CN111321762A - Accurate basement building method - Google Patents

Accurate basement building method Download PDF

Info

Publication number
CN111321762A
CN111321762A CN202010136663.1A CN202010136663A CN111321762A CN 111321762 A CN111321762 A CN 111321762A CN 202010136663 A CN202010136663 A CN 202010136663A CN 111321762 A CN111321762 A CN 111321762A
Authority
CN
China
Prior art keywords
split
basement
side wall
side walls
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010136663.1A
Other languages
Chinese (zh)
Inventor
吴如军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Shengte Construction Technology Development Co ltd
Original Assignee
Guangzhou Shengte Construction Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shengte Construction Technology Development Co ltd filed Critical Guangzhou Shengte Construction Technology Development Co ltd
Priority to CN202010136663.1A priority Critical patent/CN111321762A/en
Publication of CN111321762A publication Critical patent/CN111321762A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Electromagnetism (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A method for accurately building a basement. The basement is located right below the building, and S1, a support pile for supporting the building is driven downwards from the ground of the building; s2, defining the horizontal plane position of the side wall of the basement at the periphery of the building, and presetting the split female side wall of the basement at the horizontal plane position; s3, driving the side walls of the split nuts into the ground respectively; s4, excavating from the ground to the underground at the inner periphery of the area defined by the side walls of the split female, wherein the excavating depth is smaller than the embedding depth of the side walls of the split female, so that a lower supporting soil layer is reserved below the side of the split female, and the lower supporting soil layer is used for supporting the lower part of the side walls of the split female in the horizontal direction; s5, arranging a supporting structure to support the upper part of the side wall of the split female, and hollowing out other soil layers except the lower soil protection layer in the area defined by the side wall of the split female; s6, connecting the split female side walls into a whole to form the side walls of the basement; and S7, pouring the top wall and the bottom wall of the basement and respectively connecting the top wall and the bottom wall of the basement with the split female side walls to form the basement.

Description

Accurate basement building method
Technical Field
The invention relates to a method for building basements for existing buildings, in particular to a precise method for building basements.
Background
At present, in the prior art, a method for building a basement in an existing building is described in the background of chinese patent CN 201310040277: the basement building envelope and the waterproof curtain are built firstly, then the brick wall is built on the outer side of the basement building envelope, concrete is filled between the building envelope and the brick wall, the waterproof layer and the waterproof protective layer are made after cement mortar is cut outside the brick wall, the reinforcing steel bar is bound to the inner wall template after the waterproof protective layer is made, and concrete is poured to form the basement wall. The method comprises the following steps: (1) digging a foundation pit, and erecting a supporting structure on the inner side wall of the foundation pit, wherein one end of the supporting structure is connected with the inner side wall of the foundation pit, and the other end of the supporting structure is connected with the bottom wall of the foundation pit; (2) and pouring to form the wall of the basement.
The defects of the prior art are as follows: in the prior art, only the bottom of a basement is provided with a supporting structure, but the upper part of the basement is not provided with the supporting structure, so that the wall of the side wall of the basement is deviated during construction, and the supporting is not stable enough.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention aims to provide an accurate method for additionally building the basement, which can stably support and build the basement.
The method for accurately building the basement, wherein the basement is positioned right below a building, comprises the following steps: s1, driving a support pile downwards from the ground of the building for supporting the building; s2, defining the horizontal plane position of the side wall of the basement at the periphery of the building, and presetting the split female side wall of the basement at the horizontal plane position; s3, driving the side walls of the split nuts into the ground respectively; s4, excavating from the ground to the underground at the inner periphery of the area defined by the side walls of the split female, wherein the excavating depth is smaller than the embedding depth of the side walls of the split female, so that a lower supporting soil layer is reserved below the side of the split female, and the lower supporting soil layer is used for supporting the lower part of the side walls of the split female in the horizontal direction; s5, arranging a supporting structure to support the upper part of the side wall of the split female, and hollowing out other soil layers except the lower soil protection layer in the area defined by the side wall of the split female; s6, connecting the split female side walls into a whole to form the side walls of the basement; and S7, pouring the top wall and the bottom wall of the basement and respectively connecting the top wall and the bottom wall of the basement with the split female side walls to form the basement.
Further, the "pouring of the basement bottom wall" refers to pouring of the top wall and the bottom wall of the basement on the surface of the lower supporting soil layer.
Furthermore, the split main side wall is divided into a plurality of segments of split sub side walls in the height direction, and the lowermost segment is a basic segment of split sub side walls; further comprising the steps of: S3-A, placing the side walls of the split sub-bodies of the basic section on the ground; S3-B, driving the side wall of the split sub of the foundation section on the ground into the ground; S3-C, welding and lengthening the steel bars on the side wall of the split sub of the foundation section driven into the ground in the S3-B upwards, and pouring the side wall of the split sub of the next section on the ground; and S3-D, driving the side wall of the next section of the split sub into the ground.
Furthermore, when a section of the split sub-side wall is driven in, the inner periphery of the area defined by the split main-side wall is excavated from top to bottom, and the excavating depth is equal to the height of the split sub-side wall, so that a new lower supporting soil layer is formed at the lower part of the base section split sub-side wall.
Has the advantages that: the lower supporting soil layer does not need to be specially built, the lower supporting soil layer has the same effect as a supporting structure, the lower supporting soil layer is used for supporting the lower portion of the split female side wall, only one supporting structure is needed to be arranged for supporting the upper portion of the split female side wall, the upper portion and the lower portion of the split female side wall are supported, and the supporting structure is stable.
Drawings
FIG. 1 is a schematic view of the position relationship of a basement according to the present invention;
fig. 2 is a schematic view of the basement after the building is completed.
Wherein: 1. a building; 2. supporting piles; 3. a basement; 4. a ground surface; 5. a split female sidewall; 6. a lower supporting soil layer; 7. basement bottom wall.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and the detailed description, and it should be noted that any combination of the embodiments or technical features described below can be used to form a new embodiment without conflict.
As shown in fig. 1, the present invention provides a precise method for building a basement, which includes:
s1, the constructor drives the supporting pile 2 which can support the building 1 into the ground;
s2, the constructor defines the horizontal position of the basement wall (the basement is located right below the building) at the periphery of the building according to the design position of the basement 3 (the basement is located right below the building), and then presets the split female side wall 5 of the basement at the projection of the split female side wall 5 relative to the ground 4 (i.e. on the ground); s3, driving the side walls of the split nuts into the ground respectively; s4, excavating from the ground to the underground at the inner periphery of the area defined by the side walls of the split female, wherein the excavating depth is smaller than the embedding depth of the side walls of the split female, so that a lower supporting soil layer 6 is reserved below the side of the split female, and the lower supporting soil layer is used for supporting the lower part of the side walls of the split female in the horizontal direction; s5, arranging a supporting structure (for example, a cross bar, wherein two ends of the cross bar are respectively connected with the upper parts of two split female side walls facing each other) to support the upper parts of the split female side walls, and hollowing out other soil layers in the area enclosed by the split female side walls except for the lower soil protection layer; s6, connecting the split female side walls into a whole to form the side walls of the basement; and S7, pouring the top wall and the bottom wall of the basement and respectively connecting the top wall and the bottom wall of the basement with the split female side walls to form the basement. The constructor pours the top wall and the bottom wall 7 of the basement to be connected with the split female side wall 3 to form the basement, and then can detach the supporting pile.
In fact, the bottom wall of the basement is cast directly on the surface of the underlying supporting soil, as shown in fig. 2, which has the advantage of not requiring additional installation and removal of the supporting structure.
In addition, the split mother side wall is divided into a plurality of segments of split subsidiary side walls in the height direction, and the lowest segment is the basic segment split subsidiary side wall; s3 further includes the steps of: S3-A, placing the side walls of the split sub-bodies of the basic section on the ground; S3-B, driving the side wall of the split sub of the foundation section on the ground into the ground; S3-C, welding and lengthening the steel bars on the side wall of the split sub of the foundation section driven into the ground in the S3-B upwards, and pouring the side wall of the split sub of the next section on the ground; and S3-D, driving the side wall of the next section of the split sub into the ground. When a section of the split sub-side wall is driven in, the inner periphery of the area defined by the split main side wall is excavated from top to bottom, the excavated depth is equal to the height of the split sub-side wall, so that a new lower soil protection layer is formed at the lower part of the split sub-side wall of the basic section, namely, the side wall of the split sub-side of the basic section is gradually driven to the target depth, and is driven to a certain depth and then is excavated once, and finally the split sub-side wall and the lower soil protection layer of the basic section sink to the target depth.
The above embodiments are only preferred embodiments of the present invention, and the protection scope of the present invention is not limited thereby, and any insubstantial changes and substitutions made by those skilled in the art based on the present invention are within the protection scope of the present invention.

Claims (4)

1. The method for accurately building the basement is characterized by comprising the following steps of:
s1, driving a support pile downwards from the ground of the building for supporting the building;
s2, defining the horizontal plane position of the side wall of the basement at the periphery of the building, and presetting the split female side wall of the basement at the horizontal plane position;
s3, driving the side walls of the split nuts into the ground respectively;
s4, excavating from the ground to the underground at the inner periphery of the area defined by the side walls of the split female, wherein the excavating depth is smaller than the embedding depth of the side walls of the split female, so that a lower supporting soil layer is reserved below the side of the split female, and the lower supporting soil layer is used for supporting the lower part of the side walls of the split female in the horizontal direction;
s5, arranging a supporting structure to support the upper part of the side wall of the split female, and hollowing out other soil layers except the lower soil protection layer in the area defined by the side wall of the split female;
s6, connecting the split female side walls into a whole to form the side walls of the basement;
and S7, pouring the top wall and the bottom wall of the basement and respectively connecting the top wall and the bottom wall of the basement with the split female side walls to form the basement.
2. The accurate basement building method of claim 1, wherein: the "placement of the basement bottom wall" in S6 means that the top wall and the bottom wall of the basement are placed on the surface of the lower supporting soil layer.
3. The method of adding basement to an existing building as recited in claim 1, wherein: the split main side wall is divided into a plurality of segments of split sub side walls in the height direction, and the lowest segment is the basic segment split sub side wall; s3 further includes the steps of:
S3-A, placing the side walls of the split sub-bodies of the basic section on the ground;
S3-B, driving the side wall of the split sub of the foundation section on the ground into the ground;
S3-C, welding and lengthening the steel bars on the side wall of the split sub of the foundation section driven into the ground in the S3-B upwards, and pouring the side wall of the split sub of the next section on the ground;
and S3-D, driving the side wall of the next section of the split sub into the ground.
4. A method of adding a basement to an existing building as claimed in claim 3, wherein: when a section of the split sub side wall is driven in, the inner periphery of the area enclosed by the split main side wall is excavated from top to bottom, and the excavating depth is equal to the height of the split sub side wall, so that a new lower supporting soil layer is formed at the lower part of the base section split sub side wall.
CN202010136663.1A 2020-03-02 2020-03-02 Accurate basement building method Pending CN111321762A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010136663.1A CN111321762A (en) 2020-03-02 2020-03-02 Accurate basement building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010136663.1A CN111321762A (en) 2020-03-02 2020-03-02 Accurate basement building method

Publications (1)

Publication Number Publication Date
CN111321762A true CN111321762A (en) 2020-06-23

Family

ID=71165593

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010136663.1A Pending CN111321762A (en) 2020-03-02 2020-03-02 Accurate basement building method

Country Status (1)

Country Link
CN (1) CN111321762A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2668525B1 (en) * 1990-10-30 1993-01-15 Harnois Georges PROCESS FOR THE PRODUCTION IN THE BASEMENT OF AN ADDITIONAL PREMISES.
CN102071813A (en) * 2010-11-18 2011-05-25 杭州岩土工程有限公司 Method for constructing underground garage under old building
CN102561391A (en) * 2010-12-16 2012-07-11 株式会社高丽工程及咨询 Construction method of cellar for building completed
CN107905257A (en) * 2017-11-24 2018-04-13 上海市机械施工集团有限公司 A kind of construction method of city integrated piping lane
CN110616739A (en) * 2019-09-12 2019-12-27 上海建工集团股份有限公司 Vertical construction method for underground space of existing building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2668525B1 (en) * 1990-10-30 1993-01-15 Harnois Georges PROCESS FOR THE PRODUCTION IN THE BASEMENT OF AN ADDITIONAL PREMISES.
CN102071813A (en) * 2010-11-18 2011-05-25 杭州岩土工程有限公司 Method for constructing underground garage under old building
CN102561391A (en) * 2010-12-16 2012-07-11 株式会社高丽工程及咨询 Construction method of cellar for building completed
CN107905257A (en) * 2017-11-24 2018-04-13 上海市机械施工集团有限公司 A kind of construction method of city integrated piping lane
CN110616739A (en) * 2019-09-12 2019-12-27 上海建工集团股份有限公司 Vertical construction method for underground space of existing building

Similar Documents

Publication Publication Date Title
KR100788623B1 (en) Top-down method using precast-concrete colum
CN102561721B (en) Building jacking deviation rectifying method
JP2015025292A (en) Building construction method and building
CN110158602B (en) Soft soil geological deep foundation pit supporting excavation construction structure and construction method
KR101187170B1 (en) Application of under pinning method in remodeling
KR100976621B1 (en) Construction method for basement extention
US6948885B2 (en) Method for constructing foundation
KR100976620B1 (en) Construction method for basement extention
CN111827280A (en) Ex-situ pouring, jacking and in-place hole digging pile retaining wall device and construction method thereof
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
CN111321762A (en) Accurate basement building method
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
KR101222348B1 (en) The Supporting Structure and Pressing device of Underground Structure
CN108457300B (en) Construction method for replacing support of underground large-span structure by cover-excavation method
GB2261891A (en) Installing columns e.g. below ground
JP6938198B2 (en) Construction method
KR100495243B1 (en) Self supporting retaining wall construction method
JP6534026B2 (en) Seismic isolation building and its construction method
CN114351746B (en) Mountain area river-following steep bank slope pile foundation platform and construction method
JP4146250B2 (en) Open caisson bottom plate construction method
CN115262568B (en) Deepening support and excavation construction method based on zero-field deep foundation pit
US20030084630A1 (en) Perimeter walls
JP3809340B2 (en) Reverse strike method
JP6832761B2 (en) How to rebuild the building
JP2023006744A (en) Constructing method of under-ground piled column and pile follower used therefor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200623