JP5661011B2 - Manufacturing method of superstructure for bridge, bridge and superstructure for bridge - Google Patents

Manufacturing method of superstructure for bridge, bridge and superstructure for bridge Download PDF

Info

Publication number
JP5661011B2
JP5661011B2 JP2011205287A JP2011205287A JP5661011B2 JP 5661011 B2 JP5661011 B2 JP 5661011B2 JP 2011205287 A JP2011205287 A JP 2011205287A JP 2011205287 A JP2011205287 A JP 2011205287A JP 5661011 B2 JP5661011 B2 JP 5661011B2
Authority
JP
Japan
Prior art keywords
head fixing
pile head
fixing member
pile
main girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011205287A
Other languages
Japanese (ja)
Other versions
JP2012207516A (en
Inventor
広茂 高野
広茂 高野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kochi Marutaka KK
Original Assignee
Kochi Marutaka KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kochi Marutaka KK filed Critical Kochi Marutaka KK
Priority to JP2011205287A priority Critical patent/JP5661011B2/en
Publication of JP2012207516A publication Critical patent/JP2012207516A/en
Application granted granted Critical
Publication of JP5661011B2 publication Critical patent/JP5661011B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、橋梁及びその施工時に用いる上部工に関するものであり、特に橋梁の強度を高めるものに関するものである。 The present invention relates to a bridge and a superstructure used at the time of construction thereof , and particularly relates to a bridge that increases the strength of the bridge.

従来の上部工を用いる橋梁の施工方法である杭式桟橋の施工方法について図18を用いて説明する。杭頭固定用管4が予め設置された桟橋未完成部分の主桁1を桟橋完成部分から片持ち状に張り出し、当該桟橋未完成部分の主桁1に沿って当該主桁1の張り出し先端部と桟橋完成部分との間にかけ渡された線材2を、当該主桁1と平行になるように張力調整することによって当該主桁1の方向や角度、あるいは歪み状態を完成状態に近づくように調整保持する。これにより、当該主桁1に取り付けられている杭頭固定用管4の位置を完成状態に近づけて、その杭頭固定用管4を介して管状杭5を杭打ちする。また、杭頭固定用管4が取り付けられている横桁3と主桁1とを周方向に回転可能な二重管構造で接続する。これにより、主桁1と杭頭固定用管との角度変化に対応して部品の種類を低減し、コストダウンを図ることができる。   The construction method of the pile type pier which is the construction method of the bridge using the conventional superstructure is demonstrated using FIG. The main girder 1 of the unfinished pier where the pile head fixing pipe 4 has been installed in advance is cantilevered from the completed part of the pier, and the projecting tip of the main girder 1 extends along the main girder 1 of the unfinished pier By adjusting the tension of the wire 2 passed between the bridge and the completed part of the jetty so that it is parallel to the main girder 1, the direction, angle, or distortion state of the main girder 1 is adjusted to approach the completed state. Hold. Thereby, the position of the pipe head fixing pipe 4 attached to the main girder 1 is brought close to the completed state, and the tubular pile 5 is driven through the pile head fixing pipe 4. Moreover, the cross beam 3 to which the pile head fixing pipe 4 is attached and the main beam 1 are connected by a double pipe structure that can rotate in the circumferential direction. Thereby, the kind of components can be reduced corresponding to the angle change with the main girder 1 and the pile head fixing pipe, and cost reduction can be aimed at.

特開2000−96582号公報JP 2000-96582 A

しかしながら、前述の従来の杭式桟橋の施工方法には、以下に示すような改善すべき点がある。従来の杭式桟橋の施工方法では、図18(b)に示すように、杭頭固定用管4の上面P4と覆工板6との間に間隔が生じている。このため、杭頭固定用管4上に配置される天蓋(図示せず)によってのみ、管状杭5からの突き上げと上部工自身の荷重とを保持しなければならない。このため、杭式桟橋の強度をさらに高めることが難しいという改善すべき点がある。   However, the above-described conventional method for constructing a pile jetty has the following points to be improved. In the conventional method for constructing a pile-type pier, as shown in FIG. 18 (b), an interval is generated between the upper surface P 4 of the pile head fixing pipe 4 and the lining plate 6. For this reason, only the canopy (not shown) arrange | positioned on the pipe 4 for pipe head fixing must hold | maintain the thrust from the tubular pile 5, and the load of superstructure itself. For this reason, there is a point to be improved that it is difficult to further increase the strength of the pile-type jetty.

本発明は、施工が容易で、高い強度の橋梁を施工することができる橋梁の施工の際に使用する上部工の提供を目的とする。 An object of the present invention is to provide an upper work to be used in the construction of a bridge that is easy to construct and can construct a high-strength bridge.

本発明に係る上部工の製造方法は、杭部材、及び、主桁、横桁及び杭頭固定部材を結合した上部工を製造するための上部工製造方法であって、
前記主桁は相対的に短い主桁及び相対的に長い主桁とからなり、
前記杭頭固定部材は、前記杭部材を挿通できる円筒部と、前記円筒部の一端に配置されるフランジ部と、該杭頭固定部材の中心から放射状に配置されるリブ部を有し、前記リブ部は前記円筒部の側面及び前記フランジ部に接合され、
前記円筒部及び前記フランジ部の内径は、前記杭部材の外径に略等しく、
前記杭頭固定部材の上面が前記上部工の上に配置される床版と直接的又は前記杭頭固定部材の上面を閉じる天蓋を介して間接的に接し、前記杭頭固定部材の上面が前記杭頭固定部材に挿通したときの前記杭部材の中心軸に対して垂直となるように、全ての前記杭頭固定部材の円筒部の中心が前記主桁の長手方向の中心軸と前記横桁の長手方向の中心軸との交点上に位置するように前記主桁及び前記横桁を前記杭頭固定部材の側面に結合する工程と、前記短い主桁を平坦となるように配置し、前記短い主桁の間に長い主桁を斜めに配置する工程により、前記杭頭固定部材と前記短い主桁からなる平坦な部分と前記長い主桁に沿う斜め部分とが交互に配置される傾斜面を形成し、前記主桁及び前記横桁が矩形状、梯子状、又はコの字状に配置された上部工を得ること、を特徴とする。
The superstructure manufacturing method according to the present invention is a superstructure manufacturing method for manufacturing a superstructure combining a pile member, and a main girder, a cross girder, and a pile head fixing member,
The main girder consists of a relatively short main girder and a relatively long main girder,
The pile head fixing member has a cylindrical portion through which the pile member can be inserted, a flange portion arranged at one end of the cylindrical portion, and a rib portion arranged radially from the center of the pile head fixing member, The rib portion is joined to the side surface of the cylindrical portion and the flange portion,
The inner diameter of the cylindrical portion and the flange portion is substantially equal to the outer diameter of the pile member,
The upper surface of the pile head fixing member is in direct contact with a floor slab disposed on the superstructure or indirectly through a canopy that closes the upper surface of the pile head fixing member, and the upper surface of the pile head fixing member is The center of the cylindrical portion of all the pile head fixing members is the central axis in the longitudinal direction of the main girder and the cross beam so that it is perpendicular to the central axis of the pile member when inserted into the pile head fixing member Connecting the main girder and the cross girder to the side surface of the pile head fixing member so as to be located on the intersection with the central axis in the longitudinal direction of the pile, and arranging the short main girder so as to be flat, An inclined surface in which a long main girder is diagonally arranged between short main girders, and the pile head fixing member, the flat portion composed of the short main girder, and the oblique portion along the long main girder are alternately arranged. forming, said main beam and said crossbeam is rectangular, are arranged in a ladder-like or U-shaped To obtain the superstructure, characterized by.

