JP2011169057A - Method of constructing vertical shaft - Google Patents

Method of constructing vertical shaft Download PDF

Info

Publication number
JP2011169057A
JP2011169057A JP2010035290A JP2010035290A JP2011169057A JP 2011169057 A JP2011169057 A JP 2011169057A JP 2010035290 A JP2010035290 A JP 2010035290A JP 2010035290 A JP2010035290 A JP 2010035290A JP 2011169057 A JP2011169057 A JP 2011169057A
Authority
JP
Japan
Prior art keywords
shaft
shaft wall
frozen
freezing
cooling pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010035290A
Other languages
Japanese (ja)
Other versions
JP5443200B2 (en
Inventor
Teru Yoshida
輝 吉田
Tetsuya Yarita
哲也 鎗田
Yutaka Kotaki
裕 小滝
Yukihiro Nakatani
行博 中谷
Nobuo Itabashi
信男 板橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2010035290A priority Critical patent/JP5443200B2/en
Publication of JP2011169057A publication Critical patent/JP2011169057A/en
Application granted granted Critical
Publication of JP5443200B2 publication Critical patent/JP5443200B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method of constructing a vertical shaft, which surely steps water and can shorten the work period. <P>SOLUTION: In the method of constructing the vertical shaft, a shaft bottom part D in a vertical-shaft wall body 1 is cooled with ground water B accumulated in the vertical-shaft wall body 1 after the earth and sand is discharged from the vertical-shaft wall body 1, thereby freezing the entire range of the shaft bottom part D with a predetermined thickness. Subsequently, the ground water B is discharged from the vertical-shaft wall body 1, and bottom plate concrete 6 with a frozen part 4 as a base is placed above the frozen part 4 of the shaft bottom part D within the vertical-shaft wall body 1, while the shaft bottom part D is in the frozen state. A series of these operations eliminates the need for placing the bottom plate concrete 6 underwater, and further a gap is hardly generated between the vertical-shaft wall body 1 and the shaft bottom part D by freezing the entire range of the shaft bottom part D with the predetermined thickness. Accordingly, the ground water is hard to infiltrate into the vertical-shaft wall body 1, thereby quickly and surely pumping up the ground water. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、トンネル工事などに利用される立坑の施工方法に関するものである。   The present invention relates to a shaft construction method used for tunnel construction and the like.

地下水位より深い立坑を構築する場合、立坑壁体内に湧き水(地下水)を残したまま地盤を掘削し、その後、立坑壁体の底部に水中で底盤コンクリートが打設される場合がある。その場合、立坑壁体内に侵入している湧き水は、底盤コンクリートの硬化後、ポンプによって立坑壁体から排出される。このとき、底盤コンクリートと立坑壁体との間に隙間がある場合には、その隙間から水が侵入し続けることになるので、止水する必要がある。そこで、特開2005−282199号公報には、隙間を凍結させて、湧き水の侵入を防止する止水方法が開示されている。   When constructing a shaft deeper than the groundwater level, the ground may be excavated with the spring water (groundwater) left in the shaft wall, and then bottom concrete may be placed in the bottom of the shaft wall in water. In that case, the spring water invading into the shaft wall is discharged from the shaft wall by the pump after the bottom concrete is hardened. At this time, if there is a gap between the bottom base concrete and the shaft wall body, water will continue to enter from the gap, so it is necessary to stop the water. Japanese Patent Application Laid-Open No. 2005-282199 discloses a water stop method that freezes a gap and prevents intrusion of spring water.

特開2005−282199号公報JP 2005-282199 A

しかしながら、前述した従来の立坑の施工方法では、立坑壁体内に湧き水がある状態で底盤コンクリートを打設するので、底盤コンクリートと立坑壁体との間に隙間が形成され易く、隙間が有る場合、特開2005−282199号公報に開示されているような止水対策や、再度、底盤コンクリートを打設するといった作業が必要になる。このような一連の作業は、工期が長くなると同時に、確実な止水を行い難いといった問題点がある。   However, in the conventional shaft construction method described above, since the bottom base concrete is driven in a state where there is spring water in the shaft wall body, a gap is easily formed between the bottom base concrete and the shaft wall body, and there is a gap, It is necessary to take measures against water stoppage as disclosed in Japanese Patent Application Laid-Open No. 2005-282199 and work such as placing bottom base concrete again. Such a series of work has a problem that the construction period becomes long and at the same time, it is difficult to reliably stop water.

本発明は、確実に止水を行うと同時に、工期の短縮化を可能にした立坑の施工方法を提供することを目的とする。   An object of this invention is to provide the construction method of the shaft which made it possible to shorten the construction period while performing water stop reliably.

本発明に係る立坑の施工方法は、立坑壁体を地中に構築する工程と、
土砂排出後の立坑壁体内に地下水が溜まった状態で、立坑壁体内の坑底部を冷却して、所定の厚さで坑底部の全範囲を凍結させる工程と、
坑底部が凍結状態で、立坑壁体内の地下水を排出する工程と、
坑底部が凍結状態で地下水を排出する工程と、を備えたことを特徴とする。
The construction method of the shaft according to the present invention includes a step of constructing a shaft wall body in the ground,
A step of cooling the bottom of the shaft wall in a state where groundwater has accumulated in the shaft wall after the sediment discharge, and freezing the entire range of the bottom of the shaft at a predetermined thickness;
A process of discharging groundwater in the shaft wall with the bottom of the shaft frozen,
And a step of discharging groundwater when the bottom of the well is frozen.

この立坑の施工方法においては、立坑壁体内の土砂排出後に、立坑壁体内に地下水が溜まっている状態で、立坑壁体内の坑底部を冷却して、所定の厚さで坑底部の全範囲を凍結させる。その後、立坑壁体内の地下水を排出する。そして、地下水の排出によって、立坑壁体内で坑底部の凍結部をベースとして底盤コンクリートを打設する等の後工程を安全且つ容易に行うことができる。立坑壁体には、コンクリート地中連続壁、ソイルセメント地中連続壁、ケーソン等がある。このような一連の作業によって、水中内で底盤コンクリートを打設する必要がなく、しかも、坑底部が、全範囲に渡って凍結されることで、立坑壁体と坑底部との間に隙間が発生し難く、これによって、立坑壁体内に地下水が侵入し難くなり、地下水の汲み出し作業を迅速且つ確実に行うことができる。従って、この施工方法を利用すると、確実な止水効果が得られ、工期の短縮化を図ることができる。   In this shaft construction method, after discharging the sediment in the shaft wall, with the groundwater accumulated in the shaft wall, the bottom of the shaft wall is cooled, and the entire range of the bottom of the shaft is covered with a predetermined thickness. Freeze. Thereafter, the groundwater in the shaft wall is discharged. And by discharging groundwater, it is possible to safely and easily carry out post-processes such as placing bottom concrete in the shaft wall with the frozen portion at the bottom of the shaft as a base. The shaft wall includes concrete underground continuous wall, soil cement underground continuous wall, caisson and the like. By such a series of operations, it is not necessary to place the bottom base concrete in water, and the bottom of the well is frozen over the entire range, so that there is a gap between the shaft wall and the bottom of the shaft. It is hard to generate | occur | produce, and it becomes difficult for groundwater to penetrate | invade into a shaft wall by this, and the drawing-out operation | work of groundwater can be performed rapidly and reliably. Therefore, if this construction method is used, a reliable water stop effect can be obtained and the construction period can be shortened.

また、坑底部の凍結工程において利用される凍結用配管は、略水平方向に延在する冷却管と、冷却管の両端から略鉛直方向に延在して冷却管に連通する冷媒搬送管とからなり、冷却管は、立坑壁体内に地下水が溜まった状態で、立坑壁体内の底に当たるまで沈められると好適である。
このような構成の凍結用配管を利用すると、土砂排出後に、凍結用配管を立坑壁体の上部開口から沈めるだけで良いので、作業性が良く、しかも、配管は継ぎ足しによって、長さ調整を容易に行うことができるので、現場での作業性が非常に良好である。
The freezing pipe used in the bottom bottom freezing process includes a cooling pipe extending in a substantially horizontal direction and a refrigerant transport pipe extending in a substantially vertical direction from both ends of the cooling pipe and communicating with the cooling pipe. Thus, it is preferable that the cooling pipe is submerged until it hits the bottom of the shaft wall in a state where groundwater is accumulated in the shaft wall.
When the freezing pipe having such a structure is used, it is only necessary to sink the freezing pipe from the upper opening of the shaft wall body after discharging the earth and sand, so that workability is good and the length of the pipe can be easily adjusted by adding the pipe. Therefore, workability on site is very good.

また、冷却管が立坑壁体内の底に当たった後、冷却管が埋まるように、立坑壁体内に、凍結可能な埋め戻し材が投入されると好適である。
このように、埋め戻し材によって冷却管を埋めた状態で、坑底部を凍結させるので、冷却管が水中に露出していないことに起因して、冷却の効率化を図り、坑底部を強固に冷凍させることができる。埋め戻し材としては、砂質土又は流動化処理土が好適である。
Further, it is preferable that a freezing backfill material is introduced into the shaft wall so that the cooling tube is buried after the cooling tube hits the bottom of the shaft wall.
In this way, the bottom of the well is frozen in the state where the cooling pipe is filled with the backfill material, so that the cooling pipe is not exposed in the water, so that the cooling efficiency is improved and the bottom of the well is strengthened. Can be frozen. As the backfill material, sandy soil or fluidized soil is suitable.

また、冷却管は、下方に向かって膨出するアーチ形状になっていると好適である。
このような冷却管を利用することで、下方に向かって膨出するアーチ形状の凍結部を形成することができるので、下から凍結部を押し上げるような水圧が高い場合に効果的である。
Further, it is preferable that the cooling pipe has an arch shape that bulges downward.
By using such a cooling pipe, an arch-shaped frozen part that bulges downward can be formed, which is effective when the water pressure is high to push up the frozen part from below.

また、冷却管は、上下方向で複数段に配列されていると好適である。
このような冷却管を利用すると、厚みのある凍結部を確実に形成することができる。しかも、凍結時間の短縮化により、工期の短縮化をも可能にする。
The cooling pipes are preferably arranged in a plurality of stages in the vertical direction.
When such a cooling pipe is used, a thick frozen portion can be reliably formed. In addition, the construction period can be shortened by shortening the freezing time.

また、立坑壁体の内壁面には、泥が付着するので、凍結部と接触する部分の泥を、埋め戻し材の投入前に除去すると好適である。
この場合、立坑壁体の内壁面に対する凍結部の密着性が高められることで、立坑壁体と凍結部との間で凍着剪断耐力を増大させて、止水効果を向上させることができる。
In addition, since mud adheres to the inner wall surface of the shaft wall body, it is preferable to remove mud in a portion that comes into contact with the frozen portion before the backfill material is charged.
In this case, by increasing the adhesion of the frozen portion to the inner wall surface of the shaft wall body, it is possible to increase the frosting shear strength between the shaft wall body and the frozen portion, thereby improving the water stop effect.

また、立坑壁体には、泥を除去する部分に補強繊維が混入されていると好適である。
このような構成を採用すると、内壁面に現れた補強繊維により内壁面と凍結部の付着が強まり、更なる止水効果を得ることができる。
In addition, it is preferable that reinforcing fibers are mixed in the shaft wall body in a portion where mud is removed.
If such a structure is employ | adopted, adhesion with an inner wall surface and a frozen part will become strong with the reinforcement fiber which appeared on the inner wall surface, and the further water stop effect can be acquired.

また、立坑壁体内には、別の冷凍用配管が底部まで埋設され、立坑壁体の下端より下方を冷凍させると好適である。   Further, it is preferable that another refrigeration pipe is embedded in the shaft wall to the bottom, and the lower part is frozen from the lower end of the shaft wall.

このような構成を採用すると、工事の安全上問題の無い範囲内で、立坑壁体の下端深さを、内部地盤の切削深さより浅くするか、ほぼ同程度にすることで、凍結部の周縁部が立坑壁体の下端面の一部又は全体を覆うように形成することができる。このようにすれば、下方からの水圧によって上方に押し上げられようとする凍結部を、立坑壁体の下端面が受け止めることができるので、合理的である。   By adopting such a configuration, the bottom edge depth of the shaft wall body is shallower than the cutting depth of the internal ground, or approximately the same, within the range where there is no problem in safety of construction, so that the periphery of the frozen part The part can be formed so as to cover a part or the whole of the lower end surface of the shaft wall. In this way, the frozen part that is about to be pushed upward by the water pressure from below can be received by the lower end surface of the shaft wall body, which is reasonable.

本発明によれば、確実に止水を行うと同時に、工期の短縮化を可能にする。   According to the present invention, it is possible to reliably stop the water and at the same time shorten the construction period.

本発明に係る立坑の施工方法の第1の実施形態における第1〜第3の行程を示す断面図である。It is sectional drawing which shows the 1st-3rd process in 1st Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第1の実施形態における第4〜第6の行程を示す断面図である。It is sectional drawing which shows the 4th-6th process in 1st Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第1の実施形態における第7及び第8の行程を示す断面図である。It is sectional drawing which shows the 7th and 8th process in 1st Embodiment of the construction method of the shaft which concerns on this invention. 立坑壁体内の凍結用配管の平面図である。It is a top view of piping for freezing in a shaft wall. 本発明に係る立坑の施工方法の第2の実施形態における第1〜第3の行程を示す断面図である。It is sectional drawing which shows the 1st-3rd process in 2nd Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第2の実施形態における第4〜第6の行程を示す断面図である。It is sectional drawing which shows the 4th-6th process in 2nd Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第2の実施形態における第7〜第9の行程を示す断面図である。It is sectional drawing which shows the 7th-9th process in 2nd Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第3の実施形態を示す断面図である。It is sectional drawing which shows 3rd Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第4の実施形態を示す断面図である。It is sectional drawing which shows 4th Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第5の実施形態を示す断面図である。It is sectional drawing which shows 5th Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第6の実施形態を示す断面図である。It is sectional drawing which shows 6th Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第7の実施形態を示す断面図である。It is sectional drawing which shows 7th Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第8の実施形態を示す断面図である。It is sectional drawing which shows 8th Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第9の実施形態を示す断面図である。It is sectional drawing which shows 9th Embodiment of the construction method of the shaft which concerns on this invention. 本発明に係る立坑の施工方法の第10の実施形態を示す断面図である。It is sectional drawing which shows 10th Embodiment of the construction method of the shaft which concerns on this invention.

以下、図面を参照しつつ本発明に係る立坑の施工方法の好適な実施形態について詳細に説明する。   Hereinafter, a preferred embodiment of a shaft construction method according to the present invention will be described in detail with reference to the drawings.

[第1の実施形態]
図1(a)に示すように、地平面Aから所定の深さに達するまで構築された立坑壁体1は、土砂排出後にあっても、地下水Bで満たされている。この場合、立坑壁体1の底Cは、砂地盤であり、地下水が底Cから立坑壁体1内に侵入し易い。
[First Embodiment]
As shown in FIG. 1 (a), the shaft wall 1 constructed until reaching a predetermined depth from the ground plane A is filled with groundwater B even after the earth and sand are discharged. In this case, the bottom C of the shaft wall body 1 is sand ground, and groundwater easily enters the shaft wall body 1 from the bottom C.

図1(b)に示すように、凍結用配管2を立坑壁体1の上部開口1bから地下水B内に沈める。この凍結用配管2は、水平方向に延在する冷却管2aと、冷却管2aの両端から鉛直方向に延在して冷却管2aに連通する冷媒搬送管2bとからなる。そして、この冷却管2aは、立坑壁体1の底Cに当たるまで沈められる。冷却管2aは、剥き出しの状態で水と接触し易くし、冷媒搬送管2bは断熱材によって被覆され、冷媒搬送管2bは、図示しない冷媒供給源に接続されている。   As shown in FIG. 1 (b), the freezing pipe 2 is submerged in the groundwater B from the upper opening 1 b of the shaft wall 1. The freezing pipe 2 includes a cooling pipe 2a extending in the horizontal direction and a refrigerant transport pipe 2b extending in the vertical direction from both ends of the cooling pipe 2a and communicating with the cooling pipe 2a. And this cooling pipe 2a is sunk until it hits the bottom C of the shaft wall 1. The cooling pipe 2a is easily exposed to water in an exposed state, the refrigerant transport pipe 2b is covered with a heat insulating material, and the refrigerant transport pipe 2b is connected to a refrigerant supply source (not shown).

図4に示すように、この立坑壁体1では、複数本(例えば9本)の凍結用配管2A〜2Iが利用されている。凍結用配管2A〜2Iのそれぞれの冷却管2aは、立坑壁体1の断面円形の内壁面1aの弦方向に延在すると共に、立坑壁体1の底C上で略平行に配置されている。また、凍結用配管2A〜2Iのそれぞれの冷媒搬送管2bは、立坑壁体1の内壁面1aに沿って上下方向に延在する。   As shown in FIG. 4, in this shaft wall body 1, a plurality of (for example, nine) freezing pipes 2 </ b> A to 2 </ b> I are used. The cooling pipes 2 a of the freezing pipes 2 </ b> A to 2 </ b> I extend in the chord direction of the inner wall surface 1 a having a circular cross section of the shaft wall body 1 and are disposed substantially parallel on the bottom C of the shaft wall body 1. . In addition, each refrigerant transport pipe 2 b of the freezing pipes 2 </ b> A to 2 </ b> I extends in the vertical direction along the inner wall surface 1 a of the shaft wall 1.

このような構成の凍結用配管2を利用すると、土砂排出後に、凍結用配管2を立坑壁体1の上部開口1bから沈めるだけで良いので、作業性が良く、しかも、配管は継ぎ足しによって、長さ調整を容易に行うことができるので、現場での作業性が非常に良好である。   When the freezing pipe 2 having such a configuration is used, it is only necessary to sink the freezing pipe 2 from the upper opening 1b of the shaft wall body 1 after discharging the sediment. Since the thickness can be adjusted easily, the workability on site is very good.

次に、図1(c)に示すように、立坑壁体1内に、凍結可能な埋め戻し土3が投入されて、凍結用配管2A〜2Iのそれぞれの冷却管2aを埋める。この埋め戻し土3には、砂質土や流動化処理土が利用される。このように、埋め戻し土3によって冷却管2aを埋めた状態で、坑底部Dを凍結させるので、冷却管2aが露出していないことに起因して、冷却の効率化を図り、坑底部Dを強固に冷凍させることができる。   Next, as shown in FIG.1 (c), the refillable earth | ground 3 which can be frozen is thrown in into the shaft wall body 1, and each cooling pipe 2a of the piping 2A-2I for freezing is buried. As the backfill soil 3, sandy soil or fluidized soil is used. In this way, the bottom portion D is frozen in a state where the cooling pipe 2a is filled with the backfill soil 3, so that the cooling pipe 2a is not exposed, so that the cooling efficiency is improved and the bottom portion D is obtained. Can be frozen firmly.

その後、図2(d)に示すように、各凍結用配管2A〜2I内で冷媒の流動を開始させる。そして、立坑壁体1内の坑底部Dを冷却して、所定の厚さで坑底部Dを全範囲に渡って凍結させる。このとき、坑底部Dにおいて、冷却管2aの上方及び下方が凍結し、埋め戻し土3や、掘削後の底Cより下も凍結される。この部分が、円盤状の凍結部4になる。   Then, as shown in FIG.2 (d), the refrigerant | coolant flow is started in each freezing piping 2A-2I. And the bottom part D in the shaft wall 1 is cooled, and the bottom part D is frozen by the predetermined thickness over the whole range. At this time, the upper and lower sides of the cooling pipe 2a are frozen in the bottom portion D, and are also frozen below the backfill soil 3 and the bottom C after excavation. This portion becomes a disk-shaped frozen portion 4.

その後、図2(e)に示すように、立坑壁体1内の地下水Bを排出する。このとき、埋め戻し土3Aが砂質土なら、凍結部4の上に溜まっている未凍結の余剰な埋め戻し土3Aも地下水Bと一緒にポンプにより汲み出される。   Then, as shown in FIG.2 (e), the groundwater B in the shaft wall 1 is discharged | emitted. At this time, if the backfill soil 3 </ b> A is sandy soil, the unfrozen surplus backfill soil 3 </ b> A accumulated on the freezing portion 4 is also pumped out together with the groundwater B.

その後、図2(f)に示すように、凍結部4をベースとして、凍結部4の表面に断熱シート5を敷設し、断熱シート5の上にコンクリートを打設して、底盤コンクリート6を形成する。底盤コンクリート6のコンクリートは、低温では固化し難いので、断熱シート5は、底盤コンクリート6の固化中の低温化を防止している。   Thereafter, as shown in FIG. 2 (f), the base plate concrete 6 is formed by laying the heat insulating sheet 5 on the surface of the frozen portion 4 using the frozen portion 4 as a base and placing concrete on the heat insulating sheet 5. To do. Since the concrete of the bottom base concrete 6 is hard to be solidified at a low temperature, the heat insulating sheet 5 prevents the low temperature during the solidification of the bottom base concrete 6.

底盤コンクリート6の固化後、図3(g)に示すように、各凍結用配管2A〜2I内で加熱媒体を流動させて、凍結部4を解凍する。その後、図3(h)に示すように、冷媒搬送管2bのうちで、底盤コンクリート6から露出している部分を、底盤コンクリート6の上面の位置で切断する。凍結用配管2のうちで、切断後に残った残置部分は、冷媒搬送管2bの切断開口2cからグラウト7を充填して封止され、立坑の構築作業は完了する。   After the bottom concrete 6 is solidified, as shown in FIG. 3 (g), the freezing part 4 is thawed by flowing a heating medium in each of the freezing pipes 2A to 2I. Then, as shown in FIG.3 (h), the part exposed from the bottom base concrete 6 among the refrigerant | coolant conveyance pipes 2b is cut | disconnected in the position of the upper surface of the bottom base concrete 6. FIG. In the freezing pipe 2, the remaining part after cutting is filled with the grout 7 through the cutting opening 2c of the refrigerant transport pipe 2b and sealed, and the construction work of the shaft is completed.

[第2の実施形態]
図5(a)に示すように、地平面Aから所定の深さに達するまで構築された立坑壁体1は、土砂排出後にあっても、地下水Bで満たされている。この場合、立坑壁体1の底Cは、粘土が混ざった地盤であるが、地下水が底C、または立坑壁体1と底Cとの境界部から立坑壁体1内に侵入するおそれがある。さらに、下方からの水圧の作用によって、底Cが盛り上がって破壊するおそれがある。
[Second Embodiment]
As shown in FIG. 5 (a), the shaft wall 1 constructed until reaching a predetermined depth from the ground plane A is filled with the groundwater B even after the earth and sand are discharged. In this case, although the bottom C of the shaft wall body 1 is ground mixed with clay, there is a possibility that groundwater may enter the shaft wall body 1 from the bottom C or the boundary between the shaft wall body 1 and the bottom C. . Furthermore, there exists a possibility that the bottom C may rise and be destroyed by the action of water pressure from below.

粘土が混ざった土壌は、凍結させると体積が膨脹して、凍結用配管2が押し上げられるなどの悪影響が生じるので、これを防止するため、図5(b)に示すように、立坑壁体1内に、砂質土や流動化処理土などの埋め戻し土13が投入される。この埋め戻し土13の表面13aは、平坦に均される。   When the soil mixed with clay is frozen, the volume expands and the freezing pipe 2 is pushed up. As a result, as shown in FIG. Inside, a backfilling soil 13 such as sandy soil or fluidized soil is put. The surface 13a of the backfill soil 13 is leveled flat.

図5(c)に示すように、凍結用配管2を立坑壁体1の上部開口1bから地下水B内に沈める。この凍結用配管2は、水平方向に延在する冷却管2aと、冷却管2aの両端から鉛直方向に延在して冷却管2aに連通する冷媒搬送管2bとからなる。そして、この冷却管2aは、立坑壁体1の底Eに当たるまで沈められる。冷却管2aは、剥き出しの状態で水と接触し易く、冷媒搬送管2bは断熱材によって被覆され、冷媒搬送管2bは、図示しない冷媒供給源に接続されている。なお、この場合、図4に示すような複数本(例えば9本)の凍結用配管2A〜2Iが利用されている。   As shown in FIG. 5 (c), the freezing pipe 2 is submerged in the groundwater B from the upper opening 1 b of the shaft wall 1. The freezing pipe 2 includes a cooling pipe 2a extending in the horizontal direction and a refrigerant transport pipe 2b extending in the vertical direction from both ends of the cooling pipe 2a and communicating with the cooling pipe 2a. And this cooling pipe 2a is sunk until it hits the bottom E of the shaft wall 1. The cooling pipe 2a is easily exposed to water in an exposed state, the refrigerant transport pipe 2b is covered with a heat insulating material, and the refrigerant transport pipe 2b is connected to a refrigerant supply source (not shown). In this case, a plurality of (for example, nine) freezing pipes 2A to 2I as shown in FIG. 4 are used.

次に、図6(d)に示すように、立坑壁体1内に、凍結可能な別の埋め戻し土23が投入されて、凍結用配管2A〜2Iのそれぞれの冷却管2aを埋める。この埋め戻し土23には、砂質土や流動化処理土が利用される。このように、埋め戻し土23によって冷却管2aを埋めた状態で、坑底部Dを凍結させるので、冷却管2aが露出していないことに起因して、冷却の効率化を図り、坑底部Dを強固に冷凍させることができる。   Next, as shown in FIG. 6 (d), another backfilling soil 23 that can be frozen is put into the shaft wall body 1 to fill the cooling pipes 2 a of the freezing pipes 2 </ b> A to 2 </ b> I. As the backfill soil 23, sandy soil or fluidized soil is used. Thus, since the bottom hole D is frozen in the state where the cooling pipe 2a is filled with the backfill soil 23, the cooling pipe 2a is not exposed, so that the cooling efficiency is improved, and the bottom bottom D Can be frozen firmly.

その後、図6(e)に示すように、各凍結用配管2A〜2I内で冷媒の流動を開始させる。そして、立坑壁体1内の坑底部Dを冷却して、所定の厚さで坑底部Dを全範囲に渡って凍結させる。このとき、坑底部Dにおいて、冷却管2aの上方及び下方が凍結し、埋め戻し土13,23が凍結される。この部分が、円盤状の凍結部4になる。   Thereafter, as shown in FIG. 6 (e), the refrigerant starts to flow in each of the freezing pipes 2A to 2I. And the bottom part D in the shaft wall 1 is cooled, and the bottom part D is frozen by the predetermined thickness over the whole range. At this time, the upper and lower portions of the cooling pipe 2a are frozen at the bottom portion D, and the backfill soils 13 and 23 are frozen. This portion becomes a disk-shaped frozen portion 4.

その後、図6(f)に示すように、立坑壁体1内の地下水Bを排出する。埋め戻し材が砂質土のときは、凍結部4の上に溜まっている未凍結の余剰な埋め戻し土23Aも地下水Bと一緒にポンプにより汲み出される。   Then, as shown in FIG.6 (f), the groundwater B in the shaft wall 1 is discharged | emitted. When the backfill material is sandy soil, the unfrozen surplus backfill soil 23 </ b> A accumulated on the freezing portion 4 is also pumped out together with the groundwater B.

その後、図7(g)に示すように、凍結部4をベースとして、凍結部4の表面に断熱シート5を敷設し、断熱シート5の上にコンクリートを打設して、底盤コンクリート6を形成する。底盤コンクリート6のコンクリートは、低温では固化し難いので、断熱シート5は、底盤コンクリート6の固化中の低温下を防止している。   Thereafter, as shown in FIG. 7 (g), with the frozen portion 4 as a base, a heat insulating sheet 5 is laid on the surface of the frozen portion 4, and concrete is placed on the heat insulating sheet 5 to form the bottom concrete 6 To do. Since the concrete of the bottom base concrete 6 is difficult to solidify at a low temperature, the heat insulating sheet 5 prevents the low temperature during the solidification of the bottom base concrete 6.

底盤コンクリート6の固化後、図7(h)に示すように、各凍結用配管2A〜2I内で加熱媒体を流動させて、凍結部4を解凍する。その後、図7(I)に示すように、冷媒搬送管2bのうちで、底盤コンクリート6から露出している部分を、底盤コンクリート6の上面の位置で切断する。凍結用配管2のうちで、切断後に残った残置部分には、冷媒搬送管2bの切断開口2cからグラウト7を充填して封止され、立坑の構築作業は完了する。   After the bottom base concrete 6 is solidified, as shown in FIG. 7 (h), the freezing part 4 is thawed by flowing a heating medium in each of the freezing pipes 2 </ b> A to 2 </ b> I. Thereafter, as shown in FIG. 7 (I), the portion of the refrigerant transport pipe 2 b exposed from the bottom concrete 6 is cut at the position of the top surface of the bottom concrete 6. Of the freezing pipe 2, the remaining part after cutting is filled with the grout 7 from the cutting opening 2c of the refrigerant transfer pipe 2b and sealed, and the construction work of the shaft is completed.

前述した第1及び第2の実施形態に係る立坑の施工方法においては、立坑壁体1内の土砂排出後に、立坑壁体1内に地下水Bが溜まっている状態で、立坑壁体1内の坑底部Dを冷却して、所定の厚さで坑底部Dの全範囲を凍結させる。その後、立坑壁体1内の地下水Bを排出する。地下水の排出によって、立坑壁体1内で坑底部Dの凍結部4をベースとして底盤コンクリート6を打設する等の後工程を安全且つ容易に行うことができる。坑底部Dが凍結状態で、立坑壁体1内で坑底部Dの凍結部4より上方に、凍結部4をベースとして底盤コンクリート6を打設する。地下水の排出によって、立坑壁体1内で坑底部Dの凍結部4をベースとして底盤コンクリート6を打設する等の後工程を安全且つ容易に行うことができる。   In the shaft construction method according to the first and second embodiments described above, the groundwater B is accumulated in the shaft wall body 1 after the earth and sand is discharged in the shaft wall body 1, The bottom portion D is cooled, and the entire range of the bottom portion D is frozen at a predetermined thickness. Thereafter, the groundwater B in the shaft wall 1 is discharged. By discharging the groundwater, subsequent processes such as placing the bottom base concrete 6 in the shaft wall 1 based on the frozen part 4 of the bottom part D can be performed safely and easily. With the bottom portion D frozen, a bottom concrete 6 is placed in the vertical wall body 1 above the freezing portion 4 of the bottom portion D with the frozen portion 4 as a base. By discharging the groundwater, subsequent processes such as placing the bottom base concrete 6 in the shaft wall 1 based on the frozen part 4 of the bottom part D can be performed safely and easily.

そして、底盤コンクリート6を打設して、十分な強度まで固化した後に、凍結部4を解凍する。このような一連の作業によって、水中内で底盤コンクリート6を打設する必要がなく、しかも、坑底部Dを所定の厚さで全範囲に渡って凍結させることで、立坑壁体1と坑底部Dとの間に隙間が発生し難く、これによって、立坑壁体1内に地下水が侵入し難くなり、地下水の汲み出し作業を迅速且つ確実に行うことができる。従って、この施工方法を利用すると、確実な止水効果が得られ、工期の短縮化を図ることができる。   And after putting the bottom base concrete 6 and solidifying to sufficient intensity | strength, the frozen part 4 is thawed. By such a series of operations, it is not necessary to place the bottom base concrete 6 in the water, and the bottom wall D is frozen over the entire range with a predetermined thickness, so that the shaft wall 1 and the bottom wall It is difficult for a gap to be formed between the groundwater D and the groundwater, thereby making it difficult for groundwater to enter the shaft wall body 1 so that the groundwater can be pumped out quickly and reliably. Therefore, if this construction method is used, a reliable water stop effect can be obtained and the construction period can be shortened.

本発明は、前述した実施形態に限定されないことは言うまでもない。   It goes without saying that the present invention is not limited to the embodiment described above.

図8に示すように、他の凍結用配管20は、下方に向かって膨出するアーチ形状で略水平方向に延在する冷却管20aと、冷却管20aの両端から鉛直方向に延在して冷却管20aに連通する冷媒搬送管2bとからなる。そして、複数本(例えば9本)の凍結用配管20A〜20Iのそれぞれの冷却管20aは、立坑壁体1の底Cに当たるまで沈められる。   As shown in FIG. 8, the other freezing pipes 20 have a cooling pipe 20a extending in a substantially horizontal direction with an arch shape bulging downward, and extending in the vertical direction from both ends of the cooling pipe 20a. The refrigerant transport pipe 2b communicates with the cooling pipe 20a. Then, the cooling pipes 20a of the plural (for example, nine) freezing pipes 20A to 20I are submerged until they hit the bottom C of the shaft wall body 1.

このような冷却管20aを利用することで、下方に向かって膨出するアーチ形状の凍結部4Aを形成することができるので、下から凍結部4を押し上げるような水圧が高い場合に効果的である。   By using such a cooling pipe 20a, it is possible to form an arch-shaped frozen portion 4A that bulges downward, which is effective when the water pressure that pushes up the frozen portion 4 from the bottom is high. is there.

図9に示すように、立坑壁体1内において、外側の凍結用配管30A〜30Iの冷却管30aと内側の凍結用配管40A〜40Eの冷却管40aとで上下に2段に配列されている。下側の冷却管30aに対して冷却管40aは、上から見てクロスすることなく平行に配置されている。このように、凍結部4を2段一組の冷却管30a,40aにより形成することで、厚みのある凍結部4を確実に形成することができる。しかも、凍結時間の短縮化により、工期の短縮化をも可能にする。なお、冷却管の段数が多くなればなる程、厚みのある凍結部4を容易に形成することができる。   As shown in FIG. 9, in the shaft wall 1, the cooling pipe 30a of the outer freezing pipes 30A to 30I and the cooling pipe 40a of the inner freezing pipes 40A to 40E are arranged in two stages in the vertical direction. . The cooling pipe 40a is arranged in parallel to the lower cooling pipe 30a without crossing when viewed from above. In this way, by forming the frozen portion 4 with a pair of cooling pipes 30a and 40a, a thick frozen portion 4 can be reliably formed. In addition, the construction period can be shortened by shortening the freezing time. Note that the thicker the frozen portion 4 can be easily formed as the number of cooling pipes increases.

図10に示すように、立坑壁体1内において、外側の凍結用配管50A〜50Iの冷却管50aと内側の凍結用配管60A〜60Eの冷却管60aとで上下に2段に配列されている。下側の冷却管50aは、等間隔で配置され、上側の冷却管60aは、下側の冷却管50aに対してクロスするように配置されると共に、中央部のみに配置されている。このように配列することで、凍結部4の中央部を他の部分よりも低温化させることができるので、凍結部4の中央部の高強度化を達成することができる。なお、冷却管の段数が多くなればなる程、厚みのある凍結部4を容易に形成することができる。   As shown in FIG. 10, in the shaft wall 1, the cooling pipes 50 a of the outer freezing pipes 50 </ b> A to 50 </ b> I and the cooling pipes 60 a of the inner freezing pipes 60 </ b> A to 60 </ b> E are vertically arranged in two stages. . The lower cooling pipes 50a are arranged at equal intervals, and the upper cooling pipe 60a is arranged so as to cross the lower cooling pipe 50a, and is arranged only in the center portion. By arranging in this way, the central portion of the frozen portion 4 can be cooled at a lower temperature than the other portions, so that the strength of the central portion of the frozen portion 4 can be increased. Note that the thicker the frozen portion 4 can be easily formed as the number of cooling pipes increases.

図11に示すように、立坑壁体1内において、外側の凍結用配管70A〜70Iの冷却管70a間に補強部材としてのH又はI形鋼71が配置され、凍結部4が形鋼71で補強されている。そして、形鋼71を中央部に配列することで、凍結部4の中央部を他の部分よりも強化させることができる。   As shown in FIG. 11, H or I-shaped steel 71 as a reinforcing member is disposed between the cooling pipes 70 a of the outer freezing pipes 70 </ b> A to 70 </ b> I in the shaft wall 1, and the frozen portion 4 is the shaped steel 71. It is reinforced. And the center part of the frozen part 4 can be strengthened rather than another part by arranging the shape steel 71 in the center part.

図12に示すように、凍結用配管80は、鉛直方向に延在する冷却管80aと、冷却管80aの上端から鉛直方向に延在して冷却管80aに連通する冷媒搬送管2bとからなる。凍結用配管80内は、冷媒の往復が可能なように、往管と戻管とで構成されている。このような凍結用配管80は、立坑壁体1内で底に達するまで沈められ、その本数は、任意である。このような凍結用配管80を利用することで、凍結用配管80の密な配列が可能になり、凍結時間の短縮化により、工期の短縮化をも可能にする。   As shown in FIG. 12, the freezing pipe 80 includes a cooling pipe 80a extending in the vertical direction and a refrigerant transport pipe 2b extending in the vertical direction from the upper end of the cooling pipe 80a and communicating with the cooling pipe 80a. . The inside of the freezing pipe 80 is composed of an outgoing pipe and a return pipe so that the refrigerant can reciprocate. Such freezing pipes 80 are submerged in the shaft wall 1 until reaching the bottom, and the number thereof is arbitrary. By using such a freezing pipe 80, it is possible to arrange the freezing pipes 80 in a dense manner, and it is possible to shorten the construction period by shortening the freezing time.

図13に示すように、立坑壁体1から離れた位置にパイロット立坑91が形成され、このパイロット立坑91から略水平方向に放射状に冷却管90aが延在している。凍結用配管90は、放射状に延在する冷却管90aと、冷却管90aの端部からL字状に延在して冷却管90aに連通する冷媒搬送管2bとからなる。凍結用配管90内は、冷媒の往復が可能なように、往管と戻管とで構成され、冷媒搬送管2bは、パイロット立坑91内に配置されている。このような凍結用配管90を利用することで、凍結部4の形成後に、立坑壁体1内に配管が露出することがないので、地下水Bの排出が容易になる。   As shown in FIG. 13, a pilot shaft 91 is formed at a position away from the shaft wall 1, and cooling pipes 90 a extend radially from the pilot shaft 91 in a substantially horizontal direction. The freezing pipe 90 includes a cooling pipe 90a extending radially, and a refrigerant transport pipe 2b extending in an L shape from the end of the cooling pipe 90a and communicating with the cooling pipe 90a. The freezing pipe 90 is composed of an outgoing pipe and a return pipe so that the refrigerant can reciprocate, and the refrigerant transport pipe 2 b is arranged in the pilot shaft 91. By using such a freezing pipe 90, the pipe is not exposed in the shaft wall body 1 after the formation of the frozen portion 4, so that the groundwater B can be easily discharged.

図14に示すように、立坑壁体1の内壁面1aに沿うように、直線状の凍結用配管100が配列され、立坑壁体1の中央部分には、U字状の凍結用配管101が配列されている。凍結用配管100は、鉛直方向に延在する冷却管100aと、冷却管100aの上端から鉛直方向に延在して冷却管100aに連通する冷媒搬送管2bとからなる。凍結用配管101は、水平方向に延在する冷却管101aと、冷却管101aの両端から鉛直方向に延在して冷却管101aに連通する冷媒搬送管2bとからなる。このような構成を採用することで、凍結部4と立坑壁体1の内壁面1aとの接合部分を直線状の凍結用配管100で容易かつ確実に冷却することができるので、凍結部4と立坑壁体1の内壁面1aとの接合強度を高めることができ、内壁面1a近傍における止水対策の更なる強化を図ることができる。   As shown in FIG. 14, linear freezing pipes 100 are arranged along the inner wall surface 1 a of the shaft wall body 1, and a U-shaped freezing pipe 101 is provided in the central portion of the shaft wall body 1. It is arranged. The freezing pipe 100 includes a cooling pipe 100a extending in the vertical direction, and a refrigerant transport pipe 2b extending in the vertical direction from the upper end of the cooling pipe 100a and communicating with the cooling pipe 100a. The freezing pipe 101 includes a cooling pipe 101a extending in the horizontal direction and a refrigerant transport pipe 2b extending in the vertical direction from both ends of the cooling pipe 101a and communicating with the cooling pipe 101a. By adopting such a configuration, the joint portion between the freezing portion 4 and the inner wall surface 1a of the shaft wall body 1 can be easily and reliably cooled by the straight freezing pipe 100. The joining strength with the inner wall surface 1a of the shaft wall body 1 can be increased, and further strengthening of water stoppage measures in the vicinity of the inner wall surface 1a can be achieved.

図15に示すように、立坑壁体1内で等間隔に埋設された凍結用配管21は、冷凍用配管21の下端部で立坑壁体1の下端近傍で水平方向に延在する冷却管21aと、冷却管21aの両端から鉛直方向に延在して冷却管21aに連通する冷媒搬送管2dとからなる。この冷却管21aは、立坑壁体1の下端付近を冷却することができるので、立坑壁体1の下端より下方を冷凍させることができる。なお、この凍結用配管21は、図12に示された凍結用配管80を利用してもよい。また、他の構成は、図8に示されたものと同一であるので、詳細な説明は省略する。   As shown in FIG. 15, the freezing pipe 21 embedded at equal intervals in the vertical wall 1 is a cooling pipe 21 a that extends in the horizontal direction near the lower end of the vertical wall 1 at the lower end of the freezing pipe 21. And a refrigerant transport pipe 2d that extends in the vertical direction from both ends of the cooling pipe 21a and communicates with the cooling pipe 21a. Since the cooling pipe 21 a can cool the vicinity of the lower end of the shaft wall body 1, the lower part can be frozen from the lower end of the shaft wall body 1. The freezing pipe 21 may use the freezing pipe 80 shown in FIG. Other configurations are the same as those shown in FIG. 8, and detailed description thereof is omitted.

このような構成を採用すると、工事の安全上問題の無い範囲内で、立坑壁体1の下端深さを、内部地盤の切削深さより浅くするか、ほぼ同程度にすることで、凍結部4Aの周縁部が立坑壁体1の下端面の一部又は全体を覆うように形成することができる。このようにすれば、下方からの水圧によって上方に押し上げられようとする凍結部4Aを、立坑壁体1の下端面が受け止めることができるので、合理的である。   By adopting such a configuration, the freezing portion 4A can be obtained by making the lower end depth of the shaft wall body 1 shallower than the cutting depth of the internal ground or substantially the same within a range where there is no safety problem in construction. Can be formed so as to cover a part or the whole of the lower end surface of the shaft wall 1. In this way, the frozen portion 4A that is about to be pushed upward by the water pressure from below can be received by the lower end surface of the shaft wall body 1 and is reasonable.

図10に示すように、立坑壁体1の内壁面1aは、泥が付着するので、凍結部4と接触する部分の泥を、埋め戻し土の投入前に除去する。この場合、立坑壁体1の内壁面1aに対する凍結部4の密着性が高められることで、立坑壁体1と凍結部4との間で凍着剪断耐力を増大させて、止水効果を向上させることができる。泥の除去としては、高圧水の噴射やブラシ洗浄などがある。   As shown in FIG. 10, since mud adheres to the inner wall surface 1a of the shaft wall body 1, mud in a portion that comes into contact with the frozen portion 4 is removed before the backfilling soil is charged. In this case, the adhesion of the frozen part 4 to the inner wall surface 1a of the shaft wall 1 is enhanced, thereby increasing the frosting shear strength between the shaft wall 1 and the frozen part 4 and improving the water stop effect. Can be made. Mud removal includes high pressure water injection and brush cleaning.

立坑壁体1には、泥を除去する部分に補強繊維(鋼材からなる繊維)が混入されている。このような構成を採用すると、内壁面1aに現れた補強繊維により内壁面1aと凍結部4の付着が強まり、更なる止水効果を得ることができる。   Reinforcing fibers (fibers made of steel) are mixed in the shaft wall 1 at a portion where mud is removed. If such a structure is employ | adopted, adhesion with the inner wall face 1a and the frozen part 4 will become strong with the reinforcement fiber which appeared on the inner wall face 1a, and the further water stop effect can be acquired.

埋め戻し材としては、砂質土又は流動化処理土などが好適である。   As the backfill material, sandy soil or fluidized soil is suitable.

また、立坑壁体1としては、コンクリート地中連続壁、ソイルセメント地中連続壁、ケーソン等がある。 The shaft wall 1 includes a concrete underground continuous wall, a soil cement underground continuous wall, and a caisson.

1…立坑壁体、1a…内壁面、1b…上部開口、2,2A〜2I,20A〜20I,30A〜30I,40A〜40E,50A〜50I,60A〜0E,70A〜70I…凍結用配管、2a,2d…冷却管、2b…冷媒搬送管、3…埋め戻し土、4,4A…凍結部、5…断熱シート、6…底盤コンクリート、13…埋め戻し土(埋め戻し材)、20,21…凍結用配管、20a,21a…冷却管、23…埋め戻し土(埋め戻し材)、30a,40a,50a,60a,70a…冷却管、80…凍結用配管、80a…冷却管、90…凍結用配管、90a…冷却管、100…凍結用配管、100a…冷却管、101…凍結用配管、101a…冷却管、B…地下水、C,E…底、D…坑底部。     DESCRIPTION OF SYMBOLS 1 ... Vertical wall body, 1a ... Inner wall surface, 1b ... Upper opening, 2, 2A-2I, 20A-20I, 30A-30I, 40A-40E, 50A-50I, 60A-0E, 70A-70I ... Freezing piping, 2a, 2d ... cooling pipe, 2b ... refrigerant transport pipe, 3 ... backfilling soil, 4, 4A ... freezing section, 5 ... heat insulation sheet, 6 ... bottom concrete, 13 ... backfilling soil (backfilling material), 20, 21 ... Freezing pipe, 20a, 21a ... Cooling pipe, 23 ... Backfill soil (backfilling material), 30a, 40a, 50a, 60a, 70a ... Cooling pipe, 80 ... Freezing pipe, 80a ... Cooling pipe, 90 ... Freezing Pipe for piping, 90a ... Cooling pipe, 100 ... Piping for freezing, 100a ... Cooling pipe, 101 ... Piping for freezing, 101a ... Cooling pipe, B ... Ground water, C, E ... Bottom, D ... Bottom of well.

Claims (8)

立坑壁体を地中に構築する工程と、
土砂排出後の前記立坑壁体内に地下水が溜まった状態で、前記立坑壁体内の坑底部を冷却して、所定の厚さで前記坑底部の全範囲を凍結させる工程と、
前記坑底部が凍結状態で、前記立坑壁体内の地下水を排出する工程と、
前記坑底部が凍結状態で地下水を排出する工程と、を備えたことを特徴とする立坑の施工方法。
Building a shaft wall in the ground,
A step of cooling the bottom of the shaft wall in a state where groundwater has accumulated in the shaft wall after sediment discharge, and freezing the entire range of the shaft bottom with a predetermined thickness;
A step of discharging groundwater in the shaft wall in a state where the bottom of the shaft is frozen;
And a step of discharging groundwater in a frozen state of the bottom of the shaft.
前記坑底部の凍結工程において利用される凍結用配管は、略水平方向に延在する冷却管と、前記冷却管の両端から略鉛直方向に延在して前記冷却管に連通する冷媒搬送管とからなり、前記冷却管は、前記立坑壁体内に地下水が溜まった状態で、前記立坑壁体内の底に当たるまで沈められることを特徴とする請求項1記載の立坑の施工方法。   The freezing pipe used in the freezing step of the bottom portion includes a cooling pipe extending in a substantially horizontal direction, a refrigerant transport pipe extending in a substantially vertical direction from both ends of the cooling pipe and communicating with the cooling pipe. 2. The shaft construction method according to claim 1, wherein the cooling pipe is submerged in a state where ground water is accumulated in the shaft wall until it hits a bottom of the shaft wall. 前記冷却管が前記立坑壁体内の底に当たった後、前記冷却管が埋まるように、前記立坑壁体内に、凍結可能な埋め戻し材が投入されることを特徴とする請求項2記載の立坑の施工方法。   3. The shaft according to claim 2, wherein after the cooling pipe hits the bottom of the shaft wall body, a freezeable backfill material is introduced into the shaft wall body so that the cooling pipe is buried. Construction method. 前記冷却管は、下方に向かって膨出するアーチ形状になっていることを特徴とする請求項2又は3記載の立坑の施工方法。   4. The shaft construction method according to claim 2, wherein the cooling pipe has an arch shape that bulges downward. 前記冷却管は、上下方向で複数段に配列されていることを特徴とする請求項2〜4の何れか一項に記載の立坑の施工方法。   The said cooling pipe is arranged in multiple steps in the up-down direction, The construction method of the shaft as described in any one of Claims 2-4 characterized by the above-mentioned. 前記立坑壁体の内壁面には、泥が付着するので、前記凍結部と接触する部分の泥を、埋め戻し材の投入前に除去することを特徴とする請求項3〜5の何れか一項に記載の立坑の施工方法。   6. Since mud adheres to the inner wall surface of the shaft wall body, mud in a portion that comes into contact with the frozen portion is removed before the backfilling material is charged. The construction method of the shaft described in the paragraph. 前記立坑壁体には、前記泥を除去する部分に補強繊維が混入されていることを特徴とする請求項6記載の立坑の施工方法。   The shaft construction method according to claim 6, wherein a reinforcing fiber is mixed in a portion of the shaft wall body where the mud is removed. 前記立坑壁体内には、別の冷凍用配管が底部まで埋設され、前記立坑壁体の下端より下方を冷凍させることを特徴とする請求項1〜7の何れか一項に記載の立坑の施工方法。   The construction of the shaft according to any one of claims 1 to 7, wherein another refrigeration pipe is embedded in the shaft wall to the bottom, and the lower part is frozen from the lower end of the shaft wall. Method.
JP2010035290A 2010-02-19 2010-02-19 Construction method of shaft Active JP5443200B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010035290A JP5443200B2 (en) 2010-02-19 2010-02-19 Construction method of shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010035290A JP5443200B2 (en) 2010-02-19 2010-02-19 Construction method of shaft

Publications (2)

Publication Number Publication Date
JP2011169057A true JP2011169057A (en) 2011-09-01
JP5443200B2 JP5443200B2 (en) 2014-03-19

Family

ID=44683445

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010035290A Active JP5443200B2 (en) 2010-02-19 2010-02-19 Construction method of shaft

Country Status (1)

Country Link
JP (1) JP5443200B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016027226A (en) * 2014-06-25 2016-02-18 前田建設工業株式会社 Underground continuous wall water-stop structure and method
CN107345483A (en) * 2017-08-21 2017-11-14 安徽理工大学 A kind of newly-built antiseepage mine shaft and preparation method thereof
JP2018035506A (en) * 2016-08-29 2018-03-08 鹿島建設株式会社 Construction method for underground structure
JP2021179113A (en) * 2020-05-13 2021-11-18 鹿島建設株式会社 Foundation reinforcement method, and structure
CN114198108A (en) * 2021-12-21 2022-03-18 中铁一局集团有限公司 Method for breaking and removing obstacles of shield-driven downward-passing existing station enclosure structure in water-rich sand layer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02269294A (en) * 1989-04-07 1990-11-02 Kyoei Doken:Kk Batholith forming engineering method for vertical shaft
JPH03257298A (en) * 1990-03-06 1991-11-15 Takenaka Komuten Co Ltd Construction method of large-depth large-scale underground space by ground freezing method and ground freezing pipe therefor
JP2000130065A (en) * 1998-10-23 2000-05-09 Nishimatsu Constr Co Ltd Construction method for vertical shaft

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02269294A (en) * 1989-04-07 1990-11-02 Kyoei Doken:Kk Batholith forming engineering method for vertical shaft
JPH03257298A (en) * 1990-03-06 1991-11-15 Takenaka Komuten Co Ltd Construction method of large-depth large-scale underground space by ground freezing method and ground freezing pipe therefor
JP2000130065A (en) * 1998-10-23 2000-05-09 Nishimatsu Constr Co Ltd Construction method for vertical shaft

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016027226A (en) * 2014-06-25 2016-02-18 前田建設工業株式会社 Underground continuous wall water-stop structure and method
JP2018035506A (en) * 2016-08-29 2018-03-08 鹿島建設株式会社 Construction method for underground structure
CN107345483A (en) * 2017-08-21 2017-11-14 安徽理工大学 A kind of newly-built antiseepage mine shaft and preparation method thereof
CN107345483B (en) * 2017-08-21 2023-02-28 安徽理工大学 Newly-built seepage-proof coal mine shaft and preparation method thereof
JP2021179113A (en) * 2020-05-13 2021-11-18 鹿島建設株式会社 Foundation reinforcement method, and structure
JP7333287B2 (en) 2020-05-13 2023-08-24 鹿島建設株式会社 Foundation reinforcement method and structure
CN114198108A (en) * 2021-12-21 2022-03-18 中铁一局集团有限公司 Method for breaking and removing obstacles of shield-driven downward-passing existing station enclosure structure in water-rich sand layer

Also Published As

Publication number Publication date
JP5443200B2 (en) 2014-03-19

Similar Documents

Publication Publication Date Title
CN108035335B (en) Method for constructing shaft type underground parking garage by freezing method
JP5443200B2 (en) Construction method of shaft
CN104762955B (en) A kind of Belled Pile construction method based on freezing process
US1993291A (en) Retaining wall
KR100765976B1 (en) Aquifer base pre-cast concrete box structure for the underway construction and devices that use simplicity freezing propulsion method of construction
JP5688244B2 (en) Construction method for underground structures
JP2018035506A (en) Construction method for underground structure
JP5807096B2 (en) Underground structure and cross-sectional structure of underground structure
JP6316674B2 (en) Water stop structure and method for underground continuous wall
CN206220104U (en) A kind of Frozen Soil Cylinder Foundation Supported with Composite Soil Nailing system
KR101153313B1 (en) Subsidiary casing and construction method for underground watertight wall using the same
JP5612505B2 (en) Heat collection tube construction method
JP6624441B2 (en) Construction method of the wall
JP5367537B2 (en) Construction method and structure of steel pipe sheet pile
CN104612694B (en) Freezing pipe processing method at a kind of chamber
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
RU178916U1 (en) DRILLING RIG SUPPORT USED FOR STRENGTHENING EARTH STRUCTURE
JP6072336B1 (en) Reinforcement method before repairing retaining wall structure
JP2018044337A (en) Structure and method for reinforcing embankment
JP2016027226A (en) Underground continuous wall water-stop structure and method
KR20080079090A (en) Ground freezing process of underground structure outblock
JPH0941356A (en) Freezing control method in method of freezing construction
JP6941556B2 (en) Liquefaction countermeasure method
JP6976192B2 (en) Caisson subsidence method
JP2011236613A (en) Shaft construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120920

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130731

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20131112

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20131128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20131217

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20131219

R150 Certificate of patent or registration of utility model

Ref document number: 5443200

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250