JP2015101821A - Concrete placing method - Google Patents

Concrete placing method Download PDF

Info

Publication number
JP2015101821A
JP2015101821A JP2013240588A JP2013240588A JP2015101821A JP 2015101821 A JP2015101821 A JP 2015101821A JP 2013240588 A JP2013240588 A JP 2013240588A JP 2013240588 A JP2013240588 A JP 2013240588A JP 2015101821 A JP2015101821 A JP 2015101821A
Authority
JP
Japan
Prior art keywords
concrete
supply pipe
hopper
cap
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013240588A
Other languages
Japanese (ja)
Other versions
JP6322392B2 (en
Inventor
武彦 宮本
Takehiko Miyamoto
武彦 宮本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2013240588A priority Critical patent/JP6322392B2/en
Publication of JP2015101821A publication Critical patent/JP2015101821A/en
Application granted granted Critical
Publication of JP6322392B2 publication Critical patent/JP6322392B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a concrete placing method that can prevent segregation of concrete aggregate when constructing a steel pipe concrete column.SOLUTION: The following concrete placing method is used to place concrete into a steel pile 41. This concrete placing method includes the following steps: a step S1 for constructing a steel pile 41 after preparing a hopper 10 for storing concrete and a concrete placing tool 1 that is provided with a cylindrical, flexible concrete supply pipe 20, whose inner faces are so coherent that the inner faces come into a close contact with each other, extending from the hopper 10; a step S3 for setting the hopper 10 just above the steel pile 41, setting the concrete supply pipe 20 into the steel pile 41 and arranging the concrete supply pipe 20 in a way that it runs along the central axis of the steel pile 41; and step S4 for dropping down concrete in the hopper 10 through the concrete supply pipe 20 into the steel pile 41.

Description

本発明は、コンクリート打設方法に関する。詳しくは、鋼管コンクリート柱を構築する際、鋼管内にコンクリートを打設するコンクリート打設方法に関する。   The present invention relates to a concrete placing method. Specifically, the present invention relates to a concrete placing method for placing concrete in a steel pipe when constructing a steel pipe concrete column.

従来より、充填鋼管コンクリート柱を構築する際、鋼管内にコンクリートを打設する必要がある。この場合、コンクリートの骨材が分離するのを防止するため、コンクリート打設治具を用いることが提案されている(特許文献1参照)。
具体的には、コンクリート打設治具は、コンクリートが収容されるホッパと、このホッパから延びる筒状のコンクリート装填管と、を備える。ホッパは、鋼管の直上に配置されている。コンクリート装填管は、鋼製であり、鋼管の頂部から底部近傍まで延びている。
Conventionally, when a filled steel pipe concrete column is constructed, it is necessary to cast concrete into the steel pipe. In this case, in order to prevent the concrete aggregate from separating, it has been proposed to use a concrete placing jig (see Patent Document 1).
Specifically, the concrete placing jig includes a hopper in which concrete is accommodated, and a cylindrical concrete loading tube extending from the hopper. The hopper is disposed immediately above the steel pipe. The concrete loading pipe is made of steel and extends from the top of the steel pipe to the vicinity of the bottom.

このコンクリート打設治具によれば、ホッパ内のコンクリートを、コンクリート装填管からの内部を通して鋼管内に落し込む。このとき、コンクリート装填管の先端からコンクリートを常に噴出させることで、コンクリートの落下時の衝撃を緩和して、コンクリートの骨材の分離を防止する。   According to this concrete placing jig, the concrete in the hopper is dropped into the steel pipe through the inside from the concrete loading pipe. At this time, the concrete is always ejected from the tip of the concrete loading pipe, so that the impact at the time of dropping of the concrete is alleviated and separation of the concrete aggregate is prevented.