本発明に係る橋梁は、杭部材、及び、主桁、横桁及び杭頭固定部材を結合した上部工を有する橋梁であって、
前記主桁は相対的に短い主桁及び相対的に長い主桁とからなり、
前記杭頭固定部材は、前記杭部材を挿通できる円筒部と、前記円筒部の一端に配置されるフランジ部と、該杭頭固定部材の中心から放射状に配置されるリブ部を有し、前記リブ部は前記円筒部の側面及び前記フランジ部に接合され、
前記円筒部及び前記フランジ部の内径は、前記杭部材の外径に略等しく、
前記上部工は、
全ての前記杭頭固定部材の円筒部の中心が前記主桁の長手方向の中心軸と前記横桁の長手方向の中心軸との交点上に位置するように前記主桁及び前記横桁を前記杭頭固定部材の側面に結合すること、及び前記短い主桁を平坦となるように配置し、前記短い主桁の間に長い主桁を斜めに配置することにより、前記主桁及び前記横桁が矩形状、梯子状、又はコの字状に配置されること、前記杭頭固定部材の上面が前記上部工の上に配置される床版と直接的又は前記杭頭固定部材の上面を閉じる天蓋を介して間接的に接し、前記杭頭固定部材の上面が前記杭頭固定部材に挿通したときの前記杭部材の中心軸に対して垂直であること、そして前記杭頭固定部材と前記短い主桁からなる平坦な部分と前記長い主桁に沿う斜め部分とが交互に配置される傾斜面であること、を特徴とする。
The bridge according to the present invention is a bridge having a pile member, and a superstructure combining a main girder, a cross girder, and a pile head fixing member,
The main girder consists of a relatively short main girder and a relatively long main girder,
The pile head fixing member has a cylindrical portion through which the pile member can be inserted, a flange portion arranged at one end of the cylindrical portion, and a rib portion arranged radially from the center of the pile head fixing member, The rib portion is joined to the side surface of the cylindrical portion and the flange portion,
The inner diameter of the cylindrical portion and the flange portion is substantially equal to the outer diameter of the pile member,
The superstructure is
The main girders and the cross beams are arranged so that the centers of the cylindrical portions of all the pile head fixing members are located on the intersections between the longitudinal central axis of the main girders and the longitudinal central axis of the cross girders. The main girder and the cross girder are connected to the side surface of the pile head fixing member , and the short main girder is arranged to be flat, and the long main girder is arranged obliquely between the short main girder. Is arranged in a rectangular shape, a ladder shape, or a U-shape, and the upper surface of the pile head fixing member is directly closed with the floor slab disposed on the upper work or the upper surface of the pile head fixing member. Indirect contact with the canopy, and the upper surface of the pile head fixing member is perpendicular to the central axis of the pile member when inserted through the pile head fixing member, and the pile head fixing member and the short Inclinations in which flat portions of main girders and oblique portions along the long main girders are alternately arranged It is a surface, characterized by.

本発明に係る上部工は、杭部材、及び、主桁、横桁及び前記杭部材を挿通できる円筒部を有する杭頭固定部材を結合した上部工であって、
前記主桁は相対的に短い主桁及び相対的に長い主桁とからなり、
前記杭頭固定部材は、前記円筒部の一端に配置されるフランジ部と、該杭頭固定部材の中心から放射状に配置されるリブ部を有し、
前記リブ部は前記円筒部の側面及び前記フランジ部に接合され、
前記円筒部及び前記フランジ部の内径は、前記杭部材の外径に略等しく、
全ての前記杭頭固定部材の円筒部の中心が前記主桁の長手方向の中心軸と前記横桁の長手方向の中心軸との交点上に位置するように前記主桁及び前記横桁を前記杭頭固定部材の側面に結合すること、及び前記短い主桁を平坦となるように配置し、前記短い主桁の間に長い主桁を斜めに配置することにより、前記主桁及び前記横桁を矩形状、梯子状、又はコの字状に配置し、前記杭頭固定部材の上面が前記上部工の上に配置される床版と直接的又は前記杭頭固定部材の上面を閉じる天蓋を介して間接的に接し、前記杭頭固定部材の上面が前記杭頭固定部材に挿通したときの前記杭部材の中心軸に対して垂直であること、そして前記杭頭固定部材と前記短い主桁からなる平坦な部分と前記長い主桁に沿う斜め部分とが交互に配置される傾斜面であること、を特徴とする。
The superstructure according to the present invention is a superstructure that combines a pile head and a pile head fixing member having a cylindrical portion into which a main girder, a cross girder, and the pile member can be inserted,
The main girder consists of a relatively short main girder and a relatively long main girder,
The pile head fixing member has a flange portion arranged at one end of the cylindrical portion, and a rib portion arranged radially from the center of the pile head fixing member,
The rib portion is joined to the side surface of the cylindrical portion and the flange portion,
The inner diameter of the cylindrical portion and the flange portion is substantially equal to the outer diameter of the pile member,
The main girders and the cross beams are arranged so that the centers of the cylindrical portions of all the pile head fixing members are located on the intersections between the longitudinal central axis of the main girders and the longitudinal central axis of the cross girders. The main girder and the cross girder are connected to the side surface of the pile head fixing member , and the short main girder is arranged to be flat, and the long main girder is arranged obliquely between the short main girder. Are placed in a rectangular shape, a ladder shape, or a U-shape, and a canopy that directly or directly closes the top surface of the pile head fixing member and a floor slab on which the upper surface of the pile head fixing member is disposed on the superstructure Indirectly through the pile head fixing member, the upper surface of the pile head fixing member being perpendicular to the central axis of the pile member when the pile head fixing member is inserted, and the pile head fixing member and the short main girder Are inclined surfaces in which flat portions made of and oblique portions along the long main girder are alternately arranged. It features a.

本発明に係る上部工の製造方法によれば、杭頭固定部材の上面を直接的又は間接的に床版によって閉じることができる。よって、床版の荷重を杭頭固定部材に挿通した杭部材の突き上げの力に対向させることができる。よって、橋梁の強度を高めることができる。また、管状の杭頭固定部材の上面が杭部材の中心軸に対して垂直であるので、杭部材を容易に杭頭固定部材に挿通することができる。よって、橋梁の施工を容易にできる。   According to the manufacturing method of the superstructure which concerns on this invention, the upper surface of a pile head fixing member can be closed by a floor slab directly or indirectly. Therefore, the load of the floor slab can be made to oppose the pushing-up force of the pile member inserted through the pile head fixing member. Therefore, the strength of the bridge can be increased. Moreover, since the upper surface of the tubular pile head fixing member is perpendicular to the central axis of the pile member, the pile member can be easily inserted into the pile head fixing member. Therefore, bridge construction can be facilitated.

本発明に係る上部工の製造方法によれば、杭頭固定部材に主桁、横桁を結合することができるので、上部工の形状を容易に形成することができる。よって、橋梁の施工を効率よく行うことができる。   According to the manufacturing method of the superstructure according to the present invention, the main girder and the horizontal girder can be coupled to the pile head fixing member, so that the shape of the superstructure can be easily formed. Therefore, bridge construction can be performed efficiently.

本発明に係る上部工の製造方法によれば、コの字状、矩形状、梯子状の上部工を用いることができるので、橋梁の施工における乗り込み部の施工、標準部の施工に対応した上部工を用いることができる。よって、施工に適した上部工を提供できるので、橋梁の施工を効率よく行うことができる。   According to the superstructure manufacturing method according to the present invention, since a U-shaped, rectangular, ladder-shaped superstructure can be used, the upper part corresponding to the construction of the boarding part and the standard part in the construction of the bridge Can be used. Therefore, since the superstructure suitable for construction can be provided, the construction of the bridge can be performed efficiently.

本発明に係る橋梁及び上部工によれば、杭頭固定部材の上面を直接的又は間接的に床版によって閉じることができる。よって、床版の荷重を杭頭固定部材に挿通した杭部材の突き上げの力に対向させることができる。よって、橋梁の強度を高めることができる。また、管状の杭頭固定部材の上面が杭部材の中心軸に対して垂直であるので、杭部材を容易に杭頭固定部材に挿通することができる。よって、橋梁の施工を容易にできる。   According to the bridge and the superstructure according to the present invention, the upper surface of the pile head fixing member can be directly or indirectly closed by the floor slab. Therefore, the load of the floor slab can be made to oppose the pushing-up force of the pile member inserted through the pile head fixing member. Therefore, the strength of the bridge can be increased. Moreover, since the upper surface of the tubular pile head fixing member is perpendicular to the central axis of the pile member, the pile member can be easily inserted into the pile head fixing member. Therefore, bridge construction can be facilitated.

本発明に係る橋梁の施工方法で用いる上部工の三面図である。It is a three-plane figure of the superstructure used with the construction method of the bridge concerning the present invention. 上部工101の杭頭固定部材115の構成を示す図である。It is a figure which shows the structure of the pile head fixing member 115 of the superstructure 101. FIG. 乗り込み部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of boarding part construction. 乗り込み部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of boarding part construction. 乗り込み部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of boarding part construction. 乗り込み部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of boarding part construction. 乗り込み部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of boarding part construction. 乗り込み部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of boarding part construction. 上部工101上に床版FSを施工したときの一部断面図である。It is a partial cross section figure when floor slab FS is constructed on superstructure 101. 本発明に係る橋梁の施工方法で用いる上部工の三面図である。It is a three-plane figure of the superstructure used with the construction method of the bridge concerning the present invention. 標準部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of standard part construction. 標準部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of standard part construction. 標準部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of standard part construction. 標準部施工時における、上部工を用いた橋梁の施工方法を示す図である。It is a figure which shows the construction method of the bridge using the superstructure at the time of standard part construction. 本発明に係る橋梁の施工方法で用いる上部工の三面図である。It is a three-plane figure of the superstructure used with the construction method of the bridge concerning the present invention. 上部工301上に床版FSを施工したときの一部断面図である。It is a partial cross section figure when floor FS is constructed on superstructure 301. 上部工の他の実施例を示す図である。It is a figure which shows the other Example of a superstructure. 従来の橋梁の施工方法を示す図である。It is a figure which shows the construction method of the conventional bridge.

以下、本発明の実施例について、図面を参照しながら詳細に説明していく。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

第1 上部工の構成
本発明に係る橋梁施工方法で使用する上部工101について図1を用いて説明する。上部工101は、橋梁の施工に先立って、予め組み立てておくものである。なお、組立に際しては、工場等でトラック等の運搬手段で運搬できる大きさの部品を組み立て、さらに、実際の施工現場まで運搬手段で運搬した後、施工現場において図1に示す上部工101の形態まで組み立てる。
Configuration of First Superstructure The superstructure 101 used in the bridge construction method according to the present invention will be described with reference to FIG. The superstructure 101 is assembled in advance prior to the construction of the bridge. At the time of assembly, after assembling parts of a size that can be transported by a transporting means such as a truck in a factory, and further transporting to the actual construction site by the transporting means, the form of the superstructure 101 shown in FIG. Assemble until.

ここで、図1(a)は上部工101の上面図であり、図1(b)は上部工101の正面図であり、図1(c)は上部工101の右側面図である。図1(a)に示すように、上部工101は、複数の主桁111、横桁113、及び杭頭固定部材115によって構成されている。   1A is a top view of the superstructure 101, FIG. 1B is a front view of the superstructure 101, and FIG. 1C is a right side view of the superstructure 101. As shown in FIG. 1A, the superstructure 101 includes a plurality of main girders 111, cross girders 113, and pile head fixing members 115.

主桁111及び横桁113は、梯子状に配置されている。なお、主桁111及び横桁113は、H型鋼により形成されている。   The main beam 111 and the horizontal beam 113 are arranged in a ladder shape. The main beam 111 and the horizontal beam 113 are made of H-shaped steel.

主桁111は、相対的に短い主桁111a及び相対的に長い主桁111bにより構成されている。図1(c)に示すように、主桁111a及び主桁111bは、それぞれ一端が杭頭固定部材115の側面部115a(後述)に溶接され、固定されている。また、図1(a)、(c)に示すように、主桁111a及び主桁111bの杭頭固定部材115に固定されていない他の一端は、所定の固定板、及びボルト、ナットを用いて互いに突き合わされ、直線上に接合されている。   The main girder 111 includes a relatively short main girder 111a and a relatively long main girder 111b. As shown in FIG. 1C, one end of each of the main beam 111a and the main beam 111b is welded and fixed to a side surface portion 115a (described later) of the pile head fixing member 115. Moreover, as shown to FIG. 1 (a), (c), the other end which is not being fixed to the pile head fixing member 115 of the main girder 111a and the main girder 111b uses a predetermined fixing plate, a volt | bolt, and a nut. Are joined together on a straight line.

横桁113は、所定長さの横桁113a及び横桁113bにより構成されている。図1(b)に示すように、横桁113a及び横桁113bは、それぞれ一端が杭頭固定部材115の側面部115aに溶接され、固定されている。また、図1(a)、(b)に示すように、横桁113a及び横桁113bの杭頭固定部材115に固定されていない他の一端は、所定の固定板、及びボルト、ナットを用いて互いに突き合わされ、直線上に接合されている。   The cross beam 113 is composed of a horizontal beam 113a and a horizontal beam 113b having a predetermined length. As shown in FIG. 1B, one end of each of the cross beam 113a and the cross beam 113b is welded and fixed to the side surface portion 115a of the pile head fixing member 115. Moreover, as shown to FIG. 1 (a), (b), the other end which is not being fixed to the pile head fixing member 115 of the cross beam 113a and the cross beam 113b uses a predetermined fixing plate, a volt | bolt, and a nut. Are joined together on a straight line.

図1(a)に示すように、杭頭固定部材115は、中心C5が主桁111の中心軸J1上に配置されている。また、杭頭固定部材115は、中心C5が横桁113の中心軸J3の中心軸J3上に配置されている、つまり、杭頭固定部材115は、中心C5が主桁111の中心軸J1と横桁113の中心軸J3との交点上に存在するように配置されている。これにより、上部工101の形状を容易に整えることができる。また、図1(b)に示すように、杭頭固定部材115は、上面P5が杭頭固定部材115を貫通する鋼管杭の中心軸J5に対して垂直となるように配置される。さらに、図1(c)に示すように、杭頭固定部材115を挟んで配置される主桁111は、直線上に配置される。   As shown in FIG. 1A, the pile head fixing member 115 has a center C <b> 5 disposed on the central axis J <b> 1 of the main girder 111. In addition, the pile head fixing member 115 is arranged on the center axis J3 of the center axis J3 of the cross beam 113, that is, the pile head fixing member 115 has the center C5 and the center axis J1 of the main girder 111. It arrange | positions so that it may exist on the intersection with the central axis J3 of the cross beam 113. FIG. Thereby, the shape of the superstructure 101 can be easily prepared. Moreover, as shown in FIG.1 (b), the pile head fixing member 115 is arrange | positioned so that the upper surface P5 may become perpendicular | vertical with respect to the central axis J5 of the steel pipe pile which penetrates the pile head fixing member 115. FIG. Furthermore, as shown in FIG.1 (c), the main girder 111 arrange | positioned on both sides of the pile head fixing member 115 is arrange | positioned on a straight line.

なお、各杭頭固定部材115には、主桁111a、主桁111b、及び横桁113a又は横桁113bが接合されている。ただし、図1(a)における上部工101の上端に位置する杭頭固定部材115については、杭頭固定部材115には、主桁111a、及び、横桁113a又は横桁113bのみが接合されている。なお、図1(a)〜(c)においては、各杭頭固定部材115に配置されるリブ部115c(後述)については記載を省略している。   Each pile head fixing member 115 is joined with a main beam 111a, a main beam 111b, and a horizontal beam 113a or a horizontal beam 113b. However, for the pile head fixing member 115 located at the upper end of the superstructure 101 in FIG. 1A, only the main girder 111a and the horizontal beam 113a or the horizontal beam 113b are joined to the pile head fixing member 115. Yes. In addition, in FIG. 1 (a)-(c), description is abbreviate | omitted about the rib part 115c (after-mentioned) arrange | positioned at each pile head fixing member 115. FIG.

杭頭固定部材115の構成について図2を用いて説明する。なお、図2(a)は杭頭固定部材115の上面図を、図2(b)は図2(a)に示す杭頭固定部材115のX−X断面図を、それぞれ示している。図2(a)に示すように、杭頭固定部材115は、円筒部115a、フランジ部115b、及びリブ部115cを有している。円筒部115aの一端に、フランジ部115bが配置されている。フランジ部115bには、複数の孔115dが形成されている。孔115dは、ボルト、ナットを用いて、杭頭天蓋(後述)を杭頭固定部材115に固定するために形成されている。円筒部115a及びフランジ部115bの内径は、橋脚となる鋼管杭の外形にほぼ等しい。   The configuration of the pile head fixing member 115 will be described with reference to FIG. 2A shows a top view of the pile head fixing member 115, and FIG. 2B shows an XX cross-sectional view of the pile head fixing member 115 shown in FIG. 2A. As shown in FIG. 2A, the pile head fixing member 115 has a cylindrical portion 115a, a flange portion 115b, and a rib portion 115c. A flange portion 115b is disposed at one end of the cylindrical portion 115a. A plurality of holes 115d are formed in the flange portion 115b. The holes 115d are formed to fix the pile head canopy (described later) to the pile head fixing member 115 using bolts and nuts. The inner diameters of the cylindrical portion 115a and the flange portion 115b are substantially equal to the outer shape of the steel pipe pile serving as a pier.

リブ部115cは、杭頭固定部材115の中心C5から放射状に配置される。図2(b)に示すように、リブ部115cは、円筒部115aの側面及びフランジ部115bに接合される。これにより、杭頭固定部材115の強度を増強する。   The rib portions 115c are arranged radially from the center C5 of the pile head fixing member 115. As shown in FIG. 2B, the rib portion 115c is joined to the side surface of the cylindrical portion 115a and the flange portion 115b. Thereby, the strength of the pile head fixing member 115 is increased.

第2 橋梁施工方法
上部工101を用いた橋梁施工方法について図3〜図7を用いて説明する。なお、橋梁施工方法については、橋台に対して上部工101を乗り込み部として施工する時(以下、乗り込み部施工時)と、施工済の上部工101に対して新に上部工101を施工する時(以下、標準部施工時)とに分けて説明する。
2nd bridge construction method The bridge construction method using the superstructure 101 is demonstrated using FIGS. In addition, about the bridge construction method, when constructing the superstructure 101 with respect to the abutment (hereinafter, when constructing the superstructure), and newly constructing the superstructure 101 with respect to the constructed superstructure 101 (Hereinafter, the standard part construction)

1.乗り込み部施工時
図3(a)に示すように、施工済の橋台BA上に配置したクレーン車CTによってバイブロハンマVHを用いて、所定位置に導杭G1〜導杭G4を矩形状に設置する。なお、図3(a)においては、導杭G1、導杭G3の奥側に存在する導杭G2、導杭G4については括弧書きで表している。
1. At the time of carrying-in part construction As shown in FIG. 3 (a), the guide piles G1 to G4 are installed in a rectangular shape at predetermined positions using the vibratory hammer VH by the crane truck CT arranged on the already-finished abutment BA. In addition, in Fig.3 (a), the guide pile G2 and the guide pile G4 which exist in the back | inner side of the guide pile G1 and the guide pile G3 are represented by the parenthesis writing.

次に、図3(b)に示すように、クレーン車CTを用いて、橋台BAの先端に対して平行に設置した導杭G1及び導杭G2を橋渡すように受材R1を設置する。導杭G3及び導杭G4についても同様に、受材R2を設置する。図3(c)に示すように、クレーン車CTを用いて受材R1、受材R2上に上部工101を配置する。   Next, as shown in FIG.3 (b), receiving material R1 is installed so that the guide pile G1 and the guide pile G2 installed in parallel with respect to the front-end | tip of the abutment BA may be bridged using the crane vehicle CT. Similarly, the receiving material R2 is installed for the guiding pile G3 and the guiding pile G4. As shown in FIG.3 (c), the superstructure 101 is arrange | positioned on the receiving material R1 and the receiving material R2 using the crane vehicle CT.

図4(a)に示すように、クレーン車CTを用いて、テーブルマシンTMを、上部工101の一の杭頭固定部材115上に配置する。次に、図4(b)に示すように、クレーン車CTを用いて、ダウンザホールハンマDHを上部からテーブルマシンTM及び杭頭固定部材115に挿通させる。そして、図4(c)に示すように、テーブルマシンTM及びダウンザホールハンマDHによって地盤を掘削し、鋼管杭を地盤に固定するための固定孔を形成する。   As shown to Fig.4 (a), the table machine TM is arrange | positioned on one pile head fixing member 115 of the superstructure 101 using the crane vehicle CT. Next, as shown in FIG. 4B, the down-the-hole hammer DH is inserted into the table machine TM and the pile head fixing member 115 from above using the crane vehicle CT. And as shown in FIG.4 (c), the ground is excavated by the table machine TM and the down-the-hole hammer DH, and the fixing hole for fixing a steel pipe pile to a ground is formed.

固定孔を形成し終えると、図5(a)に示すように、ダウンザホールハンマDHを上側に引き抜く。さらに、テーブルマシンTMを取り外す。これまでと同様に、図5(b)に示すように、上部工101の他の杭頭固定部材115上にテーブルマシンTMを配置し、ダウンザホールハンマDHを配置した後、地盤を掘削し、もう一つの固定孔を掘削する。そして、図5(c)に示すように、モルタルを投入したバケットBKをクレーン車CTを用いて移動させながら、トレミー管TTを用いて、根固め用のモルタルを固定孔に打設する。   When the formation of the fixing hole is completed, the down-the-hole hammer DH is pulled upward as shown in FIG. Further, the table machine TM is removed. As before, as shown in FIG. 5 (b), after placing the table machine TM on the other pile head fixing member 115 of the superstructure 101, placing the down-the-hole hammer DH, excavating the ground, Drill one fixed hole. Then, as shown in FIG. 5 (c), while the bucket BK charged with mortar is moved using the crane vehicle CT, the mortar for rooting is driven into the fixed hole using the tremy pipe TT.

図6(a)に示すように、モルタルの打設後、クレーン車CTを用いて、橋脚となる鋼管杭SPを上から杭頭固定部材115に挿通させ、固定孔に挿入する。その後、図6(b)に示すように、鋼管杭SPを固定孔に挿入した後、クレーン車CTによってモンケンHBを操作し、鋼管杭SPの杭打ちを行う。   As shown to Fig.6 (a), the steel pipe pile SP used as a bridge pier is penetrated from the top to the pile head fixing member 115, and is inserted in a fixing hole using the crane vehicle CT after placement of mortar. Then, as shown in FIG.6 (b), after inserting the steel pipe pile SP in a fixed hole, the monken HB is operated with the crane vehicle CT and the steel pipe pile SP is piled.

図7(a)に示すように、上部工101の上面から上側に突出した鋼管杭SP1を切断し、除去する。その後、図7(b)に示すように、鋼管杭SPの杭頭にモルタルを打設する。   As shown to Fig.7 (a), the steel pipe pile SP1 which protruded upwards from the upper surface of the superstructure 101 is cut | disconnected and removed. Then, as shown in FIG.7 (b), mortar is driven in the pile head of the steel pipe pile SP.

図7(c)に示すように、杭頭にモルタルを打設した後、杭頭固定部材115の上面に杭頭天蓋TCを固定する。杭頭固定部材115と杭頭天蓋TCとの固定は、杭頭固定部材115のフランジ部115bに形成されている孔115d(図2参照)及び杭頭天蓋TCに形成されている孔に所定のボルトを挿通させ、ナットで固定する。   As shown in FIG. 7 (c), after placing mortar on the pile head, the pile head canopy TC is fixed to the upper surface of the pile head fixing member 115. The pile head fixing member 115 and the pile head canopy TC are fixed to holes 115d (see FIG. 2) formed in the flange portion 115b of the pile head fixing member 115 and holes formed in the pile head canopy TC. Insert the bolt and fix it with a nut.

杭頭天蓋TCを固定した後、図8(a)に示すように、導材を撤去する。そして、図8(b)に示すように、設置した上部工101の上にクローラ用足場を敷設し、橋梁施工における乗り込み部の施工を完了する。その後、標準部施工時での橋梁施工を行う。   After fixing the pile head canopy TC, the conductive material is removed as shown in FIG. And as shown in FIG.8 (b), the crawler scaffold is laid on the installed superstructure 101, and construction of the boarding part in bridge construction is completed. After that, bridge construction will be performed at the time of construction of the standard part.

このような乗り込み部施工時における上部工101の施工の後、実施例2に示す標準部施工時における上部工201の施工を経て、上部工101上に床版FS及び調整用コンクリートASが施工される。床版FS及び調整用コンクリートACが施工された状態の上部工101の側面図を図9に示す。なお、図9においては、一部の杭頭固定部材115及び一部の鋼管杭SPを断面にて表示している。   After the construction of the superstructure 101 at the time of the entry section construction, the floor FS and the adjustment concrete AS are constructed on the superstructure 101 through the construction of the superstructure 201 at the time of the standard construction shown in Example 2. The FIG. 9 shows a side view of the superstructure 101 in a state where the floor slab FS and the adjusting concrete AC are applied. In addition, in FIG. 9, some pile head fixing members 115 and some steel pipe piles SP are displayed by the cross section.

鋼管杭SPが杭頭固定部材115の上面P5に対して垂直に杭頭固定部材115に挿通され、天蓋TCによって杭頭固定部材115の上面P5が閉じられた後、天蓋TC上に床版FSが施工される。したがって、杭頭固定部材115の上面P5は、天蓋TCを介して、間接的に床版FSの下面PFに接している。これにより、床版FSからの過重F1を、鋼管杭SPによる突き上げの力F2に対抗させることができる。よって、高い強度を有する橋梁の施工が可能となる。   After the steel pipe pile SP is inserted into the pile head fixing member 115 perpendicularly to the upper surface P5 of the pile head fixing member 115 and the upper surface P5 of the pile head fixing member 115 is closed by the canopy TC, the floor FS is placed on the canopy TC. Is constructed. Therefore, the upper surface P5 of the pile head fixing member 115 is in contact with the lower surface PF of the floor slab FS indirectly through the canopy TC. Thereby, the excess weight F1 from the floor slab FS can be made to oppose the pushing force F2 by the steel pipe pile SP. Therefore, it is possible to construct a bridge having high strength.

前述の実施例1における上部工101は、乗り込み部施工時に使用するものであった。一方、本実施例における上部工201は、施工済の上部工101に対して施工する時(以下、標準部施工時)に使用するものである。   The superstructure 101 in Example 1 described above was used at the time of construction of the boarding portion. On the other hand, the superstructure 201 in the present embodiment is used when performing construction on the superstructure 101 that has already been constructed (hereinafter referred to as standard construction).

第1 上部工の構成
本発明に係る橋梁施工方法で使用する上部工201について図10を用いて説明する。ここで、図10(a)は上部工201の上面図であり、図10(b)は上部工201の正面図であり、図10(c)は上部工201の右側面図である。なお、図10(a)〜図10(c)においては、図1(a)〜図1(c)と同様の構成については、同じ符号を付している。
Configuration of First Superstructure The superstructure 201 used in the bridge construction method according to the present invention will be described with reference to FIG. Here, FIG. 10A is a top view of the upper work 201, FIG. 10B is a front view of the upper work 201, and FIG. 10C is a right side view of the upper work 201. 10 (a) to 10 (c), the same reference numerals are given to the same configurations as those in FIGS. 1 (a) to 1 (c).

上部工201では、主桁111及び横桁113が梯子状に配置されている上部工101とは異なり、主桁111及び横桁113がコの字状に配置されている。   In the superstructure 201, unlike the superstructure 101 in which the main beam 111 and the horizontal beam 113 are arranged in a ladder shape, the main beam 111 and the horizontal beam 113 are arranged in a U-shape.

第2 標準部施工時
図11(a)に示すように、鋼管杭SP(1)及び鋼管杭SP(2)を施工済の上部工SS上にクレーン車CTを配置する。クレーン車CTによって、上部工201を所定の位置に配置し、上部工201の主桁111bと上部工SSの主桁111aとを接続する。これにより、上部工201は上部工SSに対して片持ち状態となる。なお、上部工201を所定の位置に片持ち状態とするにあたっては、接続する上部工201の主桁111bと上部工SSの主桁111aと間に線材(例えば、ピアノ線)をかけ渡し、上部工SSの主桁111aと平行になるように線材の張力を調整することによって、上部工201の主桁111bの方向、角度、歪み等の状態が完成時の状態に近づくようにしてもよい(特開2000−96582参照)。
At the time of construction of the second standard part As shown in FIG. 11 (a), the crane CT is disposed on the superstructure SS where the steel pipe pile SP (1) and the steel pipe pile SP (2) have been constructed. The upper work 201 is placed at a predetermined position by the crane truck CT, and the main beam 111b of the upper work 201 and the main beam 111a of the upper work SS are connected. As a result, the upper work 201 is cantilevered with respect to the upper work SS. When the upper work 201 is cantilevered at a predetermined position, a wire rod (for example, a piano wire) is passed between the main beam 111b of the upper work 201 to be connected and the main beam 111a of the upper work SS. By adjusting the tension of the wire rod so as to be parallel to the main girder 111a of the work SS, the state of the main girder 111b of the upper work 201, the angle, the distortion, and the like may be brought closer to the state at the time of completion ( JP 2000-96582).

次に、図11(b)に示すように、クレーン車CTを用いて、テーブルマシンTMを、上部工101の一の杭頭固定部材115上に配置する。そして、図11(c)に示すように、クレーン車CTを用いて、ダウンザホールハンマDHを上部から、テーブルマシンTM及び杭頭固定部材115に挿通させる。この際、ダウンザホールハンマDHを杭頭固定部材115の上面P5(図10参照)に対して垂直に挿入する。   Next, as shown in FIG.11 (b), the table machine TM is arrange | positioned on one pile head fixing member 115 of the superstructure 101 using the crane vehicle CT. Then, as shown in FIG. 11C, the down-the-hole hammer DH is inserted through the table machine TM and the pile head fixing member 115 from above using the crane vehicle CT. At this time, the down-the-hole hammer DH is inserted perpendicularly to the upper surface P5 (see FIG. 10) of the pile head fixing member 115.

図12(a)に示すように、テーブルマシンTM及びダウンザホールハンマDHによって地盤を掘削し、鋼管杭を地盤に固定するための固定孔を形成する。固定孔を形成し終えると、図12(b)に示すように、ダウンザホールハンマDHを上側に引き抜く。さらに、テーブルマシンTMを取り外す。そして、図12(c)に示すように、モルタルを投入したバケットBKをクレーン車CTを用いて移動させながら、トレミー管TTを用いて、根固め用のモルタルを固定孔に打設する。   As shown in FIG. 12A, the ground is excavated by the table machine TM and the down-the-hole hammer DH, and a fixing hole for fixing the steel pipe pile to the ground is formed. When the formation of the fixing hole is completed, the down-the-hole hammer DH is pulled upward as shown in FIG. Further, the table machine TM is removed. And as shown in FIG.12 (c), while moving the bucket BK which injected | thrown-in mortar using the crane vehicle CT, the mortar for rooting is driven in a fixed hole using the treme tube TT.

図13(a)に示すように、モルタルの打設後、クレーン車CTを用いて、橋脚となる鋼管杭SP(3)を上から杭頭固定部材115に挿通させ、固定孔に挿入する。この際、鋼管杭SP(3)を杭頭固定部材115の上面P5(図10参照)に対して垂直に挿入する。その後、図13(b)に示すように、鋼管杭SP(3)を固定孔に挿入した後、クレーン車CTによってモンケンHBを操作し、鋼管杭SP(3)の杭打ちを行う。   As shown in FIG. 13 (a), after placing the mortar, the steel pipe pile SP (3) serving as a bridge pier is inserted into the pile head fixing member 115 from above and inserted into the fixing hole using the crane vehicle CT. At this time, the steel pipe pile SP (3) is inserted perpendicularly to the upper surface P5 (see FIG. 10) of the pile head fixing member 115. Then, as shown in FIG.13 (b), after inserting the steel pipe pile SP (3) in a fixed hole, the monken HB is operated with the crane truck CT, and the steel pipe pile SP (3) is piled.

図13(c)に示すように、上部工201の上面から上側に突出した鋼管杭SP1(3)を切断し、除去する。   As shown in FIG. 13C, the steel pipe pile SP1 (3) protruding upward from the upper surface of the superstructure 201 is cut and removed.

その後、図14(a)に示すように、鋼管杭SPの杭頭にモルタルを打設する。杭頭にモルタルを打設した後、杭頭固定部材115の上面に杭頭天蓋TCを固定する。杭頭固定部材115と杭頭天蓋TCとの固定は、杭頭固定部材115のフランジ部115f(図2参照)に形成されている孔115g及び杭頭天蓋TCに形成されている孔に所定のボルトを挿通させ、ナットで固定する。   Then, as shown to Fig.14 (a), mortar is driven in the pile head of the steel pipe pile SP. After placing the mortar on the pile head, the pile head canopy TC is fixed to the upper surface of the pile head fixing member 115. The pile head fixing member 115 and the pile head canopy TC are fixed to a hole 115g formed in the flange portion 115f (see FIG. 2) of the pile head fixing member 115 and a hole formed in the pile head canopy TC. Insert the bolt and fix it with a nut.

