JP2012127186A - Construction method of cellar for building completed - Google Patents

Construction method of cellar for building completed Download PDF

Info

Publication number
JP2012127186A
JP2012127186A JP2011276024A JP2011276024A JP2012127186A JP 2012127186 A JP2012127186 A JP 2012127186A JP 2011276024 A JP2011276024 A JP 2011276024A JP 2011276024 A JP2011276024 A JP 2011276024A JP 2012127186 A JP2012127186 A JP 2012127186A
Authority
JP
Japan
Prior art keywords
concrete
basement
support
building
completed building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2011276024A
Other languages
Japanese (ja)
Inventor
Hang Ryong Byun
ロン ビュン,ハン
Jun-Son Kim
ソン キム,ジュン
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Korea Engineering and Consultant Co Ltd
Original Assignee
Korea Engineering and Consultant Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Korea Engineering and Consultant Co Ltd filed Critical Korea Engineering and Consultant Co Ltd
Publication of JP2012127186A publication Critical patent/JP2012127186A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0021Mortar

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method of a cellar for a building completed.SOLUTION: The construction method includes: a step of making a plurality of holes and a slot pass through bottom concrete at the bottom part of the building completed so as to be communicated with the holes, inserting a support to the inside of the slot and making a stopper projected at the lower part of the support be engaged with the lower part of the slot to fix it; a step of providing a press-in machine on the upper part of the support; a step of inserting hollow piles to the respective holes, then pushing the piles into the underground using the press-in machine, stacking other piles on the pushed-in piles every time the piles are pushed in, then successively pushing them in by the press-in machine to support the underground structure of the building completed; a step of supporting the building completed by a column pushed into the underground and excavating the lower ground of the bottom concrete of the building in order to secure an underground space; and a step of placing concrete to the horizontal surface and vertical surface of the underground space secured by the step of excavating the lower ground of the concrete.

Description

本発明は、既に竣工された建築物をそのままにした状態で、この建築物の下部地盤を掘削して地下室を施工できる竣工建築物の地下室の施工方法に係り、特に竣工建築物の底コンクリートを貫通させて固定された支持体に押込機を設け、この押込機を利用して中空パイルを一列に押し込んで形成された複数の支柱が竣工建築物を安全に支持させるようにした後、竣工建築物の地盤を掘削して地下空間を選択的に形成し、この地下空間の底面をコンクリートで打設して地下室を形成することによって、地下室を簡便かつ安全に施工でき、また狭い空間で低騒音及び低費用で施工可能な竣工建築物の地下室の施工方法に関する。   The present invention relates to a method for constructing a basement of a completed building in which a basement can be constructed by excavating the lower ground of the building while leaving the already completed building as it is. A pusher is installed on the support that is fixed by penetrating, and a plurality of struts formed by pushing the hollow piles in a row using this pusher are used to safely support the completed building. By excavating the ground of the object and selectively forming the underground space, the basement of this underground space is cast with concrete to form the basement, so that the basement can be constructed easily and safely, and low noise in a narrow space And a method for constructing a basement of a completed building that can be constructed at low cost.

既に竣工された建築物、特に大型ビルのような建築物はそれ自体が重たいため、下部地盤を掘削して地下室を確保する場合に、建築物を支持する基盤が弱くなって崩壊の危険性が極めて高いことから、事実上地下室を確保したり増設できなかった。   Buildings that have already been completed, especially buildings such as large buildings, are heavy in themselves, so when excavating the lower ground and securing a basement, the foundation supporting the building becomes weak and there is a risk of collapse Because it was extremely expensive, it was virtually impossible to secure or add a basement.

従って、地下室がないか、あるいは地下室があっても足りない建築物、特に地下駐車場の増設が必要な大型建築物の場合には、これを解決するために別の土地や建築物を購買して使用する必要があるので、これによる多額の購入費用がかかる現実的な問題点があった。   Therefore, in the case of a building that does not have a basement or that does not have a basement, especially a large building that requires an additional underground parking lot, purchase another land or building to solve this problem. Therefore, there is a practical problem that requires a large purchase cost.

このような問題点を解決するため、最近は竣工建築物の場合も地下室を施工する方法が提示されているが、建築物を支えるための別の複雑な構造物を建築物の下部に設けるようになるので、その構造が複雑であり、設置による費用が多大にかかるのみならず、作業工数が増加して工期が延び、また多くの人力の投入によって工事費がアップする問題点があった。   In order to solve these problems, recently, a method of constructing a basement has also been proposed for a completed building, but another complicated structure to support the building should be provided at the bottom of the building. Therefore, the structure is complicated, and not only the cost for installation is increased, but the number of work steps is increased, the work period is extended, and the construction cost is increased due to the input of a large amount of manpower.

本発明は、前述したような従来の竣工建築物の地下室の施工方法の諸々の問題点を解決するために案出されたもので、その目的は、竣工建築物の底コンクリートを貫通させて固定され支持体に押込機を設け、この押込機を利用して中空パイルを一列に押し込ませて形成された複数本の支柱が竣工建築物を安全に支持させた後、竣工建築物の地盤を掘削して地下空間を選択的に形成し、この地下空間の底面をコンクリートで打設して地下空間を形成することによって、地下室を簡便かつ安全に施工できるようにする竣工建築物の地下室の施工方法を提供するところにある。   The present invention was devised in order to solve various problems in the construction method of the basement of the conventional completed building as described above, and its purpose is to fix the bottom concrete of the completed building through it. The support is provided with an indenter, and the pillars formed by pushing the hollow piles in a row using the indenter safely support the completed building, and then excavate the ground of the completed building. Then, the basement of the completed building is constructed in such a way that the basement can be easily and safely constructed by selectively forming the basement and placing the bottom of the basement with concrete to form the basement. Is to provide.

本発明の他の目的は、狭い空間で低費用で竣工建築物の地下室を施工したり増築できる竣工建築物の地下室の施工方法を提供するところにある。   Another object of the present invention is to provide a method for constructing a basement of a completed building that can be constructed or expanded in a narrow space at low cost.

本発明のさらに他の目的は、油圧式押込機を使って無振動及び低騒音で支柱を押し込める竣工建築物の地下室の施工方法を提供するところにある。   Still another object of the present invention is to provide a method for constructing a basement of a completed building, in which a column can be pushed in with no vibration and low noise using a hydraulic pusher.

前述した目的を達成するための本発明に係る竣工建築物の地下室の施工方法は、竣工建築物の最下部の底コンクリートに複数の孔を形成し、この孔と連通するようにスロットを貫通させ、前記スロットの内部に支持体を挿入して支持体の下部に突出させたストッパがスロットの下部にかかって動かないように固定させるステップと、前記支持体の上部に押込機を設けるステップと、前記各孔に中空状のパイルを押し込んだ後押込機を利用して該パイルを地下に押し込ませ、パイルが押し込まれるとその時ごとに前記押し込まれた各パイルの上部に他のパイルを積層した後、前記押込機で順次に押し込ませて竣工建築物を支持して建築物を支持する支柱を押し込むステップと、地下に押し込まれた前記支柱によって竣工建築物が支持された状態で、地下空間を確保するために前記建築物の底コンクリートの下部地盤を掘削するステップと、前記コンクリートの下部地盤を掘削するステップによって確保された地下空間の水平面及び垂直面にコンクリートを打設するステップと、を含む。   In order to achieve the above-mentioned object, the construction method of the basement of the completed building according to the present invention is to form a plurality of holes in the bottom concrete at the bottom of the completed building, and to penetrate the slots so as to communicate with the holes. A step of inserting a support into the inside of the slot and fixing the stopper protruding from the bottom of the support so that it does not move on the bottom of the slot; and a step of providing a pusher on the top of the support; After pushing a hollow pile into each hole, the pile is pushed into the basement using a pushing machine, and when the pile is pushed in, another pile is stacked on top of each pushed pile. , A step of pushing in a column supporting the completed building by sequentially pushing in with the pushing machine, and a state where the completed building is supported by the column pushed into the basement A step of excavating a lower ground of the bottom concrete of the building to secure an underground space, and a step of placing concrete on a horizontal surface and a vertical surface of the underground space secured by the step of excavating the lower ground of the concrete And including.

以上説明したように、本発明に係る竣工建築物の地下室の施工方法は、竣工建築物を再施工しなくても地下室を新設したり増設できるので、建築廃棄物の発生を減らして環境汚染を防止できるのみならず、建築資材の浪費を予防することができる。   As explained above, the construction method of the basement of the completed building according to the present invention can newly install or add the basement without reconstructing the completed building, thus reducing the generation of building waste and environmental pollution. Not only can this be prevented, but waste of building materials can be prevented.

本発明は、パイルを埋設する押込機を、油圧シリンダを使用して騒音と振動が発生しなくて環境に易しい作業環境を提供できるのみならず、建築物の地下に押し込まれた複数本の支柱が建築物を支えるようになるので、従来のように建築物を支えるために複雑な別の構造物を設けなくてもよいので、作業工数を削減して短期間に施工を簡便かつ安全に行える。   The present invention provides not only a pusher for embedding piles but also a hydraulic cylinder that does not generate noise and vibration and can provide an easy working environment, and a plurality of support columns pushed into the basement of a building. Since it will support the building, there is no need to provide another complicated structure to support the building as in the past, so the work can be reduced and construction can be done easily and safely in a short period of time. .

また、竣工建築物の最下部の底面に押込機でパイルを押し込んだ後、このパイルが位置した地盤を除去して地下空間を形成するので、狭い空間で低費用で地下室を簡単に施工することができる。   Also, after pushing the pile into the bottom of the bottom of the completed building with an indenter, the ground where this pile is located is removed to form an underground space, so the basement can be easily constructed in a small space at low cost Can do.

図1は、本発明を施工する前、地下室のない地盤に竣工された建築物を示した概略図である。FIG. 1 is a schematic view showing a building completed on the ground without a basement before the construction of the present invention. 図2は、本発明に係る押込機を用いて竣工建築物の地下地盤にパイルを押し込む過程を示した図である。FIG. 2 is a diagram showing a process of pushing a pile into the underground ground of a completed building using the pushing machine according to the present invention. 図3は、本発明に係る押込機を用いて竣工建築物の地下地盤にパイルを押し込んで形成された支柱が竣工建築物を支持した状態を示した図である。FIG. 3 is a view showing a state in which a pillar formed by pushing a pile into an underground ground of a completed building using the pushing machine according to the present invention supports the completed building. 図4は、本発明に係るパイルが竣工建築物の地盤に押し込まれた状態を示した平面概略図である。FIG. 4 is a schematic plan view showing a state in which the pile according to the present invention is pushed into the ground of the completed building. 図5は、図4の状態で竣工建築物の地下地盤を掘削する過程を示した図である。FIG. 5 is a diagram showing a process of excavating the underground ground of the completed building in the state of FIG. 図6は、図4の状態で竣工建築物の地下地盤を掘削して地下1階の空間を用意した状態の図である。FIG. 6 is a diagram showing a state in which a space on the first basement floor is prepared by excavating the underground ground of the completed building in the state of FIG. 4. 図7は、図6の用意された地下1階の内部にコンクリートを打設した状態を示した図である。FIG. 7 is a diagram illustrating a state in which concrete is placed inside the prepared first basement floor of FIG. 6. 図8は、図7の地下1階の下部地盤を掘削する過程を示す図である。FIG. 8 is a diagram illustrating a process of excavating the lower ground on the first basement floor in FIG. 7. 図9は、図7の地下1階の下部地盤を掘削して地下2階の空間を用意した状態の図である。FIG. 9 is a diagram showing a state where a space on the second basement floor is prepared by excavating the lower ground on the first basement floor in FIG. 図10は、図9の用意された地下2階の内部にコンクリートを打設した状態を示した図である。FIG. 10 is a diagram illustrating a state in which concrete is placed inside the prepared second basement floor of FIG. 9. 図11は、本発明に係る押込機を竣工建築物の底面のコンクリートに設ける過程を順に示した図である。FIG. 11 is a diagram sequentially illustrating a process of providing the pushing machine according to the present invention on the concrete on the bottom surface of the completed building. 図12aは本発明に係る支持体を竣工建築物の底面に設置する前の状態を示した分解斜視図である。FIG. 12a is an exploded perspective view showing a state before the support according to the present invention is installed on the bottom surface of the completed building. 図12bは、ストッパの他の実施形態を示した部分抜粋斜視図である。FIG. 12 b is a partially extracted perspective view showing another embodiment of the stopper. 図13は、本発明に係る支持体および押込機を竣工建築物の底面に設置済みの状態を示した斜視図である。FIG. 13: is the perspective view which showed the state by which the support body and pushing machine which concern on this invention were installed in the bottom face of a completed building. 図14は、本発明を実際に施工した写真である。FIG. 14 is a photograph of the actual construction of the present invention. 図15は、本発明に係る施工の順序図である。FIG. 15 is a flow chart of construction according to the present invention. 図16は、押込機を竣工建築物の底コンクリートの下部に装着してパイルを押し込む実施形態を示した図である。FIG. 16 is a view showing an embodiment in which the pile is pushed in by attaching the pushing machine to the lower part of the bottom concrete of the completed building. 図17は、図16の方法に従って掘削を行いながら押込機を竣工建築物の底コンクリートの下部に設けて支柱を形成する過程を示した図である。FIG. 17 is a view showing a process of forming a support column by providing a pusher under the bottom concrete of a completed building while excavating according to the method of FIG. 図18は、図17の過程によって形成された地下1階の底コンクリートを打設した状態を示した図である。FIG. 18 is a view showing a state in which the bottom concrete of the first basement floor formed by the process of FIG. 17 is placed. 図19は、竣工建築物の底コンクリートの下部に押込機を支持するための補強部を増設した実施形態を示した部分抜粋図である。FIG. 19 is a partial excerpt showing an embodiment in which a reinforcing part for supporting the pushing machine is added to the lower part of the bottom concrete of the completed building. 図20は、小規模の竣工建築物に地下室が施工される前の状態を示した図である。FIG. 20 is a diagram showing a state before a basement is constructed in a small completed building. 図21は、竣工建築物の縁部に支持体と押込機を設け、パイルを押し込んで支柱を形成する施工方法による支柱形成状態を示した図である。FIG. 21 is a diagram showing a strut formation state by a construction method in which a support and a pusher are provided at the edge of a completed building and a pile is pushed in to form a strut. 図22は、図21の支柱形成後底コンクリートの下部を掘削し、コンクリートを打設した状態を示した図である。FIG. 22 is a view showing a state in which the lower concrete of the bottom concrete after excavation in FIG. 21 is excavated and the concrete is placed. 図23は、図21の竣工建築物の縁部に支持体と押込機が設けられた状態を示した部分抜粋斜視図である。FIG. 23 is a partial excerpt perspective view showing a state where a support and a pusher are provided at the edge of the completed building of FIG.

以下、添付の図面に基づき、本発明に係る竣工建築物の地下室の施工方法を詳述する。   Hereinafter, the construction method of the basement of the completed building according to the present invention will be described in detail with reference to the accompanying drawings.

本発明は、竣工建築物に地下室が無いか、あるいは地下室があっても不足して増設する場合に、簡単かつ安全な方法で、地下室を新築または増設できるようにする。   The present invention makes it possible to newly build or add a basement by a simple and safe method when the completed building does not have a basement, or when there is a basement, the basement is insufficient.

この地下室の施工方法は、竣工建築物の地下に該当する地盤に、単位パイルを積層式で押し込んだ複数本の支柱が竣工建築物を支えるようにした状態で竣工建築物の下部地盤を掘削して地下空間を作り、この地下空間の底部をコンクリートで打設して地下1階を作り、引き続き前記地下1階の下部の地盤を掘削した後、底をコンクリートで打設して地下2階を作る方法で複数層の地下室を施工できる。   The basement construction method is to excavate the lower ground of the completed building with multiple struts with unit piles pushed into the ground corresponding to the basement of the completed building to support the completed building. The basement of this basement is casted with concrete to create the first basement floor. After excavating the ground below the first basement floor, the bottom is cast with concrete and the second basement floor is constructed. A multi-layer basement can be constructed by the method of making.

ここで、施工された地下室の柱は単位パイルが一列に連結された支柱になり、前記支柱が押し込まれた位置まで地下室を施工できる。   Here, the pillars of the constructed basement are pillars in which unit piles are connected in a row, and the basement can be constructed to the position where the pillars are pushed.

本発明に係る竣工建築物の地下室の施工方法をさらに具体的に説明すれば、次の通りである。   The construction method of the basement of the completed building according to the present invention will be described more specifically as follows.

竣工建築物1の最下部の底コンクリート2に、複数個の孔3(図12aに示す)及び該孔3と連通されるようにスロット4を貫通させ、前記スロット4の内部に支持体5を挿入して、支持体5の下部に突出されたストッパ5aがスロット4の下部にかかって動かないように固定させるステップ(S1)と、前記支持体5の上部に押込機6を設けるステップ(S2)と、前記各孔3に中空状のパイル7a(図13等に示す)を挿入した後、押込機6を用いて、このパイル7aを地下に押し込ませ、パイル7aが押し込まれるごとに前記押し込まれた各パイル7aの上部に、他のパイル7aを積層した後、さらに前記押込機6で順次にパイル7aを押し込ませて、竣工建築物1を支える支柱7を押し込ませるステップ(S3)と、地下に押し込まれた前記支柱7によって竣工建築物1が支持されれば、地下空間8を確保するため、前記建築物1の底コンクリートの下部地盤を掘削するステップ(S4)と、前記コンクリートの下部地盤を掘削するステップによって確保された地下空間8の水平面及び垂直面にコンクリート8を打設するステップ(S5)と、を含む。   The bottom concrete 2 at the bottom of the completed building 1 is penetrated through a plurality of holes 3 (shown in FIG. 12 a) and a slot 4 so as to communicate with the holes 3, and a support 5 is placed inside the slot 4. Inserting and fixing the stopper 5a protruding at the lower part of the support 5 so as not to move on the lower part of the slot 4 (S1), and providing the pusher 6 on the upper part of the support 5 (S2) ) And a hollow pile 7a (shown in FIG. 13 and the like) is inserted into each hole 3, and then the pile 7a is pushed into the basement using the pusher 6, and the pile 7a is pushed in each time the pile 7a is pushed in. After laminating other piles 7a on the top of each pile 7a, the step of pushing the piles 7a sequentially with the pusher 6 and pushing the columns 7 supporting the completed building 1 (S3); The support pushed into the basement If the completed building 1 is supported by the pillar 7, in order to secure the underground space 8, a step (S4) of excavating the lower ground of the bottom concrete of the building 1 and a step of excavating the lower ground of the concrete Placing the concrete 8 on the horizontal and vertical surfaces of the secured underground space 8 (S5).

また、本発明は、前記地盤を掘削するステップの後、支柱7の外観をきれいにできるよう支柱7の外部縁に仕上げ部材(図示せず)を被せるステップをさらに含む。   Further, the present invention further includes a step of covering a finishing member (not shown) on the outer edge of the column 7 so that the appearance of the column 7 can be cleaned after the step of excavating the ground.

前記支持体5を固定させるステップ(S1)は、本出願人が特許出願して登録を受けた技術であって、図11ないし図13に示されている。   The step (S1) of fixing the support 5 is a technique that has been filed and registered by the applicant of the present invention, and is shown in FIGS.

すなわち、竣工建築物1の最下部の底コンクリート2の積載要素に前記パイル7aを挿入できるように複数の孔3を貫通させ、前記孔3の外部には前記孔3と連通されるよう複数のスロットを形成する。このようにスロット4を孔3と連通して形成する理由は、支持体5を孔3の内部に挿入した後、前記スロット4に挿入させることによって支持体5の下部に形成されたストッパ5aがコンクリート2の底面に係着できるようにするためである。このため、前記ストッパ5aを収められるようにコンクリート2の下部地盤に前記スロット4と連通される案内空間10(図11に示す)を形成する。   That is, a plurality of holes 3 are penetrated so that the pile 7 a can be inserted into the loading element of the bottom concrete 2 at the bottom of the completed building 1, and a plurality of holes 3 are communicated with the holes 3 outside the hole 3. A slot is formed. The reason for forming the slot 4 in communication with the hole 3 in this way is that the support 5 is inserted into the hole 3 and then inserted into the slot 4 so that the stopper 5a formed at the lower portion of the support 5 is formed. This is because it can be attached to the bottom surface of the concrete 2. Therefore, a guide space 10 (shown in FIG. 11) communicating with the slot 4 is formed in the lower ground of the concrete 2 so that the stopper 5a can be accommodated.

図12aにおいて、前記支持体5が挿入されるスロット4は4つ示されているが、必要に応じて加減できる。前記スロット4の直径は図12aに示したように、支持体5の下部に形成されたストッパ5aがスロット4の下部にかかって垂直方向に離脱しないように、スロット4の直径は、ストッパ5aの突出寸法より小さいことが好ましい。そして、前記ストッパ5aは図12bに示したように、支持体5の下部にコンクリートで支持体5と一体になるように形成することもできる。   In FIG. 12a, four slots 4 into which the support 5 is inserted are shown, but can be adjusted as necessary. As shown in FIG. 12a, the slot 4 has a diameter of the stopper 5a so that the stopper 5a formed at the lower portion of the support 5 does not detach from the lower portion of the support 4 in the vertical direction. It is preferably smaller than the protruding dimension. Then, as shown in FIG. 12 b, the stopper 5 a can be formed integrally with the support 5 with concrete at the lower part of the support 5.

図11に示すように、案内空間10が形成されれば、前記支持体5を各スロット4に挿入した後、支持体5の下部に突出されたストッパ5aがコンクリート2の下部に密着するまで支持体5を持ち上げた後、その状態で前記スロット4にモルタル11を打設養生して、支持体5をスロット4に固定させる。   As shown in FIG. 11, when the guide space 10 is formed, after the support body 5 is inserted into each slot 4, the support 5 is supported until the stopper 5 a protruding from the lower portion of the support body 5 comes into close contact with the lower portion of the concrete 2. After lifting the body 5, the mortar 11 is placed and cured in the slot 4 in this state, and the support body 5 is fixed to the slot 4.

前述したようにコンクリート2に支持体5が固定されれば、この支持体5の上部にパイル7aを押し込めて、竣工建築物1の地下に支柱7を設ける押込機6を設けるステップ(S2)が行われる。   If the support body 5 is fixed to the concrete 2 as described above, the step (S2) of providing the pushing machine 6 that pushes the pile 7a into the upper portion of the support body 5 and provides the column 7 in the basement of the completed building 1 is performed. Done.

前記押込機6は公知の技術であって、本発明では油圧シリンダを使用する。前記油圧シリンダは支持体5の上部に固定され、供給された油圧によってロードが昇降しつつ孔3に挿入された中空状のパイル7aを竣工建築物1の下部地盤に圧着して支柱7を押し込む。   The pusher 6 is a known technique, and in the present invention, a hydraulic cylinder is used. The hydraulic cylinder is fixed to the upper part of the support body 5, and the pile 7 a inserted into the hole 3 is pressed against the lower ground of the completed building 1 while the load is moved up and down by the supplied hydraulic pressure, and the column 7 is pushed in. .

前記支柱7を竣工建築物1の地盤に押し込むステップ3は、前ステップで予め形成された各孔3にパイル7aを一列に押し込ませて行うようになる。本発明に使用されるパイル7aは、中空パイプ状またはHビーム(H-Beam)形状を含めて、本発明に適用できる形状は使用でき、望ましくは、中空パイプ状を使用するのが良い。中空状のパイル7aは内部が空いているので、軽くて取り扱いしやすく、また押込機6により地下に押し込まれる際、岩石にかかって所要深さまで押し込み難い場合に、パイル7aの管の内部に穿孔機を入れて、この穿孔機で岩石に孔を開ける方法で押し込めば、所要深さまで到達できるようにすることができるという長所がある。   The step 3 of pushing the column 7 into the ground of the completed building 1 is performed by pushing the piles 7a into the holes 3 previously formed in the previous step. As the pile 7a used in the present invention, a shape applicable to the present invention including a hollow pipe shape or an H-beam shape can be used, and preferably a hollow pipe shape is used. Since the hollow pile 7a is vacant, it is light and easy to handle, and when pushed into the basement by the pusher 6, it is difficult to push the rock to the required depth. There is an advantage that it is possible to reach the required depth by inserting a machine and pushing it in the way of drilling rocks with this drilling machine.

前記支柱を押し込むステップ(S3)を、図11を参照して具体的に説明する。   The step (S3) of pushing in the column will be specifically described with reference to FIG.

まず、図11(f)のように、コンクリート2に予め形成された孔3にパイル7aを挿入した後、押込機6を駆動させると、ロードが下降しつつ、前記パイル7aを地盤に押し込ませ、その後前記ロードを上昇させた後、先に押し込まれたパイル7aの上部に新たなパイル7aを一列に配置した状態で、押込機6のロードを再び下降させて、前記新たなパイル7aも地盤に押し込ませる。この方法で押し込まれたパイル7aの上部に新たなパイル7aを順次に一列に配置して押し込むことによって、竣工建築物1の下部地盤に柱状の支柱7を立設することができる。   First, as shown in FIG. 11 (f), after the pile 7a is inserted into the hole 3 previously formed in the concrete 2, when the pusher 6 is driven, the load is lowered and the pile 7a is pushed into the ground. Then, after the load is raised, the load of the pusher 6 is lowered again in a state where the new piles 7a are arranged in a row above the pile 7a previously pushed, and the new pile 7a is also grounded. To push into. By placing and placing new piles 7a sequentially in a row on top of the piles 7a pushed in this way, the columnar columns 7 can be erected on the lower ground of the completed building 1.

前記支柱7を設ける過程において、押込機6がパイル7aを加圧する際、前記押込機6を装着している支持体5はパイル7aが押し込まれるほど前記パイル7aの押し込みの反対方向に押されようとするが、前記支持体5は下部に形成されたストッパ5aがスロット4の下端部に係止された状態で養生されたモルタル11によって、コンクリート2に一体に成形固着されているので、押込機6はパイル7aの反対方向に押されないようになる。   In the process of providing the column 7, when the pusher 6 presses the pile 7a, the support 5 on which the pusher 6 is mounted will be pushed in the opposite direction of the push of the pile 7a as the pile 7a is pushed. However, the support body 5 is integrally molded and fixed to the concrete 2 by the mortar 11 cured in a state where the stopper 5a formed in the lower portion is locked to the lower end portion of the slot 4, so that the pushing machine 6 will not be pushed in the opposite direction of the pile 7a.

この過程において、押込機6は、押し込まれるパイル7aの上部がコンクリート2に形成された孔3の下部に至るまで押し込ませるのが良い。その理由は、前記押し込まれたパイル7aの上部に新たなパイル7aを一列に配置して、このパイル7aを押し込む際、下部で先に押し込まれたパイル7aの上部が揺れないようにして、各パイル7aの連結部が滑らかになるようにするためである。   In this process, the pusher 6 is preferably pushed until the upper part of the pile 7a to be pushed reaches the lower part of the hole 3 formed in the concrete 2. The reason is that a new pile 7a is arranged in a row above the pushed pile 7a, and when the pile 7a is pushed in, the upper portion of the pile 7a pushed first in the lower portion does not shake, This is to make the connecting portion of the pile 7a smooth.

前記各パイル7aの端部には、隣り合うパイル7aと滑らかに嵌合可能に嵌合部(図示せず)を形成するのが望ましい。   It is desirable to form a fitting portion (not shown) at the end portion of each pile 7a so that it can be smoothly fitted to the adjacent pile 7a.

ここで、地盤に押し込まれた支柱7の深さは、押し込まれた支柱7が地下室12の柱として使用されることに鑑みて、地下空間8よりさらに深く差し込まれるべきであり、前記支柱7に追加荷重が働いても、先端がさらに挿入されない硬い地層まで挿入されるようにする。前記支柱7が硬い地層まで到達するか否かは押込機に設けられた油圧ゲージの圧力を見て分るが、圧力が高ければ支柱7が硬い地盤に到達するものであり、圧力が低ければ軟弱な地盤に位置した状態であることが分かる。   Here, the depth of the pillar 7 pushed into the ground should be inserted deeper than the underground space 8 in view of the pushed pillar 7 used as a pillar of the basement 12. Even if an additional load is applied, it is inserted until a hard formation where the tip is not further inserted. Whether or not the strut 7 reaches a hard formation can be seen by looking at the pressure of a hydraulic gauge provided in the pushing machine. If the pressure is high, the strut 7 reaches a hard ground, and if the pressure is low It can be seen that it is located on a soft ground.

前述したような方法で竣工された建築物1の地下に支柱7が立設されれば、次の工程として竣工建築物1の下部地盤を掘削するステップ(S4)が行われる。前記下部地盤を掘削するステップは、本発明の核心的な技術であると言えよう。   If the column 7 is erected in the basement of the building 1 completed by the method as described above, a step (S4) of excavating the lower ground of the completed building 1 is performed as the next step. It can be said that the step of excavating the lower ground is the core technique of the present invention.

すなわち、支柱7が立てられて竣工建築物1を安全に支持するようになると、フォークレーンやブルドーザなど掘削に必要な重装備を用いて、図5のように建築物1の側面から次第に下方向に地盤を掘削し始めて、図6のように竣工建築物1の下部に必要な面積ほど地下空間8を確保する。こうすれば、竣工建築物1の下部は地盤が除去されて、あたかも空中に浮遊されたようにも見えるが、実際には、パイル7aが一列に連結されて押し込まれた複数の支柱7によって堅固に支持されている。   That is, when the pillar 7 is erected and safely supports the completed building 1, it gradually moves downward from the side of the building 1 as shown in FIG. 5 using heavy equipment necessary for excavation such as forcrane and bulldozer. As shown in FIG. 6, the underground space 8 is secured as much as necessary in the lower part of the completed building 1. In this way, the ground of the lower part of the completed building 1 is removed and it appears as if it was suspended in the air, but in reality, the piles 7a are connected in a row and pushed firmly by the plurality of columns 7 pushed in. It is supported by.

前記支柱7の位置と数量は、竣工建築物1の構造、さらに具体的に建築物1の垂直荷重のサイズによって、支柱7の位置と数が決定されるのが望ましい。例えば、一例として図4のように建築物1のいずれの箇所が低層に形成されて垂直荷重が相対的に軽ければ、それに該当する箇所の支柱7の数は少なく、他の箇所が高層で形成されて垂直荷重が相対的に重たいと、それに該当する箇所の支柱7の数は多く、支柱7の数が多ければ、支柱7の間を粗密にしたり、1つの支柱の荷重能力を一層大きくすることもできる。   It is desirable that the position and number of the columns 7 are determined by the structure of the completed building 1 and more specifically the size of the vertical load of the building 1. For example, as shown in FIG. 4, if any part of the building 1 is formed in a low layer and the vertical load is relatively light as shown in FIG. 4, the number of supporting columns 7 is small and the other part is formed in a high layer. If the vertical load is relatively heavy, the number of support columns 7 corresponding to the vertical load is large, and if the number of support columns 7 is large, the space between the support columns 7 is increased or the load capacity of one support column is further increased. You can also.

そして、前記地盤を掘削するステップ(S4)は、竣工建築物1の地下に押し込まれた支柱7の底面が露出されない深さまで掘削し、その過程で形成された地下空間8に、図7に示すようにコンクリート9を少なくとも1回以上打設して地下室12を施工する。   And the step (S4) of excavating the ground is excavated to a depth at which the bottom surface of the column 7 pushed into the basement of the completed building 1 is not exposed, and the underground space 8 formed in the process is shown in FIG. Thus, the basement 12 is constructed by placing the concrete 9 at least once.

前述したように竣工建築物1の地下に地下空間8が確保されれば、この箇所を地下室12として作るため、地下空間8にコンクリート9を打設するステップ(S5)が行われる。   As described above, when the underground space 8 is secured in the basement of the completed building 1, a step (S <b> 5) of placing concrete 9 in the underground space 8 is performed in order to make this location as the basement 12.

前記確保された地下空間8の水平面及び垂直面にコンクリート9を打設すれば、ようやく地下室12が完成されるが、水平面は該当地下室12の底面になるので、垂直面より厚く打設することが好ましい。さらに、図8および図9に示すように、水平面の下部に地下室12を再び作って地下室12を複数層に形成する場合、地下室12の使用目的に応ずる荷重を考慮して各層の水平面は十分な耐力を有するように安全を考慮すべきである。   If the concrete 9 is placed on the horizontal and vertical surfaces of the secured underground space 8, the basement 12 is finally completed. However, since the horizontal surface is the bottom of the basement 12, it may be placed thicker than the vertical surface. preferable. Furthermore, as shown in FIGS. 8 and 9, when the basement 12 is formed again in the lower part of the horizontal plane to form the basement 12 in a plurality of layers, the horizontal plane of each layer is sufficient in consideration of the load corresponding to the purpose of use of the basement 12. Safety should be considered so that it is proof.

本発明の図10は、地下室12が地下2階の形態に構成されることを示しているが、これは竣工建築物1の地盤を掘り出して地下1階の地下空間8を確保した後、これらの水平面と垂直面をコンクリート9で打設して、地下1階の地下室12を確保し、コンクリート9の養生が完了すれば、再び前記地下1階の地下室12の水平面の下部地盤を掘削して地下2層の地下空間8を確保して、その水平面と垂直面をコンクリート9を打設して、地下2階の地下室12を完成するようになる。   FIG. 10 of the present invention shows that the basement 12 is configured in the form of the second basement floor. This is after excavating the ground of the completed building 1 to secure the basement space 8 on the first basement floor. The basement 12 of the first basement is secured by placing the horizontal and vertical planes of concrete with concrete 9, and when the curing of the concrete 9 is completed, the lower ground of the horizontal plane of the basement 12 of the first basement is excavated again. The underground space 8 of the second basement is secured, and concrete 9 is placed on the horizontal and vertical surfaces to complete the basement 12 on the second basement.

従って、前述したような施工方法でユーザの必要に応じて地下室12を複数階に作ることができる。   Therefore, the basement 12 can be made on a plurality of floors according to the needs of the user by the construction method as described above.

一方、本発明は地盤を掘削するステップ(S4)の後、支柱7の外観をきれいにできるように支柱7の外縁に仕上げ部材を被せるステップをさらに含むが、これに使用される仕上げ材は公知のものを使用する。このように支柱7が仕上げ材によって遮断され、内壁はコンクリート9で仕上がるので、これにより施工された地下室12は内部がきれいであって、あたかも新築建築物の地下室のようになる。   On the other hand, the present invention further includes a step of covering the outer edge of the column 7 with a finishing member so that the appearance of the column 7 can be cleaned after the step of excavating the ground (S4). Use things. In this way, the column 7 is blocked by the finishing material, and the inner wall is finished with concrete 9, so that the constructed basement 12 has a clean interior, as if it is a basement of a new building.

以上のように、本発明は、竣工建築物1の地下地盤が本発明を施工できる条件に適するように、地盤に押し込まれた支柱7はその外側縁が地盤と密着し、また底面が地盤によって支えられるので、大きくて重たい超大型ビルのような竣工建築物1の場合も押し込まれた支柱7が安全に支えて、その下部に地下室12を簡便に施工できる。   As described above, the present invention is such that the outer edge of the column 7 pushed into the ground is in close contact with the ground, and the bottom is grounded so that the underground ground of the completed building 1 is suitable for the conditions under which the present invention can be constructed. Since it is supported, even in the case of a completed building 1 such as a large and heavy super-large building, the pushed-in column 7 can safely support and the basement 12 can be easily constructed in the lower part thereof.

図16ないし図19には、本発明の竣工建築物の地下室の施工方法の第2実施形態を示す。   16 to 19 show a second embodiment of the basement construction method for a completed building according to the present invention.

本実施形態の施工方法は、竣工建築物1の内部で底コンクリート2を穿孔せずに、地下室12を施工できる方法である。   The construction method of the present embodiment is a method by which the basement 12 can be constructed without drilling the bottom concrete 2 inside the completed building 1.

本実施形態の施工方法は、図16に示したように、竣工建築物1の一側の下部地盤を掘削した後、露出された底コンクリート2の下部に押込機を設け、前記押込機6の設置地点でパイル7aを地盤に挿入して支柱7を形成する。   As shown in FIG. 16, the construction method according to the present embodiment excavates the lower ground on one side of the completed building 1, and then provides an indenter at the bottom of the exposed bottom concrete 2. The pile 7a is inserted into the ground at the installation point to form the column 7.

支柱7を形成した後、該支柱7の周辺部の地盤を掘削し、掘削した後露出された底コンクリート2の下部に同じ方法にて押込機6を設けた後、パイル7aを挿入施工して支柱7を形成するが、この過程を繰り返すと、図17に示されているように、竣工建築物1の底コンクリート2の下部に掘削面積が次第に広くなり、かつ形成される支柱7の数も増えるようになる。   After the column 7 is formed, the ground around the column 7 is excavated, and after the excavator 6 is provided in the same manner below the bottom concrete 2 exposed after the excavation, the pile 7a is inserted and installed. As shown in FIG. 17, the excavation area gradually increases in the lower part of the bottom concrete 2 of the completed building 1 and the number of the columns 7 to be formed is also increased. Will increase.

前述した過程を繰り返して竣工建築物1の下部地盤を十分に掘削することによって、地下空間が設けられると、図18に示すように、地下空間の底面と側面にコンクリート9を養生して地下室12を作る。そして、前記地下空間に竣工建築物1を支持するための別の柱をコンクリートで形成した後、押込機6とパイル7aを除去したり、油圧ジャッキの除去後前記パイル7aが施工されている位置にコンクリートモルタルを養生させ柱を形成することもできる。   When the underground space is provided by sufficiently excavating the lower ground of the completed building 1 by repeating the above-described process, the concrete 9 is cured on the bottom and side surfaces of the underground space as shown in FIG. make. And after forming another pillar for supporting the completed building 1 in the underground space with concrete, the pusher 6 and the pile 7a are removed, or the position where the pile 7a is constructed after removing the hydraulic jack It is also possible to cure concrete mortar and form pillars.

図19は、本実施形態の施工方法によって竣工建築物1の底コンクリート2の下部に直接に押込機6を設ける際、底コンクリート2が十分な支持強度を有しない場合に、底コンクリート2の下部に支持プレート13をさらに増設する実施形態を示した図である。   FIG. 19 shows the lower part of the bottom concrete 2 when the bottom concrete 2 does not have sufficient supporting strength when the pushing machine 6 is provided directly on the lower part of the bottom concrete 2 of the completed building 1 by the construction method of this embodiment. It is the figure which showed embodiment which further expands the support plate 13. FIG.

押込機6を通じてパイル7aを地中に挿入する際、押込機6が支持される底コンクリート2にも反力が働くようになるが、底コンクリート2の強度または厚さがパイル7aを挿入する過程で発生する反力を十分に支持できない場合、示されているように鉄筋を配筋し、コンクリートモルタルを注いで養生させることによって、押込機6が支持できる支持プレート13を形成する。勿論、底コンクリート2の層の強度が十分であれば、支持プレート13の形成を省略することもできる。   When the pile 7a is inserted into the ground through the pusher 6, a reaction force also acts on the bottom concrete 2 on which the pusher 6 is supported, but the strength or thickness of the bottom concrete 2 inserts the pile 7a. If the reaction force generated in step 1 cannot be sufficiently supported, a reinforcing plate is arranged as shown, and concrete mortar is poured and cured to form the support plate 13 that the pusher 6 can support. Of course, if the strength of the bottom concrete 2 is sufficient, the formation of the support plate 13 can be omitted.

図20ないし図23には、本発明に係る竣工建築物の地下室の施工方法の第3実施形態が示されている。   20 to 23 show a third embodiment of a construction method for a basement of a completed building according to the present invention.

本実施形態は、図20に示すように、小規模の建築物1の下部に地下室12を施工するのに適している。   This embodiment is suitable for constructing a basement 12 in the lower part of a small-scale building 1 as shown in FIG.

本実施形態の施工方法によれば、まず、図21及び図23に示すように、竣工建築物1の外側縁の底コンクリート2に孔とスロットを形成し、該当位置に支持体5を固定させてから押込機6を設ける。   According to the construction method of this embodiment, first, as shown in FIG.21 and FIG.23, a hole and a slot are formed in the bottom concrete 2 of the outer edge of the completed building 1, and the support body 5 is fixed to a corresponding position. After that, the pusher 6 is provided.

支持体5の設置と押込機6の装着過程は、前述した第1実施形態と同様である。
このように建築物1の縁部に複数の支持体5と押込機6を設置し、パイル7aを地中に挿入して中空の建築物1を支持できる複数の支柱7を形成した後、建築物1の底コンクリート2の下部の地盤を掘削し、コンクリート9で底面と側面を仕上げて地下室12を形成する。
The installation process of the support 5 and the mounting process of the pusher 6 are the same as those in the first embodiment described above.
Thus, after installing the support body 5 and the pushing machine 6 in the edge of the building 1 and inserting the pile 7a into the ground to form the support columns 7 that can support the hollow building 1, The ground below the bottom concrete 2 of the object 1 is excavated and the bottom and side surfaces are finished with concrete 9 to form a basement 12.

本実施形態の場合にも、中空の建築物1の縁部の底コンクリート2がパイル7aを挿入する過程において前記支持体5によって伝えられる反力を支持できる十分な支持強度を有しない場合には、底コンクリート2の上部または下部に支持プレート13を増設して支持強度をアップすることができる。   Also in the case of this embodiment, when the bottom concrete 2 at the edge of the hollow building 1 does not have sufficient support strength to support the reaction force transmitted by the support 5 in the process of inserting the pile 7a. Further, the support strength can be increased by adding a support plate 13 above or below the bottom concrete 2.

以上述べた本発明の第2実施形態と第3実施形態は、第1実施形態とは違って、全て竣工建築物1の内部の底コンクリート2を打設せずに施工を行えるので、パイル7aの挿入のために建築物1の内部に穿孔したり、施工完成後穿孔された孔を仕上げる別の作業を要しない。   Unlike the first embodiment, the second embodiment and the third embodiment of the present invention described above can be constructed without placing the bottom concrete 2 inside the completed building 1. Therefore, there is no need for another operation for drilling the inside of the building 1 for the insertion or finishing the drilled hole after the completion of construction.

3 : 孔 4 : スロット
5 : 支持体 5a : ストッパ
6 : 押込機 7 : 支柱
8 : 地下空間 9 : コンクリート
10 : 案内空間 11 : モルタル
12 : 地下室
3: Hole 4: Slot 5: Support 5a: Stopper 6: Pusher 7: Post 8: Underground space 9: Concrete
10: Information space 11: Mortar 12: Basement

Claims (7)

竣工建築物の最下部の底コンクリートに複数の孔を形成し、前記孔を貫通するように支持体を挿入して前記支持体の下部に突出されたストッパを、前記竣工建築物の最下部の底に動かないように固定させるステップと、
前記支持体の上部に押込機を設けるステップと、
前記各孔にパイルを挿入した後、前記押込機を用いて、前記パイルを地下に押し込ませ、前記パイルが押し込まれる度に、前記押し込まれた各パイルの上部に更に他のパイルを積層した後、前記押込機に順次に押し込ませて竣工建築物の地下に建築物を支える支柱を押し込ませるステップと、
地下に押し込まれた前記支柱によって竣工された建築物が支持された状態で、地下空間を確保するために前記建築物の底コンクリートの下部地盤を掘削するステップと、
前記コンクリートの下部地盤を掘削するステップにより確保された地下空間の水平面及び垂直面にコンクリートを打設するステップと、を含むことを特徴とする竣工建築物の地下室の施工方法。
A plurality of holes are formed in the bottom concrete at the bottom of the completed building, a support is inserted so as to pass through the holes, and a stopper protruding at the bottom of the support is provided at the bottom of the completed building. A step to fix it to the bottom,
Providing a pusher on top of the support;
After inserting a pile into each hole, using the pusher, the pile is pushed into the basement, and each time the pile is pushed, another pile is stacked on top of each pushed pile. A step of sequentially pushing the pushing machine into the basement of the completed building and pushing a column supporting the building.
Excavating the bottom ground of the bottom concrete of the building to secure an underground space in a state where the completed building is supported by the struts pushed into the basement;
Placing the concrete on the horizontal and vertical surfaces of the underground space secured by the step of excavating the lower ground of the concrete, and a method of constructing the basement of the completed building.
前記支持体を固定させるステップは、複数の支持体の上端部を結束し、各支持体の下部に突出されたストッパを、前記孔に沿って貫通されたスロットに貫通させて前記コンクリートに係止させ、前記スロットにモルタルを打設して、孔縁に支持体を固定することを特徴とする請求項1に記載の竣工建築物の地下室の施工方法。   The step of fixing the support includes binding upper ends of a plurality of supports, and locking a stopper protruding from a lower portion of each support through the slot penetrating the hole to the concrete. 2. A construction method for a basement of a completed building according to claim 1, wherein a mortar is placed in the slot, and a support is fixed to a hole edge. 前記コンクリートの下部地盤を掘削するステップは、前記竣工建築物の地下に押し込まれた支柱の底面が露出しない深さまで掘削し、その過程で形成された地下空間に、コンクリートを少なくとも1回以上打設して地下室を施工することを特徴とする請求項1または2に記載の竣工建築物の地下室の施工方法。   The step of excavating the lower ground of the concrete is excavating to a depth at which the bottom surface of the pillar pushed into the basement of the completed building is not exposed, and the concrete is placed at least once in the underground space formed in the process The basement construction method for a completed building according to claim 1 or 2, wherein the basement is constructed. 竣工建築物の底コンクリートの下部地盤を掘削し、前記底コンクリートの下部を支持するパイルを地中に挿入して複数の支柱を設けるステップと、
前記支柱を設置するために前記底コンクリートの下部地盤を掘削して確保された地下空間の底面及び側面にコンクリートを打設するステップとを含むことを特徴とする竣工建築物の地下室の施工方法。
Excavating the bottom ground of the bottom concrete of the completed building, inserting a pile supporting the bottom of the bottom concrete into the ground, and providing a plurality of struts;
And a step of placing concrete on the bottom and side surfaces of the underground space secured by excavating the lower ground of the bottom concrete for installing the support column.
前記複数の支柱を設けるステップは、前記竣工建築物の底コンクリートの下部一端を先に掘削した後に露出した底コンクリートの下部に、支持プレートを設置し、前記支持プレートに支持される押込機を通じて、パイルを地中に挿入して支柱を施工した後、
施工された支柱の周辺の地盤を掘削し、露出された前記底コンクリートの下部に支持プレートと押込機を設けた後、前記パイルを挿入して支柱を形成する一連の過程を順次に行ってなされることを特徴とする請求項4に記載の竣工建築物の地下室の施工方法。
The step of providing the plurality of struts is a method of installing a support plate at a lower portion of the bottom concrete exposed after first excavating a lower end of the bottom concrete of the completed building, and through a pusher supported by the support plate, After inserting the pile into the ground and constructing the column,
After excavating the ground around the installed struts, providing a support plate and an indenter under the exposed bottom concrete, a series of processes for forming the struts by inserting the pile are sequentially performed. The construction method of the basement of the completed building according to claim 4.
竣工建築物の縁部に、相互に所定間隔に離隔されている複数の支持体を形成するステップと、
前記支持体に押込機を設けるステップと、
前記押込機を通じてそれぞれの支持体の下部地中にパイルを挿入して前記竣工建築物を支える複数の支柱を形成するステップと、
前記支柱によって支えられた竣工建築物の下部地盤を掘削するステップと、
前記竣工建築物の下部地盤を掘削して確保された地下空間の底面及び側面にコンクリートを打設するステップとを含むことを特徴とする竣工建築物の地下室の施工方法。
Forming a plurality of supports spaced from each other at a predetermined interval on the edge of the completed building;
Providing a pusher on the support;
Inserting a pile into the lower ground of each support through the pusher to form a plurality of columns to support the completed building;
Excavating the lower ground of the completed building supported by the struts;
And a step of placing concrete on the bottom and side surfaces of the underground space secured by excavating the lower ground of the completed building.
前記支持体を形成するステップは、前記竣工建築物の下部縁の地盤を所定深さまで掘削してモルタル打設空間を形成するステップと、
前記竣工建築物の下部に連結されるように前記モルタル打設空間にコンクリートを打設して反力部を形成するステップと、
前記コンクリートが養生されて形成された前記反力部に、上下に穿孔された孔を形成し、前記孔を貫通するように支持体を挿入して、前記支持体の下部に突出されたストッパを前記建築物の最下部の底に動かないように固定させるステップとを含むことを特徴とする請求項6に記載の竣工建築物の地下室の施工方法。
The step of forming the support body includes a step of excavating the ground of the lower edge of the completed building to a predetermined depth to form a mortar placement space;
Placing concrete in the mortar placement space to be connected to the lower part of the completed building to form a reaction force part;
A hole drilled up and down is formed in the reaction force portion formed by curing the concrete, a support body is inserted so as to penetrate the hole, and a stopper projecting at the lower part of the support body is provided. The method for constructing a basement of a completed building according to claim 6, further comprising the step of fixing the bottom of the building so as not to move.
JP2011276024A 2010-12-16 2011-12-16 Construction method of cellar for building completed Pending JP2012127186A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020100129317A KR101026731B1 (en) 2010-12-16 2010-12-16 Construction method of cellar for building completed
KR10-2010-0129317 2010-12-16

Publications (1)

Publication Number Publication Date
JP2012127186A true JP2012127186A (en) 2012-07-05

Family

ID=44049552

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011276024A Pending JP2012127186A (en) 2010-12-16 2011-12-16 Construction method of cellar for building completed

Country Status (4)

Country Link
US (1) US20120155968A1 (en)
JP (1) JP2012127186A (en)
KR (1) KR101026731B1 (en)
CN (1) CN102561391A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101431621B1 (en) * 2013-03-11 2014-08-21 주식회사 엔티에스건설 Mehod for constructing underground wall in extension of undergound parking lot

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9605404B2 (en) 2013-05-29 2017-03-28 Glen G. Hale High strain dynamic load testing procedure
US9556581B2 (en) 2013-05-29 2017-01-31 Glen G. Hale Pile cap connectors
US9458593B2 (en) * 2013-05-29 2016-10-04 Glen G. Hale Deep pile foundation construction methodology for existing and new buildings
CN104120738A (en) * 2014-08-19 2014-10-29 广东南方电信规划咨询设计院有限公司 Non-migration-type supporting and protecting system and method of communication man/hand hole
CN105298757A (en) * 2015-11-26 2016-02-03 内蒙古久和能源装备有限公司 Vibration reduction and bias voltage reduction wind turbine generator set mounting structure
US10487469B2 (en) * 2016-11-16 2019-11-26 Goliathtech Inc. Support assembly for a building structure
US11299863B2 (en) * 2016-11-16 2022-04-12 Goliathtech, Inc. Support assembly for a building structure
CN108930544A (en) * 2018-07-27 2018-12-04 中铁十四局集团有限公司 A kind of broken ground underground large space method of construction
CN111321762A (en) * 2020-03-02 2020-06-23 广州市胜特建筑科技开发有限公司 Accurate basement building method
CN112240025A (en) * 2020-10-21 2021-01-19 上海隧道工程有限公司 Station foundation pit engineering cover-excavation construction method
CN114233179B (en) * 2021-12-15 2023-10-27 北京中泓升环境科技有限公司 Construction foundation drilling equipment with square and round hole switching function
CN114808929B (en) * 2022-03-07 2023-08-08 上海建工二建集团有限公司 Connection method and connection node of pile integrated cast-in-place pile and horizontal structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5016890B1 (en) * 1970-07-22 1975-06-17
JPH11166242A (en) * 1997-12-03 1999-06-22 Tsujino Kensetsu:Kk Underground space constructing method and supporting structure in underground space construction
KR20060045965A (en) * 2004-06-28 2006-05-17 마이크로소프트 코포레이션 Integrating best practices into database design
JP2009057816A (en) * 2007-08-03 2009-03-19 Taisei Ulec Kk Horizontal height correcting construction method of structure, machine tool used for its construction method and bearing power reinforcing construction method of structure

Family Cites Families (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4338047A (en) * 1980-09-15 1982-07-06 E. F. David, Inc. System for pier underpinning of settling foundation
US4854782A (en) * 1987-11-25 1989-08-08 Sandra L. May Apparatus for lifting structures
US5116355A (en) * 1991-06-11 1992-05-26 Freeman Iii Thomas R System for underpinning a building
US5269630A (en) * 1993-02-02 1993-12-14 Power Lift Foundation Repair Slab lifter
WO1997007295A1 (en) * 1995-08-17 1997-02-27 Roland Beck Building underpinning process
JPH1143955A (en) * 1997-07-28 1999-02-16 Maeda Corp Basement constructing method in existing building
JPH11350746A (en) 1998-06-11 1999-12-21 Takenaka Komuten Co Ltd Underground structure of building
US6503024B2 (en) * 2000-03-06 2003-01-07 Stan Rupiper Concrete foundation pierhead and method of lifting a foundation using a jack assembly
US6676335B1 (en) * 2000-11-07 2004-01-13 Dry Basement, Inc. Structure jacking system and method
US7163357B1 (en) * 2001-10-02 2007-01-16 Peterson James L Method and apparatus for lifting and stabilizing subsided slabs, flatwork and foundations of buildings
US6881012B2 (en) * 2002-04-24 2005-04-19 Gregory R. Covington Foundation repair system and method of installation
US6923599B2 (en) * 2002-06-24 2005-08-02 Kenneth J. Kelso In-ground lifting system and method
ITBO20020552A1 (en) * 2002-08-30 2004-02-29 Soles Societa Lavori Edili E Serbatoi Spa METHOD FOR THE CREATION OF A BASEMENT ROOM UNDER A BUILDING IN WORK.
US7090435B2 (en) * 2004-09-24 2006-08-15 Leroy Mitchell Method and apparatus for raising, leveling, and supporting displaced foundation allowing for readjustment after installation
CN100348835C (en) * 2005-06-07 2007-11-14 上海市城市建设设计研究院 Construction method of subsurface excavation and layer added by using top layer of existed basement as native cover board
KR100621669B1 (en) * 2006-05-23 2006-09-07 주식회사고려이엔시 Structure lifting and foundation strengthening method using the steel pipe
ITBO20060414A1 (en) * 2006-05-26 2007-11-27 Soles Societa Lavori Edili E Serbatoi Spa METHOD FOR LIFTING A BUILDING AFT.
KR100654228B1 (en) 2006-08-24 2006-12-06 정언섭 Structure lifting method possible to be re-lifting using pile member
CN100595395C (en) * 2007-12-27 2010-03-24 山东建筑大学 Static pressure pile process for construction of existing building basement
US8206063B2 (en) * 2008-12-30 2012-06-26 Steven Patton Concentrically loaded, adjustable piering system
EE00970U1 (en) 2009-03-31 2010-10-15 As Amhold The method of constructing a building under the architectural “flattening
CN101718092A (en) * 2009-11-27 2010-06-02 上海隧道工程股份有限公司 Environment micro-turbulence static pressing pile construction technology under low-headroom condition

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5016890B1 (en) * 1970-07-22 1975-06-17
JPH11166242A (en) * 1997-12-03 1999-06-22 Tsujino Kensetsu:Kk Underground space constructing method and supporting structure in underground space construction
KR20060045965A (en) * 2004-06-28 2006-05-17 마이크로소프트 코포레이션 Integrating best practices into database design
JP2009057816A (en) * 2007-08-03 2009-03-19 Taisei Ulec Kk Horizontal height correcting construction method of structure, machine tool used for its construction method and bearing power reinforcing construction method of structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101431621B1 (en) * 2013-03-11 2014-08-21 주식회사 엔티에스건설 Mehod for constructing underground wall in extension of undergound parking lot

Also Published As

Publication number Publication date
US20120155968A1 (en) 2012-06-21
KR101026731B1 (en) 2011-04-08
CN102561391A (en) 2012-07-11

Similar Documents

Publication Publication Date Title
JP2012127186A (en) Construction method of cellar for building completed
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
KR100967497B1 (en) Method for constructing an underground structure
KR101655077B1 (en) Construction method of block for prefabricated retaining wall
KR101041274B1 (en) Retaining wall grouting structure and method for constructing thereof
JP6274406B2 (en) Construction method of new underground structure with dismantling of existing underground structure
KR20140055639A (en) A execution method of architecture beam
KR20090050997A (en) Basement construction method using the steel pipe
KR101793037B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR101377019B1 (en) Reactive forcing device using guide rail and foundation reinforcing method therewith
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
JP2012092601A (en) Open shield machine start method of open shield method
JP5124007B2 (en) Retaining wall construction method
JP5228862B2 (en) Underground structure, construction method of underground structure
JP5367452B2 (en) Underground wall construction method and underground wall body
KR100967496B1 (en) Device for constructing an underground structure
KR20030097084A (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
KR100926323B1 (en) Constructing method for extension of underground
KR20050113450A (en) Downward reinforced-concrete underground structure using temporary assistant columns
KR20190012368A (en) Smallcaliber composite pile wall using small drilling rig at adjacent building proximity section and construction method of the same
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
KR101707376B1 (en) Structure for constructing underground structure using composite beams and the construction method thereof
RU2581853C1 (en) Method for construction of pile foundation
JP6534026B2 (en) Seismic isolation building and its construction method
KR101026112B1 (en) The construction method of underground structure using mega-structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130419

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130424

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20131001