JP2008088691A - Tunnel lining form and tunnel lining construction method - Google Patents

Tunnel lining form and tunnel lining construction method Download PDF

Info

Publication number
JP2008088691A
JP2008088691A JP2006270435A JP2006270435A JP2008088691A JP 2008088691 A JP2008088691 A JP 2008088691A JP 2006270435 A JP2006270435 A JP 2006270435A JP 2006270435 A JP2006270435 A JP 2006270435A JP 2008088691 A JP2008088691 A JP 2008088691A
Authority
JP
Japan
Prior art keywords
concrete
ceiling
tunnel lining
tunnel
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006270435A
Other languages
Japanese (ja)
Inventor
Hidetoshi Hara
秀利 原
Yukihisa Inagawa
雪久 稲川
Tomihiro Tanase
富弘 棚瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Gifu Industry Co Ltd
Original Assignee
Maeda Corp
Gifu Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp, Gifu Industry Co Ltd filed Critical Maeda Corp
Priority to JP2006270435A priority Critical patent/JP2008088691A/en
Publication of JP2008088691A publication Critical patent/JP2008088691A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To reduce a volume of concrete placed in a space in which a concrete placed state cannot be visually confirmed, and to facilitate visual confirmation in a region in which the concrete placed state can be visually confirmed, in tunnel lining construction. <P>SOLUTION: A blow-up port 40 for supplying concrete 9 at high pressure is provided in an arch 13 being a part positioned below a ceiling 10 and adjacent to the ceiling 10 in a form 1A for tunnel lining. Pressure in the blow-up port 40 is sufficient for feeding the concrete 9 to be discharged from the blow-up port 40 above the form against gravity. A window 5c allowing the worker to observe the concrete 9 placed state is provided at the ceiling 10. Concrete is placed as horizontally as possible up to a position in which the concrete placing can be visually confirmed through the window 5c by using the form 1A. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明はトンネル覆工の施工技術に関する。   The present invention relates to a tunnel lining construction technique.

地山を掘削して出来た素堀トンネルの掘削面(内壁面)をコンクリートで被覆するトンネル覆工工事では、まず素堀トンネルの掘削面にコンクリートを吹き付ける一次覆工を行う場合が多い。その後、一次覆工後のトンネル掘削面にさらにコンクリートで被覆する二次覆工を行う。   In tunnel lining work in which the excavation surface (inner wall surface) of a moat tunnel made by excavating a natural ground is covered with concrete, first, primary lining is often performed by spraying concrete onto the excavation surface of the moat tunnel. After that, a secondary lining is performed in which the tunnel excavation surface after the primary lining is further covered with concrete.

上記の二次覆工は、いわゆるセントルと称される型枠を用いてコンクリートを打設する。なお、この明細書で「打設」とは、養生硬化していないコンクリートを型枠とトンネルの内壁面との間へ充填することをいう。   In the secondary lining, concrete is placed using a so-called centle formwork. In this specification, “placement” means filling concrete that has not been cured and hardened between the mold and the inner wall surface of the tunnel.

二次覆工で用いられる型枠1は、図6,7から判るように、例えば、断面円弧形のいわゆる「かまぼこ形」であり、一次覆工終了後のトンネル(以下、単にトンネル)3の長手方向における所定位置に設置される。   As can be seen from FIGS. 6 and 7, the formwork 1 used in the secondary lining is, for example, a so-called “kamaboko shape” having an arc cross section, and a tunnel (hereinafter simply referred to as a tunnel) 3 after the primary lining is completed. It is installed at a predetermined position in the longitudinal direction.

型枠1には、その壁面全体に開閉可能な窓部5が多数設けられている。また、型枠1の内部には、二次覆工用のコンクリートを打設するコンクリート搬送管7や、打設されたコンクリート9を型枠1とトンネル内壁面3aとの間に満遍なく行き渡らせるための締固めを行うバイブレータ8が装備されている。なお符号20で示すものは型枠1内に設けられている架台である。   The mold 1 is provided with a large number of windows 5 that can be opened and closed on the entire wall surface. In addition, in order to distribute the concrete transport pipe 7 for placing concrete for secondary lining and the placed concrete 9 uniformly between the mold 1 and the inner wall surface 3a of the tunnel, inside the mold 1 Is equipped with a vibrator 8 for compaction. In addition, what is shown with the code | symbol 20 is the mount frame provided in the formwork 1. FIG.

そして、窓部5から型枠内部にコンクリート搬送管7を投入し(図8参照)、コンクリート搬送管7からコンクリート9を流し込むことで打設し、所定の肉厚を有するトンネル3の覆工を行う。   Then, the concrete conveying pipe 7 is thrown into the formwork from the window 5 (see FIG. 8), and the concrete 9 is poured from the concrete conveying pipe 7 so as to cover the tunnel 3 having a predetermined thickness. Do.

コンクリート搬送管7から排出されたコンクリート9は重力により下方に流れ(図7の矢印参照)、トンネル3の下方部分から徐々に上方に向けて充填されて行く。充填量の増加に従い、下方の窓部5から型枠内に投入していたコンクリート搬送管7は、やがてその窓部5から投入できなくなる。その場合、それまで利用していた窓部5を閉じて、今度は、当該窓部5よりも別の(通常は上方に位置する)窓部5からコンクリート搬送管7を出し、同様にコンクリート9を排出して、さらに打設を行う。   The concrete 9 discharged from the concrete transfer pipe 7 flows downward due to gravity (see the arrow in FIG. 7), and is gradually filled upward from the lower part of the tunnel 3. As the filling amount increases, the concrete conveying pipe 7 that has been put into the mold from the lower window portion 5 can no longer be put into the window portion 5. In that case, the window part 5 used so far is closed, and this time, the concrete conveying pipe 7 is taken out from the window part 5 different from the window part 5 (usually located above), and similarly the concrete 9 Is discharged and further placement is performed.

また作業者は、窓部5から打設状態を観察し、コンクリート9が行き渡っていない箇所の有無を調べ、充填漏れがないことを確認しながら作業を進める。   Further, the operator observes the placement state from the window portion 5 and checks the presence or absence of a portion where the concrete 9 is not spread, and proceeds with the operation while confirming that there is no filling leakage.

さらに、バイブレータ8を窓部5から投入して締固めを実施し、既述のように型枠1とトンネル内壁面3aとの間にコンクリート9が十分に行き渡るようにする。   Further, the vibrator 8 is inserted from the window portion 5 and compacted so that the concrete 9 is sufficiently distributed between the mold 1 and the tunnel inner wall surface 3a as described above.

一方、型枠1の最上部を天井部といい、符号10で示す。天井部10とトンネル3との間の空間部(以下、天端部)15にも、その下方のアーチ部13と同様にコンクリート9が充填される。   On the other hand, the uppermost part of the formwork 1 is referred to as a ceiling part and is denoted by reference numeral 10. The space 9 (hereinafter referred to as the top end portion) 15 between the ceiling portion 10 and the tunnel 3 is also filled with the concrete 9 like the arch portion 13 below.

天井部10のコンクリート打設は、図8に示すように、天井部10のうちトンネル3の横断面における正中線Cと型枠1の内面の交点iに吹上口11を設け、この吹上口11からコンクリート9を型枠外部に排出することにより行う。なお、便宜上、この明細書にお
いて天井部10とは、前記交点iに接線Tを引いたときに、接線Tが、型枠1の外周面と交叉することで画成される型枠1における円弧部分を横断面に有する部分をいうものとする。
As shown in FIG. 8, the concrete placement of the ceiling part 10 is provided with a blowing outlet 11 at the intersection point i between the median line C in the cross section of the tunnel 3 and the inner surface of the mold 1 in the ceiling part 10. The concrete 9 is discharged from the mold outside the mold. For the sake of convenience, in this specification, the ceiling portion 10 refers to an arc in the mold 1 that is defined by the tangent T intersecting the outer peripheral surface of the mold 1 when the tangent T is drawn at the intersection i. The part which has a part in a cross section shall be said.

また、天井部10にも窓部5と同様の開閉自在な窓部が設けられており、これを天井窓と呼称し符号5cで示す。天井窓5cは天井部10の最上位に位置する。なお正中線Cは、型枠1の横断面における中央に位置するものであるから型枠1の最上位を通る線である。   Further, the ceiling portion 10 is provided with an openable and closable window portion similar to the window portion 5, which is referred to as a ceiling window and denoted by reference numeral 5 c. The ceiling window 5 c is located at the top of the ceiling portion 10. The midline C is a line passing through the top of the mold 1 because it is located at the center of the cross section of the mold 1.

天井部10より下方に位置するアーチ部13までは、コンクリート9の打設状態を天井窓5c及びそれ以外の窓部5から作業者が確認することが可能である。これに対して、天井部10への打設を行う場合、その打設状態は窓部5を閉じた後は、視認することができない。   From the ceiling window 5 c and the other window parts 5, the operator can confirm the placement state of the concrete 9 up to the arch part 13 positioned below the ceiling part 10. On the other hand, when placing on the ceiling portion 10, the placement state cannot be visually recognized after the window portion 5 is closed.

それでも、最終的には、型枠上部の吹上口11からコンクリートを噴出させて天端部15への充填をしなければならない。従来の方法では、このような状態での施工を必要とする天端部15が大きく、天端部15が大きいほどコンクリートの充填性を確実にすることが困難である。なお、図8に示す符合Aで示される範囲は、アーチ部13の窓部5から出したコンクリート搬送管7から排出されたコンクリートだけでは、充填が不可能な領域(空間)であり、吹上口11からのコンクリート充填を必要とする範囲である。そして、当該範囲Aの存在が天端部15を大きくする要因でもあった。   Nevertheless, finally, the top end portion 15 must be filled by ejecting concrete from the blowing port 11 at the upper part of the formwork. In the conventional method, the top end portion 15 that needs to be constructed in such a state is larger, and the larger the top end portion 15 is, the more difficult it is to ensure the concrete filling property. In addition, the range shown by the symbol A shown in FIG. 8 is an area (space) in which filling is impossible only with the concrete discharged from the concrete conveying pipe 7 that has come out from the window portion 5 of the arch portion 13. 11 is a range that requires concrete filling from 11. The presence of the range A is also a factor that enlarges the top end 15.

