WO2012081653A1 - Method of installing a mounting base - Google Patents

Method of installing a mounting base Download PDF

Info

Publication number
WO2012081653A1
WO2012081653A1 PCT/JP2011/078997 JP2011078997W WO2012081653A1 WO 2012081653 A1 WO2012081653 A1 WO 2012081653A1 JP 2011078997 W JP2011078997 W JP 2011078997W WO 2012081653 A1 WO2012081653 A1 WO 2012081653A1
Authority
WO
WIPO (PCT)
Prior art keywords
metal
support bolt
concrete
metal plate
bolt
Prior art date
Application number
PCT/JP2011/078997
Other languages
French (fr)
Japanese (ja)
Inventor
一昌 高木
栄造 高木
Original Assignee
株式会社丸高工業
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社丸高工業 filed Critical 株式会社丸高工業
Publication of WO2012081653A1 publication Critical patent/WO2012081653A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Definitions

  • the present invention relates to an installation foundation construction method, and more specifically, to a new or existing concrete structure such as a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure.
  • the present invention relates to an installation foundation construction method for constructing an installation foundation used for installation.
  • Patent Document 1 discloses a solar cell panel installation structure.
  • a formwork is produced at a place where a solar cell panel is installed, and a foundation is formed and transported by placing and curing concrete in the formwork.
  • This is a structure in which the solar cell panel and its mount are assembled on the foundation.
  • the formwork since the formwork must be manufactured at the construction site, it takes time and effort to cure the concrete poured into the formwork, and in a short construction period. Cannot make a stationary structure.
  • a concrete or reinforced concrete foundation is manufactured in advance at a foundation parts manufacturing factory, and the foundation is used as a roof of a concrete structure. And transported to underground construction sites. After that, a thin cement layer is formed on the roof or underground slab installation site, the cement layer is used as an adhesive layer, the foundation is placed on top of it, and it is integrated with the slab. Prepare for. Since the solar cell panel mounting structure disclosed in Patent Document 1 does not need to produce a formwork at the construction site when forming the foundation for installing the solar cell panel, it saves that much labor, and at the construction site The construction work can be simplified, the time for curing the concrete can be omitted, and the construction period can be shortened accordingly.
  • the object of the present invention is to create a solid foundation for installing machinery and buildings on a new or existing concrete structure, reduce labor and cost required to install the foundation, and
  • the object is to provide an installation foundation construction method capable of shortening the construction period.
  • the premise of the present invention for solving the above-mentioned problem is an installation foundation construction method for constructing an installation foundation installed at a predetermined location of a new or existing concrete structure.
  • the installation foundation construction method includes a temporary mounting step of temporarily mounting a metal base having a metal pipe and a metal plate connected to the lower end of the metal pipe at a predetermined position of the concrete structure, An installation height adjustment step of adjusting the installation height from the top surface of the concrete structure of the temporarily installed metal base by adjusting the screwing position of the height adjustment bolt screwed to the plate to the metal plate; A bolt hole first drilling step for drilling a support bolt first insertion hole in the metal plate and a support bolt second insertion hole in the concrete structure in accordance with the position of the support bolt first insertion hole formed in the metal plate.
  • a frame material installation step for installing a frame material for closing a gap between the outer peripheral edge of the structure and the base between the outer peripheral edge of the metal base and the concrete structure, and the upper surface of the concrete structure and the metal plate
  • Installation foundation construction with a cement hardened material filling process that fills the space between the lower surface and cement hardened material, and a metal tube closing process that fixes the metal lid to the top of the metal tube and closes the top opening of the metal tube
  • the metal plate includes a first portion that extends radially inward of the metal tube and a second portion that extends radially outward of the metal tube.
  • the support bolt first insertion hole is drilled in the second portion of the plate, and in the bolt hole second drilling step, the support is supported on the concrete structure in accordance with the position of the support bolt first insertion hole formed in the second portion of the metal plate.
  • the bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is inserted into the second portion of the metal plate and the concrete structure through predetermined fixing means.
  • a frame material is installed between the outer peripheral edge of the second part of the bottom plate and the concrete structure to close the gap between the structure and the outer peripheral edge of the second part.
  • the concrete structure is formed of a concrete frame, a waterproof layer provided on the concrete frame, and a pressing concrete provided on the waterproof layer. , Removing the pressing concrete and waterproof layer from the concrete structure to expose the concrete frame, temporarily installing the metal base on the concrete frame, and in the bolt hole second drilling step, the support bolt formed on the second part of the metal plate According to the position of the first insertion hole, the support bolt second insertion hole is drilled in the concrete frame, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and through a predetermined fixing means. The support bolt is fixed to the second part of the metal plate and the concrete frame.
  • a concrete structure is formed of a concrete slab and a concrete beam, a waterproof layer provided on the slab and the beam, and a pressing concrete provided on the waterproof layer,
  • the pressing concrete and the waterproof layer are removed from the concrete structure to expose the slab and the beam, and the second part of the metal plate is located on the slab, and the first part of the metal tube and the metal plate.
  • the metal base is temporarily installed so that and are positioned on the beam, and in the bolt hole second drilling step, it is supported by the slab according to the position of the first support bolt insertion hole formed in the second part of the metal plate.
  • the bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is inserted into the second part of the metal plate through a predetermined fixing means. And it is fixed to the slab.
  • the support bolt first insertion hole is drilled in the first portion of the metal plate, and in the bolt hole second drilling step, it is formed in the first portion of the metal plate.
  • the support bolt second insertion hole is drilled in the concrete beam in accordance with the position of the first support bolt first insertion hole, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, The support bolt is fixed to the first and second portions of the metal plate, the slab and the beam via the fixing means.
  • the installation foundation construction method includes a waterproof layer installation step of installing a waterproof layer covering the metal base.
  • the waterproof layer installation step the waterproof layer extending outside the metal base is waterproofed to the concrete structure. Connect to the layer.
  • the second portion of the metal plate includes a first side plate that rises upward from the periphery thereof, and a second side plate that is positioned between the first side plates and rises upward from the second portion.
  • the cement hardened material filling step the cement hardened material is filled in a space surrounded by the second portion of the metal plate and the first side plate.
  • the second portion of the metal plate includes a first side plate that rises upward from the periphery thereof, and a second side plate that is positioned between the first side plates and rises upward from the second portion.
  • the connected foundation construction method includes a space closing step of fixing the top plate to the top of the space surrounded by the second portion of the metal plate and the first side plate to close the space.
  • a filling hole for filling a cement hardened material into a space is formed in a predetermined portion of the metal plate, and in the cement hardened material filling process, the cement hardened material is filled into the space from the filling hole. To do.
  • a confirmation hole for confirming the cement hardened material filled in the space is formed in a predetermined portion of the metal plate, and in the cement hardened material filling step, cement hardening in the space from the confirmation hole. While confirming the filling state of the object, the cement hardened material is filled into the space.
  • a supporting bolt fixing step for installing a frame material for closing a gap between the outer periphery of the metal base and the concrete structure and the outer periphery of the base, and a concrete
  • the foundation is made from a cement hardened material filling process that fills the space between the upper surface of the structure and the lower surface of the metal plate with a cement hardened material filling process and a metal tube closing process that fixes a metal lid to the top of the metal pipe, Since each basic part made into a general-purpose part is assembled as a unit system by each process, the construction work can be manualized and the construction work can be simplified.
  • the installation foundation construction method does not need to produce a formwork at the construction site when forming the foundation, and it is not necessary to cure the hardened cement material to create the foundation at the foundation manufacturing factory or construction site. Fixing bolts to a lightweight metal base metal plate and concrete structure, filling the space with hardened cement, and building a foundation simply by fixing a metal lid to the metal base, making a formwork In addition, the labor, cost, and time required for curing the cured cement can be saved, the construction work can be simplified, and the construction period can be greatly shortened.
  • the support bolt is fixed to the metal plate and the concrete structure, the space is filled with the hardened concrete, and after the curing period of the hardened cement has passed, the support bolt is integrated with the hardened cement.
  • the installation foundation can be firmly installed on the concrete structure, but also solar panels, antennas, water storage tanks, septic tanks, air conditioners and other machinery and equipment, It is possible to create a foundation that can be firmly equipped with buildings such as steel towers and steel structures.
  • the installation foundation construction method the space between the upper surface of the concrete structure and the lower surface of the metal plate is filled with hardened cement, and the load applied to the foundation when a machine or building is installed on the foundation is supported by the bolts. Since the load is applied to the hardened cement and the hardened cement, it will not inadvertently incline due to the load applied to the foundation, or the foundation will not collapse. Can be made.
  • the installation foundation construction method can freely adjust the installation height of the metal foundation from the top surface of the concrete structure during construction of the foundation, and can immediately respond to a request for changing the height dimension of the foundation. In the installation foundation construction method, when installing a plurality of them, the height dimensions of the foundations can be easily adjusted, and the height dimensions of the foundations can be made uniform.
  • the metal plate includes a first portion and a second portion, and in the bolt hole first drilling step, the support bolt first insertion hole is drilled in the second portion of the metal plate, and in the bolt hole second drilling step, the metal plate
  • the support bolt second insertion hole is drilled in the concrete structure in accordance with the position of the support bolt first insertion hole formed in the second portion, and the support bolt is inserted into the support bolt first and second insertion holes in the support bolt fixing step.
  • the installation foundation construction method of installing the cement is not necessary to produce the formwork at the construction site when constructing the foundation, but also to harden the cement to make the foundation at the foundation parts manufacturing factory and construction site There is no need to cure, the support bolt is fixed to the second part of the lightweight metal base metal plate and the concrete structure, and the space is filled with hardened cement and the base is simply fixed to the metal base. Can save time, cost, and time for the production of formwork and curing of hardened cement, and can simplify the construction work and greatly reduce the construction period. can do.
  • the support bolt is fixed to the metal plate and the concrete structure, the space is filled with the hardened concrete, and after the curing period of the hardened cement has passed, the support bolt is integrated with the hardened cement.
  • the installation foundation can be firmly installed on the concrete structure, but also solar panels, antennas, water storage tanks, septic tanks, air conditioners and other machinery and equipment, It is possible to create a foundation that can be firmly equipped with buildings such as steel towers and steel structures.
  • the installation foundation construction method the space between the upper surface of the concrete structure and the lower surface of the metal plate is filled with hardened cement, and the load applied to the foundation when a machine or building is installed on the foundation is supported by the bolts. Since the load is applied to the hardened cement and the hardened cement, it will not inadvertently incline due to the load applied to the foundation, or the foundation will not collapse. Can be made.
  • the installation foundation construction method secures the area of the metal plate by extending the metal plate radially outward of the metal tube to form the second part, and supports the load applied to the foundation by the metal plate, instead of the metal tube Therefore, the weight of the metal tube can be reduced, and as a result, the weight of the foundation can be reduced.
  • the concrete and waterproof layer are removed from the concrete structure to expose the concrete frame, and the metal foundation is temporarily installed in the concrete frame.
  • the bolt hole second drilling process the second part of the metal plate
  • the support bolt second insertion hole is drilled in the concrete frame in accordance with the position of the formed support bolt first insertion hole, and the support bolt is inserted and fixed in the support bolt first and second insertion holes in the support bolt fixing step.
  • the installation foundation construction method of fixing the support bolt to the second part of the metal plate and the concrete frame through the means is to fix the support bolt to the second part of the metal plate of the lightweight metal base and the concrete frame, and to cement the space.
  • the foundation can be built simply by filling the hardened material and fixing the metal lid to the metal base.
  • the construction time of that amount can be greatly shortened.
  • the installation location of the installation foundation is a concrete frame with a waterproof layer with a waterproof function on the roof or underground of an existing concrete structure, the exposure after removing the waterproof layer of the installation location
  • the foundation can be installed in the frame, and the waterproof layer near the installation location can be repaired immediately after the foundation is installed (a new waterproof layer is applied), so that the foundation can be installed quickly and the foundation can be installed.
  • the time required can be greatly reduced.
  • the pressing concrete and the waterproof layer are removed from the concrete structure to expose the slab and the beam, and the second portion of the metal plate is located on the slab, and the first of the metal tube and the metal plate
  • the metal base is temporarily installed so that the part is positioned on the beam, and in the bolt hole second drilling step, the slab is fitted to the position of the support bolt first insertion hole formed in the second part of the metal plate.
  • the support bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is fixed to the second portion of the metal plate and the slab through the fixing means.
  • the installation foundation construction method is to fix the support bolt to the second part of the metal plate of the lightweight metal base and the slab, fill the space with cement hardened material, and fix the metal lid to the metal base
  • the foundation can be built in, and it is possible to save the labor, cost, and time required for the production of the formwork and the curing of the hardened cement, and the construction work can be simplified. Can be shortened.
  • the installation foundation Even if the installation location of the installation foundation is a slab or beam with a waterproof layer with a waterproof function on the rooftop or basement of an existing concrete structure, the installation foundation after removing the waterproof layer at the installation location
  • the foundation can be installed on exposed slabs and beams, and immediately after the foundation is installed, the waterproof layer near the installation location can be repaired (a new waterproof layer is applied), so the foundation can be installed quickly and the foundation The time required for the installation of can be greatly reduced.
  • the support bolt first insertion hole is drilled in the first portion of the metal plate, and in the bolt hole second drilling step, the support bolt first insertion hole formed in the first portion of the metal plate.
  • the support bolt second insertion hole is drilled in the concrete beam according to the position, and in the support bolt fixing step, the support bolt is inserted into the first and second insertion holes of the support bolt, and the support bolt is inserted into the metal plate through the fixing means.
  • the fixed foundation construction method to fix the first and second parts to the slab and the beam is to fix the support bolt to the second part of the light metal base metal plate, the slab and the beam, and fill the space with cement hardened material
  • it is possible to build a foundation simply by fixing a metal lid to a metal base saving labor, cost, and time required for mold production and curing of hardened cement. Can be simplified, the construction time of that amount can be greatly shortened.
  • the installation foundation Even if the installation location of the installation foundation is a slab or beam with a waterproof layer with a waterproof function on the rooftop or basement of an existing concrete structure, the installation foundation after removing the waterproof layer at the installation location
  • the foundation can be installed on exposed slabs and beams, and immediately after the foundation is installed, the waterproof layer near the installation location can be repaired (a new waterproof layer is applied), so the foundation can be installed quickly and the foundation The time required for the installation of can be greatly reduced.
  • the installation foundation construction method that connects the waterproof layer that extends outside the metal base to the waterproof layer of the concrete structure is a waterproof that covers the metal base.
  • the first side plate and the second side plate are connected to the second part of the metal plate, and in the cement hardened product filling step, the space surrounded by the second part of the metal plate and the first side plate is filled with the hardened cement product.
  • the installation foundation construction method fills the space with cement hardened material, so that the support bolts are not exposed in the space and can prevent corrosion of the support bolts and loosening of the fixing bolts. It is possible to prevent the fixation with the plate from being released, and it is possible to prevent the loss of the function as the foundation due to the loosening of the bolt.
  • the mounting foundation construction method including the above prevents the deformation and breakage of the metal plate by the side plates and creates a mounting foundation having excellent strength. be able to.
  • the installation foundation construction method prevents the support bolts from being exposed to the outside and prevents water from entering the space. Therefore, the bolts can be prevented from corroding. Can be prevented from being released. Since the installation foundation only covers the top opening of the space with the top plate, compared with the case where the space is filled with hardened cement, the period of curing the hardened cement can be shortened, and the construction period is reduced accordingly. can do.
  • the installation foundation construction method for filling the cement hardened material into the space from the filling hole formed in the predetermined place of the metal tube is possible to fill the space with the cement hardened material using the filling hole. Therefore, the hardened cement can be reliably filled in the space.
  • the load applied to the foundation when a mechanical device or building is installed on the foundation can be shared between the support bolt and the hardened cemented product, which is inadvertent due to the load applied to the foundation. It is possible to create a foundation that can reliably support mechanical devices and buildings without tilting to the ground or collapsing the foundation.
  • the installation foundation construction method for filling the space with the cement hardened material while confirming the filling state of the cement hardened material in the space from the confirmation hole formed in a predetermined position of the bottom wall of the metal tube, The filling state of the cement hardened material filled in the space can be confirmed using the confirmation hole, and the cement hardened product will not be filled in the space, and the cement hardened material should be filled evenly throughout the space. Can do.
  • the load applied to the foundation when a mechanical device or building is installed on the foundation can be shared between the support bolt and the hardened cemented product, which is inadvertent due to the load applied to the foundation. It is possible to create a foundation that can reliably support mechanical devices and buildings without tilting to the ground or collapsing the foundation.
  • FIG. 2 is a sectional view taken along line AA in FIG. 1.
  • the figure which shows the construction procedure of the installation foundation which continues from FIG. The top view of a metal foundation.
  • the figure which shows the construction procedure of the installation foundation which continues from FIG. The figure which shows the construction procedure of the installation foundation which continues from FIG.
  • FIG. 11 is a sectional view taken along line BB in FIG. 10.
  • FIG. 2 is a sectional view taken along line AA in FIG. 1.
  • the top view of a metal foundation The side view of a metal foundation.
  • the figure which shows an example of the construction procedure of the installation foundation of FIG. The figure which shows the construction procedure of the installation foundation which continues from FIG.
  • the figure which shows the construction procedure of the installation foundation which continues from FIG. The figure which shows the construction procedure of the installation foundation which continues from FIG.
  • FIG. 1 is a perspective view of the installation foundation 10A shown as an example.
  • one installation foundation 10 ⁇ / b> A installed on the concrete structure 11 is illustrated, but the number of foundations 10 ⁇ / b> A is not limited to that illustrated, and generally two or more foundations 10 ⁇ / b> A are provided. It is installed in the concrete structure 11.
  • FIG. 2 is a top view of the mounting base 10A
  • FIG. 3 is a cross-sectional view taken along line AA in FIG.
  • FIG. 4 is a diagram showing an example of a construction procedure for the installation foundation 10A
  • FIG. 5 is a diagram showing a construction procedure for the installation foundation 10A continued from FIG.
  • FIG. 6 is a top view of the metal base 16
  • FIG. 7 is a side view of the metal base 16.
  • the vertical direction is indicated by an arrow X1
  • the horizontal direction is indicated by an arrow X2
  • the front-back direction is indicated by an arrow X3.
  • the concrete structure 11 is shown as a cross section, and each part of the foundation 10A excluding a part is shown as a cross section.
  • the installation foundation 10A is installed on a predetermined installation location on the rooftop or underground of a new or existing concrete structure 11 (any structure including a building).
  • the installation location is where the roof and underground slabs and beams intersect.
  • slab means “floor slab”, but in this embodiment, it is used to include not only the underground floor of the concrete structure 11 but also the roof on the roof.
  • the concrete structure 11 on which the foundation 10 ⁇ / b> A is installed includes a concrete slab 12 and a concrete beam 13, a waterproof layer 14 provided on the slab 12 and the beam 13, and a facility on the waterproof layer 14. It is formed from the holding concrete 15.
  • the waterproof layer 14 and the pressing concrete 15 do not exist, and the concrete structure 11 may be formed only from the slab 12 or the beam 13.
  • the slab 12 and the beam 13 have a plurality of reinforcing bars embedded therein.
  • the installation foundation 10A is installed on the concrete slab 12 and the concrete beam 13 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11.
  • a metal base 16 and a metal lid 17 a plurality of height adjusting bolts 18, a plurality of support bolts 19, a mortar 20 (hardened cement), a waterproof layer 21, and a molding material 22 (frame material)
  • the installation base 10A is made.
  • the installation foundation construction method will be described below, taking the case where the installation foundation 10A is installed on the roof of the concrete structure 11 as an example.
  • the installation location of the foundation 10A on the roof of the concrete structure 11 is positioned, and the installation location is marked.
  • Layer 14 is removed and slab 12 and beam 13 are exposed.
  • the concrete structure 11 of illustration is formed from the concrete slab 12, the concrete beam 13, the waterproof layer 14, and the pressing concrete 15, the concrete structure 11 is not limited to that of illustration, and is used now.
  • This installation foundation 10A can be applied to all the concrete structures having other configurations. For example, in the case of a concrete structure in which a synthetic resin is further applied to a concrete slab and a concrete beam to form a resin film, at the foundation installation location, the resin film, presser concrete and waterproof layer are removed from the concrete structure, and the slab is removed. And expose the beam.
  • a drilled portion at a position where the reinforcing bolt insertion hole 39 (bolt hole) avoids the reinforcing bars is marked on the second portion 31 of the metal plate 24.
  • a support bolt insertion hole 39 is drilled at the drilled portion of the second portion 31 of the metal plate 24 using a drill (bolt hole first drilling step).
  • the metal base 16 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site and then transported to the construction site.
  • the metal base 16 is disposed on the concrete slab 12 and the concrete beam 13 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11.
  • the metal base 16 is formed of a hollow cylindrical metal tube 23 and a metal plate 24 having a substantially rectangular planar shape.
  • the metal base 16 is manufactured by welding a metal tube 23 to the upper surface of the metal plate 24.
  • the metal tube 23 and the metal plate 24 are made of metal such as iron, aluminum, and alloy.
  • a metal tube 23 (including a first portion 30 described later on the metal plate 24) that forms the metal base 16 is disposed immediately above the concrete beam 13, and a second portion 31 described later on the metal plate 24 is disposed on the concrete slab 12. It is placed immediately above.
  • the metal base 16 is lighter than the reinforced concrete foundation because the concrete is omitted. Therefore, by using the metal base 16, the weight of the foundation 10A can be significantly reduced.
  • the metal tube 23 has each side plate 25 having a substantially rectangular shape, and its cross section is formed into a substantially rectangular shape.
  • the metal tube 23 is disposed on the upper surface of the central portion of the metal plate 24, and the lower end edge thereof is joined (fused) to the upper surface of the metal plate 24 by welding.
  • a hollow space 26 is defined by the side walls 25 in the metal tube 23, and a top opening 27 surrounded by the upper edge of the side plates 25 is formed at the top of the metal tube 23.
  • a plurality of fixing bolt screw holes 29 for screwing the lid fixing bolts 28 are formed on the top of the metal tube 23.
  • a female screw (not shown) into which the lid fixing bolt 28 is screwed is formed in the fixing bolt screw hole 29.
  • the metal plate 24 includes a first portion 30 extending radially inward (laterally inside the metal tube 23) from the lower end edge of the metal tube 23, and radially outward (laterally of the metal tube 23) from the lower end edge of the metal tube 23. And a second portion 31 extending outward in the direction).
  • a plurality of adjustment bolt screw holes 32 into which the height adjustment bolts 18 are screwed are formed in the first portion 30 (see FIG. 6).
  • a female screw (not shown) into which the height adjusting bolt 18 is screwed is formed in the adjusting bolt screw hole 32.
  • the first portion 30 is provided with a plurality of reinforcing plates 35 extending in the horizontal direction and the vertical direction.
  • the reinforcing plates 35 are joined (fused) to the inner surface of the metal tube 23 and the upper surface of the metal plate 24 by welding.
  • the reinforcing plate 35 functions as a reinforcing material that increases the strength of the metal tube 23 and the metal plate 24.
  • the second portion 31 of the metal plate 24 has both end edges (periphery) extending in the lateral direction and both side edges (periphery) extending in the front-rear direction.
  • a rectangular first side plate 36 erected upward from the end edge along both end edges thereof is joined (fused) to the second portion 31 by welding, and a rectangular erected upward from the side edge along both side edges thereof.
  • the first side plate 36 is joined (fused) by welding.
  • the first side plates 36 connected to the edge of the second portion 31 (including the first portion 30) extend in the lateral direction in parallel with each other.
  • the first side plates 36 connected to the side edges of the second portion 31 extend in the front-rear direction in parallel with each other.
  • the rectangular second side plate 37 located between the first side plates 36 and rising upward from the second portion 31 is joined (fused) to the second portion 31 of the metal plate 24 by welding.
  • the second side plates 37 extend in the front-rear direction in parallel with each other.
  • the first and second side plates 36 and 37 function as reinforcing plates that increase the strength of the second portion 31 of the metal plate 24.
  • a space 38 surrounded by the second portion 31 of the metal plate 24 and the first side plate 36 is defined in the metal base 16.
  • the space 38 is filled with mortar 20 (cured cement), and the mortar 20 is cured in the space 38 (see FIG. 3).
  • a metal top plate may be disposed on the upper surface of the second portion 31 of the metal plate 24, and the top plate may block the opening of the space 38. In this case, the space 38 is not filled with the mortar 20, and the top plate is joined (fused) to the upper end edges of the first and second side plates 36 and 37 by welding.
  • a plurality of support bolt insertion holes 39 (support bolt first insertion holes) through which the support bolts 19 are inserted are formed in the second portion 31 of the metal plate 24 (see FIG. 6).
  • the support bolt insertion hole 39 is made by a drill and penetrates the second portion 31 of the metal plate 24 in the vertical direction.
  • the support bolt insertion holes 39 are arranged at predetermined intervals in the second portion 31 in the lateral direction and the front-rear direction. In FIG. 6, eight support bolt insertion holes 39 are formed.
  • the number of the insertion holes 39 is not particularly limited, and the number is determined by structural calculation (strength calculation) performed before the foundation 10A is installed. .
  • the first portion 30 of the metal tube 23 and the metal plate 24 is positioned immediately above the concrete beam 13, and the second portion 31 of the metal plate 24 is the concrete slab 12.
  • the bolt head 45 of the height adjusting bolt 18 abuts against the upper surface of the concrete beam 13.
  • the height adjusting bolt 18 is a hexagonal bolt formed from a shaft 44 on which a male screw (not shown) is made and a bolt head 45. The shaft 44 of the height adjusting bolt 18 is screwed in advance into an adjusting bolt screwing hole 32 formed in the first portion 30 of the metal plate 24.
  • the shaft 44 of the bolt 18 gradually advances downward from the bolt screwing hole 32 and extends downward from the lower surface of the first portion 30. 45 abuts on the upper surface of the concrete beam 13. Thereby, the metal base 16 can be spaced apart from the upper surface of the concrete slab 12 or the concrete beam 13 by a predetermined dimension. Conversely, when the height adjusting bolt 18 is rotated clockwise, the shaft 44 of the bolt 18 gradually advances upward from the bolt screw hole 32 and extends upward from the lower surface of the first portion 30. Thereby, the metal base 16 can be brought close to the upper surfaces of the concrete slab 12 and the concrete beam 13.
  • the metal plate 24 of the metal base 16 is separated upward from the upper surface of the concrete slab 12 or the concrete beam 13, and the upper surface of the slab 12 or the beam 13 and the metal plate are separated.
  • a space 46 having a predetermined height is formed between the lower surface of 24.
  • the adjusting bolt 18 is rotated clockwise or counterclockwise in the adjusting bolt screwing hole 32, and the distance from the upper surface of the concrete slab 12 or the concrete beam 13 of the metal base 16 is adjusted. Adjust.
  • the height dimension of the space 46 can be adjusted by adjusting the screwing position of the height adjusting bolts 18 to the first portion 30 of the metal plate 24 of the metal base 16, and the concrete slab 12 and the concrete beam 13 can be adjusted.
  • the height dimension of the metal base 16 from the upper surface can be adjusted up to the length of the bolt 18.
  • the height dimension of the metal base 16 can be freely changed during the construction of the installation foundation 10A by using the height adjusting bolt 18, and immediately the change of the height dimension of the foundation 10A is requested. Can respond.
  • the height dimensions of the foundations 10A when installing a plurality of installation foundations 10A, the height dimensions of the foundations 10A can be easily adjusted, and the height dimensions of the foundations 10A can be made uniform.
  • the support bolt insertion hole 40 is drilled in the drilled location marked using a drill (bolt hole second drilling step).
  • the support bolt insertion hole 40 penetrates the concrete slab 12 in the vertical direction.
  • the support bolt insertion hole 40 coincides with the position of the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete slab 12 or the concrete beam 13.
  • These support bolt insertion holes 40 are arranged in the concrete slab 12 at predetermined intervals in the lateral direction and the front-rear direction.
  • FIG. 8 is a diagram showing a construction procedure of the installation foundation 10A continuing from FIG. 5
  • FIG. 9 is a diagram showing a construction procedure of the installation foundation 10A continuing from FIG.
  • the support bolts 19 are made of steel and are standardized general-purpose products having the same length and diameter, and a plurality of them are manufactured at a base part manufacturing factory other than the construction site and then transported to the construction site. .
  • the support bolt 19 has a first fixed end portion 47 and a second fixed end portion 48, and an intermediate portion 49 extending between the first and second fixed end portions 47 and 48.
  • a hexagonal double nut 50 (fixing means) is screwed onto a portion of the first fixed end portion 47 of the support bolt 19 that extends upward from the metal plate 24, and the second fixed end of the support bolt 19.
  • a hexagonal double nut 51 (fixing means) is screwed to the portion 48, and the support bolt 19 is fixed to the metal plate 24 and the concrete slab 12 (support bolt fixing step).
  • a mortar 29 cement hardening
  • mortar 20 is cured.
  • a metal top plate is disposed on the upper surface of the second portion 31 of the metal plate 24 instead of filling the mortar 20, and the space 38 is formed by the top plate.
  • the top opening is closed (space closing process). In this case, the space 38 is not filled with the mortar 20 and the top plate is joined (fused) to the upper end edges of the first and second side plates 36 and 37 by welding.
  • a triangular prism-shaped molding material 22 is placed at the intersection of the metal tube 23 and the metal plate 24, and the formation is completed.
  • the mold member 22 is fixed to the metal tube 23 and the metal plate 24 via an adhesive (not shown).
  • a triangular prism shaped molding material 22 is installed on the holding concrete 15 and the concrete slab 12, and the molding material 22 is fixed to the holding concrete 15 and the slab 12 with an adhesive (not shown) (frame material installation). Process).
  • the molding material 22 surrounds the entire outer peripheral edge of the metal tube 23.
  • the molding material 22 surrounds the entire outer peripheral edge of the metal plate 24, and the molding material 22 creates a gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24. Block it.
  • the waterproof layer 21 is formed on the outer side of each side plate 25 of the metal tube 23 and the outer side of the metal plate 24 (the upper surface of the mortar 20 filled with the space 38 or the upper surface of the top plate closing the space 38).
  • Waterproof layer installation process a plurality of thin asphalt sheets are fixed to the outside of each side plate 25 of the metal tube 23, the outside of the metal plate 24, and the outside of the molding material 22 to form the waterproof layer 21.
  • a portion (asphalt sheet fixed to the molding material 22) extending outward from the second portion 31 of the plate 24 is connected to the waterproof layer 14 of the concrete structure 11.
  • asphalt waterproofing is used to create an asphalt sheet layer by stacking multiple thin asphalt sheets.
  • the asphalt sheet is fixed to the side plate 25 of the metal tube 23, the mortar 20, the first and second side plates 36 and 37, and the molding material 22 by its adhesiveness.
  • PVC sheet waterproofing, rubber sheet waterproofing, urethane waterproofing, epoxy waterproofing, and FRP waterproofing can also be used as the waterproof layer 21.
  • the installation foundation construction method can prevent water from entering the metal foundation 16 by the waterproof layer 21 even when the installation foundation 10A is installed outdoors of the concrete structure 11, and the water enters the metal foundation 16. Corrosion and strength reduction of the base 16 can be prevented. In addition, it is possible to prevent water from entering the concrete slab 12 and the concrete beam 13, and to prevent deterioration of the slab 12, the beam 13, and the concrete structure 11 due to water entering.
  • the space 46 formed between the upper surface of the concrete slab 12 or the concrete beam 13 and the lower surface of the metal plate 24 is filled with mortar 20 (cement hardened material) (cement hardened material filling step).
  • cement hardened material filling step the mortar 20 is filled into the space 46 from the filling hole 33 while confirming the filling state of the mortar 20 in the space 46 from the confirmation hole 34.
  • the mortar 20 filled therein is cured, and the mortar 20 is joined to the upper surfaces of the concrete slab 12 and the concrete beam 13 and the lower surfaces of the first and second portions 30 and 31 of the metal plate 24.
  • the support bolt 19 is joined.
  • the hardened mortar 20 is a foundation when a building such as a solar panel, an antenna, a water tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure is mounted on the foundation 10A (on the metal lid 17).
  • the load applied to 10A is shared with the support bolt 19.
  • concrete can also be used as the hardened cement filling the space 46.
  • the space 46 can be filled with the mortar 20 by using the filling hole 33 after the support bolt 19 is fixed to the metal plate 24 or the concrete slab 12, so the space 46 is reliably filled with the mortar 20. can do. Since the installation foundation construction method can check the filling state of the mortar 20 filled in the space 46 using the confirmation hole 34, the mortar 20 is not filled in the space 46 and the mortar 20 is not filled. The entire space 46 can be filled evenly.
  • the metal lid 17 is immediately fitted into the top of the metal tube 23 to close the top opening 27 of the metal tube 23.
  • the metal lid 17 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a base part manufacturing factory other than the construction site and then transported to the construction site.
  • the metal lid 17 is made of a metal such as iron, aluminum, or alloy, and its planar shape is molded into a substantially rectangular shape.
  • a solar panel On the upper surface of the metal lid 17, although not shown in the figure, a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner or other mechanical equipment, or a fixture for installing a building such as a steel tower or steel structure is attached. It has been.
  • An angle member 41 (steel material) for fixing the lid 17 to the top of the metal tube 23 is joined (fused) by welding on the lower surface of the metal lid 17 and inside the periphery of the lid 17.
  • a draining angle material 42 (steel material) is joined (fused) to the lower surface of the metal lid 17 and the periphery of the lid 17 by welding.
  • a fixing bolt insertion hole (not shown) for inserting the lid fixing bolt 28 is made in the angle member 41, and a hexagon nut 43 is joined (fused) to the fixing bolt insertion hole by welding.
  • the lid fixing bolt 28 is screwed into the fixing bolt screwing holes 29 formed on the side plates 25 of the metal tube 23, and the angle of the metal lid 17 is The bolt 29 is inserted into the lid fixing bolt insertion hole of the material 41, and the bolt 29 is screwed to the hexagon nut 43 attached to the bolt insertion hole to fix the lid 17 to the top of the metal tube 25 (top closing step) ( FIG. 3 support).
  • the top opening 27 of the metal tube 24 is watertightly closed by the metal lid 17.
  • the molding material 22 becomes a bank which prevents the leakage of the mortar 20 before hardening, and the mortar 20 with which the space 46 was filled is a space
  • the top opening 27 can be closed with the metal lid 17 immediately after the mortar 20 is filled.
  • the mortar 20 filled in the space 46 is in an uncured state immediately after the metal lid 17 is fitted (fixed) to the top of the metal tube 25, and the lid 17 is fixed to the top of the tube 25.
  • the curing period for mortar 20 begins.
  • the curing period of the mortar 20 elapses, and the mortar 20 filled therein is cured, so that the upper surface of the concrete slab 12 (concrete casing 12) in the free end 47 of the support bolt 19 and the metal plate 24 (a portion of the free end 47 of the bolt 19 that is exposed downward from the lower surface of the plate 24) is integrated with the mortar 20 to form a reinforcing bar mortar.
  • the installation base 10A shown in FIGS. 1 to 3 is completed.
  • the top opening 27 of the metal tube 23 can be immediately closed with the metal lid 17 without waiting for the curing period of the mortar 20, and the foundation 10A can be completed.
  • the construction period can be shortened by the curing period of the mortar 20 filled in the space 46, and a plurality of foundations 10A can be constructed in parallel without waiting for the curing period.
  • a metal top plate is disposed on the upper surface of the second portion 31 of the metal plate 24 and the top opening of the space 38 is blocked by the top plate, the mortar 20 is cured as compared with the case where the space 38 is filled with the mortar 20.
  • the construction period can be shortened, and the construction period can be shortened accordingly.
  • the installation foundation construction method includes a base temporary installation process in which the metal base 16 is temporarily installed at a predetermined installation location of the concrete slab 12 and the concrete beam 13, and the temporary installation of the metal base 16 from the top surface of the slab 12 and the beam 13.
  • Bolt hole second drilling step of drilling the support bolt insertion hole 40 in the concrete slab 12 in accordance with the position of 39, the support bolt 19 is inserted into the support bolt insertion holes 39, 40, and the hexagonal double nuts 50, 51 are A support bolt fixing step for fixing the support bolt 19 to the second portion 31 of the metal plate 24 and the slab 12, and the outer peripheral edge of the metal base 16 and the concrete frame Mortar in the space 46 between the upper surface of the slab 12 and the beam 13 and the lower surface of the metal plate 24, and the frame material installation step of installing the frame material 22 that closes the gap between the frame and the outer peripheral edge of the base 16
  • the base 10A is made from a cement hardened material filling step for filling 20 and a metal tube closing step for fixing the metal lid 17 to the top of the metal tube 23. Since it is assembled, the construction work can be manualized and the construction work can be simplified.
  • the installation foundation construction method does not need to produce a formwork at the construction site when forming the installation foundation 10A, and it is not necessary to cure the mortar to make the foundation 10A at the foundation manufacturing factory or construction site.
  • the support bolt 19 is fixed to the second portion 31 of the metal plate 24 of the lightweight metal base 16 and the concrete slab 12, and immediately after the space 46 is filled with the mortar 20, the metal lid 17 is simply fixed to the metal tube 23.
  • the foundation can be constructed, and the labor, cost, and time required for mold production and mortar curing can be saved, and the construction work can be simplified and the construction period can be greatly shortened. be able to.
  • the support bolt 19 is fixed to the second portion 31 of the metal plate 24 and the concrete slab 12 and the space 46 is filled with the mortar 20, so that the installation foundation 10A is firmly installed in the concrete structure 11.
  • a foundation 10A that can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air conditioners, and buildings such as steel towers and steel structures.
  • the mortar 20 is filled in the space 46 between the upper surface of the concrete slab 12 or the concrete beam 13 and the lower surface of the metal plate 24, and the foundation is provided with mechanical equipment or a building on the foundation 10A.
  • a base 10A that can be supported on the base can be made.
  • the installation location of the installation foundation 10A is the concrete slab 12 or the concrete beam 13 having the waterproof layer 14 having a waterproof function on the roof or underground of the existing concrete structure 11, the installation location of the installation foundation 10A
  • the foundation 10A can be installed on the exposed slab 12 or beam 13 after the waterproof layer 14 is removed, and the waterproof layer near the installation location can be repaired (a new waterproof layer 21 is applied) immediately after the foundation 10A is installed. Therefore, the foundation 10A can be quickly installed, and the time required for the installation of the foundation 10A can be greatly reduced.
  • FIG. 10 is a perspective view of an installation base 10B shown as another example, and FIG. 11 is a top view of the installation base 10B.
  • FIG. 12 is a cross-sectional view taken along the line BB of FIG. 10
  • FIG. 13 is a diagram illustrating an example of a construction procedure for the installation base 10B.
  • FIG. 14 is a diagram showing a construction procedure of the mounting base 10B continued from FIG. 13, and
  • FIG. 15 is a top view of the metal base 16.
  • FIG. 16 is a side view of the metal base 16.
  • the vertical direction is indicated by an arrow X1
  • the horizontal direction is indicated by an arrow X2
  • the front-rear direction is indicated by an arrow X3.
  • the concrete structure 11 is shown as a cross section, and each part of the foundation 10B excluding a part is shown as a cross section.
  • FIG. 1 is different from that of FIG. 1 in that a plurality of support bolt insertion holes 52 and 53 for inserting support bolts 19 (anchor bolts) into the first portion 30 of the metal plate 24 and the concrete beam 13 are formed.
  • the point that the support bolt 19 is inserted into the support bolt insertion holes 52 and 53, and the support bolt 19 that is inserted into the support bolt insertion holes 52 and 53 is metal through the hexagonal double nuts 50 and 51 (fixing means).
  • the first portion 30 of the plate 24 is fixed to the concrete beam 13.
  • the other structure of this foundation 10B is the same as that of the foundation 10A of FIG. 1, while attaching
  • the installation foundation construction method will be described as follows, taking the case where the installation foundation 10B is installed on the roof of the concrete structure 11 as an example.
  • the installation foundation 10B is installed on the concrete slab 12 and the concrete beam 13 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11 as in FIG.
  • the foundation 10B is made by assembling the foundation components in a predetermined procedure.
  • the support bolt insertion hole 39 (bolt hole) is not made in the second portion 31 of the metal plate 24 described later, and the support bolt insertion is made in the second portion 31 at the construction site. Hole 39 is drilled. Further, a plurality of adjustment bolt screw holes 32 are formed in the first part 30 of the metal plate 24 in advance in a basic part manufacturing factory, and the height adjustment bolt 18 is screwed into the bolt screw holes 32. Yes.
  • each basic part metal base 16, metal lid 17, height adjustment bolt 18, support bolt 19, waterproof layer 21, molding material 22
  • a general-purpose part manufactured at a base part manufacturing factory
  • the installation location of the foundation 10B on the roof of the concrete structure 11 is positioned, and the installation location is marked.
  • the pressing concrete 15 and the waterproof layer 14 are removed from the concrete structure 11, and the slab 12 and the beam 13 are exposed (in FIG. 6).
  • a drilled portion at a position where the reinforcing bolt insertion hole 39 (bolt hole) avoids the reinforcing bars is marked on the second portion 31 of the metal plate 24.
  • a support bolt insertion hole 39 is drilled at the drilled portion of the second portion 31 of the metal plate 24 using a drill (bolt hole first drilling step).
  • the metal base 16 is formed of a metal tube 23 and a metal plate 24.
  • the first portion 30 of the metal tube 23 and the metal plate 24 is disposed immediately above the concrete beam 13, and the second portion 31 of the metal plate 24 is disposed immediately above the concrete slab 12.
  • the metal tube 23 is the same as that of the foundation 10A of FIG.
  • the metal base 16 is light as much as the concrete is omitted, and by using the base 16, the weight of the foundation 10B can be significantly reduced.
  • the metal plate 24 has a first portion 30 extending radially inward from the lower end edge of the metal tube 23 and a second portion 31 extending radially outward from the lower end edge of the metal tube 23.
  • the first portion 30 is formed with a plurality of adjustment bolt screw holes 32 into which the height adjustment bolts 18 are screwed (see FIG. 13).
  • An elliptical filling hole 33 for filling the mortar 20 is formed at the center of the first part 30, and confirmation holes 34 for checking the filling state of the mortar 20 are formed at the four corners of the first part 30. (See FIG. 15).
  • the first portion 30 is provided with a plurality of reinforcing plates 35 extending in the horizontal direction and the vertical direction.
  • the second portion 31 of the metal plate 24 is provided with a first side plate 36 that rises upward from the end edge along both end edges, and the first side plate 36 that rises upward from the side edge along both side edges. is set up. Further, a second side plate 37 that is located between the first side plates 36 and stands upward from the second portion 31 is provided. A space 38 surrounded by the second portion 31 and the first side plate 36 of the metal plate 24 is filled with mortar 20 (hardened cement), and the mortar 20 is hardened in the space 38 (see FIG. 12). . As with the base 10 ⁇ / b> A of FIG. 1, a metal top plate may be disposed on the upper surface of the second portion 31 of the metal plate 24, and the top plate may block the opening of the space 38.
  • a plurality of support bolt insertion holes 52 (support bolt first insertion holes) through which the support bolts 19 are inserted are formed in the first portion 30 of the metal plate 24.
  • the support bolt insertion hole 52 is made by a drill and penetrates the first portion 30 of the metal plate 24 in the vertical direction.
  • the support bolt insertion holes 52 are arranged in the first portion 30 in the lateral direction and the front-rear direction at a predetermined interval. In FIG. 13, four support bolt insertion holes 52 are formed, but the number of insertion holes 52 is not particularly limited, and the number is determined by structural calculation (strength calculation) performed before the foundation 10B is installed. .
  • a plurality of support bolt insertion holes 39 (support bolt first insertion holes) through which the support bolts 19 are inserted are formed in the second portion 31 of the metal plate 24. These support bolt insertion holes 39 are arranged in the second portion 31 at predetermined intervals in the lateral direction and the front-rear direction.
  • the first portion 30 of the metal tube 23 and the metal plate 24 is positioned immediately above the concrete beam 13, and the second portion 31 of the metal plate 24 is the concrete slab 12.
  • the bolt head 45 of the height adjusting bolt 18 abuts against the upper surface of the concrete beam 13.
  • the installation foundation construction method can use the height adjustment bolt 18 to freely change the height of the metal base 16 during construction of the foundation 10B, and immediately respond to the request for changing the height of the foundation 10B. can do.
  • the installation foundation construction method can easily adjust the height dimensions of the foundations 10B when a plurality of them are installed, and can make the height dimensions of the foundations 10B uniform.
  • the metal base 16 After adjusting the height dimension of the metal base 16, drilling locations of the support bolt insertion holes 40 and 53 (bolt holes) of the concrete slab 12 and the concrete beam 13 in accordance with the positions of the support bolt insertion holes 39 and 52 of the metal plate 24. Mark on. Next, the metal base 16 is temporarily retracted from the temporary installation location (installation location), and then the support bolt insertion holes 40 and 53 are drilled in the drilled locations marked using a drill (bolt hole second drilling step). ).
  • the support bolt insertion hole 40 penetrates the concrete slab 12 in the vertical direction.
  • the support bolt insertion hole 40 coincides with the position of the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete slab 12 or the concrete beam 13.
  • These support bolt insertion holes 40 are arranged in the concrete slab 12 at predetermined intervals in the lateral direction and the front-rear direction.
  • the support bolt insertion hole 53 penetrates the concrete beam 13 in the vertical direction.
  • the support bolt insertion hole 53 coincides with the position of the support bolt insertion hole 52 formed in the first portion 30 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete slab 12 or the concrete beam 13.
  • These support bolt insertion holes 53 are arranged at predetermined intervals in the lateral direction and the front-rear direction in the concrete beam 13.
  • the metal base 16 is temporarily installed again at the installation location, and as shown in FIG.
  • the support bolt 19 is inserted into the support bolt insertion holes 39 and 52 formed in the first and second portions 30 and 31, and the support bolt 19 is inserted into the support bolt insertion holes 40 and 53 formed in the slab 12 and the beam 13. Insert.
  • the first fixed end 47 extends upward from the upper surfaces of the concrete slab 12 and the concrete beam 13, and the second fixed end 48 is the slab 12.
  • the intermediate portion 49 is positioned in the support bolt insertion holes 40 and 53 of the slab 12 and the beam 13.
  • a hexagonal double nut 50 (fixing means) is screwed onto a portion of the first fixed end portion 47 of the support bolt 19 that extends upward from the metal plate 24, and the second fixed end of the support bolt 19.
  • a hexagonal double nut 51 (fixing means) is screwed to the portion 48, and the support bolt 19 is fixed to the metal plate 24, the concrete slab 12, and the concrete beam 13 (support bolt fixing step).
  • FIG. 17 is a diagram showing a construction procedure of the installation foundation 10B continued from FIG.
  • the support bolt 19 is fixed to the metal plate 24, the concrete slab 12, and the concrete beam 13, the mortar is placed in the space 38 surrounded by the second portion 31 and the first side plate 36 of the metal plate 24 as shown in FIG. 29 is filled and the mortar 20 is cured.
  • a metal top plate may be disposed on the upper surface of the second portion 31 of the metal plate 24, and the top opening of the space 38 may be blocked by the top plate. (Space closing process).
  • a triangular prism-shaped molding material 22 is placed at the intersection of the metal tube 23 and the metal plate 24, and the formation is completed.
  • the mold member 22 is fixed to the metal tube 23 and the metal plate 24 via an adhesive (not shown).
  • a triangular prism shaped molding material 22 is installed on the holding concrete 15 and the concrete slab 12, and the molding material 22 is fixed to the holding concrete 15 and the slab 12 with an adhesive (not shown) (frame material installation). Process).
  • the molding material 22 surrounds the entire outer peripheral edge of the metal tube 23.
  • the molding material 22 surrounds the entire outer peripheral edge of the metal plate 24, and the molding material 22 creates a gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24. Block it.
  • the waterproof layer 21 is formed on the outer side of each side plate 25 of the metal tube 23 and the outer side of the metal plate 24 (the upper surface of the mortar 20 filled with the space 38 or the upper surface of the top plate closing the space 38).
  • Waterproof layer installation process a plurality of thin asphalt sheets are fixed to the outer side of each side plate 25 of the metal tube 23, the outer side of the metal plate 24, and the outer side of the molding material 22, as in the base 10 ⁇ / b> A of FIG. 1. And a portion (asphalt sheet fixed to the molding material 22) extending outward from the second portion 31 of the metal plate 24 of the waterproof layer 21 is connected to the waterproof layer 14 of the concrete structure 11.
  • the installation foundation construction method can prevent water from entering the metal foundation 16 by the waterproof layer 21 even when the installation foundation 10 ⁇ / b> B is installed outdoors of the concrete structure 11, and the water enters the metal foundation 16. Corrosion and strength reduction of the base 16 can be prevented. In addition, it is possible to prevent water from entering the concrete slab 12 and the concrete beam 13, and to prevent deterioration of the slab 12, the beam 13, and the concrete structure 11 due to water entering.
  • the space 46 is filled with mortar 20 (cement hardened material filling step).
  • cement hardened material filling step the mortar 20 is filled into the space 46 from the filling hole 33 while confirming the filling state of the mortar 20 in the space 46 from the confirmation hole 34.
  • the mortar 20 filled therein is cured, and the mortar 20 is joined to the upper surfaces of the concrete slab 12 and the concrete beam 13 and the lower surfaces of the first and second portions 30 and 31 of the metal plate 24.
  • the support bolt 19 is joined.
  • the hardened mortar 20 is a foundation when a building such as a solar panel, an antenna, a water tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure is mounted on the foundation 10A (on the metal lid 17).
  • the load applied to 10A is shared with the support bolt 19.
  • the space 46 can be filled with the mortar 20 by using the filling hole 33 after the support bolt 19 is fixed to the metal plate 24 or the concrete slab 12, so the space 46 is reliably filled with the mortar 20. can do. Since the installation foundation construction method can check the filling state of the mortar 20 filled in the space 46 using the confirmation hole 34, the mortar 20 is not filled in the space 46 and the mortar 20 is not filled. The entire space 46 can be filled evenly.
  • the metal lid 17 is immediately fitted into the top of the metal tube 23 to close the top opening 27 of the metal tube 23.
  • the lid fixing bolt 28 is screwed into the fixing bolt screwing holes 29 formed on the side plates 25 of the metal tube 23, and the angle of the metal lid 17 is The bolt 29 is inserted into the lid fixing bolt insertion hole of the material 41, and the bolt 29 is screwed to the hexagon nut 43 attached to the bolt insertion hole to fix the lid 17 to the top of the metal tube 25 (top closing step) ( FIG. 12 is used).
  • the top opening 27 of the metal tube 24 is watertightly closed by the metal lid 17.
  • the molding material 22 becomes a bank which prevents the leakage of the mortar 20 before hardening, and the mortar 20 with which the space 46 was filled is a space
  • the top opening 27 can be closed with the metal lid 17 immediately after the mortar 20 is filled.
  • the mortar 20 filled in the space 46 is in an uncured state immediately after the metal lid 17 is fitted (fixed) to the top of the metal tube 25, and the lid 17 is fixed to the top of the tube 25.
  • the curing period for mortar 20 begins.
  • the curing period of the mortar 20 elapses, and the mortar 20 filled therein is hardened, whereby the concrete slab 12 (concrete frame 12) and the concrete beam 13 ( A portion extending between the upper surface of the concrete housing 13) and the metal plate 24 (a portion of the free end portion 47 of the bolt 19 exposed downward from the lower surface of the plate 24) is integrated with the mortar 20 to form a reinforcing bar mortar.
  • the installation base 10B shown in FIGS. 10 to 12 is completed.
  • the top opening 27 of the metal tube 23 can be immediately closed with the metal lid 17 without waiting for the curing period of the mortar 20, and the foundation 10B can be completed.
  • the construction period can be shortened by the curing period of the mortar 20 filled in the space 46, and a plurality of foundations 10B can be constructed in parallel without waiting for the curing period.
  • a metal top plate is disposed on the upper surface of the second portion 31 of the metal plate 24 and the top opening of the space 38 is blocked by the top plate, the mortar 20 is cured as compared with the case where the space 38 is filled with the mortar 20.
  • the construction period can be shortened, and the construction period can be shortened accordingly.
  • the installation foundation construction method includes a base temporary installation process in which the metal base 16 is temporarily installed at a predetermined installation location of the concrete slab 12 and the concrete beam 13, and the temporary installation of the metal base 16 from the top surface of the slab 12 and the beam 13.
  • Installation height adjustment process for adjusting the height, bolt hole first drilling process for drilling support bolt first insertion holes 39, 52 in the metal plate 24, and first and second portions 30, 31 of the metal plate 24
  • the installation foundation construction method does not need to produce a formwork at the construction site when forming the installation foundation 10B, and it is not necessary to cure the mortar to make the foundation 10B at the foundation manufacturing factory or construction site.
  • the support bolt 19 is fixed to the first and second portions 30 and 31 of the metal plate 24 of the lightweight metal base 16, the concrete slab 12 and the concrete beam 13, and the space 46 is filled with the mortar 20, the metal tube 23 is provided. It is possible to construct a foundation simply by fixing the metal lid 17 to the base, and save labor, cost, and time required for mold production and mortar curing, and simplify construction work. The construction period of minutes can be greatly shortened.
  • the support bolt 19 is fixed to the first and second portions 30 and 31 of the metal plate 24, the concrete slab 12 and the concrete beam 13, and the mortar 20 is filled in the space 46.
  • a foundation 10B that can be firmly installed on the concrete structure 11 and can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air-conditioning equipment, and buildings such as steel towers and steel structures. Can be made.
  • the installation foundation construction method is a foundation in which a mortar 20 is filled in a space 46 between the upper surface of the concrete slab 12 or the concrete beam 13 and the lower surface of the metal plate 24, and mechanical equipment or a building is provided on the foundation 10B. Since the load applied to 10B is shared by the support bolt 19 and the hardened mortar 20, the load applied to the foundation 10B is not inadvertently inclined or the foundation 10B is not collapsed. It is possible to make a base 10B that supports the above.
  • the installation location of the installation foundation 10B is the concrete slab 12 or the concrete beam 13 having the waterproof layer 14 having a waterproof function on the roof or underground of the existing concrete structure 11, the installation location of the installation foundation 10B
  • the foundation 10B is installed on the exposed slab 12 and the beam 13 after removing the waterproof layer 14, and the waterproof layer near the installation location can be repaired (a new waterproof layer 21 is applied) immediately after the foundation 10B is installed. Therefore, the foundation 10B can be installed quickly, and the time required for the installation of the foundation 10B can be greatly shortened.
  • FIG. 18 is a perspective view of an installation base 10C as another example
  • FIG. 19 is a cross-sectional view taken along the line CC of FIG. 18,
  • FIG. 20 is a top view of the metal base 16.
  • FIG. FIG. 21 is a side view of the metal base 16.
  • the concrete structure 11 is formed of a concrete frame 12 (including a concrete slab and a concrete beam), a waterproof layer 14 provided on the concrete frame 12, and a concrete layer 15 provided on the waterproof layer 14. ing.
  • the concrete housing 12 has a plurality of reinforcing bars embedded therein.
  • the installation foundation 10 ⁇ / b> C is installed on a concrete frame 12 in which the pressing concrete 15 and the waterproof layer 14 are removed from the concrete structure 11.
  • the mounting base 10C includes a metal base 16 (base) and a metal lid 17 (lid), a plurality of height adjusting bolts 18, a plurality of support bolts 19 (anchor bolts), a mortar 20 (hardened cement), and a waterproof layer 21.
  • the basic material is made by using each of the basic components that are generalized (standardized) of the molding material 22 (frame material) and assembling the basic components in a predetermined procedure.
  • the metal base 16 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site and then transported to the construction site.
  • the metal base 16 is disposed on a concrete frame 12 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11.
  • the metal base 16 is formed of a hollow cylindrical metal tube 23 (tube material) and a metal plate 24 (bottom plate) having a substantially rectangular planar shape.
  • the metal base 16 is manufactured by welding a metal tube 23 to the upper surface of the metal plate 24.
  • the metal tube 23 and the metal plate 24 are made of metal such as iron, aluminum, and alloy.
  • the metal base 16 is lighter than the reinforced concrete foundation because the concrete is omitted. Therefore, by using the metal base 16, the weight of the foundation 10C can be significantly reduced.
  • the metal tube 23 has each side plate 25 having a substantially rectangular shape, and its cross section is formed into a substantially rectangular shape.
  • the metal tube 23 is disposed on the upper surface of the central portion of the metal plate 24, and the lower end edge thereof is joined (fused) to the upper surface of the metal plate 24 by welding.
  • a hollow space 26 is defined by the side walls 25 in the metal tube 23, and a top opening 27 surrounded by the upper edge of the side plates 25 is formed at the top of the metal tube 23.
  • a plurality of fixing bolt screw holes 29 for screwing the lid fixing bolts 28 are formed on the top of the metal tube 23.
  • a female screw (not shown) into which the lid fixing bolt 28 is screwed is formed in the fixing bolt screw hole 29.
  • the metal plate 24 has a first portion 30 extending radially inward from the lower end edge of the metal tube 23 and a second portion 31 extending radially outward from the lower end edge of the metal tube 23.
  • a plurality of adjustment bolt screw holes 32 into which the height adjustment bolts 18 are screwed are formed in the second portion 31 (see FIG. 20).
  • a female screw (not shown) into which the height adjusting bolt 18 is screwed is formed in the adjusting bolt screw hole 32.
  • An elliptical filling hole 33 for filling the mortar 20 is formed in the central portion of the first portion 30 of the metal plate 24.
  • a confirmation hole 34 for confirming the filling state of the mortar 20 is formed in the second portion 31 (see FIG. 20).
  • the second portion 31 of the metal plate 24 has both end edges (periphery) extending in the lateral direction and both side edges (periphery) extending in the front-rear direction.
  • the metal pipe 23 and the second portion 31 of the metal plate 24 are provided with a plurality of reinforcing plates 35 extending in the vertical direction.
  • the reinforcing plates 35 are joined (fused) to the outer surface of the metal tube 23 and the upper surface of the metal plate 24 by welding.
  • the reinforcing plate 35 functions as a reinforcing material that increases the strength of the metal tube 23 and the metal plate 24.
  • a plurality of support bolt insertion holes 39 (bolt holes) through which the support bolts 19 are inserted are formed in the second portion 31 of the metal plate 24.
  • the support bolt insertion hole 39 is made by a drill and penetrates the second portion 31 of the metal plate 24 in the vertical direction.
  • These support bolt insertion holes 39 are arranged in the second portion 31 at predetermined intervals in the lateral direction and the front-rear direction.
  • four support bolt insertion holes 39 are formed, but the number of insertion holes 39 is not particularly limited, and the number is determined by structural calculation (strength calculation) performed before the foundation 10C is installed. .
  • a plurality of support bolt insertion holes 40 (bolt holes) through which the support bolts 19 are inserted are formed at the foundation installation position of the concrete frame 12.
  • the support bolt insertion hole 40 is made by a drill and extends in the vertical direction in the concrete housing 12 while avoiding the reinforcing bars embedded in the concrete housing 12.
  • the support bolt insertion hole 40 coincides with the position of the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete frame 12.
  • the support bolt insertion holes 40 are arranged at predetermined intervals in the lateral direction and the front-rear direction in the concrete housing 12.
  • the metal lid 17 is a standardized general-purpose product having the same shape and dimensions, made of metal such as iron, aluminum, and alloy, and its planar shape is formed into a substantially rectangular shape.
  • An angle member 41 (steel material) for fixing the lid 17 to the top of the metal tube 23 is joined (fused) by welding on the lower surface of the metal lid 17 and inside the periphery of the lid 17.
  • a fixing bolt insertion hole (not shown) for inserting the lid fixing bolt 28 is made in the angle member 41, and a hexagon nut 43 is joined (fused) to the fixing bolt insertion hole by welding.
  • the metal lid 17 is fixed to the top of the metal tube 24 by a lid fixing bolt 28 inserted into a fixing bolt insertion hole made in the angle member 41 and a hex nut 43 attached to the angle member 41.
  • the top opening 27 is closed watertight.
  • a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner or other mechanical equipment, or a fixture for installing a building such as a steel tower or steel structure is attached. It has been.
  • the height adjusting bolt 18 is a hexagonal bolt formed from a shaft 44 on which a male screw is made and a bolt head 45.
  • the shaft 44 of the height adjusting bolt 18 is screwed in advance into an adjusting bolt screwing hole 32 formed in the second portion 31 of the metal plate 24.
  • the shaft 44 of the bolt 18 gradually advances downward from the bolt screwing hole 32 and extends downward from the lower surface of the second portion 31.
  • 45 abuts on the upper surface of the concrete beam 13. Thereby, the metal base 16 can be spaced apart from the upper surface of the concrete housing 12 by a predetermined dimension.
  • the shaft 44 of the bolt 18 gradually advances upward from the bolt screw hole 32 and extends upward from the lower surface of the second portion 31. Thereby, the metal base 16 can be brought close to the upper surface of the concrete housing 12.
  • the metal plate 24 of the metal base 16 is separated upward from the upper surface of the concrete housing 12, and between the upper surface of the housing 12 and the lower surface of the metal plate 24.
  • a space 46 having a predetermined height is formed.
  • the height dimension of the space 46 can be adjusted by adjusting the screwing position of the height adjusting bolts 18 with respect to the second portion 31 of the metal plate 24 of the metal base 16, and the metal from the upper surface of the concrete housing 12 can be adjusted.
  • the height dimension of the base 16 can be adjusted up to the length of the bolt 18.
  • the support bolt 19 is a standardized general-purpose product having the same length and diameter.
  • the support bolt 19 is made of steel, and is inserted into a support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24. 12 is inserted into the support bolt insertion hole 40 made in the shape 12.
  • the support bolt 19 has a free end portion 47 extending upward from the upper surface of the concrete housing 12 and a fixed end portion 48 fixed to the housing 12.
  • the free end portion 47 of the support bolt 19 is inserted into a support bolt insertion hole 39 opened in the metal plate 24 and is fixed to the metal plate 24 via a hexagon nut 50 (fixing means).
  • the hexagon nut 50 is attached to a portion of the free end 47 that extends upward from the metal plate 24.
  • the fixed end 48 of the support bolt 19 is fixed to the insertion hole 40 by a resin anchor (fixing means) (not shown) injected into the support bolt insertion hole 40 of the concrete housing 12.
  • the mortar 20 is filled in a space 46 formed between the upper surface of the concrete housing 12 and the lower surface of the metal plate 24.
  • the mortar 20 is filled from a filling hole 33 formed in the metal plate 24.
  • the space 46 the mortar 20 filled therein is cured, and the mortar 20 is joined to the upper surface of the concrete housing 12 and the lower surfaces of the first and second portions 30 and 31 of the metal plate 24, and the support bolt 19. It is joined to.
  • the hardened mortar 20 is a foundation when a building such as a solar panel, an antenna, a water storage tank, a septic tank, a mechanical device such as an air conditioner, or a building such as a steel tower or steel structure is mounted on the foundation 10C (on the metal lid 17).
  • the load applied to 10C is shared with the support bolt 19.
  • the molding material 22 (frame material) is installed in the crossing part of the metal pipe 23 and the metal plate 24 and the holding concrete 15 and the concrete slab 12.
  • the molding material 22 is fixed to the metal tube 23, the slab 12, and the pressing concrete 15 with an adhesive (not shown).
  • the molding material 22 surrounds the entire outer periphery of the metal tube 23 and is placed between the outer periphery of the metal base 16 (the outer periphery of the metal plate 24) and the concrete slab 12 (concrete structure). Surrounds the entire periphery.
  • the molding material 22 closes the gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24.
  • the waterproof layer 21 is installed on the outside of each side plate 25 of the metal tube 23 to cover the entire side plate 25, and is installed on the outside of the metal plate 24 to cover the entire metal plate 24.
  • asphalt waterproofing is used in which a plurality of thin asphalt sheets are stacked to form an asphalt sheet layer.
  • the asphalt sheet is fixed to the side plate 25 of the metal tube 23, the mortar 20, and the molding material 22 due to its adhesiveness.
  • a portion extending outward from the second portion 31 of the metal plate 24 of the waterproof layer 21 (asphalt sheet fixed to the molding material 22) is connected to the waterproof layer 14 of the concrete structure 11.
  • FIG. 22 is a diagram showing an example of the construction procedure of the installation foundation 10C
  • FIG. 23 is a diagram showing the construction procedure of the installation foundation 10C continued from FIG.
  • FIG. 24 is a diagram showing a construction procedure of the installation foundation 10C continuing from FIG. 23
  • FIG. 25 is a diagram showing a construction procedure of the installation foundation 10C continuing from FIG. 22 to 25, the concrete structure 11 is shown as a cross section, and each part of the foundation 10C excluding a part is shown as a cross section.
  • the construction procedure of the foundation 10C will be described as follows, taking as an example the case where the installation foundation 10C is installed on the roof of the concrete structure 11.
  • the support bolt insertion hole 39 (bolt hole) is not made in the second portion 31 of the metal plate 24, and the support bolt insertion hole 39 is formed in the second portion 31 at the construction site. Perforate.
  • a plurality of adjustment bolt screw holes 32 are formed in the second part 31 of the metal plate 24 in advance in a basic part manufacturing factory, and the height adjustment bolt 18 is screwed into the bolt screw holes 32. Yes.
  • Each basic part (metal base 16 (base), metal lid 17 (lid), height adjustment bolt 18, support bolt 19 (anchor bolt), waterproof layer 21,
  • mold material 22 frame material
  • the installation location of the foundation 10C on the roof of the concrete structure 11 is positioned, and the installation location is marked.
  • the pressing concrete 15 and the waterproof layer 14 are removed from the concrete structure 11 at the installation location, and the concrete frame 12 is exposed.
  • a drilled portion at a position where the reinforcing bar of the support bolt insertion hole 39 (bolt hole) is torn is marked on the second portion 31 of the metal plate 24.
  • a support bolt insertion hole 39 is drilled in a drilling portion of the second portion 31 of the metal plate 24 using a drill (insertion hole bolt hole drilling step).
  • the first and second portions 30 and 31 of the metal tube 23 and the metal plate 24 are positioned on the concrete housing 12, and the bolt head 45 of the height adjusting bolt 18 is It contacts the upper surface of the concrete housing 12.
  • the base 16 is self-supporting on the top surface of the housing 12, supported by the height adjusting bolts 18 that are in contact with the top surface of the concrete housing 12.
  • the installation foundation 10C can freely change the height dimension of the metal base 16 during construction of the foundation 10C by using the height adjusting bolt 18, and immediately responds to a request for changing the height dimension of the foundation 10C. be able to.
  • the installation foundation 10C can easily adjust the height dimensions of the foundations 10C when a plurality of them are installed, and the height dimensions of the foundations 10C can be made uniform.
  • the metal base 16 After adjusting the height dimension of the metal base 16, marking is performed on the drilled portion of the support bolt insertion hole 40 (bolt hole) of the concrete housing 12 in accordance with the position of the support bolt insertion hole 39 of the metal plate 24.
  • the support bolt insertion hole 40 is drilled in the drilled location marked using a drill (insertion hole drilling step).
  • the metal base 16 After the support bolt insertion hole 40 is formed in the concrete frame 12, the metal base 16 is temporarily installed again at the installation location, and the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 as shown in FIG.
  • the support bolt 19 is inserted into the support bolt 19, and the support bolt 19 is inserted into the support bolt insertion hole 40 formed in the housing 12.
  • the intersection of the metal tube 23 and the metal plate 24 and the pressing concrete 15 and the concrete slab 12 are formed with a molding material 22 (frame Material) (frame material installation process).
  • frame Material molding material installation process.
  • the molding material 22 surrounds the entire outer peripheral edge of the metal tube 23 and the entire outer peripheral edge of the metal plate 24, and the molding material 22 has a gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24. Block.
  • the waterproof layer 21 is installed on the outside of each side plate 25 of the metal tube 23 and the outside of the metal plate 24 (outside of the molding material 22) (waterproof layer installation process).
  • a plurality of thin asphalt sheets are fixed to the outside of each side plate 25 of the metal tube 23 and the outside of the molding material 22 in the same manner as the foundation 10A in FIG.
  • the waterproof layer 21 extending from 22 is connected to the waterproof layer 14 of the concrete structure 11.
  • the installation base 10C can prevent water from entering the inside of the metal base 16 by the waterproof layer 21 even when it is installed outdoors of the concrete structure 11, and the base 16 due to water entering the inside can be prevented. Corrosion and strength reduction can be prevented.
  • the entrance of water to the concrete structure 11 can be prevented, and the deterioration of the structure 11 due to the entrance of water can be prevented.
  • the space 46 is filled with mortar 20 (cement hardened material filling step).
  • cement hardened material filling step the mortar 20 is filled into the space 46 from the filling hole 33 while confirming the filling state of the mortar 20 in the space 46 from the confirmation hole 34.
  • the mounting base 10C can fill the space 46 with the mortar 20 by using the filling hole 33 after the support bolt 19 is fixed to the metal plate 24 or the concrete housing 12, so that the space 46 is reliably filled with the mortar 20. be able to.
  • the installation base 10 ⁇ / b> C confirms the filling state of the mortar 20 filled in the space 46 using the confirmation hole 34, so that the mortar 20 is not filled in the space 46 and the mortar 20 is placed in the entire space 46. Can be filled evenly.
  • the metal lid 17 is immediately fitted into the top of the metal tube 23 to close the top opening 27 of the metal tube 23.
  • the lid fixing bolt 28 is screwed into the fixing bolt screwing holes 29 formed on the side plates 25 of the metal tube 23, and the angle of the metal lid 17 is The bolt 29 is inserted into the lid fixing bolt insertion hole of the material 41, and the bolt 29 is screwed to the hexagon nut 43 attached to the bolt insertion hole to fix the lid 17 to the top of the metal tube 25 (top closing step) ( (See FIG. 19).
  • the top opening 27 of the metal tube 25 is watertightly closed by the metal lid 17.
  • the molding material 22 becomes a bank which prevents the leakage of the mortar 20 before hardening, and the mortar 20 with which the space 46 was filled is a space
  • the top opening 27 can be closed with the metal lid 17 immediately after the mortar 20 is filled.
  • the mortar 20 filled in the space 46 is in an uncured state immediately after the metal lid 17 is fitted (fixed) to the top of the metal tube 25, and the lid 17 is fixed to the top of the tube 25.
  • the curing period for mortar 20 begins.
  • the curing period of the mortar 20 elapses, and the mortar 20 filled therein is cured, so that the upper surface of the concrete housing 12 in the free end portion 47 of the support bolt 19 and the metal plate 24 of the metal tube 25. (A portion of the free end 47 of the bolt 19 that is exposed downward from the lower surface of the plate 24) is integrated with the mortar 20 to form a reinforcing bar mortar.
  • the installation base 10C shown in FIGS. 18 and 19 is completed.
  • the top opening 27 of the metal tube 23 can be immediately closed with the metal lid 17 without waiting for the curing period of the mortar 20 to complete the foundation 10 ⁇ / b> C.
  • the construction period can be shortened by the curing period of the mortar 20 filled in the space 46, and a plurality of foundations 10C can be constructed in parallel without waiting for the curing period.
  • the installation foundation construction method includes a provisional installation process in which the metal base 16 is temporarily installed at a predetermined installation location of the concrete frame 12, and an installation height for adjusting the installation height of the temporarily installed metal base 16 from the upper surface of the frame 12.
  • a support bolt fixing step for fixing the second portion 31 and the casing 12 and a frame member 22 for closing a gap between the outer periphery of the metal base 16 and the outer periphery of the base 16 are provided between the outer periphery of the metal base 16 and the concrete casing.
  • the support bolt 19 is fixed to the second portion 31 of the metal plate 24 of the lightweight metal base 16 and the concrete casing 12, and the metal lid 17 is simply fixed to the metal tube 23 immediately after the space 46 is filled with the mortar 20.
  • the foundation can be constructed, and the labor, cost, and time required for mold production and mortar curing can be saved, and the construction work can be simplified and the construction period can be greatly shortened. be able to.
  • the support bolt 19 is fixed to the second portion 31 of the metal plate 24 and the concrete casing 12, and the space 46 is filled with the mortar 20, so that the installation foundation 10C is firmly installed on the concrete structure 11.
  • a foundation 10C that can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air conditioners, and buildings such as steel towers and steel structures.
  • the load applied to the foundation 10C when the mortar 20 is filled in the space 46 between the upper surface of the concrete frame 12 and the lower surface of the metal plate 24 and the machinery and the building are provided on the foundation 10C. Is divided between the support bolt 19 and the hardened mortar 20, so that it is not inadvertently inclined by the load applied to the foundation 10C, or the foundation 10C is not collapsed. 10C can be made.
  • the installation foundation waterproof layer 14 is installed. Since the foundation 10C is installed on the exposed housing 12 after the removal, and the waterproof layer near the installation location can be repaired (a new waterproof layer 21 is applied) immediately after the foundation 10C is installed, the foundation 10C can be quickly installed. It can be installed, and the time required to install the foundation 10C can be greatly shortened.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

Disclosed is a base installation method capable of decreasing the work and cost required for installation and capable of shortening construction time. The method of installing a mounting base involves: a foundation temporary installation step for temporarily installing a metal foundation in a mounting position in a slab and a beam; an installation height adjustment step for adjusting the screw position of height adjustment bolts relative to a metal plate and adjusting the installation height of the metal foundation; a bolt hole piercing step for piercing support bolt insertion holes in the slab to match the positions of support bolt insertion holes in the metal plate; a support bolt fixing step for inserting the support bolts (19) into the support bolt insertion holes to fix the bolts (19) to the metal plate and the slab; a cement hardener filling step for filling with mortar the space between the top surface of the slab and beam and the bottom surface of the metal plate; and a metal tube closing step for fixing a metal cover (17) to the top of the metal tube (23).

Description

据え付け基礎施工方法Installation foundation construction method
 本発明は、据え付け基礎施工方法に関し、さらに詳細には、新設または既設のコンクリート構造物にソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を設置するために使用する据付け基礎を施工する据え付け基礎施工方法に関する。 The present invention relates to an installation foundation construction method, and more specifically, to a new or existing concrete structure such as a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure. The present invention relates to an installation foundation construction method for constructing an installation foundation used for installation.
 新設または既設の鉄筋コンクリート造や鉄筋鉄骨コンクリート造等のコンクリート構造物では、屋上や地下のスラブにソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の様々な機械器具、鉄塔や鉄骨建設物等の様々な建築物が設置される。通常、そのような機械器具や建築物は、その内部への水の侵入を防ぐ目的、機械器具や建築物の背面側のメンテナンスを可能にする目的からそれらがスラブの表面に直に設置されることはなく、それらがスラブに設置された据え付け基礎の上に備え付けられる。 In new or existing concrete structures such as reinforced concrete structures and reinforced steel concrete structures, roofs and underground slabs, solar panels, antennas, water storage tanks, septic tanks, air conditioners, and other various machinery and equipment, steel towers and steel structures, etc. Various buildings are installed. Typically, such machinery and buildings are installed directly on the surface of the slab for the purpose of preventing water from entering the interior and enabling maintenance on the back side of the machinery and buildings. There is nothing, they are mounted on a mounting foundation installed in the slab.
 そのような据え付け基礎の一例として、特許文献1は、太陽電池パネル据え付け構造を開示している。特許文献1において説明されている従来技術では、太陽電池パネルの施工現場の据え付け箇所において型枠を製作し、その型枠内にコンクリートを打設・養生することにより基礎を作り、搬送されてきた太陽電池パネルおよびその架台をその基礎の上に組み付ける構造である。そのような従来技術の据え付け基礎では、施工現場で型枠を製作しなければならないから、その分の手間がかかることはもちろん、型枠内に流し込んだコンクリートの養生に時間がかかり、短い工期で据え付け構造を作ることができない。 As an example of such an installation basis, Patent Document 1 discloses a solar cell panel installation structure. In the prior art described in Patent Document 1, a formwork is produced at a place where a solar cell panel is installed, and a foundation is formed and transported by placing and curing concrete in the formwork. This is a structure in which the solar cell panel and its mount are assembled on the foundation. In such a conventional installation foundation, since the formwork must be manufactured at the construction site, it takes time and effort to cure the concrete poured into the formwork, and in a short construction period. Cannot make a stationary structure.
 かかる従来技術の問題点を解決するために、特許文献1に開示の太陽電池パネル据え付け構造では、基礎部品製造工場においてコンクリート製または鉄筋コンクリート製の基礎をあらかじめ製造し、その基礎をコンクリート構造物の屋上や地下の施工現場に搬送する。その後、屋上や地下のスラブの据え付け箇所に薄いセメント層を形成し、そのセメント層を接着層としてその上に基礎を載せてスラブと一体化し、太陽電池パネルの設置用架台をそれらの基礎の上に備え付ける。特許文献1に開示された太陽電池パネル据え付け構造は、太陽電池パネルを備え付けるための基礎を形成する際に施工現場において型枠を製作する必要がないから、その分の手間が省け、施工現場における施工作業を簡略化することができるとともに、コンクリートを養生する時間を省くことができ、その分の施工期間を短縮することができる。 In order to solve such problems of the prior art, in the solar cell panel mounting structure disclosed in Patent Document 1, a concrete or reinforced concrete foundation is manufactured in advance at a foundation parts manufacturing factory, and the foundation is used as a roof of a concrete structure. And transported to underground construction sites. After that, a thin cement layer is formed on the roof or underground slab installation site, the cement layer is used as an adhesive layer, the foundation is placed on top of it, and it is integrated with the slab. Prepare for. Since the solar cell panel mounting structure disclosed in Patent Document 1 does not need to produce a formwork at the construction site when forming the foundation for installing the solar cell panel, it saves that much labor, and at the construction site The construction work can be simplified, the time for curing the concrete can be omitted, and the construction period can be shortened accordingly.
特開平9-070188号公報JP-A-9-070188
 前記特許文献1に開示の太陽電池パネル据え付け構造では、施工現場においてコンクリートを養生する必要はないが、基礎製造工場においてコンクリートを養生して基礎を作らなければならず、基礎の製造にコンクリートの養生が必要であることに変わりはなく、基礎の製造に時間を要する。さらに、製造したコンクリート製基礎や鉄筋コンクリート製基礎を工場から施工現場に搬送する必要があり、相当な重量を有する基礎を搬送する手間を要するから、基礎を施工する労力やコストを低減することができない。また、工場で製造された基礎をスラブに固定する場合、コンクリート層を接着層としてスラブに固定する方法や凹部をスラブに形成して基礎の下端をその凹部に嵌め込む方法しか採用できず、基礎をスラブに強固に据え付けることができない。 In the solar cell panel installation structure disclosed in Patent Document 1, it is not necessary to cure the concrete at the construction site, but the foundation must be cured by curing the concrete at the foundation manufacturing plant. Is still necessary, and it takes time to manufacture the foundation. Furthermore, it is necessary to transport manufactured concrete foundations and reinforced concrete foundations from the factory to the construction site, and it takes time and labor to transport foundations with considerable weight, so it is not possible to reduce the labor and cost of constructing foundations. . Moreover, when fixing a foundation manufactured at a factory to a slab, only a method of fixing a concrete layer to the slab as an adhesive layer or a method of forming a recess in the slab and fitting the lower end of the foundation into the recess can be adopted. Cannot be firmly installed on the slab.
 本発明の目的は、新設または既設のコンクリート構造物に機械機器や建築物を備え付ける強固な基礎を作ることができ、その基礎の設置に要する労力やコストを低減することができるとともに、その基礎の施工期間を短縮することができる据え付け基礎施工方法を提供することにある。 The object of the present invention is to create a solid foundation for installing machinery and buildings on a new or existing concrete structure, reduce labor and cost required to install the foundation, and The object is to provide an installation foundation construction method capable of shortening the construction period.
 前記課題を解決するための本発明の前提は、新設または既設のコンクリート構造物の所定の箇所に設置される据え付け基礎を施工する据え付け基礎施工方法である。 The premise of the present invention for solving the above-mentioned problem is an installation foundation construction method for constructing an installation foundation installed at a predetermined location of a new or existing concrete structure.
 前記前提における本発明の特徴は、据え付け基礎施工方法が、金属管と金属管の下端につながる金属板とを有する金属土台をコンクリート構造物の所定の箇所に仮設置する土台仮設置工程と、金属板に螺着された高さ調節ボルトの金属板に対する螺着位置を調節することで、仮設置された金属土台のコンクリート構造物の上面からの設置高さを調節する設置高さ調節工程と、金属板に支持ボルト第1挿通孔を穿孔するボルト孔第1穿孔工程と、金属板に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート構造物に支持ボルト第2挿通孔を穿孔するボルト孔第2穿孔工程と、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して支持ボルトを金属板およびコンクリート構造物に固定する支持ボルト固定工程と、金属土台の外周縁とコンクリート構造物との間に構造物と土台の外周縁との間の空隙を塞ぐ枠材を設置する枠材設置工程と、コンクリート構造物の上面と金属板の下面との間の空間にセメント硬化物を充填するセメント硬化物充填工程と、金属管の頂部に金属蓋を固定して金属管の頂部開口を塞ぐ金属管閉鎖工程とを有し、据え付け基礎施工方法では、空間にセメント硬化物を充填した直後であってセメント硬化物の養生期間の経過前に、金属蓋によって金属管の頂部開口が塞がれ、金属蓋によって金属管の頂部開口が塞がれた後からセメント硬化物の養生期間が開始し、養生期間の経過後に、支持ボルトのうちのコンクリート構造物と金属板との間に延びる部分がセメント硬化物と一体になることにある。 The feature of the present invention in the above premise is that the installation foundation construction method includes a temporary mounting step of temporarily mounting a metal base having a metal pipe and a metal plate connected to the lower end of the metal pipe at a predetermined position of the concrete structure, An installation height adjustment step of adjusting the installation height from the top surface of the concrete structure of the temporarily installed metal base by adjusting the screwing position of the height adjustment bolt screwed to the plate to the metal plate; A bolt hole first drilling step for drilling a support bolt first insertion hole in the metal plate and a support bolt second insertion hole in the concrete structure in accordance with the position of the support bolt first insertion hole formed in the metal plate. The bolt hole second drilling step, and the support bolt fixing the support bolt to the metal plate and the concrete structure through predetermined fixing means by inserting the support bolt into the support bolt first and second insertion holes. A frame material installation step for installing a frame material for closing a gap between the outer peripheral edge of the structure and the base between the outer peripheral edge of the metal base and the concrete structure, and the upper surface of the concrete structure and the metal plate Installation foundation construction with a cement hardened material filling process that fills the space between the lower surface and cement hardened material, and a metal tube closing process that fixes the metal lid to the top of the metal tube and closes the top opening of the metal tube In the method, immediately after filling the space with the hardened cement material and before the curing period of the hardened cement material, the top opening of the metal tube is blocked by the metal lid, and the top opening of the metal tube is blocked by the metal lid. After that, the curing period of the hardened cement material starts, and after the curing period, the portion of the support bolt that extends between the concrete structure and the metal plate is integrated with the hardened cement material.
 本発明の一例としては、金属板が、金属管の径方向内方へ延びる第1部分と、金属管の径方向外方へ延びる第2部分とを備え、ボルト孔第1穿孔工程では、金属板の第2部分に支持ボルト第1挿通孔を穿孔し、ボルト孔第2穿孔工程では、金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート構造物に支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程では、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して支持ボルトを金属板の第2部分およびコンクリート構造物に固定し、枠材設置工程では、底板の第2部分の外周縁とコンクリート構造物との間に構造物と第2部分の外周縁との間の空隙を塞ぐ枠材を設置する。 As an example of the present invention, the metal plate includes a first portion that extends radially inward of the metal tube and a second portion that extends radially outward of the metal tube. The support bolt first insertion hole is drilled in the second portion of the plate, and in the bolt hole second drilling step, the support is supported on the concrete structure in accordance with the position of the support bolt first insertion hole formed in the second portion of the metal plate. The bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is inserted into the second portion of the metal plate and the concrete structure through predetermined fixing means. In the frame material installation step, a frame material is installed between the outer peripheral edge of the second part of the bottom plate and the concrete structure to close the gap between the structure and the outer peripheral edge of the second part.
 本発明の他の一例としては、コンクリート構造物が、コンクリート躯体と、コンクリート躯体の上に施設された防水層と、防水層の上に施設された押さえコンクリートとから形成され、土台仮設置工程では、コンクリート構造物から押さえコンクリートと防水層とを取り除いてコンクリート躯体を露出させ、金属土台をコンクリート躯体に仮設置し、ボルト孔第2穿孔工程では、金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート躯体に支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程では、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して支持ボルトを金属板の第2部分およびコンクリート躯体に固定する。 As another example of the present invention, the concrete structure is formed of a concrete frame, a waterproof layer provided on the concrete frame, and a pressing concrete provided on the waterproof layer. , Removing the pressing concrete and waterproof layer from the concrete structure to expose the concrete frame, temporarily installing the metal base on the concrete frame, and in the bolt hole second drilling step, the support bolt formed on the second part of the metal plate According to the position of the first insertion hole, the support bolt second insertion hole is drilled in the concrete frame, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and through a predetermined fixing means. The support bolt is fixed to the second part of the metal plate and the concrete frame.
 本発明の他の一例としては、コンクリート構造物が、コンクリートスラブおよびコンクリート梁と、スラブおよび梁の上に施設された防水層と、防水層の上に施設された押さえコンクリートとから形成され、土台仮設置工程では、コンクリート構造物から押さえコンクリートと防水層とを取り除いてスラブと梁とを露出させ、金属板の第2部分がスラブの上に位置するとともに、金属管と金属板の第1部分とが梁の上に位置するように、金属土台を仮設置し、ボルト孔第2穿孔工程では、金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせてスラブに支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程では、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して支持ボルトを金属板の第2部分およびスラブに固定する。 As another example of the present invention, a concrete structure is formed of a concrete slab and a concrete beam, a waterproof layer provided on the slab and the beam, and a pressing concrete provided on the waterproof layer, In the temporary installation process, the pressing concrete and the waterproof layer are removed from the concrete structure to expose the slab and the beam, and the second part of the metal plate is located on the slab, and the first part of the metal tube and the metal plate. The metal base is temporarily installed so that and are positioned on the beam, and in the bolt hole second drilling step, it is supported by the slab according to the position of the first support bolt insertion hole formed in the second part of the metal plate. The bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is inserted into the second part of the metal plate through a predetermined fixing means. And it is fixed to the slab.
 本発明の他の一例としては、ボルト孔第1穿孔工程では、金属板の第1部分に支持ボルト第1挿通孔を穿孔し、ボルト孔第2穿孔工程では、金属板の第1部分に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート梁に支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程では、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して支持ボルトを金属板の第1および第2部分とスラブおよび梁とに固定する。 As another example of the present invention, in the bolt hole first drilling step, the support bolt first insertion hole is drilled in the first portion of the metal plate, and in the bolt hole second drilling step, it is formed in the first portion of the metal plate. The support bolt second insertion hole is drilled in the concrete beam in accordance with the position of the first support bolt first insertion hole, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, The support bolt is fixed to the first and second portions of the metal plate, the slab and the beam via the fixing means.
 本発明の他の一例としては、据え付け基礎施工方法が金属土台を覆う防水層を設置する防水層設置工程を含み、防水層設置工程では、金属土台の外側に延びる防水層をコンクリート構造物の防水層につなげる。 As another example of the present invention, the installation foundation construction method includes a waterproof layer installation step of installing a waterproof layer covering the metal base. In the waterproof layer installation step, the waterproof layer extending outside the metal base is waterproofed to the concrete structure. Connect to the layer.
 本発明の他の一例として、金属板の第2部分には、その周縁から上方へ起立する第1側板と、第1側板の間に位置して第2部分から上方へ起立する第2側板とが連接され、セメント硬化物充填工程では、金属板の第2部分と第1側板とに囲繞されたスペースにセメント硬化物を充填する。 As another example of the present invention, the second portion of the metal plate includes a first side plate that rises upward from the periphery thereof, and a second side plate that is positioned between the first side plates and rises upward from the second portion. In the cement hardened material filling step, the cement hardened material is filled in a space surrounded by the second portion of the metal plate and the first side plate.
 本発明の他の一例として、金属板の第2部分には、その周縁から上方へ起立する第1側板と、第1側板の間に位置して第2部分から上方へ起立する第2側板とが連接され、据え付け基礎施工方法が、金属板の第2部分と第1側板とに囲繞されたスペースの頂部に頂板を固定してスペースを塞ぐスペース閉鎖工程を含む。 As another example of the present invention, the second portion of the metal plate includes a first side plate that rises upward from the periphery thereof, and a second side plate that is positioned between the first side plates and rises upward from the second portion. The connected foundation construction method includes a space closing step of fixing the top plate to the top of the space surrounded by the second portion of the metal plate and the first side plate to close the space.
 本発明の他の一例として、金属板の所定の箇所には、空間にセメント硬化物を充填するための充填孔が形成され、セメント硬化物充填工程では、充填孔から空間にセメント硬化物を充填する。 As another example of the present invention, a filling hole for filling a cement hardened material into a space is formed in a predetermined portion of the metal plate, and in the cement hardened material filling process, the cement hardened material is filled into the space from the filling hole. To do.
 本発明の他の一例として、金属板の所定の箇所には、空間に充填されたセメント硬化物を確認するための確認孔が形成され、セメント硬化物充填工程では、確認孔から空間におけるセメント硬化物の充填状態を確認しつつ、空間にセメント硬化物を充填する。 As another example of the present invention, a confirmation hole for confirming the cement hardened material filled in the space is formed in a predetermined portion of the metal plate, and in the cement hardened material filling step, cement hardening in the space from the confirmation hole. While confirming the filling state of the object, the cement hardened material is filled into the space.
 本発明にかかる据え付け基礎施工方法によれば、金属土台をコンクリート構造物の所定の据え付け箇所に仮設置する土台仮設置工程と、仮設置された金属土台のコンクリート構造物の上面からの設置高さを調節する設置高さ調節工程と、金属板に支持ボルト第1挿通孔を穿孔するボルト孔第1穿孔工程と、金属板に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート構造物に支持ボルト第2挿通孔を穿孔するボルト孔第2穿孔工程と、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、固定手段を介して支持ボルトを金属板およびコンクリート構造物に固定する支持ボルト固定工程と、金属土台の外周縁とコンクリート構造物との間に構造物と土台の外周縁との間の空隙を塞ぐ枠材を設置する枠材設置工程と、コンクリート構造物の上面と金属板の下面との間の空間にセメント硬化物を充填するセメント硬化物充填工程と、金属管の頂部に金属蓋を固定する金属管閉鎖工程とから基礎が作られ、汎用部品化された各基礎部品を各工程によってユニットシステムとして組み立てるから、施工作業をマニュアル化することができるとともに、施工作業を簡略化することができる。据え付け基礎施工方法は、基礎を形成する際に施工現場において型枠を製作する必要がないことはもちろん、基礎製造工場や施工現場において基礎を作るためにセメント硬化物を養生する必要はなく、支持ボルトを軽量な金属土台の金属板とコンクリート構造物とに固定し、空間にセメント硬化物を充填するとともに、金属土台に金属蓋を固定するだけで基礎を構築することができ、型枠の製作やセメント硬化物の養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。据え付け基礎施工方法は、支持ボルトを金属板およびコンクリート構造物に固定し、空間にコンクリート硬化物を充填し、セメント硬化物の養生期間が経過した後に支持ボルトがセメント硬化物と一体になり、基礎にかかる荷重を支持ボルトとセメント硬化物とで分担するから、据え付け基礎をコンクリート構造物に強固に据え付けることができるのみならず、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることが可能な基礎を作ることができる。据え付け基礎施工方法は、コンクリート構造物の上面と金属板の下面との間の空間にセメント硬化物を充填し、基礎の上に機械機器や建築物を備え付けた場合の基礎にかかる荷重を支持ボルトと硬化したセメント硬化物とに分担させるから、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持することが可能な基礎を作ることができる。据え付け基礎施工方法は、コンクリート構造物と金属土台の外周縁との間の空隙が枠材によって塞がれ、セメント硬化物を前記空間に充填したとしても、そのセメント硬化物が空隙(空間)から漏れ出すことはなく、空間にセメント硬化物を充填した直後であってセメント硬化物の養生期間を待つことなく、金属蓋によって金属管の頂部開口を塞ぐことができ、セメント硬化物の養生期間を待つことなく次の基礎の据え付け作業を行うことができるから、セメント硬化物の養生期間の分の施工期間を短縮することができ、据え付け基礎の施工期間を大幅に短縮することができる。据え付け基礎施工方法は、金属土台のコンクリート構造物の上面からの設置高さを基礎の施工中に自由に調節することができ、基礎の高さ寸法の変更要求に即座に対応することができる。据え付け基礎施工方法は、複数個のそれらを設置する場合にそれら基礎どうしの高さ寸法を容易に調節することができ、それら基礎の高さ寸法を均一に揃えることができる。 According to the installation foundation construction method according to the present invention, a temporary installation step of temporarily installing a metal foundation at a predetermined installation location of a concrete structure, and an installation height of the temporarily installed metal foundation from the top surface of the concrete structure. Adjusting the installation height, adjusting the position of the first insertion hole formed in the metal plate, and the bolt hole first drilling process for drilling the first insertion hole in the metal plate. A bolt hole second drilling step for drilling a support bolt second insertion hole, a support bolt inserted into the support bolt first and second insertion holes, and fixing the support bolt to the metal plate and the concrete structure through fixing means. A supporting bolt fixing step, a frame material installation step for installing a frame material for closing a gap between the outer periphery of the metal base and the concrete structure and the outer periphery of the base, and a concrete The foundation is made from a cement hardened material filling process that fills the space between the upper surface of the structure and the lower surface of the metal plate with a cement hardened material filling process and a metal tube closing process that fixes a metal lid to the top of the metal pipe, Since each basic part made into a general-purpose part is assembled as a unit system by each process, the construction work can be manualized and the construction work can be simplified. The installation foundation construction method does not need to produce a formwork at the construction site when forming the foundation, and it is not necessary to cure the hardened cement material to create the foundation at the foundation manufacturing factory or construction site. Fixing bolts to a lightweight metal base metal plate and concrete structure, filling the space with hardened cement, and building a foundation simply by fixing a metal lid to the metal base, making a formwork In addition, the labor, cost, and time required for curing the cured cement can be saved, the construction work can be simplified, and the construction period can be greatly shortened. In the installation foundation construction method, the support bolt is fixed to the metal plate and the concrete structure, the space is filled with the hardened concrete, and after the curing period of the hardened cement has passed, the support bolt is integrated with the hardened cement. Since the load applied to the load is shared by the support bolt and the hardened cement, not only the installation foundation can be firmly installed on the concrete structure, but also solar panels, antennas, water storage tanks, septic tanks, air conditioners and other machinery and equipment, It is possible to create a foundation that can be firmly equipped with buildings such as steel towers and steel structures. In the installation foundation construction method, the space between the upper surface of the concrete structure and the lower surface of the metal plate is filled with hardened cement, and the load applied to the foundation when a machine or building is installed on the foundation is supported by the bolts. Since the load is applied to the hardened cement and the hardened cement, it will not inadvertently incline due to the load applied to the foundation, or the foundation will not collapse. Can be made. In the installation foundation construction method, even if the gap between the concrete structure and the outer peripheral edge of the metal base is closed by the frame material, and the cement hardened product is filled in the space, the hardened cement product is removed from the gap (space). There is no leakage and the top of the metal tube can be closed with a metal lid immediately after filling the space with cement hardened material and without waiting for the cement hardened material curing period. Since the next foundation installation work can be performed without waiting, the construction period for the curing period of the hardened cement can be shortened, and the construction period of the foundation can be greatly shortened. The installation foundation construction method can freely adjust the installation height of the metal foundation from the top surface of the concrete structure during construction of the foundation, and can immediately respond to a request for changing the height dimension of the foundation. In the installation foundation construction method, when installing a plurality of them, the height dimensions of the foundations can be easily adjusted, and the height dimensions of the foundations can be made uniform.
 金属板が第1部分と第2部分とを備え、ボルト孔第1穿孔工程において、金属板の第2部分に支持ボルト第1挿通孔を穿孔し、ボルト孔第2穿孔工程において、金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート構造物に支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程において、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、固定手段を介して支持ボルトを金属板の第2部分およびコンクリート構造物に固定し、枠材設置工程において、底板の第2部分の外周縁とコンクリート構造物との間に枠材を設置する据え付け基礎施工方法は、基礎を施工する際に施工現場において型枠を製作する必要がないことはもちろん、基礎部品製造工場や施工現場において基礎を作るためにセメント硬化物を養生する必要はなく、支持ボルトを軽量な金属土台の金属板の第2部分とコンクリート構造物とに固定し、空間にセメント硬化物を充填するとともに、金属土台に金属蓋を固定するだけで基礎を構築することができ、型枠の製作やセメント硬化物の養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。据え付け基礎施工方法は、支持ボルトを金属板およびコンクリート構造物に固定し、空間にコンクリート硬化物を充填し、セメント硬化物の養生期間が経過した後に支持ボルトがセメント硬化物と一体になり、基礎にかかる荷重を支持ボルトとセメント硬化物とで分担するから、据え付け基礎をコンクリート構造物に強固に据え付けることができるのみならず、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることが可能な基礎を作ることができる。据え付け基礎施工方法は、コンクリート構造物の上面と金属板の下面との間の空間にセメント硬化物を充填し、基礎の上に機械機器や建築物を備え付けた場合の基礎にかかる荷重を支持ボルトと硬化したセメント硬化物とに分担させるから、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持することが可能な基礎を作ることができる。据え付け基礎施工方法は、金属板を金属管の径方向外方へ延ばして第2部分を形成することで金属板の面積を確保し、その金属板によって基礎にかかる荷重を支え、代わりに金属管の径方向の寸法を小さくして金属管の重量を減少させることができるから、金属管の重量を軽量化することができ、その結果として基礎の重量を軽量化することができる。 The metal plate includes a first portion and a second portion, and in the bolt hole first drilling step, the support bolt first insertion hole is drilled in the second portion of the metal plate, and in the bolt hole second drilling step, the metal plate The support bolt second insertion hole is drilled in the concrete structure in accordance with the position of the support bolt first insertion hole formed in the second portion, and the support bolt is inserted into the support bolt first and second insertion holes in the support bolt fixing step. And fixing the support bolt to the second portion of the metal plate and the concrete structure through fixing means, and in the frame material installation step, the frame material is provided between the outer peripheral edge of the second portion of the bottom plate and the concrete structure. The installation foundation construction method of installing the cement is not necessary to produce the formwork at the construction site when constructing the foundation, but also to harden the cement to make the foundation at the foundation parts manufacturing factory and construction site There is no need to cure, the support bolt is fixed to the second part of the lightweight metal base metal plate and the concrete structure, and the space is filled with hardened cement and the base is simply fixed to the metal base. Can save time, cost, and time for the production of formwork and curing of hardened cement, and can simplify the construction work and greatly reduce the construction period. can do. In the installation foundation construction method, the support bolt is fixed to the metal plate and the concrete structure, the space is filled with the hardened concrete, and after the curing period of the hardened cement has passed, the support bolt is integrated with the hardened cement. Since the load applied to the load is shared by the support bolt and the hardened cement, not only the installation foundation can be firmly installed on the concrete structure, but also solar panels, antennas, water storage tanks, septic tanks, air conditioners and other machinery and equipment, It is possible to create a foundation that can be firmly equipped with buildings such as steel towers and steel structures. In the installation foundation construction method, the space between the upper surface of the concrete structure and the lower surface of the metal plate is filled with hardened cement, and the load applied to the foundation when a machine or building is installed on the foundation is supported by the bolts. Since the load is applied to the hardened cement and the hardened cement, it will not inadvertently incline due to the load applied to the foundation, or the foundation will not collapse. Can be made. The installation foundation construction method secures the area of the metal plate by extending the metal plate radially outward of the metal tube to form the second part, and supports the load applied to the foundation by the metal plate, instead of the metal tube Therefore, the weight of the metal tube can be reduced, and as a result, the weight of the foundation can be reduced.
 土台仮設置工程において、コンクリート構造物から押さえコンクリートと防水層とを取り除いてコンクリート躯体を露出させ、金属土台をコンクリート躯体に仮設置し、ボルト孔第2穿孔工程において、金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート躯体に支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程において、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、固定手段を介して支持ボルトを金属板の第2部分およびコンクリート躯体に固定する据え付け基礎施工方法は、支持ボルトを軽量な金属土台の金属板の第2部分とコンクリート躯体とに固定し、空間にセメント硬化物を充填するとともに、金属土台に金属蓋を固定するだけで基礎を構築することができ、型枠の製作やセメント硬化物の養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。据え付け基礎施工方法は、据え付け基礎の据え付け箇所が既設のコンクリート構造物の屋上や地下に防水機能を施した防水層を備えたコンクリート躯体である場合でも、据え付け箇所の防水層を取り除いた後の露出した躯体に基礎を設置し、基礎を設置した直後に据え付け箇所近傍の防水層を補修する(新たな防水層を施す)ことができるから、基礎を迅速に設置することができ、基礎の設置に要する時間を大幅に短縮することができる。 In the foundation temporary installation process, the concrete and waterproof layer are removed from the concrete structure to expose the concrete frame, and the metal foundation is temporarily installed in the concrete frame. In the bolt hole second drilling process, the second part of the metal plate The support bolt second insertion hole is drilled in the concrete frame in accordance with the position of the formed support bolt first insertion hole, and the support bolt is inserted and fixed in the support bolt first and second insertion holes in the support bolt fixing step. The installation foundation construction method of fixing the support bolt to the second part of the metal plate and the concrete frame through the means is to fix the support bolt to the second part of the metal plate of the lightweight metal base and the concrete frame, and to cement the space. The foundation can be built simply by filling the hardened material and fixing the metal lid to the metal base. Time and cost according to the curing of the cured product, it is possible to save time, it is possible to simplify the construction work, the construction time of that amount can be greatly shortened. Even if the installation location of the installation foundation is a concrete frame with a waterproof layer with a waterproof function on the roof or underground of an existing concrete structure, the exposure after removing the waterproof layer of the installation location The foundation can be installed in the frame, and the waterproof layer near the installation location can be repaired immediately after the foundation is installed (a new waterproof layer is applied), so that the foundation can be installed quickly and the foundation can be installed. The time required can be greatly reduced.
 土台仮設置工程において、コンクリート構造物から押さえコンクリートと防水層とを取り除いてスラブと梁とを露出させ、金属板の第2部分がスラブの上に位置するとともに、金属管と金属板の第1部分とが梁の上に位置するように、金属土台を仮設置し、ボルト孔第2穿孔工程において、金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせてスラブに支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程において、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、固定手段を介して支持ボルトを金属板の第2部分およびスラブに固定する据え付け基礎施工方法は、支持ボルトを軽量な金属土台の金属板の第2部分とスラブとに固定し、空間にセメント硬化物を充填するとともに、金属土台に金属蓋を固定するだけで基礎を構築することができ、型枠の製作やセメント硬化物の養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。据え付け基礎施工方法は、据え付け基礎の据え付け箇所が既設のコンクリート構造物の屋上や地下に防水機能を施した防水層を備えたスラブや梁である場合でも、据え付け箇所の防水層を取り除いた後の露出したスラブや梁に基礎を設置し、基礎を設置した直後に据え付け箇所近傍の防水層を補修する(新たな防水層を施す)ことができるから、基礎を迅速に設置することができ、基礎の設置に要する時間を大幅に短縮することができる。 In the temporary installation process of the foundation, the pressing concrete and the waterproof layer are removed from the concrete structure to expose the slab and the beam, and the second portion of the metal plate is located on the slab, and the first of the metal tube and the metal plate The metal base is temporarily installed so that the part is positioned on the beam, and in the bolt hole second drilling step, the slab is fitted to the position of the support bolt first insertion hole formed in the second part of the metal plate. The support bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is fixed to the second portion of the metal plate and the slab through the fixing means. The installation foundation construction method is to fix the support bolt to the second part of the metal plate of the lightweight metal base and the slab, fill the space with cement hardened material, and fix the metal lid to the metal base The foundation can be built in, and it is possible to save the labor, cost, and time required for the production of the formwork and the curing of the hardened cement, and the construction work can be simplified. Can be shortened. Even if the installation location of the installation foundation is a slab or beam with a waterproof layer with a waterproof function on the rooftop or basement of an existing concrete structure, the installation foundation after removing the waterproof layer at the installation location The foundation can be installed on exposed slabs and beams, and immediately after the foundation is installed, the waterproof layer near the installation location can be repaired (a new waterproof layer is applied), so the foundation can be installed quickly and the foundation The time required for the installation of can be greatly reduced.
 ボルト孔第1穿孔工程において、金属板の第1部分に支持ボルト第1挿通孔を穿孔し、ボルト孔第2穿孔工程において、金属板の第1部分に形成された支持ボルト第1挿通孔の位置にあわせてコンクリート梁に支持ボルト第2挿通孔を穿孔し、支持ボルト固定工程において、支持ボルト第1および第2挿通孔に支持ボルトを挿通し、固定手段を介して支持ボルトを金属板の第1および第2部分とスラブおよび梁とに固定する据え付け基礎施工方法は、支持ボルトを軽量な金属土台の金属板の第2部分とスラブと梁とに固定し、空間にセメント硬化物を充填するとともに、金属土台に金属蓋を固定するだけで基礎を構築することができ、型枠の製作やセメント硬化物の養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。据え付け基礎施工方法は、据え付け基礎の据え付け箇所が既設のコンクリート構造物の屋上や地下に防水機能を施した防水層を備えたスラブや梁である場合でも、据え付け箇所の防水層を取り除いた後の露出したスラブや梁に基礎を設置し、基礎を設置した直後に据え付け箇所近傍の防水層を補修する(新たな防水層を施す)ことができるから、基礎を迅速に設置することができ、基礎の設置に要する時間を大幅に短縮することができる。 In the bolt hole first drilling step, the support bolt first insertion hole is drilled in the first portion of the metal plate, and in the bolt hole second drilling step, the support bolt first insertion hole formed in the first portion of the metal plate. The support bolt second insertion hole is drilled in the concrete beam according to the position, and in the support bolt fixing step, the support bolt is inserted into the first and second insertion holes of the support bolt, and the support bolt is inserted into the metal plate through the fixing means. The fixed foundation construction method to fix the first and second parts to the slab and the beam is to fix the support bolt to the second part of the light metal base metal plate, the slab and the beam, and fill the space with cement hardened material In addition, it is possible to build a foundation simply by fixing a metal lid to a metal base, saving labor, cost, and time required for mold production and curing of hardened cement. Can be simplified, the construction time of that amount can be greatly shortened. Even if the installation location of the installation foundation is a slab or beam with a waterproof layer with a waterproof function on the rooftop or basement of an existing concrete structure, the installation foundation after removing the waterproof layer at the installation location The foundation can be installed on exposed slabs and beams, and immediately after the foundation is installed, the waterproof layer near the installation location can be repaired (a new waterproof layer is applied), so the foundation can be installed quickly and the foundation The time required for the installation of can be greatly reduced.
 金属土台を覆う防水層を設置する防水層設置工程を含み、防水層設置工程において、金属土台の外側に延びる防水層をコンクリート構造物の防水層につなげる据え付け基礎施工方法は、金属土台を覆う防水層をコンクリート構造物の防水層につなげることによって基礎がコンクリート構造物の屋外に設置された場合でも金属土台への水の侵入を防ぐことができ、金属土台に水が進入することによる土台の腐食や強度低下を防ぐことができる。また、コンクリート構造物への水の進入を防ぐことができ、水の進入によるコンクリート構造物の劣化を防ぐことができる。 Including a waterproof layer installation process that installs a waterproof layer that covers the metal base. In the waterproof layer installation process, the installation foundation construction method that connects the waterproof layer that extends outside the metal base to the waterproof layer of the concrete structure is a waterproof that covers the metal base. By connecting the layer to the waterproof layer of the concrete structure, even if the foundation is installed outdoors in the concrete structure, it is possible to prevent water from entering the metal base, and corrosion of the base due to water entering the metal base And strength reduction can be prevented. In addition, water can be prevented from entering the concrete structure, and deterioration of the concrete structure due to water can be prevented.
 金属板の第2部分に第1側板と第2側板とが連接され、セメント硬化物充填工程において、金属板の第2部分と第1側板とに囲繞されたスペースにセメント硬化物を充填する据え付け基礎施工方法は、第1および第2側板が金属板の強度を増加させる補強板として機能するから、金属板の変形や破損がそれら側板によって防止され、優れた強度を有する据え付け基礎を作ることができる。据え付け基礎施工方法は、スペースにセメント硬化物を充填するから、支持ボルトがスペースにおいて露出することがなく、支持ボルトの腐食や固定の緩みを防ぐことができ、ボルトが腐食することによるボルトと金属板との固定の解除を防ぐことができるとともに、ボルトが緩むことによる基礎としての機能の喪失を防ぐことができる。 The first side plate and the second side plate are connected to the second part of the metal plate, and in the cement hardened product filling step, the space surrounded by the second part of the metal plate and the first side plate is filled with the hardened cement product. In the foundation construction method, since the first and second side plates function as reinforcing plates that increase the strength of the metal plate, deformation and breakage of the metal plates can be prevented by these side plates, and an installation foundation having excellent strength can be made. it can. The installation foundation construction method fills the space with cement hardened material, so that the support bolts are not exposed in the space and can prevent corrosion of the support bolts and loosening of the fixing bolts. It is possible to prevent the fixation with the plate from being released, and it is possible to prevent the loss of the function as the foundation due to the loosening of the bolt.
 金属板の第2部分に第1側板と第2側板とが連接され、金属板の第2部分と第1側板とに囲繞されたスペースの頂部に頂板を固定してスペースを塞ぐスペース閉鎖工程を含む据え付け基礎施工方法は、第1および第2側板が金属板の強度を増加させる補強板として機能するから、金属板の変形や破損がそれら側板によって防止され、優れた強度を有する据え付け基礎を作ることができる。据え付け基礎施工方法は、支持ボルトが外部に露出することがなく、スペースへの水の進入を防ぐことができるから、ボルトの腐食を防ぐことができ、ボルトが腐食することによるボルトと金属板との固定の解除を防ぐことができる。据え付け基礎は、スペースの頂部開口を頂部板で塞ぐだけなので、スペースにセメント硬化物を充填する場合と比較し、セメント硬化物を養生する期間を短縮することができ、その分の施工期間を短縮することができる。 A space closing step in which the first side plate and the second side plate are connected to the second portion of the metal plate, and the top plate is fixed to the top of the space surrounded by the second portion of the metal plate and the first side plate to close the space. Since the first and second side plates function as a reinforcing plate that increases the strength of the metal plate, the mounting foundation construction method including the above prevents the deformation and breakage of the metal plate by the side plates and creates a mounting foundation having excellent strength. be able to. The installation foundation construction method prevents the support bolts from being exposed to the outside and prevents water from entering the space. Therefore, the bolts can be prevented from corroding. Can be prevented from being released. Since the installation foundation only covers the top opening of the space with the top plate, compared with the case where the space is filled with hardened cement, the period of curing the hardened cement can be shortened, and the construction period is reduced accordingly. can do.
 セメント硬化物充填工程において、金属管の所定の箇所に形成された充填孔から空間にセメント硬化物を充填する据え付け基礎施工方法は、充填孔を利用して空間にセメント硬化物を充填することができるから、空間にセメント硬化物を確実に充填することができる。据え付け基礎施工方法は、基礎の上に機械機器や建築物を備え付けた場合の基礎にかかる荷重を支持ボルトと硬化したセメント硬化物とに分担させることができ、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持することが可能な基礎を作ることができる。 In the cement hardened material filling process, the installation foundation construction method for filling the cement hardened material into the space from the filling hole formed in the predetermined place of the metal tube is possible to fill the space with the cement hardened material using the filling hole. Therefore, the hardened cement can be reliably filled in the space. In the installation foundation construction method, the load applied to the foundation when a mechanical device or building is installed on the foundation can be shared between the support bolt and the hardened cemented product, which is inadvertent due to the load applied to the foundation. It is possible to create a foundation that can reliably support mechanical devices and buildings without tilting to the ground or collapsing the foundation.
 セメント硬化物充填工程において、金属管の底壁の所定の箇所に形成された確認孔から空間におけるセメント硬化物の充填状態を確認しつつ、空間にセメント硬化物を充填する据え付け基礎施工方法は、確認孔を利用して空間に充填されたセメント硬化物の充填状態を確認することができ、セメント硬化物が空間に偏って充填されることはなく、セメント硬化物を空間全域に満遍なく充填することができる。据え付け基礎施工方法は、基礎の上に機械機器や建築物を備え付けた場合の基礎にかかる荷重を支持ボルトと硬化したセメント硬化物とに分担させることができ、基礎にかかる荷重でそれが不用意に傾斜したり、基礎が崩壊することはなく、機械機器や建築物を確実に支持することが可能な基礎を作ることができる。 In the cement hardened material filling step, the installation foundation construction method for filling the space with the cement hardened material while confirming the filling state of the cement hardened material in the space from the confirmation hole formed in a predetermined position of the bottom wall of the metal tube, The filling state of the cement hardened material filled in the space can be confirmed using the confirmation hole, and the cement hardened product will not be filled in the space, and the cement hardened material should be filled evenly throughout the space. Can do. In the installation foundation construction method, the load applied to the foundation when a mechanical device or building is installed on the foundation can be shared between the support bolt and the hardened cemented product, which is inadvertent due to the load applied to the foundation. It is possible to create a foundation that can reliably support mechanical devices and buildings without tilting to the ground or collapsing the foundation.
一例として示す据え付け基礎の斜視図。The perspective view of the installation foundation shown as an example. 据え付け基礎の上面図。The top view of an installation foundation. 図1のA-A線断面図。FIG. 2 is a sectional view taken along line AA in FIG. 1. 据え付け基礎の施工手順の一例を示す図。The figure which shows an example of the construction procedure of an installation foundation. 図4から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 金属土台の上面図。The top view of a metal foundation. 金属土台の側面図。The side view of a metal foundation. 図5から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 図8から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 他の一例として示す据え付け基礎の斜視図。The perspective view of the installation foundation shown as another example. 据え付け基礎の上面図。The top view of an installation foundation. 図10のB-B線断面図。FIG. 11 is a sectional view taken along line BB in FIG. 10. 据え付け基礎の施工手順の一例を示す図。The figure which shows an example of the construction procedure of an installation foundation. 図13から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 金属土台の上面図。The top view of a metal foundation. 金属土台の側面図。The side view of a metal foundation. 図14から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 他の一例として示す据え付け基礎の斜視図。The perspective view of the installation foundation shown as another example. 図1のA-A線断面図。FIG. 2 is a sectional view taken along line AA in FIG. 1. 金属土台の上面図。The top view of a metal foundation. 金属土台の側面図。The side view of a metal foundation. 図18の据え付け基礎の施工手順の一例を示す図。The figure which shows an example of the construction procedure of the installation foundation of FIG. 図22から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 図23から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG. 図24から続く据え付け基礎の施工手順を示す図。The figure which shows the construction procedure of the installation foundation which continues from FIG.
 一例として示す据え付け基礎10Aの斜視図である図1等の添付の図面を参照し、本発明にかかる据え付け基礎施工方法の詳細を説明すると、以下のとおりである。図1では、コンクリート構造物11に設置された1個の据え付け基礎10Aを図示しているが、基礎10Aの個数を図示のそれに限定するものではなく、一般的には2個以上の基礎10Aがコンクリート構造物11に設置される。 The details of the installation foundation construction method according to the present invention will be described with reference to the attached drawings such as FIG. 1 which is a perspective view of the installation foundation 10A shown as an example. In FIG. 1, one installation foundation 10 </ b> A installed on the concrete structure 11 is illustrated, but the number of foundations 10 </ b> A is not limited to that illustrated, and generally two or more foundations 10 </ b> A are provided. It is installed in the concrete structure 11.
 なお、図2は、据え付け基礎10Aの上面図であり、図3は、図1のA-A線断面図である。図4は、据え付け基礎10Aの施工手順の一例を示す図であり、図5は、図4から続く据え付け基礎10Aの施工手順を示す図である。図6は、金属土台16の上面図であり、図7は、金属土台16の側面図である。図1では、上下方向を矢印X1、横方向を矢印X2で示し、前後方向を矢印X3で示す。図3~図5では、コンクリート構造物11を断面として示し、一部を除く基礎10Aの各部品を断面として示す。 2 is a top view of the mounting base 10A, and FIG. 3 is a cross-sectional view taken along line AA in FIG. FIG. 4 is a diagram showing an example of a construction procedure for the installation foundation 10A, and FIG. 5 is a diagram showing a construction procedure for the installation foundation 10A continued from FIG. FIG. 6 is a top view of the metal base 16, and FIG. 7 is a side view of the metal base 16. In FIG. 1, the vertical direction is indicated by an arrow X1, the horizontal direction is indicated by an arrow X2, and the front-back direction is indicated by an arrow X3. 3 to 5, the concrete structure 11 is shown as a cross section, and each part of the foundation 10A excluding a part is shown as a cross section.
 据え付け基礎10Aは、新設または既設のコンクリート構造物11(建物を含むあらゆる建造物)の屋上や地下の所定の据え付け箇所に設置される。据え付け箇所は、屋上や地下のスラブと梁とが交差する箇所である。ここで、「スラブ」とは、厳密には「床版」を意味するが、この実施の形態では、コンクリート構造物11の地下の床のみならず屋上の床も含む意味で用いる。 The installation foundation 10A is installed on a predetermined installation location on the rooftop or underground of a new or existing concrete structure 11 (any structure including a building). The installation location is where the roof and underground slabs and beams intersect. Here, strictly speaking, “slab” means “floor slab”, but in this embodiment, it is used to include not only the underground floor of the concrete structure 11 but also the roof on the roof.
 この基礎10Aを据え付けるコンクリート構造物11は、図4に示すように、コンクリートスラブ12およびコンクリート梁13と、スラブ12および梁13の上に施設された防水層14と、防水層14の上に施設され押さえコンクリート15とから形成されている。なお、コンクリート構造物11が地下に構築された場合、防水層14と押さえコンクリート15とが存在せず、スラブ12や梁13のみからコンクリート構造物11を形成する場合がある。また、スラブ12や梁13には、図示はしていないが、複数本の鉄筋が埋設されている。 As shown in FIG. 4, the concrete structure 11 on which the foundation 10 </ b> A is installed includes a concrete slab 12 and a concrete beam 13, a waterproof layer 14 provided on the slab 12 and the beam 13, and a facility on the waterproof layer 14. It is formed from the holding concrete 15. In addition, when the concrete structure 11 is constructed | assembled underground, the waterproof layer 14 and the pressing concrete 15 do not exist, and the concrete structure 11 may be formed only from the slab 12 or the beam 13. FIG. Although not shown, the slab 12 and the beam 13 have a plurality of reinforcing bars embedded therein.
 据え付け基礎施工方法では、据え付け基礎10Aがコンクリート構造物11から押さえコンクリート15と防水層14とを取り除いたコンクリートスラブ12およびコンクリート梁13の上に設置される。据え付け基礎施工方法では、金属土台16および金属蓋17、複数本の高さ調節ボルト18、複数本の支持ボルト19、モルタル20(セメント硬化物)、防水層21、成型材22(枠材)の汎用化(規格化)された各基礎構成部品を利用し、それら基礎構成部品を所定のマニュアル化された手順で組み立てることで据え付け基礎10Aを作る。 In the installation foundation construction method, the installation foundation 10A is installed on the concrete slab 12 and the concrete beam 13 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11. In the installation foundation construction method, a metal base 16 and a metal lid 17, a plurality of height adjusting bolts 18, a plurality of support bolts 19, a mortar 20 (hardened cement), a waterproof layer 21, and a molding material 22 (frame material) Using each general-purpose (standardized) basic component and assembling these basic components according to a predetermined manual procedure, the installation base 10A is made.
 それら基礎部品(金属土台16、金属蓋17、調節ボルト18、支持ボルト19、モルタル20、防水層21、成型材22)は、基礎部品製造工場で製造され、工場から設置現場に搬送される。なお、基礎部品製造工場からの出荷時では、後記する金属板24の第2部分31に支持ボルト挿通孔39(ボルト孔)が作られておらず、施工箇所において第2部分31に支持ボルト挿通孔39を穿孔する。また、金属板24の第1部分30には、複数の調節ボルト螺着孔32が基礎部品製造工場においてあらかじめ作られており、それらボルト螺着孔32に高さ調節ボルト18が螺着されている。 These basic parts (metal base 16, metal lid 17, adjustment bolt 18, support bolt 19, mortar 20, waterproof layer 21, molding material 22) are manufactured at the basic part manufacturing factory and transported from the factory to the installation site. At the time of shipment from the base part manufacturing factory, the support bolt insertion hole 39 (bolt hole) is not made in the second portion 31 of the metal plate 24 described later, and the support bolt insertion is made in the second portion 31 at the construction site. Hole 39 is drilled. Further, a plurality of adjustment bolt screw holes 32 are formed in the first part 30 of the metal plate 24 in advance in a basic part manufacturing factory, and the height adjustment bolt 18 is screwed into the bolt screw holes 32. Yes.
 据え付け基礎10Aをコンクリート構造物11の屋上に設置する場合を例として、据え付け基礎施工方法を説明すると、以下のとおりである。最初に、コンクリート構造物11の屋上における基礎10Aの据え付け箇所を位置決めし、その据え付け箇所にマーキングをするとともに、図4に示すように、その据え付け箇所において、コンクリート構造物11から押さえコンクリート15と防水層14とを取り除き、スラブ12および梁13を露出させる。 The installation foundation construction method will be described below, taking the case where the installation foundation 10A is installed on the roof of the concrete structure 11 as an example. First, the installation location of the foundation 10A on the roof of the concrete structure 11 is positioned, and the installation location is marked. At the installation location, as shown in FIG. Layer 14 is removed and slab 12 and beam 13 are exposed.
 なお、図示のコンクリート構造物11は、コンクリートスラブ12およびコンクリート梁13、防水層14および押さえコンクリート15から形成されているが、コンクリート構造物11を図示のそれに限定するものではなく、現在使用されている他の構成のコンクリート構造物すべてにこの据え付け基礎10Aを施工することができる。たとえば、コンクリートスラブおよびコンクリート梁の上にさらに合成樹脂を塗布して樹脂被膜を形成したコンクリート構造物の場合、基礎据え付け箇所では、コンクリート構造物から樹脂被膜と押さえコンクリートと防水層とを取り除き、スラブおよび梁を露出させる。 In addition, although the concrete structure 11 of illustration is formed from the concrete slab 12, the concrete beam 13, the waterproof layer 14, and the pressing concrete 15, the concrete structure 11 is not limited to that of illustration, and is used now. This installation foundation 10A can be applied to all the concrete structures having other configurations. For example, in the case of a concrete structure in which a synthetic resin is further applied to a concrete slab and a concrete beam to form a resin film, at the foundation installation location, the resin film, presser concrete and waterproof layer are removed from the concrete structure, and the slab is removed. And expose the beam.
 コンクリート構造物11からコンクリートスラブ12およびコンクリート梁13を露出させた後、スラブ12や梁13の内部に設置された鉄筋の位置をセンサを利用して測定する。次に、それら鉄筋を避ける位置に支持ボルト19を設置するため、支持ボルト挿通孔39(ボルト孔)の鉄筋を避けた位置の穿孔箇所を金属板24の第2部分31にマーキングする。マーキングに合わせ、ドリルを利用して金属板24の第2部分31の穿孔箇所に支持ボルト挿通孔39を穿孔する(ボルト孔第1穿孔工程)。ボルト挿通孔39を穿孔した後、図5に示すように、スラブ12および梁13における基礎据え付け箇所のマーキングに合わせ、その据え付け箇所に金属土台16を仮設置する(土台仮設置工程)。 After exposing the concrete slab 12 and the concrete beam 13 from the concrete structure 11, the positions of the reinforcing bars installed inside the slab 12 and the beam 13 are measured using a sensor. Next, in order to install the support bolt 19 at a position where the reinforcing bars are avoided, a drilled portion at a position where the reinforcing bolt insertion hole 39 (bolt hole) avoids the reinforcing bars is marked on the second portion 31 of the metal plate 24. In accordance with the marking, a support bolt insertion hole 39 is drilled at the drilled portion of the second portion 31 of the metal plate 24 using a drill (bolt hole first drilling step). After drilling the bolt insertion hole 39, as shown in FIG. 5, the metal base 16 is temporarily installed in the installation location in accordance with the marking of the foundation installation location in the slab 12 and the beam 13 (base temporary installation step).
 金属土台16は、形状や寸法が同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造された後、施工現場に搬送される。金属土台16は、コンクリート構造物11から押さえコンクリート15と防水層14とを取り除いたコンクリートスラブ12およびコンクリート梁13の上に配置される。金属土台16は、図6,7に示すように、中空筒状の金属管23と、平面形状が略矩形の金属板24とから形成されている。金属土台16は、金属板24の上面に金属管23を溶接することによって製造される。金属管23や金属板24は、鉄やアルミニウム、合金等の金属から作られている。金属土台16では、それを形成する金属管23(金属板24の後記する第1部分30を含む)がコンクリート梁13の直上に配置され、金属板24の後記する第2部分31がコンクリートスラブ12の直上に配置される。なお、金属土台16は、鉄筋コンクリート基礎と比較し、コンクリートが省かれている分だけ軽量である。ゆえに、その金属土台16を利用することで、基礎10Aの重量を大幅に軽量化することができる。 The metal base 16 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site and then transported to the construction site. The metal base 16 is disposed on the concrete slab 12 and the concrete beam 13 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11. As shown in FIGS. 6 and 7, the metal base 16 is formed of a hollow cylindrical metal tube 23 and a metal plate 24 having a substantially rectangular planar shape. The metal base 16 is manufactured by welding a metal tube 23 to the upper surface of the metal plate 24. The metal tube 23 and the metal plate 24 are made of metal such as iron, aluminum, and alloy. In the metal base 16, a metal tube 23 (including a first portion 30 described later on the metal plate 24) that forms the metal base 16 is disposed immediately above the concrete beam 13, and a second portion 31 described later on the metal plate 24 is disposed on the concrete slab 12. It is placed immediately above. The metal base 16 is lighter than the reinforced concrete foundation because the concrete is omitted. Therefore, by using the metal base 16, the weight of the foundation 10A can be significantly reduced.
 金属管23は、略矩形の各側板25を有し、その断面が略四角形に成型されている。金属管23は、金属板24の中央部の上面に配置され、その下端縁が金属板24の上面に溶接によって接合(融着)されている。金属管23にはそれら側壁25によって中空スペース26が画成され、金属管23の頂部にはそれら側板25の上端縁に囲繞された頂部開口27が形成されている。金属管23の頂部には、蓋固定ボルト28を螺着する複数の固定ボルト螺着孔29が作られている。固定ボルト螺着孔29には、蓋固定ボルト28が螺着する雌螺子(図示せず)が作られている。 The metal tube 23 has each side plate 25 having a substantially rectangular shape, and its cross section is formed into a substantially rectangular shape. The metal tube 23 is disposed on the upper surface of the central portion of the metal plate 24, and the lower end edge thereof is joined (fused) to the upper surface of the metal plate 24 by welding. A hollow space 26 is defined by the side walls 25 in the metal tube 23, and a top opening 27 surrounded by the upper edge of the side plates 25 is formed at the top of the metal tube 23. A plurality of fixing bolt screw holes 29 for screwing the lid fixing bolts 28 are formed on the top of the metal tube 23. A female screw (not shown) into which the lid fixing bolt 28 is screwed is formed in the fixing bolt screw hole 29.
 金属板24は、金属管23の下端縁から径方向内方(金属管23の横方向内側)へ延びる第1部分30と、金属管23の下端縁から径方向外方(金属管23の横方向外側)へ延びる第2部分31とを有する。第1部分30には、高さ調節ボルト18を螺着する複数の調節ボルト螺着孔32が作られている(図6参照)。調節ボルト螺着孔32には、高さ調節ボルト18が螺着する雌螺子(図示せず)が作られている。なお、第1部分30におけるボルト螺着孔32の個数や穿孔箇所に特に限定はなく、それら孔32を第1部分30の任意の箇所に作ることができる。 The metal plate 24 includes a first portion 30 extending radially inward (laterally inside the metal tube 23) from the lower end edge of the metal tube 23, and radially outward (laterally of the metal tube 23) from the lower end edge of the metal tube 23. And a second portion 31 extending outward in the direction). A plurality of adjustment bolt screw holes 32 into which the height adjustment bolts 18 are screwed are formed in the first portion 30 (see FIG. 6). A female screw (not shown) into which the height adjusting bolt 18 is screwed is formed in the adjusting bolt screw hole 32. There are no particular restrictions on the number of bolt screw holes 32 in the first portion 30 or the location of the holes, and the holes 32 can be made at any location in the first portion 30.
 金属板24の第1部分30の中央部には、モルタル20を充填するための楕円形の充填孔33が作られている。第1部分30の四隅には、モルタル20の充填状態を確認するための確認孔34が作られている(図6参照)。第1部分30には、横方向と縦方向とへ延びる複数の補強板35が設置されている。それら補強板35は、金属管23の内面と金属板24の上面とに溶接によって接合(融着)されている。補強板35は、金属管23および金属板24の強度を増加させる補強材として機能する。 In the central portion of the first portion 30 of the metal plate 24, an elliptical filling hole 33 for filling the mortar 20 is formed. Confirmation holes 34 for confirming the filling state of the mortar 20 are formed at the four corners of the first portion 30 (see FIG. 6). The first portion 30 is provided with a plurality of reinforcing plates 35 extending in the horizontal direction and the vertical direction. The reinforcing plates 35 are joined (fused) to the inner surface of the metal tube 23 and the upper surface of the metal plate 24 by welding. The reinforcing plate 35 functions as a reinforcing material that increases the strength of the metal tube 23 and the metal plate 24.
 金属板24の第2部分31は、横方向へ延びる両端縁(周縁)と、前後方向へ延びる両側縁(周縁)とを有する。第2部分31には、その両端縁に沿って端縁から上方へ起立する矩形の第1側板36が溶接によって接合(融着)され、その両側縁に沿って側縁から上方へ起立する矩形の第1側板36が溶接によって接合(融着)されている。第2部分31(第1部分30を含む)の端縁に連接された第1側板36は、互いに平行して横方向へ延びている。第2部分31の側縁に連接された第1側板36は、互いに平行して前後方向へ延びている。 The second portion 31 of the metal plate 24 has both end edges (periphery) extending in the lateral direction and both side edges (periphery) extending in the front-rear direction. A rectangular first side plate 36 erected upward from the end edge along both end edges thereof is joined (fused) to the second portion 31 by welding, and a rectangular erected upward from the side edge along both side edges thereof. The first side plate 36 is joined (fused) by welding. The first side plates 36 connected to the edge of the second portion 31 (including the first portion 30) extend in the lateral direction in parallel with each other. The first side plates 36 connected to the side edges of the second portion 31 extend in the front-rear direction in parallel with each other.
 金属板24の第2部分31には、第1側板36の間に位置して第2部分31から上方へ起立する矩形の第2側板37が溶接によって接合(融着)されている。第2側板37は、互いに平行して前後方向へ延びている。第1および第2側板36,37は、金属板24の第2部分31の強度を増加させる補強板として機能する。金属土台16には、金属板24の第2部分31と第1側板36とに囲繞されたスペース38が画成されている。スペース38には、モルタル20(セメント硬化物)が充填され、そのモルタル20がスペース38において硬化している(図3参照)。なお、図示はしていないが、金属板24の第2部分31の上面に金属製の頂板が配置され、その頂板がスペース38の開口を塞いでいてもよい。この場合、スペース38にモルタル20は充填されず、頂板が第1および第2側板36,37の上端縁に溶接によって接合(融着)される。 The rectangular second side plate 37 located between the first side plates 36 and rising upward from the second portion 31 is joined (fused) to the second portion 31 of the metal plate 24 by welding. The second side plates 37 extend in the front-rear direction in parallel with each other. The first and second side plates 36 and 37 function as reinforcing plates that increase the strength of the second portion 31 of the metal plate 24. A space 38 surrounded by the second portion 31 of the metal plate 24 and the first side plate 36 is defined in the metal base 16. The space 38 is filled with mortar 20 (cured cement), and the mortar 20 is cured in the space 38 (see FIG. 3). Although not shown, a metal top plate may be disposed on the upper surface of the second portion 31 of the metal plate 24, and the top plate may block the opening of the space 38. In this case, the space 38 is not filled with the mortar 20, and the top plate is joined (fused) to the upper end edges of the first and second side plates 36 and 37 by welding.
 金属板24の第2部分31には、支持ボルト19を挿通する複数の支持ボルト挿通孔39(支持ボルト第1挿通孔)が作られている(図6参照)。支持ボルト挿通孔39は、ドリルによって作られ、金属板24の第2部分31を上下方向へ貫通している。それら支持ボルト挿通孔39は、第2部分31において横方向と前後方向とへす所定間隔で並んでいる。図6では、支持ボルト挿通孔39が8個作られているが、挿通孔39の個数に特に限定はなく、基礎10Aを設置する前に行う構造計算(強度計算)によってその個数が決定される。 A plurality of support bolt insertion holes 39 (support bolt first insertion holes) through which the support bolts 19 are inserted are formed in the second portion 31 of the metal plate 24 (see FIG. 6). The support bolt insertion hole 39 is made by a drill and penetrates the second portion 31 of the metal plate 24 in the vertical direction. The support bolt insertion holes 39 are arranged at predetermined intervals in the second portion 31 in the lateral direction and the front-rear direction. In FIG. 6, eight support bolt insertion holes 39 are formed. However, the number of the insertion holes 39 is not particularly limited, and the number is determined by structural calculation (strength calculation) performed before the foundation 10A is installed. .
 土台仮設置工程において金属土台16を据え付け箇所に仮設置すると、金属管23および金属板24の第1部分30がコンクリート梁13の直上に位置し、金属板24の第2部分31がコンクリートスラブ12の直上に位置するとともに、高さ調節ボルト18のボルトヘッド45がコンクリート梁13の上面に当接する。据え付け箇所に金属土台16を仮設置すると、コンクリート梁13の上面に当接するそれら高さ調節ボルト18に支えられて土台16がスラブ12および梁13の上面に自立する。 When the metal base 16 is temporarily installed at the installation location in the base temporary installation process, the first portion 30 of the metal tube 23 and the metal plate 24 is positioned immediately above the concrete beam 13, and the second portion 31 of the metal plate 24 is the concrete slab 12. And the bolt head 45 of the height adjusting bolt 18 abuts against the upper surface of the concrete beam 13. When the metal base 16 is temporarily installed at the installation location, the base 16 is self-supported on the upper surfaces of the slab 12 and the beam 13 by being supported by the height adjusting bolts 18 that are in contact with the upper surface of the concrete beam 13.
 金属土台16を仮設置した後、土台16の金属板24の第1部分30に対するそれら高さ調節ボルト18の螺着位置を調節し、コンクリートスラブ12やコンクリート梁13の上面からの土台16の設置高さ(高さ寸法)(空間46の高さ寸法)を調節する(設置高さ調節工程)。高さ調節ボルト18は、雄螺子(図示せず)が作られた軸44とボルトヘッド45とから形成された六角ボルトである。高さ調節ボルト18の軸44は、金属板24の第1部分30に作られた調節ボルト螺着孔32にあらかじめ螺着されている。 After temporarily installing the metal base 16, the screwing positions of the height adjusting bolts 18 to the first portion 30 of the metal plate 24 of the base 16 are adjusted, and the base 16 is installed from the upper surface of the concrete slab 12 or the concrete beam 13. Height (height dimension) (height dimension of the space 46) is adjusted (installation height adjusting step). The height adjusting bolt 18 is a hexagonal bolt formed from a shaft 44 on which a male screw (not shown) is made and a bolt head 45. The shaft 44 of the height adjusting bolt 18 is screwed in advance into an adjusting bolt screwing hole 32 formed in the first portion 30 of the metal plate 24.
 ボルトヘッド45において高さ調節ボルト18を反時計回りに回転させると、ボルト18の軸44がボルト螺着孔32の下方へ次第に進むとともに、第1部分30の下面から下方へ延出し、ボルトヘッド45がコンクリート梁13の上面に当接する。それによって、金属土台16をコンクリートスラブ12やコンクリート梁13の上面から上方へ所定の寸法だけ離間させることができる。逆に、高さ調節ボルト18を時計回りに回転させると、ボルト18の軸44がボルト螺着孔32の上方へ次第に進むとともに、第1部分30の下面から上方へ延出する。それによって、金属土台16をコンクリートスラブ12やコンクリート梁13の上面に近づけることができる。 When the height adjusting bolt 18 is rotated counterclockwise in the bolt head 45, the shaft 44 of the bolt 18 gradually advances downward from the bolt screwing hole 32 and extends downward from the lower surface of the first portion 30. 45 abuts on the upper surface of the concrete beam 13. Thereby, the metal base 16 can be spaced apart from the upper surface of the concrete slab 12 or the concrete beam 13 by a predetermined dimension. Conversely, when the height adjusting bolt 18 is rotated clockwise, the shaft 44 of the bolt 18 gradually advances upward from the bolt screw hole 32 and extends upward from the lower surface of the first portion 30. Thereby, the metal base 16 can be brought close to the upper surfaces of the concrete slab 12 and the concrete beam 13.
 高さ調節ボルト18を調節ボルト螺着孔32において回転させることによって金属土台16の金属板24がコンクリートスラブ12やコンクリート梁13の上面から上方へ離間し、スラブ12や梁13の上面と金属板24の下面との間に所定の高さ寸法の空間46が形成される。設置高さ調節工程では、調節ボルト18を調節ボルト螺着孔32において時計回りと反時計回りとのいずれかに回転させ、金属土台16のコンクリートスラブ12やコンクリート梁13の上面からの離間寸法を調節する。金属土台16の金属板24の第1部分30に対するそれら高さ調節ボルト18の螺着位置を調節することによって、空間46の高さ寸法を調節することができ、コンクリートスラブ12やコンクリート梁13の上面からの金属土台16の高さ寸法をボルト18の長さを限度に調節することができる。 By rotating the height adjusting bolt 18 in the adjusting bolt screw hole 32, the metal plate 24 of the metal base 16 is separated upward from the upper surface of the concrete slab 12 or the concrete beam 13, and the upper surface of the slab 12 or the beam 13 and the metal plate are separated. A space 46 having a predetermined height is formed between the lower surface of 24. In the installation height adjusting step, the adjusting bolt 18 is rotated clockwise or counterclockwise in the adjusting bolt screwing hole 32, and the distance from the upper surface of the concrete slab 12 or the concrete beam 13 of the metal base 16 is adjusted. Adjust. The height dimension of the space 46 can be adjusted by adjusting the screwing position of the height adjusting bolts 18 to the first portion 30 of the metal plate 24 of the metal base 16, and the concrete slab 12 and the concrete beam 13 can be adjusted. The height dimension of the metal base 16 from the upper surface can be adjusted up to the length of the bolt 18.
 据え付け基礎施工方法は、高さ調節ボルト18を利用することで据え付け基礎10Aの施工中に金属土台16の高さ寸法を自由に変えることができ、基礎10Aの高さ寸法の変更要求に即座に対応することができる。据え付け基礎施工方法は、複数個の据え付け基礎10Aを設置する場合、それら基礎10Aどうしの高さ寸法を容易に調節することができ、それら基礎10Aの高さ寸法を均一に揃えることができる。 In the installation foundation construction method, the height dimension of the metal base 16 can be freely changed during the construction of the installation foundation 10A by using the height adjusting bolt 18, and immediately the change of the height dimension of the foundation 10A is requested. Can respond. In the installation foundation construction method, when installing a plurality of installation foundations 10A, the height dimensions of the foundations 10A can be easily adjusted, and the height dimensions of the foundations 10A can be made uniform.
 金属土台16の高さ寸法を調節した後、金属板24の支持ボルト挿通孔39の位置にあわせてコンクリートスラブ12の支持ボルト挿通孔40(ボルト孔)の穿孔箇所にマーキングをする。次に、仮設置箇所(据え付け箇所)から金属土台16を一時的に退かした後、ドリルを利用してマーキングした穿孔箇所に支持ボルト挿通孔40を穿孔する(ボルト孔第2穿孔工程)。支持ボルト挿通孔40は、コンクリートスラブ12を上下方向へ貫通している。支持ボルト挿通孔40は、金属土台16をコンクリートスラブ12やコンクリート梁13の上面に載置した場合の、金属板24の第2部分31に形成された支持ボルト挿通孔39の位置と一致する。それら支持ボルト挿通孔40は、コンクリートスラブ12において横方向と前後方向とへ所定間隔で並んでいる。 After adjusting the height dimension of the metal base 16, marking is performed on the drilled portion of the support bolt insertion hole 40 (bolt hole) of the concrete slab 12 according to the position of the support bolt insertion hole 39 of the metal plate 24. Next, after temporarily retracting the metal base 16 from the temporary installation location (installation location), the support bolt insertion hole 40 is drilled in the drilled location marked using a drill (bolt hole second drilling step). The support bolt insertion hole 40 penetrates the concrete slab 12 in the vertical direction. The support bolt insertion hole 40 coincides with the position of the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete slab 12 or the concrete beam 13. These support bolt insertion holes 40 are arranged in the concrete slab 12 at predetermined intervals in the lateral direction and the front-rear direction.
 図8は、図5から続く据え付け基礎10Aの施工手順を示す図であり、図9は、図8から続く据え付け基礎10Aの施工手順を示す図である。ボルト孔第2穿孔工程によってコンクリートスラブ12に支持ボルト挿通孔40を作った後、金属土台16を据え付け箇所に再び仮設置し、図8に示すように、金属板24の第2部分31に作られた支持ボルト挿通孔39に支持ボルト19を挿通するとともに、スラブ12に作られた支持ボルト挿通孔40に支持ボルト19を挿通する。 FIG. 8 is a diagram showing a construction procedure of the installation foundation 10A continuing from FIG. 5, and FIG. 9 is a diagram showing a construction procedure of the installation foundation 10A continuing from FIG. After the support bolt insertion hole 40 is formed in the concrete slab 12 by the bolt hole second drilling step, the metal base 16 is temporarily installed again at the installation location, and the second portion 31 of the metal plate 24 is formed as shown in FIG. The support bolt 19 is inserted into the support bolt insertion hole 39 formed, and the support bolt 19 is inserted into the support bolt insertion hole 40 formed in the slab 12.
 支持ボルト19は、鋼材から作られ、長さや直径が同一の規格化された汎用品であり、複数本のそれらが施工現場以外の基礎部品製造工場で製造された後、施工現場に搬送される。支持ボルト19は、第1固定端部47および第2固定端部48と、第1および第2固定端部47,48の間に延びる中間部49とを有する。支持ボルト19を支持ボルト挿通孔39,40に挿通すると、第1固定端部47がコンクリートスラブ12の上面から上方へ延出し、第2固定端部48がスラブ12の下面から下方へ延出するとともに、中間部49がスラブ12の支持ボルト挿通孔40に位置する。 The support bolts 19 are made of steel and are standardized general-purpose products having the same length and diameter, and a plurality of them are manufactured at a base part manufacturing factory other than the construction site and then transported to the construction site. . The support bolt 19 has a first fixed end portion 47 and a second fixed end portion 48, and an intermediate portion 49 extending between the first and second fixed end portions 47 and 48. When the support bolt 19 is inserted into the support bolt insertion holes 39, 40, the first fixed end portion 47 extends upward from the upper surface of the concrete slab 12, and the second fixed end portion 48 extends downward from the lower surface of the slab 12. At the same time, the intermediate portion 49 is positioned in the support bolt insertion hole 40 of the slab 12.
 次に、支持ボルト19の第1固定端部47のうちの金属板24から上方に延出する部分に六角二重ナット50(固定手段)を螺着するとともに、支持ボルト19の第2固定端部48に六角二重ナット51(固定手段)を螺着し、支持ボルト19を金属板24とコンクリートスラブ12とに固定する(支持ボルト固定工程)。支持ボルト19のそれら固定端部47,48に六角二重ナット50,51を螺着する場合、高さ調節ボルト18によってコンクリートスラブ12やコンクリート梁13の上面からの金属土台16の高さ寸法が既に調節されている。 Next, a hexagonal double nut 50 (fixing means) is screwed onto a portion of the first fixed end portion 47 of the support bolt 19 that extends upward from the metal plate 24, and the second fixed end of the support bolt 19. A hexagonal double nut 51 (fixing means) is screwed to the portion 48, and the support bolt 19 is fixed to the metal plate 24 and the concrete slab 12 (support bolt fixing step). When the hexagonal double nuts 50 and 51 are screwed onto the fixed ends 47 and 48 of the support bolt 19, the height dimension of the metal base 16 from the top surface of the concrete slab 12 or the concrete beam 13 is adjusted by the height adjusting bolt 18. Already adjusted.
 支持ボルト19を金属板24とコンクリートスラブ12とに固定した後、図9に示すように、金属板24の第2部分31と第1側板36とに囲繞されたスペース38にモルタル29(セメント硬化物)を充填し、モルタル20を養生させる。なお、モルタル20の養生期間をなくすため、図示はしていないが、モルタル20の充填に代えて、金属板24の第2部分31の上面に金属製の頂板を配置し、その頂板によってスペース38の頂部開口を塞ぐ(スペース閉鎖工程)。この場合、スペース38にモルタル20は充填せず、頂板を第1および第2側板36,37の上端縁に溶接によって接合(融着)する。 After the support bolt 19 is fixed to the metal plate 24 and the concrete slab 12, as shown in FIG. 9, a mortar 29 (cement hardening) is provided in a space 38 surrounded by the second portion 31 and the first side plate 36 of the metal plate 24. And mortar 20 is cured. In order to eliminate the curing period of the mortar 20, although not shown, a metal top plate is disposed on the upper surface of the second portion 31 of the metal plate 24 instead of filling the mortar 20, and the space 38 is formed by the top plate. The top opening is closed (space closing process). In this case, the space 38 is not filled with the mortar 20 and the top plate is joined (fused) to the upper end edges of the first and second side plates 36 and 37 by welding.
 モルタル20が硬化した後(養生した後)、または、頂板でスペース38の頂部開口を塞いだ後、金属管23と金属板24との交差部に三角柱状の成型材22を設置し、その成型材22を金属管23と金属板24とに接着剤(図示せず)を介して固着する。さらに、押さえコンクリート15とコンクリートスラブ12とに三角柱状の成型材22を設置し、その成型材22を押さえコンクリート15とスラブ12とに接着剤(図示せず)を介して固着する(枠材設置工程)。金属管23と金属板24との交差部に成型材22を設置すると、成型材22が金属管23の外周縁全域を取り囲む。押さえコンクリート15とコンクリートスラブ12とに成型材22を設置すると、成型材22が金属板24の外周縁全域を取り囲み、成型材22がコンクリートスラブ12と金属板24の外周縁との間の空隙を塞ぐ。 After the mortar 20 has hardened (after curing), or after the top opening of the space 38 is closed with a top plate, a triangular prism-shaped molding material 22 is placed at the intersection of the metal tube 23 and the metal plate 24, and the formation is completed. The mold member 22 is fixed to the metal tube 23 and the metal plate 24 via an adhesive (not shown). Further, a triangular prism shaped molding material 22 is installed on the holding concrete 15 and the concrete slab 12, and the molding material 22 is fixed to the holding concrete 15 and the slab 12 with an adhesive (not shown) (frame material installation). Process). When the molding material 22 is installed at the intersection between the metal tube 23 and the metal plate 24, the molding material 22 surrounds the entire outer peripheral edge of the metal tube 23. When the molding material 22 is installed on the holding concrete 15 and the concrete slab 12, the molding material 22 surrounds the entire outer peripheral edge of the metal plate 24, and the molding material 22 creates a gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24. Block it.
 成型材22を設置した後、金属管23の各側板25の外側と金属板24の外側(スペース38の充填されたモルタル20の上面、または、スペース38を塞ぐ頂板の上面)とに防水層21を設置する(防水層設置工程)。防水層設置工程では、複数の薄いアスファルトシートを金属管23の各側板25の外側と金属板24の外側と成型材22の外側とに固着して防水層21を作るとともに、防水層21の金属板24の第2部分31から外側に延びる部分(成型材22に固着されたアスファルトシート)をコンクリート構造物11の防水層14につなげる。 After the molding material 22 is installed, the waterproof layer 21 is formed on the outer side of each side plate 25 of the metal tube 23 and the outer side of the metal plate 24 (the upper surface of the mortar 20 filled with the space 38 or the upper surface of the top plate closing the space 38). (Waterproof layer installation process). In the waterproof layer installation step, a plurality of thin asphalt sheets are fixed to the outside of each side plate 25 of the metal tube 23, the outside of the metal plate 24, and the outside of the molding material 22 to form the waterproof layer 21. A portion (asphalt sheet fixed to the molding material 22) extending outward from the second portion 31 of the plate 24 is connected to the waterproof layer 14 of the concrete structure 11.
 防水層設置工程では、薄いアスファルトシートを複数重ね合わせてアスファルトシート層を作るアスファルト防水を利用している。アスファルトシートは、その接着性によって金属管23の側板25、モルタル20、第1および第2側板36,37、成型材22に固着する。なお、防水層21として、アスファルト防水の他に、塩ビシート防水やゴムシート防水、ウレタン防水やエポキシ防水、FRP防水を利用することもできる。 In the waterproof layer installation process, asphalt waterproofing is used to create an asphalt sheet layer by stacking multiple thin asphalt sheets. The asphalt sheet is fixed to the side plate 25 of the metal tube 23, the mortar 20, the first and second side plates 36 and 37, and the molding material 22 by its adhesiveness. In addition to asphalt waterproofing, PVC sheet waterproofing, rubber sheet waterproofing, urethane waterproofing, epoxy waterproofing, and FRP waterproofing can also be used as the waterproof layer 21.
 据え付け基礎施工方法は、据え付け基礎10Aがコンクリート構造物11の屋外に設置された場合でも防水層21によって金属土台16への水の侵入を防ぐことができ、金属土台16に水が進入することによる土台16の腐食や強度低下を防ぐことができる。また、コンクリートスラブ12やコンクリート梁13への水の進入を防ぐことができ、水の進入によるスラブ12や梁13,コンクリート構造物11の劣化を防ぐことができる。 The installation foundation construction method can prevent water from entering the metal foundation 16 by the waterproof layer 21 even when the installation foundation 10A is installed outdoors of the concrete structure 11, and the water enters the metal foundation 16. Corrosion and strength reduction of the base 16 can be prevented. In addition, it is possible to prevent water from entering the concrete slab 12 and the concrete beam 13, and to prevent deterioration of the slab 12, the beam 13, and the concrete structure 11 due to water entering.
 防水層21を設置した後、コンクリートスラブ12やコンクリート梁13の上面と金属板24の下面との間に形成された空間46にモルタル20(セメント硬化物)を充填する(セメント硬化物充填工程)。セメント硬化物充填工程では、確認孔34から空間46におけるモルタル20の充填状態を確認しつつ、充填孔33から空間46にモルタル20を充填する。空間46では、そこに充填されたモルタル20が硬化し、モルタル20がコンクリートスラブ12やコンクリート梁13の上面と金属板24の第1および第2部分30,31の下面とに接合されているとともに、支持ボルト19に接合されている。 After the waterproof layer 21 is installed, the space 46 formed between the upper surface of the concrete slab 12 or the concrete beam 13 and the lower surface of the metal plate 24 is filled with mortar 20 (cement hardened material) (cement hardened material filling step). . In the cement hardened material filling step, the mortar 20 is filled into the space 46 from the filling hole 33 while confirming the filling state of the mortar 20 in the space 46 from the confirmation hole 34. In the space 46, the mortar 20 filled therein is cured, and the mortar 20 is joined to the upper surfaces of the concrete slab 12 and the concrete beam 13 and the lower surfaces of the first and second portions 30 and 31 of the metal plate 24. The support bolt 19 is joined.
 空間46では、支持ボルト19の第1固定端部47のうちのコンクリートスラブ12の上面と金属板24の第2部分31との間に延びる部分がモルタル20と一体になっている。硬化したモルタル20は、基礎10Aの上(金属蓋17の上)にソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を備え付けた場合の基礎10Aにかかる荷重を支持ボルト19とともに分担する。なお、空間46に充填するセメント硬化物には、モルタル20の他に、コンクリートを利用することもできる。 In the space 46, a portion of the first fixed end portion 47 of the support bolt 19 that extends between the upper surface of the concrete slab 12 and the second portion 31 of the metal plate 24 is integrated with the mortar 20. The hardened mortar 20 is a foundation when a building such as a solar panel, an antenna, a water tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure is mounted on the foundation 10A (on the metal lid 17). The load applied to 10A is shared with the support bolt 19. In addition to the mortar 20, concrete can also be used as the hardened cement filling the space 46.
 据え付け基礎施工方法は、支持ボルト19を金属板24やコンクリートスラブ12に固定した後に充填孔33を利用して空間46にモルタル20を充填することができるから、空間46にモルタル20を確実に充填することができる。据え付け基礎施工方法は、確認孔34を利用して空間46に充填されたモルタル20の充填状態を確認することができるから、モルタル20が空間46に偏って充填されることはなく、モルタル20を空間46全域に満遍なく充填することができる。 In the installation foundation construction method, the space 46 can be filled with the mortar 20 by using the filling hole 33 after the support bolt 19 is fixed to the metal plate 24 or the concrete slab 12, so the space 46 is reliably filled with the mortar 20. can do. Since the installation foundation construction method can check the filling state of the mortar 20 filled in the space 46 using the confirmation hole 34, the mortar 20 is not filled in the space 46 and the mortar 20 is not filled. The entire space 46 can be filled evenly.
 空間46にモルタル20を充填した直後、モルタル20の養生期間を待つことなく、直ちに金属管23の頂部に金属蓋17を嵌め込み、金属管23の頂部開口27を塞ぐ。金属蓋17は、形状や寸法が同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造された後、施工現場に搬送される。金属蓋17は、鉄やアルミニウム、合金等の金属から作られ、その平面形状が略矩形に成型されている。金属蓋17の上面には、図示はしていないが、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を設置するための固定器具が取り付けられている。 Immediately after filling the space 46 with the mortar 20, without waiting for the curing period of the mortar 20, the metal lid 17 is immediately fitted into the top of the metal tube 23 to close the top opening 27 of the metal tube 23. The metal lid 17 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a base part manufacturing factory other than the construction site and then transported to the construction site. The metal lid 17 is made of a metal such as iron, aluminum, or alloy, and its planar shape is molded into a substantially rectangular shape. On the upper surface of the metal lid 17, although not shown in the figure, a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner or other mechanical equipment, or a fixture for installing a building such as a steel tower or steel structure is attached. It has been.
 金属蓋17の下面であって蓋17の周縁の内側には、蓋17を金属管23の頂部に固定するためのアングル材41(鋼材)が溶接によって接合(融着)されている。金属蓋17の下面であって蓋17の周縁には、水切り用アングル材42(鋼材)が溶接によって接合(融着)されている。アングル材41には、蓋固定ボルト28を挿通する固定ボルト挿通孔(図示せず)が作られ、その固定ボルト挿通孔に六角ナット43が溶接によって接合(融着)されている。 An angle member 41 (steel material) for fixing the lid 17 to the top of the metal tube 23 is joined (fused) by welding on the lower surface of the metal lid 17 and inside the periphery of the lid 17. A draining angle material 42 (steel material) is joined (fused) to the lower surface of the metal lid 17 and the periphery of the lid 17 by welding. A fixing bolt insertion hole (not shown) for inserting the lid fixing bolt 28 is made in the angle member 41, and a hexagon nut 43 is joined (fused) to the fixing bolt insertion hole by welding.
 金属管23の頂部に金属蓋17を嵌め込んだ後、金属管23の各側板25の上部に作られた固定ボルト螺着孔29に蓋固定ボルト28を螺着するとともに、金属蓋17のアングル材41の蓋固定ボルト挿通孔にボルト29を挿通し、ボルト挿通孔に取り付けられた六角ナット43にボルト29を螺着して蓋17を金属管25の頂部に固定する(頂部閉鎖工程)(図3援用)。金属管24の頂部開口27は、金属蓋17によって水密に塞がれている。 After fitting the metal lid 17 on the top of the metal tube 23, the lid fixing bolt 28 is screwed into the fixing bolt screwing holes 29 formed on the side plates 25 of the metal tube 23, and the angle of the metal lid 17 is The bolt 29 is inserted into the lid fixing bolt insertion hole of the material 41, and the bolt 29 is screwed to the hexagon nut 43 attached to the bolt insertion hole to fix the lid 17 to the top of the metal tube 25 (top closing step) ( FIG. 3 support). The top opening 27 of the metal tube 24 is watertightly closed by the metal lid 17.
 なお、空隙(空間46の周縁)が成型材22によって塞がれているから、成型材22が硬化前のモルタル20の漏れを防ぐ堤防となり、空間46に充填されたモルタル20が空隙(空間46)から漏れ出すことはなく、モルタル20の充填後に直ちに金属蓋17で頂部開口27を閉塞することができる。据え付け基礎10Aでは、金属管25の頂部に金属蓋17を嵌め込んだ(固定した)直後において空間46に充填されたモルタル20が未硬化状態にあり、管25の頂部に蓋17を固定した後からモルタル20の養生期間が開始する。 In addition, since the space | gap (periphery of the space 46) is obstruct | occluded by the molding material 22, the molding material 22 becomes a bank which prevents the leakage of the mortar 20 before hardening, and the mortar 20 with which the space 46 was filled is a space | gap (space 46). The top opening 27 can be closed with the metal lid 17 immediately after the mortar 20 is filled. In the mounting base 10 </ b> A, the mortar 20 filled in the space 46 is in an uncured state immediately after the metal lid 17 is fitted (fixed) to the top of the metal tube 25, and the lid 17 is fixed to the top of the tube 25. The curing period for mortar 20 begins.
 空間46では、モルタル20の養生期間が経過し、そこに充填されたモルタル20が硬化することで、支持ボルト19の自由端部47のうちのコンクリートスラブ12(コンクリート躯体12)の上面と金属板24との間に延びる部分(ボルト19の自由端部47のうちの板24の下面から下方へ露出する部分)がモルタル20と一体になり、鉄筋モルタルを形成する。以上の各工程が終了すると、図1~3に示す据え付け基礎10Aが完成する。 In the space 46, the curing period of the mortar 20 elapses, and the mortar 20 filled therein is cured, so that the upper surface of the concrete slab 12 (concrete casing 12) in the free end 47 of the support bolt 19 and the metal plate 24 (a portion of the free end 47 of the bolt 19 that is exposed downward from the lower surface of the plate 24) is integrated with the mortar 20 to form a reinforcing bar mortar. When the above steps are completed, the installation base 10A shown in FIGS. 1 to 3 is completed.
 据え付け基礎施工方法は、モルタル20を空間46に充填した直後、モルタル20の養生期間を待つことなく、直ちに金属管23の頂部開口27を金属蓋17によって塞ぎ、基礎10Aを完成させることができるから、空間46に充填したモルタル20の養生期間の分だけ施工期間を短縮することができ、養生期間を待つことなく、複数の基礎10Aの施工を平行して行うことができる。なお、金属板24の第2部分31の上面に金属製の頂板を配置し、その頂板によってスペース38の頂部開口を塞ぐ場合、スペース38にモルタル20を充填する場合と比較し、モルタル20を養生する期間を短縮することができ、その分の施工期間を短縮することができる。 In the installation foundation construction method, immediately after filling the space 46 with the mortar 20, the top opening 27 of the metal tube 23 can be immediately closed with the metal lid 17 without waiting for the curing period of the mortar 20, and the foundation 10A can be completed. The construction period can be shortened by the curing period of the mortar 20 filled in the space 46, and a plurality of foundations 10A can be constructed in parallel without waiting for the curing period. In addition, when a metal top plate is disposed on the upper surface of the second portion 31 of the metal plate 24 and the top opening of the space 38 is blocked by the top plate, the mortar 20 is cured as compared with the case where the space 38 is filled with the mortar 20. The construction period can be shortened, and the construction period can be shortened accordingly.
 据え付け基礎施工方法は、金属土台16をコンクリートスラブ12およびコンクリート梁13の所定の据え付け箇所に仮設置する土台仮設置工程と、仮設置された金属土台16のスラブ12や梁13の上面からの設置高さを調節する設置高さ調節工程と、金属板24に支持ボルト第1挿通孔39を穿孔するボルト孔第1穿孔工程と、金属板24の第2部分31に形成された支持ボルト挿通孔39の位置にあわせてコンクリートスラブ12に支持ボルト挿通孔40を穿孔するボルト孔第2穿孔工程と、それら支持ボルト挿通孔39,40に支持ボルト19を挿通し、六角二重ナット50,51を介して支持ボルト19を金属板24の第2部分31およびスラブ12に固定する支持ボルト固定工程と、金属土台16の外周縁とコンクリート躯体との間に躯体と土台16の外周縁との間の空隙を塞ぐ枠材22を設置する枠材設置工程と、スラブ12や梁13の上面と金属板24の下面との間の空間46にモルタル20を充填するセメント硬化物充填工程と、金属管23の頂部に金属蓋17を固定する金属管閉鎖工程とから基礎10Aが作られ、汎用部品化された各基礎部品を各工程によってユニットシステムとして組み立てるから、施工作業をマニュアル化することができるとともに、施工作業を簡略化することができる。 The installation foundation construction method includes a base temporary installation process in which the metal base 16 is temporarily installed at a predetermined installation location of the concrete slab 12 and the concrete beam 13, and the temporary installation of the metal base 16 from the top surface of the slab 12 and the beam 13. Installation height adjusting step for adjusting the height, first bolt hole drilling step for drilling the support bolt first insertion hole 39 in the metal plate 24, and support bolt insertion hole formed in the second portion 31 of the metal plate 24. Bolt hole second drilling step of drilling the support bolt insertion hole 40 in the concrete slab 12 in accordance with the position of 39, the support bolt 19 is inserted into the support bolt insertion holes 39, 40, and the hexagonal double nuts 50, 51 are A support bolt fixing step for fixing the support bolt 19 to the second portion 31 of the metal plate 24 and the slab 12, and the outer peripheral edge of the metal base 16 and the concrete frame Mortar in the space 46 between the upper surface of the slab 12 and the beam 13 and the lower surface of the metal plate 24, and the frame material installation step of installing the frame material 22 that closes the gap between the frame and the outer peripheral edge of the base 16 The base 10A is made from a cement hardened material filling step for filling 20 and a metal tube closing step for fixing the metal lid 17 to the top of the metal tube 23. Since it is assembled, the construction work can be manualized and the construction work can be simplified.
 据え付け基礎施工方法は、据え付け基礎10Aを形成する際に施工現場において型枠を製作する必要がないことはもちろん、基礎製造工場や施工現場において基礎10Aを作るためにモルタルを養生する必要はなく、支持ボルト19を軽量な金属土台16の金属板24の第2部分31とコンクリートスラブ12とに固定し、空間46にモルタル20を充填した直後に、金属管23に金属蓋17を固定するだけで基礎を構築することができ、型枠の製作やモルタルの養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。 The installation foundation construction method does not need to produce a formwork at the construction site when forming the installation foundation 10A, and it is not necessary to cure the mortar to make the foundation 10A at the foundation manufacturing factory or construction site. The support bolt 19 is fixed to the second portion 31 of the metal plate 24 of the lightweight metal base 16 and the concrete slab 12, and immediately after the space 46 is filled with the mortar 20, the metal lid 17 is simply fixed to the metal tube 23. The foundation can be constructed, and the labor, cost, and time required for mold production and mortar curing can be saved, and the construction work can be simplified and the construction period can be greatly shortened. be able to.
 据え付け基礎施工方法は、支持ボルト19を金属板24の第2部分31とコンクリートスラブ12とに固定し、空間46にモルタル20を充填するから、据え付け基礎10Aをコンクリート構造物11に強固に設置することができ、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることが可能な基礎10Aを作ることができる。据え付け基礎施工方法は、コンクリートスラブ12やコンクリート梁13の上面と金属板24の下面との間の空間46にモルタル20を充填し、基礎10Aの上に機械機器や建築物を備え付けた場合の基礎10Aにかかる荷重を支持ボルト19と硬化したモルタル20とに分担させるから、基礎10Aにかかる荷重でそれが不用意に傾斜したり、基礎10Aが崩壊することはなく、機械機器や建築物を確実に支持することが可能な基礎10Aを作ることができる。 In the installation foundation construction method, the support bolt 19 is fixed to the second portion 31 of the metal plate 24 and the concrete slab 12 and the space 46 is filled with the mortar 20, so that the installation foundation 10A is firmly installed in the concrete structure 11. It is possible to make a foundation 10A that can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air conditioners, and buildings such as steel towers and steel structures. In the installation foundation construction method, the mortar 20 is filled in the space 46 between the upper surface of the concrete slab 12 or the concrete beam 13 and the lower surface of the metal plate 24, and the foundation is provided with mechanical equipment or a building on the foundation 10A. Since the load applied to 10A is shared between the support bolt 19 and the hardened mortar 20, the load applied to the foundation 10A is not inadvertently inclined or the foundation 10A is not collapsed, so that the machinery and the building can be reliably obtained. A base 10A that can be supported on the base can be made.
 据え付け基礎施工方法は、据え付け基礎10Aの据え付け箇所が既設のコンクリート構造物11の屋上や地下に防水機能を施した防水層14を備えたコンクリートスラブ12やコンクリート梁13である場合でも、据え付け箇所の防水層14を取り除いた後の露出したスラブ12や梁13に基礎10Aを設置し、基礎10Aを設置した直後に据え付け箇所近傍の防水層を補修する(新たな防水層21を施す)ことができるから、基礎10Aを迅速に設置することができ、基礎10Aの設置に要する時間を大幅に短縮することができる。 Even if the installation location of the installation foundation 10A is the concrete slab 12 or the concrete beam 13 having the waterproof layer 14 having a waterproof function on the roof or underground of the existing concrete structure 11, the installation location of the installation foundation 10A The foundation 10A can be installed on the exposed slab 12 or beam 13 after the waterproof layer 14 is removed, and the waterproof layer near the installation location can be repaired (a new waterproof layer 21 is applied) immediately after the foundation 10A is installed. Therefore, the foundation 10A can be quickly installed, and the time required for the installation of the foundation 10A can be greatly reduced.
 図10は、他の一例として示す据え付け基礎10Bの斜視図であり、図11は、据え付け基礎10Bの上面図である。図12は、図10のB-B線断面図であり、図13は、据え付け基礎10Bの施工手順の一例を示す図である。図14は、図13から続く据え付け基礎10Bの施工手順を示す図であり、図15は、金属土台16の上面図である。図16は、金属土台16の側面図である。図10では、上下方向を矢印X1、横方向を矢印X2で示し、前後方向を矢印X3で示す。図12~図14では、コンクリート構造物11を断面として示し、一部を除く基礎10Bの各部品を断面として示す。 FIG. 10 is a perspective view of an installation base 10B shown as another example, and FIG. 11 is a top view of the installation base 10B. FIG. 12 is a cross-sectional view taken along the line BB of FIG. 10, and FIG. 13 is a diagram illustrating an example of a construction procedure for the installation base 10B. FIG. 14 is a diagram showing a construction procedure of the mounting base 10B continued from FIG. 13, and FIG. 15 is a top view of the metal base 16. FIG. 16 is a side view of the metal base 16. In FIG. 10, the vertical direction is indicated by an arrow X1, the horizontal direction is indicated by an arrow X2, and the front-rear direction is indicated by an arrow X3. 12 to 14, the concrete structure 11 is shown as a cross section, and each part of the foundation 10B excluding a part is shown as a cross section.
 この据え付け基礎10Bが図1のそれと異なるところは、金属板24の第1部分30とコンクリート梁13とに支持ボルト19(アンカーボルト)を挿通する複数の支持ボルト挿通孔52,53が形成され、それら支持ボルト挿通孔52,53に支持ボルト19が挿通されている点、それら支持ボルト挿通孔52,53に挿通された支持ボルト19が六角二重ナット50,51(固定手段)を介して金属板24の第1部分30とコンクリート梁13とに固定されている点にある。なお、この基礎10Bのその他の構成は、図1の基礎10Aの構成と同一であるから、図1の基礎10Aと同一の符号を付すとともに、図1の基礎10Aの説明を援用することで、この基礎10Bにおけるその他の構成の詳細な説明は省略する。 1 is different from that of FIG. 1 in that a plurality of support bolt insertion holes 52 and 53 for inserting support bolts 19 (anchor bolts) into the first portion 30 of the metal plate 24 and the concrete beam 13 are formed. The point that the support bolt 19 is inserted into the support bolt insertion holes 52 and 53, and the support bolt 19 that is inserted into the support bolt insertion holes 52 and 53 is metal through the hexagonal double nuts 50 and 51 (fixing means). The first portion 30 of the plate 24 is fixed to the concrete beam 13. In addition, since the other structure of this foundation 10B is the same as that of the foundation 10A of FIG. 1, while attaching | subjecting the code | symbol same as the foundation 10A of FIG. 1, and using description of the foundation 10A of FIG. Detailed description of other components in the foundation 10B will be omitted.
 図6を援用しつつ図13,14を参照し、据え付け基礎10Bをコンクリート構造物11の屋上に設置する場合を例として、据え付け基礎施工方法を説明すると、以下のとおりである。据え付け基礎施工方法では、図1のそれと同様に、据え付け基礎10Bがコンクリート構造物11から押さえコンクリート15と防水層14とを取り除いたコンクリートスラブ12およびコンクリート梁13の上に設置される。据え付け基礎施工方法では、金属土台16および金属蓋17、複数本の高さ調節ボルト18、複数本の支持ボルト19、モルタル20、防水層21、成型材22の汎用化(規格化)された各基礎構成部品を所定の手順で組み立てることで据え付け基礎10Bを作る。 Referring to FIGS. 13 and 14 with the aid of FIG. 6, the installation foundation construction method will be described as follows, taking the case where the installation foundation 10B is installed on the roof of the concrete structure 11 as an example. In the installation foundation construction method, the installation foundation 10B is installed on the concrete slab 12 and the concrete beam 13 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11 as in FIG. In the installation foundation construction method, each of the metal base 16 and the metal lid 17, the plurality of height adjustment bolts 18, the plurality of support bolts 19, the mortar 20, the waterproof layer 21, and the molding material 22 that are generalized (standardized). The foundation 10B is made by assembling the foundation components in a predetermined procedure.
 なお、基礎部品製造工場からの出荷時では、後記する金属板24の第2部分31に支持ボルト挿通孔39(ボルト孔)が作られておらず、施工箇所において第2部分31に支持ボルト挿通孔39を穿孔する。また、金属板24の第1部分30には、複数の調節ボルト螺着孔32が基礎部品製造工場においてあらかじめ作られており、それらボルト螺着孔32に高さ調節ボルト18が螺着されている。 At the time of shipment from the base part manufacturing factory, the support bolt insertion hole 39 (bolt hole) is not made in the second portion 31 of the metal plate 24 described later, and the support bolt insertion is made in the second portion 31 at the construction site. Hole 39 is drilled. Further, a plurality of adjustment bolt screw holes 32 are formed in the first part 30 of the metal plate 24 in advance in a basic part manufacturing factory, and the height adjustment bolt 18 is screwed into the bolt screw holes 32. Yes.
 据え付け基礎施工方法では、基礎部品製造工場で製造された汎用部品化された各基礎部品(金属土台16、金属蓋17、高さ調節ボルト18、支持ボルト19、防水層21、成型材22)を工場から施工現場に搬送した後、コンクリート構造物11の屋上における基礎10Bの据え付け箇所を位置決めし、その据え付け箇所にマーキングをする。次に、その据え付け箇所において、コンクリート構造物11から押さえコンクリート15と防水層14とを取り除き、スラブ12および梁13を露出させる(図6援用)。 In the installation foundation construction method, each basic part (metal base 16, metal lid 17, height adjustment bolt 18, support bolt 19, waterproof layer 21, molding material 22) manufactured as a general-purpose part manufactured at a base part manufacturing factory is used. After transporting from the factory to the construction site, the installation location of the foundation 10B on the roof of the concrete structure 11 is positioned, and the installation location is marked. Next, in the installation location, the pressing concrete 15 and the waterproof layer 14 are removed from the concrete structure 11, and the slab 12 and the beam 13 are exposed (in FIG. 6).
 コンクリート構造物11からコンクリートスラブ12およびコンクリート梁13を露出させた後、スラブ12や梁13の内部に設置された鉄筋の位置をセンサを利用して測定する。次に、それら鉄筋を避ける位置に支持ボルト19を設置するため、支持ボルト挿通孔39(ボルト孔)の鉄筋を避けた位置の穿孔箇所を金属板24の第2部分31にマーキングする。マーキングに合わせ、ドリルを利用して金属板24の第2部分31の穿孔箇所に支持ボルト挿通孔39を穿孔する(ボルト孔第1穿孔工程)。ボルト挿通孔39を穿孔した後、図14に示すように、スラブ12および梁13における基礎据え付け箇所のマーキングに合わせ、その据え付け箇所に金属土台16を仮設置する(土台仮設置工程)。 After exposing the concrete slab 12 and the concrete beam 13 from the concrete structure 11, the positions of the reinforcing bars installed inside the slab 12 and the beam 13 are measured using a sensor. Next, in order to install the support bolt 19 at a position where the reinforcing bars are avoided, a drilled portion at a position where the reinforcing bolt insertion hole 39 (bolt hole) avoids the reinforcing bars is marked on the second portion 31 of the metal plate 24. In accordance with the marking, a support bolt insertion hole 39 is drilled at the drilled portion of the second portion 31 of the metal plate 24 using a drill (bolt hole first drilling step). After drilling the bolt insertion hole 39, as shown in FIG. 14, the metal base 16 is temporarily installed at the installation location in accordance with the marking of the foundation installation location on the slab 12 and the beam 13 (base temporary installation step).
 金属土台16は、金属管23と金属板24とから形成されている。金属管23および金属板24の第1部分30は、コンクリート梁13の直上に配置され、金属板24の第2部分31は、コンクリートスラブ12の直上に配置されている。金属管23は、図1の基礎10Aのそれと同一である。なお、金属土台16はコンクリートが省かれている分だけ軽量であり、その土台16を利用することで、基礎10Bの重量を大幅に軽量化することができる。 The metal base 16 is formed of a metal tube 23 and a metal plate 24. The first portion 30 of the metal tube 23 and the metal plate 24 is disposed immediately above the concrete beam 13, and the second portion 31 of the metal plate 24 is disposed immediately above the concrete slab 12. The metal tube 23 is the same as that of the foundation 10A of FIG. In addition, the metal base 16 is light as much as the concrete is omitted, and by using the base 16, the weight of the foundation 10B can be significantly reduced.
 金属板24は、金属管23の下端縁から径方向内方へ延びる第1部分30と、金属管23の下端縁から径方向外方へ延びる第2部分31とを有する。第1部分30には、高さ調節ボルト18を螺着する複数の調節ボルト螺着孔32が作られている(図13参照)。第1部分30の中央部には、モルタル20を充填するための楕円形の充填孔33が作られ、第1部分30の四隅には、モルタル20の充填状態を確認するための確認孔34が作られている(図15参照)。第1部分30には、横方向と縦方向とへ延びる複数の補強板35が設置されている。 The metal plate 24 has a first portion 30 extending radially inward from the lower end edge of the metal tube 23 and a second portion 31 extending radially outward from the lower end edge of the metal tube 23. The first portion 30 is formed with a plurality of adjustment bolt screw holes 32 into which the height adjustment bolts 18 are screwed (see FIG. 13). An elliptical filling hole 33 for filling the mortar 20 is formed at the center of the first part 30, and confirmation holes 34 for checking the filling state of the mortar 20 are formed at the four corners of the first part 30. (See FIG. 15). The first portion 30 is provided with a plurality of reinforcing plates 35 extending in the horizontal direction and the vertical direction.
 金属板24の第2部分31には、その両端縁に沿って端縁から上方へ起立する第1側板36が設置され、その両側縁に沿って側縁から上方へ起立する第1側板36が設置されている。さらに、第1側板36の間に位置して第2部分31から上方へ起立する第2側板37が設置されている。金属板24の第2部分31と第1側板36とに囲繞されたスペース38には、モルタル20(セメント硬化物)が充填され、そのモルタル20がスペース38において硬化している(図12参照)。なお、図1の基礎10Aと同様に、金属板24の第2部分31の上面に金属製の頂板が配置され、その頂板がスペース38の開口を塞いでいてもよい。 The second portion 31 of the metal plate 24 is provided with a first side plate 36 that rises upward from the end edge along both end edges, and the first side plate 36 that rises upward from the side edge along both side edges. is set up. Further, a second side plate 37 that is located between the first side plates 36 and stands upward from the second portion 31 is provided. A space 38 surrounded by the second portion 31 and the first side plate 36 of the metal plate 24 is filled with mortar 20 (hardened cement), and the mortar 20 is hardened in the space 38 (see FIG. 12). . As with the base 10 </ b> A of FIG. 1, a metal top plate may be disposed on the upper surface of the second portion 31 of the metal plate 24, and the top plate may block the opening of the space 38.
 金属板24の第1部分30には、支持ボルト19を挿通する複数の支持ボルト挿通孔52(支持ボルト第1挿通孔)が作られている。支持ボルト挿通孔52は、ドリルによって作られ、金属板24の第1部分30を上下方向へ貫通している。それら支持ボルト挿通孔52は、第1部分30において横方向と前後方向とへ所定間隔で並んでいる。図13では、支持ボルト挿通孔52が4個作られているが、挿通孔52の個数に特に限定はなく、基礎10Bを設置する前に行う構造計算(強度計算)によってその個数が決定される。金属板24の第2部分31には、支持ボルト19を挿通する複数の支持ボルト挿通孔39(支持ボルト第1挿通孔)が作られている。それら支持ボルト挿通孔39は、第2部分31において横方向と前後方向とへ所定間隔で並んでいる。 A plurality of support bolt insertion holes 52 (support bolt first insertion holes) through which the support bolts 19 are inserted are formed in the first portion 30 of the metal plate 24. The support bolt insertion hole 52 is made by a drill and penetrates the first portion 30 of the metal plate 24 in the vertical direction. The support bolt insertion holes 52 are arranged in the first portion 30 in the lateral direction and the front-rear direction at a predetermined interval. In FIG. 13, four support bolt insertion holes 52 are formed, but the number of insertion holes 52 is not particularly limited, and the number is determined by structural calculation (strength calculation) performed before the foundation 10B is installed. . A plurality of support bolt insertion holes 39 (support bolt first insertion holes) through which the support bolts 19 are inserted are formed in the second portion 31 of the metal plate 24. These support bolt insertion holes 39 are arranged in the second portion 31 at predetermined intervals in the lateral direction and the front-rear direction.
 土台仮設置工程において金属土台16を据え付け箇所に仮設置すると、金属管23および金属板24の第1部分30がコンクリート梁13の直上に位置し、金属板24の第2部分31がコンクリートスラブ12の直上に位置するとともに、高さ調節ボルト18のボルトヘッド45がコンクリート梁13の上面に当接する。据え付け箇所に金属土台16を仮設置すると、コンクリート梁13の上面に当接する高さそれら調節ボルト18に支えられて土台16がスラブ12および梁13の上面に自立する。 When the metal base 16 is temporarily installed at the installation location in the base temporary installation process, the first portion 30 of the metal tube 23 and the metal plate 24 is positioned immediately above the concrete beam 13, and the second portion 31 of the metal plate 24 is the concrete slab 12. And the bolt head 45 of the height adjusting bolt 18 abuts against the upper surface of the concrete beam 13. When the metal base 16 is temporarily installed at the installation location, the base 16 is self-supporting on the upper surfaces of the slab 12 and the beam 13 supported by the height adjusting bolts 18 that contact the upper surface of the concrete beam 13.
 金属土台16を仮設置した後、土台16の金属板24の第1部分30に対するそれら高さ調節ボルト18の螺着位置を調節し、コンクリートスラブ12やコンクリート梁13の上面からの土台16の設置高さ(高さ寸法)(空間46の高さ寸法)を調節する(設置高さ調節工程)。据え付け基礎施工方法は、高さ調節ボルト18を利用することで基礎10Bの施工中に金属土台16の高さ寸法を自由に変えることができ、基礎10Bの高さ寸法の変更要求に即座に対応することができる。据え付け基礎施工方法は、複数個のそれらを設置する場合にそれら基礎10Bどうしの高さ寸法を容易に調節することができ、それら基礎10Bの高さ寸法を均一に揃えることができる。 After temporarily installing the metal base 16, the screwing positions of the height adjusting bolts 18 to the first portion 30 of the metal plate 24 of the base 16 are adjusted, and the base 16 is installed from the upper surface of the concrete slab 12 or the concrete beam 13. Height (height dimension) (height dimension of the space 46) is adjusted (installation height adjusting step). The installation foundation construction method can use the height adjustment bolt 18 to freely change the height of the metal base 16 during construction of the foundation 10B, and immediately respond to the request for changing the height of the foundation 10B. can do. The installation foundation construction method can easily adjust the height dimensions of the foundations 10B when a plurality of them are installed, and can make the height dimensions of the foundations 10B uniform.
 金属土台16の高さ寸法を調節した後、金属板24の支持ボルト挿通孔39,52の位置にあわせてコンクリートスラブ12およびコンクリート梁13の支持ボルト挿通孔40,53(ボルト孔)の穿孔箇所にマーキングをする。次に、仮設置箇所(据え付け箇所)から金属土台16を一時的に退かした後、ドリルを利用してマーキングした穿孔箇所に支持ボルト挿通孔40,53を穿孔する(ボルト孔第2穿孔工程)。 After adjusting the height dimension of the metal base 16, drilling locations of the support bolt insertion holes 40 and 53 (bolt holes) of the concrete slab 12 and the concrete beam 13 in accordance with the positions of the support bolt insertion holes 39 and 52 of the metal plate 24. Mark on. Next, the metal base 16 is temporarily retracted from the temporary installation location (installation location), and then the support bolt insertion holes 40 and 53 are drilled in the drilled locations marked using a drill (bolt hole second drilling step). ).
 支持ボルト挿通孔40は、コンクリートスラブ12を上下方向へ貫通している。支持ボルト挿通孔40は、金属土台16をコンクリートスラブ12やコンクリート梁13の上面に載置した場合の、金属板24の第2部分31に形成された支持ボルト挿通孔39の位置と一致する。それら支持ボルト挿通孔40は、コンクリートスラブ12において横方向と前後方向とへ所定間隔で並んでいる。 The support bolt insertion hole 40 penetrates the concrete slab 12 in the vertical direction. The support bolt insertion hole 40 coincides with the position of the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete slab 12 or the concrete beam 13. These support bolt insertion holes 40 are arranged in the concrete slab 12 at predetermined intervals in the lateral direction and the front-rear direction.
 支持ボルト挿通孔53は、コンクリート梁13を上下方向へ貫通している。支持ボルト挿通孔53は、金属土台16をコンクリートスラブ12やコンクリート梁13の上面に載置した場合の、金属板24の第1部分30に形成された支持ボルト挿通孔52の位置と一致する。それら支持ボルト挿通孔53は、コンクリート梁13において横方向と前後方向とへ所定間隔で並んでいる。 The support bolt insertion hole 53 penetrates the concrete beam 13 in the vertical direction. The support bolt insertion hole 53 coincides with the position of the support bolt insertion hole 52 formed in the first portion 30 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete slab 12 or the concrete beam 13. These support bolt insertion holes 53 are arranged at predetermined intervals in the lateral direction and the front-rear direction in the concrete beam 13.
 ボルト孔第2穿孔工程によってコンクリートスラブ12やコンクリート梁13に支持ボルト挿通孔40,53を作った後、金属土台16を据え付け箇所に再び仮設置し、図14に示すように、金属板24の第1および第2部分30,31に作られた支持ボルト挿通孔39,52に支持ボルト19を挿通するとともに、スラブ12および梁13に作られた支持ボルト挿通孔40,53に支持ボルト19を挿通する。 After the support bolt insertion holes 40 and 53 are formed in the concrete slab 12 and the concrete beam 13 by the second bolt hole drilling step, the metal base 16 is temporarily installed again at the installation location, and as shown in FIG. The support bolt 19 is inserted into the support bolt insertion holes 39 and 52 formed in the first and second portions 30 and 31, and the support bolt 19 is inserted into the support bolt insertion holes 40 and 53 formed in the slab 12 and the beam 13. Insert.
 支持ボルト19を支持ボルト挿通孔39,40,52,53に挿通すると、第1固定端部47がコンクリートスラブ12およびコンクリート梁13の上面から上方へ延出し、第2固定端部48がスラブ12および梁13の下面から下方へ延出するとともに、中間部49がスラブ12および梁13の支持ボルト挿通孔40,53に位置する。次に、支持ボルト19の第1固定端部47のうちの金属板24から上方に延出する部分に六角二重ナット50(固定手段)を螺着するとともに、支持ボルト19の第2固定端部48に六角二重ナット51(固定手段)を螺着し、支持ボルト19を金属板24とコンクリートスラブ12とコンクリート梁13とに固定する(支持ボルト固定工程)。支持ボルト19のそれら固定端部47,48に六角二重ナット50,51を螺着する場合、高さ調節ボルト18によってコンクリートスラブ12やコンクリート梁13の上面からの金属土台16の高さ寸法が既に調節されている。 When the support bolt 19 is inserted into the support bolt insertion holes 39, 40, 52, 53, the first fixed end 47 extends upward from the upper surfaces of the concrete slab 12 and the concrete beam 13, and the second fixed end 48 is the slab 12. The intermediate portion 49 is positioned in the support bolt insertion holes 40 and 53 of the slab 12 and the beam 13. Next, a hexagonal double nut 50 (fixing means) is screwed onto a portion of the first fixed end portion 47 of the support bolt 19 that extends upward from the metal plate 24, and the second fixed end of the support bolt 19. A hexagonal double nut 51 (fixing means) is screwed to the portion 48, and the support bolt 19 is fixed to the metal plate 24, the concrete slab 12, and the concrete beam 13 (support bolt fixing step). When the hexagonal double nuts 50 and 51 are screwed onto the fixed ends 47 and 48 of the support bolt 19, the height dimension of the metal base 16 from the top surface of the concrete slab 12 or the concrete beam 13 is adjusted by the height adjusting bolt 18. Already adjusted.
 図17は、図14から続く据え付け基礎10Bの施工手順を示す図である。支持ボルト19を金属板24とコンクリートスラブ12とコンクリート梁13とに固定した後、図17に示すように、金属板24の第2部分31と第1側板36とに囲繞されたスペース38にモルタル29を充填し、モルタル20を養生させる。なお、図1の基礎10Aと同様に、モルタル20の充填に代えて、金属板24の第2部分31の上面に金属製の頂板を配置し、その頂板によってスペース38の頂部開口を塞いでもよい(スペース閉鎖工程)。 FIG. 17 is a diagram showing a construction procedure of the installation foundation 10B continued from FIG. After the support bolt 19 is fixed to the metal plate 24, the concrete slab 12, and the concrete beam 13, the mortar is placed in the space 38 surrounded by the second portion 31 and the first side plate 36 of the metal plate 24 as shown in FIG. 29 is filled and the mortar 20 is cured. 1, instead of filling the mortar 20, a metal top plate may be disposed on the upper surface of the second portion 31 of the metal plate 24, and the top opening of the space 38 may be blocked by the top plate. (Space closing process).
 モルタル20が硬化した後(養生した後)、または、頂板でスペース38の頂部開口を塞いだ後、金属管23と金属板24との交差部に三角柱状の成型材22を設置し、その成型材22を金属管23と金属板24とに接着剤(図示せず)を介して固着する。さらに、押さえコンクリート15とコンクリートスラブ12とに三角柱状の成型材22を設置し、その成型材22を押さえコンクリート15とスラブ12とに接着剤(図示せず)を介して固着する(枠材設置工程)。金属管23と金属板24との交差部に成型材22を設置すると、成型材22が金属管23の外周縁全域を取り囲む。押さえコンクリート15とコンクリートスラブ12とに成型材22を設置すると、成型材22が金属板24の外周縁全域を取り囲み、成型材22がコンクリートスラブ12と金属板24の外周縁との間の空隙を塞ぐ。 After the mortar 20 has hardened (after curing), or after the top opening of the space 38 is closed with a top plate, a triangular prism-shaped molding material 22 is placed at the intersection of the metal tube 23 and the metal plate 24, and the formation is completed. The mold member 22 is fixed to the metal tube 23 and the metal plate 24 via an adhesive (not shown). Further, a triangular prism shaped molding material 22 is installed on the holding concrete 15 and the concrete slab 12, and the molding material 22 is fixed to the holding concrete 15 and the slab 12 with an adhesive (not shown) (frame material installation). Process). When the molding material 22 is installed at the intersection between the metal tube 23 and the metal plate 24, the molding material 22 surrounds the entire outer peripheral edge of the metal tube 23. When the molding material 22 is installed on the holding concrete 15 and the concrete slab 12, the molding material 22 surrounds the entire outer peripheral edge of the metal plate 24, and the molding material 22 creates a gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24. Block it.
 成型材22を設置した後、金属管23の各側板25の外側と金属板24の外側(スペース38の充填されたモルタル20の上面、または、スペース38を塞ぐ頂板の上面)とに防水層21を設置する(防水層設置工程)。防水層設置工程では、図1の基礎10Aと同様に、複数の薄いアスファルトシートを金属管23の各側板25の外側と金属板24の外側と成型材22の外側とに固着して防水層21を作るとともに、防水層21の金属板24の第2部分31から外側に延びる部分(成型材22に固着されたアスファルトシート)をコンクリート構造物11の防水層14につなげる。 After the molding material 22 is installed, the waterproof layer 21 is formed on the outer side of each side plate 25 of the metal tube 23 and the outer side of the metal plate 24 (the upper surface of the mortar 20 filled with the space 38 or the upper surface of the top plate closing the space 38). (Waterproof layer installation process). In the waterproof layer installation step, a plurality of thin asphalt sheets are fixed to the outer side of each side plate 25 of the metal tube 23, the outer side of the metal plate 24, and the outer side of the molding material 22, as in the base 10 </ b> A of FIG. 1. And a portion (asphalt sheet fixed to the molding material 22) extending outward from the second portion 31 of the metal plate 24 of the waterproof layer 21 is connected to the waterproof layer 14 of the concrete structure 11.
 据え付け基礎施工方法は、据え付け基礎10Bがコンクリート構造物11の屋外に設置された場合でも防水層21によって金属土台16への水の侵入を防ぐことができ、金属土台16に水が進入することによる土台16の腐食や強度低下を防ぐことができる。また、コンクリートスラブ12やコンクリート梁13への水の進入を防ぐことができ、水の進入によるスラブ12や梁13,コンクリート構造物11の劣化を防ぐことができる。 The installation foundation construction method can prevent water from entering the metal foundation 16 by the waterproof layer 21 even when the installation foundation 10 </ b> B is installed outdoors of the concrete structure 11, and the water enters the metal foundation 16. Corrosion and strength reduction of the base 16 can be prevented. In addition, it is possible to prevent water from entering the concrete slab 12 and the concrete beam 13, and to prevent deterioration of the slab 12, the beam 13, and the concrete structure 11 due to water entering.
 防水層21を設置した後、空間46にモルタル20を充填する(セメント硬化物充填工程)。セメント硬化物充填工程では、確認孔34から空間46におけるモルタル20の充填状態を確認しつつ、充填孔33から空間46にモルタル20を充填する。空間46では、そこに充填されたモルタル20が硬化し、モルタル20がコンクリートスラブ12やコンクリート梁13の上面と金属板24の第1および第2部分30,31の下面とに接合されているとともに、支持ボルト19に接合されている。 After installing the waterproof layer 21, the space 46 is filled with mortar 20 (cement hardened material filling step). In the cement hardened material filling step, the mortar 20 is filled into the space 46 from the filling hole 33 while confirming the filling state of the mortar 20 in the space 46 from the confirmation hole 34. In the space 46, the mortar 20 filled therein is cured, and the mortar 20 is joined to the upper surfaces of the concrete slab 12 and the concrete beam 13 and the lower surfaces of the first and second portions 30 and 31 of the metal plate 24. The support bolt 19 is joined.
 空間46では、支持ボルト19の第1固定端部47のうちのコンクリートスラブ12の上面と金属板24の第2部分31との間に延びる部分がモルタル20と一体になっている。硬化したモルタル20は、基礎10Aの上(金属蓋17の上)にソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を備え付けた場合の基礎10Aにかかる荷重を支持ボルト19とともに分担する。 In the space 46, a portion of the first fixed end portion 47 of the support bolt 19 that extends between the upper surface of the concrete slab 12 and the second portion 31 of the metal plate 24 is integrated with the mortar 20. The hardened mortar 20 is a foundation when a building such as a solar panel, an antenna, a water tank, a septic tank, an air conditioner, or a building such as a steel tower or a steel structure is mounted on the foundation 10A (on the metal lid 17). The load applied to 10A is shared with the support bolt 19.
 据え付け基礎施工方法は、支持ボルト19を金属板24やコンクリートスラブ12に固定した後に充填孔33を利用して空間46にモルタル20を充填することができるから、空間46にモルタル20を確実に充填することができる。据え付け基礎施工方法は、確認孔34を利用して空間46に充填されたモルタル20の充填状態を確認することができるから、モルタル20が空間46に偏って充填されることはなく、モルタル20を空間46全域に満遍なく充填することができる。 In the installation foundation construction method, the space 46 can be filled with the mortar 20 by using the filling hole 33 after the support bolt 19 is fixed to the metal plate 24 or the concrete slab 12, so the space 46 is reliably filled with the mortar 20. can do. Since the installation foundation construction method can check the filling state of the mortar 20 filled in the space 46 using the confirmation hole 34, the mortar 20 is not filled in the space 46 and the mortar 20 is not filled. The entire space 46 can be filled evenly.
 空間46にモルタル20を充填した直後、モルタル20の養生期間を待つことなく、直ちに金属管23の頂部に金属蓋17を嵌め込み、金属管23の頂部開口27を塞ぐ。金属管23の頂部に金属蓋17を嵌め込んだ後、金属管23の各側板25の上部に作られた固定ボルト螺着孔29に蓋固定ボルト28を螺着するとともに、金属蓋17のアングル材41の蓋固定ボルト挿通孔にボルト29を挿通し、ボルト挿通孔に取り付けられた六角ナット43にボルト29を螺着して蓋17を金属管25の頂部に固定する(頂部閉鎖工程)(図12援用)。金属管24の頂部開口27は、金属蓋17によって水密に塞がれている。 Immediately after filling the space 46 with the mortar 20, without waiting for the curing period of the mortar 20, the metal lid 17 is immediately fitted into the top of the metal tube 23 to close the top opening 27 of the metal tube 23. After fitting the metal lid 17 on the top of the metal tube 23, the lid fixing bolt 28 is screwed into the fixing bolt screwing holes 29 formed on the side plates 25 of the metal tube 23, and the angle of the metal lid 17 is The bolt 29 is inserted into the lid fixing bolt insertion hole of the material 41, and the bolt 29 is screwed to the hexagon nut 43 attached to the bolt insertion hole to fix the lid 17 to the top of the metal tube 25 (top closing step) ( FIG. 12 is used). The top opening 27 of the metal tube 24 is watertightly closed by the metal lid 17.
 なお、空隙(空間46の周縁)が成型材22によって塞がれているから、成型材22が硬化前のモルタル20の漏れを防ぐ堤防となり、空間46に充填されたモルタル20が空隙(空間46)から漏れ出すことはなく、モルタル20の充填後に直ちに金属蓋17で頂部開口27を閉塞することができる。据え付け基礎10Bでは、金属管25の頂部に金属蓋17を嵌め込んだ(固定した)直後において空間46に充填されたモルタル20が未硬化状態にあり、管25の頂部に蓋17を固定した後からモルタル20の養生期間が開始する。 In addition, since the space | gap (periphery of the space 46) is obstruct | occluded by the molding material 22, the molding material 22 becomes a bank which prevents the leakage of the mortar 20 before hardening, and the mortar 20 with which the space 46 was filled is a space | gap (space 46). The top opening 27 can be closed with the metal lid 17 immediately after the mortar 20 is filled. In the mounting base 10 </ b> B, the mortar 20 filled in the space 46 is in an uncured state immediately after the metal lid 17 is fitted (fixed) to the top of the metal tube 25, and the lid 17 is fixed to the top of the tube 25. The curing period for mortar 20 begins.
 空間46では、モルタル20の養生期間が経過し、そこに充填されたモルタル20が硬化することで、支持ボルト19の自由端部47のうちのコンクリートスラブ12(コンクリート躯体12)およびコンクリート梁13(コンクリート躯体13)の上面と金属板24との間に延びる部分(ボルト19の自由端部47のうちの板24の下面から下方へ露出する部分)がモルタル20と一体になり、鉄筋モルタルを形成する。以上の各工程が終了すると、図10~12に示す据え付け基礎10Bが完成する。 In the space 46, the curing period of the mortar 20 elapses, and the mortar 20 filled therein is hardened, whereby the concrete slab 12 (concrete frame 12) and the concrete beam 13 ( A portion extending between the upper surface of the concrete housing 13) and the metal plate 24 (a portion of the free end portion 47 of the bolt 19 exposed downward from the lower surface of the plate 24) is integrated with the mortar 20 to form a reinforcing bar mortar. To do. When the above steps are completed, the installation base 10B shown in FIGS. 10 to 12 is completed.
 据え付け基礎施工方法は、モルタル20を空間46に充填した直後、モルタル20の養生期間を待つことなく、直ちに金属管23の頂部開口27を金属蓋17によって塞ぎ、基礎10Bを完成させることができるから、空間46に充填したモルタル20の養生期間の分だけ施工期間を短縮することができ、養生期間を待つことなく、複数の基礎10Bの施工を平行して行うことができる。なお、金属板24の第2部分31の上面に金属製の頂板を配置し、その頂板によってスペース38の頂部開口を塞ぐ場合、スペース38にモルタル20を充填する場合と比較し、モルタル20を養生する期間を短縮することができ、その分の施工期間を短縮することができる。 In the installation foundation construction method, immediately after filling the space 46 with the mortar 20, the top opening 27 of the metal tube 23 can be immediately closed with the metal lid 17 without waiting for the curing period of the mortar 20, and the foundation 10B can be completed. The construction period can be shortened by the curing period of the mortar 20 filled in the space 46, and a plurality of foundations 10B can be constructed in parallel without waiting for the curing period. In addition, when a metal top plate is disposed on the upper surface of the second portion 31 of the metal plate 24 and the top opening of the space 38 is blocked by the top plate, the mortar 20 is cured as compared with the case where the space 38 is filled with the mortar 20. The construction period can be shortened, and the construction period can be shortened accordingly.
 据え付け基礎施工方法は、金属土台16をコンクリートスラブ12およびコンクリート梁13の所定の据え付け箇所に仮設置する土台仮設置工程と、仮設置された金属土台16のスラブ12や梁13の上面からの設置高さを調節する設置高さ調節工程と、金属板24に支持ボルト第1挿通孔39,52を穿孔するボルト孔第1穿孔工程と、金属板24の第1および第2部分30,31に形成された支持ボルト挿通孔39,52の位置にあわせてスラブ12および梁13に支持ボルト挿通孔40,53を穿孔するボルト孔第2穿孔工程と、それら支持ボルト挿通孔39,40,52,53に支持ボルト19を挿通し、六角二重ナット50,51を介して支持ボルト19を金属板24の第1および第2部分30,31とスラブ12および梁13とに固定する支持ボルト固定工程と、金属土台16の外周縁とコンクリート躯体との間に躯体と土台16の外周縁との間の空隙を塞ぐ枠材22を設置する枠材設置工程と、スラブ12や梁13の上面と金属板24の下面との間の空間46にモルタル20を充填するセメント硬化物充填工程と、金属管23の頂部に金属蓋17を固定する金属管閉鎖工程とから基礎10Bが作られ、汎用部品化された各基礎部品を各工程によってユニットシステムとして組み立てるから、施工作業をマニュアル化することができるとともに、施工作業を簡略化することができる。 The installation foundation construction method includes a base temporary installation process in which the metal base 16 is temporarily installed at a predetermined installation location of the concrete slab 12 and the concrete beam 13, and the temporary installation of the metal base 16 from the top surface of the slab 12 and the beam 13. Installation height adjustment process for adjusting the height, bolt hole first drilling process for drilling support bolt first insertion holes 39, 52 in the metal plate 24, and first and second portions 30, 31 of the metal plate 24 A bolt hole second drilling step of drilling the support bolt insertion holes 40, 53 in the slab 12 and the beam 13 in accordance with the positions of the formed support bolt insertion holes 39, 52, and the support bolt insertion holes 39, 40, 52, 53, the support bolt 19 is inserted, and the support bolt 19 is inserted into the first and second portions 30 and 31 of the metal plate 24 via the hexagonal double nuts 50 and 51, the slab 12 and the beam 13 A supporting bolt fixing step for fixing the frame member 22, a frame member installing step for installing a frame member 22 for closing a gap between the outer peripheral edge of the metal base 16 and the outer periphery of the concrete base 16 and the outer peripheral edge of the base 16; From the cement hardened material filling step of filling the space 46 between the upper surface of the beam 13 and the lower surface of the metal plate 24 with the mortar 20 and the metal tube closing step of fixing the metal lid 17 to the top of the metal tube 23, the foundation 10B. Since each basic part made into a general-purpose part is assembled as a unit system by each process, the construction work can be made manual and the construction work can be simplified.
 据え付け基礎施工方法は、据え付け基礎10Bを形成する際に施工現場において型枠を製作する必要がないことはもちろん、基礎製造工場や施工現場において基礎10Bを作るためにモルタルを養生する必要はなく、支持ボルト19を軽量な金属土台16の金属板24の第1および第2部分30,31とコンクリートスラブ12およびコンクリート梁13とに固定し、空間46にモルタル20を充填した直後に、金属管23に金属蓋17を固定するだけで基礎を構築することができ、型枠の製作やモルタルの養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。 The installation foundation construction method does not need to produce a formwork at the construction site when forming the installation foundation 10B, and it is not necessary to cure the mortar to make the foundation 10B at the foundation manufacturing factory or construction site. Immediately after the support bolt 19 is fixed to the first and second portions 30 and 31 of the metal plate 24 of the lightweight metal base 16, the concrete slab 12 and the concrete beam 13, and the space 46 is filled with the mortar 20, the metal tube 23 is provided. It is possible to construct a foundation simply by fixing the metal lid 17 to the base, and save labor, cost, and time required for mold production and mortar curing, and simplify construction work. The construction period of minutes can be greatly shortened.
 据え付け基礎施工方法は、支持ボルト19を金属板24の第1および第2部分30,31とコンクリートスラブ12およびコンクリート梁13とに固定し、空間46にモルタル20を充填するから、据え付け基礎10Bをコンクリート構造物11に強固に設置することができ、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることが可能な基礎10Bを作ることができる。据え付け基礎施工方法は、コンクリートスラブ12やコンクリート梁13の上面と金属板24の下面との間の空間46にモルタル20を充填し、基礎10Bの上に機械機器や建築物を備え付けた場合の基礎10Bにかかる荷重を支持ボルト19と硬化したモルタル20とに分担させるから、基礎10Bにかかる荷重でそれが不用意に傾斜したり、基礎10Bが崩壊することはなく、機械機器や建築物を確実に支持する基礎10Bを作ることができる。 In the installation foundation construction method, the support bolt 19 is fixed to the first and second portions 30 and 31 of the metal plate 24, the concrete slab 12 and the concrete beam 13, and the mortar 20 is filled in the space 46. A foundation 10B that can be firmly installed on the concrete structure 11 and can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air-conditioning equipment, and buildings such as steel towers and steel structures. Can be made. The installation foundation construction method is a foundation in which a mortar 20 is filled in a space 46 between the upper surface of the concrete slab 12 or the concrete beam 13 and the lower surface of the metal plate 24, and mechanical equipment or a building is provided on the foundation 10B. Since the load applied to 10B is shared by the support bolt 19 and the hardened mortar 20, the load applied to the foundation 10B is not inadvertently inclined or the foundation 10B is not collapsed. It is possible to make a base 10B that supports the above.
 据え付け基礎施工方法は、据え付け基礎10Bの据え付け箇所が既設のコンクリート構造物11の屋上や地下に防水機能を施した防水層14を備えたコンクリートスラブ12やコンクリート梁13である場合でも、据え付け箇所の防水層14を取り除いた後の露出したスラブ12や梁13に基礎10Bを設置し、基礎10Bを設置した直後に据え付け箇所近傍の防水層を補修する(新たな防水層21を施す)ことができるから、基礎10Bを迅速に設置することができ、基礎10Bの設置に要する時間を大幅に短縮することができる。 Even if the installation location of the installation foundation 10B is the concrete slab 12 or the concrete beam 13 having the waterproof layer 14 having a waterproof function on the roof or underground of the existing concrete structure 11, the installation location of the installation foundation 10B The foundation 10B is installed on the exposed slab 12 and the beam 13 after removing the waterproof layer 14, and the waterproof layer near the installation location can be repaired (a new waterproof layer 21 is applied) immediately after the foundation 10B is installed. Therefore, the foundation 10B can be installed quickly, and the time required for the installation of the foundation 10B can be greatly shortened.
 図18は、他の一例として示す据え付け基礎10Cの斜視図であり、図19は、図18のC-C線断面図であり、図20は、金属土台16の上面図である。図21は、金属土台16の側面図である。図18では、上下方向を矢印X1、横方向を矢印X2で示し、前後方向を矢印X3で示す。コンクリート構造物11は、コンクリート躯体12(コンクリートスラブやコンクリート梁を含む)と、コンクリート躯体12の上に施設された防水層14と、防水層14の上に施設されたコンクリート層15とから形成されている。コンクリート躯体12には、図示はしていないが、複数本の鉄筋が埋設されている。 18 is a perspective view of an installation base 10C as another example, FIG. 19 is a cross-sectional view taken along the line CC of FIG. 18, and FIG. 20 is a top view of the metal base 16. FIG. FIG. 21 is a side view of the metal base 16. In FIG. 18, the vertical direction is indicated by an arrow X1, the horizontal direction is indicated by an arrow X2, and the front-back direction is indicated by an arrow X3. The concrete structure 11 is formed of a concrete frame 12 (including a concrete slab and a concrete beam), a waterproof layer 14 provided on the concrete frame 12, and a concrete layer 15 provided on the waterproof layer 14. ing. Although not shown, the concrete housing 12 has a plurality of reinforcing bars embedded therein.
 据え付け基礎10Cは、それがコンクリート構造物11から押さえコンクリート15と防水層14とを取り除いたコンクリート躯体12の上に設置される。据え付け基礎10Cは、金属土台16(土台)および金属蓋17(蓋)、複数本の高さ調節ボルト18、複数本の支持ボルト19(アンカーボルト)、モルタル20(セメント硬化物)、防水層21、成型材22(枠材)の汎用化(規格化)された各基礎構成部品を利用し、それら基礎構成部品を所定の手順で組み立てることから作られている。 The installation foundation 10 </ b> C is installed on a concrete frame 12 in which the pressing concrete 15 and the waterproof layer 14 are removed from the concrete structure 11. The mounting base 10C includes a metal base 16 (base) and a metal lid 17 (lid), a plurality of height adjusting bolts 18, a plurality of support bolts 19 (anchor bolts), a mortar 20 (hardened cement), and a waterproof layer 21. The basic material is made by using each of the basic components that are generalized (standardized) of the molding material 22 (frame material) and assembling the basic components in a predetermined procedure.
 金属土台16は、形状や寸法が同一の規格化された汎用品であり、複数個のそれらが施工現場以外の基礎部品製造工場で製造された後、施工現場に搬送される。金属土台16は、コンクリート構造物11から押さえコンクリート15と防水層14とを取り除いたコンクリート躯体12の上に配置されている。金属土台16は、中空筒状の金属管23(管材)と、平面形状が略矩形の金属板24(底板)とから形成されている。金属土台16は、金属板24の上面に金属管23を溶接することによって製造される。金属管23や金属板24は、鉄やアルミニウム、合金等の金属から作られている。なお、金属土台16は、鉄筋コンクリート基礎と比較し、コンクリートが省かれている分だけ軽量である。ゆえに、その金属土台16を利用することで、基礎10Cの重量を大幅に軽量化することができる。 The metal base 16 is a standardized general-purpose product having the same shape and dimensions, and a plurality of them are manufactured at a basic part manufacturing factory other than the construction site and then transported to the construction site. The metal base 16 is disposed on a concrete frame 12 obtained by removing the pressing concrete 15 and the waterproof layer 14 from the concrete structure 11. The metal base 16 is formed of a hollow cylindrical metal tube 23 (tube material) and a metal plate 24 (bottom plate) having a substantially rectangular planar shape. The metal base 16 is manufactured by welding a metal tube 23 to the upper surface of the metal plate 24. The metal tube 23 and the metal plate 24 are made of metal such as iron, aluminum, and alloy. The metal base 16 is lighter than the reinforced concrete foundation because the concrete is omitted. Therefore, by using the metal base 16, the weight of the foundation 10C can be significantly reduced.
 金属管23は、略矩形の各側板25を有し、その断面が略四角形に成型されている。金属管23は、金属板24の中央部の上面に配置され、その下端縁が金属板24の上面に溶接によって接合(融着)されている。金属管23にはそれら側壁25によって中空スペース26が画成され、金属管23の頂部にはそれら側板25の上端縁に囲繞された頂部開口27が形成されている。金属管23の頂部には、蓋固定ボルト28を螺着する複数の固定ボルト螺着孔29が作られている。固定ボルト螺着孔29には、蓋固定ボルト28が螺着する雌螺子(図示せず)が作られている。 The metal tube 23 has each side plate 25 having a substantially rectangular shape, and its cross section is formed into a substantially rectangular shape. The metal tube 23 is disposed on the upper surface of the central portion of the metal plate 24, and the lower end edge thereof is joined (fused) to the upper surface of the metal plate 24 by welding. A hollow space 26 is defined by the side walls 25 in the metal tube 23, and a top opening 27 surrounded by the upper edge of the side plates 25 is formed at the top of the metal tube 23. A plurality of fixing bolt screw holes 29 for screwing the lid fixing bolts 28 are formed on the top of the metal tube 23. A female screw (not shown) into which the lid fixing bolt 28 is screwed is formed in the fixing bolt screw hole 29.
 金属板24は、金属管23の下端縁から径方向内方へ延びる第1部分30と、金属管23の下端縁から径方向外方へ延びる第2部分31とを有する。第2部分31には、高さ調節ボルト18を螺着する複数の調節ボルト螺着孔32が作られている(図20参照)。調節ボルト螺着孔32には、高さ調節ボルト18が螺着する雌螺子(図示せず)が作られている。なお、第2部分31におけるボルト螺着孔32の個数や穿孔箇所に特に限定はなく、それら孔32を第2部分31の任意の箇所に作ることができる。金属板24の第1部分30の中央部には、モルタル20を充填するための楕円形の充填孔33が作られている。第2部分31には、モルタル20の充填状態を確認するための確認孔34が作られている(図20参照)。 The metal plate 24 has a first portion 30 extending radially inward from the lower end edge of the metal tube 23 and a second portion 31 extending radially outward from the lower end edge of the metal tube 23. A plurality of adjustment bolt screw holes 32 into which the height adjustment bolts 18 are screwed are formed in the second portion 31 (see FIG. 20). A female screw (not shown) into which the height adjusting bolt 18 is screwed is formed in the adjusting bolt screw hole 32. There are no particular limitations on the number of bolt screw holes 32 and the drilling locations in the second portion 31, and the holes 32 can be made at any location in the second portion 31. An elliptical filling hole 33 for filling the mortar 20 is formed in the central portion of the first portion 30 of the metal plate 24. A confirmation hole 34 for confirming the filling state of the mortar 20 is formed in the second portion 31 (see FIG. 20).
 金属板24の第2部分31は、横方向へ延びる両端縁(周縁)と、前後方向へ延びる両側縁(周縁)とを有する。金属管23と金属板24の第2部分31とは、上下方向へ延びる複数の補強板35が設置されている。それら補強板35は、金属管23の外面と金属板24の上面とに溶接によって接合(融着)されている。補強板35は、金属管23および金属板24の強度を増加させる補強材として機能する。 The second portion 31 of the metal plate 24 has both end edges (periphery) extending in the lateral direction and both side edges (periphery) extending in the front-rear direction. The metal pipe 23 and the second portion 31 of the metal plate 24 are provided with a plurality of reinforcing plates 35 extending in the vertical direction. The reinforcing plates 35 are joined (fused) to the outer surface of the metal tube 23 and the upper surface of the metal plate 24 by welding. The reinforcing plate 35 functions as a reinforcing material that increases the strength of the metal tube 23 and the metal plate 24.
 金属板24の第2部分31には、支持ボルト19を挿通する複数の支持ボルト挿通孔39(ボルト孔)が作られている。支持ボルト挿通孔39は、ドリルによって作られ、金属板24の第2部分31を上下方向へ貫通している。それら支持ボルト挿通孔39は、第2部分31において横方向と前後方向とへ所定間隔で並んでいる。図20では、支持ボルト挿通孔39が4個作られているが、挿通孔39の個数に特に限定はなく、基礎10Cを設置する前に行う構造計算(強度計算)によってその個数が決定される。 A plurality of support bolt insertion holes 39 (bolt holes) through which the support bolts 19 are inserted are formed in the second portion 31 of the metal plate 24. The support bolt insertion hole 39 is made by a drill and penetrates the second portion 31 of the metal plate 24 in the vertical direction. These support bolt insertion holes 39 are arranged in the second portion 31 at predetermined intervals in the lateral direction and the front-rear direction. In FIG. 20, four support bolt insertion holes 39 are formed, but the number of insertion holes 39 is not particularly limited, and the number is determined by structural calculation (strength calculation) performed before the foundation 10C is installed. .
 なお、コンクリート躯体12の基礎据え付け位置には、それら支持ボルト19を挿通する複数の支持ボルト挿通孔40(ボルト孔)が作られている。支持ボルト挿通孔40は、ドリルによって作られ、コンクリート躯体12に埋設された鉄筋を避けた状態で、コンクリート躯体12において上下方向へ延びている。支持ボルト挿通孔40は、金属土台16をコンクリート躯体12の上面に載置した場合の、金属板24の第2部分31に形成された支持ボルト挿通孔39の位置と一致する。それら支持ボルト挿通孔40は、コンクリート躯体12において横方向と前後方向とへ所定間隔で並んでいる。 A plurality of support bolt insertion holes 40 (bolt holes) through which the support bolts 19 are inserted are formed at the foundation installation position of the concrete frame 12. The support bolt insertion hole 40 is made by a drill and extends in the vertical direction in the concrete housing 12 while avoiding the reinforcing bars embedded in the concrete housing 12. The support bolt insertion hole 40 coincides with the position of the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 when the metal base 16 is placed on the upper surface of the concrete frame 12. The support bolt insertion holes 40 are arranged at predetermined intervals in the lateral direction and the front-rear direction in the concrete housing 12.
 金属蓋17は、形状や寸法が同一の規格化された汎用品であり、鉄やアルミニウム、合金等の金属から作られ、その平面形状が略矩形に成型されている。金属蓋17の下面であって蓋17の周縁の内側には、蓋17を金属管23の頂部に固定するためのアングル材41(鋼材)が溶接によって接合(融着)されている。アングル材41には、蓋固定ボルト28を挿通する固定ボルト挿通孔(図示せず)が作られ、その固定ボルト挿通孔に六角ナット43が溶接によって接合(融着)されている。 The metal lid 17 is a standardized general-purpose product having the same shape and dimensions, made of metal such as iron, aluminum, and alloy, and its planar shape is formed into a substantially rectangular shape. An angle member 41 (steel material) for fixing the lid 17 to the top of the metal tube 23 is joined (fused) by welding on the lower surface of the metal lid 17 and inside the periphery of the lid 17. A fixing bolt insertion hole (not shown) for inserting the lid fixing bolt 28 is made in the angle member 41, and a hexagon nut 43 is joined (fused) to the fixing bolt insertion hole by welding.
 金属蓋17は、アングル材41に作られた固定ボルト挿通孔に挿通された蓋固定ボルト28とアングル材41に取り付けられた六角ナット43とによって金属管24の頂部に固定され、金属管24の頂部開口27を水密に塞いでいる。金属蓋17の上面には、図示はしていないが、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を設置するための固定器具が取り付けられている。 The metal lid 17 is fixed to the top of the metal tube 24 by a lid fixing bolt 28 inserted into a fixing bolt insertion hole made in the angle member 41 and a hex nut 43 attached to the angle member 41. The top opening 27 is closed watertight. On the upper surface of the metal lid 17, although not shown in the figure, a solar panel, an antenna, a water storage tank, a septic tank, an air conditioner or other mechanical equipment, or a fixture for installing a building such as a steel tower or steel structure is attached. It has been.
 高さ調節ボルト18は、雄螺子が作られた軸44とボルトヘッド45とから形成された六角ボルトである。高さ調節ボルト18の軸44は、金属板24の第2部分31に作られた調節ボルト螺着孔32にあらかじめ螺着されている。ボルトヘッド45において高さ調節ボルト18を反時計回りに回転させると、ボルト18の軸44がボルト螺着孔32の下方へ次第に進むとともに、第2部分31の下面から下方へ延出し、ボルトヘッド45がコンクリート梁13の上面に当接する。それによって、金属土台16をコンクリート躯体12の上面から上方へ所定の寸法だけ離間させることができる。逆に、高さ調節ボルト18を時計回りに回転させると、ボルト18の軸44がボルト螺着孔32の上方へ次第に進むとともに、第2部分31の下面から上方へ延出する。それによって、金属土台16をコンクリート躯体12の上面に近づけることができる。 The height adjusting bolt 18 is a hexagonal bolt formed from a shaft 44 on which a male screw is made and a bolt head 45. The shaft 44 of the height adjusting bolt 18 is screwed in advance into an adjusting bolt screwing hole 32 formed in the second portion 31 of the metal plate 24. When the height adjusting bolt 18 is rotated counterclockwise in the bolt head 45, the shaft 44 of the bolt 18 gradually advances downward from the bolt screwing hole 32 and extends downward from the lower surface of the second portion 31. 45 abuts on the upper surface of the concrete beam 13. Thereby, the metal base 16 can be spaced apart from the upper surface of the concrete housing 12 by a predetermined dimension. On the other hand, when the height adjusting bolt 18 is rotated clockwise, the shaft 44 of the bolt 18 gradually advances upward from the bolt screw hole 32 and extends upward from the lower surface of the second portion 31. Thereby, the metal base 16 can be brought close to the upper surface of the concrete housing 12.
 高さ調節ボルト18を調節ボルト螺着孔32において回転させることによって金属土台16の金属板24がコンクリート躯体12の上面から上方へ離間し、躯体12の上面と金属板24の下面との間に所定の高さ寸法の空間46が形成される。金属土台16の金属板24の第2部分31に対するそれら高さ調節ボルト18の螺着位置を調節することによって、空間46の高さ寸法を調節することができ、コンクリート躯体12の上面からの金属土台16の高さ寸法をボルト18の長さを限度に調節することができる。 By rotating the height adjusting bolt 18 in the adjusting bolt screwing hole 32, the metal plate 24 of the metal base 16 is separated upward from the upper surface of the concrete housing 12, and between the upper surface of the housing 12 and the lower surface of the metal plate 24. A space 46 having a predetermined height is formed. The height dimension of the space 46 can be adjusted by adjusting the screwing position of the height adjusting bolts 18 with respect to the second portion 31 of the metal plate 24 of the metal base 16, and the metal from the upper surface of the concrete housing 12 can be adjusted. The height dimension of the base 16 can be adjusted up to the length of the bolt 18.
 支持ボルト19は、長さや直径が同一の規格化された汎用品であり、鋼材から作られ、金属板24の第2部分31に作られた支持ボルト挿通孔39に挿通され、さらに、コンクリート躯体12に作られた支持ボルト挿通孔40に挿通されている。支持ボルト19は、コンクリート躯体12の上面から上方へ延びる自由端部47と、躯体12に固定された固定端部48とを有する。 The support bolt 19 is a standardized general-purpose product having the same length and diameter. The support bolt 19 is made of steel, and is inserted into a support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24. 12 is inserted into the support bolt insertion hole 40 made in the shape 12. The support bolt 19 has a free end portion 47 extending upward from the upper surface of the concrete housing 12 and a fixed end portion 48 fixed to the housing 12.
 支持ボルト19の自由端部47は、金属板24に開口する支持ボルト挿通孔39に挿通され、六角ナット50(固定手段)を介して金属板24に固定されている。六角ナット50は、自由端部47の金属板24から上方に延出する部分に取り付けられている。支持ボルト19の固定端部48は、コンクリート躯体12の支持ボルト挿通孔40に注入された樹脂アンカー(固定手段)(図示せず)によって挿通孔40に固定されている。支持ボルト19の自由端部47に六角ナット50を螺着する場合、高さ調節ボルト18によってコンクリート躯体12の上面からの金属土台16の高さ寸法が既に調節されている。 The free end portion 47 of the support bolt 19 is inserted into a support bolt insertion hole 39 opened in the metal plate 24 and is fixed to the metal plate 24 via a hexagon nut 50 (fixing means). The hexagon nut 50 is attached to a portion of the free end 47 that extends upward from the metal plate 24. The fixed end 48 of the support bolt 19 is fixed to the insertion hole 40 by a resin anchor (fixing means) (not shown) injected into the support bolt insertion hole 40 of the concrete housing 12. When the hexagon nut 50 is screwed onto the free end 47 of the support bolt 19, the height dimension of the metal base 16 from the upper surface of the concrete housing 12 has already been adjusted by the height adjusting bolt 18.
 モルタル20は、コンクリート躯体12の上面と金属板24の下面との間に形成された空間46に充填されている。モルタル20は、金属板24に形成された充填孔33から充填される。空間46では、そこに充填されたモルタル20が硬化し、モルタル20がコンクリート躯体12の上面と金属板24の第1および第2部分30,31の下面とに接合されているとともに、支持ボルト19に接合されている。 The mortar 20 is filled in a space 46 formed between the upper surface of the concrete housing 12 and the lower surface of the metal plate 24. The mortar 20 is filled from a filling hole 33 formed in the metal plate 24. In the space 46, the mortar 20 filled therein is cured, and the mortar 20 is joined to the upper surface of the concrete housing 12 and the lower surfaces of the first and second portions 30 and 31 of the metal plate 24, and the support bolt 19. It is joined to.
 空間46では、支持ボルト19の自由端部47のうちのコンクリート躯体12の上面と金属板24の第2部分31との間に延びる部分がモルタル20と一体になっている。硬化したモルタル20は、基礎10Cの上(金属蓋17の上)にソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を備え付けた場合の基礎10Cにかかる荷重を支持ボルト19とともに分担する。 In the space 46, the portion of the free end 47 of the support bolt 19 that extends between the upper surface of the concrete housing 12 and the second portion 31 of the metal plate 24 is integrated with the mortar 20. The hardened mortar 20 is a foundation when a building such as a solar panel, an antenna, a water storage tank, a septic tank, a mechanical device such as an air conditioner, or a building such as a steel tower or steel structure is mounted on the foundation 10C (on the metal lid 17). The load applied to 10C is shared with the support bolt 19.
 金属管23と金属板24との交差部および押さえコンクリート15とコンクリートスラブ12とには、成型材22(枠材)が設置されている。成型材22は、金属管23やスラブ12、押さえコンクリート15に接着剤(図示せず)を介して固着されている。成型材22は、金属管23外周縁全域を取り囲むとともに、金属土台16の外周縁(金属板24の外周縁)とコンクリートスラブ12(コンクリート構造物)との間に設置されて金属板24の外周縁全域を取り囲んでいる。成型材22は、コンクリートスラブ12と金属板24の外周縁との間の空隙を塞いでいる。 The molding material 22 (frame material) is installed in the crossing part of the metal pipe 23 and the metal plate 24 and the holding concrete 15 and the concrete slab 12. The molding material 22 is fixed to the metal tube 23, the slab 12, and the pressing concrete 15 with an adhesive (not shown). The molding material 22 surrounds the entire outer periphery of the metal tube 23 and is placed between the outer periphery of the metal base 16 (the outer periphery of the metal plate 24) and the concrete slab 12 (concrete structure). Surrounds the entire periphery. The molding material 22 closes the gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24.
 防水層21は、金属管23の各側板25の外側に設置されて側板25全域を覆うとともに、金属板24の外側に設置されて金属板24全域を覆っている。防水層21には、薄いアスファルトシートを複数重ね合わせてアスファルトシート層を作るアスファルト防水が利用されている。アスファルトシートは、その接着性によって金属管23の側板25、モルタル20、成型材22に固着している。防水層21の金属板24の第2部分31から外側に延びる部分(成型材22に固着されたアスファルトシート)は、コンクリート構造物11の防水層14につながっている。 The waterproof layer 21 is installed on the outside of each side plate 25 of the metal tube 23 to cover the entire side plate 25, and is installed on the outside of the metal plate 24 to cover the entire metal plate 24. As the waterproof layer 21, asphalt waterproofing is used in which a plurality of thin asphalt sheets are stacked to form an asphalt sheet layer. The asphalt sheet is fixed to the side plate 25 of the metal tube 23, the mortar 20, and the molding material 22 due to its adhesiveness. A portion extending outward from the second portion 31 of the metal plate 24 of the waterproof layer 21 (asphalt sheet fixed to the molding material 22) is connected to the waterproof layer 14 of the concrete structure 11.
 図22は、据え付け基礎10Cの施工手順の一例を示す図であり、図23は、図22から続く据え付け基礎10Cの施工手順を示す図である。図24は、図23から続く据え付け基礎10Cの施工手順を示す図であり、図25は、図24から続く据え付け基礎10Cの施工手順を示す図である。図22~図25では、コンクリート構造物11を断面として示し、一部を除く基礎10Cの各部品を断面として示す。図22~図25を参照し、据え付け基礎10Cをコンクリート構造物11の屋上に設置する場合を例として、基礎10Cの施工手順を説明すると、以下のとおりである。 FIG. 22 is a diagram showing an example of the construction procedure of the installation foundation 10C, and FIG. 23 is a diagram showing the construction procedure of the installation foundation 10C continued from FIG. FIG. 24 is a diagram showing a construction procedure of the installation foundation 10C continuing from FIG. 23, and FIG. 25 is a diagram showing a construction procedure of the installation foundation 10C continuing from FIG. 22 to 25, the concrete structure 11 is shown as a cross section, and each part of the foundation 10C excluding a part is shown as a cross section. With reference to FIGS. 22 to 25, the construction procedure of the foundation 10C will be described as follows, taking as an example the case where the installation foundation 10C is installed on the roof of the concrete structure 11.
 なお、基礎部品製造工場からの出荷時では、金属板24の第2部分31に支持ボルト挿通孔39(ボルト孔)が作られておらず、施工箇所において第2部分31に支持ボルト挿通孔39を穿孔する。また、金属板24の第2部分31には、複数の調節ボルト螺着孔32が基礎部品製造工場においてあらかじめ作られており、それらボルト螺着孔32に高さ調節ボルト18が螺着されている。 At the time of shipment from the base part manufacturing factory, the support bolt insertion hole 39 (bolt hole) is not made in the second portion 31 of the metal plate 24, and the support bolt insertion hole 39 is formed in the second portion 31 at the construction site. Perforate. In addition, a plurality of adjustment bolt screw holes 32 are formed in the second part 31 of the metal plate 24 in advance in a basic part manufacturing factory, and the height adjustment bolt 18 is screwed into the bolt screw holes 32. Yes.
 基礎部品製造工場で製造された汎用部品化された各基礎部品(金属土台16(土台)、金属蓋17(蓋)、高さ調節ボルト18、支持ボルト19(アンカーボルト)、防水層21、成型材22(枠材))を工場から施工現場に搬送した後、コンクリート構造物11の屋上における基礎10Cの据え付け箇所を位置決めし、その据え付け箇所にマーキングをする。次に、その据え付け箇所において、コンクリート構造物11から押さえコンクリート15と防水層14とを取り除き、コンクリート躯体12を露出させる。 Each basic part (metal base 16 (base), metal lid 17 (lid), height adjustment bolt 18, support bolt 19 (anchor bolt), waterproof layer 21, After the mold material 22 (frame material) is transported from the factory to the construction site, the installation location of the foundation 10C on the roof of the concrete structure 11 is positioned, and the installation location is marked. Next, the pressing concrete 15 and the waterproof layer 14 are removed from the concrete structure 11 at the installation location, and the concrete frame 12 is exposed.
 コンクリート構造物11からコンクリート躯体12を露出させた後、躯体12の内部に設置された鉄筋の位置をセンサを利用して測定する。次に、それら鉄筋を避ける位置に支持ボルト19を設置するため、支持ボルト挿通孔39(ボルト孔)の鉄筋を裂けた位置の穿孔箇所を金属板24の第2部分31にマーキングする。マーキングに合わせ、ドリルを利用して金属板24の第2部分31の穿孔箇所に支持ボルト挿通孔39を穿孔する(挿通孔ボルト孔穿孔工程)。ボルト挿通孔39を穿孔した後、図23に示すように、コンクリート躯体12における基礎据え付け箇所のマーキングに合わせ、その据え付け箇所に金属土台16を仮設置する(土台仮設置工程)。 After exposing the concrete housing 12 from the concrete structure 11, the position of the reinforcing bar installed in the housing 12 is measured using a sensor. Next, in order to install the support bolt 19 at a position where these reinforcing bars are avoided, a drilled portion at a position where the reinforcing bar of the support bolt insertion hole 39 (bolt hole) is torn is marked on the second portion 31 of the metal plate 24. In accordance with the marking, a support bolt insertion hole 39 is drilled in a drilling portion of the second portion 31 of the metal plate 24 using a drill (insertion hole bolt hole drilling step). After drilling the bolt insertion hole 39, as shown in FIG. 23, the metal base 16 is temporarily installed at the installation location in accordance with the marking of the foundation installation location in the concrete housing 12 (base temporary installation step).
 土台仮設置工程において金属土台16を仮設置すると、金属管23および金属板24の第1および第2部分30,31がコンクリート躯体12の上に位置し、高さ調節ボルト18のボルトヘッド45がコンクリート躯体12の上面に当接する。据え付け箇所に金属土台16を仮設置すると、コンクリート躯体12の上面に当接するそれら高さ調節ボルト18に支えられて土台16が躯体12の上面に自立する。 When the metal base 16 is temporarily installed in the base temporary installation process, the first and second portions 30 and 31 of the metal tube 23 and the metal plate 24 are positioned on the concrete housing 12, and the bolt head 45 of the height adjusting bolt 18 is It contacts the upper surface of the concrete housing 12. When the metal base 16 is temporarily installed at the installation location, the base 16 is self-supporting on the top surface of the housing 12, supported by the height adjusting bolts 18 that are in contact with the top surface of the concrete housing 12.
 金属土台16を仮設置した後、土台16の金属板24の第2部分31に対するそれら高さ調節ボルト18の螺着位置を調節し、コンクリート躯体の上面からの土台16の設置高さ(高さ寸法)(空間46の高さ寸法)を調節する(設置高さ調節工程)。据え付け基礎10Cは、高さ調節ボルト18を利用することで基礎10Cの施工中に金属土台16の高さ寸法を自由に変えることができ、基礎10Cの高さ寸法の変更要求に即座に対応することができる。据え付け基礎10Cは、複数個のそれらを設置する場合にそれら基礎10Cどうしの高さ寸法を容易に調節することができ、それら基礎10Cの高さ寸法を均一に揃えることができる。 After the metal base 16 is temporarily installed, the screwing position of the height adjusting bolts 18 to the second portion 31 of the metal plate 24 of the base 16 is adjusted, and the installation height (height of the base 16 from the upper surface of the concrete frame is adjusted. (Dimension) (height dimension of the space 46) is adjusted (installation height adjusting step). The installation foundation 10C can freely change the height dimension of the metal base 16 during construction of the foundation 10C by using the height adjusting bolt 18, and immediately responds to a request for changing the height dimension of the foundation 10C. be able to. The installation foundation 10C can easily adjust the height dimensions of the foundations 10C when a plurality of them are installed, and the height dimensions of the foundations 10C can be made uniform.
 金属土台16の高さ寸法を調節した後、金属板24の支持ボルト挿通孔39の位置にあわせてコンクリート躯体12の支持ボルト挿通孔40(ボルト孔)の穿孔箇所にマーキングをする。次に、仮設置箇所(据え付け箇所)から金属土台16を一時的に退かした後、ドリルを利用してマーキングした穿孔箇所に支持ボルト挿通孔40を穿孔する(挿通孔穿孔工程)。コンクリート躯体12に支持ボルト挿通孔40を作った後、金属土台16を据え付け箇所に再び仮設置し、図24に示すように、金属板24の第2部分31に作られた支持ボルト挿通孔39に支持ボルト19を挿通するとともに、躯体12に作られた支持ボルト挿通孔40に支持ボルト19を挿通する。 After adjusting the height dimension of the metal base 16, marking is performed on the drilled portion of the support bolt insertion hole 40 (bolt hole) of the concrete housing 12 in accordance with the position of the support bolt insertion hole 39 of the metal plate 24. Next, after the metal base 16 is temporarily retracted from the temporary installation location (installation location), the support bolt insertion hole 40 is drilled in the drilled location marked using a drill (insertion hole drilling step). After the support bolt insertion hole 40 is formed in the concrete frame 12, the metal base 16 is temporarily installed again at the installation location, and the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 as shown in FIG. The support bolt 19 is inserted into the support bolt 19, and the support bolt 19 is inserted into the support bolt insertion hole 40 formed in the housing 12.
 支持ボルト19を支持ボルト挿通孔39,40に挿通すると、自由端部47がコンクリート躯体12の上面から上方へ延出し、固定端部48が躯体12の支持ボルト挿通孔40に位置する。なお、支持ボルト挿通孔40には樹脂アンカー(固定手段)(図示せず)が注入されており、支持ボルト19の固定端部48が樹脂アンカーによって挿通孔40に固定されている。次に、支持ボルト19の自由端部47のうちの金属板24から上方に延出する部分に六角ナット50を螺着し、支持ボルト19を金属板24とコンクリート躯体12とに固定する(支持ボルト固定工程)。 When the support bolt 19 is inserted into the support bolt insertion holes 39 and 40, the free end portion 47 extends upward from the upper surface of the concrete housing 12, and the fixed end portion 48 is positioned in the support bolt insertion hole 40 of the housing 12. A resin anchor (fixing means) (not shown) is injected into the support bolt insertion hole 40, and the fixed end portion 48 of the support bolt 19 is fixed to the insertion hole 40 by the resin anchor. Next, a hexagon nut 50 is screwed into a portion of the free end portion 47 of the support bolt 19 that extends upward from the metal plate 24, and the support bolt 19 is fixed to the metal plate 24 and the concrete casing 12 (support). Bolt fixing process).
 支持ボルト19を金属板24とコンクリート躯体12とに固定した後、図25に示すように、金属管23と金属板24との交差部および押さえコンクリート15とコンクリートスラブ12とに成型材22(枠材)を設置する(枠材設置工程)。成型材22を設置すると、成型材22が金属管23外周縁全域を取り囲むとともに、金属板24の外周縁全域を取り囲み、成型材22がコンクリートスラブ12と金属板24の外周縁との間の空隙を塞ぐ。 After the support bolt 19 is fixed to the metal plate 24 and the concrete housing 12, as shown in FIG. 25, the intersection of the metal tube 23 and the metal plate 24 and the pressing concrete 15 and the concrete slab 12 are formed with a molding material 22 (frame Material) (frame material installation process). When the molding material 22 is installed, the molding material 22 surrounds the entire outer peripheral edge of the metal tube 23 and the entire outer peripheral edge of the metal plate 24, and the molding material 22 has a gap between the concrete slab 12 and the outer peripheral edge of the metal plate 24. Block.
 成型材22を設置した後、金属管23の各側板25の外側と金属板24の外側(成型材22の外側)とに防水層21を設置する(防水層設置工程)。防水層設置工程では、図1の基礎10Aと同様に、複数の薄いアスファルトシートを金属管23の各側板25の外側と成型材22の外側とに固着して防水層21を作るとともに、成型材22から延びる防水層21をコンクリート構造物11の防水層14につなげる。据え付け基礎10Cは、それがコンクリート構造物11の屋外に設置された場合でも防水層21によって金属土台16の内部への水の侵入を防ぐことができ、内部に水が進入することによる土台16の腐食や強度低下を防ぐことができる。また、コンクリート構造物11への水の進入を防ぐことができ、水の進入による構造物11の劣化を防ぐことができる。 After the molding material 22 is installed, the waterproof layer 21 is installed on the outside of each side plate 25 of the metal tube 23 and the outside of the metal plate 24 (outside of the molding material 22) (waterproof layer installation process). In the waterproof layer installation step, a plurality of thin asphalt sheets are fixed to the outside of each side plate 25 of the metal tube 23 and the outside of the molding material 22 in the same manner as the foundation 10A in FIG. The waterproof layer 21 extending from 22 is connected to the waterproof layer 14 of the concrete structure 11. The installation base 10C can prevent water from entering the inside of the metal base 16 by the waterproof layer 21 even when it is installed outdoors of the concrete structure 11, and the base 16 due to water entering the inside can be prevented. Corrosion and strength reduction can be prevented. Moreover, the entrance of water to the concrete structure 11 can be prevented, and the deterioration of the structure 11 due to the entrance of water can be prevented.
 防水層21を設置した後、空間46にモルタル20を充填する(セメント硬化物充填工程)。セメント硬化物充填工程では、確認孔34から空間46におけるモルタル20の充填状態を確認しつつ、充填孔33から空間46にモルタル20を充填する。据え付け基礎10Cは、支持ボルト19を金属板24やコンクリート躯体12に固定した後に充填孔33を利用して空間46にモルタル20を充填することができるから、空間46にモルタル20を確実に充填することができる。据え付け基礎10Cは、確認孔34を利用して空間46に充填されたモルタル20の充填状態を確認することで、モルタル20が空間46に偏って充填されることはなく、モルタル20を空間46全域に満遍なく充填することができる。 After installing the waterproof layer 21, the space 46 is filled with mortar 20 (cement hardened material filling step). In the cement hardened material filling step, the mortar 20 is filled into the space 46 from the filling hole 33 while confirming the filling state of the mortar 20 in the space 46 from the confirmation hole 34. The mounting base 10C can fill the space 46 with the mortar 20 by using the filling hole 33 after the support bolt 19 is fixed to the metal plate 24 or the concrete housing 12, so that the space 46 is reliably filled with the mortar 20. be able to. The installation base 10 </ b> C confirms the filling state of the mortar 20 filled in the space 46 using the confirmation hole 34, so that the mortar 20 is not filled in the space 46 and the mortar 20 is placed in the entire space 46. Can be filled evenly.
 空間46にモルタル20を充填した直後、モルタル20の養生期間を待つことなく、直ちに金属管23の頂部に金属蓋17を嵌め込み、金属管23の頂部開口27を塞ぐ。金属管23の頂部に金属蓋17を嵌め込んだ後、金属管23の各側板25の上部に作られた固定ボルト螺着孔29に蓋固定ボルト28を螺着するとともに、金属蓋17のアングル材41の蓋固定ボルト挿通孔にボルト29を挿通し、ボルト挿通孔に取り付けられた六角ナット43にボルト29を螺着して蓋17を金属管25の頂部に固定する(頂部閉鎖工程)(図19参照)。金属管25の頂部開口27は、金属蓋17によって水密に閉塞される。 Immediately after filling the space 46 with the mortar 20, without waiting for the curing period of the mortar 20, the metal lid 17 is immediately fitted into the top of the metal tube 23 to close the top opening 27 of the metal tube 23. After fitting the metal lid 17 on the top of the metal tube 23, the lid fixing bolt 28 is screwed into the fixing bolt screwing holes 29 formed on the side plates 25 of the metal tube 23, and the angle of the metal lid 17 is The bolt 29 is inserted into the lid fixing bolt insertion hole of the material 41, and the bolt 29 is screwed to the hexagon nut 43 attached to the bolt insertion hole to fix the lid 17 to the top of the metal tube 25 (top closing step) ( (See FIG. 19). The top opening 27 of the metal tube 25 is watertightly closed by the metal lid 17.
 なお、空隙(空間46の周縁)が成型材22によって塞がれているから、成型材22が硬化前のモルタル20の漏れを防ぐ堤防となり、空間46に充填されたモルタル20が空隙(空間46)から漏れ出すことはなく、モルタル20の充填後に直ちに金属蓋17で頂部開口27を閉塞することができる。据え付け基礎10Cでは、金属管25の頂部に金属蓋17を嵌め込んだ(固定した)直後において空間46に充填されたモルタル20が未硬化状態にあり、管25の頂部に蓋17を固定した後からモルタル20の養生期間が開始する。 In addition, since the space | gap (periphery of the space 46) is obstruct | occluded by the molding material 22, the molding material 22 becomes a bank which prevents the leakage of the mortar 20 before hardening, and the mortar 20 with which the space 46 was filled is a space | gap (space 46). The top opening 27 can be closed with the metal lid 17 immediately after the mortar 20 is filled. In the mounting base 10 </ b> C, the mortar 20 filled in the space 46 is in an uncured state immediately after the metal lid 17 is fitted (fixed) to the top of the metal tube 25, and the lid 17 is fixed to the top of the tube 25. The curing period for mortar 20 begins.
 空間46では、モルタル20の養生期間が経過し、そこに充填されたモルタル20が硬化することで、支持ボルト19の自由端部47のうちのコンクリート躯体12の上面と金属管25の金属板24との間に延びる部分(ボルト19の自由端部47のうちの板24の下面から下方へ露出する部分)がモルタル20と一体になり、鉄筋モルタルを形成する。以上の各工程が終了すると、図18,19に示す据え付け基礎10Cが完成する。 In the space 46, the curing period of the mortar 20 elapses, and the mortar 20 filled therein is cured, so that the upper surface of the concrete housing 12 in the free end portion 47 of the support bolt 19 and the metal plate 24 of the metal tube 25. (A portion of the free end 47 of the bolt 19 that is exposed downward from the lower surface of the plate 24) is integrated with the mortar 20 to form a reinforcing bar mortar. When the above steps are completed, the installation base 10C shown in FIGS. 18 and 19 is completed.
 据え付け基礎施工方法は、モルタル20を空間46に充填した直後、モルタル20の養生期間を待つことなく、直ちに金属管23の頂部開口27を金属蓋17によって塞ぎ、基礎10Cを完成させることができるから、空間46に充填したモルタル20の養生期間の分だけ施工期間を短縮することができ、養生期間を待つことなく、複数の基礎10Cの施工を平行して行うことができる。 In the installation foundation construction method, immediately after filling the space 46 with the mortar 20, the top opening 27 of the metal tube 23 can be immediately closed with the metal lid 17 without waiting for the curing period of the mortar 20 to complete the foundation 10 </ b> C. The construction period can be shortened by the curing period of the mortar 20 filled in the space 46, and a plurality of foundations 10C can be constructed in parallel without waiting for the curing period.
 据え付け基礎施工方法は、金属土台16をコンクリート躯体12の所定の据え付け箇所に仮設置する土台仮設置工程と、仮設置された金属土台16の躯体12の上面からの設置高さを調節する設置高さ調節工程と、金属板24に支持ボルト第1挿通孔39を穿孔するボルト孔第1穿孔工程と、金属板24の第2部分31に形成された支持ボルト挿通孔39の位置にあわせて躯体12に支持ボルト挿通孔40を穿孔するボルト孔第2穿孔工程と、それら支持ボルト挿通孔39,40に支持ボルト19を挿通し、六角二重ナット50を介して支持ボルト19を金属板24の第2部分31と躯体12とに固定する支持ボルト固定工程と、金属土台16の外周縁とコンクリート躯体との間に躯体と土台16の外周縁との間の空隙を塞ぐ枠材22を設置する枠材設置工程と、躯体12の上面と金属板24の下面との間の空間46にモルタル20を充填するセメント硬化物充填工程と、金属管23の頂部に金属蓋17を固定する金属管閉鎖工程とから基礎10Cが作られ、汎用部品化された各基礎部品を各工程によってユニットシステムとして組み立てるから、施工作業をマニュアル化することができるとともに、施工作業を簡略化することができる。 The installation foundation construction method includes a provisional installation process in which the metal base 16 is temporarily installed at a predetermined installation location of the concrete frame 12, and an installation height for adjusting the installation height of the temporarily installed metal base 16 from the upper surface of the frame 12. The height adjustment step, the bolt hole first drilling step of drilling the support bolt first insertion hole 39 in the metal plate 24, and the support bolt insertion hole 39 formed in the second portion 31 of the metal plate 24 in accordance with the position 12 through which the support bolt insertion hole 40 is drilled, the support bolt 19 is inserted into the support bolt insertion holes 39 and 40, and the support bolt 19 is attached to the metal plate 24 via the hexagonal double nut 50. A support bolt fixing step for fixing the second portion 31 and the casing 12 and a frame member 22 for closing a gap between the outer periphery of the metal base 16 and the outer periphery of the base 16 are provided between the outer periphery of the metal base 16 and the concrete casing. A frame material installation step, a cement hardened material filling step of filling the space 46 between the upper surface of the housing 12 and the lower surface of the metal plate 24 with the mortar 20, and a metal tube for fixing the metal lid 17 on the top of the metal tube 23 Since the foundation 10C is made from the closing process, and each basic part made into a general-purpose part is assembled as a unit system by each process, the construction work can be made manual and the construction work can be simplified.
 据え付け基礎施工方法は、据え付け基礎10Cを形成する際に施工現場において型枠を製作する必要がないことはもちろん、基礎製造工場や施工現場において基礎10Cを作るためにモルタルを養生する必要はなく、支持ボルト19を軽量な金属土台16の金属板24の第2部分31とコンクリート躯体12とに固定し、空間46にモルタル20を充填した直後に、金属管23に金属蓋17を固定するだけで基礎を構築することができ、型枠の製作やモルタルの養生にかかる手間やコスト、時間を省くことができるとともに、施工作業を簡略化することができ、その分の施工期間を大幅に短縮することができる。 In the installation foundation construction method, it is not necessary to produce a formwork at the construction site when forming the installation foundation 10C, and it is not necessary to cure the mortar to make the foundation 10C at the foundation manufacturing factory or construction site. The support bolt 19 is fixed to the second portion 31 of the metal plate 24 of the lightweight metal base 16 and the concrete casing 12, and the metal lid 17 is simply fixed to the metal tube 23 immediately after the space 46 is filled with the mortar 20. The foundation can be constructed, and the labor, cost, and time required for mold production and mortar curing can be saved, and the construction work can be simplified and the construction period can be greatly shortened. be able to.
 据え付け基礎施工方法は、支持ボルト19を金属板24の第2部分31とコンクリート躯体12とに固定し、空間46にモルタル20を充填するから、据え付け基礎10Cをコンクリート構造物11に強固に設置することができ、ソーラーパネルやアンテナ、貯水槽、浄化槽、空調機器等の機械器具、鉄塔や鉄骨建設物等の建築物を強固に備え付けることが可能な基礎10Cを作ることができる。据え付け基礎施工方法は、コンクリート躯体12の上面と金属板24の下面との間の空間46にモルタル20を充填し、基礎10Cの上に機械機器や建築物を備え付けた場合の基礎10Cにかかる荷重を支持ボルト19と硬化したモルタル20とに分担させるから、基礎10Cにかかる荷重でそれが不用意に傾斜したり、基礎10Cが崩壊することはなく、機械機器や建築物を確実に支持する基礎10Cを作ることができる。 In the installation foundation construction method, the support bolt 19 is fixed to the second portion 31 of the metal plate 24 and the concrete casing 12, and the space 46 is filled with the mortar 20, so that the installation foundation 10C is firmly installed on the concrete structure 11. It is possible to make a foundation 10C that can be firmly equipped with solar panels, antennas, water storage tanks, septic tanks, machinery and equipment such as air conditioners, and buildings such as steel towers and steel structures. In the installation foundation construction method, the load applied to the foundation 10C when the mortar 20 is filled in the space 46 between the upper surface of the concrete frame 12 and the lower surface of the metal plate 24 and the machinery and the building are provided on the foundation 10C. Is divided between the support bolt 19 and the hardened mortar 20, so that it is not inadvertently inclined by the load applied to the foundation 10C, or the foundation 10C is not collapsed. 10C can be made.
 据え付け基礎施工方法は、据え付け基礎10Cの据え付け箇所が既設のコンクリート構造物11の屋上や地下に防水機能を施した防水層14を備えたコンクリート躯体12である場合でも、据え付け箇所の防水層14を取り除いた後の露出した躯体12に基礎10Cを設置し、基礎10Cを設置した直後に据え付け箇所近傍の防水層を補修する(新たな防水層21を施す)ことができるから、基礎10Cを迅速に設置することができ、基礎10Cの設置に要する時間を大幅に短縮することができる。 Even if the installation location of the installation foundation 10C is the concrete frame 12 provided with the waterproof layer 14 having a waterproof function on the roof or underground of the existing concrete structure 11, the installation foundation waterproof layer 14 is installed. Since the foundation 10C is installed on the exposed housing 12 after the removal, and the waterproof layer near the installation location can be repaired (a new waterproof layer 21 is applied) immediately after the foundation 10C is installed, the foundation 10C can be quickly installed. It can be installed, and the time required to install the foundation 10C can be greatly shortened.
 10A  据え付け基礎
 10B  据え付け基礎
 10C  据え付け基礎
 11  コンクリート構造物
 12  コンクリートスラブ(コンクリート躯体)
 13  コンクリート梁(コンクリート躯体)
 14  防水層
 15  押さえコンクリート
 16  金属土台
 17  金属蓋
 18  高さ調節ボルト
 19  支持ボルト
 20  モルタル(セメント硬化物)
 21  防水層
 22  成型材(枠材)
 23  金属管
 24  金属板
 26  中空スペース
 27  頂部開口
 30  第1部分
 31  第2部分
 33  充填孔
 34  確認孔
 36  第1側板
 37  第2側板
 39  支持ボルト挿通孔(支持ボルト第1挿通孔)
 40  支持ボルト挿通孔(支持ボルト第2挿通孔)
 46  空間
 47  第1固定端部
 48  第2固定端部
 50  六角二重ナット(固定手段)
 51  六角二重ナット(固定手段)
 52  支持ボルト挿通孔(支持ボルト第1挿通孔)
 53  支持ボルト挿通孔(支持ボルト第2挿通孔)
10A Installation Foundation 10B Installation Foundation 10C Installation Foundation 11 Concrete Structure 12 Concrete Slab (Concrete Frame)
13 Concrete beams (concrete frame)
14 Waterproofing layer 15 Pressing concrete 16 Metal base 17 Metal lid 18 Height adjustment bolt 19 Support bolt 20 Mortar (hardened cement)
21 Waterproofing layer 22 Molding material (frame material)
23 Metal tube 24 Metal plate 26 Hollow space 27 Top opening 30 First part 31 Second part 33 Filling hole 34 Confirmation hole 36 First side plate 37 Second side plate 39 Support bolt insertion hole (support bolt first insertion hole)
40 Support bolt insertion hole (support bolt second insertion hole)
46 Space 47 First fixed end 48 Second fixed end 50 Hexagon double nut (fixing means)
51 Hexagon double nut (fixing means)
52 Support bolt insertion hole (support bolt first insertion hole)
53 Support bolt insertion hole (support bolt second insertion hole)

Claims (10)

  1.  新設または既設のコンクリート構造物の所定の箇所に設置される据え付け基礎を施工する据え付け基礎施工方法において、
     前記据え付け基礎施工方法が、金属管と前記金属管の下端につながる金属板とを有する金属土台を前記コンクリート構造物の所定の箇所に仮設置する土台仮設置工程と、前記金属板に螺着された高さ調節ボルトの該金属板に対する螺着位置を調節することで、前記仮設置された金属土台の前記コンクリート構造物の上面からの設置高さを調節する設置高さ調節工程と、前記金属板に支持ボルト第1挿通孔を穿孔するボルト孔第1穿孔工程と、前記金属板に形成された支持ボルト第1挿通孔の位置にあわせて前記コンクリート構造物に支持ボルト第2挿通孔を穿孔するボルト孔第2穿孔工程と、前記支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して前記支持ボルトを前記金属板および前記コンクリート構造物に固定する支持ボルト固定工程と、前記金属土台の外周縁と前記コンクリート構造物との間に該構造物と該土台の外周縁との間の空隙を塞ぐ枠材を設置する枠材設置工程と、前記コンクリート構造物の上面と前記金属板の下面との間の空間にセメント硬化物を充填するセメント硬化物充填工程と、前記金属管の頂部に金属蓋を固定して該金属管の頂部開口を塞ぐ金属管閉鎖工程とを有し、
     前記据え付け基礎施工方法では、前記空間にセメント硬化物を充填した直後であって該セメント硬化物の養生期間の経過前に、前記金属蓋によって前記金属管の頂部開口が塞がれ、前記金属蓋によって前記金属管の頂部開口が塞がれた後からセメント硬化物の養生期間が開始し、前記養生期間の経過後に、前記支持ボルトのうちの前記コンクリート構造物と前記金属板との間に延びる部分が前記セメント硬化物と一体になることを特徴とする据え付け基礎施工方法。
    In the installation foundation construction method for constructing the installation foundation installed at a predetermined location of a new or existing concrete structure,
    The mounting foundation construction method includes a base temporary installation step of temporarily installing a metal base having a metal pipe and a metal plate connected to a lower end of the metal pipe at a predetermined position of the concrete structure, and screwed to the metal plate. Adjusting the installation position of the temporarily installed metal base from the top surface of the concrete structure by adjusting the screwing position of the height adjusting bolt to the metal plate; A bolt hole first drilling step for drilling a first support bolt insertion hole in the plate, and a second support bolt insertion hole in the concrete structure according to the position of the first support bolt insertion hole formed in the metal plate Bolt hole second drilling step, inserting the support bolt into the first and second insertion holes of the support bolt, and inserting the support bolt into the metal plate and the concrete structure through a predetermined fixing means. A supporting bolt fixing step, a frame material installation step of installing a frame material that closes a gap between the structure and the outer peripheral edge of the foundation, between the outer periphery of the metal base and the concrete structure; A cement hardened material filling step of filling a space between the upper surface of the concrete structure and the lower surface of the metal plate with a cement hardened material, and fixing a metal lid to the top of the metal tube to open a top opening of the metal tube. A metal tube closing process for closing,
    In the installation foundation construction method, immediately after the cement hardened material is filled into the space and before the curing period of the cement hardened material has elapsed, a top opening of the metal tube is closed by the metal lid, and the metal lid After the top opening of the metal tube is closed by the above, a curing period of the hardened cement material is started and, after the curing period, extends between the concrete structure of the support bolt and the metal plate. An installation foundation construction method, wherein a portion is integrated with the hardened cement material.
  2.  前記金属板が、前記金属管の径方向内方へ延びる第1部分と、前記金属管の径方向外方へ延びる第2部分とを備え、前記ボルト孔第1穿孔工程では、前記金属板の第2部分に前記支持ボルト第1挿通孔を穿孔し、前記ボルト孔第2穿孔工程では、前記金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせて前記コンクリート構造物に支持ボルト第2挿通孔を穿孔し、前記支持ボルト固定工程では、前記支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して前記支持ボルトを前記金属板の第2部分および前記コンクリート構造物に固定し、前記枠材設置工程では、前記底板の第2部分の外周縁と前記コンクリート構造物との間に該構造物と該第2部分の外周縁との間の空隙を塞ぐ前記枠材を設置する請求項1記載の据え付け基礎施工方法。 The metal plate includes a first portion extending radially inward of the metal tube and a second portion extending radially outward of the metal tube, and in the bolt hole first drilling step, The support bolt first insertion hole is drilled in the second portion, and in the second bolt hole drilling step, the concrete structure is matched with the position of the support bolt first insertion hole formed in the second portion of the metal plate. The support bolt second insertion hole is drilled, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, and the support bolt is inserted into the metal plate via a predetermined fixing means. Fixed to the second part and the concrete structure, and in the frame material installation step, between the outer periphery of the second part of the bottom plate and the outer periphery of the second part between the concrete structure and the second part. Install the frame material to close the gap between Mounting base construction method according to claim 1, wherein.
  3.  前記コンクリート構造物が、コンクリート躯体と、前記コンクリート躯体の上に施設された防水層と、前記防水層の上に施設された押さえコンクリートとから形成され、前記土台仮設置工程では、前記コンクリート構造物から前記押さえコンクリートと前記防水層とを取り除いて前記コンクリート躯体を露出させ、前記金属土台を前記コンクリート躯体に仮設置し、前記ボルト孔第2穿孔工程では、前記金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせて前記コンクリート躯体に支持ボルト第2挿通孔を穿孔し、前記支持ボルト固定工程では、前記支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して前記支持ボルトを前記金属板の第2部分および前記コンクリート躯体に固定する請求項2記載の据え付け基礎施工方法。 The concrete structure is formed from a concrete frame, a waterproof layer provided on the concrete frame, and a pressing concrete provided on the waterproof layer. In the temporary mounting step, the concrete structure is formed. The pressing concrete and the waterproof layer are removed from the concrete casing to expose the concrete base, the metal base is temporarily installed on the concrete casing, and the bolt hole second drilling step is formed in the second portion of the metal plate. The support bolt second insertion hole is drilled in the concrete frame in accordance with the position of the support bolt first insertion hole, and in the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes, The said support bolt is fixed to the 2nd part of the said metal plate, and the said concrete frame via predetermined fixing means. In the mounting base construction method of the placement.
  4.  前記コンクリート構造物が、コンクリートスラブおよびコンクリート梁と、前記スラブおよび梁の上に施設された防水層と、前記防水層の上に施設された押さえコンクリートとから形成され、前記土台仮設置工程では、前記コンクリート構造物から前記押さえコンクリートと前記防水層とを取り除いて前記スラブと前記梁とを露出させ、前記金属板の第2部分が前記スラブの上に位置するとともに、前記金属管と前記金属板の第1部分とが前記梁の上に位置するように、前記金属土台を仮設置し、前記ボルト孔第2穿孔工程では、前記金属板の第2部分に形成された支持ボルト第1挿通孔の位置にあわせて前記スラブに支持ボルト第2挿通孔を穿孔し、前記支持ボルト固定工程では、前記支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して前記支持ボルトを前記金属板の第2部分および前記スラブに固定する請求項2記載の据え付け基礎施工方法。 The concrete structure is formed from a concrete slab and a concrete beam, a waterproof layer provided on the slab and a beam, and a pressing concrete provided on the waterproof layer, The pressing concrete and the waterproof layer are removed from the concrete structure to expose the slab and the beam, and the second portion of the metal plate is positioned on the slab, and the metal tube and the metal plate The metal base is temporarily installed so that the first portion of the metal plate is positioned on the beam, and in the bolt hole second drilling step, the support bolt first insertion hole formed in the second portion of the metal plate The support bolt second insertion hole is drilled in the slab in accordance with the position of the support bolt. In the support bolt fixing step, the support bolt is inserted into the support bolt first and second insertion holes. And, mounting base construction method according to claim 2, wherein for fixing the support bolt in the second portion and the slab of the metal plate via the predetermined fixing means.
  5.  前記ボルト孔第1穿孔工程では、前記金属板の第1部分に前記支持ボルト第1挿通孔を穿孔し、前記ボルト孔第2穿孔工程では、前記金属板の第1部分に形成された支持ボルト第1挿通孔の位置にあわせて前記コンクリート梁に支持ボルト第2挿通孔を穿孔し、前記支持ボルト固定工程では、前記支持ボルト第1および第2挿通孔に支持ボルトを挿通し、所定の固定手段を介して前記支持ボルトを前記金属板の第1および第2部分と前記スラブおよび梁とに固定する請求項4記載の据え付け基礎施工方法。 In the bolt hole first drilling step, the support bolt first insertion hole is drilled in the first portion of the metal plate, and in the bolt hole second drilling step, the support bolt formed in the first portion of the metal plate. A second support bolt insertion hole is drilled in the concrete beam in accordance with the position of the first insertion hole, and in the support bolt fixing step, a support bolt is inserted into the first and second insertion holes of the support bolt, and predetermined fixing is performed. The installation foundation construction method according to claim 4, wherein the support bolt is fixed to the first and second portions of the metal plate and the slab and the beam through means.
  6.  前記据え付け基礎施工方法が、前記金属土台を覆う防水層を設置する防水層設置工程を含み、前記防水層設置工程では、前記金属土台の外側に延びる前記防水層を前記コンクリート構造物の防水層につなげる請求項3または請求項5に記載の据え付け基礎施工方法。 The installation foundation construction method includes a waterproof layer installation step of installing a waterproof layer covering the metal base, and in the waterproof layer installation step, the waterproof layer extending outside the metal base is used as a waterproof layer of the concrete structure. The installation foundation construction method according to claim 3 or claim 5 to be connected.
  7.  前記金属板の第2部分には、その周縁から上方へ起立する第1側板と、前記第1側板の間に位置して前記第2部分から上方へ起立する第2側板とが連接され、前記セメント硬化物充填工程では、前記金属板の第2部分と前記第1側板とに囲繞されたスペースに前記セメント硬化物を充填する請求項1ないし請求項6いずれかに記載の据え付け基礎施工方法。 The second portion of the metal plate is connected to a first side plate that rises upward from a peripheral edge thereof, and a second side plate that is positioned between the first side plate and rises upward from the second portion. The installation foundation construction method according to any one of claims 1 to 6, wherein, in the hardened material filling step, the cement hardened material is filled in a space surrounded by the second portion of the metal plate and the first side plate.
  8.  前記金属板の第2部分には、その周縁から上方へ起立する第1側板と、前記第1側板の間に位置して前記第2部分から上方へ起立する第2側板とが連接され、前記据え付け基礎施工方法が、前記金属板の第2部分と前記第1側板とに囲繞されたスペースの頂部に頂板を固定して前記スペースを塞ぐスペース閉鎖工程を含む請求項1ないし請求項6いずれかに記載の据え付け基礎施工方法。 The second portion of the metal plate is connected to a first side plate that rises upward from a peripheral edge thereof, and a second side plate that is positioned between the first side plate and rises upward from the second portion. The foundation construction method includes a space closing step of fixing the top plate to a top portion of a space surrounded by the second portion of the metal plate and the first side plate to close the space. The installation foundation construction method described.
  9.  前記金属板の所定の箇所には、前記空間に前記セメント硬化物を充填するための充填孔が形成され、前記セメント硬化物充填工程では、前記充填孔から前記空間にセメント硬化物を充填する請求項1ないし請求項8いずれかに記載の据え付け基礎施工方法。 A filling hole for filling the space with the cement hardened material is formed in a predetermined portion of the metal plate, and the cement hardened material is filled into the space from the filling hole in the cement hardened material filling step. The installation foundation construction method according to claim 1.
  10.  前記金属板の所定の箇所には、前記空間に充填された前記セメント硬化物を確認するための確認孔が形成され、前記セメント硬化物充填工程では、前記確認孔から前記空間におけるセメント硬化物の充填状態を確認しつつ、前記空間にセメント硬化物を充填する請求項1ないし請求項9いずれかに記載の据え付け基礎施工方法。 A confirmation hole for confirming the cement hardened material filled in the space is formed in a predetermined portion of the metal plate, and in the cement hardened material filling step, the cement hardened material in the space from the confirmation hole is formed. The installation foundation construction method according to any one of claims 1 to 9, wherein the space is filled with a hardened cement material while confirming a filling state.
PCT/JP2011/078997 2010-12-15 2011-12-15 Method of installing a mounting base WO2012081653A1 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
JP2010-279068 2010-12-15
JP2010279068 2010-12-15
JP2011272952A JP2012140848A (en) 2010-12-15 2011-12-14 Construction method for installation foundation
JP2011-272952 2011-12-14

Publications (1)

Publication Number Publication Date
WO2012081653A1 true WO2012081653A1 (en) 2012-06-21

Family

ID=46244747

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2011/078997 WO2012081653A1 (en) 2010-12-15 2011-12-15 Method of installing a mounting base

Country Status (2)

Country Link
JP (1) JP2012140848A (en)
WO (1) WO2012081653A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105275008A (en) * 2014-07-23 2016-01-27 贵阳铝镁设计研究院有限公司 Method for preventing top face of large-sized equipment foundation from cracking and extension device
EP4050160A1 (en) * 2021-02-24 2022-08-31 Sommer Anlagentechnik GmbH Method for manufacturing a foundation of a production plant, foundation anchoring box and production plant

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6446773B2 (en) 2013-11-19 2019-01-09 株式会社Ihi Low temperature tank
JP6395396B2 (en) * 2014-02-18 2018-09-26 三菱重工業株式会社 Device mounting device and device mounting method
CN106638667A (en) * 2017-02-17 2017-05-10 邯郸金隅太行水泥有限责任公司 Easy, convenient and precise alignment system for large equipment replacement and installation and assembly alignment method
CN112695797A (en) * 2020-12-14 2021-04-23 太原重工工程技术有限公司 Method for protecting embedded bolt during cutting equipment foundation
WO2023225976A1 (en) * 2022-05-27 2023-11-30 蓝星(北京)化工机械有限公司 Foundation structure for high-temperature storage tank

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003138699A (en) * 2001-10-30 2003-05-14 Airec Engineering Corp Method for installing new equipment and foundation member
JP2006225951A (en) * 2005-02-17 2006-08-31 Tajima Roofing Co Ltd Frame device on waterproof layer, frame device mounting structure on waterproof layer, and frame device mounting method
JP2009167754A (en) * 2008-01-18 2009-07-30 Cosmo System Kk Base frame for setting facility equipment and method of setting the base frame
JP3164441U (en) * 2010-06-30 2010-12-02 日本エフ・アール・ピー株式会社 The structure of the foundation that supports the installation stand for equipment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003138699A (en) * 2001-10-30 2003-05-14 Airec Engineering Corp Method for installing new equipment and foundation member
JP2006225951A (en) * 2005-02-17 2006-08-31 Tajima Roofing Co Ltd Frame device on waterproof layer, frame device mounting structure on waterproof layer, and frame device mounting method
JP2009167754A (en) * 2008-01-18 2009-07-30 Cosmo System Kk Base frame for setting facility equipment and method of setting the base frame
JP3164441U (en) * 2010-06-30 2010-12-02 日本エフ・アール・ピー株式会社 The structure of the foundation that supports the installation stand for equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105275008A (en) * 2014-07-23 2016-01-27 贵阳铝镁设计研究院有限公司 Method for preventing top face of large-sized equipment foundation from cracking and extension device
EP4050160A1 (en) * 2021-02-24 2022-08-31 Sommer Anlagentechnik GmbH Method for manufacturing a foundation of a production plant, foundation anchoring box and production plant

Also Published As

Publication number Publication date
JP2012140848A (en) 2012-07-26

Similar Documents

Publication Publication Date Title
JP6041485B2 (en) Installation base
WO2012081652A1 (en) Mounting base
WO2012081653A1 (en) Method of installing a mounting base
JP5921116B2 (en) Installation foundation construction method
JP4597199B2 (en) Foundation frame for installation of equipment and installation method of the foundation frame
JP5576207B2 (en) Installation foundation and its construction method
KR20230090300A (en) A twin wall structure using a PC panel and method for manufacturing of it
JP5921176B2 (en) Installation foundation construction method
WO2001002657A1 (en) Structure
JP5927683B1 (en) Substructure installation method
KR102002429B1 (en) Sandwich precast concrete wall and construction method using the same
KR101862567B1 (en) Standardization of Mat Foundation assembling House system
JP5469467B2 (en) Support structure for equipment on the rooftop
JP6091740B2 (en) Installation base
KR20190046336A (en) Sandwich precast concrete wall and manufacturing method thereof
JP5978445B2 (en) Installation foundation structure
JP2018123537A (en) Method of constructing mat foundation, tubular formwork and mat foundation structure
JP3172665U (en) Installation base
KR20200053874A (en) Centrifugal casted rectangular PC column with hollow section and manufacturing method thereof
JP3244102U (en) Steel house foundation structure and anchor set used therein
KR200406140Y1 (en) Mold and d-type manhole manufactured by mold
JP2007040012A (en) Joint method of reinforced concrete column and beam connecting member
JPH0470492A (en) Method for setting up gate post or the like and stabilizing board used in this method
KR20150084313A (en) Apparatus for fixing basis and method for constructing basis using the same

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11848200

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 11848200

Country of ref document: EP

Kind code of ref document: A1