CN103669389A - Corrugated pipe fixing method for positioning foundation bolt - Google Patents
Corrugated pipe fixing method for positioning foundation bolt Download PDFInfo
- Publication number
- CN103669389A CN103669389A CN201210362529.9A CN201210362529A CN103669389A CN 103669389 A CN103669389 A CN 103669389A CN 201210362529 A CN201210362529 A CN 201210362529A CN 103669389 A CN103669389 A CN 103669389A
- Authority
- CN
- China
- Prior art keywords
- bellows
- corrugated pipe
- rebars
- positioning
- foundation bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention relates to a corrugated pipe fixing method for positioning a foundation bolt. According to the method, an equipment basis is built firstly, then a corrugated pipe with a diameter and depth slightly larger than those of a preformed hole is selected, and the upper end and the lower end of the corrugated pipe are both sealed with steel covers with diameters equal to the diameter of the corrugated pipe. The method further comprises the steps that a, the upper portion, the middle portion and the lower portion of the outer side of the corrugated pipe are respectively and sequentially clamed with two rebars in both the longitudinal direction and the horizontal direction to form an intersecting-parallel shape, the two rebars clamping the upper portion of the corrugated pipe are connected with rebars on the upper row of the equipment basis in a welding mode, and the rebars clamping the middle portion of the corrugated pipe and the rebars clamping the lower portion of the corrugated pipe are connected with a supporting system of the equipment basis in a welding mode; b, at least one rebar is welded to the bottom end of the corrugated pipe to serve as a bottom support, and at least one rebar is additionally arranged at the top end of the corrugated pipe to serve as a capping. According to the corrugated pipe fixing method for positioning the foundation bolt, fast and accurate positioning is achieved, and the accuracy of a foundation bolt hole is guaranteed.
Description
Technical field
The present invention relates to a kind of bellows fixing means, specifically the bellows fixing means of positioning stone bolt.
Background technology
Large equipment base stone bolt hole number is many, accuracy requires high.How to guarantee that the accurate location of anchor (bolt) hole is crucial, first consider to adopt which kind of material to make mould, then which kind of mode consideration adopts fix.If adopt veneer as mould: one, fabrication cycle is long, can not meet duration needs; Two, partly bolt holes slenderness ratio is larger, and as adopted pattern glue plywood to make mould, form removable difficulty, is difficult to guarantee not clamping of concrete; And hole inwall dabbing difficulty.Three, in concreting process, due to the necessary back cover of mould end opening, pattern glue plywood mould can not weld, and mould can produce buoyancy, is difficult to guarantee bolt hole projected depth.
Summary of the invention
The present invention is intended to overcome the defect of prior art, and a kind of bellows fixing means of positioning stone bolt is provided, can be fast, accurate location, guaranteed the accuracy of anchor (bolt) hole.
In order to solve the problems of the technologies described above, the present invention is achieved in that
A kind of bellows fixing means of positioning stone bolt, first build equipment Foundations, then select diameter and the large bellows of depth ratio preformed hole, it is characterized in that: at the two ends up and down of bellows, all adopt and the isodiametric steel cap seal of bellows mouth, it also comprises the steps:
A. the longitudinal and transverse direction of the upper, middle and lower outside bellows is clamped with two reinforcing bars respectively successively, become groined type, and two reinforcing bars that clamp bellows top are welded to connect with the upper placing of reinforcement of equipment Foundations, will clamp in the middle part of bellows and the reinforcing bar of bottom and the support system of equipment Foundations are welded to connect;
B. in the weldering of the bottom of bellows end, establish at least one reinforcing bar as collet.
The bellows fixing means of described positioning stone bolt, is characterized in that: on the top of bellows, set up at least one reinforcing bar and bear down on one.
The bellows fixing means of described positioning stone bolt, is characterized in that: it also comprises S drag hook, by S drag hook, bellows and equipment Foundations colligation is firm.
The invention has the beneficial effects as follows: the fixing means of bellows has guaranteed the accuracy of anchor (bolt) hole, improved the pre-buried speed of anchor (bolt) hole, reduced the Mold Making time, save manually, reduced cost.
Accompanying drawing explanation
Below in conjunction with drawings and embodiments, the present invention is described in further detail:
Fig. 1 is structural representation of the present invention.
Fig. 2 is the top of line pipe and the structural representation that reinforcing bar is established in bottom weldering.
The specific embodiment
As shown in Figure 1: a kind of bellows fixing means of positioning stone bolt, first build equipment Foundations, then select the bigger bellows 1 of diameter and depth ratio preformed hole, all adopt and isodiametric steel lid 2 sealings of bellows at the two ends up and down of bellows, it also comprises the steps:
A. the longitudinal and transverse direction of the upper, middle and lower outside bellows uses respectively two reinforcing bars 3 by its clamping successively, become groined type, and two reinforcing bars that clamp bellows top are welded to connect with the upper placing of reinforcement of equipment Foundations, will clamp in the middle part of bellows and the reinforcing bar of bottom and the support system of equipment Foundations are welded to connect;
As shown in Figure 2: b. establishes two reinforcing bars 3 as collet in the weldering of the bottom of bellows 1 end; On the top of bellows, setting up two reinforcing bars 3 bears down on one.The present invention also comprises S drag hook, by S drag hook, bellows and equipment Foundations colligation is firm.
Claims (3)
1. the bellows fixing means of a positioning stone bolt, first build equipment Foundations, then select diameter and the large bellows of depth ratio preformed hole, it is characterized in that: at the two ends up and down of bellows, all adopt and the isodiametric steel cap seal of bellows mouth, it also comprises the steps:
A. the longitudinal and transverse direction of the upper, middle and lower outside bellows is clamped with two reinforcing bars respectively successively, become groined type, and two reinforcing bars that clamp bellows top are welded to connect with the upper placing of reinforcement of equipment Foundations, will clamp in the middle part of bellows and the reinforcing bar of bottom and the support system of equipment Foundations are welded to connect;
B. in the weldering of the bottom of bellows end, establish at least one reinforcing bar as collet.
2. the bellows fixing means of positioning stone bolt according to claim 1, is characterized in that: on the top of bellows, set up at least one reinforcing bar and bear down on one.
3. the bellows fixing means of positioning stone bolt according to claim 1 and 2, is characterized in that: it also comprises S drag hook, by S drag hook, bellows and equipment Foundations colligation is firm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210362529.9A CN103669389A (en) | 2012-09-26 | 2012-09-26 | Corrugated pipe fixing method for positioning foundation bolt |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210362529.9A CN103669389A (en) | 2012-09-26 | 2012-09-26 | Corrugated pipe fixing method for positioning foundation bolt |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103669389A true CN103669389A (en) | 2014-03-26 |
Family
ID=50308103
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210362529.9A Pending CN103669389A (en) | 2012-09-26 | 2012-09-26 | Corrugated pipe fixing method for positioning foundation bolt |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103669389A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105887916A (en) * | 2014-11-27 | 2016-08-24 | 华北冶建工程建设有限公司 | New method for construction after bolt embedment |
CN105401591B (en) * | 2014-09-03 | 2017-11-28 | 五冶集团上海有限公司 | Pre-embedded bolt corrugated sleeve installation method |
CN109386009A (en) * | 2017-08-04 | 2019-02-26 | 上海宝冶集团有限公司 | Equipment anchor bolt buries the construction tool and method of reserving hole |
CN113530056A (en) * | 2021-07-16 | 2021-10-22 | 中国二十二冶集团有限公司 | Method for pre-embedding corrugated pipe on top plate |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03265800A (en) * | 1990-03-13 | 1991-11-26 | Toshiba Corp | Method of installing equipment |
CN101806069A (en) * | 2010-04-16 | 2010-08-18 | 天津二十冶建设有限公司 | Integrated fixation and installation method for bolt |
CN201794088U (en) * | 2010-08-12 | 2011-04-13 | 中冶成工上海五冶建设有限公司 | Foundation bolt positioner |
JP2012072648A (en) * | 2010-09-01 | 2012-04-12 | Marutaka Kogyo Inc | Installed foundation construction method |
-
2012
- 2012-09-26 CN CN201210362529.9A patent/CN103669389A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03265800A (en) * | 1990-03-13 | 1991-11-26 | Toshiba Corp | Method of installing equipment |
CN101806069A (en) * | 2010-04-16 | 2010-08-18 | 天津二十冶建设有限公司 | Integrated fixation and installation method for bolt |
CN201794088U (en) * | 2010-08-12 | 2011-04-13 | 中冶成工上海五冶建设有限公司 | Foundation bolt positioner |
JP2012072648A (en) * | 2010-09-01 | 2012-04-12 | Marutaka Kogyo Inc | Installed foundation construction method |
Non-Patent Citations (1)
Title |
---|
严正庭等: "《混凝土结构实用构造手册》", 31 July 1997, 中国建筑工业出版社, article "第四节 用波纹螺旋套管的地脚螺栓预留孔工法", pages: 493-497 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105401591B (en) * | 2014-09-03 | 2017-11-28 | 五冶集团上海有限公司 | Pre-embedded bolt corrugated sleeve installation method |
CN105887916A (en) * | 2014-11-27 | 2016-08-24 | 华北冶建工程建设有限公司 | New method for construction after bolt embedment |
CN109386009A (en) * | 2017-08-04 | 2019-02-26 | 上海宝冶集团有限公司 | Equipment anchor bolt buries the construction tool and method of reserving hole |
CN113530056A (en) * | 2021-07-16 | 2021-10-22 | 中国二十二冶集团有限公司 | Method for pre-embedding corrugated pipe on top plate |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207194000U (en) | A kind of transmission line of electricity prefabricated tubular pile cushion cap anchor | |
CN106703306B (en) | Precast concrete parapet component and connection structure thereof | |
CN103669389A (en) | Corrugated pipe fixing method for positioning foundation bolt | |
CN103276895B (en) | Die supporting method of reversed-cone-shaped column cap die | |
CN210917458U (en) | City utility tunnel unilateral side mould frock subassembly | |
CN109208823B (en) | Quick-assembly built-in steel box type concrete filled steel tube column and production process thereof | |
CN110700319A (en) | Comprehensive pipe gallery is with unilateral formwork frock | |
CN105201204A (en) | Method and structure for preventing root rotting in pouring process of column legs of reinforced concrete columns | |
CN112302209B (en) | Steel and concrete shear wall mixed structure and manufacturing method thereof | |
CN104196023A (en) | Precast concrete tubular pile tip with mechanical connection device and using method of precast concrete tubular pile tip | |
CN205259618U (en) | Cast -in -place floor gauge control device of concrete | |
CN202925975U (en) | Steel funnel for coal blending bunker | |
CN113718793B (en) | Cover-excavation construction fender post structure and construction method | |
CN206000021U (en) | Attachment structure at concrete frame structure prefabricated post and beam slab node | |
CN211057855U (en) | Comprehensive pipe gallery is with unilateral formwork frock | |
CN104153386B (en) | Pile foundation support table periphery facade bed course tool-type punching block and construction method thereof | |
CN207331733U (en) | A kind of concrete column leg structure | |
CN107620314A (en) | The construction method and concrete column leg structure of a kind of concrete suspension column | |
CN210551995U (en) | Prefabricated post production mould | |
CN203004045U (en) | Hopper for concrete falling | |
CN202559746U (en) | Continuing device for upper-lower-layer shear wall during pouring | |
CN204098031U (en) | A kind of concrete precast pipe pile pile top with mechanical connecting device | |
CN205476442U (en) | A wall pouring mode structure is led to anti - L shape concrete | |
CN217711099U (en) | Prefabricated post structure convenient to high-efficient connection | |
CN201981785U (en) | Bracket pole for overall concrete pouring scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140326 |
|
RJ01 | Rejection of invention patent application after publication |