また、型枠側部では上方に向かうに従い勾配が緩やかになるため、打設したコンクリートが流下する位置までしか打設できない。したがって、かかる原因によってもアーチ部上部における打設に時間を要するという問題がある。   Further, since the gradient becomes gentler toward the upper side at the mold side, it can only be placed up to a position where the poured concrete flows down. Accordingly, there is a problem that it takes time to drive the upper portion of the arch portion due to such a cause.

さらに、窓部5のコンクリート搬送管7による充填作業では、コンクリートを型枠内に自然落下により流し込むので、水平に打設することが困難であり、打設状態を視認することが難しい。
特開2003−227297号公報
Furthermore, in the filling operation by the concrete conveying pipe 7 of the window portion 5, since concrete is poured into the mold by natural fall, it is difficult to place it horizontally and it is difficult to visually check the placement state.
JP 2003-227297 A

本発明は上記事情に鑑みてされたものであり、その解決しようとする課題は、トンネル覆工の施工において、打設状態が視認できない空間(天端部等)へのコンクリート打設量をできるだけ少なくし、一方、打設状態が視認できる領域での視認を容易にする技術を提供することにある。   The present invention has been made in view of the above circumstances, and the problem to be solved is that the concrete placement amount in a space where the placement state cannot be visually recognized (such as the top end portion) can be reduced in the tunnel lining construction. On the other hand, it is to provide a technique for facilitating visual recognition in an area where the placement state can be visually recognized.

本発明のトンネル覆工用の型枠は、トンネル覆工用の型枠において、前記型枠のうちその天井部よりも下方に位置し、かつ当該天井部に隣接する部分であるアーチ部には、コンクリートを加圧して噴出する吹上口が設けられ、前記天井部には、前記コンクリートの打設状態を観察する窓部が設けられているとともに、当該窓部の近傍には型枠の最上位に位置する最上位吹上口が設けられていることを特徴とする。   The tunnel lining formwork of the present invention is a tunnel lining formwork, wherein the arch part is located below the ceiling part of the formwork and adjacent to the ceiling part. A blow-up port for pressing and discharging the concrete is provided, and the ceiling portion is provided with a window portion for observing the placement state of the concrete, and in the vicinity of the window portion, the uppermost position of the mold The uppermost blowing outlet located in is provided.

前記アーチ部に設けられている吹上口から加圧によって吐出されるコンクリートは、重力に抗して型枠の上方に向けて打設することも可能であるので、当該吹上口から供給されるコンクリートを、短時間に前記天井部の最上位付近まで供給することできる。   Since the concrete discharged by pressurization from the air outlet provided in the arch portion can be placed toward the upper side of the mold against gravity, the concrete supplied from the air outlet Can be supplied to the vicinity of the top of the ceiling in a short time.

したがって、その後に最上位吹上口によるコンクリート充填がなされる天端部の容積を
小さくすることができる。
Accordingly, it is possible to reduce the volume of the top end portion where the concrete is filled by the uppermost blowing outlet thereafter.

最上位吹上口もアーチ部の吹上口も十分高圧な吐出圧により前記コンクリートを吐出するものであり、前記アーチ部に設けられている吹上口は、前記天井部を囲繞するように複数配置することが望ましい。   The uppermost blowing outlet and the blowing outlet of the arch part discharge the concrete with a sufficiently high discharge pressure, and a plurality of blowing openings provided in the arch part are arranged so as to surround the ceiling part. Is desirable.

この場合、アーチ部の吹上口を切り替えて打設することで、天井部の最上位付近まで水平にコンクリートが打設することが可能であり、作業者は、アーチ部の吹上口によるコンクリートの打設状態を、天井部の窓部から容易に確認できる。   In this case, it is possible to place the concrete horizontally up to the vicinity of the top of the ceiling by switching the blast of the arch part. The installation state can be easily confirmed from the window of the ceiling.

この結果、アーチ部の吹上口からの吐出によって打設された天井部周りのコンクリートには、天井部の窓部から作業者の目が十分に行き届くようにできるので、打設の際に型枠とトンネル内壁面との間にコンクリートが行き渡っていないことに起因する、たとえば隙間の発生を抑制することができる。   As a result, the concrete around the ceiling placed by discharging from the air outlet of the arch can be made to reach the operator's eyes sufficiently from the window of the ceiling. For example, it is possible to suppress the occurrence of a gap due to the fact that the concrete does not spread between the wall and the inner wall surface of the tunnel.

上記のような型枠を利用したトンネル覆工の施工は、前記アーチ部に設けられている吹上口からコンクリートを加圧して噴出させ、この吹上口の下方及び上方における型枠及びトンネルの間にコンクリートを充填し、打設面が水平になるように前記天井部の最上位付近までコンクリートを打設する工程を含むことを特徴とする。   The tunnel lining construction using the above-mentioned formwork is made by pressing concrete from the air outlet provided in the arch part and ejecting it between the formwork and the tunnel below and above this air outlet. The method includes filling concrete and placing the concrete up to the vicinity of the top of the ceiling so that the placing surface is horizontal.

前記複数の吹上口からコンクリートを吐出するにあたり、前記天井部周りにおいて、コンクリートがほぼ均一に供給されるように、当該複数の吹上口から吐出されるコンクリートの吐出量及び吐出時間を調整しながら吐出する工程を有するようにしてもよい。   When discharging concrete from the plurality of air outlets, the concrete is discharged while adjusting the discharge amount and time of the concrete discharged from the air outlets so that the concrete is supplied substantially uniformly around the ceiling. You may make it have the process to do.

前記コンクリートによる打設の位置が、前記天井部の最上位付近に到達した後、前記最上位吹上口からコンクリートを噴出させる工程を実施することを特徴とすることもできる。   It is also possible to carry out a step of ejecting concrete from the uppermost air outlet after the position of placing by the concrete reaches the uppermost vicinity of the ceiling portion.

前記コンクリートによる打設の位置が、前記天井部の最上位付近に達したら、当該打設部分にバイブレータで振動を与える工程を有することもできる。   When the concrete placement position reaches near the topmost position of the ceiling portion, a step of applying vibration to the placement portion with a vibrator may be included.

本発明のトンネル覆工の施工方法によれば、アーチ部の吹上口よりも上方にコンクリートを打設できるので、天端部15を小さくすることができる。よって、最上位吹上口によってなされるコンクリートの打設量及び打設時間をそれだけ減少させることができる。   According to the tunnel lining construction method of the present invention, since the concrete can be placed above the air outlet of the arch portion, the top end portion 15 can be made small. Therefore, it is possible to reduce the amount and time of placing concrete by the uppermost blowing outlet.

また、コンクリートを水平に打設することが容易になるので、天井部の窓部から作業者が打設状態を視認できる範囲を広げることができる。その結果、型枠とトンネル内壁面との間にコンクリートが行き渡っていないことに起因する隙間の発生を効果的に抑制することができる。   Moreover, since it becomes easy to place concrete concrete horizontally, the range which an operator can visually recognize the placement state from the window part of a ceiling part can be expanded. As a result, it is possible to effectively suppress the generation of a gap due to the fact that concrete does not spread between the formwork and the inner wall surface of the tunnel.

さらに、短時間で打設が完了するため、コンクリートの品質が向上する。   Furthermore, since the placement is completed in a short time, the quality of the concrete is improved.

以下、本発明のトンネル覆工用の型枠およびトンネル覆工の施工方法の実施の形態(以下、実施形態)を添付した図面を参照して説明する。   DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments of a tunnel lining form and a tunnel lining construction method of the present invention (hereinafter referred to as embodiments) will be described with reference to the accompanying drawings.

なお、従来技術と同一の部分には、同一の符号を付して説明を省略する。   In addition, the same code | symbol is attached | subjected to the part same as a prior art, and description is abbreviate | omitted.

図1〜5に示すように、トンネル覆工用の型枠1Aが従来の型枠1と相違する点は、次
の通りである。
(イ)型枠1Aのうちその天井部10よりも下方に位置し、かつ天井部10に隣接する部分であるアーチ部13に、コンクリート9を高圧で吹き上げる複数の吹上口40を設けたこと(図4,5参照)。
(ロ)吹上口40の高圧は、吹上口40から吐出されるコンクリート9を重力に抗して型枠1Aの上方へ向けるに十分な圧を有することにある(図4において吹上口40から上方に向かう矢印a参照)。
As shown in FIGS. 1 to 5, the tunnel lining mold 1 </ b> A is different from the conventional mold 1 as follows.
(A) A plurality of blast ports 40 for blowing concrete 9 at high pressure are provided in the arch portion 13 which is located below the ceiling portion 10 of the mold 1A and adjacent to the ceiling portion 10 ( (See FIGS. 4 and 5).
(B) The high pressure of the blow-up port 40 is to have sufficient pressure to direct the concrete 9 discharged from the blow-up port 40 upward of the mold 1A against gravity (in FIG. 4, upward from the blow-up port 40). See arrow a).

したがって、これら相違点及びそれらに関連する箇所につき、以下詳しく説明する。   Therefore, these differences and the parts related to them will be described in detail below.

吹上口40は、図5に示すように、天井部10の左右両側に2つずつ合計4つ配置され、その結果、型枠1Aの天井部10を囲繞するようになっている。   As shown in FIG. 5, a total of four blowing openings 40 are arranged on the left and right sides of the ceiling portion 10, and as a result, surround the ceiling portion 10 of the mold 1 </ b> A.

これら4つの吹上口40からコンクリート9を吐出するにあたり、天井部10周りにおいて、コンクリート9がほぼ均一に充填されるように、吐出されるコンクリート9の量を調整しながら吐出する。例えば、図5の左上に位置する吹上口40に係るコンクリート9の充填効率が悪く、他の吹上口40に係る打設領域に貯まるコンクリート9よりも少ない場合には、前記左上に位置する吹上口40からのコンクリート9の吐出量を他の吹上口40のそれよりも増やしたり、吐出時間を長くしたりする。すなわち、コンクリート9を圧入することで充填度を増大させ、どの吹上口40に係る打設であってもできる限り打設面が水平になるようにコンクリート9を打設する。   When discharging the concrete 9 from the four air outlets 40, the concrete 9 is discharged while adjusting the amount of the discharged concrete 9 so that the concrete 9 is almost uniformly filled around the ceiling portion 10. For example, when the filling efficiency of the concrete 9 related to the air outlet 40 located in the upper left of FIG. 5 is poor and less than the concrete 9 accumulated in the placement area related to the other air outlet 40, the air outlet located in the upper left The discharge amount of the concrete 9 from 40 is increased more than that of the other blowing openings 40, or the discharge time is lengthened. That is, the filling degree is increased by press-fitting the concrete 9, and the concrete 9 is placed so that the placement surface is as horizontal as possible regardless of the placement related to any air outlet 40.

また、勾配が緩くなる型枠1の上方では、コンクリート9の打設速度が遅くなり、従来の方法では充填密度が低下する問題があったが、本発明の方法では、吹上口40がコンクリート9を加圧して噴出させるので、吹上口40の下方にも上方にも打設可能で、いずれの側においても充填密度が高くなる。   In addition, the casting speed of the concrete 9 is slow above the mold 1 where the gradient becomes gentle, and the conventional method has a problem that the filling density is lowered. However, in the method of the present invention, the blowing port 40 is provided with the concrete 9. Is pressurized and ejected, so that it can be placed both below and above the blow-up port 40, and the packing density increases on either side.

この場合、短時間での打設が可能であるので、コンクリート9が固まるトラブルが抑制される。すなわち、コンクリート9の固化が進行しない状態で打設を完了することで、コンクリート9の充填度を飛躍的に増大させることができる。   In this case, since the placing in a short time is possible, the trouble that the concrete 9 hardens is suppressed. That is, the filling degree of the concrete 9 can be drastically increased by completing the placement without solidifying the concrete 9.

なお、天井部10の最上位に位置する吹上口11は、アーチ部13にある吹上口40との対比で最上位吹上口11ということにする。最上位吹上口11は、吹上口40による充填が終了した後、天井部10とトンネル内壁面3aとの間の空間部である天端部15にコンクリート9を充填するために使用し、十分高圧な吐出圧によりコンクリート9を吐出する。また、最上位吹上口11の予備として、天井部10にはその長手方向に予備吹上口11aが設けられている(図5参照)。   Note that the blowing outlet 11 located at the top of the ceiling 10 is referred to as the highest blowing outlet 11 in comparison with the blowing outlet 40 in the arch part 13. The uppermost blow-up port 11 is used to fill the concrete 9 in the top end 15 which is a space between the ceiling 10 and the tunnel inner wall surface 3a after the filling by the blow-up port 40 is completed. Concrete 9 is discharged with a suitable discharge pressure. Further, as a reserve for the uppermost blow-up port 11, a preliminary blow-up port 11a is provided in the ceiling portion 10 in the longitudinal direction (see FIG. 5).

また、型枠1Aにあっては、バイブレータ8に加え、例えば特開2003−227297号公報に開示の引き抜きバイブレータ80を利用している(図3,4参照)。   Further, in the mold 1A, in addition to the vibrator 8, for example, a drawing vibrator 80 disclosed in Japanese Patent Laid-Open No. 2003-227297 is used (see FIGS. 3 and 4).

次にこのような構成のトンネル覆工用の型枠1Aを用いたトンネル覆工の施工方法について述べる。   Next, a tunnel lining construction method using the tunnel lining mold 1A having such a configuration will be described.

本実施形態に係るトンネル覆工の施工方法は、次の(i)〜(v)のステップからなる。
(i)アーチ部13に設けられている吹上口40から供給されるコンクリート9を、天井部10の最上位とほぼ水平になる箇所(図4のコンクリート9の上位面参照)にまで打設するステップ。
(ii)アーチ部13に設けられている吹上口40から供給されたコンクリート9による打
設の位置が、天井部10の最上位とほぼ水平になる箇所に至ることを天井部10の天井窓5cから作業者が観測するステップ。
(iii)コンクリート9による打設の位置が、天井部10の最上位とほぼ水平になると、
最上位吹上口11からコンクリート9を吐出するステップ。
(iv)アーチ部13に設けられている複数の吹上口40からコンクリート9を吐出する
にあたり、天井部10周りにおいて、コンクリート9がほぼ均一に供給されるように、吹上口40から吐出されるコンクリート9の吐出量及び吐出時間を調整しながら吐出するステップ。
(v)コンクリート9による打設の位置が、天井部10の最上位とほぼ水平になると、当該打設部分にバイブレータ8,80で振動を与えるステップ。
The tunnel lining construction method according to this embodiment includes the following steps (i) to (v).
(I) The concrete 9 supplied from the air outlet 40 provided in the arch part 13 is driven to a place (refer to the upper surface of the concrete 9 in FIG. 4) that is substantially horizontal with the uppermost part of the ceiling part 10. Step.
(Ii) The ceiling window 5c of the ceiling portion 10 indicates that the position of placement by the concrete 9 supplied from the air outlet 40 provided in the arch portion 13 reaches a location that is substantially horizontal with the top of the ceiling portion 10. Steps observed by the worker.
(Iii) When the placement position of the concrete 9 is almost horizontal with the top of the ceiling 10,
Discharging the concrete 9 from the uppermost blowing port 11;
(Iv) When discharging the concrete 9 from the plurality of blowing openings 40 provided in the arch portion 13, the concrete discharged from the blowing openings 40 so that the concrete 9 is supplied substantially uniformly around the ceiling portion 10. A step of discharging while adjusting the discharge amount and discharge time of No. 9.
(V) A step of applying vibrations to the placement portion with vibrators 8 and 80 when the placement position of the concrete 9 is substantially horizontal with the top of the ceiling portion 10.

次に本実施形態の作用効果について述べる。   Next, the effect of this embodiment is described.

アーチ部13に設けられている複数の吹上口40から吐出されるコンクリート9は、重力に抗して型枠1Aの上方である天井部10に向けて打設することが可能であるから、吹上口40から供給されるコンクリート9を、天井部10の最上位とほぼ水平になる箇所にまで打設することができる。   Since the concrete 9 discharged from the plurality of air outlets 40 provided in the arch portion 13 can be placed toward the ceiling portion 10 above the formwork 1A against gravity, The concrete 9 supplied from the mouth 40 can be placed up to a place that is substantially horizontal with the top of the ceiling 10.

上記のように、水平に打設することで天井窓5cから作業者が打設状態を視認できる範囲を広げられる。   As described above, by placing horizontally, the range in which the operator can visually recognize the placement state from the ceiling window 5c can be expanded.

また、従来は、コンクリート搬送管7をアーチ部13に設けた窓部5から出し、コンクリート搬送管7からコンクリート9を排出してコンクリート充填を行っていたが、コンクリート搬送管7の代わりにコンクリート9を型枠1Aの上方へ向けるに十分な圧を有する吹上口40を用いたことにより、これまではかなわなかった空間A(図8,図5参照)へのコンクリート9の充填が可能になるので、それだけ天端部15の容積を小さくすることができる。よって、天端部15でのコンクリート9の充填性を確実にすることができる。特に型枠1Aとトンネル内壁面3aとの間にコンクリート9が行き渡っていないことに起因する隙間の発生を効果的に抑制することができる。   Conventionally, the concrete conveying pipe 7 is taken out from the window 5 provided in the arch portion 13 and the concrete 9 is discharged from the concrete conveying pipe 7 to fill the concrete. However, instead of the concrete conveying pipe 7, the concrete 9 By using the blow-up port 40 having sufficient pressure to direct the upper side of the mold 1A, the concrete 9 can be filled into the space A (see FIGS. 8 and 5), which has not been achieved so far. Thus, the volume of the top end 15 can be reduced accordingly. Therefore, the filling property of the concrete 9 at the top end portion 15 can be ensured. In particular, it is possible to effectively suppress the generation of a gap due to the fact that the concrete 9 is not spread between the mold 1A and the tunnel inner wall surface 3a.

また、天井部10周りを天井窓5cから作業者が一望したときに、4つの吹上口40から吐出されるコンクリート9が、天井部10の最上位とほぼ水平になる箇所にまで充填(打設)されたことを確認できる状態になる(図4参照)。この場合は、わずかに残された天端部15に対し、最上位吹上口11を用いてコンクリート9を充填すればよい状況となる。   Further, when an operator overlooks the ceiling portion 10 from the ceiling window 5c, the concrete 9 discharged from the four blow-up openings 40 is filled (placed) to a place that is substantially horizontal with the topmost portion of the ceiling portion 10. ) Can be confirmed (see FIG. 4). In this case, it becomes a situation that the concrete 9 may be filled using the uppermost blow-up port 11 with respect to the top end portion 15 that remains slightly.

上記のように、吹上口40はその下方のみならず上方にもコンクリート9を打設できるので、この方法による打設可能範囲が広がる結果、打設状態を作業者が視認できない空間である天端部15へのコンクリート打設量を少なくすることができる。打設状態が視認できない天端部15の打設作業は、打設量及び打設時間を最小限にすることが重要であるが、これを実現することで天端部15へのコンクリート9の充填性を向上させることができる。   As described above, since the concrete 9 can be placed not only below but also above the blow-up opening 40, the possible placement range by this method is widened. As a result, the ceiling is a space where the worker cannot visually recognize the placement state. The amount of concrete placed on the portion 15 can be reduced. It is important to minimize the amount and time of placing the top end 15 where the placement state cannot be visually recognized. However, by realizing this, the concrete 9 can be placed on the top end 15. Fillability can be improved.

なお、本発明は上述の図示例にのみ限定されるものではなく、本発明の要旨を逸脱しない範囲内において種種変更を加え得ることは勿論である。例えば鋼管の形状は、角形鋼管でもよい。なおその場合リング板も矩形状となるのは勿論である。   In addition, this invention is not limited only to the above-mentioned illustration example, Of course, various changes can be added within the range which does not deviate from the summary of this invention. For example, the shape of the steel pipe may be a square steel pipe. In this case, of course, the ring plate is also rectangular.