特に、このコンクリート打設治具を用いて充填鋼管コンクリート柱を構築する場合、予め、鉄骨製作工場にて、建物の2、3層分に相当する鋼管柱を製作し、この鋼管柱を建設現場に搬入して建て込んだ後、このコンクリート打設治具を用いてコンクリートを充填する。したがって、コンクリートの落下高さは、ホッパから鋼管柱内部の下端面までとなるので、骨材が分離するおそれが高くなる。   In particular, when constructing a filled steel pipe concrete column using this concrete placing jig, steel pipe columns corresponding to two or three layers of the building are manufactured in advance at the steel frame manufacturing factory, and this steel pipe column is then constructed at the construction site. After carrying in and building, concrete is filled using this concrete placing jig. Therefore, since the fall height of the concrete is from the hopper to the lower end surface inside the steel pipe column, there is a high possibility that the aggregate is separated.

特開平5−272240号公報Japanese Patent Laid-Open No. 5-272240

しかしながら、実際には、生コンクリート車の切り替えや、バイブレータの盛り替え作業などがあるので、コンクリート装填管の先端からコンクリートを常に噴出させることは困難であり、コンクリートの骨材の分離を防ぐことは難しかった。   However, in reality, there is a changeover of a ready-mixed concrete car and a refilling work of vibrators, so it is difficult to always eject concrete from the tip of the concrete loading pipe, and it is difficult to prevent separation of the concrete aggregate. was difficult.

本発明は、鋼管コンクリート柱を構築する際に、コンクリートの骨材の分離を防止できるコンクリート打設方法を提供することを目的とする。   An object of this invention is to provide the concrete placement method which can prevent isolation | separation of the aggregate of concrete, when constructing a steel pipe concrete pillar.

請求項1に記載のコンクリート打設方法は、柱(例えば、後述の鋼管コンクリート柱40)のコンクリート打設方法であって、コンクリートが収容されるホッパ(例えば、後述のホッパ10)と、当該ホッパから延びて少なくとも一部の内面同士が密着した筒状でありかつ可撓性を有するコンクリート供給管(例えば、後述のコンクリート供給管20)と、を備えるコンクリート打設治具(例えば、後述のコンクリート打設治具1)を用意しておき、前記柱の型枠((例えば、後述の鋼管41)を建て込む工程(例えば、後述のステップS1)と、当該型枠の直上に前記ホッパを配置するとともに、前記コンクリート供給管を当該型枠内で柱軸に沿って配置する工程(例えば、後述のステップS3)と、前記ホッパ内のコンクリートを、前記コンクリート供給管の内部を通して前記鋼管内に落し込む工程(例えば、後述のステップS4)と、を備えることを特徴とする。   The concrete placement method according to claim 1 is a concrete placement method for a column (for example, a steel pipe concrete column 40 described later), a hopper (for example, a hopper 10 described later) in which concrete is accommodated, and the hopper. And a concrete supply pipe (for example, concrete supply pipe 20 described later) having a cylindrical shape in which at least some of the inner surfaces are in close contact with each other and having flexibility. A placing jig 1) is prepared, and a step (for example, step S1 to be described later) in which the pillar formwork (for example, a steel pipe 41 described later) is built, and the hopper is disposed immediately above the formwork. And a step of arranging the concrete supply pipe along the column axis in the mold (for example, step S3 described later), and the concrete in the hopper, Step On drop in said steel tube through the interior of the Nkurito supply pipe (e.g., step S4 described later), characterized in that it comprises a a.

ここで、前記コンクリート柱は、鋼管(例えば、後述の鋼管41)と、当該鋼管内に充填されたコンクリート(例えば、後述のコンクリート42)と、を備える鋼管コンクリート柱(例えば、後述の鋼管コンクリート柱40)であり、前記型枠は、前記鋼管であることが好ましい。   Here, the concrete column includes a steel pipe concrete column (for example, a later-described steel pipe concrete column) including a steel pipe (for example, a later-described steel tube 41) and concrete (for example, a later-described concrete 42) filled in the steel pipe. 40), and the mold is preferably the steel pipe.

この発明によれば、コンクリート供給管を、可撓性を有する材料で形成しかつ少なくとも一部の内面同士が密着した筒状としたので、ホッパからコンクリート供給管にコンクリートを供給すると、コンクリート供給管のうちコンクリート体に押された部分のみが膨れて、コンクリート供給管のコンクリート体よりも下側や上側の部分は依然として内面同士が密着した状態、つまり潰れた状態である。したがって、コンクリート体がコンクリート供給管に包まれた状態で落下するので、コンクリート体に加わる衝撃を確実に緩和でき、コンクリート体の骨材の分離を防止しながらコンクリートを打設できる。特に、鋼管コンクリート柱にコンクリートを打設する場合には、コンクリートの落下高さが高くなるため、顕著な効果がある。   According to the present invention, since the concrete supply pipe is formed of a flexible material and has a cylindrical shape in which at least some of the inner surfaces are in close contact with each other, when the concrete is supplied from the hopper to the concrete supply pipe, the concrete supply pipe Of these, only the portion pressed by the concrete body swells, and the lower and upper portions of the concrete supply pipe are still in contact with each other, that is, in a crushed state. Therefore, since the concrete body falls while being wrapped in the concrete supply pipe, the impact applied to the concrete body can be reliably mitigated, and the concrete can be placed while preventing the separation of the aggregate of the concrete body. In particular, when concrete is cast on a steel pipe concrete column, the drop height of the concrete increases, so that there is a remarkable effect.

請求項2に記載のコンクリート打設方法は、前記コンクリート供給管の先端には、キャップ(例えば、後述のキャップ30)が取り付けられ、当該キャップには、複数の開口部(例えば、後述の開口部31)が形成されていることを特徴とする。   In the concrete placing method according to claim 2, a cap (for example, a cap 30 described later) is attached to a tip of the concrete supply pipe, and a plurality of openings (for example, an opening described later) is attached to the cap. 31) is formed.

この発明によれば、コンクリート供給管の先端にキャップを取り付けて、このキャップに複数の開口部を形成したので、落下するコンクリート体がこのキャップで受け止められて、その後、開口部から吐出されるので、コンクリート体に加わる衝撃をさらに緩和できる。
また、コンクリートを打設する際、コンクリート供給管の先端に取り付けたキャップが、既に流し込んだコンクリートに埋まった状態で、コンクリート供給管の内部を通してコンクリートを落とし込むことにより、コンクリートに空気が混入するのを防止できる。
According to the present invention, the cap is attached to the tip of the concrete supply pipe, and a plurality of openings are formed in the cap. Therefore, the falling concrete body is received by the cap and is then discharged from the opening. The impact on the concrete body can be further reduced.
In addition, when placing concrete, the cap attached to the tip of the concrete supply pipe is buried in the concrete that has already been poured in, and the concrete is dropped through the inside of the concrete supply pipe to prevent air from entering the concrete. Can be prevented.

請求項3に記載のコンクリート打設方法は、前記キャップと前記ホッパとは、ワイヤ(例えば、後述のワイヤ34)で連結されることを特徴とする。   The concrete placement method according to claim 3 is characterized in that the cap and the hopper are connected by a wire (for example, a wire 34 described later).

この発明によれば、キャップとホッパとをワイヤで連結したので、コンクリート供給管の先端からキャップが脱落するのを防止できる。   According to this invention, since the cap and the hopper are connected by the wire, it is possible to prevent the cap from dropping from the tip of the concrete supply pipe.

本発明によれば、コンクリート供給管を、可撓性を有する材料で形成内面同士が密着した筒状としたので、ホッパからコンクリート供給管にコンクリートを供給すると、コンクリート供給管のうちコンクリート体に押された部分のみが膨れて、コンクリート供給管のコンクリート体よりも下側や上側の部分は依然として内面同士が密着した状態、つまり潰れた状態である。したがって、コンクリート体がコンクリート供給管に包まれた状態で落下するので、コンクリート体に加わる衝撃を確実に緩和でき、コンクリート体の骨材の分離を防止しながらコンクリートを打設できる。   According to the present invention, the concrete supply pipe is made of a flexible material and has a cylindrical shape whose inner surfaces are in close contact with each other. Therefore, when concrete is supplied from the hopper to the concrete supply pipe, the concrete supply pipe is pressed against the concrete body. Only the portion that has been swelled is expanded, and the lower and upper portions of the concrete supply pipe are still in contact with each other, that is, in a crushed state. Therefore, since the concrete body falls while being wrapped in the concrete supply pipe, the impact applied to the concrete body can be reliably mitigated, and the concrete can be placed while preventing the separation of the aggregate of the concrete body.

本発明の一実施形態に係るコンクリート打設方法に用いられるコンクリート打設治具の側面図である。It is a side view of the concrete placement jig used for the concrete placement method concerning one embodiment of the present invention. 前記実施形態に係るコンクリート打設治具のキャップ斜視図である。It is a cap perspective view of the concrete placement jig concerning the embodiment. 前記実施形態に係るコンクリート打設方法によりコンクリートを打設する手順のフローチャートである。It is a flowchart of the procedure which places concrete by the concrete placement method which concerns on the said embodiment. 前記実施形態に係るコンクリート打設方法によりコンクリートを打設する手順を説明するための側断面図(その1)である。It is a sectional side view (the 1) for demonstrating the procedure which places concrete by the concrete placement method which concerns on the said embodiment. 前記実施形態に係るコンクリート打設方法によりコンクリートを打設する手順を説明するための側断面図(その2)である。It is a sectional side view (the 2) for demonstrating the procedure which places concrete by the concrete placement method which concerns on the said embodiment. 前記実施形態に係るコンクリート打設方法によりコンクリートが落下する状態を示す側断面図である。It is a sectional side view which shows the state in which concrete falls by the concrete placement method which concerns on the said embodiment. 前記実施形態に係るコンクリート打設方法によりコンクリートを打設する手順を説明するための側断面図(その3)である。It is a sectional side view (the 3) for demonstrating the procedure which places concrete by the concrete placement method which concerns on the said embodiment.

以下、本発明の一実施形態について、図面を参照しながら説明する。
図1は、本発明の一実施形態に係るコンクリート打設方法に用いられるコンクリート打設治具1の側面図である。
コンクリート打設治具1は、コンクリートが収容されるホッパ10と、このホッパ10から延びる筒状のコンクリート供給管20と、このコンクリート供給管20の先端に取り付けられたキャップ30と、を備える。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a side view of a concrete placing jig 1 used in a concrete placing method according to an embodiment of the present invention.
The concrete placing jig 1 includes a hopper 10 in which concrete is accommodated, a cylindrical concrete supply pipe 20 extending from the hopper 10, and a cap 30 attached to the tip of the concrete supply pipe 20.

ホッパ10は、上面が開放された箱状である。このホッパ10は、下方に向かうに従って内径が細くなる漏斗状であり、このホッパ10の下端には、リモコン操作により開閉可能な排出口11が設けられている。   The hopper 10 has a box shape with an upper surface opened. The hopper 10 has a funnel shape in which the inner diameter becomes thinner as it goes downward, and a discharge port 11 that can be opened and closed by remote control operation is provided at the lower end of the hopper 10.

コンクリート供給管20は、ホッパ10の排出口11に接続されている。このコンクリート供給管20は、ポリ塩化ビニルで形成されて可撓性を有しており、内面同士が密着した筒状となっている。このコンクリート供給管20には、先端から所定間隔例えば50cmおきに、目印21がつけられている。   The concrete supply pipe 20 is connected to the discharge port 11 of the hopper 10. The concrete supply pipe 20 is made of polyvinyl chloride, has flexibility, and has a cylindrical shape in which inner surfaces are in close contact with each other. The concrete supply pipe 20 is provided with marks 21 at predetermined intervals, for example, every 50 cm from the tip.

図2は、キャップ30の斜視図である。
キャップ30は、先端に向かうに従って細くなる形状であり、このキャップ30には、複数の開口部31が形成されている。
具体的には、このキャップ30は、円筒形状の基部32と、この基部32の先端縁から延出して互いに接合された帯状の帯状部材33と、を備える。上述の開口部31は、これら帯状部材33同士の隙間となっている。
キャップ30の基部32とホッパ10とは、ワイヤ34で連結されている。
FIG. 2 is a perspective view of the cap 30.
The cap 30 has a shape that becomes thinner toward the tip, and a plurality of openings 31 are formed in the cap 30.
Specifically, the cap 30 includes a cylindrical base portion 32 and a belt-like belt-like member 33 that extends from the tip edge of the base portion 32 and is joined to each other. The opening 31 described above is a gap between the band-shaped members 33.
The base 32 of the cap 30 and the hopper 10 are connected by a wire 34.

以下、本発明のコンクリート打設治具1を用いて、鋼管コンクリート柱40のコンクリートを打設する手順について、図3のフローチャートを参照しながら説明する。
鋼管コンクリート柱40は、筒状で下面が塞がれた型枠としての鋼管41と、この鋼管41内に充填されたコンクリート42と、を備えるものである(図7参照)。
Hereinafter, the procedure for placing the concrete of the steel pipe concrete pillar 40 using the concrete placing jig 1 of the present invention will be described with reference to the flowchart of FIG.
The steel pipe concrete pillar 40 is provided with a steel pipe 41 as a mold having a cylindrical shape whose lower surface is closed, and a concrete 42 filled in the steel pipe 41 (see FIG. 7).

ステップS1では、図4に示すように、鋼管コンクリート柱40の鋼管41を床躯体2上に建て込む。このとき、鋼管41の柱頭部近傍と床躯体2との間に転倒防止ワイヤ51を張って、鋼管41の転倒を防止する。その後、この鋼管41の建入れを調整する。   In step S1, the steel pipe 41 of the steel pipe concrete pillar 40 is built on the floor frame 2 as shown in FIG. At this time, the fall prevention wire 51 is stretched between the vicinity of the column head of the steel pipe 41 and the floor frame 2 to prevent the steel pipe 41 from falling. Thereafter, the installation of the steel pipe 41 is adjusted.

ステップS2では、図4に示すように、鋼管41を囲んで床躯体2上に仮設足場50を架設する。この仮設足場50は、ここでは、7段の枠組足場である。   In step S <b> 2, as shown in FIG. 4, a temporary scaffold 50 is installed on the floor frame 2 so as to surround the steel pipe 41. The temporary scaffold 50 is a seven-stage frame scaffold here.

ステップS3では、図5に示すように、コンクリート打設治具1を鋼管41にセットする。
すなわち、コンクリート打設治具1のホッパ10にコンクリートを収容し、その後、クレーン52によりこのホッパ10を吊り上げて、鋼管41の直上に配置する。また、コンクリート供給管20を鋼管41内に投入して、コンクリート供給管20を鋼管41の中心軸つまり柱軸に沿って配置する。
In step S3, the concrete placing jig 1 is set on the steel pipe 41 as shown in FIG.
That is, the concrete is accommodated in the hopper 10 of the concrete placing jig 1, and then the hopper 10 is lifted by the crane 52 and disposed immediately above the steel pipe 41. Further, the concrete supply pipe 20 is put into the steel pipe 41, and the concrete supply pipe 20 is arranged along the central axis of the steel pipe 41, that is, the column axis.

ステップS4では、鋼管41内にコンクリートを打設する。
すなわち、リモコン操作により、ホッパ10の排出口11を適宜開閉して、ホッパ10内のコンクリートを、コンクリート供給管20の内部を通して鋼管41内に落し込む。
In step S4, concrete is placed in the steel pipe 41.
That is, the discharge port 11 of the hopper 10 is appropriately opened and closed by a remote control operation, and the concrete in the hopper 10 is dropped into the steel pipe 41 through the concrete supply pipe 20.

コンクリート供給管20にコンクリート体43を供給すると、図6に示すように、コンクリート供給管20のうちコンクリート体43に押された部分のみが膨れて、コンクリート供給管のコンクリート体43よりも下側や上側の部分は依然として内面同士が密着した状態、つまり潰れた状態となる。したがって、コンクリート体43はコンクリート供給管20に包まれた状態で落下する。   When the concrete body 43 is supplied to the concrete supply pipe 20, as shown in FIG. 6, only the portion pressed by the concrete body 43 in the concrete supply pipe 20 swells, and the concrete supply pipe 20 is lower than the concrete body 43. The upper part is still in a state where the inner surfaces are in close contact with each other, that is, in a crushed state. Therefore, the concrete body 43 falls in a state wrapped in the concrete supply pipe 20.