そして、図14(b)に示すように、設置した上部工201の上にクローラ用足場を敷設する。その後、図14(c)に示すように、鋼管杭SP(3)の施工と同様にして、鋼管杭SP(4)を施工し、クローラ用足場を敷設する。これにより、クレーン車CTによる床版の敷設のための領域を確保する。そして、既に敷設したクローラ用足場を除去した後、除去した領域に床版を敷設する。これにより、橋梁施工における標準部の施工を完了する。   Then, as shown in FIG. 14B, a crawler scaffold is laid on the installed superstructure 201. Then, as shown in FIG.14 (c), steel pipe pile SP (4) is constructed similarly to construction of steel pipe pile SP (3), and the crawler scaffold is laid. Thereby, the area | region for laying the floor slab by the crane vehicle CT is ensured. Then, after removing the already laid crawler scaffold, a floor slab is laid in the removed area. Thereby, the construction of the standard part in the bridge construction is completed.

前述の実施例1及び実施例2における橋梁の施工方法では、水平に床版を敷設した。本実施例における橋梁の施工は、所定の斜度でもって床版を敷設するものである。   In the bridge construction method in Example 1 and Example 2 described above, the floor slab was laid horizontally. In the construction of the bridge in this embodiment, a floor slab is laid with a predetermined inclination.

第1 上部工の構成
本発明に係る橋梁施工方法で使用する上部工301について図15を用いて説明する。上部工301は、斜度を有する橋梁を施工する際に使用するものである。ここで、図15(a)は上部工301の上面図であり、図15(b)は上部工301の正面図であり、図15(c)は上部工301の右側面図である。なお、図15(a)〜図15(c)においては、図1(a)〜図1(c)と同様の構成については、同じ符号を付し、詳細な記述については省略する。
First Superstructure Configuration The superstructure 301 used in the bridge construction method according to the present invention will be described with reference to FIG. The superstructure 301 is used when constructing a bridge having an inclination. 15A is a top view of the upper work 301, FIG. 15B is a front view of the upper work 301, and FIG. 15C is a right side view of the upper work 301. In FIGS. 15A to 15C, the same components as those in FIGS. 1A to 1C are denoted by the same reference numerals, and detailed description thereof is omitted.

上部工301は、主桁311、横桁113及び杭頭固定部材115を有している。主桁311及び横桁113は、梯子状に配置されている。また、主桁311及び横桁113は、H型鋼により形成されている。   The superstructure 301 includes a main beam 311, a horizontal beam 113, and a pile head fixing member 115. The main beam 311 and the horizontal beam 113 are arranged in a ladder shape. The main beam 311 and the horizontal beam 113 are made of H-shaped steel.

主桁311は、相対的に短い主桁311a、311c及び相対的に長い主桁311bにより構成されている。図15(c)に示すように、主桁311a及び主桁311cは、それぞれ一端が杭頭固定部材115の側面部115a(図2参照)に溶接され、固定されている。また、図1(a)、(c)に示すように、主桁311bの両端は、主桁311の杭頭固定部材115に固定されていない一端と、所定の固定板、及びボルト、ナットを用いて互いに突き合わされ、直線上に接合されている。   The main girder 311 is composed of relatively short main girders 311a and 311c and a relatively long main girder 311b. As shown in FIG. 15C, one end of each of the main girder 311a and the main girder 311c is welded and fixed to the side surface portion 115a (see FIG. 2) of the pile head fixing member 115. As shown in FIGS. 1A and 1C, both ends of the main girder 311b are connected to one end of the main girder 311 not fixed to the pile head fixing member 115, a predetermined fixing plate, bolts and nuts. Using each other and joined on a straight line.

図15(a)に示すように、杭頭固定部材115は、中心C5が主桁311の中心軸J1上に配置されている。また、杭頭固定部材115は、中心C5が横桁113の中心軸J3の中心軸J3上に配置されている、つまり、杭頭固定部材115は、中心C5が主桁311の中心軸J1と横桁113の中心軸J3との交点上に存在するように配置されている。また、図15(b)に示すように、杭頭固定部材115は、上面P5が杭頭固定部材115を貫通する鋼管杭の中心軸J5に対して垂直となるように配置される。さらに、図15(c)に示すように、杭頭固定部材115を挟んで配置される主桁311a、311cは、直線上に配置される。一方、主桁311a及び主桁311cの間に接続される主桁311bは、斜めに配置される。つまり、図15(c)に示すように、上部工301は、杭頭固定部材115周辺の平坦な部分と主桁311bに沿う斜めの部分とが交互に配置される傾斜面を有している。 As shown in FIG. 15A, the pile head fixing member 115 has the center C <b> 5 disposed on the central axis J <b> 1 of the main girder 311. In addition, the pile head fixing member 115 is arranged on the center axis J3 of the center axis J3 of the cross beam 113, that is, the pile head fixing member 115 has the center C5 and the center axis J1 of the main girder 311. It arrange | positions so that it may exist on the intersection with the central axis J3 of the cross beam 113. FIG. 15B, the pile head fixing member 115 is disposed so that the upper surface P5 is perpendicular to the central axis J5 of the steel pipe pile passing through the pile head fixing member 115. Furthermore, as shown in FIG.15 (c), the main girders 311a and 311c arrange | positioned on both sides of the pile head fixing member 115 are arrange | positioned on a straight line. On the other hand, the main beam 311b connected between the main beam 311a and the main beam 311c is arranged obliquely. That is, as shown in FIG. 15C, the superstructure 301 has an inclined surface in which flat portions around the pile head fixing member 115 and oblique portions along the main beam 311b are alternately arranged. .

第2 上部工301を用いた施工
上部工301を用いた乗り込み部施工時における橋梁の施工については、実施例1と同様である。また、標準部施工時における施工においては、実施例2と同様に、コの字状(図10参照)で、主桁311の主桁311bが斜めに配置される上部工を用いて施工する。標準部施工時における橋梁の施工については、実施例2と同様である。
Construction using the second superstructure 301 The construction of the bridge at the time of entry work construction using the superstructure 301 is the same as in the first embodiment. Moreover, in the construction at the time of construction of the standard part, similarly to the second embodiment, construction is performed using an upper work in which the main girder 311b of the main girder 311 is obliquely arranged in a U-shape (see FIG. 10). The construction of the bridge at the time of construction of the standard part is the same as in Example 2.

ここで、床版FS及び調整用コンクリートASが施工された状態の上部工301の側面図を図16に示す。なお、図16においては、一部の杭頭固定部材115及び一部の鋼管杭SPを断面にて表示している。   Here, FIG. 16 shows a side view of the superstructure 301 in a state in which the floor slab FS and the adjustment concrete AS are applied. In addition, in FIG. 16, some pile head fixing members 115 and some steel pipe piles SP are displayed by the cross section.

実施例1における上部工101を用いた施工と同様に、上部工301を用いた施工においても、鋼管杭SPが杭頭固定部材115の上面P5に対して垂直に杭頭固定部材115に挿通され、天蓋TCによって杭頭固定部材115の上面P5が閉じられた後、天蓋TC上に床版FSが施工される。したがって、杭頭固定部材115の上面P5は、天蓋TCを介して、間接的に床版FSの下面PFに接している。これにより、床版FSからの過重F1を、鋼管杭SPによる突き上げの力F2に対抗させることができる。よって、高い強度を有する橋梁の施工が可能となる。なお、上部工301を用いて所定の傾斜面を形成するために、調整用コンクリートAC2を施工する。   Similarly to the construction using the superstructure 101 in the first embodiment, also in the construction using the superstructure 301, the steel pipe pile SP is inserted into the pile head fixing member 115 perpendicularly to the upper surface P5 of the pile head fixing member 115. After the top surface P5 of the pile head fixing member 115 is closed by the canopy TC, the floor slab FS is constructed on the canopy TC. Therefore, the upper surface P5 of the pile head fixing member 115 is in contact with the lower surface PF of the floor slab FS indirectly through the canopy TC. Thereby, the excess weight F1 from the floor slab FS can be made to oppose the pushing force F2 by the steel pipe pile SP. Therefore, it is possible to construct a bridge having high strength. In addition, in order to form a predetermined inclined surface using the superstructure 301, the adjustment concrete AC2 is applied.

[その他の実施形態]
(1)上部工の形状:前述の実施例1においては、上部工101は梯子状としたが、矩形状であっても良い。実施例3にける上部工301についても同様である。また、前述の実施例2においては、上部工201は、コの字状としたが、複数のコの字状の上部工201を連結したものであってもより。連結の際には主桁111aと主桁111bとを直線上に連結すればよい。
[Other Embodiments]
(1) Shape of superstructure: In the first embodiment, the superstructure 101 has a ladder shape, but may have a rectangular shape. The same applies to the superstructure 301 in the third embodiment. In the second embodiment, the upper work 201 has a U-shape, but a plurality of U-shaped upper works 201 may be connected. What is necessary is just to connect the main beam 111a and the main beam 111b on the straight line in the case of connection.

また、前述の実施例1においては、上部工101のように2つの主桁111a、主桁111bを結合して杭頭固定部材115間に配置される主桁111を形成していたが(図1参照)、杭頭固定部材115間に配置される主桁を形成する主桁の数については限定されない。例えば、図17(a)、(b)に示す上部工102のように、3つの主桁112a、主桁112b及び主桁112cを結合して主桁112を形成する。さらに、複数の主桁を結合することなく、1つの主桁によって杭頭固定部材115間に配置される主桁を形成するようにしてもよい。この場合、主桁の両端には杭頭固定部材115が結合される。   In the first embodiment, the main girder 111 arranged between the pile head fixing members 115 is formed by connecting the two main girders 111a and the main girder 111b as in the superstructure 101 (FIG. 1), the number of main beams forming the main beam arranged between the pile head fixing members 115 is not limited. For example, as in the superstructure 102 shown in FIGS. 17A and 17B, three main beams 112a, main beams 112b, and main beams 112c are combined to form the main beam 112. Furthermore, you may make it form the main beam arrange | positioned between the pile head fixing members 115 by one main beam, without couple | bonding a several main beam. In this case, pile head fixing members 115 are coupled to both ends of the main beam.

横桁についても主桁と同様に、杭頭固定部材115間に配置される横桁を形成する横桁の数については、限定されない。例えば、図17(a)、(b)に示す上部工102のように、1つの横桁114によって杭頭固定部材115間に配置される横桁を形成するようにしてもよい。   Similarly to the main beam, the number of the horizontal beam forming the horizontal beam arranged between the pile head fixing members 115 is not limited. For example, you may make it form the cross beam arrange | positioned between the pile head fixing members 115 by one cross beam 114 like the superstructure 102 shown to Fig.17 (a), (b).

(2)横桁の結合:前述の実施例1〜実施例3においては、横桁113は、杭頭固定部材115に結合するものとしたが、各上部工における主桁に結合し、上部工を矩形状、梯子状、コの字状とするようにしてもよい。   (2) Coupling of cross beam: In the above-described first to third embodiments, the cross beam 113 is connected to the pile head fixing member 115. May be rectangular, ladder, or U-shaped.

101・・・・・上部工
111・・・・・主桁
111a・・・主桁
111b・・・主桁
113・・・・・横桁
113a・・・横桁
113b・・・横桁
115・・・・・杭頭固定部材
P5・・・・・上面
FS・・・・・床版
201・・・・・上部工
301・・・・・上部工
311・・・・・主桁
311a・・・主桁
311b・・・主桁
311c・・・主桁
102・・・・・上部工
112・・・・・主桁
112a・・・主桁
112b・・・主桁
112c・・・主桁
114・・・・・横桁
101 ··· Superstructure 111 ··· Main girder 111a ··· Main girder 111b ··· Main girder 113 ··· Horizontal girder 113a ··· Horizontal girder 113b ··· Horizontal girder 115 · ··· Pile head fixing member P5 ··· Upper surface FS ··· Floor slab 201 · · · Upper work 301 · · Upper work 311 · · · Main girder 311a ···・ Main girder 311b ... Main girder 311c ... Main girder 102 ... Superstructure 112 ... Main girder 112a ... Main girder 112b ... Main girder 112c ... Main girder 114 ...... Horizontal girder

Claims (3)