本発明に係るトンネル覆工用の型枠を用いてトンネル覆工の施工を行っている状態を示す横断面図である。It is a cross-sectional view which shows the state which is constructing the tunnel lining using the tunnel lining formwork according to the present invention. 本発明に係るトンネル覆工用の型枠を用いてトンネル覆工の施工を行っている状態を示す側面図である。It is a side view which shows the state which is constructing tunnel lining using the tunnel lining formwork which concerns on this invention. 本発明に係るトンネル覆工用の型枠を用いてトンネル覆工の施工を行っている状態を示す斜視図である。It is a perspective view which shows the state which is performing construction of tunnel lining using the formwork for tunnel lining concerning this invention. 図1の要部拡大図である。It is a principal part enlarged view of FIG. 本発明に係るトンネル覆工用の型枠の平面図である。It is a top view of the formwork for tunnel lining which concerns on this invention. 従来技術を説明するための図であって図1に相当する横断面図である。It is a figure for demonstrating a prior art, Comprising: It is a cross-sectional view equivalent to FIG. 従来技術を説明するための図であって図2に相当する側面図である。It is a figure for demonstrating a prior art, and is a side view equivalent to FIG. 図6の要部拡大図である。It is a principal part enlarged view of FIG.

符号の説明Explanation of symbols

1 型枠
1A 型枠
3 トンネル
3a トンネル掘削面(内壁面)
5 窓部
5c 天井窓
7 コンクリート搬送管
8 バイブレータ
9 コンクリート
10 天井部
11 最上位吹上口
11a 予備吹上口
13 アーチ部
20 足場
40 吹上口
80 引き抜きバイブレータ
C 正中線
T 接線
i 交点
a 吹上口から型枠の上方に向かうコンクリートを示す線
1 Formwork 1A Formwork 3 Tunnel 3a Tunnel excavation surface (inner wall surface)
DESCRIPTION OF SYMBOLS 5 Window part 5c Ceiling window 7 Concrete conveyance pipe 8 Vibrator 9 Concrete 10 Ceiling part 11 Uppermost blowing outlet 11a Preliminary blowing opening 13 Arch part 20 Scaffolding 40 Lifting opening 80 Pulling vibrator C Midline T Tangent i Intersection a From blowing opening Line showing concrete facing upward

Claims (5)

トンネル覆工用の型枠において、
前記型枠のうちその天井部よりも下方に位置し、かつ当該天井部に隣接する部分であるアーチ部には、コンクリートを加圧して噴出する吹上口が設けられ、
前記天井部には、前記コンクリートの打設状態を観察する窓部が設けられているとともに、当該窓部の近傍には、型枠の最上位に位置する最上位吹上口が設けられていることを特徴とするトンネル覆工用の型枠。
In the formwork for tunnel lining,
The arch portion, which is located below the ceiling portion of the mold and adjacent to the ceiling portion, is provided with a blow-up port that pressurizes and ejects concrete.
The ceiling part is provided with a window part for observing the placement state of the concrete, and an uppermost air outlet located at the uppermost part of the mold is provided in the vicinity of the window part. Formwork for tunnel lining characterized by
前記吹上口は、前記天井部を囲繞するように複数配置されていることを特徴とする請求項1に記載のトンネル覆工用の型枠。   2. The tunnel lining form according to claim 1, wherein a plurality of the air outlets are arranged so as to surround the ceiling portion. 請求項2に記載の型枠を利用したトンネル覆工の施工方法であって、
前記アーチ部に設けられている吹上口からコンクリートを加圧して噴出させ、この吹上口の下方及び上方における型枠及びトンネルの間にコンクリートを充填し、打設面が水平になるように前記天井部の最上位付近までコンクリートを打設する工程を含むトンネル覆工の施工方法。
A tunnel lining construction method using the mold according to claim 2,
The concrete is pressurized and ejected from the air outlet provided in the arch, the concrete is filled between the formwork and the tunnel below and above the air outlet, and the ceiling is placed so that the casting surface is horizontal. Tunnel lining method including the process of placing concrete up to the top of the section.
前記コンクリートによる打設の位置が、前記天井部の最上位付近に到達した後、前記最上位吹上口からコンクリートを噴出させる工程を実施することを特徴とする請求項3に記載のトンネル覆工の施工方法。   4. The tunnel lining according to claim 3, wherein a step of ejecting the concrete from the uppermost outlet is performed after the position of placement by the concrete reaches the uppermost vicinity of the ceiling portion. 5. Construction method. 前記コンクリートによる打設の位置が、前記天井部の最上位付近に到達すると、当該打設部分にバイブレータで振動を与えることを特徴とする請求項4に記載のトンネル覆工の施工方法。   5. The tunnel lining construction method according to claim 4, wherein when the concrete placement position reaches near the uppermost position of the ceiling portion, vibration is applied to the placement portion with a vibrator.
JP2006270435A 2006-10-02 2006-10-02 Tunnel lining form and tunnel lining construction method Pending JP2008088691A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006270435A JP2008088691A (en) 2006-10-02 2006-10-02 Tunnel lining form and tunnel lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006270435A JP2008088691A (en) 2006-10-02 2006-10-02 Tunnel lining form and tunnel lining construction method

Publications (1)

Publication Number Publication Date
JP2008088691A true JP2008088691A (en) 2008-04-17

Family

ID=39373122

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006270435A Pending JP2008088691A (en) 2006-10-02 2006-10-02 Tunnel lining form and tunnel lining construction method

Country Status (1)

Country Link
JP (1) JP2008088691A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011184934A (en) * 2010-03-08 2011-09-22 Shimizu Corp Method of lining of tunnel
CN102493817A (en) * 2011-12-29 2012-06-13 湖南省交通规划勘察设计院 Tunnel with opening and open cut channel structure
KR101420073B1 (en) * 2014-01-15 2014-07-15 최인걸 Method and Aparatus to prevent cracks in tunnel lining concrete
CN108316062A (en) * 2018-02-11 2018-07-24 中铁二院工程集团有限责任公司 A kind of control device and its construction method of non-fragment orbit tunnel arching of bottom
JP2019073892A (en) * 2017-10-16 2019-05-16 飛島建設株式会社 Installation method and installation equipment of tunnel secondary lining concrete
JP2020023864A (en) * 2018-08-03 2020-02-13 株式会社奥村組 Tunnel lining concrete placement method
JP2021055355A (en) * 2019-09-30 2021-04-08 前田建設工業株式会社 Concrete placement method at top end part of tunnel and formwork equipment for tunnel lining

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001280094A (en) * 2000-01-27 2001-10-10 Nishimatsu Constr Co Ltd Tunnel lining device and tunnel lining method
JP2001336397A (en) * 2000-05-30 2001-12-07 Ohbayashi Corp Compactible injection apparatus for tunnel lining concrete
JP2002030894A (en) * 2000-07-19 2002-01-31 Nishimatsu Constr Co Ltd Method of placing secondary lining concrete, and framework for the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001280094A (en) * 2000-01-27 2001-10-10 Nishimatsu Constr Co Ltd Tunnel lining device and tunnel lining method
JP2001336397A (en) * 2000-05-30 2001-12-07 Ohbayashi Corp Compactible injection apparatus for tunnel lining concrete
JP2002030894A (en) * 2000-07-19 2002-01-31 Nishimatsu Constr Co Ltd Method of placing secondary lining concrete, and framework for the same

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011184934A (en) * 2010-03-08 2011-09-22 Shimizu Corp Method of lining of tunnel
CN102493817A (en) * 2011-12-29 2012-06-13 湖南省交通规划勘察设计院 Tunnel with opening and open cut channel structure
KR101420073B1 (en) * 2014-01-15 2014-07-15 최인걸 Method and Aparatus to prevent cracks in tunnel lining concrete
JP2019073892A (en) * 2017-10-16 2019-05-16 飛島建設株式会社 Installation method and installation equipment of tunnel secondary lining concrete
CN108316062A (en) * 2018-02-11 2018-07-24 中铁二院工程集团有限责任公司 A kind of control device and its construction method of non-fragment orbit tunnel arching of bottom
CN108316062B (en) * 2018-02-11 2020-04-21 中铁二院工程集团有限责任公司 Construction method of control device for tunnel bottom upper arch of ballastless track
JP2020023864A (en) * 2018-08-03 2020-02-13 株式会社奥村組 Tunnel lining concrete placement method
JP2021055355A (en) * 2019-09-30 2021-04-08 前田建設工業株式会社 Concrete placement method at top end part of tunnel and formwork equipment for tunnel lining
JP7437902B2 (en) 2019-09-30 2024-02-26 前田建設工業株式会社 Concrete placement method at the top of the tunnel

Similar Documents

Publication Publication Date Title
JP2008088691A (en) Tunnel lining form and tunnel lining construction method
JP2008088696A (en) Tunnel lining construction method
JP4910200B2 (en) Sectional repair method for concrete structures
JP4802166B2 (en) Synthetic segment manufacturing method
CN106437164A (en) Buffer device for downward ultra-deep composite pumping of concrete
CN111893992A (en) Static breaking construction method for interior of pile head of cast-in-situ bored pile
JP2015090030A (en) Tunnel lining construction method and management method for tunnel lining concrete placing
JP2011026777A (en) Pneumatic form
JP2020094458A (en) Placement method of tunnel lining concrete
JP5192346B2 (en) Pile head processing method
JP4666259B2 (en) Vanishing model casting method
JP6322392B2 (en) Concrete placement method
JP2010163830A (en) Mold for tunnel lining
JP2020045611A (en) Pile head treatment method
JP7248528B2 (en) Concrete filling jig, concrete filling method
JP4905987B2 (en) Mud pit
JP5861272B2 (en) How to drain excess water and air from cast concrete
CN107939094A (en) Conical concrete construction of funnel method
JP2018076650A (en) Pile head processing construction method
JP5358393B2 (en) Formwork for producing a segment and method for producing a segment using the formwork
JP4310212B2 (en) Filling through holes in buildings
JP3911121B2 (en) Pile head processing apparatus and pile head processing method
JP4145867B2 (en) Synthetic segment manufacturing method and synthetic segment
KR102526362B1 (en) Apparatus for constructing downward vertical structure
JP6773065B2 (en) How to disassemble the burner

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110107

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110118

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110228

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20110823