その後、図7に示すように、クレーン52によりコンクリート供給管20を図7中矢印方向に徐々に引き上げて、キャップ30が既に流し込んだコンクリート内に埋まった状態を維持しながら、鋼管41の上端近傍までコンクリートを打設する。   Thereafter, as shown in FIG. 7, the concrete supply pipe 20 is gradually pulled up in the direction of the arrow in FIG. 7 by the crane 52, and the vicinity of the upper end of the steel pipe 41 is maintained while maintaining the state where the cap 30 is already buried in the poured concrete. Put concrete up to.

このとき、スチールテープ53でコンクリート42の表面の高さ位置を測定するとともに、コンクリート供給管20の目印21によりコンクリート供給管20の高さ位置を確認して、コンクリート供給管20の先端に取り付けられたキャップ30がコンクリート42内に僅かに埋まるようにする。   At this time, the height position of the surface of the concrete 42 is measured with the steel tape 53, and the height position of the concrete supply pipe 20 is confirmed by the mark 21 of the concrete supply pipe 20 and attached to the tip of the concrete supply pipe 20. The cap 30 is slightly buried in the concrete 42.

本実施形態によれば、以下のような効果がある。
(1)コンクリート供給管20を、可撓性を有する材料で形成しかつ内面同士が密着した筒状としたので、ホッパ10からコンクリート供給管20にコンクリート42を供給すると、コンクリート供給管20のうちコンクリート体43に押された部分のみが膨れて、コンクリート供給管20のコンクリート体43よりも下側や上側の部分は依然として内面同士が密着した状態、つまり潰れた状態となる。したがって、コンクリート体43がコンクリート供給管20に包まれた状態で落下するので、コンクリート体43に加わる衝撃を確実に緩和でき、コンクリート体43の骨材の分離を防止しながらコンクリート42を打設できる。
According to this embodiment, there are the following effects.
(1) Since the concrete supply pipe 20 is formed of a flexible material and has a cylindrical shape whose inner surfaces are in close contact with each other, when the concrete 42 is supplied from the hopper 10 to the concrete supply pipe 20, the concrete supply pipe 20 Only the portion pressed by the concrete body 43 swells, and the lower and upper portions of the concrete supply pipe 20 are still in a state where the inner surfaces are in close contact with each other, that is, in a crushed state. Therefore, since the concrete body 43 falls in a state of being wrapped in the concrete supply pipe 20, the impact applied to the concrete body 43 can be surely mitigated, and the concrete 42 can be placed while preventing the separation of the aggregate of the concrete body 43. .

(2)コンクリート供給管20の先端にキャップ30を取り付けて、このキャップ30に複数の開口部31を形成したので、落下するコンクリート体43がこのキャップ30で受け止められて、その後、開口部31から吐出されるので、コンクリート体43に加わる衝撃をさらに緩和できる。
また、コンクリートを打設する際、コンクリート供給管20の先端に取り付けたキャップ30が、既に流し込んだコンクリートに埋まった状態で、コンクリート供給管20の内部を通してコンクリートを落とし込むことにより、コンクリートに空気が混入するのを防止できる。
(2) Since the cap 30 is attached to the tip of the concrete supply pipe 20 and the plurality of openings 31 are formed in the cap 30, the falling concrete body 43 is received by the cap 30, and then from the opening 31. Since it is discharged, the impact applied to the concrete body 43 can be further alleviated.
In addition, when placing concrete, the cap 30 attached to the tip of the concrete supply pipe 20 is buried in the already poured concrete, and the concrete is dropped through the concrete supply pipe 20 so that air is mixed into the concrete. Can be prevented.

(2)キャップ30の基部32とホッパ10とをワイヤ34で連結したので、コンクリート供給管の先端からキャップが脱落するのを防止できる。   (2) Since the base portion 32 of the cap 30 and the hopper 10 are connected by the wire 34, the cap can be prevented from falling off from the tip of the concrete supply pipe.

なお、本発明は前記実施形態に限定されるものではなく、本発明の目的を達成できる範囲での変形、改良等は本発明に含まれるものである。   It should be noted that the present invention is not limited to the above-described embodiment, and modifications, improvements, etc. within a scope that can achieve the object of the present invention are included in the present invention.

1…コンクリート打設治具
2…床躯体
10…ホッパ
11…排出口
20…コンクリート供給管
21…目印
30…キャップ
31…開口部
32…基部
33…帯状部材
34…ワイヤ
40…鋼管コンクリート柱
41…鋼管(型枠)
42…コンクリート
43…コンクリート体
50…仮設足場
51…転倒防止ワイヤ
52…クレーン
53…スチールテープ
DESCRIPTION OF SYMBOLS 1 ... Concrete placement jig 2 ... Floor frame 10 ... Hopper 11 ... Discharge port 20 ... Concrete supply pipe 21 ... Mark 30 ... Cap 31 ... Opening 32 ... Base 33 ... Band-shaped member 34 ... Wire 40 ... Steel pipe concrete pillar 41 ... Steel pipe (formwork)
42 ... Concrete 43 ... Concrete body 50 ... Temporary scaffolding 51 ... Tumble prevention wire 52 ... Crane 53 ... Steel tape

Claims (3)

柱のコンクリート打設方法であって、
コンクリートが収容されるホッパと、当該ホッパから延びて少なくとも一部の内面同士が密着した筒状でありかつ可撓性を有するコンクリート供給管と、を備えるコンクリート打設治具を用意しておき、
前記柱の型枠を建て込む工程と、
当該型枠の直上に前記ホッパを配置するとともに、前記コンクリート供給管を当該型枠内で柱軸に沿って配置する工程と、
前記ホッパ内のコンクリートを、前記コンクリート供給管の内部を通して前記型枠内に落し込む工程と、を備えることを特徴とするコンクリート打設方法。
A method of placing concrete in a pillar,
Preparing a concrete placing jig comprising a hopper for containing concrete, and a cylindrical and flexible concrete supply pipe extending from the hopper and having at least a part of inner surfaces in close contact with each other,
Building the pillar formwork;
Placing the hopper directly above the formwork, and placing the concrete supply pipe along the column axis in the formwork;
Dropping the concrete in the hopper into the mold through the inside of the concrete supply pipe.
前記コンクリート供給管の先端には、キャップが取り付けられ、
当該キャップには、複数の開口部が形成されていることを特徴とする請求項1に記載のコンクリート打設方法。
A cap is attached to the tip of the concrete supply pipe,
The concrete placing method according to claim 1, wherein a plurality of openings are formed in the cap.
前記キャップと前記ホッパとは、ワイヤで連結されることを特徴とする請求項2に記載のコンクリート打設方法。   The concrete placing method according to claim 2, wherein the cap and the hopper are connected by a wire.
JP2013240588A 2013-11-21 2013-11-21 Concrete placement method Active JP6322392B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013240588A JP6322392B2 (en) 2013-11-21 2013-11-21 Concrete placement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013240588A JP6322392B2 (en) 2013-11-21 2013-11-21 Concrete placement method

Publications (2)

Publication Number Publication Date
JP2015101821A true JP2015101821A (en) 2015-06-04
JP6322392B2 JP6322392B2 (en) 2018-05-09

Family

ID=53377779

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013240588A Active JP6322392B2 (en) 2013-11-21 2013-11-21 Concrete placement method

Country Status (1)

Country Link
JP (1) JP6322392B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691681A (en) * 2020-06-09 2020-09-22 浙江东南网架股份有限公司 Method for mounting outer frame cylinder structure of diagonal steel pipe grid column
CN112376567A (en) * 2020-11-05 2021-02-19 中国建筑土木建设有限公司 Large-volume concrete chute pouring system and construction method thereof
CN112459070A (en) * 2020-11-30 2021-03-09 四川仟坤建设集团有限责任公司 Large-volume concrete pouring device and pouring method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS547017U (en) * 1977-06-17 1979-01-18
JPS5519334A (en) * 1978-07-25 1980-02-12 Takenaka Komuten Co Method and device for feeding fresh concrete with large fall
US4838465A (en) * 1983-06-02 1989-06-13 Lynn Metzger Guide bar for a hose which is physically manipulated by workers to deliver a high density material to a predeterminated site
JPH04119053U (en) * 1991-04-08 1992-10-23 株式会社フジタ Steel pipe column filling concrete placement equipment
JPH0711606A (en) * 1993-06-25 1995-01-13 Mitsui Constr Co Ltd Expansion tremie pipe
JP2000110352A (en) * 1999-07-21 2000-04-18 Nishimatsu Constr Co Ltd Concrete placing method and concrete placing method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS547017U (en) * 1977-06-17 1979-01-18
JPS5519334A (en) * 1978-07-25 1980-02-12 Takenaka Komuten Co Method and device for feeding fresh concrete with large fall
US4838465A (en) * 1983-06-02 1989-06-13 Lynn Metzger Guide bar for a hose which is physically manipulated by workers to deliver a high density material to a predeterminated site
JPH04119053U (en) * 1991-04-08 1992-10-23 株式会社フジタ Steel pipe column filling concrete placement equipment
JPH0711606A (en) * 1993-06-25 1995-01-13 Mitsui Constr Co Ltd Expansion tremie pipe
JP2000110352A (en) * 1999-07-21 2000-04-18 Nishimatsu Constr Co Ltd Concrete placing method and concrete placing method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691681A (en) * 2020-06-09 2020-09-22 浙江东南网架股份有限公司 Method for mounting outer frame cylinder structure of diagonal steel pipe grid column
CN112376567A (en) * 2020-11-05 2021-02-19 中国建筑土木建设有限公司 Large-volume concrete chute pouring system and construction method thereof
CN112459070A (en) * 2020-11-30 2021-03-09 四川仟坤建设集团有限责任公司 Large-volume concrete pouring device and pouring method thereof
CN112459070B (en) * 2020-11-30 2022-02-08 四川仟坤建设集团有限责任公司 Large-volume concrete pouring device and pouring method thereof

Also Published As

Publication number Publication date
JP6322392B2 (en) 2018-05-09

Similar Documents

Publication Publication Date Title
JP6322392B2 (en) Concrete placement method
JP2008088696A (en) Tunnel lining construction method
JP2017210865A5 (en)
JP4902609B2 (en) Reinforcing body for steel pipe column and method for reinforcing steel pipe column using the reinforcing body
CN106284428A (en) A kind of concrete column method for supporting of building structure post-cast strip
JP2008088691A (en) Tunnel lining form and tunnel lining construction method
JP2013159905A (en) Cooling method of concrete structure
JP7076363B2 (en) How to place tunnel lining concrete
KR101218185B1 (en) Vertically moving slipform device by winch
JP2018059357A (en) Method for introducing prestress to cast in-situ concrete
KR101324365B1 (en) Flange for Underwater Concrete Casting and Method for Underwater Concrete Casting Thereof
JP4904072B2 (en) Manufacturing method of pretension member
JP4815262B2 (en) Tunnel lining method and formwork apparatus
CN104164974A (en) Building casting method and casting mold system used for building casting method
JP5638435B2 (en) Column fixing method, column used in the method, concrete hopper used in the method
JP7370213B2 (en) Concrete pouring hopper
KR20150010899A (en) Concrete divider for outlet can be opened and closed
JP6430146B2 (en) Steel pipe covered concrete pile
CN203008239U (en) Reinforcement steel protection layer cushion block
JP6767853B2 (en) Building demolition material unloading system and building demolition material unloading method
KR200445586Y1 (en) Level spacer for ground concrete work
CN207032043U (en) Box beam door opening support stamping die sandbox
JP4813219B2 (en) Brickwork method for converter
KR20160117940A (en) Transport carrier of a construction materials
JP5777050B2 (en) Side wall construction method for concrete structures

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160721

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170425

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170530

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170711

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20171102

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20171207

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180316

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180409

R150 Certificate of patent or registration of utility model

Ref document number: 6322392

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250