JP2012182979A - 負荷予想のためのシステム及び方法 - Google Patents
負荷予想のためのシステム及び方法 Download PDFInfo
- Publication number
- JP2012182979A JP2012182979A JP2012033485A JP2012033485A JP2012182979A JP 2012182979 A JP2012182979 A JP 2012182979A JP 2012033485 A JP2012033485 A JP 2012033485A JP 2012033485 A JP2012033485 A JP 2012033485A JP 2012182979 A JP2012182979 A JP 2012182979A
- Authority
- JP
- Japan
- Prior art keywords
- day
- load
- value
- forecast
- past observed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 29
- 238000004590 computer program Methods 0.000 claims description 2
- 238000013277 forecasting method Methods 0.000 abstract 1
- 230000005540 biological transmission Effects 0.000 description 10
- 238000007726 management method Methods 0.000 description 8
- 230000005611 electricity Effects 0.000 description 7
- 238000004422 calculation algorithm Methods 0.000 description 5
- 238000010248 power generation Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 230000004044 response Effects 0.000 description 3
- 238000013480 data collection Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 238000007476 Maximum Likelihood Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 239000003990 capacitor Substances 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000000052 comparative effect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 238000010561 standard procedure Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/003—Load forecast, e.g. methods or systems for forecasting future load demand
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Economics (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Power Engineering (AREA)
- Quality & Reliability (AREA)
- Game Theory and Decision Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Development Economics (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
【解決手段】当該日に関する負荷予想の方法(50)は、それより前の少なくとも3日の過去の観測負荷値を取得するステップ(52)と、過去の観測負荷値に関連付けされた未知のウェイトを含む当該日の負荷予想と過去の観測負荷値との間の関係を特定するステップ(54)と、を含む。この未知のウェイトの値は、それ以前の少なくとも1日の負荷予想を該それ以前の少なくとも1日の観測負荷値と比較することによって決定される(56)。次いでこの決定したウェイト値は、当該日の負荷を予想するために当該日の負荷予想と過去の観測負荷値との間の関係において用いられる(58)。
【選択図】図2
Description
上式において、a、b及びcは未知のウェイトであり、かつa*LD_0、b*LD_1及びc*LD_2はウェイト付与済みの観測負荷である。ステップ56では、未知のウェイトa、b及びcを特定するために直前の日の負荷予想数式LD_fが直前の日の実際負荷または観測負荷LD_0と比較される。
上式において、LD_15、LD_9及びLD_2は5月15日(表1第5列)、5月9日(表1第3列)及び5月2日(表1第1列)のそれぞれにおける観測負荷である。次いで未知のウェイトa、b及びcを決定するために数式(2)が解かれる。一実施形態では、数式(2)を解くために曲線当てはめアルゴリズムを用いることがある。この曲線当てはめアルゴリズムは、最小二乗アルゴリズムまたは最大尤度推定アルゴリズムを含むことがある。最小二乗アルゴリズムは過剰決定系(overdetermined system)すなわち本事例の場合と同様に未知数の数より多くの数の数式が存在するような数式組に関する近似解に関する標準的な方式であることは当業者であれば理解されよう。この方式に基づくと、数式(2)に対する解の1つは、a=0.295、b=0.741及びc=0.133とし得る。未知のウェイトの値が決定された後、ステップ58において既知となったこのウェイト値が当該日の負荷を予想するために利用される。したがって、5月17日の負荷予想に関する数式は次式のようになる。
+0.133*LD_3 (3)
LD_16、LD_10及びLD_3の値は負荷LD_17を予想するために表1から取得することが可能である。表1に示したタイプのデータは典型的には、例えば従来のSCADAシステムから取得することができる。
上式において、Eは予想負荷と観測負荷の間の誤差である。別の実施形態では、単一予測と複数回予測の両方を同時に用いることがある。
12 発電所
14 送電サブステーション
16 配電サブステーション
18 負荷
20 1次送電線
22 2次送電線
24 ユーティリティ制御センター
26 監視制御及びデータ収集(SCADA)システム
28 エネルギー管理システム(EMS)
30 需要応答管理システム(DRMS)
32 配電管理システム(DMS)
50 負荷予想の方法を表した流れ図
52 方法のステップ
54 方法のステップ
56 方法のステップ
58 方法のステップ
70 予想負荷と観測負荷の比較プロット
72 予想負荷
74 観測負荷
76 水平軸
78 垂直軸
80 予想負荷と観測負荷の比較プロット
90 予想負荷と観測負荷の比較プロット
100 予想負荷と観測負荷の比較プロット
120 単一回予測対複数回予測の比較プロット
122 実際の負荷プロフィール
124 単一予測の負荷プロフィール
126 複数回予測の負荷プロフィール
150 負荷予想モジュール
152 データベース
154 数式特定モジュール
156 ウェイト値特定モジュール
158 負荷予測モジュール
Claims (10)
- 当該日に関する負荷予想の方法(50)であって、
それより前の少なくとも3日の過去の観測負荷値を取得するステップ(52)と、
過去の観測負荷値に関連付けされた未知のウェイトを含む当該日の負荷予想と過去の観測負荷値との間の関係を特定するステップ(54)と、
それ以前の少なくとも1日の負荷予想を該それ以前の少なくとも1日の過去の観測負荷値を比較することによって未知のウェイトのウェイト値を決定するステップ(56)と、
当該日の負荷予想と過去の観測負荷値との間の関係についての前記決定済みウェイト値を用いて当該日の負荷を予想するステップ(58)と、
を含む方法。 - 前記それより前の少なくとも3日は、直前日と、1週前の日と、2週前の日と、を含む、請求項1に記載の方法。
- 前記それより前の少なくとも3日は、その日が異なるカテゴリーでない限りにおける直前日と、1週前の日と、2週前の日と、を含むと共に、そのカテゴリーには平日の日、週末の日及び祝祭日を含む、請求項1に記載の方法。
- 未知のウェイトのウェイト値を決定する前記ステップは、当該日の負荷予想と過去の観測負荷値との間の関係に関する解を決定するステップを含む、請求項1に記載の方法。
- 前記当該日は勤務日でありかつ前記過去の観測負荷データのいずれかが祝祭日に関するものである場合に、該祝祭日に近い勤務日の負荷データを利用する、請求項1に記載の方法。
- 当該日の予想負荷と当該日の実際負荷の間の誤差がしきい値を超えた場合に、当該日に関する負荷を複数回予想する、請求項1に記載の方法。
- 電力グリッドのための負荷予想モジュール(150)であって、
それより前の少なくとも3日の過去の観測負荷値からなるデータベース(152)と、
過去の観測負荷値に関連付けされた未知のウェイトを含む当該日の負荷予想と過去の観測負荷値の間の関係を特定するための数式特定モジュール(154)と、
それ以前の少なくとも1日の負荷予想を該それ以前の少なくとも1日の過去の観測負荷値を比較することによって未知のウェイトのウェイト値を決定するためのウェイト値特定モジュール(156)と、
当該日の負荷予想の間の関係についての前記決定済みウェイト値を用いることによって当該日の負荷を予想するための負荷予測モジュール(158)と、
を備える負荷予想モジュール(150)。 - 前記それより前の少なくとも3日は、直前日と、1週前の日と、2週前の日と、を含む、請求項7に記載のシステム。
- 前記それより前の少なくとも3日は、その日が異なるカテゴリーでない限りにおける直前日と、1週前の日と、2週前の日と、を含むと共に、そのカテゴリーには平日の日、週末の日及び祝祭日を含む、請求項7に記載のシステム。
- プロセッサによって実行させたときにそのプロセッサに対して、当該日に関する負荷予想の方法(50)であって、
それより前の少なくとも3日の過去の観測負荷値を取得するステップ(52)と、
過去の観測負荷値に関連付けされた未知のウェイトを含む当該日の負荷予想と過去の観測負荷値との間の関係を特定するステップ(54)と、
それ以前の少なくとも1日の負荷予想を該それ以前の少なくとも1日の観測負荷値と比較することによって未知のウェイトのウェイト値を決定するステップ(56)と、
当該日の負荷予想と過去の観測負荷値との間の関係についての前記決定済みウェイト値を用いて当該日の負荷を予想するステップ(58)と、
を含む方法(50)を実施させるコンピュータプログラムの非一時的コンピュータ読み取り可能命令を含むコンピュータ読み取り可能媒体。
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/036,828 US8392031B2 (en) | 2011-02-28 | 2011-02-28 | System and method for load forecasting |
US13/036,828 | 2011-02-28 |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2012182979A true JP2012182979A (ja) | 2012-09-20 |
Family
ID=45841174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2012033485A Pending JP2012182979A (ja) | 2011-02-28 | 2012-02-20 | 負荷予想のためのシステム及び方法 |
Country Status (5)
Country | Link |
---|---|
US (1) | US8392031B2 (ja) |
EP (1) | EP2493046B1 (ja) |
JP (1) | JP2012182979A (ja) |
AU (2) | AU2012201008A1 (ja) |
CA (1) | CA2769129A1 (ja) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014161208A (ja) * | 2013-02-20 | 2014-09-04 | Mitsubishi Electric Corp | 負荷の電力消費量を求める方法およびシステム |
JP2016503477A (ja) * | 2012-11-15 | 2016-02-04 | フリース,ケヴィン,リー | 監視、分析、制御用統合自動システムを用いて加熱、冷却、発電、エネルギー貯蔵を提供する冷却、熱、電力併給ハイブリッドトリジェネレーションシステムマイクログリッド |
CN105429300A (zh) * | 2015-12-16 | 2016-03-23 | 徐承柬 | 用电监控方法及系统 |
Families Citing this family (35)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9356447B2 (en) * | 2012-07-24 | 2016-05-31 | International Business Machines Corporation | Predictive phase balancing for demand response |
CN103208813B (zh) * | 2013-01-21 | 2015-03-25 | 云南电网公司电网规划研究中心 | 一种准确计及风电影响的电力系统日调峰能力评估方法 |
CN103346555B (zh) * | 2013-05-23 | 2015-03-25 | 国家电网公司 | 一种输电网负荷供应充裕度评估方法及在线评估系统 |
CN103390902B (zh) * | 2013-06-04 | 2015-04-29 | 国家电网公司 | 一种基于最小二乘法的光伏电站超短期功率预测方法 |
US20150058061A1 (en) * | 2013-08-26 | 2015-02-26 | Magdy Salama | Zonal energy management and optimization systems for smart grids applications |
CN103559655B (zh) * | 2013-11-15 | 2016-05-25 | 哈尔滨工业大学 | 基于数据挖掘的微网新型馈线负荷的预测方法 |
CN103679295A (zh) * | 2013-12-23 | 2014-03-26 | 孟德峰 | 企业配电网电力负荷预测网络建立方法、预测方法及系统 |
CN103854069A (zh) * | 2014-02-20 | 2014-06-11 | 深圳供电局有限公司 | 基于分布式能源站接入的调峰评估方法及系统 |
CN104050517A (zh) * | 2014-06-27 | 2014-09-17 | 哈尔滨工业大学 | 基于grnn神经网络的光伏发电预测方法 |
DE102014010117A1 (de) * | 2014-07-08 | 2016-01-14 | Evohaus Gmbh | Prognose- und Steuerungssystem für den Strombezug von Haushalten |
CN104077636A (zh) * | 2014-07-24 | 2014-10-01 | 国网山东省电力公司泰安供电公司 | 一种电网短期负荷分析和预测的方法 |
CN105335539B (zh) * | 2014-08-08 | 2018-11-06 | 国家电网公司 | 用于电力负荷的数据处理方法和装置 |
CN104239984A (zh) * | 2014-10-20 | 2014-12-24 | 国网上海市电力公司 | 用于电网领域的不同分类用户组合的快速负荷预测方法 |
KR102293136B1 (ko) * | 2014-10-22 | 2021-08-26 | 삼성전자주식회사 | 비휘발성 메모리 장치, 그것을 포함하는 저장 장치 및 그것의 동작 방법 |
US9829880B2 (en) | 2014-11-20 | 2017-11-28 | General Electric Company | System and method for modelling load in an electrical power network |
CN104599055A (zh) * | 2015-01-04 | 2015-05-06 | 湘潭大学 | 一种钢铁企业的电力负荷需量管理方法 |
CN104617603A (zh) * | 2015-01-23 | 2015-05-13 | 云南电网有限责任公司电力科学研究院 | 一种防止水电站agc功率波动的方法 |
CN104835000A (zh) * | 2015-04-28 | 2015-08-12 | 国网上海市电力公司 | 一种考虑预安排停电的配电网可靠性评估方法 |
CN104850962A (zh) * | 2015-06-01 | 2015-08-19 | 国网上海市电力公司 | 一种考虑预安排停电的配电网可靠性评估方法 |
CN104866974A (zh) * | 2015-06-01 | 2015-08-26 | 国网上海市电力公司 | 一种考虑预安排停电的配电网可靠性评估设备 |
US10197984B2 (en) | 2015-10-12 | 2019-02-05 | International Business Machines Corporation | Automated energy load forecaster |
EP3389162A4 (en) * | 2015-12-10 | 2018-12-05 | Mitsubishi Electric Corporation | Power control device, operation plan planning method, and program |
CN105826921B (zh) * | 2016-05-26 | 2017-04-12 | 广东电网有限责任公司佛山供电局 | 一种基于变压器运行数据的配电网负荷预测方法及系统 |
CN106022546B (zh) * | 2016-06-30 | 2022-03-08 | 中国电力科学研究院 | 一种基于居民小区负荷成长周期的负荷预测方法 |
CN106651654A (zh) * | 2016-12-20 | 2017-05-10 | 国网湖南省电力公司 | 发电计划安全校核中传输电量计算和分区电量调整方法 |
WO2018200861A1 (en) * | 2017-04-27 | 2018-11-01 | Johnson Controls Technology Company | Building energy system with stochastic model predictive control |
CN107122924A (zh) * | 2017-05-31 | 2017-09-01 | 国家电网公司 | 一种智能配用电系统承载能力评估方法 |
CN107506843A (zh) * | 2017-07-03 | 2017-12-22 | 国网上海市电力公司 | 一种短期负荷预测方法及装置 |
US10700523B2 (en) | 2017-08-28 | 2020-06-30 | General Electric Company | System and method for distribution load forecasting in a power grid |
CN109523309B (zh) * | 2018-10-26 | 2021-04-30 | 武汉华中思能科技有限公司 | 一种基于潮流分析计算的电力报价仿真方法及系统 |
CN109670696B (zh) * | 2018-12-13 | 2022-12-09 | 海南电网有限责任公司 | 一种基于运行大数据的线路重过载预测方法 |
CN111692721B (zh) | 2019-03-15 | 2023-09-22 | 开利公司 | 用于空气调节系统的控制方法 |
CN110163429B (zh) * | 2019-05-10 | 2023-06-09 | 湖南大学 | 一种基于相似日优化筛选的短期负荷预测方法 |
CN110942174A (zh) * | 2019-10-18 | 2020-03-31 | 广东电网有限责任公司 | 一种适用于功能园区的负荷预测方法 |
CN112633642B (zh) * | 2020-12-09 | 2023-02-03 | 中国南方电网有限责任公司 | 电力系统备用需求预测方法、系统、装置及存储介质 |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03212702A (ja) * | 1990-01-18 | 1991-09-18 | Tokyo Electric Power Co Inc:The | 需要予測支援システム |
JPH0772904A (ja) * | 1993-09-06 | 1995-03-17 | Toshiba Corp | 電力需要予測装置 |
JPH08308108A (ja) * | 1995-04-27 | 1996-11-22 | Hitachi Ltd | 電力需要量予測方法およびその装置 |
JP2000270473A (ja) * | 1999-03-15 | 2000-09-29 | Fuji Electric Co Ltd | 電力需要量予測方法 |
US20040246643A1 (en) * | 2003-05-13 | 2004-12-09 | Dingguo Chen | Very short term load prediction |
JP2005128808A (ja) * | 2003-10-24 | 2005-05-19 | Mitsubishi Electric Corp | 予測装置 |
JP2007047996A (ja) * | 2005-08-09 | 2007-02-22 | Tokyo Electric Power Co Inc:The | 需要予測装置及び方法並びにプログラム |
JP2007241360A (ja) * | 2006-03-06 | 2007-09-20 | Osaka Gas Co Ltd | エネルギ需要量予測支援システム |
JP2009206011A (ja) * | 2008-02-29 | 2009-09-10 | Mitsubishi Heavy Ind Ltd | 燃料電池発電システム |
JP2010081783A (ja) * | 2008-09-25 | 2010-04-08 | Kankoku Denryoku Kosha | 顧客基準負荷算出のための負荷予測比較分析システム |
JP2010211780A (ja) * | 2009-02-13 | 2010-09-24 | Meidensha Corp | 電力エネルギー監視システム |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB0110153D0 (en) * | 2001-04-25 | 2001-06-20 | Isis Innovation | Improvements in or relating to forecasting |
US7496655B2 (en) * | 2002-05-01 | 2009-02-24 | Satyam Computer Services Limited Of Mayfair Centre | System and method for static and dynamic load analyses of communication network |
US7519506B2 (en) * | 2002-11-06 | 2009-04-14 | Antonio Trias | System and method for monitoring and managing electrical power transmission and distribution networks |
EP1678574A4 (en) * | 2003-10-10 | 2007-02-07 | Erlach Julian Van | ANALYSIS OF GOODS BASED ON THE YIELD PROCESS REQUIRED |
US20080046387A1 (en) * | 2006-07-23 | 2008-02-21 | Rajeev Gopal | System and method for policy based control of local electrical energy generation and use |
WO2008115256A1 (en) * | 2007-03-16 | 2008-09-25 | I-Conserve, Llc | System and method for monitoring and estimating energy resource consumption |
AU2008356120A1 (en) * | 2007-11-07 | 2009-11-12 | Edsa Micro Corporation | Systems and methods for real-time forecasting and predicting of electrical peaks and managing the energy, health, reliability, and performance of electrical power systems based on an artificial adaptive neural network |
US8121741B2 (en) * | 2008-05-09 | 2012-02-21 | International Business Machines Corporation | Intelligent monitoring of an electrical utility grid |
US8364609B2 (en) * | 2009-01-14 | 2013-01-29 | Integral Analytics, Inc. | Optimization of microgrid energy use and distribution |
-
2011
- 2011-02-28 US US13/036,828 patent/US8392031B2/en active Active
-
2012
- 2012-02-20 JP JP2012033485A patent/JP2012182979A/ja active Pending
- 2012-02-21 AU AU2012201008A patent/AU2012201008A1/en not_active Abandoned
- 2012-02-23 CA CA2769129A patent/CA2769129A1/en not_active Abandoned
- 2012-02-27 EP EP12157062.6A patent/EP2493046B1/en not_active Not-in-force
-
2017
- 2017-03-29 AU AU2017202088A patent/AU2017202088B2/en not_active Ceased
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03212702A (ja) * | 1990-01-18 | 1991-09-18 | Tokyo Electric Power Co Inc:The | 需要予測支援システム |
JPH0772904A (ja) * | 1993-09-06 | 1995-03-17 | Toshiba Corp | 電力需要予測装置 |
JPH08308108A (ja) * | 1995-04-27 | 1996-11-22 | Hitachi Ltd | 電力需要量予測方法およびその装置 |
JP2000270473A (ja) * | 1999-03-15 | 2000-09-29 | Fuji Electric Co Ltd | 電力需要量予測方法 |
US20040246643A1 (en) * | 2003-05-13 | 2004-12-09 | Dingguo Chen | Very short term load prediction |
JP2005128808A (ja) * | 2003-10-24 | 2005-05-19 | Mitsubishi Electric Corp | 予測装置 |
JP2007047996A (ja) * | 2005-08-09 | 2007-02-22 | Tokyo Electric Power Co Inc:The | 需要予測装置及び方法並びにプログラム |
JP2007241360A (ja) * | 2006-03-06 | 2007-09-20 | Osaka Gas Co Ltd | エネルギ需要量予測支援システム |
JP2009206011A (ja) * | 2008-02-29 | 2009-09-10 | Mitsubishi Heavy Ind Ltd | 燃料電池発電システム |
JP2010081783A (ja) * | 2008-09-25 | 2010-04-08 | Kankoku Denryoku Kosha | 顧客基準負荷算出のための負荷予測比較分析システム |
JP2010211780A (ja) * | 2009-02-13 | 2010-09-24 | Meidensha Corp | 電力エネルギー監視システム |
Non-Patent Citations (3)
Title |
---|
"将来の売り上げを予測する", MICROSOFT(R) OFFICE FOR WINDOWS(R) 95 活用ガイド, vol. 初版 第14刷, JPN6016044627, 30 April 1998 (1998-04-30), pages 383 - 387, ISSN: 0003443679 * |
中村 陽一,山城 迪,宮本 衛市,YOICHI NAKAMURA, SUSUMU YAMASHIRO, EIICHI MIYAMOTO: "周期係数モデルによる翌日総需要予測 Demand Forecasting for the Following Day by Cyclic Coefficients", 電気学会論文誌B(電力・エネルギー部門誌) THE TRANSACTIONS OF THE INSTITUTE OF ELECTRICAL ENGINEERS, vol. 113, no. 12, JPN6017010291, 20 December 1993 (1993-12-20), JP, pages 1381 - 1388, ISSN: 0003524309 * |
城井田 勝仁: "07 過去の売上から、5年後の売上を予測する", いちばんやさしい EXCELゴールシーク&ソルバー, vol. 第1版 第1刷, JPN6016044624, 1 April 2009 (2009-04-01), JP, pages 66 - 69, ISSN: 0003443678 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016503477A (ja) * | 2012-11-15 | 2016-02-04 | フリース,ケヴィン,リー | 監視、分析、制御用統合自動システムを用いて加熱、冷却、発電、エネルギー貯蔵を提供する冷却、熱、電力併給ハイブリッドトリジェネレーションシステムマイクログリッド |
JP2014161208A (ja) * | 2013-02-20 | 2014-09-04 | Mitsubishi Electric Corp | 負荷の電力消費量を求める方法およびシステム |
CN105429300A (zh) * | 2015-12-16 | 2016-03-23 | 徐承柬 | 用电监控方法及系统 |
Also Published As
Publication number | Publication date |
---|---|
US8392031B2 (en) | 2013-03-05 |
US20120221158A1 (en) | 2012-08-30 |
EP2493046A3 (en) | 2013-09-18 |
CA2769129A1 (en) | 2012-08-28 |
AU2012201008A1 (en) | 2012-09-13 |
NZ598326A (en) | 2013-08-30 |
AU2017202088A1 (en) | 2017-04-20 |
AU2017202088B2 (en) | 2018-04-19 |
EP2493046A2 (en) | 2012-08-29 |
EP2493046B1 (en) | 2016-08-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2017202088B2 (en) | System and method for load forecasting | |
KR101872557B1 (ko) | 에너지 소비 관리 | |
Shi et al. | Resilience-oriented DG siting and sizing considering stochastic scenario reduction | |
US10908198B2 (en) | Determining meter phase using interval voltage measurements | |
Cossent et al. | Distribution network costs under different penetration levels of distributed generation | |
Nick et al. | Wind power optimal capacity allocation to remote areas taking into account transmission connection requirements | |
KR20140105506A (ko) | 전력 생산 용량의 적응 및 에너지 저장 유닛 사이즈의 결정 | |
JP2012217331A (ja) | コンデンサバンクを動作させるためのシステムおよび方法 | |
JP2017517042A (ja) | ユーティリティ作業員予測のためのシステムおよび方法 | |
JP2014071901A (ja) | 需要応答管理のための方法およびシステム | |
JP2016019358A (ja) | 需要予測装置、コンピュータプログラム、スマートメーター及び蓄電装置 | |
Wu et al. | A power balancing method of distributed generation and electric vehicle charging for minimizing operation cost of distribution systems with uncertainties | |
JP5962770B2 (ja) | 電力系統制御システム及び電力系統制御方法 | |
JPWO2018221330A1 (ja) | 管理方法及び管理装置 | |
JPWO2012114372A1 (ja) | 電力需要管理システム及び電力需要管理方法 | |
Sidorov et al. | Enhancing reliability of electricity supply of city electric networks cities of Dushanbe | |
US20130218623A1 (en) | Power cost converting apparatus, power plan supporting apparatus, and computer readable storage medium | |
JP2012217248A (ja) | 配電系統電圧制御装置 | |
Pillai et al. | Facilitating higher photovoltaic penetration in residential distribution networks using demand side management and active voltage control | |
Keyvani et al. | Coordinated investment in wind‐rich regions using dynamic line rating, energy storage and distributed static series compensation to facilitate congestion management | |
US20130218624A1 (en) | Power plan supporting apparatus and computer readable storage medium | |
BR102012004211A2 (pt) | método de previsão de carga para um dia atual, módulo de previsão de carga para uma rede elétrica, sistema e meio legível por computador | |
JP2022532091A (ja) | 動的予測、集約、および妥当性確認のための機器および方法 | |
US11079786B2 (en) | Predictive method, apparatus and program product for weather adjustment of resource usage data | |
Lee et al. | Determinants of reserve margin volatility: A new approach toward managing energy supply and demand |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20150218 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20151014 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20151110 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20160126 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20160614 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20160908 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20161122 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20170216 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20170328 |