杭部材、及び、主桁、横桁及び杭頭固定部材を結合した上部工を製造するための上部工製造方法であって、
前記主桁は相対的に短い主桁及び相対的に長い主桁とからなり、
前記杭頭固定部材は、前記杭部材を挿通できる円筒部と、前記円筒部の一端に配置されるフランジ部と、該杭頭固定部材の中心から放射状に配置されるリブ部を有し、前記リブ部は前記円筒部の側面及び前記フランジ部に接合され、
前記円筒部及び前記フランジ部の内径は、前記杭部材の外径に略等しく、
前記杭頭固定部材の上面が前記上部工の上に配置される床版と直接的又は前記杭頭固定部材の上面を閉じる天蓋を介して間接的に接し、前記杭頭固定部材の上面が前記杭頭固定部材に挿通したときの前記杭部材の中心軸に対して垂直となるように、全ての前記杭頭固定部材の円筒部の中心が前記主桁の長手方向の中心軸と前記横桁の長手方向の中心軸との交点上に位置するように前記主桁及び前記横桁を前記杭頭固定部材の側面に結合する工程と、前記短い主桁を平坦となるように配置し、前記短い主桁の間に長い主桁を斜めに配置する工程により、前記杭頭固定部材と前記短い主桁からなる平坦な部分と前記長い主桁に沿う斜め部分とが交互に配置される傾斜面を形成し、前記主桁及び前記横桁が矩形状、梯子状、又はコの字状に配置された上部工を得ること、
を特徴とする上部工の製造方法。
A superstructure manufacturing method for manufacturing a superstructure combining a pile member, and a main girder, a cross girder, and a pile head fixing member,
The main girder consists of a relatively short main girder and a relatively long main girder,
The pile head fixing member has a cylindrical portion through which the pile member can be inserted, a flange portion arranged at one end of the cylindrical portion, and a rib portion arranged radially from the center of the pile head fixing member, The rib portion is joined to the side surface of the cylindrical portion and the flange portion,
The inner diameter of the cylindrical portion and the flange portion is substantially equal to the outer diameter of the pile member,
The upper surface of the pile head fixing member is in direct contact with a floor slab disposed on the superstructure or indirectly through a canopy that closes the upper surface of the pile head fixing member, and the upper surface of the pile head fixing member is The center of the cylindrical portion of all the pile head fixing members is the central axis in the longitudinal direction of the main girder and the cross beam so that it is perpendicular to the central axis of the pile member when inserted into the pile head fixing member Connecting the main girder and the cross girder to the side surface of the pile head fixing member so as to be located on the intersection with the central axis in the longitudinal direction of the pile, and arranging the short main girder so as to be flat, An inclined surface in which a long main girder is diagonally arranged between short main girders, and the pile head fixing member, the flat portion composed of the short main girder, and the oblique portion along the long main girder are alternately arranged. forming, said main beam and said crossbeam is rectangular, are arranged in a ladder-like or U-shaped Possible to obtain the superstructure,
The manufacturing method of the superstructure characterized by this.
杭部材、及び、主桁、横桁及び杭頭固定部材を結合した上部工を有する橋梁であって、
前記主桁は相対的に短い主桁及び相対的に長い主桁とからなり、
前記杭頭固定部材は、前記杭部材を挿通できる円筒部と、前記円筒部の一端に配置されるフランジ部と、該杭頭固定部材の中心から放射状に配置されるリブ部を有し、前記リブ部は前記円筒部の側面及び前記フランジ部に接合され、
前記円筒部及び前記フランジ部の内径は、前記杭部材の外径に略等しく、
前記上部工は、
全ての前記杭頭固定部材の円筒部の中心が前記主桁の長手方向の中心軸と前記横桁の長手方向の中心軸との交点上に位置するように前記主桁及び前記横桁を前記杭頭固定部材の側面に結合すること、及び前記短い主桁を平坦となるように配置し、前記短い主桁の間に長い主桁を斜めに配置することにより、前記主桁及び前記横桁が矩形状、梯子状、又はコの字状に配置されること、前記杭頭固定部材の上面が前記上部工の上に配置される床版と直接的又は前記杭頭固定部材の上面を閉じる天蓋を介して間接的に接し、前記杭頭固定部材の上面が前記杭頭固定部材に挿通したときの前記杭部材の中心軸に対して垂直であること、そして前記杭頭固定部材と前記短い主桁からなる平坦な部分と前記長い主桁に沿う斜め部分とが交互に配置される傾斜面であること、
を特徴とする橋梁。
A pile member and a bridge having a superstructure combining a main girder, a cross girder and a pile head fixing member,
The main girder consists of a relatively short main girder and a relatively long main girder,
The pile head fixing member has a cylindrical portion through which the pile member can be inserted, a flange portion arranged at one end of the cylindrical portion, and a rib portion arranged radially from the center of the pile head fixing member, The rib portion is joined to the side surface of the cylindrical portion and the flange portion,
The inner diameter of the cylindrical portion and the flange portion is substantially equal to the outer diameter of the pile member,
The superstructure is
The main girders and the cross beams are arranged so that the centers of the cylindrical portions of all the pile head fixing members are located on the intersections between the longitudinal central axis of the main girders and the longitudinal central axis of the cross girders. The main girder and the cross girder are connected to the side surface of the pile head fixing member , and the short main girder is arranged to be flat, and the long main girder is arranged obliquely between the short main girder. Is arranged in a rectangular shape, a ladder shape, or a U-shape, and the upper surface of the pile head fixing member is directly closed with the floor slab disposed on the upper work or the upper surface of the pile head fixing member. Indirect contact with the canopy, and the upper surface of the pile head fixing member is perpendicular to the central axis of the pile member when inserted through the pile head fixing member, and the pile head fixing member and the short Inclinations in which flat portions of main girders and oblique portions along the long main girders are alternately arranged It is a surface,
A bridge characterized by
杭部材、及び、主桁、横桁及び前記杭部材を挿通できる円筒部を有する杭頭固定部材を結合した上部工であって、
前記主桁は相対的に短い主桁及び相対的に長い主桁とからなり、
前記杭頭固定部材は、前記円筒部の一端に配置されるフランジ部と、該杭頭固定部材の中心から放射状に配置されるリブ部を有し、
前記リブ部は前記円筒部の側面及び前記フランジ部に接合され、
前記円筒部及び前記フランジ部の内径は、前記杭部材の外径に略等しく、
全ての前記杭頭固定部材の円筒部の中心が前記主桁の長手方向の中心軸と前記横桁の長手方向の中心軸との交点上に位置するように前記主桁及び前記横桁を前記杭頭固定部材の側面に結合すること、及び前記短い主桁を平坦となるように配置し、前記短い主桁の間に長い主桁を斜めに配置することにより、前記主桁及び前記横桁を矩形状、梯子状、又はコの字状に配置し、前記杭頭固定部材の上面が前記上部工の上に配置される床版と直接的又は前記杭頭固定部材の上面を閉じる天蓋を介して間接的に接し、前記杭頭固定部材の上面が前記杭頭固定部材に挿通したときの前記杭部材の中心軸に対して垂直であること、そして前記杭頭固定部材と前記短い主桁からなる平坦な部分と前記長い主桁に沿う斜め部分とが交互に配置される傾斜面であること、
を特徴とする橋梁の施工に用いる上部工。
A pile member, and a superstructure combining a pile head fixing member having a main girder, a horizontal girder, and a cylindrical portion through which the pile member can be inserted,
The main girder consists of a relatively short main girder and a relatively long main girder,
The pile head fixing member has a flange portion arranged at one end of the cylindrical portion, and a rib portion arranged radially from the center of the pile head fixing member,
The rib portion is joined to the side surface of the cylindrical portion and the flange portion,
The inner diameter of the cylindrical portion and the flange portion is substantially equal to the outer diameter of the pile member,
The main girders and the cross beams are arranged so that the centers of the cylindrical portions of all the pile head fixing members are located on the intersections between the longitudinal central axis of the main girders and the longitudinal central axis of the cross girders. The main girder and the cross girder are connected to the side surface of the pile head fixing member , and the short main girder is arranged to be flat, and the long main girder is arranged obliquely between the short main girder. Are placed in a rectangular shape, a ladder shape, or a U-shape, and a canopy that directly or directly closes the top surface of the pile head fixing member and a floor slab on which the upper surface of the pile head fixing member is disposed on the superstructure Indirectly through the pile head fixing member, the upper surface of the pile head fixing member being perpendicular to the central axis of the pile member when the pile head fixing member is inserted, and the pile head fixing member and the short main girder Are inclined surfaces in which flat portions made of and oblique portions along the long main girder are alternately arranged. That,
Superstructure used for the construction of bridges characterized by
JP2011205287A 2011-09-20 2011-09-20 Manufacturing method of superstructure for bridge, bridge and superstructure for bridge Active JP5661011B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011205287A JP5661011B2 (en) 2011-09-20 2011-09-20 Manufacturing method of superstructure for bridge, bridge and superstructure for bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011205287A JP5661011B2 (en) 2011-09-20 2011-09-20 Manufacturing method of superstructure for bridge, bridge and superstructure for bridge

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2011071175 Division 2011-03-28

Publications (2)

Publication Number Publication Date
JP2012207516A JP2012207516A (en) 2012-10-25
JP5661011B2 true JP5661011B2 (en) 2015-01-28

Family

ID=47187475

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011205287A Active JP5661011B2 (en) 2011-09-20 2011-09-20 Manufacturing method of superstructure for bridge, bridge and superstructure for bridge

Country Status (1)

Country Link
JP (1) JP5661011B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5718861B2 (en) * 2012-06-25 2015-05-13 日本ジュウキケンセツ株式会社 Construction method of pile-type pier
CN106536825B (en) * 2014-06-30 2019-11-01 株式会社高知丸高 Method for bridge construction and bridge structure
KR101542192B1 (en) 2014-12-02 2015-08-05 우경기술주식회사 The structure of steel bridge system and method for constructing bridge using the same
JP5977904B1 (en) * 2016-04-13 2016-08-24 ヒロセ株式会社 Construction method of simple temporary bridge
JP6034531B1 (en) * 2016-08-03 2016-11-30 ヒロセ株式会社 Construction method of simple temporary bridge

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06322743A (en) * 1993-05-13 1994-11-22 Kawasaki Steel Corp Construction of artificial ground
JP2000248526A (en) * 1999-03-03 2000-09-12 Nippon Steel Corp Pier structure and constructing method thereof
JP2000257006A (en) * 1999-03-04 2000-09-19 Nippon Steel Corp Artificial ground structure and its construction method
JP2000282403A (en) * 1999-03-30 2000-10-10 Kawasaki Steel Corp Artificial ground for road and its construction method
JP4648998B2 (en) * 2005-04-25 2011-03-09 株式会社横山基礎工事 Earth disposal equipment

Also Published As

Publication number Publication date
JP2012207516A (en) 2012-10-25

Similar Documents

Publication Publication Date Title
JP5661011B2 (en) Manufacturing method of superstructure for bridge, bridge and superstructure for bridge
JP5050228B2 (en) Ramen bridge construction method with cane member
KR101868677B1 (en) Connection unit for coupling main steel girder and ancillary steel girder and, connection methods using the same
JP2009161974A (en) Reinforced concrete beam construction method
JP3249789B2 (en) Reinforcement method for columnar structures
JP7490128B2 (en) Road Structure
JP5977904B1 (en) Construction method of simple temporary bridge
JP2008031733A (en) Bridge erection method
JP2009041272A (en) Construction method for bridge
JP5825644B2 (en) Pier construction method
WO2016001997A1 (en) Bridge construction method and bridge structure
JP5602455B2 (en) Beam members and building structures
JP5282972B2 (en) Column-beam joint reinforcement structure
JP4572028B2 (en) Steel-concrete composite truss joint structure and steel-concrete composite truss erection method
JP2017110442A (en) Joining structure of steel pipe column
JP2000017613A (en) Connection of corrugated steel plate web girder
RU2280122C1 (en) Bridge span structure
JP6655746B2 (en) Bridge structure and floor slab replacement method
JP6138192B2 (en) Steel pipe pile construction method
CN108252215A (en) Connection structure of the board-like Suo-tower of trepanning and preparation method thereof
JP7219529B2 (en) Combination structure of steel materials, shoring structure and construction method
JP2007016509A (en) Joining method of juxtaposed tunnels
JP2020070589A (en) Reinforcement structure for column base part of steel column
JP3845297B2 (en) Structure of joint between column and beam
JP7447879B2 (en) Construction methods for steel walls, structures, and structures

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130227

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131122

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20131204

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140130

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140331

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140528

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20141105

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20141202

R150 Certificate of patent or registration of utility model

Ref document number: 5661011

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250