore-forming device of bridge fabrication machine pile foundation construction

Also Published As

Publication number Publication date
JP2001131938A (en) 2001-05-15

Similar Documents

Publication Publication Date Title
CN105386408B (en) Deep-water bridge pile foundation construction method
WO2020114523A1 (en) Double-wall cofferdam and pier construction method
CN107700366B (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN101696578A (en) Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway
CN106930277A (en) A kind of construction of manual-excavation cast-in-place pile method
JP6681148B2 (en) Bridge construction method, pillars and guide means used in the bridge construction method
JP4190112B2 (en) Construction method of hand-drawn pier
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN109989407B (en) Roadbed pile tube curtain supporting structure behind newly-added two-line platform of railway
CN113293708B (en) Method for mounting and dismounting through type steel pipe pile foundation of underwater cast-in-place beam support
WO2023207250A1 (en) Construction method for rapidly driving trestle steel pipe pile into sloped bare rock
CN110847047B (en) Open sea bare rock trestle construction method
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN114411721B (en) Replacement construction method for steel trestle bridge forming and then anchoring steel pipe pile
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
CN209958372U (en) Railway newly-added second-line platform back way foundation pile pipe curtain supporting structure
CN211312225U (en) Pile-column integrated structure based on bridge transformed from existing road surface
KR100819379B1 (en) Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction
CN219930699U (en) Shallow thin cover layer steel trestle
CN215051970U (en) Steel trestle structure of deep water bare rock stratum river channel
KR102392517B1 (en) Top-down method using by double beam system
CN207452669U (en) The naked simple trestle of rock river bed of hard stone based on steel buttress anchor pile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060906

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080502

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080527

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080724

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080826

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080916

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110926

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120926

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130926

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees