JP2012072648A - Installed foundation construction method - Google Patents

Installed foundation construction method Download PDF

Info

Publication number
JP2012072648A
JP2012072648A JP2011189665A JP2011189665A JP2012072648A JP 2012072648 A JP2012072648 A JP 2012072648A JP 2011189665 A JP2011189665 A JP 2011189665A JP 2011189665 A JP2011189665 A JP 2011189665A JP 2012072648 A JP2012072648 A JP 2012072648A
Authority
JP
Japan
Prior art keywords
installation
construction method
bottom wall
foundation
foundation construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2011189665A
Other languages
Japanese (ja)
Other versions
JP5921116B2 (en
Inventor
Kazumasa Takagi
一昌 高木
Eizo Takagi
栄造 高木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Marutaka Kogyo Inc
Original Assignee
Marutaka Kogyo Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Marutaka Kogyo Inc filed Critical Marutaka Kogyo Inc
Priority to JP2011189665A priority Critical patent/JP5921116B2/en
Publication of JP2012072648A publication Critical patent/JP2012072648A/en
Application granted granted Critical
Publication of JP5921116B2 publication Critical patent/JP5921116B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a foundation construction method capable of reducing labor and costs required for installation of a foundation and capable of shortening a construction period for the installation of the foundation.SOLUTION: An installed foundation construction method comprises: an anchor bolt installation step of installing a plurality of anchor bolts 15 in locations for installing a foundation 10; a metal pipe fixing step of fixing a steel pipe 19 to free ends 18 of the anchor bolts 15 in the state of separating the steel pipe 19 upward from a concrete skeleton 12; a waterproof member installation step of installing a waterproof member 31 outside a side wall 21 of the steel pipe 19; a cement-hardened material infilling step of infilling mortar 35 into space 29; a top closing step of fixing a cover 36 to the top of the steel pipe 19; and a protective member installation step of installing a calcium silicate plate 41 outside the waterproof member 31.

Description

本発明は、据え付け基礎施工方法に関し、さらに詳細には、新設または既設のコンクリート構造物にソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を設置するために使用する据付け基礎を施工する据え付け基礎施工方法に関する。   The present invention relates to an installation foundation construction method, and more specifically, to a new or existing concrete structure such as a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure. The present invention relates to an installation foundation construction method for constructing an installation foundation used for installation.

新設または既設の鉄筋コンクリート造や鉄筋鉄骨コンクリート造等のコンクリート構造物では、屋上や地下のスラブにソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の様々な機械器具、鉄塔や鉄骨建設物等の様々な建築物が設置される。通常、そのような機械器具や建築物は、その内部への水の侵入を防ぐ目的、機械器具や建築物の背面側のメンテナンスを可能にする目的からそれらがスラブの表面に直に設置されることはなく、それらがスラブに据え付けられた据え付け基礎の上に備え付けられる。   In new or existing concrete structures such as reinforced concrete structures and reinforced steel concrete structures, roofs and underground slabs, solar panels, antennas, water storage tanks, septic tanks, air conditioners, and other various machinery and equipment, steel towers and steel structures, etc. Various buildings are installed. Typically, such machinery and buildings are installed directly on the surface of the slab for the purpose of preventing water from entering the interior and enabling maintenance on the back side of the machinery and buildings. There is nothing, they are mounted on a mounting foundation mounted on a slab.

そのような据え付け基礎の一例として、特許文献1は、太陽電池パネル据え付け構造を開示している。特許文献1において説明されている従来技術では、太陽電池パネルの施工現場の据え付け箇所において型枠を製作し、その型枠内にコンクリートを打設・養生することにより基礎を作り、搬送されてきた太陽電池パネルおよびその架台をその基礎の上に組み付ける構造である。そのような従来技術の据え付け基礎では、施工現場で型枠を製作しなければならないから、その分の手間がかかることはもちろん、型枠内に流し込んだコンクリートの養生に時間がかかり、短い工期で据え付け構造を作ることができない。   As an example of such an installation foundation, Patent Document 1 discloses a solar cell panel installation structure. In the prior art described in Patent Document 1, a formwork is produced at a place where a solar cell panel is installed, and a foundation is formed and transported by placing and curing concrete in the formwork. This is a structure in which the solar cell panel and its mount are assembled on the foundation. In such a conventional installation foundation, since the formwork must be manufactured at the construction site, it takes time and effort to cure the concrete poured into the formwork, and in a short construction period. Cannot make a stationary structure.

かかる従来技術の問題点を解決するために、特許文献1に開示の太陽電池パネル据え付け構造では、基礎部品製造工場においてコンクリート製または鉄筋コンクリート製の基礎をあらかじめ製造し、その基礎をコンクリート構造物の屋上や地下の施工現場に搬送する。その後、屋上や地下のスラブの据え付け箇所に薄いセメント層を形成し、そのセメント層を接着層としてその上に基礎を載せてスラブと一体化し、太陽電池パネルの設置用架台をそれらの基礎の上に備え付ける。特許文献1に開示された太陽電池パネル据え付け構造は、太陽電池パネルを備え付けるための基礎を形成する際に施工現場において型枠を製作する必要がないから、その分の手間が省け、施工現場における施工作業を簡略化することができるとともに、コンクリートを養生する時間を省くことができ、その分の工期を短縮することができる。   In order to solve such problems of the prior art, in the solar cell panel mounting structure disclosed in Patent Document 1, a concrete or reinforced concrete foundation is manufactured in advance at a foundation parts manufacturing factory, and the foundation is used as a roof of a concrete structure. And transported to underground construction sites. After that, a thin cement layer is formed on the roof or underground slab installation site, the cement layer is used as an adhesive layer, the foundation is placed on top of it, and it is integrated with the slab. Prepare for. Since the solar cell panel mounting structure disclosed in Patent Document 1 does not need to produce a formwork at the construction site when forming the foundation for installing the solar cell panel, it saves that much labor, and at the construction site The construction work can be simplified, the time for curing the concrete can be omitted, and the construction period can be shortened.

特開平9−070188号公報JP-A-9-070188

前記特許文献1に開示の太陽電池パネル据え付け構造では、施工現場でコンクリートを養生する必要はないが、基礎製造工場においてコンクリートを養生して基礎を作らなければならず、基礎の製造にコンクリートの養生が必要であることに変わりはない。さらに、製造した基礎を工場から施工現場に搬送することになり、相当な重量を有する基礎を搬送する手間を要するから、基礎を施工する労力やコストを低減することができない。また、工場で製造された基礎をスラブに固定する場合、コンクリート層を接着層としてスラブに固定する方法や凹部をスラブに形成して基礎の下端をその凹部に嵌め込む方法しか採用できず、基礎をスラブに強固に据え付けることができない。   In the solar cell panel mounting structure disclosed in Patent Document 1, it is not necessary to cure the concrete at the construction site, but the foundation must be made by curing the concrete at the foundation manufacturing factory. Is still necessary. Furthermore, since the manufactured foundation is transported from the factory to the construction site, and labor is required to transport the foundation having a considerable weight, the labor and cost for constructing the foundation cannot be reduced. Moreover, when fixing a foundation manufactured at a factory to a slab, only a method of fixing a concrete layer to the slab as an adhesive layer or a method of forming a recess in the slab and fitting the lower end of the foundation into the recess can be adopted. Cannot be firmly installed on the slab.

本発明の目的は、新設または既設のコンクリート構造物に機械機器や建築物を備え付ける強固な基礎を作ることができ、その基礎の据え付けに要する労力やコストを低減することができるとともに、その基礎の据え付けの工期を短縮することができる基礎施工方法を提供することにある。   The object of the present invention is to make a strong foundation for installing machinery and buildings on a new or existing concrete structure, reduce the labor and cost required to install the foundation, and The object is to provide a foundation construction method capable of shortening the installation period.

前記課題を解決するための本発明の前提は、新設または既設のコンクリート構造物の所定の据え付け箇所に据え付けられる据え付け基礎を施工する据え付け基礎施工方法である。   The premise of the present invention for solving the above-mentioned problem is an installation foundation construction method for constructing an installation foundation to be installed at a predetermined installation location of a new or existing concrete structure.

前記前提における本発明の特徴は、据え付け基礎施工方法が、据え付け箇所に複数のアンカーボルトの固定端部を固定してそれらアンカーボルトの自由端部をコンクリート構造物から上方へ起立させるアンカーボルト設置工程と、底壁およびその底壁の周縁から上方へ延びる周壁を有する金属管をコンクリート構造物から上方へ離間させた状態でアンカーボルトの自由端部に固定手段を介して固定する金属管固定工程と、コンクリート構造物と金属管の底壁との間に形成された空間にセメント硬化物を充填するセメント硬化物充填工程と、金属管の頂部に金属蓋を固定して金属管の頂部開口を閉塞する頂部閉塞工程とを有することにある。   The feature of the present invention based on the above premise is that the installation foundation construction method includes fixing the fixed ends of a plurality of anchor bolts at the installation location and raising the free ends of the anchor bolts upward from the concrete structure. And a metal tube fixing step of fixing a metal tube having a bottom wall and a peripheral wall extending upward from the periphery of the bottom wall to a free end portion of the anchor bolt via a fixing means in a state of being spaced upward from the concrete structure. The cement hardened material filling process fills the space formed between the concrete structure and the bottom wall of the metal tube, and the top of the metal tube is closed by fixing the metal lid to the top of the metal tube. And a top closing step.

本発明の一例としては、据え付け基礎施工方法が、コンクリート構造物と金属管の底壁の周縁との間に延びる空隙を塞ぐ成型材を金属管の底壁の周縁の外側近傍に設置する成型材設置工程を含み、セメント硬化物充填工程では、コンクリート構造物と金属管の底壁と成型材とに囲繞された空間にセメント硬化物を充填し、頂部閉鎖工程では、空間に充填されたセメント硬化物の養生期間を待つことなく、空間にセメント硬化物を充填した直後に金属蓋を金属管の頂部に固定する。   As an example of the present invention, the mounting foundation construction method is a molding material in which a molding material that closes a gap extending between the concrete structure and the peripheral edge of the bottom wall of the metal pipe is installed near the outer periphery of the peripheral edge of the bottom wall of the metal pipe. Including the installation process, in the cement hardened material filling process, the cement hardened material is filled in the space surrounded by the concrete structure, the bottom wall of the metal tube and the molding material, and in the top closing process, the cement hardened filling the space. Without waiting for the curing period of the object, the metal lid is fixed to the top of the metal tube immediately after the space is filled with the hardened cement material.

本発明の他の一例として、据え付け基礎施工方法では、金属管の頂部に金属蓋を固定した直後において空間に充填されたセメント硬化物が未硬化状態にあり、金属管の頂部に金属蓋を固定した後からセメント硬化物の養生期間が開始し、養生期間が経過した後に、アンカーボルトの自由端部のうちのコンクリート構造物の表面と金属管の底壁との間に延びる部分が空間に充填されたセメント硬化物と一体になる。   As another example of the present invention, in the installation foundation construction method, immediately after the metal lid is fixed to the top of the metal tube, the hardened cement filled in the space is in an uncured state, and the metal lid is fixed to the top of the metal tube. After the curing period of the cement hardened material has started, the portion extending between the surface of the concrete structure and the bottom wall of the metal tube at the free end of the anchor bolt fills the space after the curing period has elapsed. It is united with the hardened cement material.

本発明の他の一例としては、据え付け基礎施工方法が、金属管を据え付け箇所に仮設置する仮設置工程と、金属管を仮設置した後に、アンカーボルトの自由端部に対する金属管の底壁の固定位置を調節してコンクリート構造物からの金属管の設置高さを調節する設置高さ調節工程とを含み、金属管固定工程では、金属管の設置高さを調節した後にアンカーボルトの自由端部に金属管の底壁を固定する。   As another example of the present invention, the installation foundation construction method includes a temporary installation step in which the metal pipe is temporarily installed at the installation location, and after the temporary installation of the metal pipe, the bottom wall of the metal pipe with respect to the free end of the anchor bolt. Adjusting the fixing position to adjust the installation height of the metal pipe from the concrete structure. In the metal pipe fixing process, after adjusting the installation height of the metal pipe, the free end of the anchor bolt Fix the bottom wall of the metal tube to the part.

本発明の他の一例としては、据え付け基礎施工方法が金属管の底壁に開口する螺着孔に螺着されて金属管の高さ寸法を調節する高さ調節ボルトを含み、設置高さ調節工程では、高さ調節ボルトの金属管の底壁に対する螺着位置を調節することによって空間の高さ寸法を調節可能かつコンクリート構造物の表面からの金属管の高さ寸法を調節可能である。   As another example of the present invention, the installation foundation construction method includes a height adjustment bolt that is screwed into a screw hole that is opened in the bottom wall of the metal pipe and adjusts the height dimension of the metal pipe, and adjusts the installation height. In the process, the height dimension of the space can be adjusted by adjusting the screwing position of the height adjusting bolt to the bottom wall of the metal pipe, and the height dimension of the metal pipe from the surface of the concrete structure can be adjusted.

本発明の他の一例としては、コンクリート構造物が、コンクリート躯体と、コンクリート躯体の上に施設された防水層と、防水層の上に施設されたコンクリート層とから形成され、アンカーボルト設置工程では、コンクリート構造物からコンクリート層と防水層とを取り除いてコンクリート躯体を露出させ、コンクリート躯体の据え付け箇所にアンカーボルトの固定端部を固定し、金属管固定工程では、金属管をコンクリート躯体から上方へ離間させた状態でそれらアンカーボルトの自由端部に固定する。   As another example of the present invention, a concrete structure is formed of a concrete frame, a waterproof layer provided on the concrete frame, and a concrete layer provided on the waterproof layer. The concrete layer and the waterproof layer are removed from the concrete structure to expose the concrete frame, and the fixed end of the anchor bolt is fixed to the installation position of the concrete frame. In the metal tube fixing process, the metal tube is moved upward from the concrete frame. The anchor bolts are fixed to the free ends of the anchor bolts in a separated state.

本発明の他の一例としては、据え付け基礎施工方法が金属管の周壁の外側に防水部材を設置する防水部材設置工程を含み、防水部材が、金属管の周壁の外側に固定された発泡材と、発泡材の外側に固定された防水層とから形成されている。   As another example of the present invention, the installation foundation construction method includes a waterproof member installation step of installing a waterproof member on the outside of the peripheral wall of the metal tube, and the waterproof member is fixed to the outside of the peripheral wall of the metal tube; And a waterproof layer fixed to the outside of the foam material.

本発明の他の一例として、防水部材設置工程では、金属管の底壁の側に延びる防水部材の防水層をコンクリート構造物の防水層につなげる。   As another example of the present invention, in the waterproof member installation step, the waterproof layer of the waterproof member extending to the bottom wall side of the metal tube is connected to the waterproof layer of the concrete structure.

本発明の他の一例としては、据え付け基礎施工方法が防水部材を衝撃から保護する乾式保護部材を防水部材の外側に設置する保護部材設置工程を含む。   As another example of the present invention, the installation foundation construction method includes a protection member installation step in which a dry protection member that protects the waterproof member from impact is installed outside the waterproof member.

本発明の他の一例として、金属管の底壁の中央部には、コンクリート構造物と金属管の底壁との間の空間にセメント硬化物を充填するための充填孔が形成され、セメント硬化物充填工程では、充填孔から空間にセメント硬化物を充填する。   As another example of the present invention, a filling hole for filling cement hardened material into a space between the concrete structure and the bottom wall of the metal pipe is formed in the center portion of the bottom wall of the metal pipe. In the object filling step, the cement hardened material is filled into the space from the filling hole.

本発明の他の一例として、金属管の底壁の所定の箇所には、コンクリート構造物と金属管の底壁との間の空間に充填されたセメント硬化物を確認するための確認孔が形成され、セメント硬化物充填工程では、確認孔から空間におけるセメント硬化物の充填状態を確認する。   As another example of the present invention, a confirmation hole for confirming cement hardened material filled in a space between the concrete structure and the bottom wall of the metal pipe is formed in a predetermined portion of the bottom wall of the metal pipe. In the cement hardened material filling step, the filling state of the cement hardened material in the space is confirmed from the confirmation hole.

本発明にかかる据え付け基礎施工方法によれば、据え付け箇所に複数のアンカーボルトを設置するアンカーボルト設置工程と、金属管をコンクリート構造物から上方へ離間させた状態でアンカーボルトの自由端部に固定する金属管固定工程と、空間にセメント硬化物を充填するセメント硬化物充填工程と、金属管の頂部に金属蓋を固定する頂部閉塞工程とから基礎が作られ、汎用部品化された各基礎部品を各工程によってユニットシステムとして組み立てるから、施工作業をマニュアル化することができるとともに、施工作業を簡略化することができる。据え付け基礎施工方法は、基礎を形成する際に施工現場において型枠を製作する必要がないことはもちろん、基礎製造工場や施工現場において基礎を作るためにセメント硬化物を養生する必要はなく、コンクリート構造物に固定された複数のアンカーボルトに中空の軽量な金属管を固定し、その金属管に金属蓋を固定するだけであり、型枠の製作やセメント硬化物の養生にかかる手間や時間を省くことができ、その分の工期を短縮することができる。据え付け基礎施工方法は、複数のアンカーボルトの固定端部をコンクリート構造物に固定し、それらアンカーボルトの自由端部に金属管を固定するから、据え付け基礎をコンクリート構造物に強固に据え付けることができ、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることができる。据え付け基礎施工方法は、コンクリート構造物の表面と金属管の底壁との間の空間にセメント硬化物を充填し、基礎の上に機械機器や建築物を強固に備え付けた場合の基礎にかかる荷重をアンカーボルトとセメント硬化物とで分担させるから、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持する基礎を作ることができる。   According to the installation foundation construction method according to the present invention, an anchor bolt installation process in which a plurality of anchor bolts are installed at the installation location, and the metal pipe is fixed to the free end of the anchor bolt in a state of being spaced upward from the concrete structure. Each base part is made into a general-purpose part from the metal pipe fixing process, the cement hardened material filling process for filling the space with cement hardened material, and the top closing process for fixing the metal lid to the top of the metal pipe As a unit system is assembled by each process, the construction work can be manualized and the construction work can be simplified. In the installation foundation construction method, it is not necessary to produce a formwork at the construction site when forming the foundation, and it is not necessary to cure the hardened cement to create the foundation at the foundation manufacturing factory or construction site. Simply fix a hollow lightweight metal tube to multiple anchor bolts fixed to the structure, and then fix the metal lid to the metal tube, which saves time and effort for making the formwork and curing the hardened cement. It can be omitted and the construction period can be shortened. In the installation foundation construction method, the fixed ends of multiple anchor bolts are fixed to a concrete structure, and metal pipes are fixed to the free ends of the anchor bolts, so that the installation foundation can be firmly installed on the concrete structure. It can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air conditioners, and buildings such as steel towers and steel structures. In the installation foundation construction method, the load applied to the foundation when a hardened cement material is filled in the space between the surface of the concrete structure and the bottom wall of the metal pipe, and mechanical equipment and buildings are firmly installed on the foundation. Since the anchor bolt and the hardened cement material are shared, the load applied to the foundation will not incline inadvertently or the foundation will not collapse, making it possible to create a foundation that reliably supports machinery and buildings. it can.

コンクリート構造物と金属管の底壁の周縁との間に延びる空隙を塞ぐ成型材を金属管の底壁の周縁の外側近傍に設置する成型材設置工程を含み、コンクリート構造物と金属管の底壁と成型材とに囲繞された空間にセメント硬化物を充填し、空間に充填されたセメント硬化物の養生期間を待つことなく、空間にセメント硬化物を充填した直後に金属蓋を金属管の頂部に固定する据え付け基礎施工方法は、底壁の周縁の外側近傍に設置された成型材が硬化前のセメント硬化物の漏れを防ぐ堤防となり、空間に充填されたセメント硬化物がその空間から漏れ出すことがないから、底壁の周縁の外側近傍にセメント硬化物のための型枠を設置する必要がなく、型枠を設置するための手間や時間を省くことができ、据え付け基礎の工期を大幅に短縮することができる。据え付け基礎施工方法は、空間に充填されたセメント硬化物の養生期間を待つことなく、空間にセメント硬化物を充填した直後に金属蓋を金属管の頂部に固定することができ、セメント硬化物の養生期間を待つことなく次の基礎の施工を行うことができるから、セメント硬化物の養生期間の分の工期を短縮することができ、据え付け基礎の工期を大幅に短縮することができる。   Including a molding material installation step of installing a molding material for closing a gap extending between the concrete structure and the peripheral edge of the bottom wall of the metal pipe in the vicinity of the outside of the peripheral edge of the bottom wall of the metal pipe; Fill the space surrounded by the wall and molding material with cement hardened material, and wait for the curing period of the cement hardened material filled in the space, and immediately after filling the space with cement hardened material, put the metal lid on the metal tube The fixed foundation construction method to be fixed to the top is that the molding material installed near the outside of the periphery of the bottom wall serves as an embankment to prevent leakage of the hardened cement before hardening, and the hardened cement filled in the space leaks from that space. It is not necessary to install a mold for cemented material near the outside of the peripheral edge of the bottom wall, so it is possible to save labor and time for installing the mold and save the construction period of the installation foundation. Drastically shorten Door can be. The installation foundation construction method can fix the metal lid to the top of the metal tube immediately after filling the space with the cement hardened material without waiting for the curing period of the hardened cement material filled in the space. Since the next foundation can be constructed without waiting for the curing period, the construction period for the curing period of the hardened cement can be shortened, and the construction period of the installation foundation can be greatly shortened.

金属管の頂部に金属蓋を固定した直後において空間に充填されたセメント硬化物が未硬化状態にあり、金属管の頂部に金属蓋を固定した後からセメント硬化物の養生期間が開始し、養生期間が経過した後にアンカーボルトの自由端部のうちのコンクリート構造物の表面と金属管の底壁との間に延びる部分が空間に充填されたセメント硬化物と一体になる据え付け基礎施工方法は、空間に充填されたセメント硬化物が硬化する以前に金属蓋を金属管の頂部に固定することができ、セメント硬化物の養生期間を待つことなく次の基礎の施工を行うことができるから、セメント硬化物の養生期間の分の工期を短縮することができ、据え付け基礎の工期を大幅に短縮することができる。据え付け基礎施工方法は、養生期間が経過した後にアンカーボルトの部分がセメント硬化物と一体になり、基礎の上に機械機器や建築物を強固に備え付けた場合の基礎にかかる荷重をアンカーボルトとセメント硬化物とで分担するから、コンクリート構造物の据え付け箇所に強固に据え付けられた基礎を作ることができる。   Immediately after fixing the metal lid to the top of the metal tube, the cement hardened material filled in the space is in an uncured state, and after the metal lid is fixed to the top of the metal tube, the curing period of the cement hardened material starts, The fixed foundation construction method in which the portion extending between the surface of the concrete structure and the bottom wall of the metal pipe in the free end of the anchor bolt is integrated with the hardened cement filled in the space after the period has elapsed. Before the hardened cement filled in the space hardens, the metal lid can be fixed to the top of the metal tube, so that the next foundation can be constructed without waiting for the curing time of the hardened cement. The work period corresponding to the curing period of the cured product can be shortened, and the work period of the installation foundation can be greatly shortened. In the installation foundation construction method, after the curing period has elapsed, the anchor bolt part is integrated with the hardened cement material, and the load applied to the foundation when a mechanical device or building is firmly mounted on the foundation is fixed to the anchor bolt and cement. Since it is shared with the hardened material, it is possible to create a foundation that is firmly installed at the installation location of the concrete structure.

金属管を据え付け箇所に仮設置する仮設置工程と、金属管を仮設置した後にアンカーボルトの自由端部に対する金属管の底壁の固定位置を調節してコンクリート構造物からの金属管の設置高さを調節する設置高さ調節工程とを含む据え付け基礎施工方法は、基礎の施工中にその高さ寸法を自由に変えることができ、基礎の高さ寸法の変更要求に即座に対応することができる。据え付け基礎施工方法は、複数個のそれらを設置する場合にそれら基礎どうしの高さ寸法を容易に調節することができ、それら基礎の高さ寸法を均一に揃えることができる。   Temporary installation process where the metal pipe is temporarily installed at the installation location, and after the metal pipe is temporarily installed, the installation position of the metal pipe from the concrete structure is adjusted by adjusting the fixing position of the bottom wall of the metal pipe relative to the free end of the anchor bolt The installation foundation adjustment method including the installation height adjustment process to adjust the height can change the height dimension freely during the construction of the foundation and can respond immediately to the change request of the foundation height dimension. it can. In the installation foundation construction method, when installing a plurality of them, the height dimensions of the foundations can be easily adjusted, and the height dimensions of the foundations can be made uniform.

設置高さ調節工程において、高さ調節ボルトの金属管の底壁に対する螺着位置を調節することによって空間の高さ寸法を調節可能かつコンクリート構造物の表面からの金属管の高さ寸法を調節可能な据え付け基礎施工方法は、高さ調節ボルトを利用することで基礎の施工中にその高さ寸法を自由に変えることができ、基礎の高さ寸法の変更要求に即座に対応することができる。据え付け基礎施工方法は、複数個のそれらを設置する場合にそれら基礎どうしの高さ寸法を容易に調節することができ、それら基礎の高さ寸法を均一に揃えることができる。   In the installation height adjustment process, the height of the space can be adjusted by adjusting the screwing position of the height adjustment bolt to the bottom wall of the metal tube, and the height of the metal tube from the surface of the concrete structure can be adjusted. Possible installation foundation construction methods can use height adjustment bolts to freely change the height dimension during foundation construction, and can respond immediately to changes in the foundation height dimension. . In the installation foundation construction method, when installing a plurality of them, the height dimensions of the foundations can be easily adjusted, and the height dimensions of the foundations can be made uniform.

アンカーボルト設置工程において、コンクリート構造物からコンクリート層と防水層とを取り除いてコンクリート躯体を露出させ、コンクリート躯体の据え付け箇所にアンカーボルトの固定端部を固定し、金属管固定工程において、金属管をコンクリート躯体から上方へ離間させた状態でそれらアンカーボルトの自由端部に固定する据え付け基礎施工方法は、機械機器や建築物を設置する設置箇所が既設のコンクリート構造物の屋上や地下に防水機能を施した防水処理層を備えたスラブである場合でも、設置箇所の防水処理層を取り除いた後の露出したコンクリート躯体に基礎を設置し、基礎を設置した直後に設置箇所近傍の防水処理層を補修する(新たな防水処理層を施す)ことができるから、基礎を迅速に設置することができ、基礎の設置に要する工期を短縮することができる。   In the anchor bolt installation process, the concrete layer and the waterproof layer are removed from the concrete structure to expose the concrete frame, and the anchor bolt fixing end is fixed to the installation position of the concrete frame. The installation foundation construction method, in which the anchor bolts are fixed to the free ends of the anchor bolts while being spaced apart upward from the concrete frame, has a waterproof function on the rooftop and underground of existing concrete structures where the installation location for mechanical equipment and buildings is installed. Even if it is a slab with a waterproof layer applied, install the foundation on the exposed concrete frame after removing the waterproof layer at the installation location, and repair the waterproof treatment layer near the installation location immediately after installing the foundation (With a new waterproofing layer), the foundation can be installed quickly, It is possible to shorten the construction period required for.

金属管の周壁の外側に防水部材を設置する防水部材設置工程を含み、防水部材が金属管の周壁の外側に固定された発泡材と発泡材の外側に固定された防水層とから形成される据え付け基礎施工方法は、基礎をコンクリート構造物の屋上に設置した場合に防水部材によって基礎の内部への水の侵入を防ぐことができ、内部に水が進入することによる基礎の劣化を防ぐことができる。   Including a waterproof member installation step of installing a waterproof member on the outside of the peripheral wall of the metal tube, wherein the waterproof member is formed of a foam material fixed to the outside of the peripheral wall of the metal tube and a waterproof layer fixed to the outside of the foam material The installation foundation construction method can prevent water from entering the inside of the foundation with a waterproofing member when the foundation is installed on the roof of a concrete structure, and prevent deterioration of the foundation due to water entering the inside. it can.

防水部材設置工程において、金属管の底壁の側に延びる防水部材の防水層をコンクリート構造物の防水層につなげる据え付け基礎施工方法は、基礎をコンクリート構造物の屋上に設置した場合に防水層によって基礎の内部への水の侵入を防ぐことができることはもちろん、コンクリート構造物への水の進入を防ぐことができ、水の進入による基礎の劣化やコンクリート構造物の劣化を防ぐことができる。   In the waterproof member installation process, the installation foundation construction method that connects the waterproof layer of the waterproof member extending to the bottom wall side of the metal pipe to the waterproof layer of the concrete structure is the same as when the foundation is installed on the roof of the concrete structure. In addition to preventing water from entering the inside of the foundation, water can be prevented from entering the concrete structure, and deterioration of the foundation and concrete structure due to water entry can be prevented.

防水部材を衝撃から保護する乾式保護部材を防水部材の外側に設置する保護部材設置工程を含む据え付け基礎施工方法は、基礎の外側から衝撃が加えられたとしても、保護部材によってその衝撃が吸収されるから、衝撃によって防水部材が破損することはなく、防水部材によって基礎やコンクリート構造物の内部への水の侵入を防ぐことができ、内部に水が進入することによる基礎の劣化やコンクリート構造物の劣化を防ぐことができる。   The installation foundation construction method that includes a protective member installation process that installs a dry protection member that protects the waterproof member from impacts outside the waterproof member, even if an impact is applied from the outside of the foundation, the impact is absorbed by the protective member. Therefore, the waterproof member is not damaged by the impact, and the waterproof member can prevent water from entering the foundation or the concrete structure, and the deterioration of the foundation or the concrete structure caused by the water entering the inside. Can be prevented.

セメント硬化物充填工程において、金属管の底壁の中央部に形成された充填孔から空間にセメント硬化物を充填する据え付け基礎施工方法は、金属管をアンカーボルトに固定した後に充填孔を利用して空間にセメント硬化物を充填することができるから、空間にセメント硬化物を確実に充填することができる。据え付け基礎施工方法は、充填孔が金属管の底壁の中央部に形成されているから、セメント硬化物が空間に偏って充填されることはなく、セメント硬化物を空間全域に満遍なく充填することができる。据え付け基礎施工方法は、基礎の上に機械機器や建築物を備え付けた場合の基礎にかかる荷重をアンカーボルトとセメント硬化物とに分担させることができ、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持する基礎を作ることができる。   In the cement hardened product filling process, the installation foundation construction method that fills the cement hardened material into the space from the filling hole formed in the center part of the bottom wall of the metal pipe uses the filling hole after fixing the metal pipe to the anchor bolt. Thus, the cement hardened product can be filled into the space, and the cement hardened product can be reliably filled into the space. In the installation foundation construction method, the filling hole is formed in the center of the bottom wall of the metal tube, so the hardened cement is not filled in the space, and the hardened cement is filled evenly throughout the space. Can do. In the installation foundation construction method, the load applied to the foundation when mechanical equipment or a building is installed on the foundation can be shared between the anchor bolt and the hardened cement, and the load applied to the foundation inclines it carelessly. And the foundation will not collapse, and you can make a foundation that supports machinery and buildings reliably.

セメント硬化物充填工程において、金属管の底壁の所定の箇所に形成された確認孔から空間におけるセメント硬化物の充填状態を確認する据え付け基礎施工方法は、確認孔を利用して空間に充填されたセメント硬化物の充填状態を確認することができ、セメント硬化物が空間に偏って充填されることはなく、セメント硬化物を空間全域に満遍なく充填することができる。据え付け基礎施工方法は、基礎の上に機械機器や建築物を備え付けた場合の基礎にかかる荷重をアンカーボルトとセメント硬化物とに分担させることができ、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持する基礎を作ることができる。   In the cement hardened material filling process, the installation foundation construction method for confirming the filling state of cement hardened material in the space from the confirmation hole formed at a predetermined location on the bottom wall of the metal tube is filled into the space using the confirmation hole. The state of filling of the hardened cement can be confirmed, the hardened cement is not filled in the space, and the hardened cement can be uniformly filled in the entire space. In the installation foundation construction method, the load applied to the foundation when mechanical equipment or a building is installed on the foundation can be shared between the anchor bolt and the hardened cement, and the load applied to the foundation inclines it carelessly. And the foundation will not collapse, and you can make a foundation that supports machinery and buildings reliably.

一例として示す据え付け基礎の斜視図。The perspective view of the installation foundation shown as an example. 据え付け基礎の作成手順の一例を示す図。The figure which shows an example of the preparation procedure of an installation foundation. 図2から続く据え付け基礎の作成手順を示す図。The figure which shows the preparation procedure of the installation foundation which continues from FIG. 鋼管の側面図。The side view of a steel pipe. 鋼管の上面図。The top view of a steel pipe. 図3から続く据え付け基礎の作成手順を示す図。The figure which shows the preparation procedure of the installation foundation which continues from FIG. 図6から続く据え付け基礎の作成手順を示す図。The figure which shows the preparation procedure of the installation foundation which continues from FIG. 図7から続く据え付け基礎の作成手順を示す図。The figure which shows the preparation procedure of the installation foundation which continues from FIG. 図8から続く据え付け基礎の作成手順を示す図。The figure which shows the preparation procedure of the installation foundation which continues from FIG. 図9から続く据え付け基礎の作成手順を示す図。The figure which shows the preparation procedure of the installation foundation which continues from FIG. 蓋を取り外した状態の据え付け基礎の上面図。The top view of the installation foundation of the state which removed the cover. 蓋を取り付けた状態の据え付け基礎の上面図。The top view of the installation foundation of the state which attached the lid | cover.

一例として示す据え付け基礎10の斜視図である図1等の添付の図面を参照し、本発明にかかる据え付け基礎施工方法の詳細を説明すると、以下のとおりである。図1では、コンクリート構造物11に設置された1個の据え付け基礎10を図示しているが、基礎10の個数を図示のそれに限定するものではなく、2個以上の基礎10がコンクリート構造物11に設置される場合もある。なお、図2は、据え付け基礎10の作成手順の一例を示す図であり、図3は、図2から続く据え付け基礎10の作成手順を示す図である。図2,3では、コンクリート構造物11を断面として示す。図1や後記する図10では、上下方向を矢印L、横方向を矢印Mで示し、前後方向を矢印N(図1のみ)で示す。   The details of the installation foundation construction method according to the present invention will be described with reference to the accompanying drawings such as FIG. 1 which is a perspective view of the installation foundation 10 shown as an example. In FIG. 1, one installation foundation 10 installed in the concrete structure 11 is illustrated, but the number of foundations 10 is not limited to that illustrated, and two or more foundations 10 include the concrete structure 11. It may be installed in. FIG. 2 is a diagram showing an example of a procedure for creating the installation foundation 10, and FIG. 3 is a diagram showing a procedure for creating the installation foundation 10 continuing from FIG. 2 and 3, the concrete structure 11 is shown as a cross section. In FIG. 1 and FIG. 10 described later, the vertical direction is indicated by an arrow L, the horizontal direction is indicated by an arrow M, and the front-rear direction is indicated by an arrow N (only in FIG. 1).

据え付け基礎10は、新設または既設のコンクリート構造物11の屋上や地下のスラブの所定の据え付け箇所に設置される。ここで、「スラブ」とは、厳密には「床版」を意味するが、この実施の形態では、コンクリート構造物11の地下の床のみならず屋上も含む意味で用いる。据え付け基礎施工方法は、中空の鋼管19(金属管)および蓋36(金属蓋)、複数の高さ調節ボルト24および複数のアンカーボルト15、モルタル35(セメント硬化物)、防水部材31、成型材34(面取材あるいはキャント)、ケイ酸カルシウム板41(乾式の保護部材)の汎用部品化された各基礎部品を利用し、それら基礎部品を所定のマニュアル化された手順で組み立てることで基礎10を作る。それら基礎部品(鋼管19、蓋36、アンカーボルト15、高さ調節ボルト24、防水部材31、成型材34、ケイ酸カルシウム板41)は、基礎部品製造工場で製造され、工場から設置現場に搬送される。   The installation foundation 10 is installed at a predetermined installation location on a roof of a new or existing concrete structure 11 or an underground slab. Here, “slab” strictly means “floor slab”, but in this embodiment, it is used to include not only the underground floor of the concrete structure 11 but also the rooftop. The installation foundation construction method includes a hollow steel pipe 19 (metal pipe) and a lid 36 (metal lid), a plurality of height adjusting bolts 24 and a plurality of anchor bolts 15, a mortar 35 (hardened cement), a waterproof member 31, and a molding material. 34 (chamfering material or cant), using each basic part made into a general-purpose part of calcium silicate board 41 (dry-type protective member), and assembling those basic parts in a predetermined manual procedure, create. These basic parts (steel pipe 19, lid 36, anchor bolt 15, height adjusting bolt 24, waterproof member 31, molded material 34, calcium silicate plate 41) are manufactured at the basic part manufacturing factory and transported from the factory to the installation site. Is done.

据え付け基礎10をコンクリート構造物11の屋上に設置する場合を例として、基礎施工方法を説明すると、以下のとおりである。コンクリート構造物11の屋上のスラブは、図2に示すように、コンクリート躯体12と、コンクリート躯体12の上に施設された防水層13と、防水層13の上に施設されたコンクリート層14とから形成されている。最初に、コンクリート構造物11の屋上における基礎10の据え付け箇所を位置決めし、その据え付け箇所にマーキングをするとともに、その据え付け箇所において、コンクリート構造物11からコンクリート層14と防水層13とを取り除いてコンクリート躯体12を露出させる。   Taking the case where the installation foundation 10 is installed on the roof of the concrete structure 11 as an example, the foundation construction method will be described as follows. As shown in FIG. 2, the roof slab of the concrete structure 11 includes a concrete frame 12, a waterproof layer 13 provided on the concrete frame 12, and a concrete layer 14 provided on the waterproof layer 13. Is formed. First, the installation location of the foundation 10 on the roof of the concrete structure 11 is positioned, and the installation location is marked, and the concrete layer 14 and the waterproof layer 13 are removed from the concrete structure 11 at the installation location. The housing 12 is exposed.

なお、図示のコンクリート構造物11は、コンクリート躯体12と防水層13とコンクリート層14とから形成されているが、コンクリート構造物11を図示のそれに限定するものではなく、現在使用されている他の構成のコンクリート構造物すべてにこの施工方法を実施することができる。たとえば、コンクリート層14の上にさらに合成樹脂を塗布して樹脂被膜を形成したコンクリート構造物の場合、基礎10の据え付け箇所では、コンクリート構造物から樹脂被膜とコンクリート層14と防水層13とを取り除いてコンクリート躯体12を露出させる。また、コンクリート構造物11が地下に構築された場合、防水層13とコンクリート層14とが存在せず、コンクリート躯体12単独でコンクリート構造物11を形成する。   In addition, although the concrete structure 11 of illustration is formed from the concrete frame 12, the waterproof layer 13, and the concrete layer 14, the concrete structure 11 is not limited to that of illustration and other currently used This construction method can be carried out on all concrete structures. For example, in the case of a concrete structure in which a synthetic resin is further applied on the concrete layer 14 to form a resin film, the resin film, the concrete layer 14 and the waterproof layer 13 are removed from the concrete structure at the installation location of the foundation 10. The concrete housing 12 is exposed. When the concrete structure 11 is constructed underground, the waterproof layer 13 and the concrete layer 14 do not exist, and the concrete structure 11 is formed by the concrete frame 12 alone.

コンクリート躯体12を露出させた後、躯体12における基礎10の据え付け箇所にアンカーボルト15を挿入する複数のアンカーホール16を穿孔し、それらアンカーホール16に樹脂接着剤(図示せず)を注入する。アンカーホール16は、掘削機を利用し、コンクリート躯体12を所定の深さ掘削することから作られる。次に、図3に示すように、それらアンカーホール16にアンカーボルト15を挿入する(アンカーボルト設置工程)。   After the concrete housing 12 is exposed, a plurality of anchor holes 16 for inserting the anchor bolts 15 are drilled in the installation locations of the foundation 10 in the housing 12, and a resin adhesive (not shown) is injected into the anchor holes 16. The anchor hole 16 is formed by excavating the concrete frame 12 to a predetermined depth using an excavator. Next, as shown in FIG. 3, anchor bolts 15 are inserted into the anchor holes 16 (anchor bolt installation step).

アンカーボルト設置工程では、アンカーボルト15の固定端部17をコンクリート躯体12に形成されたアンカーホール16に挿入し、アンカーボルト15の自由端部18をコンクリート躯体12(コンクリート構造物11)の表面から上方へ起立させる。アンカーボルト15の固定端部17は、その周面が樹脂接着剤を介してアンカーホール16に固定され、アンカーボルト15の自由端部18は、コンクリート躯体12(コンクリート構造物11)の表面から上方へ立ち上がる。なお、それらアンカーボルト15は、長さや直径が同一の規格化された汎用品であり、複数本のそれらが施工現場以外の基礎部品製造工場で製造される。アンカーボルト15は、鋼材から作られている。アンカーボルト15のそれら端部17,18には、雄螺子(図示せず)が作られている。   In the anchor bolt installation step, the fixed end 17 of the anchor bolt 15 is inserted into the anchor hole 16 formed in the concrete housing 12, and the free end 18 of the anchor bolt 15 is inserted from the surface of the concrete housing 12 (concrete structure 11). Stand up. The fixed end portion 17 of the anchor bolt 15 has its peripheral surface fixed to the anchor hole 16 via a resin adhesive, and the free end portion 18 of the anchor bolt 15 extends upward from the surface of the concrete frame 12 (concrete structure 11). Get up to. The anchor bolts 15 are standardized general-purpose products having the same length and diameter, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site. The anchor bolt 15 is made of steel. Male screws (not shown) are formed at the end portions 17 and 18 of the anchor bolt 15.

図4は、鋼管19の側面図であり、図5は、鋼管19の上面図である。図6は、図3から続く据え付け基礎の作成手順を示す図である。図6では、コンクリート構造物11を断面として示し、一部を除く基礎10の部品を断面として示す。鋼管19は、形状や寸法が同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造される。鋼管19は、平面形状が略矩形の底壁20と、底壁20の周縁42から上方へ延びる平面形状が略矩形の各側壁21(周壁)とを備え、底を有する角筒状に成型されている。鋼管19は、鋼材から作られた各側壁21の底部に鋼材から作られた底壁20の周縁42を溶接することによって製造される。鋼管19の頂部には、それら側壁21によって囲繞された頂部開口22が形成されている。なお、金属管は、鋼材の他に、アルミニウムや合金から作ることもできる。   FIG. 4 is a side view of the steel pipe 19 and FIG. 5 is a top view of the steel pipe 19. FIG. 6 is a diagram showing a procedure for creating an installation base continued from FIG. 3. In FIG. 6, the concrete structure 11 is shown as a cross section, and parts of the foundation 10 excluding a part are shown as a cross section. The steel pipe 19 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site. The steel pipe 19 includes a bottom wall 20 having a substantially rectangular planar shape and each side wall 21 (peripheral wall) having a substantially rectangular planar shape extending upward from the peripheral edge 42 of the bottom wall 20 and is molded into a rectangular tube shape having a bottom. ing. The steel pipe 19 is manufactured by welding the peripheral edge 42 of the bottom wall 20 made of steel to the bottom of each side wall 21 made of steel. A top opening 22 surrounded by the side walls 21 is formed at the top of the steel pipe 19. In addition, a metal pipe can also be made from aluminum and an alloy other than steel materials.

鋼管19の側壁21の頂部には、複数の固定ボルト螺着孔23が作られている。固定ボルト螺着孔23には、雌螺子(図示せず)が作られている。鋼管19の底壁20には、高さ調節ボルト24(図4参照)を螺着する複数の調節ボルト螺着孔25とアンカーボルト15を挿通する複数のアンカーボルト挿通孔26とが作られている(図5参照)。アンカーボルト挿通孔26は、現場において作られる。ボルト螺着孔23には、雌螺子(図示せず)が作られている。   A plurality of fixing bolt screw holes 23 are formed at the top of the side wall 21 of the steel pipe 19. A female screw (not shown) is formed in the fixing bolt screw hole 23. The bottom wall 20 of the steel pipe 19 is formed with a plurality of adjustment bolt screwing holes 25 for screwing height adjustment bolts 24 (see FIG. 4) and a plurality of anchor bolt insertion holes 26 for inserting the anchor bolts 15. (See FIG. 5). The anchor bolt insertion hole 26 is made in the field. A female screw (not shown) is formed in the bolt screw hole 23.

高さ調節ボルト24は、雄螺子(図示せず)が作られた軸とボルトヘッドとから形成された六角ボルトである。高さ調節ボルト24の軸は、底壁20に作られた調節ボルト螺着孔25に螺着されている。なお、底壁20におけるボルト螺着孔26やアンカーボルト挿通孔26の穿孔箇所に特に限定はなく、それら孔25,26を底壁20の任意の箇所に作ることができる。底壁20の中央部には、円形の充填孔27が作られている。底壁20の四隅には、充填状態を確認するための確認孔28が作られている。   The height adjusting bolt 24 is a hexagonal bolt formed from a shaft on which a male screw (not shown) is made and a bolt head. The shaft of the height adjusting bolt 24 is screwed into an adjusting bolt screwing hole 25 formed in the bottom wall 20. In addition, there is no limitation in particular in the drilling location of the bolt screw hole 26 in the bottom wall 20, and the anchor bolt insertion hole 26, These holes 25 and 26 can be made in the arbitrary locations of the bottom wall 20. FIG. A circular filling hole 27 is formed in the center of the bottom wall 20. In the four corners of the bottom wall 20, confirmation holes 28 for confirming the filling state are formed.

アンカーボルト15をアンカーホール16に設置した後、鋼管19を据え付け箇所に仮設置する(仮設置工程)。仮設置工程では、ドリルを利用し、アンカーホール16の位置(アンカーボルト15の位置)にあわせて鋼管19の底壁20にアンカーボルト挿通孔26を穿孔する。鋼管19を据え付け箇所に移動させ、図6に示すように、鋼管19の底壁20に形成されたアンカーボルト挿通孔26にアンカーボルト15を通し、高さ調節ボルト24のボルトヘッドをコンクリート躯体12の表面に当接させ、鋼管19を据え付け箇所に仮設置する。   After the anchor bolt 15 is installed in the anchor hole 16, the steel pipe 19 is temporarily installed at the installation location (temporary installation process). In the temporary installation step, a drill is used to drill the anchor bolt insertion hole 26 in the bottom wall 20 of the steel pipe 19 in accordance with the position of the anchor hole 16 (position of the anchor bolt 15). The steel pipe 19 is moved to the installation location, and as shown in FIG. 6, the anchor bolt 15 is passed through the anchor bolt insertion hole 26 formed in the bottom wall 20 of the steel pipe 19, and the bolt head of the height adjusting bolt 24 is connected to the concrete housing 12. The steel pipe 19 is temporarily installed at the installation location.

鋼管19を仮設置した後、アンカーボルト15の自由端部18に対する鋼管19の底壁20の固定位置を調節してコンクリート躯体12の表面からの鋼管19の設置高さを調節する(設置高さ調節工程)。設置高さ調節工程では、高さ調節ボルト24を時計回りと反時計回りとのいずれかに回転させ、鋼管19の底壁20に対するそれら高さ調節ボルト24の螺着位置を調節することによって、コンクリート躯体12の表面と鋼管19の底壁20との間の空間29の高さ寸法を調節し、コンクリート躯体12の表面からの鋼管19の底壁20の高さ寸法を調節する。   After temporarily installing the steel pipe 19, the fixing position of the bottom wall 20 of the steel pipe 19 with respect to the free end 18 of the anchor bolt 15 is adjusted to adjust the installation height of the steel pipe 19 from the surface of the concrete frame 12 (installation height). Adjustment process). In the installation height adjusting step, the height adjusting bolt 24 is rotated clockwise or counterclockwise, and the screwing position of the height adjusting bolt 24 with respect to the bottom wall 20 of the steel pipe 19 is adjusted. The height dimension of the space 29 between the surface of the concrete casing 12 and the bottom wall 20 of the steel pipe 19 is adjusted, and the height dimension of the bottom wall 20 of the steel pipe 19 from the surface of the concrete casing 12 is adjusted.

具体的には、ボルトヘッドにおいて高さ調節ボルト24を反時計回りに回転させると、ボルト24のボルトヘッドがコンクリート躯体12の表面に当接しつつ、ボルト24の軸がボルト螺着孔25の下方へ次第に進むとともに、底壁20の下面から下方に延出する。それによって、鋼管19をコンクリート躯体12の表面から上方に離間させることができる。逆に、高さ調節ボルト24を時計回りに回転させると、ボルト24の軸がボルト螺着孔25の上方へ次第に進むとともに、底壁12の下面から上方へ延出する。それによって、鋼管19をコンクリート躯体12の表面に近づけることができる。   Specifically, when the height adjustment bolt 24 is rotated counterclockwise in the bolt head, the bolt head of the bolt 24 abuts against the surface of the concrete housing 12 and the shaft of the bolt 24 is below the bolt screw hole 25. As it progresses gradually, it extends downward from the lower surface of the bottom wall 20. Thereby, the steel pipe 19 can be separated upward from the surface of the concrete housing 12. Conversely, when the height adjusting bolt 24 is rotated clockwise, the shaft of the bolt 24 gradually moves upward from the bolt screw hole 25 and extends upward from the lower surface of the bottom wall 12. Thereby, the steel pipe 19 can be brought close to the surface of the concrete housing 12.

高さ調節ボルト24を調節ボルト螺着孔25において回転させることによって鋼管19の底壁20がコンクリート躯体12の表面から上方へ離間し、コンクリート躯体12の表面と鋼管19の底壁20との間に所定の高さ寸法の空間29が形成される。鋼管19の底壁20に対するそれら高さ調節ボルト24の螺着位置を調節することによって、空間29の高さ寸法を調節することができ、コンクリート躯体12の表面からの鋼管19の底壁20の高さ寸法を調節することができる。   By rotating the height adjusting bolt 24 in the adjusting bolt screw hole 25, the bottom wall 20 of the steel pipe 19 is separated upward from the surface of the concrete housing 12, and between the surface of the concrete housing 12 and the bottom wall 20 of the steel pipe 19. A space 29 having a predetermined height is formed. By adjusting the screwing position of these height adjusting bolts 24 with respect to the bottom wall 20 of the steel pipe 19, the height dimension of the space 29 can be adjusted, and the bottom wall 20 of the steel pipe 19 from the surface of the concrete housing 12 can be adjusted. The height dimension can be adjusted.

なお、図示はしていないが、高さ調節ボルト24を利用せずにコンクリート躯体12の表面からの鋼管19の高さ寸法を調節することもできる。この場合は、アンカーボルト15の自由端部18のうちの底壁20の下面から下方へ露出する部分(コンクリート躯体12の表面と鋼管19の底壁20との間に延びる部分)に六角ナットを螺着する。そのナットを反時計回り回転させると、ナットがアンカーボルト15の自由端部18において下方へ移動し、鋼管19をコンクリート躯体12の表面に近づけることができる。逆に、ナットを時計回りに回転させると、ナットがアンカーボルトの自由端部において上方へ移動し、鋼管19をコンクリート躯体12の表面から上方に離間させることができる。   Although not shown, the height dimension of the steel pipe 19 from the surface of the concrete housing 12 can be adjusted without using the height adjusting bolt 24. In this case, a hexagon nut is attached to a portion of the free end portion 18 of the anchor bolt 15 that is exposed downward from the lower surface of the bottom wall 20 (a portion extending between the surface of the concrete housing 12 and the bottom wall 20 of the steel pipe 19). Screw it on. When the nut is rotated counterclockwise, the nut moves downward at the free end 18 of the anchor bolt 15, and the steel pipe 19 can be brought close to the surface of the concrete housing 12. Conversely, when the nut is rotated clockwise, the nut moves upward at the free end of the anchor bolt, and the steel pipe 19 can be separated upward from the surface of the concrete housing 12.

アンカーボルト15の自由端部18のうちの底壁20の下面から下方へ露出する部分に螺着するナットの回転によって鋼管19の底壁20がコンクリート躯体12の表面から上方へ離間し、コンクリート躯体12の表面と鋼管19の底壁20との間に所定の高さ寸法の空間29が形成される。アンカーボルト15の自由端部18の部分に対するナットの螺着位置を調節することによって、空間29の高さ寸法を調節することができ、コンクリート躯体12の表面からの鋼管19の高さ寸法を調節することができる。   The bottom wall 20 of the steel pipe 19 is separated upward from the surface of the concrete housing 12 by rotation of a nut screwed to a portion of the free end portion 18 of the anchor bolt 15 that is exposed downward from the lower surface of the bottom wall 20. A space 29 having a predetermined height is formed between the 12 surfaces and the bottom wall 20 of the steel pipe 19. By adjusting the screwing position of the nut with respect to the free end portion 18 of the anchor bolt 15, the height dimension of the space 29 can be adjusted, and the height dimension of the steel pipe 19 from the surface of the concrete housing 12 is adjusted. can do.

据え付け基礎施工方法は、高さ調節ボルト24を利用することで基礎10の施工中にその高さ寸法を自由に変えることができ、基礎10の高さ寸法の変更要求に即座に対応することができる。据え付け基礎施工方法は、複数個の基礎10をコンクリート構造物11に設置する場合、それら基礎10どうしの高さ寸法を容易に調節することができ、それら基礎10の高さ寸法を均一に揃えることができる。   The installation foundation construction method can change the height dimension freely during construction of the foundation 10 by using the height adjusting bolt 24, and can immediately respond to the change request of the height dimension of the foundation 10. it can. In the installation foundation construction method, when a plurality of foundations 10 are installed on the concrete structure 11, the height dimensions of the foundations 10 can be easily adjusted, and the height dimensions of the foundations 10 are made uniform. Can do.

図7は、図6から続く据え付け基礎の作成手順を示す図であり、図8は、図7から続く据え付け基礎の作成手順を示す図である。図7,8では、コンクリート構造物11を断面として示し、一部を除く基礎10の部品を断面として示す。高さ調節ボルト24を利用して空間29の高さ寸法を調節した後、図7に示すように、アンカーボルト15の自由端部18のうちの鋼管19の底壁20から上方へ延びる部分に六角二重ナット30を螺着し、高さ調節ボルト24とそれら二重ナット30と(固定手段)で鋼管19をアンカーボルト15の自由端部18に固定する(金属管固定工程)。なお、高さ調節ボルト24を利用せずに空間29の高さ寸法を調節した後は、アンカーボルト15の自由端部18のうちの鋼管19の底壁20から上方へ延びる部分に六角二重ナット30を螺着し、六角二重ナット30と六角ナットと(固定手段)で鋼管19をアンカーボルト15の自由端部18に固定する(金属管固定工程)。   FIG. 7 is a diagram showing a procedure for creating an installation foundation continued from FIG. 6, and FIG. 8 is a diagram showing a procedure for creating the installation foundation continuing from FIG. 7. 7 and 8, the concrete structure 11 is shown as a cross section, and parts of the foundation 10 excluding a part are shown as a cross section. After adjusting the height dimension of the space 29 using the height adjusting bolt 24, as shown in FIG. 7, a portion of the free end portion 18 of the anchor bolt 15 that extends upward from the bottom wall 20 of the steel pipe 19 is formed. The hexagonal double nut 30 is screwed, and the steel pipe 19 is fixed to the free end 18 of the anchor bolt 15 with the height adjusting bolt 24 and the double nut 30 (fixing means) (metal pipe fixing step). In addition, after adjusting the height dimension of the space 29 without using the height adjusting bolt 24, a hexagonal double is formed on a portion of the free end portion 18 of the anchor bolt 15 that extends upward from the bottom wall 20 of the steel pipe 19. The nut 30 is screwed, and the steel pipe 19 is fixed to the free end 18 of the anchor bolt 15 with the hexagonal double nut 30 and the hexagonal nut (fixing means) (metal pipe fixing step).

次に、鋼管19の側壁21(周壁)の外側に防水部材31を設置する(防水部材設置工程)。防水部材31は、側壁21の外側に固定された所定厚みの発泡材32と、発泡材32の外側に固定された防水層33とから形成されている。発泡材32は、その平面形状が矩形の4個のそれらを側壁21に固着し、中空角柱状に組み立てることで作られている。発泡材32は、大きさや厚みが同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造される。   Next, the waterproof member 31 is installed outside the side wall 21 (circumferential wall) of the steel pipe 19 (waterproof member installation step). The waterproof member 31 is formed of a foam material 32 having a predetermined thickness fixed to the outside of the side wall 21 and a waterproof layer 33 fixed to the outside of the foam material 32. The foamed material 32 is made by fixing four of the rectangular planar shapes to the side wall 21 and assembling them into a hollow prism shape. The foam material 32 is a standardized general-purpose product having the same size and thickness, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site.

防水部材設置工程では、平面形状が矩形の4個の発泡材32を用意し、それら発泡材32が各側壁21の外面全域を覆うように、それら発泡材32を側壁21の外側に配置し、それら発泡材32を各側壁21に接着剤(図示せず)およびビス(図示せず)を介して固着する。それら発泡材32を側壁21に固着した後、三角柱状の成型材34を鋼管19の底壁20の側であって発泡材32の外側(底壁20の周縁42の外側近傍)に設置する(成型材設置工程)。   In the waterproof member installation step, four foam materials 32 having a rectangular planar shape are prepared, and the foam materials 32 are arranged outside the side walls 21 so that the foam materials 32 cover the entire outer surface of each side wall 21. The foam materials 32 are fixed to the side walls 21 with an adhesive (not shown) and screws (not shown). After fixing these foam materials 32 to the side wall 21, a triangular prism shaped molding material 34 is placed on the bottom wall 20 side of the steel pipe 19 and outside the foam material 32 (near the outer periphery 42 of the bottom wall 20) ( Molding material installation process).

成型材34は、発泡材32の外面に接着剤(図示せず)を介して固着される。成型材34は、コンクリート躯体12の表面と鋼管19の底壁20の周縁42との間に延びる所定高さの空隙(空間29の周縁)を取り囲み、発泡材32とともにその空隙を塞ぐ。なお、図7では発泡材32が空間29にも配置されているが、発泡材32の下端が空間29の直上で終わり、発泡材32の下端の下に成型材34が配置されていてもよい。この場合は、成型材34が空隙(空間29の周縁)を取り囲み、成型材34のみによって空隙が塞がれる。成型材34は、発泡材やプラスチック、木、金属(鉄やアルミニウム等)のいずれかから作られている。   The molding material 34 is fixed to the outer surface of the foam material 32 via an adhesive (not shown). The molding material 34 surrounds a gap of a predetermined height (periphery of the space 29) extending between the surface of the concrete housing 12 and the peripheral edge 42 of the bottom wall 20 of the steel pipe 19, and closes the void together with the foam material 32. In FIG. 7, the foam material 32 is also disposed in the space 29, but the lower end of the foam material 32 ends immediately above the space 29, and the molding material 34 may be disposed under the lower end of the foam material 32. . In this case, the molding material 34 surrounds the gap (periphery of the space 29), and the gap is closed only by the molding material 34. The molding material 34 is made of any one of foam material, plastic, wood, and metal (iron, aluminum, etc.).

成型材34を設置した後、複数の薄いアスファルトシートを発泡材32の外面と成型材34の外面とに固着して防水層33を作るとともに、成型材34に固着した防水層33(鋼管19の底壁20の側に延びる防水層33)をコンクリート構造物11の防水層13につなげる。防水層33には、薄いアスファルトシートを複数重ね合わせて防水層33を作るアスファルト防水が利用されている。アスファルトシートは、その接着性によって発泡材32の外面と成型材34の外面とに固着している。なお、防水層33として、アスファルト防水の他に、塩ビシート防水やゴムシート防水、ウレタン防水やエポキシ防水、FRP防水を利用することもできる。   After the molding material 34 is installed, a plurality of thin asphalt sheets are fixed to the outer surface of the foam material 32 and the outer surface of the molding material 34 to form the waterproof layer 33, and the waterproof layer 33 (the steel pipe 19 of the steel pipe 19 is fixed to the molding material 34. The waterproof layer 33) extending to the bottom wall 20 side is connected to the waterproof layer 13 of the concrete structure 11. As the waterproof layer 33, asphalt waterproofing is used in which a plurality of thin asphalt sheets are stacked to form the waterproof layer 33. The asphalt sheet is fixed to the outer surface of the foam material 32 and the outer surface of the molding material 34 by its adhesiveness. In addition to asphalt waterproofing, PVC sheet waterproofing, rubber sheet waterproofing, urethane waterproofing, epoxy waterproofing, and FRP waterproofing can be used as the waterproof layer 33.

なお、防水部材31が防水層33のみから形成されていてもよい。この場合は、図示はしていないが、成型材34を鋼管19の底壁20の側であって発泡材32の外側(底壁20の周縁42の外側近傍)に設置し(成型材設置工程)、成型材34によって空隙(空間29の周縁)を塞いだ後、複数の薄いアスファルトシートを鋼管19の外面と成型材34の外面とに固着して防水層33を作り、成型材34に固着した防水層33(鋼管19の底壁20の側に延びる防水層33)をコンクリート構造物11の防水層13につなげる。   The waterproof member 31 may be formed only from the waterproof layer 33. In this case, although not shown, the molding material 34 is installed on the bottom wall 20 side of the steel pipe 19 and outside the foam material 32 (near the outer periphery 42 of the bottom wall 20) (molding material installation process). ) After closing the gap (periphery of the space 29) with the molding material 34, a plurality of thin asphalt sheets are fixed to the outer surface of the steel pipe 19 and the outer surface of the molding material 34 to form a waterproof layer 33 and fixed to the molding material 34. The waterproof layer 33 (waterproof layer 33 extending toward the bottom wall 20 of the steel pipe 19) is connected to the waterproof layer 13 of the concrete structure 11.

据え付け基礎施工方法は、鋼管19の側壁21の外側に防水部材31を設置するとともに、鋼管19の底壁20の側に延びる防水部材31の防水層33をコンクリート構造物11の防水層13につなげるから、基礎10をコンクリート構造物11の屋上に設置した場合に防水層13,33によって基礎10の内部への水の侵入を防ぐことができるとともに、コンクリート構造物11への水の進入を防ぐことができ、水の進入による基礎10の劣化やコンクリート構造物11の劣化を防ぐことができる。   In the installation foundation construction method, the waterproof member 31 is installed outside the side wall 21 of the steel pipe 19, and the waterproof layer 33 of the waterproof member 31 extending to the bottom wall 20 side of the steel pipe 19 is connected to the waterproof layer 13 of the concrete structure 11. Therefore, when the foundation 10 is installed on the roof of the concrete structure 11, the waterproof layers 13 and 33 can prevent water from entering the foundation 10 and prevent water from entering the concrete structure 11. It is possible to prevent deterioration of the foundation 10 and the concrete structure 11 due to the ingress of water.

防水部材31を設置した後、図8に示すように、コンクリート躯体12の表面と鋼管19の底壁20との間に形成された空間29(コンクリート躯体12の表面と鋼管19の底壁20と成型材34とに囲繞された空間29)にモルタル35(セメント硬化物)を充填する(セメント硬化物充填工程)。セメント硬化物充填工程では、確認孔28から空間29におけるモルタル35の充填状態を確認しつつ、充填孔27から空間29にモルタル35を充填する。   After installing the waterproof member 31, as shown in FIG. 8, a space 29 formed between the surface of the concrete housing 12 and the bottom wall 20 of the steel pipe 19 (the surface of the concrete housing 12 and the bottom wall 20 of the steel pipe 19). The space 29) surrounded by the molding material 34 is filled with mortar 35 (hardened cement material) (cement hardened material filling step). In the cement hardened material filling step, the mortar 35 is filled into the space 29 from the filling hole 27 while confirming the filling state of the mortar 35 in the space 29 from the confirmation hole 28.

据え付け基礎施工方法は、鋼管19の底壁20の中央部に形成された充填孔27から空間29にモルタル35を充填するから、モルタル35が空間29に偏って充填されることはなく、モルタル35を空間29全域に満遍なく充填することができる。また、確認孔28から空間29におけるモルタル35の充填状態を確認することができるから、確認孔28からモルタル35の充填状態を確認しつつ、充填作業を行うことで、空間29におけるモルタル35の偏りを防ぐことができ、モルタル35を空間29全域に満遍なく充填することができる。   Since the installation foundation construction method fills the space 29 with the mortar 35 from the filling hole 27 formed in the center portion of the bottom wall 20 of the steel pipe 19, the mortar 35 is not filled in the space 29, and the mortar 35 is not filled. Can be uniformly filled in the entire space 29. Further, since the filling state of the mortar 35 in the space 29 can be confirmed from the confirmation hole 28, the biasing of the mortar 35 in the space 29 is performed by performing the filling operation while confirming the filling state of the mortar 35 from the confirmation hole 28. Thus, the mortar 35 can be uniformly filled in the entire space 29.

図9は、図8から続く据え付け基礎の作成手順を示す図であり、図10は、図9から続く据え付け基礎の作成手順を示す図である。図11は、蓋36を取り外した状態の据え付け基礎の上面図であり、図12は、蓋36を取り付けた状態の据え付け基礎の上面図である。図10,11では、コンクリート構造物11を断面として示し、一部を除く基礎10の部品を断面として示す。   FIG. 9 is a diagram showing a procedure for creating an installation foundation continuing from FIG. 8, and FIG. 10 is a diagram showing a procedure for creating the installation foundation continuing from FIG. FIG. 11 is a top view of the installation foundation with the lid 36 removed, and FIG. 12 is a top view of the installation foundation with the lid 36 attached. 10 and 11, the concrete structure 11 is shown as a cross section, and parts of the foundation 10 excluding a part are shown as a cross section.

空間29にモルタル35を充填した後、モルタル35の養生期間を待つことなく、直ちに鋼管19の頂部に蓋36を嵌め込み(蓋36を鋼管19の頂部に固定)、鋼管19の頂部開口22を閉塞する(頂部閉塞工程)。なお、空隙(空間29の周縁)が発泡材32や成型材34によって塞がれているから、発泡材32や成型材34が硬化前のモルタル35の漏れを防ぐ堤防となり、空間29に充填されたモルタル35が空隙(空間29)から漏れ出すことはなく、モルタル35の充填後に直ちに蓋36で頂部開口22を閉塞することができる。据え付け基礎施工方法では、鋼管19の頂部に蓋36を嵌め込んだ(固定した)直後において空間29に充填されたモルタル35が未硬化状態にあり、鋼管19の頂部に蓋36を固定した後からモルタル35の養生期間が開始する。   After filling the space 29 with the mortar 35, the lid 36 is immediately fitted into the top of the steel pipe 19 without waiting for the curing period of the mortar 35 (the lid 36 is fixed to the top of the steel pipe 19), and the top opening 22 of the steel pipe 19 is closed. (Top closing step). Since the gap (periphery of the space 29) is blocked by the foam material 32 and the molding material 34, the foam material 32 and the molding material 34 serve as an embankment that prevents leakage of the mortar 35 before curing, and the space 29 is filled. Further, the mortar 35 does not leak from the gap (space 29), and the top opening 22 can be closed with the lid 36 immediately after the mortar 35 is filled. In the installation foundation construction method, the mortar 35 filled in the space 29 is in an uncured state immediately after the lid 36 is fitted (fixed) to the top of the steel pipe 19, and after the lid 36 is fixed to the top of the steel pipe 19. The curing period for the mortar 35 begins.

蓋36は、形状や寸法が同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造される。蓋36は、鋼材から作られ、その平面形状が略矩形に成型されている。蓋36の裏面であって蓋36の周縁の内側には、蓋36を鋼管19に固定するためのアングル材37(鋼材)が溶接によって取り付けられている。蓋36の裏面であって蓋36の周縁には、水切り用アングル38(鋼材)が溶接によって取り付けられている。アングル材37には、蓋固定ボルト39を挿通するボルト挿通孔(図示せず)が作られ、そのボルト挿通孔に六角ナット40が溶接によって取り付けられている。   The lid 36 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site. The lid 36 is made of a steel material, and its planar shape is formed into a substantially rectangular shape. An angle member 37 (steel material) for fixing the lid 36 to the steel pipe 19 is attached by welding on the back surface of the lid 36 and inside the periphery of the lid 36. A draining angle 38 (steel material) is attached to the rear surface of the lid 36 and on the periphery of the lid 36 by welding. The angle member 37 is formed with a bolt insertion hole (not shown) through which the lid fixing bolt 39 is inserted, and a hexagon nut 40 is attached to the bolt insertion hole by welding.

なお、蓋36の上面には、図示はしていないが、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を設置するための固定器具が取り付けられている。なお、金属蓋36は、鋼材の他に、アルミニウムや合金から作ることもできる。頂部閉塞工程では、鋼管19の頂部に蓋36を嵌め込んだ後、鋼管19の側壁21の上部に作られた固定ボルト螺着孔23に蓋固定ボルト39を螺着するとともに、蓋36のアングル材37の蓋固定ボルト挿通孔にボルト39を挿通し、ボルト挿通孔に取り付けられた六角ナット40にボルト39を螺着して蓋36を鋼管19の頂部に固定する。鋼管19の頂部開口22は、蓋36によって水密に閉塞される。   Although not shown in the figure, a fixing device for installing a building such as a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure is provided on the upper surface of the lid 36. It is attached. The metal lid 36 can be made of aluminum or an alloy in addition to the steel material. In the top closing step, after the lid 36 is fitted into the top of the steel pipe 19, the lid fixing bolt 39 is screwed into the fixing bolt screw hole 23 formed in the upper part of the side wall 21 of the steel pipe 19, and the angle of the lid 36 is The bolt 39 is inserted into the lid fixing bolt insertion hole of the material 37, and the bolt 39 is screwed to the hexagon nut 40 attached to the bolt insertion hole to fix the lid 36 to the top of the steel pipe 19. The top opening 22 of the steel pipe 19 is watertightly closed by a lid 36.

空間29では、モルタル35の養生期間が経過し、そこに充填されたモルタル35が硬化することで、アンカーボルト15の自由端部18のうちのコンクリート躯体12の表面と鋼管19の底壁20との間に延びる部分(アンカーボルト15の自由端部18のうちの底壁20の下面から下方へ露出する部分)がモルタル35と一体になり、鉄筋モルタルを形成する。   In the space 29, the curing period of the mortar 35 elapses, and the mortar 35 filled therein is cured, so that the surface of the concrete housing 12 in the free end portion 18 of the anchor bolt 15 and the bottom wall 20 of the steel pipe 19 (The portion exposed downward from the lower surface of the bottom wall 20 in the free end portion 18 of the anchor bolt 15) is integrated with the mortar 35 to form a reinforcing bar mortar.

硬化したモルタル35は、基礎10の上にソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を備え付けた場合の基礎10にかかる荷重をアンカーボルト15とともに分担する。なお、空間29に充填するセメント硬化物には、モルタル35の他に、コンクリートを利用することもできる。コンクリートを利用する場合、アンカーボルト15の自由端部18のうちの底壁20の下面から下方へ露出する部分がコンクリートと一体になり、鉄筋コンクリートを形成する。   The hardened mortar 35 is used to fix the load applied to the foundation 10 when the solar panel, antenna, water storage tank, septic tank, air conditioner and other machinery and equipment such as steel towers and steel structures are provided on the foundation 10 as anchor bolts. Share with 15. In addition to the mortar 35, concrete can also be used as the hardened cement filling the space 29. When concrete is used, a portion of the free end portion 18 of the anchor bolt 15 that is exposed downward from the lower surface of the bottom wall 20 is integrated with the concrete to form reinforced concrete.

鋼管19の頂部に蓋36を固定した後、ケイ酸カルシウム板41(乾式保護部材)を防水部材31の外側に設置する(保護部材設置工程)。ケイ酸カルシウム板41は、大きさや厚みが同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造される。保護部材設置工程では、平面形状が矩形の4個のケイ酸カルシウム板41を用意し、それらケイ酸カルシウム板41が防水部材31(アスファルトシート)全域を覆うように、それらケイ酸カルシウム板41を防水部材31の外側に配置し、板41の頂部を固定金具(図示せず)を介して蓋36の底面に固定し、板41の底部を固定金具(図示せず)を介してコンクリート構造物11のコンクリート層14の表面に固定する。以上の各工程が終了すると図11に示す据え付け基礎10が完成する。   After fixing the lid 36 to the top of the steel pipe 19, a calcium silicate plate 41 (dry protection member) is installed outside the waterproof member 31 (protection member installation step). The calcium silicate plate 41 is a standardized general-purpose product having the same size and thickness, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site. In the protective member installation step, four calcium silicate plates 41 having a rectangular planar shape are prepared, and the calcium silicate plates 41 are arranged so that the calcium silicate plates 41 cover the entire waterproof member 31 (asphalt sheet). Arranged outside the waterproof member 31, the top of the plate 41 is fixed to the bottom surface of the lid 36 via a fixing bracket (not shown), and the bottom of the plate 41 is fixed to the concrete structure via a fixing bracket (not shown). 11 is fixed to the surface of the concrete layer 14. When the above steps are completed, the installation base 10 shown in FIG. 11 is completed.

据え付け基礎施工方法は、防水部材31を衝撃から保護するケイ酸カルシウム板41(保護部材)を防水部材31の外側に設置するから、基礎10の外側から衝撃が加えられたとしても、ケイ酸カルシウム板41によってその衝撃が吸収され、衝撃によって防水部材31が破損することはなく、防水部材31によって基礎10やコンクリート構造物11の内部への水の侵入を防ぐことができ、内部に水が進入することによる基礎10の劣化やコンクリート構造物11の劣化を防ぐことができる。   In the installation foundation construction method, since the calcium silicate plate 41 (protective member) that protects the waterproof member 31 from impact is installed outside the waterproof member 31, even if an impact is applied from the outside of the foundation 10, the calcium silicate The impact is absorbed by the plate 41, and the waterproof member 31 is not damaged by the impact. The waterproof member 31 can prevent water from entering the foundation 10 or the concrete structure 11, and water can enter the interior. It is possible to prevent the deterioration of the foundation 10 and the concrete structure 11 due to the operation.

据え付け基礎施工方法は、基礎10の据え付け箇所に複数のアンカーボルト15を設置するアンカーボルト設置工程と、鋼管19をコンクリート躯体12(コンクリート構造物11)から上方へ離間させた状態でアンカーボルト15の自由端部18に固定する金属管固定工程と、成型材34を鋼管19の底壁20の周縁42の外側近傍に設置する成型材設置工程と、鋼管19の側壁21の外側に防水部材31を設置する防水部材設置工程と、空間29にモルタル35を充填するセメント硬化物充填工程と、鋼管19の頂部に蓋36を固定する頂部閉塞工程と、ケイ酸カルシウム板41を防水部材31の外側に設置する保護部材設置工程とから基礎10が作られ、汎用部品化された各基礎部品をそれら工程によってユニットシステムとして組み立てるから、施工作業をマニュアル化することができるとともに、施工作業を簡略化することができる。   The installation foundation construction method includes an anchor bolt installation process in which a plurality of anchor bolts 15 are installed at the installation location of the foundation 10, and the anchor bolts 15 in a state where the steel pipe 19 is spaced upward from the concrete frame 12 (concrete structure 11). A metal tube fixing step for fixing to the free end 18, a molding material installation step for installing the molding material 34 in the vicinity of the outer periphery 42 of the bottom wall 20 of the steel pipe 19, and a waterproof member 31 on the outer side of the side wall 21 of the steel pipe 19. A waterproof member installation step for installing, a cement hardened material filling step for filling the space 29 with mortar 35, a top closing step for fixing the lid 36 to the top of the steel pipe 19, and a calcium silicate plate 41 on the outside of the waterproof member 31 The base 10 is made from the protective member installation process to be installed, and each basic part made into a general-purpose part is assembled as a unit system by those processes. Since the ether, it is possible to manual of the construction work, it is possible to simplify the construction work.

据え付け基礎施工方法は、基礎10を形成する際に施工現場において型枠を製作する必要がないことはもちろん、基礎製造工場や施工現場において基礎10を作るためにモルタル35を養生する必要はなく、コンクリート躯体12に固定された複数のアンカーボルト15に中空の軽量な鋼管19を固定し、その鋼管19の外側に防水部材31とケイ酸カルシウム板41とを固定するとともに、鋼管19に蓋36を固定するだけであり、型枠の製作やモルタルの養生にかかる手間や時間を省くことができ、その分の工期を短縮することができる。   In the installation foundation construction method, it is not necessary to produce a formwork at the construction site when forming the foundation 10, and it is not necessary to cure the mortar 35 to make the foundation 10 at the foundation manufacturing factory or construction site. A hollow lightweight steel pipe 19 is fixed to a plurality of anchor bolts 15 fixed to the concrete housing 12, a waterproof member 31 and a calcium silicate plate 41 are fixed to the outside of the steel pipe 19, and a lid 36 is attached to the steel pipe 19. It is only fixed, and the labor and time required for the production of the mold and the curing of the mortar can be saved, and the work period can be shortened accordingly.

据え付け基礎施工方法は、複数のアンカーボルト15の固定端部17をコンクリート躯体12に固定し、それらアンカーボルト15の自由端部18に鋼管19を固定するから、据え付け基礎10をコンクリート構造物11に強固に据え付けることができ、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることができる。据え付け基礎施工方法は、コンクリート躯体12の表面と鋼管19の底壁20との間の空間29にモルタル35を充填し、基礎10の上に機械機器や建築物を備え付けた場合の基礎10にかかる荷重をアンカーボルト15とモルタル35とで分担させることができるから、基礎10にかかる荷重でそれが不用意に傾斜したり、基礎10が崩壊することはなく、機械機器や建築物を確実に支持する基礎10を作る。   In the installation foundation construction method, the fixed ends 17 of the plurality of anchor bolts 15 are fixed to the concrete frame 12, and the steel pipe 19 is fixed to the free ends 18 of the anchor bolts 15. Therefore, the installation foundation 10 is fixed to the concrete structure 11. It can be firmly installed, and can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air conditioners, and buildings such as steel towers and steel frame constructions. The installation foundation construction method is applied to the foundation 10 when a mortar 35 is filled in a space 29 between the surface of the concrete frame 12 and the bottom wall 20 of the steel pipe 19, and mechanical equipment or a building is provided on the foundation 10. Since the load can be shared between the anchor bolt 15 and the mortar 35, the load applied to the foundation 10 does not inadvertently incline or the foundation 10 collapses, and the machine equipment and the building are reliably supported. Make a foundation 10 to do.

据え付け基礎施工方法は、鋼管19の底壁20の周縁42の外側近傍に設置された成型材34が硬化前のモルタル35(セメント硬化物)の漏れを防ぐ堤防となり、空間29に充填されたモルタル35がその空間29から漏れ出すことがないから、底壁20の周縁42の外側近傍にモルタル35のための型枠を設置する必要がなく、型枠を設置するための手間や時間を省くことができ、据え付け基礎10の工期を大幅に短縮することができる。据え付け基礎施工方法は、空間29に充填されたモルタル35の養生期間を待つことなく、空間28にモルタル35を充填した直後に蓋36を鋼管19の頂部に固定することができ、モルタル35の養生期間を待つことなく次の基礎10の施工を行うことができるから、モルタル35の養生期間の分の工期を短縮することができ、据え付け基礎10の工期を大幅に短縮することができる。   In the installation foundation construction method, the molding material 34 installed in the vicinity of the outer periphery 42 of the bottom wall 20 of the steel pipe 19 serves as an embankment that prevents leakage of the mortar 35 (hardened cement) before hardening, and the mortar filled in the space 29 35 does not leak out of the space 29, so that it is not necessary to install a mold for the mortar 35 in the vicinity of the outer periphery 42 of the bottom wall 20, and time and labor for installing the mold can be saved. The construction period of the installation foundation 10 can be greatly shortened. The installation foundation construction method can fix the lid 36 to the top of the steel pipe 19 immediately after filling the space 28 with the mortar 35 without waiting for the curing period of the mortar 35 filled in the space 29. Since the next foundation 10 can be constructed without waiting for the period, the construction period for the curing period of the mortar 35 can be shortened, and the construction period of the installation foundation 10 can be greatly shortened.

10 据え付け基礎
11 コンクリート構造物
12 コンクリート躯体
13 防水層
14 コンクリート層
15 アンカーボルト
16 アンカーホール
17 固定端部
18 自由端部
19 鋼管(金属管)
20 底壁
21 側壁(周壁)
22 頂部開口
24 高さ調節ボルト
27 充填孔
28 確認孔
29 空間
31 防水部材
32 発泡材
33 防水層
34 成型材
35 モルタル(セメント硬化物)
36 蓋(金属蓋)
41 ケイ酸カルシウム板(乾式保護部材)
42 周縁
DESCRIPTION OF SYMBOLS 10 Installation foundation 11 Concrete structure 12 Concrete frame 13 Waterproof layer 14 Concrete layer 15 Anchor bolt 16 Anchor hole 17 Fixed end part 18 Free end part 19 Steel pipe (metal pipe)
20 Bottom wall 21 Side wall (peripheral wall)
22 Top opening 24 Height adjustment bolt 27 Filling hole 28 Confirmation hole 29 Space 31 Waterproof member 32 Foam material 33 Waterproof layer 34 Molding material 35 Mortar (hardened cement)
36 Lid (metal lid)
41 Calcium silicate board (dry protection member)
42

Claims (11)

新設または既設のコンクリート構造物の所定の据え付け箇所に据え付けられる据え付け基礎を施工する据え付け基礎施工方法において、
前記据え付け基礎施工方法が、前記据え付け箇所に複数のアンカーボルトの固定端部を固定してそれらアンカーボルトの自由端部を前記コンクリート構造物から上方へ起立させるアンカーボルト設置工程と、底壁およびその底壁の周縁から上方へ延びる周壁を有する金属管を前記コンクリート構造物から上方へ離間させた状態で前記アンカーボルトの自由端部に固定手段を介して固定する金属管固定工程と、前記コンクリート構造物と前記金属管の底壁との間に形成された空間にセメント硬化物を充填するセメント硬化物充填工程と、前記金属管の頂部に金属蓋を固定して該金属管の頂部開口を閉塞する頂部閉塞工程とを有することを特徴とする据え付け基礎施工方法。
In an installation foundation construction method for constructing an installation foundation to be installed at a predetermined installation location of a new or existing concrete structure,
The installation foundation construction method includes an anchor bolt installation step of fixing fixed ends of a plurality of anchor bolts to the installation location and raising the free ends of the anchor bolts upward from the concrete structure; a bottom wall; and A metal pipe fixing step of fixing a metal pipe having a peripheral wall extending upward from a peripheral edge of the bottom wall to a free end portion of the anchor bolt via a fixing means in a state of being spaced apart from the concrete structure; and the concrete structure A cement hardened material filling step of filling the space formed between the object and the bottom wall of the metal tube with a cement hardened material, and fixing the metal lid to the top of the metal tube to close the top opening of the metal tube A top foundation closing method characterized by comprising: a top closing step.
前記据え付け基礎施工方法が、前記コンクリート構造物と前記金属管の底壁の周縁との間に延びる空隙を塞ぐ成型材を該金属管の底壁の周縁の外側近傍に設置する成型材設置工程を含み、前記セメント硬化物充填工程では、前記コンクリート構造物と前記金属管の底壁と前記成型材とに囲繞された前記空間にセメント硬化物を充填し、前記頂部閉鎖工程では、前記空間に充填されたセメント硬化物の養生期間を待つことなく、前記空間にセメント硬化物を充填した直後に前記金属蓋を前記金属管の頂部に固定する請求項1記載の据え付け基礎施工方法。   The installation foundation construction method includes a molding material installation step of installing a molding material that closes a gap extending between the concrete structure and a peripheral edge of the bottom wall of the metal pipe in the vicinity of the outside of the peripheral edge of the bottom wall of the metal pipe. In the cement hardened material filling step, the space surrounded by the concrete structure, the bottom wall of the metal tube, and the molding material is filled with cement hardened material, and in the top closing step, the space is filled. The installation foundation construction method according to claim 1, wherein the metal lid is fixed to the top of the metal pipe immediately after the space is filled with the cement hardened material without waiting for a curing period of the hardened cement hardened material. 前記据え付け基礎施工方法では、前記金属管の頂部に前記金属蓋を固定した直後において前記空間に充填されたセメント硬化物が未硬化状態にあり、前記金属管の頂部に前記金属蓋を固定した後からセメント硬化物の養生期間が開始し、前記養生期間が経過した後に、前記アンカーボルトの自由端部のうちの前記コンクリート構造物の表面と前記金属管の底壁との間に延びる部分が前記空間に充填されたセメント硬化物と一体になる請求項2記載の据え付け基礎施工方法。   In the installation foundation construction method, immediately after fixing the metal lid to the top of the metal tube, the hardened cement filled in the space is in an uncured state, and after fixing the metal lid to the top of the metal tube After the curing period of the cement hardened material starts and the curing period has elapsed, a portion of the free end of the anchor bolt that extends between the surface of the concrete structure and the bottom wall of the metal tube is The installation foundation construction method according to claim 2, which is integrated with the hardened cement filled in the space. 前記据え付け基礎施工方法が、前記金属管を前記据え付け箇所に仮設置する仮設置工程と、前記金属管を仮設置した後に、前記アンカーボルトの自由端部に対する前記金属管の底壁の固定位置を調節して前記コンクリート構造物からの該金属管の設置高さを調節する設置高さ調節工程とを含み、前記金属管固定工程では、前記金属管の設置高さを調節した後に前記アンカーボルトの自由端部に該金属管の底壁を固定する請求項1ないし請求項3いずれかに記載の据え付け基礎施工方法。   The installation foundation construction method includes a temporary installation step in which the metal pipe is temporarily installed at the installation location, and a temporary position of the metal pipe, and a fixed position of the bottom wall of the metal pipe with respect to a free end of the anchor bolt. Adjusting the installation height of the metal pipe from the concrete structure to adjust the installation height of the anchor bolt after adjusting the installation height of the metal pipe in the metal pipe fixing step. The installation foundation construction method according to any one of claims 1 to 3, wherein a bottom wall of the metal pipe is fixed to a free end. 前記据え付け基礎施工方法が、前記金属管の底壁に開口する螺着孔に螺着されて該金属管の高さ寸法を調節する高さ調節ボルトを含み、前記設置高さ調節工程では、前記高さ調節ボルトの前記金属管の底壁に対する螺着位置を調節することによって前記空間の高さ寸法を調節可能かつ前記コンクリート構造物の表面からの該金属管の高さ寸法を調節可能である請求項4記載の据え付け基礎施工方法。   The installation foundation construction method includes a height adjustment bolt that is screwed into a screw hole that is opened in a bottom wall of the metal tube to adjust a height dimension of the metal tube, and in the installation height adjustment step, The height dimension of the space can be adjusted and the height dimension of the metal tube from the surface of the concrete structure can be adjusted by adjusting the screwing position of the height adjusting bolt to the bottom wall of the metal tube. The installation foundation construction method according to claim 4. 前記コンクリート構造物が、コンクリート躯体と、前記コンクリート躯体の上に施設された防水層と、前記防水層の上に施設されたコンクリート層とから形成され、前記アンカーボルト設置工程では、前記コンクリート構造物から前記コンクリート層と前記防水層とを取り除いて前記コンクリート躯体を露出させ、前記コンクリート躯体の据え付け箇所に前記アンカーボルトの固定端部を固定し、前記金属管固定工程では、前記金属管を前記コンクリート躯体から上方へ離間させた状態でそれらアンカーボルトの自由端部に固定する請求項1ないし請求項5いずれかに記載の据え付け基礎施工方法。   The concrete structure is formed of a concrete case, a waterproof layer provided on the concrete case, and a concrete layer provided on the waterproof layer. In the anchor bolt installation step, the concrete structure is formed. The concrete layer and the waterproof layer are removed from the concrete casing to expose the concrete casing, and a fixed end of the anchor bolt is fixed to an installation location of the concrete casing. In the metal pipe fixing step, the metal pipe is connected to the concrete The installation foundation construction method according to any one of claims 1 to 5, wherein the anchor bolts are fixed to the free ends of the anchor bolts while being spaced apart upward from the housing. 前記据え付け基礎施工方法が、前記金属管の周壁の外側に防水部材を設置する防水部材設置工程を含み、前記防水部材が、前記金属管の周壁の外側に固定された発泡材と、前記発泡材の外側に固定された防水層とから形成されている請求項1ないし請求項6いずれかに記載の据え付け基礎施工方法。   The installation foundation construction method includes a waterproof member installation step of installing a waterproof member on the outer side of the peripheral wall of the metal tube, and the waterproof member is fixed to the outer side of the peripheral wall of the metal tube, and the foamed material The installation foundation construction method according to any one of claims 1 to 6, wherein the installation foundation construction method is formed from a waterproof layer fixed to the outer side of the base. 前記防水部材設置工程では、前記金属管の底壁の側に延びる前記防水部材の防水層を前記コンクリート構造物の防水層につなげる請求項7記載の据え付け基礎施工方法。   The installation foundation construction method according to claim 7, wherein, in the waterproof member installation step, the waterproof layer of the waterproof member extending toward the bottom wall of the metal pipe is connected to the waterproof layer of the concrete structure. 前記据え付け基礎施工方法が、前記防水部材を衝撃から保護する乾式保護部材を該防水部材の外側に設置する保護部材設置工程を含む請求項7または請求項8に記載の据え付け基礎施工方法。   The installation foundation construction method according to claim 7 or 8, wherein the installation foundation construction method includes a protection member installation step of installing a dry-type protection member that protects the waterproof member from an impact outside the waterproof member. 前記金属板管の底壁の中央部には、前記コンクリート構造物と前記金属管の底壁との間の空間に前記セメント硬化物を充填するための充填孔が形成され、前記セメント硬化物充填工程では、前記充填孔から前記空間にセメント硬化物を充填する請求項1ないし請求項9いずれかに記載の据え付け基礎施工方法。   A filling hole for filling the cement hardened material into a space between the concrete structure and the bottom wall of the metal pipe is formed in a central portion of the bottom wall of the metal plate tube, and filling the cement hardened material The installation foundation construction method according to any one of claims 1 to 9, wherein in the step, the hardened cement material is filled into the space from the filling hole. 前記金属管の底壁の所定の箇所には、前記コンクリート構造物と前記金属管の底壁との間の空間に充填された前記セメント硬化物を確認するための確認孔が形成され、前記セメント硬化物充填工程では、前記確認孔から前記空間におけるセメント硬化物の充填状態を確認する請求項1ないし請求項10いずれかに記載の据え付け基礎施工方法。   A confirmation hole for confirming the cement hardened material filled in a space between the concrete structure and the bottom wall of the metal tube is formed at a predetermined position of the bottom wall of the metal tube, and the cement is formed. The fixed foundation construction method according to any one of claims 1 to 10, wherein in the cured product filling step, a state of filling of the cement cured product in the space is confirmed from the confirmation hole.
JP2011189665A 2010-09-01 2011-08-31 Installation foundation construction method Expired - Fee Related JP5921116B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011189665A JP5921116B2 (en) 2010-09-01 2011-08-31 Installation foundation construction method

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2010195640 2010-09-01
JP2010195640 2010-09-01
JP2011189665A JP5921116B2 (en) 2010-09-01 2011-08-31 Installation foundation construction method

Publications (2)

Publication Number Publication Date
JP2012072648A true JP2012072648A (en) 2012-04-12
JP5921116B2 JP5921116B2 (en) 2016-05-24

Family

ID=46169089

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011189665A Expired - Fee Related JP5921116B2 (en) 2010-09-01 2011-08-31 Installation foundation construction method

Country Status (1)

Country Link
JP (1) JP5921116B2 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103352476A (en) * 2013-07-22 2013-10-16 陕西建工集团第十一建筑工程有限公司 Large-scale bolt high-precision pre-burying construction method
CN103628498A (en) * 2012-08-29 2014-03-12 中国二十冶集团有限公司 T-shaped foundation bolt hole plugging method
CN103669389A (en) * 2012-09-26 2014-03-26 上海宝冶集团有限公司 Corrugated pipe fixing method for positioning foundation bolt
JP2014080824A (en) * 2012-10-18 2014-05-08 Takenaka Komuten Co Ltd Method for constructing foundation structure by utilizing skeleton of existing structure, and foundation structure
CN104278798A (en) * 2014-09-01 2015-01-14 湖北源盛钢构有限公司 Fastening process of steel structure column foot concrete and fixed connection device of steel structure column foot concrete
CN105155573A (en) * 2015-07-02 2015-12-16 同济大学建筑设计研究院(集团)有限公司 Offshore wind turbine barrel-in-barrel foundation
CN107254979A (en) * 2017-05-27 2017-10-17 中国核工业第五建设有限公司 The installation method of ground flare cylinder
CN108963918A (en) * 2018-10-12 2018-12-07 北京城建集团有限责任公司 A kind of guardrail basis interior[exterior device and its construction method
JP2021011700A (en) * 2019-07-04 2021-02-04 株式会社竹中工務店 Rooftop facility foundation structure and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118724A (en) * 2016-11-29 2018-06-05 中国二十冶集团有限公司 T-bolt anchor box leak blocking method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03265800A (en) * 1990-03-13 1991-11-26 Toshiba Corp Method of installing equipment
JP2006225951A (en) * 2005-02-17 2006-08-31 Tajima Roofing Co Ltd Frame device on waterproof layer, frame device mounting structure on waterproof layer, and frame device mounting method
JP2009167754A (en) * 2008-01-18 2009-07-30 Cosmo System Kk Base frame for setting facility equipment and method of setting the base frame

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03265800A (en) * 1990-03-13 1991-11-26 Toshiba Corp Method of installing equipment
JP2006225951A (en) * 2005-02-17 2006-08-31 Tajima Roofing Co Ltd Frame device on waterproof layer, frame device mounting structure on waterproof layer, and frame device mounting method
JP2009167754A (en) * 2008-01-18 2009-07-30 Cosmo System Kk Base frame for setting facility equipment and method of setting the base frame

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628498B (en) * 2012-08-29 2016-08-10 中国二十冶集团有限公司 T-shaped foundation bolt hole method for blocking
CN103628498A (en) * 2012-08-29 2014-03-12 中国二十冶集团有限公司 T-shaped foundation bolt hole plugging method
CN103669389A (en) * 2012-09-26 2014-03-26 上海宝冶集团有限公司 Corrugated pipe fixing method for positioning foundation bolt
JP2014080824A (en) * 2012-10-18 2014-05-08 Takenaka Komuten Co Ltd Method for constructing foundation structure by utilizing skeleton of existing structure, and foundation structure
CN103352476B (en) * 2013-07-22 2015-03-04 陕西建工集团第十一建筑工程有限公司 Large-scale bolt high-precision pre-burying construction method
CN103352476A (en) * 2013-07-22 2013-10-16 陕西建工集团第十一建筑工程有限公司 Large-scale bolt high-precision pre-burying construction method
CN104278798A (en) * 2014-09-01 2015-01-14 湖北源盛钢构有限公司 Fastening process of steel structure column foot concrete and fixed connection device of steel structure column foot concrete
CN105155573A (en) * 2015-07-02 2015-12-16 同济大学建筑设计研究院(集团)有限公司 Offshore wind turbine barrel-in-barrel foundation
CN107254979A (en) * 2017-05-27 2017-10-17 中国核工业第五建设有限公司 The installation method of ground flare cylinder
CN108963918A (en) * 2018-10-12 2018-12-07 北京城建集团有限责任公司 A kind of guardrail basis interior[exterior device and its construction method
CN108963918B (en) * 2018-10-12 2024-05-28 北京城建集团有限责任公司 Internal wiring box device of guardrail foundation and construction method thereof
JP2021011700A (en) * 2019-07-04 2021-02-04 株式会社竹中工務店 Rooftop facility foundation structure and construction method thereof
JP7269807B2 (en) 2019-07-04 2023-05-09 株式会社竹中工務店 Rooftop facility foundation structure and its construction method

Also Published As

Publication number Publication date
JP5921116B2 (en) 2016-05-24

Similar Documents

Publication Publication Date Title
JP5921116B2 (en) Installation foundation construction method
JP6041485B2 (en) Installation base
US9068320B2 (en) Mounting base
JP4597199B2 (en) Foundation frame for installation of equipment and installation method of the foundation frame
JP5576207B2 (en) Installation foundation and its construction method
WO2012081653A1 (en) Method of installing a mounting base
JP2019157614A (en) Foundation formwork structure for house and method for constructing foundation formwork
KR20100009802A (en) All precast concrete prefabricated water storage tank using precast concrete panel for retaining wall
JP4454607B2 (en) Rise basis
JP5921176B2 (en) Installation foundation construction method
CN114135023A (en) Assembled building outer wall and construction method
KR100726111B1 (en) Bathroom bottom manufacture method using precast concreat slab
JP6091740B2 (en) Installation base
JP3172665U (en) Installation base
JP5469467B2 (en) Support structure for equipment on the rooftop
KR101862567B1 (en) Standardization of Mat Foundation assembling House system
JP5927683B1 (en) Substructure installation method
KR101441943B1 (en) Rainwater storage tank having semi-automatic connecting member and receptacle and construction method thereof
JP5978445B2 (en) Installation foundation structure
CN115506593B (en) Garage top wall column construction method
KR200263619Y1 (en) Underground support structure of under construction using a complex material synthetic panel
JPH0786261B2 (en) Floor construction method for buildings
KR101441940B1 (en) Rainwater storage tank having semi-automatic connecting member and construction method thereof
JP2015014178A (en) Rooftop piping-leading out box
CN112144871A (en) Water-stopping reinforcement method for concrete sheet

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140826

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150514

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150519

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150713

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150915

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151109

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160329

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160412

R150 Certificate of patent or registration of utility model

Ref document number: 5921116

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees